COMMONWEALTH ELECTRIC CO
10-K, 1994-03-31
Previous: NATIONAL WESTERN LIFE INSURANCE CO, 10-K, 1994-03-31
Next: COMMONWEALTH ENERGY SYSTEM, 10-K, 1994-03-31



                                    PAGE 1

               UNITED STATES SECURITIES AND EXCHANGE COMMISSION
                         Washington, D. C. 20549-1004

                                   Form 10-K

                 ANNUAL REPORT PURSUANT TO SECTION 13 OR 15(d)
                    OF THE SECURITIES EXCHANGE ACT OF 1934
(Mark One)
 X  ANNUAL REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES
    EXCHANGE ACT OF 1934 [FEE REQUIRED]

    For the fiscal year ended December 31, 1993

                                      OR

    TRANSITION REPORT PURSUANT TO SECTION 13 OR 15(d) OF THE SECURITIES
    EXCHANGE ACT OF 1934 [NO FEE REQUIRED]

    For the transition period from ________________ to ________________

                         Commission file number 2-7749

                         COMMONWEALTH ELECTRIC COMPANY
            (Exact name of registrant as specified in its charter)

        Massachusetts                                   04-1659070     
(State or other jurisdiction of                      (I.R.S. Employer
incorporation or organization)                      Identification No.)

One Main Street, Cambridge, Massachusetts                02142-9150
(Address of principal executive offices)                 (Zip Code)


                                 617-225-4000                    
             (Registrant's telephone number, including area code)

          Securities registered pursuant to Section 12(b) of the Act:

    Title of each class      Name of each exchange on which registered
           None                              None

          Securities registered pursuant to Section 12(g) of the Act:

                                Title of Class
                                     None

Indicate by check mark whether the registrant (1) has filed all reports
required to be filed by Section 13 or 15(d) of the Securities Exchange Act of
1934 during the preceding 12 months (or for such shorter period that the
registrant was required to file such reports) and (2) has been subject to such
filing requirements for the past 90 days. YES  x  NO    

Indicate the number of shares outstanding of each of the issuer's classes of
common stock, as of the latest practicable date.

                                                     Outstanding at
       Class of Common Stock                         March 15, 1994
    Common Stock, $25 par value                      2,043,972 shares


The Company meets the conditions set forth in General Instruction J(1)(a) and
(b) of Form 10-K as a wholly-owned subsidiary and is filing this Form with the
reduced disclosure format.

Documents Incorporated by Reference                  Part in Form 10-K
              None                                     Not Applicable

List of Exhibits begins on page 39 of this report.
                                    PAGE 2

                         COMMONWEALTH ELECTRIC COMPANY
                       FORM 10-K      DECEMBER 31, 1993

                               TABLE OF CONTENTS

                                    PART I
                                                                    PAGE

Item  1.    Business........................................         3

              General.......................................         3
              Electric Power Supply.........................         3
              New England Power Pool........................         4
              Power Contracts and Capacity
                Acquisition and Disposition Agreement.......         5
              Energy Mix....................................         5
              Rates and Regulation..........................         6
                (a) Rate Proceedings........................         6
                (b) Cost Recovery...........................         6
                (c) Economic Development Rate...............         7
              Construction and Financing....................         8
              Employees.....................................         8

Item  2.    Properties......................................         8

Item  3.    Legal Proceedings...............................         8



                                    PART II


Item  5.    Market for the Registrant's Common Stock and
            Related Stockholder Matters.....................         9

Item  7.    Management's Discussion and Analysis of
            Results of Operations...........................        10

Item  8.    Financial Statements and Supplementary Data.....        17

Item  9.    Changes in and Disagreements with Accountants
            on Accounting and Financial Disclosure..........        17



                                    PART IV


Item 14.    Exhibits, Financial Statement Schedules and
            Reports on Form 8-K.............................        38



Signatures..................................................        57

                                    PAGE 3

                         COMMONWEALTH ELECTRIC COMPANY
                                    PART I.

Item 1. Business

    General  Commonwealth Electric Company (the Company) is engaged in the
generation, transmission, distribution and sale of electricity at retail to
approximately 307,700 customers (including 48,400 seasonal) in 40 communities
located in southeastern Massachusetts, including Cape Cod and the island of
Martha's Vineyard, having an approximate year-round population of 549,000 and
a large influx of summer residents.  The results of the 1990 federal census
taken in the Company's service area indicated a population increase of 18.1%
since 1980.  Also, the Company sells power to the New England Power Pool
(NEPOOL) and is actively pursuing sales of certain available capacity to other
utilities in and outside the New England region.

    The Company, which was organized on April 4, 1850 pursuant to a special
act of the legislature of the Commonwealth of Massachusetts, operates under
the jurisdiction of the Massachusetts Department of Public Utilities (DPU),
which regulates retail rates, accounting, issuance of securities and other
matters.  In addition, the Company files its wholesale rates with the Federal
Energy Regulatory Commission (FERC).  Since the date of its organization, the
Company has from time to time acquired or disposed of the property and
franchises of or merged with various gas or electric companies.  The Company
is a wholly-owned subsidiary of Commonwealth Energy System ("System"), which,
together with its subsidiaries, is collectively referred to as "the system."

    By virtue of its charter, which is unlimited in time, the Company distrib-
utes electricity without direct competition in kind from any privately or
municipally-owned utilities.  Alternate sources of energy are available to
customers within the service territory, but competition from these sources to
date has not been a significant factor affecting the Company.  Of the Com-
pany's 1993 retail electric unit sales, 49% was sold to residential customers,
32% to commercial customers, 10% to industrial and 9% to municipal and other
customers.

    Electric Power Supply

    The Company relies almost entirely on purchased power to meet its electric
energy requirements.  The Company owns generating facilities with a total
capacity of 13.8 MW, which are principally used for emergency and peaking
purposes.  The Company also has a joint-ownership interest of 8.8 MW in
Central Maine Power Company's oil-fired Wyman Unit 4.

    Power purchases for the Company and Cambridge Electric Light Company
(Cambridge Electric), the other wholly-owned electric distribution subsidiary
of the System, are arranged in accordance with their requirements.  These
arrangements include purchases from Canal Electric Company (Canal), another
wholly-owned subsidiary of the System.  Canal is a wholesale electric generat-
ing company located in Sandwich, Massachusetts and an important source of
purchased power for the Company.  Under long-term contracts, system entitle-
ments include one-quarter (143 MW) of the capacity and energy of Canal Unit 1
and one-half (292 MW) of the capacity and energy of Canal Unit 2.  In 1991,
Canal, on behalf of the Company, exchanged 50 MW of the system's entitlement
in Canal Unit 2 with Central Vermont Public Service Corporation (CVPS) for 25
MW each of CVPS's entitlement in the Vermont Yankee nuclear power plant and
the Merrimack 2 coal-fired unit through October 1995 in order to reduce the
                                    PAGE 4

                         COMMONWEALTH ELECTRIC COMPANY

Company's reliance on oil-fired generation.  Additionally, in 1993, Canal
executed an exchange transaction with New England Power Company whereby 20 MW
of Canal Unit 2 was exchanged for 20 MW of Bear Swamp Unit Nos. 1 and 2
through October 1993.  On November 1, 1993, the exchange was increased to 50
MW through April 1997.  The Bear Swamp Units are pumped storage hydro-electric
generating facilities.

    In response to solicitations made to the NEPOOL member companies by
Northeast Utilities (NU), Canal, on behalf of the Company and Cambridge
Electric, agreed to purchase entitlements through various contracts ranging up
to five years in length.  The terms of the five-year agreement stipulate the
purchase of 50 MW, on average, from NU annually from November 1989 through
October 1994.  The Company and Cambridge Electric are each appropriated a
portion of the power received from NU based on need.

    In addition, the Company has a 73.1 MW entitlement from a nuclear unit in
Plymouth, Massachusetts (Pilgrim) under a life-of-the-unit contract with
Boston Edison Company.  Also, through Canal's equity ownership in Hydro-Quebec
Phase II and its 3.52% interest in the Seabrook nuclear power plant, the
Company has entitlements of 48.2 MW and 32.4 MW, respectively.  In-state non-
utility sources which provide a portion of the Company's requirements include
67.0 MW from the SEMASS waste-to-energy plant (which includes 20.8 MW from the
expansion unit which went on-line May 17, 1993), 10.0 MW from Boott Hydropow-
er, Inc., 2.0 MW from Swift River Company and 0.5 MW from Pioneer Hydropower,
Inc.  In addition, the Company has contracted to purchase power from: (1) five
natural gas-fired cogenerating facilities as follows: 23.8 MW from Consolidat-
ed Power Company; 31.4 MW from Pepperell Power Associates; 44 MW from North-
east Energy Associates, and effective July 31 and September 1, 1993, 51 MW and
27.5 MW from Masspower and Altresco Pittsfield, L.P., respectively, and (2),
61.8 MW from Dartmouth Power Associates, a natural gas-fired independent power
producer.

    The Company expects to provide for future peak load plus reserve require-
ments through existing and planned system generation, including purchasing
available capacity from neighboring utilities and/or non-utility generators. 
These and other bulk electric power purchases are necessary in order to
fulfill the system's NEPOOL obligation and for Canal to acquire and deliver
sufficient electric generating capacity to meet the Company's and Cambridge
Electric's capacity requirements.

    New England Power Pool

    The Company, together with other electric utility companies in the New
England area, is a member of NEPOOL, which was formed in 1971 to provide for
the joint planning and operation of electric systems throughout New England.

    NEPOOL operates a centralized dispatching facility to ensure reliability
of service and to dispatch the most economically available generating units of
member companies to fulfill the region's energy requirements.  This concept is
accomplished through the use of computers to monitor and forecast load
requirements and provide for the economic dispatch of generation.

    The Company and the System's other electric subsidiaries are also members
of the Northeast Power Coordinating Council (NPCC), an advisory organization
that includes the major power systems in New England and New York plus the
                                    PAGE 5

                         COMMONWEALTH ELECTRIC COMPANY

provinces of Ontario and New Brunswick in Canada.  NPCC establishes criteria
and standards for reliability and serves as a vehicle for coordination in the
planning and operation of these systems in enhancing reliability.

    The reserve requirements used by the NEPOOL participants in planning
future additions are determined by NEPOOL to meet the reliability criteria
recommended by NPCC.  The system estimates that, during the next ten years,
reserve requirements so determined will be in the range of 23% to 29% of peak
load.

    Power Contracts and Capacity Acquisition and Disposition Agreement

    The Company has long-term contracts for the purchase of electricity from
various sources.  In addition, the Company's future generation needs will be
met substantially through a Capacity Acquisition and Disposition Agreement
with Canal.  For further information on this agreement, refer to Note 2(b) of
the Notes to Financial Statements filed under Item 8 of this report.

    Energy Mix

    The Company's energy mix, including purchased power, was as follows:

                                     1993      1992       1991

       Oil                            27%       39%        36%
       Nuclear                        20        22         28
       Natural gas                    35        24         19
       Waste-to-energy                11         9         10
       Hydro                           4         3          4
       Coal                            3         3          3
         Total                       100%      100%       100%

    The Company's energy mix has shifted during the last several years from
oil to natural gas and other types of generation due to the availability of
capacity from independent power producing (IPP) facilities and cogenerating
units and, to a lesser extent, an effort to reduce its reliance on oil.  As
stated in the "Electric Power Supply" section above, in 1993, the Company
began receiving power from two gas-fired sources (Altresco Pittsfield and
Masspower), additional energy from the expansion of a waste-to-energy plant
(SEMASS) and extended commitments from a pumped storage facility (Bear Swamp)
in exchange for power from the oil-fired Canal Unit 2.  In 1991, Canal
arranged for a long-term exchange of power with certain CVPS nuclear (Vermont
Yankee) and a coal-fired unit (Merrimack 2).  In certain circumstances, it is
possible to exchange capacity with another utility so that the mix of power
improves the pricing for dispatch for both the seller and the purchaser.  The
Canal/Bear Swamp transaction alone will save the Company's customers $2.7
million over a four-year period that began in June 1993.  These exchanges and
other future capacity purchase power contracts with natural gas-fired IPPs
will continue to shift the Company's energy mix from oil to other sources.  In
addition, the Company is actively pursuing sales of certain available capacity
to utilities in and outside the New England region.
                                    PAGE 6

                         COMMONWEALTH ELECTRIC COMPANY

    Rates and Regulation 

       (a) Rate Proceedings

    The Company operates under the jurisdiction of the DPU, which regulates
retail rates, accounting, issuance of securities and other matters.  In
addition, the Company files its respective wholesale rates with FERC. 

    The DPU requires historic test-year information to support changes in
rates.  In its last base rate filing with the DPU in December 1990, the
Company requested a $17.3 million revenue increase.  On July 1, 1991, the DPU
issued an order increasing the Company's retail electric revenues by $10.9
million or 3.1% over the test year ended June 30, 1990.  The DPU also ordered
the Company to undertake an independent management audit in 1992.  In October
1992, the DPU released the results of the audit which evaluated existing
activities and processes and identified opportunities for improved operations
in the areas of strategic planning, budget development, control of capital and
operational costs, management of outside services, employment policies and
customer services.  Throughout 1993, follow-up discussions were held between
Commonwealth Electric and the DPU regarding the status of each audit recommen-
dation with both parties expressing overall satisfaction with their progress. 
Changes in the implementation plan were discussed, with the plan expected to
be complete in 1994.

       (b) Cost Recovery

    Rate Schedule  The Company files a Fuel Charge rate schedule, subject to
DPU regulation, under which it is allowed current recovery, from retail
customers, of fuel used in electric generation and a substantial portion of
purchased power, demand and transmission costs.  This schedule requires the
quarterly computation of a Fuel Charge decimal based on forecasts of fuel,
purchased power and transmission costs and billed unit sales for each period. 
To the extent that collections under the rate schedule do not match actual
costs for that period, an appropriate adjustment is reflected in the calcula-
tion of the decimal for the next calendar quarter.

    Purchased Power  The Company has long-term contracts for the purchase of
electricity from various sources.  Generally, these contracts are for fixed
periods and require that the Company pay a demand charge for its capacity
entitlement and an energy charge to cover the cost of fuel.  The DPU ordered
the Company, effective July 1, 1991, to collect its capacity-related costs
associated with certain long-term power arrangements through base rates. 
Prior to that date, the Company was recovering these costs through its Fuel
Charge.  The current recovery mechanism utilizes a cost per kilowatthour (KWH)
factor that is calculated using historical (test-period) capacity costs and
unit sales.  This factor is then applied to current monthly KWH sales.  When
current period capacity costs and/or unit sales vary from test-period levels,
the Company experiences a revenue excess or shortfall which can have a
significant impact on net income.  All other capacity and energy-related
purchased power costs are recovered through the Fuel Charge.  The Company and
Cambridge Electric made a filing in late 1992 with the DPU seeking an alterna-
tive method of recovery.  This request was denied in a letter order issued on
October 6, 1993.  However, the Company and Cambridge Electric were encouraged
by the DPU's acknowledgement that the issues presented warrant further
consideration.  The DPU encouraged each company to continue to work with other
                                    PAGE 7

                         COMMONWEALTH ELECTRIC COMPANY

interested parties, including the Attorney General of Massachusetts, to reach
a consensus solution on the issue for consideration in each company's next
base rate proceeding.

    Conservation and Load Management Programs  The Company and Cambridge Elec-
tric have received approval from the DPU to recover conservation and load
management program (C&LM) costs.  The programs offer opportunities to all
customers to save energy by investing in C&LM measures.  The overall objective
of the programs is to reduce capacity and energy requirements which in turn
reduce the cost of providing service.  The Company has Conservation Charge
(CC) rate schedules which allow for current cost recovery from retail custom-
ers.  On June 30, 1993, the DPU issued an order in Phase I of a C&LM filing by
the Company and Cambridge Electric which authorizes the recovery of "lost base
revenues" from electric customers.  The recovery of lost base revenues is
allowed by the DPU to encourage effective implementation of C&LM programs. 
The KWH savings that are realized as a result of the successful implementation
of C&LM programs serve as the basis for determining lost base revenues.  The
amount to be recovered is approximately $3.5 million for the Company and is
based on anticipated KWH savings for the eighteen-month period beginning
January 1, 1993.  The revenue will be recovered from customers over a twelve-
month period which began July 1, 1993.  Through December 31, 1993, the Company
had recovered approximately $2.3 million in lost base revenue.

    On October 25, 1993, the DPU issued an order in Phase II of the C&LM
proceeding.  In that order, the DPU disallowed approximately $195,000 in
expenditures that it determined exceeded benefits to customers.  In addition,
the DPU ruled that approximately $1.1 million in C&LM Task Force related
expenditures are not recoverable by the Company "at this time" because certain
programs have yet to be implemented and thus ratepayers are receiving no
current benefits.  The Company removed these costs from the current CC decimal
and is continuing with the development of the programs and plans to seek
recovery of these costs in a subsequent filing with the DPU.  Based on the
language in the order and subsequent discussions with the parties involved in
the proceeding, management believes that the ultimate recovery of a substan-
tial portion of these costs is likely.

    Seabrook Costs  The full commission of the FERC, in a final order issued
on August 4, 1992, approved full recovery of Canal's investment in the
Seabrook nuclear power plant.  The Company and Cambridge Electric had been
billing, subject to refund, Seabrook 1 charges to their retail customers since
August 1, 1990 through Fuel Charge decimals approved by the DPU.  In its June
1, 1993 rate decision, the DPU allowed Cambridge Electric to recover its
Seabrook 1 costs in base rates.  However, the Company continues to recover
these costs through the Fuel Charge.

    The Company and Cambridge Electric collect, through their respective Fuel
Charge, amounts being billed to them by Canal for costs associated with
Seabrook 2 (over a ten-year period ending in 1997) pursuant to a Capacity
Acquisition Agreement the terms of which were approved by both FERC and the
DPU.

       (c) Economic Development Rate

    In an effort to foster industrial development in its service area, the
Company began offering an Economic Development Rate (EDR) on October 1, 1991.
                                    PAGE 8

                         COMMONWEALTH ELECTRIC COMPANY

The rate is offered to new or existing commercial and industrial customers who
have an electric demand of 500 kilowatts or more and meet specific financial
and other criteria.  As of December 31, 1993, twenty-two industrial customers
are benefitting from this special rate.  The rate is available for a six-year
term.  In 1993, the DPU conducted a generic investigation into EDRs and
rendered a decision on September 1, 1993 that established rate design guide-
lines and minimum customer eligibility requirements.  The Company refiled its
EDRs to comply with the ruling.  The Company also received approval for a
Vacant Space Rate which it filed in conformance with the new EDR guidelines
that is available to qualifying small commercial and industrial customers who
establish loads in previously unoccupied building space.

    Construction and Financing

    Information concerning the Company's financing and construction programs
is contained in Note 2(a) of Notes to Financial Statements filed under Item 8
of this report.

    Employees

    The total number of full-time employees for the Company declined 12% to
917 in 1993 from 1,042 employees at year-end 1992 due to a second quarter work
force reduction.  Of the current total, 602 employees (66%) are represented by
the Brotherhood of Utility Workers of New England, Inc. under three separate
collective bargaining units with agreements expiring October 31, 1994,
September 30, 1996 and October 31, 1997.  Employee relations have generally
been satisfactory and management views the current work force level to be
appropriate to service the Company's customers.

Item 2. Properties

    The principal properties of the Company consist of an integrated system of
transmission and distribution lines, substations, an office building in the
Town of Wareham, Massachusetts and other structures such as garages and
service buildings.  In addition, the Company owns and operates, for standby
and emergency purposes only, two diesel plants with a combined capability of
13.8 MW located on the island of Martha's Vineyard.  The Company also has a
1.4% joint-ownership interest in Central Maine Power Company's Wyman Unit 4
with an entitlement of 8.8 MW.

    The Company also owns a 60 MW steam electric generating station located in
New Bedford, Massachusetts.  This unit, which ceased operations in October
1992, was abandoned in 1993.  As a result, the net book value of the plant of
approximately $4 million was reclassified from Property, Plant and Equipment
to a regulatory asset in anticipation of recovery.

    At December 31, 1993, the electric transmission and distribution system
consisted of 5,691 pole miles of overhead lines, 3,423 cable miles of under-
ground line, 142 substations and 326,674 active customer meters.

Item 3. Legal Proceedings

    The Company is not a party to any pending material legal proceeding.
                                    PAGE 9

                         COMMONWEALTH ELECTRIC COMPANY

                                    PART II.


Item 5.   Market for the Registrant's Common Stock and Related Stockholder
          Matters

      (a) Principal Market

          Not applicable.  The Company is a wholly-owned subsidiary of Common-
          wealth Energy System.

      (b) Number of Shareholders at December 31, 1993

          One

      (c) Frequency and Amount of Dividends Declared in 1993 and 1992

                      1993                            1992            
                             Per Share                       Per Share
          Declaration Date     Amount     Declaration Date     Amount 

          January 28, 1993     $1.90      February 24, 1992     $1.45
          April 23, 1993        1.10      April 27, 1992         1.20
          October 18, 1993      3.20      October 19, 1992       2.50
                               $6.20                            $5.15

          In 1992 and on January 28, 1993, dividends were declared on the
          1,606,472 outstanding shares of common stock of the Company.  On
          April 23, 1993 and October 18, 1993, dividends were declared on the 
          2,043,972 outstanding shares of common stock of the Company.

          Reference is made to Note 6 of the Notes to Financial Statements
          filed under Item 8 of this report for the restriction against the
          payment of cash dividends.

      (d) Future dividends may vary depending upon the Company's earnings and
          capital requirements as well as financial and other conditions
          existing at that time.
                                    PAGE 10

                         COMMONWEALTH ELECTRIC COMPANY

Item 7. Management's Discussion and Analysis of Results of Operations

    The following is a discussion of certain significant factors which have
affected operating revenues, expenses and net income during the periods
included in the accompanying statements of income and is presented to facili-
tate an understanding of the results of operations.  This discussion should be
read in conjunction with Item 1 of this report and the Notes to Financial
Statements filed under Item 8 of this report.

    A summary of the period to period changes in the principal items included
in the statements of income for the years ended December 31, 1993 and 1992, is
shown below:

                                        Years Ended         Years Ended
                                        December 31,        December 31,
                                       1993 and 1992       1992 and 1991
                                             Increase (Decrease)
                                            (Dollars in Thousands)

Electric Operating Revenues         $ 20 991     5.1%     $(13 746)   (3.2)%

Operating Expenses -
 Electricity purchased for resale
   and fuel                           30 664    12.1         8 755     3.6
 Transmission                           (404)   (7.7)       (1 831)  (25.9)
 Other operation                      (7 275)   (9.6)        3 430     4.7
 Maintenance                          (1 429)  (11.8)         (712)   (5.5)
 Depreciation                             20     0.1           528     3.6
 Conservation and load management     (7 661)  (64.8)      (22 373)  (65.4)  
 Taxes -
   Federal and state income            3 602   101.3        (1 258)  (26.1)
   Local property and other              349     4.5           869    12.6
                                      17 866     4.6       (12 592)   (3.2)

Operating Income                       3 125    13.2        (1 154)   (4.7)

Other Income                              (4)   (1.6)         (258)  (50.5)

Income Before Interest Charges         3 121    13.1        (1 412)   (5.6)

Interest Charges                          47     0.3          (559)   (3.6)

Net Income                          $  3 074    34.1      $   (853)   (8.7)

Retail Unit Sales MWH Increase        22 203     0.7         7 106     0.2

                                    PAGE 11

                         COMMONWEALTH ELECTRIC COMPANY

Revenues and Unit Sales

   The following is a summary of unit sales and customers for the periods
indicated:
                                       Years Ended December 31,            
                                1993               1992               1991
                                          %                  %
Unit Sales (MWH):                       Change             Change

 Residential                 1 587 338   0.1    1 586 577   2.7    1 545 308
 Commercial                  1 030 050   1.2    1 018 162  (4.0)   1 060 622
 Industrial                    328 220   0.7      325 912  (1.0)     329 173
 Municipal and other           282 630   2.6      275 384   4.4      263 826
   Total retail              3 228 238   0.7    3 206 035   0.2    3 198 929
 Sales to other utilities    1 284 724  29.5      991 954  11.3      891 452
   Total                     4 512 962   7.5    4 197 989   2.6    4 090 381

Customers - 12 Month Average:

 Residential (1)               269 736   1.2      266 513   0.2      265 969
 Commercial (1)                 34 362   0.4       34 348   0.9       34 057
 Industrial                        326   1.2          322  (5.8)         342
 Municipal and other             3 315   3.7        3 198   4.7        3 055
   Total                       307 739   1.1      304 381   0.3      303 423

(1) Includes seasonal customers of 48,364 in 1993, 47,527 in 1992 and 47,200 
    in 1991.  Service is considered to be "seasonal" when the kilowatthours
    used in the billing months ending between June 1 and September 30 exceed
    the kilowatthours used in the preceding eight months.

    In 1993, operating revenues increased $21 million or 5.1% due primarily to
the increase in purchased power and fuel costs of $30.7 million (12.1%), a
7.5% increase in total unit sales and the recovery of approximately $2.3
million in lost base revenues related to conservation and load management
(C&LM) programs.  Partially offsetting these increases was a lower level ($7.7
million) of C&LM program costs.  Included in revenues were wholesale sales to
NEPOOL and to non-associate utilities of $26.5 million, $22.3 million and
$20.5 million in 1993, 1992 and 1991, respectively.  Fluctuations in the level
of wholesale electric sales have little, if any, impact on earnings.

    The Company has received approval from the Massachusetts Department of
Public Utilities (DPU) to recover in revenues current costs associated with
C&LM programs through the operation of a Conservation Charge (CC) decimal on a
dollar-for-dollar basis.  To the extent that these expenses increase or
decrease from period to period based on customer participation, a corre-
sponding change will occur in revenues.

    1992 operating revenues decreased $13.7 million or 3.2% despite an
increase in fuel and purchased power costs of $8.8 million (3.6%), a slight
increase in retail unit sales and a full year of higher base rates for the
Company.  This reduction was due primarily to a $22.4 million or 65.4%
decrease in C&LM costs recovered by the Company.

    Revenues during a portion of 1991 and through 1993 also reflect the impact
of the Company's Economic Development Rate which became effective on October
                                    PAGE 12

                         COMMONWEALTH ELECTRIC COMPANY

1, 1991.  Revenues were lower by $1.5 million, $1.3 million and $552,000 in
1993, 1992 and 1991, respectively.  These amounts represent the difference
between what certain commercial and industrial customers would have paid prior
to the availability of this rate.  For additional information on this special
rate, refer to the "Economic Development Rate" section in Item 1 of this
report.

    Although 1993 retail electric unit sales increased by less than 1%, each
customer segment did show improvement.  Unit sales reflect moderate growth in
customers, primarily residential, a greater demand for power from commercial
and seasonal customers reflecting an improving economy and, to a lesser
extent, more extreme weather conditions resulting in additional use to meet
heating or air conditioning requirements, offset somewhat by the impact of
conservation programs.  Retail electric unit sales were virtually unchanged in
1992 due primarily to a 2.7% increase in the residential sector caused by a
return to normal (colder) temperatures, resulting in a more normal heating
season in the first and fourth quarters of the year, offset somewhat by a
cooler than average summer period, C&LM programs and the difficult economic
conditions in communities served by the Company.

Purchased Power, Fuel and Transmission

    The cost of fuel used for electric generation and purchased power per KWH
sold was $.063, $.061 and $.060 for 1993, 1992 and 1991, respectively.  These
costs constitute 66%, 62% and 58% of electric operating revenues for the
respective years.  The upward trend since 1991 reflects the impact of the
Company's contractual obligations to take higher-cost power contracted for in
the 1980s when the Company's customer base grew dramatically and forecasts
predicted continued growth.  These contracts, which are typically long-term,
will continue to drive costs up as additional capacity comes on line.  The
Company is currently involved in negotiations to restructure or buy out
certain of these long-term contracts.

    For 1993 and 1992, fuel and purchased power costs increased $30.7 million
or 12.1% and $8.8 million or 3.6%, respectively, due to higher unit sales in
both years and the contractual obligations discussed above including addition-
al power purchases from certain gas-fired independent power producing (IPP)
facilities.  Both 1993 and 1992 reflect reduced purchases from Canal Electric
Company's units and other oil-fired units.  The increased costs for power from
the IPPs and other sources were offset somewhat by lower Seabrook 1 costs in
both years.  Reflected in purchased power and fuel for 1993 and 1992 was a
reduction in fuel costs of nearly $900,000 and $1.5 million, respectively, due
to the closing of the Company's Cannon Street generating station in late 1992
and a decline in other Company generation.

    In addition, purchased power and fuel expense for 1993 and 1992 includes
$5.1 million and $1.5 million, respectively, for capacity-related costs
associated with certain purchased power contracts that were not recovered in
revenues due to the mechanism established by the DPU.  The impact of this
under-recovery reduced net income by $3.1 million and $906,000 in 1993 and
1992, respectively. (Refer to the "Purchased Power" section in Item 1 on page
6 of this report.)

    As more fully discussed in the "Energy Mix" section of Item 1 of this
report, the Company's energy mix has shifted during the last several years
                                    PAGE 13

                         COMMONWEALTH ELECTRIC COMPANY

from oil to natural gas and other types of generation due to the availability
of capacity from IPP facilities and, to a lesser extent, an effort to reduce
its reliance on oil.

    Oil-fired generation, although reduced from prior years' levels, still
accounts for a major percentage of the Company's total sources, including
purchased power.  Reflected in the 1993 and 1992 cost is the increased use of
a cleaner burning but more expensive (1% sulphur) fuel oil at Canal.  Average
oil prices in 1993 at Canal's generating plant were $14.02 per barrel as
compared to $12.95 and $12.53 per barrel in 1992 and 1991, respectively.  In
compliance with restrictions on stack emissions, the Commonwealth of Massa-
chusetts mandated a reduction in sulphur dioxide emissions requiring the
periodic use of lower-sulphur (1%) content oil.  In 1993, 1% oil averaged
$15.16 per barrel for Canal, a 12.1% decrease from the $17.25 cost in 1992. 
However, lower-sulphur oil displaced 57.5% of the higher-sulphur (2.2%)
content oil as compared to 24% in 1992.  This higher cost oil is reflected in
the total average cost per barrel for 1993 and 1992 but was not used at Canal
in 1991.  The price of oil at Canal is expected to average approximately
$15.62 per barrel in 1994.

    Shown below is an analysis of fuel, purchased power and C&LM costs
together with base rate components of retail electric revenue:

                                            Percent of Retail Electric Revenue
                                                 1993       1992       1991
Revenue components:
    Costs recovered in Fuel or
       Conservation Charges                       52.2%      48.4%     57.6%
    Conservation and power costs in base rates    12.8       15.5       8.7
    Base rates and other                          35.0       36.1      33.7
                                                 100.0%     100.0%    100.0%

    Historically, revenue collected through base rates has been designed to
reimburse the Company for all costs of operation other than fuel, purchased
power and transmission expenses and provide a fair return on the capital
invested in the business.  As a result of the DPU's approval of new retail
rates effective July 1, 1991, the Company was ordered to collect certain long-
term capacity-related purchased power costs ($56.8 million in 1993, $52.9
million in 1992 and $26.2 million in 1991) and a portion of costs related to
its C&LM programs ($8.6 million in 1992 and $8.3 million in 1991) through its
base rates.  Beginning February 1, 1992, the Company's recovery of C&LM costs
were split from base rates through a separately stated Conservation Charge
(CC) decimal based on KWH used.
                                    PAGE 14

                         COMMONWEALTH ELECTRIC COMPANY

    The following is an analysis of the Company's revenue components and
current recoverable costs for the years 1993, 1992 and 1991:


                                       Years Ended December 31,            
                                 1993              1992               1991
                                          (Dollars in Thousands)
                                         %                   %
 Retail electric revenue:              Change              Change

   Costs recovered in Fuel
   or Conservation Charges    $210 717  12.4    $187 474   (19.2)  $232 086

   Conservation Charges and
   power costs in base rates    51 749 (14.0)     60 188    71.3     35 146
   Base rates and other        141 555   1.4     139 579     3.0    135 531
   Total retail revenue        404 021   4.3     387 241    (3.9)   402 763
 Total wholesale revenue        26 463  18.9      22 252     8.7     20 476
   Total revenue              $430 484   5.1    $409 493    (3.2)  $423 239

Other Operation

    In 1993, other operation decreased $7.3 million or 9.6% due to the absence
in the current year of costs associated with the Company's Cannon Street
generating station ($1.5 million) and the net savings of $1.1 million ($2.9
million in payroll savings less $1.8 million in severance costs) associated
with the second quarter work force reduction which is expected to save more
than $4 million annually in direct payroll costs.  Also contributing to the
lower costs in 1993 was the provision for bad debts expense which declined $2
million or 39.2% due to better payment experience reflecting improving
economic conditions, lower affiliate services company charges ($1 million) due
to the work force reduction and the absence in the current year of consulting
fees ($900,000) associated with the independent management audit conducted in
1992.  Also contributing to the lower expense level in 1993 was a decline in
employee medical and life insurance costs of $700,000 and lower liability
insurance costs of $300,000 due to fewer and less costly claims.  Offsetting
these decreases somewhat was an increase in pension costs of $600,000.

    Major factors contributing to the 4.7% increase in other operation in 1992
were the higher cost ($1.2 million) of medical and other types of insurance
and approximately $900,000 for consulting fees associated with the aforemen-
tioned management audit.  Also, computer-related and other professional
services provided to the Company by an affiliate services company were higher
by $1.2 million in 1992.  The provision for bad debts increased by $70,000
reflecting the difficult economic conditions in the Company's service territo-
ry and a decline in fuel assistance programs.  Certain factors offsetting
these increases were: 1) a $1.7 million reduction in net pension expense as a
result of asset valuation changes and the Company's deferral of $1.4 million
of accrued pension costs pursuant to current rate-making; and 2) continued
positive results from the Company's cost containment efforts, including
reduced overtime, work force reductions through attrition, early retirements
and the elimination of forty positions and associated costs relating to the
closing of the Company's Cannon Street generating station on October 1.
                                    PAGE 15

                         COMMONWEALTH ELECTRIC COMPANY

    The total number of full-time employees declined 17.6% to 917 in 1993 from
1,113 employees at year-end 1991.  Management views the current work force
level to be appropriate for service to its customers.

Maintenance

    Maintenance continued to decrease in 1993 from 1992 and 1991 levels due
primarily to reduced transmission and distribution-related costs and, to a
lesser extent, the decreased use and subsequent closing of the Cannon Street
facility.

Depreciation, Conservation and Load Management and Taxes

    Depreciation expense was virtually unchanged compared to 1992 reflecting a
somewhat level depreciable plant base resulting from the abandonment of the
Cannon Street generating station offsetting the impact of additions during the
period.  In 1992 depreciation expense rose 3.6% as a result of a higher level
of plant in service, particularly additions to transmission and distribution
facilities.

    C&LM costs for 1993 and 1992 included cash expenditures of $3.7 million
and $8.1 million, respectively, and amortization of previously deferred costs
which amounted to $500,000 in 1993 and $3.7 million in 1992.

    Income tax expense increased due to the significantly higher level of
pretax income and, to a lesser extent, an increase in the federal income tax
rate to 35%, retroactive to January 1, 1993.  In 1992, income tax expense
decreased $1.3 million or 26.1% as a result of lower pretax income.

    The 1993 and 1992 increases in local property and other taxes reflect a
combination of higher property tax rates and/or assessments in certain cities
and towns in the Company's service area.

Other Income and Interest Charges

    In 1993, the slight decrease in other income was due to the absence in
1993 of interest income from overpayment of Seabrook costs ($232,000) which
were refunded to customers in 1992, a decrease in the interest on the unamor-
tized portion of prior period conservation and load management program costs
($71,000) and a loss ($38,000) resulting from the disposition of the Cannon
Street station oil inventory.  This decrease was somewhat offset by an
increase in interest income ($201,000) from loans to affiliated companies and
a reduction in other income deductions ($117,000) that reflects a $75,000
reversal (in the third quarter of 1993) of a 1992 charge related to the
Company's 2.5% interest in the Yankee Atomic Power Company.  This reversal was
made as a result of a Federal Energy Regulatory Commission audit in late 1993.

    The decline in other income in 1992 was due to a decrease in interest
income ($208,000) from overpayment of Seabrook costs which were recovered in
early 1992 and the inclusion in 1992 of industry-related membership fees
($120,000) in other income deductions which were included in other operation
expense in 1991.  Also included in 1992 is the Company's write-off of Hurri-
cane Bob (August 1991) expenses of $9.2 million ($5.7 million after-tax) which
had been deferred in 1991 and an equal after-tax amount of the regulatory
                                    PAGE 16

                         COMMONWEALTH ELECTRIC COMPANY

liability related to deferred income taxes that would have otherwise been
returned to customers.

    In 1993, short-term interest charges decreased $2.5 million due to lower
interest rates and a lower average level of borrowings.  Interest rates on
short-term borrowings averaged 3.4% in 1993 compared to 4% in 1992.  In addi-
tion, 1993 reflects the absence of interest paid to customers in 1992
($232,000) relating to the overcollection of Seabrook costs.  The decreases in
short-term interest charges were nearly offset by increases in long-term
charges of $2.4 million in 1993, reflecting the issuance of $65 million in new
long-term debt in March 1993.

    Total interest charges decreased 3.6% in 1992 due to the 9.7% decline in
short-term interest charges ($456,000) and the 3.1% decline in long-term
interest charges ($348,000).  Despite a higher average level of short-term
borrowings created, in part, by the retirement of the Company's $7.5 million
Series D Note, short-term interest declined due to lower interest rates on
bank borrowings which averaged 4% for 1992 as compared to 6.3% for 1991.  In
addition, accrued interest on the overcollection of Seabrook 1 costs noted
above decreased $208,000.

Financing Activity

    On March 31, 1993, the Company issued long-term notes totaling $65
million.  The notes, which were sold through a private placement with institu-
tional investors, consisted of the following:

         10 Year, 7.43% Notes, Due 2003                  $15,000,000
         15 Year, 7.70% Notes, Due 2008                   10,000,000
         20 Year, 7.98% Notes, Due 2013                   25,000,000
         30 Year, 8.47% Notes, Due 2023                   15,000,000
                                                         $65,000,000

    The proceeds from the notes, together with the proceeds from the Company's
sale of 437,500 shares of common stock to the System for $35 million, were
used to repay outstanding short-term borrowings incurred to temporarily
finance additions to property, plant and equipment and to retire $21.8 million
of three series of long-term debt on March 1, 1993, as follows:

         Series E, 8.125% Notes, Due 1995                $ 4,860,000
         Series B, 6.125% Notes, Due 1997                  4,440,000
         Series F, 8.375% Notes, Due 1998                 12,000,000
                                                         $21,300,000

    The Company paid a premium totaling $337,000 on the early retirement of
debt and is amortizing this amount to expense over the remaining original life
of the retired issues.

New Accounting Standards

    Effective January 1, 1993, the Company adopted the provisions of State-
ment of Financial Accounting Standards No. 106, "Employers' Accounting for
Postretirement Benefits Other Than Pensions."  For further information, refer
to Note 4(b) of the Notes to Financial Statements.
                                    PAGE 17

                         COMMONWEALTH ELECTRIC COMPANY

    In 1992, the Financial Accounting Standards Board issued Statement of
Financial Accounting Standards No. 112, "Employers' Accounting for Postemploy-
ment Benefits" (SFAS 112).  The Company is required to adopt this statement
effective January 1, 1994.  SFAS 112 requires employers to recognize the
obligation to provide benefits to former or inactive employees after employ-
ment but before retirement (postemployment).  Those benefits include salary
continuation, supplemental employment benefits, severance benefits, disabili-
ty-related benefits and continuation of health care and life insurance
coverage if each of the following conditions are met: 1) the obligation is
attributable to employee services already rendered, 2) employees' rights to
those benefits accumulate or vest, 3) payment of the benefits is probable and
4) the cost of the benefits can be reasonably estimated.  The Company believes
that the adoption of the provisions of SFAS 112 will not have a material
impact on its financial position or results of operations.

Item 8.  Financial Statements and Supplementary Data

    The Company's financial statements required by this item are filed here-
with on pages 18 through 37 of this report.

Item 9.  Changes in and Disagreements With Accountants on Accounting
             and Financial Disclosure

    None.
                                    PAGE 18

                         COMMONWEALTH ELECTRIC COMPANY

Item 8. Financial Statements and Supplementary Data

                   REPORT OF INDEPENDENT PUBLIC ACCOUNTANTS

To Commonwealth Electric Company:

    We have audited the accompanying balance sheets of COMMONWEALTH ELECTRIC
COMPANY (a Massachusetts corporation and wholly-owned subsidiary of Common-
wealth Energy System) as of December 31, 1993 and 1992, and the related
statements of income, retained earnings and cash flows for each of the three
years in the period ended December 31, 1993.  These financial statements and
the schedules referred to below are the responsibility of the Company's
management.  Our responsibility is to express an opinion on these financial
statements and schedules based upon our audits.

    We conducted our audits in accordance with generally accepted auditing
standards.  Those standards require that we plan and perform the audit to
obtain reasonable assurance about whether the financial statements are free of
material misstatement.  An audit includes examining, on a test basis, evidence
supporting the amounts and disclosures in the financial statements.  An audit
also includes assessing the accounting principles used and significant
estimates made by management, as well as evaluating the overall financial
statement presentation.  We believe that our audits provide a reasonable basis
for our opinion.

    In our opinion, the financial statements referred to above present
fairly, in all material respects, the financial position of Commonwealth
Electric Company as of December 31, 1993 and 1992, and the results of its
operations and its cash flows for each of the three years in the period ended
December 31, 1993, in conformity with generally accepted accounting princi-
ples.

    As discussed in Note 4 to the financial statements, effective January 1,
1993, the Company changed its method of accounting for costs associated with
postretirement benefits other than pensions.

    Our audits were made for the purpose of forming an opinion on the basic
financial statements taken as a whole.  The schedules listed in the index to
financial statements and schedules are presented for purposes of complying
with the Securities and Exchange Commission's rules and are not part of the
basic financial statements.  These schedules have been subjected to the
auditing procedures applied in the audits of the basic financial statements
and, in our opinion, fairly state in all material respects the financial data
required to be set forth therein in relation to the basic financial statements
taken as a whole.



                                                        ARTHUR ANDERSEN & CO.
                                                        Arthur Andersen & Co.

Boston, Massachusetts,
February 17, 1994.
                                    PAGE 19

                         COMMONWEALTH ELECTRIC COMPANY
                  INDEX TO FINANCIAL STATEMENTS AND SCHEDULES
                                   PART II.


FINANCIAL STATEMENTS

    Balance Sheets at December 31, 1993 and 1992

    Statements of Income for the Years Ended December 31, 1993, 1992 and 1991

    Statements of Retained Earnings for the Years Ended December 31, 1993, 
    1992 and 1991

    Statements of Cash Flows for the Years Ended December 31, 1993, 1992 and 
    1991

    Notes to Financial Statements


                                   PART IV.


SCHEDULES

  III   Investments in, Equity in Earnings of, and Dividends Received from 
        Related Parties for the Years Ended December 31, 1991, 1992 and 1993

  V     Property, Plant and Equipment for the Years Ended December 31, 1993, 
        1992 and 1991

  VI    Accumulated Depreciation of Property, Plant and Equipment for the 
        Years Ended December 31, 1993, 1992 and 1991

  VIII  Valuation and Qualifying Accounts for the Years Ended December 31, 
        1993, 1992 and 1991

  IX    Short-Term Borrowings for the Years Ended December 31, 1993, 1992 and
        1991

SCHEDULES OMITTED

   All other schedules are not submitted because they are not applicable or
not required or because the required information is included in the financial
statements or notes thereto.

   Financial statements of 50% or less owned companies accounted for by the
equity method have been omitted because they do not, considered individually,
constitute a significant subsidiary.
                                    PAGE 20

                         COMMONWEALTH ELECTRIC COMPANY
                                BALANCE SHEETS
                          DECEMBER 31, 1993 AND 1992
                                    ASSETS



                                                         1993        1992
                                                      (Dollars in Thousands)

PROPERTY, PLANT AND EQUIPMENT, at original cost         $475 348   $476 839
 Less - Accumulated depreciation                         133 349    135 684
                                                         341 999    341 155
 Add - Construction work in progress                       5 478      4 794
                                                         347 477    345 949


INVESTMENTS
 Equity in nuclear electric power company                    601        601
 Other                                                        14         14
                                                             615        615


CURRENT ASSETS
 Cash                                                      2 794        507
 Advances to affiliates                                    4 485        -  
 Accounts receivable -
   Affiliated companies                                    2 413      3 906
   Customers, less reserves of $3,268,000 in 1993
     and $3,131,000 in 1992                               38 743     36 366
 Unbilled revenues                                         9 332     15 444
 Inventories, at average cost -
   Materials and supplies                                  4 658      6 040
   Electric production fuel oil                              202        485
 Prepaid property taxes                                    2 538      2 380
 Other                                                     1 927      1 547
                                                          67 092     66 675

DEFERRED CHARGES (Notes 1, 2 and 4)                       34 619     25 300

                                                        $449 803   $438 539


                                    PAGE 21

                         COMMONWEALTH ELECTRIC COMPANY
                                BALANCE SHEETS
                          DECEMBER 31, 1993 AND 1992
                        CAPITALIZATION AND LIABILITIES

                                                         1993        1992
                                                     (Dollars in Thousands)
CAPITALIZATION
 Common Equity -
   Common stock, $25 par value -
     Authorized and outstanding - 
       2,043,972 shares in 1993 and
       1,606,472 shares in 1992,
       wholly-owned by Commonwealth
       Energy System (Parent)                           $ 51 099   $ 40 162
   Amounts paid in excess of par value                    97 112     73 049
   Retained earnings (Note 6)                             15 118     14 882
                                                         163 329    128 093
 Long-term debt, including premiums, less
   current sinking fund requirements (Note 5)            158 858    116 213
                                                         322 187    244 306

CURRENT LIABILITIES
 Interim Financing (Note 5) -
   Notes payable to banks                                    -       67 275
   Advances from affiliates                                  -       11 840
                                                             -       79 115

 Other Current Liabilities -
   Current sinking fund requirements                       1 053        537
   Accounts payable -
     Affiliated companies                                 10 088     10 797
     Other                                                22 044     17 231
   Accrued taxes -
     Local property and other                              3 017      2 637
     Income                                                2 337        610
   Accrued interest                                        4 027      3 092
   Other                                                   9 098      7 003
                                                          51 664     41 907
                                                          51 664    121 022
DEFERRED CREDITS
 Accumulated deferred income taxes                        39 396     34 346
 Unamortized investment tax credits                        8 430      8 876
 Other                                                    28 126     29 989
                                                          75 952     73 211
COMMITMENTS AND CONTINGENCIES (Note 2)
                                                        $449 803   $438 539




  The accompanying notes are an integral part of these financial statements.


                                    PAGE 22

                         COMMONWEALTH ELECTRIC COMPANY
                             STATEMENTS OF INCOME
             FOR THE YEARS ENDED DECEMBER 31, 1993, 1992 AND 1991



                                            1993         1992       1991
                                                (Dollars in Thousands)


ELECTRIC OPERATING REVENUES               $430 484     $409 493    $423 239

OPERATING EXPENSES
 Electricity purchased for resale
    and fuel                               284 980      254 316     245 561
 Transmission                                4 836        5 240       7 071
 Other operation                            68 797       76 072      72 642
 Maintenance                                10 714       12 143      12 855
 Depreciation                               15 032       15 012      14 484
 Conservation and load
    management                               4 165       11 826      34 199
 Taxes -
    Income (Note 3)                          7 158        3 556       4 814
    Local property                           5 023        4 694       3 730
    Payroll and other                        3 066        3 046       3 141
                                           403 771      385 905     398 497

OPERATING INCOME                            26 713       23 588      24 742

OTHER INCOME, net                              249          253         511

INCOME BEFORE INTEREST CHARGES              26 962       23 841      25 253

INTEREST CHARGES
 Long-term debt                             13 252       10 891      11 239
 Other interest charges                      1 738        4 248       4 704
 Allowance for borrowed funds used
    during construction                       (106)        (302)       (547)
                                            14 884       14 837      15 396

NET INCOME                                $ 12 078     $  9 004    $  9 857













    The accompanying notes are an integral part of these financial statements.
                                    PAGE 23

                         COMMONWEALTH ELECTRIC COMPANY
                        STATEMENTS OF RETAINED EARNINGS
             FOR THE YEARS ENDED DECEMBER 31, 1993, 1992 AND 1991




                                            1993         1992        1991
                                               (Dollars in Thousands)

Balance at beginning of year              $14 882      $14 151     $12 246

Add (Deduct):
 Net income                                12 078        9 004       9 857
 Cash dividends on common stock           (11 842)      (8 273)     (7 952)

Balance at end of year                    $15 118      $14 882     $14 151





































 The accompanying notes are an integral part of these financial statements.
                                    PAGE 24

                         COMMONWEALTH ELECTRIC COMPANY
                           STATEMENTS OF CASH FLOWS
             FOR THE YEARS ENDED DECEMBER 31, 1993, 1992 AND 1991


                                                 1993       1992       1991
                                                    (Dollars in Thousands)
OPERATING ACTIVITIES
  Net income                                  $ 12 078   $  9 004   $  9 857
  Effects of non-cash items -
    Depreciation and amortization               16 447     19 666     25 224
    Deferred income taxes                        4 407     (5 176)      (729)
    Investment tax credits                        (446)      (452)      (482)
    Earnings from corporate joint ventures         -          (75)       (73)
  Change in working capital exclusive of cash
      and interim financing -
    Accounts receivable and unbilled
      revenues                                   5 228      7 119     (7 485)
    Income taxes, net                            1 727     (3 705)    (2 280)
    Local property and other taxes, net            222        (25)       390
    Accounts payable and other                   8 935     (2 159)     4 608
  Uncollected postretirement benefits
    costs (Note 4)                              (4 087)       -          -  
  All other operating items                     (5 590)     7 580    (10 856)

Net cash provided by operating activities       38 921     31 777     18 174

INVESTING ACTIVITIES
  Additions to property, plant and
    equipment (exclusive of AFUDC)             (18 631)   (20 821)   (31 303)
  Allowance for borrowed funds used
    during construction                           (106)      (302)      (547)
  Advances to affiliates                        (4 485)       -          -  

Net cash used for investing activities         (23 222)   (21 123)   (31 850)

FINANCING ACTIVITIES
  Long-term debt issues                         65 000        -          -  
  Sale of common stock to Parent                35 000        -          -  
  Payment of dividends                         (11 842)    (8 273)    (7 952)
  Proceeds from (payment of)
    short-term borrowings                      (67 275)     3 975     15 050
  Advances from (payment to) affiliates        (11 840)     2 290      7 215
  Long-term debt issues refunded               (21 300)    (7 522)       -  
  Retirement of long-term debt
    through sinking funds                       (1 155)      (631)      (636)
Net cash provided by (used for)
  financing activities                         (13 412)   (10 161)    13 677

Net increase in cash                             2 287        493          1
Cash at beginning of period                        507         14         13
Cash at end of period                         $  2 794   $    507   $     14



  The accompanying notes are an integral part of these financial statements.
                                    PAGE 25

                         COMMONWEALTH ELECTRIC COMPANY
                         NOTES TO FINANCIAL STATEMENTS

(1) Significant Accounting Policies

    (a) General and Regulatory

    Commonwealth Electric Company (the Company) is a wholly-owned subsidiary
of Commonwealth Energy System.  The parent company is referred to in this
report as the "System" and, together with its subsidiaries, is collectively
referred to as "the system."  The Company is regulated as to rates, accounting
and other matters by various authorities including the Federal Energy Regula-
tory Commission (FERC) and the Massachusetts Department of Public Utilities
(DPU).  The System is an exempt holding company under the provisions of the
Public Utility Holding Company Act of 1935 and, in addition to its investment
in the Company, has interests in other utility companies and several non-
regulated companies.

    The Company has established various regulatory assets in cases where the
DPU and/or the FERC have permitted, or are expected to permit, recovery of
specific costs over time.  At December 31, 1993, principal regulatory assets
included in deferred charges were $8.6 million for unrecovered plant and
decommissioning costs for the Yankee Atomic nuclear plant, $7.4 million in
litigation costs associated with a settlement agreement with Boston Edison
Company relative to the Pilgrim nuclear power plant, $4.4 million in abandon-
ment costs for the Cannon Street generating station and $4.1 million for
postretirement benefits costs.  The more significant regulatory liabilities,
reflected in deferred credits, include $8.6 million related to the Yankee
Atomic nuclear plant and $4 million related to income taxes.

    (b) Reclassifications

    Certain prior year amounts are reclassified from time to time to conform
with the presentation used in the current year's financial statements.

    (c) Transactions with Affiliates

    Transactions between the Company and other system companies include
purchases and sales of electricity, including purchases from Canal Electric
Company (Canal), an affiliate wholesale electric generating company.  Other
costs billed by Canal relate to the abandonment of Seabrook 2 for the three
years ending in 1993 and the recovery of a portion of Seabrook 1 pre-commer-
cial operation financing costs in 1991.  In addition, payments for management,
accounting, data processing and other services are made to affiliate COM/Ener-
gy Services Company.  Transactions with other system companies are subject to
review by the DPU.

    The Company's operating revenues include the following major intercompany
transactions for the periods indicated:
                                                         Purchased Power
                                                         and Transmission
    Period Ended   Purchased Power     Purchased Power      From Canal
    December 31,     Canal Units         Seabrook 1          As Agent    
                                   (Dollars in Thousands)
       1993            $40 537             $36 467            $20 881
       1992             46 844              37 482             22 992
       1991             53 547              50 912             26 422
                                    PAGE 26

                         COMMONWEALTH ELECTRIC COMPANY

    The Company sold electricity to other affiliates, primarily station
service for Canal, totaling $2,973,000, $2,733,000 and $8,065,000 in 1993,
1992 and 1991, respectively, and the Company also purchased natural gas from
affiliate Commonwealth Gas Company totaling $106,000 in 1992 and $1,288,000 in
1991 (there were no purchases in 1993).

    (d) Operating Revenues

    Customers are billed for their use of electricity on a cycle basis
throughout the month.  To reflect revenues in the proper period, the estimated
amount of unbilled sales revenue is recorded each month.

    The Company is generally permitted to bill customers currently for fuel
used in electric production, purchased power and transmission costs, and
conservation and load management costs through adjustment clauses.  Amounts
recoverable under these clauses are subject to review and adjustment by the
DPU.  The Company collects a portion of capacity-related purchased power costs
associated with certain long-term power arrangements through base rates.  The
amount of such fuel and energy costs incurred but not yet reflected in
customers' bills, which totaled $3,056,000 in 1993 and $6,918,000 in 1992, is
recorded as unbilled revenues.

    (e) Depreciation

    Depreciation is provided using the straight-line method at rates intended
to amortize the original cost and the estimated cost of removal less salvage
of properties over their estimated economic lives.  The average composite
depreciation rates were 3.31% in 1993 and 3.39% in 1992 and 1991.

    (f) Maintenance

    Expenditures for repairs of property and replacement and renewal of items
determined to be less than units of property are charged to maintenance
expense.  Additions, replacements and renewals of property considered to be
units of property are charged to the appropriate plant accounts.  Upon
retirement, accumulated depreciation is charged with the original cost of
property units and the cost of removal less salvage.

    (g) Allowance for Funds Used During Construction

    Under applicable rate-making practices, the Company is permitted to
include an allowance for funds used during construction (AFUDC) as an element
of its depreciable property costs.  This allowance is based on the amount of
construction work in progress that is not included in the rate base on which
the Company earns a return.  An amount equal to the AFUDC capitalized in the
current period is reflected in the accompanying Statements of Income.

    While AFUDC does not provide funds currently, these amounts are recover-
able in revenues over the service life of the constructed property.  The
amount of AFUDC recorded was at a weighted average rate of 4% in 1993, 4.50%
in 1992 and 6.75% in 1991.
                                    PAGE 27

                         COMMONWEALTH ELECTRIC COMPANY

(2) Commitments and Contingencies

    (a) Financing and Construction Programs

    The Company is engaged in a continuous construction program presently
estimated at $141 million for the five-year period 1994 through 1998.  Of that
amount, $24.8 million is estimated for 1994.  The program is subject to
periodic review and revision because of factors such as changes in business
conditions, rates of customer growth, effects of inflation, maintenance of
reliable and safe service, equipment delivery schedules, licensing delays,
availability and cost of capital and environmental factors.  The Company
expects to finance these expenditures on an interim basis with internally
generated funds and short-term borrowings which are ultimately expected to be
repaid with the proceeds from sales of long-term debt and equity securities.

    (b) Power Contracts

    The Company has long-term contracts for the purchase of electricity from
various sources.  Generally, these contracts are for fixed periods and require
that the Company pay a demand charge for the capacity entitlement and an
energy charge to cover the cost of fuel.  In addition, the Company pays its
share of decommissioning expense to non-affiliate Boston Edison Company, the
operator of the Pilgrim nuclear facility, as a cost of electricity purchased
for resale.

    The Company has entered into Power Contracts with Canal for a portion of
the capacity from Canal Units 1 and 2.  In addition, Canal seeks to secure
bulk electric power on a single system basis to provide cost savings for the
customers of the Company and Cambridge Electric under terms of a Capacity
Acquisition and Disposition Agreement (CADA) which has been accepted for
filing as an amendment to Canal's rate schedule by the FERC.  The CADA allows
Canal to act as agent for the Company and Cambridge Electric in the procure-
ment of additional capacity for one or both companies, or, to sell a portion
of each company's entitlement of capacity and/or energy produced by Canal Unit
2.  Such "Commitments" are in effect for Seabrook 1, Phases I and II of Hydro-
Quebec, New England Power Company (Bear Swamp Units), Green Mountain Power
Corporation, Northeast Utilities and for Central Vermont Public Service Corp.
(Vermont Yankee and Merrimac 2 Unit).  Exchange agreements are in place with
several of these utilities whereby, in certain circumstances, it is possible
to exchange capacity so that the mix of power improves the pricing for
dispatch for both the seller and the purchaser.  Power contracts are in place,
whereby Canal bills or credits the Company and Cambridge Electric for the
costs or revenues received associated with these facilities.  The Company and
Cambridge Electric, in turn, have billed or are billing these net charges (net
of revenues from sales) to their customers through rates which are subject to
DPU approval.
                                    PAGE 28

                         COMMONWEALTH ELECTRIC COMPANY

    Pertinent information with respect to life-of-the-unit contracts for power
from the Pilgrim unit and an ownership in Central Maine Power Company's Wyman
Unit 4, an oil-fired unit, is as follows:
                                                                Wyman
                                                 Pilgrim        Unit 4
                                                 (Dollars in Thousands)

    Joint Ownership                                 -            1.4%
    Plant Entitlement                              11.0%         1.4%
    Plant Capability (MW)                         664.7         619.2
    Company's Entitlement (MW)                     73.1           8.8
    Contract Expiration Date                       2012           -
    1991 Actual Cost                            $30 992          $296
    1992 Actual Cost                             37 516           332
    1993 Actual Cost                             40 578           163
    1994 Estimated Cost                          41 963           205

    The Company has also contracted to purchase power and transmission
capacity from various other generating and transmission facilities as follows:

                                                                Estimated  
                      1991           1992           1993           1994    
                   MW    Cost     MW    Cost     MW    Cost     MW    Cost  
                                   (Dollars in Thousands)
Purchased Power -
  Nuclear         82.6 $42 016    6.8 $ 1 560    3.7 $  1 187   2.2 $    506
  Hydro           30.9  13 052   14.0  11 784   15.1    9 731  15.0   11 087
  Cogenerating   117.0  34 938  162.0  69 742  161.0  104 719 261.5  135 363
  Waste-to-energy
    and other     92.1  33 009   78.9  31 336   74.7   36 013  72.1   35 862
Transmission -
  (Hydro-Quebec)   -     3 884    -     2 991    -      3 015   -      3 165

   Costs under these and other contracts are included in electricity pur-
chased for resale and fuel in the accompanying Statements of Income and are
recoverable in revenues through either the Fuel Charge or in base rates.

   (c) Yankee Atomic Nuclear Power Plant

   On February 26, 1992, the Board of Directors of Yankee Atomic Electric
Company agreed to permanently discontinue power operation of its plant and, in
time, decommission that facility.  This plant provided less than 1% of the
Company's capacity.  The Company's 2.5% investment in Yankee Atomic is
approximately $600,000.  Presently, purchased power costs, which include a
provision for ultimate decommissioning of the unit, are billed to the Company
and collected from customers.

   The Company has estimated its unrecovered share of all costs associated
with the shutdown of the facility, recovery of its respective plant investment
and decommissioning and closing the plant to be approximately $8.6 million. 
This amount is reflected in the accompanying Balance Sheets as a liability and
a corresponding regulatory asset at December 31, 1993.
                                    PAGE 29

                         COMMONWEALTH ELECTRIC COMPANY

   (d) Environmental Matters

   The Company is subject to laws and regulations administered by federal,
state and local authorities relating to the quality of the environment.  These
laws and regulations affect, among other things, the siting and operation of
electric generating and transmission facilities and can require the installa-
tion of expensive air and water pollution control equipment.  These regula-
tions have had an impact upon the Company's operations in the past and will
continue to have an impact upon future operations, capital costs and construc-
tion schedules of major facilities.

(3) Income Taxes

   For financial reporting purposes, the Company provides federal and state
income taxes on a separate return basis.  However, for federal income tax
purposes, the Company's taxable income and deductions are included in the
consolidated income tax return of the System and it makes tax payments or
receives refunds on the basis of its tax attributes in the tax return in
accordance with applicable regulations.

   The following is a summary of the Company's provisions for income taxes
for the years ended December 31, 1993, 1992 and 1991.

                                            1993       1992       1991
                                              (Dollars in Thousands) 
    Federal
        Current                           $ 2 627    $   (15)   $ 4 948
        Deferred                            3 705     (4 548)      (668)
        Investment tax credits               (446)      (452)      (482)
                                            5 886     (5 015)     3 798
    State
        Current                               570        (34)     1 057
        Deferred                              749        348        (61)
                                            1 319        314        996
                                            7 205     (4 701)     4 794
    Amortization of regulatory liability
    relating to deferred income taxes         (47)      (976)       -  
                                          $ 7 158    $(5 677)   $ 4 794

    Federal and state income taxes
    charged to:
        Operating expense                 $ 7 158    $ 3 556    $ 4 814
        Other income                          -       (9 233)       (20)
                                          $ 7 158    $(5 677)   $ 4 794

    Effective January 1, 1992, the Company adopted the provisions of Statement
of Financial Accounting Standards No. 109, "Accounting for Income Taxes" (SFAS
No. 109).  SFAS No. 109 requires recognition of deferred tax liabilities and
assets for the expected future tax consequences of events that have been
included in the financial statements or tax returns.  Under this method,
deferred tax liabilities and assets are determined based on the difference
between the financial statement and tax basis of assets and liabilities using
tax rates in effect in the year in which the differences are expected to
reverse.

                                    PAGE 30

                         COMMONWEALTH ELECTRIC COMPANY

    Accumulated deferred income taxes consisted of the following in 1993 and
1992:
                                             1993          1992
                                           (Dollars in Thousands)

    Liabilities
      Property-related                     $44 837       $40 483
      Litigation costs                       2 886         2 957
      Postretirement benefits plan           2 222           376
      All other                              1 918         2 050
                                            51 863        45 866

    Assets
      Investment tax credit                  5 441         5 507
      Pension plan                           1 384         1 302
      Regulatory liability                     -             630
      Uncollectible accounts                 1 282         1 137
      All other                              2 463         1 706
                                            10 570        10 282
    Accumulated deferred income taxes      $41 293       $35 584

    The year-end deferred income tax liability above includes a current
deferred tax liability of $1,897,000 in 1993 and $1,238,000 in 1992 which was
reported in accrued income taxes in the accompanying Balance Sheets.

    The following table, detailing the significant timing differences for 1991
which resulted in deferred income taxes, is required to be disclosed pursuant
to accounting standards for income taxes in effect prior to adoption of SFAS
No. 109:
                                                           1991
                                                  (Dollars in Thousands)

    Accelerated depreciation                             $ 3 593
    Seabrook power contract settlement                    (2 229)
    Capitalized interest during construction                (150)
    Contributions in aid of construction                    (451)
    Capitalized leases                                      (579)
    Pension costs and deferred compensation                 (394)
    Conservation and load management                      (4 370)
    Replacement power costs                                1 656
    Transmission costs                                      (508)
    Storm damage                                           3 638
    Voluntary retirement program                             (20)
    Other                                                   (915)
        Deferred income tax provision                     $ (729)
                                    PAGE 31

                         COMMONWEALTH ELECTRIC COMPANY

    The total income tax provision set forth above represents 37% in 1993,
(171)% in 1992 and 33% in 1991 of income before such taxes.  The following
table reconciles the statutory federal income tax rate to these percentages:

                                             1993        1992         1991
                                                            (000's)

    Federal statutory rate                    35%     34%  $ 1 131     34%
    Increase (Decrease) from statutory rate:
     Amortization of regulatory liability
        relating to deferred income taxes      -    (173)   (5 768)     -
     State tax net of federal tax benefit      4       7       228      5
     Amortization of investment tax credit    (2)    (14)     (452)    (3)
     Tax versus book depreciation              1       3       111      1
     Amortization of excess
        deferred reserves                      -     (28)     (920)    (3)
     Other                                    (1)     -         (7)    (1)
    Effective federal tax rate                37%   (171)% $(5 677)    33%

    On April 22, 1992, the Company reached a settlement agreement with the
Attorney General of Massachusetts and a consumer group, which was approved by
the DPU.  The settlement resulted in the issuance of an accounting order
authorizing the Company's retention of $5.7 million in excess deferred taxes
subject to obtaining a favorable ruling from the Internal Revenue Service
which was received on November 30, 1992.

    In accordance with the above settlement agreement, the Company wrote off
in 1992 storm damage costs of $9.2 million ($5.7 million net of tax).  The
balance of the excess reserves that would have been returned to customers was
removed from the deferred tax reserve account and, after adjustment to its
pretax amount as required by SFAS 109, was credited to a liability account. 
The excess reserves/regulatory liability which the Company would retain
pursuant to the settlement agreement was also removed from this liability
account and credited to other income together with the related income taxes. 
These amounts were classified as income tax expense and were used in the
reconciliation of the income tax rate.

    As a result of the Revenue Reconciliation Act of 1993, the Company's
federal income tax rate increased to 35% effective January 1, 1993.

(4) Employee Benefit Plans

    (a) Pension

    The Company has a noncontributory pension plan covering substantially all
regular employees who have attained the age of 21 and have completed a year of
service.  Pension benefits are based on an employee's years of service and
compensation.  The Company makes monthly contributions to the plan consistent
with the funding requirements of the Employee Retirement Income Security Act
of 1974.
                                    PAGE 32

                         COMMONWEALTH ELECTRIC COMPANY

    Components of pension expense were as follows:

                                                  1993       1992       1991
                                                    (Dollars in Thousands)

    Service cost                               $  2 630   $  2 728   $  2 815
    Interest cost                                 9 283      8 506      7 532
    Return on plan assets                       (16 412)   (10 992)   (20 677)
    Net amortization and deferral                 9 130      4 235     15 209
    Total pension expense                         4 631      4 477      4 879
    Transfers to affiliated companies, net         (465)      (609)      (575)
    Less: Amounts capitalized and deferred        1 379      2 127        839
    Net pension expense                        $  2 787   $  1 741   $  3 465

    The following economic assumptions were used to measure year-end obliga-
tions and the estimated pension expense for the subsequent year:

                                                  1993       1992       1991

    Discount rate                                  7.25%      8.50%      8.50%
    Assumed rate of return                         8.50       8.50       8.50
    Rate of increase in future compensation        4.50       5.50       5.50

    Pension expense reflects the use of the projected unit credit method which
is also the actuarial cost method used in determining future funding of the
plan.  The Company, in accordance with current rate-making, is deferring the
difference between pension contribution, which is allowed currently in base
rates, and pension expense recognized pursuant to Statement of Financial
Accounting Standards No. 87, "Employers' Accounting for Pensions."  The funded
status of the Company's pension plan (using a measurement date of December 31)
is as follows:

                                                   1993           1992
                                                  (Dollars in Thousands)
    Accumulated benefit obligation:
        Vested                                  $ (95 433)     $ (74 178)
        Nonvested                                 (13 030)        (5 815)
                                                $(108 463)     $ (79 993)

    Projected benefit obligation                $(131 066)     $(104 024)
    Plan assets at fair market value              120 685        107 529
    Projected benefit obligation less
        (greater) than plan assets                (10 381)         3 505
    Unamortized transition obligation               5 146          5 789
    Unrecognized prior service cost                 5 520          4 139
    Unrecognized gain                              (5 095)       (17 321)
    Accrued pension liability                   $  (4 810)     $  (3 888)

    Plan assets consist primarily of fixed income and equity securities. 
Fluctuations in the fair market value of plan assets will affect pension
expense in future years.  The increase in the accumulated benefit obligation
and the projected benefit obligation from December 31, 1992 to December 31,
1993 was primarily due to a reduction of the discount rate in light of current
interest rates.
                                    PAGE 33

                         COMMONWEALTH ELECTRIC COMPANY

    (b) Other Postretirement Benefits

    Through December 31, 1992, the Company provided postretirement health care
and life insurance benefits to eligible retired employees.  Employees became
eligible for these benefits if their age plus years of service at retirement
equaled 75 or more provided, however, that such service was performed for the
Company or another subsidiary of the System.  As of January 1, 1993, the
Company eliminated postretirement health care benefits for those nonbargaining
employees who were less than 40 years of age or had less than 12 years of
service at that date.  Under certain circumstances, eligible employees are now
required to make contributions for postretirement benefits.  Certain bargain-
ing employees are also participating under these new eligibility requirements.

    Effective January 1, 1993, the Company adopted the provisions of Statement
of Financial Accounting Standards No. 106, "Employers' Accounting for Postre-
tirement Benefits Other Than Pensions" (SFAS No. 106).  This new standard
requires the accrual of the expected cost of such benefits during the employ-
ees' years of service and the recognition of an actuarially determined postre-
tirement benefit obligation earned by existing retirees.  The assumptions and
calculations involved in determining the accrual and the accumulated postre-
tirement benefit obligation (APBO) closely parallel pension accounting
requirements.  The cumulative effect of implementation of SFAS No. 106 as of
January 1, 1993 was approximately $48.3 million which is being amortized over
20 years.  Prior to 1993, the cost of postretirement benefits was recognized
as the benefits were paid.  The cost of retiree medical care and life insur-
ance benefits under the traditional pay-as-you-go method totaled $1,915,000
during 1992 and $1,668,000 in 1991.

    In 1993, the Company began making contributions to various voluntary
employee beneficiary association (VEBA) trusts that were established pursuant
to section 501(c)9 of the Internal Revenue Code (the Code).  The Company also
made contributions to a sub-account of its pension plan pursuant to section
401(h) of the Code to satisfy a portion of its postretirement benefit obliga-
tion.  The Company contributed approximately $5,964,000 to these trusts during
1993.

    The net periodic postretirement benefit cost for the year ended December
31, 1993 included the following components:

                                                               1993
                                                     (Dollars in Thousands)

   Service cost                                              $ 1 093
   Interest cost                                               4 103
   Return on plan assets                                        (292)
   Amortization of transition obligation over 20 years         2 417
   Net amortization and deferral                                   3
      Total postretirement benefit cost                        7 324
   Less: Amounts capitalized and deferred                      5 701
      Net postretirement benefit cost                        $ 1 623
                                    PAGE 34

                         COMMONWEALTH ELECTRIC COMPANY

   The funded status of the Company's postretirement benefit plan using a
measurement date of December 31, 1993 is as follows:

                                                                1993
                                                      (Dollars in Thousands)

   Accumulated postretirement benefit obligation:
     Retirees                                                $ (27 520)
     Active participants                                       (23 033)
                                                               (50 553)
   Plan assets at fair market value                              5 308
   Projected postretirement benefit obligation greater
     than plan assets                                          (45 245)
   Unamortized transition obligation                            45 917
   Unrecognized gain                                              (672)
                                                             $     -  

   In determining its estimated APBO and the funded status of the plan, the
Company assumed a discount rate of 7.25%, an expected long-term rate of return
on plan assets of 8.5%, and a medical care cost trend rate of 9%, which
gradually decreases to 5% in the year 2007 and remains at that level thereaf-
ter.  The estimate also reflects a trend rate of 14.9% for reimbursement of
Medicare Part B premiums which decreases to 5% by 2007 and a dental care trend
rate of 5% in all years.  A one percent change in the medical trend rate would
have an $836,000 impact on the Company's annual expense (interest component -
$564,000; service cost - $272,000) and would change the accumulated benefit
obligation by $6.9 million.

   Plan assets consist primarily of fixed income and equity securities.
Fluctuations in the fair market value of plan assets will affect postretire-
ment benefit expense in future years.

   The DPU's policy on postretirement benefits is to allow in rates the
maximum tax deductible contributions made to trusts that have been established
specifically to pay postretirement benefits.  Effective with its June 1, 1993
rate order from the DPU, Cambridge Electric was allowed to recover its SFAS
No. 106 expense in base rates over a four-year phase-in period with carrying
costs on the deferred balance.  The Company intends to seek recovery in its
next rate proceeding.  While the Company is unable to predict the outcome of
that rate proceeding, it believes the DPU will authorize similar rate treat-
ment as provided to Cambridge Electric and other Massachusetts electric and
gas companies for the recovery of the cost of these benefits.  Further, based
on recent DPU action and discussions with regulators, the Company believes
that it is appropriate to record the difference between the amount included in
rates and SFAS No. 106 costs as a regulatory asset.  At December 31, 1993,
this deferral amounted to approximately $4.1 million.

   (c) Savings Plan

   The Company has an Employees Savings Plan that provides for Company
contributions equal to contributions by eligible employees of up to four
percent of each employee's compensation rate.  Effective January 1, 1993, the
rate was increased to five percent for those employees no longer eligible for
postretirement benefits other than pensions.  The Company's contribution was
$1,700,000 in 1993, $1,808,000 in 1992 and $1,703,000 in 1991.
                                    PAGE 35

                         COMMONWEALTH ELECTRIC COMPANY

(5) Long-Term Debt and Interim Financing

    (a) Long-Term Debt Maturities and Retirements

    Long-term debt outstanding, exclusive of current maturities, current
sinking fund requirements and related premiums, is as follows:

                                              Original  Balance December 31,
                                               Issue      1993       1992
                                                  (Dollars in Thousands)

   25-Year Notes -
        Series E, 8 1/8%, due 1995           $  9 000   $    -     $  4 860
        Series F, 8 3/8%, due 1998             20 000        -       12 000
   30-Year Notes -
        Series B, 6 1/8%, due 1997              6 000        -        4 440
   15-Year Term Loan, 9.30%, due 2002          30 000     30 000     30 000
   25-Year Term Loan, 9.37%, due 2012          20 000     18 947     20 000
   10-Year Notes, 7.43%, due 2003              15 000     15 000        -
   15-Year Notes, 9.50%, due 2004              15 000     15 000     15 000
   15-Year Notes, 7.70%, due 2008              10 000     10 000        -
   18-Year Notes, 9.55%, due 2007              10 000     10 000     10 000
   20-Year Notes, 7.98%, due 2013              25 000     25 000        -
   25-Year Notes, 9.53%, due 2014              10 000     10 000     10 000
   30-Year Notes, 9.60%, due 2019              10 000     10 000     10 000
   30-Year Notes, 8.47%, due 2023              15 000     15 000        -  
                                                        $158 947   $116 300

    The balance of long-term debt at December 31, 1992 was exclusive of
$103,000 principal amount purchased by the Company and deposited with the
Trustee in anticipation of future sinking fund requirements.  The Company may
continue to purchase its outstanding notes in advance of sinking fund require-
ments under favorable conditions.

    Under terms of its Indentures of Trust, the Company is required to make
periodic sinking fund payments for retirement of outstanding long-term debt. 
The required sinking fund payments for the five years subsequent to December
31, 1993 are as follows:

                            Year        Sinking Funds
                                   (Dollars in Thousands)

                            1994           $1 053
                            1995            1 053
                            1996            3 553
                            1997            3 553
                            1998            3 553

    (b) Notes Payable to Banks

    The Company and other system companies maintain both committed and
uncommitted lines of credit for the short-term financing of their construction
programs and other corporate purposes.  As of December 31, 1993, system
companies had $115 million of committed lines of credit that will expire at
varying intervals in 1994.  These lines are normally renewed upon expiration
                                    PAGE 36

                         COMMONWEALTH ELECTRIC COMPANY

and require annual fees up to .1875% of the individual line.  At December 31,
1993, the uncommitted lines of credit totaled $70 million.  Interest rates on 
the outstanding borrowings generally are at an adjusted money market rate.  At
December 31, 1993, the Company had no notes payable to banks.  The Company had
short-term notes payable to banks totaling $67,275,000 at December 31, 1992.

    (c) Advances from Affiliates

    At December 31, 1993, the Company had no notes payable to the System.  The
Company had short-term notes payable to the System totaling $8,445,000 at
December 31, 1992.  These notes are written for a term of eleven months and
twenty-nine days.  Interest is at the prime rate (6% at December 31, 1992) and
is adjusted for changes in the rate during the term of the notes.

    The Company is a member of the COM/Energy Money Pool (the Pool), an
arrangement among the subsidiaries of the System, whereby short-term cash
surpluses are used to help meet the short-term borrowing needs of the utility
subsidiaries.  In general, lenders to the Pool receive a higher rate of return
than they otherwise would on such investments, while borrowers pay a lower
interest rate than those available from banks.  The Company had $4,485,000
invested in the Pool at December 31, 1993, but had borrowings from the Pool of
$3,395,000 at December 31, 1992.

    (d) Disclosures about Fair Value of Financial Instruments

    As required by Statement of Financial Accounting Standards No. 107,
"Disclosures about Fair Value of Financial Instruments," the fair value of
certain financial instruments included in the accompanying Balance Sheets as
of December 31, 1993 and 1992 are as follows:

                                1993                        1992        
                                     (Dollars in Thousands)

                       Carrying        Fair       Carrying        Fair  
                         Value         Value        Value         Value 

    Long-Term Debt     $159 911      $184 180     $116 750      $128 600

    The carrying amount of cash, advances to/from affiliates and notes payable
to banks approximates the fair value because of the short maturity of the
instruments.

    The estimated fair value of long-term debt is based upon quoted market
prices of the same or similar issues or on the current rates offered for debt
with the same remaining maturity.  The fair values shown above do not purport
to represent the amounts at which those obligations would be settled.

(6) Dividend Restriction

    At December 31, 1993, approximately $11,700,000 of retained earnings was
restricted against the payment of cash dividends by terms of the Indenture of
Trust securing long-term debt.  As of the same date, retained earnings also
included approximately $218,000 representing the Company's equity in undis-
tributed earnings of Yankee Atomic Electric Company.
                                    PAGE 37

                         COMMONWEALTH ELECTRIC COMPANY

(7) Lease Obligations

    The Company leases equipment and office space under arrangements that are
classified as operating leases.  These lease agreements are for terms of one
year or longer.  Leases currently in effect contain no provisions which
prohibit the Company from entering into future lease agreements or obliga-
tions.

    Future minimum lease payments, by period and in the aggregate, of non-can-
celable operating leases consisted of the following at December 31, 1993:

                                                    Operating Leases
                                                  (Dollars in Thousands)

                  1994                                   $ 3 412
                  1995                                     2 832
                  1996                                     2 020
                  1997                                       773
                  1998                                       352
                  Beyond 1998                              1 192
                  Total future minimum lease payments    $10 581

    Total rent expense for all operating leases, except those with terms of a
month or less, amounted to $3,491,000 in 1993, $3,669,000 in 1992 and
$3,783,000 in 1991.  There were no contingent rentals and no sublease rentals
for the years 1993, 1992 and 1991.

(8) Supplemental Disclosures of Cash Flow Information

    The Company's supplemental information concerning cash flow activities is
as follows:

                                                  1993      1992      1991
                                                   (Dollars in Thousands)
    Cash paid during the periods for:
        Interest (net of capitalized amounts)   $ 13 074  $ 14 084  $ 14 714
        Income taxes                               2 438     1 491     6 275
                                    PAGE 38

                         COMMONWEALTH ELECTRIC COMPANY
                                   PART IV.

Item 14.Exhibits, Financial Statement Schedules and Reports on Form 8-K

(a) 1.  Index to Financial Statements

        Financial statements and notes thereto of the Company together with 
        the Report of Independent Public Accountants, are filed under Item 8
        of this report and listed on the Index to Financial Statements and
        Schedules (page 19).

(a) 2.  Index to Financial Statement Schedules

        Filed herewith at page(s) indicated -

        Schedule III - Investments in, Equity in Earnings of, and Dividends
        Received from Related Parties - Years Ended December 31, 1991, 1992
        and 1993 (page 50).

        Schedule V - Property, Plant and Equipment - Years Ended December 31,
        1993, 1992 and 1991 (pages 51-53).

        Schedule VI - Accumulated Depreciation of Property, Plant and Equip-
        ment - Years Ended December 31, 1993, 1992 and 1991 (page 54).

        Schedule VIII - Valuation and Qualifying Accounts - Years Ended Decem-
        ber 31, 1993, 1992 and 1991 (page 55).

        Schedule IX - Short-term Borrowings - Years Ended December 31, 1993,
        1992 and 1991 (page 56).

(a) 3.  Exhibits:
                              Notes to Exhibits -

    a.  Unless otherwise designated, the exhibits listed below are incorporat-
        ed by reference to the appropriate exhibit numbers and the Securities
        and Exchange Commission file numbers indicated in parentheses.

    b.  If applicable, as designated by an asterisk, certain documents previ-
        ously filed by the Company have been disposed of by the Commission
        pursuant to its Records Control Schedule and are hereby being refiled
        by the Company.

    c.  During 1981, the Company sold its gas business and properties to
        Commonwealth Gas and changed its corporate name from New Bedford Gas
        and Edison Light Company to Commonwealth Electric Company.

    d.  The following is a glossary of Commonwealth Energy System and subsid-
        iary companies' acronyms that are used throughout the following
        Exhibit Index:

        CES ...................... Commonwealth Energy System
        CEL ...................... Cambridge Electric Light Company
        CEC ...................... Canal Electric Company
        CG ....................... Commonwealth Gas Company
        NBGEL .................... New Bedford Gas and Edison Light Co.
                                    PAGE 39

                         COMMONWEALTH ELECTRIC COMPANY

                                Exhibit Index:

Exhibit 3. Articles of incorporation and by-laws

3.1.1      By-laws of the Company as amended, (Refiled as Exhibit 1 to the CE
           1991 Form 10-K, File No. 2-7749).

3.1.2      Articles of Incorporation, as amended, of NBGEL, including certif-
           ication of name change to Commonwealth Electric Company as filed
           with the Massachusetts Secretary of State on March 1, 1981 (Re-
           filed as Exhibit 1 to the CE 1990 Form 10-K, File No. 2-7749).

Exhibit 4. Instruments defining the rights of security holders, including
           indentures.

4.1.1      Original Indenture on Form S-1 (Nov., 1948) (Exhibit 7(a), File
           No. 2-7749).
4.1.2      First Supplemental on Form S-1 (Oct., 1950) (Exhibit 7(a-1), File
           No. 2-8605).
4.1.3      Second Supplemental (Exhibit 1 to the CE 1984 Form 10-K, File No.
           2-7749).
4.1.4      Third Supplemental on Form 8-K (Feb., 1962) (Exhibit A, File No.
           2-7749).
4.1.5      Fourth Supplemental (Exhibit 2 to the CE 1984 Form 10-K, File No.
           2-7749).
4.1.6      Fifth Supplemental (Exhibit 3 to the CE 1984 Form 10-K, File No.
           2-7749).
4.1.7      Sixth Supplemental (Exhibit 4 to the CE 1984 Form 10-K, File No.
           2-7749).
4.1.8      Seventh Supplemental on Form S-1 (Dec., 1975) (Exhibit 4(b)2, File
           No. 2-54955).

           Cape & Vineyard Electric Company**:

4.1.9      Original Indenture on Form S-1 (Apr., 1957) (Exhibit 4(b)1, File
           No. 2-26429).
4.1.10     First Supplemental (Exhibit 5 to the CE 1984 Form 10-K, File No.
           2-7749).
4.1.11     Second Supplemental (Exhibit 6 to the CE 1984 Form 10-K, File No.
           2-7749).

                 **Merged with the Company on January 1, 1971

Exhibit 10. Material Contracts.

10.1       Power contracts.

10.1.1     Power contracts between CEC (Unit 1) and NBGEL and CEL dated
           December 1, 1965 (Exhibit 13(a)(1-4) to the CEC Form S-1, File No.
           2-30057).

10.1.2     Power contract between Yankee Atomic Electric Company (YAEC) and
           NBGEL dated June 30, 1959, as amended April 1, 1975 (Refiled as
           Exhibit 2 to the CE 1991 Form 10-K, File No. 2-7749).
                                    PAGE 40

                         COMMONWEALTH ELECTRIC COMPANY

10.1.2.1   Second, Third and Fourth Amendments to 10.1.2 as amended October
           1, 1980, April 1, 1985 and May 6, 1988, respectively (Exhibit 1 to
           the CE Form 10-Q (June 1988), File No. 2-7749).

10.1.2.2   Fifth and Sixth Amendments to 10.1.2 as amended June 26, 1989 and
           July 1, 1989, respectively (Exhibit 3 to the CE Form 10-Q (Septem-
           ber 1989), File No. 2-7749).

10.1.3     Agreement between NBGEL and Boston Edison Company (BECO) for the
           purchase of electricity from BECO's Pilgrim Unit No. 1 dated Aug-
           ust 1, 1972 (Exhibit 7 to the CE 1984 Form 10-K, File No. 2-7749).

10.1.3.1   Service Agreement between NBGEL and BECO for purchase of stand-by
           power for BECO's Pilgrim Station dated August 16, 1978 (Exhibit 1
           to the CE 1988 Form 10-K, File No. 2-7749).

10.1.3.2   System Power Sales Agreement by and between CE and BECO dated July
           12, 1984 (Exhibit 1 to the CE Form 10-Q (September 1984), File No.
           2-7749).

10.1.3.3   Power Exchange Agreement by and between BECO and CE dated December
           1, 1984 (Exhibit 16 to the CE 1984 Form 10-K, File No. 2-7749).

10.1.4     Agreement for Joint-Ownership, Construction and Operation of New
           Hampshire Nuclear Units (Seabrook) dated May 1, 1973 (Exhibit
           13(N) to the NBGEL Form S-1 dated October 1973, File No. 2-49013),
           and as amended below:

10.1.4.1   First through Fifth Amendments to 10.1.4 as amended May 24, 1974,
           June 21, 1974, September 25, 1974, October 25, 1974 and January
           31, 1975, respectively (Exhibit 13(m) to the NBGEL Form S-1 (No-
           vember 7, 1975), File No. 2-54995).

10.1.4.2   Sixth through Eleventh Amendments to 10.1.4 as amended April 18,
           1979, April 25, 1979, June 8, 1979, October 11, 1979 and December
           15, 1979, respectively (Refiled as Exhibit 1 to the CEC 1989 Form
           10-K, File No. 2-30057).

10.1.4.3   Twelfth through Fourteenth Amendments to 10.1.4 as amended May 16,
           1980, December 31, 1980 and June 1, 1982, respectively (Refiled as
           Exhibits 1, 2, and 3 to the CE 1992 Form 10-K, File No.2-7749).

10.1.4.4   Fifteenth and Sixteenth Amendments to 10.1.4 as amended April 27,
           1984 and June 15, 1984, respectively (Exhibit 1 to the CEC Form
           10-Q (June 1984), File No. 2-30057).

10.1.4.5   Seventeenth Amendment to 10.1.4 as amended March 8, 1985 (Exhibit
           1 to the CEC Form 10-Q (March 1985), File No. 2-30057).

10.1.4.6   Eighteenth Amendment to 10.1.4 as amended March 14, 1986 (Exhibit
           1 to the CEC Form 10-Q (March 1986), File No. 2-30057).

10.1.4.7   Nineteenth Amendment to 10.1.4 as amended May 1, 1986 (Exhibit 1
           to the CEC Form 10-Q (June 1986), File No. 2-30057).
                                    PAGE 41

                         COMMONWEALTH ELECTRIC COMPANY

10.1.4.8   Twentieth Amendment to 10.1.4 as amended September 19, 1986 (Ex-
           hibit 1 to the CEC 1986 Form 10-K, File No. 2-30057).

10.1.4.9   Twenty-First Amendment to 10.1.4 as amended November 12, 1987
           (Exhibit 1 to the CEC 1987 Form 10-K, File No. 2-30057).

10.1.4.10  Settlement Agreement and Twenty-Second Amendment to 10.1.4, both
           dated January 13, 1989 (Exhibit 4 to the CEC 1988 Form 10-K, File
           No. 2-30057).

10.1.5     Interim Agreement to Preserve and Protect the Assets of and In-
           vestment in the New Hampshire Nuclear Units dated April 27, 1984
           (Exhibit 2 to the CEC Form 10-Q (June 1984), File No. 2-30057).

10.1.6     Resolutions proposed by Merrill Lynch Capital Markets and adopted
           by the Joint-Owners of the Seabrook Nuclear Project regarding
           Project financing, dated May 14, 1984 (Exhibit 1 to the CEC Form
           10-Q (March 1984), File No. 2-30057).

10.1.7     Agreement for Seabrook Project Disbursing Agent establishing YAEC
           as the disbursing agent under the Joint-Ownership Agreement, dated
           May 23, 1984 (Exhibit 4 to the CEC Form 10-Q (June 1984), File No.
           2-30057).

10.1.7.1   First Amendment to 10.1.7 as amended March 8, 1985 (Exhibit 2 to
           the CEC Form 10-Q (March 1985), File No. 2-30057).

10.1.7.2   Second through Fifth Amendments to 10.1.7 as amended May 20, 1985,
           June 18, 1985, January 2, 1986 and November 12, 1987, respectively
           (Exhibit 4 to the CEC 1987 Form 10-K, File No. 2-30057).

10.1.8     Purchase and Sale Agreement together with an implementing Addendum
           dated December 31, 1981, between CE and CEC, for the purchase and
           sale of the CE 3.52% joint-ownership interest in the Seabrook
           units, dated January 2, 1981 (Refiled as Exhibit 4 to the CE 1992
           Form 10-K, File No. 2-7749).

10.1.8.1   Agreement to transfer ownership, construction and operational
           interest in the Seabrook Units 1 and 2 from CE to CEC dated Janu-
           ary 2, 1981 (Refiled as Exhibit 3 to the CE 1991 Form 10-K, File
           No. 2-7749).

10.1.9     Termination Supplement between CEC, CE and CEL for Seabrook Unit
           2, dated December 8, 1986 (Exhibit 3 to the CEC 1986 Form 10-K,
           File No. 2-30057).

10.1.10    Power Contract, as amended to February 28, 1990, superseding the
           Power Contract dated September 1, 1986 and amendment dated June 1,
           1988, between CEC (seller) and CE and CEL (purchasers) for sell-
           er's entire share of the Net Unit Capability of Seabrook 1 and
           related energy (Exhibit 1 to the CEC Form 10-Q (March 1990), File
           No. 2-30057).
                                    PAGE 42

                         COMMONWEALTH ELECTRIC COMPANY

10.1.11    Agreement between NBGEL and Central Maine Power Company (CMP), for
           the joint-ownership, construction and operation of William F.
           Wyman Unit No. 4 dated November 1, 1974 together with Amendment
           No. 1 dated June 30, 1975 (Exhibit 13(N) to the NBGEL Form S-1,
           File No. 2-54955).

10.1.11.1  Amendments No. 2 and 3 to 10.1.11 as amended August 16, 1976 and
           December 31, 1978 (Exhibit 5(a) 14 to the System's Form S-16 (June
           1979), File No. 2-64731).

10.1.12    Contract between CEC and NBGEL and CEL, affiliated companies, for
           the sale of specified amounts of electricity from Canal Unit 2
           dated January 12, 1976 (Exhibit 7 to the System's 1985 Form 10-K,
           File No. 1-7316).

10.1.13    Capacity Acquisition Agreement between CEC,CEL and CE dated Sep-
           tember 25, 1980 (Exhibit 1 to the CEC 1991 Form 10-K, File No. 2-
           30057).

10.1.13.1  Supplement to 10.1.13 consisting of three Capacity Acquisition
           Commitments each dated May 7, 1987, concerning Phases I and II of
           the Hydro-Quebec Project and electricity acquired from Connecticut
           Light and Power Company CL&P) (Exhibit 1 to the CEC Form 10-Q
           (September 1987), File No. 2-30057).

10.1.13.2  Supplements to 10.1.13 consisting of two Capacity Acquisition
           Commitments each dated October 31, 1988, concerning electricity
           acquired from Western Massachusetts Electric Company and/or CL&P
           for periods ranging from November 1, 1988 to October 31, 1994
           (Exhibit 2 to the CEC Form 10-Q (September 1989), File No. 2-
           30057).

10.1.13.3  Amendment to 10.1.13 as amended and restated June 1, 1993, hence-
           forth referred to as the Capacity Acquisition and Disposition
           Agreement, whereby CEC, as agent, in addition to acquiring power
           may also sell bulk electric power which CEL and/or the Company
           owns or otherwise has the right to sell (Exhibit 1 to the CEC Form
           10-Q (September 1993), File No. 2-30057).

10.1.13.4  Capacity Disposition Commitment dated June 25, 1993 by and between
           CEC (Unit 2) and the Company for the sale of a portion of the Com-
           pany's entitlement in Unit 2 to Green Mountain Power Corp.(Exhibit
           2 to the CEC Form 10-Q (September 1993), File No. 2-30057).

10.1.14    Phase 1 Vermont Transmission Line Support Agreement and Amendment
           No. 1 thereto between Vermont Electric Transmission Company, Inc.
           and certain other New England utilities, dated December 1, 1981
           and June 1, 1982, respectively (Refiled as Exhibits 5 and 6 to the
           1992 CE Form 10-K, File No. 2-7749).

10.1.14.1  Amendment No. 2 to 10.1.14 as amended November 1, 1982 (Exhibit 5
           to the CE Form 10-Q (June 1984), File No. 2-7749).

10.1.14.2  Amendment No. 3 to 10.1.14 as amended January 1, 1986 (Exhibit 2
           to the CE 1986 Form 10-K, File No. 2-7749).
                                    PAGE 43

                         COMMONWEALTH ELECTRIC COMPANY

10.1.15    Participation Agreement between MEPCO and CEL and/or NBGEL dated
           June 20, 1969 for construction of a 345 KV transmission line
           between Wiscasset, Maine and Mactaquac, New Brunswick, Canada and
           for the purchase of base and peaking capacity from the NBEPC
           (Exhibit 13 to the CES 1984 Form 10-K, File No. 1-7316).

10.1.15.1  Supplement Amending 10.1.15 as amended June 24, 1970 (Exhibit 8 to
           the CES Form S-7, Amendment No. 1, File No. 2-38372).

10.1.16    Power Purchase Agreement (Revised) between Weweantic Hydro Associ-
           ates and the Company for the purchase of available hydro-electric
           energy produced by a facility located in Wareham, MA, originally
           dated December 13, 1982, revised and dated March 12, 1993 (Filed
           as Exhibit 1 to the CE Form 10-Q (June 1993), File No. 2-7749).

10.1.17*   Power Purchase Agreement between Pioneer Hydropower, Inc. and CE
           for the purchase of available hydro-electric energy produced by a
           facility located in Ware, Massachusetts, dated September 1, 1983
           (Refiled herewith as Exhibit 1).

10.1.18*   Power Purchase Agreement between Corporation Investments, Inc.
           (CI), and CE for the purchase of available hydro-electric energy
           produced by a facility located in Lowell, Massachusetts, dated
           January 10, 1983 (Refiled herewith as Exhibit 2).

10.1.18.1  Amendment to 10.1.18 between CI and Boott Hydropower, Inc., an
           assignee therefrom, and CE, as amended March 6, 1985 (Exhibit 8 to
           the CE 1984 Form 10-K, File No. 2-7749).

10.1.19    Phase 1 Terminal Facility Support Agreement dated December 1,
           1981, Amendment No. 1 dated June 1, 1982 and Amendment No. 2 dated
           November 1, 1982, between New England Electric Transmission Corpo-
           ration (NEET), other New England utilities and CE (Exhibit 1 to
           the CE Form 10-Q (June 1984), File No. 2-7749).

10.1.19.1  Amendment No. 3 to 10.1.19 (Exhibit 2 to the CE Form 10-Q (June
           1986), File No. 2-7749).

10.1.20    Preliminary Quebec Interconnection Support Agreement dated May 1,
           1981, Amendment No. 1 dated September 1, 1981, Amendment No. 2
           dated June 1, 1982, Amendment No. 3 dated November 1, 1982, Amend-
           ment No. 4 dated March 1, 1983 and Amendment No. 5 dated June 1,
           1983 among certain New England Power Pool (NEPOOL) utilities
           (Exhibit 2 to the CE Form 10-Q (June 1984), File No. 2-7749).

10.1.21    Agreement with Respect to Use of Quebec Interconnection dated
           December 1, 1981, Amendment No. 1 dated May 1, 1982 and Amendment
           No. 2 dated November 1, 1982 among certain NEPOOL utilities (Ex-
           hibit 3 to the CE Form 10-Q (June 1984), File No. 2-7749).

10.1.21.1  Amendatory Agreement No. 3 to 10.1.21 as amended June 1, 1990,
           among certain NEPOOL utilities (Exhibit 1 to the CEC Form 10-Q
           (September 1990), File No. 2-30057).
                                    PAGE 44

                         COMMONWEALTH ELECTRIC COMPANY

10.1.22    Phase I New Hampshire Transmission Line Support Agreement between
           NEET and certain other New England Utilities dated December 1,
           1981 (Exhibit 4 to the CE Form 10-Q (June 1984), File No. 2-7749).

10.1.23    Agreement, dated September 1, 1985, with Respect To Amendment of
           Agreement With Respect To Use Of Quebec Interconnection, dated
           December 1, 1981, among certain NEPOOL utilities to include Phase
           II facilities in the definition of "Project" (Exhibit 1 to the CEC
           Form 10-Q (September 1985), File No. 2-30057).

10.1.24    Preliminary Quebec Interconnection Support Agreement - Phase II
           among certain New England electric utilities dated June 1, 1984
           (Exhibit 6 to the CE Form 10-Q (June 1984), File No. 2-7749).

10.1.24.1  First, Second and Third Amendments to 10.1.24 as amended March 1,
           1985, January 1, 1986 and March 1, 1987, respectively (Exhibit 1
           to the CEC Form 10-Q (March 1987), File No. 2-30057).

10.1.24.2  Fifth, Sixth and Seventh Amendments to 10.1.24 as amended October
           15, 1987, December 15, 1987 and March 1, 1988, respectively (Ex-
           hibit 1 to the CEC Form 10-Q (June 1988), File No. 2-30057).

10.1.24.3  Fourth and Eighth Amendments to 10.1.24 as amended July 1, 1987
           and August 1, 1988, respectively (Exhibit 3 to the CEC Form 10-Q
           (September 1988), File No. 2-30057).

10.1.24.4  Ninth and Tenth Amendments to 10.1.24 as amended November 1, 1988
           and January 15, 1989, respectively (Exhibit 2 to the CEC 1988 Form
           10-K, File No. 2-30057).

10.1.24.5  Eleventh Amendment to 10.1.24 as amended November 1, 1989 (Exhibit
           4 to the CEC 1989 Form 10-K, File No. 2-30057).

10.1.24.6  Twelfth Amendment to 10.1.24 as amended April 1, 1990 (Exhibit 1
           to the CEC Form 10-Q (June 1990), File No. 2-30057).

10.1.25    Phase II Equity Funding Agreement for New England Hydro-Transmis-
           sion Electric Company, Inc. (New England Hydro) (Massachusetts),
           dated June 1, 1985, between New England Hydro and certain NEPOOL
           utilities (Exhibit 2 to the CEC Form 10-Q (September 1985), File
           No. 2-30057).

10.1.26    Phase II Massachusetts Transmission Facilities Support Agreement
           dated June 1, 1985, refiled as a single agreement incorporating
           Amendments 1 through 7 dated May 1, 1986 through January 1, 1989,
           respectively, between New England Hydro and certain NEPOOL utili-
           ties (Exhibit 2 to the CEC Form 10-Q (September 1990), File No. 2-
           30057).

10.1.27    Phase II New Hampshire Transmission Facilities Support Agreement
           dated June 1, 1985, refiled as a single agreement incorporating
           Amendments 1 through 8 dated May 1, 1986 through January 1, 1990,
           respectively, between New England Hydro-Transmission Corporation
           (New Hampshire Hydro) and certain NEPOOL utilities (Exhibit 3 to
           the CEC Form 10-Q (September 1990), File No. 2-30057).
                                    PAGE 45

                         COMMONWEALTH ELECTRIC COMPANY

10.1.28    Phase II Equity Funding Agreement for New Hampshire Hydro, dated
           June 1, 1985, between New Hampshire Hydro and certain NEPOOL util-
           ities (Ex. 3 to the CEC Form 10-Q (Sept. 1985), File No. 2-30057).

10.1.28.1  Amendment No. 1 to 10.1.28 dated May 1, 1986 (Exhibit 6 to the CEC
           Form 10-Q (March 1987), File No. 2-30057).

10.1.28.2  Amendment No. 2 to 10.1.28 as amended September 1, 1987 (Exhibit 3
           to the CEC Form 10-Q (September 1987), File No. 2-30057).

10.1.29    Phase II New England Power AC Facilities Support Agreement, dated
           June 1, 1985, between NEP and certain NEPOOL utilities (Exhibit 6
           to the CEC Form 10-Q (September 1985), File No. 2-30057).

10.1.29.1  Amendments Nos. 1 and 2 to 10.1.29 as amended May 1, 1986 and
           February 1, 1987, respectively (Exhibit 5 to the CEC Form 10-Q
           (March 1987), File No. 2-30057).

10.1.29.2  Amendments Nos. 3 and 4 to 10.1.29 as amended June 1, 1987 and
           September 1, 1987, respectively (Exhibit 5 to the CEC Form 10-Q
           (September 1987), File No. 2-30057).

10.1.30    Phase II Boston Edison AC Facilities Support Agreement, dated June
           1, 1985, between BECO and certain NEPOOL utilities (Exhibit 7 to
           the CEC Form 10-Q (September 1985), File No. 2-30057).

10.1.30.1  Amendments Nos. 1 and 2 to 10.1.30 as amended May 1, 1986 and
           February 1, 1987, respectively (Exhibit 2 to the CEC Form 10-Q
           (March 1987), File No. 2-30057).

10.1.30.2  Amendments Nos. 3 and 4 to 10.1.30 as amended June 1, 1987 and
           September 1, 1987, respectively (Exhibit 4 to the CEC Form 10-Q
           (September 1987), File No. 2-30057).

10.1.31    Agreement Authorizing Execution of Phase II Firm Energy Contract,
           dated September 1, 1985, among certain NEPOOL utilities in regard
           to participation in the purchase of power from Hydro-Quebec (Ex-
           hibit 8 to the CEC Form 10-Q (September 1985), File No. 2-30057).

10.1.32    System Power Sales Agreement by and between CE, as seller, and
           Central Vermont Public Service Corporation (CVPS), as buyer, dated
           September 15, 1984 (Exhibit 2 to the CE Form 10-Q (September
           1984), File No. 2-7749).

10.1.32.1  System Sales Agreement by CVPS, as seller, and CE, as buyer, dated
           September 15, 1984 (Exhibit 9 to the CE 1984 Form 10-K, File No.
           2-7749).

10.1.32.2  System Sales and Exchange Agreement by and between CVPS and CE on
           energy transactions, dated September 15, 1984 (Exhibit 10 to the
           CE 1984 Form 10-K, File No. 2-7749).

10.1.32.3  System Exchange Agreement by and between CE and CVPS for the
           exchange of capacity and associated energy, dated September 3,
           1985 (Exhibit 1 to the CE 1985 Form 10-K, File No. 2-7749).
                                    PAGE 46

                         COMMONWEALTH ELECTRIC COMPANY

10.1.32.4  Purchase Agreement by and between CEC and CVPS for the purchase of
           capacity from CEC for the term March 1, 1991 to October 31, 1995,
           dated March 1, 1991 (Exhibit 1 to CEC Form 10-Q (June 1991), File
           No. 2-30057).

10.1.32.5  Power Sale Agreement by and between CEC and CVPS for the purchase
           of 50 MW of capacity from CVPS's units (25 MW from Vermont Yankee
           and 25 MW from Merrimack 2) for the term of March 1, 1991 to
           October 31, 1995, dated March 1, 1991 (Exhibit 2 to CEC Form 10-Q
           (June 1991), File No. 2-30057).

10.1.33    Agreements by and between Swift River Company and CE for the
           purchase of available hydro-electric energy to be produced by
           units located in Chicopee and North Willbraham, Massachusetts,
           both dated September 1, 1983 (Exhibits 11 and 12 to the CE 1984
           Form 10-K, File No. 2-7749).

10.1.33.1  Transmission Service Agreement between Northeast Utilities' compa-
           nies (NU) - The Connecticut Light and Power Company (CL&P) and
           Western Massachusetts Electric Company (WMECO), and CE for NU
           companies to transmit power purchased from Swift River Company's
           Chicopee Units to CE, dated October 1, 1984 (Exhibit 14 to the CE
           1984 Form 10-K, File No. 2-7749).

10.1.33.2  Transformation Agreement between WMECO and CE whereby WMECO is to
           transform power to CE from the Chicopee Units, dated December 1,
           1984 (Exhibit 15 to the CE 1984 Form 10-K, File No. 2-7749).

10.1.34    System Power Sales Agreement by and between CL&P and WMECO, as
           buyers, and CE, as seller, dated January 13, 1984 (Exhibit 13 to
           the CE 1984 Form 10-K, File No. 2-7749).

10.1.35    System Power Sales Agreement by and between CL&P, WMECO, as sell-
           ers, and CEL, as buyer, of power in excess of firm power customer
           requirements from the electric systems of the NU Companies, dated
           June 1, 1984, as effective October 25, 1985 (Exhibit 1 to CEL 1985
           Form 10-K, File No. 2-7909).

10.1.36    Power Purchase Agreement with Respect to South Meadow Unit Nos.
           11, 12, 13, and 14 of the NU system company of CL&P (seller) and
           CE (buyer), dated November 1, 1985 (Exhibit 1 to the CE Form 10-Q
           (June 1986), File No. 2-7749).

10.1.37    Power Purchase Agreement by and between SEMASS Partnership, as
           seller, to construct, operate and own a solid waste disposal
           facility at its site in Rochester, Massachusetts and CE, as buyer
           of electric energy and capacity, dated September 8, 1981 (Exhibit
           17 to the CE 1984 Form 10-K, File No. 2-7749).

10.1.37.1  Power Sales Agreement to 10.1.37 for all capacity and related
           energy produced, dated October 31, 1985 (Exhibit 2 to the CE 1985
           Form 10-K, File No. 2-7749).
                                    PAGE 47

                         COMMONWEALTH ELECTRIC COMPANY

10.1.37.2  Amendment to 10.1.37 for all additional electric capacity and
           related energy to be produced by an addition to the Original Unit,
           dated March 14, 1990 (Exhibit 1 to the CE Form 10-Q (June 1990),
           File No. 2-7749).

10.1.37.3  Second Amendment to 10.1.37.2 for all additional electric capacity
           and related energy to be produced by an addition to the Original
           Unit, dated May 24, 1991 (Exhibit 1 to the CE Form 10-Q (June
           1991), File No. 2-7749).

10.1.38    System Power Sales Agreement by and between CE (seller) and NEP
           (buyer), dated January 6, 1984 (Exhibit 1 to the CE Form 10-Q
           (June 1985), File No. 2-7749).

10.1.39    Service Agreement by and between CE and NEP dated March 24, 1984,
           whereas CE agrees to purchase short-term power applicable to NEP'S
           FERC Electric Tariff Number 5 (Exhibit 1 to the CE Form 10-Q (June
           1987), File No. 2-7749).

10.1.40    Power Sale Agreement by and between CE (buyer) and Northeast
           Energy Associates, Ltd. (NEA) (seller) of electric energy and
           capacity, dated November 26, 1986 (Exhibit 1 to the CE Form 10-Q
           (March 1987), File No. 2-7749).

10.1.40.1  First Amendment to 10.1.40 as amended August 15, 1988 (Exhibit 1
           to the CE Form 10-Q (September 1988), File No. 2-7749).

10.1.40.2  Second Amendment to 10.1.40 as amended January 1, 1989 (Exhibit 2
           to the CE 1988 Form 10-K, File No. 2-7749).

10.1.40.3  Power Sale Agreement dated August 15, 1988 between NEA and CE for
           the purchase of 21 MW of electricity (Exhibit 2 to the CE Form
           10-Q (September 1988), File No. 2-7749).

10.1.40.4  Amendment to 10.1.40.3 as amended January 1, 1989 (Exhibit 3 to
           the CE 1988 Form 10-K, File No. 2-7749).

10.1.41    Power Sale Agreement by and between CE (buyer) and CPC Lowell
           Cogeneration Corp.(seller) of all capacity and related energy
           produced, dated September 29, 1986 (Exhibit 2 to the CE Form 10-Q
           (March 1987), File No. 2-7749).

10.1.41.1  Restatement of 10.1.41 as restated March 30, 1987 (Exhibit 2 to
           the CE Form 10-Q (June 1987), File No. 2-7749).

10.1.42    Power Sale Agreement by and between CE (buyer) and Pepperell Power
           Associates Limited Partnership (seller) of all electricity pro-
           duced from a 38 KW generating unit, dated April 13, 1987 (Exhibit
           3 to the CE Form 10-Q (March 1987), File No. 2-7749).

10.1.43    Power Contract between CEC (seller) and CE and CEL (purchasers)
           dated August 14, 1989 whereby purchasers agree to purchase the
           capacity and energy from seller's "Slice-of-System" entitlement
           from CL&P for the term of November 1, 1989 to October 31, 1994
           (Exh. 1 to the CEC Form 10-Q (September 1989), File No. 2-30057).
                                    PAGE 48

                         COMMONWEALTH ELECTRIC COMPANY

10.1.43.1  Power Sale Agreement dated November 1, 1988, by and between CEC
           (buyer) and CL&P (seller), whereby buyer will purchase generating
           capacity totaling 250 MW from various seller's units ("Slice of
           System") for the term November 1, 1989 to October 31, 1994 (Exhib-
           it 3 to the CEC 1988 Form 10-K, File No. 2-30057).

10.1.44    Exchange of Power Agreement between Montaup Electric Company and
           CE dated January 17, 1991 (Exhibit 2 to the CE Form 10-Q (Septem-
           ber 1991), File No. 2-7749).

10.1.44.1  First Amendment, dated November 24, 1992, to Exchange of Power 
           Agreement between Montaup Electric Company and the Company dated
           January 17, 1991 (Exhibit 1 to the CE Form 10-Q (March 1993), File
           No. 2-7749).

10.1.45    System Power Exchange Agreement by and between CE and New England 
           Power Company dated January 16, 1992 (Exhibit 1 to the CE Form 10-
           Q (March 1992), File No. 2-7749).

10.1.45.1  First Amendment, dated September 8, 1992, to 10.1.45, dated 
           January 16, 1992 (Exhibit 1 to the CE Form 10-Q (Sept. 1992), File
           No. 2-7749).

10.1.45.2  Second Amendment, dated March 2, 1993, to System Power Exchange
           Agreement by and between the Company and New England Power Company
           dated January 16, 1992 (Exhibit 2 to the CE Form 10-Q (March
           1993), File No. 2-7749).

10.1.46    Power Purchase Agreement and First Amendment, dated September 5, 
           1989 and August 3, 1990, respectively, by and between CE (buyer)
           and Dartmouth Power Associates Limited Partnership (seller),
           whereby buyer will purchase all of the energy (67.6 MW) produced
           by a single gas turbine unit (Exhibit 1 to the CE Form 10-Q (June
           1992), File No. 2-7749).

10.1.47    Power Purchase Agreement by and between Masspower (seller) 
           and the Company (buyer) for a 11.11% entitlement to the electric
           capacity and related energy of a 240 MW gas-fired cogeneration
           facility, dated February 14, 1992 (Exhibit 1 to the CE Form 10-Q
           (September 1993), File No. 2-7749).

10.1.48    Power Sale Agreement by and between Altresco Pittsfield, L.P. 
           (seller) and the Company (buyer) for a 17.2% entitlement to the
           electric capacity and related energy of a 160 MW gas-fired cogen-
           eration facility, dated February 20, 1992 (Exhibit 2 to the CE
           Form 10-Q (September 1993), File No. 2-7749).

10.1.48.1  System Exchange Agreement by and among Altresco Pittsfield, L.P., 
           CEL, the Company and New England Power Company, dated July 2, 1993
           (Exhibit 3 to the CE Form 10-Q (September 1993), File No. 2-7749).
                                    PAGE 49

                         COMMONWEALTH ELECTRIC COMPANY

10.2       Other agreements.

10.2.1     Pension Plan for Employees of Commonwealth Energy System and
           Subsidiary Companies as amended and restated January 1, 1993
           (Exhibit 1 to the CES Form 10-Q (Sept. 1993), File No. 1-7316).

10.2.2     Employees Savings Plan of Commonwealth Energy System and Subsid-
           iary Companies as amended and restated as of January 1, 1993 (Ex-
           hibit 2 to the CES Form 10-Q (September 1993), File No. 1-7316).

10.2.3     New England Power Pool Agreement (NEPOOL) dated September 1, 1971
           as amended through August 1, 1977, between NEGEA Service Corpora-
           tion, as agent for CEL, CEC, NBGEL, and various other electric
           utilities operating in New England together with amendments dated
           August 15, 1978, January 31, 1979 and February 1, 1980 (Exhibit
           5(c)13 to New England Gas and Electric Association's Form S-16
           (April 1980), File No. 2-64731).

10.2.3.1   Thirteenth Amendment to 10.2.3 as amended September 1, 1981 (Re-
           filed as Exhibit 3 to the CES 1991 Form 10-K, File No. 1-7316).

10.2.3.2   Fourteenth through Twentieth Amendments to 10.2.3 as amended
           December 1, 1981, June 1, 1982, June 15, 1983, October 1, 1983,
           August 1, 1985, August 15, 1985 and September 1, 1985, respective-
           ly (Exhibit 4 to the CES Form 10-Q (Sept. 1985), File No. 1-7316).

10.2.3.3   Twenty-first Amendment to 10.2.3 as amended to January 1, 1986
           (Exhibit 1 to the CES Form 10-Q (March 1986), File No. 1-7316).

10.2.3.4   Twenty-second Amendment to 10.2.3 as amended to September 1, 1986
           (Exhibit 1 to the CES Form 10-Q (Sept. 1986), File No. 1-7316).

10.2.3.5   Twenty-third Amendment to 10.2.3 as amended to April 30, 1987
           (Exhibit 1 to the CES Form 10-Q (June 1987), File No. 1-7316).

10.2.3.6   Twenty-fourth Amendment to 10.2.3 as amended March 1, 1988 (Exhib-
           it 1 to the CES Form 10-Q (March 1989), File No. 1-7316).

10.2.3.7   Twenty-fifth Amendment to 10.2.3. as amended to May 1, 1988 (Ex-
           hibit 1 to the CES Form 10-Q (March 1988), File No. 1-7316).

10.2.3.8   Twenty-sixth Agreement to 10.2.3 as amended March 15, 1989 (Exhib-
           it 1 to the CES Form 10-Q (March 1989), File No. 1-7316).

10.2.3.9   Twenty-seventh Agreement to 10.2.3 as amended October 1, 1990
           (Exhibit 3 to the CES 1990 Form 10-K, File No. 1-7316).

(b)        Reports on Form 8-K

           No reports on Form 8-K were filed during the three months ended
           December 31, 1993.
                                    PAGE 50

SCHEDULE III

                         COMMONWEALTH ELECTRIC COMPANY
         INVESTMENTS IN, EQUITY IN EARNINGS OF, AND DIVIDENDS RECEIVED
                             FROM RELATED PARTIES                     

             FOR THE YEARS ENDED DECEMBER 31, 1991, 1992 AND 1993

                            (Dollars in Thousands)

Name of Issuer and
Description of Investment

Common Stock - Yankee Atomic Electric Company

Balance, December 31, 1990

    Number of Shares:  3 835

    Amount                                                $524

          1991            
Add: Equity in Earnings                                     73

Less: Dividends Received                                    71

Balance, December 31, 1991                                 526


          1992            
Add: Equity in Earnings                                     75

Less: Dividends Received                                    - 

Balance, December 31, 1992                                 601


          1993            
Add: Equity in Earnings                                     -

Less: Dividends Received                                    - 

Balance, December 31, 1993                                $601


There were no changes in the number of shares held during the years 1991, 1992
or 1993.

Under terms of the capital funds agreements and power contracts, no stock may
be sold or transferred except to another stockholder and, as such, no market
exists for these securities.

See Note 2(c) of the Notes to Financial Statements included in Item 8 of this
report for a discussion of the permanent closing of the nuclear plant owned by
Yankee Atomic Electric Company.
                                    PAGE 51

<TABLE>
SCHEDULE V
                                        COMMONWEALTH ELECTRIC COMPANY
                                      PROPERTY, PLANT AND EQUIPMENT (A)
                                    FOR THE YEAR ENDED DECEMBER 31, 1993


<CAPTION>
                                           Balance                   Retirements                   Balance
                                          Beginning  Additions       Charged To                    End of
Classification                             of Year    at Cost     Reserve     Other  Transfers(B)   Year  
                                                           (Dollars in Thousands)
<S>                                       <C>        <C>           <C>         <C>   <C>          <C>
ELECTRIC
 Intangible plant                         $  1 837   $   -         $  -        $ -   $      -     $  1 837
 Land and rights of way                      7 885         5          -          1          -        7 889
 Structures and leasehold improvements      24 995       654           69        -          -       25 580
 Production equipment                        4 078       (10)          24        -         24        4 068
 Transmission equipment                     87 740     2 505          678        -         13       89 580
 Distribution equipment                    324 440    14 787        3 326        -         (9)     335 892
 General equipment, vehicles and other      24 205       112           64        -    (15 560)       8 693
    Total plant in service                 475 180    18 053        4 161        1    (15 532)     473 539
 Construction work in progress               4 794       684          -          -        -          5 478
    Total electric                         479 974    18 737        4 161        1    (15 532)     479 017

OTHER
 Miscellaneous physical property             1 659       -            -          -        150        1 809
    Total property, plant and equipment   $481 633   $18 737       $4 161      $ 1   $(15 382)    $480 826

<FN>
    (A) Refer to Note 1 of Notes to Financial Statements for depreciation method and rates.
    (B) Represents the abandoned Cannon Street Generating Station reclassified to Deferred Charges.  
        Amounts transferred from Property Held for Future Use to Deferred Charges (net of accumulated
        depreciation of $11,010,000) in anticipation of recovery.
</TABLE>
                                                   PAGE 52

<TABLE>
SCHEDULE V
                                        COMMONWEALTH ELECTRIC COMPANY
                                      PROPERTY, PLANT AND EQUIPMENT (A)
                                    FOR THE YEAR ENDED DECEMBER 31, 1992


<CAPTION>
                                           Balance                    Retirements                  Balance
                                          Beginning  Additions        Charged To                   End of
Classification                             of Year    at Cost      Reserve    Other    Transfers    Year  
                                                           (Dollars in Thousands)         (B)
<S>                                       <C>        <C>         <C>           <C>     <C>        <C>
ELECTRIC
 Intangible plant                         $  1 837   $   -       $  -          $ -     $      -   $  1 837
 Land and rights of way                      7 927       195        -            -         (237)     7 885
 Structures and leasehold improvements      30 039       143         13          -       (5 174)    24 995
 Production equipment                       15 610        63          1          -      (11 594)     4 078
 Transmission equipment                     79 519     9 287      1 047          -          (19)    87 740
 Distribution equipment                    311 824    16 117      3 495          -           (6)   324 440
 General equipment, vehicles and other       8 601       228         82          -       15 458     24 205
    Total plant in service                 455 357    26 033      4 638          -       (1 572)   475 180
 Construction work in progress               9 704    (4 910)       -            -          -        4 794
    Total electric                         465 061    21 123      4 638          -       (1 572)   479 974

OTHER
 Miscellaneous physical property                87       -          -            -        1 572      1 659
    Total property, plant and equipment   $465 148   $21 123     $4 638        $ -      $   -     $481 633

<FN>
    (A) Refer to Note 1 of Notes to Financial Statements for depreciation method and rates.
    (B) Principally Cannon Street generating station which ceased power generation on October 1.
        Applicable plant balances transferred to Property Held for Future Use from Plant in Service.
</TABLE>
                                                   PAGE 53

<TABLE>
SCHEDULE V
                                        COMMONWEALTH ELECTRIC COMPANY
                                      PROPERTY, PLANT AND EQUIPMENT (A)
                                    FOR THE YEAR ENDED DECEMBER 31, 1991


<CAPTION>
                                           Balance                    Retirements                  Balance
                                          Beginning  Additions        Charged To                   End of
Classification                             of Year    at Cost      Reserve    Other    Transfers    Year  
                                                           (Dollars in Thousands)
<S>                                       <C>        <C>         <C>          <C>        <C>      <C>
ELECTRIC
 Intangible plant                         $  1 678   $   159     $  -         $  -       $  -     $  1 837
 Land and rights of way                      7 912        13        -            1          3        7 927
 Structures and leasehold improvements      29 249       604       (186)         -          -       30 039
 Production equipment                       15 386       235         11          -          -       15 610
 Transmission equipment                     76 944     2 643         69          -          1       79 519
 Distribution equipment                    288 460    26 331      2 966          -         (1)     311 824
 General equipment, vehicles and other       8 453       373        221          -         (4)       8 601
    Total plant in service                 428 082    30 358      3 081          1         (1)     455 357
 Construction work in progress               8 212     1 492        -            -          -        9 704
    Total electric                         436 294    31 850      3 081          1         (1)     465 061

OTHER
 Miscellaneous physical property                86       -          -            -          1           87
    Total property, plant and equipment   $436 380   $31 850     $3 081        $ 1       $  -     $465 148

<FN>
    (A) Refer to Note 1 of Notes to Financial Statements for depreciation method and rates.
</TABLE>
                                                   PAGE 54

<TABLE>
SCHEDULE VI
                                        COMMONWEALTH ELECTRIC COMPANY
                        ACCUMULATED DEPRECIATION OF PROPERTY, PLANT AND EQUIPMENT (A)
                            FOR THE YEARS ENDED DECEMBER 31, 1993, 1992 AND 1991

                                           (Dollars in Thousands)
<CAPTION>
                                                 Provision             
           Balance at Transferred               Clearing   Amortization                             Balance
Classifi-  Beginning  to Deferred Charged to  Accounts and of Leasehold             Removal         at End
cation      of Year   Charges (B) Operations  Other Income Improvements Retirements  Cost   Salvage of Year


                                        YEAR ENDED DECEMBER 31, 1993                                        
<S>         <C>        <C>          <C>          <C>          <C>          <C>      <C>     <C>     <C>
Electric    $135 684   $(11 010)    $15 032      $     -      $ 424        $4 162   $3 263  $ 644   $133 349



                                        YEAR ENDED DECEMBER 31, 1992                                        
<S>         <C>        <C>          <C>          <C>          <C>          <C>      <C>     <C>     <C>
Electric    $128 253   $    -       $15 012      $     5      $ 422        $4 638   $4 291  $ 921   $135 684



                                        YEAR ENDED DECEMBER 31, 1991                                        
<S>         <C>        <C>          <C>          <C>          <C>          <C>      <C>     <C>     <C>
Electric    $118 646   $    -       $14 484      $     -      $ 434        $3 081   $2 802  $ 572   $128 253


<FN>
          (A) Refer to Note 1 of Notes to Financial Statements for depreciation method and rates.
          (B) Represents accumulated depreciation applicable to the abandoned Cannon Street generating 
              station reclassified to Deferred Charges.
</TABLE>
                                 PAGE 55

                                                              SCHEDULE VIII

                         COMMONWEALTH ELECTRIC COMPANY
                       VALUATION AND QUALIFYING ACCOUNTS
             FOR THE YEARS ENDED DECEMBER 31, 1993, 1992 and 1991

                            (Dollars in Thousands)





                                        Additions     
                      Balance   Provision                Deductions    Balance
                     Beginning  Charged to                Accounts     at End
Description           of Year   Operations  Recoveries   Written Off   of Year

Allowance for 
  Doubtful Accounts             Year Ended December 31, 1993

                      $3 131      $3 173       $783         $3 819      $3 268


                                Year Ended December 31, 1992

                      $2 653      $5 216       $854         $5 592      $3 131


                                Year Ended December 31, 1991

                      $2 341      $5 286       $985         $5 959      $2 653
                                    PAGE 56

SCHEDULE IX

                         COMMONWEALTH ELECTRIC COMPANY
                           SHORT-TERM BORROWINGS (a)
             FOR THE YEARS ENDED DECEMBER 31, 1993, 1992 AND 1991
                            (Dollars in Thousands)

                                        Maximum                   Weighted
                          Weighted      Month-End    Average      Average
Category of               Average       Amount       Amount       Interest
Aggregate     Balance     Interest      Outstanding  Outstanding  Rate
Short-Term    at End      Rate at End   During       During the   During the
Borrowings    of Period   of Period     the Period   Period (b)   Period (c)

December 31, 1993
Notes Payable
  to Banks       $   -        -           $80 350       $16 121      3.4%

Notes Payable
  to System      $   -        -           $12 970       $ 2 451      6.0%

COM/Energy
  Money Pool     $   -        -           $ 4 005       $   858      3.2%

December 31, 1992
Notes Payable
  to Banks       $67 275      3.8%        $68 700       $62 460      4.0%

Notes Payable
  to System      $ 8 445      6.0%        $11 030       $ 7 765      6.3%

COM/Energy
  Money Pool     $ 3 395      3.4%        $ 6 060       $ 3 856      3.7%

December 31, 1991
Notes Payable
  to Banks       $63 300      5.5%        $68 250       $55 612      6.3%

Notes Payable
  to System      $ 5 950      6.5%        $ 5 950       $ 2 167      8.3%

COM/Energy
  Money Pool     $ 3 600      4.6%        $ 3 795       $ 2 878      5.8%

(a)   Refer to Note 5 of Notes to Financial Statements filed under Item 8 of
      this report for the general terms of each category of short-term
      borrowings.

(b)   The average amount outstanding during the period is determined by
      averaging the level of month-end principal balances outstanding for the
      prior thirteen-month period ending December 31.

(c)   The weighted average interest rate during the period is determined by
      averaging the interest rates in effect on all loans transacted for the
      twelve-month period ended December 31.
                                    PAGE 57

                         COMMONWEALTH ELECTRIC COMPANY
                       FORM 10-K      DECEMBER 31, 1993

                                  SIGNATURES

      Pursuant to the requirements of Section 13 or 15(d) of the Securities
Exchange Act of 1934, the registrant has duly caused this report to be signed
on its behalf by the undersigned, thereunto duly authorized.

                                     COMMONWEALTH ELECTRIC COMPANY
                                             (Registrant)

                                By:  WILLIAM G. POIST             
                                     William G. Poist,
                                     Chairman of the Board and
                                     Chief Executive Officer

     Pursuant to the requirements of the Securities Exchange Act of 1934, this
report has been signed below by the following persons on behalf of the
registrant and in the capacities and on the dates indicated.

Principal Executive Officers:   

WILLIAM G. POIST                            March 30, 1994
William G. Poist,
Chairman of the Board and
Chief Executive Officer

R. D. WRIGHT                                March 28, 1994
Russell D. Wright,
President and Chief Operating Officer

Principal Financial Officer:

JAMES D. RAPPOLI                            March 30, 1994
James D. Rappoli,
Financial Vice President and Treasurer

Principal Accounting Officer:

JOHN A. WHALEN                              March 28, 1994
John A. Whalen,
Comptroller

A majority of the Board of Directors:

WILLIAM G. POIST                            March 30, 1994
William G. Poist, Director

JAMES D. RAPPOLI                            March 30, 1994
James D. Rappoli, Director

R. D. WRIGHT                                March 28, 1994
Russell D. Wright, Director



                             PAGE 1

                                                         EXHIBIT 1

     AGREEMENT entered into this first day of September, 1983 by and between
Commonwealth Electric Company, a Massachusetts corporation with offices
located at 2421 Cranberry Highway, Wareham, Massachusetts 02571 ("Company")
and Pioneer Hydropower, Incorporated, ("Pioneer") a Massachusetts corporation
with offices located at 148 State Street, Boston, Massachusetts 02109 ("Sell-
er").

     Seller owns and operates a hydro-electric generating facility (the
"Plant"), at its site in Ware, Massachusetts. Seller wishes to sell and the
Company wishes to buy electric energy from the Plant, all pursuant to the
terms and conditions as set forth in this Agreement.

     THEREFORE, the parties, each in consideration of the agreements of the
other, hereby agree as follows:

ARTICLE I. Sale of Power by Seller.

     (a) Seller agrees to sell and deliver to New England Power Company
("NEPCO"), and the Company agrees to purchase and accept delivery from NEPCO
of all electric energy produced by the Plant during the term of this Agree-
ment, except that the Seller shall have the option not to sell and deliver
such electric energy as may be needed from time to time to satisfy Plant
requirements ("Net Plant Output").

     (b) The Company shall not be obligated to purchase or take delivery of
electric energy from the Plant unless, in the reasonable judgment of the
Company, the Plant is staffed, operated and maintained in a manner consistent
with the standards applicable to generating facilities owned and operated by
participants in the New England Power Pool ("NEPOOL"), as such standards may
be in effect from time to time during the term of this Agreement. The Plant
must be made available for NEPOOL dispatch in accordance with the provisions
of Section 12.2 of the NEPOOL Agreement dated September 1, 1971 as amended
("NEPOOL Agreement").

     (c) Without limiting the generality of Article 1(b) hereof, Seller shall
be obligated hereby to undergo periodic capability audits pursuant to the
terms of Section 8.13 of the NEPOOL Agreement. In the event that the Plant
demonstrates a Capability (as defined at Section 15.6 of the NEPOOL Agreement)
that is less than the "Qualified Capacity" of such Plant ("Capacity Deficien-
cy"), the Company may assess Seller a charge equal to the Capability Respon-
sibility Adjustment Charge established from time to time by NEPOOL pursuant to
the provisions of Section 9.4 of the NEPOOL Agreement multiplied by such
Capacity Deficiency. The Qualified Capacity of the Plant shall be determined
by a capability audit conducted, under the general supervision of the adminis-
trative committee established by Article X(f) of this Agreement, during the
first winter period following the effective date of this Agreement. Such
Qualified Capacity shall be the winter period Net Capability of the Plant (as
computed pursuant to said capability audit) which shall be the same as the
Capability of the Plant calculated pursuant to Section 15.6 of the NEPOOL
Agreement. Notwithstanding the foregoing, if such winter period Net Capability
of the plant is less than thirteen hundred ten (1310) kilowatts, the Qualified
Capacity of the Plant shall be thirteen hundred ten (1310) kilowatts.
                             PAGE 2

     (d) The Company reserves the right to impose reasonable conditions
consistent with the NEPOOL standards that are in effect from time to time 
during the term of this Agreement in substitution for the foregoing NEPOOL
standards if NEPOOL ceases to establish such standards or if the Company
should cease its participation in NEPOOL during the life of this Agreement.

ARTICLE II. Effective Date and Term.

     (a) This Agreement shall become effective upon the date that electric
energy is first delivered to Company by NEPCO, and unless sooner terminated in
accordance with any applicable provision of this Agreement, shall remain in
full force and effect for an initial term of thirty (30) years.

     Seller agrees to notify the Company at the end of the twenty ninth (29)
year of its rights and intention to continue operation of the Plant beyond the
initial term. In the event that Seller has the right to continue operation of
the Plant and sell power to the Company beyond the initial term, this Agree-
ment shall be renewed or extended at the Company's sole option by the giving
of written notice to Seller within six (6) months following receipt of notice
from Seller of such continued operation, said renewal to be for a term of
fifteen (15) years.

     Seller agrees to use all reasonable efforts to continue operation of the
Plant beyond the initial term.

ARTICLE III. Purchase Price.

     (a) From and after the date of initial commencement of deliveries of
electric energy from the Plant ("Start Date"), the Company shall pay Seller
each month an amount equal to the greatest of:

          (1) the Energy Purchase Price as determined in accordance with
Appendix A to this Agreement multiplied times the quantity of electric energy
delivered to the Company by NEPCO hereunder, or

          (2) eighty-four mills ($0.084) per kilowatt-hour ("Floor Energy
Price") multiplied times the quantity of electric energy delivered to the
Company by NEPCO hereunder, or

          (3) beginning January 1, 1992 and ending at the close of the
fifteenth (15th) year following the Start Date, the Floor Energy Price per
kilowatthour ("Adjusted Floor Energy Price") shall be determined by the
following formula:

          Adjusted Floor Energy Price = 84 mills
          + PGNP-2 x [9.1 + PGNP-1 (14.1)]

          Where:    PGNP-1 is the cumulative percentage change in the
                    Gross National Product Implicit Price Deflator
                    ("PGNP") published by the United States Department of
                    Commerce between the Start Date and December 31, 1991,
                    and PGNP-2 is the cumulative percentage change in the
                    PGNPafter January 1, 1992, multiplied times the quan-
                    tity of electric energy delivered to the Company by
                    NEPCO hereunder.
                             PAGE 3

In the event the United States Department of Commerce should cease to publish
the PGNP, the Company and Seller shall mutually agree upon a satisfactory
replacement therefor or, failing to so agree, shall submit matter to arbitra-
tion in accordance with the appropriate provisions of this Agreement.

The Company has entered an agreement of even date herewith and similar hereto
with Swift River Company relative to a hydro electric facility known as
Chicopee. The amount of the Floor Energy Price of eighty-four mills ($0.084)
per kilowatthour shown in Article III(a)(2) and (3) above is contingent upon
Chicopee entering commercial operation no later than December 31, 1984. In the
event that Chicopee does not enter commercial operation by December 31, 1984,
the Floor Energy Price shall be reduced to eighty-two mills ($0.082) per
kilowatthour and any payments made to Seller using such Floor Energy Price
from the Start Date to December 31, 1984 shall be re-calculated and adjusted
to reflect such reduction.

     (b) For the purpose of implementing Article III(a) of this Agreement,
the Company shall pay Seller each month an amount determined in accordance
with paragraph (1) thereof. Amounts payable to Seller pursuant to Article
III(a)(1) shall be determined for each billing period on an estimated basis
and paid monthly in accordance with Article VII hereof, subject to a final
determination and reconciliation at the end of each such billing period
established pursuant to Appendix A hereof. For purposes of such monthly
payments, an estimated Energy Purchase Price for each rating period (as
defined in Appendix A hereof) shall be determined as set forth in such
Appendix A by setting Factor 0-2 equal to Factor 0-1. Such estimated Energy
Purchase Price for each rating period shall be multiplied by the quantity of
electric energy (measured in kilowatt-hours) delivered to the Company by
Seller during such rating period during such month. Following the close of
each such billing period, the Company will promptly determine its actual
Energy Purchase Price for each rating period. Any difference between the
forecast and actual Energy Purchase Price for the same billing period shall be
subject to reconciling adjustment during the first month of the next subse-
quent billing period.

     (c) If the Company determines that the Energy Purchase Price, computed
with Factor R set equal to one-hundred percent (100%), exceeds the Company's
avoided energy costs (as hereinafter defined), the Company may propose a
change to Appendix A by giving Seller written notice thereof. Such proposed
change shall be limited to the methodology for determining or calculating the
Company's avoided energy costs and shall not deviate from the principle that
the average decremental cost shall at least approximate the most costly ten
percent (10%) of the load placed upon the Company's system by its firm-service
customers during the relevant billing period. In the event that Seller fails
to accept said proposed change and Seller and Company are unable to agree in
writing upon a mutually satisfactory revised Appendix A within sixty (60) days
of the giving of such notice, either the Seller or the Company may submit the
matter to arbitration pursuant to the provisions of Article X(g) and (h)
below. During the period of time in which said matter is in arbitration, the
proposed revised Appendix A originally offered by the Company shall govern the
computation of the Energy Purchase Price. Within thirty (30) days following
resolution of said dispute by arbitration, the Company shall recompute, in
accordance with said resolution, all amounts paid to, Seller during the
pendency of such dispute and debit or credit Seller's account as appropriate. 
                             PAGE 4

     (d) Avoided energy cost as used herein shall mean the incremental cost
to the Company of electric energy which the Company would have generated or
purchased but for the purchase of electric energy from Seller.

     (e) Any taxes on the production or sale of electric energy furnished by
the Seller to the Company under this Agreement shall be the obligation of and
paid by the Seller as and when due.

ARTICLE IV. Energy Purchase Bank.

     (a) The Company will establish an account within its records, to be
known as the Energy Purchase Bank, which shall be maintained separately from
all other accounts therein. The Energy Purchase Bank shall be solely used to
record such periodic energy purchase (and related) transactions and associated
account balances as are specified within this Agreement as affecting such
Energy Purchase Bank.

     (b) During the term of this Agreement, the difference between any
amounts paid to Seller pursuant to the Floor Energy Price or the Adjusted
Floor Energy Price and the amount that would have been paid to Seller under
the Energy Purchase Price, computed with Factor R set equal to one-hundred
percent (100%), shall be debited to the Energy Purchase Bank.

     (c) During any billing period for which the Energy Purchase Bank
contains a debit balance and for which the Energy Purchase Price, computed
with Factor R set equal to one hundred percent (100%), exceeds the Floor
Energy Price or the Adjusted Floor Energy Price, the Energy Purchase Bank
shall be credited as follows:

     (1) if the Energy Purchase Price with Factor R set at 100% exceeds the 
     Floor or Adjusted Floor Energy Price, then one-half of said difference
     multiplied by the number of kilowatt hours purchased from Seller during
     such billing period shall be credited to the Energy Purchase Bank and
     one-half of said difference multiplied as specified above shall be paid
     to Seller.

     (2) provided nevertheless, that for the purpose of this subarticle, if 
     the actual avoided energy cost exceeds the projections attached hereto
     as Appendix B, then all of the difference between said actual avoided
     costs for the year in question and those shown on Appendix B shall be
     credited to the Energy Purchase Bank until the debit balance in said
     Bank reaches zero, at which time the payment to Seller shall be calcu-
     lated according to Appendix A, using actual avoided cost figures. Said
     procedure shall continue throughout the term of this Agreement until any
     debit balance in the Energy Purchase Bank is reduced to zero. Any debit
     balance of the Energy Purchase Bank shall bear interest at a rate per
     annum which shall be at all times equal to the Base Rate of The First
     National Bank of Boston (or its successors) which shall mean the rate of
     interest designated by such Bank as its Base Rate and usually charged by
     it to substantial and responsible borrowers, as in effect from time to
     time. Each change in the said Base Rate shall be effective at the
     beginning of the business day on which such change occurs.
                             PAGE 5

ARTICLE V. Delivery by Seller.

     Electric energy generated by the Seller at the Plant shall be delivered
by NEPCO (pursuant to a Service Agreement between the Company and NEPCO of
even date herewith) to the Company at the 345,000 volt bus located in the
Canal Electric Company switchyard at Sandwich, Massachusetts ("point of
delivery") in the form of three-phase, sixty hertz alternating current at
approximately 345,000 volts nominal. All electric energy produced by Seller
and delivered to NEPCO for transmission to the Company shall be adjusted for
any transmission losses on NEPCO's system and any payments made by Company to
Seller pursuant to Article III above shall be determined based on the net
kilowatthours of electric energy delivered by NEPCO to Company at the point of
delivery. It is understood that any payments by the Company to Seller made in
accordance with Article III above shall be net of payments made by the Company
to NEPCO for the transmission of such electric energy generated by Seller.

     Seller shall obtain and continuously maintain insurance, bond, or other
debt instrument in form and amount satisfactory to the Company sufficient to
reimburse the Company in full for any obligation it may incur with NEPCO under
the above-mentioned Service Agreement for any period during which Seller is
not producing electric energy under this Agreement. The Company shall be the
specified beneficiary under the insurance, bond or debt instrument and
evidence of the effectiveness of such insurance, bond, or debt instrument must
be filed with the Company at all times during the term of this Agreement or
the Company shall have the right to withhold payment hereunder.

ARTICLE VI. Meters and Metering.

     (a) The Company shall have the right to review and approve the metering
installations required to record the quantities of electricity purchased from
the Seller. Such metering equipment will be capable, inter alia, of providing
data required to determine kilowatt-hours per hour purchased during each hour
of each rating period established by Appendix A hereto as well as total
electric energy purchased per rating period under the terms of this Agreement.
Seller shall install, own, operate and maintain such metering equipment, which
equipment shall be located at Seller's bus (or buses). If, for any reason, it
is impractical to install meters at such bus (or buses), appropriate adjust-
ments shall be made to reflect the actual amount of electric energy which
would have been recorded by meters located at such bus (or buses).

     (b) Seller shall maintain all metering equipment installed pursuant
hereto accurate by regular testing and calibration in comparison to recognized
standards. The metering equipment shall be sealed, and Seller will comply with
any reasonable request of the Company with regard to the presence of the
Company's representative when such seals are to be broken or when the meters
are to be inspected, tested or adjusted. The Company may request, at any time,
a test of the accuracy of any metering equipment installed pursuant hereto and
shall bear the costs thereof in the event that said requests are made more
frequently than once in each twelve months. The results of all meter calibra-
tions or tests, whether or not performed at the Company's request, shall be
open to examination by the Company at all reasonable times.

     (c) Any meter tested and found to register less than or equal to
one-half of one percent (0.5%) above or below the recognized comparative
standard shall be considered correct and accurate. If as a result of such
                             PAGE 6

tests, the metering equipment is found to be defective or inaccurate, Seller
shall restore it to a condition of accuracy or replace it. In such event,
adjustment shall be made by the Company correcting all measurements made by
the defective or inaccurate meter for either (i) the actual period during
which inaccurate measurements were made, if determinable to the mutual
satisfaction of the Company and Seller or (ii) if such period is not so
determinable, for a period equal to one-half of the time elapsed since the
last prior test, but in no event greater than twelve months.

     (d) Other provisions of this Article VI notwithstanding, the Company may
elect to install its own metering equipment in supplement to the Seller's
metering equipment. Should the Company so elect and should any metering
equipment installed by the Seller fail to register the amount of electric
energy delivered to the Company during any period of time, the Company's
metering equipment shall be used to determine the amount of electric energy so
delivered in lieu of the Company's estimates thereof. If the Company wishes
its metering equipment to be so used, the Company agrees to operate, maintain
and read such equipment according to the standards established by this Article
VI. The Seller agrees, upon request of the Company, to provide a suitable
location at the Plant for installation of the Company's meters at no cost to
the Company.

     (e) Upon written request of the Company, Seller shall install and bear
the cost of such telemetering equipment and data circuits as the Company may
reasonably require for the transmission of various metered values to its
operations center. The design of and equipment specifications for such
telemetering equipment and data circuits shall be approved by the Company
prior to installation thereof by Seller.

     (f) Seller shall read its meters daily for determination of the amount
of purchases by the Company under the terms of this Agreement and shall supply
the results of such meter readings to the Company on the morning of the next
working day.

ARTICLE VII. Payment.

     (a) The Company shall determine the quantity of electric energy pur-
chased from Seller monthly based upon the metered values obtained in
accordance with the several provisions of Article VI of this Agreement
adjusted for any transmission losses as appropriate. The Company, after giving
due effect to any reconciling adjustments necessary and deducting transmission
payments made pursuant to Article V hereof ("Net Payment") shall pay to a
specially designated account established by Seller for such electric energy
monthly within thirty (30) calendar days following receipt of such metered
values from Seller for the last day in each prior calendar month and shall
show the derivation of such Net Payment in such detail as Seller may reason-
ably request from time to time.

     (b) In the event that any data required for the purpose of determining
payment hereunder are unavailable when required, such unavailable data may be
estimated by the Company, subject to any required adjustment based upon actual
data in a subsequent payment month.

     (c) In the event that, for any month, the quantity of electric energy
purchased from Seller is such that the Net Payment to Seller would be less
                             PAGE 7

than zero, such Net Payment shall be deemed to be a billing to Seller by the
Company. Any such billing shall be due and payable within thirty (30) calendar
days following receipt of metered values from Seller for the last day in the
prior calendar month.

ARTICLE VIII. Governmental Regulation.

     (a) This Agreement shall be submitted by the Company to the Massachu-
setts Department of Public Utilities ("MDPU") in accordance with Section 94A,
Chapter 164, of the Massachusetts General Laws and applicable regulations of
the MDPU, and the Company shall use its best efforts to obtain expeditious
approval thereof in accordance with such law and regulations.

     (b) It shall be the responsibility of each party hereto individually to
take all necessary actions to satisfy any regulatory requirements which may be
imposed upon such party by any federal, state or municipal statute, rule,
regulation or ordinance which may be in effect from time to time relative to
the performance of such party hereunder.

     (c) This Agreement and all rights and obligations of the parties
hereunder are subject to all applicable state and federal laws and all duly
promulgated orders and duly authorized actions of governmental authorities.

     (d) The interpretation and performance of this Agreement shall be in
accordance with and controlled by the laws of the Commonwealth of Massachu-
setts.

ARTICLE IX. Liability and Force Majeure.

     (a) The parties hereto shall be excused from performing hereunder and
shall not be liable in damages or otherwise if and only to the extent that
they are unable to do so or are prevented from doing so by statute or regula-
tion or by action of any court or public authority having or purporting to
have jurisdiction in the premises; or by loss or impairment of the supply of
electricity; or by a break or fault in the Company's or other transmitting
company's transmission or distribution system or failure or improper operation
of transformers, switches or other equipment necessary for receipt of electric
energy from Seller; or by reason of storm, flood, fire, earthquake, explosion,
civil disturbance, labor dispute, act of God or the public enemy, failure of
any supplier to perform, restraint by a court or regulatory agency, or any
other cause, whether or not similar thereto, beyond the reasonable control of
the affected party. Each party shall have the obligation to operate in
accordance with good utility practices at all times and to use diligent effort
to remove any cause of failure to supply or receive electric energy hereunder.
Neither the Company nor Seller shall, in any event, be liable to the other or
to any third party for any consequential, indirect or special damages to
persons or property, whether arising in tort, contract or otherwise, by reason
of this Agreement or any services performed or undertaken to be performed by
the Company or Seller hereunder, except as otherwise expressly provided
herein.

     (b) Whenever the Company's system or the systems with which it is
directly or indirectly interconnected experience a "System Emergency", or
whenever it is needful or desirable to aid in the restoration of service on
its system or on the systems with which it is directly or indirectly intercon-
                             PAGE 8

nected, the Company may, in its reasonable judgment, curtail or interrupt the
taking of electric energy hereunder, provided such curtailment or interruption
shall continue only for so long as is reasonably necessary. Such curtailment,
interruption, or reduction shall not be deemed to be a default by the Company
nor shall the Company be liable therefor to Seller or to any other party. A
System Emergency means a condition on a utility's system which is likely to
result in an imminent significant disruption of service or is imminently
likely to endanger life or property. Notwithstanding any other provision of
this Agreement to the contrary, in the event that the Company cannot receive
electric energy from Seller into its own system because of a System Emergency
but such System Emergency does not prevent Seller from delivering such
electric energy to another utility with which the Company is interconnected,
the Company shall pay Seller for such electric energy so delivered the exact
amount, if any, that the Company receives in payment or credit from such
utility for the delivery of such electric energy.
     
     (c) The Company and the Seller agree that each shall be responsible for
the electricity on its respective side of the point of delivery and shall
indemnify, save harmless and defend the other against all claims, demands,
costs or expenses for loss, damage or injury to persons or property in any
manner directly or indirectly arising from, connected with or growing out of
the presence or use of electricity or the transmission of electricity over the
wires, cables, devices or appurtenances owned by it, its agents or suppliers,
saving only such loss, damage or injury as may be caused by the willful or
negligent act of the other. The Company and the Seller respectively assume
full responsibility in connection with the service rendered hereunder for
their respective wires, cables and other devices used in connection with said
service. Each party hereto shall be solely liable for all claims of its own
employees arising from any workmen's compensation laws.

     (d) Neither by inspection nor non-rejection nor in any other way does
either party give any warranty, expressed or implied, as to the adequacy,
safety or other characteristics of any equipment, apparatus or devices,
installed on the premises of or used by the other party, its agents or
suppliers. Neither party shall be liable to the other for damages resulting in
any way from its taking or supplying of electric energy pursuant to the terms
of this Agreement or from the presence or operation of its apparatus, meters,
appurtenances or other equipment on the premises of the other party.

     (e) Seller may from time to time withdraw the Plant from service and
cease to supply electric energy to the Company as necessary to perform
scheduled or unscheduled maintenance or repair upon the Plant. Seller shall
comply with the provisions of NEPOOL Operating Procedure No. 5 as in effect
from time to time when planning any scheduled maintenance or repair upon the
Plant. Seller shall give the Company such notice as may be practicable the
circumstances when withdrawing the Plant from service for unscheduled mainte-
nance or repair.

ARTICLE X. Miscellaneous Provisions

     (a) This Agreement constitutes the entire agreement between the parties
relating to the subject matter hereof, and all previous agreements, discus-
sions, communications and correspondence with respect to the subject matter
hereof are superseded by the execution of this Agreement.
                             PAGE 9

     (b) This Agreement may not be modified or amended except in writing
signed by or on behalf of both parties by their duly authorized officers.

     (c) Any qualified and properly identified employee of the Company shall
have access to the Plant at all reasonable times for the purpose of reading or
inspecting meters, examining the operation of the Plant or other purposes
reasonably related to the Company's performance under the terms of this
Agreement. Such access shall not interfere with Seller's normal business
operations.

     (d) This Agreement shall inure to the benefit of and bind the respective
successors and permitted assigns of the parties hereto, provided, however,
that no assignment by Seller or any successor or assignee of Seller of its
rights and obligations hereunder, except an assignment to a wholly-owned
subsidiary whose principal functions are to hold Seller's ownership interest
in and to operate the Plant, shall be made or become effective without the
prior written consent of the Company in each case obtained. The Company will
provide consent to any assignment of Seller's rights and obligations hereunder
to the extent necessary for Seller to obtain construction or permanent
financing for the Plant with an institutional lender and to assure that the
Company's right to receive the output of the Plant shall apply as against any
person or entity that might obtain title and possession of the Plant pursuant
to such financing.

     (e) All notices required or permitted under this Agreement shall be in
writing and shall be deemed to have been given when delivered personally or
deposited in the mails, postage prepaid, registered mail addressed to the
party to whom notice is being given at its address set forth above. Either
party may change its address by notice similarly given.

     (f) The parties hereto agree to establish an administrative committee.
Such committee will be empowered to do all acts and things necessary to
implement the intent of the parties hereto as set forth herein and to take
such further actions as may be required in the circumstances, provided that
they are not inconsistent with this Agreement. The Company and Seller shall
have equal representation upon said committee.

     (g) In the case of any dispute between the parties with respect to the
interpretation of this Agreement, or the performance of the same, or under
Article III(d) above, either party may give notice in writing to the other of
its desire to submit such questions to arbitration, and may designate an
arbitrator. Within thirty (30) days after the receipt of such notice, the
other party may, in writing, serve upon the party invoking such arbitration a
notice designating an arbitrator on its behalf. The two arbitrators so chosen
shall, within twenty (20) days after the appointment of the second arbitrator,
in writing, designate a third arbitrator. Upon the failure of the party
notified to appoint the second arbitrator within such time, the party invoking
such arbitration may proceed with the single arbitrator. If the first and
second arbitrators are unable to agree on a third arbitrator within twenty
(20) days of the appointment of the second arbitrator, the first and second
arbitrator shall invoke the services of the American Arbitration Association
to appoint a third arbitrator. Said third arbitrator shall, to the extent
practicable, have special competence and experience with respect to the
subject matter under consideration. An arbitrator so appointed shall have full
authority to act pursuant to this Article. No arbitrator, whether chosen by a
                             PAGE 10

party hereto or appointed, shall have the power to amend or add to this
Agreement.

     (h) The party calling the arbitration shall, within twenty (20) days
after either the failure of the other party to name an arbitrator, or the
appointment of the third arbitrator, as the case may be, fix, in writing, a
time and a place of hearing, to be not less than twenty (20) days from
delivery of notice to the other party. The arbitrator or arbitrators shall,
thereupon, proceed promptly to hear and determine the controversy pursuant to
the then-current rules of the American Arbitration Association for the conduct
of commercial arbitration proceedings, except that if such rules shall
conflict with the then current provisions of the laws of the Commonwealth of
Massachusetts relating to arbitration, such conflict shall be governed by the
then current provisions of the laws of the Commonwealth of Massachusetts
relating to arbitration. Such arbitrator or arbitrators shall fix a time
within which the matter shall be submitted to him or them by either or both of
the parties, and shall make his or their decision, within ten (10) days after
the final submission to him or them unless, for good reasons to be certified
by him or them in writing, he or they shall extend such time. The decision of
the single arbitrator, or two of the three arbitrators, shall be taken as the
arbitration decision. Such decision shall be made in writing and in duplicate,
and one copy shall be delivered to each of the parties. The expense of the
arbitration shall be borne by the unsuccessful party, unless the arbitrator or
arbitrators by his or their award shall otherwise provide, except that each
party shall pay the costs of its own counsel. Each party shall accept and
abide by the decision. The award of the arbitral tribunal shall be final
except as otherwise provided by applicable law. Judgment upon such award may
be entered by the prevailing party in any court having jurisdiction thereof,
or application may be made by such party to any such court for judicial
acceptance of such award and an order of enforcement.

     IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be
executed as of the day and year first above written.

                                      COMMONWEALTH ELECTRIC COMPANY


                                      By: J. V. Donovan            

                                      Its: Executive Vice President

                                      PIONEER HYDROPOWER, INC.


                                      By: Peter B. Clark           
                                      Its: President
                             PAGE 11

                           APPENDIX A
                      ENERGY PURCHASE PRICE

     The Energy Purchase Price applicable to electric energy delivered to the
Company by Seller during any billing period will be equal to the rate, taken
to the nearest one-tenth of a mill per kilowatt-hour, determined in accordance
with the following formula, separately applied to each rating period hereinaf-
ter defined:

                       P = R x F (0-2/0-1)

Where:    P = Energy purchase price
          R = Avoided cost ratio
          F = Average decremental cost of generated and/or purchased energy
          0-2 = Actual cost of energy produced and/or purchased from fossil
          fuels
          0-1 = Estimated cost of energy produced and/or purchased from 
          fossil fuels

(1) Definitions

(a) Factor R. Commencing on the Start Date and continuing until December 31,
1999, Factor R shall be eighty percent (80%). Commencing January 1, 2000, and
continuing until December 31, 2010, Factor R shall be reduced from said eighty
percent (80%), one percentage point on each successive January 1. Commencing
January 1, 2011 and continuing until December 31, 2015, Factor R shall be
reduced by two percentage points on each successive January 1.

(b) Factor F. Factor F shall be the Company's estimated average decremental
cost of generated and/or purchased energy as delivered to its system, sepa-
rately determined (as set forth herein) for each billing period hereinafter
defined. Factor F shall be computed not more than sixty (60) days prior to the
beginning of such billing period.

Said average decremental cost of energy shall be defined by the following
formula, taken to the nearest one-tenth of a mill per kilowatt-hour:

               F =  Cost1 - Cost2
                    KWHl - KWH2

     where: Cost1 and KWH1 represent the estimated cost and quantity (respec-
          tively) of energy generated and/or purchased by the Company to
          meet one-hundred percent (100%) of the load placed upon its system
          by its firm-service customers during any billing period.

          Cost2 and KWH2 represent the estimated cost and quantity (respec
          tively) of energy generated and/or purchased by the Company to
          meet ninety percent (90%) of the load placed upon its system by
          its firm-service customers during the same billing period.

     (c) Factors O. The two Factors O shall be the average cost of energy
generated by and/or purchased from generating units fired with fossil fuels
during any billing period, either as actually experienced by the Company
during such billing period (Factor O2) or as estimated by the Company for such
                             PAGE 12

billing period (Factor Ol) and as included in its computations determining the
average decremental cost of energy, all measured to the nearest one-tenth of a
mill per kilowatt-hour.

(2) Billing Period

     A billing period hereunder shall be any three (3) month period beginning
January first, April first, July first and October first of any year during
the term of this Agreement.

(3) Rating Periods

     There shall be two rating periods for purposes of computing the Energy
Purchase Prices. The Peak Period shall be defined as all hours in the billing
period from 9:00 A.M. to 9:00 P.M. Eastern Standard Time on weekdays (Monday
through Friday). The Off-Peak Period shall include all hours in the billing
period not included in the Peak Period. The Company reserves the right to
revise the definition of its rating periods from time to time during the term
of this Agreement upon reasonable notice to Seller.
                             PAGE 13

                           APPENDIX B

                  Projected Avoided Energy Cost

               Year                   $.00/KWH

               1983                     4.74
               1984                     4.93
               1985                     5.32
               1986                     5.95
               1987                     6.48
               1988                     7.17
               1989                     8.20
               1990                     9.38
               1991                     10.62
               1992                     12.54
               1993                     14.36
               1994                     16.27
               1995                     12.20
               1996                     13.03
               1997                     14.27
               1998                     15.08
               1999                     17.24
               2000                     19.66
               2001                     22.23
               2002                     24.49
                             PAGE 14

                           SCHEDULE B

                  COMMONWEALTH ELECTRIC COMPANY
                      ENERGY PURCHASED FROM
                PIONEER HYDROPOWER, INCORPORATED
               TWELVE MONTHS ENDING AUGUST 31,1984


                            ESTIMATED KWH    ESTIMATED COST
                            PURCHASED        OF ENERGY (*)

     1983SEPTEMBER            180,000         $15,120
         OCTOBER              240,000          20,160
         NOVEMBER             360,000          30,240
         DECEMBER             540,000          45,360
     1984JANUARY              600,000          50,400
         FEBRUARY             600,000          50,400
         MARCH                960,000          80,640
         APRIL                900,000          75,600
         MAY                  720,000          60,480
         JUNE                 480,000          40,320
         JULY                 240,000          20,160
         AUGUST               180,000          15,120

     TOTAL 12 MONTHS        6,000,000        $504,000


         (*) BASED UPON AN ENERGY PURCHASE PRICE OF $0.084 PER KWH, THE 
         MINIMUM ENERGY PURCHASE PRICE STATED AT SECTION III(A)(2) OF THE
         AGREEMENT.


                                    PAGE 1

                                                                  EXHIBIT 2
                                  SCHEDULE A





Filing Public Utility:


                         COMMONWEALTH ELECTRIC COMPANY












Qualifying Small Power Producer or Cogenerator:

                         CORPORATION INVESTMENTS, INC.










Service Provided:

      Agreement for the purchase of electric energy produced by Corporation 
      Investments, Inc. at its hydro-electric generating facility in Lowell,
      Massachusetts.
                                    PAGE 2

      AGREEMENT entered into this 10th day of January, 1983 by and between
Commonwealth Electric Company, a Massachusetts corporation with offices
located at 2421 Cranberry Highway, Wareham, Massachusetts 02571 ("Company")
and Corporation Investments, Inc., a Massachusetts corporation with offices
located at 9 Central Street, Lowell, Massachusetts 01853 ("Seller").

      Seller plans to construct, own and operate an hydro-electric generating
facility (the "Plant"), at its site in Lowell, Massachusetts, as more fully
described and defined within Seller's "Application for License: Plant No.
2790, Lowell Hydroelectric Plant", dated May 20, 1980 as amended and tendered
for filing with the Federal Energy Regulatory Commission ("FERC"). Seller
wishes to sell and the Company wishes to buy electric energy from the Plant,
all pursuant to the terms and conditions as set forth in this Agreement.

THEREFORE, the parties, each in consideration of the agreements of the other,
hereby agree as follows:

ARTICLE I.  Sale of Power by Seller.

      (a) Seller agrees to sell and deliver, and the Company agrees to
purchase and accept delivery of, all electric energy produced by the Plant
during the term of this Agreement, except that the Seller shall have the
option not to sell and deliver such electric energy as may be needed from time
to time to satisfy Plant requirements ("Net Plant Output").

      (b) Seller shall have the option to reduce the quantity of electric
energy sold to the Company under the provisions of this Agreement by an amount
not in excess of forty-nine percent (49%) of the Net Plant Output under the
following conditions:

      (1) Seller must exercise such option not later than six (6) months from
the date first above-written, and

      (2) Seller may exercise such option only once, and only for the purpose
of selling the electric energy to the Massachusetts Municipal Wholesale
Electric Company ("MMWEC"), and

      (3) Seller may offer to sell to MMWEC only on the same terms and
conditions upon which it has agreed to sell to the Company.

      (c) The Company shall not be obligated to purchase or take delivery of
electric energy from the Plant unless, in the reasonable judgment of the
Company, the Plant is staffed, operated and maintained in a manner consistent
with the standards applicable to generating facilities owned and operated by
participants in the New England Power Pool ("NEPOOL"), as such standards may
be in effect from time to time during the term of this Agreement. The Plant
must be made available for NEPOOL dispatch in accordance with the provisions
of Section 12.2 of the NEPOOL Agreement dated September 1, 1971 as amended
("NEPOOL Agreement").

      (d) Without limiting the generality of Article I(c) hereof, Seller shall
be obligated hereby to undergo periodic capability audits pursuant to the
terms of Section 8.13 of the NEPOOL Agreement. In the event that the Plant
demonstrates a Capability (as defined at Section 15.6 of the NEPOOL Agreement)
that is less than the "Qualified Capacity" of the Plant ("Capacity Deficien-
                                    PAGE 3

cy"), the Company may assess Seller a charge equal to the Capability Responsi-
bility Adjustment Charge established from time to time by NEPOOL pursuant to
the provisions of Section 9.4 of the NEPOOL Agreement multiplied by such
Capacity Deficiency. In the event that Seller has elected to reduce the
quantity of electric energy sold to the Company pursuant to its option in
Article I(b) above, then in case of a Capacity Deficiency, the Company may
only assess Seller a charge equal to the Capability Responsibility Adjustment
Charge established from time to time by NEPOOL pursuant to the provisions of
Section 9.4 of the NEPOOL Agreement multiplied by the factor that results from
multiplying the total Capacity Deficiency times the percentage of Net Plant
Output that the Company is entitled to purchase. The Qualified Capacity of the
Plant shall be determined once in a capability audit conducted, under the
general supervision of the administrative committee established by Article
X(f) of this Agreement, during the first winter period following the date of
commercial operation of the Plant. Such Qualified Capacity shall be the winter
period Net Capability of the Plant (as computed pursuant to said capability
audit) which shall be the same as the Capability of the Plant calculated
pursuant to Section 15.6 of the NEPOOL Agreement. Notwithstanding the forego-
ing, if such winter period Net Capability of the Plant is less than twenty
thousand (20,000) kilowatts, the Qualified Capacity of the Plant shall be
twenty thousand (20,000) kilowatts.

      (e) The Company reserves the right to impose reasonable conditions
consistent with the NEPOOL standards that are in effect from time to time
during the term of this Agreement in substitution for the foregoing NEPOOL
standards if NEPOOL ceases to establish such standards or if the Company
should cease its participation in NEPOOL during the life of this Agreement.

      (f) During a reasonable period of time prior to the date of commercial
operation of the Plant ("Testing Period"), the Plant may generate some
electric energy ("Test Power"). The Company agrees to take and pay for any
Test Power offered for sale and delivered to it by Seller during the Testing
Period, subject to the following conditions: (i) the tests conducted during
the Testing Period shall be in accordance with standard industry practice and
done under the general supervision of the administrative committee established
by Article X(f) of this Agreement, and (ii) the Company shall pay for any Test
Power monthly at a price equal to the Energy Purchase Price established by
Article III(a)(1) hereof, computed with Factor R set equal to eighty-five
percent (85%,).

ARTICLE II. Effective Date and Term.

      (a) This Agreement shall become effective upon the date first
above-written, and unless sooner terminated in accordance with any applicable
provision of this Agreement, shall remain in full force and effect for a term
equal to the initial term of the license for the Plant as issued by the FERC.
In the event that such license is renewed or extended, this Agreement may
similarly be renewed or extended at the Company's sole option by the giving of
written notice to Seller within six (6) months following receipt of notice
from Seller of the renewal or extension of such license. Seller agrees to use
all reasonable efforts to secure a renewal or extension of such license, as
the case may be.

      (b) The Seller shall have the option, exercisable upon not less than
sixty (60) days written notice to the Company, to terminate this Agreement at
                                    PAGE 4

a date not later than November 1, 1983 if: 
            (1) Seller is unable to obtain financing for the costs of the
acquisition and construction of the Plant upon terms and at a rate of interest
acceptable to Seller, or

            (2) Seller is unable to contract for transmission services
necessary to deliver electric energy to the Company on terms and conditions
acceptable to Seller, or

            (3) FERC fails to license the Plant or issues such a license for
an initial term of less than twenty-five (25) years.

      (c) The Company shall have the option, exercisable upon not less than
sixty (60) days written notice to Seller, to terminate this Agreement if the
Plant has not entered or cannot reasonably be expected to enter commercial
service by December 31, 1986.

      (d) Upon any termination pursuant to Articles II(b) or II(c) hereof,
neither party shall have any liability to the other except such liabilities,
if any, which shall have been incurred hereunder prior to such termination,
which liabilities shall continue until satisfied.

ARTICLE III. Purchase Price.

      (a) From and after the date of commercial operation of the Plant
(currently estimated to be February 1, 1985), the Company shall pay Seller
semi-annually an amount equal to the greatest of:

            (1) the Energy Purchase Price as determined in accordance with
Appendix A to this Agreement multiplied times the quantity of electric energy
delivered to the Company by Seller hereunder, or

            (2) ninety mills ($0.090) per kilowatt-hour ("Floor Energy Price")
multiplied times the quantity of electric energy delivered to the Company by
Seller hereunder, or

            (3) beginning January 1, 1992 and ending at the close of the
fifteenth (15th) year following the date of commercial operation of the Plant,
a price per kilowatt-hour ("Adjusted Floor Energy Price") determined by the
following formula:

            Adjusted Floor Energy Price = 90 mills
            + PGNP-2 x [16.8 + PGNP-l (11.1)]

            Where:PGNP-1 is the cumulative percentage change in the Gross 
                         National Product Implicit Price Deflator ("PGNP")
                         published by the United States Department of Commerce
                         between the date of commercial operation of the Plant
                         and December 31, 1991, and

                  PGNP-2 is the cumulative percentage change in the PGNP after
                  January 1, 1992, multiplied times the quantity of electric
                  energy delivered to the Company by Seller hereunder. In the
                  event the United States Department of Commerce should cease
                  to publish the PGNP, the Company and Seller shall mutually
                                    PAGE 5

                  agree upon a satisfactory replacement therefor or, failing
                  to so agree, shall submit the matter to arbitration in 
                  accordance with the appropriate provisions of this Agree-
                  ment.

      (b) For the purpose of implementing Article III(a) of this Agreement,
the Company shall pay Seller each month an amount determined in accordance
with paragraph (1) thereof, subject to semi-annual reconciliation as set forth
in Article III(c) below. Amounts payable to Seller pursuant to Article
III(a)(1) shall be determined on an estimated basis and paid monthly in
accordance with Article VII hereof, subject to a final determination and
reconciliation at the end of each billing period established pursuant to
Appendix A hereof. For purposes of such monthly payments, an estimated Energy
Purchase Price for each rating period (as defined in Appendix A hereof) shall
be determined as set forth in such Appendix A by setting Factor O-2 equal to
Factor O-1. Such estimated Energy Purchase Price for each rating period shall
be multiplied by the quantity of electric energy (measured in kilowatt-hours)
delivered to the Company by Seller during such rating period during such
month. Following the close of each such billing period, the Company will
promptly determine its actual Energy Purchase Price for each rating period.
Any difference between the forecast and actual Energy Purchase Price for the
same billing period shall be subject to reconciling adjustment during the
first month of the next subsequent billing period.

      (c) The Company shall semi-annually compute the weighted average price
paid for electric energy purchased hereunder during the semi-annual period
then ending by dividing the total of the monthly payments to Seller for
electric energy by the total kilowatt-hours purchased. In the event that such
weighted average semi-annual price is less than the Floor Energy Price or the
Adjusted Floor Energy Price, the Company shall pay to Seller an amount equal
to the difference between such weighted average semi-annual price and the
greater of the Floor Energy Price or the Adjusted Floor Energy Price, multi-
plied by the total kilowatt-hours purchased from Seller, all during such
semi-annual period. Any "Semi-Annual Adjustments" under this Article III(c)
shall be made during the first month following the semi-annual period which is
being adjusted according to the provisions hereof.

      (d) If, after the first fifteen (15) years following the date of
commercial operation of the Plant, the Company determines that the Energy
Purchase Price, computed with Factor R set equal to one-hundred percent
(100%), exceeds the Company's avoided energy costs (as hereinafter defined),
the Company may propose a change to Appendix A by giving Seller written notice
thereof. Such proposed change shall be limited to the methodology for deter-
mining or calculating the Company's avoided energy costs and shall not deviate
from the principle that the average decremental cost shall at least approxi-
mate the most costly ten percent (10%) of the load placed upon the Company's
system by its firm-service customers during the relevant billing period. In
the event that Seller fails to accept said proposed change and Seller and
Company are unable to agree in writing upon a mutually satisfactory revised
Appendix A within sixty (60) days of the giving of such notice, either the
Seller or the Company may submit the matter to arbitration pursuant to the
provisions of Article X(g) and (h) below. During the period of time in which
said matter is in arbitration, the proposed revised Appendix A originally
offered by the Company shall govern the computation of the Energy Purchase
Price. Within thirty (30) days following resolution of said dispute by
                                    PAGE 6

arbitration, the Company shall recompute, in accordance with said resolution,
all amounts paid to Seller during the pendency of such dispute and debit or
credit Seller's account as appropriate.

      (e) Avoided energy cost as used herein shall mean the incremental cost
to the Company of electric energy which the Company would have generated or
purchased but for the purchase of electric energy from Seller.

      (f) Any taxes on the production or sale of electric energy furnished by
the Seller to the Company under this Agreement shall be the obligation of and
paid by the Seller as and when due.

ARTICLE IV. Energy Purchase Bank.

      (a) The Company will establish an account within its records, to be
known as the Energy Purchase Bank, which shall be maintained separately from
all other accounts therein. The Energy Purchase Bank shall be solely used to
record such periodic energy purchase (and related) transactions and associated
account balances as are specified within this Agreement as affecting such
Energy Purchase Bank.

      (b) During the period beginning January 1, 1992 and ending at the close
of the fifteenth year following the date of commercial operation of the Plant,
the difference between any amounts paid to Seller pursuant to the Adjusted
Floor Energy Price and the amounts that would have been paid to Seller under
the greater of the Energy Purchase Price or the Floor Energy Price, whichever
would otherwise have been applicable, shall be debited to the Energy Purchase
Bank. Except during such period, there shall be no debit entries to the Energy
Purchase Bank during the term of this Agreement.

      (c) During any billing period for which the Energy Purchase Bank
contains a debit balance and for which the Energy Purchase Price exceeds both
the Floor Energy Price and the Adjusted Floor Energy Price, any payment to
Seller for electric energy purchased hereunder shall be reduced by an amount
equal to the difference between the Energy Purchase Price and the greater of
either the Floor Energy Price or the Adjusted Floor Energy Price multiplied by
the number of kilowatt-hours purchased from Seller during such billing period
(which amount shall in no event exceed the then-current debit balance of the
Energy Purchase Bank). Such amount shall be credited to the Energy Purchase
Bank. Said procedure shall continue throughout the term of this Agreement
until the debit balance in the Energy Purchase Bank is reduced to zero. Any
debit balance of the Energy Purchase Bank shall bear interest at a rate per
annum which shall be at all times equal to the Base Rate of The First National
Bank of Boston (or its successors) which shall mean the rate of interest
designated by such Bank as its Base Rate and usually charged by it to substan-
tial and responsible borrowers, as in effect from time to time. Each change in
the said Base Rate shall be effective at the beginning of the business day on
which such change occurs.

ARTICLE V.  Delivery by Seller.

      Electric energy generated by the Seller at the Plant shall be delivered
to the Company at the 345,000 volt bus located in the Canal Electric Company
switchyard at Sandwich, Massachusetts ("point of delivery") in the form of
three-phase, sixty hertz alternating current at approximately 345,000 volts
                                    PAGE 7

nominal. Seller shall bear the sole cost and responsibility for securing
transmission services adequate for the delivery to the Company at the point of
delivery of electric energy purchased by the Company hereunder.

ARTICLE VI. Meters and Metering.

      (a) The Company shall have the right to review and approve the metering
installations required to record the quantities of electricity purchased from
the Seller. Such metering equipment will be capable, inter alia, of providing
data required to determine kilowatt-hours per hour purchased during each hour
of each rating period established by Appendix A hereto as well as total
electric energy purchased per rating period under the terms of this Agreement.
Seller shall install, own, operate and maintain such metering equipment, which
equipment shall be located at Seller's bus (or buses). If, for any reason, it
is impractical to install meters at such bus (or buses), appropriate adjust-
ments shall be made to reflect the actual amount of electric energy which
would have been recorded by meters located at such bus (or buses).

      (b) Seller shall maintain all metering equipment installed pursuant
hereto accurate by regular testing and calibration in comparison to recognized
standards. The metering equipment shall be sealed, and Seller will comply with
any reasonable request of the Company with regard to the presence of the
Company's representative when such seals are to be broken or when the meters
are to be inspected, tested or adjusted. The Company may request, at any time,
a test of the accuracy of any metering equipment installed pursuant hereto and
shall bear the costs thereof in the event that said requests are made more
frequently than once in each twelve months. The results of all meter calibra-
tions or tests, whether or not performed at the Company's request, shall be
open to examination by the Company at all reasonable times.

      (c) Any meter tested and found to register less than or equal to
one-half of one percent (0.5%) above or below the recognized comparative
standard shall be considered correct and accurate. If as a result of such
tests, the metering equipment is found to be defective or inaccurate, Seller
shall restore it to a condition of accuracy or replace it. In such event,
adjustment shall be made by the Company correcting all measurements made by
the defective or inaccurate meter for either (i) the actual period during
which inaccurate measurements were made, if determinable to the mutual
satisfaction of the Company and Seller or (ii) if such period is not so
determinable, for a period equal to one-half of the time elapsed since the
last prior test, but in no event greater than twelve months.

      (d) Other provisions of this Article VI notwithstanding, the Company may
elect to install its own metering equipment in supplement to the Seller's
metering equipment. Should the Company so elect and should any metering
equipment installed by the Seller fail to register the amount of electric
energy delivered to the Company during any period of time, the Company's
metering equipment shall be used to determine the amount of electric energy so
delivered in lieu of the Company's estimates thereof. If the Company wishes
its metering equipment to be so used, the Company agrees to operate, maintain
and read such equipment according to the standards established by this Article
VI. The Seller agrees, upon request of the Company, to provide a suitable
location at the Plant for installation of the Company's meters at no cost to
the Company.
                                    PAGE 8

      (e) Upon written request of the Company, Seller shall install and bear
the cost of such telemetering equipment and data circuits as the Company may
reasonably require for the transmission of various metered values to its
operations center. The design of and equipment specifications for such
telemetering equipment and data circuits shall be approved by the Company
prior to installation thereof by Seller.

      (f) Seller shall read its meters on or about the last working day of
each calendar month for determination of the amount of purchases by the
Company under the terms of this Agreement and shall supply the results of such
meter readings to the Company within five (5) business days following the
taking thereof. The time period between two successive meter readings shall be
deemed to be a month for purposes of this Agreement.

ARTICLE VII.      Payment.

      (a) The Company shall determine the quantity of electric energy pur-
chased from Seller monthly based upon the metered values obtained in accor-
dance with the several provisions of Article VI of this Agreement as appropri-
ate. The Company, after giving due effect to any reconciling adjustments
necessary, shall pay Seller for such electric energy monthly within twenty
(20) calendar days following receipt of such metered values from Seller and
shall show the derivation of such payment in such detail as Seller may
reasonably request from time to time.

      (b) In the event that any data required for the purpose of determining
payment hereunder are unavailable when required, such unavailable data may be
estimated by the Company, subject to any required adjustment based upon actual
data in a subsequent payment month.

ARTICLE VIII.     Governmental Regulation.

      (a) This Agreement shall, within ten (10) days of the date hereof, be
submitted by the Company to the Massachusetts Department of Public Utilities
("MDPU") in accordance with Section 94A, Chapter 164, of the Massachusetts
General Laws and applicable regulations of the MDPU, and the Company shall use
its best efforts to obtain expeditious approval thereof in accordance with
such law and regulations.

      (b) It shall be the responsibility of each party hereto individually to
take all necessary actions to satisfy any regulatory requirements which may be
imposed upon such party by any federal, state or municipal statute, rule,
regulation or ordinance which may be in effect from time to time relative to
the performance of such party hereunder.

      (c) This Agreement and all rights and obligations of the parties
hereunder are subject to all applicable state and federal laws and all duly
promulgated orders and duly authorized actions of governmental authorities.

      (d) The interpretation and performance of this Agreement shall be in
accordance with and controlled by the laws of the Commonwealth of Massachu-
setts.
                                    PAGE 9

ARTICLE IX. Liability and Force Majeure.

      (a) The parties hereto shall be excused from performing hereunder and
shall not be liable in damages or otherwise if and only to the extent that
they are unable to do so or are prevented from doing so by statute or regula-
tion or by action of any court or public authority having or purporting to
have jurisdiction in the premises; or by loss or impairment of the supply of
electricity; or by a break or fault in the Company's transmission or distribu-
tion system or failure or improper operation of transformers, switches or
other equipment necessary for receipt of electric energy from Seller; or by
reason of storm, flood, fire, earthquake, explosion, civil disturbance, labor
dispute, act of God or the public enemy, failure of any supplier to perform,
restraint by a court or regulatory agency, or any other cause, whether or not
similar thereto, beyond the reasonable control of the affected party. Each
party shall have the obligation to operate in accordance with good utility
practices at all times and to use diligent effort to remove any cause of
failure to supply or receive electric energy hereunder. Neither the Company
nor Seller shall, in any event, be liable to the other or to any third party
for any consequential, indirect or special damages to persons or property,
whether arising in tort, contract or otherwise, by reason of this Agreement or
any services performed or undertaken to be performed by the Company or Seller
hereunder, except as otherwise expressly provided herein.

      (b) Whenever the Company's system or the systems with which it is
directly or indirectly interconnected experience a "System Emergency", or
whenever it is needful or desirable to aid in the restoration of service on
its system or on the systems with which it is directly or indirectly intercon-
nected, the Company may, in its reasonable judgment, curtail or interrupt the
taking of electric energy hereunder, provided such curtailment or interruption
shall continue only for so long as is reasonably necessary. Such curtailment,
interruption, or reduction shall not be deemed to be a default by the Company
nor shall the Company be liable therefor to Seller or to any other party. A
System Emergency means a condition on a utility's system which is likely to
result in an imminent significant disruption of service or is imminently
likely to endanger life or property. Notwithstanding any other provision of
this Agreement to the contrary, in the event that the Company cannot receive
electric energy from Seller into its own system because of a System Emergency
but such System Emergency does not prevent Seller from delivering such
electric energy to another utility with which the Company is interconnected,
the Company shall pay Seller for such electric energy so delivered the exact
amount, if any, that the Company receives in payment or credit from such
utility for the delivery of such electric energy.

      (c) The Company and the Seller agree that each shall be responsible for
the electricity on its respective side of the point of delivery and shall
indemnify, save harmless and defend the other against all claims, demands,
costs or expenses for loss, damage or injury to persons or property in any
manner directly or indirectly arising from, connected with or growing out of
the presence or use of electricity or the transmission of electricity over the
wires, cables, devices or appurtenances owned by it, its agents or suppliers,
saving only such loss, damage or injury as may be caused by the willful or
negligent act of the other. The Company and the Seller respectively assume
full responsibility in connection with the service rendered hereunder for
their respective wires, cables and other devices used in connection with said
service. Each party hereto shall be solely liable for all claims of its own
                                    PAGE 10

employees arising from any workmen's compensation laws.

      (d) Neither by inspection nor non-rejection nor in any other way does
either party give any warranty, expressed or implied, as to the adequacy,
safety or other characteristics of any equipment, apparatus or devices,
installed on the premises of or used by the other party, its agents or
suppliers. Neither party shall be liable to the other for damages resulting in
any way from its taking or supplying of electric energy pursuant to the terms
of this Agreement or from the presence or operation of its apparatus, meters,
appurtenances or other equipment on the premises of the other party.

      (e) Seller may from time to time withdraw the Plant from service and
cease to supply electric energy to the Company as necessary to perform
scheduled or unscheduled maintenance or repair upon the Plant. Seller shall
comply with the provisions of NEPOOL Operating Procedure No. 5 as in effect
from time to time when planning any scheduled maintenance or repair upon the
Plant. Seller shall give the Company such notice as may be practicable in the
circumstances when withdrawing the Plant from service for unscheduled mainte-
nance or repair.

ARTICLE X.  Miscellaneous Provisions

      (a) This Agreement constitutes the entire Agreement between the parties
relating to the subject matter hereof, and all previous agreements, discus-
sions, communications and correspondence with respect to the subject matter
hereof are superseded by the execution of this Agreement.

      (b) This Agreement may not be modified or amended except in writing
signed by or on behalf of both parties by their duly authorized officers.

      (c) Any qualified and properly identified employee of the Company shall
have access to the Plant at all reasonable times for the purpose of reading or
inspecting meters, examining the operation of the Plant or other purposes
reasonably related to the Company's performance under the terms of this
Agreement. Such access shall not interfere with Seller's normal business
operations.

      (d) This Agreement shall inure to the benefit of and bind the respective
successors and permitted assigns of the parties hereto, provided, however,
that no assignment by Seller or any successor or assignee of Seller of its
rights and obligations hereunder, except an assignment to a wholly-owned
subsidiary whose principal functions are to hold Seller's ownership interest
in and to operate the Plant, shall be made or become effective without the
prior written consent of the Company in each case obtained. The Company will
provide consent to any assignment of Seller's rights and obligations hereunder
to the extent necessary for Seller to obtain construction or permanent
financing for the Plant with an institutional lender and to assure that the
Company's right to receive the output of the Plant shall apply as against any
person or entity that might obtain title and possession of the Plant pursuant
to such financing.

      (e) All notices required or permitted under this Agreement shall be in
writing and shall be deemed to have been given when delivered personally or
deposited in the mails, postage prepaid, registered mail addressed to the
party to whom notice is being given at its address set forth above. Either
                                    PAGE 11

party may change its address by notice similarly given.

      (f) The parties hereto agree to establish an administrative committee.
Such committee will be empowered to do all acts and things necessary to
implement the intent of the parties hereto as set forth herein and to take
such further actions as may be required in the circumstances, provided that
they are not inconsistent with this Agreement. The Company and Seller shall
have equal representation upon said committee.

      (g) In the case of any dispute between the parties with respect to the
interpretation of this Agreement, or the performance of the same, or under
Article III(d) above, either party may give notice in writing to the other of
its desire to submit such questions to arbitration, and may designate an
arbitrator. Within thirty (30) days after the receipt of such notice, the
other party may, in writing, serve upon the party invoking such arbitration, a
notice designating an arbitrator on its behalf. The two arbitrators so chosen
shall, within twenty (20) days after the appointment of the second arbitrator,
in writing, designate a third arbitrator. Upon the failure of the party
notified to appoint the second arbitrator within such time, the party invoking
such arbitration may proceed with the single arbitrator. If the first and
second arbitrators are unable to agree on a third arbitrator within twenty
(20) days of the appointment of the second arbitrator, the first and second
arbitrator shall invoke the services of the American Arbitration Association
to appoint a third arbitrator. Said third arbitrator shall, to the extent
practicable, have special competence and experience with respect to the
subject matter under consideration. An arbitrator so appointed shall have full
authority to act pursuant to this Article. No arbitrator, whether chosen by a
party hereto or appointed, shall have the power to amend or add to this
Agreement.

      (h) The party calling the arbitration shall, within twenty (20) days
after either the failure of the other party to name an arbitrator, or the
appointment of the third arbitrator, as the case may be, fix, in writing, a
time and a place of hearing, to be not less than twenty (20) days from
delivery of notice to the other party. The arbitrator or arbitrators shall,
thereupon, proceed promptly to hear and determine the controversy pursuant to
the then-current rules of the American Arbitration Association for the conduct
of commercial arbitration proceedings, except that if such rules shall
conflict with the then current provisions of the laws of the Commonwealth of
Massachusetts relating to arbitration, such conflict shall be governed by the
then current provisions of the laws of the Commonwealth of Massachusetts
relating to arbitration. Such arbitrator or arbitrators shall fix a time
within which the matter shall be submitted to him or them by either or both of
the parties, and shall make his or their decision, within ten (10) days after
the final submission to him or them unless, for good reasons to be certified
by him or them in writing, he or they shall extend such time. The decision of
the single arbitrator, or two of the three arbitrators, shall be taken as the
arbitration decision. Such decision shall be made in writing and in duplicate,
and one copy shall be delivered to each of the parties. The expense of the
arbitration shall be borne by the unsuccessful party, unless the arbitrator or
arbitrators by his or their award shall otherwise provide, except that each
party shall pay the costs of its own counsel. Each party shall accept and
abide by the decision. The award of the arbitral tribunal shall be final
except as otherwise provided by applicable law. Judgment upon such award may
be entered by the prevailing party in any court having jurisdiction thereof,
                                    PAGE 12

or application may be made by such party to any such court for judicial
acceptance of such award and an order of enforcement.

IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be
executed as of the day and year first above written.

                                          COMMONWEALTH ELECTRIC COMPANY


                                          By:                         
                                                  J. V. Donovan,
                                              Executive Vice President



                                          CORPORATION INVESTMENTS, INC.


                                          By:                          
                                                 Eldred L. Field,
                                                     Chairman
                                    PAGE 13

                                  APPENDIX A

                             ENERGY PURCHASE PRICE

      The Energy Purchase Price applicable to electric energy delivered to the
Company by Seller during any billing period will be equal to the rate, taken
to the nearest one-tenth of a mill per kilowatt-hour, determined in accordance
with the following formula, separately applied to each rating period hereinaf-
ter defined:

                              P = R X F (O-2/O-1)

Where:      P = Energy purchase price

            R = Avoided cost ratio

            F = Average decremental cost of generated and/or purchased 
                  energy.

            O-2 = Actual cost of energy produced and/or purchased from fossil
                  fuels

            O-1 = Estimated cost of energy produced and/or purchased from 
                  fossil fuels

(1) Definitions

      (a) Factor R. During the first fifteen (15) years following the date of
commercial operation of the Plant, Factor R shall be eighty-five percent
(85%). During the sixteenth such year, Factor R shall be eighty percent (80%).
During the seventeenth such year and for the remaining term of this Agreement,
Factor R shall be seventy-five percent (75%).

      (b) Factor F. Factor F shall be the Company's estimated average
decremental cost of generated and/or purchased energy as delivered to its
system, separately determined (as set forth herein) for each billing period
hereinafter defined. Factor F shall be computed not more than sixty (60) days
prior to the beginning of such billing period.

Said average decremental cost of energy shall be defined by the following
formula, taken to the nearest one-tenth of a mill per kilowatt-hour:

      F = Cost-1 - Cost-2/KWH-1 - KWH-2

            where:       Cost-1 and KWH-1 represent the estimated cost and 
                         quantity (respectively) of energy generated and/or
                         purchased by the Company to meet one-hundred percent
                         (100%) of the load placed upon its system by its
                         firm-service customers during any billing period.

                         Cost-2 and KWH-2 represent the estimated cost and 
                         quantity (respectively) of energy generated and/or
                         purchased by the Company to meet ninety percent (90%)
                         of the load placed upon its system by its firm ser-
                         vice customers during the same billing period.
                                    PAGE 14

      (c) Factors O. The two Factors O shall be the average cost of energy
generated by and/or purchased from generating units fired with fossil fuels
during any billing period, either as actually experienced by the Company
during such billing period (Factor O-2) or as estimated by the Company for
such billing period (Factor O-1) and as included in its computations determin-
ing the average decremental cost of energy, all measured to the nearest
one-tenth of a mill per kilowatt-hour.

(2) Billing Period

      A billing period hereunder shall be any three (3) month period beginning
January first, April first, July first and October first of any year during
the term of this Agreement.

(3) Rating Periods

      There shall be two rating periods for purposes of computing the Energy
Purchase Prices. The Peak Period shall be defined as all hours in the billing
period from 9:00 A.M. to 9:00 P.M. Eastern Standard Time on weekdays (Monday
through Friday). The Off-Peak Period shall include all hours in the billing
period not included in the Peak Period. The Company reserves the right to
revise the definition of its rating periods from time to time during the term
of this Agreement upon reasonable notice to Seller.
                                    PAGE 15

                                  SCHEDULE B


                         COMMONWEALTH ELECTRIC COMPANY
             ESTIMATED PURCHASE FROM CORPORATION INVESTMENTS, INC.
                     TWELVE MONTHS ENDING JANUARY 31, 1986


               ENERGY PURCHASE (KWH)             COST OF ENERGY (* )
             PEAK      OFF-PEAK   TOTAL       PEAK      OFF-PEAK  TOTAL
  1985

February      3146760   5594240    8741000     283208    503482    786690

March         3117960   5543040    8661000     280616    498874    779490

April         3494160   6211840    9706000     314474    559066    873540

May           3102480   5515520    8618000     279223    496397    775620

June          3672360   6528640   10201000     330512    587578    918090

July          2682360   4768640    7451000     241412    429178    670590

August        1539720   2737280    4277000     138575    246355    384930

September     1285920   2286080    3572000     115733    205747    321480

October       1198440   2130560    3329000     107860    191750    299610

November      1729440   3074560    4804000     155650    276710    432360

December      2708280   4814720    7523000     243745    433325    677070

  1986

January       3282120   5834880    9117000     295391    525139    820530

Total
12 mos.      30960000  55040000   86000000    2786400   4953600   7740000


(*) The energy purchase price is estimated to be 90 mills
per kwh pursuant to Article III(a)(2) of the agreement.


© 2022 IncJournal is not affiliated with or endorsed by the U.S. Securities and Exchange Commission