CENTRAL MAINE POWER CO
8-K, 1996-04-19
ELECTRIC SERVICES
Previous: BROWN GROUP INC, 10-K405, 1996-04-19
Next: EKCO GROUP INC /DE/, S-1, 1996-04-19



                       SECURITIES AND EXCHANGE COMMISSION

                             Washington, D.C. 20549


                                    FORM 8-K


                                 CURRENT REPORT


                     Pursuant to Section 13 or 15(d) of the
                         Securities Exchange Act of 1934



        Date of Report (Date of earliest event reported): April 17, 1996



                           CENTRAL MAINE POWER COMPANY
             (Exact name of registrant as specified in its charter)




           Maine                   1-5139              01-0042740
(State of Incorporation)           (Commission         (IRS Employer
                                   File Number)        Identification Number)




                      83 Edison Drive, Augusta, Maine 04336
               (Address of principal executive offices) (zip code)



       Registrant's telephone number, including area code: (207) 623-3521










<PAGE>




Item 1 through Item 4.  Not applicable.

Item 5.  Other Events.


         Company  stranded-cost  filing. As previously reported, on February 27,
1995,  the Maine Public  Utilities  Commission  ("MPUC")  issued a proposed rule
relating to electric  utilities  that it stated was "intended to help smooth the
transition to a more  competitive  environment  by  establishing  principles and
procedures  for the  determination  and recovery of stranded  costs in specified
circumstances".  The  proposed  rule,  although  limited in its  application  to
electric-utility   municipalization   situations,   recognized   certain  costs,
including long-term purchased-power  obligations and regulatory assets, as being
potential  stranded  costs and specified an "exit fee" as the means for recovery
of such costs. The proposed rule, however,  also included a built-in "mitigation
factor" that would have reduced the recoverable  amount by 50 percent.  On March
29, 1995, as part of a broader Notice of Proposed Rulemaking ("NOPR") related to
open  transmission  access and stranded  costs,  and designed to facilitate  the
development of a competitive  market,  the Federal Energy Regulatory  Commission
("FERC")  expressed  support for the  principle of full recovery by utilities of
their  "legitimate and  verifiable"  stranded costs. On April 18, 1995, the MPUC
terminated its rulemaking proceeding to avoid duplicative proceedings.

         Also as previously reported, in June 1995 the Maine Legislature enacted
a resolve  that  initiated  a process to develop  recommendations  on the future
structure  of the  electric  utility  industry  in  Maine.  After  a work  group
appointed by the Legislature and representing  many diverse  interests failed to
reach a consensus on a recommendation by the late-1995 reporting  deadline,  the
MPUC,  as the next step in the process,  commenced a study of electric-  utility
restructuring by soliciting  "detailed  proposals and plans for achieving retail
competition in Maine by the year 2000". On January 31, 1996, again as previously
reported,  the  Company  filed its  initial  comments  on  issues  raised by the
Legislature and the MPUC, along with a restructuring proposal calling for, among
other things, the legal separation of the Company's generating assets, contracts
and obligations from its  transmission and distribution  assets and obligations,
and full recovery of strandable costs through a transition  charge to all retail
customers.  Other  interested  parties  submitted  a  variety  of  comments  and
proposals.  In its proposal the Company estimated its potential  strandable-cost
exposure as of December 31, 1995, to be as much as $2 billion, with above-market
purchased-power   contracts  with   non-utility   generators   responsible   for
approximately  60  percent  of  that  amount  and  deferred   regulatory  assets
approximately 25 percent.

         On April 17, 1996, in part in reaction to  developments  in its service
territory  discussed  below,  the  Company  filed  with the MPUC (1) a  petition
requesting  that  the  MPUC  re-open  the  terminated  stranded-cost  rulemaking
proceeding (the "Petition to Re-open"),


<PAGE>



and (2) a proposed "Interim Competitive  Transition Charge Tariff" (the "Interim
Tariff"),  including a request for  immediate  effectiveness.  In its filing the
Company stated that it was critical that utilities,  customers and the financial
markets  "know the rules  and  guidelines"  that  would be  associated  with the
recovery of strandable costs during the transition to competition.  To that end,
the  Company  urged the MPUC to  reinforce  its  earlier  commitment  to prevent
shifting of strandable  costs from one group of customers to another and to hold
departing  customers  responsible for their  allocable share of such costs.  The
Company also pointed out that  promulgation of a final  stranded-cost  rule on a
parallel track with the MPUC's  contemporaneous  electric-utility  restructuring
proceeding  would allow the MPUC to have in place a clear means for an "economic
transition  to  competition"  when  the  MPUC  offers  its   recommendations  on
restructuring to the Maine Legislature at the end of 1996.

         The  Company's  Petition to Re-open  requests  that the MPUC reopen its
rulemaking  proceeding  on stranded  costs and issue a proposed rule for comment
and consideration  that would broadly address its application to retail wheeling
and self-generation,  rather than only  municipalization  issues, and that would
adopt several  significant  principles.  The principles urged by the Company for
adoption by the MPUC include, among others: (1) that all legitimate,  verifiable
and unmitigatable  strandable costs should be allowed to be recovered;  (2) that
the shifting of costs  either to  remaining  customers or investors by departing
customers is not  consistent  with economic  efficiency and should be avoided to
the  greatest  extent  possible;  and (3) that  the  mechanism  established  for
recovery of stranded costs be a non-bypassable charge applying whether customers
remain connected to the distribution or transmission  system or depart from that
system.   The  other  stated  principles  deal  with  the  establishment  of  an
appropriate  period  for  the  transition  to  competition  and an  approach  to
measuring such costs annually.

         Stressing the  immediacy of the threat of  uneconomic  bypassing of the
Company's  system and the  resulting  cost  shifting and price risk to remaining
customers,  the  Company  reported  in  its  filing  that  Hannaford  Bros.  Co.
("Hannaford"),   one  of  its  largest  customers,   had  recently  installed  a
natural-gas-fired  self-  generation unit in  Scarborough,  Maine, at one of its
larger supermarkets in the Company's service territory.  The Company pointed out
that Hannaford had 33 locations in the Company's service territory,  including a
substantial  number of large  supermarkets,  and that Hannaford had informed the
Company in discussions  with the Company of its intention to install  widespread
self-generation  at its stores in the Company's  service territory by the end of
1996.

         In seeking approval of the second part of its MPUC filing,  the Interim
Tariff,  the Company  asserted that the Interim Tariff would address the present
and potential  risks caused by large customers  bypassing the Company's  system,
including such risks as: (1) the


<PAGE>



installation  of  "uneconomic"  generation  (where  the  cost of the  customer's
alternative is higher than the market rate of power),  such as that installed or
planned by Hannaford,  a practice that is contrary to long-standing Maine energy
policy  and  statutory  law;  (2) de  facto  restructuring,  before  either  the
Legislature  or the MPUC has completed its review,  putting at risk any benefits
for  residential  and other  remaining  customers;  (3) the  appearance  that an
"escape  mechanism"  to avoidance of  responsibility  for costs is available for
those who leave the  Company's  system before such  responsibility  for costs is
settled; (4) the shifting of costs from those who can "escape",  typically large
customers,  to those who  cannot,  typically  smaller  customers,  or to utility
investors; and (5) the sending of a "negative message" to the financial markets,
a  stakeholder  in  electric  utility   restructuring   whose  participation  in
restructuring is vital, with ensuing increased uncertainty and risk. To overcome
those risks,  the Company  requested that the Interim  Tariff become  effective,
subject to refund,  for all applicable  situations  that arise on or after April
29,  1996,  the  requested  effective  date of the Interim  Tariff.  The Company
pointed out that it was  necessary,  under the  circumstances  described  in its
filing,  to have in place  an  interim  means to  recover  stranded  costs  from
departing  customers  while the  longer-term  issues  are being  decided  in the
re-opened  stranded-cost  rulemaking in parallel with the ongoing  restructuring
proceeding.  The Interim  Tariff is  designed  to provide for the  recovery of a
major portion,  but only the uneconomic  portion,  of those costs from departing
large  customers,  subject to refund of any  amounts  that  exceed  the  amounts
ultimately determined by the MPUC in its reopened stranded-cost proceeding to be
appropriate.

         The Company cannot predict  whether other customers of the Company will
elect  to  install   self-generation   units  before  the  issues   relating  to
responsibility for stranded costs are resolved.  The Company also cannot predict
whether or when Hannaford will elect to install additional self-generation units
at any or all of its other 32  locations  in the  Company's  service  territory,
although many of such  locations may not be of  appropriate  size and electrical
load  characteristics  for  self-generation to be economical at those locations,
even if Hannaford should be successful in avoiding  responsibility  for stranded
costs.  If  Hannaford  should  choose to  install  self-generation  at its other
locations with electrical  characteristics  similar to the Scarborough location,
the  Company  estimates  that  the  costs  stranded  by  such  action  would  be
approximately $3.5 million. Finally, the Company cannot predict whether the MPUC
will approve the Interim  Tariff or otherwise  allow the recovery of some or all
of the  costs  that may be  stranded  as a result of the  installation  of self-
generation facilities by customers of the Company.

Item 6 through 8.  Not applicable.


<PAGE>


                                    SIGNATURE



         Pursuant to the  requirements  of the Securities  Exchange Act of 1934,
the  Registrant  has duly  caused  this report to be signed on its behalf by the
undersigned thereunto duly authorized.

                                       CENTRAL MAINE POWER COMPANY


                                       By:  ----------------------------------
                                            D. E. Marsh
                                            Vice President, Corporate Services,
                                            Treasurer and Chief Financial
                                            Officer

Dated:  April 19, 1996


<PAGE>




© 2022 IncJournal is not affiliated with or endorsed by the U.S. Securities and Exchange Commission