Exhibit K-2

Memorandum re NCE Tie-Line Project

     In connection with the  Commission's  1997 order approving the formation of
NCE, the company undertook to construct a new transmission line  interconnecting
PSCo and SPS within five years of the consummation of that merger. Based on that
commitment,  the  Commission  found  that the  combined  PSCo  and SPS  electric
operations  "are  capable of physical  interconnection."  New Century  Energies,
Inc.,  Holding Co. Act Release No.  26748 (Aug.  1, 1997)  ("1997  Order").  The
Commission  further noted that,  "In the event that New Century  Energies at any
time  determines  not to  construct  the  tie or  the  tie is not  substantially
completed  within  five years of the date of  consummation  of the  merger,  New
Century Energies will file a post-effective amendment concerning the measures it
will take to ensure the requirements of section 2(a)(29)(A) are satisfied."

     Since the  issuance of the 1997 Order,  NCE has made  substantial  progress
toward the completion of the tie-line.  Phase 1 of the line,  construction  of a
230-mile, 345 kV line from Amarillo, Texas to Holcomb, Kansas, is expected to be
completed  in the  third  quarter  of 2001.  There  has been  some  delay in the
construction of Phase 2, a 100-mile, 345 kV line from Holcomb,  Kansas to Lamar,
Colorado and a HVDC  facility.  Attached is a chart  detailing the various steps
NCE has taken and will take to complete this process. In particular:

     1.   As  required by the FERC order  approving  the merger of PSCo and SPS,
          those  companies  engaged in an  open-planning  process to analyze and
          plan the  tie-line.  The process  involved  the  formation of a "Study
          Committee"  consisting  of over fifty  members  representing  electric
          companies,   reliability  councils,   state  regulatory   commissions,
          consulting groups and electric marketers.  PSCo and SPS concluded this
          process on August 27, 1998,  with the  announcement  of their selected
          tie-line  alternative.  The fairness and  thoroughness of the regional
          planning  process is  demonstrated  by the fact that no  participating
          party sought  review of the proposed  project or otherwise  questioned
          the process itself.

     2.   SPS has sought and obtained a siting permit for both Phase 1 and Phase
          2 construction in Kansas from the Kansas Commission.

     3.   On September 30, 1999,  SPS applied for a Certificate  of  Convenience
          and  Necessity  ("CCN")  from the  Texas  Commission  for Phase 1 line
          construction  in Texas. On February 14, 2000, the parties in the Texas
          proceeding  filed a unanimous  stipulation  requesting  that the Texas
          Commission grant the  application.  The  Administrative  Law Judge has
          issued a proposed order recommending  approval of the CCN request and,
          by order dated May 10,  2000,  the Texas  Commission  approved the CNN
          request.

     4.   The Phase 2  tie-line  will pass  through  only one  Colorado  county,
          Prowers County.  In Colorado,  county  governments -- not the Colorado
          Commission -- have facilities siting authority.  On September 9, 1999,
          the Prowers County Planning Commission approved the Special Use Permit
          that  allows  for  construction  of the  Phase  2  tie-line  and  HVDC
          converter within the county.

     5.   NCE has obtained easements for 40% of the Texas  rights-of-way and 60%
          of the Kansas rights-of-way for Phase 1 of the tie-line.

     6.   NCE has obtained  easements  for 36% of the Kansas  rights-of-way  and
          100% of the Colorado rights-of-way for Phase 2 of the tie-line.

NCE already has spent more than $10 million in  expenditures  in connection with
the tie-line project.

     NCE had  originally  planned to  complete  the entire  construction  of the
tie-line by year-end 2001. In early 1999,  however,  NCE announced that due to a
number of factors, including changes to the PSCo and SPS load forecasts and fuel
prices,  it  would  instead  adopt  the  phased  approach  described  above.  If
necessary,  NCE will file a post-effective amendment in File No. 70-8787, asking
the Commission to extend the time for completing the tie line.

     The  requested  extension  will enable  PSCo to comply with the  procedural
requirements  of the  Colorado  Commission.  PSCo had included the tie-line as a
planning  assumption in its 1999 Draft Integrated  Resource Plan ("IRP"),  which
showed PSCo's  resource  needs for a twenty-year  period  commencing in 1999 and
which also included a six-year  resource  acquisition  period of 2000-2005.  The
effect of this  assumption  would have been to enable  PSCo to avoid the need to
acquire an amount of firm  capacity  it would  otherwise  have had to acquire to
meet its  projected  peak in 2005,  the last year of the 1999 Draft IRP resource
acquisition period. In a recent order, however, the Colorado Commission rejected
inclusion of the tie-line as a planning assumption and found that "a certificate
of  public  convenience  and  necessity  [("CPCN")]  proceeding,  and not an IRP
docket,  is  the  appropriate  forum  to  evaluate  the  varied  advantages  and
disadvantages of the proposed tieline." Application of Public Service Company of
Colorado for an Order Approving Its 1999 Integrated  Resource Plan, Decision No.
C00-311 (March 15, 2000)./1/

--------
1    It is important to understand the context in which the Colorado  Commission
     issued  this  order.  Although  not  explicitly  stated in the  order,  the
     Colorado  Commission  has had a  long-standing  policy of requiring PSCo to
     consider  purchases from third parties to meet its resources  needs and had
     previously  expressed  concern about PSCo's recent  reliance on self-supply
     and affiliate  arrangements to supply its resource  needs.  The reason that
     the tie-line  would have enabled  PSCo to defer the  acquisition  of needed
     capacity  is because  PSCo,  using a completed  tie-line,  would be able to
     access  capacity on the SPS system.  The assumption  that PSCo would obtain
     such capacity  from an  affiliate,  however,  was not  consistent  with the
     Commission's  policies.  Moreover,  in light of the generation  divestiture
     that SPS plans to undertake to comply with Texas SB-7,  as discussed in the
     Application/Declaration  to which this  memorandum is an exhibit,  SPS will
     not have the level of generation upon which the capacity  deferral  benefit
     in PSCo's 1999 Draft IRP was premised.
----------

     In response to that  order,  PSCo will file for a CPCN for the  tie-line on
the  basis  that:   (1)  the   tie-line   will   improve   reliability   on  the
transmission-constrained  PSCo system;  (2) the tie-line will enable PSCo to tap
into MAPP and the SPP in the Eastern Interconnect as both a buyer (enabling PSCo
to make  economy  power  purchases  lowering its  operating  costs) and a seller
(permitting  PSCo to make  economy  energy  sales  for the  benefit  of both its
customers and shareholders);  and (3) the tie-line will enable PSCo to lower its
operating reserve levels,  again enabling PSCo to lower its operating costs. NCE
believes these reasons will convincingly  demonstrate the need for completion of
the tie-line.

     NCE anticipates filing the CPCN application with the Colorado Commission on
or before  September 29, 2000.  Under its rules,  the Colorado  Commission  must
issue its decision  within 210 days of the date of the filing.  Thus, NCE should
receive its CPCN for Phase 2 of the  tie-line  by the end of April  2001,  which
would allow the company to complete construction of the tie-line.

     Pending  completion of the  tie-line,  NCE  anticipates  that there will be
opportunities  for PSCo and SPS to exchange  power under the Xcel System's Joint
Operating Agreement ("JOA"),  which the FERC approved in its order approving the
NCE/NSP  merger.   The  JOA,  which  is  described  more  fully  in  the  Merger
Application,  will become  effective upon the completion of the NCE/NSP  merger.
NCE anticipates that the Xcel companies will be able to obtain both firm (mostly
short-term) and nonfirm  transmission between the PSCo and SPS systems needed to
engage in transactions under the JOA, once it becomes effective. In light of the
present availability of transmission,  we believe that following the merger PSCo
and SPS will be able to obtain the transmission  services necessary to engage in
power transactions under the JOA, even before the tie-line is completed.

     It  is  Xcel's  understanding,   as  explained  above,  that  the  Colorado
Commission  will issue its order on or before  April 30, 2001 -- within the five
years contemplated by the 1997 NCE Order.


SPS/PSCo TRANSMISSION LINE INTERCONNECT PROJECT MILESTONES


--------------------------------------------------------------------------------
Milestone                             Date                     Status
--------------------------------------------------------------------------------
Southwestern Public Service Company   8/22/95                  Completed
("SPS") and Public Service Company
of Colorado ("PSCo") announced an
agreement to merge forming New
Century Energies, Inc. ("NCE").
--------------------------------------------------------------------------------
SPS and PSCo initiate an open         9/96                     Completed
planning study process, the Joint
Transmission Planning Study ("the
Study"), by inviting 205 regional
utilities, federal and state
regulatory agencies and
environmental organizations to
participate.
--------------------------------------------------------------------------------
SPS and PSCo merge NCE.               8/1/97                   Completed
--------------------------------------------------------------------------------
The Study Report approved by Study    9/18/97                  Completed
Committee.
--------------------------------------------------------------------------------
Open Solicitation Process Request     10/1/97                  Completed
for Proposal ("RFP") issued.
--------------------------------------------------------------------------------
The Study Report released.            10/6/97                  Completed
--------------------------------------------------------------------------------
Open Solicitation Process RFP bids    11/7/97                  Completed
due.
--------------------------------------------------------------------------------
RFP bid  evaluation  conducted  by    11/7/97 - 7/31/98        Completed
Hagler Bailly Consulting, Inc. ("HB")
--------------------------------------------------------------------------------
HB's report "Evaluations of           7/31/98                  Completed
Proposals for PSCo/SPS Transmission
Interconnection Solicitation"
released.
--------------------------------------------------------------------------------
HB's report "PSCo/SPS Transmission    8/26/98                  Completed
Interconnection Solicitation
Supplemental Report" released.
--------------------------------------------------------------------------------
Selection Conference held by NCE.     8/27/98                  Completed
Final Project Alternative 5X
presented as selected alternative.
This alternative consists of a
345 kV line from Amarillo, TX
(Potter County Interchange) to
Garden City, KS (Sunflower Electric
Power Corporation's Holcomb
Generating Station) and thence
to Lamar, Colorado and PSCo's
jointly-owned Lamar Substation.
A High Voltage Direct Current
("HVDC") Converter sited at Lamar
Substation.
--------------------------------------------------------------------------------
Interconnection Team formed for       9/98                     Completed
pursuing logistics of line
construction.
--------------------------------------------------------------------------------
State regulatory commission           10/98 - 3/99             Completed
meetings held to discuss filing
requirements.
--------------------------------------------------------------------------------
Community meetings for presentation   10/98 - 2/99             Completed
of proposed line corridors held in
Colorado, Kansas, Oklahoma and
Texas.
--------------------------------------------------------------------------------
Vendor presentations for HVDC         11/98 - 1/99             Completed
converter conducted.
--------------------------------------------------------------------------------
NCE splits interconnection project    1/99                     Completed
into two phases.  Phase 1 consists
of the line construction from
Amarillo, TX to Holcomb, KS.  Phase
2 consists of line construction
form Holcomb, KS to Lamar, CO and
the construction of the HVDC
Converter.
--------------------------------------------------------------------------------
Application made requesting a         4/29/99                  Completed
Siting Permit from the Kansas
Corporation Commission ("KCC") for
both Phase 1 and Phase 2
construction in Kansas.
--------------------------------------------------------------------------------
KCC Public Hearing on Siting Permit   5/26/99                  Completed
application held.
--------------------------------------------------------------------------------
KCC Technical Hearing on Siting       6/17/99                  Completed
Permit application held.
--------------------------------------------------------------------------------
Application made requesting Special   7/12/99                  Completed
Use Permit ("Permit") from Prowers
County (Colorado) Planning
Commission. (County governments
have siting authority in Colorado.)
--------------------------------------------------------------------------------
KCC order granting Siting Permit      7/19/99                  Completed
issued.
--------------------------------------------------------------------------------
Prowers County Planning Commission    8/3/99                   Completed
held hearing on Permit during which
Planning Commission voted approval
and forwarded application to
County Commission.
--------------------------------------------------------------------------------
Prowers County Commission Hearing     8/30/99                  Completed
held.  Permit issue referred to
county counsel for document
drafting.
--------------------------------------------------------------------------------
Special Use Permit granted by         9/9/99                   Completed
Prowers County Commission.
--------------------------------------------------------------------------------
Application made requesting a         9/30/99                  Completed
Certificate of Convenience and
Necessity ("CCN") from Public
Utility Commission of Texas
("PUCT") for Phase 1 line
construction in Texas.
--------------------------------------------------------------------------------
Sunflower Electric Power              1/28/00                  Completed
Corporation and SPS sign
Interconnection Agreement
--------------------------------------------------------------------------------
Stipulation filed by parties in       2/14/00                  Completed
Texas CCN docket (PUCT Docket
No. 21460) requesting that the
PUCT grant application.
--------------------------------------------------------------------------------
Right-of-Way ("ROW") acquisition      3/22/00                  Completed
completed in Colorado.  (Texas ROW:
Potter County 55%, Moore County
46%, Sherman County 14%, Hansford
County 26%. Oklahoma ROW: Texas
County 24%. Kansas ROW: Phase 1
(Stevens, Grant, Kearney and Finney
Counties) 61%, Phase 2 (Finney and
Hamilton Counties) 36%.
--------------------------------------------------------------------------------
PUCT order granting CPCN issued.      4/1/00                   Pending
--------------------------------------------------------------------------------
Application requesting Certificate    7/00                     Planned
of Public Convenience and Necessity
("CPCN") to construct Phase 2
submitted to Colorado Public
Utilities Commission ("CPUC").
--------------------------------------------------------------------------------
Construction begins on Phase 1.       11/00                    Planned
--------------------------------------------------------------------------------
CPUC order granting CPCN for Phase    3/01                     Planned
2 construction.
--------------------------------------------------------------------------------
Construction completed on Phase 1     9/01                     Planned
and line energized.
--------------------------------------------------------------------------------
Construction begins on Phase 2.       Planned                  Planned
--------------------------------------------------------------------------------
Construction completed on Phase 2;    Planned                  Planned
line and HVDC converter energized.
--------------------------------------------------------------------------------