IRUTIL CO INC
20FR12G, EX-10, 2000-08-09
Previous: IRUTIL CO INC, 20FR12G, EX-10, 2000-08-09
Next: IRUTIL CO INC, 20FR12G, EX-27, 2000-08-09



<PAGE> 60
EXHIBIT 10.2

MEMORANDUM OF AGREEMENT

     THIS MEMORANDUM OF AGREEMENT ("MOA") effectived as of the
13th day of December, 1997 between Cotabato Electric Cooperative
Inc. North Cotabato, Philippines ("COTELCO") as one party, and
ESI E&C Co., Inc.,  Palm Beach, Florida, USA ("ESI") as the other
party. COTELCO and ESIEC are each referred to as a "Party" and
jointly as "Parties."

I.   Premises

*    Philippines requires renewable energy, regionally developed
     in the Philippines

*    COTELCO has solicited and received interest from ESI to
     invest in COTELCO

*    COTELCO has the rights, permits, licenses, and
     pre-feasibility study to the Kabacan 8MW mini-hydro project,
     and

*    COTELCO has the rights, permits, licenses and going power
     distribution business.

     Following the evaluation of the proposals received and
subsequent negotiations, COTELCO and ESI mated a PARTNERSHIP for
designing, building, owning, and operating the Kabacan 8MW
mini-hydro project and an investment in COTELCO.

     The Project will serve the Philippines under a long term
Power Purchase Agreement ("PPA").

     Commencing with the effective date of this MOA, the Parties
Wed to work together exclusively in good faith, negotiate various
contracts and agreements required to permit the PARTNERSHIP to
proceed to finance, construct, own, and operate the Project.

2.  Joint Responsibilities/Ownership of the Parties.

2.1  The Parties agreed to developed within 90 days of the
     effective date of this MOA or as mutually agreed, the
     specific parameters for the Project, including but not
     limited to, the location and size of the plant site, future
     expansion requirements, configuration of the electrical
     interconnection, total list and schedule of all approvals,
     licenses and permit requirements and the scope of the
     Environmental Impact Assessment.

2.2  The Parties agreed that total project cost will be secured
     by ESI E&C Co., Inc.


<PAGE> 61

2.3  The Parties will own the PARTNERSHIP as follows:

     *    COTELCO - 10% of all outstanding shares of PARTNERSHIP
     *    ESI     - 90% of all outstanding shares of PARTNERSHIP

3.   Responsibilities of ESI

ESI shall

3.1  Submit to COTELCO a draft Shareholders Agreement,
     Implementation Agreement, Power Purchase Agreement, other
     necessary contractual documents, and a milestone schedule
     within 90 days of completing Article 2 of this MOA;

3.2  Submit applications or requests, as appropriate, for
     approvals, licenses and permits within 90 days following the
     completion of Article 2 of this MOA:

<illegible>

4.   Responsibilities of COTELCO

COTELCO shall:

4.1  Confirm within 60 days of completing Article 2 of this MOA,
     the site characteristics and site size for the Project, all
     relevant drawings, plans, studies, etc. and future expansion
     requirements;

4.2  Within 120 days following ESI's submissions of applications
     and requests for approval, pursuant to Article 3.2 above,
     assist to deliver all permits. licenses, and approvals
     necessary for EST to finance, construct and operate the
     Project

4.3  Confirm within 30 days of ESI's submittal of the
     requirements pursuant to Article 3.3 above, that COTELCO
     will be able to satisfy or assist to have such requirements,
     consistent with do Article 7, below, of the PPA and
     Financial Closing.

5.   Price Basis

     The Parties agree that the monthly invoicing by PARTNERSHIP
for new monthly energy and capacity contracted for by off-takers
at the metering point shall be composed of

     * Capacity Fee      PESO/Kw/Month based upon 8 Mw
     * Energy Fee        PESO/KwHr

     *    The average is approximately 10% below the new avoided
          cost of NPC.

<PAGE> 62

6.   Financing

     ESI shall make best efforts to secure financing for the
Project within the time frame stipulated in Article 7 below. If
the financial closing has not occurred prior to the construction
start date, ESI shall fund the initial phase of design of the
Project from equity and begin the detailed design phase.

7.   Time Schedule

     Subject to all the other items and conditions in this MOA,
the Parties agree that the following time schedule shall be the
basis for execution of the Project's first phase:

     Commence Engineering, three (3) months after MOA signed.

     Execute the PPA and Implementation Agreement in twelve to
     fourteen (12-14) months after MOA signed.

     Financial Closing, sixteen (16) months after MOA signed.

     Construction Mobilization, twenty (20) months after MOA
     signed.

     Commission the Project, three (36) months after MOA signed.

8.   Technical Basis

     The Parties agree that the power plant design shall be based
on ESI's transfer of technology.

9.   Confidentiality

     Information supplied by the Parties to each other or in
connection with the Project shall be kept confidential and the
Parties shall not disclose such information to any other entity
or person, except that ESI may provide certain information on
confidential basis to third parties no required for financing the
Project.

     The Parties also represent that such signature is duly
authorized and that no further action is required to enable them
to perform, their obligations under this MOA.










<PAGE> 63

For COTELCO;                       For ESI;

BY: /s/ Wilfredo A. Juloya         BY: /s/ David E. Atkinson
Print: Wilfredo A. Juloya          Print: David E. Atkinson
Title: President, COTELCO BOD      Title: President, ESI E&C Co.,
                                   Inc.
Date: Saturday 13 December 1997    Date: Saturday, 13 December
                                   1997

Witnessed by:

/s/ Elmer B. Bautista
General Manager, COTELCO

/s/ Polerio "Phol" R. Babao Jr. I
Regional Manager, ESI E&C  Co., Inc. (Philippines)





© 2022 IncJournal is not affiliated with or endorsed by the U.S. Securities and Exchange Commission