<PAGE>

                                                Filed Pursuant to Rule 424(b)(3)
                                                Registration No. 333-91391

PROSPECTUS

                                  $308,500,000

                             [LOGO Appears Here]

                              AES IRONWOOD, L.L.C.
                        Offer to Exchange All Outstanding
                      8.857% Senior Secured Bonds due 2025
                For 8.857% Senior Secured Exchange Bonds due 2025

                             ----------------------

THE NEW BONDS:
      o  Interest Payments: Interest on the bonds will be payable every three
         months, on February 28, May 31, August 31 and November 30 of each year,
         beginning August 31, 1999.

      o  Security: The new bonds will rank equally with all of our other senior
         debt secured by a lien on and security interest in shared collateral,
         which consists of substantially all of our assets. In addition, the
         indenture accounts, the debt service reserve account and the debt
         service reserve letter of credit, other than to the extent the
         provider's right to specific proceeds under the debt service reserve
         letter of credit, are separate collateral solely for the benefit of the
         holders of the new bonds.

      o  Ranking: The new bonds rank equally in right of payment with all other
         present and future senior debt and senior in right of payment to all
         subordinated debt.

      o  Listing: The new bonds will not be listed on any securities exchange or
         NASDAQ.

THE EXCHANGE OFFER:
      o  Expiration: 5:00 p.m. New York City time on May 12, 2000, unless
         otherwise extended.

      o  Tendered Bonds: All old bonds that are validly tendered and not validly
         withdrawn at the expiration of the exchange offer will be exchanged for
         an equal principal amount of new bonds that are registered under the
         Securities Act of 1933.

      o  Tax Consequences: The exchange of old bonds for new bonds will not be a
         taxable event for U.S. federal income tax purposes.

      o  We are not making this exchange offer in any state or jurisdiction
         where it is not permitted.


YOU SHOULD CAREFULLY CONSIDER THE "RISK FACTORS" BEGINNING ON PAGE 17 OF THIS
PROSPECTUS BEFORE PARTICIPATING IN THE EXCHANGE OFFER OR INVESTING IN THE NEW
BONDS ISSUED IN THE EXCHANGE OFFER.


Neither the Securities and Exchange Commission nor any state securities
commission has approved or disapproved these securities or determined if this
prospectus is truthful or complete. Any representation to the contrary is a
criminal offense.

                               ------------------

              The date of this prospectus is March 31, 2000.


<PAGE>


                                TABLE OF CONTENTS

                                Page                                      Page
                                ----                                      ----



PROSPECTUS SUMMARY.................1       CERTAIN RELATIONSHIPS AND RELATED
SUMMARY OF THE TERMS OF THE NEW            TRANSACTIONS......................42
BONDS .............................1       SUMMARY OF PRINCIPAL PROJECT
SUMMARY OF THE EXCHANGE OFFER......6       CONTRACTS.........................43
SUMMARY OF RISK FACTORS...........11       ROLE OF THE INDEPENDENT ENGINEER..70
SUMMARY OF INDEPENDENT ENGINEER'S          DESCRIPTION OF THE NEW BONDS......72
REPORT............................12       SUMMARY OF PRINCIPAL FINANCING
SUMMARY OF INDEPENDENT POWER               DOCUMENTS.........................80
CONSULTANT'S REPORT...............15       PLAN OF DISTRIBUTION.............107
SUMMARY OF SIGNIFICANT PROJECT             UNITED STATES FEDERAL INCOME TAX
CONTRACTS.........................16       CONSIDERATIONS...................107
RISK FACTORS......................17       LEGAL MATTERS....................107
USE OF PROCEEDS...................24       EXPERTS..........................108
CAPITALIZATION....................25       WHERE YOU CAN FIND MORE
CALCULATION OF EARNINGS TO FIXED           INFORMATION......................108
CHARGES DEFICIENCY................25       INDEX TO FINANCIAL STATEMENTS....F-1
THE EXCHANGE OFFER................26       ANNEX A: GLOSSARY OF TECHNICAL
SELECTED FINANCIAL DATA...........35       TERMS............................A-1
MANAGEMENT'S DISCUSSION AND                ANNEX B: INDEPENDENT ENGINEER'S
ANALYSIS OF FINANCIAL CONDITION            REPORT...........................B-1
AND RESULTS OF OPERATIONS.........36       ANNEX C: INDEPENDENT POWER
OUR BUSINESS......................38       CONSULTANT'S REPORT..............C-1
OUR MANAGEMENT....................40




                            ------------------------


      This prospectus is part of a registration statement we filed with the
Securities and Exchange Commission. You should rely only on the information or
representations provided in this prospectus. We have not authorized any person
to provide information other than that provided in this prospectus. We are not
making an offer of these securities in any jurisdiction where the offer is not
permitted. You should not assume that the information in this prospectus is
accurate as of any date other than the date on the front page of this
prospectus.



      Each broker-dealer that receives new bonds for its own account under the
exchange offer must acknowledge that it will deliver a prospectus in connection
with any resale of the new bonds. The letter of transmittal states that by so
acknowledging and by delivering a prospectus, a broker-dealer will not be deemed
to admit that it is an "underwriter" within the meaning of the Securities Act.
This prospectus, as it may be amended or supplemented from time to time, may be
used by a broker-dealer in connection with resales of new bonds received in
exchange for old bonds where the old bonds were acquired by the broker-dealer as
a result of market-making activities or other trading activities. We have agreed
that, starting on the expiration date of the exchange offer and ending on the
close of business 270 days after the expiration date, we will make this
prospectus available to any broker-dealer for use in connection with any resale.
See "PLAN OF DISTRIBUTION."


                             UK SELLING RESTRICTIONS


      The new bonds may not be offered or sold in or into the United Kingdom
except to persons whose ordinary activities involve acquiring, holding, managing
or disposing of investments, as principal or agent, for the purposes of their
businesses, or in other circumstances that do not constitute an offer to the
public in the United Kingdom for the purposes of the Public Offers of Securities
Regulations 1995 or the Financial Services Act 1986, and this prospectus may
only be issued or passed on to persons in the United Kingdom if the persons are
of a kind described in article 11(3) of the Financial Services Act 1986
(Investment Advertisements) (Exemptions) Order 1996 or if the persons are
persons to whom this prospectus may otherwise lawfully be issued or passed on.




                                       i

<PAGE>


                               PROSPECTUS SUMMARY



      This summary highlights selected information from this prospectus but does
not contain all of the information that is important to you. To understand all
of the terms of the exchange offer and to attain a more complete understanding
of our business and financial situation, you should read carefully this entire
prospectus. For an explanation of specific technical terms used in this
prospectus, please read "ANNEX A: GLOSSARY OF TECHNICAL TERMS."


                      SUMMARY OF THE TERMS OF THE NEW BONDS


      The exchange offer relates to the exchange of up to $308,500,000 principal
amount of new bonds for an equal principal amount of old bonds. The form and
terms of the new bonds are substantially identical to the form and terms of the
old bonds, except the new bonds will be registered under the Securities Act.
Therefore, the new bonds will not bear legends restricting their transfer. The
new bonds will evidence the same debt as the old bonds, which they replace, and
both the old bonds and the new bonds are governed by the same indenture.


Issuer:                 AES Ironwood, L.L.C.

Securities Offered:     $308,500,000 aggregate principal amount of
                        8.857% Exchange Senior Secured Bonds due 2025.

Interest:               We will pay interest on the bonds every three months, on
                        each February 28, May 31, August 31 and November 30,
                        beginning on the first payment date after the last date
                        to which interest has been paid.

Final Maturity Date:    November 30, 2025.


Principal Repayment:    We will pay principal on the new bonds in
                        installments quarterly on each February 28, May 31,
                        August 31 and November 30, commencing February 28, 2002
                        to the registered owners on the immediately preceding
                        record date as described under "DESCRIPTION OF THE NEW
                        BONDS--Payment of Interest and Principal."


Ratings:                The new bonds are expected to be rated "BBB-" from
                        Standard & Poor's Rating Group and "Baa3" from Moody's
                        Investors Services, Inc., the same ratings borne by the
                        old bonds. See "DESCRIPTION OF THE NEW BONDS--Ratings."


Summary of
Coverage Ratios:        You will find projected coverage ratios with respect to
                        the bonds in the projections included in the independent
                        engineer's report, which we have attached as Annex B,
                        and these ratios are subject to the qualifications,
                        limitations and exclusions described in the independent
                        engineer's report. The following ratios reflect the base
                        case assumptions described in the independent engineer's
                        report.



                                                                      Post-Power
                                                        During Power   Purchase
                                           Full Term     Purchase      Agreement
                                          of the Bonds Agreement Term   Period
                                          ------------ --------------   ------
                  Debt Service Coverage
                     Minimum.............     1.45        1.45           5.77
                     Average.............     2.30        1.46           5.81
                  Interest Coverage
                     Minimum.............     1.58        1.58          18.45
                     Average.............    11.13        2.59          47.03


                        As described in the independent engineer's report, these
                        projections are subject to risks, uncertainties and
                        other factors which could cause actual results to differ
                        materially from those stated. We cannot assure that
                        these projected coverage ratios will be achieved. See
                        "ANNEX B: INDEPENDENT ENGINEER'S REPORT" and "RISK
                        FACTORS."


Optional Redemption:    We may redeem any of the new bonds, in whole or in part,
                        at any time at a redemption price equal to:

                        o     100% of the principal amount; plus

                        o     accrued interest; plus


                                       1

<PAGE>


                        o     a make-whole premium calculated using a discount
                              rate equal to the interest rate on comparable U.S.
                              Treasury securities plus 50 basis points.

Mandatory
Redemption:             We must redeem all of the new bonds, in whole or in
                        part, at a redemption price equal to 100% of the
                        principal amount plus accrued interest if:

                        o     we receive casualty proceeds, eminent domain
                              proceeds or specific performance liquidated
                              damages from Siemens Westinghouse under the
                              construction agreement; and

                        o     in each case, specified additional conditions are
                              satisfied.


                        We must redeem all of the new bonds, in whole or in
                        part, at a redemption price equal to 100% of the
                        principal amount plus accrued interest if we receive
                        proceeds under the guaranty provided by The Williams
                        Companies, Inc. because we terminated the power purchase
                        agreement as a result of an event of default by Williams
                        Energy. See "DESCRIPTION OF THE NEW BONDS--Mandatory
                        Redemption."



Resale of the New
Bonds:                  We believe that beneficial interests in the new bonds
                        may be offered for resale, resold and otherwise
                        transferred by most owners of the new bonds without
                        further compliance with the registration and prospectus
                        delivery requirements of the Securities Act so long as:


                        o     you are acquiring the new bonds in the ordinary
                              course of your business;

                        o     you are not participating, and have no arrangement
                              or understanding with any person to participate,
                              in the distribution of the new bonds; and

                        o     you are not an insider or a related party of ours.


                        This belief is based upon existing interpretations of
                        the staff of the SEC's Division of Corporation Finance
                        described in several no-action letters issued to third
                        parties unrelated to us and subject to important
                        restrictions described in "THE EXCHANGE OFFER--Purpose
                        and Effect of the Exchange Offer." We do not intend to
                        seek our own no-action letter. If our belief is wrong
                        and you transfer a new bond without delivering a
                        prospectus meeting the requirements of the Securities
                        Act or without an exemption from the requirements, you
                        may incur liability under the Securities Act. We do not
                        and will not assume or indemnify you against this
                        liability. There can be no assurance that the staff of
                        the SEC's Division of Corporation Finance would make a
                        similar determination about the new bonds as it has in
                        no-action letters about exchanges of the securities of
                        other companies.


                        Only broker-dealers that acquired the old bonds as a
                        result of market-making or other trading activities may
                        participate in the exchange offer. Each broker-dealer
                        that receives new bonds for its own account in the
                        exchange offer must acknowledge that it will deliver a
                        prospectus in connection with any resale of those new
                        bonds. This prospectus, as it may be amended or
                        supplemented from time to time, may be used by a
                        broker-dealer in connection with those resales.

                        Broker-dealers that acquired old bonds directly from us
                        may not rely on the interpretations of the SEC referred
                        to above. Accordingly, in order to sell their bonds,
                        broker-dealers that acquired old bonds directly from us
                        must comply with the registration and prospectus
                        delivery requirements, including being named as a
                        selling security holder in any resale prospectus.

                        Old bonds that are not tendered for exchange will
                        continue to be subject to existing transfer restrictions
                        and will not have registration rights. Therefore, the
                        market for secondary resales of any old bonds that are
                        not tendered for exchange is likely to be minimal.


Equity Contributions:   We have entered into an equity subscription agreement
                        with AES Ironwood, Inc. under which AES Ironwood, Inc.
                        agreed to contribute up to $50,149,285 in equity to us
                        to fund project costs. AES Ironwood, Inc.'s obligation
                        under the equity subscription agreement will be


                                       2

<PAGE>


                        supported by an acceptable letter of credit or an
                        acceptable bond. AES Ironwood, Inc. will fund amounts
                        available under the equity subscription agreement when
                        all funds in the construction account have been used or
                        during the continuation of an event of default under the
                        indenture, whichever occurs first. We have the option of
                        treating a portion or all of the equity contribution as
                        affiliate subordinated debt. Subject to the conditions
                        described in the equity subscription agreement and the
                        collateral agency agreement, including achievement of
                        final completion of our facility, funding of all
                        required amounts and deposits under the collateral
                        agency agreement and absence of any default, any equity
                        which remains committed under the equity subscription
                        agreement but unfunded after the commercial operation
                        date may be canceled. The commercial operation date is
                        the date initial startup testing at our facility has
                        been successfully completed and all necessary approvals,
                        permits, and authorizations have been obtained to allow
                        us to begin selling energy and capacity.



Ranking:                Other than the bonds, which have an aggregate principal
                        balance of $308.5 million, we do not have any
                        outstanding long-term debt. The new bonds will:


                        o    rank equally in right of payment with all future
                             senior secured debt; and

                        o    rank senior in right of payment to all subordinated
                             debt.


                        Any debt incurred under the debt service reserve
                        letter of credit or the construction period letter of
                        credit will rank equally in right of payment with the
                        new bonds. There are currently no drawings
                        outstanding under those letters of credit.


Collateral:             The new bonds will rank equally with all of our other
                        senior debt by a lien on and security interest in the
                        collateral.

                        o     The indenture accounts, the debt service reserve
                              account and the debt service reserve letter of
                              credit, other than to the extent of the letter of
                              credit provider's right to specific proceeds, will
                              constitute separate collateral solely for the
                              benefit of the holders of the bonds.

                        o     The collateral for the benefit of holders of
                              senior debt, including holders of the new bonds,
                              will include:

                              o     all of our revenues;

                              o     the project accounts, other than the debt
                                    service reserve account;

                              o     all of our real and personal property;

                              o     proceeds of insurance, condemnation and
                                    liquidated damages payments, if any;

                              o     all project contracts;

                              o     all ownership interests in our company; and

                              o     the equity contribution and all rights under
                                    the equity subscription agreement.


Limited Recourse:       All obligations in connection with the new bonds will be
                        solely our obligations. The bondholders will have no
                        claim against or recourse to the holders of our
                        ownership interests or any of our affiliates or any of
                        their incorporators, stockholders, directors, officers
                        or employees for the repayment of the new bonds, except
                        to the extent of their obligations under the transaction
                        documents, including the equity contribution and the
                        pledge of AES Ironwood, Inc.'s ownership interests in
                        our company.


Debt Service
Reserve Account:        We will be required to fund or provide for the funding
                        of a debt service reserve account on the commercial
                        operation date, the guaranteed completion date or
                        December 31, 2002, whichever occurs first, in an amount
                        sufficient to pay principal and interest due on the
                        bonds on the next two payment dates plus, if we provide
                        a letter of credit in lieu of funding the debt service
                        reserve account, six months of interest on the maximum
                        amount of the letter of credit. We anticipate satisfying
                        this requirement by providing a letter of credit issued
                        by Dresdner Bank AG, New York Branch or another
                        financial institution rated at least "A" by Standard &
                        Poor's and "A2" by Moody's.


                                       3

<PAGE>



Change in Control:      While the new bonds are outstanding, the indenture
                        requires The AES Corporation to maintain directly or
                        indirectly at least 51% of both of the voting and
                        economic interests in our company. If The AES
                        Corporation desires to reduce its voting or economic
                        interest in AES Ironwood, L.L.C. below 51%, either we
                        must receive confirmation of the initial ratings of the
                        bonds or the holders of at least two-thirds in aggregate
                        principal amount of the bonds must approve the change in
                        ownership.


Other Principal
Covenants:              The indenture contains limitations on, among other
                        actions:

                        o     incurring additional indebtedness;
                        o     granting liens on our property;
                        o     distributing equity and paying subordinated
                              indebtedness issued by our affiliates;
                        o     entering into transactions with our affiliates;
                        o     amending, terminating or assigning of project
                              contracts; and
                        o     fundamental changes or disposition of assets.

                        See "SUMMARY OF PRINCIPAL FINANCING
                        DOCUMENTS--Indenture--Negative Covenants."


Form, Denomination and
Registration of Bonds:  New bonds will be issued in fully registered form
                        without coupons in denominations of U.S.$100,000 and any
                        integral multiple of US$1,000 in excess thereof and will
                        be represented by one or more global bonds, each
                        registered in the name of a nominee of DTC. Beneficial
                        interests in the global bonds will be shown on, and
                        transfers of the beneficial interests will be effected
                        only through, the book-entry records maintained by DTC
                        and its direct and indirect participants, including the
                        Euroclear Systems and Cedel Bank.


Governing Law:          The new bonds, the indenture and the other principal
                        financing documents, other than the mortgage, are
                        governed by the laws of the State of New York. The
                        mortgage is governed by the laws of the Commonwealth of
                        Pennsylvania.


Intercreditor
Arrangements:           The collateral agency agreement requires the vote of
                        senior creditors holding at least one-third of our debt
                        to direct specified actions of the collateral agent. The
                        collateral agent, who is appointed by the senior
                        creditors to act on their behalf, may be directed to
                        exercise its rights to seek immediate repayment of the
                        bonds or its other rights under the collateral agency
                        agreement following:



                        o     an event of default under the debt service reserve
                              letter of credit and reimbursement agreement under
                              which the letter of credit provider will provide
                              to us the letter of credit to fund the debt
                              service reserve account;



                        o     an event of default under the construction period
                              letter of credit and reimbursement agreement,
                              under which the letter of credit provider has
                              provided to us the letter of credit if the
                              commercial operation date is not achieved;


                        o     an event of default under the indenture; or

                        o     a bankruptcy event with respect to us. The bonds
                              will represent approximately 95%, without giving
                              effect to any construction period letter of
                              credit, of the combined credit exposure, and, in
                              respect of matters voted on by the senior
                              creditors, the trustee under the indenture will
                              vote all bonds according to the votes of a
                              majority of bondholders voting. See "SUMMARY OF
                              PRINCIPAL FINANCING DOCUMENTS--Collateral Agency
                              Agreement."


                                       4

<PAGE>


Accounts and
Flows of Funds:         Following the commercial operation date, project
                        revenues will be deposited in accounts established under
                        the financing documents and held by the trustee and the
                        collateral agent. In most circumstances, operating
                        revenues will be applied in the following order:

                        o     operating and maintenance costs, including any
                              working capital loans;
                        o     fees, costs and expenses of the trustee,
                              collateral agent, debt service reserve letter of
                              credit provider and any construction period letter
                              of credit provider;
                        o     interest payments on the bonds, debt service
                              reserve letter of credit loans and any
                              construction period letter of credit loans;
                        o     principal payments on the bonds and any
                              construction period letter of credit loans;
                        o     replenishment of the debt service reserve account
                              and principal payments on debt service reserve
                              letter of credit loans;
                        o     required deposits in the major maintenance reserve
                              account;
                        o     non-dispatch payments to Williams Energy;
                        o     fuel conversion volume rebate payments to Williams
                              Energy;
                        o     subordinated bonuses to Siemens Westinghouse, if
                              any;
                        o     repayment of third-party subordinated debt; and
                        o     subject to the restricted payments test, permitted
                              distributions to persons holding ownership
                              interests in our company.

                        Under circumstances involving a termination or
                        non-renewal of the debt service reserve letter of credit
                        or specified delays in repayment of the principal amount
                        of debt service reserve letter of credit loans,
                        principal repayments of drawings on the debt service
                        reserve letter of credit will be made at the same
                        priority as principal on the new bonds. Under certain
                        circumstances, if no default or event of default under
                        the indenture is continuing, we may from time to time
                        withdraw funds then deposited in specified accounts
                        established under the financing documents so long as we
                        provide to the collateral agent acceptable credit
                        support to ensure repayment of the withdrawn funds. See
                        "SUMMARY OF PRINCIPAL FINANCING DOCUMENTS--Collateral
                        Agency Agreement--Payments During Operating Period" and
                        "--Advances."

Independent Engineer:   Stone & Webster Management Consultants, Inc., as the
                        independent engineer, is responsible for confirming the
                        reasonableness of specific statements and projections
                        made in specified certificates required to be provided,
                        including with respect to:

                        o     satisfaction of specific requirements under the
                              construction agreement;

                        o     the cost of and occurrence of the completion of
                              rebuilding, repairing or restoring our facility
                              following an event of loss or event of eminent
                              domain;

                        o     under specified circumstances, the calculation of
                              debt service coverage ratios and the consistency
                              of assumptions made in connection therewith;

                        o     whether any termination, amendment or modification
                              of any project contract would reasonably be
                              expected to have a material adverse effect; and

                        o     specified tests required for the issuance of
                              additional debt.


                                       5

<PAGE>





                          SUMMARY OF THE EXCHANGE OFFER



      We summarize the terms of the exchange offer below. You should read the
discussion under the heading "THE EXCHANGE OFFER" beginning on page 26 for
further information regarding the exchange offer and resale of the new bonds.



The Exchange Offer:     We are offering to exchange up to $308,500,000 aggregate
                        principal amount of new bonds, which have been
                        registered under the Securities Act, for up to
                        $308,500,000 aggregate principal amount of old bonds,
                        which we issued on June 25, 1999 in a private offering.
                        In order for your old bonds to be exchanged, you must
                        properly tender them prior to the expiration of the
                        exchange offer. All old bonds that are validly tendered
                        and not validly withdrawn will be exchanged. We will
                        issue new bonds on or promptly after the expiration of
                        the exchange offer. Old bonds may be exchanged for new
                        bonds only in integral multiples of $1,000.



Registration Rights
Agreement:              We sold the old bonds on June 25, 1999 to the initial
                        purchasers of the old bonds. Simultaneously with that
                        sale we signed a registration rights agreement with the
                        initial purchasers which requires us to conduct this
                        exchange offer.



                        You have the right pursuant to the registration rights
                        agreement to exchange your old bonds for new bonds with
                        substantially identical terms. This exchange offer is
                        intended to satisfy this right. After the exchange offer
                        is complete, you will no longer be entitled to any
                        exchange or registration rights with respect to old
                        bonds you do not tender for exchange.



Consequences of Failure
to Exchange Your
Old Bonds:              If you do not exchange your old bonds for new bonds
                        pursuant to the exchange offer, you will continue to be
                        subject to the restrictions on transfer provided in the
                        old bonds and the indenture. In general, the old bonds
                        may not be offered or sold unless registered under the
                        Securities Act, except pursuant to an exemption from, or
                        in a transaction not subject to, the Securities Act and
                        applicable state securities laws. We do not currently
                        plan to register the old bonds under the Securities Act.
                        To the extent that old bonds are tendered and accepted
                        in the exchange offer, the trading market for untendered
                        old bonds and tendered but unaccepted old bonds will be
                        adversely affected.



Expiration Date:        The exchange offer will expire at 5:00 p.m., New York
                        City time, on May 12, 2000, or a later date and time to
                        which we may extend it, in which case the term
                        "expiration date" will mean the latest date and time to
                        which the exchange offer is extended. Notwithstanding
                        the preceding sentence, we will not extend the
                        expiration date beyond September 30, 2000.



Withdrawal of Tenders:  You may withdraw your tender of old bonds at any time
                        prior to the expiration date by delivering written
                        notice of your withdrawal to the exchange agent in
                        accordance with the withdrawal procedures described in
                        this prospectus. We will return to you, without charge,
                        promptly after the expiration or termination of the
                        exchange offer any old bonds that you tendered but that
                        were not accepted for exchange. The new bonds will be
                        issued on or promptly after the expiration date.



Conditions to
the Exchange Offer:     We will not be required to accept old bonds for exchange
                        if the exchange offer would violate applicable law or
                        any legal action has been instituted or threatened that
                        would impair our ability to proceed with the exchange
                        offer. The exchange offer is not conditioned upon any
                        minimum aggregate principal amount of old bonds being
                        tendered. We reserve the right to terminate the exchange
                        offer if certain specified conditions have not been
                        satisfied and to waive any condition or otherwise amend
                        the terms of the exchange offer in any respect. Please
                        read the section "THE EXCHANGE OFFER--Conditions to the
                        Exchange Offer" on page 29 for more information
                        regarding the conditions to the exchange offer.



                                       6

<PAGE>



Procedures for
Tendering Old
Bonds and
Representations:        If your old bonds are held through The Depository Trust
                        Company and you wish to participate in the exchange
                        offer, you may do so through one of the following
                        methods:



                        o     Delivery of a Letter of Transmittal. You must
                              complete and sign a letter of transmittal in
                              accordance with the instructions contained in the
                              letter of transmittal and forward the letter of
                              transmittal by mail, facsimile transmission or
                              hand delivery, together with any other required
                              documents, to the exchange agent, either with the
                              old bonds to be tendered or in compliance with the
                              specified procedures for guaranteed delivery of
                              the old bonds; or



                        o     Automated Tender Offer Program of The Depository
                              Trust Company. If you tender under this program,
                              you will agree to be bound by the letter of
                              transmittal that we are providing with this
                              prospectus as though you had signed the letter of
                              transmittal.



                        Under both methods, by signing or agreeing to be bound
                        by the letter of transmittal, you will represent to us
                        that, among other things:



                        o     any new bonds that you receive are being acquired
                              in the ordinary course of your business;



                        o     you have no arrangement or understanding with any
                              person or entity to participate in any
                              distribution of the new bonds;



                        o     you are not engaged in and do not intend to engage
                              in any distribution of the new bonds;



                        o     if you are a broker-dealer that will receive new
                              bonds for your own account in exchange for old
                              bonds, you acquired those bonds as a result of
                              market-making activities or other trading
                              activities and you will deliver a prospectus, as
                              required by law, in connection with any resale of
                              the new bonds; and



                        o     you are not our "affiliate," as defined in Rule
                              405 of the Securities Act.



                        Please do not send your letter of transmittal or
                        certificates representing your old bonds to us. Those
                        documents should only be sent to the exchange agent.
                        Questions regarding how to tender and requests for
                        information should be directed to the exchange agent.



Special Procedures for
Beneficial Owners:      If you own a beneficial interest in old bonds that are
                        registered in the name of a broker, dealer, commercial
                        bank, trust company or other nominee, and you wish to
                        tender the old bonds in the exchange offer, you should
                        contact the registered holder promptly and instruct the
                        registered holder to tender on your behalf.



Consequences of Not
Complying with
Exchange Offer
Procedures:             You are responsible for complying with all exchange
                        offer procedures. You will only receive new bonds in
                        exchange for your old bonds if, prior to the expiration
                        date, you deliver to the exchange agent (1) the letter
                        of transmittal, properly completed and duly executed,
                        (2) any other documents or signature guarantees required
                        by the letter of transmittal certificates for the old
                        bonds or a book-entry confirmation of a book-entry
                        transfer of the old and (3) bonds into the exchange
                        agent's account at DTC.

                        Any old bonds you hold and do not tender, or which you
                        tender but which are not accepted for exchange, will
                        remain outstanding. You will not have any appraisal or
                        dissenters' rights in connection with the exchange
                        offer.

                                       7

<PAGE>



                        You should allow sufficient time to ensure that the
                        exchange agent receives all required documents before
                        the expiration of the exchange offer. Neither we nor the
                        exchange agent has any duty to inform you of defects or
                        irregularities with respect to your tender of old bonds
                        for exchange.



Guaranteed Delivery
Procedures:             If you wish to tender your old bonds and cannot comply,
                        prior to the expiration date, with the applicable
                        procedures for tendering old bonds described above and
                        under "THE EXCHANGE OFFER--Procedures for Tendering",
                        you must tender your old bonds according to the
                        guaranteed delivery procedures described in "THE
                        EXCHANGE OFFER--Guaranteed Delivery Procedures"
                        beginning on page 31.



U.S. Federal Income
Tax Consideration:      The exchange of old bonds for new bonds in the exchange
                        offer will not be a taxable event for U.S. federal
                        income tax purposes. Please read "UNITED STATES FEDERAL
                        INCOME TAX CONSIDERATIONS" on page 107.



Use of Proceeds:        We will not receive any cash proceeds from the issuance
                        of new bonds. We intend to use the net proceeds from the
                        sale of the old bonds, together with an approximately
                        $50 million equity contribution, to:



                        o     fund the engineering, procurement, construction,
                              testing and commissioning of our facility;



                        o     pay legal, accounting and other related fees and
                              expenses in connection with the financing and
                              development of our project; and



                        o     pay project costs, including interest on the
                              bonds.



                               The Exchange Agent



      We have appointed The Bank of New York as exchange agent for the exchange
offer. You should direct questions and requests for assistance, requests for
additional copies of this prospectus or of the letter of transmittal and
requests for the notice of guaranteed delivery to the exchange agent addressed
as follows: The Bank of New York, 101 Barclay Street, 7E, New York, New York
10286; (212) 815-5988. Eligible institutions may make requests by facsimile at
(212) 815-6339.



                                       8

<PAGE>




                              AES Ironwood, L.L.C.



      AES Ironwood, L.L.C was formed to develop, construct, own, operate and
maintain a gas-fired electric generating power plant in Lebanon County,
Pennsylvania. We are in the developmental stage and currently have no operating
revenues. All of the equity interests in our company are owned by AES Ironwood,
Inc., a wholly-owned subsidiary of The AES Corporation. The AES Corporation will
provide funds to AES Ironwood, Inc. so that AES Ironwood, Inc. can make an
equity contribution to us to fund project costs. AES Ironwood, Inc. currently
has no operations outside of its activities in connection with our project and
does not anticipate undertaking any operations not associated with our project.
AES Ironwood, Inc. has no assets other than its membership interests in us and
AES Prescott, L.L.C., which will provide development, construction management
and operations and maintenance services to us. AES Prescott has no operations
outside of its activities in connection with our project. The AES Corporation
will supply AES Prescott with personnel and services necessary to carry out its
obligations to us. The AES Corporation is a public company and is subject to the
informational requirements of the Securities Exchange Act of 1934 and, in
accordance therewith, files reports, proxy statements and other information,
including financial reports, with the SEC. See "WHERE YOU CAN FIND MORE
INFORMATION."



      The following organizational chart illustrates the relationship among our
company, AES Ironwood, Inc., AES Prescott and The AES Corporation:






                               The AES Corporation
                                       |
                                       |
                                       |
                               AES Ironwood, Inc.
                                       |
                                       |
                       ----------------------------------
                       |                                |
                       |                                |
             AES Ironwood, L.L.C.              AES Prescott, L.L.C.






                                  Our Facility



      Our facility, which is still under construction, consists of a 705
megawatt (net) gas-fired combined cycle electric generating facility with
oil-firing capability. We expect our facility to become operational by
approximately June 30, 2001. We will not receive any revenues from the power
purchase agreement or otherwise before our facility becomes operational, at
which time we will begin to receive revenues under the power purchase agreement.
We will sell all of our facility's capacity, and provide fuel conversion and
ancillary services, to Williams Energy under a long-term power purchase
agreement. After the expiration of the 20-year term of the power purchase
agreement, we will enter into other power purchase agreements or operate our
facility as a merchant plant (i.e., an electric generation facility with no
dedicated long-term power purchase agreement).



      Our facility will be located in South Lebanon Township, Lebanon County,
Pennsylvania on property owned by us. Our facility will be designed, engineered,
procured and constructed for us by Siemens Westinghouse Power



                                       9

<PAGE>



Corporation under a fixed-price construction agreement. Among other components,
our facility will use two Siemens Westinghouse model 501G combustion turbines
with hydrogen-cooled generators, two unfired heat recovery steam generators and
one multicylinder steam turbine with a hydrogen-cooled generator. Siemens
Westinghouse will provide us with specific combustion turbine maintenance
services and spare parts for an initial term of between eight and 10 years,
depending on the timing of scheduled outages, under a maintenance services
agreement. Under the power purchase agreement, Williams Energy or its affiliates
will supply fuel necessary to allow us to provide capacity, fuel conversion and
ancillary services to Williams Energy. AES Prescott, the operator, will provide
development, construction management and operations and maintenance services for
our facility under an operations agreement. We will provide installation,
operation and maintenance of facilities necessary to interconnect our facility
to the transmission system of Metropolitan Edison Company, under an
interconnection agreement.



                              -------------------


      AES Ironwood, L.L.C. is a Delaware limited liability company with
principal executive offices located at 305 Prescott Road, Lebanon,
Pennsylvania 17042.  Our telephone number is (717) 228-1328.



                                       10

<PAGE>



                             SUMMARY OF RISK FACTORS



      You should read the "Risk Factors" section of this prospectus as well as
the other cautionary statements contained in this prospectus before tendering
your old bonds for new bonds or making an investment in the new bonds. The
following is a summary of the risks that are discussed in detail in this
prospectus:



Our cash flow and our ability to service the bonds will be adversely impacted
if:



      o  the commercial operations of our facility are significantly delayed or
         are otherwise unable to general sufficient cash flow;



      o  the financial condition of parties that we depend on deteriorates and
         cannot be replaced or they breach their obligations to us;



      o  we encounter significant construction delays and any liquidated
         damages, contingency funds, or insurance proceeds available to us are
         likely to be insufficient to cover our financial needs;



      o  the insurance we have obtained is inadequate in the event of a total
         loss or taking of our facility;



      o  unexpected events increase our expenses or reduce our projected
         revenues once we are operational;



      o  compliance with environmental and other regulatory matters cause
         significant delays or expenses; and



      o  we incur additional indebtedness as permitted under the indenture or
         make drawings under letters of credit.



In the event of a default, you may have limited or no recourse because:



      o  we are the sole legally responsible party in the event that the
         proceeds from the bonds, the equity contribution and the liquidation of
         the collateral are exhausted; and



      o  the collateral agency agreement contains provisions that may limit the
         remedies that could be exercised in respect of the events of default,
         other than a bankruptcy event of default, unless and until the required
         senior parties have directed the collateral agent to do so.



The success of our project and future operations may be impaired because:



      o  the combustion turbine to be used in our facility has no significant
         operating experience, and we may incur problems relating to start-up,
         commissioning and performance; and



      o  following the expiration of the power purchase agreement, our facility
         is expected to become a merchant facility and we don't know if we will
         be able to find adequate purchasers or otherwise compete effectively in
         the merchant market.



Undue reliance should not be placed on projections and forward-looking
statements because:



      o  projections and their underlying assumptions are subject to significant
         uncertainties and actual results often differ, perhaps materially, from
         those projected; and



      o  forward-looking statements are based on current expectations and our
         knowledge of facts as of the date of this prospectus and are subject to
         various risks and uncertainties that are outside of our control.



                                       11

<PAGE>


                   SUMMARY OF INDEPENDENT ENGINEER'S REPORT

      Stone & Webster, with the assistance of Stone & Webster Engineering
Corporation, has prepared the independent engineer's report concerning specific
technical, environmental and economic aspects of our facility. We have attached
the independent engineer's report as Annex B to this prospectus. The independent
engineer's report includes, among other things, a conceptual design review of
our facility, a review of the significant project contracts and a review of
financial projections, including annual revenues, expenses and debt service
coverage for our facility during the period the bonds are scheduled to remain
outstanding. We retained Stone & Webster to prepare the independent engineer's
report because it is a leading consulting engineering firm which devotes a
substantial portion of its resources to providing services related to the
technical, environmental and economic aspects of power projects. Neither we, nor
any of our affiliates, is affiliated with Stone & Webster. We do not intend to
update the economic projections in the independent engineer's report from June
18, 1999, the date it was prepared.

      For purposes of reviewing the projected operating results, Stone & Webster
relied on specific assumptions regarding material contingencies and other
matters that are not within our control or that of Stone & Webster or any other
person. Each of these assumptions is described in the independent engineer's
report. These assumptions are inherently subject to significant uncertainties,
and actual results will differ, perhaps materially, from those projected. See
"RISK FACTORS."

      Subject to the information contained, and the assumptions and
qualifications made, in Stone & Webster's report, Stone & Webster expressed the
following opinions:

      1.    The facility design, as specified in the construction agreement, is
in accordance with standard industry practice. Siemens Westinghouse possesses
the organization and personnel to execute its obligations under the construction
agreement and the maintenance services agreement, and is familiar with the
construction and maintenance of large electrical generation facilities. Our
project construction schedule proposed by Siemens Westinghouse is achievable and
is consistent with the terms of the power purchase agreement.

      2.    Stone & Webster views the 501G combustion turbine as an advancement
in high-temperature advanced technology combustion turbines for Siemens
Westinghouse and is typical of the normal design evolution for manufacturers.
Many of the design concepts incorporated in the 501G are rooted firmly in the
501 series and are complemented by improvements which have been tested in the
501F series or predicted by extensive modeling or full scale testing. The first
501G unit is expected to begin commercial operation later in 1999. The various
501G components and designs have been individually shop tested and computer
analyzed. Siemens Westinghouse's 501G is gaining commercial acceptance as
demonstrated by the fact that 17 of Siemens Westinghouse's 501Gs have been sold
to date in the United States.


      3.     The combustion turbines for our project are scheduled to become the
third and fourth 501Gs in operation. As a result, our project will benefit from
approximately 25 months of facility start-up, extensive testing and operating
experience of the first installation of 501Gs (McIntosh Project) and
approximately nine months of operating experience from the second installation
of 501Gs (Millenium Project). Because the 501G has no commercial operating
experience, the initial unit availability of the 501G may be lower in the early
years of operation than is the case with combustion turbine units currently in
operation that use mature technology. Lower initial unit availability has been
reflected in the base case and a sensitivity case has been included in the
projected operating results utilizing lower availability than that described in
the base case.


      4.    A sustained period of commercial operation at full load conditions
followed by an inspection of the combustion turbine is necessary to predict with
any certainty the types of start-up and operational problems, if any, that the
501G may encounter. However, our project will benefit from the start-up testing
and inspection programs implemented by Siemens Westinghouse at the McIntosh and
Millenium units. Siemens Westinghouse has also invested in, and has stated that
it will make available to our project, a complete set of risk parts for the
entire combustion turbine gas path. In addition, under the maintenance services
agreement, Siemens Westinghouse will provide combustion turbine spare parts to
our project. This full set of gas path risk parts to be made available by
Siemens Westinghouse and the maintenance services agreement long term spare
parts program will minimize the duration of any unscheduled combustion
turbine-related outages that require the replacement of parts by having the most
commonly replaced parts readily available. In addition, Siemens Westinghouse has
the resources and capabilities to resolve any problem that may arise with the
501Gs.


                                       12

<PAGE>


      5.    The steam turbine and electrical generator designs are acceptable
and in accordance with standard industry practice.

      6.    If designed and constructed in accordance with the construction
agreement and operated and maintained in accordance with the maintenance
services agreement and the operations agreement, our facility should be capable
of meeting the net output contract requirements specified in our projected
operating results.

      7.    The liquidated damages provisions of the construction agreement are
reasonable. The one-year warranty period is acceptable based on the commercial
terms of the construction agreement in conjunction with the one-year warranty in
the maintenance services agreement. These two agreements, although independent,
are complementary and afford our project a greater degree of protection than is
available from the construction agreement alone. Under both agreements, Siemens
Westinghouse is obligated to notify AES Ironwood, L.L.C. of any engineering or
design defects that may be manifested in any of Siemens Westinghouse's fleet of
501Gs. In addition, the risk of a component failure occurring after the one year
construction agreement warranty is mitigated because the projected operating
results indicate our project will have adequate revenues to insure the purchase
of components that can be reasonably assumed to require replacement. Component
failures associated with casualty events are generally covered by insurance
policies. The performance testing plan, as specified in the construction
agreement, is acceptable, customary and should adequately demonstrate our
project's performance.

      8.    Williams Energy possesses the organization and personnel to execute
its obligations under the power purchase agreement and is familiar with the
provision of fuel to, and purchase of electricity from, large electrical
generation facilities.

      9.    Williams Energy has executed specific agreements with Texas Eastern
Transmission Corporation to provide natural gas delivery services to AES
Ironwood, L.L.C. These agreements require Texas Eastern to construct, own and
operate an approximate three-mile pipeline from its mainline to our facility.
Stone & Webster has not, however, independently verified the design of the
natural gas pipeline which will interconnect our facility to the interstate gas
pipeline that will serve our facility nor its proposed construction schedule.

      10.   Our facility can feasibly be electrically integrated into the
Pennsylvania/New Jersey/Maryland (or "PJM") power pool market, and no known
transmission limitations will inhibit the feasible evacuation of our facility's
full net capacity both under summer and winter conditions.

      11.   Stone & Webster will independently verify the design of the make-up
water supply pipeline when it becomes available. The proposed pipeline
construction schedule appears reasonable and achievable. Stone & Webster does
not know of any reason why the City of Lebanon Authority should be unable to
perform its obligations under the effluent supply agreement.

      12.   AES Prescott, as an affiliate of The AES Corporation and with the
assistance of Siemens Westinghouse under the terms of the maintenance services
agreement, should be capable of operating and maintaining our facility in
accordance with standard industry practices.

      13.   The technical requirements described in the project contracts are
comprehensive, reasonable and achievable as well as consistent within and
between the various documents.

      14.   The Phase I environmental site assessments conducted by an
independent environmental consultant which indicated no significant
environmental issues were performed in accordance with standard industry
practice and their results appear reasonable.

      15.   A majority of our project's required permits have been acquired and
our project's permit acquisition plan for those permits not yet required is
reasonable.

      16.   AES Ironwood, L.L.C. has received a determination that our facility
is an exempt wholesale generator under the applicable rules of the Federal
Energy Regulatory Commission.

      17.   Assuming our facility is constructed, operated and maintained in
accordance with the terms of the construction agreement, the power purchase
agreement, the operations agreement and the maintenance services agreement, then
it is reasonable to assume that our facility will be able to operate in a manner
consistent with applicable permit limits for a period at least equal to the term
of the bonds.


                                       13

<PAGE>


      18.   The construction agreement price is competitive relative to similar
facilities and our project's proposed operating and maintenance expenses are
consistent with other comparable projects.

      19.   The technical assumptions utilized in the independent power
consultant's report by Hagler Bailly are reasonable.

      20.   Stone & Webster reviewed the technical and commercial assumptions
and the calculation methodology of our project's financial pro forma model. The
technical assumptions assumed in the projected operating results are reasonable
and are consistent with the project contracts. The financial pro forma model
fairly presents, in Stone & Webster's judgment, projected revenues and projected
expenses under the base case assumptions. Therefore, the projected operating
results are a reasonable forecast of AES Ironwood, L.L.C.'s financial results
under the base case assumptions.

      21.   The principal amount of the bonds, when combined with the equity
contributions and interest earned during the construction period, should be
sufficient to pay the costs of constructing our project and interest on the
bonds through the end of the construction period.


      22.   The projected revenues from the sale of capacity are more than
adequate to pay the annual operating and maintenance expenses, including
provisions for major maintenance, other operating expenses and debt service
based on Stone & Webster's studies and analyses of our project and the
assumptions described in the independent engineer's report. The average and
minimum debt service coverage ratios for the full term of the bonds are 2.30x
and 1.45x, respectively. The average and minimum debt service coverage ratios
during the term of the power purchase agreement are 1.46x and 1.45x,
respectively. The average and minimum debt service coverage ratios during the
post-power purchase agreement period for the debt are 5.81x and 5.77x,
respectively.


      23.   Assuming deficiencies of up to 6% for heat rate and 5% for capacity,
the average debt service coverage ratios, over the term of the bonds, after
payment of liquidated damages due to a failure to achieve heat rate and capacity
guarantees, are projected to remain approximately the same as the debt service
coverage ratios in the base case.

      The independent engineer's report should be read by all prospective
investors in its entirety. Stone & Webster is subject to the informational
requirements of the Exchange Act, and in accordance therewith, files reports,
proxy statements and other information with SEC. See "WHERE YOU CAN FIND MORE
INFORMATION."


                                       14

<PAGE>


               SUMMARY OF INDEPENDENT POWER CONSULTANT'S REPORT

      Hagler Bailly Consulting, Inc. has prepared the independent power
consultant's report, which we have attached as Annex C to this prospectus. We
have retained Hagler Bailly to forecast our facility's use and future electric
energy prices because it is an independent consulting firm which provides
various energy-related consulting services, including services related to the
marketing and fuel supply aspects of power projects. Neither we, nor any of our
affiliates, is affiliated with Hagler Bailly.

      Hagler Bailly's report includes, among other things,

      o  a forecast of our facility's utilization during the period after the
         end of the power purchase agreement term and

      o  a forecast of electric energy prices during the power purchase
         agreement term and electric energy and capacity prices during the
         period after the end of the power purchase agreement term.


      Subject to the information contained, and the assumptions and other
limitations stated, in Hagler Bailly's report, including the qualifications
described in the forward of the report, Hagler Bailly has expressed the
following opinions, among others:


      1.    Our facility's dispatch position on the supply curve will be highly
competitive and well below the highest priced baseload coal plant during the
period after the end of the power purchase agreement term, and during the term
of the power purchase agreement, due to our facility's high efficiency, low
production costs and the influence of demand growth in conjunction with unit
retirements.

      2.    Our facility is expected to have an average capacity factor of 90.7%
during the period after the end of the power purchase agreement term. The
addition of new, more efficient gas-fired power generation facilities in PJM
power pool market over time is not expected to affect our facility's dispatch.

      3.    Even using the price assumptions contained in the independent
engineer's report, our facility's average capacity factor remains significantly
high at 89.6% during the period after the end of the power purchase agreement
term.

      4.    During the term of the power purchase agreement, the economics of
our project are not sensitive to fuel prices because the costs of fuel are the
responsibility of Williams Energy under the power purchase agreement's fuel
tolling provisions.


      Hagler Bailly's report, including the qualifications described in the
forward of the report, should be read by all bondholders in its entirety. We do
not intend to update the facility utilization and energy price forecast, except
to the extent required under the indenture. See "SUMMARY OF PRINCIPAL FINANCING
DOCUMENTS--Indenture--Affirmative Covenants." Hagler Bailly is subject to the
informational requirements of the Exchange Act, and in accordance therewith,
files reports, proxy statements and other information with the SEC. See "WHERE
YOU CAN FIND MORE INFORMATION."



                                       15

<PAGE>


                   SUMMARY OF SIGNIFICANT PROJECT CONTRACTS

                Power Purchase Agreement and Related Guaranty


      Under the terms of the power purchase agreement, we will, for a term of 20
years beginning on the commercial operation date of our facility, which is the
date initial startup testing at the facility has been successfully completed and
all necessary approvals, permits, and authorizations have been obtained, sell
all of our facility's net electrical output and provide fuel conversion and
ancillary services to Williams Energy. Williams Energy is obligated to pay us
for our facility's net capacity, which payments are expected to be adequate to
cover our debt service and our fixed operation and maintenance costs and, at the
same time, provide us a return on equity. Net capacity is the maximum amount of
electricity generated by our facility minus the electricity used at our
facility. Williams Energy will be obligated to pay us whether or not it requires
our facility to generate energy and even if it is unable to take any energy, so
long as our facility is available for operation. Williams Energy is also
obligated to supply us with all of the fuel necessary to provide net capacity,
ancillary services and fuel conversion services to it. Fuel conversion services
consist of the combustion of natural gas and fuel oil in order to generate
electric energy. Ancillary services consist of services necessary to support the
transmission of capacity and energy.



      The Williams Companies, Inc. will provide us with a guaranty of Williams
Energy's payment obligations to us under the power purchase agreement and to pay
damages if Williams Energy fails to pay us. The Williams Companies, Inc.'s
payment obligations under the guaranty are capped at an amount equal to 125% of
the sum of the principal amount of the new bonds plus the maximum debt service
reserve account required balance. The Williams Companies, Inc. files quarterly
and annual audited reports with the Commission under the 1934 Exchange Act,
which are publicly available; Williams Energy does not issue separate audited
financial statements. As security for our obligations under the power purchase
agreement, we are required to provide to Williams Energy either a guaranty from
The AES Corporation or a letter of credit in the amount of $30 million. To
satisfy our obligation, we have provided to Williams Energy a letter of credit
which will terminate when our facility begins commercial operation. See "SUMMARY
OF PRINCIPAL FINANCING DOCUMENTS--Construction Period Letter of Credit and
Reimbursement Agreement."


                 Construction Agreement and Related Guaranty


      Under a construction agreement, Siemens Westinghouse will design,
engineer, procure and construct our facility so that it will be complete and
ready to operate. Siemens Westinghouse is wholly owned by Siemens Corporation
which is, in turn, wholly owned by Siemens A.G. Siemens Westinghouse's
obligations under the construction agreement will be guaranteed by Siemens
Corporation. The contract price payable to Siemens Westinghouse is $214,950,000,
which is to be paid in installments in accordance with the payment and milestone
schedule included in the construction agreement. The contract price may be
adjusted as described in the construction agreement, including as a result of
unexpected or uncontrollable events or modifications to the scope of work to be
provided by Siemens Westinghouse. Siemens Westinghouse has guaranteed that our
facility will be mechanically complete and specific performance requirements
will be satisfied so that our facility will be commercially operational by the
date which is approximately 23-1/2 months after we have given it full notice to
proceed, which we did on June 8, 1999. If our facility does not satisfy the
applicable completion requirements by the date guaranteed by Siemens
Westinghouse and the failure to satisfy the applicable completion requirements
is not excused in accordance with the terms of the construction agreement,
Siemens Westinghouse will be obligated to pay us delay liquidated damages in the
amounts specified in the construction agreement. Siemens Westinghouse has
guaranteed specific availability levels for our facility and if those levels are
not demonstrated during a 45-day period before final acceptance of our facility
by us, we may withhold specified payments to Siemens Westinghouse. Siemens
Westinghouse has also guaranteed that during performance testing, our facility
will generate a specified amount of electrical energy and meet specified thermal
efficiency rates when using natural gas and fuel oil. If Siemens Westinghouse
cannot meet these testing requirements it will be required to pay us performance
liquidated damages in the amounts specified in the construction agreement. The
total liability of Siemens Westinghouse for delays in completion, together with
its liability for any performance shortfalls, is limited in the aggregate to an
amount equal to 45% of the contract price. The construction agreement also
contains a sub-limit on Siemens Westinghouse's liability for delays in
completion of our facility in an amount equal to 20% of the contract price. The
total aggregate cap on liability of Siemens Westinghouse under the construction
agreement, including liquidated damages, but excluding specified indemnity
obligations, is limited to an amount not to exceed the contract price, as
adjusted.



                                       16

<PAGE>


                                  RISK FACTORS

      Before tendering your old bonds for new bonds or investing in the new
bonds, you should be aware that there are various risks involved in your
investment. We have discussed below the material risks that you should consider
in making your investment decision. You should consider carefully these risk
factors, together with all of the other information included in this prospectus.

If the commercial operations of our facility are significantly delayed, or are
otherwise unable to generate sufficient cash flow, we may not be able to pay our
operating expenses or service the bonds.

      Construction of our facility currently is scheduled to be completed within
23-1/2 months from the date Siemens Westinghouse receives from us a full notice
to proceed under the construction agreement. We gave full notice on June 8,
1999. We will not receive any material revenues unless and until our facility
achieves commercial operation. Once our facility commences operation, principal
and interest on the bonds will be payable principally from revenues received by
us under the power purchase agreement. Operation and maintenance expenses of our
facility generally are payable before payment of debt service with respect to
the bonds. No representation or assurance can be made that our facility will be
successfully constructed or that, if our facility is successfully constructed,
revenues will be sufficient to pay the operation and maintenance expenses of our
facility and principal of and interest on the bonds. We have no assets other
than our facility, the project contracts and other assets and contract rights
related to our facility. Once our equity contribution is made to fund project
construction costs, our debt to capitalization ratio will be .8638 to 1.

      Until our facility commences operation, debt service on the bonds will be
payable solely from funds on deposit in the construction account, which deposit
was made with a portion of the net proceeds from the issuance of the old bonds,
any investment earnings, specific contingency and other funds held under the
collateral agency agreement and the indenture, insurance proceeds, if any, and
liquidated damages payable under the construction agreement. The construction
interest account under the indenture will contain an amount sufficient to pay
interest on the bonds only through 45 days following the guaranteed provisional
acceptance date under the construction agreement, without giving effect to any
extensions. Thus, if there is a prolonged delay beyond the guaranteed
provisional acceptance date in our facility's attaining commercial operation, we
cannot assure that sufficient sources of funds will be available to make
payments of principal of, premium, if any, and interest on the bonds.

      During the term of the power purchase agreement, our ability to make
payments of principal of, premium, if any, and interest on the bonds will be
substantially a function of (1) the ability of our facility to operate at levels
which provide sufficient revenues from sales to Williams Energy after the
payment of all operation and maintenance expenses and specific other expenses
paid prior to debt service and (2) the ability of Williams Energy to make
required payments under the power purchase agreement. Fixed payments under the
power purchase agreement may be reduced significantly or eliminated during
periods when our facility's availability fails to meet required levels under the
power purchase agreement. With specific exceptions, fixed payments will not be
made by Williams Energy during unexpected or uncontrollable events which prevent
our facility from operating. Following the expiration of the term of the power
purchase agreement, our ability to make payments of principal of, premium, if
any, and interest on the bonds will be substantially a function of:


      o  our ability to find purchasers of electric generating capacity and
         energy from our facility;
      o  the availability of adequate market prices for capacity, energy and
         ancillary services;
      o  our ability to procure sufficient quantities of fuel at competitive
         prices; and
      o  the ability of our facility to operate at levels which provide
         sufficient revenues from the sale of electric generating capacity,
         energy and ancillary services to power purchasers after the payment of
         all operation and maintenance expenses and certain other expenses paid
         prior to service.


In the event that we exhaust the proceeds from the bonds, the equity
contribution and the liquidation of the collateral, the holders of the bonds
will have limited or no recourse in the event of a default.


      Because we are a special-purpose company, our ability to make payments of
principal of, any premium, and interest on the bonds will be entirely dependent
on the performance of our obligations under the project contracts and financing
documents. Our obligations under the financing documents will be obligations
solely of ours, secured solely by the collateral. If we default in our
obligations under the financing documents, we cannot assure that realization on
the collateral would provide sufficient funds to repay all amounts due on the
bonds.



                                       17

<PAGE>


      None of the owners of the ownership interests in our company nor any
affiliate, incorporator, stockholder, partner, officer, director or employee of
ours, will guarantee the payment of the bonds or has any obligation with respect
to the payment of the bonds. The collateral includes a pledge of AES Ironwood,
Inc.'s ownership interests in AES Ironwood, L.L.C., and under the equity
subscription agreement, AES Ironwood, Inc. has agreed to contribute in the
aggregate up to $50,149,285 to us to fund project costs. However, neither AES
Ironwood, Inc. nor any of its affiliates has any obligation to contribute sums
in excess of the amount required to be advanced under the equity subscription
agreement. If the proceeds of the bonds and the equity contribution required
under the equity subscription agreement are insufficient to fund the successful
development, construction, start-up and testing of our facility, we may not have
other sources of funds available to complete our facility.

      The bonds will be secured by liens on substantially all of our assets
related to our facility, including all of the project contracts. If a default
occurs under the indenture or other financing documents, we cannot assure that
an exercise of remedies, including foreclosing on the assets in a judicial
proceeding, would provide sufficient funds to repay all amounts due on the
bonds. As result of specific provisions of the documents under which we obtained
our rights in and to the facility site, it is unlikely that the real estate
comprising a portion of the collateral could be used for any purpose other than
an electric generating facility.


If the parties that we depend on breach their obligations to us, our cash flow
and ability to service the bonds will be impaired.



      During the term of the power purchase agreement, we will be dependent on
Williams Energy for revenues from sales of capacity, ancillary services and
energy from our facility and on Williams Energy and its affiliates for fuel
supply and transportation. We are dependent on Metropolitan Edison for
connection of our facility to the electric transmission grid, as well as on
other third-party sources of goods and services which constitute the principal
inputs to our facility's operations. Any material breach by any of these parties
of their obligations under the project contracts will adversely affect our cash
flows and will impair our ability to make payments of principal of and interest
on the bonds.


      The other parties to the project contracts have the right to terminate
and/or withhold payments or performance under the contracts if specific events
occur. If a project contract were to be terminated due to nonperformance by us
or by the other party to the contract, our ability to enter into a substitute
agreement having substantially equivalent terms and conditions is uncertain.

If Williams Energy's financial condition deteriorates or it breaches its
obligations to us and cannot be adequately replaced, we may not be able to
service the bonds.


      Williams Energy currently is our sole customer for purchases of capacity,
ancillary services and energy. Williams Energy's payments under the power
purchase agreement are expected to provide all of our revenues during the term
of the power purchase agreement. It is uncertain whether we would be able to
find another purchaser on similar terms for our facility's output if Williams
Energy were not performing under the power purchase agreement. If another
purchaser or purchasers could be found, we cannot assure that the price paid by
that purchaser or purchasers would be sufficient to enable us to make payments
in respect of the bonds. Any material failure by Williams Energy to make
capacity and fuel conversion payments under the power purchase agreement will
therefore have a material adverse effect on revenues and our ability to make
payments in respect of the bonds.


      The ability of Williams Energy to meet its obligations under the power
purchase agreement will be dependent on Williams Energy's financial condition
generally, and Williams Energy's financial condition will in part be dependent
upon its ability to sell our facility's capacity and electric energy at adequate
prices.


      As we have described in this prospectus, The Williams Companies, Inc. will
provide to us a guaranty of Williams Energy's obligations under the power
purchase agreement to make fixed payments and to pay damages if Williams Energy
fails to make the fixed payments. The Williams Companies, Inc.'s obligations
under that guaranty are capped at an amount equal to 125% of the sum of (x) the
principal amount of the bonds plus (y) the maximum debt service reserve account
required balance.


If we encounter significant construction delays, any liquidated damages,
contingency funds, or insurance proceeds may be insufficient to service the
bonds.


      As with any major construction undertaking, completion of our facility
could be delayed or prevented, or cost overruns could be incurred, as a result
of numerous factors, including shortages of material, labor disputes, weather
interferences, difficulties in obtaining necessary permits or in meeting permit
conditions or unforeseen engineering,


                                       18

<PAGE>

environmental or geological problems. We cannot assure that any available
liquidated damages or contingency funds or the proceeds of any insurance and
warranties would be sufficient to pay for any significant cost overruns or
redeem a sufficient principal amount of the bonds so that projected debt service
coverage ratios can be achieved or maintained. In particular, we are required to
pay principal of any premium, and interest on the bonds without regard to any
unexpected or uncontrollable events under the construction agreement.



      If as a result of unexpected or uncontrollable events specified in the
construction agreement or specified acts or omissions by us, completion of our
facility is delayed or prevented, or our facility cannot achieve operation in
accordance with design specifications and performance guarantees, Siemens
Westinghouse will not be obligated to pay liquidated damages. Under these
circumstances, no proceeds of insurance may be available to us or any proceeds
that are available may not be sufficient to pay our debt service or increased
costs. Generally, Siemens Westinghouse will not be obligated to pay liquidated
damages for events or circumstances that adversely affect its ability to perform
its obligations under the construction agreement to the extent that the events
or circumstances are beyond its reasonable control and are not caused by its or
its subcontractors' negligence or lack of due diligence and could not have been
avoided by the use of its reasonable efforts. In addition, the date for
achievement of provisional acceptance and the guaranteed provisional acceptance
under the construction agreement could be subject to adjustment as a result of
unexpected or uncontrollable events.


      The power purchase agreement requires that the commercial operation date
occur by no later than June 30, 2001, which may be extended under the terms of
the power purchase agreement to no later than December 31, 2002. Our project
capital budget includes adequate funds for the payment of amounts that may be
required to extend the commercial operation under the power purchase agreement.
If the commercial operation date fails to occur by that date, as so extended,
Williams Energy may terminate the power purchase agreement.

      Under the construction agreement, we are responsible for a number of
matters in connection with the construction, completion and start-up of our
facility. While we believe that we have made adequate arrangements to assure
timely performance of our responsibilities, we are relying on other parties to
enable us to perform our responsibilities under the construction agreement and
we cannot be certain that the other parties will meet their obligations under
their contracts. See "SUMMARY OF PRINCIPAL PROJECT CONTRACTS--Construction
Agreement."

Because the facility has not yet been constructed and our company has no
operating history, various unexpected events may increase our expenses or reduce
our revenues and impair our ability to service the bonds.


      Because our facility has not yet been constructed, it has no operating
history. Operation of our facility could be affected by many factors, including
start-up problems, the breakdown or failure of equipment or processes, the
performance of our facility below expected levels of output or efficiency,
failure to operate at design specifications, labor disputes, changes in law,
failure to obtain necessary permits or to meet permit conditions, government
exercise of eminent domain power or similar events and catastrophic events
including fires, explosions, earthquakes and droughts. The occurrence of these
events could significantly reduce or eliminate revenues or significantly
increase the expenses of our facility, thereby jeopardizing our ability to make
payments on the bonds. In addition, the liability of AES Prescott for failure to
perform under the operations agreement is subject to specific limitations and
AES Prescott is not required to post a performance bond. The proceeds of any
available insurance and limited warranties may not be adequate to cover our lost
revenues or increased costs. See "SUMMARY OF PRINCIPAL PROJECT CONTRACTS--Power
Purchase Agreement" and "--Operations Agreement."


Because the combustion turbines to be used in our facility have no significant
operating experience, our project may incur problems relating to start-up,
commissioning and performance.

      The Siemens Westinghouse 501G combustion turbines to be used in our
facility are the manufacturer's latest development in combustion turbines whose
fundamental design basis is based upon the Siemens Westinghouse 501 series.
However, the 501G combustion turbine currently has no significant operating
experience and may have unit availability lower than combustion turbine units
using mature technologies. Thus, we cannot assure that our project will not
incur problems relating to start-up, commissioning and performance that could
jeopardize the achievement of Provisional Acceptance, timely commencement of
commercial operations of our facility or the performance of our facility during
its commercial operation. For a discussion of the 501G technology and related
risks, see "ANNEX B: INDEPENDENT ENGINEER'S REPORT--Facility Design."


                                       19

<PAGE>


Following the expiration of the power purchase agreement, our facility is
expected to become a merchant facility and we cannot assure that we will be able
to find adequate purchasers or otherwise compete effectively in the merchant
market.

      At the end of the term of the power purchase agreement, at which time
27.1% of the bonds are expected to remain outstanding, our facility is expected
to become a merchant facility, i.e., an electric generation facility with no
dedicated long-term power purchase agreement, and Williams Energy's obligation
to provide fuel will cease. If the power purchase agreement is terminated prior
to its stated term as a result of an event of default or otherwise, our facility
could enter a merchant phase sooner than the anticipated termination date of the
power purchase agreement. Given the uncertainty regarding the performance of our
facility, future environmental regulation, competition from other generating
facilities, including possibly some owned by The AES Corporation and its
affiliates, fuel prices and other market conditions that may prevail in the
future in the PJM power pool market, we cannot assure that we will be able to
find purchasers or otherwise compete effectively in the merchant market.


      Also, there are current legal and regulatory limitations on our ability to
operate our facility on a merchant basis. Our rate schedule when filed with FERC
will be limited to sales to Williams Energy. Under current law, before we could
engage in sales to any other entities, we will be required to seek additional
market-based rate authority from FERC. Although we do not currently anticipate
that we would encounter material difficulty in obtaining this additional
market-based rate authority, we cannot assure that FERC will grant this
authority. In addition, our status as an exempt wholesale generator under
federal law prohibits us from making retail sales of electricity in the United
States. We currently anticipate that electric energy generated by our facility
will be sold primarily in the wholesale market both during the term of the power
purchase agreement and after our facility becomes a merchant plant.
Nevertheless, if we were to desire to participate directly in the retail
electric market when that market develops, we would be precluded from doing so
absent a change in federal law. Under current federal law, however, we would not
be precluded from making sales to a power marketer, including an affiliate,
which could in turn make retail sales.


Compliance with environmental and other regulatory matters could cause
significant delays and expenses that may impair our ability to service the
bonds.

General


      We are subject to a number of statutory and regulatory standards and
required approvals relating to energy, labor and environmental laws. Although
the necessary environmental permits for the commencement of construction of our
facility have been obtained, we are required to comply with the terms of our
environmental permits and to obtain other permits for the construction and
operation of our facility. Several of our permits have not yet been obtained,
and some cannot be obtained until our facility has commenced operation. Under
specific circumstances, delay in receipt of or failure to obtain the permits
could delay completion of the construction of our facility or prevent the
operation of our facility.



      Some permits that have been obtained by us in connection with our facility
will require amendment prior to commercial operation of our facility and others
will require renewal or reissuance during the life of our facility. While we
have no reason to believe that the permits cannot be amended or will not be
renewed or reissued, our inability to amend, renew or obtain reissuance of these
permits in the future could cause the suspension of construction or operation of
our facility.


      The permits that have been obtained and that will be obtained contain
ongoing requirements. Failure to satisfy and maintain any permit conditions or
other applicable requirements could delay or prevent completion of the
construction of our facility, prevent the operation of our facility and/or
result in additional costs. If our facility attains commercial operation, we
cannot assure that our facility will operate within the limits established by
the permits or approvals. See "OUR BUSINESS--Permits and Regulatory Approvals"
and "ANNEX B: INDEPENDENT ENGINEER'S REPORT--Environmental and Permitting."

Energy Regulatory Matters

      We believe that we have obtained all material energy-related federal,
state and local approvals required as of the date of this prospectus to
construct and operate our facility. Although not currently required, additional
regulatory approvals, including renewals, extensions, transfers, assignments,
reissuances or similar actions, may be required in the future due to a change in
laws and regulations, a change in our power purchasers or for other reasons. We
cannot assure that we will be able to (1) obtain all required regulatory
approvals that we do not yet have or that we may require in the future, (2)
obtain any necessary modifications to existing regulatory approvals or (3)
maintain required regulatory


                                       20

<PAGE>


approvals. Delay in obtaining or failure to obtain and maintain in full force
and effect any regulatory approvals, or amendments, or delay or failure to
satisfy any conditions or applicable requirements, could prevent operation of
our facility or sales to third parties, or could result in additional costs to
us. Our business also could be materially and adversely affected as a result of
statutory or regulatory changes or judicial or administrative interpretations of
existing laws and regulations that impose more comprehensive or stringent
requirements on us.

The insurance we have obtained may be inadequate in the event of a total loss or
taking of our facility, and we cannot assure that the insurance proceeds we
receive will be sufficient to satisfy all of our indebtedness.


      We are obligated under the financing documents and other project contracts
to obtain and keep in force comprehensive insurance with respect to our
facility, including general liability insurance and machinery coverage, business
interruption insurance, delay in start-up insurance and all-risk property damage
insurance, including, among other things, damage caused by fire, floods or
hurricanes. We cannot assure that the insurance coverage will be available in
the future at commercially reasonable costs or that the amounts for which we are
insured or amounts which we receive under insurance coverage will cover all
losses. If there is a total loss or taking of our facility, we cannot assure
that the insurance proceeds we receive will be sufficient to satisfy all our
indebtedness, including the redemption of the bonds as required under the
indenture. See "SUMMARY OF PRINCIPAL FINANCING DOCUMENTS--Indenture."



The incurrence of additional indebtedness may impair our ability to service the
bonds.


      We may issue additional bonds and we may incur additional indebtedness at
any time or from time to time, in accordance with the terms of the indenture.
Any additional bonds will, and any additional senior debt, may rank equally with
all our senior secured indebtedness. The issuance of additional bonds, other
than for refinancing purposes, or additional senior debt would create additional
claims against the collateral under the security documents and could result in a
reduction in debt service coverage ratios and cash available to make payments of
principal of and interest on the bonds. See "SUMMARY OF PRINCIPAL FINANCING
DOCUMENTS--Indenture."


      Subject to limitations described in the indenture, we are permitted to
incur subordinated debt, which may be secured by a junior lien on the
collateral, for purposes allowed under the indenture. Although subordinated debt
would be subject to limitations contained in the collateral agency agreement
concerning the ability of the holders of subordinated debt to declare defaults,
exercise remedies or institute specified legal proceedings, the incurrence of
subordinated debt would increase our leverage and the total debt service payable
by us. In addition, the holders of subordinated debt may be our secured
creditors and therefore have the rights available to secured creditors under
federal and state law.


Drawings under letters of credit may increase payments of debt service on senior
debt.

      Drawings under the debt service reserve letter of credit will be converted
into debt service reserve letter of credit loans which will mature five years
after the date of the loans. Interest on debt service reserve letter of credit
loans is payable at the same level in the flow of funds as payments of interest
on other senior debt, including the bonds. Principal on debt service reserve
letter of credit loans is generally payable out of available cash flow after the
payment of principal on the bonds. In specific circumstances, however, principal
payments on any drawings under the debt service reserve letter of credit will be
made at the same level in the flow of funds as payments of principal on the
bonds.


      If the construction period letter of credit is issued and our facility is
not completed within the time period specified in the power purchase agreement,
as may be extended, Williams Energy may draw on the construction period letter
of credit. Drawings under the construction period letter of credit will be
converted into construction period letter of credit loans under any construction
period letter of credit reimbursement agreement that will mature in 10 years
from the conversion. Principal of and interest on any construction period letter
of credit loans under the construction period letter of credit reimbursement
agreement will be made at the same respective levels in the flow of funds as
payments of principal and of interest on the bonds.



      Thus, drawings on the construction period letter of credit and, in
specific circumstances, drawings under the debt service reserve letter of
credit, will increase payments of debt service on senior debt. We cannot assure
that our revenues from sales of capacity and fuel conversion services under the
power purchase agreement or otherwise would be sufficient to cover the increases
in debt service payments. The lenders under the debt service reserve letter of
credit reimbursement agreement and the construction period letter of credit
reimbursement agreement will rank equally with the bonds by a lien on and
security interest in the collateral.



                                       21

<PAGE>


The collateral agency agreement contains provisions that may limit the remedies
that could be exercised in respect of the event of default, other than a
bankruptcy event of default, unless and until the required senior parties have
directed the collateral agent to do so.


      We have entered into a collateral agency agreement with our senior
creditors designating the collateral agent as the agent for each of the senior
creditors. The collateral agency agreement requires the affirmative vote of
senior creditors holding at least a majority of the outstanding combined
exposure to direct specific actions of the collateral agent, including the
exercise of remedies following a trigger event. Because the affirmative vote of
these required senior creditors is required before the collateral agent can
exercise remedies under the collateral agency agreement and the other security
documents following most events of default, if an event of default under the
indenture were to occur, no remedies could be exercised in respect of the event
of default, other than a bankruptcy event of default, unless and until the
required senior creditors have directed the collateral agent to do so. If the
holders of the bonds do not constitute holders of at least a majority of the
outstanding combined exposure, the trustee and the holders of the bonds may not
be able to direct the collateral agent to exercise remedies in respect of an
event of default under the indenture without the affirmative vote of other
senior creditors. In addition, under the terms of the other financing documents,
we may not terminate, amend or otherwise modify any provision of the indenture,
any other security document or any subordinated loan agreement, if the
termination, amendment or modification could, in the reasonable opinion of the
creditors who are parties to the other financing documents, reasonably be
expected to have a material adverse effect on the rights and benefits of the
creditors. See "SUMMARY OF PRINCIPAL FINANCING DOCUMENTS--Collateral Agency
Agreement."


Projections and the assumptions underlying those projections used in the
projections are inherently subject to significant uncertainties and actual
results may differ, perhaps materially, from those projected and should not be
unduly relied upon.

      The financing of our facility has been structured on the basis of
assumptions and projections with respect to our facility's potential revenue
generating capacity and associated costs over the term of the bonds. Stone &
Webster, as independent engineer, has evaluated the technical, environmental and
economic aspects of our project. Stone & Webster's report contains a discussion
of the many assumptions utilized in preparing these projections. Investors
should review Stone & Webster's report in its entirety.

      Projections of future operations and the economic results of those
operations included in Stone & Webster's report have been prepared by us and
reviewed by Stone & Webster on the basis of present knowledge and assumptions
which we and Stone & Webster believe to be reasonable. Our independent auditors
have not examined, reviewed or compiled the projections and, accordingly, do not
express an opinion or any other form of assurance with respect to them. After
the issuance of the bonds, neither we nor Stone & Webster will provide the
holders of the bonds with revised projections or any report of the differences
between the projections and actual operating results later achieved by our
project.


      For purposes of preparing the projections, assumptions were made, of
necessity, with respect to completion of construction, availability and
performance of our facility, dispatch levels, capital expenditures, operation
and maintenance expenditures, the revenues that we will receive for capacity and
electric energy, the availability of fuel, our tax treatment, general business
and economic conditions and several other material contingencies and other
matters that are not within our control and the outcome of which cannot be
predicted by us, Stone & Webster, or any other person with any certainty of
accuracy. These assumptions and the other assumptions used in the projections
are inherently subject to significant uncertainties and actual results will
differ, perhaps materially, from those projected. Accordingly, the projections
do not necessarily indicate current values or future performance and neither we,
Stone & Webster, nor any other person assumes any responsibility for their
accuracy. Therefore, no representation is made or intended, and none should be
inferred with respect to the likely existence of any particular future set of
facts or circumstances. If actual results are materially less favorable than
those shown or if the assumptions used in formulating the projections prove to
be incorrect, our ability to make payments of principal of, premium, if any, and
interest on the bonds may be adversely affected.


Cautionary note regarding forward-looking statements.


      This prospectus includes forward-looking statements. We have based these
forward-looking statements on our current expectations and projections about
future events based upon our knowledge of facts as of the date of this
prospectus and our assumptions about future events. These forward-looking
statements are subject to various risks and


                                       22

<PAGE>

uncertainties that may be outside of our control, including the factors
discussed in the "RISK FACTORS" section beginning on page 17.




We use words like "anticipate," "estimate," "project," "plan," "expect" and
similar expressions to help identify forward-looking statements in this
prospectus.


      In light of these uncertainties and assumptions, the actual events or
results may be very different from those expressed or implied in the
forward-looking statements in this prospectus or may not occur. We have no
obligation to publicly update or revise any forward-looking statement, whether
as a result of new information, future events or otherwise.



                                       23

<PAGE>



                               USE OF PROCEEDS


      We will not receive any cash proceeds from the issuance of the new bonds.
In consideration for issuing the new bonds, we will receive in exchange a like
principal amount of old bonds. The old bonds surrendered in exchange for the new
bonds will be retired and canceled and cannot be reissued. Accordingly, issuance
of the new bonds will not change our capitalization. We intend to use the net
proceeds from the sale of the old bonds, together with an approximately $50
million equity contribution, approximately as follows:




                                                  (thousands)



      Construction Costs.......................    $238,000
      Other Hard (Construction-Related) Costs..     $13,944
      Legal, Accounting, Consulting and Other
        Development and Construction Costs.....     $21,345
      Initial Working Capital..................      $1,800
      Net Interest During Construction.........     $51,141
      Start-up and Other Soft Costs............     $15,419
      Company's Contingency....................     $17,000


            TOTAL USES OF FUNDS................    $358,649
                                                    =======

      As of January 31, 2000:

      o the following line items have been paid in their entirety:

        - Legal, Accounting, Consulting and Other Development and Construction
            Costs;

      o the following line items have been partially paid as follows (in
thousands):

        - Construction Costs - $210,700,

        - Other Hard (Construction-Related) Costs - $2,000,

        - Net Interest During Construction - $16,400 and

        - Start-up and Other Soft Costs - $8,600;

      o the following line items have not been used:

        - Initial Working Capital and

        - Company's Contingency.




                                       24

<PAGE>


                                 CAPITALIZATION


      The following table sets forth our capitalization as of December 31, 1999.
The following information should be read in conjunction with the consolidated
financial statements and related notes thereto and the other financial
information contained elsewhere in this prospectus. See "SELECTED FINANCIAL
DATA" and "MANAGEMENT'S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND
RESULTS OF OPERATIONS."


      Long-Term Debt:


                                                    (thousands)



            Long Term Bonds....................      $308,500
                                                      =======



      Funds available from the issuance of the old bonds will be drawn from time
to time to fund construction of our facility. Once the available old bond
proceeds have been used, AES Ironwood, Inc. agrees to fund up to approximately
$50.1 million of project costs to be contributed to us pursuant to the equity
subscription agreement.



             CALCULATION OF EARNINGS TO FIXED CHARGES DEFICIENCY



       EARNINGS                                  December 31, 1999
                                                    (thousands)



             Pretax Income......................     $(2,641)
             Fixed Charges......................      14,237
             Capitalized Interest...............      (8,438)
                                                     --------
             Net Total..........................     $ 3,158
                                                     ========



       FIXED CHARGES
             Interest Expense...................     $ 5,755
             Capitalized Interest...............       8,438
             Other..............................          44
                                                     --------
             Total..............................     $14,237
                                                     ========




     The dollar amount of the deficiency of earnings to fixed charges is:
($11,079) (in thousands).



                                       25

<PAGE>


                               THE EXCHANGE OFFER


Purpose and Effect of the Exchange Offer

      In connection with the issuance of the old bonds, we entered into a
registration rights agreement. Under the registration rights agreement, we
agreed to:

      o  prepare and file a registration statement with the SEC for an exchange
         of the new bonds for the old bonds under the Securities Act;

      o  use our reasonable efforts to cause the registration statement to
         become effective within 180 days following the original issuance of the
         old bonds;

      o  keep the exchange offer open for acceptance for a period of not less
         than 30 days, or longer, if required by law, after the date the
         registration statement is declared effective by the SEC; and

      o  accept for exchange all old bonds validly tendered by and not withdrawn
         in accordance with the terms of the exchange offer registration
         statement.

      As soon as practicable after the exchange offer registration statement
becomes effective, we will offer the holders of old bonds who are not prohibited
by any law or policy of the SEC from participating in this exchange offer the
opportunity to exchange their old bonds for new bonds registered under the
Securities Act that are substantially identical to the old bonds, except that
the new bonds will not contain terms with respect to transfer restrictions,
registration rights and additional interest.

      Under limited circumstances, we will use our reasonable best efforts to
cause the SEC to declare effective a shelf registration statement with respect
to the resale of the old bonds and keep the statement effective for up to two
years after the effective date of the shelf registration statement. These
circumstances include:

      o  if any changes in law or their interpretations by the staff of the SEC
         do not permit us to effect the exchange offer as contemplated by the
         registration rights agreement;

      o  if the exchange offer is not consummated within 220 days after June 25,
         1999, or by January 31, 2000;

      o  if any of Lehman Brothers, Morgan Stanley Dean Witter or Dresdner
         Kleinwort Benson North America, as initial purchasers of the old bonds,
         so requests with respect to old bonds held by it following consummation
         of the exchange offer; and

      o  if any holder of the old bonds notifies us that it is not permitted to
         participate in the exchange offer or has participated in the exchange
         offer and has received new bonds that are not freely tradeable.


      Interest in addition to the interest otherwise due will accrue on the
bonds at a rate of 0.5% per annum if the exchange offer is not consummated or
the shelf registration statement is not declared effective by the SEC on or
prior to 220 days after June 25, 1999, or by January 31, 2000. Any additional
interest will accrue on the old bonds from and including the date on which the
circumstances giving rise to the additional interest will occur to but excluding
the date on which all the circumstances have been cured. Any additional interest
will be payable on the bond payment dates.


      To exchange your old bonds for transferable new bonds in the exchange
offer, you will be required to make the following representations:

      o  any new bonds that you receive will be acquired in the ordinary course
         of your business;

      o  you have no arrangement or understanding with any person or entity to
         participate in the distribution of the new bonds;

      o  you are not our "affiliate," as defined in Rule 405 of the Securities
         Act;

      o  you are not a broker-dealer, and you are not engaged in and do not
         intend to engage in the distribution of the new bonds; and


      o  if you are a broker-dealer that will receive new bonds for your own
         account in exchange for old bonds, you acquired those bonds as a result
         of market-making activities or other trading activities and you will
         deliver a prospectus, as required by law, in connection with any resale
         of the new bonds.



                                       26

<PAGE>



      In addition, if we are required to file a shelf registration statement, we
may require you to deliver information to be used in connection with the shelf
registration statement in order to have your bonds included in the shelf
registration statement. A holder who sells old bonds under the shelf
registration statement generally will be required to be named as a selling
security holder in the related prospectus and to deliver a prospectus to
purchasers. The holder will also be subject to the civil liability provisions
under the Securities Act in connection with the sale of old bonds under the
shelf registration statement and will be bound by the provisions of the
registration rights agreement that are applicable to the holder, including
indemnification obligations.


      The description of the registration rights agreement contained in this
section is a summary only. For more information, you may review the provisions
of the registration rights agreement that we filed with the SEC as an exhibit to
the registration statement of which this prospectus is a part.

Resale of New Bonds

      Based on the interpretations of the SEC staff in no-action letters issued
to third parties, we believe that new bonds issued under the exchange offer may
be offered for resale, resold and otherwise transferred by you as the holder of
the new bonds without compliance with the registration and prospectus delivery
provisions of the Securities Act, if:

      o  you are not our "affiliate" within the meaning of Rule 405 under the
         Securities Act;


      o  the new bonds are acquired in the ordinary course of your business; and



      o  you do not intend to participate in any distribution of the new bonds.



      Broker-dealers that acquired old bonds directly from us may not rely on
the interpretations of the SEC described above. Accordingly, in order to sell
their bonds, broker-dealers that acquired old bonds directly from us must comply
with the registration and prospectus delivery requirements, including being
named as a selling security holder in any resale prospectus. If you are a
broker-dealer that will receive new bonds for your own account in exchange for
old bonds, you acquired those bonds as a result of market-making activities or
other trading activities and you will deliver a prospectus, as required by law,
in connection with any resale of the new bonds. Only broker-dealers that
acquired old bonds as a result of market-making or other trading activities may
participate in the exchange offer.


      If you do not satisfy the above conditions, you


      o  cannot rely on the interpretations by the SEC staff; and


      o  must comply with the registration and prospectus delivery requirements
         of the Securities Act in connection with a secondary resale
         transaction.


      We do not intend to seek our own no-action letter, and there can be no
assurance that the SEC staff would make a similar determination with respect to
the new bonds as it has in prior no-action letters issued to other parties. In
November 1998, the SEC proposed certain changes to the regulatory structure for
offerings registered under the Securities Act. The SEC has stated that, if these
proposals are adopted, the SEC staff will repeal its interpretations described
in prior no-action letters. We cannot predict whether these proposals will be
adopted or, if they are adopted, when and in what form they will be adopted.



      If an exemption from registration is not available, any bondholder
intending to distribute new bonds should be covered by an effective registration
statement under the Securities Act containing the selling bondholder's
information required by Item 507 of Regulation S-K under the Securities Act.
This prospectus may be used for an offer to resell, resale or other retransfer
of new bonds only as specifically described in this prospectus. Please read the
section captioned "PLAN OF DISTRIBUTION" for more details regarding the transfer
of new bonds.


Terms of the Exchange Offer

      Upon the terms and subject to the conditions described in this prospectus
and in the letter of transmittal, we will accept for exchange any old bonds
properly tendered and not withdrawn prior to the expiration date. We will issue
new bonds in principal amount equal to the principal amount of old bonds
surrendered under the exchange offer. Old bonds may be tendered for new bonds
only in integral multiples of $1,000.

      The exchange offer is not conditioned upon any minimum aggregate principal
amount of old bonds being tendered for exchange.


                                       27

<PAGE>


      As of the date of this prospectus, $308,500,000 aggregate principal amount
of the old bonds are outstanding. This prospectus and the letter of transmittal
are being sent to all registered holders of old bonds. There will be no fixed
record date for determining registered holders of old bonds entitled to
participate in the exchange offer.


      We intend to conduct the exchange offer in accordance with the provisions
of the registration rights agreement, the applicable requirements of the
Securities Act and the Exchange Act and the rules and regulations of the SEC.
Old bonds that are not tendered for exchange in the exchange offer will remain
outstanding and continue to accrue interest and will be entitled to the rights
and benefits the holders have under the indenture relating to the bonds and the
registration rights agreement.


      We will be deemed to have accepted for exchange properly tendered old
bonds when we have given oral or written notice of the acceptance to the
exchange agent and complied with the applicable provisions of the registration
rights agreement. The exchange agent will act as agent for the tendering holders
for the purposes of receiving the new bonds from us.

      If you tender old bonds in the exchange offer, you will not be required to
pay brokerage commissions or fees or, subject to the instructions in the letter
of transmittal, transfer taxes with respect to the exchange of old bonds. We
will pay all charges and expenses, other than applicable taxes described below,
in connecting with the exchange offer. It is important that you read the section
labeled "--Fees and Expenses" for more details regarding fees and expenses
incurred in the exchange offer.

      We will return any old bonds that we do not accept for exchange for any
reason without expense to their tendering holder as promptly as practicable
after the expiration or termination of the exchange offer.


      Neither we nor our board of directors makes any recommendation to holders
of the old bonds as to whether to tender or refrain from tendering all or any
portion of their old bonds in the exchange offer. In addition, no one has been
authorized to make any recommendation to holders of the old bonds. Holders of
the old bonds must make their own decision whether to tender pursuant to the
exchange offer, and, if so, the aggregate amount of old bonds to tender after
reading this prospectus and the letter of transmittal and consulting with their
advisers, if any, based on their financial position and requirements.


Expiration Date

      The exchange offer will expire at 5:00 p.m., New York City time, May 12,
2000, unless, in our sole discretion, we extend it. Notwithstanding the
preceding, we will not extend the expiration date beyond September 30,
2000.

Extensions, Delays in Acceptance, Termination or Amendment


      We expressly reserve the right, at any time or various times, to extend
the period of time during which the exchange offer is open. We may delay
acceptance of any old bonds by giving oral or written notice of the extension to
their holders. During any extensions, all old bonds previously tendered will
remain subject to the exchange offer, and we may accept them for exchange.


      In order to extend the exchange offer, we will notify the exchange agent
orally or in writing of any extension. We will notify the registered holders of
old bonds of the extension no later than 9:00 a.m., New York City time, on the
business day after the previously scheduled expiration date.

      If any of the conditions described below under "--Conditions to the
Exchange Offer" have not been satisfied, we reserve the right, in our sole
discretion:

      o  to delay accepting for exchange any old bonds;

      o  to extend the exchange offer; or

      o  to terminate the exchange offer


by giving oral or written notice of the delay, extension or termination to the
exchange agent. Subject to the terms of the registration rights agreement, we
also reserve the right to amend the terms of the exchange offer in any manner.



      Any delay in acceptance, extension, termination or amendment will be
followed as promptly as practicable by oral or written notice to the registered
holders of old bonds. If we amend the exchange offer in a manner that we
determine to constitute a material change, we will promptly file a
post-effective amendment to the registration statement



                                       28

<PAGE>



and disclose the amendment by means of a prospectus supplement when the
post-effective amendment has been declared effective by the SEC. The supplement
will be distributed to the registered holders of the old bonds. Depending upon
the significance of the amendment and the manner of disclosure to the registered
holders, we will extend the exchange offer if the exchange offer would otherwise
expire during any period of delay.


Conditions to the Exchange Offer

      Despite any other term of the exchange offer, we will not be required to
accept for exchange, or exchange any new bonds for, any old bonds, and we may
terminate the exchange offer as provided in this prospectus before accepting any
old bonds for exchange, if in our reasonable judgment:

      o  the exchange offer, or the making of any exchange by a holder of old
         bonds, would violate applicable law or any applicable interpretation of
         the staff of the SEC; or

      o  any action or proceeding has been instituted or threatened in any court
         or by or before any governmental agency with respect to the exchange
         offer that, in our judgment, would reasonably be expected to impair our
         ability to proceed with the exchange offer.


      In addition, we will not be obligated to accept for exchange the old bonds
of any holder that has not made to us the representations described under
"--Purpose and Effect of the Exchange Offer," "--Procedures for Tendering" and
"PLAN OF DISTRIBUTION" and any other representations as may be reasonably
necessary under applicable SEC rules, regulations or interpretations to make
available to us an appropriate form for registration of the new bonds under the
Securities Act.


      We expressly reserve the right to amend or terminate the exchange offer
and to reject for exchange any old bonds not previously accepted for exchange,
upon the occurrence of any of the conditions to the exchange offer specified
above. We will give oral or written notice of any extension, amendment,
non-acceptance or termination to the registered holders of the old bonds as
promptly as practicable.


      These conditions are for our sole benefit and we may assert them in whole
or in part at any time or at various times in our sole discretion. If we fail at
any time to exercise any of these rights, this failure will not mean that we
have waived our rights. Each right will be deemed an ongoing right that we may
assert at any time or at various times. If any waiver or amendment constitutes a
material change to the exchange offer, we will promptly disclose the waiver or
amendment by means of a prospectus supplement that will be distributed to the
registered holders of the old bonds. In this case, we will extend the exchange
offer to the extent required by the Exchange Act to provide holders of old bonds
the opportunity to effectively consider the additional information and to factor
this information into their investment decision.



      In addition, we will not accept for exchange any old bonds tendered, and
will not issue new bonds in exchange for any old bonds, if at the time any stop
order has been threatened or is in effect with respect to the registration
statement of which this prospectus constitutes a part or the qualification of
the indenture relating to the bonds under the Trust Indenture Act of 1939.


Procedures for Tendering

How to Tender Generally


      Only a holder of old bonds may tender the old bonds in the exchange offer.
To tender in the exchange offer, a holder must:


      o  complete, sign and date the letter of transmittal, or a facsimile of
         the letter of transmittal;

      o  have the signature on the letter of transmittal guaranteed if the
         letter of transmittal so requires; and


      o  mail or deliver the letter of transmittal or facsimile to the exchange
         agent prior to the expiration date; or


      o  comply with the automated tender offer program procedures of DTC,
         described below.

      In addition, either:


      o  the exchange agent must receive, prior to the expiration date, a timely
         confirmation of book-entry transfer of the old bonds into the exchange
         agent's account at DTC according to the procedure for book-entry
         transfer described below or a properly transmitted agent's message; or



                                       29

<PAGE>


      o  the holder must comply with the guaranteed delivery procedures
         described below.

      To be tendered effectively, the exchange agent must receive any physical
delivery of the letter of transmittal and other required documents at its
address provided above under "SUMMARY OF THE EXCHANGE OFFER--The Exchange Agent"
prior to the expiration date.

      The tender by a holder that is not withdrawn prior to the expiration date
will constitute an agreement between the holder and us in accordance with the
terms and subject to the conditions described in this prospectus and in the
letter of transmittal.

      The method of delivery of the letter of transmittal and all other required
documents to the exchange agent is at your election and risk. Rather than mail
these items, we recommend that you use an overnight or hand delivery service. In
all cases, you should allow sufficient time to assure delivery to the exchange
agent before the expiration date. You should not send the letter of transmittal
to us. You may request your brokers, dealers, commercial banks, trust companies
or other nominees to effect the above transactions for you.

How to Tender if You Are a Beneficial Owner

      If you beneficially own old bonds that are registered in the name of a
broker, dealer, commercial bank, trust company or other nominee and you wish to
tender those bonds, you should contact the registered holder promptly and
instruct it to tender on your behalf.

Signatures and Signature Guarantees

      You must have signatures on a letter of transmittal or a notice of
withdrawal, as described below, guaranteed by a member firm of a registered
national securities exchange or of the National Association of Securities
Dealers, Inc., a commercial bank or trust company having an office or
correspondent in the United States, or an "eligible guarantor institution"
within the meaning of Rule 17Ad-15 under the Exchange Act, that is a member of
one of the recognized signature guarantee programs identified in the letter of
transmittal, unless the old bonds are tendered:

      o  by a registered holder who has not completed the box entitled "SPECIAL
         ISSUANCE INSTRUCTIONS" or "SPECIAL DELIVERY INSTRUCTIONS" on the letter
         of transmittal; or

      o  for the account of a member firm of a registered national securities
         exchange or of the National Association of Securities Dealers, Inc., a
         commercial bank or trust company having an office or correspondence in
         the United States, or an eligible guarantor institution.

      If the letter of transmittal or any bonds or bond powers are signed by
trustees, executors, administrators, guardians, attorneys-in-fact, officers of
corporations or others acting in a fiduciary or representative capacity, those
persons should so indicate when signing. Unless waived by us, they should also
submit evidence satisfactory to us of their authority to deliver the letter of
transmittal.

Tendering Through DTC's Automated Tender Offer Program

      The exchange agent and DTC have confirmed that any financial institution
that is a participant in DTC's system may use DTC's automated tender offer
program to tender. Participants in the program may, instead of physically
completing and signing the letter of transmittal and delivering it to the
exchange agent, transmit their acceptance of the exchange offer electronically.
They may do so by causing DTC to transfer the old bonds to the exchange agent in
accordance with its procedures for transfer. DTC will then send an agent's
message to the exchange agent.

      The term "agent's message" means a message transmitted by DTC, received by
the exchange agent and forming part of the book-entry confirmation, to the
effect that:


      o  DTC has received an express acknowledgment from a participant in its
         automated tender offer program that is tendering old bonds that are the
         subject of the book-entry confirmation;



      o  the participant has received and agrees to be bound by the terms of the
         letter of transmittal or, in the case of an agent's message relating to
         guaranteed delivery, that the participant has received and agrees to be
         bound by the applicable notice of guaranteed delivery; and



      o  the agreement may be enforced against the participant.



                                       30

<PAGE>


Determinations Under the Exchange Offer


      We will determine in our sole discretion all questions as to the validity,
form, eligibility, time of receipt, acceptance of tendered old bonds and
withdrawal of tendered old bonds. Our determination will be final and binding on
all parties. We reserve the absolute right to reject any old bonds not properly
tendered or any old bonds our acceptance of which would, in the opinion of our
counsel, be unlawful. We also reserve the right to waive any defect,
irregularities or conditions of tender as to particular old bonds. Our
interpretation of the terms and conditions of the exchange offer, including the
instructions in the letter of transmittal, will be final and binding on all
parties. Unless waived, all defects or irregularities in connection with tenders
of old bonds must be cured within the time as we will determine. Although we
intend to notify holders of defects or irregularities with respect to tenders of
old bonds, neither we, the exchange agent nor any other person will incur any
liability for failure to give the notification. Tenders of old bonds will not be
deemed made until the defects or irregularities have been cured or waived. Any
old bonds received by the exchange agent that are not properly tendered and as
to which the defects or irregularities have not been cured or waived will be
returned to the tendering holder, unless otherwise provided in the letter of
transmittal, as soon as practicable following the expiration date.


When We Will Issue New Bonds

      In all cases, we will issue new bonds for old bonds that we have accepted
for exchange under the exchange offer only after the exchange agent timely
receives:


      o  old bonds or a timely book-entry confirmation of the old bonds into the
         exchange agent's account at DTC; and


      o  a properly completed and duly executed letter of transmittal and all
         other required documents or a properly transmitted agent's message.

Return of Old Bonds Not Accepted or Excepted


      If we do not accept any tendered old bonds for exchange for any reason
described in the terms and conditions of the exchange offer or if old bonds are
submitted for a greater principal amount than the holder desires to exchange,
the unaccepted or non-exchanged old bonds will be returned without expense to
their tendering holder. In the case of old bonds tendered by book-entry transfer
into the exchange agent's account at DTC according to the procedures described
below, the non-exchanged old bonds will be credited to an account maintained
with DTC. These actions will occur as promptly as practicable after the
expiration or termination of the exchange offer.


Your Representation to Us

      By signing or agreeing to be bound by the letter of transmittal, you will
represent to us that, among other things:


      o  any new bonds that you receive are being acquired in the ordinary
         course of your business;



      o  you have no arrangement or understanding with any person or entity to
         participate in any distribution of the new bonds;



      o  you are not engaged in and do not intend to engage in any distribution
         of the new bonds;



      o  if you are a broker-dealer that will receive new bonds for your own
         account in exchange for old bonds, you acquired those bonds as a result
         of market-making activities or other trading activities and you will
         deliver a prospectus, as required by law, in connection with any resale
         of the new bonds; and


      o  you are not our "affiliate," as defined in Rule 405 of the Securities
         Act.

Book-Entry Transfer


      The exchange agent will establish an account with respect to the old bonds
at DTC for purposes of the exchange offer promptly after the date of this
prospectus. Any financial institution participating in DTC's system may make
book-entry delivery of old bonds by causing DTC to transfer the old bonds into
the exchange agent's account at DTC in accordance with DTC's procedures for
transfer.


Guaranteed Delivery Procedures

      If you wish to tender your old bonds but you cannot deliver the letter of
transmittal or any other required documents to the exchange agent or comply with
the applicable procedures under DTC's automated tender offer program prior to
the expiration date, you may still tender if:


                                       31

<PAGE>


      o  the tender is made through a member firm of a registered national
         securities exchange or of the National Association of Securities
         Dealers, Inc., a commercial bank or trust company having an office or
         correspondent in the United States, or an eligible guarantor
         institution;


      o  prior to the expiration date, the exchange agent receives from the
         member firm of a registered national securities exchange or of the
         National Association of Securities Dealers, Inc., commercial bank or
         trust company having an office or correspondent in the United States,
         or eligible guarantor institution either a properly completed and duly
         executed notice of guaranteed delivery by facsimile transmission, mail
         or hand delivery or a properly transmitted agent's message and notice
         of guaranteed delivery:


         o  setting forth your name and address, the registered number(s) of
            your old bonds and the principal amount of old bonds tendered;

         o  stating that the tender is being made thereby; and


         o  guaranteeing that, within three New York Stock Exchange trading days
            after the expiration date, the letter of transmittal or facsimile
            thereof, together with the old bonds or a book-entry confirmation,
            and any other documents required by the letter of transmittal will
            be deposited by the eligible guarantor institution with the exchange
            agent;


      and


      o  the exchange agent receives the properly completed and executed letter
         of transmittal or facsimile thereof, as well as a book-entry
         confirmation, and all other documents required by the letter of
         transmittal, within three New York Stock Exchange trading days after
         the expiration date.


      Upon request to the exchange agent, a notice of guaranteed delivery will
be sent you if you wish to tender your old bonds according to the guaranteed
delivery procedures described above.

Withdrawal of Tenders

      Except as otherwise provided in this prospectus, you may withdraw your
tender at any time prior to the expiration date.

      For a withdrawal to be effective:

      o  the exchange agent must receive a written notice of withdrawal at one
         of the addressees listed under "SUMMARY OF THE EXCHANGE OFFER--The
         Exchange Agent," or

      o  you must comply with the appropriate procedures of DTC's automated
         tender offer program system.

      Any notice of withdrawal must:

      o  specify the name of the person who tendered the old bonds to be
         withdrawn; and


      o  identify the old bonds to be withdrawn, including the principal amount
         of the old bonds.


      If old bonds have been tendered under the procedure for book-entry
transfer described above, any notice of withdrawal must specify the name and
number of the account at DTC to be credited with the withdrawn old bonds and
otherwise comply with the procedures of DTC.


      We will determine all questions as to the validity, form, eligibility and
time of receipt of notice of withdrawal, and our determination will be final and
binding on all parties. We will deem any old bonds so withdrawn not to have been
validly tendered for exchange for purposes of the exchange offer.


      Any old bonds that have been tendered for exchange but that are not
exchanged for any reason will be credited to an account maintained with DTC for
the old bonds. This crediting will take place as soon as practicable after
withdrawal, rejection of tender or termination of the exchange offer. You may
retender properly withdrawn old bonds by following one of the procedures
described under "--Procedures for Tendering" above at any time on or prior to
the expiration date.


                                       32

<PAGE>


Exchange Agent

      The Bank of New York has been appointed exchange agent of the exchange
offer. Questions and requests for assistance and requests for additional copies
of this prospectus or of the letter of transmittal should be directed to the
exchange agent addressed as follows:

By Registered Mail or Certified Mail         By Overnight Courier

The Bank of New York                         The Bank of New York
101 Barclay Street, 7E                       101 Barclay Street, 7E
New York, NY  10286                          New York, NY  10286
Attention: Carolle Montreuil                 Attention: Carolle Montreuil

By Telephone                                 By Facsimile
(212) 815-5920                               (212) 815-6339

Fees and Expenses

      We will bear the expenses of soliciting tenders. The principal
solicitation is being made by mail; however, we may make additional solicitation
by telegraph, telephone or in person by our officers and regular employees and
those of our affiliates.

      We have not retained any dealer-manager in connection with the exchange
offer and will not make any payments to broker-dealers or other soliciting
acceptances of the exchange offer. We will, however, pay the exchange agent
reasonable and customary fees for its services and reimburse it for its related
reasonable out-of-pocket expenses.

      We will pay the cash expenses to be incurred in connection with the
exchange offer. They include:

      o  SEC registration fees;

      o  fees and expenses of the exchange agent and trustee;

      o  accounting and legal fees and printing costs; and

      o  related fees and expenses.

Transfer Taxes

      We will pay all transfer taxes, if any, applicable to the exchange of old
bonds under the exchange offer. The tendering holder, however, will be required
to pay any transfer taxes, whether imposed on the registered holder or any other
person, if:

      o  certificates representing old bonds for principal amounts not tendered
         or accepted for exchange are to be delivered to, or are to be issued in
         the name of, any person other than the registered holder of old bonds
         tendered;

      o  tendered old bonds are registered in the name of any person other than
         the person signing the letter of transmittal; or

      o  a transfer tax is imposed for any reason other than the exchange of old
         bonds under the exchange offer.


If satisfactory evidence of payment of any transfer taxes payable by a bond
holder is not submitted with the letter of transmittal, the amount of the
transfer taxes will be billed directly to that tendering holder.


Consequences of Failure to Exchange


      If you do not exchange your old bonds for new bonds under the exchange
offer, you will remain subject to the existing restrictions on transfer of the
old bonds, and the market for secondary resales is likely to be minimal. In
general, you may not offer or sell the old bonds unless they are registered
under the Securities Act, or if the offer or sale is exempt from registration
under the Securities Act and applicable state securities laws. Except as
required by the registration rights agreement, we do not intend to register the
old bonds under the Securities Act. Unless they are broker-dealers selling under
certain circumstances, holders of old bonds will no longer have any rights under
the registration rights agreement. Broker-dealers that are not eligible to
participate in the exchange offer may have additional rights under the
registration rights agreement to facilitate the sale of their old bonds.



                                       33

<PAGE>


Accounting Treatment

      We will record the new bonds in our accounting records at the same
carrying value as the old bonds, which is the aggregate principal amount of the
old bonds, as reflected in our accounting records on the date of exchange.
Accordingly, we will not recognize any gain or loss for accounting purposes in
connection with the exchange offer. Participation in the exchange offer is
voluntary, and you should carefully consider whether to accept. You are urged to
consult your financial and tax advisors in making your own decision on what
action to take.

Further Bond Acquisition

      We may in the future seek to acquire untendered old bonds in open market
or privately negotiated transactions, through subsequent exchange offers or
otherwise. We have no present plans to acquire any old bonds that are not
tendered in the exchange offer or to file a registration statement to permit
resales of any untendered old bonds.


                                       34

<PAGE>


                             SELECTED FINANCIAL DATA


      Our selected financial data is presented below and consists of our summary
balance sheet information as of December 31, 1999, which should be read in
conjunction with "MANAGEMENT'S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION
AND RESULTS OF OPERATIONS" and with our financial statements appearing elsewhere
in this prospectus. We began construction of our facility in June 1999 and,
since we are in the development stage, we currently have no operating revenues.
All construction costs and all project development costs have been capitalized
and will continue to be capitalized until the commencement of commercial
operation of our facility. Accordingly, only balance sheet data is presented and
no ratio of earnings to fixed charges has been computed since it would not be
meaningful. The balance sheet information as of December 31, 1999 and the
statement of operations for the period ended December 31, 1999 have been derived
from our financial statements which have been audited by Deloitte & Touche LLP,
independent public accountants, whose report appears elsewhere in this
prospectus.



                              AES Ironwood, L.L.C.
                        (Development Stage Enterprise)
               As of and for the period ended December 31, 1999


                                                          (thousands)


            Assets
            Current Assets                                     $23,638
            Investments Held by Trustee (1)                     68,145
            Land                                                   528
            Construction in Progress                           244,563
            Deferred Financing Costs                             2,447
            Certificate of Deposit                                 385
            Other Assets                                           317
                                                                ------



            Total Assets                                      $340,023
                                                               =======



            Liabilities & Member's Deficit
            Current Liabilities                                $23,928
            Bond Financing                                     308,500
            Other Long-Term Liabilities                         10,236
            Member's Deficit                                    (2,641)



            Total Liabilities & Member's Deficit              $340,023
                                                               =======



            Operating Expenses:
            General and Administrative Expenses                 $  169
                                                                   ---
            Net Operating loss                                  $  169
                                                                   ---



            Interest Income                                      3,283
            Interest Expense                                    (5,755)



            NET LOSS                                           $(2,641)
                                                                ======



            Cash Paid for Construction
            in Progress Since Inception                       $212,526
                                                               =======


- ------------------------
(1) This amount consists of funds held pending expenditure by us for
construction of our facility, interest payments to bondholders during the
construction period, and investment earnings thereon.


                                       35

<PAGE>


         MANAGEMENT'S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION
                            AND RESULTS OF OPERATIONS
General

      We were formed on October 30, 1998 to develop, construct, own, operate and
maintain our facility. We were dormant until June 25, 1999, the date of the sale
of the old bonds. We are in the development stage and have no operating
revenues. We obtained $308,500,000 of project funding from the sale of the old
bonds. The total cost of the construction of our facility is estimated to be
approximately $359 million, which will be financed by the proceeds from the sale
of the old bonds and the equity contribution described below.

      Our facility is still under construction and we expect it to be completed
and operational by approximately June 30, 2001.

Equity Contributions

      Under the equity subscription agreement, AES Ironwood, Inc. is obligated
to contribute up to approximately $50.1 million to us to fund project costs. AES
Ironwood, Inc.'s obligation to make the contributions is, and will be, supported
by an acceptable letter of credit or an acceptable bond.

Results of Operations


      For the period from June 25, 1999 (inception) through December 31, 1999,
costs in the amount of $244,563,000 pertaining to the cost of the construction
of our facility have been capitalized as Construction Work in Progress and are
included as assets on the balance sheet. Interest capitalized during this period
was approximately $8.4 million. The cost of purchasing land for construction of
our facility has been separately identified on the balance sheet.



      From June 25, 1999 through December 31, 1999, general and administrative
costs of $169,000 were incurred. These costs did not directly relate to
construction and are included as expenses in the Statement of Operations.


      A portion of the proceeds from the sale of the old bonds have not yet been
expended on construction and were invested by the trustee. The interest income
earned on these invested funds is included in the Statement of Operations.

      The interest expense incurred on the portion of the old bond proceeds
expended during the construction period is capitalized to Construction in
Progress and is included on the balance sheet. Interest expense incurred on the
old bond proceeds not spent on construction of our facility are included as
interest expense in the Statement of Operations.


      For the period from June 25, 1999 through December 31, 1999,
non-capitalizable costs plus interest expense and less interest income resulted
in a net loss on the December 31, 1999 Statement of Operations of approximately
$2.6 million. The results of operations may not be comparable with the results
of operations during future periods, especially when our facility begins
commercial operations in 2001.


Liquidity and Capital Resources

      We believe that the net proceeds from the sale of the old bonds, together
with the equity contribution, will be sufficient to (1) fund the engineering,
procurement, construction, testing and commissioning of our facility until it is
placed in commercial operation, (2) pay certain fees and expenses in connection
with the financing and development of our project and (3) pay project costs,
including interest on the bonds. After our facility is placed in commercial
operation, we will depend on our revenues under the power purchase agreement,
and after the power purchase agreement expires, we will depend on market sales
of electricity.

      In order to provide liquidity in the event of cash flow shortfalls, the
debt service reserve account will contain an amount equal to the debt service
reserve account required balance through cash funding, issuance of the debt
service reserve letter of credit or a combination of the two.


      As of December 31, 1999, apart from commitments totalling $238,000,000
arising from the construction of our facility, we have committed to two
additional capital expenditures totaling $5.7 million. One is for a pipeline for
$2.5 million and the other is for a pumping station for $3.2 million. We expect
to pay these amounts in fiscal year 2000. These amounts are expected to be paid
out of the proceeds from the sale of the old bonds and the equity contribution.


Business Strategy and Outlook

      Our overall business strategy is to market and sell all of its net
capacity, fuel conversion and ancillary services to Williams Energy during the
term of the power purchase agreement. After expiration of the power purchase
agreement,


                                       36

<PAGE>


we anticipate selling our facility's capacity, ancillary services and energy
under a power purchase agreement or into the PJM power pool market. We intend to
cause our facility to be managed, operated and maintained in compliance with the
project contracts and all applicable legal requirements.


                                       37

<PAGE>


                                  OUR BUSINESS

General

      We are a Delaware limited liability company formed to develop, construct,
own, operate and maintain our project and manage the production of electric
generating capacity, ancillary services and energy at our facility. After the
commercial operation date, our sole business will be the ownership and operation
of our project. We own the land on which our facility will be located. Our
facility will be designed, engineered, procured and constructed for us by
Siemens Westinghouse Power Corporation on a fixed-price, turnkey basis under the
construction agreement. Siemens Westinghouse will provide combustion turbine
maintenance services and spare parts with respect to our facility for an initial
term of between eight and 10 years, depending on the timing of scheduled
outages, under the maintenance services agreement. AES Prescott, a wholly-owned
subsidiary of The AES Corporation, will provide development, construction
management and operations and maintenance services for the project under the
operations agreement.

      We have entered into a power purchase agreement for a term of 20 years
under which Williams Energy has committed to purchase all of the net capacity,
fuel conversion and ancillary services of our facility. Net capacity is the
maximum amount of electricity generated by our facility net of electricity used
at our facility. Fuel conversion services consist of the combustion of natural
gas and fuel oil in order to generate electric energy. Ancillary services
consist of services necessary to support the transmission of capacity and
energy. Williams Energy is obligated to supply us with all natural gas and/or
fuel oil necessary to provide net capacity, fuel conversion services and
ancillary services under the power purchase agreement. We anticipate that during
the term of the power purchase agreement substantially all of our revenues will
be derived from payments made under the power purchase agreement.

Our Property

      Since we are a development stage company, our principal property is the
land for the facility site, which we own. The facility site is located in South
Lebanon Township, Lebanon County, Pennsylvania on an approximately 35-acre
parcel of land. We have access, utility, drainage and construction easements
across neighboring property. We are able to use these easements as long as there
is no default under the agreements with the owner of the adjacent property and
we are using the facility site for a power plant. We intend to construct a
railspur to facilitate the transportation of heavy equipment to the facility
site, but will not maintain rights in the railspur after construction has been
completed. We have title insurance in connection with our property rights.

      Under the indenture and the other related financing documents, our rights
and interests in our property rights are encumbered by mortgages, security
agreements, collateral assignments and pledges for the benefit of the
bondholders and other senior creditors.

      For a description of our facility, see "PROSPECTUS SUMMARY--Our Facility."

Competition


      Under the power purchase agreement, Williams Energy will be required to
purchase all of our facility's capacity and energy. Therefore, during the term
of the power purchase agreement, competition from other capacity and energy
providers will only become an issue if Williams Energy breaches its agreement
and ceases to purchase our capacity and energy or the power purchase agreement
is otherwise terminated or not performed in accordance with its terms. Following
the term of the power purchase agreement, we anticipate selling our facility's
net capacity, ancillary services and energy under a power purchase agreement or
into the PJM power pool market. At that time, we will face competition from
other generating facilities selling into the PJM power pool market including,
possibly, other facilities owned by The AES Corporation or its affiliates.


Employees

      Other than the officers listed under "OUR MANAGEMENT--Management", we have
no employees and do not anticipate having any employees in the future. Under the
operations agreement, AES Prescott will manage the development and construction
of and will operate and maintain our facility. The direct labor personnel and
the plant operations management will be employees of The AES Corporation
provided to AES Prescott under the services agreement.

Insurance

      As owner of our facility, we will maintain a comprehensive insurance
program as required under the indenture and underwritten by recognized insurance
companies. Among other insurance policies, we will maintain commercial


                                       38

<PAGE>


general liability insurance, permanent property insurance for full replacement
value of our facility and business interruption insurance covering at least 12
months of debt service and fixed operation and maintenance expenses. We have
obtained title insurance in an amount equal to the principal amount of the
bonds.

      AES Prescott, as operator of our facility, will maintain, among other
insurance policies, workers' compensation insurance, or evidence of
self-insurance, if required, and comprehensive automobile bodily injury and
property damage liability insurance.

Legal Proceedings

      We are not party to any legal proceedings.

Permits and Regulatory Approvals


      AES Prescott, as operator of our facility, and AES Ironwood, L.L.C., as
owner of our facility, must comply with numerous federal, state and local
regulatory requirements including environmental requirements in the operation of
our facility. The material regulatory permits and authorizations that we must
obtain for construction and operation are described in the independent
engineer's report, which is attached as Annex B to this prospectus.



      On March 31, 1999, we received a certification from FERC that we are an
Exempt Wholesale Generator. Certification as an exempt Wholesale Generator
exempts us from regulation under the Public Utility Holding Company Act of 1935.
We will maintain this status so long as we continue to make only wholesale sales
of electricity, which we intend to do. Prior to commercial operation, we will be
required to file the power purchase agreement with FERC and obtain approval for
the rates contained therein. We anticipate filing with FERC and obtaining the
approval prior to the end of 2000. We may also need to obtain FERC approval for
sales of electricity at market-based rates after the power purchase agreement is
no longer in effect.


      On March 29, 1999, we received our Prevention of Significant Deterioration
Permit, or "air permit", from the Pennsylvania Department of Environmental
Protection. The appeal period in respect of the air permit expired on May 3,
1999 and no appeal was filed. The air permit requires that our facility be
constructed in a manner that will allow it to meet specified limitations on
emissions of air pollutants. Under the construction agreement, Siemens
Westinghouse is required to construct our facility to meet these requirements.


      We are subject to a number of statutory and regulatory standards and
required approvals relating to energy, labor and environmental laws. Although
the necessary environmental permits for the commencement of construction of our
facility have been obtained, we are required to comply with the terms of our
environmental permits and to obtain other permits for the construction and
operation of our facility. Several of the permits have not yet been obtained,
and some cannot be obtained until operation of our facility has commenced. Under
specific circumstances, delay in receipt of or failure to obtain the permits
could delay completion of the construction of our facility or prevent the
operation of our facility, however, we do not expect any delay or failure to
obtain these permits to materially delay completion of construction or operation
of the facility.


      Some permits that we have obtained in connection with our facility will
require amendment prior to commercial operation of our facility and others will
require renewal or reissuance during the life of our facility. While we have no
reason to believe that the permits cannot be amended or will not be renewed or
reissued, our inability to amend, renew or obtain reissuance of these permits in
the future could cause the suspension of construction or operation of our
facility.


      The permits that have been obtained and that will be obtained contain
ongoing requirements. Failure to satisfy and maintain any the permit conditions
or other applicable requirements could delay or prevent completion of the
construction of our facility, prevent the operation of our facility and/or
result in additional costs. See "ANNEX B: INDEPENDENT ENGINEER'S
REPORT--Environmental and Permitting."

                                       39

<PAGE>


                                 OUR MANAGEMENT

Management

      We are a Delaware limited liability company and have no employees other
than our officers. Our officers receive no compensation for their services to us
or for any transaction between us and any of our affiliates. We are managed by
our Board of Directors under the terms of our Limited Liability Company
Agreement, dated as of November 1, 1998. The following table sets forth the
names, ages and positions of our directors and executive officers and their
positions with us. Our directors are elected annually and each elected director
holds office until the director's successor is elected and qualified or the
director resigns or is removed. Our officers are elected from time to time by
vote of the Board of Directors.

Name                          Age               Position(s)
- ----                          ---               -----------

John Ruggirello...............49                President
Barry Sharp...................40                Director, Vice President and
                                                  Chief Financial Officer
William Luraschi..............36                Vice President and Secretary
Patricia Rollin...............38                Vice President
Stephen Dahm..................54                Vice President
Kevin Polchow.................38                Vice President
Bart Rossi....................51                Vice President

William Hoagland..............39                Treasurer

Maureen Shearer...............36                Assistant Secretary
Dennis Bakke..................54                Director
Roger Naill...................52                Director

      John Ruggirello, 49, has served as President of AES Ironwood, L.L.C.
since November 1998.  He is Senior Vice President of The AES Corporation.
Mr. Ruggirello also serves as the President of AES Enterprise, a business
development and plant operations division serving the Mid-Atlantic United
States since 1994.  Prior to his current position, Mr. Ruggirello was plant
manager of AES Beaver Valley.  Mr. Ruggirello spends approximately  20% of
his time in his capacity as Senior Vice President of The AES Corporation.

      Barry Sharp, 40, has served as Director, Vice President and Chief
Financial Officer of AES Ironwood, L.L.C. since November 1998. He is currently
Senior Vice President and Chief Financial Officer of The AES Corporation. He
joined The AES Corporation as Director of Finance and Administration in 1986.
Prior to The AES Corporation, he held various positions with Arthur Anderson &
Company and Marriott. Mr. Sharp spends approximately 95% of his time in his
capacity as Senior Vice President and Chief Financial Officer of The AES
Corporation.

      William Luraschi, 36, has served as Vice President of AES Ironwood, L.L.C.
since November 1998. He is currently Vice President, Secretary and General
Counsel of The AES Corporation. He joined The AES Corporation as General Counsel
in 1995. Prior to joining The AES Corporation, he was an attorney at the law
offices of Chadbourne and Parke. Mr. Luraschi spends approximately 95%of his
time in his capacity as Vice President, Secretary and General Counsel of The AES
Corporation.

      Patricia Rollin, 38, has served as Vice President of AES Ironwood, L.L.C.
since November 1998. She is also a Vice President of AES Enterprise. She served
as Director of Investor Relations of The AES Corporation from 1994 through 1995.
She joined The AES Corporation Corporate Strategic Planning in 1984.

      Stephen Dahm, 54, has served as Vice President  of  AES Ironwood,
L.L.C. since November 1998.  He is a Project Director of AES Ironwood,
L.L.C.  Prior to joining AES Ironwood, L.L.C., he served as Vice President
and Project Director for AES Lal Pir and PakGen.  Mr. Dahm joined The AES
Corporation in 1994 after 18 years with Bechtel.

      Kevin Polchow, 38, has served as Vice President of AES Ironwood, L.L.C.
since November 1998.  Mr. Polchow is currently the Tax Director of The AES
Corporation.  He assumed that position in 1994.  Prior to joining The AES
Corporation, Mr. Polchow served as a Senior Manager at Deloitte & Touche LLP.

      Bart Rossi, 51, has served as Vice President of AES Ironwood, L.L.C.
since November 1998. Mr. Rossi is currently a Project Engineering Director at
The AES Corporation.  He assumed that position in 1996. Prior to joining The
AES Corporation, Mr. Rossi served as a Chief  Engineer for Ebasco Services,
Inc.


                                       40

<PAGE>


      William Hoagland, 39, has served as Vice President of AES Ironwood,
L.L.C. since November 1998.  Mr. Hoagland is currently Director of Finance
and Administration of The AES Corporation and has held that position since
1994.  Prior to joining The AES Corporation, Mr. Hoagland was an auditor at
Deloitte & Touche LLP.


      Maureen B. Shearer, 36, has served as Secretary of AES Ironwood, L.L.C.
since November 1998.  She is currently Corporate Paralegal of The AES
Corporation and has held that position since 1995.  She joined The AES
Corporation as an Executive Assistant in 1989. Prior to joining The AES
Corporation, Ms. Shearer served active duty with the U.S. Coast Guard.

      Dennis Bakke, 54, has served as Director of AES Ironwood, L.L.C. since
November 1998. He is currently the President and CEO of The AES Corporation. He
assumed this position in 1994. He became the President and Chief Operating
Officer of The AES Corporation in 1987 and served as Executive Vice President
from 1981 to 1987. Mr. Bakke spends approximately 95% of his time in his
capacity as President and CEO of The AES Corporation.

      Roger F. Naill, 52, has served as Director of AES Ironwood, L.L.C.
since November 1998.  He is Senior Vice President of The AES Corporation and
heads The AES Corporation Corporate Strategic Planning Group.  He assumed
that position in 1981.  Mr. Naill spends approximately 95% of his time in his
capacity as Senior Vice President of The AES Corporation.


      Each of the officers and directors listed above is currently an officer,
director or employee of The AES Corporation or an affiliate of The AES
Corporation and receives compensation from The AES Corporation or the affiliate.
We are not a party to any agreement with The AES Corporation or its affiliates
governing the compensation paid to our officers, directors or employees. These
persons are paid by The AES Corporation or its affiliates, as applicable, in the
normal course of their employment with the relevant party. No cash or non-cash
compensation is currently proposed to be paid in the current calendar year by
AES Ironwood, L.L.C. to any of the officers and directors listed above.



                                       41

<PAGE>


                CERTAIN RELATIONSHIPS AND RELATED TRANSACTIONS

Certain Affiliations

      We, AES Ironwood, Inc. and AES Prescott are each wholly-owned indirect
subsidiaries of The AES Corporation. The AES Corporation has agreed to provide
AES Ironwood, Inc. sufficient funds for AES Ironwood, Inc. to contribute up to
$50,149,285 to us to fund project costs under an equity subscription agreement.
Other than the equity subscription agreement, the only other business we intend
to transact with any of our affiliates is an operations agreement with AES
Prescott.

Other Relationships and Related Transactions

      The AES Corporation. The AES Corporation is a leading global power company
committed to supplying electricity in a socially responsible way. The AES
Corporation currently has assets in excess of $10 billion and employs
approximately 44,500 people around the world. Under a services agreement, The
AES Corporation will supply to AES Prescott all of the personnel and services
necessary for AES Prescott to comply with its obligations under the operations
agreement.

      AES Ironwood, Inc.  AES Ironwood, Inc. is a Delaware corporation and a
wholly-owned subsidiary of The AES Corporation.  AES Ironwood, Inc. currently
has no operations outside of its activities in connection with our project
and does not anticipate undertaking any operations not associated with our
project.  AES Ironwood, Inc. owns all of the ownership interests in our
company and AES Prescott and, under the pledge agreement, AES Ironwood, Inc.
has pledged to the collateral agent all of its ownership interests in our
company.

      AES Prescott, L.L.C.. AES Prescott is a Delaware limited liability company
and wholly-owned subsidiary of AES Ironwood, Inc. and was established on October
30, 1998. We have entered into the operations agreement with AES Prescott under
which AES Prescott will manage the development and construction of and will
operate and maintain our facility. Minimum amounts payable under the operations
agreement during the construction period are $125,000 per month. Once commercial
operation is achieved, payments for operation management services will be
approximately $400,000 per quarter. The direct labor personnel and the plant
operations management will be provided to AES Prescott by The AES Corporation
under the services agreement entered into by AES Prescott and The AES
Corporation.


                                       42

<PAGE>



                    SUMMARY OF PRINCIPAL PROJECT CONTRACTS

      The following chart sets forth the parties to our project contracts and
each contract is described in more detail below:


<TABLE>

<S>                            <C>                   <C>
- -----------------------|
        Guaranty       |
                       |
- -----------------------|------|
The Williams Companies,|      |
          Inc.         |      |
- -----------------------|      |
          |                   |
          |                   |
- -----------------------|      |                      |--------------------------
     Power Purchase    |      |                      |   Operations Agreement
       Agreement       |      |                      |
- -----------------------|----| |                 |----|--------------------------
    Williams Energy    |    | |                 |    |    AES Prescott, L.L.C.
  Marketing & Trading  |    | |                 |    |
        Company        |    | |                 |    |--------------------------
- -----------------------|    | |                 |
                           |----------------------|
                           |    AES Ironwood,     |
- -----------------------|   |        L.L.C.        |  |--------------------------
 Construction Contract |---|----------------------|--| Interconnection Agreement
                       |    | |                 |    |
- -----------------------|    | |                 |    |--------------------------
 Siemens Westinghouse  |    | |                 |    |    Metropolitan Edison
   Power Corporation   |    | |                 |    |         Company
- -----------------------|    | |                 |    |--------------------------
          |                 | |                 |
          |                 | |                 |
- -----------------------|    | |                 |    |--------------------------
 Maintenance Services  |    | |                 |    | Effluent Supply Agreement
       Agreement       |    | |                 |    |
- -----------------------|----| |                 |----|--------------------------
 Siemens Westinghouse  |      |                 |    | City of Lebanon Authority
   Power Corporation   |      |                 |    |
- -----------------------|      |                 |    |--------------------------
          |                   |                 |
          |                   |                 |
- -----------------------|      |                 |    |--------------------------
       Guaranty        |      |                 |    |  Real Estate Agreements
                       |      |                 |    |
- -----------------------|------|                 |----|--------------------------
  Siemens Corporation  |                             |    Pennsy Supply, Inc.
                       |                             |
- -----------------------|                             |--------------------------
</TABLE>


      The following summaries contain the material terms of the principal
project contracts. All capitalized terms used in the following summaries and not
otherwise defined in this prospectus have the meanings given to them in Annex A
to this prospectus.


                            Power Purchase Agreement

      We have entered into an Amended and Restated Power Purchase Agreement,
dated as of February 5, 1999, with Williams Energy for the sale to Williams
Energy of all of the electric energy and capacity produced by our facility as
well as ancillary services and fuel conversion services.



                                       43
<PAGE>

Term

         The term of the power purchase agreement extends for 20 years after the
first contract anniversary date, which is the last day in the month in which the
commercial operation date occurs. The commercial operation date occurs when

         o        the Initial Start-Up Testing of our facility has been
                  successfully completed,

         o        we have received all approvals from PJM Interconnection,
                  L.L.C., which is the independent system operator that operates
                  the Transmission System to which our facility will
                  interconnect, and

         o        we have obtained all required permits and authorizations for
                  operation of our facility.


         If the commercial operation date has not occurred by June 30, 2001 for
any reason, including the continued existence of or delay caused by a force
majeure event affecting us, other than any delay caused by any act or failure to
act by Williams Energy or any of its affiliates where the action is required
under the power purchase agreement, Williams Energy will have the right to
terminate the power purchase agreement. We, however, can extend the commercial
operation date to December 31, 2001 (1) if we provide an opinion from a
third-party engineer that the commercial operation date will occur no later than
December 31, 2001 (the "Free Extension Option"), or (2) by giving Williams
Energy written notice of such extension no later than April 30, 2001, and paying
to Williams Energy a specified amount (for which we believe we have made
adequate provisions in the project budget) by no later than June 30, 2001 (the
"First Paid Extension Option").



         If we qualify for the Free Extension Option or elect the First Paid
Extension Option, if the commercial operation date has not occurred by the Final
CO Date for any reason, other than as a result of a delay in exercising an
interconnection agreement or any act or failure to act by Williams Energy or any
of its affiliates, where the action is required under the power purchase
agreement, Williams Energy will have the right to terminate the power purchase
agreement. We, however, can extend the Final CO Date to and including December
31, 2002 by giving Williams Energy written notice of the estimated extension
required no later than October 31, 2001 and paying to Williams Energy certain
specified amounts for each day of such extension (the "Second Paid Extension
Option").



         If we elect the Second Paid Extension Option and the commercial
operation date does not occur by December 31, 2002 for any reason whatsoever,
including the continued existence of or delay caused by a force majeure event
affecting us, other than as a result of a delay in exercising an interconnection
agreement or any act or failure to act by Williams Energy or any of its
affiliates where the action is required under the power purchase agreement,
Williams Energy will have the absolute right to terminate the power purchase
agreement.


Purchase and Sale of Capacity and Services


         During the term, commencing with the commercial operation date, we must
sell and make available to Williams Energy on an exclusive basis, and Williams
Energy must purchase and pay for, our facility's net capacity and ability to
generate electric energy.



         In addition, during the term, commencing with the commercial operation
date, we must perform for Williams Energy on an exclusive basis, and Williams
Energy must purchase and pay for, fuel conversion services, which consist of the
generation of electric energy from fuel provided by Williams Energy.


Fuel Conversion and Other Services


         As instructed by us, Williams Energy must deliver or cause to be
delivered to us at the Gas Delivery Point and Oil Delivery Point on an exclusive
basis all quantities of natural gas and fuel oil, respectively, as we required:


         o        to generate Net Electric Energy and/or ancillary services,

         o        to perform Start-Ups,

         o        to perform Shutdowns, and

         o        to operate our facility during any period other than a
                  Start-Up, Shutdown or Dispatch Period for any reason.


         Williams Energy will be responsible for the construction of all Gas
Interconnection Facilities. If the Gas Interconnection Facilities have not been
constructed and/or Williams Energy is unable for any reason to deliver natural
gas to our facility by the date that our facility would otherwise be prepared to
begin Initial Start-Up Testing, and but for the failure to provide the natural
gas our facility is otherwise ready, or would otherwise have been ready, to
begin the


                                       44
<PAGE>

testing, then Williams Energy must commence making payments to us for each day
of delay beginning on the Start-Up Testing Date and continuing until the date
that natural gas is delivered to our facility for Initial Start-Up Testing, in
an amount for each day of delay which is equal to one-thirtieth of the
applicable total fixed payment. Upon the expiration of the power purchase
agreement or any termination of the power purchase agreement as the result of
Williams Energy's default, we will have the right to purchase the Gas
Interconnection Facilities from Williams Energy, or if Williams Energy does not
own the Gas Interconnection Facilities, Williams Energy must assign to us all of
its rights to transportation services using the Gas Interconnection Facilities.



         Williams Energy will be responsible for the cost of procurement and
installation of the Oil Metering Equipment. Williams Energy will be solely
responsible for all costs and expenses related to the supply and transportation
of natural gas and fuel oil to the Gas Delivery Point and Oil Delivery Point,
respectively. We will be responsible for all costs and expenses related to the
transportation of natural gas and fuel oil at and from the Gas Delivery Point
and Oil Delivery Point to our facility. At our request, instead of delivering
fuel oil to the applicable Oil Delivery Point, Williams Energy must deliver or
cause to be delivered the quantities of fuel oil as requested to any off-site
storage facility approved by Williams Energy and delivery to that site will be
deemed delivery to the Oil Delivery Point. We will be responsible for all costs
and expenses related to the transportation of the fuel oil from the off-site
storage facility to our facility.



         We will be responsible for the installation, operation and maintenance
at the facility site, at our sole cost and expense, of fuel oil storage tank(s)
capable of storing a volume of usable fuel oil sufficient to operate our
facility at maximum facility capacity output for two continuous days. We will
not be obligated to operate our facility on fuel oil for more than an operating
hour equivalent that is consistent with our air permit.


Pricing and Payments


         For each month of the term after the commercial operation date,
Williams Energy must pay us for our facility's net capacity, successful
Start-Ups and associated Shutdowns, other services and fuel conversion services
at the applicable rates described in the power purchase agreement. Each monthly
payment by Williams Energy will consist of a total fixed payment, a fuel
conversion payment and a start-up payment. The total fixed payment, which is
payable regardless of facility dispatch by Williams Energy but is subject to
adjustment based on facility availability, is calculated by multiplying a fixed
capacity rate for each contract year by our facility's net capacity in the
billing month and is anticipated to be sufficient to cover our debt service and
fixed operating and maintenance costs and to provide us a return on equity. The
fuel conversion payment is intended to cover our variable operating and
maintenance costs and escalates annually based on an escalation index described
in the power purchase agreement. In addition, we may receive heat rate bonuses
or be required to pay heat rate penalties.



         Prior to the commercial operation date, and during specific facility
tests thereafter, we will purchase natural gas from Williams Energy. Williams
Energy will sell to us the natural gas at prices specified in the power purchase
agreement, and we will sell to Williams Energy at the Electric Delivery Point
any Net Electric Energy produced during those periods at 90% of the Energy
Market Clearing Price.



         Williams Energy will be entitled to an annual fuel conversion volume
rebate if its dispatch of our facility exceeds specified levels and specified
monthly non-dispatch payments if, under specific circumstances, our facility is
not available for dispatch. All fuel conversion volume rebate payments and
non-dispatch payments must be made to Williams Energy after debt service and
specified other payments but prior to any distribution to holders of the equity
interests in our company. Fuel conversion volume rebate payments must be paid to
Williams Energy within 30 days after the end of the contract year in which the
payments have been earned and non-dispatch payments must be paid to Williams
Energy within 20 days after the end of the month on which a payment obligation
arises. Fuel conversion volume rebate payments and any non-dispatch payments
owed to Williams Energy and not paid when due must be paid, together with
interest, when funds become available to us at the priority level described
above.


Project Development


         Our facility will be located at the facility site. If we are unable to
obtain all required permits and approvals for the site within one year after the
execution date of the power purchase agreement, however, the parties must in
good faith seek to identify a mutually agreeable alternative site within the PJM
power pool market to be acquired by us as a location for our facility.
Furthermore, if the alternate site is not agreed to by the parties within an
additional one-year period, the power purchase agreement will terminate with no
further liability to either party.



         We must provide to Williams Energy within 10 days after the completion
of Initial Start-Up Testing, pertinent written data substantiating our
facility's capability to provide net capacity.




                                       45
<PAGE>


         We must, at our own cost and expense, obtain as and when required all
approvals, permits, licenses and other authorizations from governmental
authorities as may be required to construct, operate and maintain our facility,
the Interconnection Facilities and Protective Gas Apparatus and to perform our
obligations under the power purchase agreement, and during the term, we must
obtain all additional governmental approvals, permits, licenses and
authorizations as may be required with respect to our facility as soon as
practicable.


Initial Start-Up Testing; Commercial Operation


         We must provide to Williams Energy (1) written notice, at least 30 days
in advance, of the expected commercial operation date and (2) a copy of the
notice of commercial operation within five days after the commercial operation
date. Williams Energy will have the right to be present at Initial Start-Up
Testing of our facility.


Interconnection and Metering Equipment


         At our sole cost and expense, we will own and design, construct,
install and maintain, or be responsible for the design, construction,
installation and maintenance of our facility, the Interconnection Facilities and
Protective Gas Apparatus needed to generate and deliver Net Electric Energy
and/or ancillary services to the Electric Delivery Point in order to fulfill our
obligations under the power purchase agreement, including all Interconnection
Facilities and Protective Gas Apparatus that may be located at any switchyard
and/or substation to be built at our facility. Our facility, the Interconnection
Facilities and Protective Gas Apparatus must be designed, constructed and
completed in a good and workmanlike manner and in accordance with accepted
electrical practices, with respect to our facility and Interconnection
Facilities, or in accordance with standard gas industry practices, with respect
to Protective Gas Apparatus, so that the expected useful life of our facility,
the Interconnection Facilities and Protective Gas Apparatus will be not less
than the term of the power purchase agreement.



         We will be solely responsible for the negotiation and execution of the
interconnection agreement with Metropolitan Edison under which Metropolitan
Edison will own and be responsible for the Electric Metering Equipment and the
design, installation, construction and maintenance of the electrical facilities
and protective apparatus, including any transmission equipment and related
facilities, necessary to interconnect Metropolitan Edison's electrical system
with our facility at the Electric Delivery Point. Williams Energy must reimburse
us for the reasonable Metropolitan Edison costs (i.e., transmission facility
upgrades, Metropolitan Edison protective apparatus and other equipment,
Metropolitan Edison electric meters, and Metropolitan Edison costs for PJM and
other required interconnection-related studies) incurred, or to be reimbursed,
by us under the interconnection agreement up to a maximum amount which is in
excess of the costs anticipated to be incurred by us under the interconnection
agreement.



         Williams Energy will be responsible for the installation, maintenance
and testing of the Gas Metering Equipment, to the extent not otherwise
installed, maintained and tested by the supplier of gas transportation services,
and Oil Metering Equipment, as reasonably approved by us.



         All Electric Metering Equipment, Gas Metering Equipment and Oil
Metering Equipment, whether owned by us or by a third party, must be operated,
maintained and tested in accordance with accepted electrical practices, in the
case of the Electric Metering Equipment, and in accordance with applicable
industry standards, in the case of the Gas Metering Equipment and Oil Metering
Equipment.


Operation; Dispatch


         Our facility, the Interconnection Facilities and the Protective Gas
Apparatus must be operated in accordance with accepted electrical practices and
applicable requirements and guidelines reasonably adopted by Metropolitan Edison
from time to time and applied consistently to Metropolitan Edison's electric
generating facilities, with respect to our facility and Interconnection
Facilities, or in accordance with standard gas industry practices, with respect
to Protective Gas Apparatus. If a conflict between the terms and conditions of
the power purchase agreement and Metropolitan Edison requirements, Metropolitan
Edison requirements will control.



         We must operate our facility in parallel with Metropolitan Edison's
electrical system with governor control and the Net Electric Energy to be
delivered by us under the power purchase agreement must be three-phase, 60
hertz, alternating current at a nominal voltage acceptable to Metropolitan
Edison at the Electric Delivery Point, must not adversely affect the voltage,
frequency, waveshape or Power Factor of power at the Electric Delivery Point and
must be delivered to the Electric Delivery Point in a manner acceptable to
Metropolitan Edison.



         The power purchase agreement acknowledges that Metropolitan Edison has
the right to require us to disconnect our facility from Metropolitan Edison's
electrical system, or otherwise curtail, interrupt or reduce deliveries of Net



                                       46
<PAGE>

Electric Energy, for specific safety or emergency reasons. If our facility has
been disconnected for these reasons, Williams Energy will continue to be
obligated to make total fixed payments for at least 24 hours after the
occurrence of the disconnection of our facility by Metropolitan Edison.



         We must use commercially reasonable efforts to promptly correct any
condition at our facility which necessitates the disconnection of our facility
from Metropolitan Edison's electrical system or the reduction, curtailment or
interruption of electrical output of our facility.



         Williams Energy will have the exclusive right to schedule the operation
of our facility or a unit in accordance with the provisions of the power
purchase agreement so long as the scheduling is consistent with the design
limitations of our facility, applicable law, regulations and permits, and
manufacturers' reasonable recommendations for operating limits with respect to
our facility and major components.



         During Initial Start-Up Testing and up to two times each year
thereafter, we must demonstrate, in accordance with the then-applicable criteria
of PJM, applicable generally to independent power and Metropolitan Edison
generating facilities in PJM of similar technology, the capability of our
facility to produce and maintain, as required for the demonstration, our
facility's net capacity.


Maintenance


         At all times during the term of the power purchase agreement, we must,
at our sole cost and expense, maintain our facility, the Protective Gas
Apparatus, and, consistent with the terms of the interconnection agreement, the
Interconnection Facilities. Maintenance must be performed in accordance with
accepted electrical practices, with respect to our facility and Interconnection
Facilities, or in accordance with standard gas industry practices, with respect
to Protective Gas Apparatus, and manufacturers' recommended maintenance
procedures and in accordance with the maintenance provisions of the power
purchase agreement.


Metering, Billing, Payment and Taxes


         Net Electric Energy delivered by us to Williams Energy must be metered
at the Electric Delivery Point, using Metropolitan Edison's Electric Metering
Equipment on an hour-by-hour basis, or any shorter intervals as may be necessary
to implement the power purchase agreement, are technically feasible using the
metering equipment, and are agreed to by Metropolitan Edison.



         We must provide to Williams Energy a monthly statement using
Metropolitan Edison's meters, or back-up Electric Metering Equipment installed
by us if Metropolitan Edison's electric meters are not functional. The statement
must describe the amount of Net Electric Energy delivered by us to Williams
Energy in each hour and the computation of the amount due from Williams Energy
to us and any other amounts as may then be due and payable by Williams Energy to
us. Williams Energy must pay us the net amount shown to be due to us on the
monthly statement.



         Except as otherwise specified in the power purchase agreement, each
party will have the right to set off against any and all amounts owed by it
under the power purchase agreement past due amounts owed to it under the power
purchase agreement by the other party.



         The payments by Williams Energy to us do not include reimbursement for,
and Williams Energy is liable for and must pay, cause to be paid, or reimburse
us if we have paid, all taxes imposed on or with respect to natural gas or fuel
oil or the use or consumption or transportation, other than any of the taxes for
which we are liable as described in the following paragraph or on Net Electric
Energy or the use and consumption thereof after the Electric Delivery Point.
Williams Energy must indemnify, defend and hold us harmless from any liability
for these taxes.



         Except as provided in the previous paragraph and except for specified
taxes that may be imposed in the future, the payments by Williams Energy to us
include full reimbursement for, and we will be liable for and must pay, or cause
to be paid, or reimburse Williams Energy if Williams Energy has paid, all taxes.
If Williams Energy is required to remit any tax for which we are responsible,
the amount must be deducted from any sums due to us. We must indemnify, defend
and hold harmless Williams Energy from any liability for these taxes.


Dispute Resolution


         If the parties are in dispute with respect to specified matters
relating to the term, Gas Interconnection Facilities, maintenance and billing
and metering, and they do not resolve the dispute within seven days of notifying
the other party in writing of the existence of the dispute, a committee
consisting of two officers of each party must meet and attempt in good faith to
resolve the dispute. If the committee does not resolve the dispute within seven
days following their initial


                                       47
<PAGE>

meeting, then a single third-party engineer must be designated to consider and
decide the issues raised by the dispute unless both parties determine that
further discussions by the committee are merited. The selection of the
third-party engineer must be made from the list of engineers described in the
power purchase agreement.



         Each party must designate in writing to the other party from time to
time a representative who must be authorized to resolve any dispute relating to
the subject matter of the power purchase agreement not referred to in the
preceding paragraph.



         If any dispute is not resolved between the parties within 30 days from
the date on which a party provided to the other party a written notice of the
dispute, then the dispute must be settled exclusively and finally by arbitration
in accordance with the procedures described in the power purchase agreement,
except for disputes described in the second preceding paragraph.



         The dispute resolution provisions of the power purchase agreement will
survive the termination or expiration of the power purchase agreement.


Insurance


         We must keep our facility continuously insured against loss or damage
in the amounts and for the risks that property of similar character is usually
so insured by entities owning and operating like properties.



         We and the operator of our facility must each procure or cause to be
procured and must maintain in effect continuously during the term of the power
purchase agreement minimum insurance coverage for our facility: workers'
compensation; employer's liability; commercial general liability; bodily injury;
property damage; blanket contractual; underground, explosion and collapse
hazard; products and completed operations hazard; broad form property damage;
personal injury; automobile liability, bodily injury and property damage; and
commercial umbrella liability.



         We must procure and maintain in effect continuously during the term of
the power purchase agreement, "all risk" property insurance in sufficient
amounts to cover and otherwise insure for the full replacement cost of our
facility and business interruption insurance covering 100% of our continuing
fixed operating expenses and debt service for a period of at least 12 months
arising from any loss insured against by our "all risk" property insurance.


Force Majeure


         A party will be excused from performing its obligations under the power
purchase agreement and will not be liable in damages or otherwise to the other
party if and to the extent the party declares that it is unable to perform or is
prevented from performing an obligation under the power purchase agreement by a
force majeure condition, except for any obligations and/or liabilities under the
power purchase agreement to pay money, which will not be excused, and except to
the extent an obligation accrues prior to the occurrence or existence of a force
majeure condition so long as:


         o        the party declaring its inability to perform by virtue of
                  force majeure, as promptly as practicable after the occurrence
                  of the force majeure condition, but in no event more than five
                  days later, gives the other party written notice describing,
                  in detail, the nature, extent and expected duration of the
                  force majeure condition;

         o        the suspension of performance is of no greater scope and of no
                  longer duration than is reasonably required by the force
                  majeure condition;

         o        the party declaring force majeure uses all commercially
                  reasonable efforts to remedy its inability to perform; and


         o        once the party declaring force majeure is able to resume
                  performance of its obligations excused as a result of the
                  force majeure condition, it promptly gives written notice to
                  the other party.



         Irrespective of whether the force majeure condition is declared by
Williams Energy or us, the time period of a force majeure will be excluded from
the calculation of all payments under the power purchase agreement and Williams
Energy must be under no obligation to pay us any of the payments described in
the power purchase agreement. If Williams Energy declares a force majeure,
however, it must, subject to its right to terminate the power purchase agreement
if the force majeure has not been fully corrected or alleviated within 18 months
of the declaration, continue to pay us only the applicable monthly total fixed
payment as described in the power purchase agreement until the earlier of (1)
the termination of the force majeure condition or (2) the termination of the
power purchase agreement. Furthermore, if we declare a force majeure due to an
action or inaction of Metropolitan Edison that prevents us from delivering Net



                                       48
<PAGE>

Electric Energy to the Electric Delivery Point, Williams Energy must continue to
pay the applicable portion of the total fixed payment for the first 24 hours of
the period.



         Notwithstanding anything to the contrary contained in the power
purchase agreement, except as may expressly be provided in the power purchase
agreement, the term force majeure will not include the following nor will the
following excuse a party's performance:



         o        The failure to complete our facility by or to achieve the
                  commercial operation date as extended under the power purchase
                  agreement, which failure is caused by, arises out of or
                  results from the acts or omissions of us, and/or from the acts
                  or omissions of any third party, unless, and then only to the
                  extent that, any acts or omissions of the third party (1)
                  would itself be excused under the power purchase agreement by
                  virtue of a force majeure condition, or (2) is the result of a
                  failure of Williams Energy to provide fuel to our facility
                  under the power purchase agreement;



         o        Any reduction, curtailment or interruption of generation or
                  operation of our facility, or of the ability of Williams
                  Energy to accept or transmit Net Electric Energy, whether in
                  whole or in part, which reduction, curtailment or interruption
                  is caused by or arises from the acts or omissions of any third
                  party providing services or supplies to the party claiming
                  force majeure, including any vendor or supplier to either
                  party of materials, equipment, supplies or services, or any
                  inability of Metropolitan Edison to deliver Net Electric
                  Energy to Williams Energy, unless, and then only to the extent
                  that, any acts or omissions would itself be excused under the
                  power purchase agreement as a force majeure;


         o        Any outage, whether or not due to the fault or negligence of
                  us, of our facility attributable to a defect or inadequacy in
                  the manufacture, design or installation of our facility that
                  prevents, curtails, interrupts or reduces the ability of our
                  facility to generate Net Electric Energy or the ability of us
                  to perform our obligations under the power purchase agreement;
                  or


         o        To the extent that the party claiming force majeure failed to
                  prevent or remedy the force majeure condition by taking all
                  commercially reasonable acts, short of litigation if the
                  remedy requires litigation, and, except as otherwise provided
                  in the power purchase agreement, failed to resume performance
                  under the power purchase agreement with reasonable dispatch
                  after the termination of the force majeure condition; or


         o        To the extent that the claiming party's failure to perform was
                  caused by lack of funds; or

         o        To the extent Williams Energy is unable to perform due to a
                  shortage of natural gas or fuel oil supply not caused by an
                  event of force majeure; or


         o        Because of an increase or decrease in the market price of
                  electric energy/capacity, natural gas or fuel oil, or because
                  it is uneconomic for the party to perform its obligations
                  under the power purchase agreement.



         Neither party will be required to settle any strike, walkout, lockout
or other labor dispute on terms which, in the sole judgment of the party
involved in the dispute, are contrary to its interest.



         Williams Energy will have the right to terminate the power purchase
agreement if a force majeure has been declared by us and the effect of the force
majeure has not been fully corrected or alleviated within 18 months after the
date the force majeure was declared. Williams Energy, however, will not have the
right to terminate the power purchase agreement if (1) the force majeure was
caused by Williams Energy or (2) the force majeure event does not prevent or
materially limit Williams Energy's ability to sell our facility's net capacity
into or through the PJM power pool market or to a third party.


Events of Default; Termination; Remedies


         The following will constitute events of default under the power
purchase agreement:


         o        breach of any term or condition of the power purchase
                  agreement, including, but not limited to, (1) any failure to
                  maintain or to renew any security, (2) any breach of a
                  representation, warranty or covenant or (3) failure of either
                  party to make a required payment to the other party;


         o        our facility is not available to provide fuel conversion
                  services to Williams Energy during any period of 180
                  consecutive days after the commercial operation date, except
                  as may be excused by force majeure or the absence of available
                  natural gas, or if the non-availability is caused by act or
                  failure by Williams Energy where the action is required by the
                  power purchase agreement;




                                       49
<PAGE>

         o        we sell or supply Net Electric Energy, ancillary services or
                  capacity from our facility, or agree to do the same, to any
                  person or entity other than Williams Energy, without the prior
                  approval of Williams Energy;

         o        failure by us for 30 consecutive days to perform regular and
                  required maintenance, testing or inspection of the
                  Interconnection Facilities, our facility and/or other electric
                  equipment and facilities;


         o        failure by us for 30 consecutive days to correct or resolve a
                  material violation of any code, regulation and/or statute
                  applicable to the construction, installation, operation or
                  maintenance of our facility, the Interconnection Facilities,
                  Protective Gas Apparatus or any other electric equipment and
                  facilities required to be constructed and operated under the
                  power purchase agreement when the violation impairs our
                  continued ability to perform under the power purchase
                  agreement;


         o        involuntary bankruptcy or insolvency of either party and
                  continues for more than 60 days;

         o        voluntary bankruptcy or insolvency by either party;

         o        any modifications, alterations or other changes to our
                  facility by or on behalf of us which prevent us from
                  fulfilling, or materially diminishes our ability to fulfill,
                  our obligations, duties, rights and responsibilities under the
                  power purchase agreement and which after reasonable notice and
                  opportunity to cure, are not corrected;


         o        there will be outstanding for more than 60 days any
                  unsatisfied final, non-appealable judgment against us in an
                  amount exceeding $500,000, unless the existence of the
                  unsatisfied judgment does not materially affect our ability to
                  perform our obligations under the power purchase agreement;
                  and



         o        (1) The AES Corporation will cease to own, directly or
                  indirectly, beneficially and of record, at least 50 percent of
                  the equity interests in our company or will cease to possess
                  the power to direct or cause the direction of our management
                  or policies or (2) any person or an affiliate, other than The
                  AES Corporation or an affiliate, authorized to act as a power
                  marketer by FERC will own, directly or indirectly,
                  beneficially or of record, any of the equity interests in our
                  company.



         Upon the occurrence of any event of default, other than an event of
default for voluntary bankruptcy or insolvency, for which no notice will be
required or opportunity to cure permitted, the party not in default, to the
extent the party has actual knowledge of the occurrence of the event of default,
must give prompt written notice of the default to the defaulting party. The
notice must describe, in reasonable detail, the nature of the default and, where
known and applicable, the steps necessary to cure the default. The defaulting
party must have 30 days, but only two business days in the case of a default for
failure to make a requested payment to the non-defaulting party under the power
purchase agreement, following receipt of the notice either to cure the default
or commence in good faith all the steps as are necessary and appropriate to cure
the default if the default cannot be completely cured within the 30-day period.



         If the defaulting party fails to cure the default or take the steps as
provided under the preceding paragraph, and immediately upon the occurrence of
any event of default for voluntary bankruptcy or insolvency, the power purchase
agreement may be terminated by the non-defaulting party, without any liability
or responsibility whatsoever, by written notice to the party in default. The
non-defaulting party may exercise all the rights and remedies as are available
to it to recover damages caused by the default.


Security


         We agreed to compensate Williams Energy for any actual damages it
suffers or incurs as the result of its reliance upon the delivery of our
facility's net capacity, ancillary services and fuel conversion services, to the
extent the damages cannot be mitigated fully. We further agreed that the damages
Williams Energy may suffer under these circumstances will be any and all
reasonable costs incurred by Williams Energy in excess of costs that would have
been incurred had the commercial operation date occurred on or before June 30,
2001, as the date may be extended under the power purchase agreement.



         As required by the power purchase agreement, we have provided to
Williams Energy a guaranty of our performance and payment obligations under the
power purchase agreement from The AES Corporation in the amount of $30 million,
which guaranty must terminate on the commercial operation date. At any time that
The AES Corporation's senior unsecured debt is no longer rated investment grade
by Standard & Poor's or Moody's, or at any time at our option, we must provide
the financial security for the guaranty amount as specified in the following
paragraph. Upon the provision of the guaranty or other financial security
referred to in this paragraph, the guaranty provided by The AES Corporation
under the provisions of the original power purchase agreement must be canceled
and returned to us.




                                       50
<PAGE>


         We must provide to Williams Energy, within 30 days after a reduction in
the unsecured debt rating of The AES Corporation as described above, or at any
time if payment is so secured at our option, security in the form of a single
letter of credit, satisfactory to Williams Energy in form and substance, upon
which Williams Energy may draw if our facility does not achieve the commercial
operation date by the date specified in the power purchase agreement, as the
date may be extended. If the security contains an expiration date, either
express or implied, we must renew the security not later than 30 days prior to
the expiration date and must contemporaneously provide written notice of the
renewal to Williams Energy. If we fail to renew the security as described above,
Williams Energy is entitled to demand and receive payment thereunder on or after
three days after written notice of the failure is provided to us, and in the
event the amount so drawn must be deposited in an interest bearing escrow
account and must be returned to us at the commercial operation date unless
otherwise drawn on by Williams Energy in satisfaction of our obligations under
the preceding security provisions. The requirement for the security must
terminate upon the commercial operation date.



         Williams Energy has provided to us a guarantee, issued by The Williams
Companies, Inc., of Williams Energy's performance and payment obligations under
the power purchase. If The Williams Companies, Inc. is no longer rated
investment grade, however, the guarantee must, within 30 days after the loss of
the rating, be replaced by a guarantee from another affiliate of Williams Energy
that is rated investment grade or by other security acceptable to us, including
a letter of credit which meets the requirements of the power purchase agreement.


Assignment

         Generally, neither the power purchase agreement nor any rights, duties,
interests or obligations thereunder may be assigned, transferred, pledged or
otherwise encumbered or disposed of, by operation of law or otherwise without
the prior written consent of the other party.


         We agreed that we will not sell, transfer, assign, lease or otherwise
dispose of our facility or any substantial portion thereof or interest therein
necessary to perform our obligations under the power purchase agreement to any
person that is a FERC-authorized power marketer or an affiliate without the
prior written consent of Williams Energy, which consent must not be unreasonably
withheld.


                             Construction Agreement

         We, as assignee of AES Ironwood, Inc., have entered into an Agreement
for Engineering, Procurement and Construction Services, dated as of September
23, 1998, as amended, with Siemens Westinghouse for Siemens Westinghouse to
perform services in connection with the design, engineering, procurement, site
preparation and clearing, civil works, construction, start-up, training and
testing and to provide all materials and equipment (excluding operational spare
parts), machinery, tools, construction fuels, chemicals and utilities, labor,
transportation, administration and other services and items (collectively and
separately, the "Services") for our facility.

Siemens Westinghouse's Services and Other Obligations


         Siemens Westinghouse must complete our project by performing or causing
to be performed all of the Services. The Services will include: engineering and
design; construction and construction management; providing design documents,
instruction manuals, a project procedures manual and quality assurance plan;
procurement of all materials, equipment and supplies and all contractor and
subcontractor labor and manufacturing and related services; providing a spare
parts list; providing all labor and personnel; obtaining some applicable permits
and providing information to assist us in obtaining other applicable permits;
performing inspection, expediting, quality surveillance and traffic services;
transporting, shipping, receiving and marshalling all materials, equipment and
supplies and other items; providing storage for all materials, supplies and
equipment and procurement or disposal of all soil and gravel (including
remediation and disposal of specific hazardous materials); providing for design,
construction and installation of Electrical Interconnection Facilities
(including Electric Metering Equipment, automatic regulation equipment,
Protective Apparatus and control system equipment) and reviewing other
Metropolitan Edison interconnections to our facility (including gas and water
pipelines); performing Performance Tests and Power Purchase Agreement Output
Tests; providing for start-up and initial operation functions; providing
specified spare parts, waste disposal services, chemicals, consumables and
utilities.



         The Services will also include: training our personnel prior to
Provisional Acceptance; providing us and our designee with access to the
facility site; obtaining additional necessary real estate rights; clean-up and
waste disposal (including hazardous materials brought to the facility site by
Siemens Westinghouse or the subcontractors); submitting a construction schedule
and progress reports; payment of contractor taxes; employee identification and
security arrangements; protecting adjoining utilities and public and private
lands from damage; paying appropriate royalties and license fees; providing
final releases and waivers to us; posting collateral or providing other
assurances if major


                                       51
<PAGE>

subcontractors fail to furnish final waivers; maintaining labor relations and
project labor agreements; providing further assurances; coordinating with other
contractors; and causing Siemens Corporation to execute and deliver the related
guaranty.


Construction and Start-Up


         Except for specific Services the performance of which has already
commenced, Siemens Westinghouse must commence performance of the Services on the
date specified in our notice to proceed. Siemens Westinghouse must perform the
Services in accordance with prudent utility practices, generally accepted
standards of professional care, skill, diligence and competence applicable to
engineering, construction and project management practices, all applicable laws,
all applicable permits, the real estate rights, the quality assurance plan,
Metropolitan Edison electrical interconnection requirements, the environmental
requirements and safety precautions described in the construction agreement, and
all of the requirements necessary to maintain the warranties granted by the
subcontractors under the construction agreement. Siemens Westinghouse must
perform the Services in accordance with our construction schedule and must cause


         o        each Construction Progress Milestone to be achieved on or
                  prior to the applicable Construction Progress Milestone Date,

         o        either Provisional Acceptance or Interim Acceptance of our
                  facility to occur on or prior to the Guaranteed Provisional
                  Acceptance Date and

         o        Final Acceptance of our facility to occur on or before the
                  Guaranteed Final Acceptance Date.


         Siemens Westinghouse must perform the Services so that our facility,
when operated in accordance with the instruction manual and the Power Purchase
Agreement Operating Requirements, regardless of whether our facility is operated
at 705 megawatts or at a different output, on natural gas and on fuel oil,
respectively, as of Provisional Acceptance, Interim Acceptance and Final
Acceptance, will comply with all applicable laws and applicable permits,
Metropolitan Edison electrical interconnection requirements and the Guaranteed
Emissions Limits in accordance with the Completed Performance Test requirements.


Contract Price and Payment


         The adjusted contract price, including base Scope Changes through the
date of the construction agreement, is $238 million and commencing on the
construction commencement date is to be paid in installments in accordance with
the Payment and Milestone Schedule. The contract price may be adjusted as a
result of Scope Changes. We must make scheduled payments to Siemens Westinghouse
upon receipt of Siemens Westinghouse's payment request unless the independent
engineer fails to confirm the matters certified to by Siemens Westinghouse in
the request, in which case we may defer the scheduled payments until the
condition is satisfied. We must withhold from each scheduled payment 5%, other
than our project completion payment, of the payment until after Final
Acceptance. At Final Acceptance, we must pay all Retainage except for $1,000,000
and 150% of the cost of completing all Punch List items. We must pay our project
completion payment, including all remaining Retainage within 30 days after
Project Completion. Upon the termination of the construction agreement, Siemens
Westinghouse will be entitled to a termination payment equal to the scheduled
payments due and owing, Retainage and termination costs incurred by Siemens
Westinghouse and subcontractors. We are not obligated to make any payment to
Siemens Westinghouse at any time Siemens Westinghouse is in material breach of
the construction agreement, unless Siemens Westinghouse is diligently pursuing a
cure. All payments are subject to release of claims.


Our Required Services

         Our responsibilities include: designating a representative for our
project; furnishing Siemens Westinghouse access to the facility site; securing
specified applicable permits and real estate rights; providing specified
start-up personnel; furnishing water, water delivery facilities, specified spare
parts, water disposal services and consumables; providing permanent utilities
for the start-up, testing and operation of our facility; providing fuel supply
arrangements; providing electrical interconnection facilities arrangements;
furnishing approvals; administering third-party contracts; causing The AES
Corporation to provide a pre-financial closing guaranty.


         If we fail to meet any of our obligations under the construction
agreement, then, to the extent that Siemens Westinghouse was reasonably delayed
in the performance of the Services as a direct result thereof, an equitable
adjustment to one or more of the contract price, the Guaranteed Completion
Dates, the Construction Progress Milestone Dates, the Payment and Milestone
Schedule and our construction schedule, and, as appropriate, the other
provisions of


                                       52
<PAGE>

the construction agreement that may be affected thereby, will be made by
agreement between us and Siemens Westinghouse.


Completion and Acceptance of our Project

Mechanical Completion


         Mechanical Completion will be achieved when:


         o        All equipment and facilities necessary for the full, safe and
                  reliable operation of our facility have been properly
                  constructed, installed, insulated and protected where
                  required, and correctly adjusted, and can be safely used for
                  their intended purposes in accordance with the instruction
                  manual and all applicable laws and applicable permits;

         o        The tests required for Mechanical Completion that are
                  identified in the construction agreement have been
                  successfully completed;

         o        Our facility is fully and properly interconnected and
                  synchronized with the electrical system of Metropolitan Edison
                  in accordance with Metropolitan Edison electrical
                  interconnection requirements, and all features and equipment
                  of our facility are capable of operating simultaneously; and


         o        The complete performance by Siemens Westinghouse of all the
                  Services relating to our facility under the construction
                  agreement, except for any remaining Punch List items,
                  Performance Tests, Power Purchase Agreement Output Tests and
                  Reliability Run, in compliance with the standards of
                  performance described in the construction agreement, so that
                  our facility meets all of the applicable requirements
                  described in the construction agreement but excluding the
                  achievement of the Guaranteed Emission Limits and the
                  Performance Guarantees.



         When Siemens Westinghouse believes that it has achieved Mechanical
Completion, it must deliver to us the Notice of Mechanical Completion. Within 10
days of receipt of the Notice of Mechanical Completion, if it is satisfied that
the Mechanical Completion requirements have been met, we must deliver to Siemens
Westinghouse a Mechanical Completion Certificate. If reasonable cause exists for
doing so, we must notify Siemens Westinghouse in writing that Mechanical
Completion has not been achieved, stating the reasons therefor. If Mechanical
Completion has not been achieved as so determined by us, Siemens Westinghouse
must promptly do so or perform the additional Services that will achieve
Mechanical Completion of our facility and must issue to us another Notice of
Mechanical Completion. The procedure must be repeated as necessary until
Mechanical Completion of our facility has been achieved.


Performance Tests and Power Purchase Agreement Output Tests


         Once Mechanical Completion has been achieved, Siemens Westinghouse must
perform the Performance Tests and Power Purchase Agreement Output Tests in
accordance with criteria described in the construction agreement. Siemens
Westinghouse must give us notice of the Performance Tests and Power Purchase
Agreement Output Tests. We must arrange for the disposition of output during
start-up and testing. Siemens Westinghouse may declare the Performance Test or
the Power Purchase Agreement Output Test to be a Completed Performance Test or a
Completed Power Purchase Agreement Output Test, respectively, if during the
tests the operation of our facility complies with applicable laws, applicable
permits, Guaranteed Emissions Limits and other required standards.


Provisional Acceptance


         Provisional Acceptance will be achieved when:


         o        Siemens Westinghouse has concluded a Completed Performance
                  Test in which our facility, while operating on natural gas,
                  demonstrates during a minimum of two 2-hour tests an average
                  net electrical output and a net heat rate of 95% (or higher)
                  of the natural gas-based Electrical Output Guarantee and 108%
                  (or lower) of the natural gas-based Heat Rate Guarantee;

         o        Siemens Westinghouse has concluded a Completed Power Purchase
                  Agreement Output Test in which our facility demonstrates (1) a
                  level of achievement of 95% (or higher) of the natural
                  gas-based Electrical Output Guarantee, while operating on
                  natural gas, and (2) to our reasonable satisfaction, the other
                  capabilities required to be demonstrated under the
                  construction agreement; and

         o        Our facility has achieved, and continues to satisfy, the
                  requirements of Mechanical Completion.



                                       53
<PAGE>


         When Siemens Westinghouse believes that it has achieved Provisional
Acceptance of our facility, it must deliver to us a Notice of Provisional
Acceptance. If we are satisfied that the Provisional Acceptance requirements
have been met, we must deliver to Siemens Westinghouse a Provisional Acceptance
Certificate. If reasonable cause exists for doing so, we must notify Siemens
Westinghouse in writing that Provisional Acceptance of our facility has not been
achieved, stating the reasons therefor. If we determine that Provisional
Acceptance of our facility has not been achieved, Siemens Westinghouse must
promptly do so or perform the additional Services as will achieve Provisional
Acceptance and, if Siemens Westinghouse believes that Provisional Acceptance of
our facility has been achieved, must issue to us another Notice of Provisional
Acceptance. Unless Interim Acceptance or Final Acceptance of our facility has
previously occurred, the procedure must be repeated as necessary until
Provisional Acceptance of our facility has been achieved. Upon the earliest to
occur of Provisional Acceptance, Interim Acceptance and Final Acceptance of our
facility, we must take possession and control our facility and will thereafter
be solely responsible for its operation and maintenance. After we take
possession and control of our facility, Siemens Westinghouse must have
reasonable access to our facility to complete the Services.


Interim Acceptance


         Interim Acceptance will be achieved when:



         o        Siemens Westinghouse has concluded a Completed Performance
                  Test in which our facility, while operating on natural gas,
                  demonstrates during the Performance Test an average net
                  electrical output and a net heat rate (each as measured and
                  corrected to the design operating conditions, all in
                  accordance with the procedures described in the construction
                  agreement) of 95% (or higher) of the natural gas-based
                  Electrical Output Guarantee (but in no event lower than the
                  percentage of the natural gas-based Electrical Output
                  Guarantee demonstrated by the applicable Completed Performance
                  Test and Completed Power Purchase Agreement Output Test at
                  Provisional Acceptance, if applicable) and 104% (or lower) of
                  the natural gas-based Heat Rate Guarantee;


         o        If neither Provisional Acceptance nor Interim Acceptance of
                  our facility has occurred, Siemens Westinghouse has completed
                  a Completed Power Purchase Agreement Output Test in accordance
                  with the construction agreement to be concluded in which our
                  facility demonstrates (1) a level of achievement of 95% (or
                  higher) of the natural gas-based Electrical Output Guarantee,
                  while operating on natural gas, and (2) to Metropolitan
                  Edison's reasonable satisfaction, the other capabilities
                  required to be so demonstrated under the construction
                  agreement;

         o        Our facility has achieved, and continues to satisfy the
                  requirements for the achievement of, Mechanical Completion;
                  and

         o        Siemens Westinghouse has completed performance of the Services
                  except for (1) Punch List items and (2) Services that are
                  required by the terms of the construction agreement to be
                  completed after the achievement of Interim Acceptance.


         When Siemens Westinghouse believes that it has achieved Interim
Acceptance of our facility, it must deliver to us a Notice of Interim
Acceptance. If we are satisfied that the Interim Acceptance requirements have
been met, we must deliver to Siemens Westinghouse an Interim Acceptance
Certificate. If reasonable cause exists for doing so, we must notify Siemens
Westinghouse in writing that Interim Acceptance of our facility has not been
achieved, stating the reasons therefor. If we determine that Interim Acceptance
has not been achieved, Siemens Westinghouse must promptly take the action or
perform the additional Services as will achieve Interim Acceptance and, if
Siemens Westinghouse believes that Interim Acceptance of our facility has been
achieved, must issue to us another Notice of Interim Acceptance. Unless Final
Acceptance of our facility must have previously occurred, the procedure must be
repeated as necessary until Interim Acceptance of our facility has been
achieved.


Final Acceptance


         Final Acceptance will be achieved when:



         o        Siemens Westinghouse has concluded a Completed Performance
                  Test in which our facility, while operating separately on
                  natural gas and on fuel oil, demonstrates during the
                  Performance Test an average net electrical output and a net
                  heat rate of 100% (or higher) of each of the corresponding
                  natural gas-based and fuel oil-based Electrical Output
                  Guarantees and 100% (or lower) of each of the corresponding
                  natural gas-based and fuel oil-based Heat Rate Guarantees;




                                       54
<PAGE>


         o        If neither Provisional Acceptance nor Interim Acceptance of
                  our facility has occurred or if we have requested that a new
                  Completed Power Purchase Agreement Output Test be conducted in
                  connection with Final Acceptance of our facility, Siemens
                  Westinghouse has concluded a Completed Power Purchase
                  Agreement Output Test in which our facility demonstrates (1) a
                  level of achievement of 100% (or higher) of the natural
                  gas-based Electrical Output Guarantee, while operating on
                  natural gas, and (2) to Metropolitan Edison's reasonable
                  satisfaction, the other capabilities required to be so
                  demonstrated under the construction agreement;


         o        our facility has achieved, and continues to satisfy the
                  requirements for the achievement of, Mechanical Completion;

         o        the Reliability Guarantee has been achieved under the
                  construction agreement; and

         o        Siemens Westinghouse has completed performance of the Services
                  except for (1) Punch List items and (2) Services that are
                  required by the terms of the construction agreement to be
                  completed after the achievement of Final Acceptance, such as
                  Siemens Westinghouse's warranty obligations.


         The Reliability Guarantee will have been achieved if and only if our
facility demonstrates an average equivalent availability of not less than 92%
while operating over a period of at least 45 consecutive days in accordance with
applicable laws, applicable permits, Metropolitan Edison electrical
interconnection requirements, the Power Purchase Agreement Operating
Requirements, the Guaranteed Emissions Limits, the instruction manual and the
power purchase agreement.



         When Siemens Westinghouse believes that it has achieved Final
Acceptance of our facility, it must deliver to us a Notice of Final Acceptance.
If we are satisfied that the Final Acceptance requirements have been met, we
must deliver to Siemens Westinghouse a Final Acceptance Certificate. If
reasonable cause exists for doing so, we must notify Siemens Westinghouse in
writing that Final Acceptance has not been achieved, stating the reasons
therefor. If we determine that Final Acceptance has not been achieved, Siemens
Westinghouse must promptly do so or perform the additional Services as will
achieve Final Acceptance and must issue to us another Notice of Final
Acceptance. The procedure must be repeated as necessary until Final Acceptance
has been achieved or deemed to have occurred.



         At any time, by giving notice to Siemens Westinghouse, we, in our sole
discretion may elect to effect Final Acceptance, in which case Final Acceptance
will be deemed effective as of the date of the notice, and Siemens Westinghouse
will have no liability to us for any amounts thereafter arising as Performance
Guarantee Payments, other than any Interim Period rebates that arose prior to
the election by us, for failure of our facility to achieve any or all of the
applicable Performance Guarantees.



         At any time after Provisional Acceptance or Interim Acceptance of our
facility has been achieved, Siemens Westinghouse may, after exhausting all
reasonable repair and replacement alternatives in order to achieve the
applicable Performance Guarantees for Final Acceptance, so long as the
Reliability Guarantee will have been achieved, give to us notice of its
intention to elect to declare Final Acceptance. In that event, Siemens
Westinghouse may elect to use the results of the most recent eligible Completed
Performance Test for the purpose of determining our facility's level of
achievement of the Performance Guarantees. Final Acceptance will be deemed
effective as of the last to occur of (1) the date of our receipt of the
declaration and report of the final Completed Performance Test, or, as
applicable, the most recent Completed Performance Test, (2) the date of our
receipt of the declaration and report of any additional Completed Power Purchase
Agreement Output Test required by us in connection with Final Acceptance and (3)
the effective date of the achievement of the Reliability Guarantee.



         If on or before the Guaranteed Final Acceptance Date (1) our facility
has achieved either Provisional Acceptance or Interim Acceptance, (2) the most
recent Completed Performance Test has satisfied the relevant provisions of the
construction agreement and (3) the Reliability Guarantee has been achieved, then
Final Acceptance of our facility will be deemed to occur on the Guaranteed Final
Acceptance Date. If (1) on or before the Guaranteed Final Acceptance Date, our
facility has achieved at least Provisional Acceptance or Interim Acceptance and
has achieved all other requirements for Final Acceptance except for the
Reliability Guarantee and (2) within 90 days after the Guaranteed Final
Acceptance Date, the Reliability Guarantee has been achieved and all other
requirements for Final Acceptance continue to be satisfied at that time, then
Final Acceptance of our facility will be deemed to occur on the date on which
the Reliability Guarantee is achieved.


Project Completion


         Project Completion will be achieved under the construction agreement
when:




                                       55
<PAGE>


         o        Final Acceptance of our facility will have occurred and the
                  Performance Guarantees with respect to our facility will have
                  been achieved, or in lieu of achievement of the Performance
                  Guarantees, applicable rebates under the construction
                  agreement will have been paid, we will have elected Final
                  Acceptance;



         o        The Reliability Guarantee will have been achieved;



         o        Siemens Westinghouse will have demonstrated during the
                  Completed Performance Test that the operation of our facility
                  does not exceed the Guaranteed Emissions Limits;



         o        The requirements for achieving Mechanical Completion of our
                  facility will continue to be met;



         o        The Punch List items will have been completed in accordance
                  with the construction agreement; and



         o        Siemens Westinghouse will have performed all of the Services,
                  other than those Services, such as Siemens Westinghouse's
                  warranty obligations, which by their nature are intended to be
                  performed after Project Completion.



         When Siemens Westinghouse believes that it has achieved Project
Completion, it must deliver to us a Notice of Project Completion. If we are
satisfied that the Final Acceptance requirements have been met, we must deliver
to Siemens Westinghouse a Project Completion Certificate. If reasonable cause
exists for doing so, we must notify Siemens Westinghouse in writing that Project
Completion has not been achieved, stating the reasons therefor. If our Project
Completion has not been achieved as so determined by us, Siemens Westinghouse
must promptly take do so or perform the additional Services as will achieve
Project Completion and must issue to us another Notice of Project Completion.
The procedure must be repeated as necessary until Project Completion is
achieved.



         Siemens Westinghouse will be obligated to achieve Project Completion
within 180 days after Final Acceptance of our facility. If Siemens Westinghouse
does not achieve our Project Completion on or before our Project Completion
Deadline or if we determine that Siemens Westinghouse is not proceeding with all
due diligence to complete the Services in order to achieve Project Completion by
the deadline, we may retain another contractor to complete the work at
contractor's expense.


Price Rebate for Failure to Meet Guarantees

Completion Dates


         Siemens Westinghouse guarantees that (1) at least one of Provisional
Acceptance, Interim Acceptance or Final Acceptance of our facility will be
achieved on or before the Guaranteed Provisional Acceptance Date and (2) Final
Acceptance of our facility will be achieved on or before the Guaranteed Final
Acceptance Date.



         If none of Provisional Acceptance, Interim Acceptance or Final
Acceptance of our facility occurs by the date that is 45 days after the
Guaranteed Provisional Acceptance Date, Siemens Westinghouse must pay us
$110,000 per day for each day Provisional Acceptance, Interim Acceptance or
Final Acceptance is later than the Guaranteed Provisional Acceptance Date, but
in no event will the aggregate amount of the payments be greater than the Delay
LD SubCap.



         If none of Provisional Acceptance, Interim Acceptance and Final
Acceptance of our facility occurs on or before the date that is 40 days after
the Guaranteed Provisional Acceptance Date, Siemens Westinghouse must, on the
date, submit for approval by us and the independent engineer a Plan to
accelerate the performance of the Services as necessary in order to achieve (1)
at least one of Provisional Acceptance, Interim Acceptance and Final Acceptance
of our facility by the date that is 12 months after the Guaranteed Provisional
Acceptance Date and (2) Final Acceptance of our facility by the Guaranteed Final
Acceptance Date. If the Plan is not approved by us and the independent engineer,
Siemens Westinghouse must revise the Plan and resubmit a revised Plan for
approval by us and the independent engineer.



         If Provisional Acceptance, Interim Acceptance and Final Acceptance,
whichever is the earlier to occur, of our facility occurs prior to the
Guaranteed Provisional Acceptance Date, we must pay Siemens Westinghouse $50,000
per day as an early completion bonus, for each day by which Provisional
Acceptance, Interim Acceptance and Final Acceptance precedes the Guaranteed
Provisional Acceptance Date, but in no event will the aggregate amount of the
bonus exceed $3,000,000.




                                       56
<PAGE>

Performance Guarantees

Electrical Output


         If the average net electrical output of our facility at Provisional
Acceptance or Interim Acceptance, whichever is the earlier to occur, is less
than the natural gas-based Electrical Output Guarantee, then Siemens
Westinghouse must pay us, as a rebate, for each day during the Interim Period,
an amount equal to $0.22 per day for each kilowatt by which the average net
electrical output is less than the natural gas-based Electrical Output
Guarantee.



         Upon Final Acceptance, if (1) the average net electrical output of our
facility during the natural gas-fired portion of the Completed Performance Test
is less than the natural gas-based Electrical Output Guarantee, then we must pay
Siemens Westinghouse, as a rebate, an amount equal to $550 for each kilowatt by
which the average net electrical output is less than the natural gas-based
Electrical Output Guarantee and (2) the fuel oil-based portion of the Completed
Performance Test is less than the fuel oil-based Electrical Output Guarantee,
then Siemens Westinghouse must pay us, as a rebate, an amount equal to $30 for
each kilowatt by which the average net electrical output is less than the fuel
oil-based Electrical Output Guarantee.



         Upon Final Acceptance, if the average net electrical output of our
facility during the natural gas-fired portion of the Completed Performance Test
is greater than the natural gas-based Electrical Output Guarantee, then Siemens
Westinghouse must pay us as a bonus, an amount equal to 50% of the net
incremental revenues received by us during the period of the first three years
following the commercial operation date as a result of (1) any power purchase
agreement concluded with a utility whereby the utility purchases the excess
output, (2) any short-term sales of the excess output, and (3) any spot sales of
the excess output, in each of the cases (1) through (3) above after subtracting
all incremental costs and taxes associated with the excess output, so long as
the aggregate amount of any bonus does not in any event exceed $275 per kilowatt
of excess capacity.


Heat Rate Guarantees


         If the average net heat rate of our facility at Provisional Acceptance
and/or Interim Acceptance, if having occurred before Final Acceptance, exceeds
the natural gas-based Heat Rate Guarantee, then Siemens Westinghouse must pay
us, as a rebate, for each day during the Interim Period, an amount equal to $44
per day for each BTU/KwH by which the measured net heat rate is greater than the
natural gas-based Heat Rate Guarantee.



         Upon Final Acceptance, if the net heat rate of our facility during (1)
the natural gas-fired portion of the Completed Performance Test exceeds the
natural gas-based Heat Rate Guarantee, then Siemens Westinghouse must pay us, as
a rebate, an amount equal to $162,300 for each BTU/KwH by which the measured
heat rate is greater than the natural gas-based Heat Rate Guarantee, and (2) the
fuel oil-fired portion of the Completed Performance Test exceeds the natural
gas-based Heat Rate Guarantee, then Siemens Westinghouse must pay us, as a
rebate, an amount equal to $17,000 for each BTU/KwH by which the measured heat
rate is greater than the fuel oil-based Heat Rate Guarantee.



         Upon Final Acceptance, if the average net heat rate during the natural
gas-fired portion of the Completed Performance Test is less than the natural
gas-based Heat Rate Guarantee, then we must pay Siemens Westinghouse, as a
bonus, an amount equal to $40,000 for each BTU/KwH by which the measured heat
rate is less that the natural gas-based Heat Rate Guarantee so long as that the
aggregate amount of any bonus does not in any event exceed $3,000,000.


Liability and Damages

Limitation of Liability


         In no event will Siemens Westinghouse's liability exceed (1) the Delay
LD SubCap and (2) the Total LD SubCap.


Consequential Damages


         Neither party nor any of its contractors, subcontractors or other
agents providing equipment, material or services for our project will be liable
for any indirect, incidental, special or consequential loss or damage of any
type.


Aggregate Liability of Contractor


         The total aggregate liability of Siemens Westinghouse and any of its
subcontractors; including liabilities covered by the Delay LD SubCap and the
Total LD SubCap, to us will not in any event exceed an amount equal to the
contract price so long as the limitation of liability will not apply to
obligations to remove liens or to make indemnification payments.




                                       57
<PAGE>

Warranties and Guarantees

         Siemens Westinghouse warrants and guarantees that during the applicable
warranty period


         o        all machinery, equipment, materials, systems, supplies and
                  other items comprising our project must be new and of
                  first-rate quality which satisfies Metropolitan Edison-grade
                  standards and in accordance with prudent utility practices and
                  the specifications described in the construction agreement,
                  suitable for the use in generating electric energy and
                  capacity under the climatic and normal operating conditions
                  and free from defective workmanship or materials,


         o        it will perform all of its design, construction, engineering
                  and other Services in accordance with the construction
                  agreement,


         o        our project and its components must be free from all defects
                  caused by errors or omissions in engineering and design, as
                  determined by reference to prudent utility practices, and must
                  comply with all applicable laws, all applicable permits,
                  Metropolitan Edison electrical interconnection requirements,
                  the Power Purchase Agreement Operating Requirements and the
                  Guaranteed Emissions Limits and



         o        the completed project must perform its intended functions of
                  generating electric energy and capacity as a complete,
                  integrated operating system as contemplated in the
                  construction agreement. If we notify Siemens Westinghouse
                  within 30 days after the expiration of the applicable warranty
                  period of any defects or deficiencies discovered during the
                  applicable warranty period, Siemens Westinghouse must promptly
                  reperform any of the services at its own expense to correct
                  any errors omissions, defect or deficiencies and, in the case
                  of defective or otherwise deficient machinery, equipment,
                  materials, systems supplies or other items, replace or repair
                  the same at its own expense. Siemens Westinghouse warrants and
                  guarantees that, to the extent we have made all payments then
                  due to Siemens Westinghouse, title to our facility and all
                  work, materials, supplies and equipment must pass to us free
                  and clear of all liens, other than any permitted liens. Other
                  than the warranties and guarantees provided in the
                  construction agreement there are no other warranties of any
                  kind, whether statutory, express or implied relating to the
                  Services.



         During the applicable warranty period, Siemens Westinghouse must
promptly notify us of any engineering and design defects which are manifested in
any of Siemens Westinghouse's fleet of 501G combustion turbines under
construction, start-up or testing or in operation during the warranty period and
which could reasonably be expected to be common to the fleet or this facility.
Upon the notification from Siemens Westinghouse of a fleet-wide or common defect
and otherwise upon notification from us no later than 30 days after the
expiration of the applicable warranty period of any defects or deficiencies in
our project or any component, we must, subject to the provisions of the
construction agreement, make our facility or the subject Equipment available to
Siemens Westinghouse for Siemens Westinghouse to re-perform, replace or, at its
option, repair the same at its expense so that it is in compliance with the
standards warranted and guaranteed, all in accordance with the construction
agreement.


Force Majeure

Force Majeure Event


         A force majeure event means any act or event that prevents the affected
party from performing its obligations, other than the payment of money, under
the construction agreement or complying with any conditions required to be
complied with under the construction agreement if the act or event is beyond the
reasonable control of and not the fault of the affected party and the party has
been unable by the exercise of due diligence to overcome or mitigate the effects
of the act or event. Force majeure events include, but are not limited to, acts
of declared or undeclared war, sabotage, landslides, revolution, terrorism,
flood, tidal wave, hurricane, lightning, earthquake, fire, explosion, civil
disturbance, insurrection or riot, act of God or the public enemy, action
(including unreasonable delay or failure to act) of a court or public authority,
or strikes or other labor disputes of a regional or national character that are
not limited to only the employees of Siemens Westinghouse or its subcontractors
and that are not due to the breach of a labor contract or applicable law by the
party claiming force majeure or any of its subcontractors. Force majeure events
do not include (1) strikes, work stoppages and labor disputes or unrest of any
kind that involve only employees of Siemens Westinghouse or any subcontractors,
except as expressly provided in the preceding sentence, (2) late delivery of
materials or equipment, except to the extent caused by a force majeure event and
(3) economic hardship.




                                       58
<PAGE>

Excused Performance


         If either party is rendered wholly or partly unable to perform its
obligations because of a force majeure event, that party will be excused from
whatever performance is affected by the force majeure event to the extent so
affected so long as:


         o        the non-performing party gives the other party prompt notice
                  describing the particulars of the occurrence;

         o        the suspension of performance is of no greater scope and of no
                  longer duration than is reasonably required by the force
                  majeure event;

         o        the non-performing party exercises all reasonable efforts to
                  mitigate or limit damages to the other party;

         o        the non-performing party uses its best efforts to continue to
                  perform its obligations under the construction agreement and
                  to correct or cure the event or condition excusing
                  performance; and


         o        when the non-performing party is able to resume performance of
                  its obligations, that party must give the other party written
                  notice to that effect and must promptly resume performance
                  under the construction agreement.


Scope Changes

Scope Changes


         We may order Scope Changes to the Services, in which event one or more
of the contract price, the Construction Progress Milestone Dates, the Guaranteed
Completion Dates, the Payment and Milestone Schedule, our construction schedule
and the Performance Guarantees will be adjusted accordingly, if necessary. All
Scope Changes must be authorized by a Scope Change Order and only we or our
representative may issue Scope Change Orders.



         As soon as Siemens Westinghouse becomes aware of any circumstances
which it has reason to believe may necessitate a Scope Change, Siemens
Westinghouse must issue to us a Scope Change Order Notice at its expense. If we
desire to make a Scope Change, in response to a Scope Change Order Notice or
otherwise, we must submit a Scope Change Order Request to Siemens Westinghouse.
Siemens Westinghouse must promptly review the Scope Change Order Request and
notify us in writing of the options for implementing the proposed Scope Change
and the effect, if any, each option would have on the contract price, the
Guaranteed Completion Dates, the Construction Progress Milestone Dates, the
Payment and Milestone Schedule, our construction schedule and the Performance
Guarantees.



         No Scope Change Order will be issued and no adjustment of the contract
price, the Guaranteed Completion Dates, the Construction Progress Milestone
Dates, the Payment and Milestone Schedule, our construction schedule or the
Performance Guarantees will be made in connection with any correction of errors,
omission, deficiencies, or improper or defective work on the part of Siemens
Westinghouse or any subcontractors in the performance of the Services. Changes
due to changes in applicable laws or applicable permits occurring after the date
of the construction agreement must be treated as Scope Changes.


Effect of Force Majeure Event


         If and to the extent that any force majeure events affect Siemens
Westinghouse's ability to meet the Guaranteed Completion Dates, or the
Construction Progress Milestone Dates, an equitable adjustment in one or more of
the dates, the Payment and Milestone Schedule and our construction schedule must
be made by agreement between us and Siemens Westinghouse. No adjustment to the
Performance Guarantees and, except as otherwise expressly described below, the
contract price must be made as a result of a force majeure event. If Siemens
Westinghouse is delayed in the performance of the Services by a force majeure
event, then:



         o        to the extent that the delay(s) are, in the aggregate, six
                  months or less, Siemens Westinghouse must absorb all of its
                  costs and expenses resulting from the delay(s); and



         o        to the extent that the delay(s) are, in the aggregate, more
                  than six months, Siemens Westinghouse must be reimbursed by us
                  for those incremental costs and expenses resulting from the
                  delay(s) which are incurred by Siemens Westinghouse after the
                  six-month period.


Price Change


         An increase or decrease in the contract price, if any, resulting from a
Scope Change requested by us or made under the construction agreement must be
determined, upon the mutual agreement of the parties.




                                       59
<PAGE>

Continued Performance Pending Resolution of Disputes


         If a dispute regarding the amount of any increase or decrease in
Siemens Westinghouse's costs with respect to a Scope Change, Siemens
Westinghouse must proceed with the performance of the Scope Change promptly
following our execution of the corresponding Scope Change Order.



         If hazardous materials were not identified in an environmental site
assessment report delivered by us to Siemens Westinghouse prior to the
construction commencement date and were not brought onto the facility site by
Siemens Westinghouse or any of its subcontractors, then Siemens Westinghouse
will be entitled to a Scope Change under the construction agreement.


Insurance

General


         Siemens Westinghouse must provide and maintain the following types of
insurance at all times while it or any subcontractor is performing the Services:
workers' compensation insurance and employers' liability insurance; commercial
general liability insurance; business automobile liability insurance; commercial
umbrella and/or excess insurance; "all-risk" builder's risk insurance; and ocean
marine cargo insurance. Before permitting any of its subcontractors to perform
any Services at the facility site, Siemens Westinghouse must obtain a
certificate of insurance from each subcontractor evidencing that each
subcontractor has obtained insurance in the amounts and against the risks as is
consistent with Siemens Westinghouse's customary practices for the types of
subcontracts for projects of similar type and capacity to our project. All
insurance policies supplied by Siemens Westinghouse must include a waiver of any
right of subrogation of the insurers and of any right of the insurers to any
set-off, counterclaim or deduction.


Cost of Premiums


         Construction Insurance: Siemens Westinghouse must bear responsibility
for payment of all premiums for insurance coverage required to be provided by
Siemens Westinghouse.



         Operating Insurance: we will be responsible for obtaining, on the terms
and conditions as we and our financing parties reasonably deem to be
appropriate, "all-risk" property insurance, including "business interruption"
coverage, for our facility for the period commencing with the first to occur of
Provisional Acceptance, Interim Acceptance and Final Acceptance.


Risk of Loss


         With respect to our facility, until the Risk Transfer Date, Siemens
Westinghouse must bear the risk of loss and full responsibility for the costs of
replacement, repair or reconstruction resulting from any damage to or
destruction of our facility or any materials, equipment, tools and supplies,
which are purchased for permanent installation in or for use during construction
of our facility.



         After the Risk Transfer Date with respect to our facility, we must bear
all risk of loss and full responsibility for repair, replacement or
reconstruction with respect to any loss, damage or destruction to our facility
which occurs after the Risk Transfer Date.


Termination

Termination for Company's Convenience


         We may for its convenience terminate any part of the Services or all
remaining Services at any time upon 30 days' prior written notice to Siemens
Westinghouse specifying the part of the Services to be terminated and the
effective date of termination. We may elect to suspend completion of all or any
part of the Services upon 10 days' prior written notice to Siemens Westinghouse
or, in emergency situations upon prior notice as circumstances permit.


Termination by Contractor


         If we fail to pay to Siemens Westinghouse any payment and our failure
continues for 20 days, then (1) Siemens Westinghouse may suspend its performance
of the Services upon 10 days' prior written notice to us, which suspension may
continue until the time as the payment, plus accrued interest, is paid to
Siemens Westinghouse, and/or (2) if the payment has not been made prior to the
commencement of a suspension by Siemens Westinghouse under clause (1) above,
Siemens Westinghouse may terminate the construction agreement upon 60 days'
prior written notice to us so long as the termination does not become effective
if the payment, plus accrued interest, is made to Siemens Westinghouse


                                       60
<PAGE>

prior to the end of the notice period. In the event of a suspension, an
equitable adjustment to one or more of the contract price, the Guaranteed
Completion Dates, the Construction Progress Milestone Dates, the Payment and
Milestone Schedule and our construction schedule, and, as appropriate, the other
provisions of the construction agreement that may be affected thereby, must be
made by agreement between us and Siemens Westinghouse. If we have suspended
completion of all or any part of the Services in accordance with the
construction agreement for a period in excess of two years in the aggregate,
Siemens Westinghouse may, at its option, at any time thereafter so long as the
suspension continues, give written notice to Company that Siemens Westinghouse
desires to terminate the suspended Services. Unless we order Siemens
Westinghouse to resume performance of the suspended services within 10 days of
the receipt of the notice from Siemens Westinghouse, the suspended Services will
be deemed to have been terminated by us for its convenience. If the occurrence
of one or more force majeure events prevents Siemens Westinghouse from
performing the Services for a period of 365 consecutive days, Siemens
Westinghouse may, at its option, give written notice to us of its desire to
terminate the construction agreement.


Consequences of Termination


         o        Upon any termination, we may, unless the termination is
                  pursuant to any default Siemens Westinghouse will be paid all
                  amounts due and owing to it under the construction agreement
                  and it is not deemed to constitute a waiver by Siemens
                  Westinghouse of any rights to payment it may have as a result
                  of a non-default related termination in the event of a
                  termination pursuant to a default, at its option elect to have
                  itself, or its designee, which may include any other affiliate
                  of The AES Corporation or any third-party purchaser, (1)
                  assume responsibility for and take title to and possession of
                  our project and any or all work, materials or equipment
                  remaining at the facility site and (2) succeed automatically,
                  without the necessity of any further action by Siemens
                  Westinghouse, to the interests of Siemens Westinghouse in any
                  or all items procured by Siemens Westinghouse for our project
                  and in any and all contracts and subcontracts entered into
                  between Siemens Westinghouse and any subcontractor with
                  respect to the equipment specified in the construction
                  agreement with respect to any or all other subcontractors
                  selected by us which are materially necessary to the timely
                  completion of our project, Siemens Westinghouse must use all
                  reasonable efforts to enable us, or our designee, to succeed
                  to Siemens Westinghouse's interests thereunder.


         o        If any termination occurs, we may, without prejudice to any
                  other right or remedy it may have, at its option, finish the
                  Services by whatever method we may deem expedient.

Default and Remedies

Contractor's Default

         Siemens Westinghouse's events of default include: voluntary bankruptcy
or insolvency; involuntary bankruptcy or insolvency; materially adverse
misleading or false representation or warranty; improper assignment; failure to
maintain required insurance; failure to comply with applicable laws or
applicable permits; cessation or abandonment of the performance of Services;
termination or repudiation of, or default under the related guaranty; failure to
supply sufficient skilled workers or suitable material or equipment; failure to
make payment when due for labor, equipment or materials; non-occurrence of
Provisional Acceptance, Interim Acceptance, Final Acceptance and Construction
Progress Milestones; and failure to remedy non-performance or non-observance of
any provision in the construction agreement.

Company's Rights and Remedies


      If Siemens Westinghouse is in default of its obligations, We will have any
or all of the following rights and remedies, in addition to any other rights and
remedies that may be available to us under the construction agreement or at law
or in equity, and Siemens Westinghouse will have the following obligations:



         o        We may, without prejudice to any other right or remedy we may
                  have under the construction agreement or at law or in equity,
                  terminate the construction agreement in whole or in part
                  immediately upon delivery of notice to Siemens Westinghouse.
                  In case of partial termination, the parties must mutually
                  agree upon a Scope Change Order to make equitable adjustments,
                  including the reduction and/or deletion of obligations of the
                  parties commensurate with the reduced scope Siemens
                  Westinghouse must have after taking into account the partial
                  termination, to one or more of the Guaranteed Completion
                  Dates, the Construction Progress Milestone Dates, the contract
                  price, the Payment and Milestone Schedule, our construction
                  schedule, the Performance Guarantees and the other provisions
                  of the construction agreement which may be affected thereby,
                  as appropriate. If the parties are unable to reach mutual
                  agreement as to the Scope Change Order and the dispute
                  resolution procedures described in the construction agreement
                  are invoked, the procedures must give due


                                       61
<PAGE>

                  consideration to customary terms and conditions under which
                  Siemens Westinghouse has entered subcontracts with third party
                  prime contractors covering services substantially similar to
                  those Services which are not being terminated.



         o        If requested by us, Siemens Westinghouse must withdraw from
                  the facility site, must assign to us its subcontracts, to the
                  extent permitted therein, as we may request, and must remove
                  the materials, equipment, tools and instruments used by, and
                  any debris and waste materials generated by, Siemens
                  Westinghouse in the performance of the Services as we may
                  direct, and we, without incurring any liability to Siemens
                  Westinghouse (other than the obligation to return to Siemens
                  Westinghouse at the completion of our project the materials
                  that are not consumed or incorporated into our project, solely
                  on an "as is, where is" basis without any representation or
                  warranty of any kind whatsoever) may take possession of any
                  and all designs, drawings, materials, equipment, tools,
                  instruments, purchase orders, schedules and facilities of
                  Siemens Westinghouse at the facility site that we deem
                  necessary to complete the Services.


Assignment

Consent Required


         Generally, neither we nor Siemens Westinghouse will have any right to
assign or delegate any of their respective rights or obligations under the
construction agreement either voluntarily or involuntarily or by operation of
law.


                         Maintenance Services Agreement

         We, as assignee of AES Ironwood, Inc., have entered into the
Maintenance Program Parts, Shop Repairs and Scheduled Outage TFA Services
Contract, dated as of September 23, 1998, with Siemens Westinghouse by which
Siemens Westinghouse will provide us with, among other things, combustion
turbine parts, shop repairs and scheduled outage technical field assistance
services.


         The maintenance services agreement became effective on the date of
execution and unless terminated early, must terminate upon completion of shop
repairs performed by Siemens Westinghouse following the eighth Scheduled Outage
of the applicable Combustion Turbine or 10 years from initial synchronization of
the applicable combustion turbine, whichever occurs first.


Scope of Work

         During the term of the maintenance services agreement, and in
accordance with the Scheduled Outage plan, Siemens Westinghouse is required to
do the following:

         o        deliver the type and quantity of New Program Parts for
                  installation of the Combustion Turbine;

         o        repair/refurbish Program Parts and equipment for the
                  Combustion Turbine;

         o        provide Miscellaneous Hardware;

         o        provide us with material safety data sheets for all hazardous
                  materials Siemens Westinghouse intends to bring/use on the
                  facility site;

         o        provide the services of a maintenance program engineer to
                  manage the Combustion Turbine maintenance program; and

         o        provide TFA Services.

         We are responsible for, among other things:

         o        storing and maintaining parts, materials and tools to be used
                  in or on the Combustion Turbine;

         o        maintaining and operating the Combustion Turbine consistently
                  with the warranty conditions;

         o        ensuring that its operator and maintenance personnel are
                  properly trained;

         o        transporting Program Parts in need of repair/refurbish; and

         o        providing Siemens Westinghouse, on a monthly basis, with the
                  required Equivalent Starts and EBHs.



                                       62
<PAGE>

         We and Siemens Westinghouse will jointly develop the Scheduled Outage
plan. The Scheduled Outage plan will be consistent with the terms and conditions
of the power purchase agreement.

Early Replacement


         If it is determined that due to normal wear and tear a Program Part(s)
for the Combustion Turbine has failed or will not last until the next Scheduled
Outage, and the part has to be repaired before the scheduled replacement period,
Siemens Westinghouse will replace the Program Part by moving up a New Program
Part which is otherwise scheduled to be delivered at a later date. The contract
price for the replacement will not be affected if the replacement date is less
than or equal to one year earlier than the Scheduled Outage during which the
Program Part was scheduled to be replaced. If the actual replacement date for a
Program Part is more than one year earlier than the Scheduled Outage at which
point the Program Part was scheduled to be replaced, the early replacement will
result in an adjustment to the Payment Schedule. Siemens Westinghouse has the
final decision with regard to the replacement or refurbishment associated with
any Program Part. If we dispute Siemens Westinghouse's decision, we may seek to
resolve the dispute in accordance with the dispute resolution procedures
discussed below.


Parts Life Credit


         After applicable warranty periods described in the maintenance services
agreement and the construction agreement, Siemens Westinghouse will provide a
parts life credit if a Program Part requires replacement due to normal wear and
tear prior to meeting its expected useful life. Siemens Westinghouse has the
final decision with regard to actual parts life and the degree of repair or
refurbishment associated with any Program Parts. The parts life credit will be
calculated in terms of EBHs and Equivalent Starts. The price of the replacement
part will be adjusted for inflation. If we dispute Siemens Westinghouse's
decision, we may seek to resolve the dispute in accordance with the dispute
resolution procedures discussed below.


Contract Price and Payment Terms

         Siemens Westinghouse will invoice us monthly and payments are then due
within 25 days. The fees assessed by Siemens Westinghouse will be based on the
number of EBHs accumulated by the applicable Combustion Turbine as adjusted for
inflation. The contract price will be the aggregate number of fees as adjusted
plus any additional payment amount mutually agreed to by the parties under a
Change Order.

Unscheduled Outages and Unscheduled Outage Work


         If during the term of the maintenance services agreement an Unscheduled
Outage occurs resulting from (1) the non-conformity of New Program Parts; (2)
the failing of a Shop Repair; (3) a Program Part requiring replacement due to
normal wear and tear prior to achieving its expected life in terms of EBHs or
Equivalent Starts; or (4) the failure of a Service, performed by Siemens
Westinghouse, we must hire Siemens Westinghouse, to the extent not supplied by
Siemens Westinghouse as a warranty remedy under Siemens Westinghouse's
warranties under the maintenance services agreement to supply any additional
parts, Miscellaneous Hardware, Shop Repairs and TFA Services under a Change
Order. We will be entitled to any applicable parts life credit with respect to
Program Parts as well as a discount for TFA Services. If the Unscheduled Outage
occurs within a specified number of EBHs of a Scheduled Outage and it was
anticipated that the additional parts, Miscellaneous Hardware, Shop Repairs and
TFA Services to be used in the Unscheduled Outage were to be used during the
upcoming Scheduled Outage, the upcoming Scheduled Outage must be moved up in
time to become the Unscheduled Outage/moved-up Scheduled Outage. We will not be
required to pay any additional money for the Program Parts, Miscellaneous
Hardware, Shop Repairs and TFA Services.



         If any Program Parts are delivered by Siemens Westinghouse within 15
days of receipt of the Change Order, we will pay to Siemens Westinghouse the
price for the Program Part described in the maintenance services agreement plus
a specified percentage. Any Program Part delivered after 30 days of the Change
Order will cost us the price described in the maintenance services agreement
minus a specified percentage.


Changes in Operating Restrictions


         The maintenance services agreement requires that each Combustion
Turbine will be operated in accordance with the requirements of the power
purchase agreement and prudent utility practices, with 8,000 EBH/year and 100
Equivalent Starts per year by using natural gas fuel or liquid fuel and water.
Should the actual operations differ from these operating parameters which causes
a Scheduled Outage to be planned/performed earlier or later than as expected,
then, under a Change Order, an adjustment in the scope, schedule, and price must
be made.




                                       63
<PAGE>

Warranties


         Siemens Westinghouse warrants that the New Program Parts, Miscellaneous
Hardware and any Shop Repairs must conform to standards of design, materials and
workmanship consistent with generally accepted practices of the electric utility
industry. The warranty period with respect to Program Parts, Hardware and Shop
Repair is until the earlier of one year from the date of installation of the
original Program Part or Hardware, a specific number of starts or fired hours
after installation of the Program Parts and Hardware, or three years from the
date of delivery of the original Program Part, Hardware, and in the case of Shop
Repair, three years from completion of the work. Warranties on the Program Parts
and Hardware must not expire more than one year after the conclusion of the
maintenance services agreement. Siemens Westinghouse will repair or replace any
Program Part or Hardware, at its cost, if notified of any failure or
non-conformity of the Program Part or Hardware during the warranty period.



         Siemens Westinghouse also warrants that the Services of its personnel
and technical information transmitted will be competent and consistent with
prudent utility practices and the Services will comply in all material respects
with laws and will be free from defects in workmanship for a period of one year
from the date of completion of that item of Services. The warranties on the
Services must expire no later than one year after the termination or end of the
term of the maintenance services agreement.



         In addition, Siemens Westinghouse warrants any Program Part removed
during a Scheduled Outage and delivered by us to the designated facility for
repair will be repaired and delivered by Siemens Westinghouse within 26 weeks.
If Siemens Westinghouse does not deliver the Program Part within this time frame
or does not provide a New Program Part in lieu of the Program Part being Shop
Repaired and an outage occurs which requires the a Program Part, Siemens
Westinghouse will pay us liquidated damages for each day the Program Part is not
repaired and delivered the aggregate of which liquidated damage payments must
not exceed a maximum annual cap. If upon reaching the maximum cap on aggregate
liquidated damages, Siemens Westinghouse still has not repaired and delivered
the Program Part, we may elect to terminate the maintenance services agreement
because Siemens Westinghouse will be considered to have failed to perform its
material obligations.



         Except for the express warranties described in the maintenance services
agreement, Siemens Westinghouse makes no other warranties or representations of
any kind. No implied statutory warranty of merchantibility or fitness for a
particular purpose applies.


         The warranties provided by Siemens Westinghouse are conditioned upon
(1) our receipt, handling, storage, operation and maintenance of our project,
including any Program Parts and Miscellaneous Hardware, being done in accordance
with the terms of the Combustion Turbine instruction manuals; (2) operation of
the Combustion Turbine in accordance with the terms of the maintenance services
agreement; (3) repair of accidental damage done consistently with the equipment
manufacturer's recommendations; (4) us providing Siemens Westinghouse with
access to the facility site to perform its services under the maintenance
services agreement; and (5) hiring Siemens Westinghouse to provide TFA Services,
Program Parts, Shop Repairs and Miscellaneous Hardware required to dissemble,
repair and reassemble the Combustion Turbine.

Insurance


         Siemens Westinghouse must maintain in full force and effect during the
term of the maintenance services agreement the following required insurance
coverage: commercial general liability, workers' compensation, umbrella excess
liability and business automobile liability. All the policies of workers'
compensation must provide a waiver of subrogation rights against us.



         We must maintain in full force and effect during the term of the
maintenance services agreement the following required insurance coverage:
property insurance, commercial general liability, workers' compensation,
umbrella excess liability and business automobile liability insurance. The
policies of property insurance and workers' compensation must include waivers of
subrogation rights against Siemens Westinghouse.


Termination

         We may terminate the maintenance services agreement if:

         o        specific bankruptcy events affecting Siemens Westinghouse
                  occur;



                                       64
<PAGE>


         o        Siemens Westinghouse fails to perform or observe in any
                  material respect any provision in the maintenance services
                  agreement and fails to (1) promptly commence to cure and
                  diligently pursue the cure of the failure or (2) remedy the
                  failure within 45 days after Siemens Westinghouse receives
                  written notice of the failure;


         o        we terminate the construction agreement due to the
                  contractor's default thereunder or due to our inability to
                  obtain construction financing or environmental operating
                  permits; or

         o        the contractor terminates the construction agreement for any
                  reason other than our default thereunder.

         Notwithstanding the preceding, we may terminate the maintenance
services agreement at any time for its convenience following the completion of
the first major outage of both Combustion Turbines. In addition, the maintenance
services agreement will automatically terminate if:

         o        We terminate the construction agreement for reasons other than
                  (1) the default of the contractor and (2) our inability to
                  obtain permits for our project or


         o        the contractor terminates the construction agreement for our
                  default thereunder. If the termination occurs, Siemens
                  Westinghouse must discontinue any work or services being
                  performed and continue to protect our property. Siemens
                  Westinghouse must transfer title to and deliver any New
                  Program Parts and Miscellaneous Hardware already purchased by
                  us. We must pay Siemens Westinghouse those amounts owed at the
                  time of termination.


Limitation of Liability


         We agreed that the remedies provided in the maintenance services
agreement are exclusive and that under no circumstances must the total aggregate
liability of Siemens Westinghouse during a given year exceed 100% of the
contract price payable to Siemens Westinghouse for that given year under the
maintenance services agreement. We further agreed that under no circumstances
must the total aggregate liability of Siemens Westinghouse for liquidated
damages during a given year exceed a specified percentage of the contract price
payable to Siemens Westinghouse for that given year under the maintenance
services agreement. We further agreed that under no circumstances must the total
aggregate liability of Siemens Westinghouse exceed a specified percentage of the
contract price payable to Siemens Westinghouse under the maintenance services
agreement.


Force Majeure


         Neither party will be liable for failure to perform any obligation or
delay in performance, excluding payment, to the extent the failure or delay is
caused by any act or event beyond the reasonable control of the affected party
or Siemens Westinghouse's suppliers so long as the act or event is not the fault
or the result of negligence of the affected party and the party has been unable
by exercise of reasonable diligence to overcome or mitigate the effects of the
act or event. Force majeure includes: any act of God; act of civil or military
authority; act of war whether declared or undeclared; act (including delay,
failure to act, or priority) of any governmental authority; civil disturbance;
insurrection or riot; sabotage; fire; inclement weather conditions; earthquake;
flood; strikes, work stoppages or other labor difficulties of a regional or
national character which are not limited to only the employees of Siemens
Westinghouse or its subcontractors or suppliers and which are not due to the
breach of an applicable labor contract by the party claiming force majeure;
embargo; fuel or energy shortage; delay or accident in shipping or
transportation to the extent attributable to another force majeure; changes in
laws which substantially prevents a party from complying with its obligations in
conformity with its requirements under the maintenance services agreement or
failure or delay beyond its reasonable control in obtaining necessary
manufacturing facilities, labor, or materials from usual sources to the extent
attributable to another force majeure; or failure of any principal contractor to
provide equipment to the extent attributable to another force majeure. Force
majeure does not include: (1) economic hardship, (2) changes in market
conditions or (3) except due to an event of force majeure, late delivery of
Program Parts or other Equipment.



         If a delay in performance is excusable due to a force majeure, the date
of delivery or time for performance of the work will be extended by a period of
time reasonably necessary to overcome the effect of the force majeure and if the
force majeure lasts for a period longer than 30 days and the delay directly
increases Siemens Westinghouse's costs or expenses, we, after reviewing Siemens
Westinghouse's additional direct costs and expenses, will reimburse Siemens
Westinghouse for its reasonable additional direct costs and expenses incurred
after 30 days from the beginning of the force majeure resulting from the delay.




                                       65
<PAGE>

                            Interconnection Agreement

         We have entered into a Generation Facility Transmission Interconnection
Agreement, dated as of March 23, 1999, with Metropolitan Edison for the
installation, operation and maintenance of the facilities necessary to
interconnect our facility to the transmission system of Metropolitan Edison.
Under the interconnection agreement, we and Metropolitan Edison will construct,
own, operate and maintain the Interconnection Facilities. We will be responsible
for all of the costs of construction, operation and maintenance of the
Interconnection Facilities, including those owned by Metropolitan Edison.

Scope

         The interconnection agreement will become effective on the effective
date established by FERC and will continue in full force and effect until a
mutually agreeable termination date not to exceed the retirement date for our
facility.

Metropolitan Edison's Obligations

         Metropolitan Edison will install, own, operate and maintain, at our
cost and expense, a portion of the Interconnection Facilities, including, but
not limited to specific substation protective relaying equipment and a 230 kV
power circuit breaker. The facilities to be installed by Metropolitan Edison,
together with the facilities to be installed by us, are those necessary to allow
the interconnection of our facility with the transmission system of Metropolitan
Edison.


         Metropolitan Edison is to complete the installation of the facilities
necessary to permit us to energize the switch yard and to begin commissioning of
our facility by June 30, 2000. If those facilities are completed prior to June
30, 2000, Metropolitan Edison will be paid an early completion bonus of $5,000
for each day of early completion up to and including 30 days (May 31, 2000). If
those facilities are completed after June 30, 2000, Metropolitan Edison will pay
delay damages of $5,000 for each day of delay up to and including 42 days
(August 11, 2000). We will also have the ability to take over the completion of
these facilities if it becomes apparent that Metropolitan Edison will not be
able to complete them within the 42-day period, Metropolitan Edison has not
proposed a reasonable recovery plan, and we can demonstrate that we are able to
complete the facilities more quickly than Metropolitan Edison.


         Metropolitan Edison is to complete the installation of its portion of
the Interconnection Facilities and specific transmission system reinforcements
necessary to permit the dispatch of the full output of our facility by August
31, 2000.

Company's Obligations

         We will install, own, operate and maintain a portion of the
Interconnection Facilities, including, but not limited to, a 230 kV switchyard,
including generator step up transformers, instrument transformers, revenue
metering, power circuit breakers, control and protective relay panels,
supervisory control and data acquisition equipment, and protective relaying
equipment.

         We will reimburse Metropolitan Edison for its actual costs of
installing the Interconnection Facilities. Our payments to Metropolitan Edison
consist of an advance payment of $500,000 on the execution date of the
interconnection agreement, another payment of $40,000 within 30 days of the
execution date of the interconnection agreement (for work undertaken by
Metropolitan Edison prior to December 17, 1998), a payment of $1,000,000 at
financial closing and monthly invoices for the work performed.

         We are obligated to modify our portion of the Interconnection
Facilities as may be required to conform to changes in good utility practice or
as required by PJM.

         We are obligated to keep our facility insured against loss or damage in
accordance with the minimum coverages specified in the interconnection
agreement.

Operation and Maintenance of Interconnection Facilities

         The parties are obligated to operate and maintain their respective
portions of the Interconnection Facilities in accordance with good utility
practices and the requirements and guidelines of PJM and Metropolitan Edison.


         Metropolitan Edison will have the right to disconnect our facility from
its Transmission System and/or curtail, interrupt or reduce the output of our
facility when operation of our facility or the Interconnection Facilities
adversely affects the quality of service rendered by Metropolitan Edison or
interferes with the safe and reliable operation of its Transmission System or
the regional transmission system. Metropolitan Edison, however, is obligated to
use reasonable efforts to minimize any disconnection, curtailment, interruption
or reduction in output.



                                       66
<PAGE>

         In accordance with good utility practice, Metropolitan Edison may
remove the Interconnection Facilities from service as necessary to perform
maintenance or testing or to install or replace equipment on the Interconnection
Facilities or the Transmission System. Metropolitan Edison is obligated to use
due diligence to restore the Interconnection Facilities to service as promptly
as practicable.


         In addition, if we fail to operate, maintain, administer, or insure our
facility or its portion of the Interconnection Facilities, Metropolitan Edison
may, following 30 days' notice and opportunity to cure the failure, disconnect
our facility from the Transmission System.


Force Majeure


         If either party is delayed in or prevented from performing or carrying
out its obligations under the interconnection agreement by reason of force
majeure, the party will not be liable to the other party for or on account of
any loss, damage, injury or expense resulting from or arising out of the delay
or prevention so long as the party encountering the delay or prevention uses due
diligence to remove the cause or causes thereof.


Default

         The events of default under the interconnection agreement are:

         o        breach of a material term or condition and uncured failure to
                  provide a required schedule, report or notice;

         o        failure or refusal of a party to permit the representatives
                  of the other party access to maintenance records, or its
                  Interconnection Facilities or Protective Apparatus;

         o        appointment by a court of a receiver or liquidator or trustee
                  that is not discharged within 60 days, issuance by a court of
                  a decree adjudicating a party as bankrupt or insolvent or
                  sequestering a substantial part of its property that has not
                  been discharged within 60 days after its entry, or filing of a
                  petition to declare a party bankrupt or to reorganize a party
                  under the Federal Bankruptcy Code or similar state statute
                  that has not been dismissed within 60 days;

         o        voluntary filing by a party of a petition in bankruptcy or
                  consent to the filing of a bankruptcy or reorganization
                  petition, an assignment for the benefit of creditors, an
                  admission by a party in writing of its inability to pay its
                  debts as they come due, or consent to the appointment of a
                  receiver, trustee, or liquidator of a party or any part of its
                  property; and


         o        failure to provide the other party with reasonable written
                  assurance of the party's ability to perform any of the
                  material duties and responsibilities under the interconnection
                  agreement within 60 days of a reasonable request for the
                  assurance.



         Upon an event of default, the non-defaulting party may give notice of
the event of default to the defaulting party. The defaulting party will have 60
days following the receipt of the notice to cure the default or to commence in
good faith the steps necessary to cure a default that cannot be cured within
that 60-day period. If the defaulting party fails to cure its default within 60
days or fails to take the steps necessary to cure a default that cannot be cured
within a 60-day period, the non-defaulting party will have the right to
terminate the interconnection agreement.



         Metropolitan Edison will have the right to operate and/or to purchase
specific equipment, facilities and appurtenances from us that are necessary for
Metropolitan Edison to operate and maintain its Transmission System if (1) we
commence bankruptcy proceedings or petitions for the appointment of a trustee or
other custodian, liquidator, or receiver, (2) a court issues a decree for relief
of us or appoints a trustee or other custodian, liquidator, or receiver for us
or a substantial part of our assets and the decree is not dismissed within 60
days or (3) we cease operation for 30 consecutive days without having an
assignee, successor, or transferee in place.


                              Operations Agreement


         We have entered into a Development and Operations Services Agreement,
dated as of June 1, 1999, with AES Prescott by which AES Prescott will provide
development and construction management services and, after the commercial
operation date, operating and maintenance services for our facility for a period
of 27 years. Under the operations agreement, AES Prescott will be responsible
for, among other things, preparing plans and budgets related to start-up and
commercial operation of our facility, providing qualified operating personnel,
making repairs, purchasing consumables and spare parts (not otherwise provided
under the maintenance services agreement) and providing other services as needed
according to industry standards. AES Prescott will be compensated for the
services on a cost plus


                                       67
<PAGE>

fixed-fee basis. Under the services agreement between AES Prescott and The AES
Corporation, The AES Corporation will provide to AES Prescott all of the
personnel and services necessary for AES Prescott to comply with its obligations
under the operations agreement.


                            Effluent Supply Agreement

         We, as assignee of AES Ironwood, Inc., have entered into an Effluent
Supply Agreement, dated as of March 3, 1998, with the City of Lebanon Authority,
by which City of Lebanon Authority will provide effluent to be used by us at the
electric generating facility to be constructed in South Lebanon Township,
Pennsylvania.

Supply of Effluent

Effluent Supply


         Subsequent to completion of the pipeline connecting our facility with
the wastewater treatment facility owned and operated by City of Lebanon
Authority and throughout the term of the effluent supply agreement, City of
Lebanon Authority must make available to us a supply of effluent not less than
2,160,000 gallons per day. In the event of a shortfall, we may elect to accept
potable water from City of Lebanon Authority in accordance with the effluent
supply agreement.



         We will not be obligated to purchase any minimum amount of effluent and
will be entitled to seek and obtain water from other available sources. City of
Lebanon Authority must use its best efforts to comply with requests by us for
excess effluent, which must not exceed (1) 4,600,000 gallons per day or (2)
1,679,000,000 gallons per calendar year. In addition, City of Lebanon Authority
must use its best efforts to meet our minimum effluent requirements.


Compensation


         We will pay City of Lebanon Authority monthly for all effluent
delivered to the point of delivery during the prior month. The base rate for
effluent supplied will be: (1) for 0-2,160,000 gallons per day, $0.29 per
thousand gallons and (2) for 2,160,000 or greater gallons per day, $0.21 per
thousand gallons, which rates will be subject to annual adjustments for
inflation.


Pipeline and Real Estate Rights

Concerning the Pipeline


         We will be solely responsible, at its cost and expense, for
constructing and installing the pipeline.



         We and City of Lebanon Authority must cooperate in good faith to obtain
the necessary real estate rights for constructing, operating, maintaining and
accessing the pipeline.


Operation and Maintenance


         The City of Lebanon Authority must operate and maintain the pipeline in
accordance with the effluent supply agreement, and as compensation, we must pay
to City of Lebanon Authority $18,250 per year, which amount will be subject to
annual adjustment for inflation.


Capital Improvements

         The effluent supply agreement provides for capital improvements.

Potable Water


         The City of Lebanon Authority must make available to us on a continuous
basis a potable water supply of not less than 50 gallons per minute. We will not
be obligated to purchase a minimum amount of potable water, but must pay the
City of Lebanon Authority for potable water accepted at the potable delivery
point at the rate applicable to us described in City of Lebanon Authority's
applicable rate schedule.


Force Majeure


         If either party is unable to carry out any obligation under the
effluent supply agreement due to force majeure, the effluent supply agreement
must remain in effect, but the obligation will be suspended for the period
necessary as a result of the force majeure so long as: (1) the non-performing
party gives the other party written notice not later than 48 hours after the
occurrence of the force majeure describing the particulars of the force majeure;
(2) the suspension of performance is of no greater scope and of longer duration
than is required by the force majeure; and (3) the non-


                                       68
<PAGE>

performing party uses its best efforts to remedy its inability to perform.
Notwithstanding the preceding, the settlement of strikes, lockouts, and other
labor disputes will be entirely within the discretion of the affected party, and
the party will not be required to settle any strike, lockout or other labor
dispute on terms which it deems inadvisable.


Term


         The term of the effluent supply agreement will be 25 years unless
terminated early as a result of (1) our inability to obtain financing for our
project; (2) our inability to obtain necessary approvals to construct and
operate our project; (3) failure by us to deliver the commencement notice by
December 31, 2004, or (4) the occurrence of any event of default.


Early Termination for Event of Default


         A party may terminate the effluent supply agreement (1) upon a
bankruptcy event of the other party or (2) if the other party fails to perform
or observe any of its material obligations under the effluent supply agreement
within the time contemplated by the effluent supply agreement and the failure
continues for a period of time greater than 30 days from the defaulting party.


                            Pennsy Supply Agreements

         We, as assignee of AES Ironwood, Inc., have entered into an Agreement
Relating to Real Estate, dated as of October 22, 1998, with Pennsy Supply, Inc.
under which Pennsy Supply has agreed to grant to us specific easements and the
right to pump water from Pennsy Supply-owned property. The easements, which are
primarily for access and utility purposes, would run from property owned by us,
on which it will develop and construct its electric generating facility, across
property owned by Pennsy Supply and require that our property be used as a power
plant. Pennsy Supply has also agreed to grant to us easements with respect to
storm-water facilities and construction of a rail spur. Pennsy Supply will make
water available to us during construction and testing of our facility and for as
long as we operate our facility. We will bear all costs and expenses with
respect to water-pumping. In consideration for the easements and the
water-pumping rights, we have agreed to convey to Pennsy Supply title to a
parcel of land adjacent to the property owned by us.

         We have also entered into an Easement and Right of Access Agreement,
dated as of April 15, 1999, with Pennsy Supply under which Pennsy Supply has
granted us the rights and easements referred to in the prior paragraph as well
as specific other rights and easements required by us for the construction and
operation of our facility.




                                       69
<PAGE>

                        ROLE OF THE INDEPENDENT ENGINEER

         Stone & Webster will initially serve as the independent engineer in
accordance with the indenture.

         Under a consulting services agreement with us, and in accordance with
the indenture, the independent engineer is responsible for confirming the
reasonableness of statements and projections made in specified certificates
required to be provided, including with respect to

         o        satisfaction of certain requirements under the construction
                  agreement;

         o        the cost of and occurrence of the completion of rebuilding,
                  repairing or restoring of our facility following an event of
                  loss;


         o        under specified circumstances, the calculation of debt service
                  coverage ratios and the consistency of assumptions made in
                  connection with the calculations;


         o        whether any termination, amendment or modification of any
                  project contract would reasonably be expected to have a
                  material adverse effect; and

         o        specified tests required for the issuance of additional debt.


         The trustee may remove the independent engineer if at any time the
independent engineer becomes incapable of acting or is, or is reasonably likely
to be, adjudged bankrupt or insolvent or a receiver is appointed for, or any
public officer takes charge or control of, the independent engineer or its
property or its affairs for the purpose of rehabilitation, conservation or
liquidation, and must appoint a successor independent engineer. Within 30 days
of receipt by the trustee of a written notification from us to the effect that
the independent engineer has failed to carry out its obligations in a timely
manner, and in other circumstances, the trustee must remove the independent
engineer and appoint a successor independent engineer from those engineers then
listed on a schedule to the indenture. We will pay for all services performed by
the independent engineer and its reasonable costs and expenses related to the
services.



         If we and the independent engineer are in dispute in respect of a
notice, plan, report, certificate or budget and we are unable to resolve the
dispute within seven days of the independent engineer expressing its
disagreement with the notice, plan, report, certificate or budget, a single
independent third-party engineer will be designated to consider and decide the
issues raised by the dispute. The selection of the third-party engineer will be
made from the list of engineers described below. We must designate the
third-party engineer from the list not later than the third day following the
expiration of the seven-day period described above and the designation will
become effective in three days. Within three days of the designation of a
third-party engineer, we and the independent engineer will submit to the
third-party engineer a notice setting forth in detail the person's position in
respect of the issues in dispute. The notice will include supporting
documentation, if appropriate.



         The third-party engineer must complete all proceedings and issue his
decision with regard to the issues in dispute as promptly as reasonably
possible, but in any event within 10 days of the date on which he is designated
as third-party engineer, unless the third-party engineer reasonably determines
that additional time is required in order to give adequate consideration to the
issues raised. In that case the third-party engineer must state in writing his
reasons for believing that additional time is needed and must specify the
additional period required, which period must not exceed 10 days without our
agreement.



         If the third-party engineer determines that the position described in
the independent engineer's notice is correct, it must so state and must state
the corrective actions to be taken by us. In that case, we must promptly take
the corrective actions. We must thereafter bear all costs which may arise from
actions taken under the third-party engineer's decision. If the third-party
engineer determines that the position described in the independent engineer's
notice is not correct, it must so state and must state the appropriate actions
to be taken by us. In that case, we must take the appropriate actions and for
purposes of the indenture, the independent engineer and the trustee will be
deemed to have approved, confirmed, concurred in or consented to the notice,
plan, report, certificate or budget in dispute. The decision of the third-party
engineer will be final and non-appealable. We will bear all reasonable costs
incurred by the third-party engineer in connection with this dispute resolution
mechanism.



         The third-party engineer will be chosen from the list of qualified
engineers described in a schedule to the indenture. The list will also be used
by the trustee to choose a successor independent engineer. At any time either we
or the trustee may remove a particular engineer from the list by obtaining the
other person's reasonable consent to the


                                       70
<PAGE>

removal. However, neither we nor the trustee may remove a name or names from the
list if the removal would leave the list without at least two names, unless, at
the same time, we and the trustee reasonably agree to the addition of one or
more names to the list. During January of each year, we and the independent
engineer will review the current list of third-party engineers and give notice
to the trustee of any proposed additions to the list and any intended deletions.
Intended deletions will automatically become effective 30 days after the trustee
received notice unless the trustee makes a written objection within 30 days and
so long as the deletions do not leave the list fewer than two names. Proposed
additions to the list will automatically become effective 30 days after the
trustee received notice unless the trustee makes a written objection within 30
days. We may add a new name or names to the list of third-party engineers at any
time so long as no person will be added to the list or authorized to act as
third-party engineer unless the person is a competent firm of professional
engineers or consultants with a national reputation.






                                       71
<PAGE>

                          DESCRIPTION OF THE NEW BONDS

General

         We will issue new bonds under the indenture, dated as of June 25, 1999,
between us and the trustee. This is the same indenture under which the old bonds
were issued. We summarize below certain provisions of the indenture, but do not
restate the indenture in its entirety. We urge you to read the indenture because
it, and not this description, defines your rights as a holder of the notes.
Copies of the indenture and the other financing documents are available for
inspection during normal business hours at the offices of the trustee. The new
bonds will be issued in fully registered form without coupons and in
denominations of $100,000 and any integral multiple of $1,000 in excess thereof.

         The indenture permits us to issue new bonds and any future senior
secured indebtedness under a supplemental indenture as may be authorized from
time to time in accordance with the indenture. We may also issue, subject to the
indenture, any other series of debt issued under the indenture through a
supplemental indenture on terms we established. See "SUMMARY OF PRINCIPAL
FINANCING DOCUMENTS--Indenture--Supplemental Indentures."

         The new bonds will be direct obligations of ours and will be secured by
the collateral to the same extent as the old bonds.

Principal Amount, Interest Rate and Stated Maturity


         We will issue the new bonds in the aggregate principal amount of
$308,500,000. The new bonds will bear interest at the rate per annum described
on the cover of this prospectus and have a final maturity date of November 30,
2025.


Payment of Interest and Principal


         We will pay interest on the bonds every three months, on each February
28, May 31, August 31 and November 30, commencing August 31, 1999, to the
registered owners on the immediately preceding record date, as that information
appears on our books and records.



                                       72
<PAGE>

         We will pay principal on the new bonds in installments semiannually on
each February 28, May 31, August 31 and November 30, commencing February 28,
2002, to the registered owners on the immediately preceding record date as
follows:

                  PERCENTAGE OF ORIGINAL PRINCIPAL AMOUNT PAYABLE

YEAR    FEBRUARY 28       MAY 31      AUGUST 31     NOVEMBER 30    ANNUAL TOTAL
- ----    -----------       ------      ---------     -----------    ------------

2002      0.1600%        0.1600%       0.1600%        0.1600%         0.6400%
2003      0.3850%        0.3850%       0.3850%        0.3850%         1.5400%
2004      0.5150%        0.5150%       0.5150%        0.5150%         2.0600%
2005      0.5700%        0.5700%       0.5700%        0.5700%         2.2800%
2006      0.5800%        0.5800%       0.5800%        0.5800%         2.3200%
2007      0.7400%        0.7400%       0.7400%        0.7400%         2.9600%
2008      0.9200%        0.9200%       0.9200%        0.9200%         3.6800%
2009      0.7800%        0.7800%       0.7800%        0.7800%         3.1200%
2010      0.8150%        0.8150%       0.8150%        0.8150%         3.2600%
2011      1.0300%        1.0300%       1.0300%        1.0300%         4.1200%
2012      0.7600%        0.7600%       0.7600%        0.7600%         3.0400%
2013      0.9600%        0.9600%       0.9600%        0.9600%         3.8400%
2014      1.2900%        1.2900%       1.2900%        1.2900%         5.1600%
2015      1.2400%        1.2400%       1.2400%        1.2400%         4.9600%
2016      1.3550%        1.3550%       1.3550%        1.3550%         5.4200%
2017      1.4650%        1.4650%       1.4650%        1.4650%         5.8600%
2018      1.0100%        1.0100%       1.0100%        1.0100%         4.0400%
2019      1.2050%        1.2050%       1.2050%        1.2050%         4.8200%
2020      1.6250%        1.6250%       1.6250%        1.6250%         6.5000%
2021      1.6500%        1.6500%       1.2000%        1.2000%         5.7000%
2022      1.3900%        1.3900%       1.3900%        1.3900%         5.5600%
2023      1.5000%        1.5000%       1.5000%        1.5000%         6.0000%
2024      1.5500%        1.5500%       1.5500%        1.5500%         6.2000%
2025      1.7300%        1.7300%       1.7300%        1.7300%         6.9200%
                                                                      =======
                                                                         100%


         At our direction the trustee must round principal amounts to be
redeemed to the nearest $1,000.


         Interest will be computed on the basis of a 360-day year comprised of
twelve 30-day months and, for any period shorter than a full month, on the basis
of the actual number of days elapsed. Interest on the new bonds will accrue from
the most recent date to which interest has been paid on the old bonds.

Payment and Paying Agents


         Principal, make-whole premium, if any, and interest in respect of the
new bonds will be payable at the office of the paying agent in the County of New
York, The City of New York. The trustee will serve as the principal paying agent
and transfer agent. The new bonds may be presented for payment of principal at
the office of any paying agent. Payments in respect of principal of the new
bonds will be made only against surrender of the new bonds. Payment in respect
of interest on any interest payment date with respect to any new bond will be
made to the person in whose name the new bond is registered on February 1, May
1, August 1 and November 1, each date a "regular record date", as the case may
be, immediately preceding the interest payment date, except that interest
payable at maturity will be payable to the person to whom the principal of the
new bond is paid. All payments of principal and interest with respect to
certificated new bonds, if any, will be made by dollar check drawn on a bank in
The City of New York or, for bondholders of at least U.S.$1,000,000 in aggregate
principal amount of bonds, by wire transfer to a dollar account maintained by
the payee with a bank in The City of New York so long as a written request from
the bondholder to that effect designating the account is received by the trustee
or the paying agent no later than the regular record date immediately preceding
the interest payment date. Unless the designation is revoked, any designation
made by the


                                       73
<PAGE>

bondholder with respect to the certificated bonds will remain in effect with
respect to any future payments with respect to the certificated bonds payable to
the bondholder. Payments with respect to global bonds will be made to DTC or its
nominee, as bondholder, under DTC's rules, regulations and procedures.



         If any payment in respect of a new bond is due on a day that is, at any
place of payment, not a business day, the bondholder will not be entitled to
payment of the amount due until the next succeeding business day at the place of
payment and will not be entitled to any further interest or other payment in
respect of any delay.



         The indenture provides that any money paid by us to the trustee for any
payment with respect to the new bonds that remains unclaimed for two years will
be repaid to us, and thereafter the bondholder will look only to us for payments
thereof as an unsecured creditor, and we will not be liable to pay any taxes or
other duties in connection with the payment. Unless otherwise provided by
applicable law, the right to receive payment of principal and interest on any
new bond, whether at maturity, redemption or otherwise, will become void at the
end of five years from the relevant date thereof, or the shorter period as may
be prescribed by applicable law.



         Subject to specific limitations described in the indenture, we reserve
the right at any time to vary or terminate the appointment of the securities
registrar or any paying agent or transfer agent with or without cause, upon
giving 30 days' written notice to the securities registrar, the paying agent or
transfer agent, as the case may be, and the trustee, and to appoint another
securities registrar or additional or other paying agents or transfer agents and
to approve any change in the specified offices through which any paying agent or
transfer agent acts so long as we will at all times maintain a securities
registrar, paying agent and transfer agent in the County of New York, The City
of New York.


Optional Redemption

         We may redeem all of the new bonds of each series, in whole or in part,
at our option at any time, at a redemption price equal to the outstanding
principal amount plus accrued and unpaid interest to the redemption date,
together with the applicable make-whole premium.

Mandatory Redemption

Event of Loss and Event of Eminent Domain


         If either an event of loss or an event of eminent domain occurs, as
soon as reasonably practicable but no later than the date of receipt by us or
the collateral agent of casualty proceeds or eminent domain proceeds, as the
case may be, we must make a reasonable good faith determination as to whether
(1) our facility or any portion can be rebuilt, repaired or restored to permit
operation on a commercially feasible basis and (2) the casualty proceeds or the
eminent domain proceeds, as the case may be, together with any other amounts
that are available to us for the rebuilding, repair or restoration are
sufficient to permit the rebuilding, repair or restoration of our facility or a
portion thereof. Our determination must be evidenced by a certificate as to
redemption filed with the collateral agent which, if we determine that our
facility or a portion thereof can be rebuilt, repaired or restored to permit
operation on a commercially feasible basis and that the casualty proceeds or the
eminent domain proceeds, as the case may be, together with any other amounts
that are available to us for the rebuilding, repair or restoration, are
sufficient, must also describe a reasonable good faith estimate by us of the
total cost of the rebuilding, repair or restoration. We must deliver to the
collateral agent at the time it delivers the certificate as to redemption a
certificate of the independent engineer, dated the date of the certificate as to
redemption, confirming that, based upon reasonable investigation and review of
the determination made by us, the independent engineer believes the
determination and the estimate of the total cost, if any, described in the
certificate as to redemption to be reasonable.


         We must redeem all of the new bonds upon an event of loss or an event
of eminent domain:

         o        in whole, at a redemption price equal to 100% of the principal
                  amount together with any accrued and unpaid interest through
                  the redemption date, within 90 days after receipt by the
                  trustee of casualty proceeds or eminent domain proceeds if our
                  facility is substantially destroyed and cannot be rebuilt,
                  repaired or restored to permit operation on a commercially
                  feasible basis or an event of eminent domain has occurred and
                  our facility cannot be operated on a commercially feasible
                  basis, as the case may be. Our obligation to redeem the bonds
                  upon an event of loss or an event of eminent domain under the
                  preceding circumstances is not limited to the casualty
                  proceeds or eminent domain proceeds actually received; or


         o        in part, at a redemption price equal to 100% of the principal
                  amount together with any accrued and unpaid interest through
                  the redemption date, within 90 days after receipt by the
                  trustee of casualty proceeds or eminent domain proceeds if a
                  portion of our facility is destroyed or taken but our facility
                  can be rebuilt, repaired or


                                       74
<PAGE>

                  restored to permit operation on a commercially feasible basis.
                  The aggregate amount of the new bonds to be redeemed under
                  this paragraph will equal the amount received by the trustee
                  in accordance with the applicable provision of the collateral
                  agency agreement. The new bonds, however, must not be subject
                  to mandatory redemption when the proceeds not used for
                  rebuilding, repair or restoration do not exceed $5 million and
                  we certify to the trustee, which certification is confirmed by
                  the independent engineer, that (1) the proceeds are not needed
                  for rebuilding, repair or restoration of our facility or (2)
                  not using the proceeds for the rebuilding, repair or
                  restoration of our facility would not reasonably be expected
                  to result in a material adverse effect.



         Any eminent domain proceeds and casualty proceeds received by the
trustee under the two preceding paragraphs must be deposited in the redemption
subaccount.


Upon Receipt of Performance Liquidated Damages Under the Construction
Agreement


         If we receive performance liquidated damages under the construction
agreement, we must, as soon as reasonably practicable, make a reasonable good
faith determination as to whether:



         o        it is technically feasible to modify, repair or replace any
                  portion of our facility in order to remedy the circumstances
                  giving rise to the obligation of Siemens Westinghouse to pay
                  the performance liquidated damages;



         o        the performance liquidated damages, together with any other
                  amounts that are available to us for the modification, repair
                  or replacement, are sufficient to permit the modification,
                  repair or replacement, including the making of all required
                  payments of interest and principal on our indebtedness during
                  the modification, repair or replacement;



         o        the projected average senior debt service coverage ratio,
                  after giving effect to the modification, repair or replacement
                  and the application of the performance liquidated damages to
                  accomplish the same, during the power purchase agreement term
                  (taken as one period) and the post-power purchase agreement
                  period (taken as one period) would be equal to or greater than
                  the projected average senior debt service coverage ratio
                  described in the base case projections for each period
                  included in this prospectus; and



         o        the projected minimum senior debt service coverage ratio,
                  after giving effect to the modification, repair or replacement
                  and the application of the performance liquidated damages to
                  accomplish the same, during the power purchase agreement term
                  and the post-power purchase agreement period would be equal to
                  or greater than the projected minimum senior debt service
                  coverage ratio described in the base case projections for each
                  period included in this prospectus.



Our determination must be evidenced by an officer's certificate, together with
supporting detail as the collateral agent or the independent engineer may
reasonably request, filed with the collateral agent which, if we determine that
the portion of our facility can be modified, repaired or replaced and that the
other statements described above are true, must also describe our reasonable
good faith estimate of the total cost of the modification, repair or
replacement. We must deliver to the collateral agent at the time we deliver the
officer's certificate referred to above a certificate of the independent
engineer, dated the date of the officer's certificate, stating that, based upon
reasonable investigation and review of the determinations, assumptions,
conclusions and estimates of costs made by us, the independent engineer believes
the determinations, assumptions, conclusions and estimates of costs described in
the officer's certificate are reasonable.



      If the requirements of the preceding paragraph are satisfied, the
collateral agent must apply the amounts received from Siemens Westinghouse to
the payment, or reimbursement to the extent the same have been paid or satisfied
by us, of the costs of modification, repair and replacement of that portion of
our facility that requires modification, repair or replacement in order to
remedy the circumstances giving rise to the obligation of Siemens Westinghouse
to pay the performance liquidated damages. Upon receipt of an officer's
certificate from us, confirmed by the independent engineer, certifying that


         o        all modifications, repairs or replacements of that portion of
                  our facility that requires modification, repair or replacement
                  in order to remedy the circumstances giving rise to the
                  obligation of Siemens Westinghouse to pay performance
                  liquidated damages have been completed and

         o        the projected debt service coverage ratio tests referred to in
                  the immediately preceding paragraph continue to be met,

                                       75

<PAGE>


the collateral agent must transfer all remaining proceeds of the performance
liquidated damages to us or to whomever we in writing direct.


         If the requirements of the preceding paragraph are not satisfied, then
we must redeem the new bonds.


         Any performance liquidated damages under the construction agreement
received by the trustee under the preceding paragraph must be deposited in the
redemption subaccount.


Upon Receipt of Proceeds Under the Guaranty by The Williams Companies, Inc.


         If the power purchase agreement is terminated as a result of an event
of default by Williams Energy and we receive proceeds under the guaranty
provided by The Williams Companies, Inc. in respect thereof, we must redeem the
new bonds, in whole or in part, at a redemption price equal to 100% of the
principal amount together with any accrued and unpaid interest to the redemption
date, as soon as reasonably practicable, but in any event within 90 days of the
receipt of the proceeds. After the payment of specific administrative fees, the
aggregate amount of the new bonds to be redeemed under this paragraph, including
accrued and unpaid interest, will equal an amount which is equal to the amount
paid under the guaranty provided by The Williams Companies, Inc. multiplied by a
fraction the numerator of which is the then outstanding principal amount of the
new bonds and accrued and unpaid interest and the denominator of which is the
principal of and accrued and unpaid interest on all senior debt including the
new bonds.


Ratings


         The new bonds are expected to be rated "BBB-" by Standard & Poor's and
"Baa3" by Moody's. The ratings reflect only the views of the rating agencies at
the time the rating is issued, and any explanation of the significance of the
ratings may only be obtained from the rating agency. There is no assurance that
the ratings will remain in effect for any given period of time or that the
ratings will not be lowered, suspended or withdrawn entirely by the rating
agency, if, in the rating agency's judgment, circumstances so warrant. Any
lowering, suspension or withdrawal of any rating may have an adverse effect on
the market price or marketability of the new bonds.


Book-Entry, Delivery and Form


         The new bonds will initially be represented by one or more permanent
global bonds in definitive, fully registered book-entry form that will be
registered in the name of Cede & Co., the global bond holder, as nominee of DTC.
The global bonds will be deposited on behalf of the acquirors of the new bonds
represented thereby with a custodian for DTC for credit to the respective
accounts of the acquirors or to the other accounts as they may direct at DTC.
See "THE EXCHANGE OFFER--Procedures for Tendering--Book-Entry Transfer."


The Global Bonds

         We expect that under procedures established by DTC:


         o        upon deposit of the global bonds with DTC or its custodian,
                  DTC will credit on its internal system portions of the global
                  bonds that must be comprised of the corresponding respective
                  amounts of the global bonds to the respective accounts of
                  persons who have accounts with the depositary; and


         o        ownership of the bonds will be shown on, and the transfer of
                  ownership thereof will be effected only through, records
                  maintained by DTC or its nominee, with respect to interests of
                  persons, or "participants," who have accounts with DTC , and
                  the records of participants, with respect to interests of
                  persons other than participants.


         So long as DTC or its nominee is the registered owner or holder of any
of the bonds, DTC or the nominee will be considered the sole owner or holder of
the bonds represented by the global bonds for all purposes under the indenture
and under the bonds represented thereby. No beneficial owner of an interest in
the global bonds will be able to transfer the interest except in accordance with
the applicable procedures of DTC in addition to those provided for under the
indenture.



         Payments on the bonds represented by the global bonds will be made to
DTC or its nominee, as the case may be, as the registered owner of the global
bonds. Neither we, the trustee nor any paying agent under the indenture will
have any responsibility or liability for any aspect of the records relating to
or payments made on account of beneficial ownership interests in the global
bonds or for maintaining, supervising or reviewing any records relating to the
beneficial ownership interest.



         We expect that DTC or its nominee, upon receipt of any payment on the
bonds represented by the global bonds, will credit participants' accounts with
payments in amounts proportionate to their respective beneficial interests in
the


                                       76
<PAGE>

global bonds as shown in the records of DTC or its nominee. We also expect that
payments by participants to owners of beneficial interests in the global bonds
held through the participants will be governed by standing instructions and
customary practice as is now the case with securities held for the accounts of
customers registered in the names of nominees for the customers. The payment
will be the responsibility of the participants.


         Transfers between participants in DTC will be effected in accordance
with DTC rules and will be settled in immediately available funds.


         DTC has advised us that it will take any action permitted to be taken
by a holder of bonds, including the presentation of bonds for exchange as
described below, only at the direction of one or more participants to whose
account the DTC interests in the global bonds are credited and only in respect
of the aggregate principal amount as to which the participant or participants
has or have given the direction. However, if there is an event of default under
the indenture, DTC will exchange the global bonds for certificated securities
that it will distribute to its participants.


         DTC has advised us as follows:

         o        DTC is a limited-purpose trust company organized under the New
                  York Banking Law, a "banking organization" within the meaning
                  of the New York Banking Law, a member of the Federal Reserve
                  System, a "clearing corporation" within the meaning of the New
                  York Uniform Commercial Code and a "clearing agency"
                  registered under the provisions of Section 17A of the Exchange
                  Act;


         o        DTC holds securities that its participants deposit with DTC
                  and facilitates the settlement among participants of
                  securities transactions, the as transfers and pledges, in
                  deposited securities through electronic computerized
                  book-entry changes in participants' accounts, thereby
                  eliminating the need for physical movement of securities
                  certificates;


         o        Direct participants include securities brokers and dealers,
                  banks, trust companies, clearing corporations and other
                  organizations;

         o        DTC is owned by a number of its participants and by the New
                  York Stock Exchange, Inc., the American Stock Exchange, Inc.
                  and the National Association of Securities Dealers, Inc.;


         o        Access to the DTC system is also available to others the as
                  securities brokers and dealers, banks and trust companies that
                  clear through or maintain a custodial relationship with a
                  direct participant, either directly or indirectly; and


         o        The rules applicable to DTC and its participants are on file
                  with the SEC.


         Although DTC is expected to follow these procedures in order to
facilitate transfers of interests in the global bonds among participants of DTC,
it is under no obligation to perform the procedures, and the procedures may be
discontinued at any time. Neither we nor the trustee will have any
responsibility for the performance by DTC or its direct or indirect participants
of their respective obligations under the rules and procedures governing their
operations.


Certificated Securities

         As of the date of this prospectus, all of the interests in old bonds
are in book-entry form. It is not expected that any old bonds will be in
registered certificated form at the time of the exchange. It is expected that
all old bonds before the exchange, and all bonds outstanding after the exchange,
will be represented by global certificates for bonds in bearer form held by The
Bank of New York as depositary and that DTC will have a book-entry interest in
those bonds. Beneficial interests in those bonds will be held through
participants in DTC acting as securities intermediaries. Therefore, references
in this section to bonds are references to beneficial interests in the bonds in
book-entry form except where the discussion is explicitly about certificated
bonds, and references to owners are to owners of those beneficial interests.

         Interests in the global bonds will be exchanged for certificated
securities if:

         o        DTC or any successor depositary notifies us that it is
                  unwilling or unable to continue as depositary for the global
                  bonds, or DTC ceases to become a "clearing agency" registered
                  under the Exchange Act, and a successor depositary is not
                  appointed by us within 90 days;


         o        an event of default has occurred and is continuing with
                  respect to the bonds and the registrar has received a request
                  from DTC or any successor depository to issue certificated
                  securities within 30 days of the request; or




                                       77
<PAGE>

         o        we determine not to have the bonds represented by global
                  bonds.


         Upon the occurrence of any of the events described in the preceding
sentence, we will cause the appropriate certificates securities to be delivered.
Neither we nor the trustee will be liable for any delay by DTC or any successor
depository or its nominee in identifying the beneficial owners of the related
bonds. Each person may conclusively rely on instructions from DTC or any
successor depository or the nominee for all purposes, including the registration
and delivery and the respective principal amounts, of the new bonds to be
issued.


         Owners of old bonds should instruct the brokers, dealers, commercial
banks or trust companies with whom they have securities accounts or their
nominees to tender for them. Exchanges by owners will be represented by an
exchange of global certificates for old bonds held by the depositary for global
certificates for new bonds. If fewer than all old bonds are tendered for
exchange, the depositary will hold separate global certificates for bonds
representing the appropriate aggregate amounts of remaining old bonds and of new
bonds.

Same-Day Settlement and Payment


         The indenture requires that payments in respect of the bonds
represented by the global bonds, including principal, premium, if any, and
interest, be made by wire transfer of immediately available funds to the
accounts specified by the global bond holder. With respect to certificated
bonds, if any, we will make all payments of principal, premium, if any, and
interest by wire transfer of immediately available funds to the accounts
specified by the holders thereof or, if no account is specified, by mailing a
check to each holder's registered address. Secondary trading in long-term bonds
and debentures of corporate issues is generally settled in clearinghouse or
next-day funds. In contrast, bonds represented by the global bonds are expected
to be eligible to trade in the PORTAL market and to trade in DTC's Same-Day
Funds Settlement System, and any permitted secondary market trading activity in
the bonds will, therefore, be required by DTC to be settled in immediately
available funds. We expect that secondary trading in the certificated bonds will
also be settled in immediately available funds.



         Because of time zone differences, the securities account of a Euroclear
or Cedel participant purchasing an interest in global bonds from a participant
in DTC will be credited, and any crediting will be reported to the relevant
Euroclear or Cedel participant, during the securities settlement processing day,
which must be a business day for Euroclear or Cedel, immediately following the
settlement date of DTC. DTC has advised us that cash received in Euroclear or
Cedel as a result of sales of interests in a global bond by or through a
Euroclear or Cedel participant to a participant in DTC will be received with
value on the settlement date of DTC but will be available in the relevant
Euroclear or Cedel cash account only as of the business day for Euroclear or
Cedel following DTC's settlement date.


Year 2000

         DTC management is aware that some computer applications, systems, and
the like for processing data that are dependent upon calendar dates, including
dates before, on, and after January 1, 2000, may encounter "Year 2000 problems."
DTC has informed its participants and other members of the financial community
that it has developed and is implementing a program so that its systems, as the
same relate to the timely payment of distributions, including principal and
income payments, to securityholders, book-entry deliveries, and settlement of
trades within DTC, continue to function appropriately. This program includes a
technical assessment and a remediation plan, each of which is complete.
Additionally, DTC's plan includes a testing phase which is expected to be
completed within approximate time frames.


         However, DTC's ability to perform property its services is also
dependent upon other parties, including but not limited to issuers and their
agents, as well as third-party vendors from whom DTC licenses software and
hardware, and third-party vendors on whom DTC relies for information or the
provision of services, including, telecommunication and electrical utility
service providers, among others. DTC has informed the financial community that
it is contacting, and will continue to contact, third-party vendors from whom
DTC acquires services to: (1) impress upon them the importance of the services
being Year 2000 compliant and (2) determine the extent of their efforts for Year
2000 remediation, and as appropriate, testing, of their services. In addition,
DTC is in the process of developing the contingency plans as it deems
appropriate.


Limited Recourse Nature of the New Bonds


         All obligations in connection with the new bonds are solely of our
obligations. The bondholders must have recourse only to us and the collateral
for repayment of the new bonds. No holder of ownership interests in our company
or any other affiliate of ours or any of their respective incorporators,
stockholders, directors, officers or employees has or will guarantee the payment
of the new bonds. The bondholders must have no claim against or recourse to the
holders of



                                       78
<PAGE>

the ownership interests in our company or any other affiliate of ours or their
respective incorporators, stockholders, directors, officers or employees by
operation of law or otherwise for the repayment of the new bonds.


                                       79

<PAGE>

                    SUMMARY OF PRINCIPAL FINANCING DOCUMENTS


         The following summaries contain the material terms of the principal
financing documents. All capitalized terms used in the following and not
otherwise defined in this prospectus have the meanings given to them in Annex A
to this prospectus.


                                    Indenture

Accounts

Indenture Accounts


         The following accounts have been established by the trustee: the bond
payment account, including the interest payment subaccount, the principal
payment subaccount and the redemption subaccount, and the construction interest
account. All amounts from time to time held in each indenture account must be
held in the name of the trustee subject to the lien and security interest
granted under the indenture and in the custody of the depositary bank on behalf
of the trustee.


Bond Payment Account


         The trustee must deposit (1) all funds received by it for the payment
of interest on the bonds into the interest payment subaccount of the bond
payment account for disbursement in accordance with the indenture and (2) all
funds received by it for the payment of principal on the bonds, including any
funds transferred from the redemption subaccount of the bond payment account,
into the principal payment subaccount of the bond payment account for
disbursement in accordance with the indenture.


Construction Interest Account


         The trustee must deposit all funds received by it for the payment of
interest on the bonds from and including the date of original issuance of the
bonds then outstanding to and through the commercial operation date into the
construction interest account. The trustee will disburse from the construction
interest account the amount required to pay interest on the bonds when due,
whether on an interest payment date or upon call for redemption or by
acceleration or otherwise. On the commercial operation date and upon our
delivery to the collateral agent and the trustee of a commercial operation
certificate, the trustee must transfer all funds remaining in the construction
interest account to the bond payment account for deposit in the interest payment
subaccount.


Interest Payment Subaccount, Principal Payment Subaccount and Redemption
Subaccount

         o The trustee is authorized and directed to disburse from the interest
payment subaccount, the amount required to pay interest on the bonds when due,
whether on an interest payment date or upon call for redemption or by
acceleration or otherwise.

         o The trustee is authorized and directed to disburse from the principal
payment subaccount, the amount required to pay principal on the bonds when due,
whether on a principal payment date or upon call for redemption or by
acceleration or otherwise.


         o The trustee is authorized and directed to disburse funds from the
redemption subaccount, when amounts on deposit therein equal or exceed
$5,000,000, for the redemption of bonds in accordance with the indenture. The
preceding notwithstanding, the trustee must transfer funds remaining in the
redemption subaccount for more than one year and not applied to the redemption
of bonds under the indenture to the principal payment subaccount for application
by the trustee in accordance with the indenture.


Affirmative Covenants

         We have made the following affirmative covenants in the indenture:

Payment of Principal, Premium, if any, and Interest


         We must punctually pay, or cause to be paid, the principal of, any
premium, and interest on, and all other amounts payable in respect of, the bonds
in accordance with their terms and the terms of the indenture and of the related
series supplemental indenture.




                                       80
<PAGE>

Reporting Requirements


         We must furnish to the senior creditors:



         (1) as soon as practicable and in any event within 60 days after the
end of the first, second and third quarterly accounting periods of each fiscal
year, commencing with the quarter ending September 30, 1999, an unaudited
balance sheet as of the last day of the quarterly period and the related
statements of income and cash flows, and reports of all dividends and other
distributions paid to owners during the quarterly period prepared in accordance
with GAAP and, in the case of second and third quarterly periods, for the
portion of the fiscal year ending with the last day of the quarterly period;



         (2) as soon as practicable and in any event within 120 days after the
end of each fiscal year, commencing with the fiscal year ended December 31,
1999, a balance sheet as of the end of the year and the related statements of
income and cash flow during the year;



         (3) at the time of the delivery of the financial statements provided
for in clauses (1) and (2) above, an officer's certificate to the effect that,
to the best of the officer's knowledge, (a) we are in compliance with all of our
material obligations under the terms of the transaction documents the
non-performance of which has resulted or could reasonably be expected to result
in a material adverse effect and (b) to the best of the officer's knowledge, no
default or event of default has occurred and is continuing to occur or, if any
default or event of default has occurred and is continuing to occur, specifying
the extent of the default and what action we are taking or propose to take; and


         (4) each of the following items:


         o written notice of the occurrence of any event or condition which
constitutes an event of default and an officer's certificate, setting forth the
details of the default or condition and the action which we are taking or
propose to take promptly after we obtain actual knowledge of the occurrence;



         o written notice of the occurrence of any event of eminent domain or
any event of loss and an officer's certificate, setting forth the details and
the action which we are taking or propose to take promptly after we obtain
actual knowledge of the occurrence; and



         o until the occurrence of the commercial operation date, within 45 days
after the end of each fiscal quarter, starting with our quarter ending September
30, 1999, a quarterly construction report describing the progress of our
facility's construction and expenditure of funds;



         (5) we must furnish or cause to be furnished to the senior creditors no
later than six months prior to the expiration of the term of the power purchase
agreement an independent forecast prepared by an independent consultant which
sets forth projections of (a) electricity prices for the PJM power pool market
(or if the market no longer exists at the time, any successor market or
substitute market as determined in good faith by us which approximates, to the
extent practicable, the region) and (b) gas prices on a delivered basis to our
facility, in each case on at least an annual basis through the final maturity
date for the bonds. We, however, should not be required to provide the
independent forecast if:



         o        we enter into a replacement power purchase agreement,
                  effective as of the expiration of the power purchase agreement
                  and extending to at least the final maturity date for the
                  bonds,



         o        the projected senior debt service coverage ratio through the
                  final maturity date for the bonds, based on the provisions of
                  the replacement power purchase agreement are greater than 2.0
                  to 1 and



         o        the senior unsecured long term debt of the power purchaser(s)
                  under the agreement(s) is rated at least investment grade;



         (6) upon the request of any bondholder, or the trustee on behalf of a
holder of a beneficial interest in the bonds, we must furnish the information
specified in paragraph (d)(4) of Rule 144A to the bondholder, and holders of
beneficial interests in the bonds, to a prospective purchaser of the bonds, and
prospective purchasers of beneficial interests in the bonds, who is a Qualified
Institutional Buyer or Institutional Accredited Investor or to the trustee for
delivery to the bondholder or prospective purchaser of the bonds, as the case
may be, unless, at the time of the request, we are subject to the reporting
requirements of Section 13 or 15(d) of the Exchange Act;



         (7) all information provided to the senior creditors under clauses (1),
(2), (3) and (4) above must also be provided by the trustee (a) to the
bondholders and (b) to holders of beneficial interests in the bonds or
prospective


                                       81
<PAGE>

purchasers of the bonds or beneficial interests in the bonds upon written
request to the trustee, which may be a single continuing request. We must
furnish the trustee, upon its request, with sufficient copies of all the
information to accommodate the requests of the holders of beneficial interests
in the bonds; and



         (8) the information specified in paragraphs (1), (2), (3), (4) and (5)
above must be provided to each rating agency concurrently with its delivery to
the senior creditors.


Insurance Report

Insurance


         We must maintain or cause to be maintained in accordance with the terms
of the indenture the following insurance coverages: (1) during construction of
our facility, builder's risk, delayed start-up, comprehensive general liability,
workers' compensation and employer's liability, automobile liability and
umbrella liability; and (2) subsequent to transfer of care, custody and control
of the facility to us, all risk property and boiler and machinery insurance,
business interruption, comprehensive general liability, workers' compensation
and employer's liability, automobile liability and umbrella liability. All
policies of insurance except workers' compensation and automobile liability
policies must name the collateral agent and Williams Energy as additional
insureds. If at any time any of the required insurance is no longer be available
on commercially reasonable terms, as confirmed by the independent insurance
adviser, we must procure substitute insurance coverage reasonably satisfactory
to the independent insurance advisor that is the most equivalent to the required
coverage and that is available on commercially reasonable terms.


Maintenance of Existence, Liens and Governmental Approvals


         We must at all times:



         o preserve and maintain in full force and effect (1) its existence as a
limited liability company and its good standing under the laws of the State of
Delaware and (2) its qualification to do business in each other jurisdiction in
which the character of the properties owned or leased by it or in which the
transaction of its business as conducted or proposed to be conducted makes the
qualification necessary;


         o obtain and maintain in full force and effect all governmental
approvals, including maintaining compliance with environmental laws, and other
consents and approvals required at any time in connection with the construction,
maintenance, ownership or operation of our facility;

         o preserve and maintain good and marketable title to its properties and
assets, subject to no liens other than permitted liens; and

         o preserve and maintain liens of the senior creditors on the
collateral.

Operating and Maintenance


         We must, or must cause the operator to, use, maintain and operate our
facility and the facility site in compliance with generally accepted prudent
operating and maintenance practices and the material provisions of all relevant
project contracts.


Compliance with Applicable Laws


         We must comply with, and must ensure that our facility is constructed
and operated in compliance with, and must make alterations to our facility and
the facility site as may be required for compliance with, all applicable laws,
environmental laws and governmental approvals, except where noncompliance would
not reasonably be expected to result in a material adverse effect.


Project Contracts; Guaranty by The Williams Companies, Inc.; Operation of our
Facility


         We must (1) perform and observe in all material respects our covenants
and agreements contained in any of our project contracts, (2) enforce, defend
and protect all of our rights contained in any of our project contracts and (3)
take all reasonable and necessary actions to prevent the termination or
cancellation of any of our project contracts, except in case of (1) and (2)
above, where the non-performance could not reasonably be expected to have a
material adverse effect.



         We (1) will fully enforce our rights under the guaranty provided by The
Williams Companies, Inc. and the power purchase agreement with respect to
substitute security under the circumstances provided for therein and (2) will
not, without the consent of bondholders holding a majority in outstanding
principal amount of the bonds, make a demand


                                       82
<PAGE>

for or take any legal action under the guaranty provided by The Williams
Companies, Inc. if, as a result of payments made under the demand or legal
action by us, the aggregate amount available under the guaranty provided by The
Williams Companies, Inc. would be less than or equal to the principal amount of
the then outstanding senior debt, including the undrawn portions of the maximum
amounts of any debt service reserve letter of credit or construction period
letter of credit. We will (1) upon any payment event of default or other event
of default under the power purchase agreement, exercise our rights to terminate
the power purchase agreement in accordance with its terms, (2) if of any
termination of the power purchase agreement, fully enforce its rights under the
guaranty provided by The Williams Companies, Inc. and (3) use any amounts
obtained under the guaranty provided by The Williams Companies, Inc. to redeem
the bonds in accordance with the indenture and to pay principal and interest on
our other senior debt in accordance with the financing documents and in each
case in accordance with the collateral agency agreement.



         We will (1) exercise all of our rights under the operations agreement
to terminate the agreement if (a) a bankruptcy event in respect of the operator
has occurred and is continuing and (b) the operator has failed to perform any
material obligation under the operations agreement and (2) exercise our rights
under the operations agreement to cause the operator to terminate the services
agreement under the terms of that agreement if (a) a bankruptcy event in respect
of The AES Corporation has occurred and is continuing and (b) The AES
Corporation has failed to perform any material obligation under the services
agreement.


Annual Budget


         Not less than 30 days prior to (1) the anticipated commercial operation
date, and thereafter (2) the commencement of each fiscal year, we must provide
to the senior creditors and the rating agencies an annual budget. The first
annual budget must cover the period from the commercial operation date through
the end of the fiscal year in which the commercial operation date occurs, and if
the period consists of less than six months, for the immediately succeeding
fiscal year. Each annual budget must specify the estimated sales of capacity and
energy under the power purchase agreement and any replacement power purchase
agreement and all other sales of capacity and energy, the estimated rates and
revenues for each category of the sales, all operating and maintenance costs, a
manpower forecast, a periodic inspection, maintenance and repair schedule, a
description of all required capital expenditures and the underlying operating
assumption and implementation plans for the fiscal year covered by the annual
budget. We must operate and maintain our facility, or cause our facility to be
operated and maintained, in accordance with the annual budget other than
deviations resulting from operating requirements under our project contracts or
prudent operating and maintenance practices.


Insurance Report


         Within 30 days after the end of each fiscal year, we must submit to the
senior creditors and each rating agency that currently is rating any of the
bonds then outstanding a certificate (1) listing all insurance being carried by,
or on behalf of, us under the indenture and (2) certifying that all insurance
policies required to be maintained under our project contracts and the indenture
are in full force and effect and all premiums therefor have been fully paid.


Inspection


         The senior creditors will have the right, upon reasonable advance
written notice, to inspect our facility and the facility site from time to time
so long as we have the right to specify reasonable dates and times for any the
inspection in order to avoid any material interference with operation of our
facility.


Construction of our Facility


         We must cause the construction of our facility to be prosecuted and
completed with diligence and continuity, except for interruptions provided for
in the construction agreement or due to events of force majeure, which events of
force majeure we must use our best efforts to mitigate, in a good and
workmanlike manner and in accordance with sound, generally accepted building and
engineering practices, all material applicable governmental requirements and the
construction agreement. We must at all times cause a complete set of the current
and, when available, as-built plans, and all supplements, relating to our
facility to be maintained on the facility site or Siemens Westinghouse's offices
and available for inspection by thereto independent engineer.


Contractor Performance Tests; Final Acceptance


         The independent engineer will have the right to witness and verify the
performance tests required by the construction agreement. We must not, without
the prior written confirmation by the independent engineer, either


                                       83
<PAGE>

(1) grant the Final Acceptance Certificate to Siemens Westinghouse under the
construction agreement or (2) elect to effect Final Acceptance under the
construction agreement.


Casualty Proceeds; Eminent Domain Proceeds


         We must cause all casualty proceeds and eminent domain proceeds to be
deposited in the restoration account under the collateral agency agreement.


Payment of Taxes and Impositions


         We will pay or cause to be paid, before any fine, interest or penalty
is imposed, all impositions. If, under any applicable law, any impositions may
at our option be paid in installments whether or not interest accrues on the
unpaid balance, we will have the right to exercise the option and to pay or
cause to be paid the impositions and any accrued interest in installments as
they fall due and before any fine, penalty, further interest or cost may be
added so long as no event of default then exists.



         We will pay all taxes and other governmental charges (including stamp
taxes) assessed by any governmental authorities and imposed on the collateral
agent, its successors or assignees, by reason of the collateral agent's
ownership of the mortgage or the other security documents or payable by either
us or the collateral agent upon any modification, amendment, extension and/or
consolidation. We will also pay any tax imposed directly or indirectly on the
mortgage in lieu of a tax on the mortgaged property or any part thereof, whether
by reason of (1) the passage after the date of the mortgage of any law of the
Commonwealth of Pennsylvania deducting from the value of real property for the
purposes of taxation any lien, (2) any change in the laws for the taxation of
mortgages or debts secured by mortgages for state or local purposes, (3) a
change in the means of collection of any the tax or (4) any tax, now or
hereafter assessed against the mortgage or assessed against, or withheld from,
any payments made by us under the indenture.



         We will not claim or demand or be entitled to any credit or credits for
the payment of any Impositions, and no deduction must otherwise be made or
claimed from the taxable value of the mortgaged property, or any part thereof,
by reason of the mortgage.


Preservation of Lien of Mortgage

         We will (1) preserve our right, title and interest in and to the
mortgaged property and will warrant and defend the same against any and all
claims and demands whatsoever, (2) continue to have full power and lawful
authority to encumber and convey the mortgaged property as provided in the
mortgage and (3) maintain and preserve the priority of the lien of the mortgage
until all of the obligations under the financing documents are paid and
performed in full.

Negative Covenants

         We will make the following negative covenants:

Limitations on Additional Indebtedness


         We must not create or incur or suffer to exist any indebtedness or
lease obligations except for:


         o        the bonds;

         o        indebtedness incurred under the debt service reserve letter of
                  credit and reimbursement agreement or any construction period
                  letter of credit and reimbursement agreement;

         o        letters of credit and other financial obligations arising
                  under our project contracts;


         o        subordinated debt of affiliates;



         o        purchase money obligations incurred to finance specific items
                  of equipment that do not comprise an integral part of our
                  project that extend only to the equipment being financed and
                  that do not in the aggregate have annual debt service or lease
                  obligations exceeding $5 million;



         o        trade accounts payable, other than for borrowed money,
                  arising, and accrued expenses incurred, in the ordinary course
                  of business so long as the trade accounts payable are payable
                  within 90 days of the date the respective goods are delivered
                  or the respective services are rendered;



         o        obligations in respect of surety bonds or similar instruments
                  in an aggregate amount not exceeding $5 million outstanding at
                  any one time;




                                       84
<PAGE>

         o        any lines of credit for working capital purposes in the
                  maximum amount of $5 million;


         o        senior debt used for an expansion of our facility; however, we
                  may issue senior debt if (1) (a) the projected average senior
                  debt service coverage ratio, after giving effect to the senior
                  debt, is at least 1.50 to 1.0 through the end of the power
                  purchase agreement term (taken as one period) and at least
                  2.50 to 1.0 during the post-power purchase agreement period
                  (taken as one period) and (b) the projected minimum senior
                  debt service coverage ratio, after giving effect to the senior
                  debt, is at least 1.30 to 1.0 through the end of the power
                  purchase agreement term and at least 2.15 to 1.0 during the
                  post-power purchase agreement period; (2) we provide a ratings
                  reaffirmation from each of the rating agencies; and (3) the
                  trustee does not, within 60 days of notice to holders of the
                  bonds setting forth a summary of the terms of the senior debt
                  and a description of the facilities to be constructed with the
                  proceeds of the senior debt, receive an instruction from
                  persons holding a majority in principal amount of the bonds
                  not to permit the issuance of the senior debt; and



         o        senior debt or subordinated debt, from persons who are not our
                  affiliates, for required modifications to our facility and
                  optional modifications to our facility; however, we may issue
                  (1) senior debt on a parity basis with the bonds only for
                  required modifications to our facility and only if (a) the
                  projected average senior debt service coverage ratio, after
                  giving effect to the senior debt, is at least 1.30 to 1.0
                  through the end of the power purchase agreement term (taken as
                  one period) and at least 2.0 to 1.0 during the post-power
                  purchase agreement period (taken as one period) or (b) we
                  provide a ratings reaffirmation from each of the rating
                  agencies; (2) subordinated debt for required modifications to
                  our facility only if (x) the projected average total debt
                  service coverage ratio, after taking into account the
                  subordinated debt, is at least 1.20 to 1.0 through the end of
                  the power purchase agreement term (taken as one period) and at
                  least 1.65 to 1.0 during the post-power purchase agreement
                  period (taken as one period) and (B) the projected minimum
                  total debt service coverage ratio, after giving effect to the
                  subordinated debt, is at least 1.1 to 1.0 through the power
                  purchase agreement term and at least 1.35 to 1.0 during the
                  post-power purchase agreement period, or (2) we provide a
                  ratings reaffirmation from each of the rating agencies; or (3)
                  subordinated debt for optional modifications to our facility
                  only if we provide a ratings reaffirmation from each of the
                  rating agencies. In the case of clauses (2) and (3) of the
                  preceding proviso, the final maturity date of the subordinated
                  debt must not be earlier than the final maturity date for the
                  bonds and the average life of the subordinated debt must be no
                  shorter than the average remaining life of the bonds.


Restricted Payments


         We must not make any payments restricted under the indenture unless the
distribution conditions described in the collateral agency agreement have been
satisfied. See "SUMMARY OF PRINCIPAL FINANCING DOCUMENTS--Collateral Agency
Agreement--Distribution Account."


Prohibition of Change in Control


         We must not engage in, or permit to occur, any change in control, where
change in control means any failure by The AES Corporation, at all times while
bonds are outstanding, to maintain directly or indirectly at least a 51% voting
and economic interest in our company, unless prior to giving effect to the
reduction in the voting or economic interest of The AES Corporation in our
company either (1) each of the rating agencies provides a ratings reaffirmation
to the trustee or (2) the reduction in The AES Corporation's voting or economic
interest has been approved by bondholders holding at least 66-2/3% in aggregate
principal amount of the bonds.


Nature of Business


         We must not engage in any business other than the development,
financing, construction and operation and maintenance of our facility as
contemplated by our project contracts.


Amendments to Project Contracts


         We must not, except as otherwise expressly described in the financing
documents, terminate, amend or modify, other than immaterial amendments or
modifications as certified by us, any of our project contracts to which we are a
party, or consent to any assignment by another party, unless (1) we certify to
the senior creditors that the termination, amendment, modification or assignment
is not reasonably expected to result in a material adverse effect and the
termination, amendment, modification or assignment is not reasonably expected to
materially increase the likelihood of the occurrence of a future material
adverse effect and (2) the independent engineer does not within 10 business days
of receipt of the certificate disagree in writing to the certification provided
under clause (1). We, however, shall not:




                                       85
<PAGE>


         o        amend or modify the power purchase agreement unless in
                  addition to the requirements of clauses (1) and (2) above, we
                  certify that the amendment or modification would not cause our
                  net operating revenues to decrease by more than 5% and the
                  certification is confirmed by the independent engineer,



         o        except as otherwise expressly described in the financing
                  documents, terminate the power purchase agreement or consent
                  to any release of, assignment by or change in the identity of
                  Williams Energy unless (1) within 90 days of the termination
                  or consent resulting from an event of default by Williams
                  Energy under the power purchase agreement, or prior to any the
                  termination or consent or for any other reason we (a) enter
                  into a replacement power purchase agreement or (b) provide the
                  senior creditors and each of the rating agencies with a power
                  marketing plan and (2) we provide to the trustee and the
                  collateral agent a ratings reaffirmation from each rating
                  agency within the 90-day period or prior to the termination or
                  consent, as the case may be, or


         o        release or modify in any way the guaranty provided by The
                  Williams Companies, Inc. unless we obtain substitute security
                  therefor under the power purchase agreement.

Prohibition on Fundamental Changes and Disposition of Assets


         We must not enter into any transaction of merger or consolidation,
change our form of organization or our business, liquidate or dissolve
ourselves, or suffer any liquidation or dissolution, except as permitted in the
indenture. We must not amend its governing instruments except where the
amendment could not reasonably be expected to result in a material adverse
effect. We must not purchase or otherwise acquire all or substantially all of
the assets of any other person unless we may maintain ownership interests in
subsidiaries if the subsidiaries are involved in operation, maintenance or fuel
supply for our facility. In addition, except as contemplated by our project
contracts or permitted under the indenture, or as authorized by the first and
second provisos below, we must not sell, lease (as lessor) or transfer (as
transferor) any property or assets material to the operation of our facility
except in the ordinary course of business to the extent that the property is
worn out or is no longer useful or necessary in connection with the operation of
our facility. Furthermore, we:



         o        must not sell, lease or transfer any of the property or assets
                  without the written approval of the collateral agent, if the
                  aggregate fair market value of all sales, leases and transfers
                  in the current fiscal year exceeds $5 million; and



         o        may loan useful spare parts to other electric power generating
                  facilities owned by an affiliate of ours without prior
                  approval of the trustee or the collateral agent on the
                  conditions that, with respect to any spare part whose value is
                  in excess of $50,000, (1) at the time of the loan the
                  recipient of the spare part enters into an enforceable
                  obligation to replace the spare part in kind, or to pay to us
                  an amount equal to the replacement value of the spare part,
                  within 30 days of our demand for the same and (2) we certify
                  to the collateral agent that the spare part is not be
                  necessary for a planned outage or for scheduled maintenance of
                  our facility prior to being replaced, and the certificate is
                  confirmed by the independent engineer.


Liens


         We must not create or suffer to exist or permit any lien upon or with
respect to any of our properties, other than permitted liens.


Transactions with Affiliates


         We must not enter into any transactions with our affiliates other than
(1) the operations agreement and the equity subscription agreement and (2)
transactions in the ordinary course of business on fair and reasonable terms as
favorable to us as we would obtain in an arm's length transaction with an
unaffiliated third party.


Change Orders


         We must not initiate or approve any change order under the construction
agreement that individually exceeds $5,000,000 or when aggregated with all other
change orders exceeds $10,000,000, unless we certify in writing to the
collateral agent that (1) the change order is technically feasible, (2) the
change order is not reasonably expected to materially and adversely affect the
operation or reliability of our facility, (3) the implementation of the change
order is not reasonably expected to cause the commercial operation date to occur
after December 31, 2002 and (4) adequate funds are available to us to fund the
change orders and other project costs through the commercial operation date, and
the certification is confirmed by the independent engineer.




                                       86
<PAGE>

Events of Default


         Events of default under the indenture will include the following:



         o We fail to pay any principal, interest or any premium including any
make-whole premium, on a bond when the same becomes due and payable, whether
when it is scheduled to mature or upon any required prepayment or by
acceleration or otherwise and the failure continues for 10 or more days; or



         o Any representation or warranty made by us in the indenture proves to
have been false or misleading in any respect when made, confirmed or furnished
and the inaccuracy has resulted or is reasonably expected to result in a
material adverse effect on us and the circumstances surrounding the
misrepresentation continues uncured for 30 or more days from its discovery;
however, if we commence efforts to cure the factual situation resulting in the
misrepresentation within the 30-day period, we may continue to effect the cure
of the misrepresentation, and the misrepresentation will not be deemed to be an
event of default, for an additional 60 days so long as an authorized
representative of ours certifies that no other event of default has occurred and
is continuing and we are diligently pursuing the cure; or



         o We fail to maintain insurance in accordance with the indenture; or



         o We fail to perform or observe covenants or agreements in the
indenture with respect to the following: maintenance of existence and
governmental approvals; nature of business; compliance with applicable laws;
amendments to project contracts; prohibition on fundamental changes and
disposition of assets; liens; indebtedness; or restricted payments; and any
failure continues uncured for more than 30 days after we have actual knowledge
of the failure; or



         o A change in control occurs; or



         o We fail to perform or observe any of our covenants or agreements
contained in any other provision of the indenture not discussed above and the
failure continues uncured for more than 30 days after we have actual knowledge
of the failure; however, if we commence efforts to cure the default within the
30-day period and are diligently attempting to cure the default, and certifies
to the trustee the steps it is taking, we may continue to effect the cure of the
default, and the default will not be deemed an event of default, for an
additional 60 days so long as we certify that no other event of default has
occurred and is continuing and we are diligently pursuing the cure; or



         o We or, so long as The AES Corporation has any outstanding obligations
under any acceptable credit support, The AES Corporation or, so long as AES
Ironwood, Inc. has any outstanding obligations under the equity subscription
agreement, AES Ironwood, Inc. (1) apply for or consent to the appointment of, or
the taking of possession by, a receiver, custodian, trustee or liquidator of
itself or of all or substantially all of its property, (2) admit in writing its
inability, or be generally unable, to pay its debts as the debts become due, (3)
make a general assignment of the benefit of its creditors, (4) commence a
voluntary case under the Bankruptcy Code, (5) file a petition seeking to take
advantage of any law relating to bankruptcy, insolvency, reorganization,
winding-up or the composition or readjustment of debts, (6) fail to controvert
in a timely and appropriate manner, or acquiesce in writing to, any petition
filed against the person in an involuntary case under the Bankruptcy Code or (7)
take any corporate or other action for the purpose of effecting any of the
preceding; or



         o A proceeding or case is commenced without our application or consent
or, so long as The AES Corporation has any obligations under any acceptable
credit support, The AES Corporation or, so long as AES Ironwood, Inc. has any
outstanding obligations under the equity subscription agreement, AES Ironwood,
Inc., in any court of competent jurisdiction, seeking (1) its liquidation,
reorganization, dissolution, winding-up or the composition or readjustment of
debts, (2) the appointment of a trustee, receiver, custodian, liquidator or the
like of the person under any law relating to bankruptcy, insolvency,
reorganization, winding-up or the composition or adjustment of debts, and the
proceeding or case continues undismissed, or any order, judgment or decree
approving or ordering any of the preceding is entered and continues unstayed and
in effect, for a period of 90 or more consecutive days, or (3) any order for
relief against the person is entered in an involuntary case under the Bankruptcy
Code (each event described in this paragraph and in the preceding clause
referred to as a "bankruptcy event"); or



         o A final and non-appealable judgment or judgments for the payment of
money of more than $15,000,000 is rendered against us, and the same remain
unpaid or unstayed for a period of more than 60 or more consecutive days from
the date it is entered; or



         o An "event of default" has occurred and is continuing under the debt
service reserve letter of credit and reimbursement agreement, the construction
period letter of credit and reimbursement agreement or any other


                                       87
<PAGE>

indebtedness of ours the holder of which, or an agent or trustee therefor, is a
party to the collateral agency agreement, other than indebtedness incurred under
the indenture, or an "event of default" has occurred and is continuing in
respect of any other indebtedness of ours of more than $15,000,000; or



         o With respect to any project contract: (1) the project contract is
declared unenforceable by a governmental authority, (2) any other party denies
it has a material obligation under the project contract or (3) any other party
defaults in respect of its obligations under the project contract, and in the
case of each event described in clause (1), (2) or (3), the event would be
likely to result in a material adverse effect; however, none of the events will
be an event of default under the indenture if within 180 days (90 days in
respect of the power purchase agreement or the construction agreement) from the
occurrence of the event (a) the other party resumes performance or enters into
an alternative agreement with us or (b) we enter into a replacement contract or
contracts with another party or parties which (A) contain, as certified by us,
substantially equivalent terms and conditions or, if the terms and conditions
are no longer available on a commercially reasonable basis, the terms and
conditions then available on a commercially reasonable basis and (B) either (1)
we provide to the trustee and the collateral agent a ratings reaffirmation from
each rating agency or (2) we certify that we would, after giving effect to the
alternative agreement, maintain a projected minimum senior debt service coverage
ratio in any year during the remaining term of the bonds equal to or greater
than the lesser of (x) the projected minimum annual senior debt service coverage
ratio which would have been in effect had performance under the original project
contract continued and (y) 1.25 to 1.0 or (c) in the case of the power purchase
agreement, we deliver to the trustee and collateral agent a power marketing plan
and obtains a ratings reaffirmation from each rating agency; or



         o Any grant of a lien contained in the security documents ceases to be
effective to grant a perfected lien to the trustee or the collateral agent on a
material portion of the collateral described in the security documents with the
priority purported to be created thereby; however, we must have 10 days from
actual knowledge to cure the cessation; or


         o The construction of our facility is permanently abandoned; or


         o AES Ironwood, Inc. fails to perform or breaches any of its payment
obligations under the equity subscription agreement and the failure or breach
continues for 10 business days or more; or



         o Any acceptable credit provider fails to perform or breaches any of
its payment obligations under any acceptable credit support and the failure or
breach continues for 10 business days or more.


Remedies upon Default


         (1) If one or more events of default has occurred and is continuing,
then:



         o in the case of a bankruptcy event, the entire principal amount of the
bonds then outstanding, all interest accrued and not paid thereon, and any
premiums payable under the bonds and the indenture will automatically become due
and payable without presentment, demand, protest or notice of any kind, all of
which are waived; or



         o in the case of any other event of default, the trustee may, and upon
written direction of the bondholders holding not less than one-third of the
aggregate principal amount of outstanding bonds, the trustee will, by notice to
us, declare the entire principal amount of the bonds, all accrued and unpaid
interest, and any premium payable under the bonds and the indenture to be due
and payable, and the same will become due and payable without presentment,
demand, protest or further notice of any kind, all of which are waived; or



         o the trustee will, if the required bondholders request in writing to
the trustee, direct the collateral agent, to the extent permitted under the
collateral agency agreement, to take possession of all the collateral and, under
the collateral agency agreement, to sell the collateral, as and to the extent
permitted under the collateral agency agreement;



         (2) If an event of default occurs and is continuing and is known to the
trustee, the trustee will mail to each bondholder a notice of the event of
default within 30 days after its occurrence. Except in the case of an event of
default in payment of principal of or interest on any bond, the trustee may
withhold the notice to the bondholders if a committee of its trust officers in
good faith determines that withholding the notice is in the interest of the
bondholders;



         (3) At any time after the principal of the bonds become due and payable
upon a declared, but not an automatic, acceleration as provided in the
indenture, and before any judgment or decree for the payment of all or any
portion of the money so due, is entered, the bondholders of not less than a
majority in aggregate principal amount of the bonds then outstanding, by written
notice to us and the trustee, may rescind and annul the declaration and its
consequences if:




                                       88
<PAGE>


         o there has been paid to or deposited with the trustee a sum sufficient
to pay


         (a)      all overdue installments of interest on the bonds,


         (b)      the principal of and any premium on any bonds that have become
                  due otherwise than by the declaration of acceleration and
                  interest at the respective rates provided in the bonds for
                  late payments of principal or premium,



         (c)      to the extent that payment of the interest is lawful, interest
                  upon overdue installments of interest at the respective rates
                  provided in the bonds for late payments of interest, and


         (d)      all sums paid or advanced by the trustee under the indenture
                  and the reasonable compensation, expenses, disbursements, and
                  advances of the trustee, its agents and counsel, and


         o all events of default, other than the non-payment of the principal of
the bonds that has become due solely by the acceleration, have been cured or
waived as provided in the indenture;



No rescission will affect any subsequent default or impair any right consequent.



         Except as otherwise specifically provided in the indenture, the holders
of a majority in principal amount of the bonds will have the right to direct the
time, place and method of conducting any proceeding for any remedy available to
the trustee or exercising any power conferred on the trustee; so long as (1) the
direction does not conflict with any law or the indenture or the collateral
agency agreement and (2) the trustee may take any other action deemed proper by
the trustee which is not inconsistent with the direction.


         All rights and remedies available to the bondholders, or to the trustee
with respect to the collateral, or otherwise under the security documents, are
subject to the collateral agency agreement, including the ability to enforce any
remedy and the limitations on the trustee's ability to vote the interests
represented by the bonds.

Affiliate Cure Rights


         Any affiliate of ours will, at its option, have the right, but not the
obligation, to cure any events of default for which cures are applicable.


Trustee


         The Bank of New York, as successor to IBJ Whitehall Bank & Trust
Company, will act as the trustee under the indenture. The indenture provides
that the trustee will not be liable in connection with the performance of its
duties thereunder, except for its own gross negligence, bad faith or willful
misconduct. The trustee may become the owner of any bonds, with the same rights
it would have if it were not the trustee, and may carry any monies held by the
trustee on deposit with itself and will not have any liability for interest upon
any the monies.



         The trustee may resign at any time and be discharged from its duties
and obligations under the indenture by giving written notice to us and upon
appointment and acceptance of a successor. The trustee may be removed at any
time by the holders of not less than a majority in principal amount of then
outstanding bonds. We or any holder who has been a bona fide holder of a
security for at least six months may remove the trustee if (1) the trustee fails
to comply with the provisions of the indenture regarding conflicting interests,
(2) the trustee ceases to be eligible as required under the indenture and fails
to resign after written request, (3) the trustee becomes bankrupt or insolvent
or (4) the trustee fails to carry out its obligations in a timely manner.
Notwithstanding the preceding, no resignation or removal of the trustee and no
appointment of a successor trustee will become effective until the acceptance of
appointment by the successor trustee.



         Except during the continuance of an event of default under the
indenture, the trustee will perform only the duties as are specifically
described in the indenture. During the existence of an event of default, the
trustee will exercise the of the rights and powers vested in it by the
indenture, and use the same degree of care and skill in their exercise as a
prudent person would exercise or use under the circumstances in the conduct of
the person's own affairs.



         The indenture contains limitations on our rights to obtain payments of
claims in specific cases or to realize on specific property received by us in
respect of any claim as security or otherwise. The trustee is permitted to
engage in other transactions with us; however, if it acquires any "conflicting
interest", as defined in the indenture, it must eliminate the conflict or resign
as trustee under the indenture.




                                       89
<PAGE>

Supplemental Indentures

Supplemental Indentures and Amendments without the Consent of Bondholders

         Without the consent of the bondholders, we and the trustee, at any time
and from time to time, may enter into one or more supplemental indentures in
form reasonably satisfactory to the trustee and may amend any of the other
financing documents, for any of the following purposes:

         o        to establish the form and terms of bonds of any series
                  permitted by the indenture;


         o        to evidence the succession of another entity to us and the
                  assumption by any successor of our covenants under the bonds
                  and the indenture;


         o        to evidence the succession of a new trustee or a co-trustee or
                  separate trustee under the indenture;

         o        to add to the covenants of us, for the benefit of the
                  bondholders, or to surrender any right or power conferred upon
                  us under the indenture;

         o        to convey, transfer and assign to the trustee, and to subject
                  to the lien of the indenture, additional properties or assets
                  and to correct or amplify the description of any property at
                  any time subject to the lien of the indenture or to assure,
                  convey and confirm unto the trustee any property subject or
                  required to be subject to the lien of the indenture;

         o        to facilitate the issuance of bonds in uncertificated form;


         o        to change or eliminate any provision of the indenture;
                  however, if the change or elimination would adversely affect
                  the interests of the holders of any bonds of any series, the
                  change or elimination will become effective with respect to
                  the series only when no bond of the series remains
                  outstanding;



         o        to comply with changes in applicable law; however, no
                  amendment or supplement must result in a material adverse
                  effect or otherwise adversely affect the interests of the
                  holders of any bonds in any material respect;



         o        to make any changes required by Standard & Poor's or Moody's
                  or any other nationally recognized securities rating agency as
                  a condition to the issuance or maintenance of the then current
                  rating on the bonds or any series thereof so long as any
                  change does not result in a material adverse effect or
                  otherwise adversely affect the interests of the holders of any
                  bonds in any material respect; or



         o        to cure any ambiguity, to correct or supplement any provision
                  of the indenture that may be defective or inconsistent with
                  any other provision of the indenture, or to make any other
                  provisions with respect to matters or questions arising under
                  the indenture so long as the action does not adversely affect
                  the interest of the bondholders of any series in any material
                  respect.


Supplemental Indentures with the Consent of Bondholders


         With the consent of the bondholders of not less than a majority in
aggregate principal amount of outstanding bonds of all series, we and the
trustee may, and the trustee must, enter into one or more supplemental
indentures for the purpose of adding any provisions to or changing in any manner
or eliminating any of the provisions of, the indenture. No supplemental
indenture, however, may, without the consent of each bondholder directly
affected thereby: (1) change the stated maturity of any bond (or, if the
principal is payable in installments, the stated maturity of the installment),
or of any payment of interest, or the dates or circumstances of payment of any
premium on any bond, or change the principal amount or the interest or any
premium payable upon redemption, or change the place of payment where, or the
currency in which, any bond or any premium or the interest is payable, or impair
the right to institute suit for the enforcement of the payment of principal or
interest on or after the stated maturity (or, in the case of redemption, on or
after the redemption date) or the payment of premium, if any, on or after the
date the premium becomes due and payable; or (2) except for permitted liens,
permit the creation of any lien prior to or, equally with the lien of any of the
security documents with respect to any of the collateral, or terminate the lien
on any collateral or deprive any bondholder of the security afforded by the lien
of the indenture; or (3) reduce the percentage in principal amount of the bonds
then outstanding, the consent of whose bondholders is required for any
supplemental indenture, or the consent of whose bondholders is required for any
waiver provided for in the indenture, or reduce the requirements for quorum or
voting; or (4) modify specified provisions of the indenture relating to remedies
following an event of default, except to increase the percentage of the
principal amount of the bonds required to waive past defaults.




                                       90
<PAGE>

Satisfaction and Discharge

         We may terminate the indenture by delivering all bonds then outstanding
to the trustee for cancellation and by paying all sums payable under the
indenture and by effecting delivery of officer's certificates and an opinion of
counsel stating that all conditions precedent have been satisfied.


         In addition to the preceding, bonds then outstanding will, prior to the
stated maturity, be deemed to be paid, and our indebtedness will be deemed to be
satisfied and discharged, at any time all the conditions described below have
been satisfied:



         o We have irrevocably deposited with the trustee, in trust, monies or
permitted investments in an amount sufficient to pay when due, without
reinvestment, the principal of and any premium and interest due and to become
due on the bonds then outstanding on or prior to the stated maturity of the
final installments of principal or upon redemption or prepayment;



         o We have delivered to the trustee an order stating that monies
deposited with the trustee or in permitted investments must be held by the
trustee, in trust, as provided in the indenture;



         o in the case of redemption or prepayment of the bonds then
outstanding, the notice necessary for the validity of the redemption or
prepayment has been given, or irrevocable authority must have been given by us
to the trustee to give the notice; and



         o there has been delivered to the trustee an opinion of counsel to the
effect that as a result of a change in applicable law after the date of the
indenture the satisfaction and discharge of the indebtedness with respect to the
bonds then outstanding will not be deemed to be, or result in, a taxable event
with respect to holders of bonds then outstanding for purposes of United States
Federal income taxation unless the trustee has received documentary evidence
that the bondholders either are not subject to, or are exempt from, United
States Federal income taxation.


                           Collateral Agency Agreement

Project Accounts

         The following trust accounts will be established and created with and
in the name of the collateral agent: construction account; revenue account;
operating and maintenance account; debt service reserve account; debt service
reserve letter of credit reimbursement fund; construction period letter of
credit reimbursement fund; restoration account; major maintenance reserve
account; fuel conversion volume rebate account; subordinated debt account; and
distribution account.

Collection of Project Revenues


         We must arrange for the direct payment to the collateral agent of all
project revenues, and to the extent any the project revenues are at any time
received by us prior to the commercial operation date, we must hold all revenues
and other amounts in trust for the collateral agent and must transfer to the
collateral agent for deposit of the project revenues in the construction account
in each case as soon as reasonably practical but no later than three business
days after receipt, duly endorsed, if necessary, to the collateral agent.


Advances


         Notwithstanding any other provision of the collateral agency agreement
to the contrary, we may withdraw funds on deposit in or credited to any of the
project accounts other than the construction account and the debt service
reserve account (the a withdrawal, an "advance"). At the time of the making of
the advance, however, no default or event of default has occurred and be
continuing and our obligations to repay the advances must be supported by
acceptable credit support. We must repay immediately or cause to be repaid any
advances to the extent that the funds on deposit in the project accounts other
than the construction account and the debt service reserve account are
insufficient to make the necessary withdrawals and transfers. In addition, we
must cause to be repaid immediately the aggregate amount of all advances upon
the occurrence of:



         o a default in the payment of principal of, any premium, or interest on
the bonds or under the debt service reserve letter of credit and reimbursement
agreement, the construction period letter of credit and reimbursement agreement
or any working capital facility,


         o any event of default,



                                       91
<PAGE>

         o any default by an acceptable credit provider in respect of its
obligations under its acceptable credit support or


         o our failure to provide, within five business days, acceptable credit
support in respect of its obligations to repay advances upon the failure of the
acceptable credit provider to meet the requirements of the definition thereof.
Any amounts so repaid must be allocated to and deposited in the project accounts
other than the construction account and the debt service reserve account to
which the repayment is required to be made as directed by us in an officer's
certificate.


Construction Account

         On the date of original issuance of the old bonds, the net proceeds of
the sale of the old bonds received by us were transferred to the collateral
agent for deposit in the construction account.


         On that date, the collateral agent applied the amounts in the
construction account to the payment, or reimbursement, to the extent the same
had been paid or satisfied by us, of project costs. Each requisition after that
date must be submitted to the collateral agent no less than three business days
in advance of the drawing date and must include the following:



         (1) a certification that the proceeds will be used solely to pay
project costs in accordance with the indenture;


         (2) a certification that work performed to date has been satisfactorily
performed in a good and workmanlike manner and according to the construction
agreement;


         (3) a statement that undisbursed funds in the construction account,
together with funds available under the equity subscription agreement and other
available sources of funds, are reasonably expected to be sufficient to complete
our facility by December 31, 2002;


         (4) a statement that no default or event of default under the
indenture, the debt service reserve letter of credit and reimbursement
agreement, the construction period letter of credit and reimbursement agreement
or any working capital facility has occurred and is continuing;

         (5) a statement that all proceeds of prior requisitions have been
expended or applied under the provisions of the financing documents and that the
items for which amounts are requested in the subject requisition have not been
the basis for a previous requisition;

         (6) a certification that required insurance, material governmental
approvals and necessary project contracts are in full force and effect; and


         (7) a certification that specified representations described in the
indenture are true and correct in all material respects.



         If we cannot satisfy the requirements of clauses (1) or (5) of the
preceding paragraph, the collateral agent can not release funds from the
construction account in respect of the requisition until the clauses are
satisfied. If we cannot satisfy clauses (2), (3), (4), (6) or (7) of the
preceding paragraph, but the collateral agent receives a requisition signed by
us, the contents of which must be confirmed by the independent engineer:



         o specifying and identifying the failure, and the causes for the
failure, to satisfy the requirements of the clauses (2), (3), (4), (6) or (7) of
the preceding paragraph and



         o certifying that (i) the requirements of clauses (1) and (5) of the
preceding paragraph are satisfied, (ii) there exists no bankruptcy event in
respect of us or AES Ironwood, Inc. and (iii) each of the construction
agreement, the power purchase agreement, required insurance policies and
material governmental approvals needed for construction of our facility is in
full force and effect, then the collateral agent must disburse funds in
accordance with the requisition.



         Within 15 days of receipt of the requisition, the collateral agent must
give notice to the senior creditors describing the failure and specifying that,
unless the required senior creditors give notice to the collateral agent of
their objection to payment of further requisitions containing any the specified
failures, the collateral agent will continue to make payment of the requisitions
from available funds in the construction account, unless the collateral agent
has received, by the second business day prior to the time of payment of the
requisition, notice of objection from the required senior creditors.




                                       92
<PAGE>


      Notwithstanding the preceding, the collateral agent will not release funds
from the construction account in respect of a requisition if a Trigger Event has
occurred and be continuing until the collateral agent determines that the
Trigger Event is no longer continuing or the required senior creditors give
instructions to the collateral agent as to application of funds.


Payments on Commercial Operation Date


         Not later than 10 days after receipt by the collateral agent of a
certificate from us, the contents of which must be confirmed in writing by the
independent engineer, certifying, among other things, that (1) all conditions to
the commencement of commercial operation under the power purchase agreement have
been satisfied, (2) the construction period letter of credit has been terminated
or drawn, (3) all permits then required have been obtained and (4) no default is
continuing, the collateral agent must, after retaining in the construction
account the amount, if any, specified by us as necessary to pay project costs
which are not then due and payable, transfer all remaining funds in the
construction account, plus any amounts available under and under the equity
subscription agreement to the extent necessary to fund first through fifth
below, by wire transfer to the following accounts and recipients in the
following order of priority:


         first, to the operating and maintenance account, an amount to the
extent available, as specified by us but in any event, no less than one-month's
non-fuel operating and maintenance costs;

         second, to the bond payment account, an amount, to the extent
available, as specified by us for funding of the interest payment subaccount and
principal payment subaccount;

         third, to the debt service reserve account, an amount as specified by
us equal to the debt service reserve account required balance to the extent not
already funded or provided through a debt service reserve letter of credit;

         fourth, if applicable, to the construction period letter of credit
provider, an amount equal to the principal of and interest on any construction
period letter of credit loans outstanding on the commercial operation date;

         fifth, to the major maintenance reserve account, an amount as specified
by us equal to any initial deposit required therein; and

         sixth, to the revenue account, any remaining amounts.

Payments During Operating Period


         After the transfer specified in the above paragraphs regarding payments
on the commercial operation date and upon receipt by the collateral agent of,
not less than three business days prior to the date of the proposed transfer, an
officer's certificate detailing the amounts to be paid, the collateral agent
must transfer all remaining funds in the revenue account by wire transfer in the
following order of priority:


         first, as and when required, (1) to any working capital provider, an
amount certified by us as the amount, if any, then payable under any working
capital facility; and (2) as and when requested, to the operating and
maintenance account, the amount certified by us as necessary for payment of
operating and maintenance costs;


         second, on a monthly basis, (1) to the trustee and the collateral
agent, any amounts certified by us as the amounts then due and payable in
respect of trustee claims and collateral agent claims, respectively; (2) to any
debt service reserve letter of credit provider, any amounts certified by us as
the amounts then due and payable in respect of debt service reserve letter of
credit provider claims; and (3) to any construction period letter of credit
provider, any amounts certified by us as the amounts then due and payable in
respect of construction period letter of credit provider claims; however, if
funds in the revenue account are insufficient on any date to make the payments
specified in this paragraph second, distribution of funds must be made ratably
to the specified recipients;



         third, on a monthly basis, (1) to the trustee, for deposit in the
interest payment subaccount, an amount equal to one-third of the interest
becoming due on the bonds on the next succeeding bond payment date; (2) to the
debt service reserve letter of credit reimbursement fund, (a) an amount equal to
one-third of the interest becoming due on any debt service reserve letter of
credit loan on the next succeeding bond payment date, plus one-third of any fees
becoming due under the debt service reserve letter of credit and reimbursement
agreement on the next succeeding bond payment date, (b) an amount equal to
one-third of the interest becoming due on any debt service reserve bond on the
next succeeding bond payment date and (c) an amount equal to one-third of the
interest becoming due on any debt service reserve letter of credit term loan on
the next succeeding bond payment date; and (3) to the construction period letter
of credit reimbursement fund, an amount equal to one-third of the interest
becoming due on any construction period letter of credit loan on the next
succeeding bond payment date, plus one-third of any fees becoming due under the
construction period


                                       93
<PAGE>

letter of credit and reimbursement agreement on the next succeeding bond payment
date; however, if funds in the revenue account are insufficient on any date to
make the payments specified in this paragraph third, distribution of funds must
be made ratably to the specified recipients;



         fourth, on a monthly basis, (1) to the trustee, for deposit in the
principal payment subaccount, an amount equal to one-third of the principal
becoming due on the bonds on the next succeeding bond payment date; (2) to the
debt service reserve letter of credit reimbursement fund, (a) an amount equal to
one-third of the principal becoming due on any debt service reserve bond on the
next succeeding bond payment date, and (b) an amount equal to one-third of the
principal becoming due on any debt service reserve letter of credit term loan on
the next bond payment date; and (3) to the construction period letter of credit
reimbursement fund, an amount equal to one-third of the principal becoming due
on any construction period letter of credit loan on the next succeeding bond
payment date; however, if funds in the revenue account are insufficient on any
date to make the payments specified in this paragraph fourth, distribution of
funds must be made ratably to the specified recipients;



         fifth, on a monthly basis, (1) to the debt service reserve letter of
credit provider, an amount equal to the outstanding principal amount of any debt
service reserve letter of credit loans that have not been converted to debt
service reserve term loans or debt service reserve bonds, and (2) to the
collateral agent for deposit in the debt service reserve account, an amount
necessary to fund the debt service reserve account up to the debt service
reserve account required balance, taking into account any amounts remaining
available to be drawn under the debt service reserve letter of credit; however,
if amounts available for drawing under the debt service reserve letter of credit
are not being reinstated to the full extent of payments made to the debt service
reserve letter of credit provider and funds in the revenue account are
insufficient on any date to make the payments specified in this paragraph fifth,
distribution of funds must be made ratably to the specified recipients;



         sixth, on a monthly basis, to the major maintenance reserve account,
amounts necessary to cause the balance to be equal to the minimum balance
required at that time under the annual budget;


         seventh, on a monthly basis, to us for payment to Williams Energy, the
amount, if any, certified by us as required to make any non-dispatch payments,
as defined in the power purchase agreement, to Williams Energy under the power
purchase agreement;

         eighth, on a monthly basis, to the fuel conversion volume rebate
account, an amount equal to one-twelfth of the amount specified by us that would
be owed to Williams Energy at the end of the then current fiscal year under the
power purchase agreement;


         ninth, on a monthly basis, if any subordinated debt is outstanding, to
the subordinated debt account, (x) an amount equal to one-third or one-sixth,
depending on the interest payment schedule of the subordinated debt, of the
interest becoming due on the subordinated debt on the next succeeding interest
payment date for the subordinated debt, plus (y) one-third or one-sixth,
depending on the amortization schedule of the subordinated debt, of the
principal becoming due on the subordinated debt on the next applicable principal
payment date;


         tenth, on a monthly basis, to Siemens Westinghouse, an amount equal to
any subordinated bonuses payable to Siemens Westinghouse under the construction
agreement; and


         eleventh, on a monthly basis, to the distribution account, any
remaining amounts for payment of distributions to holders of ownership
interests, including any payment in respect of principal or interest then due on
affiliate subordinated debt so long as the distribution conditions described in
the collateral agency agreement are satisfied.



         When making the transfers specified above, each transfer will be
adjusted as necessary, taking into account investment gains or losses in the
project account or indenture account and further adjusting the transfers by the
amount of any prior over-fundings or any prior shortfalls in the project account
or indenture account, to ensure that the aggregate amounts so transferred to the
project accounts or indenture accounts are sufficient to pay the amount due and
payable from the project accounts and indenture accounts on the applicable
payment date.


Debt Service Reserve Account


         The collateral agent must hold the debt service reserve letter of
credit as security agent for the trustee and the debt service reserve letter of
credit provider to the extent of its interest therein. Upon the occurrence of
the commercial operation date, the debt service reserve account must be funded,
if necessary, from monies available in the construction account for the relevant
purpose in an amount up to the debt service reserve account required balance.
Subsequent to the commercial operation date, the debt service reserve account
must be funded, if necessary, from monies transferred from


                                       94
<PAGE>

the revenue account. When determining (1) the amount, if any, required to be
deposited into the debt service reserve account from time to time or (2) whether
the debt service reserve account has deposited therein the debt service reserve
account required balance, amounts on deposit in the debt service reserve account
must be aggregated with the amount available to be drawn under the debt service
reserve letter of credit.



         When there are insufficient monies in the bond payment account on any
bond payment date to pay the interest or principal then due on the bonds, the
collateral agent must, in the following order of priority: first, withdraw
monies on deposit in the debt service reserve account; and second, draw on the
debt service reserve letter of credit in accordance with the terms and
provisions up to the amount available for the purpose thereunder, in each case,
to the extent necessary to make the interest or principal payment on the bonds
and transfer the monies to the trustee for deposit in the bond payment account
for application against the payment.



         If the collateral agent receives a written notice from us stating that
there has been a reduction in the long-term debt rating of the debt service
reserve letter of credit provider below the required rating, or if a responsible
officer of the collateral agent otherwise becomes aware of the reduction, and
the debt service reserve letter of credit has not been replaced within the time
period specified therefor, the collateral agent must draw on the debt service
reserve letter of credit in the amount necessary to fund the debt service
reserve account up to the debt service reserve account required balance.



         If the collateral agent receives a notice from the debt service reserve
letter of credit provider stating that the debt service reserve letter of credit
provider must terminate the debt service reserve letter of credit on the date
specified in the notice, the collateral agent must, within three business days
of receipt of the notice, draw on the debt service reserve letter of credit in
an amount equal to the amount necessary to fund the debt service reserve account
up to the debt service reserve account required balance and the debt service
reserve letter of credit must automatically terminate.



         If a Trigger Event has occurred and is continuing and the collateral
agent has received the written request of the required senior creditors
contained in senior creditor certificates and the notice has not been rescinded,
then the collateral agent, upon receipt of an officer's certificate of setting
forth the debt service reserve account required balance, must draw on the debt
service reserve letter of credit in an amount equal to the amount necessary to
fund the debt service reserve account up to the debt service reserve account
required balance, and the debt service reserve letter of credit will
automatically terminate.



         If, subsequent to the commercial operation date, monies transferred to
the debt service reserve letter of credit provider under clause third under
"--Payments During Operating Period" above are insufficient to repay the
interest on any debt service reserve letter of credit loans due or becoming due
on the first day of the month, the collateral agent, upon receipt of a
certificate of an authorized officer of the debt service reserve letter of
credit provider notifying the collateral agent of the existence, and setting
forth the amount, of the shortfall, within two business days of receipt of the
certificate must draw on the debt service reserve letter of credit in an amount
equal to the amount of the shortfall and transfer the amount to the debt service
reserve letter of credit provider in payment, in whole or part, of the interest
on the debt service reserve letter of credit loans. Notwithstanding the
preceding, in no event must any draw on the debt service reserve letter of
credit described in this paragraph individually or in the aggregate with all
other the draws, less any draws previously reimbursed, exceed six months of
interest on the maximum stated amount of the debt service reserve letter of
credit.



         Unless the debt service reserve letter of credit is not extended or
replaced or unless there has been an event of default under the debt service
reserve letter of credit as described under "SUMMARY OF PRINCIPAL FINANCING
DOCUMENTS--Debt Service Reserve Letter of Credit and Reimbursement Agreement,"
amounts available for drawing under the debt service reserve letter of credit
must be reinstated immediately to the extent of any reimbursement of principal
of debt service reserve letter of credit loans, but not debt service reserve
bonds or debt service reserve letter of credit term loans.



         If we and the debt service reserve letter of credit provider agree to
issue or reinstate the debt service reserve letter of credit in an amount that,
when aggregated with cash on deposit in the debt service reserve account would
exceed the debt service reserve account required balance, the collateral agent
must, within two business days of receipt by the collateral agent of (1) the
reissued or reinstated debt service reserve letter of credit, and (2) an
officer's certificate of, transfer an amount equal to the excess amount to the
revenue account for application in accordance with the applicable provisions of
the collateral agency agreement so long as the amount of the debt service
reserve letter of credit may not exceed the debt service reserve account
required balance.




                                       95
<PAGE>

Distribution Account


         The distribution account must be funded from funds transferred from the
revenue accounts in accordance with the collateral agency agreement. On any date
on which the conditions described below are satisfied, funds on deposit in or
credited to the distribution account may be distributed to, or as directed by,
us for the payment of affiliate subordinated debt, the making of distributions
to the holders of ownership interests in our company or any other lawful
purpose, upon receipt by the collateral agent of an officer's certificate of
requesting a distribution and certifying that:



         (1) all of our project accounts and the bond payment account must be
funded to their required levels;



         (2) no (a) default or event of default under the indenture, (b) default
or event of default under the debt service reserve letter of credit and
reimbursement agreement, (c) default or event of default under any construction
period letter of credit and reimbursement agreement or (d) default under any
working capital arrangements, if any, has occurred and is continuing;


         (3) the commercial operation date has occurred and at least one
complete fiscal quarter thereafter has elapsed;


         (4) if the requested distribution is to be made during the power
purchase agreement term, (a) the senior debt service coverage ratio for the
preceding four fiscal quarters, (or with respect to any date prior to the first
anniversary of the commercial operation date, for the number of complete fiscal
quarters since the commercial operation date), measured as one period, is
greater than or equal to 1.2 to 1 and (b) based on projections prepared by us on
a reasonable basis, the projected senior debt service coverage ratio for the
succeeding four fiscal quarters (including the quarter in which the distribution
is to be made) (or, with respect to any date within the 12-month period prior to
the end of the power purchase agreement term, the number of complete fiscal
quarters, if any, until the end of the power purchase agreement term) is
projected to be greater than or equal to 1.2 to 1; and



         (5) if the requested distribution is to be made on or after the date
which is six months prior to the end of the power purchase agreement term, (a)
the senior debt service coverage ratio for the preceding four fiscal quarters
(or, with respect to any date within the first 12 months of the post-power
purchase agreement period, the number of complete fiscal quarters, if any, since
the start of the post-power purchase agreement period) measured as one period,
is greater than or equal to 1.70 to 1.0 (or 1.2 to 1.0 with respect to the
period occurring prior to the end of the power purchase agreement term) and (b)
based on projections prepared by us on a reasonable basis, the projected senior
debt service coverage ratio for the succeeding eight fiscal quarters (including
the fiscal quarter in which the distribution is to be made) or, with respect to
any date within the 24-month period prior to the final maturity date for the
bonds, the number of complete fiscal quarters, if any, until the final maturity
date for the bonds, in each case measured as one period, is projected to be
greater than or equal to 1.70 to 1 (or 1.2 to 1 with respect to the period
occurring prior to the end of the power purchase agreement term), each as
certified by an authorized officer; however,



         o        if distributions are blocked because we fail to satisfy the
                  conditions of clause (5)(b) above, then in lieu of the
                  coverage ratio test described in the clause, the projected
                  senior debt service coverage ratio through the final maturity
                  date for the bonds, measured as one period, must be 1.70 to 1
                  in order to satisfy clause (5)(b) in respect of amounts then
                  on deposit in the distribution account;



         o        for purposes of calculating the projected senior debt service
                  coverage ratios in clauses (5)(b) above, we must use (A) for
                  electricity prices, either (x) the electricity prices
                  forecasted in the most recent independent forecast furnished
                  to the trustee, in each case, during the relevant period of
                  calculation, or (y) if and to the extent that electricity
                  sales during the relevant period of calculation are made under
                  one or more power sales agreements at prices other than prices
                  which are by their terms market prices, the electricity prices
                  under the power sales agreements and (B) for gas prices,
                  either (x) the gas prices forecasted in the most recent
                  independent forecast furnished to the trustee, in each case,
                  during the relevant period of calculation, or (y) if and to
                  the extent that gas purchases during the relevant period of
                  calculation are made under one or more gas purchase agreements
                  at prices other than prices which are by their terms market
                  prices, the gas prices under the gas purchase agreements;



         o        if, and to the extent that, (A) at least 75% of our facility's
                  net capacity is subject to one or more power sales agreements
                  on terms, other than pricing, substantially similar to the
                  power purchase agreement, but excluding the provision for gas
                  to be supplied for fuel conversion services by Williams
                  Energy, or on commercially reasonable terms (other than
                  pricing) typical of power sales agreements entered into at the
                  time for the same term, in each case with a term of not less
                  than one year during the relevant period


                                       96
<PAGE>

                  of calculation, and (B) at least 75% of the gas supply for our
                  facility is subject to one or more gas supply agreements on
                  commercially reasonable terms (other than pricing) typical of
                  gas supply agreements entered into at the time for the same
                  term, in each case with a term of not less than one year
                  during the relevant period of calculation (compliance with the
                  requirements to be certified by us), then clause (5) above
                  will be deemed satisfied, if the senior debt service coverage
                  ratio and the projected senior debt service coverage ratio
                  referred to in the clause (5) are each equal to or greater
                  than 1.30 to 1 for the portions of the time periods referred
                  to in the clause (5) in which the agreements were or are to be
                  in effect, as certified by us; and


         o        if amounts on deposit in or credited to the revenue account
                  are insufficient to make the transfers described in priorities
                  first through sixth above under "Payments During Operating
                  Period," amounts on deposit in or credited to the distribution
                  account will be transferred to the revenue account to the
                  extent necessary and applied in accordance with the collateral
                  agency agreement.

Restoration Account


         All casualty proceeds and eminent domain proceeds must be deposited
into the restoration account. Subject to the provisions described below, the
collateral agent must apply the amounts in the restoration account to the
payment, or reimbursement to the extent the same have been paid or satisfied by
us, of the costs of rebuilding, repair and restoration of our facility or any
part that has been affected by an event of loss or an event of eminent domain.



         The collateral agent is authorized to disburse from the restoration
account the amount required to be paid for the repair or replacement of our
facility or any part as specified in the preceding paragraph. The collateral
agent is authorized and directed to issue its checks or transfer funds
electronically for each disbursement from the restoration account, upon receipt
of a restoration certificate signed by our authorized representative, and
approved by the independent engineer. No approval of the independent engineer,
however, will be required if less than $5,000,000 is requested under the
requisition or requisitions in any one fiscal year. The collateral agent will be
entitled to rely on all certifications and statements in the restoration
certificate. The collateral agent must keep and maintain adequate records
pertaining to the restoration account and all disbursements therefrom and must
file an accounting with us and the independent engineer within three months
following the last business day of each fiscal year.



         If an event of loss or an event of eminent domain occurs with respect
to any collateral, we must (1) diligently pursue all our rights to compensation
against any person with respect to the event of loss or event of eminent domain,
(2) in our reasonable judgment compromise or settle any claim against any person
with respect to the event of loss or event of eminent domain and (3) hold all
amounts of casualty proceeds or eminent domain proceeds, including instruments,
received in respect of any event of loss or event of eminent domain, after
deducting all reasonable expenses incurred by it in litigating, arbitrating,
compromising or settling any claims, in trust for the benefit of the collateral
agent segregated from other funds of ours and will promptly transfer to the
collateral agent for deposit in the restoration account the casualty proceeds or
eminent domain proceeds.



         If either an event of loss or an event of eminent domain occurs, as
soon as reasonably practicable but no later than the date of receipt by us or
the collateral agent of eminent domain proceeds or casualty proceeds, as the
case may be, we must make a reasonable good faith determination as to whether
(1) our facility or any portion can be rebuilt, repaired or restored to permit
operation of our facility or a portion on a commercially feasible basis and (2)
the casualty proceeds or the eminent domain proceeds, as the case may be,
together with any other amounts that are available to us for the rebuilding,
repair or restoration, are sufficient to permit the rebuilding, repair or
restoration of our facility or a portion thereof, including the making of all
required payments of interest and principal on our indebtedness during the
rebuilding, repair or restoration. Our determination must be evidenced by a
certificate as to redemption filed with the collateral agent which, if we
determines that our facility or a portion can be rebuilt, repaired or restored
to permit operation on a commercially feasible basis and that the casualty
proceeds or the eminent domain proceeds, as the case may be, together with any
other amounts that are available to us for the rebuilding, repair or
restoration, are sufficient, must also describe a reasonable good faith estimate
by us of the total cost of the rebuilding, repair or restoration. We must
deliver to the collateral agent at the time we deliver the certificate as to
redemption, a certificate of the independent engineer, dated the date of the
certificate as to redemption, stating that, based upon reasonable investigation
and review of the determination made by us, the independent engineer believes
the determination and the estimate of the total cost described in the
certificate as to redemption to be reasonable.



         If, following an event of loss or event of eminent domain, the
determination is made that our facility cannot be rebuilt, repaired or restored
to permit operation on a commercially feasible basis or that the casualty
proceeds or the


                                       97
<PAGE>

eminent domain proceeds, together with any other amounts that are available to
us for the rebuilding, repair or restoration, are not sufficient to permit the
rebuilding, repair or restoration, all of the casualty proceeds or the eminent
domain proceeds, as the case may be, must be distributed as provided below.



         If, following an event of loss or event of eminent domain, the
determination is made that the entire facility can be rebuilt, repaired or
restored to permit operation on a commercially feasible basis and that the
casualty proceeds or the eminent domain proceeds, together with any other
amounts that are available to us for the rebuilding, repair or restoration, are
sufficient to permit the rebuilding, repair or restoration, all of the casualty
proceeds or the eminent domain proceeds, as the case may be, together with the
other amounts as are available to us for the rebuilding, repair or restoration,
must be deposited in the restoration account and applied as provided below.



         If, following an event of loss or event of eminent domain, the
determination is made that a portion of our facility can be rebuilt, repaired or
restored to permit operation on a commercially feasible basis and that the
casualty proceeds or the eminent domain proceeds, together with any other
amounts that are available to us for the rebuilding, repair or restoration, are
sufficient to permit the rebuilding, repair or restoration, (1) an amount equal
to the estimate of the total cost of the rebuilding, repair or restoration
described in the certificate as to redemption filed with the collateral agent
must be deposited in the restoration account and applied as provided below, and
(2) the amount, if any, by which all of the casualty proceeds or the eminent
domain proceeds, as the case may be, exceed the estimate of the total cost must
be distributed as provided below.



         If we receive casualty proceeds or eminent domain proceeds, as the case
may be, from an event of loss or an event of eminent domain that do not exceed
in the aggregate $5,000,000 during any fiscal year, we will not have to make the
good faith determination referred to above and the casualty proceeds or the
eminent domain proceeds, as the case may be, must be deposited in the
restoration account and applied for the rebuilding, repair or restoration of our
facility without any approval of the independent engineer.


Application of Casualty and Eminent Domain Proceeds and Buy-Down Amounts


         If the determination is made that all or a portion of our facility is
incapable of being rebuilt, repaired or restored to permit operation on a
commercially feasible basis, all casualty proceeds or eminent domain proceeds
received by the collateral agent and not deposited in the restoration account
must be distributed by the collateral agent within five business days of receipt
in the following order of priorities:



         first, to the collateral agent, the debt service reserve letter of
credit provider, the construction period letter of credit provider and the
trustee, ratably, in an amount equal to the amounts owed in respect of the
collateral agent claims, the trustee claims, the debt service reserve letter of
credit provider claims and the construction period letter of credit provider
claims, respectively, due and payable as of the date of the distribution;


         second, to the senior creditors, ratably, an amount equal to the unpaid
amount of all financing liabilities owed to the senior creditors, including the
amount required to be applied to a mandatory redemption of the bonds under the
indenture;


         third, to the subordinated debt providers, ratably, an amount equal to
the unpaid amount owed to the subordinated debt providers by us under any
subordinated loan agreement; and



         fourth, to us or our successors or assigns or to whomever may be
lawfully entitled to receive the same or as a court of competent jurisdiction
may direct, any surplus then remaining from the proceeds.



         At the time the collateral agent is to make a distribution under clause
second in the immediately preceding paragraph, the collateral agent must
deposit, with the same priority as that distribution, ratably into two separate
trust account to be maintained by the collateral agent as follows:


         o in the first account, an amount up to the amount equal to the maximum
amount available to be drawn under the debt service reserve letter of credit,
and not represented by a debt service reserve letter of credit loan, debt
service reserve letter of credit term loan or debt service reserve bond, and


         o in the second account, an amount up to the amount available to be
drawn under any construction period letter of credit, and not represented by a
construction period letter of credit loan; however, if funds available are
insufficient to make all payments required under clause second of the preceding
paragraph and the required deposits provided for in this sentence, distribution
of funds must be made ratably to the specified recipients. The collateral agent
must hold the funds in the separate accounts until receipt of a written notice
or notices from the debt service reserve letter


                                       98
<PAGE>

of credit provider and/or the construction period letter of credit provider, as
the case may be, to the effect that either (1) a drawing has been made on its
letter of credit or (2) its letter of credit has expired or terminated without a
drawing being made thereunder. Upon receipt of a notice or notices specified in
clause (1) of the preceding sentence, the collateral agent must distribute to
the debt service reserve letter of credit provider and/or the construction
period letter of credit provider, as the case may be, that proportionate share
of the amount in the relevant separate account referred to above, equal to the
drawing's proportionate share of the letter of credit collateralized by the
account. Upon receipt of a notice or notices specified in clause (2) of the
second preceding sentence, the collateral agent must distribute from the
relevant separate account, in accordance with clauses second, third and fourth
above and without regard to this paragraph, to the appropriate persons an amount
equal to the amount in the separate account.



         All amounts received by us from Siemens Westinghouse as performance
liquidated damages under the construction agreement must be deposited into a
separate account maintained by the depositary bank on behalf of the collateral
agent. If the requisite officer's certificate is delivered, the collateral agent
is authorized to disburse from the separate account the amount required to be
paid for the modification, repair or replacement of that portion of our facility
that requires modification, repair or replacement in order to remedy the
circumstances giving rise to the obligation of Siemens Westinghouse under the
construction agreement to pay the amounts received by us from Siemens
Westinghouse as performance liquidated damages under the construction agreement.



         As soon as reasonably practicable following our receipt or the
collateral agent's receipt of amounts received by us from Siemens Westinghouse
as performance liquidated damages under the construction agreement, we will make
a reasonable good faith determination as to whether:



         o it is technically feasible to modify, repair or replace that portion
of our facility that requires modification, repair or replacement in order to
remedy the circumstances giving rise to the obligation of Siemens Westinghouse
under the construction agreement to pay the amounts received by us from Siemens
Westinghouse as performance liquidated damages under the construction agreement,



         o the amounts received by us from Siemens Westinghouse as performance
liquidated damages under the construction agreement, together with any other
amounts that are available to us for the modification, repair or replacement,
are sufficient to permit the modification, repair or replacement, including the
making of all required payments of interest and principal on our indebtedness
during the modification, repair or replacement,



         o the projected average senior debt service coverage ratio, after
giving effect to the modification, repair or replacement and the application of
the amounts received by us from Siemens Westinghouse as performance liquidated
damages under the construction agreement to accomplish the same, during the
power purchase agreement term (taken as one period) and the post-power purchase
agreement period (taken as one period) is equal to or greater than the projected
average senior debt service coverage ratio described in the base case
projections for each the period described in this prospectus and



         o the projected minimum senior debt service coverage ratio, after
giving effect to the modification, repair or replacement and the application of
the amounts received by us from Siemens Westinghouse as performance liquidated
damages under the construction agreement to accomplish the same, during the
power purchase agreement term and the post-power purchase agreement period is
equal to or greater than the projected minimum senior debt service coverage
ratio for each the period described in the base case projections described in
this prospectus.



         Upon receipt of an officer's certificate, confirmed by the independent
engineer, certifying that all modifications, repairs or replacements of that
portion of our facility that requires modification, repair or replacement in
order to remedy the circumstances giving rise to the obligation of Siemens
Westinghouse under the construction agreement to pay amounts received by us from
Siemens Westinghouse as performance liquidated damages under the construction
agreement have been completed, the collateral agent must transfer all funds
remaining in the separate account first, to the accounts as are specified in the
collateral agency agreement and second, to us or to whomsoever we direct.



         If we cannot provide the officer's certificate to permit the
application of amounts received by us from Siemens Westinghouse as performance
liquidated damages under the construction agreement toward the modification,
repair or replacement of that portion of our facility or the independent
engineer fails to confirm the officer's certificate, the collateral agent must
distribute all amounts received by us from Siemens Westinghouse as performance
liquidated damages under the construction agreement ratably, based on the amount
owing to the specified recipient, to (1) the trustee in respect of the amount of
the bonds then outstanding for redemption of bonds in accordance with the
indenture, (2) the debt service reserve letter of credit provider in respect of
the outstanding amount of debt service reserve loans and


                                       99
<PAGE>

(3) the construction period letter of credit provider in respect of the
outstanding amount of any construction period letter of credit loan.



         At the time the collateral agent is to make a distribution under the
immediately preceding paragraph, the collateral agent must deposit into two
separate trust accounts to be maintained by the collateral agent as follows:


         o in the first account, an amount up to the amount available to be
drawn under the debt service reserve letter of credit, and not represented by a
debt service reserve letter of credit loan, a debt service reserve term loan or
debt service reserve bond, and


         o in the second account an amount up to the amount available to be
drawn under any construction period letter of credit, and not represented by a
construction period letter of credit loan; however, if funds available are
insufficient to make all payments required under clause second of the first
paragraph of this section and the required deposits provided for in this
sentence, distribution of funds must be made ratably to the specified
recipients. The collateral agent must hold the funds in the separate account
until receipt of a written notice or notices from the debt service reserve
letter of credit provider and/or the construction period letter of credit
provider, as the case may be to the effect that either (1) a drawing has been
made on the letter of credit or (2) the letter of credit has expired or
terminated without a drawing being made thereunder. Upon receipt of a notice or
notices specified in clause (1) in the preceding sentence, the collateral agent
must distribute to the debt service reserve letter of credit provider and/or
construction period letter of credit provider, as the case may be, that
proportionate share of the amount in the relevant separate account referred to
above, equal to the drawing's proportionate share of the letter of credit
collateralized by the account. Upon receipt of a notice or notices specified in
clause (2) in the second preceding sentence, the collateral agent must
distribute from the relevant separate account to the appropriate persons an
amount equal to the amount in the separate account.


Exercise of Rights Under Security Documents

         The collateral agency agreement provides, among other things, that:


         o if a Trigger Event has occurred and is continuing, and only in that
event, upon the written request of the required senior creditors contained in
senior creditor certificates, the collateral agent, on behalf of the trustee,
the debt service reserve letter of credit provider, the construction period
letter of credit provider and any other senior creditor that is a party to the
collateral agency agreement, will be permitted to take any and all actions and
to exercise any and all rights, remedies and options which it may have under the
security documents or the collateral agency agreement; however, if the
underlying event which caused the Trigger Event is a bankruptcy event in respect
of us of which the collateral agent has received written notice, no written
request of the required senior creditors will be required in order to permit the
collateral agent following the Trigger Event to take any and all actions and to
exercise any and all rights, remedies and options which it may have under the
security documents or the collateral agency agreement;


         o the senior creditors will give each other and the collateral agent
written notice of the occurrence of an event of default and of a Trigger Event
as soon as practicable after the occurrence;

         o the senior creditors acknowledge and agree that all funds held by the
trustee in the indenture accounts are held for the benefit of the bondholders;

         o the senior creditors acknowledge and agree that all funds held in the
debt service reserve account by the collateral agent is held for the benefit of
the trustee on behalf of the bondholders;


         o no senior creditor and no class or classes of senior creditors will
have any right (1) to direct the collateral agent to take any action in respect
of the collateral other than in accordance with the collateral agency agreement
or (2) to take any action with respect to the collateral either independently of
the collateral agent or other than to direct the collateral agent in writing to
take action in accordance with the collateral agency agreement; and



         o the senior creditors acknowledge and agree that if (1) there is an
event of default under the indenture and the event of default is not caused
directly or indirectly by a default or event of default under the power purchase
agreement and (2) they direct the collateral agent to accelerate the bonds, the
collateral agent will be obligated to provide Williams Energy the opportunity
for 90 days to purchase our facility for an amount equal to the greater of (x)
the fair market value of our facility and (y) all financing liabilities due and
owing to the senior creditors and any subordinated debt provider, and if
Williams Energy offers to purchase our facility for the amount within the
period, the collateral agent must take the actions as required to consummate the
sale as directed by the required senior creditors in senior creditor
certificates.




                                      100
<PAGE>


         In giving directions and otherwise exercising rights under the security
documents and the collateral agency agreement, the trustee must vote, or
otherwise represent, that portion of the combined credit exposure represented by
all bonds then outstanding according to the votes of a majority of the principal
amount of bonds held by responding bondholders. The trustee must not make
requests, give directions or vote on a proportional basis.


Application of Foreclosure Proceeds


         Following the receipt of proceeds under the guaranty provided by The
Williams Companies, Inc. as a result of a termination of the power purchase
agreement or a foreclosure or other exercise of remedies following a Trigger
Event, the proceeds of any sale, disposition or other realization by the
collateral agent or by a senior creditor upon the collateral under the security
documents must be distributed in the following order of priorities:



         first, to the collateral agent, the trustee, the debt service reserve
letter of credit provider and the construction period letter of credit provider,
ratably, all administrative fees, costs and expenses owed to the parties under
the financing documents;



         second, to the senior creditors, ratably, based on the amount owing to
the specified recipients, an amount equal to the unpaid amount of all financing
liabilities owed to or required to be deposited for the account of the senior
creditors by us;



         third, to any subordinated debt providers, ratably, an amount equal to
the unpaid obligations owed to or required to be deposited for the account of
the subordinated debt providers by us under any subordinated loan agreement; and


         fourth, to us or to whomever may be lawfully entitled to receive the
same or as a court of competent jurisdiction may direct, any surplus remaining
after giving effect to clauses first, second and third above.

Subordination Provisions


         Any subordinated debt must be subordinate and subject in right of
payment to the prior payment of all senior debt. Unless and until all senior
debt, whether of principal of and interest and premium or prepayment or
liquidation penalty on the senior debt and fees and expenses incurred with
enforcement of the same, has been paid in full in cash, (1) no payment on
account of any subordinated debt can be made to any subordinated debt provider
by us or by the collateral agent or the depositary bank on behalf of us and (2)
no subordinated debt provider can ask, demand, sue for, take or receive from us,
by set-off or any other manner, or seek any other remedy allowed at law or in
equity against us for breach of our obligations under any instrument
representing subordinated debt.



         Upon any insolvency, bankruptcy or similar proceeding relating to us or
our creditors, or any liquidation, dissolution or other winding-up, or any
assignment for the benefit of creditors or any other marshaling of our assets
and liabilities, the senior creditors will be entitled to receive payment in
full in cash of all amounts due or to become due on or in respect of all senior
debt, or provision will be made for the payment, before any subordinated debt
provider is entitled to receive any payment with respect to subordinated debt.



         Subject to the payment in full in cash of all senior debt, the
subordinated debt providers will be subrogated to the rights of the senior
creditors to receive payments and distributions of cash, property and securities
applicable to the senior debt until the subordinated debt is paid in full in
cash.


      Debt Service Reserve Letter of Credit and Reimbursement Agreement


         Dresdner Bank AG, New York Branch, under a debt service reserve letter
of credit and reimbursement agreement, has agreed to provide the debt service
reserve letter of credit for use by us in connection with our project. The
financing documents require that the debt service reserve account be funded in
an amount equal to the debt service reserve account required balance on or
before the anticipated commercial operation date. Accordingly, we have entered
into the debt service reserve letter of credit and reimbursement agreement in
order to satisfy this obligation.



         The debt service reserve letter of credit provider will issue the debt
service reserve letter of credit on or before the earlier of (1) the commercial
operation date, (2) the guaranteed completion date or (3) December 31, 2002 for
our account in an amount up to $17,529,452, the maximum stated amount, to be
held by the collateral agent to serve as a debt service reserve facility for our
project. There will be no condition precedent to the debt service reserve letter
of credit provider's obligation to issue the debt service reserve letter of
credit, other than the occurrence of the earliest of the dates specified in the
first sentence of the following paragraph.




                                      101
<PAGE>


         The collateral agent will have the right to make drawings on the debt
service reserve letter of credit beginning on the earliest of (1) the commercial
operation date, (2) the Guaranteed Completion Date and (3) December 31, 2002.
The collateral agent may make drawings under the debt service reserve letter of
credit upon the occurrence of the following events: (1) there being insufficient
monies in the bond payment account on any interest payment date or principal
payment date to pay interest or principal then due, after application of funds
from the debt service reserve account; (2) upon receipt of a notice from us that
the long-term debt rating of the debt service reserve letter of credit provider
is less than "A" as determined by Standard & Poor's or "A2" as determined by
Moody's and the debt service reserve letter of credit has not been replaced
within the time period specified therein; (3) if a Trigger Event under the
collateral agency agreement has occurred and is continuing; (4) upon receipt of
a notice from the debt service reserve letter of credit provider on the day 45
days prior to its stated expiration date that the debt service reserve letter of
credit will not be extended or replaced by the close of business; and (5) if,
subsequent to the commercial operation date, moneys transferred to the debt
service reserve letter of credit provider from the revenue account are
insufficient to repay the interest on any debt service reserve letter of credit
loans. The collateral agent will apply the proceeds of each drawing: (a) in the
case of clauses (1) and (5) of the preceding sentence, to payment of the
relevant obligation and (b) in the case of clauses (2), (3) and (4) of the
preceding sentence, to the debt service reserve account until there is deposited
therein an aggregate amount equal to the debt service reserve account required
balance.



         Subject to the conditions of drawing, the debt service reserve letter
of credit will, unless extended, mature, expire or terminate on the earlier of
(1) five years from the date of issuance of the debt service reserve letter of
credit and (2) the occurrence of an event of default under the debt service
reserve letter of credit. The debt service reserve letter of credit, however,
may not be terminated upon the occurrence of an event of default under the debt
service reserve letter of credit without the debt service reserve letter of
credit provider first giving the collateral agent and the trustee written notice
at least 60 days prior to the termination during which period the collateral
agent is entitled to draw on the debt service reserve letter of credit as
described above under "--Collateral Agency Agreement--Debt Service Reserve
Account." The debt service reserve letter of credit provider must also provide a
copy of the written notice to us at the time the notice is given to the
collateral agent and the trustee.



         We will have the right to terminate or reduce the debt service reserve
letter of credit upon the receipt by the debt service reserve letter of credit
provider of notice from the trustee consenting to the termination or reduction.


         The debt service reserve letter of credit is subject to renewal for
additional periods of one or more years at the sole discretion of the agent
under the debt service reserve letter of credit and reimbursement agreement.

         The amount available for drawing under the debt service reserve letter
of credit will be reduced upon (1) making draws thereunder, (2) the reduction of
the debt service reserve account required balance and (3) certain deposits of
cash in the debt service reserve account.

Debt Service Reserve Letter of Credit Loans


         Each drawing on the debt service reserve letter of credit will
constitute the making of a loan to us by the debt service reserve letter of
credit provider. We must pay interest on the unpaid principal amount of each
outstanding debt service reserve letter of credit loan from the date the debt
service reserve letter of credit loan is made until the principal amount has
been repaid in full at a rate per annum equal, at our option, to either (1) the
adjusted base rate plus 1% or (2) the Eurodollar rate plus the applicable
margin. The adjusted base rate will equal the higher of (1) the federal funds
rate plus 50 basis points and (2) the rate of interest officially announced or
published by the debt service reserve letter of credit provider as its "prime"
or "reference" rate. The Eurodollar rate will be determined by reference to the
offered rates that appear on Telerate page 3750 for deposits in dollars two
London banking days prior to the date on which the rate is to become applicable
to a debt service reserve letter of credit loan.



         Each debt service reserve letter of credit loan will be evidenced by a
note in favor of the debt service reserve letter of credit provider. We must pay
the interest on any debt service reserve letter of credit loan out of cash
available in the revenue account at the same level in the flow of funds as
interest on other senior debt and must repay the principal amount of any debt
service reserve letter of credit loans out of cash available in the revenue
account after payment of debt service on all senior debt other than principal of
debt service reserve letter of credit loans. Each debt service reserve letter of
credit loan will mature five years after the date the debt service reserve
letter of credit loan is made.



         Unless the debt service reserve letter of credit is not extended or
replaced or unless there has been an event of default under the debt service
reserve letter of credit as described under "--Debt Service Reserve Letter of
Credit and Reimbursement Agreement," amounts available for drawing under the
debt service reserve letter of credit must be


                                      102
<PAGE>

reinstated immediately to the extent of any reimbursement of principal of debt
service reserve letter of credit loans, but not debt service reserve bonds or
debt service reserve letter of credit term loans.


Non-Renewal of Debt Service Reserve Letter of Credit


         If the debt service reserve letter of credit is not extended or
replaced at least 45 days prior to its termination date, or the credit rating of
the debt service reserve letter of credit provider is less than the required
rating and we do not within 45 days replace the debt service reserve letter of
credit with a letter of credit issued by a financial institution which meets the
required rating, the collateral agent will draw on the debt service reserve
letter of credit, the drawing due to non-extension or non-replacement of the
debt service reserve letter of credit, a "debt service reserve letter of credit
term loan", in an amount equal to the lesser of (1) the amount available to be
drawn under the letter of credit and (2) the difference between (x) the debt
service reserve account required balance and (y) amounts then on deposit in the
debt service reserve account, and will deposit the drawing into the debt service
reserve account. A debt service reserve letter of credit term loan will amortize
under a "mortgage-style" amortization schedule and the maturity date of any debt
service reserve letter of credit term loan will be 10 years after the date the
loan is made. Interest on and principal of any debt service reserve letter of
credit term loan will be paid, respectively, at the same levels as interest on
and principal of the bonds.


Conversion into Debt Service Reserve Bonds


         If by the date 30 months after the making of a debt service reserve
letter of credit loan, we have failed to repay at least 50% of the original
amount of the debt service reserve letter of credit loan, or if by the maturity
date of the debt service reserve letter of credit loan we have failed to repay
the debt service reserve letter of credit loan in full, then from and after the
applicable date, the debt service reserve letter of credit loan may, at the
option of the debt service reserve letter of credit provider, be converted into
a new security, a debt service reserve bond, having a principal amount equal to
the remaining principal amount of the debt service reserve letter of credit loan
so converted. Each debt service reserve bond must be amortized on the same
amortization schedule as the bonds and mature on the same maturity date as the
bonds. Interest on and principal of any debt service reserve bond will be paid,
respectively, at the same levels as interest on and principal of the bonds.


Covenants


         The covenants contained in the indenture will be incorporated by
reference, with appropriate substitution of parties, in the debt service reserve
letter of credit and reimbursement agreement as if described in full in the debt
service reserve letter of credit and reimbursement agreement.


Debt Service Reserve Letter of Credit Events of Default


         Each of the following will be an event of default under the debt
service reserve letter of credit and reimbursement agreement: (1) any amount due
under the debt service reserve letter of credit and reimbursement agreement or
any debt service reserve letter of credit note is not paid in full within 15
days after the due date ; (2) an "event of default" under the indenture has
occurred and is continuing or (3) an "event of default" under the construction
period letter of credit and reimbursement agreement has occurred and is
continuing.


Remedies


         Upon the occurrence and during the continuation of an event of default
under the debt service reserve letter of credit, at the request of the banks
holding 66-2/3% or more of the debt service reserve letter of credit commitment,
the debt service reserve letter of credit provider may (1) after notice as
required in the financing documents, terminate the debt service reserve letter
of credit, (2) declare all amounts owing under the debt service reserve letter
of credit and reimbursement agreement and any debt service reserve letter of
credit note to be forthwith due and payable, including amounts not yet advanced
under the debt service reserve letter of credit, which will upon being so
advanced be and become immediately due and payable, whereupon the obligations
will become and be due and payable, without presentment, demand or protest; (3)
terminate our ability to cause the reinstatement of the stated amount through
the reimbursement of drawings; and (4) terminate our ability of to continue any
debt service reserve letter of credit loans as, or to convert debt service
reserve letter of credit loans to, Eurodollar rate loans so long as the debt
service reserve letter of credit provider does not have the right to exercise
any other remedies except in accordance with the provisions of the collateral
agency agreement.




                                      103
<PAGE>

        Construction Period Letter of Credit and Reimbursement Agreement


         Dresdner Bank AG, New York Branch, under a construction period letter
of credit and reimbursement agreement, issued the construction period letter of
credit for our account in the amount of $30,000,000 and in favor of Williams
Energy. Williams Energy may make drawings under the construction period letter
of credit if our facility has not achieved the commercial operation date by the
date specified in the power purchase agreement, as the date may be extended in
accordance with the provisions of the power purchase agreement.



         Subject to the conditions of drawing, the construction period letter of
credit will mature, expire or terminate on the earliest to occur of (1) the date
on which the construction period letter of credit provider receives notice from
Williams Energy that the commercial operation date has occurred; (2) four years
from the date of issuance of the construction period letter of credit; and (3)
the occurrence of an event of default under the construction period letter of
credit. The construction period letter of credit; however, will not be
terminated upon the occurrence of an event of default under the construction
period letter of credit without the construction period letter of credit
provider first giving the collateral agent and Williams Energy written notice at
least 45 days prior to the termination. The construction period letter of credit
provider must also provide a copy of the written notice to us at the time the
notice is given to the collateral agent and Williams Energy.



         We will have the right to terminate or reduce the construction period
letter of credit upon the receipt by the construction period letter of credit
provider of notice from Williams Energy consenting to the termination or
reduction. The amount available for drawing under the construction period letter
of credit will be reduced upon making draws thereunder.


Construction Period Letter of Credit Loans


         Each drawing on the construction period letter of credit will
constitute the making by the construction period letter of credit provider of a
loan. We must pay interest on the unpaid principal amount of each outstanding
construction period letter of credit loan from the date the construction period
letter of credit loan is made until the principal amount has been repaid in full
at a rate per annum equal, at our option of, to either (1) the adjusted base
rate plus the applicable margin or (2) the Eurodollar rate plus the applicable
margin. The adjusted base rate will equal the higher of (1) the federal funds
rate plus 0.50% and (2) the rate of interest officially announced or published
by the construction period letter of credit provider as its "prime" or
"reference" rate. The Eurodollar rate will be determined by reference to the
offered rates that appear on Telerate page 3750 for deposits in dollars two
London banking days prior to the date on which the rate is to become applicable
to a construction period letter of credit loan.



         The construction period letter of credit loan will be evidenced by a
note in favor of the construction period letter of credit provider. We must pay
the interest on and repay the principal amount, based on mortgage-style
amortizations, of any construction period letter of credit loan out of cash
available in the revenue account at the same level as interest on and the
principal of the bonds. Each construction period letter of credit loan will
mature 10 years after the date the construction period letter of credit loan is
made.


Covenants


         The covenants contained in the indenture will be incorporated by
reference, with appropriate substitution of parties, in the construction period
letter of credit and reimbursement agreement as if described in full in the
construction period letter of credit and reimbursement agreement.


Construction Period Letter of Credit Events of Default


         Each of the following will be an event of default under the
construction period letter of credit and reimbursement agreement: (1) any amount
due under the construction period letter of credit and reimbursement agreement
or any construction period letter of credit note is not paid in full within 15
days after the due date; (2) an "event of default" under the indenture has
occurred and is continuing; and (3) an "event of default" under the debt service
reserve letter of credit and reimbursement agreement has occurred and is
continuing.


Remedies


         Upon the occurrence and during the continuation of an event of default
under the construction period letter of credit, at the request of the banks
holding 2/3 or more of the construction period letter of credit commitment, the
construction period letter of credit provider may (1) terminate the construction
period letter of credit, (2) declare all amounts owing under the construction
period letter of credit and reimbursement agreement and any construction period



                                      104
<PAGE>

letter of credit note to be forthwith due and payable, including amounts not yet
advanced under the construction period letter of credit, which will upon being
so advanced be and become immediately due and payable, whereupon the obligations
will become and be due and payable, without presentment, demand or protest and
(3) terminate our ability to continue construction period letter of credit loans
as or to convert construction period letter of credit loans to Eurodollar rate
loans so long as the construction period letter of credit provider does not have
the right to exercise any other remedies except in accordance with the
provisions of the collateral agency agreement.


                          Equity Subscription Agreement


         Under an equity subscription agreement entered into by and among us,
AES Ironwood, Inc. and the collateral agent, AES Ironwood, Inc. has agreed to
contribute equity, or make or cause to be made subordinated loans, to us from
time to time during the construction period (each loan, an "equity
contribution") at the request of the collateral agent, if the amounts then on
deposit in the construction account are insufficient to make the transfers
required to pay project costs as specified in the collateral agency agreement.
The obligation of AES Ironwood, Inc. to make equity contributions is supported
by bonds issued by an insurance company. The AES Corporation is obligated to
repay the insurance company any amounts drawn under the bonds. If AES Ironwood,
Inc. fails to pay any amounts due under the equity subscription agreement, the
collateral agent can draw on these insurance company bonds for payment of the
necessary amount. AES Ironwood, Inc.'s obligation to make equity contributions
will commence when all proceeds of the offering of the old bonds have been
utilized but will not at any time exceed, in the aggregate, $50,149,285. All
equity contributions will be deposited in the construction account and applied
as described under "--Collateral Agency Agreement--Construction Account."



         The equity subscription agreement also provides that upon the
occurrence of an event of default under the indenture, AES Ironwood, Inc. will
be obligated to make an equity contribution to us in an amount equal to
$50,149,285 less the aggregate of all equity contributions previously deposited
into the construction account. Any equity contribution following an event of
default will be deposited in the construction account and may be used to prepay
bonds and other outstanding senior permitted indebtedness in accordance with the
terms of the collateral agency agreement.



         Subject to specified conditions under the equity subscription
agreement, any "excess" equity which remains committed but unfunded at Final
Acceptance may be canceled. Conditions to the cancellation of the "excess"
equity commitments include (1) the absence of any default or event of default
under the indenture or any other financing document, (2) achievement of final
completion, (3) the occurrence of the commercial operation date and (4) funding
of all accounts, including the debt service reserve account, under, and to the
extent required by, the indenture and the collateral agency agreement.


                             Consents to Assignments


         In connection with the collateral assignment of all contract rights
held by us, including rights under our project contracts, the collateral agent
will receive an executed consent to assignment from third parties party to the
project contracts. In each consent, the applicable third party will, in respect
of our project contracts to which it is a party, among other matters, (1)
consent to the collateral assignment to the collateral agent on behalf of the
senior creditors, (2) agree to pay all amounts, if any, receivable by us
thereunder directly into the revenue account created under the collateral agency
agreement, (3) agree to matters concerning the exercise of remedies by the
collateral agent upon an event of default under the collateral agency agreement
and (4) agree to the exercise by the senior creditors of specific cure rights
with respect to our project contracts.


                                    Mortgage


         We, as mortgagor, will enter into the mortgage and will mortgage and
grant a security interest to the collateral agent for the benefit of the senior
creditors all of our rights, titles and interests in and to all real property
interests, including fee interests, easement interests and leasehold interests,
if any, to the facility site, our facility and any easements and all fixtures,
equipment and improvements, all accounts, subject to the terms of the indenture,
and personal property now owned or hereafter acquired. our rights in any leases
affecting the real property, including rights to receive income, will be
assigned by us to the collateral agent under the assignment of leases and
income.


         The events of default under the mortgage incorporate by reference those
provided in the indenture. Under the terms of the mortgage, the collateral agent
may, upon the occurrence and during the continuance of an event of default and
satisfaction of conditions contained in the collateral agency agreement, take
possession of all collateral covered by the mortgage.



                                      105
<PAGE>

         Proceeds from the exercise of remedies under the mortgage will be
applied in accordance with the security documents and the collateral agency
agreement.

                               Security Agreement

         We will enter into the security agreement with the collateral agent for
the benefit of the senior creditors providing for the granting of a security
interest in all of our personal property interests including, but not limited
to, all contract rights, equipment, receivables, accounts, insurance proceeds,
eminent domain proceeds, rights under any governmental approval, to the extent
permitted by applicable law, and patents and trademarks, including all proceeds
and all documents evidencing all monies and investment therein. Upon the
occurrence of a Trigger Event under the collateral agency agreement, remedies
may be exercised under the security agreement.

         Under the terms of the security agreement, the collateral agent may,
upon the occurrence and during the continuance of an event of default and
satisfaction of conditions contained in the collateral agency agreement, take
possession of all of the collateral covered by the security agreement.

         Proceeds from the exercise of remedies under the security agreement
will be applied in accordance with the security documents.

                                Pledge Agreement


         Under the pledge agreement to be entered into by AES Ironwood, Inc. in
favor of the collateral agent, AES Ironwood, Inc. will pledge to the collateral
agent, acting on behalf of the senior creditors, all of its ownership interests
in our company, and all rights under or derived therefrom, currently owned or
later acquired and all distributions, cash, instruments and other property and
proceeds, and all rights associated therewith, from time to time receivable or
otherwise distributable with respect to or in exchange for the ownership
interests.




                                      106
<PAGE>

                              PLAN OF DISTRIBUTION


         Except as described below, a broker-dealer may not participate in the
exchange offer in connection with a distribution of the new bonds. Each
broker-dealer that receives new bonds for its own account under the exchange
offer must acknowledge that it will deliver a prospectus in connection with any
resale of the new bonds. Based on SEC staff interpretations, a broker-dealer
could use this prospectus, as it may be amended or supplemented from time to
time, in connection with resales of new bonds received in the exchange offer
where the beneficial interests in old bonds for which they were exchanged were
acquired as a result of market-making activities or other trading activities. We
have agreed that for a period not to exceed 270 days to make this prospectus, as
amended or supplemented, available to any broker-dealer for use in connection
with any resale. In addition, until 120 days after the consummation of the
exchange offer, all dealers effecting transactions in the new bonds may be
required to deliver a prospectus.



         The information described above concerning SEC staff interpretations is
not intended to constitute legal advice, and broker-dealers should consult their
own legal advisors with respect to these matters.


         We will not receive any proceeds from the exchange offer or any sale of
new bonds by broker-dealers. New bonds received by broker-dealers for their own
account under the exchange offer may be sold from time to time in one or more
transactions in the over-the-counter market, in negotiated transactions, through
the writing of options on the new bonds or a combination of those methods of
resale, at market prices prevailing at the time of resale, at the time of
resale, at prices related to those prevailing market prices or negotiated
prices. Any resale may be made directly to purchasers or to or through brokers
or dealers who may receive compensation in the form of commissions or
concessions from any broker-dealer and/or the purchasers of any new bonds. Any
broker-dealer that resells new bonds that were received by it for its own
account under the exchange offer and any broker or dealer that participates in a
distribution of the new bonds may be deemed to be an "underwriter" within the
meaning of the Securities Act and any profit on any resale of new bonds and any
commissions or concessions received by any of those persons may be deemed to be
underwriting compensation under the Securities Act. Any broker or dealer
registered under the Exchange Act who holds old bonds that were acquired for its
own account as a result of market-making activities or other trading activities,
other than old bonds acquired directly from us, may exchange those old bonds
under the exchange offer; however, that broker or dealer may be deemed to be an
"underwriter" within the meaning of the Securities Act and must, therefore,
deliver a prospectus meeting the requirements of the Securities Act in
connection with any resales of the new bonds received by the broker or dealer in
the exchange offer. This prospectus delivery requirement may be satisfied by the
delivery by that broker or dealer of this prospectus. The letter of transmittal
states that by acknowledging that it will deliver and by delivering a
prospectus, a broker-dealer will not be deemed to admit that it is an
"underwriter" within the meaning of the Securities Act.

         We have agreed to pay the expenses of registration of the new bonds and
will indemnify the holders of the new bonds, including any broker-dealers,
against certain liabilities, including liabilities under the Securities Act.


         Prior to the exchange offer, there has been no public market for the
old bonds. We do not intend to apply for listing of the new bonds on any
securities exchange. There can be no assurance that an active market for the new
bonds will develop. To the extent that a market for the new bonds develops, the
market value of the new bonds will depend on market conditions (including yields
on alternative investments general economic conditions), our financial condition
and other conditions. Those conditions might cause the new bonds, to the extent
that they are actively traded, to trade at a significant discount from face
value. We have not entered into any arrangement or understanding with any person
to distribute the new bonds to be received in the exchange offer.


         We have not agreed to compensate broker-dealers who effect the exchange
of old bonds on behalf of holders.

                 UNITED STATES FEDERAL INCOME TAX CONSIDERATIONS


         Because the new bonds will be identical to the old bonds in all
relevant economic respects, the exchange of the old bonds for the new bonds will
not be treated as an exchange for United States federal income tax purposes.
Consequently, there will be no United States federal income tax consequences to
the exchange, and holders of the new bonds will continue to account for the
bonds for federal income tax purposes as if the exchange had not taken place.


                                  LEGAL MATTERS

         The validity of the new bonds will be passed upon for us by Hunton &
Williams, New York, New York.



                                      107
<PAGE>

                                     EXPERTS


         The independent engineer's report included as Annex B to this
prospectus has been prepared by Stone & Webster and is included herein in
reliance upon the authority of the firm and its affiliates as experts in the
review of the design, construction and operation of electric generating
facilities. The independent power consultant's report included as Annex C to
this prospectus has been prepared by Hagler Bailly and is included herein in
reliance upon the authority of the firm as experts in the analysis of power
markets, including future market demand, future market prices for electric
energy and capacity and related matters, for electric generating facilities.



         This document has been prepared by the management of our company and
includes financial statements audited by Deloitte & Touche LLP as stated in
their independent auditors' report accompanying those financial statements.
These financial statements are included in this prospectus in reliance upon the
independent auditors' report of the firm given upon their authority as experts
in accounting and auditing. The management of our company is responsible for the
accuracy and completeness of this document, including the "Prospective Financial
Information" appearing in Annex B, and Deloitte & Touche LLP makes no warranty
as to any of the information contained herein, and no representations except as
contained in its independent auditors' report.


                       WHERE YOU CAN FIND MORE INFORMATION


         Upon consummation of the exchange offer, we will be subject to the
informational requirements of the Exchange Act and will file reports and other
information with the SEC. Reports and other information filed by us with the SEC
can be inspected without charge and copied, upon payment of prescribed rates, at
the public reference facilities maintained by the SEC located at Room 1024, 450
Fifth Street, NW, Washington, DC 20549, and at the regional offices of the SEC
located at 7 World Trade Center, 13th Floor, New York, New York 10048 and the
Northwest Atrium Center, 500 West Madison Street, Suite 1400, Chicago, Illinois
60661-2511. Copies of the material and any part will also be available by mail
from the Public Reference Section of the SEC, located at 450 Fifth Street, NW,
Washington, DC 20549, at prescribed rates.



         The AES Corporation and The Williams Companies, Inc. are subject to the
informational requirements of the Exchange Act and, in accordance, file reports,
proxy statements and other information, including financial statements, with the
SEC. The reports, proxy statements and other information may be inspected
without charge and copied, upon payment of prescribed rates, at the offices of
the SEC located at Room 1024, 450 Fifth Street, NW, Washington, DC 20549, and at
the regional offices of the SEC located at 7 World Trade Center, 13th Floor, New
York, New York 10048 and the Northwest Atrium Center, 500 West Madison Street,
Suite 1400, Chicago, Illinois 60661-2511. Copies of the material and any part
will also be available by mail from the Public Reference Section of the SEC,
located at 450 Fifth Street, NW, Washington, DC 20549.


         The SEC also maintains a Website that contains reports and other
information regarding registrants that file electronically with the SEC. The
address of that site is (http:\\www.sec.gov).






                                      108

<PAGE>


                              AES IRONWOOD, L.L.C.
            (A Development Stage Enterprise, An Indirect Wholly Owned
                    Subsidiary of The AES Corporation, Inc.)

                  Index to Financial Statements for the Period
                     from June 25 through December 31, 1999


                                                                            Page

Independent Auditors' Report.................................................F-2

Balance Sheet................................................................F-3

Statement of Operations......................................................F-4

Statement of Changes in Member's Deficit.....................................F-5

Statement of Cash Flows......................................................F-6

Notes to Financial Statements................................................F-7




                                      F-1
<PAGE>


INDEPENDENT AUDITORS' REPORT


To the Member of
  AES Ironwood, L.L.C.:


We have audited the accompanying balance sheet of AES Ironwood, L.L.C. (an
indirect wholly owned subsidiary of The AES Corporation, Inc. and a development
stage enterprise) (the Company) as of December 31, 1999, and the related
statements of operations, changes in member's deficit and cash flows for the
period from June 25, 1999 (inception) through December 31, 1999. These
financial statements are the responsibility of the Company's management. Our
responsibility is to express an opinion on these financial statements based on
our audit.



We conducted our audit in accordance with generally accepted auditing standards.
Those standards require that we plan and perform the audit to obtain reasonable
assurance about whether the financial statements are free of material
misstatement. An audit includes examining, on a test basis, evidence supporting
the amounts and disclosures in the financial statements. An audit also includes
assessing the accounting principles used and significant estimates made by
management, as well as evaluating the overall financial statement presentation.
We believe that our audit provides a reasonable basis for our opinion.



In our opinion, such financial statements present fairly, in all material
respects, the financial position of AES Ironwood, L.L.C., as of December 31,
1999, and the results of its operations and its cash flows for the period from
June 25, 1999 (inception) through December 31, 1999, in conformity with
generally accepted accounting principles.



  /s/ Deloitte & Touche LLP



McLean, Virginia
January 31, 2000




                                      F-2
<PAGE>

AES IRONWOOD, L.L.C. (A Development Stage Enterprise)

BALANCE SHEET
DECEMBER 31, 1999
(In Thousands)
- --------------------------------------------------------------------------------


<TABLE>
<S>                                                                                   <C>
ASSETS

CURRENT ASSETS:
   Cash                                                                                 $    633
   Interest receivable                                                                       437
   Investments held by trustee - at cost, which approximates market value                 22,568
                                                                                      ----------


              Total current assets                                                        23,638


LAND                                                                                         528


CONSTRUCTION IN PROGRESS                                                                 244,563


CERTIFICATE OF DEPOSIT                                                                       385


DEFERRED FINANCING COSTS - Net of accumulated amortization of $44                          2,447


INVESTMENTS HELD BY TRUSTEE - at cost, which approximates market value                    68,145


OTHER ASSETS                                                                                 317
                                                                                      ----------


TOTAL ASSETS                                                                          $  340,023
                                                                                      ==========


LIABILITIES AND MEMBER'S DEFICIT

CURRENT LIABILITIES:
   Accounts payable                                                                   $   20,139
   Accrued interest                                                                        2,429
   Payable to affiliates                                                                     918
   Payable to parent                                                                         442
                                                                                      ----------


              Total current liabilities                                                   23,928


RETENTION PAYABLE                                                                         10,236


BONDS PAYABLE                                                                            308,500
                                                                                      ----------


              Total liabilities                                                          342,664
                                                                                      ----------


COMMITMENTS (Notes 4, 5, 6, and 7)

MEMBER'S DEFICIT:
   Common stock, $1 par value - 10 shares authorized, none issued or outstanding            --
   Accumulated deficit                                                                    (2,641)
                                                                                      -----------


              Total member's deficit                                                      (2,641)
                                                                                      -----------

TOTAL LIABILITIES AND MEMBER'S DEFICIT                                                $  340,023
                                                                                      ==========

</TABLE>

See notes to financial statements.


                                      F-3
<PAGE>

AES IRONWOOD, L.L.C. (A Development Stage Enterprise)


STATEMENT OF OPERATIONS
PERIOD FROM JUNE 25, 1999 (INCEPTION) THROUGH DECEMBER 31, 1999
(In Thousands)
- --------------------------------------------------------------------------------


OPERATING EXPENSES:
   General and administrative costs                 $    (169)
                                                    ----------


              Operating loss                             (169)


OTHER INCOME/EXPENSE:
   Interest income                                      3,283
   Interest expense                                    (5,755)
                                                    ----------


NET LOSS                                            $  (2,641)
                                                    ==========



See notes to financial statements.


                                      F-4
<PAGE>

AES IRONWOOD, L.L.C. (A Development Stage Enterprise)

STATEMENT OF CHANGES IN MEMBER'S DEFICIT
PERIOD FROM JUNE 25, 1999 (INCEPTION) THROUGH DECEMBER 31, 1999
(In Thousands)
- --------------------------------------------------------------------------------

                                     Common
                                      Stock           Accumulated
                                 ---------------   ------------------
                                 Shares   Amount   Deficit     Total
                                 ------   ------   -------    -------
BALANCE, JUNE 25, 1999              --    $  --    $    --    $    --

    Net loss                        --       --     (2,641)    (2,641)
                                 ------   ------   -------    -------


BALANCE, DECEMBER 31, 1999          --    $  --    $(2,641)   $(2,641)
                                 ======   ======   =======    =======


See notes to financial statements.

                                       F-5


<PAGE>

AES IRONWOOD, L.L.C. (A Development Stage Enterprise)

STATEMENT OF CASH FLOWS
FOR THE PERIOD FROM JUNE 25, 1999 (INCEPTION) THROUGH DECEMBER 31, 1999
(In Thousands)
- -------------------------------------------------------------------------------


OPERATING ACTIVITIES
    Net loss                                                $  (2,641)
    Amortization of deferred financing costs                       44
    Change in:
      Interest receivable                                        (437)
      Accrued interest                                          1,742
                                                            ---------


                Net cash used in operating activities          (1,292)


INVESTING ACTIVITIES:
    Payments for construction in progress                    (212,526)
    Payments for land                                            (528)
    Payments to debt service reserve                          (90,713)
    Purchase of other assets                                     (317)

                Net cash used in investing activities        (304,084)
                                                            ---------


FINANCING ACTIVITIES:
    Proceeds from project debt issuance                       308,500
    Payments for deferred financing costs                      (2,491)
                                                            ---------


                Net cash provided by financing activities     306,009
                                                            ---------


NET INCREASE IN CASH AND CASH EQUIVALENTS                         633


CASH AND CASH EQUIVALENTS, BEGINNING OF PERIOD                     --
                                                            ---------


CASH AND CASH EQUIVALENTS, END OF PERIOD                    $     633
                                                            =========


SUPPLEMENTAL DISCLOSURE:
    Interest  paid                                          $  11,764
                                                            =========


See notes to financial statements.


                                      F-6
<PAGE>


AES IRONWOOD, L.L.C. (A Development Stage Enterprise)

NOTES TO FINANCIAL STATEMENTS
FOR THE PERIOD FROM JUNE 25, 1999 (INCEPTION) THROUGH DECEMBER 31, 1999
- --------------------------------------------------------------------------------


1.       ORGANIZATION


         AES, Ironwood, L.L.C. (the Company) was incorporated on October 30,
         1998, in the state of Delaware, to develop, construct, and operate a
         705-megawatt (MW) gas-fired, combined cycle electric generating
         facility in South Lebanon Township, Pennsylvania (the Plant). The
         Company was considered dormant until June 25, 1999, at which time the
         project financing and certain related agreements were consummated
         (hereinafter, inception). The Plant, currently under construction, will
         consist of two Westinghouse 501 G combustion turbines, two heat
         recovery steam generators, and one steam turbine. The Plant will
         produce and sell electricity, as well as provide fuel conversion and
         ancillary services, solely to Williams Energy Marketing and Trading
         Company (Williams) under a power purchase agreement (the PPA) with a
         term of 20 years that will commence on the Plant's anticipated
         commercial operation date, June 30, 2001 (see Note 5).


         The Company is in the development stage and is not expected to generate
         any operating revenues until the Plant achieves commercial operations.
         As with any new business venture of this size and nature, operation of
         the Plant could be affected by many factors. Management of the Company
         believes that the assets of the Company are realizable.


         The Company is a wholly owned subsidiary of AES Ironwood, Inc.
         (Ironwood), which is a wholly owned subsidiary of The AES Corporation
         (AES). Ironwood has no assets other than its ownership interests in the
         Company and AES Prescott, L.L.C. (see Note 7). It has no operations and
         is not expected to have any operations. Its only income will be from
         distributions it receives from the Company and AES Prescott, L.L.C,
         once the Company achieves commercial operation. The equity that
         Ironwood is to provide to the Company will be provided to Ironwood by
         AES, which owns all of the stock of Ironwood. AES files quarterly and
         annual audited reports with the Securities and Exchange Commission
         under the 1934 Exchange Act, which are publicly available. Ironwood's
         equity contribution obligations are required to be supported by either
         an insurance bond or letter of credit. Currently those obligations are
         supported by an insurance bond issued to the collateral agent (see Note
         6).

         On June 25, 1999, the Company issued $308.5 million in senior secured
         bonds (see Note 4) for the purpose of providing financing for the
         construction of the Plant and to fund, through the construction period,
         interest payments to the bondholders.

         Pursuant to an Equity Subscription Agreement, Ironwood has agreed to
         contribute up to approximately $50.1 million to the Company to fund
         construction after the bond proceeds have been fully utilized (see Note
         4).

2.       SIGNIFICANT ACCOUNTING POLICIES

         Cash and Cash Equivalents - The Company considers unrestricted cash on
         hand, deposits in banks, and investments with original maturities of
         three months or less to be cash and cash equivalents for the purpose of
         the statement of cash flows.


                                      F-7
<PAGE>


         Investments Held by Trustee - The Company is required to maintain a
         construction funding account for the payment of certain qualifying
         construction costs and a construction interest account from which
         quarterly interest payments are to be made. As of December 31, 1999,
         these amounts were fully invested in money market accounts. The
         balances in the construction funding account and the construction
         interest account were approximately $50 million and $40 million,
         respectively, as of December 31, 1999.



         Construction in Progress - Costs incurred in developing the Plant,
         including progress payments, engineering costs, management and
         development fees, interest, and other costs related to construction are
         capitalized. Total interest capitalized on the project financing debt
         was approximately $8.4 million, as of December 31, 1999. Certain costs
         related to construction activities were paid by AES prior to the
         issuance of the bonds. These amounts include approximately $105.4
         million of construction progress payments and $20.1 million in other
         incurred costs. These costs are reflected within construction in
         progress, and were reimbursed to AES out of the bond proceeds.



         Other Assets - Pursuant to the provisions of 25 Pa. Code Section 127,
         Subchapter E, New Source Review, the Company must secure nitrogen oxide
         (NOX) Emission Reduction Credits (ERCs) in the amount of 509 tons per
         year and volatile organic compound ERCs in the amount of 179 tons
         per year prior to the commencement of commercial operations. As of
         December 31, 1999, the Company had purchased a portion of the NOX ERCs
         which are reported as Other Assets and will be expensed when used upon
         commencement of commercial operations.


         Deferred Financing Costs - Financing costs are deferred and are being
         amortized using the straight-line method over the expected period for
         which the financing was obtained, which does not differ materially from
         the effective interest method of amortization.


         Accounts Payable and Contract Retention Payable - Amounts currently
         payable for construction billings and those amounts billed by Siemens
         Westinghouse Power Corporation (the Contractor) in accordance with the
         engineering, procurement and construction contract (the EPC) but
         retained by the Company until construction is complete are included in
         accounts payable and contract retention payable, respectively. These
         liabilities are expected to be paid from investment balances (bond
         proceeds) or equity funding from Ironwood.


         Use of Estimates - The preparation of financial statements in
         conformity with generally accepted accounting principles requires the
         Company to make estimates and assumptions that affect reported amounts
         of assets and liabilities and disclosures of contingent assets and
         liabilities as of the date of the financial statements, as well as the
         reported amounts of revenues and expenses during the reporting period.
         Actual results could differ from those estimates.

         Income Taxes - The Company is a limited liability corporation and is
         treated as a partnership for tax purposes. Therefore, it does not pay
         income taxes, and no provision for income taxes has been reflected in
         the accompanying financial statements.

         Comprehensive Income - In 1999, the Company adopted Statement of
         Financial Accounting Standards No. 130, Reporting Comprehensive Income
         (SFAS 130) which establishes rules for the reporting of comprehensive
         income and its components. The adoption of SFAS 130 had no impact on
         the Company's financial statements as the Company had no items of other
         comprehensive income.

         Start-Up Costs - In 1999 the Company adopted AICPA Statement of
         Position (SOP) 98-5, Reporting on the Costs of Start-Up Activities,
         which requires that start-up and organizational costs be expensed as


                                      F-8
<PAGE>

         incurred. As such, no costs to which the Statement applies have been
         capitalized in the accompanying balance sheet.

         Fiscal Year-End - The Company's fiscal year ends on December 31.

3.       NEW ACCOUNTING PRONOUNCEMENTS


         In June 1998, Statement of Financial Accounting Standards No. 133,
         Accounting for Derivative Instruments and Hedging Activities (SFAS
         133), which established standards for the accounting and reporting of
         derivative financial instruments and hedging activities, was issued. As
         amended by SFAS 137, the standard will be adopted by the Company during
         fiscal year 2001. The Company is currently evaluating the impact of
         such adoption.


4.       BONDS PAYABLE

         On June 25, 1999, the Company issued $308.5 million of 8.857% senior
         secured bonds due 2025 (the Bonds) to qualified institutional buyers
         and/or institutional accredited investors, pursuant to a transaction
         exempt from registration under the Securities and Exchange Act of 1933
         (the Act) in accordance with Rule 144A of the Act. The net proceeds of
         the bonds (after deferred financing costs), approximately $306 million,
         are to be used to fund the construction of the Plant and, during the
         construction period, for interest payments to bondholders.


         Interest on the Bonds is payable quarterly in arrears, commencing on
         February 28, 2002. The final maturity date for the Bonds is November
         30, 2025.

         Principal & Interest Repayment Schedule (in thousands):

                  Year and Interest       Principal

                  2000                    $  27,324
                  2001                       27,324
                  2002                       29,233
                  2003                       31,742
                  2004                       32,780
                  2005-2025                 617,500
                                          ---------
                  Total Payments            765,903


                  Less Interest portion    (457,403)
                                          ---------


                  Principal               $ 308,500
                                          =========


         Future Maturities of Debt - Scheduled principal maturities of the bonds
         at December 31, 1999, are (in thousands):



                  2000                  $     --
                  2001                        --
                  2002                     1,974
                  2003                     4,751
                  2004 and thereafter    301,775
                                        --------


                  TOTAL                 $308,500
                                        ========



                                      F-9
<PAGE>

         Optional Redemption - The Bonds are subject to optional redemption, in
         whole or in part, at any time at a redemption price equal to 100% of
         the principal amount plus accrued interest, together with a premium
         calculated using a discount rate equal to the interest rate on
         comparable U.S. Treasury securities plus 50 basis points.


         Mandatory Redemption - The Bonds are subject to mandatory redemption,
         in whole or in part, at a redemption price equivalent to 100% of the
         principal amount plus accrued interest under certain situations
         pursuant to receiving insurance proceeds or liquidated damages from
         failure under the EPC with the Contractor  or in certain instances in
         which payments are received under the PPA with Williams under the event
         of default, at which time the Company has terminated the PPA.


         Registration Rights - The Company was obligated to register the Bonds
         under the Act with the Securities and Exchange Commission within 220
         days of the initial sale of the Bonds. The registration was not
         completed within the required time frame. As a result, effective
         January 30, 2000, the interest rate payable on the Bonds, previously
         fixed at 8.875%, increased by 50 basis points.


         Collateral for the Bonds consists of the Plant and related facilities,
         all agreements relating to the operation of the project, the bank and
         investment accounts of the Company, and all ownership interests in the
         Company, as prescribed under the trust indenture (the Indenture). The
         Company is also bound by a collateral agency agreement (the Collateral
         Agency Agreement) and an equity subscription agreement (the Equity
         Subscription Agreement).

         Indenture - The Indenture contains limitations on the Company incurring
         additional indebtedness, granting liens on the Company's property,
         distributing equity and paying subordinated indebtedness issued by
         affiliates of the Company, entering into transactions with affiliates,
         amending, terminating or assigning any of the Company's contracts and
         fundamental changes or disposition of assets.

         Collateral Agency Agreement - The Collateral Agency Agreement requires
         the Company to fund or provide the funding for a debt service reserve
         fund, which is expected to commence on June 30, 2001. The amount
         required for funding the debt service reserve fund is equal to six
         months scheduled payments of principal and interest on the bonds.


         Equity Subscription Agreement - The Company, along with Ironwood, has
         entered into an Equity Subscription Agreement, pursuant to which
         Ironwood has agreed to contribute up to approximately $50.1 million to
         the Company to fund project costs. This amount is secured by an
         acceptable bond issued by Ironwood. Ironwood will fund these amounts as
         they come due upon the earlier of (a) expenditure of all funds that
         have been established for construction or (b) the occurrence and during
         the continuation of an event of default, as defined under the
         Indenture. A portion of this equity requirement may be made in the form
         of affiliate debt, between Ironwood and the Company, which is
         subordinate to the Bonds.


         Covenants - The Indenture, Collateral Agency Agreement, and Equity
         Subscription Agreement contain specific covenants and requirements to
         be met by the Company.


5.       POWER PURCHASE AGREEMENT

         The Company and Williams have entered into a PPA for the sale of all
         electric energy and capacity produced by the Plant, as well as
         ancillary services and fuel conversion services. The term of the PPA is
         20 years, commencing when the construction of the Plant is complete and
         the Plant is commercially viable to produce electricity and related
         capacity, as well as to provide ancillary and fuel conversion services.
         Payment obligations to the Company are guaranteed by The Williams
         Companies, Inc.
                                      F-10
<PAGE>

         Such payment obligations under the guarantee are capped at an amount
         equal to 125% of the sum of the principal amounts of the bonds plus the
         maximum debt service reserve account required balance. The Company has
         provided Williams a guaranty issued by AES of specific payment
         obligations should the Plant not achieve commercial operation by June
         30, 2001. AES's liability under the guaranty is capped at $30 million.
         The Company has the option, and may be required under specific
         conditions described in the PPA, to replace the guaranty issued by AES
         with a letter of credit issued by a commercial bank. In such case, the
         repayment obligations with respect to drawings under the letter of
         credit are to be a senior debt obligation of the Company.


         Fuel Conversion and Other Services - As instructed by the Company,
         Williams has the obligation to deliver, on an exclusive basis, all
         quantities of natural gas and fuel oil required by the Plant to
         generate electricity or ancillary services, to start-up or shut-down
         the plant, and to operate the Plant during any period other than a
         start-up, shut-down, or required dispatch by Williams for any reason.


6.       COMMITMENTS AND CONTINGENCIES


         EPC - The Company has entered into a fixed-price turnkey agreement with
         the Contractor for the design, engineering, procurement and
         construction of the Plant. The Contractor will provide the Company with
         specific combustion turbine maintenance services and spare parts for an
         initial term of between eight and ten years under a maintenance service
         agreement. As of December 31, 1999, the Company was liable to the
         Contractor for a retention payment as part of the total contract price
         due at the completion of the contract for approximately $10.2 million.
         Water Supply - The Company has entered into a contract with the City of
         Lebanon Authority (the Authority) for the purchase of 50 percent of the
         water use of the Plant. The contract has a term of 25 years. Costs
         associated with the use of water by the Plant under this contract are
         based on gallons used per day at prices specified under the contract
         terms. The Company has also entered into an agreement with Pennsy
         Supply, Inc. which will provide the remaining 50 percent of
         the water use of the Plant.


         Interconnection Agreement - The Company has entered into an
         interconnection agreement with GPU Energy (GPU) to transmit the
         electricity generated by the Plant to the transmission grid so that it
         may be sold as prescribed under the Company's PPA. The agreement is in
         effect for the life of the Plant, yet may be terminated by mutual
         consent of both GPU and the Company under certain circumstances as
         detailed in the agreement. Costs associated with the agreement are
         based on electricity transmitted via GPU at a variable price, the PJM
         (Pennsylvania/New Jersey/Maryland) Tariff, as charged by GPU to the
         Company, which is comprised of both service cost and asset recovery
         cost, as determined by GPU and approved by the Federal Energy
         Regulatory Committee (FERC).


         Water Supply Pipeline - The Company has entered into two agreements in
         relation to the construction of the water supply pipeline. The
         first agreement is between the Company and G.L. Marks Contracting,
         Inc., for the construction of the water pipeline for approximately $2.5
         million. The second agreement is between the Company and Conewago
         Enterprises, Inc., for the construction of the pumping station, at an
         estimated cost of approximately $3.2 million.



         Letter of Credit - The Company also has a letter of credit agreement
         outstanding to fund the construction of an access road to the plant
         during construction. In connection with this letter of credit, the
         Company has made a collateral deposit into a certificate of deposit
         account of approximately $385,000, which equals the amount available
         under this agreement.



                                      F-11

<PAGE>

         Surety Bond Agreement - Ironwood has a surety bond agreement for $50.1
         million in relation to its equity subscription agreement. Annual
         commitment fees will be assessed based on the amount outstanding during
         the year.

7.       RELATED PARTY TRANSACTIONS


         Effective June 1999, the Company entered into a 27-year development and
         construction management agreement with AES Prescott, L.L.C. (Prescott),
         another wholly owned subsidiary of Ironwood, to provide certain support
         services required by the Company for the development and construction
         of the Plant. Under this agreement Prescott will also provide
         operations management services for the Plant once commercial operation
         is attained. Minimum amounts payable under the contract during the
         construction period are $120,000 per month. Once commercial operation
         is achieved, payments for operations management services will be
         approximately $400,000 per quarter.



         During the construction period, the construction management fees will
         be paid to Prescott from the investment balances or from equity
         funding. Through December 31, 1999, $875,000 in construction management
         fees were incurred, were charged to construction in progress, and are
         payable to Prescott.


8.       FAIR VALUE OF FINANCIAL INSTRUMENTS

         The estimated fair values of the Company's financial instruments have
         been determined using available market information. The estimates are
         not necessarily indicative of the amounts the Company could realize in
         a current market exchange. The use of different market assumptions
         and/or estimation methodologies may have a material effect on the
         estimated fair value amounts.


         The fair value of the Company's restricted investments approximates
         their carrying value. The estimated fair value of the Bonds as of
         December 31, 1999, based on quoted market prices of similarly rated
         bonds with similar maturities, does not differ materially from their
         carrying value.


9.       SEGMENT INFORMATION


         Under the provisions of Statement of Financial Accounting Standards No.
         131, Disclosure About Segments of an Enterprise and Related
         Information, the Company's business is expected to be operated as one
         reportable segment, with operating income or loss being the measure of
         performance evaluated by the chief operating decision maker. As
         described in Notes 1 and 5, the Company's primary customer will be
         Williams, which is expected to provide all of the revenues of the
         Company during the term of the PPA.

                                   * * * * * *


                                      F-12
<PAGE>

- --------------------------------------------------------------------------------
                                     ANNEX A
                           GLOSSARY OF TECHNICAL TERMS
- --------------------------------------------------------------------------------

<PAGE>

         I. GLOSSARY OF TECHNICAL TERMS


         The following terms will have the following meanings and the meanings
are equally applicable to both the singular and plural forms of the terms
defined. Any term defined below by reference to any agreement or instrument will
have the meaning whether or not the agreement or instrument is in effect. Unless
otherwise specified, any agreement or instrument defined or referred to below
will include any amendments, modifications and supplements and waivers made in
accordance with the terms of the agreement or instrument. Any reference to a
person includes the successors and permitted assigns of that person.


         "Change Order" means a written change order by either us or Siemens
Westinghouse, acceptable to the other party, requesting changes within the scope
of the maintenance services agreement.

         "Combustion Turbine" means one of our facility's two 501G combustion
turbines furnished by Siemens Westinghouse under the construction agreement or
any replacement 501G combustion turbine furnished by Siemens Westinghouse or one
of its affiliates under the construction agreement.

         "Completed Power Purchase Agreement Output Test" means, with respect to
our facility, any Power Purchase Agreement Output Test established as a
Completed Power Purchase Agreement Output Test in accordance with the
construction agreement.

         "Completed Performance Tests" means, with respect to our facility, any
Performance Test established as a Completed Performance Test in accordance with
the provisions of the construction agreement.


         "Construction Progress Milestone Dates" means the dates, as specified
in the construction agreement, by which the Construction Progress Milestones are
required to have been fully completed in accordance with the standards of
performance described in the construction agreement.


         "Construction Progress Milestones" means the construction progress
milestones specified in the construction agreement.

         "Delay LD SubCap" means the sub-limit on Siemens Westinghouse's
liability under the construction agreement for delays in completion of our
facility, the aggregate amount of which is equal to 20% of the contract price.

         "Dispatch Period" means a period of time during which the Williams
Energy has requested delivery of Net Electric Energy and/or the provision of
ancillary services under the power purchase agreement starting with a beginning
requested dispatch hour and concluding with an ending requested dispatch hour. A
Dispatch Period may continue for more than one calendar day.

         "EBH" means the calculated result of equivalent base load hours
incurred by the Combustion Turbines as determined in accordance with the
maintenance services agreement.

         "Electric Delivery Point" means the physical point at which Net
Electric Energy and/or ancillary services are delivered and measured.

         "Electric Metering Equipment" means the electric meters and associated
equipment, including metering transformers and meters for measuring
kilowatt-hours and reactive volt-ampere hours, owned by Metropolitan Edison,
which will be operated and maintained in accordance with the interconnection
agreement and which will be utilized in determining the amount of Net Electric
Energy and/or ancillary services delivered by us to the Electric Delivery Point
under the power purchase agreement.


         "Electrical Output Guarantee" means the guarantee by Siemens
Westinghouse to us that, with respect to the Completed Performance Test, if
Provisional Acceptance or Interim Acceptance occurs prior to Final Acceptance,
at the earlier to occur of Provisional Acceptance or Interim Acceptance, the
average net electrical output of our facility during the Completed Performance
Test will be greater than or equal to the applicable electrical output guarantee
as described in the Warranty Data Sheet.


         "Equipment" means all of the materials, apparatus, structures, tools,
supplies or other goods provided by Siemens Westinghouse or any subcontractor
which are incorporated into our facility or provided by Siemens Westinghouse as
part of the Services and retained by us after Final Acceptance in accordance
with the construction agreement.

         "Equivalent Starts" means the calculated result of equivalent starts
determined in accordance with the maintenance
services agreement.



                                      A-1
<PAGE>


         "Final Acceptance Certificate" will mean the certificate submitted by
us to Siemens Westinghouse stating that the final Acceptance requirements under
the construction agreement have been satisfied.


         "Final Acceptance" means the achievement or deemed achievement of our
facility's performance under the construction agreement.

         "Final CO Date" means December 31, 2001.


         "First Paid Extension Option" means our option to extend the commercial
operation date to December 31, 2001, by giving Williams Energy written notice of
the extension no later than April 30, 2001, and paying to Williams Energy a
specified amount by no later than June 30, 2001.


         "Free Extension Option" means our option to extend the commercial
operation date to December 31, 2001, if we provide an opinion to Williams Energy
from a third-party engineer that the commercial operation date will occur no
later than December 31, 2001.

         "Gas Interconnection Facilities" means the interconnection and delivery
facilities necessary for delivery of natural gas (including the Gas Metering
Equipment, but excluding compressors).

         "Gas Metering Equipment" means gas meters and associated equipment
utilized in determining the amount of natural gas delivered to us by the
Williams Energy under the power purchase agreement, and the amount of natural
gas consumed by our facility.

         "Guaranteed Completion Date" means the date which is 24 months after
the delivery by us to Siemens Westinghouse of the notice to proceed under the
construction agreement.


         "Guaranteed Emissions Limits" means the standards for emission by our
facility of all gaseous, particulate, liquid and noise pollutants as described
in the Warranty Data Sheet and the other or more stringent standards (if any)
under all applicable laws and applicable permits.



         "Guaranteed Final Acceptance Date" means twelve (12) months after the
Guaranteed Provisional Acceptance Date, unless on or before the end of the
twelve (12) month period (1) our facility has achieved Interim Acceptance or (2)
our facility has achieved Provisional Acceptance and Siemens Westinghouse will
have submitted a Plan to us and the independent engineer that demonstrates to
our reasonable satisfaction and to that of the independent engineer that Siemens
Westinghouse will achieve Interim Acceptance of our facility on or before the
date that is twenty-four (24) months after the Guaranteed Provisional Acceptance
Date, in either of which cases the Guaranteed Final Acceptance Date will be
twenty-four (24) months after the Guaranteed Provisional Acceptance Date and in
any case which date is subject to adjustment as expressly provided in the
construction agreement.


         "Guaranteed Provisional Acceptance Date" means February 28, 2001, which
date is subject to adjustment as expressly provided in the construction
agreement.


         "Heat Rate Guarantee" means the guarantee by Siemens Westinghouse to us
that if Provisional Acceptance and/or Interim Acceptance occurs prior to Final
Acceptance, at the Provisional Acceptance and Interim Acceptance of our
facility, the net heat rate of our facility during the Completed Performance
Test, calculated in BTUs per kilowatt-hour, will be equal to or less than the
applicable heat rate guarantee as described in the Warranty Data Sheet.


         "Initial Start-Up Testing" means the operation and testing of our
facility prior to the commercial operation date, including performance tests, to
determine, among other things, the operating characteristics of our facility,
our facility's capacity and our facility's ability to meet our obligations under
the power purchase agreement.

         "Interconnection Facilities" means all structures, facilities,
equipment, auxiliary equipment, devices and apparatus including the Protective
Apparatus directly or indirectly required and installed to interconnect and
deliver Net Electric Energy and ancillary services from our facility to the
Electric Delivery Point including electric transmission and/or distribution
lines, transformation, switching, Electric Metering Equipment, any other
metering equipment, communications, and safety equipment, including equipment
required to protect (1) the Metropolitan Edison's electrical system and its
customers from faults occurring at our facility and (2) our facility from faults
occurring on Metropolitan Edison's electrical system or on the electrical
systems of others to which the Metropolitan Edison's electrical system is
directly or indirectly connected.


         "Interim Acceptance Certificate" will mean the certificate submitted by
us to Siemens Westinghouse stating that the Interim Acceptance requirements
under the construction agreement have been satisfied.


         "Interim Acceptance" means the achievement of performance of the
"Services" under the construction agreement.



                                      A-2
<PAGE>

         "Interim Period" means the period of time, if any, commencing with the
earlier to occur of Provisional Acceptance or Interim Acceptance of our facility
and ending at Final Acceptance.

         "Mechanical Completion Certificate" means the certificate submitted by
us to Siemens Westinghouse stating that the Mechanical Completion requirements
under the construction agreement have been satisfied.

         "Mechanical Completion" means the mechanical completion of our facility
under the provisions of the construction agreement.

         "Miscellaneous Hardware" means miscellaneous hardware items including
but not limited to pins, springs, studs, gaskets, tie wires, fasteners, screws,
washers, nuts, bolts which are required to roll out and roll in the Program
Parts which is supplied by Siemens Westinghouse under the maintenance services
agreement or in accordance with a Change Order.

         "Net Electric Energy" means the gross amount of electric energy
generated by our facility at the direction of the Williams Energy, less station
service requirements and any transformation and transmission line losses to the
Electric Delivery Point, and delivered by us to the Metropolitan Edison's
electric system at the Electric Delivery Point.

         "New Program Parts" means the Program Part(s) which are supplied by
Siemens Westinghouse under maintenance services agreement, when they are new and
unused.

         "Notice of Final Acceptance" means the notice delivered by Siemens
Westinghouse to us stating that it believes that it has achieved Final
Acceptance of our facility.

         "Notice of Interim Acceptance" means the notice delivered by Siemens
Westinghouse to us stating that it believes that it has achieved Interim
Acceptance of our facility.

         "Notice of Mechanical Completion" means the notice delivered by Siemens
Westinghouse to us stating that it believes that it has achieved Mechanical
Completion of our facility.

         "Notice of Project Completion" means the notice delivered by Siemens
Westinghouse to us stating that the Project Completion requirements under the
construction agreement have been satisfied.


         "Notice of Provisional Acceptance" will mean the notice delivered by
Siemens Westinghouse to us stating it has achieved Provisional Acceptance of the
Facility.



         "Notice of Reliability Guarantee Achievement" will mean the notice
delivered by Siemens Westinghouse to us stating it has achieved the Reliability
Guarantee.


         "Oil Delivery Point" means the physical point at which fuel oil is
delivered and measured.

         "Oil Metering Equipment" means the oil meters and associated equipment
utilized in determining the amount of fuel oil delivered to us by Williams
Energy and the amount of fuel oil consumed by our facility.


         "Payment and Milestone Schedule" means the schedule of payments and
milestones as described in the construction agreement.


         "Performance Guarantee" means the guarantee by Siemens Westinghouse to
us that (1) our facility will be capable of achieving all the applicable
performance specifications referred to in the construction agreement during a
Completed Performance Test at the earlier to occur of Provisional Acceptance or
Interim Acceptance of our facility and (2) our facility will be capable of
achieving all the applicable performance specifications referred to in the
construction agreement during a Completed Performance Test at Final Acceptance
of our facility.

         "Performance Guarantee Payments" means the payments by Siemens
Westinghouse to us as rebates if (1) our facility fails to achieve the natural
gas-based Heat Rate Guarantee during the period, if any, commencing with the
earlier to occur of Provisional Acceptance and Interim Acceptance of our
facility and continuing until Final Acceptance of our facility, (2) our facility
fails to achieve the natural gas-based Electrical Output Guarantee during the
period, if any, commencing with the earlier to occur of Provisional Acceptance
and Interim Acceptance and continuing until Final Acceptance of the Facility, or
(3) our facility fails to achieve any of the applicable natural gas-based and
fuel oil-based Performance Guarantees at Final Acceptance of our facility, as
the case may be.

         "Performance Tests" means the operation of our facility by or on behalf
of Siemens Westinghouse in accordance with the provisions of the construction
agreement and in accordance with applicable laws, applicable permits, the
electrical interconnection requirements and the Power Purchase Agreement
Operating Requirements, for the purpose of determining the compliance with the
Guaranteed Emissions Limits and the level of achievement of the Performance
Guarantees.

                                      A-3
<PAGE>


         "Plan" will mean a written plan prepared by Siemens Westinghouse to
accelerate the performance of the Services as necessary in order to achieve
Final Acceptance of our facility no later than the Guaranteed Final Acceptance
Date.


         "Power Factor" means the ratio of real power expressed in watts to
apparent power, expressed in volt- amperes.


         "Power Purchase Agreement Operating Requirements" means those
procedures and requirements relating to the operation and maintenance of our
facility described in the power purchase agreement.


         "Power Purchase Agreement Output Tests" means the operation of our
facility by or on behalf of Siemens Westinghouse in accordance with the
construction agreement and in accordance with applicable laws, applicable
permits, the electrical interconnection requirements and the Power Purchase
Agreement Operating Requirements for the purpose of determining the level
achievement of Electrical Output Guarantee.

         "Program Part(s)" means the number and type of part(s) of the
Combustion Turbine that are listed in the maintenance services agreement.

         "Project Completion Certificate" means the certificate delivered by us
to Siemens Westinghouse stating that the Project Completion requirements under
the construction agreement have been satisfied.

         "Project Completion Deadline" means one hundred eighty (180) days after
Final Acceptance of our facility.


         "Project Completion Payment" means will have the meaning described in
Section 4.7.4 hereof.


         "Project Completion" means the acceptance by us of the completed
project from Siemens Westinghouse in accordance with the construction agreement.


         "Protective Apparatus" means the equipment and apparatus on our side of
the Electric Delivery Point, including, but not limited to, protective relays,
circuit breakers, necessary or appropriate to isolate our facility from
Metropolitan Edison's electrical system consistent with accepted electrical
practices.



         "Protective Gas Apparatus" means the equipment and apparatus on our
side of the Gas Delivery Point necessary to maintain the safety of our facility
consistent with standard gas industry practices.


         "Provisional Acceptance" means the achievement of performance pursuant
to the provisions of the construction agreement.

         "Provisional Acceptance Certificate" means the certificate delivered by
us to Siemens Westinghouse stating that the Provisional Acceptance requirements
under the construction agreement have been satisfied.


         "Punch List" means the list prepared by us with the full cooperation of
Siemens Westinghouse, which list will describe all items of work which remain to
be performed in order to ensure that our facility fully complies with all of the
standards and requirements described in the construction agreement.



         "Reliability Guarantee" means the guarantee by Siemens Westinghouse to
us that, in no event later than the occurrence of Final Acceptance of our
facility, our facility will have successfully completed the Reliability Run.


         "Reliability Run" means the operation of our facility for forty-five
(45) consecutive days in accordance with applicable laws, applicable permits,
the Guaranteed Emissions Limits, the instruction manual, the electrical
interconnection requirements, the Power Purchase Agreement Operating
Requirements and the construction agreement.

         "Retainage" means an amount equal to 5% of each of our scheduled
payments, other than our project completion payment, to Siemens Westinghouse
under the construction agreement, which we may withhold until after Final
Acceptance if the independent engineer fails to confirm the matters certified to
by Siemens Westinghouse in its payment request.

         "Risk Transfer Date" means the earlier to occur of (1) delivery by us
of the Provisional Acceptance Certificate the Interim Acceptance Certificate in
the Final Acceptance Certificate or (2) the earlier transfer of our facility to
us upon termination of the Construction Agreement.

         "Scheduled Outage" means a planned outage of the applicable Combustion
Turbine, scheduled by us and Siemens Westinghouse, during which the applicable
TFA Services described in the maintenance services agreement will be performed.
A Scheduled Outage will commence when the Combustion Turbine breaker is opened
and will end when Siemens Westinghouse has completed its applicable TFA Services
for the given Scheduled Outage and Siemens Westinghouse has submitted to us
written notice of completion and we have concurred.



                                      A-4
<PAGE>

         "Scope Change Order Notice" means a written notice to us issued by
Siemens Westinghouse indicating that we believes a Scope Change Order is
required in connection with the performance of the Services.

         "Scope Change Order Request" means a written notice proposal issued and
signed by us requesting a Scope Change, submitted to Siemens Westinghouse by us
pursuant to the construction agreement.

         "Scope Change Order" means a written order to Siemens Westinghouse
issued and signed by us authorizing a Scope Change and, if appropriate, an
adjustment in one or more of the contract price, the Guaranteed Completion
Dates, the Payment and Milestone Schedule, the Construction Progress Milestone
Dates, the Project Schedule and the Performance Guarantees or any other
amendment of the terms and conditions of the construction agreement.

         "Scope Changes" means any material addition to, deletion from,
suspension of or other modification to our facility or to the quality, function
or intent of our facility, including any addition, deletion, suspension or other
modification which requires a change in one or more of the contract price, the
Guaranteed Completion Dates, the Payment and Milestone Schedule, the
Construction Progress Milestone Dates, the Project Schedule and the Performance
Guarantees.


         "Second Paid Extension Option" means our option to extend the Final CO
Date to and including December 31, 2002 by giving Williams Energy written notice
of the estimated extension required no later than October 31, 2001 and paying to
Williams Energy specific amounts for each day of the extension.


         "Services" means the services provided by Siemens Westinghouse under
the construction agreement.

         "Shop Repair" means shop repair/refurbishment work performed by Siemens
Westinghouse on Program Parts at its manufacturing plant, its services facility
or a suitable facility selected by Siemens Westinghouse.

         "Shutdowns" means an actual shutdown of a unit of our facility, as
evidenced by the opening of its Combustion Turbine's breaker, or our facility,
as evidenced by the opening of all of its breakers, immediately following the
ending requested dispatch hour of a Dispatch Period or pursuant to an early
shutdown notice.

         "Start-Up Testing Date" means the date our facility would be prepared
to begin Initial Start-Up Testing.

         "Start-Ups" means a successful Start-Up of our facility or a unit
necessary to comply with the schedule or request by Williams Energy for a
Dispatch Period for our facility immediately preceding a beginning requested
dispatch hour.


         "TFA Services" means the advise and consultation given to our personnel
by a field service representative of Siemens Westinghouse under the maintenance
activities performed by others at the facility site and (2) any of Siemens
Westinghouse's recommended quality assurance procedures for activities performed
at the facility site so long as TFA Services do not include management
supervision or regulation of our personnel, agents or contractors.


         "Total LD SubCap" means the limitation Siemens Westinghouse's total
liability for delays in completion together with its liability for any
performance shortfalls, the aggregate amount of which is equal to 45% of the
contract price.

         "Transmission System" means the electric transmission facilities amend,
controlled operated by Metropolitan Edison.

         "Trigger Event" means (1) an "event of default" under the Indenture and
an acceleration of the indebtedness issued thereunder; (2) an "event of default"
under the debt service reserve letter of credit and reimbursement agreement and
an acceleration of the indebtedness incurred by us thereunder; (3) an "event of
default" under the construction period letter of credit and reimbursement
agreement and an acceleration of the indebtedness incurred by us thereunder; (4)
an "event of default" or the equivalent under any working capital facility and
an acceleration of the indebtedness incurred by us thereunder; or (5) a
bankruptcy event in respect of us and the expiration of the shortest applicable
grace period.


                                      A-5
<PAGE>
- --------------------------------------------------------------------------------

                                      ANNEX B

                          INDEPENDENT ENGINEER'S REPORT

- --------------------------------------------------------------------------------


<PAGE>

[GRAPHIC OMITTED]

Stone & Webster
Management Consultants, Inc.

- --------------------------------------------------------------------------------

                   Independent Technical Consultant's Report
                                     on the
                      AES Ironwood, L.L.C.. Power Project
                                 June 18, 1999

                                  Prepared by
                  Stone & Webster Management Consultants, Inc.



                                      B-1
<PAGE>


                                  LEGAL NOTICE

This report was prepared by Stone & Webster Management Consultants, Inc. with
the assistance of its affiliated company, Stone & Webster Engineering
Corporation, together hereafter referred to as Stone & Webster, expressly for
Lehman Brothers Inc. ("Lehman Brothers"). Neither Stone & Webster, Lehman
Brothers, nor any person acting on their behalf: (a) makes any warranty, express
or implied, with respect to the use of any information or methods disclosed in
this report; or (b) assumes any liability with respect to the use of any
information or methods disclosed in this report.




                                       B-2
<PAGE>



                                Table of Contents
<TABLE>

<S>                                                                                                     <C>
1.         Executive Summary.............................................................................5

   1.1     PROJECT DESCRIPTION...........................................................................6
   1.2     CONCLUSIONS...................................................................................7

2.         Scope of Work................................................................................12


3.         Facility Design..............................................................................13

   3.1     FACILITY DESCRIPTION.........................................................................13
   3.2     SITE LOCATION AND DESCRIPTION................................................................13
   3.3     COMBUSTION TURBINE GENERATOR.................................................................14
   3.4     HEAT RECOVERY STEAM GENERATOR................................................................20
   3.5     STEAM TURBINE................................................................................20
   3.6     ELECTRIC GENERATOR...........................................................................21
   3.7     BALANCE OF PLANT SYSTEMS.....................................................................21
   3.8     FUEL SYSTEMS.................................................................................26
   3.9     ELECTRICAL SYSTEMS...........................................................................28
   3.10    SWITCHYARD...................................................................................28
   3.11    INSTRUMENT AND CONTROL SYSTEMS...............................................................29
   3.12    CIVIL AND STRUCTURAL DESIGN..................................................................29
   3.13    INTERCONNECTIONS.............................................................................32

4.         Environmental and Permitting.................................................................36

   4.1     ENVIRONMENTAL SITE ASSESSMENT................................................................36
   4.2     PERMITTING...................................................................................36

5.         Project Agreements...........................................................................40

   5.1     POWER PURCHASE AGREEMENT.....................................................................40
   5.2     INTERCONNECTION AGREEMENT....................................................................43
   5.3     ENGINEERING, PROCUREMENT, AND CONSTRUCTION SERVICES..........................................43
   5.4     MANAGEMENT AND OPERATIONS AGREEMENT..........................................................48
   5.5     SERVICES AGREEMENT...........................................................................49
   5.6     EFFLUENT SUPPLY AGREEMENT....................................................................49
   5.7     AGREEMENT RELATING TO REAL ESTATE............................................................50
   5.8     MAINTENANCE PROGRAM PARTS, SHOP REPAIRS AND SCHEDULED OUTAGE TFA SERVICES CONTRACT...........50

6.         Principal Project Participants...............................................................52

   6.1     AES IRONWOOD, LLC............................................................................52
   6.2     AES PRESCOTT, LLC............................................................................52
   6.3     WILLIAMS ENERGY MARKETING & TRADING COMPANY..................................................52
   6.4     SIEMENS WESTINGHOUSE POWER CORPORATION.......................................................53
</TABLE>


                                      B-3
<PAGE>
<TABLE>
<S>                                                                                                     <C>

7.         Assessment of Projected Operating Results....................................................54

   7.1     OVERVIEW.....................................................................................54
   7.2     PRINCIPAL CONSIDERATIONS AND ASSUMPTIONS.....................................................54
   7.3     PROJECT COST.................................................................................56
   7.4     POWER PRODUCTION.............................................................................57
   7.5     REVENUES.....................................................................................58
   7.6     OPERATING EXPENSES...........................................................................59
   7.7     FINANCING ASSUMPTIONS........................................................................61
   7.8     PROJECTED OPERATING RESULTS..................................................................62
   7.9     SENSITIVITY ANALYSES.........................................................................62
   7.10    LIQUIDATED DAMAGES ANALYSES..................................................................65
</TABLE>



Exhibit I

Base Case

Increased O&M Sensitivity (Case #1)

Increased Heat Rate Sensitivity (Case #2)

Decreased Availability Sensitivity (Case #3)

Hagler Bailey High Gas Price Sensitivity (Case #4)

Hagler Bailly Low Demand Growth Sensitivity (Case #5)


Exhibit II

Document Log


                                      B-4
<PAGE>


1.       Executive Summary

Stone & Webster Management Consultants, Inc. is pleased to provide this report
(the "Report") which summarizes our independent technical review (the "Review")
of the proposed AES Ironwood Project (the "Project"). The Project will consist
of a nominal 705 megawatt ("MW") net combined cycle electric generating facility
(the "Facility") to be located in South Lebanon Township, Pennsylvania and the
associated Project documents and agreements.

The Review was conducted by Stone & Webster Management Consultants, Inc. with
the assistance of Stone & Webster Engineering Corporation (collectively, "Stone
& Webster"). The Review was conducted by Stone & Webster for the purpose of
producing this Report on behalf of Lehman Brothers as Initial Purchaser of
certain bonds (the "Bonds") to be issued by AES Ironwood, LLC ("AES Ironwood"),
pursuant to Rule 144A under the Securities Act of 1933, as amended, to finance
the construction and initial start-up and testing of the Facility. The Bonds are
to be offered in the United States to qualified institutional buyers and
institutional accredited investors and in offshore transactions complying with
Regulation S under the Securities Act of 1933 as amended.

The scope of the Review included the conceptual design and interfaces of the
Project; the proposed Siemens Westinghouse Power Corporation ("SWPC") 501G
combustion turbine technology; the projected performance of the Project; the
Phase I site assessments for the Project; the issued permits for the Project;
the technical assumptions utilized in the Pennsylvania/New Jersey/Maryland
("PJM") Market Study prepared by Hagler-Bailly Consulting Inc. ("Hagler Bailly")
and dated June 1, 1999; and the Project's projected operating results through
validation of the Project pro forma and verification of the model results (the
"Projected Operating Results").

Stone & Webster also reviewed the principal contracts and agreements associated
with the Project. These included the Power Purchase Agreement dated February 5,
1999 ("PPA"), the Generation Facility Transmission Interconnection Agreement
with Metropolitan Edison Company ("MET-ED") dated March 23, 1999
("Interconnection Agreement"), the Engineering, Procurement and Construction
Services Agreement dated September 23, 1998 as amended ("EPC Contract"), the
Effluent Supply Agreement dated March 3, 1998 ("ESA"), the Maintenance Program
Parts, Shop Repairs and Scheduled Outage TFA Services Contract dated September
23, 1998 ("Maintenance Services Agreement") and the Agreement Relating to Real
Estate dated October 22, 1998 (collectively the "Project Agreements"). Stone &
Webster reviewed the Project Agreements from a technical and economic standpoint
to assess the adequacy, compatibility, and reasonableness of their terms and
conditions. Stone & Webster made no determination as to the validity and
enforceability of the Project documents and permits. However, for the purposes
of this Report, we have assumed the Project Agreements and contracts will be
fully enforceable in accordance with their respective terms and that all parties
will comply with the provisions of their


                                      B-5
<PAGE>

respective agreements. Stone & Webster also conducted a site visit on October
21, 1998 and made general field observations, specifically the existing above
ground condition of the site.

1.1      Project Description

The Project is being developed and will be owned, operated, and maintained by
AES Ironwood. AES Ironwood is a limited liability company, organized and
existing under the laws of Delaware. AES Ironwood was formed to develop,
construct, own, and operate the Project. AES Ironwood is a special purpose
project company and a wholly owned subsidiary of AES Ironwood Inc. AES Ironwood
Inc. is a wholly owned subsidiary of The AES Corporation ("AES"). AES, which was
founded in 1981, is one of the world's largest global power companies and owns
or has an interest in 97 electric generating plants totaling over 26,000 MW in
18 countries. AES also distributes power in Brazil, El Salvador and Argentina,
and heat in Kazakhstan. AES operates gas-fired, oil-fired, hydropower and solid
fuel plants and employs approximately 40,000 people around the world. As of
December 31, 1998, AES had assets worth $10.8 billion. AES Prescott, L.L.C,
("AES Prescott"), a Delaware limited liability company and a wholly owned
subsidiary of AES Ironwood, Inc., will manage the development and construction
of the Project pursuant to a development and construction management agreement
between AES Prescott and AES Ironwood.

The Facility will have a nominal 705 MW designed electric generating capacity
and will be comprised of the following major equipment: two SWPC model 501G
combustion turbines (the "501G") with hydrogen cooled generators, two unfired,
three pressure level reheat heat recovery steam generators ("HRSGs"), one
multicylinder reheat condensing steam turbine with hydrogen cooled generator,
one water cooled condenser using a forced draft cooling tower, one integrated
control system, and a 230 kV switchyard. The combustion turbines, the steam
turbine, and their associated generators will be located indoors. The two HRSGs
and associated auxiliary equipment will be located outdoors.

The Facility will be designed for base load and/or cyclic operation capable of
startup and shutdown on a dispatchable basis. The combustion turbines will
primarily burn natural gas supplied by way of a pipeline with provisions to burn
Jet A ("fuel oil") as a backup fuel. Each combustion turbine will be coupled
with a three pressure level reheat HRSG that will generate steam to operate the
steam turbine. Electrical generators connected to the two combustion turbines
and the steam turbine will be connected to the switchyard through individual
generator step up transformers. These transformers will raise the generated
voltage to 230 kV for connection into the PJM interconnected electrical system.

The Facility will be designed as a zero liquid discharge facility with its raw
water supply requirements coming from two sources: the adjacent Pennsy Supply,
Inc. quarry and the City of Lebanon Wastewater Treatment Plant ("WWTP") by way
of an approximately 6.5 mile effluent ("makeup water") pipeline. Potable water
will also be supplied by the City of Lebanon Authority (the "Authority").


                                      B-6
<PAGE>


Stone & Webster reviewed the TRC Environmental Corporation ("TRC") Phase 1
Environmental Site Assessment Reports performed for the site consisting of the
Martin property and the RESCO Products property. The assessment for the Martin
property revealed no evidence of recognized concerns to the subject property.
The only environmental condition identified for the RESCO Products property is
the presence of asbestos in two roofing materials: the tar coating of the Butler
Building/add-on roof and the roof tar paper of a small attached shed at the rear
of the Butler Building. Stone & Webster agrees with TRC's opinion that removal
of these structures and the asbestos is not considered a major environmental
issue.

Electrical power produced by the Project will be sold to Williams Energy
Marketing & Trading Company ("Williams") under the terms of a 20 year PPA. The
PPA calls for Williams to purchase Facility capacity, ancillary services, and
fuel conversion services pursuant to the terms of the PPA. In addition, the PPA
provides for the supply and transport of the natural gas and fuel oil to the
Facility by Williams. The natural gas will be supplied by way of a pipeline to
the site boundary. The fuel oil will be supplied by truck. A two-day fuel oil
supply will be stored in the Facility's fuel oil storage tank.

Following expiration of the 20-year term of the PPA, the Facility will be
operated as a merchant power plant. AES Ironwood will be responsible for the
procurement of fuel and will sell its output directly into the PJM power pool
(or pursuant to bilateral contracts).

Under the terms of the EPC Contract, SWPC, a wholly owned subsidiary of Siemens
Corporation, will act as the primary Contractor and will be responsible for the
engineering, procurement, and construction of the Project on a turnkey, lump-sum
basis. All of SWPC's obligations under the EPC Contract are unconditionally
guaranteed by Siemens Corporation. Siemens Corporation is a wholly owned
subsidiary of Siemens AG and is the entity through which Siemens AG conducts all
of its U.S. business.

The Provisional Notice to Proceed ("PNTP") was provided to SWPC on September 23,
1998 and several milestones have been achieved to date by SWPC. The full Notice
to Proceed ("NTP") will occur at or before financial closing of AES Ironwood.
The Project Guaranteed Provisional Acceptance date is 23 months and two weeks
following NTP.

AES personnel will operate the Facility pursuant to a Management and Operations
Services Agreement ("Operations Agreement") between AES Prescott and AES
Ironwood. The Project will purchase combustion turbine parts, shop repairs, and
scheduled outage services from SWPC.

1.2      Conclusions

Set forth below are the principal findings and conclusions which Stone & Webster
has reached regarding the Project. For a complete understanding of the
estimates, assumptions, and


                                      B-7
<PAGE>

calculations upon which these findings and conclusions are based, this Report
should be read in its entirety.

1.     The Facility design, as specified in the EPC Contract, is in accordance
       with standard industry practice. SWPC possesses the organization and
       personnel to execute its obligations under the EPC Contract and the
       Maintenance Services Agreement, and is familiar with the construction and
       maintenance of large electrical generation facilities. The Project
       construction schedule proposed by SWPC is achievable and is consistent
       with the terms of the PPA.

2.     Stone & Webster views the SWPC 501G combustion turbine as an
       advancement in high-temperature advanced technology combustion turbines
       for SWPC and is typical of the normal design evolution for manufacturers.
       Many of the design concepts incorporated in the 501G are rooted firmly in
       the 501 series and are complemented by improvements which have been
       tested in the 501F series or predicted by extensive modeling or full
       scale testing. The first 501G unit is expected to begin commercial
       operation later in 1999. The various 501G components and designs have
       been individually shop tested and computer analyzed. SWPC's 501G is
       gaining commercial acceptance as demonstrated by the fact that 17 of
       SWPC's 501Gs have been sold to date in the United States.

3.     The combustion turbines for the Project are scheduled to become the
       third and fourth 501Gs in operation. As a result the Project will benefit
       from approximately 25 months of facility startup, extensive testing, and
       operating experience of the first installation of 501Gs (McIntosh
       Project) and approximately nine months of such experience from the second
       installation of 501Gs (Millenium Project). Because the 501G has no
       commercial operating experience, the initial unit availability of the
       501G may be lower in the early years of operation than is the case with
       combustion turbine units currently in operation that use mature
       technology. Lower initial unit availability has been reflected as in the
       Base Case and a sensitivity case has been included in the Projected
       Operating Results utilizing lower availability than that set forth in the
       Base Case.

4.     A sustained period of commercial operation at full load conditions
       followed by an inspection of the combustion turbine is necessary to
       predict with any certainty the types of startup and operational problems,
       if any, that the 501G may encounter. However, the Project will benefit
       from the startup testing and inspection programs implemented by SWPC at
       the McIntosh and Millenium units. SWPC has also invested in and has
       stated that it will make available to the Project a complete set of risk
       parts for the entire combustion turbine gas path. In addition, under the
       Maintenance Services Agreement SWPC will provide combustion turbine spare
       parts to the Project. This full set of gas path risk parts to be made
       available by SWPC and the Maintenance Services Agreement long term spare
       parts program will minimize the duration of any unscheduled combustion
       turbine-related outages that require the replacement of parts by having
       the most commonly replaced parts


                                      B-8
<PAGE>

       readily available. In addition, SWPC has the resources and capabilities
       to resolve any problem that may arise with the 501Gs.

5.     The steam turbine and electrical generator designs are acceptable and in
       accordance with standard industry practice.

6.     If designed and constructed in accordance with the EPC Contract and
       operated and maintained in accordance with the Maintenance Services
       Agreement and the Operations Agreement, the Facility should be capable of
       meeting the net output contract requirements specified in the Projected
       Operating Results.

7.     The liquidated damages provisions of the EPC Contract are reasonable.
       The one year warranty period is acceptable based on the commercial terms
       of the EPC Contract in conjunction with the one year warranty in the
       Maintenance Services Agreement. These two agreements, although
       independent, are complementary and afford the Project a greater degree of
       protection than is available from the EPC Contract alone. Under both
       agreements, SWPC is obligated to notify AES Ironwood of any engineering
       or design defects that may be manifested in any of SWPC's fleet of 501Gs.
       In addition, the risk of a component failure occurring after the one year
       EPC Contract warranty is mitigated because the Projected Operating
       Results indicate the Project will have adequate revenues to insure the
       purchase of components that can be reasonably assumed to require
       replacement. Component failures associated with casualty events are
       generally covered by insurance policies. The Performance Testing Plan, as
       specified in the EPC Contract, is acceptable, customary, and should
       adequately demonstrate the Project's performance.

8.     Williams possesses the organization and personnel to execute its
       obligations under the PPA, and is familiar with the provision of fuel to,
       and purchase of electricity from, large electrical generation facilities.

9.     Williams has executed certain agreements with Texas Eastern Transmission
       Corporation ("TETCO") to provide natural gas delivery services to AES
       Ironwood. These agreements require TETCO to construct own and operate an
       approximate three-mile pipeline from the TETCO mainline to the Facility.
       Stone & Webster, however, has not independently verified the design of
       the natural gas pipeline which will interconnect the Facility to the
       interstate gas pipeline that will serve the Facility nor its proposed
       construction schedule.

10.    The Facility can feasibly be electrically integrated into the PJM system,
       and no known transmission limitations will inhibit the feasible
       evacuation of the Facility's full net capacity both under summer and
       winter conditions.

11.    Stone & Webster will independently verify the design of the make-up water
       supply pipeline when it becomes available. The proposed pipeline
       construction schedule appears reasonable and achievable. Stone & Webster
       does not know of any reason why the City of Lebanon Authority should be
       unable to perform its obligations under the ESA.


                                      B-9
<PAGE>

12.    AES Prescott, as an affiliate of AES and with the assistance of SWPC
       under the terms of the Maintenance Services Agreement, should be capable
       of operating and maintaining the Facility in accordance with standard
       industry practices.

13.    The technical requirements described in the Project Agreements are
       comprehensive, reasonable, and achievable as well as consistent within
       and between the various documents.

14.    The Phase I environmental site assessments conducted by TRC which
       indicated no significant environmental issues were performed in
       accordance with standard industry practice and their results appear
       reasonable.

15.    A majority of the Project's required permits have been acquired and the
       Project's permit acquisition plan for those permits not yet required is
       reasonable.

16.    AES Ironwood has received a determination that the Facility is an Exempt
       Wholesale Generator ("EWG") under the applicable rules of Federal Energy
       Regulatory Commission ("FERC").

17.    Assuming the Facility is constructed, operated, and maintained in
       accordance with the terms of the EPC Contract, PPA, the Operations
       Agreement, and the Maintenance Services Agreement then it is reasonable
       to assume that the Facility will be able to operate in a manner
       consistent with applicable permit limits for a period at least equal to
       the term of the Bonds.

18.    The Project's EPC Contract price is competitive relative to similar
       facilities and the Project's proposed operating and maintenance expenses
       are consistent with other comparable projects.

19.    The technical assumptions utilized in the Hagler Bailly PJM Market Study
       Analysis are reasonable.

20.    Stone & Webster reviewed the technical and commercial assumptions and the
       calculation methodology of the Project financial pro forma model. The
       technical assumptions assumed in the Projected Operating Results are
       reasonable and are consistent with the Project Agreements. The financial
       pro forma model fairly presents, in our judgment, projected revenues and
       projected expenses under the Base Case Assumptions. Therefore, the
       Projected Operating Results are a reasonable forecast of the Company's
       financial results under the Base Case Assumptions.

21.    The principal amount of the Bonds, when combined with the equity
       contributions and interest earned during the construction period, should
       be sufficient to pay the costs of constructing the project and interest
       on the Bonds through the end of the construction period.


                                      B-10
<PAGE>

22.    The projected revenues from the sale of capacity are more than adequate
       to pay the annual operating and maintenance expenses (including
       provisions for major maintenance), other operating expenses, and debt
       service based on Stone & Webster's studies and analyses of the Project
       and the assumptions set forth in this Report. The average and minimum
       debt service coverage ratios ("DSCR's") for the full term of the Bonds
       are 2.30x and 1.45x, respectively. The average and minimum DSCRs during
       the PPA period are 1.46x and 1.45x, respectively. The average and minimum
       DSCRs during the merchant period for the debt are 5.81x and 5.77x,
       respectively.

23.    Assuming deficiencies of up to 6% for heat rate and 5% for capacity, the
       average DSCRs over the term of the Bonds, after payment of the liquidated
       damages due to a failure to achieve heat rate and capacity guarantees,
       are projected to remain approximately the same as the DSCRs in the Base
       Case.


                                      B-11
<PAGE>


2.     Scope of Work

Stone & Webster was retained to perform a review of the Project in accordance
with a September 30, 1998 agreement with AES Ironwood, Inc. The review was
conducted by Stone & Webster for the purpose of producing this Report on behalf
of Lehman Brothers as Initial Purchaser of certain Rule 144A bonds to be offered
in the United States by AES Ironwood pursuant to rule 144A under the Securities
Act of 1933 as amended to finance the construction and initial start-up and
testing of the Facility, which bonds are to be issued to qualified institutional
buyers and institutional accredited investors and in offshore transactions
complying with Regulation S under the Securities Act of 1933. The scope of the
Review included the following:

       o  SWPC 501G combustion turbine proposed as the technology basis of the
          Project

       o  Projected performance of the Project

       o  Projected Operating & Maintenance ("O&M") expenses

       o  Conceptual design and interfaces of the Project

       o  Project Phase I site assessments

       o  Issued permits for the Project

       o  Technical assumptions utilized in the PJM market study of June 1,
          1999, prepared by Hagler Bailly

       o  Projected operating results in the Project financial pro forma model

Stone & Webster also reviewed the PPA, the Interconnection Agreement, the EPC
Contract, the ESA, the Maintenance Services Agreement, and the Agreement
Relating to Real Estate from a technical and economic standpoint to assess the
adequacy and reasonableness of their terms and conditions. Stone & Webster has
made no determination as to the validity and enforceability of the Project
Agreements. However, for the purposes of this Report, we have assumed the
Project Agreements will be fully enforceable in accordance with their respective
terms and that all parties will comply with the provisions of their respective
agreements.

Stone & Webster conducted a site visit on October 21, 1998 and made general
field observations, specifically the existing above ground condition of the
site. During the review, Stone & Webster reviewed Project information and
interviewed representatives of both AES and SWPC to verify the adequacy of the
Facility design and reasonableness of the technical assumptions.


                                      B-12
<PAGE>


3.     Facility Design

Stone & Webster reviewed the design of the Facility and its major components and
interface designs, as specified in Appendix A of the EPC Contract. In general,
Stone & Webster is of the opinion that the Facility design, as specified in the
EPC Contract, is in accordance with standard industry practice and that, if
designed and constructed in accordance with the EPC Contract and operated and
maintained within standard industry practices, the Facility should be capable of
meeting the net output contract requirements specified in the Projected
Operating Results.

3.1    Facility Description

The Facility is designed to have a nominal 705 MW (net) electric generating
capacity and will consist of the following major equipment: two SWPC model 501G
combustion turbines with hydrogen cooled generators, two unfired, three pressure
level reheat HRSGs, one SWPC multi-cylinder reheat condensing steam turbine with
hydrogen-cooled generator, one water cooled condenser using a forced draft
cooling tower, one integrated control system, and a 230 kV switchyard. The
combustion turbines, the steam turbine, and their associated generators will be
located indoors. The two HRSGs and associated auxiliary equipment will be
located outdoors.

The Facility will be configured as a 2 x 1 combined cycle facility designed for
base load and/or cyclic operation capable of startup and shutdown on a
dispatchable basis. The Facility can be operated at various part load conditions
and with one combustion turbine out of service.

3.2    Site Location and Description

The Project site is located in South Lebanon Township approximately one mile
east of the City of Lebanon, adjacent to the Pennsy Supply, Inc. quarry, south
of Route 422 and west of Prescott Road. The site is actively farmed and there
are no wetland resource areas on the site. The site is approximately 35 acres of
industrially zoned land and is landlocked and relatively flat. It is surrounded
by Pennsy Supply quarry tailing piles to the east and north, active quarry pits
to the west and the Conrail mainline to the south. Access to the site will be by
way of a driveway to be constructed by SWPC on Prescott Road, which is a State
Highway that runs north to south. A 50-foot easement has been obtained by AES
Ironwood from Prescott Road across the former Resco Products property that is
parallel to the Conrail tracks. A railspur for the transportation of heavy
equipment to the site will be constructed by the Project to facilitate the
delivery of heavy equipment to the site in this easement.

The October 21, 1998 site visit noted above, which also included a visit to the
WWTP, combined with a review of Project documents provided by AES formed the
basis for our opinion regarding the site. In particular, Stone & Webster relied
on the geotechnical reports prepared by Schnabel in September and October of
1998.


                                      B-13
<PAGE>

3.3    Combustion Turbine Generator

The 501G is the latest product offering from SWPC in the design evolution of the
(formerly Westinghouse) 501 series combustion turbine generator. The 501G
combines the latest advancements in SWPC's low NOx combustion technology,
compressor design, blade designs and cooling schemes, with proven fundamental
design concepts of the SWPC 501 series such as two-bearing single-shaft
construction, cold end drive, horizontally split casings, and axial exhaust. The
resulting combustion turbine is an advanced design, more powerful,
high-temperature, highly efficient, low emission producing derivative of the 501
series that is based on design concepts that have evolved with the development
of the 501 series combustion turbines. The result is a derivative that is based
on demonstrated concepts of the 501 series and improvements in design, high
temperature metallurgy, efficiency and lower emissions.

While many of the fundamental design concepts of the 501F combustion turbine
remain unchanged in the 501G, some new component designs are utilized in the
501G combustion turbine. The most significant changes are the introduction of a
steam cooled transition piece and a redesign of the first row turbine blades.
SWPC reports that the design concepts and design criteria as well as some of the
design codes used in the 501G design are the same as in the 501F and that to
produce state-of-the-art compressor and turbine designs, additional aero
industry engine-derived computer codes were used in the 501G design. These codes
were verified against test rig and combustion turbine test results, including
501F shop test results.

Stone & Webster views the 501G combustion turbine as an advancement in
high-temperature advanced technology combustion turbines for SWPC and is typical
of the normal design evolution for manufacturers. Many of the design concepts
are rooted firmly in the 501 series and are complemented by improvements which
have been tested in the 501F series with further refinements predicted from
extensive modeling or full scale testing. Although we note that the combustion
turbine does not have any commercial operating experience as an assembled unit,
the Project will benefit from the testing and monitoring of other 501G units
scheduled to begin commercial operation well before the Project's scheduled
commercial operation date.

                                      B-14
<PAGE>

SWPC provided Stone & Webster with a listing of seventeen customers that have
committed to purchasing the 501G. This listing is provided in the following
table:


<TABLE>
<CAPTION>

=======================================================================================================================
                                                   501G Customer Listing
=======================================================================================================================
                                                                                              Anticipated Commercial
   Number of Units         Name of Plant                               Owner                      Operation Date
- -----------------------------------------------------------------------------------------------------------------------
<S>       <C>           <C>                               <C>                                        <C>
          1             McIntosh #5                       City of Lakeland, Florida                  7/10/99
- -----------------------------------------------------------------------------------------------------------------------
          1             Millenium                         Millenium Power Partners                   8/20/00
                                                          (U.S. Generating Company)
- -----------------------------------------------------------------------------------------------------------------------
          2             AES Ironwood                      AES Ironwood                               5/15/01
- -----------------------------------------------------------------------------------------------------------------------
          2             Magic Valley                      Calpine Corporation                        4/01/01
- -----------------------------------------------------------------------------------------------------------------------
         11             Letters of Intent                 Confidential Clients                       Various
=======================================================================================================================
</TABLE>


The combustion turbines for the Project are currently scheduled to become the
third and fourth 501G combustion turbines in operation. An extensive testing
program for the McIntosh #5 unit began operation in April of 1999. This testing
program will include testing of the engine performance, emissions, thermal and
mechanical performance of components, and other key performance parameters with
over 2000 engine instruments. The engine will then be inspected and engine
instrumentation will be removed prior to commercial operation which will begin
in July of 1999 to satisfy summer peak power needs. This will provide
approximately 25 months of facility start up, extensive testing, and operating
experience prior to AES Ironwood's anticipated COD.

SWPC provided Stone & Webster with an overview of the test instrumentation that
will be utilized at the McIntosh Project. The operations monitoring will employ
1200 temperature, 500 pressure, and 200 strain gauges, which will monitor key
areas of the turbine. The test plan is focused on thermal and performance data
including emissions data, combustion mapping, and thermal paint testing. The
McIntosh #5 program will also include scheduled inspections after the first 200
and 400 equivalent starts to observe the durability of the unit in simple cycle
in cyclic operation. SWPC indicates that it has developed detailed risk
mitigation plans to implement the results of the McIntosh testing program,
including how to best utilize the lessons learned during this testing into the
AES Ironwood and other 501G units. The extensive testing program at the McIntosh
unit should reduce technical risks for the Project because it will provide an
opportunity to validate the 501G design through both testing and actual
operating experience prior to operating the Project's 501G units.

In addition, U. S. Generating Company's Millenium plant, a 1x1 501G combined
cycle unit is scheduled to go into base load operation in mid-2000. As a result,
there will also be approximately nine months of start-up testing amid base load
operation at that unit prior to Ironwood's scheduled COD.


                                      B-15
<PAGE>

Because the 501G combustion turbine has no commercial operating experience,
initial unit availability of the 501G may be lower in the early years of
operation than the availability of units, which use more mature technologies.
While SWPC's 501F combustion turbine has reportedly experienced availability
factors greater than 90%, Stone & Webster believes that conservative
availability assumptions should be used for early operation of the 501G. Thus,
we have assumed a conservative availability factor (85%) in the Project
financial pro forma model sensitivity case for the first two years of commercial
operation.

3.3.1  Compressor Section

The purpose of the compressor section of the combustion turbine is to produce
sufficient volumes of pressurized air to support combustion at the combustors,
provide cooling air to various components, and to generate rotational energy by
increasing mass-flow through the turbine section.

The compressor section for the 501G is composed of a 16-stage axial flow design
with a pressure ratio of approximately 19.5:1. The compressor includes
inter-stage bleeds for starting and component cooling in various down-stream
locations. While the compressor design is new, it has conventional variable
inlet guide vanes for improved low-speed surge characteristics and part load
performance. The new design also maintains the use of the inner shroud sealing
system and abradable seals currently in use on the model 501F combustion
turbines.

SWPC developed the new compressor for the 501G using three-dimensional flow
field computer codes through a licensing agreement with Rolls Royce. The new
compressor was designed with the same number of stages as in the 501F
predecessor combustion turbine, but has increased the final pressure ratio and
flow by approximately 25%. To accommodate the increase in flow, SWPC has
increased the mean diameter of the compressor stages. All rotor blades have the
same root design that were used on the 501F, which allows the blades to be
removed with the rotor in place (with the covers off) and should aid in the
maintenance of the machine.

Additionally, the rear stages of the new 501G compressor have larger diameters
than the 501F, which SWPC represents helps balance spindle thrust. The sixteen
stages of compressor blades are fabricated in two 180 degree diaphragms, same as
for the 501F, to facilitate field removal. While the new compressor design does
not have any commercial operating experience, SWPC has undertaken extensive
full-scale testing of the new compressor and the results have met SWPC's
performance expectations and demonstrated the mechanical integrity of the
compressor in a full scale testing environment.

The full scale W501ATS compressor, which is the 501G compressor with four stages
added at the rear, was extensively tested to verify its operational
characteristics, aerodynamic performance and mechanical integrity. The
compressor was instrumented with more than 500 individual sensors. The test
program included starting characteristics optimization, variable stator
optimization,


                                      B-16
<PAGE>

design point performance optimization, compressor map definition, blade
vibration and diaphragm strain gauge measurements. The test results confirmed
aerodynamic performance and mechanical predictions. Test results on selected
blades and diaphragms showed excellent correlation of vibration characteristics
between prediction and measurement.

3.3.2  Combustor Section

The combustor section of the combustion turbine mixes and burns the supplied
fuel and compressed air (from the compressor discharge) and produces hot gases
used to rotate the downstream turbine. The combustion system consists of 16
individual combustor "cans" that are mounted circumferentially around the
combustion turbine. The combustors are of the dry low NOx ("DLN") type, have
dual fuel capability, and incorporate recent design changes to eliminate the
coking problems of the 501F when firing oil. This is accomplished through the
use of dual direction water purging and a design change that incorporates an oil
piping configuration that eliminates any trapped oil in the combustor.
Additional design modifications to the dual fuel nozzles or "rockets" improve
flame temperature consistency, thereby eliminating local hot spots within the
flame region.

The latest DLN combustor is a modified version of previous DLN combustors. SWPC
reports that the new combustor has reportedly undergone successful lab tests at
the high pressure facilities located in the Arnold Engineering Development
Center of the U.S. Air Force, in Tullahoma, Tennessee, and SWPC has similar
(though not identical) DLN combustors installed at several locations.

The DLN combustion system and the selective catalytic reduction ("SCR") system
in the HRSG both act to reduce NOx emissions, which are a byproduct of the
combustion process. The system is designed to achieve 4 ppmvd on natural gas and
10 ppmvd on fuel oil, both at 15% O2 at the exhaust stack of the HRSG under base
load conditions.

Another design improvement is the addition of supplementary gas injectors in the
"top hat" section for use while firing in the gaseous fueled mode. According to
SWPC, the "top hat" section promotes better fuel-air mixing and more homogeneous
fuel-air ratios, leading to lower NOx and CO emissions with improved combustor
stability.

The length of the 501G combustor is reduced from its predecessor, the 501F. The
air-cooled aft section of the 501F combustor has been eliminated and
incorporated into a new steam cooled transition piece. This provides two
advantages: steam-cooled transition walls operate cooler than air-cooled walls;
and the air formerly used for cooling is now routed to the head end of the
combustor to make it run leaner while increasing mass flow, output and
efficiency. The new steam cooled transition piece of the 501G is made of Inconel
617 material, and is a significant change from the 501F combustion turbine. The
transition piece is also provided with cooling passages around the
circumference, and in passages on each side of weld seams. The steam


                                      B-17
<PAGE>

cooled transition piece receives steam from the intermediate pressure ("IP")
section of the three-pressure HRSG. The transition piece is over-cooled by
approximately 25% at part loads to accommodate an increase in cooling
requirements during a large load increase. The IP boiler is designed for a
capacity 30% greater than the maximum expected transition-cooling requirements.
This conservative design capacity should provide adequate margin to ensure the
security of the steam flow to the transition piece during transient load
conditions. During normal operation at base load (non-transient conditions), the
excess capacity is dumped by way of a control valve to the cold reheat system.
In order to provide even cooling over the length of the transition piece, SWPC
supplies both ends of the transition with steam and collects the heated (hotter)
steam near the center of the transition piece in a collection ring.

The burner outlet temperature of the 501G is approximately the same as the 501F
combustion turbine, but the rotor inlet temperature ("RIT") is approximately
140(degrees)F higher. This increase in rotor inlet temperature is accomplished
through the use of the aforementioned steam cooled transition piece and
improvements in turbine material and cooling improvements, which will be
discussed later in this section.

3.3.3  Turbine Section

The turbine section of the combustion turbine produces the rotational energy
required to drive the compressor and generate electrical power. This is
accomplished in the 501G combustion turbine with approximately 15% fewer turbine
parts than in the 501F.

The 501G combustion turbine has a four-stage turbine section, which incorporates
improved cooling throughout and uses its directional solidified ("DS") blades in
rotating rows one and two. The aerodynamic airfoil shapes were optimized using a
three-dimensional flow analysis.

SWPC has incorporated a series of improvements for the cooling of blades and
vanes in the turbine section which include: use of turbulators; serpentine
cooling passages; shaped film cooling holes; and a more extensive use of an
improved thermal barrier coating application.

The Row 1 vane cooling design is an enhancement of the 501F design, using three
impingement inserts in combination with an array of film-cooling holes and
trailing edge pin-fin system. All three cavities take direct compressor
discharge air to maximize the available pressure head. "Shower Head" cooling is
used at the leading edge of the row one vane, while film cooling is used at
selected pressure and suction side locations which limits vane wall thermal
gradients and external surface temperatures. SWPC represents that the low cycle
fatigue design criteria is satisfied by the control of wall gradients. The Row 2
vane cooling uses twin impingement inserts with film-cooling holes and trailing
edge pin-fin system. Row 3 vanes are convection-cooled by the admission of
cooling air into the airfoil's three-cavity multipass center. Row 4 vanes are
not internally cooled. The metal temperatures of the 501G airfoils are greater
than those of the 501F


                                      B-18
<PAGE>


combustion turbine. However, according to SWPC improvements in cooling designs
help maintain metal temperatures safely below metal temperature limits.

The first and second stage blades are manufactured from DS material, and are
cooled by a combination of convection techniques by way of multipass serpentine
passages and trailing edge cooling air ejection. While the DS blades used in
Rows 1 and 2 represent SWPC's first commercial use of this material, this
technology is not new. Rolls Royce, the manufacturer of the SWPC DS blades, has
successfully manufactured DS blades for use in several other manufacturer's
combustion turbines.

Similar to the analysis of the compressor blades and vanes, the design of the
turbine blades and vanes uses three-dimensional flow analysis developed by Rolls
Royce for the development and verification of the aerodynamic airfoil shapes.

3.3.4  Risk Mitigation

SWPC has followed a conservative design process for the 501G combustion turbine,
executed a risk analysis as part of a plan designed to ensure mechanical
integrity, and has invested in a complete set of "risk parts" for the combustion
turbine's entire gas path. This set of "risk parts" alone amounts to an
investment by SWPC of over $10,000,000. This set of risk parts is in addition to
the long-term spare parts program that is included pursuant to the Maintenance
Services Agreement. The risk parts include the compressor blades and diaphragms,
the turbine blades and vane segments, and the combustor system (nozzles,
baskets, and transitions). This investment is significant not only in monetary
terms, but also in terms of unit availability and manufacturer commitment. The
full set of gas path risk parts made available by SWPC and the Maintenance
Services Agreement long term spare parts program will minimize the duration of
any unscheduled combustion turbine-related outages that require the replacement
of parts by having the most commonly replaced parts readily available.

SWPC's risk mitigation program for the 501G Program goes beyond what is
typically utilized during the introduction of a manufacturer's latest model
design. It is strongly supported by a dedicated manufacturing team with stated
component procurement plans, an established parts supply chain, and a proactive
monitoring program designed to quickly incorporate design changes into the parts
inventory program.

3.3.5  CTG Conclusions

A sustained period of operation at full load conditions followed by an
inspection of the combustion turbines is necessary to predict with any certainty
the types of startup and operational problems, if any, that may be encountered
with the 501Gs. However, SWPC has made significant financial and organizational
investments in the 501G technology. Stone & Webster


                                      B-19
<PAGE>

believes that SWPC has the resources and capabilities to resolve any problems
that may arise with the 501G.

Because the 501G combustion turbine has no commercial operating experience
initial unit availability of the 501G may be lower in the early years of
operation than the availability of units using mature technologies. While SWPC's
501F combustion turbine has reportedly experienced availability factors greater
than 90%, Stone & Webster believes that conservative availability assumptions
should be used for early operation of the 501G. It is not uncommon in the
industry for new combustion turbines to experience availability factors during
the first years of operation in the mid-eighty percent range. Thus, we have
assumed a conservative availability factor (85%) in the Project financial pro
forma model sensitivity case for the first two years of commercial operation.

3.4    Heat Recovery Steam Generator

Stone & Webster reviewed the functional specification and scope of supply
provided in the EPC Contract and understands that Hangjung has been selected as
the HRSG vendor and that the detailed design specifications will be reviewed by
Stone & Webster. The scope of supply for the HRSG includes the HRSG internals,
ducting, and insulation, the stack, the SCR, the ammonia storage system, the
continuous emissions monitoring system ("CEMS"), and the associated piping,
valves and instrumentation. The CEMS scope includes oxygen, CO, and NOx
analyzers.

The functional specification describes the two HRSG's as being of the horizontal
gas path (vertical tubes), natural water circulation, three pressure level,
reheat type. Each HRSG will have high pressure ("HP"), IP, and low pressure
("LP") superheaters, reheaters, economizers, and evaporator sections. Each HRSG
will be equipped with an SCR system to reduce the stack NOx emission levels and
a spool piece for the possible future addition of a CO catalyst. The HRSGs will
have no duct firing capability. The HRSGs will be designed in accordance with
the ASME Code Section I for pressure parts and ANSI/ASME B31.1 for power piping.

Stone & Webster is of the opinion that HRSG scope description is suitable for
the Project and in accordance with standard industry practice.

3.5    Steam Turbine

The steam turbine will be a model 2F32 two case tandem compound design with a
side exhaust double flow low pressure element. The steam turbine will be
directly connected by rigid coupling to a hydrogen inner-cooled generator, which
produces electrical power.

The steam turbine will consist of a primary turbine inlet, combined HP/IP
turbine, and the double flow LP turbine. The two primary steam supply sources to
the turbine are main and reheat steam. The steam flow to the turbine is
controlled by the main steam and reheat steam inlet valves. The


                                      B-20
<PAGE>

HP/IP turbine receives steam from the main steam and reheat steam supply and
converts it to rotational power to drive the generator. The LP turbine receives
steam from the IP exhaust by way of the crossover piping and converts it to
rotational power to drive the generator. The last stage blade design is a model
72R. This design has a 32.1 inch vane section and a 63.4 square foot exhaust
annulus area.

With respect to operational experience, SWPC provided a sample list showing four
existing units of similar configuration but with different loadings or ratings.
SWPC reports an exhaust flow rate of 1,398,070 lb/hr, which leads Stone &
Webster to believe that the exhaust velocity would approach 786 ft/sec. This
rate is within SWPC's experience and is considered by Stone & Webster to be
acceptable. Stone & Webster is of the opinion that the steam turbine design is
acceptable and in accordance with standard industry practice.

3.6    Electric Generator

The three electric generators are designated by SWPC as model 2-97x134. The
generators will be hydrogen inner-cooled synchronous 3600 rpm, 60 Hz machines
rated at 288,000 kVA at 16 kV. The generators will be designed for a leading
power factor of 0.95 and a 0.90 lagging power factor at the generator terminals
at 60 psig hydrogen gas pressure. The generators will have Class F insulation
with Class B temperature rise for both the stator and the rotor. The generators
will have a short circuit ratio of 0.53 at nominal capacity and are to be
fabricated in accordance with ANSI standards C50.10, C50.13, and C50.14, as
appropriate.

Despite the fact that the generator, as described in the EPC Contract, utilizes
a design with little operating experience, it appears to be sized properly. The
proposed generator was first utilized on the Hines Energy Project for Florida
Power Corp. (2 x 2 x 1 - combined cycle) and is expected to begin commissioning
in early 1999. According to SWPC, thirteen generators of this design have been
sold. The generator design (2-97x135) from which the proposed generator was
developed was first introduced in 1958 and was offered until 1975. A total of 26
units were sold ranging from 200 MVA to 270 MVA. Stone & Webster is of the
opinion that the generator design is acceptable and in accordance with standard
industry practice.

3.7    Balance of Plant Systems

Stone & Webster reviewed the general configuration of the Facility balance of
plant ("BOP") systems identified in this section. These systems although
important do not generally take on as high a degree of risk significance as the
main power island, which consists of the combustion turbines, HRSGs, and the
steam turbine. Stone & Webster's BOP system review focused on ensuring that the
specific system designs were consistent with standard industry practice.

As is typical of a project at this phase in design, the detailed system and
component technical information that is developed during the detailed design
phase and is required to independently verify a system's capabilities was not
available for Stone & Webster's review. The conceptual


                                      B-21
<PAGE>

description of the BOP systems and Stone & Webster's opinions are described in
the following sections.

In general, Stone & Webster is of the opinion that the BOP systems described
below are consistent with standard industry practice and any individual issues
identified during our review are presented in their respective sections. AES
Ironwood has informed us that after the individual system and component vendors
have been selected and the individual system designs and component
specifications are available, the Project will conduct a detailed BOP design
review to ensure compliance.

3.7.1  Condensate and Feedwater System

The condensate and feedwater systems are auxiliary systems supporting the HRSG.
Condensate is collected in the hotwell of the condenser and pumped by two of
three 50% capacity pumps to the suction side of the feedwater pumps. Each HRSG
is equipped with one 100% capacity feedwater pump that delivers feedwater to the
HRSG. The feedwater pumps will be either split-case or segmented ring section
design. The pump is electric motor driven and is located adjacent to the HRSG. A
demineralized condensate water storage tank is provided to allow for 12 hours of
base load operation.

The condenser will have titanium tubes and will consist of two segregate shells
with the hotwells connected by an equilibrium line. The condenser will be
designed to accommodate the exhaust from the steam turbine plus the
miscellaneous drains from the steam system and to allow for 100% steam bypass of
the steam turbine.

The single feedwater pumping system configuration proposed for the Project is
becoming widely used in combined cycle plants, as the cost of the
reconfiguration generally outweighs the assumed benefit. Stone & Webster has
been informed that the single pump configuration is part of the SWPC reference
plant design. The current configuration is such that the failure of either of
the feedwater pumps will result in shutting down the corresponding combustion
turbine, its associated HRSG, and the power loss associated with losing
approximately half of the steam input to the steam turbine. Stone & Webster has
recommended increased feedwater pump redundancy. As a result, the Project has
committed to carrying one complete spare pump, including casing in store plus
normal spares. This will reduce the equipment outage and downtime associated
with a feedpump failure.

3.7.2  Cycle Makeup System

The cycle makeup system supplies and stores demineralized water for makeup to
the HRSG and also supplies water for the combustion turbine water injection and
water washing. The system consists of one condensate storage tank, two 100%
capacity cycle makeup pumps designed for normal makeup to the cycle when water
is not being injected into the combustion turbine, and one


                                      B-22
<PAGE>

100% capacity pump designed to handle makeup to the unit including water
injection to the combustion turbine.

The water supply to the system is provided from the cycle makeup treatment
system. The demineralized water from the mixed bed exchangers discharges to the
condensate storage tank. Two 100% capacity cycle makeup pumps are provided for
normal system operations without water injection to the combustion turbine. The
cycle makeup pumps take suction from the condensate storage tank. An automatic
recirculation control valve is provided for each cycle makeup pump for minimum
flow recirculation to prevent overheating and cavitating the pumps during
startup and low flow operation.

The system is designed to provide makeup water under all normal operating
conditions. The two 100% cycle makeup pumps are sized to provide adequate flow
and pressure for normal system operations. The single 100% capacity cycle makeup
pump is designed to provide adequate water flow and pressure. The intention is
to use the pump during combustion turbine water injection operation.

3.7.3  Condenser Air Removal System

The condenser air removal system evacuates the condenser steam space of
noncondensable gases during steam turbine generator operation and rapidly
reduces the condenser pressure from atmospheric pressure during plant startup.
The vacuum breaker valve allows air to enter the condenser to reduce the coast
down time of the steam turbine generator after shutdown. The system will consist
of two stage, twin element steam jet air ejectors with inter and after
condensers for holding operation, a hogging steam jet air ejector for startup,
and one vacuum breaker valve.

3.7.4  Raw Water System

The Facility raw water requirements will be supplied from the Pennsy Supply
quarry pits located adjacent to the site and the WWTP located approximately 6.5
miles west of the site. A waterline and pumping equipment will be constructed as
part of the EPC Contract will transport the raw water from the Pennsy Supply
quarry pits. The WWTP supply will be transported by way of a pumping station and
an 18-inch diameter pipeline.

The raw water system provides water for cooling tower makeup, cycle makeup,
evaporative cooler supply, fire water and miscellaneous plant services such as
washdown. The raw water system consists of the following major components:
quarry water supply, WWTP water supply, two 100% (1500 gpm each) raw water
forwarding pumps, raw water/fire water storage tank, and the associated piping,
valves, and instrumentation.


                                      B-23
<PAGE>

3.7.5  Circulating Water System

The circulating water system will consist of two 50% capacity circulating water
pumps, a double shell water-cooled condenser, and a direct contact, mechanical
draft cooling tower. Water from the cooling tower basin will be pumped by the
circulating water pumps to the condenser and then to the cooling tower in a
single pressurized piping circuit. The heated cooling water will be cooled in a
mechanical draft, direct contact cooling tower. The underground circulating
water piping will be welded steel pipe with an internal epoxy coating and an
external asphalt blanket and the above ground piping will be uncoated carbon
steel.

The circulating water pumps will be designed in accordance with requirements of
the Hydraulic Institute Standards, and the condenser will be designed in
accordance with the requirements of the Heat Exchange Institute Standards for
Steam Surface Condensers. The design capacity of each circulating water pump
will be based on 50% of the circulating water flow at the contract plant
performance guarantee points, rounded to the next higher 1000 gpm.

The cooling tower will be a wood frame, counterflow mechanical draft cooling
tower constructed on top of the concrete cooling tower basin or at SWPC's option
a concrete tower structure may be used. Each of the two pumps takes suction from
the cooling tower basin and discharges into a common circulating water header.
This main header is divided into smaller headers, which feed the condenser and
auxiliary cooling water system. The heated discharge from each header is
recombined and the heated water is returned to the cooling tower. At the cooling
tower, the return line is divided into equally sized lines, each of which
services one cooling tower cell. The circulating water pump pit will be located
at the end of the basin. A trash rack, removable for cleaning, will be located
upstream of the circulating water pump pit to protect the circulating water
pumps from debris in the cooling tower basin. The tower also includes a fire
protection system and a lightning protection system.

3.7.6  Auxiliary Cooling Water System

The auxiliary closed loop cooling water system will supply cooling water for
various equipment heat exchangers. The system will consist of two 100% capacity
auxiliary cooling pumps, two plate and frame type closed cooling water heat
exchangers, and the associated piping, valves, piping and instrumentation.

The auxiliary cooling water pumps supply water to the Facility's various cooling
loads. The heated cooling water flows to the closed cooling water heat
exchanger, which is cooled by circulating water from the open loop. The loop is
completed as the cooled water flows to the suction of the auxiliary cooling
pumps.


                                      B-24
<PAGE>

3.7.7  Fire Protection Systems

Fire protection is provided by a ring header, hydrants and hose stations
supplied from the raw/fire water tank. The fire protection system gives a visual
indication of actuation at the local control panel. There are two independent
systems. An automatically actuated dry chemical type system is provided for the
exhaust bearing area of the turbine. The system consists of temperature sensing
devices, spray nozzles, dry chemical tank, and interconnecting piping and
wiring. In accordance with the U.S. National Fire Protection Agency ("NFPA")
standards there is an FM-200 based fire protection system for total flooding
protection of the turbine enclosure and the electrical and control units. .

3.7.8  Wastewater System

The Facility wastewater system will be designed as a zero discharge system
("ZDS") to eliminate liquid waste streams. All treated wastewater to the
Facility will be discharged as cooling tower evaporation or vapor through
Facility vents. The solids, in the waste water or introduced as chemical
additives, will be removed by the system which will first concentrate the waste
and then produce a chemical precipitate which is filtered to dryness for
ultimate disposal in a landfill. AES Ironwood represents that the sludge, which
has a high proportion of calcium carbonate, has commercial use as feed stock for
FGD systems. AES Ironwood is currently negotiating a commercial agreement to
sell the sludge and avoid landfilling.

Stone & Webster understands that the Project is still evaluating options for the
design of the ZDS and that SWPC has offered the Project alternative ZDS systems.
The maximum requirements for the ZDS system will be experienced when the
Facility is operating at full load on fuel oil during the winter months. The
alternatives being evaluated depend on whether the proposed design is based on
normal gas operations or on oil operation. If the Project accepts the gas
option, then it will be responsible for obtaining portable demineralizer
trailers to meet the oil fired case requirements. The Project is examining
proposals for portable demineralizers with second pass RO units. These proposals
would ensure at least 100 hours operation per demineralizer trailer between
regenerations. The Project expects to resolve this issue in early 1999. The
Project has been advised by SWPC that the net power guarantee includes the net
parasitic load for the ZDS. AES Ironwood represents that once a system design
has been selected, it will be reviewed to ensure operational conformance.

Stone & Webster also understands that SWPC has proposed the use of one 100%
brine concentrator and one 100% crystalizer. The vendor selection of these two
key components should emphasize equipment reliability due to the lack of
redundancy in this key system.


                                      B-25
<PAGE>

3.7.9  Compressed Air System

The compressed air system will supply compressed air at the required capacity
and pressure for service air and instrument air requirements. The instrument air
system supplies dry instrument quality air at the required pressure and capacity
to all pneumatic controls, transmitters, instruments, and valve operators. The
system will consist of two 100% capacity, air cooled, motor driven air
compressors, one service air receiver, one instrument air receiver, and two 100%
skid mounted refrigeration type air dryers, with electric motor driver and two
coalescing filters for each dryer. The instrument air will be designed to
conform to the Instrument Society of America ("ISA") Quality Standards for
Instrument Air. During normal operation, either air compressor can provide
compressed air to the system.

3.7.10 Compressed Gas Storage System

The compressed gas storage system will consist of the hydrogen gas system, the
carbon dioxide system, and the nitrogen system. The hydrogen system supplies
hydrogen gas to the hydrogen cooled generators. The carbon dioxide system stores
and transfers carbon dioxide gas to the generator cooling and purge systems for
generator purging. The nitrogen system supplies nitrogen for inerting the HRSGs
and main cycle piping during an extended outage. The compressed gas system will
consist of a hydrogen tube trailer, hydrogen valve manifold, carbon dioxide
valve manifold, a nitrogen valve manifold, and the associated piping and
instrumentation.

3.7.11 Ammonia Storage and Forwarding System

The ammonia storage and forwarding system will store and supply ammonia for the
SCR. The system will consist of two 10,000 gallon aqueous ammonia storage tanks,
one for each HRSG, that provide approximately a seven day supply of ammonia, two
ammonia forwarding pumps, an ammonia injection skid, and associated piping and
instrumentation.

3.8    Fuel Systems

The Facility will be designed with natural gas fuel as the primary fuel for the
combustion turbines with fuel oil as the backup fuel supply. It is projected
that the Facility will operate a majority of the time on natural gas but may
operate up to 31 days per year on fuel oil pursuant to the terms of the PPA. The
Project pro forma financial model assumes 12 days operation on fuel oil during
the PPA period based on estimates by CC Pace, the Project's independent fuel
consultant. The PPA incorporates the natural gas and fuel oil specifications
consistent with EPC Contract specifications.

With respect to natural gas pressure, the EPC Contract assumes that the natural
gas line is able to supply a minimum of 450 psig at the Facility boundary. The
PPA defines natural gas as being at


                                      B-26
<PAGE>

a pressure equal to the pressure on the Texas Eastern pipeline, data from the
pipeline demonstrates that the pressure is generally in excess of 700 psig.

3.8.1  Fuel Gas System

The fuel gas system receives natural gas supplied from the natural gas supply
pipeline at the Facility boundary and transports it to the combustion turbines.
The system will consist of the fuel gas filter separators provided locally at
each combustion turbine, fuel gas heater, knock out drums, and associated piping
and instrumentation.

Natural gas will be supplied to the system by a natural gas pipeline to a single
connection located at the Facility boundary. A shutoff valve and duplex strainer
will be provided in the gas supply piping. Individual fuel gas heaters will be
provided for heating the fuel gas supply to the respective combustion turbines.
Natural gas fuel will be heated using IP feedwater to approximately
440(degrees)F. A liquid separator/leak detector will be installed downstream of
the fuel gas heater to detect any water in the gas supply resulting from a
leaking fuel gas preheater. On detection of fuel gas heater leakage, the
isolation valves will close and a bypass valve will open automatically to
isolate and bypass the fuel gas heater. Control valves provided with the
combustion turbine packages will regulate gas pressure to the combustion turbine
fuel nozzles. A valving arrangement will provide positive isolation of the fuel
supply system at the combustion turbine. The fuel gas supply pressure required
for the combustion turbines will be at least 650 psig at the combustion turbine
connection. If required, the combustion turbines can be switched over from
natural gas to fuel oil online without shutting down the Facility.

3.8.2  Fuel Oil System

The fuel oil system receives, stores, and transports fuel oil for operating the
combustion turbines. The fuel oil system consists of one 2,300,000 gallon fixed
roof fuel oil storage tank on a ring wall foundation, a fuel oil tank truck
unloading area, a fuel oil truck unloading skid, air eliminators, and
accessories including flame arrestor with conservation vent, fuel oil metering
skid, and a lined berm containment.

Fuel oil will be delivered to the site by truck and unloaded at the unloading
station to the fuel oil storage tank. Duplex fuel oil strainers will be provided
at the inlet to the unloading station. An air eliminator and flow totalizing
meter will be provided at the discharge of the unloading station to verify fuel
oil deliveries. The fuel oil storage tank will be a cone roof, double wall with
double bottom carbon steel tank on a ring wall foundation. The fuel oil storage
tank will be constructed in accordance with American Petroleum Institute ("API")
Standard 650.

Fuel oil will be supplied to the fuel oil forwarding pumps from the fuel oil
storage tank. The fuel oil forwarding system will be equipped with two 100%
capacity forwarding pumps. Fuel oil pressure and flow to the combustion turbines
will be controlled by a recirculation valve in the


                                      B-27
<PAGE>

combustion turbine fuel oil skid which will control the fuel oil supply pressure
by recirculating fuel back to the fuel oil storage tank.

3.9    Electrical Systems

Stone & Webster reviewed the general configuration of the Facility electrical
systems identified in this section. Stone & Webster's electrical system review
focused on ensuring that the individual system designs were consistent with
standard industry practice. As is typical of a project at this phase of design,
the detailed system and component technical information that is developed during
the detailed design phase and is required to independently verify a systems
capabilities was not available for Stone & Webster's review. The conceptual
description of the electrical systems as well as Stone & Webster findings are
provided in the following sections.

In general, Stone & Webster is of the opinion that the electrical systems
described below are consistent with standard industry practice. AES Ironwood has
stated that when the individual system and component vendors have been selected
and the individual system designs and component specifications are available, a
design review will be conducted by the Project to ensure compliance.

3.9.1  Normal Station Service Power

Two station auxiliary transformers will provide power from the switchyard to the
Facility auxiliary loads. Station auxiliary transformers step down the voltage
from 230 kV to 6.9 kV to 480 V and lower voltage levels suitable for equipment
needs. A medium voltage switchgear bus will supply power to medium voltage
motors, and medium to low voltage transformers. These transformers feed low
voltage switchgear, motor control centers, and other loads.

3.9.2  Emergency Power

Emergency power systems also exist to assist Facility operations. The emergency
systems include uninterruptible power supplies and direct current ("DC") power.
Uninterruptible power and DC/battery power are provided for equipment that must
operate under all conditions, such as lube oil pumps and turning gear to ensure
a proper cool down process of the turbines during an emergency trip. The
Facility does not have black start capability. Startup of the Facility is by way
of electrical backfeed through the station auxiliary transformer off the 230 kV
utility grid system.

3.10     Switchyard

Electrical power generated through the combustion turbine and steam turbine
generators at 16 kV is transformed to 230 kV for delivery to the switchyard. The
Facility will electrically interconnect with the PJM electrical system through
an existing MET-ED 230 kV transmission line located


                                      B-28
<PAGE>

approximately 0.25 mile to the west of the Facility which will tie into the
Facility's switchyard.

Three main transformers will be provided for this service. The combustion
turbine generators and the steam turbine generator will be connected to its own
two winding, oil filled step up transformer which increases the voltage from the
generator terminals to the interconnecting voltage at the high side terminals.
Synchronization and protection of the combustion turbine generator and the steam
turbine generator are achieved by power circuit breakers in the switchyard.
These circuit breakers isolate the power generating station from the
interconnecting system. The combustion turbine generators and steam turbine
generator will be connected to their step-up transformers by an isolated phase
bus duct.

The switchyard will have a 230 kV conventional, outdoor, open air, radial design
featuring a provision for two outgoing transmission lines. The switchyard will
extend from the high voltage terminals of the generator step-up transformers and
station auxiliary transformers to the interface with MET-ED's two outgoing
transmission circuits. The transmission line protective relays and the remote
terminal units ("RTUs") that will interface with the Transmission/Distribution
Control Center and the Energy Control Center will be provided by MET-ED. This
equipment will be installed in the switchyard control building.

The EPC Contract states that optional switchyard arrangements, metering, and
protective relaying schemes can be provided and that SWPC will work with the
Project and MET-ED to establish the specific requirements for the switchyard and
Facility interfaces with MET-ED. The switchyard requirements will also be
further defined as part of the Project Interconnection Agreement, which is
currently under negotiation between AES Ironwood and GPU Energy, Inc. ("GPU").

3.11   Instrument and Control Systems

Stone & Webster understands that the original Project instrument and control
system design was based on the Westinghouse Distributed Processing Family
("WDPF") Control System. Since the Westinghouse Power Generation acquisition by
Siemens, SWPC now utilizes and would prefer to provide to the Facility a Siemens
Control System. Stone & Webster believes that either of these two systems would
be acceptable and in accordance with standard industry practice.

3.12   Civil and Structural Design

The Project's civil and structural design parameters have been appropriately
specified in accordance with the geotechnical investigations conducted on-site
to date, as well as applicable engineering codes and standards relating to the
type of construction proposed at the site. It is noted that SWPC has accepted
the risk of any additional foundation requirements as necessary based on a
detailed geotechnical investigation to be performed during the detailed design
phase of the Project. The structural design criteria outlined in the EPC
Contract appear adequate to comply with the Project requirements. The materials
of construction specified in the building


                                      B-29
<PAGE>

finish schedule are appropriate for the intended application. The minimum
required strength of materials, stipulated in the design criteria, are
consistent with industry standards. The established loadings and maximum design
conditions comply with the referenced codes, site development requirements and
foundation design criteria. Stone & Webster are of the opinion that the
structural design is reasonable and adequate for operation of the Facility as
contemplated in the Project Agreements.

3.12.1 Geotechnical Evaluation

The bedrock units beneath the site are dolomite and limestone. Sinkhole
development has been identified near the site area. Laboratory testing was
performed to classify the soils. The geotechnical investigation indicated that
the subsurface soils are very soft to very stiff residual soils, which are
overly poor to moderate quality dolomite bedrock. The residual soils are
classified as high plasticity sandy clays and silts. The thickness of the
residual soil varies; however, the soil deposit is generally about 20 feet deep
in the site area. The exploration borings and resistivity surveys indicate that
the underlying bedrock is highly variable in quality and depth. The bedrock
surface is expected to be quite variable and have high points, due to the
weathering characteristics of the carbonate bedrock units. Exploration borings
and probe holes were drilled in suspect solution areas that were identified by
the resistivity survey. No large underground solution cavities or clay filled
features were identified to the depths explored at the location of critical
structures.

Blasting operations at the Pennsy Supply quarry adjacent to the site can be
performed within 25 feet of the property line. Pennsylvania law limits the
blasting. In addition under the EPC Contract, SWPC acknowledges that prior to
the execution of the EPC Contract SWPC has made a complete and careful
examination of the nature and character of the soils and terrain of the site
that might affect SWPC's ability to construct the Facility.

Stone & Webster believes that the exploration and testing programs were
conducted in accordance with good engineering practice and were appropriate for
the planned Facility and anticipated site conditions. Stone & Webster is of the
opinion that the Project site is suitable for the Facility provided that the
site construction is performed incorporating the recommendations of the Schnabel
Report of September 1998. These recommendations are discussed in Section 3.12.5
of this report.

3.12.2 Groundwater

Groundwater was not encountered during the drilling at the test boring
locations. Based on these observations, the groundwater level is believed to be
below the depth of the excavations proposed for this Project. Groundwater is
present at a depth below the site and dewatering operations at the adjacent
Penney Supply quarry presently controls the level.


                                      B-30
<PAGE>

3.12.3 Water Supply

Stone & Webster reviewed a number of documents in its evaluation of the
availability of raw water to the Project including: the approvals from the
Susquehanna and Delaware River Basin Commission, the Final Hydrologic Analysis,
Availability of Groundwater from the Pennsy Supply Quarry, Proposed Ironwood
Power Plant, Lebanon, Pennsylvania by Schnabel Engineering Associates, February
26, 1998, and the Application for Water Withdrawal for AES Ironwood Power Plant,
Submitted to the Delaware River Basin Commission and the Susquehanna River
Basin, by TRC Environmental Corporation, April, 1998.

The make-up water supply for the Project will be obtained from the WWTP and from
the current dewatering operations at the adjacent Pennsy Supply quarry. Under
normal operating conditions, 1.44 MGD of water from the WWTP will be pumped to
the Facility through a pipeline. The remaining 2.16 MGD of water required by the
Facility will be obtained from the quarry dewatering operations. When the
Facility is operating on fuel oil, 2.16 MGD of water may be diverted from the
WWTP and the remainder 2.16 MGD will be obtained from the quarry dewatering
operations.

A review of documents provided to Stone & Webster indicates that an adequate
make-up water supply is available to meet the Facility generation demands. The
split for providing make-up water from both the WWTP and the Pennsy quarry
satisfies the river basin commissions environmental requirements. Approval has
been obtained from the Delaware River Basin Commission on April 24, 1998 and the
Susquehanna River Basin Commission on June 9, 1998 for this proposed make-up
water supply approach.

Should quarry operations cease in the future or supply from the WWTP need
adjustment, an adequate make-up water supply could be obtained from groundwater
sources at or near the site or pumped from a flooded quarry. New agreements with
the commissions would have to be worked out at that time and are considered by
Stone & Webster to be attainable, if they are required.

3.12.4 Site Grading and Drainage System

The site grading and drainage system will be designed to comply with all
applicable federal, regional, and local regulations. Topographic modifications
to the site area may be required to provide positive overall drainage. Surface
drainage onsite will consist of overland and open channel flow. Channels and
ditches will generally be trapezoidal in cross section, of sufficient width to
facilitate easy cleaning, and mildly sloping so that erosion is prevented. The
storm drainage system will be designed for a rainfall intensity of five inches
per hour. Site specific drainage facilities will be designed for the flow
resulting from a 25 year rainfall or regional and local code requirements,
whichever is greater. The Facility main complex area will be moderately graded
for effective drainage.


                                      B-31
<PAGE>

3.12.5 Foundations

The site is considered suitable for development of the Project. The proposed
structures can be placed on mat or spread foundations. Recommendations are
provided in the Schnabel Report for deep and shallow foundation systems. The
Schnabel Report recommends that foundations for the larger, heavier structures
be supported on compacted dense graded crushed stone structural fill. All
residual soil and boulders should be removed beneath the foundation area.
Placement of the structural fill will start at the contact with the weathered
bedrock or very hard residual soil. An allowable bearing pressure of 10,000 psf
is expected for structures supported in this manner. Adequate quantities of
quality structural fill materials are available from the rock quarries in the
vicinity of the site.

The support buildings and other lightly loaded structures can be supported on
spread foundations on suitable stiff to hard natural soils or compacted fill,
using an allowable bearing pressure of at least 2,000 psf. The above ground
storage tanks can be supported on the stiff to hard residual soils, weathered
rock, or structural fill.

The exploration program indicates that some rock excavation may be required for
installation of the circulating water lines. The Schnabel Report also includes
recommendations for site preparation and inspections that should be performed
beneath critical structures to preclude development over an area of potential
solution activity. Subsequent to the date of the Schnabel Report, SWPC obtained
additional data on quarry blasting operations and has indicated that it is
revising its foundation design criteria to reflect that additional data.

3.12.6 Stack

The common stack height will be 175 feet and is to be constructed in accordance
with ASME/ANSI standards and will be made from carbon steel. The location of
test ports and sampling platform will meet USEPA siting criteria of 40 CFR 60.

3.13   Interconnections

3.13.1 Fuel Interconnection

The natural gas fuel supply to the Facility will be transported by way of a
pipeline that will be designed to supply a minimum of 700 psig at the Facility
boundary as discussed in Section 3.8 of this Report. Fuel will be supplied to
the Facility by Williams in accordance with the PPA as discussed in Section 5 of
this Report. Williams is responsible for the construction of all gas
interconnection and delivery facilities necessary for delivery of natural gas.
Pipeline permitting, design, and construction is also the responsibility of
Williams. The fuel oil will be supplied by truck, and a two-day supply will be
stored in the Facility's fuel oil storage tank.


                                      B-32
<PAGE>

Williams has executed certain agreements with TETCO to provide natural gas
delivery services to the Facility. These agreements require TETCO to construct
own and operate an approximate three-mile pipeline from the TETCO mainline to
the Facility. Under these agreements, TETCO is required to have the lateral
completed by September 1, 2000. Stone & Webster has not independently verified
the design of the pipeline, however we know of no reason why Williams should be
unable to perform its obligations under the PPA.

3.13.2 Electrical Interconnection

The Project electrical interconnection design was previously discussed in the
Switchyard Section of this Report. In addition, Stone & Webster reviewed
available information to assess the general feasibility (from an electrical
standpoint) of integrating the Project into the PJM power transmission system.
The review focused on assessing whether there were additional steady-state
transmission constraints, which could be attributed to the Project. The review
relied primarily on information in the public domain provided by the
Mid-Atlantic Area Council ("MAAC") reliability council of the North American
Electric Reliability Council ("NERC") in filings before the FERC. The MAAC
region consists of 15 full time members and 31 associate members serving over 22
million people in a 48,700 square-mile area. The region includes all of Delaware
and the District of Columbia, major portions of Pennsylvania, New Jersey, and
Maryland, and a small part of Virginia. All utilities in the PJM system are a
part of MAAC. In particular, the following information, submitted to the FERC as
part of the 1998 Form 715 filing, was reviewed:

       o      Transmission planning reliability criteria of the MAAC region
              (Part 4 of Form 715)

       o      Transmission planning assessment practices of MAAC (Part 5 of Form
              715)

       o      Evaluation of transmission system performance of the MAAC system
              (Part 6 of Form 715)

       o      Transmission planning reliability criteria of the GPU utilities
              (Part 4 of Form 715)

       o      Transmission planning assessment practices of the GPU utilities
              (Part 5 of Form 715)

       o      Evaluation of transmission system performance of the GPU utility
              system (Part 6 of Form 715)

       o      Load flow simulations of the MAAC system for the following
              conditions: (1) 1998 summer, (2) 1998/99 winter, (3) 1999 summer,
              (4) 1999/2000 winter, (5) 2002 summer, (6) 2002/03 winter, (7)
              2007 summer


                                      B-33
<PAGE>

Stone & Webster also reviewed a report titled "Reliability Assessment
1998-2007", prepared by NERC and dated September, 1998, and a letter report from
GPU to AES Ironwood dated February 4, 1999, regarding the results of system
studies (the "System Study Report").

The Project was modeled by GPU in the planning of its transmission system for
the period 1998-2007 and simulated in all load flow cases for years 2002 and
beyond, but not before, since: (1) FERC Form 715 instructions explicitly
indicate that load flow cases that are submitted as part of the filing should be
those "regularly used by the utility in its own planning", and (2) the Project
is scheduled to come on-line in 2001. Thus, 2002 is the first year in which the
Project appears in the simulations.

The Project is modeled in the load flow cases as three separate generators (at
buses 1736 "AES-GEN1", 1737 "AES-GEN2", and 1738 "AES-GEN3", all at 230 kV).
These buses are in turn connected to the Prescott 230 kV bus, and from there to
the South Lebanon and Jonestown 230 kV buses (1163 and 1175, respectively). In
all cases (i.e., summer and winter), each unit is modeled as generating 212 MW,
for a combined production of 636 MW. The generators are in area 27 of the load
flow (area "MET-ED"), which in year 2002 exports about 246 MW.

GPU has represented that it has confirmed that the transmission system will
accept the Facility output of up to 662 MW (summer) and 797 MW (winter).

Based on this representation, Stone & Webster is of the opinion that the Project
can be feasibly integrated into the PJM system and that no known transmission
limitations will inhibit the feasible evacuation of the Project's full net
capacity both under summer and winter conditions.

3.13.3 Water Interconnection

The Project has agreements in place to draw water for cooling the Facility from
two independent sources. The Pennsy Supply quarry, located directly adjacent to
the Project site on Prescott Road, and an agreement with the City of Lebanon
Authority to use treated effluent water from their facility, located on Ridge
View Road. Access to both water sources will be designed and constructed to
serve the full Facility needs from either or both sources. An approximately 6.5
mile pipeline will be designed and constructed to transport the water from the
WWTP to the Facility.

In order to construct the pipeline, which will be owned and operated by the
Authority, Rights-of-Way ("ROW") must be acquired from eleven landowners. The
ROWs provide the Project with the permission to utilize the various landowners'
property to construct the pipeline beneath the surface of the property. Most of
the ROWs are represented to be within an already-existing utility easement.
Gannett Fleming, Inc. has surveyed all the properties and the Project has
secured ten of the eleven ROWs. The last ROW is expected to be secured in June
1999.


                                      B-34
<PAGE>


Applications for the road crossings, county occupancy permits, and railroad
crossings have been submitted and are currently awaiting approval.

Stone & Webster will independently verify the design of the pipeline when it
becomes available. The proposed construction schedule appears to be reasonable
and achievable. We do not know of any reason why the Authority should be unable
to perform its obligations under the ESA.


                                      B-35
<PAGE>


4.     Environmental and Permitting

4.1    Environmental Site Assessment

Stone & Webster reviewed the Environmental Site Assessment of Martin/Ziegler
Property and the Environmental Site Assessment and Preliminary Asbestos Survey
of RESCO Products Property by TRC Environmental Corporation, of March 1998 and
April 1998. The assessment for the Martin property revealed no evidence of
recognized concerns to the subject property. The only environmental condition
identified for the RESCO Products property is the presence of asbestos in two
roofing materials; the tar coating of the Butler Building/add-on roof and the
roof tar paper of a small attached shed at the rear of the Butler Building.
Removal of these structures and the asbestos is not considered to be a major
environmental issue. Both property locations may have radon presence in
groundwater that might be obtained from wells. Radon is characteristic of the
geologic units in the area for groundwater wells.

The past and present land use of these properties and the adjacent properties
are not anticipated to create any conditions that would result in a major
environmental concern. Groundwater beneath the Project site area drains into the
adjacent quarry and is presently pumped to surface drains. No contamination has
been identified within this groundwater regime.

Stone & Webster is of the opinion that the assessments reviewed were performed
in accordance with standard industry practice and their results appear
reasonable.

4.2    Permitting

The EPC Contract (Appendix F) sets forth a list of applicable permits and
approvals that are required by federal, state, and local agencies. This list
also identifies who is responsible for obtaining the permit or approval. The
Project has represented that this list is comprehensive and that no other
permits other than possibly some ministerial permits are required for the
construction and operation of the Project.

SWPC and AES Ironwood are individually or jointly responsible for obtaining the
permits and authorizations described in the following table. Stone & Webster has
relied upon the Project to confirm that all necessary permits or authorizations
have been identified and that the permits have either been obtained or will be
granted in a timely manner without adversely affecting the Project's schedule.


                                      B-36
<PAGE>
<TABLE>
<CAPTION>

====================================================================================================================
                                         Applicable Permits and Approvals
====================================================================================================================
              Agency                         Applicable Permits                             Status
- --------------------------------------------------------------------------------------------------------------------
<S>                                 <C>                                    <C>
Federal Energy Regulatory           Exempt Wholesale Generator             Issued March 29, 1999
Commission                          Certification
- --------------------------------------------------------------------------------------------------------------------
PaDEP                               PSD/State Air Permit                   Final March 29, 1999
- --------------------------------------------------------------------------------------------------------------------
U.S. Dept. of Energy, Office        Fuel Use Act Certification             Approved
of Fossil Energy
- --------------------------------------------------------------------------------------------------------------------
PaDOT                               Roadway Access Permits from            Approved
                                    Prescott Road to site
- --------------------------------------------------------------------------------------------------------------------
PaDEP                               NPDES, PAG-2                           Approved
- --------------------------------------------------------------------------------------------------------------------
PaDEP                               NPDES General Permits #4, # 4 #5       Approved
                                    #7
- --------------------------------------------------------------------------------------------------------------------
PaDEP                               NPDES Part 1 Construction              Approved
- --------------------------------------------------------------------------------------------------------------------
Pa Dept of Labor and Industry       Onsite Oil Storage Tank                Part of
                                    (1)      Permission to construct       SWPC Construction Permit
                                    (2)      Permit for construction
- --------------------------------------------------------------------------------------------------------------------
Delaware River Basin                Water Use Approval as per Section      Approved
                                    3.8 of DRDC regulations
- --------------------------------------------------------------------------------------------------------------------
Susquehanna River Basin             Water Use Approval                     Approved
Commission
- --------------------------------------------------------------------------------------------------------------------
Lebanon County                      Soil Erosion and Sediment Control      Approved
Conservation District               Approval
- --------------------------------------------------------------------------------------------------------------------
Conrail/Norfolk Southern            Railroad Crossing Approval and         Approval Agreements Pending
                                    Railspur Construction
- --------------------------------------------------------------------------------------------------------------------
Lebanon Zoning Hearing              Stack Height Variance Approval for     Approved
Board                               Power Plant
- --------------------------------------------------------------------------------------------------------------------
South Lebanon  Board of             Land Development Approval for          Approved
Supervisors                         Power Plant
- --------------------------------------------------------------------------------------------------------------------
South Lebanon  Board of             Subdivision Approval for Access        Approved
Supervisors                         Road
- --------------------------------------------------------------------------------------------------------------------
South Lebanon                       Onsite septic approval for sanitary    Conceptually Approved
Township/Lebanon County             discharge
- --------------------------------------------------------------------------------------------------------------------
City of Lebanon Authority           Agreement for Supply of treated        Approved
                                    effluent and construction, operation
                                    and maintenance of pipeline
- --------------------------------------------------------------------------------------------------------------------
Lebanon County                      Building Permit                        To be acquired prior to construction
Planning Department
- --------------------------------------------------------------------------------------------------------------------
Federal  Aviation                   Notice of Alteration or Proposed       Approved
Administration                      Construction for AES Ironwood
                                    Facility Stack
====================================================================================================================
</TABLE>


                                      B-37
<PAGE>

Stone & Webster is of the opinion that the permits and authorizations that have
been granted are consistent with the Project's present phase of development.

Stone & Webster has reviewed the permits and approvals identified in this
section. Stone & Webster is of the opinion that if this facility is constructed,
operated and maintained in accordance with the terms of the EPC Contract, PPA,
and the Maintenance Services Agreement, and if the natural gas and fuel oil
provided by Williams are within the quality limits specified in the EPC
Contract, then it is reasonable to assume that the Project should satisfy the
permit limitations of the issued permits and have a useful life beyond the final
maturity date of the Bonds.

Stone & Webster notes that the quantity of ammonia to be stored on site (two
10,000 gallon tanks of aqueous ammonia) is sufficient to subject this Facility
to the risk management and reporting programs administered by the EPA and OSHA.
However, compliance with these programs should not have any effect on either
project cost or schedule.

4.2.1  Prevention of Significant Deterioration Permit

The Project submitted the Prevention of Significant Deterioration Permit ("PSD")
air permit application forms to the Pennsylvania Department of Environmental
Protection ("PaDEP") in May 1998 as part of the Plan Approval Application for
the AES Ironwood Facility (the "Plan Approval Application"). The application was
deemed complete in August 1998, a draft PSD Air Permit was issued on December
23, 1998 and a public hearing was held on February 18, 1999. The final PSD Air
Permit was issued to AES Ironwood on March 29, 1999.

The application form sets forth atmospheric emissions limits for NOx, CO, and
volatile organic compounds ("VOC") which are consistent with or above the EPC
Contract emissions warranties. With respect to VOC and particulate matter
("PM"), the permitted emissions will be based upon stack test results and/or
vendor guarantees. Emissions of SO2 will be determined by fuel sulfur sampling
and mass balance calculations.

The Plan Approval Application includes a summary of proposed permit limits.
Stone & Webster reviewed the Pennsylvania modified Chapter 139 PM sampling
protocol report of 1998 which reports only the "front-end" portion of the
sampling train emissions. AES Ironwood's environmental consultant also advised
Stone & Webster that the calculated permit limits for ammonia salts (from the
SCR) are to be included in the total emissions of PM. These amounts are
reflected in the emission tables provided to TRC by SWPC for the 501G emissions.
We believe that this is a conservative approach to estimating the emissions as
measured under the current Pennsylvania PM sampling protocol as represented by
AES Ironwood's environmental consultant.


                                      B-38
<PAGE>


Although the manufacturer for the SCR system has yet to be selected, Stone &
Webster has reviewed the design criteria for the SCR system, discussed the
emissions testing performed on the 501G combustor nozzles with SWPC, and
analyzed the similarities in the turbine firing temperatures of the 501F and
501G gas turbines. Based on these actions coupled with our knowledge of the 501F
gas turbine, Stone & Webster believes that the 501G will be able to achieve and
maintain compliance with the Project's Air Permit during full load operation.

The PSD Permit expires on June 30, 2002, by which time AES needs to have
completed construction, start-up, commissioning, environmental testing and
performance testing, and begun commercial operation. During this period of time,
AES is required to compile its initial emissions testing report and submit an
application to the PaDEP for an "operating" permit. In addition, Condition 3.c
of the PSD Permit authorizes "temporary" operation for a period of 180 days from
the date of "commencement of operation". This 180-day period should be
sufficient for start-up, commissioning, environmental testing, performance
testing and operating permit application compilation and submittal.

4.2.2  Exempt Wholesale Generator Status

AES Ironwood filed for certification of the Facility as an EWG under the
applicable rules of the FERC on February 24, 1999. AES Ironwood has received a
determination that the Facility is an EWG under the applicable rules of FERC.


                                      B-39
<PAGE>


5.     Project Agreements

Stone & Webster reviewed the primary contracts and agreements associated with
the Project. These included the PPA, the EPC Contract, the ESA, and the
Maintenance Services Agreement. Stone & Webster reviewed the agreements from a
technical and economic standpoint to assess the adequacy and reasonableness of
their terms and conditions. Legal, financial, and other important aspects of the
agreements associated with the project were not considered under this review.
This Report describes only portions of the Project Agreements as needed for the
discussion of the Facility's related issues. A complete description or legal
evaluation of the contracts and documents related to the Facility is beyond the
scope of this report, and Stone & Webster is not providing legal counsel
opinions regarding the legal interpretation of any contract language. Adherence
to industry standards and good engineering practice was assessed where
appropriate. Provided below is a summary of our findings for each of the
reviewed agreements.

5.1    Power Purchase Agreement

Stone & Webster reviewed the PPA. Certain of the provisions of the PPA are
discussed below. For a summary of the material terms of the PPA, reference is
made to "Description of Project Contracts - Power Purchase Agreement" in the
Offering Memorandum of AES Ironwood with respect to the Bonds to which the
Report is appended (the "Offering Circular").

5.1.1  Term

The term of the PPA is for a period of 20 years after the Contract Anniversary
Date that is the last day of the month in which the Commercial Operation Date
("COD") occurs. If the COD has not occurred prior to June 30, 2001, subject to
the extension as described below except for a Force Majeure or a delay caused by
Williams, Williams has the right to terminate the PPA without liability or
responsibility unless AES Ironwood has either:

       o      Demonstrated to Williams that the COD will occur no later than
              December 31, 2001, or

       o      Was unable to execute an Interconnection Agreement with GPU. to
              maintain the Facility construction schedule ("Interconnect Delay")

In these cases AES Ironwood has the right to extend the COD to December 31, 2001
("Free Extension Option"). In the event the above described conditions are not
met then AES Ironwood has the right to extend the COD to and including December
31, 2001, by giving Williams a written notice of extension no later than April
30, 2001 and paying Williams a specified amount no later than June 30, 2001.


                                      B-40
<PAGE>

In the event AES Ironwood qualifies and elects the Free Extension Option but the
COD does not occur by December 31, 2001 then AES Ironwood can elect to:

       o      extend the COD up to and including December 31, 2002 by making
              certain daily payments, and

       o      pay Williams an amount equal to the lesser of:

              actual damages Williams suffers or incurs after December 31,
              2001, or up to a specified cap

In the event AES Ironwood qualifies for the Free Extension Option or elects the
First Paid Extension Option and the COD has not occurred prior to December 31,
2001, except for a delay caused by Williams, a Force Majeure delay, or an
Interconnect Delay then Williams has the right to terminate the PPA without
liability or responsibility, provided that AES Ironwood has the right to extend
the final COD to December 31, 2002, by giving Williams written notice of the
extension no later than October 31, 2001, and making Williams certain daily
payments.

In the event AES Ironwood elects the Second Paid Extension Option and the COD
does not occur by December 31, 2002 for any reason except as a result of an
Interconnect Delay, Force Majeure, or a delay caused by Williams, then Williams
has the absolute right to terminate the PPA without liability or responsibility.

The Provisional NTP was provided to SWPC on September 23, 1998 and several
milestones have been achieved to date by SWPC. The Full NTP will occur on or
about June 1, 1999. Pursuant to the terms of the PPA, AES Ironwood has the
option to extend the COD to December 31, 2001 by paying Williams a specified
amount if there is a delay in the June 30, 2001 COD. The Delay in Financial
Closing/SWPC Continued Performance Agreement between SWPC and AES Ironwood
extends the date by which the Commencement Date must occur to June 1, 1999. Not
withstanding the above stated provisions SWPC agreed in a letter to AES Ironwood
dated May 12, 1999 to not exercise its right to suspend its performance of
services between June 1, 1999 and June 21, 1999. The Guaranteed Provisional
Acceptance Date is 23 months and two weeks following full NTP.

Based on the EPC Contract, if SWPC fails to achieve the Provisional, Interim, or
Final a specified amount per day. If Provisional, Interim, or Final Acceptance
occurs six months after the Guaranteed Provisional Acceptance Date, AES Ironwood
would receive liquidated damages, which amount, together with contingencies and
prefunded IDC, is sufficient to cover the amounts AES Ironwood would be required
to pay Williams to extend the COD to December 31, 2001, plus approximately 190
days in debt service after the Guaranteed Provisional Acceptance Date beyond
December 31, 1999. Based on the EPC Contract, the total liquidated damages
associated with a delay in the Guaranteed Provisional Acceptance Date is a
maximum of 20% of the contract price. If the COD is delayed to December 31,
2002, AES Ironwood would receive liquidated damages,


                                      B-41
<PAGE>


which amount, together with contingencies and prefunded IDC, is sufficient to
cover the additional payments to Williams plus approximately one year in debt
service after the Guaranteed Provisional Acceptance Date.

5.1.2  Fuel Conversion and Associated Services

Williams is obligated to supply and transport the fuel (natural gas and fuel
oil) to generate net electric energy, perform start-ups and shutdowns, and
operate the Facility during any period other that during a dispatch period.
Williams is responsible for all costs and expenses related to the supply and
transportation of the natural gas and fuel oil to the fuel delivery point(s).

AES Ironwood is responsible for all costs and expenses related to the supply and
transportation of the natural gas and fuel oil from the fuel delivery point(s)
to the Facility. AES Ironwood is required to provide fuel oil storage capacity
sufficient to operate the plant at full output for at least 2 days. If AES
Ironwood elects to use offsite fuel oil storage, then AES Ironwood is
responsible for arranging transportation to the Facility from that remote
location. AES Ironwood is not obligated to operate the Facility on fuel oil for
more than 31 days or 744 hours per year.

Williams is responsible for the construction of the Gas Interconnection
Facilities. In the event that the Gas Interconnection Facilities have not been
constructed or Williams is unable to deliver gas to the Facility to support the
initial start-up testing, Williams will pay AES Ironwood certain specified
amounts for each day of the delay from the date on which the Facility would
otherwise (but for the absence of gas) be ready for start-up testing until the
gas is delivered to the site.

5.1.3  PPA Payments

Williams will pay AES Ironwood for facility capacity, fuel conversion services,
and ancillary services. Each monthly billing payment is the sum of the total
fixed payment, fuel conversion payment, and the start-up payment. For each month
of the PPA term Williams is responsible to pay AES Ironwood for the fixed
payments for facility capacity, fuel conversion services and ancillary services
at the rates specified in Appendix 1 of the PPA. The PPA also includes certain
heat rate bonus and penalty payments, startup cost payments and penalties
payable by AES Ironwood for failure to be available for dispatch under certain
conditions.

5.1.4  Interconnection and Metering Equipment

AES Ironwood at its cost and expense will design, construct, install, own, and
maintain the Interconnection Facilities and Protective Gas Apparatus needed to
deliver the net electric energy to the electricity delivery point. AES Ironwood
is also responsible for the negotiation and execution of an Interconnection
Agreement with the host utility. The host utility will own and be responsible
for the design, installation, construction, and maintenance of the electric
metering equipment and any transmission equipment and related facilities
necessary to interconnect with


                                      B-42
<PAGE>


the host utility at the electric delivery point. Williams is required to
reimburse AES Ironwood up to a specified amount for reasonable costs incurred by
the host utility under the Interconnection Agreement. Williams is responsible
for installing, maintaining, calibrating, and testing the gas and oil metering
equipment. Net electric energy will be metered on an hour-by hour basis at the
metering point. Williams will pay to AES Ironwood the net amount shown on the
monthly statement within 30 days following the end of the applicable billing
month.

5.2    Interconnection Agreement

Stone & Webster reviewed the Interconnection Agreement by and between MET-ED
d/b/a GPU and AES Ironwood. Certain provisions of the Interconnection Agreement
are discussed below. For a summary of the material terms of the agreement,
reference is made to "Description of Project Contracts - Interconnection
Agreement" in the Offering Circular.

In general, Stone & Webster found that the Interconnection Agreement is
comparable to other similar agreements with which Stone & Webster is familiar.
In addition, the technical requirements for operating the transmission
interconnection (Appendix C of the Agreement) and system protection and control
(Appendix D), and for the installation of the interconnection (Appendix E)
appears to be reasonable.

5.3    Engineering, Procurement, and Construction Services

Stone & Webster reviewed the executed EPC Contract between AES Ironwood and
SWPC. Certain provisions of the EPC Contract are discussed below. For a summary
of the material terms of the agreement, reference is made to "Description of
Project Contracts - EPC Agreement" in the Offering Circular.

The EPC Contract is for a 705 MW combined cycle facility to be located in South
Lebanon Township near Lebanon, Pennsylvania. SWPC will provide a Facility which
is intended to have at least a 25-year useful life (when operated and maintained
in accordance with the Instruction Manual, the PPA, and the manufacturers'
recommendations. We believe the EPC Contract scope adequately describes the
services to be performed and is technically complete. SWPC's scope of services
is presented in detail in Appendix A of the EPC Contract. Our assessment of
SWPC's scope of services and the technical descriptions are presented in Chapter
3 of this report. This price includes agreed to and estimated price changes for
scope changes agreed to by AES Ironwood through the date of this Report, but
does not include certain scope changes currently under discussion, the price of
which are included in "Other Hard Costs" as described in Section 7.3. The total
current contract price is $238.0 million.


                                      B-43
<PAGE>

5.3.1  SWPC Responsibilities

SWPC's responsibilities under the EPC Contract include the design, engineering,
procurement, and construction of the facility; startup, training, and testing;
and the supply of all machinery, equipment (excluding operational spare parts),
tools, construction fuels, chemicals, etc. to complete the Project. SWPC will be
responsible for all tasks necessary to complete the Project other than those
specifically assigned to AES Ironwood in Appendix A. SWPC will also prepare a
Quality Assurance Plan (Appendix K). SWPC will use this plan to ensure that the
construction and engineering methods and standards required are adhered to or
achieved. SWPC will develop a list of recommended operational spare parts and a
price list. This will be delivered to AES Ironwood at least 12 months prior to
the scheduled date for PA.

SWPC also has certain obligations with respect to labor and personnel,
permitting and permitting support, inspection and expediting, personnel
training, cleanup and waste disposal, security, coordination with other
contractors, and management and supervision of its subcontractors. Stone &
Webster believes that these areas of contractor responsibility have been
addressed adequately in the EPC Contract. SWPC is required to coordinate its
functions with other contractors involved with the Project. SWPC is also
required to arrange for construction-period water supply facilities, but the EPC
Contract does not address the disposal of construction-period sanitary waste
disposal.

SWPC will provide training to AES Prescott's operation staff. Beginning six
months prior to the Project Guaranteed Provisional Acceptance Date, SWPC will
provide on-site classroom training for AES Prescott's O&M staff. The training
curriculum is more completely described in Appendix A of the EPC Contract. In
addition to SWPC's own training it will also coordinate any Subcontractor
training sessions in a manner sufficient to provide the personnel with an
adequate understanding of the O&M aspects of each dimension of the Project as an
integrated whole. Stone & Webster agrees with this overall approach to preparing
and training the O&M staff.

Within 60 days of the Guaranteed Provisional Acceptance Date, SWPC will submit
to AES Ironwood a detailed electronic construction schedule consistent with the
schedule outlined in Appendix C of the EPC Contract. As soon as practical but no
later than 120 days after the Guaranteed Provisional Acceptance Date, SWPC will
provide AES Ironwood with a critical path method ("CPM") schedule for the
Project including activity duration for each major component of the Services
provided by SWPC.


                                      B-44
<PAGE>

5.3.2  AES Ironwood Responsibilities

AES Ironwood is responsible for certain services associated with the EPC
Contract. These activities relate to: the appointment of an Owner's
representative; acquisition of the Facility site and access for SWPC;
acquisition of all applicable permits and real estate rights for the facility;
providing startup personnel; arranging for certain construction utilities (waste
disposal after the risk transfer date), fuel, and electrical interconnection
facilities on the utility side. These responsibilities are reasonable and
customary for this type of transaction.

5.3.3  Construction Schedule

AES Ironwood issued a Provisional Notice to Proceed as of September 23, 1998,
which required SWPC to begin the Services, including a full release of the
engineering, manufacturing, and procurement of the equipment on the date
specified. AES Ironwood is obligated to pay SWPC for all pre-Commencement Date
Services actually performed.

Stone & Webster reviewed the sequencing of events necessary to achieve Final
Acceptance of the Project and the criteria of each milestone. We believe that
the milestone criteria are technically reasonable. The significant milestones
are Mechanical Completion, Provisional Acceptance, Interim Acceptance, Final
Acceptance, and Project Completion. The Performance Tests and the PPA Output
Tests are conducted after Mechanical Completion in order to meet Provisional
Acceptance. The Reliability Run is required in order to meet Final Acceptance.
Project Completion occurs after Final Acceptance.

Interim Acceptance ("IA") is a milestone more specific to this agreement. IA
occurs when the gas-based electrical output and heat rate guarantee is not less
than those levels demonstrated during the completed performance test at
Provisional Acceptance.

5.3.4  Contract Price and Payment Schedule

The contract price (as adjusted for scope changes) will be paid out to SWPC in
installments over the construction schedule. The payments began with Provisional
Notice to Proceed and continue through construction according to the Payment and
Milestone Schedule (Appendix B). Retainage in the amount of 5% is withheld from
each scheduled payment except for the project completion payment. Stone &
Webster generally experiences retainage in the order of 5-10% of the contract
price. Upon achieving Final Acceptance of the Facility and the receipt of
documentation that all requirements have been satisfied, all the retainage may
be paid to the Contractor, except that AES Ironwood can hold back an amount
equal to $1 million and 150% of the punch list. Within 30 days after the Project
Completion all remaining retainage will be paid to SWPC.

AES Ironwood may deduct and set-off against any part of the balance due or to
become due from SWPC to AES Ironwood in connection with this agreement. If this
set-off amount is later


                                      B-45
<PAGE>


determined not to have been due from SWPC, then SWPC will be entitled to
interest on the set-off amount. The EPC Contract allows for change orders that
may be initiated by AES Ironwood or SWPC. The change order protocol allows for
adjustments to both pricing and schedule. The protocol utilized in this EPC
Contract is similar to other contracts with which we are familiar and is
technically acceptable.

5.3.5  Performance Testing Plans

To demonstrate Final Acceptance, SWPC must demonstrate 100% of the gas-based and
fuel oil-based electrical output and heat rate guarantees during the performance
test, or demonstrate in a completed PPA output test the achievement of 100% of
the gas-based electrical output guarantee and satisfy AES Ironwood that the
capabilities outlined in Part B of Appendix B are achieved. In addition,
Mechanical Completion must be satisfied and the Reliability Guarantee achieved.
Also, the reliability run must be completed no later than the occurrence of
Final Acceptance of the Facility.

Stone & Webster reviewed the performance testing plan. The performance tests
will be performed in accordance with PTC-46, the test code for overall plant
performance testing. A plant specific performance test procedure will be written
by SWPC and submitted to AES Ironwood 90 days prior to the test. Stone & Webster
believes that the performance testing plan as specified in the EPC Contract
Appendix D is acceptable, customary, and should adequately demonstrate the
Project's performance.

AES Ironwood can elect Final Acceptance. In this scenario, SWPC has no liability
to AES Ironwood for any performance guarantee payments arising thereafter for
failure of the Facility to achieve any or all of the performance guarantees
applicable. SWPC can elect Final Acceptance. In this case SWPC must have
completed a performance test which demonstrates at least a level of 95% of the
gas-based and fuel oil-based electrical output and 108% of the gas-based and
fuel oil-based heat rate. SWPC is then obligated to pay all of the performance
guarantee payments as determined by the final or most recent completed
performance test. SWPC also must pay any Provisional Acceptance late completion
payments required.

5.3.6  Performance Guarantees

SWPC is required to design and construct the Facility to achieve certain
guaranteed performance levels in regards to capacity, heat rate, and
reliability.

The Performance Guarantees are designed to ensure that the Project's performance
meets or exceeds the minimum operating parameters of the PPA.


                                      B-46
<PAGE>


5.3.7  Warranty Period

The EPC Contract provides a warranty for all machinery, engineering and design,
and for situations involving corrections, additions, repairs or replacements.
With respect to all machinery, equipment, materials, systems, supplies and other
items comprising the Project, the warranty period is the earlier to occur of (i)
12 months following the first to occur of Provisional Acceptance, Interim
Acceptance and Final Acceptance and (ii) with respect to the machinery,
equipment, materials, systems, supplies and other items comprising each unit,
the date on which such unit has operated for 8,000 equivalent operating hours
following the first to occur of Provisional Acceptance, Interim Acceptance, and
Final Acceptance.

With respect to the engineering and design of the Project and its components, 12
months following the first to occur of Provisional Acceptance, Interim
Acceptance and Final Acceptance; and in the case of any correction, addition,
repair or replacement to any machinery, equipment, materials, systems, supplies
or other items, including without limitation the engineering or design thereof,
during any existing warranty period, with respect to such machinery, equipment,
materials, systems, supplies or other items, twelve months after the date of
such correction, addition, repair or replacement, but in no event later than 24
months after the originally scheduled expiration date of the applicable initial
warranty period.

In addition, the EPC Contract states that SWPC warrants and guarantees that the
design of the Facility is based on a useful life design objective for a period
not less than 25 years from the COD.

Stone & Webster is of the opinion that the warranty period is acceptable based
on the commercial terms of the EPC Contract in conjunction with the Maintenance
Services Agreement. These two agreements, although independent, are
complementary and afford the Project a greater degree of protection that is
available from the EPC Contract alone. The risk posed by the possibility of a
component failure that occurs after the expiration of the one year EPC Contract
warranty has been mitigated because the revenues presented in the Projected
Operating Results are sufficient to allow the purchase of replacement
components. Component failures associated with catastrophic failures are
generally covered by insurance policies.

5.3.8  Liquidated Damages

If there is a shortfall in either electrical output or heat rate SWPC will pay
AES Ironwood rebates for failure to meet both interim and final performance
requirements. SWPC guarantees to AES Ironwood to demonstrate a performance level
equivalent to the performance guarantees at least by Final Acceptance. SWPC
agrees to pay a specified amount per kilowatt for each kilowatt less than the
gas-based electrical output guarantee and a specified amount per kilowatt for
each kilowatt less than the fuel oil-based output guarantee, as of Final
Acceptance. The output rebate


                                      B-47
<PAGE>

for the gas-based operation is sufficient to motivate SWPC to meet their
gas-based electrical output guarantee.

SWPC will pay to AES Ironwood specified rebate amounts for each Btu/kWh that the
heat rate exceeds the heat rate guarantees for gas and Jet A fuel, including
interim rebates for heat rate while firing gas during the period from interim
acceptance until Final Acceptance. The heat rate rebates are sufficient to
motivate SWPC to meet their heat rate guarantees.

SWPC guarantees that at least one of the Provisional Acceptance, Interim
Acceptance, or Final Acceptance will occur on or before the Guaranteed
Provisional Acceptance Date, and that Final Acceptance will occur on or before
the Guaranteed Final Acceptance Date. If SWPC fails to achieve the Provisional,
Interim or Final Acceptance by the Guaranteed Provisional Acceptance Date, then
SWPC will pay AES Ironwood a specified dollar amount per day. If SWPC does not
achieve Provisional, Interim, or Final Acceptance within 40 days of the
Guaranteed Provisional Acceptance Date, then SWPC must provide an acceptable
plan to achieve acceptance within 12 months after the Guaranteed Provisional
Acceptance Date and the Final Acceptance of the Facility by the Guaranteed Final
Acceptance Date. The Provisional Acceptance Late Completion Payments cannot
exceed 20% of the contract price. If Final Acceptance does not occur on or
before the Guaranteed Final Acceptance Date, the Provisional Acceptance Late
Completion Payments, together with contingencies and prefunded IDC, will be
sufficient to cover the Williams payment plus debt service commitment for
approximately one year after the Guaranteed Provisional Acceptance Date.

The total aggregate Performance Guarantee Payment is equal to the lesser of the
aggregate total of the Performance Guarantee Payments or the total liquidated
damages subcap less all Provisional Acceptance Late Completion Payments. The
total liquidated damages subcap, including the Performance Guarantee Payment and
all Provisional Acceptance Late Completion Payments, cannot exceed 45% of the
contract price.

Stone & Webster believes, based on its review, that the liquidated damages
provisions are sufficient to motivate SWPC to meet their contractual
obligations.

5.4    Management and Operations Agreement

Stone & Webster reviewed the Operations Agreement and Services Agreement between
AES Ironwood and AES Prescott. Certain provisions of the agreement are discussed
below. For a summary of the material terms of the agreement, reference is made
to "Description of the Project Contracts - Operations Agreement" in the Offering
Circular.

Under the Operations Agreement AES Prescott is obligated to supply personnel and
support services required by AES Ironwood to supervise the development and
construction of the Project until the COD and to maintain and operate the
Facility following the COD through the remaining


                                      B-48
<PAGE>


term of the agreement. The agreement commences on the execution date and
terminates the last day of the month in the 27th anniversary of the execution
date.

Stone & Webster is of the opinion that the Operations Agreement is reasonable
and believes that each Party is capable of fulfilling all of its obligations
therein.

5.5    Services Agreement

Stone & Webster reviewed the Services Agreement between AES and AES Prescott.
Certain provisions of the agreement are discussed below. For a summary of the
material terms of the agreement, reference is made to "Description of the
Project Contracts - Services Agreement" in the Offering Circular.

AES will provide certain personnel and support services to AES Prescott in order
for AES Prescott to perform its obligations under the Services Agreement. The
Services Agreement commences on the execution date and terminates the last day
of the month in the 27th anniversary of the execution date.

Stone & Webster is of the opinion that the Services Agreement is reasonable and
believes that each Party is capable of fulfilling all of its obligations
therein.

5.6    Effluent Supply Agreement

Stone & Webster reviewed the ESA between AES Ironwood and the City of Lebanon
Authority. Certain provisions of the agreement are discussed below. For a
summary of the material terms of the agreement, reference is made to
"Description of the Project Contracts - Effluent Supply Agreement" in the
Offering Circular.

The agreement was executed on March 3, 1998. The City of Lebanon Authority
operates a publicly owned wastewater treatment facility for the handling,
treatment, and disposal of wastewater, which meets applicable governmental
requirements. The City of Lebanon Authority is willing to provide this treated
effluent to the Project for use at the Facility. The term of this Agreement is
25 years with no more than four successive five-year extensions. The makeup
water will be delivered to the Project by way of a nominal 6.5 mile pipeline
with pumphouse and ancillary facilities. The pipeline is about 18 inches in
diameter and is designed for a capacity of 3,000 gallons per minute. The point
of delivery is located at or inside the Project property. In addition to the
treated effluent the City of Lebanon Authority will also supply potable water to
the Project.

Stone & Webster is of the opinion that the ESA is technically reasonable and
believes that each Party is capable of fulfilling all of its obligations
therein.


                                      B-49
<PAGE>

5.7    Agreement Relating to Real Estate

Stone & Webster reviewed the Agreement Related to Real Estate between AES
Ironwood and Pennsy Supply, Inc. ("Pennsy"), dated October 22, 1998. Certain
provisions of the agreement are discussed below. For a summary of the material
terms of the agreement, reference is made to "Description of Project Contracts
Agreement Relating to Real Estate" in the Offering Circular.

AES is the equitable owner of the 35-acre property on which it intends to build
the Project. Pennsy currently owns tracts of land that border the AES property.
The agreement addresses certain real estate transfer, access and easement
agreements, and water pumping arrangements.

Additionally, the agreement confers preferred vendor status upon Pennsy for the
supply of certain construction materials to AES Ironwood. Responsibilities of
the parties regarding applications and permits including associated fees and
costs of construction and maintenance are delineated in the agreement and appear
reasonable. Based on other real estate agreements evaluated by Stone & Webster,
the terms of this agreement appear reasonable.

5.8    Maintenance Program Parts, Shop Repairs and Scheduled Outage
       TFA Services Contract

Stone & Webster reviewed the executed Maintenance Services Agreement between AES
Ironwood and SWPC for the Project. Certain provisions of the agreement are
discussed below. For a summary of the material terms of the agreement, reference
is made to "Description of Project Contracts - Maintenance Program Parts, Shop
Repairs and Scheduled Outage TFA Services Contract" in the Offering Circular.

SWPC agrees to provide the parts and technical advice required to conduct the
major maintenance for the combustion turbines. SWPC provides a warranty for its
parts and the advice it provides in exchange for a fee paid by AES Ironwood.
Under the terms of the Maintenance Services Agreement, all major maintenance and
parts are to be provided by SWPC, even if the particular item is not covered by
the original equipment warranty or some provision of this services agreement.
The Maintenance Services Agreement obligates SWPC to notify AES Ironwood of any
engineering or design defects that develop in the 501G fleet and provide
remedial action.

The Maintenance Services Agreement provides combustion turbine major maintenance
(including all scheduled outages) and spare parts for this Project in a
reasonable manner for approximately the initial eight years of operation. This
service provided by an a affiliate of the combustion turbine supplier reduces
the risk of using improper parts or maintenance being conducted improperly on
the combustion turbines due to the close involvement of the original equipment
manufacturer's trained personnel. The Maintenance Services Agreement provides
risk mitigation by providing a warranty on parts provided as part of the
Agreement. The warranty period ends


                                      B-50
<PAGE>

with the earlier of one year from date of installation of the part, 8000
equivalent base hours of operation, or 100 starts of the combustion turbine. The
Maintenance Services Agreement levelizes the major maintenance parts costs and
indexes costs to the type of combustion turbine operation in a reasonable and
consistent fashion. Under the agreement, AES Ironwood is responsible for labor
and supervision of labor for the major maintenance activities and the normal and
routine maintenance for the combustion turbines. These costs are included in the
operation and maintenance budget and accounted for in the Project's Projected
Operating Results. The Maintenance Services Agreement also obligates SWPC to
notify AES Ironwood of any engineering or design defects that develop in the
501G fleet and to provide remedial action. SWPC's scope of supply requirements
under the Maintenance Services Agreement are reasonable and consistent with
standard industry practice.



                                      B-51
<PAGE>

6.     Principal Project Participants

Stone & Webster reviewed the major Project participants and believe each should
be capable of fulfilling their obligations to one another as specified in the
various contracts and agreements of the Project.

6.1    AES Ironwood, LLC

AES Ironwood is a limited liability company, organized and existing under the
laws of Delaware. AES Ironwood was formed to develop, own, and operate the
Project. AES Ironwood is a special purpose project company and a subsidiary of
AES Ironwood, Inc.. AES Ironwood Inc. is a wholly owned subsidiary of The AES
Corporation ("AES"). AES is one of the world's largest global power companies
owning or having an interest in 97 plants totaling over 26,000 MW in 16
countries.

AES was founded in 1981 and has 18 years of experience developing and operating
large, complex power generating facilities. AES also distributes power in
Brazil, El Salvador and Argentina and heat in Kazakhstan. AES operates
gas-fired, oil-fired, hydropower, and solid-fuel plants, and employs
approximately 40,000 people around the world. AES currently owns assets worth in
excess of $10 billion. AES end-of-year 1998 revenue was $2.5 billion with a net
income of $308 million.

Stone & Webster believes that AES Ironwood, as an affiliate of AES and with the
assistance of SWPC under the terms of the Maintenance Services Agreement, should
be capable of operating and maintaining the Facility in accordance with standard
industry practices.

6.2    AES Prescott, LLC

AES Prescott is a Delaware limited liability company and a wholly owned
subsidiary of AES Ironwood, Inc. AES Prescott will manage the development and
construction of the Project pursuant to a development and construction
management agreement between AES Prescott and AES Ironwood. Stone & Webster
believes that AES Prescott, as an affiliate of AES, should be capable of
managing the development and construction of the Project.

6.3    Williams Energy Marketing & Trading Company

Williams is the Project's power purchaser and fuel supplier. Williams is a
corporation organized and existing under the laws of the State of Delaware and
is a wholly owned subsidiary of the Williams Companies. The Williams Companies,
through its subsidiaries, is engaged in the transportation and sale of natural
gas and petroleum products, and is engaged in energy commodity trading and
marketing. For the nine months ended September 1998, revenues were $5.64 billion
with a net income of $160 million.


                                      B-52
<PAGE>

Stone & Webster believes that Williams possesses the organization and personnel
to execute its obligations under the PPA, and is familiar with the provision of
fuel and purchase of electricity from large electrical generation facilities.

6.4    Siemens Westinghouse Power Corporation

SWPC is the Project's EPC contractor. SWPC is a newly formed Delaware
corporation that was formed in 1998 when Siemens Corporation acquired the
Westinghouse Power Generation business from the CBS Corporation in August 1998.
SWPC, headquartered in Orlando, Florida, is the regional business division for
the Americas and operates engineering and manufacturing centers in North
America.

Siemens Corporation owns all of the SWPC stock and is an industry leader in
telecommunications; energy and power; transportation; information systems and
other products. For the first nine months of fiscal year 1997/1998 Siemens' U.S.
businesses, with more than 55,000 employees, recorded sales of $7.0 billion.
Siemens AG, based in Berlin and Munich, owns all of the Siemens Corporation
stock and is one of the world's largest electrical engineering and electronics
companies and employs over 400,000 people worldwide in more than 190 countries.

Stone & Webster believes that SWPC possesses the organization and personnel to
execute its obligations under the EPC Contract, and is familiar with the
construction of large electrical generation facilities. Stone & Webster also
believes SWPC considers the 501G technology advancement as being extremely
important to its continued participation in the advanced combustion turbine
market and therefore will ensure that the initial project installations are
closely supported.


                                      B-53
<PAGE>


7.     Assessment of Projected Operating Results

7.1    Overview

The Projected Operating Results consist of a pro forma financial model for AES
Ironwood (the "Base Case"). Stone & Webster has reviewed the assumptions, data,
and the calculations necessary to support the cash flow projections of cash flow
available for debt service. Stone & Webster has verified that the underlying
model assumptions are consistent with the expected performance and the
commercial terms of the Project Agreements. Stone & Webster has validated key
calculations to ensure that the resulting revenues, expenses, cash flow, and
DSCRs were correctly calculated. Stone & Webster has reviewed the Projected
Operating Results and compared them to data provided in the Project Agreements,
data provided to Stone & Webster and power industry public information. Stone &
Webster has not reviewed the tax and depreciation assumptions, which were
provided by AES Ironwood, and financing assumptions, including the amortization
schedule and interest rates, which were provided by Lehman Brothers.

Lastly, Stone & Webster performed several sensitivities to determine the impact
of certain variables on the DSCRs. The Projected Operating Results for the Base
Case and the sensitivity cases are included in Exhibit I of this Report. The
Projected Operating Results are calculated in nominal dollars based on an
assumed inflation rate of 3% per annum.

7.2    Principal Considerations and Assumptions

In preparing this Report and the conclusions contained herein, Stone & Webster
has made certain assumptions with respect to the conditions, which may exist, or
events, which may occur in the future. While Stone & Webster believes these
assumptions to be reasonable for the purpose of this Report, they are dependent
on future events, and actual conditions may differ from those assumed. In
addition, Stone & Webster has used and relied on information provided to us by
sources that we believe to be reliable. Stone & Webster believes that the use of
this information and assumptions is reasonable for the purposes of our Report.
However, some assumptions may vary significantly due to unanticipated events and
circumstances. To the extent that actual future conditions may differ from those
assumed in this Report, or provided to us by others, the actual results will
vary from those forecast. This Report summarizes our work up to the date of the
Report and changes in conditions occurring or that became known after such date
could affect the Projected Operating Results.

The principal considerations and assumptions related to the Projected Operating
Results are listed below:

1.     Stone & Webster has assumed that the Project will be designed and
       built in accordance with the design specifications and the construction
       schedule dictated in the EPC contract.


                                      B-54
<PAGE>

2.     The electricity market energy and capacity price projections, which
       are relevant during the post PPA period were prepared by Hagler Bailly
       for Lehman Brothers, in its capacity as Initial Purchaser, using a market
       simulation model. Stone & Webster reviewed the technical inputs to the
       Hagler Bailly model and found them to be reasonable. Stone & Webster did
       not independently verify the methodology used by Hagler Bailly to develop
       the energy or capacity price forecasts nor verify the accuracy of the
       forecasts.

3.     Stone & Webster has made no determination as to the validity and
       enforceability of any contract, agreement, rule, or regulation as
       applicable to the Facility and its operations. For the purposes of this
       Report, Stone & Webster has assumed that all contracts, agreements,
       rules, or regulations will be valid and fully enforceable in accordance
       with the terms and that all parties will comply with the provisions of
       their respective agreements.

4.     Williams will arrange for the procurement and delivery of the fuel to
       the Facility and will purchase all available capacity, ancillary
       services, and energy from AES Ironwood in accordance with the PPA.

5.     Stone & Webster has reviewed the capital and O&M budgets for AES
       Ironwood. We have assumed that the Facility will operate and be
       maintained in accordance with the Operations Agreement, O&M and capital
       budgets, standard industry practice, and in a safe and environmentally
       responsible manner.

6.     Stone & Webster has assumed for purposes of the Projected Operating
       Results that AES Ironwood will operate the Facility pursuant to the PPA
       through the end of the first quarter of 2021 and as a merchant plant for
       the term of the Bonds.

7.     Stone & Webster has assumed that the maintenance will be performed by
       AES Prescott in accordance with the Operations Agreement and by SWPC in
       accordance with the Maintenance Services Agreement.

8.     The natural gas and fuel oil prices are inputs to the Hagler Bailly
       model. Stone & Webster reviewed the fuel price forecasts provided by the
       independent fuel consultant, CC Pace. It is assumed that the fuel will be
       available in sufficient quantities and at the prices forecasted for the
       period covered in the Projected Operating Results.

9.     Stone & Webster has assumed that all licenses, permits, and approvals
       required to construct and operate the Project which have not been
       obtained will be obtained in a timely basis and any changes that may be
       required to any permits will not materially affect the design, operation,
       cost, or maintenance of the Project.

10.    Stone & Webster has assumed that AES Ironwood will be able to
       purchase emission allowances, to the extent any are required, on an as
       needed basis to comply with the emission limits. We have assumed that
       emission offsets will be available for purchase at the prices forecasted
       in the Projected Operating Results. Stone & Webster has not evaluated the
       feasibility or cost of AES Ironwood implementing alternate strategies for
       complying with its emission limits.


                                      B-55
<PAGE>

11.    Stone & Webster has not evaluated the non-operating expenses
       projected by AES Ironwood including property and capital franchise taxes,
       insurance, and general and administrative expenses.


7.3    Project Cost

Stone & Webster evaluated AES Ironwood's estimate for the total Project costs
included in the pro forma financial model. The Projected Operating Results Base
Case total Project construction costs are estimated to be $342 million
(excluding contingency) or approximately $485/kW (net) in the pro forma
financial model. The breakdown of the total Project costs is provided in the
following table:
<TABLE>
<CAPTION>


                  ========================================================================
                                            Total Project Costs
                                                ($ million)
                  ========================================================================
<S>                                                                               <C>
                  EPC Contract                                                    $238.00
                  Other Hard (Construction-Related) Costs                           13.94
                  Other Development and Construction Costs                          21.35
                  Initial Working Capital                                            1.80
                  Net Interest During Construction                                  51.14
                  Start-up and Other Soft Costs                                     15.42
                  Company's Contingency                                             17.00
                  ------------------------------------------------------------------------
                  Total Project Costs                                             $358.65
                  ========================================================================
</TABLE>

Stone & Webster evaluated the Project's lump sum fixed price for the EPC
Contract of $238.0 million (including adjustments), which is equivalent to
approximately $338/kW (net). The EPC Contract price is very competitive relative
to similar facilities.

The non-EPC portion of the total Project cost includes construction management
costs, start-up costs, insurance, financing costs including IDC as well as
lenders, legal, and consultants fees, and working capital. The subtotal of the
non-EPC portion of the total Project cost, excluding contingency, equals $104
million, or 29% of the total Project costs, which is within the range of other
similar projects.

The Project development costs represent slightly less than 5% of the total
Project cost, which is reasonable for a project of this type. The Base Case
assumes $1.8 million for the initial working capital, which is equivalent to 45
days of non-fuel O&M expenses. The financial model assumes


                                      B-56
<PAGE>

a 4.7% contingency in the total Project cost, which based on our experience, is
typical of similar projects.

The financial model currently has $1.85 million in its capital budget for the
initial spare parts. AES Ironwood intends to designate those operational spare
parts approximately one year before commercial operations. In addition, there
are $5.4 million worth of combustion turbine maintenance spares imbedded in the
Maintenance Service Agreement, which will be available during the first 8000
EBH. SWPC has committed to stock one complete set of hot gas path parts for
every four combustion turbines sold.

7.4    Power Production

Stone & Webster evaluated the technical assumptions associated with the
performance of the Project for electricity production. The Base Case assumes a
705 MW net Facility capacity at site conditions, a 92.5% average availability
factor ("AF"), and 88.1% average capacity factor over the 26-year term of the
Bond issue. AF is defined as the total hours in a year (i.e., 8760) minus
planned maintenance hours and forced outage hours. Capacity factor is defined as
the actual hours of operation (i.e., dispatched) over the year.

The Base Case assumes that the Facility will continue to operate as a merchant
facility after the expiration of the 20-year PPA. Under the merchant operation
the Facility capacity is assumed to operate at a degraded net full load Facility
capacity at site conditions ranging from 698 MW while operating on natural gas
to 621 MW while operating on fuel oil.

7.4.1  Power Plant Availability

Power plant availability is a function of many variables, including design and
construction quality, operation and maintenance practices, and fuel quality. In
order to be conservative, the Base Case assumes a lower AF in years one and two
than in subsequent years. AES Ironwood projects the AF to be 90.4% in the first
two years and an average of 92.7% in subsequent years.

7.4.2  Capacity Factor

The Facility capacity factor is based on Hagler Bailley's economic dispatch of
AES Ironwood within the context of its PJM market study. Stone & Webster did not
independently verify the methodology that Hagler Bailly used to develop the
capacity factor nor verify the accuracy of the forecast. Hagler Bailly projected
for the Base Case that the AES Ironwood will have an average capacity factor of
88.1% during the term of the PPA and the post PPA period.


                                      B-57
<PAGE>

7.4.3  Capacity

The Base Case Projected Operating Results are based on the net Facility capacity
operating on natural gas at site conditions adjusted to 92(degrees)F and
including degradation. The Base Case model assumes a 4% degradation factor for
output over the six-year maintenance cycle, which is standard for similar
facilities. Stone & Webster considers the assumed degradation to be within the
range of expected degradation for such power generation facilities.

7.5    Revenues

Williams is obligated for a period of 20 years from the COD to purchase the
Facility capacity, approximately 655 MW +/-10% (summer capacity) at 92(degrees)F
when firing on natural gas pursuant to the PPA. Williams will pay AES Ironwood
for the Facility capacity, fuel conversion services, and ancillary services
provided under the PPA. The Project revenues are calculated based on the pricing
and payment structure defined in Appendix 1 of the PPA. The revenues for the
first full calendar year (Year 2002) are $60.2 million.

The Total Fixed Payment is based on a Fixed Capacity Rate, which has a set
schedule for the 20-year term of the PPA. If the Project Equivalent Availability
Factor ("EAF") as defined in Appendix 1 to the PPA is greater than 85%, there is
an Annual Availability Energy Adjustment ("AAEA") payable to AES Ironwood. The
Annual Availability Capacity Adjustment ("AACA") will be calculated as a credit
to Williams each year based on the EAF if the EAF is lower than 85%. For the
Base Case there is no AACA projected for the 20-year term of the PPA. The AAEA
and AACA are paid in the first quarter of the operating year following the end
of the previous year.

Williams provides fuel to the Project for conversion into energy. Consequently,
the Project is not responsible for the cost of fuel. Rather Williams pays a fee
to AES Ironwood to convert the fuel into energy. The Fuel Conversion Rates are
escalated annually at the Gross Domestic Product Implicit Price Deflator
("GDPIPD"). The Base Case assumes a GDPIPD of 3%.

In addition to the fuel conversion revenue, Williams is required to pay AES
Ironwood an energy efficiency bonus or penalty ("HRB/HRP"). The energy
efficiency bonus or penalty is based on the difference between the Heat Rate
Target ("HRT") while operating on natural gas and the actual Facility Heat Rate
("FHR"), net electric energy delivered, and the natural gas price index.

The Base Case assumes a 2% degradation factor for heat rate over the six-year
maintenance cycle, which is standard for similar facilities. Stone & Webster
considers the assumed degradation to be within the range of expected degradation
for such power generation facilities. After 20 years from COD at the end of the
PPA term, the Base Case assumes that the Project net capacity and energy will be
sold into the PJM system for a period through and beyond the maturity of the
Bonds. Hagler Bailly estimated the Base Case first merchant operating year


                                      B-58
<PAGE>

(2021) AES Ironwood plant-specific energy and capacity market price projections
in 1996 dollars at $27.16/MWh and $5.38/MWh, respectively. The total operating
revenue for the first full merchant calendar year (Year 2022) is $379 million,
which includes AAEA revenues earned in the final operating year of the PPA term.

7.6    Operating Expenses

The estimated Project expenses during the PPA period consist of non-fuel fixed
and variable expenses. The natural gas and fuel oil will be supplied and
transported to the Project under the terms established in the PPA. During the
PPA period, Williams will arrange for the procurement and delivery of the
natural gas and fuel oil to the applicable Facility fuel delivery point. After
the PPA period, AES Ironwood will be responsible for the procurement and
delivery of all the fuel to the Facility.

In the pro forma, the estimated O&M expenses are in nominal dollars reflecting
an assumed 3% inflation per year. The first full calendar year (Year 2002) fixed
and variable non-fuel O&M expenses, which total $17.2 million, and are detailed
in the following table.
<TABLE>
<CAPTION>

                  ===========================================================================
                                       Estimated Non-Fuel O&M Expenses
                                                (2002 $ ,000)
                  ===========================================================================
<S>                                                                                    <C>
                    Fixed O&M                                                          $13.2
                    Variable O&M                                                         2.1
                    Administration                                                       0.3
                    Operating Insurance                                                  0.6
                    Property Taxes                                                       0.9
                  ---------------------------------------------------------------------------
                  Total Non-Fuel O&M Expenses                                          $17.2
                  ===========================================================================
</TABLE>

Stone & Webster reviewed the O&M assumptions utilized in the Projected Operating
Results. The information reviewed included assumptions and forecasts for unit
performance; staffing functions and levels; annual O&M budget summary; and unit
overhaul plans and schedules. Stone & Webster compared the information with its
experience with plants of similar configuration and Utility Data Institute cost
and staffing information for similar plants. Stone & Webster considers these
Project assumptions to be reasonable and comparable to other facilities of
similar design.


                                      B-59
<PAGE>

7.6.1  Maintenance Schedule

All maintenance work and spare parts replacement for the combustion turbine
during the first eight years of the Facility operations will be provided by SWPC
through the Maintenance Services Agreement and thereafter will be the
responsibility of AES Ironwood. The O&M schedule and budget assumes that each
combustion turbine accumulates 8000 EBH each year. SWPC's recommended frequency
for annual inspections, hot gas path inspections, and major overhauls are being
used. In addition, AES Ironwood has included in the schedule and budget a "cover
lift" for every hot gas path inspection in order to restore any performance
degradation experienced since the previous major overhaul. Stone & Webster
believes that AES Ironwood's planned overhaul and maintenance schedule is
reasonable and adequate to support its operational and business objectives.

7.6.2  Operations and Maintenance Budget

Stone & Webster reviewed the non-fuel fixed, variable, and major maintenance
expenses in the Projected Operating Results. Stone & Webster believes that the
O&M budget is sufficient to support the planned staffing level, the maintenance
and overhaul schedule, and the project's performance and business objectives.

7.6.3  O&M Staffing Levels

AES Ironwood's planned functional positions and staffing levels were reviewed
and are considered satisfactory to operate and maintain the Facility safely in
accordance with the operational and regulatory requirements. The staffing levels
compare favorably with and are typical of those found in similarly configured
plants that Stone & Webster has reviewed. Our review also included the resume of
the proposed Project Plant Manager, who appears to have relevant experience in
similar plants and has previously demonstrated the requisite skills to perform
satisfactorily for AES Ironwood. Stone & Webster believes that the staffing
levels are adequate to support AES Ironwood's operational and business
objectives.

7.6.4  Emission Compliance Costs

The Projected Operating Results include an emission compliance limit cost. AES
Ironwood will be required to purchase allowances equal to one ton per year for
all SO2 emitted from the Facility and for all NOx emitted from the Facility
during the summer ozone season (defined as May through September). The Base Case
assumes that the Project will need approximately 150 tons of NOx allowances per
year at the current market value of $2,200 per ton for a vintage 2001 allowance.
The Project has already secured NOx allowances for the first two years of
operation and has capitalized these costs. NOx allowance costs in the year 2003
are projected to be $0.4 million. The Base Case assumes that the Project will
need approximately 198 tons of SO2 allowances per year, commencing at COD in
year 2001, at the current market value of $200 per


                                      B-60
<PAGE>

ton. The SO2 allowance cost for 2001 is $0.02 million. Both the NOx and SO2
allowance costs are projected to increase at 3% per annum.

7.6.5  Fuel Expense

In operating year 21, the term of the PPA will end and AES Ironwood will be
responsible for providing the fuel for the Facility to operate as a merchant
plant. The Base Case assumes that the fuel will be purchased at the price
stipulated in the CC Pace Fuel Forecast. The delivered natural gas price will
start at $2.44/mmBtu in real 1996$'s in year 2001 and increases to $2.64/mmBtu
in real 1996$'s in the first merchant operating year, 2021. Per the terms of the
PPA, Williams will supply Jet A fuel oil to the Facility throughout the 20-year
PPA. Following the PPA period, the Facility will purchase No. 2 fuel oil. The
No. 2 fuel oil price is projected by CC Pace to be $3.69/mmBtu in 1996$ in 2021.
The fuel expense assumed during the post PPA period is based on the Facility
heat rate at ISO conditions, the Facility capacity factor, and the unit cost of
fuel. The fuel expense for the first full calendar year of merchant operation is
$219.2 million. When AES Ironwood becomes a merchant plant, the fuel expense
will be the single largest expense.

The CC Pace Fuel Forecast is given in 1998$'s. The Hagler Bailly report assumes
that the fuel expenses are in 1996$'s and are escalated at 2.5%. The unit fuel
costs used in the CC Pace Fuel Forecast are shown in the following table.
<TABLE>
<CAPTION>

           ==========================================================================================
                                              Fuel Price Forecast
           ==========================================================================================
                                     Delivered Natural Gas             Delivered No. 2 Fuel Oil

                 Year                   ($1996/mmBtu)                       ($1996/mmBtu)
           ------------------------------------------------------------------------------------------
<S>               <C>                         <C>                                <C>
                  2021                        2.64                               3.69
                  2022                        2.65                               3.69
                  2023                        2.67                               3.69
                  2024                        2.68                               3.69
                  2025                        2.69                               3.69
           ==========================================================================================
</TABLE>

The CC Pace Fuel Forecast for the PJM area is consistent with Stone & Webster's
forecasts for fuels.

7.7    Financing Assumptions

Lehman Brothers provided the financing assumptions for the $358.65 million
Project cost. The source of funds will consist of $50.15 million in equity and
$308.5 million. The capital cost items are allocated monthly during the
construction period to calculate releases of Bond proceeds and interest during
construction ("IDC"). The combined annual debt service (principal plus


                                      B-61
<PAGE>

interest, annual administrative and LOC fees) during the post construction
period ranges from a low of $16.3 million in 2001 to a high of $35.4 million in
2008.

7.8    Projected Operating Results

The Projected Operating Results are shown in Exhibit I of this Report. On the
basis of our studies and analyses of the Project, the Project Agreements and the
assumptions set forth in this Report, the projected revenues from the sale of
fuel conversion services, capacity, and ancillary services are more than
adequate to pay the annual O&M expenses (including provisions for major
maintenance), other operating expenses, and debt service.

The Base Case indicate the following DSCRs:
<TABLE>
<CAPTION>

               ==================================================================================
                                                   Base Case

                                             Debt Service Coverage
               ==================================================================================
                                                    Minimum                     Average
               ----------------------------------------------------------------------------------
<S>                                                 <C>                         <C>
               PPA Period
               ----------------------------------------------------------------------------------
                                                    1.45x                       1.46x
               ----------------------------------------------------------------------------------
               Post PPA Term
               ----------------------------------------------------------------------------------
                                                     5.77x                       5.81x
               ----------------------------------------------------------------------------------
               Full Term of the Bonds
               ----------------------------------------------------------------------------------
                                                     1.45x                       2.30x
               ==================================================================================
</TABLE>

7.9    Sensitivity Analyses

Due to uncertainties necessarily inherent in relying on assumptions and
projections, it should be anticipated that actual operating results would
differ, perhaps, materially, from those assumed and described herein. In order
to demonstrate the impact of certain circumstances on the Projected Operating
Results, certain sensitivity analyses have been developed by Stone & Webster. It
should be noted that other examples could have been considered, and those
presented are not intended to reflect the full extent of possible impacts on the
Project.

Stone & Webster performed several sensitivity analyses using the pro forma
financial model by varying the following Project specific key input parameters
including power plant availability, heat rate degradation factors, and O&M
costs.

7.9.1  Project Sensitivities

The three Project sensitivities include increasing the Base Case O&M costs,
increasing the Base Case heat rate, and decreasing the Base Case AF.


                                      B-62
<PAGE>

Operation and Maintenance Cost Sensitivity - The Base Case O&M costs were
increased by 15%. The resulting average and minimum DSCRs for the PPA term, the
post PPA term, and the full term of the Bonds are summarized in the following
table.
<TABLE>
<CAPTION>

               ==================================================================================
                                              Sensitivity Case 1

                                           Operation and Maintenance

                                         Debt Service Coverage Ratios
               ==================================================================================
                                                    Minimum                     Average
               ----------------------------------------------------------------------------------
<S>                                                  <C>                         <C>
               PPA Term
               ----------------------------------------------------------------------------------
                                                    1.29x                       1.38x
               ----------------------------------------------------------------------------------
               Post PPA Term
               ----------------------------------------------------------------------------------
                                                     5.58x                       5.64x
               ----------------------------------------------------------------------------------
               Full Term of the Bonds
               ----------------------------------------------------------------------------------
                                                     1.29x                       2.20x
               ==================================================================================
</TABLE>

Heat Rate Degradation Factors - To test the sensitivity of the Projected
Operating Results to heat rate, Stone & Webster increased the Base Case heat
rate by 5% (ignoring liquidated damages "by-downs'). The resulting average and
minimum DSCRs for the PPA term, the full term, and the post PPA term are
summarized in the following table.
<TABLE>
<CAPTION>

               ==================================================================================
                                              Sensitivity Case 2

                                             Heat Rate Degradation

                                         Debt Service Coverage Ratios
               ==================================================================================
                                                    Minimum                     Average
               ----------------------------------------------------------------------------------
<S>                                                  <C>                         <C>
               PPA Term
               ----------------------------------------------------------------------------------
                                                     1.11x                       1.24x
               ----------------------------------------------------------------------------------
               Post PPA Term
               ----------------------------------------------------------------------------------
                                                     5.26x                       5.29x
               ----------------------------------------------------------------------------------
               Full Term of the Bonds
               ----------------------------------------------------------------------------------
                                                     1.11x                       2.02x
               ==================================================================================
</TABLE>

Availability Factor Sensitivity - To test the pro forma sensitivity the Base
Case AF assumption was changed. The Base Case AF is 90.4% for the first two
years and ranges from 89.2% to 93.7% for the remaining life of the Facility. Due
to the evolutionary nature of the 501G gas turbine design Stone & Webster took a
more conservative approach and estimated the Facility AF to be approximately 85%
in the first two years and to increase to 90% in the remaining years of the term
of the Bonds. The resulting average and minimum DSCRs for the PPA term, the full
term, and the post PPA term are summarized in the following table.


                                      B-63
<PAGE>

<TABLE>
<CAPTION>

               ==================================================================================
                                              Sensitivity Case 3

                                              Availability Factor

                                         Debt Service Coverage Ratios
              ==================================================================================
                                                    Minimum                     Average
              -----------------------------------------------------------------------------------
<S>                                                  <C>                         <C>
               PPA Term
              -----------------------------------------------------------------------------------
                                                     1.41x                       1.43x
              -----------------------------------------------------------------------------------
               Post PPA Term
              -----------------------------------------------------------------------------------
                                                     5.70x                       5.73x
              -----------------------------------------------------------------------------------
               Full Term of the Bond
              -----------------------------------------------------------------------------------
                                                     1.41x                       2.26x
              ==================================================================================
</TABLE>

7.9.2  Hagler Bailly Sensitivities

In addition, sensitivity of the Project results was assessed for the two
downside alternatives, Low Demand Growth Case and a High Gas Price Case. The
High Gas Price and Low Demand Growth scenarios were taken from the Hagler Bailly
forecasts. Stone & Webster applied the two Hagler Bailly "macroeconomic"
downside sensitivities to the Base Case.

High Gas Price - The natural gas prices were uniformly increased by $0.50 per
mmBtu (in 1996$) above the CC Pace forecast levels. The resulting average and
minimum DSCRs for the post PPA term are summarized in the following table.
<TABLE>
<CAPTION>

            =====================================================================================
                                      Sensitivity Case 4 - High Gas Price

                                         Debt Service Coverage Ratios
            =====================================================================================
                                                                       Minimum        Average
            -------------------------------------------------------------------------------------
<S>                                                                     <C>            <C>
               Post PPA Term
            -------------------------------------------------------------------------------------
                                                                        4.98x          5.13x
            =====================================================================================
</TABLE>


                                      B-64
<PAGE>


Low Demand Growth - The demand growth rates were reduced by a third, compared to
the Base Case, for the period 2017 through 2025. In this case the peak and total
demand grew at only 0.50% and 1.00% per annum, respectively beginning in 2017,
while new capacity building remained per the Hagler Bailly base case. The
resulting average and minimum DSCRs for the post PPA term are summarized in the
following table.
<TABLE>
<CAPTION>

            =====================================================================================
                                    Sensitivity Case 5 - Low Demand Growth

                                         Debt Service Coverage Ratios
            =====================================================================================
                                                                       Minimum        Average
            -------------------------------------------------------------------------------------
<S>                                                                     <C>            <C>
               Post PPA Term
            -------------------------------------------------------------------------------------
                                                                        4.70x          4.93x
            =====================================================================================
</TABLE>

7.10   Liquidated Damages Analyses

Stone & Webster reviewed the impact on the average DSCRs if SWPC fails to pass
certain performance tests and there is a long-term performance deficiency over
the term of the Bonds. It was assumed that the performance liquidated damages
paid to AES Ironwood by SWPC would be used to buy down the Bonds on a pro rata
basis. The analysis was performed to demonstrate that the liquidated damages for
the guaranteed net electrical output and guaranteed net heat rate are sufficient
to maintain the DSCRs at the same level as projected in the Base Case.

It is projected that the average DSCRs over the term of the Bonds, after payment
of the liquidated damages due to a failure to achieve the guaranteed net
electrical output and the guaranteed net heat rate, will generally remain at the
same level as the average DSCRs in the Base Case for deficiencies up to
approximately 5% in net electrical output and 6% in net heat rate.

SWPC is required to pay liquidated damages for a delay in the Facility
completion. SWPC will pay AES Ironwood $110,000 for each day after the required
Facility completion date that the Facility completion is not achieved. The
liquidated damages for a delay in the Facility completion cannot exceed 20% of
the contract price. Such payment, together with contingencies and prefunded IDC,
will be sufficient to cover the Williams payment plus debt service commitment
for approximately one year after the Guaranteed Provisional Acceptance Date.

                                      B-65
<PAGE>




                                    Exhibit I




Base Case

Increased O&M Sensitivity (Case #1)

Increased Heat Rate Sensitivity (Case #2)

Decreased Availability Sensitivity (Case #3)

Hagler Bailey High Gas Price Sensitivity (Case #4)

Hagler Bailly Low Demand Growth Sensitivity (Case #5)


                                      B-66

<PAGE>
                                                                    Confidential

                                    Exhibit I
                    AES Ironwood Projected Operating Results
                                    Base Case
<TABLE>
<CAPTION>
                                                                                     PPA Period
                                                ------------------------------------------------------------------------------------
Year Ending December 31,                         2001    2002   2003    2004    2005   2006    2007    2008    2009   2010    2011
                                                ------------------------------------------------------------------------------------
<S>                                              <C>     <C>    <C>     <C>     <C>    <C>     <C>     <C>     <C>    <C>     <C>
Net Operating Revenues ($million)
      PPA Revenues                               35.1    60.2   60.4    63.4    65.4   65.0    68.0    70.1    64.1   63.1    65.5
      Merchant Revenues                             -       -      -       -       -      -       -       -       -      -       -

                                                ------------------------------------------------------------------------------------
      Total Operating Revenues                   35.1    60.2   60.4    63.4    65.4   65.0    68.0    70.1    64.1   63.1    65.5
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Interest Earned on Accounts ($million)            0.1     0.2    0.2     0.2     0.2    0.2     0.2     0.3     0.2    0.3     0.5
                                                ------------------------------------------------------------------------------------

Operating Expenses ($million)
      Fuel                                          -       -      -       -       -      -       -       -       -      -       -
      Fixed O&M                                   7.0    13.2    9.5    10.6    12.3    9.8    11.5    13.4    11.2   10.6    10.6
      Variable O&M                                1.3     2.1    2.2     2.3     2.4    5.2     4.5     2.7     2.7    2.8     3.0
      Administration                              0.2     0.3    0.3     0.3     0.3    0.3     0.3     0.3     0.3    0.4     0.4
      Insurance                                     -     0.6    1.1     1.1     1.2    1.2     1.2     1.3     1.3    1.3     1.4
      Property Taxes                              0.5     0.9    0.9     1.0     1.0    1.0     1.1     1.1     1.1    1.2     1.2
      Local Taxes                                 0.0     0.0    0.1     0.1     0.1    0.1     0.2     0.2     0.3    0.3     0.3

                                                ------------------------------------------------------------------------------------
      Total Operating Expenses                    8.9    17.2   14.1    15.4    17.3   17.7    18.9    19.0    16.9   16.6    16.8
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Cash Flow Available for Debt Service ($million)  26.3    43.2   46.6    48.2    48.3   47.5    49.4    51.4    47.4   46.8    49.2
                                                ------------------------------------------------------------------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding             308.5   306.5  301.8   295.4   288.4  281.2   272.1   260.7   251.1  241.1   228.4
          Principal and Interest                 15.9    29.2   31.7    32.9    33.0   32.5    33.7    35.1    32.4   32.0    33.6
          LOC & Administrative Fees               0.4     0.3    0.3     0.3     0.3    0.3     0.3     0.3     0.3    0.3     0.3

                                                ------------------------------------------------------------------------------------
      Total Debt Service                         16.3    29.6   32.0    33.2    33.3   32.8    34.0    35.4    32.7   32.3    33.9
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Annual Debt Service Coverage                     1.61x   1.46x  1.45x   1.45x   1.45x  1.45x   1.45x   1.45x   1.45x  1.45x   1.45x
                                                ------------------------------------------------------------------------------------
<CAPTION>
                                                                                   PPA Period
                                                ---------------------------------------------------------------------------
Year Ending December 31,                         2012    2013   2014    2015    2016   2017    2018    2019    2020  2021*
                                                ---------------------------------------------------------------------------
<S>                                             <C>     <C>    <C>     <C>     <C>    <C>     <C>     <C>     <C>   <C>
Net Operating Revenues ($million)
      PPA Revenues                               65.6    67.3   67.1    64.8    66.2   65.8    63.0    64.4    64.6   27.5
      Merchant Revenues                             -       -      -       -       -      -       -       -       -  215.3

                                                ---------------------------------------------------------------------------
      Total Operating Revenues                   65.6    67.3   67.1    64.8    66.2   65.8    63.0    64.4    64.6  242.8
                                                ---------------------------------------------------------------------------
                                                ---------------------------------------------------------------------------
Interest Earned on Accounts ($million)            0.3     0.3    0.4     0.2     0.3    0.5     0.3     0.3     0.4    0.2
                                                ---------------------------------------------------------------------------

Operating Expenses ($million)
      Fuel                                          -       -      -       -       -      -       -       -       -  123.4
      Fixed O&M                                  13.3    13.5   11.5    11.7    12.8   12.6    15.7    16.1    13.7   13.6
      Variable O&M                                6.3     5.5    3.3     3.3     3.5    3.6     7.6     6.6     4.0    4.1
      Administration                              0.4     0.4    0.4     0.4     0.4    0.4     0.4     0.5     0.5    0.5
      Insurance                                   1.4     1.5    1.5     1.6     1.6    1.7     1.7     1.8     1.8    1.9
      Property Taxes                              1.2     1.3    1.3     1.3     1.4    1.4     1.5     1.5     1.5    1.6
      Local Taxes                                 0.2     0.2    0.3     0.3     0.4    0.4     0.4     0.4     0.4    0.9

                                                ---------------------------------------------------------------------------
      Total Operating Expenses                   22.9    22.3   18.2    18.7    20.1   20.1    27.3    26.9    22.0  146.0
                                                ---------------------------------------------------------------------------
                                                ---------------------------------------------------------------------------
Cash Flow Available for Debt Service ($million)  43.0    45.3   49.3    46.4    46.4   46.2    36.0    37.8    43.0   97.1
                                                ---------------------------------------------------------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding             219.0   207.1  191.2   175.9   159.2  141.1   128.6   113.8    93.7   76.1
          Principal and Interest                 29.3    30.8   33.7    31.7    31.7   31.6    24.5    25.8    29.5   25.2
          LOC & Administrative Fees               0.3     0.3    0.3     0.3     0.3    0.3     0.2     0.3     0.3    0.2

                                                ---------------------------------------------------------------------------
      Total Debt Service                         29.6    31.1   34.0    32.0    32.0   31.9    24.8    26.0    29.7   25.5
                                                ---------------------------------------------------------------------------
                                                ---------------------------------------------------------------------------
Annual Debt Service Coverage                     1.45x   1.45x  1.45x   1.45x   1.45x  1.45x   1.45x   1.45x   1.45x  3.81x
                                                ---------------------------------------------------------------------------
<CAPTION>
                                                =============================
                                                       Post PPA Period
                                                -----------------------------
Year Ending December 31,                         2022    2023   2024    2025
                                                -----------------------------
<S>                                             <C>     <C>    <C>     <C>
Net Operating Revenues ($million)
      PPA Revenues                                  -       -      -       -
      Merchant Revenues                         378.9   389.7  391.5   416.2

                                                -----------------------------
      Total Operating Revenues                  378.9   389.7  391.5   416.2
                                                -----------------------------
                                                -----------------------------
Interest Earned on Accounts ($million)            0.3     0.6    0.3     0.2
                                                -----------------------------

Operating Expenses ($million)
      Fuel                                      219.2   228.8  226.8   238.4
      Fixed O&M                                  13.3    14.9   19.3    18.7
      Variable O&M                                4.2     4.4    9.1     7.9
      Administration                              0.5     0.5    0.5     0.6
      Insurance                                   1.9     2.0    2.0     2.1
      Property Taxes                              1.6     1.7    1.7     1.8
      Local Taxes                                 1.6     2.3    3.0     3.8

                                                -----------------------------
      Total Operating Expenses                  242.4   254.6  262.4   273.2
                                                -----------------------------
                                                -----------------------------
Cash Flow Available for Debt Service ($million) 136.8   135.7  129.4   143.3
                                                -----------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding              59.0    40.5   21.3     0.0
          Principal and Interest                 23.3    23.1   22.1    22.5
          LOC & Administrative Fees               0.2     0.2    0.2     0.2

                                                -----------------------------
      Total Debt Service                         23.6    23.3   22.3    22.7
                                                -----------------------------
                                                -----------------------------
Annual Debt Service Coverage                     5.81x   5.81x  5.80x   5.77x
                                                =============================
</TABLE>

* The first five months of 2021 include PPA cash flow and the last seven months
  of 2021 include Post PPA cash flow. The resulting blended DSCR is 3.81.

Average Debt Coverage During PPA                     1.46x

Minimum Debt Coverage During PPA                     1.45x

Average Debt Coverage Post PPA                       5.81x

Minimum Debt Coverage Post PPA                       5.77x

Average Debt Coverage During                         2.30x
   Bond Term

                                                                          B - 67
<PAGE>
                                                                    Confidential
                                    Exhibit I
                     AES Ironwood Projected Operating Results
                       Increased O&M Sensitivity (Case #1)
<TABLE>
<CAPTION>
                                                                                    PPA Period
                                                ------------------------------------------------------------------------------------
Year Ending December 31,                         2001    2002   2003    2004    2005   2006    2007    2008    2009   2010    2011
                                                ------------------------------------------------------------------------------------
<S>                                             <C>     <C>    <C>     <C>     <C>    <C>     <C>     <C>     <C>    <C>     <C>
Net Operating Revenues ($million)
      PPA Revenues                               35.1    60.2   60.4    63.4    65.4   65.0    68.0    70.1    64.1   63.1    65.5
      Merchant Revenues                             -       -      -       -       -      -       -       -       -      -       -

                                                ------------------------------------------------------------------------------------
      Total Operating Revenues                   35.1    60.2   60.4    63.4    65.4   65.0    68.0    70.1    64.1   63.1    65.5
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Interest Earned on Accounts ($million)            0.1     0.2    0.2     0.2     0.2    0.2     0.2     0.3     0.2    0.3     0.5
                                                ------------------------------------------------------------------------------------

Operating Expenses ($million)
      Fuel                                          -       -      -       -       -      -       -       -       -      -       -
      Fixed O&M                                   7.4    13.9    9.7    11.0    13.1   10.3    12.1    14.2    12.5   12.2    12.2
      Variable O&M                                1.4     2.5    2.5     2.7     2.8    6.0     5.2     3.1     3.1    3.2     3.4
      Administration                              0.2     0.3    0.3     0.3     0.4    0.4     0.4     0.4     0.4    0.4     0.4
      Insurance                                     -     0.7    1.3     1.3     1.3    1.4     1.4     1.5     1.5    1.5     1.6
      Property Taxes                              0.6     1.0    1.1     1.1     1.1    1.2     1.2     1.2     1.3    1.3     1.4
      Local Taxes                                 0.0     0.0    0.1     0.1     0.1    0.1     0.2     0.2     0.3    0.3     0.3

                                                ------------------------------------------------------------------------------------
      Total Operating Expenses                    9.6    18.5   14.9    16.5    18.8   19.3    20.5    20.6    19.0   19.0    19.2
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Cash Flow Available for Debt Service ($million)  25.7    41.9   45.7    47.1    46.8   45.9    47.7    49.8    45.3   44.5    46.8
                                                ------------------------------------------------------------------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding             308.5   306.5  301.8   295.4   288.4  281.2   272.1   260.7   251.1  241.1   228.4
          Principal and Interest                 15.9    29.2   31.7    32.9    33.0   32.5    33.7    35.1    32.4   32.0    33.6
          LOC & Administrative Fees               0.4     0.3    0.3     0.3     0.3    0.3     0.3     0.3     0.3    0.3     0.3

                                                ------------------------------------------------------------------------------------

      Total Debt Service                         16.3    29.6   32.0    33.2    33.3   32.8    34.0    35.4    32.7   32.3    33.9
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Annual Debt Service Coverage                     1.57x   1.42x  1.43x   1.42x   1.41x  1.40x   1.40x   1.41x   1.39x  1.38x   1.38x
                                                ------------------------------------------------------------------------------------
<CAPTION>
                                                                                     PPA Period
                                                ----------------------------------------------------------------------------
Year Ending December 31,                         2012    2013   2014    2015    2016   2017    2018    2019    2020  2021*
                                                ----------------------------------------------------------------------------
<S>                                             <C>     <C>    <C>     <C>     <C>    <C>     <C>     <C>     <C>    <C>
Net Operating Revenues ($million)
      PPA Revenues                               65.6    67.3   67.1    64.8    66.2   65.8    63.0    64.4    64.6   27.5
      Merchant Revenues                             -       -      -       -       -      -       -       -       -  215.3

                                                ----------------------------------------------------------------------------
      Total Operating Revenues                   65.6    67.3   67.1    64.8    66.2   65.8    63.0    64.4    64.6  242.8
                                                ----------------------------------------------------------------------------
                                                ----------------------------------------------------------------------------
Interest Earned on Accounts ($million)            0.3     0.3    0.4     0.3     0.3    0.6     0.3     0.3     0.5    0.3
                                                ----------------------------------------------------------------------------

Operating Expenses ($million)
      Fuel                                          -       -      -       -       -      -       -       -       -  123.4
      Fixed O&M                                  15.3    15.4   13.2    13.5    14.7   14.5    18.1    18.5    15.8   15.8
      Variable O&M                                7.3     6.3    3.7     3.8     4.0    4.2     8.7     7.6     4.6    4.7
      Administration                              0.4     0.4    0.5     0.5     0.5    0.5     0.5     0.5     0.5    0.6
      Insurance                                   1.6     1.7    1.7     1.8     1.8    1.9     2.0     2.0     2.1    2.1
      Property Taxes                              1.4     1.4    1.5     1.5     1.6    1.6     1.7     1.7     1.8    1.8
      Local Taxes                                 0.2     0.2    0.3     0.3     0.4    0.4     0.4     0.4     0.4    0.9

                                                ----------------------------------------------------------------------------
      Total Operating Expenses                   26.3    25.5   20.9    21.5    23.0   23.1    31.4    30.7    25.2  149.3
                                                ----------------------------------------------------------------------------
                                                ----------------------------------------------------------------------------
Cash Flow Available for Debt Service ($million)  39.6    42.0   46.6    43.6    43.5   43.4    32.0    33.9    39.8   93.7
                                                ----------------------------------------------------------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding             219.0   207.1  191.2   175.9   159.2  141.1   128.6   113.8    93.7  76.1
          Principal and Interest                 29.3    30.8   33.7    31.7    31.7   31.6    24.5    25.8    29.5  25.2
          LOC & Administrative Fees               0.3     0.3    0.3     0.3     0.3    0.3     0.2     0.3     0.3   0.2

                                                ----------------------------------------------------------------------------
      Total Debt Service                         29.6    31.1   34.0    32.0    32.0   31.9    24.8    26.0    29.7  25.5
                                                ----------------------------------------------------------------------------
                                                ----------------------------------------------------------------------------
Annual Debt Service Coverage                     1.34x   1.35x  1.37x   1.36x   1.36x  1.36x   1.29x   1.30x   1.34x 3.68x
                                                ----------------------------------------------------------------------------
<CAPTION>
                                                =============================
                                                        Post PPA Period
                                                -----------------------------
Year Ending December 31,                         2022    2023   2024    2025
                                                -----------------------------
<S>                                             <C>     <C>    <C>    <C>
Net Operating Revenues ($million)
      PPA Revenues                                  -       -      -       -
      Merchant Revenues                         378.9   389.7  391.5   416.2

                                                -----------------------------
      Total Operating Revenues                  378.9   389.7  391.5   416.2
                                                -----------------------------
                                                -----------------------------
Interest Earned on Accounts ($million)            0.3     0.6    0.4     0.2
                                                -----------------------------

Operating Expenses ($million)
      Fuel                                      219.2   228.8  226.8   238.4
      Fixed O&M                                  15.5    17.1   22.2    21.4
      Variable O&M                                4.9     5.0   10.5     9.1
      Administration                              0.6     0.6    0.6     0.6
      Insurance                                   2.2     2.3    2.3     2.4
      Property Taxes                              1.9     1.9    2.0     2.1
      Local Taxes                                 1.6     2.3    3.0     3.8

                                                -----------------------------
      Total Operating Expenses                  245.9   258.1  267.3   277.8
                                                -----------------------------
                                                -----------------------------
Cash Flow Available for Debt Service ($million) 133.4   132.2  124.5   138.6
                                                -----------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding              59.0    40.5   21.3     0.0
          Principal and Interest                 23.3    23.1   22.1    22.5
          LOC & Administrative Fees               0.2     0.2    0.2     0.2

                                                -----------------------------
      Total Debt Service                         23.6    23.3   22.3    22.7
                                                -----------------------------
                                                -----------------------------
Annual Debt Service Coverage                     5.66x   5.67x  5.58x   5.59x
                                                =============================
</TABLE>

* The first five months of 2021 include PPA cash flow and the last seven months
  of 2021 include Post PPA cash flow. The resulting blended DSCR is 3.68.

Average Debt Coverage During PPA                     1.38x

Minimum Debt Coverage During PPA                     1.29x

Average Debt Coverage Post PPA                       5.64x

Minimum Debt Coverage Post PPA                       5.58x

Average Debt Coverage During                         2.20x
   Bond Term

                                                                          B - 68
<PAGE>
                                                                    Confidential
                                    Exhibit I
                    AES Ironwood Projected Operating Results
                    Increased Heat Rate Sensitivity (Case #2)
<TABLE>
<CAPTION>
                                                                                     PPA Period
                                                ------------------------------------------------------------------------------------
Year Ending December 31,                         2001    2002   2003    2004    2005   2006    2007    2008    2009   2010    2011
                                                ------------------------------------------------------------------------------------
<S>                                             <C>     <C>    <C>     <C>     <C>    <C>     <C>     <C>     <C>    <C>     <C>
Net Operating Revenues ($million)
      PPA Revenues                               32.3    55.4   55.5    58.2    59.9   59.6    62.2    64.0    58.0   56.6    58.6
      Merchant Revenues                             -       -      -       -       -      -       -       -       -      -       -

                                                ------------------------------------------------------------------------------------
      Total Operating Revenues                   32.3    55.4   55.5    58.2    59.9   59.6    62.2    64.0    58.0   56.6    58.6
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Interest Earned on Accounts ($million)            0.1     0.2    0.2     0.2     0.2    0.2     0.2     0.3     0.2    0.3     0.5
                                                ------------------------------------------------------------------------------------

Operating Expenses ($million)
      Fuel                                          -       -      -       -       -      -       -       -       -      -       -
      Fixed O&M                                   5.6    12.3    9.4    10.5    12.2    9.8    11.4    13.2    11.2   10.5    10.4
      Variable O&M                                1.3     2.1    2.2     2.3     2.4    5.2     4.5     2.7     2.7    2.8     3.0
      Administration                              0.2     0.3    0.3     0.3     0.3    0.3     0.3     0.3     0.3    0.4     0.4
      Insurance                                     -     0.6    1.1     1.1     1.2    1.2     1.2     1.3     1.3    1.3     1.4
      Property Taxes                              0.5     0.9    0.9     1.0     1.0    1.0     1.1     1.1     1.1    1.2     1.2
      Local Taxes                                 0.0     0.0    0.1     0.1     0.1    0.1     0.2     0.2     0.3    0.3     0.3

                                                ------------------------------------------------------------------------------------
      Total Operating Expenses                    7.6   16.3    14.0    15.3    17.2   17.7    18.7    18.8    16.9   16.4    16.6
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Cash Flow Available for Debt Service ($million)  24.9    39.3   41.7    43.1    42.9   42.0    43.7    45.4    41.3   40.5    42.5
                                                ------------------------------------------------------------------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding             308.5   306.5  301.8   295.4   288.4  281.2   272.1   260.7   251.1  241.1   228.4
          Principal and Interest                 15.9    29.2   31.7    32.9    33.0   32.5    33.7    35.1    32.4   32.0    33.6
          LOC & Administrative Fees               0.4     0.3    0.3     0.3     0.3    0.3     0.3     0.3     0.3    0.3     0.3

                                                ------------------------------------------------------------------------------------
      Total Debt Service                         16.3    29.6   32.0    33.2    33.3   32.8    34.0    35.4    32.7   32.3    33.9
                                                ------------------------------------------------------------------------------------
Annual Debt Service Coverage                     1.53x   1.33x  1.30x   1.30x   1.29x  1.28x   1.28x   1.28x   1.26x  1.26x   1.25x
                                                ------------------------------------------------------------------------------------
<CAPTION>
                                                                                   PPA Period
                                                ----------------------------------------------------------------------------
Year Ending December 31,                         2012    2013   2014    2015    2016   2017    2018    2019    2020  2021*
                                                ----------------------------------------------------------------------------
<S>                                             <C>     <C>    <C>     <C>     <C>    <C>     <C>     <C>     <C>    <C>
Net Operating Revenues ($million)
      PPA Revenues                               58.6    60.0   59.4    57.0    57.8   57.2    54.4    55.3    54.9   23.5
      Merchant Revenues                             -       -      -       -       -      -       -       -       -  215.3

                                                ----------------------------------------------------------------------------
      Total Operating Revenues                   58.6    60.0   59.4    57.0    57.8   57.2    54.4    55.3    54.9  238.7
                                                ----------------------------------------------------------------------------
                                                ----------------------------------------------------------------------------
Interest Earned on Accounts ($million)            0.3     0.3    0.4     0.2     0.3    0.5     0.3     0.3     0.4    0.2
                                                ----------------------------------------------------------------------------

Operating Expenses ($million)
      Fuel                                          -       -      -       -       -      -       -       -       -  129.6
      Fixed O&M                                  13.3    13.3   11.3    11.6    12.6   12.5    15.7    15.9    13.5   16.3
      Variable O&M                                6.3     5.5    3.3     3.3     3.5    3.6     7.6     6.6     4.0    4.1
      Administration                              0.4     0.4    0.4     0.4     0.4    0.4     0.4     0.5     0.5    0.5
      Insurance                                   1.4     1.5    1.5     1.6     1.6    1.7     1.7     1.8     1.8    1.9
      Property Taxes                              1.2     1.3    1.3     1.3     1.4    1.4     1.5     1.5     1.5    1.6
      Local Taxes                                 0.2     0.2    0.3     0.3     0.4    0.4     0.4     0.4     0.4    0.9

                                                ----------------------------------------------------------------------------
      Total Operating Expenses                   22.9    22.1   18.0    18.6    19.9   20.0    27.3    26.6    21.7  154.8
                                                ----------------------------------------------------------------------------
                                                ----------------------------------------------------------------------------
Cash Flow Available for Debt Service ($million)  36.1    38.2   41.8    38.6    38.3   37.7    27.4    29.0    33.6   84.1
                                                ----------------------------------------------------------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding             219.0   207.1  191.2   175.9   159.2  141.1   128.6   113.8    93.7   76.1
          Principal and Interest                 29.3    30.8   33.7    31.7    31.7   31.6    24.5    25.8    29.5   25.2
          LOC & Administrative Fees               0.3     0.3    0.3     0.3     0.3    0.3     0.2     0.3     0.3    0.2

                                                ----------------------------------------------------------------------------
      Total Debt Service                         29.6    31.1   34.0    32.0    32.0   31.9    24.8    26.0    29.7   25.5
                                                ----------------------------------------------------------------------------
Annual Debt Service Coverage                     1.22x   1.23x  1.23x   1.21x   1.20x  1.18x   1.11x   1.11x   1.13x  3.30x
                                                ----------------------------------------------------------------------------
<CAPTION>
                                                =============================
                                                       Post PPA Period
                                                -----------------------------
Year Ending December 31,                         2022    2023   2024    2025
                                                -----------------------------
<S>                                             <C>     <C>    <C>    <C>
Net Operating Revenues ($million)
      PPA Revenues                                  -       -      -       -
      Merchant Revenues                         378.9   389.7  391.5   416.2

                                                -----------------------------
      Total Operating Revenues                  378.9   389.7  391.5   416.2
                                                -----------------------------
                                                -----------------------------
Interest Earned on Accounts ($million)            0.3     0.6    0.3     0.2
                                                -----------------------------

Operating Expenses ($million)
      Fuel                                      230.2   240.2  238.1   250.3
      Fixed O&M                                  15.3    14.9   19.3    18.7
      Variable O&M                                4.2     4.4    9.1     7.9
      Administration                              0.5     0.5    0.5     0.6
      Insurance                                   1.9     2.0    2.0     2.1
      Property Taxes                              1.6     1.7    1.7     1.8
      Local Taxes                                 1.6     2.3    3.0     3.8

                                                -----------------------------
      Total Operating Expenses                  255.3   266.0  273.8   285.1
                                                -----------------------------
                                                -----------------------------
Cash Flow Available for Debt Service ($million) 123.8   124.2  118.1   131.3
                                                -----------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding              59.0    40.5   21.3     0.0
          Principal and Interest                 23.3    23.1   22.1    22.5
          LOC & Administrative Fees               0.2     0.2    0.2     0.2

                                                -----------------------------
      Total Debt Service                         23.6    23.3   22.3    22.7
                                                -----------------------------
Annual Debt Service Coverage                     5.26x   5.32x  5.29x   5.29x
                                                =============================
</TABLE>

* The first five months of 2021 include PPA cash flow and the last seven months
  of 2021 include Post PPA cash flow. The resulting blended DSCR is 3.30.

Average Debt Coverage During PPA                     1.24x

Minimum Debt Coverage During PPA                     1.11x

Average Debt Coverage Post PPA                       5.29x

Minimum Debt Coverage Post PPA                       5.26x

Average Debt Coverage During                         2.02x
   Bond Term

                                                                          B - 69
<PAGE>
                                                                    Confidential
                                    Exhibit I
                    AES Ironwood Projected Operating Results
                  Decreased Availability Sensitivity (Case #3)
<TABLE>
<CAPTION>
                                                                                     PPA Period
                                                ------------------------------------------------------------------------------------
Year Ending December 31,                         2001    2002   2003    2004    2005   2006    2007    2008    2009   2010    2011
                                                ------------------------------------------------------------------------------------
<S>                                             <C>     <C>    <C>     <C>     <C>    <C>     <C>     <C>     <C>    <C>     <C>
Net Operating Revenues ($million)
      PPA Revenues                               35.1    59.9   59.9    62.8    64.6   64.2    67.3    69.3    63.2   62.3    64.7
      Merchant Revenues                             -       -      -       -       -      -       -       -       -      -       -

                                                ------------------------------------------------------------------------------------
      Total Operating Revenues                   35.1    59.9   59.9    62.8    64.6   64.2    67.3    69.3    63.2   62.3    64.7
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Interest Earned on Accounts ($million)            0.1     0.2    0.2     0.2     0.2    0.2     0.2     0.3     0.2    0.3     0.5
                                                ------------------------------------------------------------------------------------

Operating Expenses ($million)
      Fuel                                          -       -      -       -       -      -       -       -       -      -       -
      Fixed O&M                                   7.0    13.1    9.4    10.7    12.3    9.8    11.6    13.4    11.2   10.6    10.6
      Variable O&M                                1.3     2.1    2.2     2.3     2.4    5.2     4.5     2.7     2.7    2.8     3.0
      Administration                              0.2     0.3    0.3     0.3     0.3    0.3     0.3     0.3     0.3    0.4     0.4
      Insurance                                     -     0.6    1.1     1.1     1.2    1.2     1.2     1.3     1.3    1.3     1.4
      Property Taxes                              0.5     0.9    0.9     1.0     1.0    1.0     1.1     1.1     1.1    1.2     1.2
      Local Taxes                                 0.0     0.0    0.1     0.1     0.1    0.1     0.2     0.2     0.3    0.3     0.3

                                                ------------------------------------------------------------------------------------
      Total Operating Expenses                    8.9    17.1   13.9    15.5    17.3   17.7    18.9    19.0    16.9   16.6    16.8
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Cash Flow Available for Debt Service ($million)  26.3    43.0   46.1    47.5    47.5   46.7    48.6    50.6    46.6   46.0    48.3
                                                ------------------------------------------------------------------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding             308.5   306.5  301.8   295.4   288.4  281.2   272.1   260.7   251.1  241.1   228.4
          Principal and Interest                 15.9    29.2   31.7    32.9    33.0   32.5    33.7    35.1    32.4   32.0    33.6
          LOC & Administrative Fees               0.4     0.3    0.3     0.3     0.3    0.3     0.3     0.3     0.3    0.3     0.3
                                                ------------------------------------------------------------------------------------
      Total Debt Service                         16.3    29.6   32.0    33.2    33.3   32.8    34.0    35.4    32.7   32.3    33.9
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Annual Debt Service Coverage                     1.61x   1.45x  1.44x   1.43x   1.43x  1.43x   1.43x   1.43x   1.42x  1.43x   1.42x
                                                ------------------------------------------------------------------------------------
<CAPTION>
                                                                                   PPA Period
                                                ----------------------------------------------------------------------------
Year Ending December 31,                         2012    2013   2014    2015    2016   2017    2018    2019    2020  2021*
                                                ----------------------------------------------------------------------------
<S>                                             <C>     <C>    <C>     <C>     <C>    <C>     <C>     <C>     <C>    <C>
Net Operating Revenues ($million)
      PPA Revenues                               64.6    66.4   66.2    63.8    65.2   64.8    61.8    63.3    63.4   26.4
      Merchant Revenues                             -       -      -       -       -      -       -       -       -  213.7

                                                ----------------------------------------------------------------------------
      Total Operating Revenues                   64.6    66.4   66.2    63.8    65.2   64.8    61.8    63.3    63.4  240.0
                                                ----------------------------------------------------------------------------
                                                ----------------------------------------------------------------------------
Interest Earned on Accounts ($million)            0.3     0.3    0.4     0.2     0.3    0.5     0.3     0.3     0.4    0.2
                                                ----------------------------------------------------------------------------

Operating Expenses ($million)
      Fuel                                          -       -      -       -       -      -       -       -       -  122.4
      Fixed O&M                                  13.2    13.5   11.5    11.6    12.9   12.5    15.6    16.2    13.7   13.6
      Variable O&M                                6.3     5.5    3.3     3.3     3.5    3.6     7.6     6.6     4.0    4.1
      Administration                              0.4     0.4    0.4     0.4     0.4    0.4     0.4     0.5     0.5    0.5
      Insurance                                   1.4     1.5    1.5     1.6     1.6    1.7     1.7     1.8     1.8    1.9
      Property Taxes                              1.2     1.3    1.3     1.3     1.4    1.4     1.5     1.5     1.5    1.6
      Local Taxes                                 0.2     0.2    0.3     0.3     0.4    0.4     0.4     0.4     0.4    0.9

                                                ----------------------------------------------------------------------------
      Total Operating Expenses                   22.8    22.3   18.2    18.6    20.2   20.1    27.2    26.9    22.0  144.9
                                                ----------------------------------------------------------------------------
                                                ----------------------------------------------------------------------------
Cash Flow Available for Debt Service ($million)  42.1    44.3   48.4    45.4    45.4   45.2    34.9    36.7    41.9   95.4
                                                ----------------------------------------------------------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding             219.0   207.1  191.2   175.9   159.2  141.1   128.6   113.8    93.7   76.1
          Principal and Interest                 29.3    30.8   33.7    31.7    31.7   31.6    24.5    25.8    29.5   25.2
          LOC & Administrative Fees               0.3     0.3    0.3     0.3     0.3    0.3     0.2     0.3     0.3    0.2

                                                ----------------------------------------------------------------------------
      Total Debt Service                         29.6    31.1   34.0    32.0    32.0   31.9    24.8    26.0    29.7   25.5
                                                ----------------------------------------------------------------------------
                                                ----------------------------------------------------------------------------
Annual Debt Service Coverage                     1.42x   1.42x  1.42x   1.42x   1.42x  1.42x   1.41x   1.41x   1.41x  3.74x
                                                ----------------------------------------------------------------------------
<CAPTION>
                                                =============================
                                                       Post PPA Period
                                                -----------------------------
Year Ending December 31,                         2022    2023   2024    2025
                                                -----------------------------
<S>                                             <C>     <C>    <C>     <C>
Net Operating Revenues ($million)
      PPA Revenues                               (0.1)      -      -       -
      Merchant Revenues                         373.5   381.8  387.8   411.3

                                                -----------------------------
      Total Operating Revenues                  373.4   381.8  387.8   411.3
                                                -----------------------------
                                                -----------------------------
Interest Earned on Accounts ($million)            0.3     0.6    0.3     0.2
                                                -----------------------------

Operating Expenses ($million)
      Fuel                                      215.8   223.4  224.2   235.1
      Fixed O&M                                  13.7    14.9   19.3    18.7
      Variable O&M                                4.2     4.3    9.0     7.8
      Administration                              0.5     0.5    0.5     0.6
      Insurance                                   1.9     2.0    2.0     2.1
      Property Taxes                              1.6     1.7    1.7     1.8
      Local Taxes                                 1.6     2.3    3.0     3.8

                                                -----------------------------
      Total Operating Expenses                  239.4   249.0  259.8   269.8
                                                -----------------------------
                                                -----------------------------
Cash Flow Available for Debt Service ($million) 134.3   133.3  128.3   141.7
                                                -----------------------------
Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding              59.0    40.5   21.3     0.0
          Principal and Interest                 23.3    23.1   22.1    22.5
          LOC & Administrative Fees               0.2     0.2    0.2     0.2

                                                -----------------------------
      Total Debt Service                         23.6    23.3   22.3    22.7
                                                -----------------------------
                                                -----------------------------
Annual Debt Service Coverage                     5.70x   5.71x  5.75x   5.71x
                                                =============================
</TABLE>

* The first five months of 2021 include PPA cash flow and the last seven months
  of 2021 include Post PPA cash flow. The resulting blended DSCR is 3.74.

Average Debt Coverage During PPA                     1.43x

Minimum Debt Coverage During PPA                     1.41x

Average Debt Coverage Post PPA                       5.73x

Minimum Debt Coverage Post PPA                       5.70x

Average Debt Coverage During                         2.26x
   Bond Term

                                                                          B - 70
<PAGE>
                                                                    Confidential
                                    Exhibit I
                    AES Ironwood Projected Operating Results
               Hagler Bailly High Gas Price Sensitivity (Case #4)
<TABLE>
<CAPTION>
                                                                                     PPA Period
                                                ------------------------------------------------------------------------------------
Year Ending December 31,                         2001    2002   2003    2004    2005   2006    2007    2008    2009   2010    2011
                                                ------------------------------------------------------------------------------------
<S>                                             <C>     <C>    <C>     <C>     <C>    <C>     <C>     <C>     <C>    <C>     <C>
Net Operating Revenues ($million)
      PPA Revenues                               34.8    59.4   59.6    62.5    64.3   63.9    67.0    68.8    62.6   61.8    64.3
      Merchant Revenues                             -       -      -       -       -      -       -       -       -      -       -

                                                ------------------------------------------------------------------------------------
      Total Operating Revenues                   34.8    59.4   59.6    62.5    64.3   63.9    67.0    68.8    62.6   61.8    64.3
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Interest Earned on Accounts ($million)            0.1     0.2    0.2     0.2     0.2    0.2     0.2     0.3     0.2    0.3     0.5
                                                ------------------------------------------------------------------------------------

Operating Expenses ($million)
      Fuel                                          -       -      -       -       -      -       -       -       -      -       -
      Fixed O&M                                   7.0    13.1    9.4    10.6    12.2    9.8    11.6    13.3    11.1   10.7    10.6
      Variable O&M                                1.2     2.0    2.1     2.2     2.3    5.1     4.4     2.5     2.5    2.7     2.8
      Administration                              0.2     0.3    0.3     0.3     0.3    0.3     0.3     0.3     0.3    0.4     0.4
      Insurance                                     -     0.6    1.1     1.1     1.2    1.2     1.2     1.3     1.3    1.3     1.4
      Property Taxes                              0.5     0.9    0.9     1.0     1.0    1.0     1.1     1.1     1.1    1.2     1.2
      Local Taxes                                 0.0     0.0    0.1     0.1     0.1    0.1     0.2     0.2     0.3    0.3     0.3

                                                ------------------------------------------------------------------------------------
      Total Operating Expenses                    8.9    17.0   13.8    15.3    17.1   17.5    18.8    18.8    16.6   16.4    16.6
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Cash Flow Available for Debt Service ($million)  26.0    42.6   45.9    47.4    47.4   46.6    48.4    50.4    46.2   45.7    48.1
                                                ------------------------------------------------------------------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding             308.5   306.5  301.8   295.4   288.4  281.2   272.1   260.7   251.1  241.1   228.4
          Principal and Interest                 15.9    29.2   31.7    32.9    33.0   32.5    33.7    35.1    32.4   32.0    33.6
          LOC & Administrative Fees               0.4     0.3    0.3     0.3     0.3    0.3     0.3     0.3     0.3    0.3     0.3

                                                ------------------------------------------------------------------------------------
      Total Debt Service                         16.3    29.6   32.0    33.2    33.3   32.8    34.0    35.4    32.7   32.3    33.9
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Annual Debt Service Coverage                     1.60x   1.44x  1.43x   1.43x   1.43x  1.42x   1.42x   1.42x   1.41x  1.42x   1.42x
                                                ------------------------------------------------------------------------------------
<CAPTION>
                                                                                   PPA Period
                                                ----------------------------------------------------------------------------
Year Ending December 31,                         2012    2013   2014    2015    2016   2017    2018    2019    2020  2021*
                                                ----------------------------------------------------------------------------
<S>                                             <C>     <C>    <C>     <C>     <C>    <C>     <C>     <C>     <C>    <C>
Net Operating Revenues ($million)
      PPA Revenues                               64.2    66.2   66.0    63.6    65.3   65.1    61.9    63.4    63.7   26.7
      Merchant Revenues                             -       -      -       -       -      -       -       -       -  225.7

                                                ----------------------------------------------------------------------------
      Total Operating Revenues                   64.2    66.2   66.0    63.6    65.3   65.1    61.9    63.4    63.7  252.3
                                                ----------------------------------------------------------------------------
                                                ----------------------------------------------------------------------------
Interest Earned on Accounts ($million)            0.3     0.3    0.4     0.2     0.3    0.5     0.3     0.3     0.4    0.2
                                                ----------------------------------------------------------------------------

Operating Expenses ($million)
      Fuel                                          -       -      -       -       -      -       -       -       -  141.6
      Fixed O&M                                  13.2    13.5   11.4    11.6    12.9   12.6    15.6    16.2    13.8   13.5
      Variable O&M                                6.2     5.3    3.1     3.2     3.4    3.5     7.5     6.5     3.9    4.0
      Administration                              0.4     0.4    0.4     0.4     0.4    0.4     0.4     0.5     0.5    0.5
      Insurance                                   1.4     1.5    1.5     1.6     1.6    1.7     1.7     1.8     1.8    1.9
      Property Taxes                              1.2     1.3    1.3     1.3     1.4    1.4     1.5     1.5     1.5    1.6
      Local Taxes                                 0.2     0.2    0.3     0.3     0.4    0.4     0.4     0.4     0.4    0.9

                                                ----------------------------------------------------------------------------
      Total Operating Expenses                   22.6    22.3   18.1    18.4    20.1   20.0    27.1    26.8    22.0  163.9
                                                ----------------------------------------------------------------------------
                                                ----------------------------------------------------------------------------
Cash Flow Available for Debt Service ($million)  41.9    44.2   48.4    45.4    45.5   45.6    35.2    36.8    42.2   88.6
                                                ----------------------------------------------------------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding             219.0   207.1  191.2   175.9   159.2  141.1   128.6   113.8    93.7   76.1
          Principal and Interest                 29.3    30.8   33.7    31.7    31.7   31.6    24.5    25.8    29.5   25.2
          LOC & Administrative Fees               0.3     0.3    0.3     0.3     0.3    0.3     0.2     0.3     0.3    0.2

                                                ----------------------------------------------------------------------------
      Total Debt Service                         29.6    31.1   34.0    32.0    32.0   31.9    24.8    26.0    29.7   25.5
                                                ----------------------------------------------------------------------------
                                                ----------------------------------------------------------------------------
Annual Debt Service Coverage                     1.42x   1.42x  1.42x   1.42x   1.42x  1.43x   1.42x   1.41x   1.42x  3.48x
                                                ----------------------------------------------------------------------------
<CAPTION>
                                                =============================
                                                       Post PPA Period
                                                -----------------------------
Year Ending December 31,                         2022    2023   2024    2025
                                                -----------------------------
<S>                                             <C>     <C>    <C>     <C>
Net Operating Revenues ($million)
      PPA Revenues                                  -       -      -       -
      Merchant Revenues                         398.8   407.0  405.7   432.2

                                                -----------------------------
      Total Operating Revenues                  398.8   407.0  405.7   432.2
                                                -----------------------------
                                                -----------------------------
Interest Earned on Accounts ($million)            0.3     0.6    0.3     0.2
                                                -----------------------------

Operating Expenses ($million)
      Fuel                                      251.5   261.6  259.5   273.5
      Fixed O&M                                  13.7    14.9   19.3    18.7
      Variable O&M                                4.2     4.3    9.0     7.9
      Administration                              0.5     0.5    0.5     0.6
      Insurance                                   1.9     2.0    2.0     2.1
      Property Taxes                              1.6     1.7    1.7     1.8
      Local Taxes                                 1.6     2.3    3.0     3.8

                                                -----------------------------
      Total Operating Expenses                  275.0   287.3  295.1   308.2
                                                -----------------------------
                                                -----------------------------
Cash Flow Available for Debt Service ($million) 124.2   120.3  110.9   124.2
                                                -----------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding              59.0    40.5   21.3     0.0
          Principal and Interest                 23.3    23.1   22.1    22.5
          LOC & Administrative Fees               0.2     0.2    0.2     0.2

                                                -----------------------------
      Total Debt Service                         23.6    23.3   22.3    22.7
                                                -----------------------------
                                                -----------------------------
Annual Debt Service Coverage                     5.27x   5.15x  4.98x   5.00x
                                                =============================
</TABLE>

* The first five months of 2021 include PPA cash flow and the last seven months
  of 2021 include Post PPA cash flow. The resulting blended DSCR is 3.48.

Average Debt Coverage During PPA                     1.43x

Minimum Debt Coverage During PPA                     1.41x

Average Debt Coverage Post PPA                       5.13x

Minimum Debt Coverage Post PPA                       4.98x

Average Debt Coverage During                         2.14x
   Bond Term

                                                                          B - 71
<PAGE>
                                                                    Confidential
                                    Exhibit I
                    AES Ironwood Projected Operating Results
              Hagler Bailly Low Demand Growth Sensitivity (Case #5)
<TABLE>
<CAPTION>
                                                                                     PPA Period
                                                ------------------------------------------------------------------------------------
Year Ending December 31,                         2001    2002   2003    2004    2005   2006    2007    2008    2009   2010    2011
                                                ------------------------------------------------------------------------------------
<S>                                             <C>     <C>    <C>     <C>     <C>    <C>     <C>     <C>     <C>    <C>     <C>
Net Operating Revenues ($million)
      PPA Revenues                               35.1    60.2   60.4    63.4    65.4   65.0    68.0    70.1    64.1   63.1    65.5
      Merchant Revenues                             -       -      -       -       -      -       -       -       -      -       -

                                                ------------------------------------------------------------------------------------
      Total Operating Revenues                   35.1    60.2   60.4    63.4    65.4   65.0    68.0    70.1    64.1   63.1    65.5
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Interest Earned on Accounts ($million)            0.1     0.2    0.2     0.2     0.2    0.2     0.2     0.3     0.2    0.3     0.5
                                                ------------------------------------------------------------------------------------

Operating Expenses ($million)
      Fuel                                          -       -      -       -       -      -       -       -       -      -       -
      Fixed O&M                                   7.0    13.2    9.5    10.6    12.3    9.8    11.5    13.4    11.2   10.6    10.6
      Variable O&M                                1.3     2.1    2.2     2.3     2.4    5.2     4.5     2.7     2.7    2.8     3.0
      Administration                              0.2     0.3    0.3     0.3     0.3    0.3     0.3     0.3     0.3    0.4     0.4
      Insurance                                     -     0.6    1.1     1.1     1.2    1.2     1.2     1.3     1.3    1.3     1.4
      Property Taxes                              0.5     0.9    0.9     1.0     1.0    1.0     1.1     1.1     1.1    1.2     1.2
      Local Taxes                                 0.0     0.0    0.1     0.1     0.1    0.1     0.2     0.2     0.3    0.3     0.3

                                                ------------------------------------------------------------------------------------
      Total Operating Expenses                    8.9    17.2   14.1    15.4    17.3   17.7    18.9    19.0    16.9   16.6    16.8
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Cash Flow Available for Debt Service ($million)  26.3    43.2   46.6    48.2    48.3   47.5    49.4    51.4    47.4   46.8    49.2
                                                ------------------------------------------------------------------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding             308.5   306.5  301.8   295.4   288.4  281.2   272.1   260.7   251.1  241.1   228.4
          Principal and Interest                 15.9    29.2   31.7    32.9    33.0   32.5    33.7    35.1    32.4   32.0    33.6
          LOC & Administrative Fees               0.4     0.3    0.3     0.3     0.3    0.3     0.3     0.3     0.3    0.3     0.3

                                                ------------------------------------------------------------------------------------
      Total Debt Service                         16.3    29.6   32.0    33.2    33.3   32.8    34.0    35.4    32.7   32.3    33.9
                                                ------------------------------------------------------------------------------------
                                                ------------------------------------------------------------------------------------
Annual Debt Service Coverage                     1.61x   1.46x  1.45x   1.45x   1.45x  1.45x   1.45x   1.45x   1.45x  1.45x   1.45x
                                                ------------------------------------------------------------------------------------
<CAPTION>
                                                                                   PPA Period
                                                ----------------------------------------------------------------------------
Year Ending December 31,                         2012    2013   2014    2015    2016   2017    2018    2019    2020  2021*
                                                ----------------------------------------------------------------------------
<S>                                             <C>     <C>    <C>     <C>     <C>    <C>     <C>     <C>     <C>    <C>
Net Operating Revenues ($million)
      PPA Revenues                               65.6    67.3   67.1    64.8    66.2   65.8    62.8    64.2    64.3   27.3
      Merchant Revenues                             -       -      -       -       -      -       -       -       -  203.5

                                                ----------------------------------------------------------------------------
      Total Operating Revenues                   65.6    67.3   67.1    64.8    66.2   65.8    62.8    64.2    64.3  230.7
                                                ----------------------------------------------------------------------------
                                                ----------------------------------------------------------------------------
Interest Earned on Accounts ($million)            0.3     0.3    0.4     0.2     0.3    0.5     0.3     0.3     0.4    0.2
                                                ----------------------------------------------------------------------------

Operating Expenses ($million)
      Fuel                                          -       -      -       -       -      -       -       -       -  122.8
      Fixed O&M                                  13.3    13.5   11.5    11.7    12.8   12.6    15.6    16.1    13.7   13.6
      Variable O&M                                6.3     5.5    3.3     3.3     3.5    3.6     7.6     6.6     4.0    4.1
      Administration                              0.4     0.4    0.4     0.4     0.4    0.4     0.4     0.5     0.5    0.5
      Insurance                                   1.4     1.5    1.5     1.6     1.6    1.7     1.7     1.8     1.8    1.9
      Property Taxes                              1.2     1.3    1.3     1.3     1.4    1.4     1.5     1.5     1.5    1.6
      Local Taxes                                 0.2     0.2    0.3     0.3     0.4    0.4     0.4     0.4     0.4    0.9

                                                ----------------------------------------------------------------------------
      Total Operating Expenses                   22.9    22.3   18.2    18.7    20.1   20.1    27.2    26.8    22.0  145.3
                                                ----------------------------------------------------------------------------
                                                ----------------------------------------------------------------------------
Cash Flow Available for Debt Service ($million)  43.0    45.3   49.3    46.4    46.4   46.2    35.9    37.6    42.8   85.7
                                                ----------------------------------------------------------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding             219.0   207.1  191.2   175.9   159.2  141.1   128.6   113.8    93.7   76.1
          Principal and Interest                 29.3    30.8   33.7    31.7    31.7   31.6    24.5    25.8    29.5   25.2
          LOC & Administrative Fees               0.3     0.3    0.3     0.3     0.3    0.3     0.2     0.3     0.3    0.2

                                                ----------------------------------------------------------------------------
      Total Debt Service                         29.6    31.1   34.0    32.0    32.0   31.9    24.8    26.0    29.7   25.5
                                                ----------------------------------------------------------------------------
                                                ----------------------------------------------------------------------------
Annual Debt Service Coverage                     1.45x   1.45x  1.45x   1.45x   1.45x  1.45x   1.45x   1.44x   1.44x  3.36x
                                                ----------------------------------------------------------------------------
<CAPTION>
                                                =============================
                                                       Post PPA Period
                                                -----------------------------
Year Ending December 31,                         2022    2023   2024    2025
                                                -----------------------------
<S>                                             <C>     <C>    <C>     <C>
Net Operating Revenues ($million)
      PPA Revenues                                  -       -      -       -
      Merchant Revenues                         359.0   370.1  367.6   385.8

                                                -----------------------------
      Total Operating Revenues                  359.0   370.1  367.6   385.8
                                                -----------------------------
                                                -----------------------------
Interest Earned on Accounts ($million)            0.3     0.6    0.3     0.2
                                                -----------------------------

Operating Expenses ($million)
      Fuel                                      217.6   226.3  224.1   234.7
      Fixed O&M                                  13.5    14.9   19.3    18.7
      Variable O&M                                4.2     4.3    9.0     7.8
      Administration                              0.5     0.5    0.5     0.6
      Insurance                                   1.9     2.0    2.0     2.1
      Property Taxes                              1.6     1.7    1.7     1.8
      Local Taxes                                 1.6     2.3    3.0     3.8

                                                -----------------------------
      Total Operating Expenses                  240.9   252.0  259.7   269.4
                                                -----------------------------
                                                -----------------------------
Cash Flow Available for Debt Service ($million) 118.4   118.6  108.3   116.6
                                                -----------------------------

Annual Debt Service ($million)
      Facility Bonds
          B-O-Y Balance Outstanding              59.0    40.5   21.3     0.0
          Principal and Interest                 23.3    23.1   22.1    22.5
          LOC & Administrative Fees               0.2     0.2    0.2     0.2

                                                -----------------------------
      Total Debt Service                         23.6    23.3   22.3    22.7
                                                -----------------------------
                                                -----------------------------
Annual Debt Service Coverage                     5.03x   5.08x  4.86x   4.70x
                                                =============================
</TABLE>

* The first five months of 2021 include PPA cash flow and the last seven months
  of 2021 include Post PPA cash flow. The resulting blended DSCR is 3.36.

Average Debt Coverage During PPA                     1.46x

Minimum Debt Coverage During PPA                     1.44x

Average Debt Coverage Post PPA                       4.93x

Minimum Debt Coverage Post PPA                       4.70x

Average Debt Coverage During                         2.13x
   Bond Term
                                                                          B - 72

<PAGE>

[GRAPHIC OMITTED]

Stone & Webster                                             AES Ironwood Project
Management Consultants, Inc.                        Independent Technical Review
- --------------------------------------------------------------------------------




                                   Exhibit II

                                  Document Log











                                     B - 73
<PAGE>

[GRAPHIC OMITTED]

Stone & Webster                                             AES Ironwood Project
Management Consultants, Inc.                        Independent Technical Review
- --------------------------------------------------------------------------------

                                   Exhibit II

                                  Document Log

- --------------------------------------------------------------------------------
No.      Reference
- --------------------------------------------------------------------------------
1.       Draft property lease between Consolidated Rail Corporation and AES
         Ironwood
- --------------------------------------------------------------------------------
2.       Draft Sidetrack Agreement between Consolidated Rail Corporation and AES
         Ironwood
- --------------------------------------------------------------------------------
3.       Draft Rail Corporation License Agreement for Undergrade Watermain
         Occupation
- --------------------------------------------------------------------------------
4.       Agreement relating to real estate dated October 22, 1998
- --------------------------------------------------------------------------------
5.       EWG Application
- --------------------------------------------------------------------------------
6.       Effluent Supply Agreement
- --------------------------------------------------------------------------------
7.       Amended and Restated Operating Agreement of PJM Interconnection, LLC
         dated June 2, 1997
- --------------------------------------------------------------------------------
8.       Maintenance Program Parts, Shop Repairs and Scheduled Outage TFA
         Services Contract last revised November 19, 1998
- --------------------------------------------------------------------------------
9.       Draft Generation Facility Transmission Interconnection Agreement
         between Metropolitan Edison Company d/b/a AES Ironwood LLC
- --------------------------------------------------------------------------------
10.      Amended and Restated Power Purchase Agreement by and between AES
         Ironwood LLC and Williams Energy Marketing & Trading Company
- --------------------------------------------------------------------------------
11.      Agreement for Engineering, Procurement and Construction Services
         between AES Ironwood, Inc. ("Owner") and Siemens Westinghouse Power
         Corporation dated September 23, 1998
- --------------------------------------------------------------------------------
12.      Report on MHI 501G for KEPCO Ilijan Power Project
- --------------------------------------------------------------------------------
13.      Draft report on MHI 501G Combustion Turbine Generator dated December
         14, 1998
- --------------------------------------------------------------------------------
14.      Hagler Bailly Report prepared for Lehman Brothers on the Projected
         Competitiveness of the Ironwood Power Project in the PJM Market dated
         February 1999 and draft report dated October 1998
- --------------------------------------------------------------------------------
15.      Agreement for Engineering, Procurement and Construction Services
- --------------------------------------------------------------------------------
16.      EPC Appendix A
- --------------------------------------------------------------------------------
17.      Effluent Supply Agreement with City of Lebanon Authority
- --------------------------------------------------------------------------------
18.      Maintenance Program Parts, Shop Repairs and Scheduled Outage TFA
         Services Contract
- --------------------------------------------------------------------------------
19.      SWPC Engineering Flow Schematics Drawings F8210010-F8210480-10/01/98
- --------------------------------------------------------------------------------
20.      NPDES Permit # PAR-10-P082
- --------------------------------------------------------------------------------
21.      Letter dated November 18, 1998 from K. Friederich Updergrafe to Ian
         Miller re POTW Water Supply Pipeline and Pumping Station
- --------------------------------------------------------------------------------
22.      Fax to Debra Richert dated April 22, 1999 from Alicia Sinn re the final
         plan approval for the Ironwood facility issued by PaDEP on 3/29/99
- --------------------------------------------------------------------------------
23.      Copy of letter to Patricia Rollin dated February 3, 1999 concerning the
         Delay in Financial Closing
- --------------------------------------------------------------------------------
24.      Letter to John Garvey from Jeffrey Jacobsohn dated November 16, 1998 re
         the Facility Emission Rates for PSD Application
- --------------------------------------------------------------------------------
25.      Memo to John Garvey from Bart Rossi dated November 25, 1998 regarding
         the AES Ironwood Emissions Data
- --------------------------------------------------------------------------------
26.      Specification For A Heat Recovery Steam Generator for the AES Ironwood
         Project received by SWMCI in Boston on February 24, 1999
- --------------------------------------------------------------------------------
27.      Williams Fuel Plan for AES Ironwood fax dated February 5, 1999
- --------------------------------------------------------------------------------
28.      Fax to John Garvey from Ian Miller dated March 12, 1999 regarding the
         Gas Pressure and Compressors
- --------------------------------------------------------------------------------
29.      Fax copy of the PJM Regional Fuel Forecast 1998 - 2031 for AES Ironwood
         dated January 19, 1999
- --------------------------------------------------------------------------------

                                     B - 74
<PAGE>
[GRAPHIC OMITTED]

Stone & Webster                                             AES Ironwood Project
Management Consultants, Inc.                        Independent Technical Review
- --------------------------------------------------------------------------------


- --------------------------------------------------------------------------------
30.      Draft Evaluation Report of Oil Combustion profile for AES Ironwood
         Prepared for AES Corporation by CC Pace Resources dated February 25,
         1999
- --------------------------------------------------------------------------------
31.      Letter to Bart Rossi from Jeffrey Jacobsohn regarding Stone & Webster's
         questions dated March 2, 1999 received by fax
- --------------------------------------------------------------------------------
32.      Letter to Bart Rossi from Jeffrey Jacobsohn regarding Combustion
         Turbine degradation dated March 1, 1999 received by fax
- --------------------------------------------------------------------------------
33.      Fax from Gary Dzikowski to Ian Miller regarding DLN Combustors dated
         February 16, 1999
- --------------------------------------------------------------------------------
34.      Fax from Jeffrey Jacobsohn to Bart Rossi regarding the Revised Warranty
         Data sheet dated February 12, 1999 received by Fax
- --------------------------------------------------------------------------------
35.      Letter to Steve Dahm from Jeffrey M. Jacobsohn dated January 29, 1999
         regarding Information for Financial Closing received by Fax
- --------------------------------------------------------------------------------
36.      Faxed memo dated January 19, 1999 from Siemens Westinghouse concerning
         Stone & Webster Issues
- --------------------------------------------------------------------------------
37.      Faxed memo dated January 21, 1999 from Gary Dzikowski at Siemens
         Westinghouse to Ian Miller concerning Fleet Risk Management Spares
         received by Fax
- --------------------------------------------------------------------------------
38.      Letter dated December 11, 1998 to John Garvey from Jeffrey M. Jacobsohn
         regarding Degradation of the Combustion Turbine
- --------------------------------------------------------------------------------
39.      Fax memo to John Garvey from Jeff Jacobsohn dated December 2, 1998
         regarding the revised Heat Balance information
- --------------------------------------------------------------------------------
40.      Letter dated November 16, 1998 to John Garvey from Jeffrey Jacobsohn
         regarding the Facility Emission Rates for PSD Application
- --------------------------------------------------------------------------------
41.      Letter dated November 12, 1998 to John Garvey from Jeffrey Jacobsohn
         regarding Additional Responses to Various S&W information requests
- --------------------------------------------------------------------------------
42.      Letter dated November 4, 1998 to John Garvey from Jeffrey Jacobsohn
         regarding Responses to S&W AES Ironwood Additional Information Requests
         from S&W dated November 3, 1998
- --------------------------------------------------------------------------------
43.      Letter received from Jeffrey M. Jacobsohn in response to a S&W fax
         dated October 29, 1998 regarding water balances
- --------------------------------------------------------------------------------
44.      Letter to John Garvey dated November 3, 1998 from Jeffrey Jacobsohn
         regarding Responses to S&W Request for Additional Information on a
         letter and fax dated October 29, 1998
- --------------------------------------------------------------------------------
45.      Letter to John Garvey dated November 5, 1998 in response to our letter
         for IE Information in our letter dated October 28, 1998
- --------------------------------------------------------------------------------
46.      Letter to John Garvey in response to our Letter Dated October 26, 1998
         for additional information regarding Technical Questions
- --------------------------------------------------------------------------------
47.      Letter to Robert Golden dated December 7, 1998 with a copy to John
         Garvey enclosing one set each of the approved Land Development Plan for
         Prescott Road
- --------------------------------------------------------------------------------
48.      Fax to John Garvey from Eileen Cates transmitting the Outstanding
         Issues dated January 29, 1999
- --------------------------------------------------------------------------------
49.      Memo from Gary Dzikowski to Ian Miller dated January 14, 1999 providing
         responses to questions concerning the HRSG Spec
- --------------------------------------------------------------------------------
50.      Memo from Ian Miller to Gary Dzikowski dated December 14, 1998
         regarding ZDS and demin water.
- --------------------------------------------------------------------------------
51.      Letter from Patricia Rollin to GPU Energy dated January 11, 1999
         concerning the AES Ironwood Interconnection
- --------------------------------------------------------------------------------
52.      Letter to Patricia Rollin from GPU Energy referring to the letter of
         January 11, 1999 concerning the AES Ironwood Interconnection
- --------------------------------------------------------------------------------
53.      Letter to Steve Dahm from Jeffrey Jacobsohn regarding the minutes of
         January 21, 1999 meeting
- --------------------------------------------------------------------------------
54.      Letter dated January 26, 1999 to Ian Miller from GPU regarding the
         Preliminary Interconnection facilities Cost
- --------------------------------------------------------------------------------
                                     B - 75
<PAGE>

[GRAPHIC OMITTED]

Stone & Webster                                             AES Ironwood Project
Management Consultants, Inc.                        Independent Technical Review
- --------------------------------------------------------------------------------



- --------------------------------------------------------------------------------
55.      Letter dated March 3, 1999 to John Garvey from Anthony P. Letizia at
         TRC regarding the confirmation of Revised Pennsylvania Title 25 Chapter
         139
- --------------------------------------------------------------------------------
56.      Letter to Ian Miller dated October 7, 1998 from the Lebanon County
         Conservation District concerning the General Permit Issuance, NPDES
         Permit #: PAR-10-PO82
- --------------------------------------------------------------------------------
57.      Fax copy of the Petition for an interpretation and variance dated
         February 11, 1998
- --------------------------------------------------------------------------------
58.      Letter to Buck Applewhite & John Garvey dated September 30, 1998 from
         Eileen Cates dated September 30, 1998 concerning the technical
         information that will be used for this report
- --------------------------------------------------------------------------------
59.      Copy of a fax listing the required permits and approvals for AES
         Ironwood dated November 6, 1998
- -------------------------------------------------------------------------------
60.      Letter from Paula B. Ballaron to Patricia L. Rollin from the
         Susquehanna River Basin Commission approving the project
- --------------------------------------------------------------------------------
61.      Notice of Commission Action Docket NoD-97-45 for the Surface Water
         Withdrawal/Importation
- --------------------------------------------------------------------------------
62.      Letter received by fax dated April 22, 1999 from the United States
         Environmental Protection Agency regarding the review of the draft plan
         approval for AES Ironwood
- --------------------------------------------------------------------------------
63.      Letter received dated April 7, 1999 between Jeffrey Jacobsohn and
         Patrician Rollin regarding AES Ironwood Payment Schedule Revision I
         Letter Agreement
- --------------------------------------------------------------------------------
64.      Letter received dated March 31, 1999 between Jeffrey Jacobsohn and
         Patricia Rollin regarding AES Ironwood Financial Closing Later than
         March 31, 1999 Continued Performance Letter Agreement
- --------------------------------------------------------------------------------
65.      Letter dated March 24, 1999 to Bart Rossi from Jeffrey M. Jacobsohn re
         CO Catalyst Emissions Warrantly
- --------------------------------------------------------------------------------
66.      Letter dated April 22, 1999 to Patricia Rollin from Jeffrey M.
         Jacobsohn re Gas Specifications Clarification Letter
- --------------------------------------------------------------------------------
67.      Letter dated May 12, 1999 to Patricia Rollin from Jeffrey Jacobsohn re
         Delay in Commencement Date after June 1, 1999
- --------------------------------------------------------------------------------
68.      Letter dated May 19, 1999 to Patricia Rollin from Philip Scalzo re
         Williams executed certain agreements with Texas Eastern Transmission
         Corporation
- --------------------------------------------------------------------------------
69.      Memo from Jeffrey Jacobsohn of SWPC to Patty Rollin of AES concerning
         the estimated performance impact of the gas compressor deletion
- --------------------------------------------------------------------------------


                                     B - 76

<PAGE>

         ------------------------------------------------------------

                                   ANNEX C

                              INDEPENDENT POWER
                             CONSULTANT'S REPORT

         ------------------------------------------------------------
<PAGE>

                           PROJECTED COMPETITIVENESS
                          OF THE IRONWOOD POWER PLANT
                               IN THE PJM MARKET


                          Privileged and Confidential


                                  Prepared for:

                                 Lehman Brothers
                            3 World Financial Center
                             New York, NY 10285-1600


                                  Prepared by:


                         Hagler Bailly Consulting, Inc.
                               1776 Eye Street, NW
                                    Suite 500
                              Washington, DC 20006
                                 (202) 223-6665


                                    Contact:
                                 Alan L. Madian


                                  June 1, 1999

                                      C-1
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

- --------------------------------------------------------------------------------

                                    CONTENTS
<TABLE>
<S>                                                                                                            <C>
Foreword          ................................................................................................6

Executive Summary

         S.1      The Project.....................................................................................7
         S.2      PJM Market Structure............................................................................7
                  S.2.1    Procedure..............................................................................8
         S.3      Key Base Case Assumptions and Sensitivity Cases.................................................9
         S.4      Forecasted Results.............................................................................11
         S.5      Conclusions....................................................................................17

Chapter 1         Introduction

         1.1      Background.....................................................................................18
         1.2      Organization of the Report.....................................................................18

Chapter 2         Ironwood Project

         2.1      The Ironwood Project...........................................................................20

Chapter 3         Proposed Market Structure In PJM

         3.1      Background.....................................................................................22
         3.2      The PJM Market.................................................................................23
                  3.2.1    The Spot Energy Market................................................................23
                  3.2.2    Installed Capacity Market.............................................................25

Chapter 4         Approach To Market Price Forecasting

         4.1      Introduction...................................................................................27
         4.2      Issues in Predicting Market Prices.............................................................27
                  4.2.1    Issues in the Capacity Markets........................................................27
                  4.2.2    Ancillary Services....................................................................29
         4.3      Approach to Market Price Forecasting...........................................................30
                  4.3.1    Market Characteristics................................................................31
                  4.3.2    Predicting Energy Prices and Dispatch.................................................31
                  4.3.3    Predicting Capacity Prices: The Capacity Market Simulation Model......................32
                  4.3.4    Market Entry and Exit.................................................................33
</TABLE>

                                      C-2
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

- --------------------------------------------------------------------------------
<TABLE>
<S>                                                                                                             <C>
Chapter 5         Market Price Forecasting: Assumptions and Assumption Development

         5.1      Introduction...................................................................................35
         5.2      Production Cost Model Input Assumptions........................................................35
                  5.2.1    Existing Generation Units.............................................................37
                  5.2.2    Load Growth...........................................................................40
                  5.2.3    Fuel Prices...........................................................................42
                  5.2.4    Energy Import/Export Forecast.........................................................44
                  5.2.5    Transmission Constraints..............................................................45
         5.3      Capacity Market Simulation:  Model Input Assumptions...........................................46
                  5.3.1    Existing Units Going-Forward Costs....................................................46
                  5.3.2    New Generating Capacity...............................................................47

Chapter 6         Market Price Forecasts

         6.1      Introduction...................................................................................49
         6.2      PJM Capacity and Energy Price Forecasts........................................................49
                  6.2.1    Base Case.............................................................................49
         6.3      Implications for AES Ironwood..................................................................56

Chapter 7         Conclusions....................................................................................62
</TABLE>

                                      C-3
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

- --------------------------------------------------------------------------------
                                     TABLES
<TABLE>
<S>                                                                                                             <C>
Executive Summary

         S.1      Delivered Fuel Prices (1996 $/MMBtu)...........................................................10
         S.2      PJM All-In Average (Energy + Capacity) Prices (1996 $).........................................12

Chapter 5         Market Price Forecasting: Assumptions and Assumption Development

         5.1      Variable Operating Costs (1996 $ per MWh)......................................................38
         5.2      Nuclear Unit Retirement Dates..................................................................40
         5.3      Delivered Fuel Prices (1996 $/MMBtu)...........................................................42
         5.4      Imports and Exports (1996 $ per MWh)...........................................................45
         5.5      Emergency Imports..............................................................................45
         5.6      New Generating Unit Characteristics (1996 $)...................................................48

Chapter 6         Market Price Forecasts

         6.1      PJM Capacity Additions and Retirements.........................................................51
         6.2      PJM Unweighted Average Energy Prices (1996 $/MWh)..............................................53
         6.3      PJM Capacity Prices (1996 $/kW-yr).............................................................54
         6.4      PJM All-In Average (Energy + Capacity) Prices (1996 $).........................................55
</TABLE>

                                      C-4
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

- --------------------------------------------------------------------------------
                                     FIGURES
<TABLE>
<S>                                                                                                              <C>
Executive Summary

         S.1      PJM Unweighted Average Energy Prices 1996 $....................................................13
         S.2      AES Ironwood Capacity Factors..................................................................14
         S.3      PJM Supply Curves (1996 $/MWh).................................................................15

Chapter 4         Approach to Market Price Forecasting

         4.1      Approach to Developing Capacity and Energy Prices..............................................30
         4.2      Example Supply and Demand Curve................................................................33

Chapter 5         Market Price Forecasting: Assumptions and Assumption Development

         5.1      Forecast of Allowance Prices (1996 $ per Ton)..................................................39
         5.2      Cumulative Demand Growth in PJM................................................................41
         5.3      Delivered Natural Gas Prices 1996 $............................................................43
         5.4      PJM Generation Weighted Average Delivered Coal Prices 1996 $...................................44

Chapter 6         Market Price Forecasts

         6.1      PJM Unweighted Average Energy Prices 1996 $....................................................52
         6.2      AES Ironwood Capacity Factors..................................................................56
         6.3      Ironwood's Energy Revenue vs. PJM's Time-Weighted Average
                  Energy Price 1996 $ ...........................................................................58
         6.4      PJM Supply Curves (1996 $/MWh)..............................................................59-61
</TABLE>

                                      C-5
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

- --------------------------------------------------------------------------------

                                    FOREWORD

This report presents Hagler Bailly's analysis of the market for power in the
Pennsylvania, New Jersey, Maryland (PJM) power pool.

i.       Some information in the report is necessarily based on predications and
         estimates of future events and behaviors.

ii.      Such predictions or estimates may differ from that which other experts
         specializing in the electricity industry might present.

iii.     The provision of a report by Hagler Bailly does not obviate the need
         for potential investors to make further appropriate inquiries as to the
         accuracy of the information included therein, or to undertake an
         analysis of its own.

iv.      This report is not intended to be a complete and exhaustive analysis of
         the subject issues and therefore will not consider some factors that
         are important to a potential investor's decision-making.

v.       Hagler Bailly and its employees cannot accept liability for loss
         suffered in consequence of reliance on the report. Nothing in our
         report should be taken as a promise or guarantee as to the occurrence
         of any future events.

                                 FOREWORD o C-6
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

- --------------------------------------------------------------------------------
                                EXECUTIVE SUMMARY

Hagler Bailly Consulting, Inc. (Hagler Bailly) was retained by AES Ironwood,
Inc., on behalf of, and to prepare this report solely for, Lehman Brothers, as
Initial Purchaser of certain Rule 144A bonds to be offered by AES Ironwood, LLC
to finance the construction, initial start-up and testing of the Ironwood
facility. We have been retained to independently forecast future market prices
for electric capacity and energy in the Pennsylvania, New Jersey, Maryland (PJM)
power pool and to assess the competitive position of the AES Ironwood Facility
in PJM during the term of the bonds. This document presents the results of our
analysis.

S.1      THE PROJECT

AES Ironwood, LLC ("AES Ironwood"), a wholly owned subsidiary of the AES
Corporation ("AES"), proposes to build and operate a 705 MW (net) gas
combined-cycle power station ("the Project"). The AES Ironwood power station
will employ Siemens Westinghouse 5O1G technology and will be fueled primarily by
natural gas. The facility will sell its entire output to the Williams Energy
Marketing and Trading Company under a fixed price 20 year power purchase
agreement ("PPA") and will operate as a merchant plant (or under bilateral
contracts) from the expiration of the PPA. The facility will be located in South
Lebanon Township, Pennsylvania in the Central region of the Pennsylvania, New
Jersey, Maryland (PJM) power pool.

S.2      PJM MARKET STRUCTURE

The PJM market may be characterized on the supply side as competitive except for
the limited hours when transmission is constrained. New capacity is expected to
be composed predominantly of gas-fueled combined cycle units, though simple
cycle combustion turbines ("peakers") will be added, especially in areas with
substantial base load capacity.

We have modeled the future PJM market with both an energy market and a capacity
market. This is not to say that a separate capacity market will necessarily
continue well into the future. However, in the absence of a separate installed
capacity market, an at least equivalent revenue increase would be required in
the energy or ancillary services market to maintain reserve margins at levels
prospectively thought to be essential by system operators and regulators.

                                 FOREWORD o C-7
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

We have assumed that energy market participants will base dispatch and payment
in the PJM market upon competitive energy bidding and that the bidding will
shortly cease to be cost-based for investor owned utilities (IOUs), as is
currently required by regulation.

The PJM Independent System Operator (ISO), which became operational at the
beginning of 1998, has set reserve generation capacity requirements on all
load-serving entities (LSEs). These reserve requirements require that
load-serving entities that are short of capacity acquire it from others. The PJM
ISO has established a capacity market to facilitate capacity provision but
bilateral arrangements are also accommodated.

Transmission constraints within PJM play a modest role in the operation of the
PJM market. There are three defined regions within PJM, West, Central, and East
(see Maps 5-1 and 5-2). Each of the historic utilities functions as a control
area. Nodal pricing (i.e., pricing that reflects location-specific factors, such
as transmission constraints) has been implemented recently. The direction of
power flow within PJM is generally from the west, which has a preponderance of
the pool's lower-cost coal units, to the east. Transmission capacity is not
expected to expand significantly within PJM, but no additional important
constraints are forecast.

S.2.1    Procedure

In our analysis, we have used the RealTime(TM) model to simulate future market
conditions and operation. RealTime(TM), a chronological production cost model,
was used to estimate energy prices and revenues through the year 2025. In each
hour the model schedules the units in a least-cost manner based upon fuel cost,
start-up cost, emission cost, and variable O&M cost. The hourly marginal cost is
determined by the cost of the least-expensive unit available to follow
increasing load, which becomes the market price for that hour. Given that
production cost modeling is inherently cost-based, conservative adjustments were
made to the model to account for expected upward pressure on price resulting
from the evolving bid-based system and market power phenomena./1

PowerWorld(TM), a load flow model, was used to determine if Ironwood would
impose additional burdens on the PJM transmission system and if the plant's
location would lead to its being dispatched less than anticipated due to
transmission constraints. The model was also used to assess whether Ironwood
could expect to receive higher revenues due to contributions to voltage support
or for transmission constraint-reducing flows.

To address capacity revenue requirements, Hagler Bailly utilized a model that
calculates the additional revenue, above that earned from energy sales, needed
to meet the revenue requirement

- ----------
1        Market power occurs when strategic behavior is possible. This can
         occur, for example, when a single plant bids just under the price of
         the next highest cost plant in the stack, or when operators of multiple
         plants withdraw one or more in order to increase the total revenue they
         will receive from those that remain on. Market power can be the result
         of collusion, but collusion is not necessary for market power to be
         present.

                                 FOREWORD o C-8
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

of the marginal plant entering the market. Plants at the end of their useful
lives, and those that do not recover their going-forward costs are retired.
Based on that model, we have estimated capacity payments necessary to maintain
an installed capacity margin of approximately 18 percent including the PJM
authorized curtailable load margin. The revenue requirement of a new plant
equals the net revenue needed to cover operating costs, taxes, interest and
payment of a target return on equity.

The results from these models provide the basis for the evaluation of the
competitiveness of the Ironwood plant during and after the PPA period, including
the determination of the PJM market revenues to AES Ironwood under merchant
operation.

S.3      KEY BASE CASE ASSUMPTIONS AND SENSITIVITY CASES

The key assumptions that drive the results in this analysis include demand
growth, fuel prices, capacity additions and reserve margin requirements, and the
retirement of nuclear stations. Assumptions were developed for a Base Case and
two downside sensitivities, a Low Demand Growth Case and a High Gas Price Case.

The Base Case represents the most probable market scenario and consequently what
Hagler Bailly believes to be the most likely performance forecast and
competitive position for Ironwood. The sensitivity cases are intended to test
the Project under significantly more adverse circumstances.

Demand

Our load forecast is based upon the actual 1995 PJM hourly load profile. Hagler
Bailly has forecast that PJM peak demand (load) will grow at 1.00% annually
through 2009 and at 0.75% thereafter. Annual energy growth has been forecast at
1.50% through 2002, at 2.00% from 2003 to 2009, and at 1.50% thereafter.

Fuel prices

CC Pace Consulting, LLC ("CC Pace") provided our fossil fuel price forecasts.
Coal price projections were assessed on a plant by plant basis, while gas and
oil were based upon regional zones. Table S-1 summarizes the fuel price
forecasts used in the Base Case.

                                 FOREWORD o C-9
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

                                    Table S-1
                      Delivered Fuel Prices (1996$/MMBtu)/1
<TABLE>
<CAPTION>
                                                                                 Average
                                                                                 Annual %
            Fuel                 1998      2005      2010      2020      2025    Change/4
- -------------------------------------------------------------------------------------------
<S>                             <C>        <C>       <C>       <C>      <C>          <C>
Natural Gas - PJM East/2        $2.57      $2.48     $2.52     $2.63    $2.69        0.17%
- -------------------------------------------------------------------------------------------
Natural Gas - PJM West          $2.47      $2.38     $2.43     $2.53    $2.60        0.18%
- -------------------------------------------------------------------------------------------
Residual #6                     $2.10      $2.41     $2.41     $2.41    $2.41        0.51%
- -------------------------------------------------------------------------------------------
Distillate #2                   $3.20      $3.69     $3.69     $3.69    $3.69        0.53%
- -------------------------------------------------------------------------------------------
Jet A                           $3.40      $3.89     $3.89     $3.89    $3.89        0.50%
- -------------------------------------------------------------------------------------------
Coal/3                          $1.36      $1.15     $1.09     $1.03    $1.04        -1.00%
- -------------------------------------------------------------------------------------------
</TABLE>
1  Fuel price estimates are left in real 1996$s to maintain consistency with a
   proprietary Hagler Bailly RealTime(TM) database.
2  Ironwood is forecast to use PJM East natural gas. The Henry Hub to PJM East
   basis (transportation) differential is approximately $0.52 per MMBtu.
3  Coal prices were provided on a plant specific basis. Average prices represent
   the average for all the coal consumed in a given year. The 1998 price is for
   the period Oct. 1997 - Sept. 1998.
4  Calculated from 1998 to 2025.

Capacity Additions

It is our belief that PJM will continue to impose a required reserve margin with
a target of 18%. Actual reserve levels will not remain constant but instead will
fluctuate around this value. We anticipate net capacity additions of 13,221 MW
between 1999 and 2025. All of the new capacity is gas-fired combustion turbines
(CT) or combined cycle (CC) units.

Nuclear Retirements

The retirement dates for PJM nuclear units are based on the expiration dates of
current operating licenses, with the exceptions of Oyster Creek 1, which GPU
Energy ("GPU") intends to retire toward the end of 2000, and Salem-2, which we
retire at the end of 2002.

Sensitivity Assumptions

As noted above, we considered two sensitivity cases:

o        In the Low Demand Growth Case, the growth rates are reduced by a third,
         compared to the Base Case, for the period 2017 through 2025. In this
         case peak and total demand grow at only 0.50% and 1.00% per annum,
         respectively, beginning in 2017.

o        In the High Natural Gas Price Case, natural gas prices are uniformly
         $0.50 per MMBtu (in 1996 $) above the CC Pace forecast levels.

                                 FOREWORD o C-10
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

Except as noted above, the assumptions underlying all three cases are identical.

S.4      FORECASTED RESULTS

Hagler Bailly used the RealTime(TM) production cost model and other analytical
tools to forecast energy and capacity prices for PJM. The resulting PJM "all-in"
price (i.e., capacity price plus energy price) forecast for the Base Case is
$27.70/MWh in 2002, $27.96/MWh in 2012, and $29.98/MWh in 2022 (all in constant
1996 dollars/2). Table S-2 (on the next page) summarizes the price forecasts.

Forecasted energy prices for PJM are shown in Figure S-1. In the Base Case,
energy market prices show a steady, slow price growth throughout the study
period. Prices (time-weighted) begin at $22.05 per MWh in 2001 and gradually
increase to $25.86 by 2025. In the High Gas Price Case, energy prices are
approximately $.60 to $1.20 per MWh above the Base Case throughout the forecast
period. In the Low Demand Growth Case, the impact of the reduction in demand
growth in 2017 can be clearly seen as a break in the price trend. By the end of
the forecast period the Low Demand Growth Case prices are about $2.00 per MWh
below the Base Case./3

- ----------
2        Fuel price estimates are left in real 1996$s to maintain consistency
         with a proprietary Hagler Bailly RealTime(TM) database.

3        Note that while energy prices in the Low Demand Growth Case are below
         the Base Case, this is due to prices remaining essentially flat in real
         terms rather than significantly declining. This flat trend in real
         prices is maintained although the Low Demand Growth Case assumes no
         adjustment to the schedule of capacity additions and retirements in
         reaction to the decline in demand growth.

                                 FOREWORD o C-11
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

                                    Table S-2
                            PJM West/Central Average
                                  All-In Prices
                                    (1996 $)/1

                                                                  Low Demand
                   Base Case            High Gas Case             Growth Case

   2001             $27.28                  $28.25                   $27.28
   2002             $27.70                  $28.59                   $27.70
   2003             $26.66                  $27.28                   $26.66
   2004             $27.65                  $28.32                   $27.65
   2005             $26.90                  $27.84                   $26.90
   2006             $27.21                  $28.24                   $27.21
   2007             $27.36                  $28.24                   $27.36
   2008             $27.96                  $28.67                   $27.96
   2009             $27.77                  $28.43                   $27.77
   2010             $28.02                  $28.89                   $28.02
   2011             $28.33                  $29.18                   $28.33
   2012             $27.96                  $29.18                   $27.96
   2013             $28.51                  $29.38                   $28.51
   2014             $28.81                  $29.81                   $28.81
   2015             $28.89                  $30.08                   $28.89
   2016             $29.54                  $30.40                   $29.54
   2017             $29.55                  $30.39                   $29.11
   2018             $29.70                  $30.36                   $29.27
   2019             $29.67                  $30.98                   $29.05
   2020             $29.41                  $30.56                   $28.87
   2021             $30.70                  $31.79                   $29.08
   2022             $29.98                  $31.17                   $28.91
   2023             $30.50                  $30.94                   $29.29
   2024             $30.68                  $31.40                   $28.76
   2025             $31.09                  $31.70                   $29.05

1  All-In prices include energy and capacity payments. Assumes a 100% capacity
   factor in calculating the capacity price per MWh. This assumption has the
   effect of understating the capacity price; for capacity factors below 100%
   the capacity payment per MWh increases. Fuel price estimates are left in real
   1996$s to maintain consistency with a proprietary Hagler Bailly RealTime(TM)
   database.

                                 FOREWORD o C-12
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

                                   Figure S-1

                     PJM West/Central Average Energy Prices
                                     1996$

                               [GRAPHIC OMITTED]


                                 FOREWORD o C-13
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

The expected operating regime of the Ironwood plant over the 25-year time frame
is indicated by the trend in capacity factor (see Figure S-2)./4 The figure
illustrates the consistent growth in utilization experienced by the Project in
the Base Case.

                                  Figures S-2

                         AES Ironwood Capacity Factors

                                [GRAPHIC OMITTED]

The average annual capacity factor is also shown in Figure S-2 for the
sensitivity cases. In both downside cases the model forecasts that Ironwood's
capacity utilization decreases somewhat from the Base Case. Nevertheless,
Ironwood's position in the stack, in terms of costs, is expected to allow it to
effectively compete with other PJM power generators. In the High Gas Price Case,
by the end of the forecast period the utilization of the plant is virtually the
same as in the Base Case. In the Low Demand Growth Case, utilization during the
merchant tail (i.e., the period beginning in the second quarter of 2021 when the
Williams PPA will expire and the plant will find new buyers for its output) is
also very similar to the Base Case. What the analysis

- ----------
4        Capacity factor is a measure of plant utilization. It is the ratio of
         actual plant output in MWh to the theoretical maximum output that would
         result from running the plant at full load every hour of the year
         (i.e., 8760 hours). The sawtooth pattern in the graph reflects major
         (every sixth year) and minor (every third year) planned maintenance
         outages.

                                 FOREWORD o C-14
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

indicates is that the growth in demand, combined with unit retirements, creates
a "floor" that provides stabile economics for the Project during the merchant
period.

Figure S-3 illustrates the position of Ironwood in the PJM supply curve in 2002,
2012, 2022 for the Base Case. The figure illustrates that Ironwood is
positioned, in all years, well below the highest cost coal unit. These results
are consistent with the high utilization of the plant shown in Figure S-2./5

                                   Figure S-3
                         PJM Supply Curves (1996 $/MWh)

                                      2002


                                [GRAPHIC OMITTED]

- ----------

5        Units positioned below the lowest cost coal unit include nuclear and
         hydro. Units positioned above the highest cost coal unit include oil
         and gas-fired steam units and combustion turbines and other peakers.
         Note that the supply curves exclude emergency power. Emergency power is
         incorporated within the RealTime(TM) model in the estimation of energy
         prices.

                                 FOREWORD o C-15
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

                              Figure S-3 (cont'd)
                         PJM Supply Curves (1996 $/MWh)

                                      2012

                               [GRAPHIC OMITTED]

                                      2022

                               [GRAPHIC OMITTED]

                                 FOREWORD o C-16
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

S.5      CONCLUSIONS

Based on our analysis, we believe that the facility's dispatch position on the
supply curve will be highly competitive and well below the highest priced
baseload coal plant during the post-PPA period (and during the term of the power
purchase agreement) due to the facility's high efficiency, low production costs,
and the influence of demand growth in conjunction with unit retirements.

The facility is expected to have an average capacity factor of 90.7% during the
post-PPA period. The addition of new, more efficient gas-fired power generation
facilities in PJM over time will not adversely affect the facility's dispatch.

Even in the two macroeconomic "downside sensitivity" cases of low demand growth
and high gas prices, the Facility's average capacity factor remains
significantly high at 89.6% during the post-PPA period.

During the term of the power purchase agreement, the economics of the Project
are not sensitive to fuel prices because the costs of fuel are the
responsibility of the power purchaser under the power purchase agreement's fuel
tolling provisions.

                                 FOREWORD o C-17
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

- --------------------------------------------------------------------------------

                                    CHAPTER 1
                                  INTRODUCTION

1.1      BACKGROUND

Hagler Bailly Consulting, Inc. (Hagler Bailly) was retained by AES Ironwood on
behalf of, and to prepare this report solely for Lehman Brothers as Initial
Purchaser of certain Rule 144A bonds to be offered by AES Ironwood, LLC to
finance the construction, start-up and initial testing of the Ironwood Facility.
We have been retained to independently assess the competitiveness of the planned
AES Ironwood power plant given forecast market prices for electric energy and
capacity in the Pennsylvania, New Jersey, Maryland (PJM) power pool. This
document presents the results of our analysis.

The Northeast power markets are undergoing profound change. Many of the
vertically integrated utilities are divesting their generation assets, and tight
pools (such as the New England Power Pool (NEPOOL), New York Power Pool ( NYPP)
and PJM) are changing as well. Historically, these pools were formed to obtain
the benefits of economic dispatch and coordinated planning. The tight pools are
being replaced by independent system operators (ISOs) with responsibility for
both system operations and market operations. Through the creation of the new
market institutions, the market participants intend to create a liquid and
vibrant market where buyers and sellers of generation services will be able to
transact business efficiently.

It is in this evolving environment that the competitive assessment presented in
this report is made. There is little doubt that forward-price forecasting is
more challenging in a changing market. Our approach is to examine the
fundamental economic prospects of AES Ironwood in the context of the planned and
forecast market.

1.2      ORGANIZATION OF THE REPORT

The remainder of this report is organized as follows:

o        Chapter 2 describes the Ironwood project.

o        Chapter 3 describes the proposed structure of the markets in PJM.

o        Chapter 4 presents our approach to developing forward-price forecasts
         for generation services.

                               INTRODUCTION o C-18
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

o        Chapter 5 discusses the development of assumptions and data to describe
         the PJM marketplace.

o        Chapter 6 presents market price forecasts for a base case and two
         downside sensitivity cases.

o        Chapter 7 presents our conclusions.

                               INTRODUCTION o C-19
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

- --------------------------------------------------------------------------------

                                    CHAPTER 2
                              THE IRONWOOD PROJECT

2.1      THE IRONWOOD PROJECT

AES Ironwood, LLC proposes to build and operate a 705 MW (net) power plant
("Ironwood") in south Lebanon Township, Pennsylvania. South Lebanon is in the
central region of PJM. The PJM ISO will operate this region's energy market and
transmission system. Ironwood will be a combined cycle power plant using Siemens
Westinghouse 501G technology.

The entire output of Ironwood will be sold to the Williams Energy Marketing and
Trading Company under a 20 year, fixed price power purchase agreement ("PPA").
It is assumed that the Ironwood facility will operate as a merchant power plant
and sell directly into the PJM market upon expiration of the PPA.

AES Ironwood expects seasonal maximum generating capacities of at least 788 MW
in winter, 705 MW in spring and fall, and 655 MW in summer. The power purchase
agreement envisages that in ordinary circumstances Ironwood will be dispatched
at 100% of available. The economics of AES Ironwood assure a high frequency of
commitment and operation at high capacity factors.

Ironwood has a ramp rate of 10 MW/minute. It is considered to have a minimum
uptime of eight hours and no minimum downtime.

A fuel conversion payment of $1.86/MWh (1996 $) is payable to the Ironwood plant
under the PPA. Ironwood's projected actual variable O&M cost is $1.71/MWh (1996
$).

Ironwood is modeled as a dual-fuel plant, generally burning natural gas but
consuming fuel oil during 25 of the highest load days of the winter./6 Since the
RealTime(TM) production cost model employed for this study must be given
specific time periods for each fuel type, we have chosen the high-load winter
days as those most likely to have tight gas supply, necessitating the use of
fuel oil to optimize economics. The plant's forced outage rate is conservatively
assumed to be 10.0% during the first year, 8.0% during the second year, and 5.0%
per year thereafter.

- ----------
6        The PPA requires Ironwood to use Jet A during fuel oil operation. Once
         the plant enters merchant operation in 2021, the model assumes the
         alternative fuel will be distillate fuel oil. Also note that the PPA
         permits up to 31 days of annual operation on fuel oil.

                           THE IRONWOOD PROJECT o C-20
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

The PPA target heat rate (contractual heat) while operating on natural gas is
higher than Ironwood's heat rate under its EPC contract.

                           THE IRONWOOD PROJECT o C-21
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

- --------------------------------------------------------------------------------

                                    CHAPTER 3
                      THE PROPOSED MARKET STRUCTURE IN PJM

One of the key factors that affect prices is the structure and institutions of
the market. This chapter describes the expected structure of generator services
for PJM.

There are a variety of power market models that are currently being considered,
and the PJM market may evolve over time to a structure that differs from that
described here. In addition, revenue and cost streams can be significantly
affected by arrangements made between the owners of generation assets and the
buyer of the plant's generation and capacity. Hagler Bailly's assessment of the
PJM market over the near to mid-term is intended to establish the context for
considering the range of variables relevant to the modeled performance of
Ironwood. In all cases, the description of the PJM market represents the most
recent intelligence, research and expert judgment of Hagler Bailly.

3.1      BACKGROUND

The PJM power pool was one of the first centrally dispatched power pools in the
United States and is one of the largest in the world. Along with other "tight
pools," the PJM power pool demonstrated that centralized dispatch and reserve
sharing among a large number of utilities could result in increased reliability
and provide cost savings for all of the participants.

As policy has shifted toward introducing greater competition in the electric
industry, tight pools such as the PJM power pool have been encouraged by the
Federal Energy Regulatory Commission (FERC) to transform themselves into
Independent System Operators. In its Open Access Rule,/7 FERC ordered public
utilities that are members of tight pools to file an open access transmission
tariff and to open membership in the pool on a nondiscriminatory basis.

In response to the FERC order, the members of the PJM power pool developed a
restructuring proposal and a pool-wide open access tariff. This restructuring
proposal created an ISO to operate the regional bulk power system, maintain
system reliability, administer specified electricity markets, and facilitate
open access to the regional transmission system under the PJM tariff. The PJM
electricity market uses market pricing for generation services, thereby
facilitating the development of a more efficient and more competitive wholesale
electricity market.

- ----------
      7 Order No. 888, FERC Stats. & Regs. Paragraph 31,036 at 31,726-27.

                      THE PROPOSED STRUCTURE IN PJM o C-22
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

PJM was the first power pool to have its open access transmission tariff
approved by FERC. The PJM bid-based energy market was initiated on April 1,
1997. PJM Interconnection, LLC was certified as an ISO by FERC on November 25,
1997. Locational marginal pricing took effect on April 1, 1998. An installed
capacity (daily capacity) market was launched on October 15, 1998.

As PJM shifts to a more competitive environment, many additional changes are
expected. In order to assess Ironwood's competitive position, a number of
critical factors were addressed. Chief among these are the market structure and
rules which define the way in which plant owners will bid and be compensated for
the energy and generation capacity that they provide to the market. Assumptions
about these market conditions were used to determine unit utilization, energy
prices and capacity prices.

3.2      THE PJM MARKET

The wholesale market structure includes the following markets for the services
of generators:

o        Spot energy market
o        Installed capacity market

Note that ancillary services do not currently have separate bid-based markets,
although such markets are under consideration, as recommended by FERC. Payments
for providing regulation are grounded in cost-based formulas. Payments for
providing operating reserves are included in an energy market daily
reconciliation.

3.2.1    The Spot Energy Market

The ISO runs the spot energy market. The closing time for submitting bids to the
ISO is noon for the energy markets the following day (for example, noon on
Tuesday for bids on energy to be generated on Wednesday). A bid to supply
generation consists of an incremental energy bid curve. For each generation
level, the curve represents the minimum price a bidder is willing to accept to
be dispatched at that generation level. The bid curve is specified by up to 10
price-quantity pairs. The same curve is used for all 24 hours of dispatch.
Bidders also specify operating constraints on their units (minimum up time,
minimum down time, ramp rates) as well as start-up costs and no-load costs.

The ISO determines location-specific market-clearing energy prices for each
hour. Prices are in dollars per megawatt-hour (MWh). Prices are based on bids
for generation, actual loads, and scheduled bilateral transactions. The ISO
constructs a commitment based upon day-ahead bids. Real-time dispatch is
conducted by the ISO by sending price signals to those generators on the margin.
These marginal generators then respond by ramping up or ramping down. The ISO
can also command units to change their output.

Settlement prices are currently calculated after the fact using dispatch data.
PJM has acquired a new energy management system that is to include a security
constrained unit commitment and

                      THE PROPOSED STRUCTURE IN PJM o C-23
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

dispatch module. At the time that this system is implemented, the current
procedures for calculating energy prices will be replaced with calculations from
the security constrained dispatch model.

The location-specific market-clearing prices include any charges for
transmission congestion. (The ISO intends in the future to also include charges
for transmission losses.) Congestion occurs when the transmission system becomes
constrained, and some generating capacity is dispatched while other generating
capacity with lower bids is not dispatched. The result is that the
market-clearing prices may differ from location to location. The locational
market-clearing prices ("locational marginal prices" in the jargon of the PJM
ISO) capture any costs associated with the out-of-order dispatch.

Important features of the spot energy market include the following:

o        Only the incremental energy bid curve is used in determining the
         market-clearing prices.

o        Generators that do not recover their start-up and minimum load costs
         over the course of a day's operations are compensated for the shortfall
         in net revenue ("negative cycle costs") with payments which ensure that
         a plant does not lose money by being required to operate by the PJM
         ISO./8

o        Aside from some interruptible load and exports, bidding is only allowed
         by generation resources.

o        Bilateral transactions are not subject to the market-clearing prices.
         However, they are subject to the same charges for transmission
         congestion included in the market-clearing prices.

o        Fixed transmission rights (FTRs) allow generators, load-serving
         entities, and others to hedge the costs associated with transmission
         congestion. An FTR has a financial analogue (transmission congestion
         credit or TCC) which is a financial right entitling holders of FTRs to
         the congestion charges associated with the difference in prices from a
         point of power injection to a point of delivery. When one obtains an
         FTR, one also acquires a TCC. TCCs thus may be used to offset the costs
         of transmission congestion. FTR's are obtained through two means:
         subscription to network service, where FTR's are assigned to the load
         based upon the location of the capacity resource and the load, or
         through purchase of firm point-to-point transmission service. In
         addition, PJM has petitioned the FERC for authority to conduct a
         periodic auction of uncommitted FTRs, and a secondary market for these
         rights is expected to develop.

- ----------
8        In any 24-hour period beginning at midnight, a generator may not lose
         money as a result of being dispatched by the ISO. If a generator does
         not recover its costs through market payments, then the amount of the
         operating loss is paid to the generator by the ISO. This means that a
         generator can not lose money from operating on any given day.

                      THE PROPOSED STRUCTURE IN PJM o C-24
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

o        Investor-owned utilities do not currently have FERC authorization for
         market-based pricing. Unless utility participants have authority for
         market-based pricing, their bids are capped at cost.

3.2.2    Installed Capacity Market

PJM has imposed generation capacity reserve requirements on all LSEs. These
requirements are expected to lead to an active capacity market. LSEs are defined
as entities providing electricity services to end-use customers under state law.
The PJM conducts an annual reliability study to determine the PJM Reserve
Requirement, defined as the level of installed reserves needed for PJM to meet
the installed generating capability requirements established within the control
area. Historically, the required reserve margin has been decreasing due mainly
to reductions in forced outage hours, and has averaged 18% to 20% over the past
five years./9

To ensure that sufficient capacity is available in the market to meet
reliability standards, PJM requires load-serving entities to own or contract
with physical generation capacity to cover their peak demand. Important features
of the installed capacity market include the following:

o        There are two capacity obligations. A load-serving entity's installed
         capacity obligation is determined two years in advance by PJM, based on
         forecast conditions. This obligation remains in place, and is known as
         the "planned-for" obligation. The planned-for obligation is then
         adjusted for actual conditions; this adjusted obligation is known as
         the "accounted-for" obligation. Capacity acquired in the installed
         capacity market satisfies the "accounted-for" obligation.

o        The amount of capacity each generator can supply is determined by a
         12-month rolling average of availability, calculated two months in
         advance of the period for which the capacity is supplied.

o        There is a day-ahead installed capacity market, and monthly markets
         extending 12 months into the future.

o        Each installed capacity market has a single market-clearing price for
         each day the market is in operation.

o        Capacity may be acquired by a load-serving entity through bilateral
         transactions with generators or other load-serving entities. PJM
         operates a bulletin board to facilitate bilateral transactions.

If a load-serving entity fails to meet its capacity requirement, a penalty is
assessed.

- ----------
9        "1997 MAAC Reliability Assessment," June 1998, Final Report, Prepared
         by PJM Interconnection, L.L.C., System Coordination Division.

                      THE PROPOSED STRUCTURE IN PJM o C-25
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

Current projections of committed new generating capacity within PJM are
insufficient to meet a reserve requirement of nearly 20% after the year 2000.
The focus of capacity planning has shifted from large, base load coal-fired
generation projects to combustion turbines and combined-cycle plants, which can
be planned and constructed in relatively short periods. However, based on
forecast reserve margins, PJM will require new capacity on line by the 2000
planning period./10

Additional elements of the evolving market for capacity in PJM are described in
the next chapter of this report.

- ----------
10       It should be noted that most LSE's in PJM have discontinued reporting
         planned capacity additions so as to avoid divulging information related
         to strategic business plans to competitors within the system. In spite
         of this understanding, it is apparent that maintenance of historical
         levels of reserve capacity may not be economically viable. The apparent
         shortage of reserve capacity supports our projection that even with an
         active capacity market reduced reserve margins are likely.

                      THE PROPOSED STRUCTURE IN PJM o C-26
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

- --------------------------------------------------------------------------------

                                    CHAPTER 4
                      APPROACH TO MARKET PRICE FORECASTING

4.1      INTRODUCTION

This chapter discusses our approach to forecasting forward prices for the
services of generation units. The first section discusses general issues related
to the capacity and ancillary services markets. The second section describes the
specific approach employed in this analysis to develop the energy and capacity
price forecasts.

4.2      ISSUES IN PREDICTING MARKET PRICES

By far the most important element of the power market is the energy market,
which will account for the vast majority of revenue. Although there is the
possibility that generators can capture margins in all markets within the PJM
pool, some of these other markets are much more difficult to assess. The
following section of the report discusses issues involved in evaluating the
value of capacity and ancillary services.

4.2.1    Issues in the Capacity Markets

         What Is the Purpose of a Capacity Market?

The Northeast markets, i.e., PJM, NYPP and NEPOOL, have all incorporated a
market for capacity as one of the key elements of the new wholesale market
design. In all three of these pools, load-serving entities have an
administrative obligation to purchase, own or control capacity. The capacity
market provides a mechanism for covering any shortfalls in the positions of load
serving entities with respect to their administrative obligations to the pool.

These three pools represent a departure from how other restructured markets have
dealt with the issue of capacity. In other markets that include some
compensation for capacity, notably the England and Wales pool, capacity payments
are determined administratively and are collected through an "uplift" charge
(basically a surcharge) that is added by the pool administrator to the

                   APPROACH TO MARKET PRICE FORECASTING o C-27
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

price of power from the pool. The PJM, NYPP and NEPOOL markets, to our
knowledge, are the first markets to attempt to institute a bid market for
capacity./11

What is the purpose of capacity compensation? Capacity payments have been
included in the market designs for several purposes:

o        Capacity payments can serve as a mechanism to encourage investment in
         new generation capacity. This was the predominant rationale for
         including capacity payments in the England and Wales pool. The premise
         is that a competitive energy market (one that tends to force energy
         prices to marginal cost) provides inadequate margins to assure the
         construction of sufficient new capacity.

o        Some regulators and market designers believe that a capacity payment
         will reduce price volatility in the energy market. The premise is that
         a fixed capacity payment provides base compensation, the result of
         which is to reduce the volatility in energy prices. If revenue
         expectations are constant, reduced volatility will reduce risk and
         financing costs.

o        In the case of PJM, NYPP and NEPOOL the rationale for a bid market in
         capacity is due, in part, to gaming that occurred in the England and
         Wales pool. There, generators strategically declared their capacity
         unavailable in order to raise capacity payments. The designers of the
         U.S. capacity markets thought, in part, that a bid market for capacity
         might reduce the opportunities for gaming./12

However, many restructured electricity markets have not included a capacity
market or a capacity payment. In fact, California, Norway, New South Wales, and
Victoria all have foregone the option of including a capacity component in the
exchange.

         Capacity Revenues Must Be Included in Market Projections

Market institutions evolve and change over time. Given that many debate whether
or not a capacity payment should be a part of the market institutions, is the
revenue we include from capacity prices at risk?

We believe not. Experience in existing energy markets shows that the energy
prices arising from the production cost model (discussed below) understate the
revenue that generators will earn

- ----------
11       Regulated electricity markets, including PJM, have provided capacity
         compensation. With deregulation, many continue to do so. What is unique
         is not the compensation but the effort to establish a bid market.

12       To be specific, capacity payments in the England and Wales pool are
         determined on a day-ahead basis by calculating the loss of load
         probability (LOLP, which depends on projected load and capacity). The
         LOLP is then multiplied by a value of lost load, which was
         administratively determined and escalates over time. Significant gaming
         occurred in the pool where generators would declare their capacity not
         to be available for the next day, thus increasing the LOLP and the
         resulting capacity payment, then declare their capacity available the
         next day to capture the inflated capacity payment.

                   APPROACH TO MARKET PRICE FORECASTING o C-28
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

from the energy market. Using a production cost model presumes that energy
prices are driven to short-run marginal cost. The result of this assumption is
that a significant number of generators (most particularly the peaking and
cycling facilities) earn insufficient margins from the energy market to cover
all of their going-forward costs. If no other payments were provided, rather
then incur these losses or retire, these generators would increase their
start-up bids in all hours in which they expected to be dispatched to at least
recover their going-forward costs. The results of this bidding behavior would be
expected to have results very similar to the method we used in projecting
capacity prices from a bid market.

There are a number of ways that these capacity revenues might be recovered.

o        First, the installed capacity markets, although unproven, may function
         well into the future.

o        Second, the installed capacity market could be replaced by an operating
         capacity market, which would have different pricing to cover going
         forward costs.

o        Third, the capacity markets could be replaced with an administrative
         market institution such as those found in the U.K. or Argentina.

o        Fourth, even if the capacity market were to disappear, generators would
         recover any shortfall in their going-forward costs by increasing their
         bid prices in the energy market above marginal cost when market
         conditions allow. If they could not do so they would exit the market
         and prices would need to increase to attract sufficient new entry to
         maintain any required capacity margin.

o        Fifth, there is a robust bilateral market that currently exists for
         capacity that is likely to persist in any new market structure.

         How Do We Model Capacity Payments?

Regardless of the ultimate form of capacity markets, we assess prices by
determining the economic worth of capacity. In our analysis, we model what the
market is willing to pay to retain plant (that might otherwise leave the market)
for reliability services. Specifically, our approach is based on a partial
equilibrium analysis that assessed returns from the energy and capacity markets
and dynamically simulated entry and exit decisions. For these reasons, we
believe that the capacity prices reflect returns that will be sustained by the
market.

Our approach to constructing capacity payments is described in more detail later
in this chapter.

4.2.2    Ancillary Services

The PJM ISO provides for revenues for ancillary services. There are,
potentially, material revenues and margins that could be attributed to these
markets. However, it is extremely difficult to predict what the forward price
curve might be in these markets, since they do not yet

                   APPROACH TO MARKET PRICE FORECASTING o C-29
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

exist in PJM and there is so little experience with bid-based systems for
ancillary services elsewhere. Hence, our price, revenue, and margin projections
have assumed that the going forward costs of the marginal unit would be covered
and that there would be no contribution from ancillary services markets that
would increase the margins of the marginal unit.

4.3      APPROACH TO MARKET PRICE FORECASTING

Figure 4-1 provides a graphical view of Hagler Bailly's process for producing
forward-price forecasts. The process begins with a definition of the
characteristics of the market, including the electric generating units currently
in operation, their production efficiencies (including heat rate curves), a
projection of plant additions (based in part on announcements and in part on an
equilibrium evaluation of market price signals), consumer demand and load, and
fuel prices.

                                   Figure 4-1
                Approach to Developing Capacity and Energy Prices

                               [GRAPHIC OMITTED]

Using these data, energy prices are projected through a comprehensive simulation
which sets energy price to the short run marginal cost, which also yields
estimates of how much each generating unit produces in the market. Capacity
prices are then projected based on our simulation of the capacity market. Next,
total returns to each generating unit are calculated and used to assess whether
market entry and exit occurs. Iteration between these three phases takes place
until stability is achieved in the energy and capacity price forecast.

Thus, this process develops prices based on a dynamic examination of market
entry and exit (including retirement) decisions made by the supply-side actors
in the market.

The following sections briefly discuss Hagler Bailly's approach to each of these
steps.

                   APPROACH TO MARKET PRICE FORECASTING o C-30
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

4.3.1    Market Characteristics

The first step is to ensure that we understand sufficiently the nature and
parameters of the market and the generation assets that participate in that
market. Hagler Bailly uses a variety of data sources to characterize the market.
These include:

o        Data identifying the generating units, consumer demand and load, and
         production capacities of existing plants. This included data from
         public sources and data extracted from Hagler Bailly's proprietary Ramp
         Up(TM) database.

o        Fuel price forecasts.

o        Planned additions, which are developed based on announced plans of
         developers (tracked in the Hagler Bailly IPP Database) and utilities
         (contained in planning council reports), weighted by our assessment of
         how much capacity will actually be built in the early stages of the
         analysis time horizon. Capacity additions subsequent to 2001 are tested
         in the entry and exit logic.

o        Retirements of nuclear plants. We review the experience of nuclear
         power plant operators (tracked in the Hagler Bailly Operating Plant
         Experience Code database) to identify the plants most likely to be
         retired before the end of their operating license and to estimate early
         retirement dates.

4.3.2    Predicting Energy Prices and Dispatch

Hagler Bailly used the RealTime(TM) production cost model to develop the PJM
wholesale market price of energy, plant operating costs, and projected dispatch
on an hourly basis for the years 2001-2025./13 RealTime(TM) incorporates unit
characteristics (e.g., heat rates, minimum and maximum capacities, ramp rate,
and fuel type), fuel costs, emissions, hourly load, imports from (exports to)
adjoining power pools and many other factors in its calculations.

Since RealTime(TM) is an hourly chronological production cost model, it
addresses each hour before moving on to the next hour. Thus, in every hour each
unit has a generation level (MW) and a cost associated with that generation. A
chronological model such as RealTime(TM) more closely simulates reality and its
uncertainties than do non-chronological models.

RealTime(TM) output includes revenue, fuel costs, emission costs, other variable
costs, profit, generation level (and capacity factor), hours connected to the
grid, forced outages, number of hot

- ----------
13       Hagler Bailly has used RealTime(TM) to project market clearing prices
         and unit operations in PJM for asset valuations, regulatory
         proceedings, and the evaluation of potential merchant plant projects
         for a number of clients. Hagler Bailly has also used RealTime(TM)
         elsewhere in the country to model prospective production costs.

                   APPROACH TO MARKET PRICE FORECASTING o C-31
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

and cold starts, and average and load-weighted marginal costs. In addition,
other reports are provided for every fossil, nuclear, and hydroelectric unit in
PJM.

An additional element of the dispatch analysis considered the impact of
transmission system characteristics and constraints. PowerWorld(TM), a load flow
model, was used to determine if Ironwood would impose additional burdens on the
PJM transmission system and if the plant's location would lead to its being
dispatched less than anticipated due to transmission constraints. We also used
the model to assess whether Ironwood could expect to receive higher revenues due
to contributions to voltage support or for transmission constraint-reducing
flows. The analysis showed that the plant's location would ease transmission
constraints from west to east, the predominant direction of flow, within PJM
Central. However, the value of this contribution is too small to measure at
present. In the future, if a nodal pricing regime is retained (i.e.,
location-specific pricing that reflects such factors as transmission
congestion), some revenue may be available for transmission congestion relief;
none is included in our results.

From the energy price analysis, Hagler Bailly determines the energy margin
(price minus variable cost) attributable to each generating unit in the market.
These margins, along with estimates of "going-forward costs," (fixed costs, such
as fixed O&M, property taxes, administrative and general expenses, employee
benefits, and incremental capital expenditures) are used in the Capacity Market
Simulation model to predict capacity prices.

4.3.3    Predicting Capacity Prices: The Capacity Market Simulation Model

Capacity payments are a mechanism for supporting an appropriate amount and mix
of capacity in the system. There are two reasons for including a capacity
payment in a forward-price analysis. First, if generators bid their short-run
marginal costs into an energy market, only inframarginal plants (those not on
the margin) earn a contribution toward their going-forward fixed costs. Plants
at the top of the supply curve receive little, if any, contribution toward their
going-forward costs. In addition, some of the baseload and cycling plants that
are not at the top of the supply curve but have high going-forward costs may not
earn a sufficient operating margin from the energy market alone to cover all of
those costs.

We predict capacity prices using our proprietary Capacity Market Simulation
Model. This model presumes that the market will retain a sufficient amount of
capacity to meet economic reliability targets. In other words, we simulate the
capacity market as consisting of a supply curve and a demand curve for
reliability (or capacity) services. We assume that the organized capacity market
is a competitive market, and that the market-clearing price for capacity is
determined by the intersection of the supply and demand curves. We construct
supply and demand curves for each year of the simulation time horizon.

The supply curve is calculated from the going-forward costs of each generating
unit. The net of going-forward costs and energy market margins, expressed on a
per-kilowatt basis, represents the minimum amount a generating unit needs to go
forward. Ranking these net costs in ascending order produces a supply curve for
capacity.

                   APPROACH TO MARKET PRICE FORECASTING o C-32
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

Next, the demand curve is estimated. The demand curve is estimated by
representing the capacity associated with a target reliability level. The demand
curve is a vertical line derived using a target reserve margin or target level
of installed capacity.

Finally, the intersection of the demand curve and the supply curve represents
the capacity payment that the market would support in that year. The capacity
price forecast is the capacity payment derived for each year of the study
period. An example supply and demand curve is shown in Figure 4-2.

For the purposes of the AES Ironwood study, Hagler Bailly applied the results of
its most recent capacity valuation studies of the PJM market. The estimated
annual capacity values average $45.19/kW-year (1996 $) for the forecast
period./14 (The annual values are shown in Chapter 6 of the report.)

                                   Figure 4-2
                        Example Supply and Demand Curve

                               [GRAPHIC OMITTED]

4.3.4    Market Entry and Exit

It is necessary to assess the feasibility and timing of new capacity additions
as well as the exit of uneconomic existing capacity. Hagler Bailly's proprietary
modeling approach serves two purposes:

- ----------
14       Additional revenues may be available in the future to generators that
         provide operating capacity services and other ancillary services, such
         as black-start capability. Such revenues are not considered in this
         analysis.

                   APPROACH TO MARKET PRICE FORECASTING o C-33
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

o        First, it identifies generating units that are not able to cover their
         going-forward costs in the energy market and are therefore at risk of
         abandoning the market.

o        Second, it provides a rational method for ascertaining the amount,
         timing, and type of capacity additions.

Hagler Bailly's approach uses a financial model to assess the decision to add
new capacity and to retire existing capacity. The approach to plant additions is
based on a set of generic plant characteristics, financing assumptions, and
economic parameters, and is an iterative process performed simultaneously with
the development of the energy price forecast and the capacity price forecast.

The methodology assesses the validity of annual capacity additions based on a
Discounted Cash Flow (DCF) model using net energy revenues determined in the
production cost model simulations, and capacity revenues determined from our
Capacity Market Simulation approach. For each increment of new capacity, a "Go"
or "No Go" decision is made based on the resulting financials. In addition,
economic retirement decisions are made at each step in the iterative process
based on the specific financial and operating characteristics of each existing
plant.

The iterative process begins with the addition of new capacity. A production
cost run is executed to determine energy prices, dispatch, and operating costs.
The Capacity Market Simulation is then performed. Financial results for the
energy and capacity markets are combined in the financial model to determine
whether the new unit is a "Go" or "No Go." If the new unit is a "Go," another
new unit is added, and the process repeated. This occurs until the next new unit
returns a "No Go."

Retirements are determined after new units are added. A financial analysis of
each unit is performed, combining the results of the energy and capacity
markets. If the cumulative operating profit (loss) for an existing unit were
negative for any five-year period, it was retired at the end of the third year
of consecutive operating loss. Although the decision criterion was somewhat
subjective, it was interpreted conservatively. Thus, if a unit lost money for
two years, was in the black over the third year, and then lost money for two
more years, the unit was maintained online.

If units were retired, the iterative process would begin again with the addition
of new capacity. In this way, the introduction of new units influences the
retirement of existing units, and the retirement of existing units enables the
introduction of new units. Since the addition of new units is "lumpy," the
iteration generally stops with new generators earning a small increment above
their cost of debt and equity. The addition of one more new unit would then push
many of the previous additions into losses. This approach reflects a game
theoretic concept of a market equilibrium.

                   APPROACH TO MARKET PRICE FORECASTING o C-34
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

- --------------------------------------------------------------------------------

                                    CHAPTER 5
                            MARKET PRICE FORECASTING:
                     ASSUMPTIONS AND ASSUMPTION DEVELOPMENT

5.1      INTRODUCTION

This section of the report describes the key assumptions used in the development
of the PJM capacity and energy market price forecasts and the related models.
The assumptions are presented in two sections. The first section describes the
inputs to the RealTime(TM) production cost model, including: (1) the
characteristics of the existing generating units (thermal, hydro, nuclear), (2)
the demand and energy forecasts, (3) fuel prices, (4) the modeling of
electricity imports/exports in the regions, and (5) intra-PJM transmission
constraints. The second section describes the inputs to the Capacity Market
Simulation Model.

5.2      PRODUCTION COST MODEL INPUT ASSUMPTIONS

As discussed above, to simulate the hourly market-clearing price of energy we
use the RealTime(TM) production-costing model. RealTime(TM) allows the
characterization of multiple transmission areas within a power pool.
Transmission areas for PJM are defined as "PJM-East" and "PJM-Central/West"
(see Map 5-1, below).

                                    Map 5-1
                                  PJM Regions

                                [GRAPHIC OMITTED]

                         MARKET PRICE FORECASTING o C-35
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

Imports and exports are modeled as contracts involving the East Central Area
Reliability Council (ECAR) and the New York Power Pool (NYPP). Map 5-2
illustrates the location of PJM, NYPP, ECAR and other adjacent power pools.

                                     Map 5-2
                              Eastern Power Pools

                               [GRAPHIC OMITTED]

Each of the PJM region's major generating units is represented individually in
the production-costing model using unit-specific cost and operating
characteristics. The RealTime(TM) model is used to perform an hour-by-hour
chronological simulation of the commitment and dispatch of generation resources.

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-36
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

5.2.1    Existing Generating Units

Fossil Units

Each fossil generating unit is characterized using the following parameters:

o        Summer and winter net capability
o        Heat-rate curve
o        Operating characteristics

         |_|      Minimum capacity
         |_|      Ramp rate
         |_|      Minimum uptime
         |_|      Minimum downtime

o        Forced outage rate
o        Scheduled maintenance outage rate
o        Variable operation and maintenance cost
o        Emission costs
o        Start fuel.

Units that operate on more than one fuel have characteristics specified for each
fuel. The development of these parameters is discussed below.

Summer and Winter Capabilities. Summer and winter capability values were
obtained from the 1997 Mid-Atlantic Area Council (MAAC) Regional Reliability
Council, EIA-411 Report. (MAAC is contiguous with PJM.)

Heat-Rate Curves for Fossil Units. Heat rate estimates were derived primarily
from Hagler Bailly's Ramp Up(TM) generation database and analysis system. Ramp
Up(TM) contains estimates of unit heat rates based on actual hourly unit
performance, as reported to the U.S. Environmental Protection Agency as part of
the Continuous Emission Monitoring (CEM) program. Where the CEM data was not
available, heat rate curves were estimated, using a proprietary Hagler Bailly
methodology, from the full load heat rates reported to the federal Energy
Information Administration (EIA) on EIA Form 860.

Operating Characteristics. The operating characteristics (minimum capacity, ramp
rate, minimum uptime, minimum downtime, forced and scheduled outage rates) are
derived from Hagler Bailly proprietary databases.

Variable Operation and Maintenance Costs. In RealTime(TM), nonfuel variable O&M
cost, hereafter referred to simply as variable O&M, is treated as if it is
directly proportional to the generation level of each unit. Variable O&M is a
problematic category because, in the short run, the truly variable portion
represents only a small part of total variable O&M costs, as traditionally
reported.

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-37
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

The variable O&M costs in RealTime are derived from FERC Form 1 data. The model
assumptions are shown below in Table 5-1.

- -------------------------------------------------------------------------------
                                    Table 5-1
                  Variable Operating Costs (1996 $ per MWh)/15
- -------------------------------------------------------------------------------
      Existing Oil, Gas, and Refuse                     $2.00/MWh
- -------------------------------------------------------------------------------
           Coal - Not Scrubbed                          $3.00/MWh
- -------------------------------------------------------------------------------
             Coal - Scrubbed                            $4.00/MWh
- -------------------------------------------------------------------------------
                 New CC                                   $1.71
- -------------------------------------------------------------------------------
                 New CT                                   $3.02
- -------------------------------------------------------------------------------

Sulfur Dioxide Emission Costs. The Clean Air Act Amendments of 1990 (CAAA)
provided for tightened restrictions on the emission of sulfur dioxide (SO2) by
fossil-fired generating stations, with the primary impact falling on coal
plants. In a departure from traditional command-type regulation, the CAAA
established a mechanism by which utilities could buy and sell rights to emit
SO2. This SO2 "allowance" system accordingly establishes a value or cost to a
utility, depending on whether it needs to purchase allowances or, if it emitting
less SO2 than it is authorized per the CAAA, it has excess allowances that it
can sell or bank for future use. Each allowance represents the right to emit one
ton of SO2.

The assumptions related to SO2 costs were based upon forward price forecasts
developed by Putnam, Hayes & Bartlett, Inc. (PHB). For the purposes of our
modeling, we assumed that SO2 emission costs were equal to the number of tons of
SO2 emitted multiplied by the price of allowances in a given year. The resulting
cost was added to the variable cost of each generating unit and included in the
development of the energy price forecast.

SO2 allowances are currently priced at about $190 per ton (1996 $). PHB
forecasts allowance prices escalating to $200 by 2001, and then gradually
ramping up to $400 by 2010, after which prices are flat in real terms (see
Figure 5-1).

Development of NOx Control Costs and Emission Rates

Because of the persistence of a widespread ozone nonattainment problem and the
recognition of NOx emissions as the primary precursor pollutant, EPA has
recently proposed the State Implementation Plan (SIP) Call. The SIP Call seeks a
70% percent reduction in NOx emissions from large NOx point sources (i.e., power
plants and industrial boilers) in 22 states starting in 2003. Despite these
large proposed reductions in NOx emissions, modeling of ozone

- ---------
15       Note: for modeling purposes all operating costs for nuclear, hydro and
         pumped storage units are assumed to be fixed.

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-38
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

concentrations suggests that many areas east of the Mississippi will be in
non-attainment of the 8-hour ozone standard. In order to avoid strict federal
penalties for ozone nonattainment, states will need to obtain further reductions
in NOx emissions. This will result in a continuous reduction in the number of
NOx allowances that are available, which will maintain NOx allowance prices
beyond 2020. The forecast SO2 and NOx price curves are shown below in Figure
5-1.

                                   Figure 5-1

                          Forecast Of Allowance Prices
                                (1996$ per Ton)

                                [GRAPHIC OMITTED]

The forward price curve for NOx emissions begins in 2001 at a price for
summer/16 NOx allowances of $2,150/ton (1996 $). The price of NOx allowances
jumps to $2,500/ton for the first summer of SIP Call regulations in 2003,
reaches $2,900 by 2005, and remains at this level through 2025./17

         Hydroelectric Units

The hydroelectric plants in the region are modeled individually, with the
exception of small plants, which are consolidated by utility and categorized as
peaking or baseload. Similar to the

- ----------
16       The summer NOx period is May 1 through September 30.

17       Source of NOx Allowance Prices: PHB Hagler Bailly estimate

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-39
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

thermal units, the maximum capacity for each unit was taken from sources cited
above for summer and winter capabilities.

         Nuclear Units

Table 5-2 lists the shutdown dates for all PJM nuclear units that retire during
the forecast period. The retirement dates are based on the expiration dates of
current operating licenses, with the exceptions of Oyster Creek 1, which GPU
intends to retire at the end of 2000, and Salem-2, which we retire at the end of
2002.

- --------------------------------------------------------------------------------
                                        Table 5-2
                              Nuclear Unit Retirement Dates
- --------------------------------------------------------------------------------
      Unit              Retirement      Summer Capacity      Cumulative Retired
                           Date              (MW)               Capacity (MW)
- --------------------------------------------------------------------------------
Oyster Creek-1           10/01/00              619                   619
- --------------------------------------------------------------------------------
Salem-2                  12/31/02            1,106                  1725
- --------------------------------------------------------------------------------
Peach Bottom-2           12/31/14            1,093                  2818
- --------------------------------------------------------------------------------
Calvert Cliff-1          12/31/15              840                  3658
- --------------------------------------------------------------------------------
Peach Bottom-3           12/31/15            1,093                  4751
- --------------------------------------------------------------------------------
T.M. Island-1            12/31/15              786                  5537
- --------------------------------------------------------------------------------
Calvert Cliff-2          12/31/17              840                  6377
- --------------------------------------------------------------------------------
Salem-1                  12/31/17            1,106                  7483
- --------------------------------------------------------------------------------
Hope Creek-1             12/31/21            1,031                  8514
- --------------------------------------------------------------------------------
Susquehanna 1            12/31/23            1,090                  9604
- --------------------------------------------------------------------------------

5.2.2    Load Growth

Our load growth assumptions have an important effect upon the analysis of the
market. With the output of generating plants and imports and exports held
constant, higher load means higher energy prices since units higher in the stack
will be dispatched to cover demand. Load, or demand, growth assessments focus on
aggregate, or total, demand and on load shape, which directly affect forecasts
of peak demand. Changes in the load shape (e.g., peak shaving) may reduce the
energy revenues despite higher aggregate demand. PJM load growth on average is
generally expected to increase at between 1.5% and 2% per annum, with peak loads
growing more slowly to reflect primarily industrial load shifting toward the
less expensive hours of the day.

In the present study, we utilized the actual hourly load variation pattern of
1995. We escalated the total load and peak load at different rates to reflect
our expectation that industrial and commercial peak loads will be shifted in the
future as time-of-day pricing and metering are extended.

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-40
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

The estimation of load growth through the next two decades is an important input
to the analysis. Hagler Bailly has done extensive work on the subject of demand
forecasting, and has selected load growth rates that are most probable given
this research and analysis. The years 2002-2009 are assigned a higher load
growth rate to reflect increased energy use as utilities finish collecting
stranded costs, making power less expensive. In the present study, the Base Case
assumptions forecast annual demand escalation at the following rates:

o        to 2002:       1.5% per annum
o        2003 to 2009:  2.0% per annum
o        2010 to 2025:  1.5% per annum

Our peak load escalation rates are as follows:

o        to 2009:       1.00% per annum
o        2010 to 2025:  0.75% per annum

We also tested the economics of Ironwood for a Low Demand Growth Case. In this
scenario both annual average and peak load growth rates for each year after 2016
are reduced by one-third, with no concomitant adjustment to the schedule of
capacity additions or retirements. This encompasses the last four years of the
PPA period and the merchant tail. Figure 5-2 illustrates the growth in average
and peak load under the Base and Low Demand Growth Cases.

                                   Figure 5-2

                        Cumulative Demand Growth in PJM

                                [GRAPHIC OMITTED]

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-41
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

5.2.3    Fuel Prices

Fossil fuel prices for this study were provided and documented by CC Pace. The
forecast for all fossil fuels is shown in Table 5-3, and summary graphs
illustrating the natural gas and coal price forecasts are presented in Figures
5-3 and 5-4.

Note that Figure 5-3 illustrates the natural gas Base Case values and the High
Gas Price Case constructed by Hagler Bailly (a uniform $0.50 per MMBtu increase
in the gas price for each year). Because the plant is gas-fired, the High Gas
Price Case represents the "downside" fuel price sensitivity.

The coal prices shown are the PJM-average delivered price for each year. The
model runs are based on individually determined coal prices for each plant, and
reflect such factors as the specific transportation costs and sulfur content
requirements of each station.

                                    Table 5-3
                      Delivered Fuel Prices (1996$/MMBtu)/1
<TABLE>
<CAPTION>
- -----------------------------------------------------------------------------------------------
                                                                                      Average
                                                                                      Annual %
             Fuel                 1998       2005      2010       2020       2025     Change/4
- -----------------------------------------------------------------------------------------------
<S>                               <C>       <C>        <C>       <C>         <C>         <C>
Natural Gas - PJM East/2          $2.57     $2.48      $2.52     $2.63       $2.69       0.17%
- -----------------------------------------------------------------------------------------------
Natural Gas - PJM West            $2.47     $2.38      $2.43     $2.53       $2.60       0.18%
- -----------------------------------------------------------------------------------------------
Residual #6                       $2.10     $2.41      $2.41     $2.41       $2.41       0.51%
- -----------------------------------------------------------------------------------------------
Distillate #2                     $3.20     $3.69      $3.69     $3.69       $3.69       0.53%
- -----------------------------------------------------------------------------------------------
Jet A                             $3.40     $3.89      $3.89     $3.89       $3.89       0.50%
- -----------------------------------------------------------------------------------------------
Coal/3                            $1.36     $1.15      $1.09     $1.03       $1.04       -1.00%
- -----------------------------------------------------------------------------------------------
1        Fuel price estimates are left in real 1996$s to maintain consistency with a
         proprietary Hagler Bailly RealTime(TM) database.

2        Ironwood is forecast to use PJM East natural gas.  The Henry Hub to PJM East basis
         (transportation) differential is approximately $0.52 per MMBtu.

3        Coal prices were provided on a plant specific basis.  Average prices represent the
         average for all the coal consumed in a given year.  The 1998 price is for the period
         Oct. 1997 - Sept. 1998.

4        Calculated from 1998 to 2025.
</TABLE>

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-42
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

                                   Figure 5-3

                       Delivered Natural Gas Prices 1996$

                                [GRAPHIC OMITTED]

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-43
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

                                   Figure 5-4

               PJM Generation Weighted Average Coal Prices 1996$

                                [GRAPHIC OMITTED]

5.2.4    Energy Import/Export Forecast

In RealTime(TM), we have modeled two electric energy imports into PJM and one
export. The imports are from ECAR and Ohio Edison-Potomac Electric Power Company
(OE-PEPCo), with maximum hourly capacities of, respectively, 4300 and 450 MW.
The export is into NYPP (maximum hourly capacity of 1000 MW). These imports and
exports are utilized when they are economical; electrical energy is imported
when the import price is less than the cost of generating that unit of energy
within PJM, and energy is exported when the price is greater than the cost of
PJM generation. All imports and exports remain in place throughout the model run
with the exception of the OE-PEPCo import, which expires at the end of 2005.
Table 5-4 displays the properties of the two imports and the export.

    MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-44
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>
<TABLE>
<CAPTION>
- ------------------------------------------------------------------------------------------------------------------
                                                    Table 5-4
                                      Imports and Exports (1996 $ per MWh)
- ------------------------------------------------------------------------------------------------------------------
                                           On-Peak
                          Location         Price in      Off-Peak     Annual Price   Maximum Hourly     Minimum
   Import/Export         within PJM          2001     Price in 2001    Escalation     Capacity (MW)    Take (MW)
- ------------------------------------------------------------------------------------------------------------------
<S>                    <C>                  <C>           <C>           <C>              <C>              <C>
ECAR Import/18         West & Central       20.75         15.25         See Note         4,300            10
- ------------------------------------------------------------------------------------------------------------------
OE-PEPCO Import        West & Central       11.94         11.94           3.0%             450            10
- ------------------------------------------------------------------------------------------------------------------
NYPP Export                 East            22.04         15.79           1.0%           1,000            10
- ------------------------------------------------------------------------------------------------------------------
</TABLE>

Emergency power purchase contracts were modeled on an economy basis using
experience Hagler Bailly has gained in the course of several market studies and
the pricing observed during the past year. Given recent market pricing during
high demand periods, the assumed pricing of the emergency power purchase
contracts is conservative. In all years of the study, the PJM market is assumed
to be able to purchase the following amounts of power for each of the two PJM
regions at the prices shown in Table 5-5. Emergency power is imported from
neighboring control areas using transmission capacity reserved for such purposes
(as provided by the capacity benefit margin).

- --------------------------------------------------------------------------------
                                    Table 5-5
                                Emergency Imports
- --------------------------------------------------------------------------------
         Quantity Available                     Price (Real 1996 $)
- --------------------------------------------------------------------------------
               500 MW                                  $100.00
- --------------------------------------------------------------------------------
               500 MW                                  $150.00
- --------------------------------------------------------------------------------
               200 MW                                  $250.00
- --------------------------------------------------------------------------------
            Additional MW                              $300.00
- --------------------------------------------------------------------------------

5.2.5    Transmission Constraints

The PJM Central-East interface has transfer capability estimated variously at
between 4,700 and 5,300 MW located near the New Jersey-Pennsylvania border.
Historically, as a consequence of this constraint a price differential exists
between the two sides of the interface about 10% of the time. RealTime(TM)
models transmission flows based on forecast price differentials resulting from
local demand and prices. This PJM East constraint generally becomes binding in
times of moderate to high demand, but not at times of peak demand. The reason
for this is that

- ----------
18       Note: ECAR import price trajectory approximates PJM trends.

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-45
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

significantly greater base-load and intermediate capacity is located in the West
and Central regions relative to the East. The East, in contrast, contains a
significant quantity of peaking capacity. Thus, as load increases more energy is
transmitted from Central to East until the constraint is reached. However, as
load levels continue to increase to peak levels, many peaking units in the East
are dispatched, lowering transmission demand. This means that plants located in
the West and Central regions receive slightly lower market prices than would be
the case if PJM were simply a single unconstrained pool.

PJM does not expect major new transmission lines to be constructed during the
study period. We have adopted this expectation.

5.3      CAPACITY MARKET SIMULATION MODEL INPUT ASSUMPTIONS

5.3.1    Existing Units Going-Forward Costs

For fossil units, annual fixed O&M costs are determined using FERC data from
1994-1996. For each year, total annual nonfuel production costs are identified.
The fossil fuel experts within Hagler Bailly assume that a reasonable proxy for
attributing nonfuel production costs to fixed and variable components is to
attribute 30% of total nonfuel costs to fixed costs, and the remainder to
variable costs. These fixed costs, in dollars, are then divided by net
capability to arrive at a cost in units of $/kW. These costs are then averaged
across years to determine an annual fixed production cost in $/kW. No
discounting is done to account for inflation, because inflation is a very small
component of the year-to-year variability for the three-year time period.

For steam units, the following adjustments are made. An increment of $4/kW for
annual G&A is added./19 Costs for employee benefits are assumed to be 50% of
total salaries reported in FERC Form 402, lines 18 and 28. Incremental capital
expenditures are assumed to be 20% of total fixed costs. These costs, which are
an important component of going-forward costs, are not reported in the FERC
production accounts.

While some FERC cost data is available at the generating unit level, most of
these data are available only at the power plant or station level. For
generating units lacking FERC data at the generating unit level, total station
annual nonfuel costs are attributed to generating units in proportion to
generating unit capacity. Since fixed production costs are calculated in units
of $/kW, this means that all generating units at a station have the same fixed
production costs per kW, unless production costs for a generating unit are
individually reported in the FERC data.

- ----------
19       An increment for annual G&A is only included for the steam units and
         not the remaining units since the steam units are the units that are
         more likely to have G&A costs that are not reflected in the FERC fixed
         O&M accounts.

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-46
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

For units not reported in the FERC data, an average value by unit type was
calculated from those units that do report FERC data. Combustion turbines and
gas turbines that were not listed in the FERC data were attributed annual fixed
production costs of $14.50/kW. Combined cycles were assigned a value of
$13.50/kW and steam units a value of $30.50/kW.

Property tax data for each unit was derived by applying a mill rate to an
assumed market value. We assumed a value for generating capacity of $400/kW.
Mill rates were assumed to vary by state and yield values averaging $9.50/kW.

5.3.2    New Generating Capacity

Projected unit characteristics for future combined cycle units (CCs) are based
upon Hagler Bailly estimates. These estimates were confirmed in conversations
with industry sources. These units were assigned seasonal maximum capacities of
788 MW, 705 MW, and 655 MW during the winter, spring/fall, and summer,
respectively. These units ramp up at 10 MW/minute, burn pipeline gas, and have a
variable O&M cost of $1.71/ MWh (1996 $). Their minimum uptime is eight hours
and they have no minimum downtime.

Unlike existing stock (those currently operating) in the model, future CCs are
assigned hot and cold start-up costs expressed in MMBtu. A cold start is defined
as a start after eight or more hours not in operation and has an average cost of
6,172 MMBtu per unit. A hot start is a start after less than eight hours of
inactivity, and its average cost is 2,482 MMBtu per unit.

Heat rates for CCs improve with time (i.e., newer units have superior technology
and performance to earlier units). Table 5-6 shows the heat rates and other key
characteristics of the generic combustion turbines (CTs) and CCs used in the
model.

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-47
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

- --------------------------------------------------------------------------------
                                    Table 5-6
                  New Generating Unit Characteristics (1996 $)
- --------------------------------------------------------------------------------
                                         CC                         CT
- --------------------------------------------------------------------------------
Summer Net Capacity (MW)               655 MW/1                   345 MW
- --------------------------------------------------------------------------------
Total Capital Cost                      $464                       $279
($/kW)
- --------------------------------------------------------------------------------
Heat Rate (Btu/kWh, for     Units installed 2001-06: 6768
full load summer            Units installed 2007-13: 6339         10,400
operation)                  Units installed 2014-25: 6235
- --------------------------------------------------------------------------------
Variable O&M ($/MWh)                    $1.71                     $3.02
- --------------------------------------------------------------------------------
Fixed O&M ($/kW Year)                   $9.75                     $5.11
- --------------------------------------------------------------------------------
1        The 655 MW (summer capacity) is equivalent to 705 MW average capacity.

Information on fixed costs, depreciation, and taxes is also developed and
incorporated within the DCF analysis to determine the economic viability of the
new unit additions. Environmental costs and overhaul expenses are not included
due to expectations that such expenses would be minimal in early years of
operation. Key economic and financial assumptions include the following:

o        Property taxes are assumed to be 1% of the initial capital costs.
         Property taxes are escalated over time at the Projected inflation rate.

o        Depreciation of the initial all-in cost of the new additions are based
         on a standard 20-year MACRS (150% DB) with mid-year convention.

o        General inflation is assumed at 2.5%.

o        Minimum after-tax return of 13.5%.

o        Income tax rate is assumed to be 35% federal and 7% state.

o        Financing assumptions of 60% debt, 40% equity.

o        Debt interest rate of 8%.

o        Debt terms are 20 years for combined cycle units with mortgage-style
         amortization.

o        Debt terms are 15 years for combustion turbine units.

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-48
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

- --------------------------------------------------------------------------------

                                    CHAPTER 6
                             MARKET PRICE FORECASTS

6.1      INTRODUCTION

This chapter presents the market price forecasts resulting from our analysis,
and our assessment of Ironwood's dispatch given these forecasts. Three cases
were developed:

o        "Base Case," which reflects our best assessment of future market
         conditions.

o        "High Gas Price Case," a downside sensitivity that tests the effect of
         higher prices for gas through a uniform increase of $.50/MMBtu relative
         to the Base Case in all years, while leaving all other fuel prices
         unchanged.

o        "Low Demand Growth Case," a downside sensitivity that tests the effect
         of a one-third reduction in PJM average and peak demand growth rates
         for each year beginning in 2017. This encompasses the last four years
         of the PPA term and each year in the post-PPA period. While demand
         growth is reduced, this case includes no corresponding adjustment to
         the schedule of capacity retirements and additions.

All three cases use the same schedule of unit additions and retirements. In the
Low Demand Growth Case this conservative assumption has the effect of
overstating the likely reserve margins and exaggerating the downward impact on
energy prices.

The remainder of this chapter of the report is organized as follows:

o        Section 6.2 presents our forecasts of power prices in PJM.

o        Section 6.3 presents our forecasts of capacity factors and of
         Ironwood's competitive position.

6.2      PJM CAPACITY AND ENERGY PRICE FORECASTS


6.2.1    Base Case

The pressing need for capacity in the PJM market is reflected in Table 6-1,
which summarizes PJM market entry and exit. During the study period, 14,744 MW
of capacity is retired and 27,965 MW of new combined cycle (CC) and combustion
turbine (CT) capacity is added, for a

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-49
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

net increase of 13,221 MW (a 25% increase, compared to current installed
capacity of 52,521 MW). These additions provide for an average reserve margin of
18.1% for the study period./20
<TABLE>
<CAPTION>
- -----------------------------------------------------------------------------------------------------------------------
                                                      Table 6-1
                                        PJM Capacity Additions and Retirements
                                                        (MW)
- -----------------------------------------------------------------------------------------------------------------------
                                                                                   Net
                                              Total                             Capacity      Cumulative     Reserve
    Year             CC         CT          Additions          Retirements      Cumulative   Net Capacity    Margin
- -----------------------------------------------------------------------------------------------------------------------
<S>                 <C>        <C>            <C>                <C>              <C>        <C>             <C>
    2001              655          -            655                (198)            457               457    17.8%
- -----------------------------------------------------------------------------------------------------------------------
    2002                -        240            240                   -             240               697    17.1%
- -----------------------------------------------------------------------------------------------------------------------
    2003            1,310      1,380          2,690              (2,264)            426             1,123    16.7%
- -----------------------------------------------------------------------------------------------------------------------
    2004            1,310      1,035          2,345              (1,791)            554             1,677    16.6%
- -----------------------------------------------------------------------------------------------------------------------
    2005            1,310        690          2,000              (1,131)            869             2,546    17.1%
- -----------------------------------------------------------------------------------------------------------------------
    2006                -        690            690                   -             690             3,236    17.2%
- -----------------------------------------------------------------------------------------------------------------------
    2007            1,310          -          1,310                   -           1,310             4,546    18.4%
- -----------------------------------------------------------------------------------------------------------------------
    2008              655          -            655                   -             655             5,201    18.8%
- -----------------------------------------------------------------------------------------------------------------------
    2009                -        690            690                   -             690             5,891    18.9%
- -----------------------------------------------------------------------------------------------------------------------
    2010              655        690          1,345                (835)            510             6,401    19.0%
- -----------------------------------------------------------------------------------------------------------------------
    2011                -        345            345                   -             345             6,746    18.7%
- -----------------------------------------------------------------------------------------------------------------------
    2012                -        345            345                   -             345             7,091    18.5%
- -----------------------------------------------------------------------------------------------------------------------
    2013              655          -            655                   -             655             7,746    18.7%
- -----------------------------------------------------------------------------------------------------------------------
    2014                -        345            345                   -             345             8,091    18.5%
- -----------------------------------------------------------------------------------------------------------------------
    2015            1,310        345          1,655              (1,093)            562             8,653    18.6%
- -----------------------------------------------------------------------------------------------------------------------
    2016            1,310      1,725          3,035              (2,719)            316             8,969    18.3%
- -----------------------------------------------------------------------------------------------------------------------
    2017                -        690            690                   -             690             9,659    18.6%
- -----------------------------------------------------------------------------------------------------------------------
    2018            1,310      1,035          2,345              (1,946)            399            10,058    18.4%
- -----------------------------------------------------------------------------------------------------------------------
    2019              655          -            655                   -             655            10,713    18.6%
- -----------------------------------------------------------------------------------------------------------------------
    2020              655          -            655                   -             655            11,368    18.8%
- -----------------------------------------------------------------------------------------------------------------------
    2021                -        345            345                (571)           (226)           11,142    17.6%
- -----------------------------------------------------------------------------------------------------------------------
    2022            1,310          -          1,310              (1,106)            204            11,346    17.8%
- -----------------------------------------------------------------------------------------------------------------------
    2023              655          -            655                   -             655            12,001    18.0%
- -----------------------------------------------------------------------------------------------------------------------
    2024            1,310        345          1,655              (1,090)            565            12,566    17.9%
- -----------------------------------------------------------------------------------------------------------------------
    2025              655          -            655                   -             655            13,221    18.1%
- -----------------------------------------------------------------------------------------------------------------------
TOTAL              17,030     10,935         27,965             (14,744)         13,221      Avg. reserve    18.1%
- -----------------------------------------------------------------------------------------------------------------------
</TABLE>

- ----------
20       Due to the abundance of inexpensive coal fired generation capacity in
         PJM-West, there are no economic additions or retirements in this
         region. All the additions in PJM are in the East and Central regions.

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-50
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

The introduction of this substantial new capacity helps to explain why the PJM
market is characterized by relatively low energy prices and relatively high
capacity prices. When many of the nuclear units are retired, they are
immediately replaced in the model by new CC and CT units to meet system
reliability requirements. These units, like the nuclear plants, have relatively
low variable costs, which perpetuates low prices in the energy market. The going
forward costs of these units, coupled with the relatively low energy market
prices, require additional revenues from the capacity market. This keeps
capacity prices high throughout the study period. By the end of 2005, 5384 MW of
uneconomic generation is retired in PJM. At the same time the system adds 7930
MW of new capacity. This new capacity, composed of both CC and CT units,
replaces the retired nuclear units. New generating capacity is added in every
year of the study period, in order to meet the growing demand for power in the
region.

At the outset of the forecast period coal generation is at the margin for over
half the hours in a year. Over time, as gas-fired units are constructed to meet
load growth and nuclear units are retired (which has the effect of increasing
the base load utilization of coal), gas-fired units become the marginal source
of power for almost a third of the hours. Since Ironwood's costs are lower than
many coal units, Ironwood is "inframarginal" in the vast majority of hours; that
is, its costs are below the costs of the marginal unit.

In the Base Case, energy market prices show a steady, slow price growth
throughout the study period. Energy prices begin at $22.05 (1996 $s/21) per MWh
in 2001 and gradually increase to $25.86 by 2025 (See Figure 6-1 and Table 6-2).

In the High Gas Price Case, energy prices are approximately $.60 to $1.20 per
MWh above the Base Case throughout the forecast period. This sensitivity
represents the "downside" fuel case because of the increase in Ironwood's fuel
costs. In the Low Demand Growth Case, the impact of the reduction in demand
growth in 2017 can be clearly seen as a break in the price trend. By the end of
the forecast period the Low Demand Growth Case prices are about $2.00 per MWh
below the Base Case./22

- -----------
21       Fuel price estimates are left in real 1996$s to maintain consistency
         with a proprietary Hagler Bailly RealTime(TM) database.

22       Note that while energy prices in the Low Demand Growth Case are below
         the Base Case, this is due to prices remaining essentially flat in real
         terms rather than significantly declining. This flat trend in real
         prices is maintained although the Low Demand Growth Case assumes no
         adjustment to the schedule of capacity additions or retirements in
         reaction to the decline in demand growth.

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-51
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

                                   Figure 6-1

                     PJM West/Central Average Energy Prices
                                     1996$

                                [GRAPHIC OMITTED]

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-52
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

                                    Table 6-2

                            PJM Average Energy Prices
                                  (1996 $/MWh)

                                         High Gas           Low Demand
                    Base Case           Price Case          Growth Case
- --------------------------------------------------------------------------------
    2001             $22.05               $23.02              $22.05
    2002             $22.47               $23.36              $22.47
    2003             $21.43               $22.05              $21.43
    2004             $22.42               $23.09              $22.42
    2005             $21.88               $22.82              $21.88
    2006             $22.15               $23.18              $22.15
    2007             $22.32               $23.20              $22.32
    2008             $22.85               $23.56              $22.85
    2009             $23.02               $23.68              $23.02
    2010             $22.98               $23.85              $22.98
    2011             $23.44               $24.29              $23.44
    2012             $22.77               $23.99              $22.77
    2013             $23.28               $24.15              $23.28
    2014             $23.58               $24.58              $23.58
    2015             $23.66               $24.85              $23.66
    2016             $24.31               $25.17              $24.31
    2017             $24.32               $25.16              $23.88
    2018             $24.51               $25.17              $24.08
    2019             $24.44               $25.75              $23.82
    2020             $24.18               $25.33              $23.64
    2021             $25.47               $26.56              $23.85
    2022             $24.75               $25.94              $23.68
    2023             $25.27               $25.71              $24.06
    2024             $25.45               $26.17              $23.53
    2025             $25.86               $26.47              $23.82

Table 6-3 presents the annual forecast of capacity values used in the study,
expressed in 1996 dollars per kW-year. Since it can be difficult to separately
assess the effects of capacity and energy prices, we also present in Table 6-4
an "all-in" price forecast that combines energy and capacity prices (calculated
using a 100% load factor). The forecasted all-in price for the Base Case is
$27.70/MWh in 2002, $27.96/MWh in 2012, and $29.98/MWh in 2022 (all in constant
1996 dollars).

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-53
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

                                   Table 6-3
                              PJM Capacity Prices
                                 (1996 $/kW-yr)

                                    All Cases
                        ---------------------------------
                             2001             $45.84
                             2002             $45.84
                             2003             $45.84
                             2004             $45.84
                             2005             $44.01
                             2006             $44.34
                             2007             $44.17
                             2008             $44.74
                             2009             $41.65
                             2010             $44.13
                             2011             $42.80
                             2012             $45.49
                             2013             $45.84
                             2014             $45.84
                             2015             $45.84
                             2016             $45.84
                             2017             $45.84
                             2018             $45.46
                             2019             $45.84
                             2020             $45.84
                             2021             $45.78
                             2022             $45.78
                             2023             $45.78
                             2024             $45.78
                             2025             $45.78

We have used the Base Case capacity values throughout. We do so since the High
Gas Case does not affect capacity requirements and the reduced energy margins
would, all else equal, increase the revenue required for new capacity. With the
Low Demand Growth Case we do not believe that the posited capacity would
actually enter the market. As capacity became overbuilt, new entrants would
delay or cancel their projects. Over some period, the supply and demand for
capacity would return to equilibrium and might go beyond equilibrium to
shortage. The posited continual overbuild is not plausible for more than a brief
period. Thus we consider this

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-54
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

sensitivity analysis to be a useful stress test for energy prices, but not a
credible capacity scenario.

                                    Table 6-4
                            PJM West/Central Average
                                  All-In Prices
                                   (1996 $)/1

                                                               Low Demand
                   Base Case          High Gas Case            Growth Case
- --------------------------------------------------------------------------------
   2001             $27.28               $28.25                  $27.28
   2002             $27.70               $28.59                  $27.70
   2003             $26.66               $27.28                  $26.66
   2004             $27.65               $28.32                  $27.65
   2005             $26.90               $27.84                  $26.90
   2006             $27.21               $28.24                  $27.21
   2007             $27.36               $28.24                  $27.36
   2008             $27.96               $28.67                  $27.96
   2009             $27.77               $28.43                  $27.77
   2010             $28.02               $28.89                  $28.02
   2011             $28.33               $29.18                  $28.33
   2012             $27.96               $29.18                  $27.96
   2013             $28.51               $29.38                  $28.51
   2014             $28.81               $29.81                  $28.81
   2015             $28.89               $30.08                  $28.89
   2016             $29.54               $30.40                  $29.54
   2017             $29.55               $30.39                  $29.11
   2018             $29.70               $30.36                  $29.27
   2019             $29.67               $30.98                  $29.05
   2020             $29.41               $30.56                  $28.87
   2021             $30.70               $31.79                  $29.08
   2022             $29.98               $31.17                  $28.91
   2023             $30.50               $30.94                  $29.29
   2024             $30.68               $31.40                  $28.76
   2025             $31.09               $31.70                  $29.05

1        Assumes a 100% capacity factor in calculating the capacity price per
         MWh. This assumption has the effect of understating the capacity price;
         for capacity factors below 100% the capacity payment per MWh increases.

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-55
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

6.3      IMPLICATIONS FOR AES IRONWOOD

In this section, we discuss capacity factors (CF)/23, energy prices, and
dispatch for Ironwood under the three cases. As shown in Figure 6-2, in the Base
Case the CF gradually rises from the 85% range to over 90% by 2019. This
improvement in utilization reflects an assumed decreased forced outage rate over
time (this is a typical pattern as units move past the "break-in" period), and
increasing demand for power in PJM in conjunction with unit retirements. During
the early years of operation we would expect Ironwood to be backed-down during
low load periods, such as some Spring and Fall weekends and some evening
periods. As load increases the number of backdown periods declines and operation
of the plant is more continuous.

                                   Figure 6-2

                         AES Ironwood Capacity Factors

                                [GRAPHIC OMITTED]

- ----------
23       The capacity factor represents how fully used the plant is in a
         specific year. It is the ratio of total MWh produced to the total MWh
         the plant could have produced if fully utilized every hour of the year
         (i.e., 8760 hours).

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-56
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

The sawtooth pattern in the figure reflects the impact of maintenance outages.
Major maintenance outages take place every six years with less significant
outages at three-year intervals.

Even in the Low Demand Growth Case the capacity factors remain above 90% during
three of the first four years of the merchant tail. In the High Gas Price Case
dispatch is degraded and the capacity factors are under 85% for the early years
of operation. However, as PJM load grows the dispatch of the plant steadily
improves and by the merchant tail is closely tracking the Base Case. In short,
demand growth combined with unit retirements creates a "floor" that stabilizes
the utilization of the Project during the merchant tail.

Simultaneous with its high utilization, the Ironwood plant achieves an average
energy price for its power that is higher than the time weighted PJM market
price for energy (a result shown in Figure 6-3 for the Base Case). AES Ironwood
will receive this higher energy price during the merchant period. (The
discussion that follows deals only with energy prices and does not cover
capacity revenues, which are discussed above.) The reasons the Ironwood plant
receives higher than average energy prices are (i) the plant is not dispatched
in the lowest price hours; (ii) the plant's planned outages are scheduled during
low price periods; iii) ramping from and to shutdown occurs predominantly in low
priced hours; and (iv) compensation is received for negative cycle costs./24
Excluding the lowest priced hours and including reimbursement for the negative
cycle costs raises the average price received by the plant above the PJM
average.

- ----------
24       Negative cycle costs are costs incurred in excess of revenues at times
         when a unit is dispatched by the ISO to provide spinning reserve,
         transmission system support, or some other service, or is kept on due
         to minimum up-time or other constraints or ISO decisions. PJM rules
         currently provide for make-whole payments to compensate generators for
         negative cycle costs, and this procedure is expected to continue.

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-57
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

                                   Figure 6-3

                       Ironwood's Energy Revenue vs PJM's
                           Average Energy Price 1996$
                                   Base Case

                                [GRAPHIC OMITTED]

The plant's economics are such that it is inframarginal to (less expensive than)
much coal generation and most other capacity in PJM. Figure 6-4 shows Ironwood's
position on the PJM supply curve for 2002, 2012, and 2022. As new, more
efficient capacity is added over time, Ironwood moves up the supply curve;
however, at the same time the curve is elongated as demand increases. The
overall effect is that Ironwood remains at a favorable point on the supply curve
throughout the study period. The figure illustrates that Ironwood is positioned,
in all years, well below the highest cost coal unit./25 These results are
consistent with the high utilization of the plant shown in Figure 6-2.

- ----------
25       Units positioned below the lowest cost coal unit include nuclear and
         hydro. Units positioned above the highest cost coal unit include oil
         and gas-fired steam units and combustion turbines and other peakers.
         Note that the supply curves exclude emergency power. Emergency power is
         incorporated within the RealTime(TM) model in the estimation of energy
         prices.

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-58
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

                                   Figure 6-4

                         PJM Supply Curves (1996 $/MWh)
                                      2002

                                [OBJECT OMITTED]

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-59
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

                               Figure 6-4 (cont.)

                         PJM Supply Curves (1996 $/MWh)
                                      2012

                                [OBJECT OMITTED]

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-60
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>


                                      2022

                                [OBJECT OMITTED]

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-61
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential
<PAGE>

- --------------------------------------------------------------------------------

                                    CHAPTER 7
                                   Conclusions

Based on our analysis, we believe that the facility's dispatch position on the
supply curve will be highly competitive and well below the highest priced
baseload coal plant during the post-PPA period (and during the term of the power
purchase agreement) due to the facility's high efficiency, low production costs,
and the influence of demand growth in conjunction with unit retirements.

The facility is expected to have an average capacity factor of 90.7% during the
post-PPA period. The addition of new, more efficient gas-fired power generation
facilities in PJM over time will not adversely affect the facility's dispatch.

Even in the two macroeconomic "downside sensitivity" cases of low demand growth
and high gas prices, the Facility's average capacity factor remains
significantly high at 89.6% during the post-PPA period.

During the term of the power purchase agreement, the economics of the Project
are not sensitive to fuel prices because the costs of fuel are the
responsibility of the power purchaser under the power purchase agreement's fuel
tolling provisions.

In summary, the economics of Ironwood appear to be robust. We cannot, of course,
account for all possible circumstances in the energy and fuel markets. What this
study does indicate is that given the operating parameters, costs, and other
modeling assumptions, and for a range of scenarios which provide a significant
test to the economics of the Project, the AES Ironwood project is financially
viable.

     MARKET PRICE FORECASTING: ASSUMPTIONS AND ASSUMPTION DEVELOPMENT o C-62
- ---------------------------------Hagler Bailly---------------------------------
                          Privileged and Confidential