CALIFORNIA ENERGY CO INC
424B1, 1995-02-16
STEAM & AIR-CONDITIONING SUPPLY
Previous: CALIFORNIA ENERGY CO INC, S-4 POS, 1995-02-16
Next: STRONG OPPORTUNITY FUND INC, DEF 14A, 1995-02-16






<PAGE>
                                              Filed Pursuant to Rule 424(b)(1)
                                                Registration File No.: 33-57191






   
    
                                16,670,000 Shares
[LOGO]
                       California Energy Company, Inc.
                                 Common Stock
                              ($.0675 par value)
                                ----------------
   
All the 16,670,000 shares of Common Stock (the "Common Stock") of California
Energy Company, Inc. (the "Company") offered hereby are being sold by the
Company. Of the 16,670,000 shares of Common Stock being offered, 13,170,000
shares are initially being offered in the United States and Canada (the "U.S.
Shares") by the U.S. Underwriters (the "U.S. Offering") and 2,000,000 shares
are initially being concurrently offered outside the United States and Canada
(the "International Shares" and, together with the U.S. Shares, the "Shares")
by the Managers (the "International Offering" and, together with the U.S.
Offering, the "Offering"). The offering price and underwriting discounts and
commissions of the U.S. Offering and the International Offering are identical.
1,500,000 shares of Common Stock being offered pursuant to this Prospectus
are expected to be purchased by Peter Kiewit Sons', Inc. ("PKS"), directly
from the Company, at a price equal to the Price to Public and PKS set forth
below. PKS has indicated an intention to acquire such shares (the "Direct
Sale"), subject to receipt and review by PKS of a final Prospectus and
conditioned upon the closing of the Offering.
    

The net proceeds of the Offering and the proceeds of the Direct Sale, together
with borrowings of up to $500 million under bank credit facilities and general
corporate funds of the Company, will be used to complete the Magma Acquisition
(as hereinafter defined). The closing of the Offering will occur concurrently
with, and is conditioned upon, the closing of the Magma Acquisition pursuant to
the All-Cash Option (as hereinafter defined).

   
The Common Stock of the Company is listed on the New York Stock Exchange under
the symbol "CE". On February 15, 1995, the last reported sale price of the
Common Stock on the New York Stock Exchange Composite Tape was $17 7/8 per
share.

    
                                ----------------
FOR A DISCUSSION OF CERTAIN FACTORS THAT SHOULD BE CONSIDERED IN CONNECTION
         WITH AN INVESTMENT IN THE COMMON STOCK, SEE "RISK FACTORS".
                                ----------------
THESE SECURITIES HAVE NOT BEEN APPROVED OR DISAPPROVED BY THE SECURITIES AND
    EXCHANGE COMMISSION OR ANY STATE SECURITIES COMMISSION NOR HAS THE
       SECURITIES AND EXCHANGE COMMISSION OR ANY STATE SECURITIES
           COMMISSION PASSED UPON THE ACCURACY OR ADEQUACY OF THIS
              PROSPECTUS. ANY REPRESENTATION TO THE CONTRARY IS
                             A CRIMINAL OFFENSE.

   
<TABLE>
<CAPTION>
                                            UNDERWRITING
                              PRICE TO      DISCOUNTS AND    PROCEEDS TO
                            PUBLIC AND PKS  COMMISSIONS(1)    COMPANY(2)
                            --------------  --------------  -------------
<S>                        <C>              <C>            <C>
Per Share  ..............      $17.00           $.51           $16.49
Total (3)  ..............   $283,390,000     $7,736,700     $275,653,300
</TABLE>

   (1) No Underwriting Discounts and Commissions are to be paid in connection
       with the Direct Sale to PKS.
   (2) Before deduction of expenses payable by the Company estimated at
       $2,132,810. Per Share Proceeds to Company reflect per share proceeds
       from the Offering but not from the Direct Sale.
   (3) The Company has granted the U.S. Underwriters and the Managers an
       option, exercisable by CS First Boston Corporation for 30 days from the
       date of this Prospectus, to purchase a maximum of 2,275,000 additional
       shares to cover over-allotments. If the option is exercised in full,
       the total Price to Public and PKS will be $322,065,000, Underwriting
       Discounts and Commissions will be $8,896,950 and Proceeds to Company
       will be $313,168,050.
                                ----------------
   The U.S. Shares are offered by the several U.S. Underwriters when, as and
if issued by the Company, delivered to and accepted by the U.S. Underwriters
and subject to their right to reject orders in whole or in part. It is
<PAGE>

         
expected that the U.S. Shares will be ready for delivery on or about February
24, 1995.



CS First Boston
           Bear, Stearns & Co. Inc.
                       Donaldson, Lufkin & Jenrette
                          Securities Corporation
                                  C.J. Lawrence/Deutsche Bank
                                     Securities Corporation
                                                      Lehman Brothers

              The date of this Prospectus is February 16, 1995.
    



<PAGE>

         
<PAGE>


 #############################################################################
              IMAGES OMITTED ON INSIDE FRONT COVER OF PROSPECTUS;
                    DATAPOINTS AND NARRATIVE SUPPLIED BELOW.
             (SEE ALSO "APPENDIX FOR GRAPHICS AND IMAGE MATERIAL"
                     AFTER BACK COVER PAGE OF PROSPECTUS.)
 #############################################################################


[LOGO]        CALIFORNIA ENERGY COMPANY, INC.'S PLANNED PROJECT
               DEVELOPMENT AND CAPACITY IMPLEMENTATION SCHEDULE
            (INCLUDES EXISTING OPERATIONS, CONTRACTS AND AWARDS)*

   
MW IN OPERATION
                                1995    1996    1997    1998    1999
                                ----    ----    ----    ----    ----
Net Megawatts (MW) Owned        354     581     1,008   1,321   1,698

Facility Gross MW Capacity      642     883     1,584   2,165   2,770
    

<TABLE>
<CAPTION>
 PROFILE OF PROJECTS**
                                FACILITY MW
                                  CAPACITY
                             ----------------
                                                NET MW                   COMMERCIAL
PROJECT                       GROSS     NET     OWNED      FUEL TYPE     OPERATION
- ---------------------------  -------  -------  --------  -------------  ------------
<S>                          <C>      <C>      <C>       <C>              <C>
PROJECTS IN OPERATION
 Coso Project                  288      264      127     geothermal       1987-90
 Salton Sea Projects           264      224      150     geothermal       1986-90
 Yuma                           55       50       50     gas                 1994
 Roosevelt Hot Springs          25       23       17     geothermal          1984
 Desert Peak                    10       10       10     geothermal          1985
                             -------  -------  --------
  Total                        642      571      354
PROJECTS UNDER CONSTRUCTION
 Upper Mahiao                  128      119      119     geothermal          1996
 Mahanagdong                   180      165       74     geothermal          1997
 Malitbog                      231      216      216     geothermal       1996-97
                             -------  -------  --------
  Total                        539      500      409
AWARDED PROJECTS
 BRPU                          163      163      163     geothermal           TBD
 Fish Lake                      36       36       36     geothermal          1996
 Newberry                       30       30       30     geothermal          1997
 Dieng                         400      400      188     geothermal       1997-99
 Patuha                        400      400      140     geothermal       1997-99
 Casecnan                      140      140       98     hydroelectric       1998
 Bali                          350      350      210     geothermal       1998-99
 Alto Peak                      70       70       70     geothermal          1997
                             -------  -------  --------
  Total                      1,589    1,589      935
                             -------  -------  --------
Total                        2,770    2,660    1,698
                             =======  =======  ========
</TABLE>
- ---------------
    * For projects under award, no assurance can be given that a power sales
      contract will be executed. In addition, substantial other contingencies
      exist with respect to awards, including without limitation, the need to
      obtain financing, permits and licenses, and the completion of
      construction.

   ** For more detailed information concerning the Company's projects, see
      "BUSINESS--International Projects; --Domestic Projects."



<PAGE>

         
<PAGE>
   
        THE WORLD'S LARGEST INDEPENDENT PRODUCER OF GEOTHERMAL POWER*

                            [MAP APPEARS HERE]

THE PHILIPPINES
- -----------------------------------------------------------
<TABLE>
<CAPTION>
              FACILITY MW CAPACITY
              --------------------
                                   NET MW
   PROJECT         GROSS    NET    OWNED       FUEL TYPE
- -----------------------------------------------------------
<S>               <C>      <C>     <C>       <C>
1 Upper Mahiao     128      119     119       geothermal
2 Mahanagdong      180      165      74       geothermal
3 Malitbog         231      216     216       geothermal
4 Casecnan         140      140      98       hydroelectric
5 Alto Peak         70       70      70       geothermal
- -----------------------------------------------------------
</TABLE>

INDONESIA
- -----------------------------------------------------------
<TABLE>
<CAPTION>
           FACILITY MW CAPACITY
           --------------------
                               NET MW
   PROJECT     GROSS    NET    OWNED     FUEL TYPE
- -----------------------------------------------------------
<S>            <C>     <C>     <C>       <C>
1 Dieng         400     400     188       geothermal
2 Patuha        400     400     140       geothermal
3 Bali          350     350     210       geothermal
- -----------------------------------------------------------
</TABLE>

UNITED STATES
- --------------------------------------------------------------------------
<TABLE>
<CAPTION>
                         FACILITY MW CAPACITY
                         --------------------
                                                     NET MW
   PROJECT                  STATE    GROSS    NET     OWNED     FUEL TYPE
- --------------------------------------------------------------------------
<S>                         <C>      <C>     <C>      <C>       <C>
1 Coso Project               CA       288     264      127       geothermal
2 Salton Sea Projects        CA       264     224      150       geothermal
3 Yuma                       AZ        55      50       50       gas
4 Roosevelt Hot Springs      UT        25      23       17       geothermal
5 Desert Peak                NV        10      10       10       geothermal
6 BRPU                       CA       163     163      163       geothermal
7 Fish Lake                  CA        36      36       36       geothermal
8 Newberry                   OR        30      30       30       geothermal
- --------------------------------------------------------------------------

</TABLE>

 * Based on the Company's estimate of aggregate MW of electric generating
   capacity in operation and under construction.
    

<PAGE>

         
<PAGE>

IN CONNECTION WITH THE OFFERING, CS FIRST BOSTON CORPORATION ON BEHALF OF THE
U.S. UNDERWRITERS AND THE MANAGERS MAY OVER-ALLOT OR EFFECT TRANSACTIONS
WHICH STABILIZE OR MAINTAIN THE MARKET PRICE OF THE COMMON STOCK AT A LEVEL
ABOVE THAT WHICH MIGHT OTHERWISE PREVAIL IN THE OPEN MARKET. SUCH
TRANSACTIONS MAY BE EFFECTED ON THE NEW YORK STOCK EXCHANGE, THE PACIFIC
STOCK EXCHANGE, THE LONDON STOCK EXCHANGE OR OTHERWISE. SUCH STABILIZING, IF
COMMENCED, MAY BE DISCONTINUED AT ANY TIME.

DURING THE OFFERING, CERTAIN PERSONS AFFILIATED WITH PERSONS PARTICIPATING IN
THE DISTRIBUTION MAY ENGAGE IN TRANSACTIONS FOR THEIR OWN ACCOUNTS OR FOR THE
ACCOUNTS OF OTHERS IN THE COMMON STOCK PURSUANT TO EXEMPTIONS FROM RULES
10B-6, 10B-7, AND 10B-8 UNDER THE EXCHANGE ACT.

                            AVAILABLE INFORMATION

   California Energy Company, Inc. (the "Company") and Magma Power Company
("Magma") are subject to the informational requirements of the Securities
Exchange Act of 1934, as amended (the "Exchange Act"), and, in accordance
therewith, each files reports, proxy statements and other information with
the Securities and Exchange Commission (the "Commission"). Such reports,
proxy statements and other information filed by the Company or Magma with the
Commission pursuant to the informational requirements of the Exchange Act may
be inspected and copied at the public reference facilities maintained by the
Commission at Room 1024, 450 Fifth Street, N.W., Washington, D.C. 20549 and
at the following Regional Offices of the Commission: Midwest Regional Office,
Citicorp Center, 500 West Madison Street, Suite 1400, Chicago, Illinois
60661; and New York Regional Office, 14th Floor, Seven World Trade Center,
New York, New York 10048. Copies of such materials can be obtained at
prescribed rates from the Public Reference Section of the Commission at
Judiciary Plaza, 450 Fifth Street, N.W., Washington, D.C. 20549. In addition,
material filed by the Company can be inspected at the offices of the New York
Stock Exchange, Inc. ("NYSE"), 20 Broad Street, New York, New York 10005, on
which the shares of common stock, par value $.0675 per share (the "Common
Stock"), of the Company are listed, at the offices of the Pacific Stock
Exchange at 301 Pine Street, San Francisco, California 94104 and 233 South
Beaudry Avenue, Los Angeles, California 90012 and at the offices of the
London Stock Exchange at International Stock Exchange, Throgmorton Street,
EC2N 1HP, London, England. Material filed by Magma can be inspected at the
offices of the National Association of Securities Dealers, Inc., 1735 K
Street, N.W., Washington, D.C. 20006.

   The Company has filed with the Commission a Registration Statement on Form
S-3 (the "Registration Statement," which term shall include all amendments,
exhibits and schedules thereto) under the Securities Act of 1933, as amended
(the "Securities Act"), with respect to the shares of Common Stock offered
pursuant to the Offering (the "Shares") and the Direct Sale. This Prospectus
does not contain all of the information set forth in the Registration
Statement, certain parts of which have been omitted in accordance with the
rules and regulations of the Commission. For further information with respect
to the Company and the Shares, reference is made to the Registration
Statement, including the exhibits and schedules filed as a part thereof and
otherwise incorporated therein. Statements made in this Prospectus as to the
contents of any contract, agreement or other document referred to are not
necessarily complete. With respect to each such contract, agreement or other
document filed as an exhibit to the Registration Statement, reference is made
to such exhibit for a more complete description of the matter involved and
each such statement shall be deemed qualified in its entirety by such
reference. Copies of the Registration Statement and the exhibits thereto may
be inspected, without charge, at the offices of the Commission, or obtained
at prescribed rates from the Public Reference Section of the Commission at
the address set forth above.

                                3

<PAGE>

         
<PAGE>

                   INCORPORATION OF DOCUMENTS BY REFERENCE

   The Company and Magma hereby incorporate by reference into the
Registration Statement of which this Prospectus is a part the following
documents previously filed with the Commission pursuant to the Exchange Act:

   1. The Company's Annual Report on Form 10-K for the fiscal year ended
December 31, 1993 (the "Company's 1993 10-K").

   2. The Company's Quarterly Reports on Form 10-Q for the quarters ended
March 31, 1994, June 30, 1994 and September 30, 1994.

   3. The Company's Current Reports on Form 8-K dated March 7, 1994, March
28, 1994, April 11, 1994, May 6, 1994, June 8, 1994, August 16, 1994,
September 22, 1994, September 30, 1994, October 6, 1994, October 26, 1994,
November 22, 1994, December 6, 1994, December 9, 1994, January 11, 1995,
January 27, 1995 and February 13, 1995.

   4. The Company's description of the Common Stock contained in the
Company's Registration Statement on Form 8-A, dated July 28, 1993, pursuant
to Section 12 of the Exchange Act, including any amendment or report filed
for the purpose of updating such description.

   5. Magma's Annual Report on Form 10-K for the fiscal year ended December
31, 1993 (the "Magma 1993 10-K").

   6. Magma's Quarterly Reports on Form 10-Q for the quarters ended March 31,
1994, June 30, 1994 and September 30, 1994.

   7. Magma's Current Reports on Form 8-K dated March 31, 1993, as amended,
October 7, 1994, December 9, 1994 and January 11, 1995.

   In addition, all reports and other documents filed by the Company or Magma
pursuant to Section 13(a), 13(c), 14 or 15(d) of the Exchange Act subsequent
to the date hereof and prior to the termination of the Offering hereby shall
be deemed to be incorporated by reference herein and to be a part hereof from
the date of filing of such reports and documents. Any statement contained in
a document incorporated or deemed to be incorporated by reference herein
shall be deemed to be modified or superseded for purposes of this Prospectus
to the extent that a statement contained herein, or in any other subsequently
filed document that also is incorporated or deemed to be incorporated by
reference herein, modifies or supersedes such statement. Any such statement
so modified or superseded shall not be deemed, except as so modified or
superseded, to constitute a part of this Prospectus.

   The Company hereby undertakes to provide without charge to each person,
including any beneficial owner, to whom this Prospectus is delivered, upon
written or oral request from such person, a copy of any and all of the
documents incorporated by reference in this Prospectus (other than exhibits
to such documents unless such exhibits are specifically incorporated by
reference into the documents that this Prospectus incorporates). Written or
oral requests for such copies should be directed to California Energy
Company, Inc., 10831 Old Mill Road, Omaha, Nebraska 68154, Attention:
Secretary (telephone no. (402) 330-8900).

                                4

<PAGE>

         
<PAGE>

                              PROSPECTUS SUMMARY

   The following summary is qualified in its entirety by the more detailed
information contained elsewhere in this Prospectus and in the information
incorporated by reference herein. In this Prospectus, all references to the
"Company" shall mean California Energy Company, Inc. and its subsidiaries, as
it currently exists and, where the context indicates, following the
completion of the Magma Acquisition described herein. References to "Magma"
refer to Magma Power Company and its subsidiaries. Terms used but not defined
in this summary have the meanings ascribed to them elsewhere in this
Prospectus. Unless otherwise indicated, all information in this Prospectus
assumes that the over-allotment option is not exercised.

                                 The Company

   California Energy Company, Inc. was founded in 1971 to develop geothermal
power production facilities. The Company is primarily engaged in the
exploration for, and development and operation of, environmentally
responsible independent power production facilities worldwide utilizing
geothermal resources or other energy sources, such as hydroelectric, natural
gas, oil and coal.

   Following completion of the acquisition of Magma as described below (the
"Magma Acquisition"), the Company will be the largest independent geothermal
power producer in the world (on the basis of the Company's estimate of
aggregate megawatts ("MW") of electric generating capacity in operation and
under construction). The Company believes it will realize certain benefits
from the acquisition of Magma which will improve the Company's competitive
position, including:

   o  Expansion and enhancement of development efforts;

   o  Benefits of increased size;

   o  Opportunities for operational and administrative cost savings; and

   o  Diversification in sources of revenues and operations.

   Subsequent to the Magma Acquisition, the Company will have an aggregate
net ownership interest of 354 MW of electric generating capacity in power
production facilities in the United States having an aggregate net capacity
of 571 MW. All of these facilities will be managed and operated by the
Company and are principally located in Southern California. In addition to
the electricity sales revenue earned from its net ownership position in such
facilities, the Company receives significant fee and royalty income from
operating such plants and managing the production from the geothermal
resource for such facilities. The Company will have an aggregate net
ownership interest of 409 MW of electric generating capacity in three
geothermal power projects in the Republic of the Philippines ("Philippines"),
having an aggregate net capacity of 500 MW, which projects are financed and
under construction. The Company is also developing eight additional projects
with executed or awarded power sales contracts in the Philippines, the
Republic of Indonesia ("Indonesia") and the United States. The Company will
have an approximate net ownership interest of 935 MW in these development
projects representing an aggregate net capacity of 1,589 MW of additional
potential electric generating capacity.

   During the next several years, the Company intends to focus its
development efforts in the international marketplace due to the rapid growth
in power requirements in the developing world and the increasing competition
in the U.S. market. The Company is actively pursuing selected opportunities
in nations where power demand is high and the Company's geothermal resource
development and operating experience, project development expertise and
strategic relationships are expected to provide it with a competitive
advantage. The Company believes that opportunities to successfully develop,
construct, finance, own and operate international power projects are
increasing as several countries have initiated the privatization of their
power generation capacity and have solicited bids from private companies to
purchase existing generating facilities or to develop new capacity. Some of
these countries, such as the Philippines and Indonesia, have extensive
geothermal resources.

   On January 10, 1995, the Company acquired approximately 51% of the
outstanding shares of common stock of Magma Power Company (the "Magma Common
Stock") through a cash tender offer

                                5

<PAGE>

         
<PAGE>

(the "Magma Tender Offer") and the Company expects that it will complete the
Magma Acquisition by acquiring the approximately 49% of the outstanding
shares of Magma Common Stock not owned by the Company (the "Remaining Magma
Shares") through a merger (the "Merger"). Magma is engaged in independent
geothermal power operations and development activities similar to those of
the Company. Upon the effective time of the Merger, each outstanding share of
Magma Common Stock (other than shares of Magma Common Stock held by the
Company, CE Acquisition Company, Inc. ("CE Sub"), a wholly owned subsidiary
of the Company, or any other direct or indirect subsidiary of the Company and
shares of Magma Common Stock held in the treasury of Magma) will be converted
into the right to receive, at the Company's election, either cash or a
combination of cash and Common Stock. If the Company elects to pay the Merger
consideration with a combination of cash and Common Stock, the consideration
paid by the Company in the Magma Tender Offer and the Merger will consist, on
a blended basis, of $28.50 per share of Magma Common Stock in cash and $10.50
per share of Magma Common Stock in market value of Common Stock, based on the
average closing price of the Common Stock on the NYSE during the 15
consecutive trading days ending on the fifth business day prior to the
effective time of the Merger (the "Average Closing Price"); provided,
however, that for purposes of the calculating the Average Closing Price, if
the Average Closing Price exceeds $18.73, the Average Closing Price shall be
deemed to be $18.73, and if the Average Closing Price is less than $14.27,
the Average Closing Price shall be deemed to be $14.27. If the Company elects
to pay the Merger consideration solely in cash (the "All-Cash Option"), the
blended consideration paid by the Company in the Magma Tender Offer and the
Merger would be $38.75 per share of Magma Common Stock. The Company currently
intends to pay the Merger consideration solely in cash, funded in significant
part with the net proceeds of the Offering and the proceeds of the Direct
Sale, but such intention is subject to change if (i) the proposed
underwriters for the Offering determine that they cannot or will not proceed
with the Offering upon terms reasonably satisfactory to the Company or (ii)
market conditions would require the issuance of a greater number of shares of
Common Stock in order to fund the Merger pursuant to the All-Cash Option than
would be required to be issued in the Merger in connection with a combination
of cash and Common Stock consideration. If the Company changes its intention
and does not elect the All-Cash Option, it will promptly withdraw the
Registration Statement. The Company currently intends to elect the All-Cash
Option at the time the Price to Public and PKS for the Offering and the
Direct Sale is determined. The closing of the Offering will occur
concurrently with, and is conditioned upon, the closing of the Merger
pursuant to the All-Cash Option. See "THE MAGMA ACQUISITION."

   Peter Kiewit Sons', Inc. ("PKS") is an approximate 44% stockholder of the
Company (on a fully diluted basis). PKS is a large employee-owned
construction, mining and telecommunications company with approximately $2.2
billion in revenues in 1993. PKS is one of the largest construction companies
in North America and has been in the construction business since 1884. Since
the initial PKS investment in the Company in 1991 (which at that time
represented approximately 25% of the Common Stock on a fully diluted basis),
a new management team has been installed and the Company's net income has
increased from $12.0 million for the 12-month period ended December 31, 1990
to $29.4 million for the nine-month period ended September 30, 1994. PKS has
indicated an intention to acquire 1,500,000 of the shares of Common Stock
being offered directly by the Company pursuant to this Prospectus (the
"Direct Sale") at the Price to Public and PKS set forth on the cover of this
Prospectus, subject to receipt and review by PKS of a final Prospectus and
conditioned upon the closing of the Offering. Any closing of the Direct Sale
will occur concurrently with and is conditioned upon the closing of the
Offering. Assuming PKS purchases such shares, following completion of the
Offering and the Direct Sale, PKS will be an approximate 33.8% stockholder of
the Company (on a fully diluted basis).

                                6

<PAGE>

         
<PAGE>

                         THE OFFERING AND DIRECT SALE

Common Stock offered by the Company:

   
  U.S. Offering ...............  13,170,000 shares

  International Offering ......   2,000,000 shares

  Direct Sale .................   1,500,000 shares
                                 -----------------
    
 Total ........................  16,670,000 shares

Common Stock outstanding
after the Offering and
Direct Sale (1) ...............  48,899,584 shares

NYSE symbol ...................  CE

Use of Proceeds ...............  The net proceeds of the Offering and the
                                 proceeds of the Direct Sale, together with
                                 borrowings of up to $500 million under bank
                                 credit facilities described herein (the
                                 "Merger Facilities") and general corporate
                                 funds of the Company, will be used to
                                 complete the Magma Acquisition. The Company
                                 presently intends to acquire the Remaining
                                 Magma Shares pursuant to the All-Cash
                                 Option. The closing of the Offering will
                                 occur concurrently with, and is conditioned
                                 upon, the closing of the Merger pursuant to
                                 the All-Cash Option. Any closing of the
                                 Direct Sale will occur concurrently with and
                                 is conditioned upon the closing of the
                                 Offering. See "USE OF PROCEEDS" and "THE
                                 MAGMA ACQUISITION--Financing."
- ---------------
   (1) Based on the number of shares of Common Stock outstanding as of
      September 30, 1994. Does not include: (i) 9,435,229 shares of Common
      Stock reserved for issuance upon the exercise of presently outstanding
      stock options; (ii) 4,444,444 shares of Common Stock issuable upon the
      conversion of the Company's Convertible Subordinated Debentures due
      July 31, 2000 (the "Debentures"); and (iii) 3,393,197 shares of Common
      Stock issuable upon conversion of the 1,247 issued and outstanding
      shares of the Company's Series C Exchangeable Redeemable Preferred
      Stock, no par value per share (the "Series C Preferred Stock").

                                7

<PAGE>

         
<PAGE>

              SUMMARY PRO FORMA UNAUDITED FINANCIAL INFORMATION

   The summary Pro Forma Unaudited Financial Information of the Company set
forth in the table below is derived from the Pro Forma Unaudited Condensed
Combined Financial Data found elsewhere in this Prospectus. Such pro forma
financial information is based on the historical Consolidated Financial
Statements of the Company incorporated in this Prospectus by reference,
adjusted to give effect to the Magma Acquisition and the financing thereof,
including the Offering and the Direct Sale. The Pro Forma Condensed Combined
Statements of Earnings for the nine months ended September 30, 1994, and for
the year ended December 31, 1993, give effect to the Magma Acquisition as if
it had occurred at the beginning of each of the periods presented pursuant to
the All-Cash Option. The Pro Forma Condensed Combined Balance Sheet as of
September 30, 1994, gives effect to the Magma Acquisition as if it had
occurred on September 30, 1994. The Pro Forma Financial Information does not
purport to represent what the Company's results of operations or financial
position would actually have been or to project the Company's results of
operations or financial position for any future period.

   The summary pro forma financial information should be read in conjunction
with the Pro Forma Unaudited Condensed Combined Financial Data and the notes
thereto included elsewhere in this Prospectus.
   
<TABLE>
<CAPTION>
                                                    YEAR ENDED      NINE MONTHS ENDED
                                                 DECEMBER 31, 1993  SEPTEMBER 30, 1994
                                                -----------------  ------------------
                                                 (IN THOUSANDS, EXCEPT PER SHARE DATA)
<S>                                                <C>                <C>
STATEMENT OF EARNINGS DATA:
Total revenue .................................     $307,305           $278,478
Cost and expenses:
  Plant operations ............................       74,855             65,095
  General and administrative and other ........       24,572             19,518
  Royalties ...................................        8,274              7,898
  Depreciation and amortization ...............       57,607             46,753
  Interest expense (net of interest
    capitalized) ..............................       78,890             80,630
                                                -----------------  ------------------
Total costs and expenses ......................      244,198            219,894
                                                -----------------  ------------------
Income before income taxes ....................       63,107             58,584
Provision for income taxes ....................       15,138             15,771
                                                -----------------  ------------------
Income from continuing operations .............       47,969             42,813
Preferred dividends ...........................        4,630              3,711
                                                -----------------  ------------------
Income available to common stockholders  ......     $ 43,339           $ 39,102
                                                =================  ==================
Income per common and common equivalent share
Assuming no dilution ..........................     $   0.79           $   0.74
                                                =================  ==================
Assuming full dilution ........................     $   0.78           $   0.72
                                                =================  ==================
Weighted average common shares outstanding  ...       55,155             52,844
                                                =================  ==================
</TABLE>

<TABLE>
<CAPTION>
                                   AS OF SEPTEMBER
                                       30, 1994
                                 ------------------
                                    (IN THOUSANDS)
<S>                                  <C>
BALANCE SHEET DATA:
Cash and short term investments ..... $  139,747
Property and plant, net .............  1,257,828
Total assets ........................  2,255,853
Total indebtedness ..................  1,476,857
Redeemable preferred stock  .........     62,350
Total stockholders' equity  .........    455,313
</TABLE>
    
                                8

<PAGE>

         
<PAGE>

                                 RISK FACTORS

   Prospective purchasers of the Shares offered hereby should consider
carefully all of the information contained in this Prospectus, including the
following:

   DEVELOPMENT UNCERTAINTY.  The Company is actively seeking to develop,
construct, own and operate new power projects utilizing geothermal and other
technologies, both domestically and internationally, the completion of any of
which is subject to substantial risk. The Company has in development or under
construction projects representing several times the MW's of those currently
in operation. Development can require the Company to expend significant sums
for preliminary engineering, permitting, legal and other expenses in
preparation for competitive bids which the Company may not win or before it
can be determined whether a project is feasible, economically attractive or
capable of being financed. Successful development and construction is
contingent upon, among other things, negotiation on terms satisfactory to the
Company of engineering, construction, fuel supply and power sales contracts
with other project participants, receipt of required governmental permits and
consents and timely implementation of construction. Further, there can be no
assurance that the Company, which will continue to be substantially leveraged
upon completion of the Magma Acquisition, will obtain access to the
substantial debt and equity capital required to continue to develop and
construct electric power projects or to refinance projects. The future growth
of the Company is dependent, in large part, upon the demand for significant
amounts of additional electrical generating capacity and its ability to
obtain contracts to supply portions of this capacity. There can be no
assurance that development efforts on any particular project, or the
Company's efforts generally, will be successful.

   DEVELOPMENT UNCERTAINTY OUTSIDE THE UNITED STATES.   Upon completion of
the Magma Acquisition, the Company will have three projects under
construction outside the United States representing an aggregate net capacity
of 500 MW of electric generating capacity of which the Company's aggregate
net ownership interest is 409 MW and a number of projects under award outside
the United States. The financing and development of projects outside the
United States entail significant political and financial risks (including,
without limitation, uncertainties associated with first-time privatization
efforts in the countries involved, currency exchange rate fluctuations,
currency repatriation restrictions, political instability, civil unrest and
expropriation) and other structuring issues that have the potential to cause
substantial delays in respect of or material impairment of the value of the
project being developed, which the Company may not be capable of fully
insuring against. The uncertainty of the legal environment in certain foreign
countries in which the Company is developing and may develop or acquire
projects could make it more difficult for the Company to enforce its rights
under agreements relating to such projects. In addition, the laws and
regulations of certain countries may limit the ability of the Company to hold
a majority interest in some of the projects that it may develop or acquire.
The Company's international projects may, in certain cases, be terminated by
the applicable foreign governments.

   EXPLORATION, DEVELOPMENT AND OPERATION UNCERTAINTIES OF GEOTHERMAL ENERGY
RESOURCES.  Geothermal exploration, development and operations are subject to
uncertainties similar to those typically associated with oil and gas
exploration and development, including dry holes and uncontrolled releases.
Because of the geological complexities of geothermal reservoirs, the
geographic area and sustainable output of geothermal reservoirs can only be
estimated and cannot be definitively established. There is, accordingly, a
risk of an unexpected decline in the capacity of geothermal wells and a risk
of geothermal reservoirs not being sufficient for sustained generation of the
electrical power capacity desired. In addition, geothermal power production
poses unusual risks of seismic activity. Accordingly, there can be no
assurance that earthquake, property damage or business interruption insurance
will be adequate to cover all potential losses sustained in the event of
serious seismic disturbances or that such insurance will be available on
commercially reasonable terms.

   The success of a geothermal project depends on the quality of the
geothermal resource and operational factors relating to the extraction of the
geothermal fluids involved in such project. The quality

                                9

<PAGE>

         
<PAGE>

of a geothermal resource is affected by a number of factors, including the
size of the reservoir, the temperature and pressure of the geothermal fluids
in such reservoir, the depth and capacity of the production and injection
wells, the amount of dissolved solids and noncondensible gases contained in
such geothermal fluids, and the permeability of the subsurface rock
formations containing such geothermal resource, including the presence,
extent and location of fractures in such rocks. The quality of a geothermal
resource may decline as a result of a number of factors, including the
intrusion of lower-temperature fluid into the producing zone. An incorrect
estimate by the Company of the quality of geothermal resource, or a decline
in such quality, could have a material adverse effect on the Company's
results of operations.

   In addition, both the cost of operations and the operating performance of
geothermal power plants may be adversely affected by a variety of operating
factors. Production and injection wells can require frequent maintenance or
replacement. Corrosion caused by high-temperature and high-salinity
geothermal fluids may compel the replacement or repair of certain equipment,
vessels or pipelines. New production and injection wells may be required for
the maintenance of current operating levels, thereby requiring substantial
capital expenditures.

   COMPETITION.  The international power production market is characterized
by numerous strong and capable competitors, many of which have more extensive
and more diversified developmental or operating experience (including
international experience) and greater financial resources than the Company.
Many of these competitors also compete in the domestic market. Further, in
recent years, the domestic power production industry has been characterized
by strong and increasing competition with respect to the industry's efforts
to obtain new power sales agreements, which has contributed to a reduction in
prices offered by utilities. In this regard, many utilities often engage in
"competitive bid" solicitations to satisfy new capacity demands. In the
domestic market, the Energy Policy Act of 1992 is expected to increase
competition.

   PRESENT DEPENDENCE ON LARGE CUSTOMER.  The Company currently relies on
long-term power purchase "Standard Offer No. 4" contracts (each, an "SO4
Agreement") with a single customer, Southern California Edison Company
("SCE"), to generate substantially all of its operating revenues. Any
material failure by SCE to fulfill its contractual obligations under any of
such contracts is likely to have a material adverse effect on the Company's
results of operations.

   CONTRACT RISKS; EXPECTED NEGATIVE IMPACT OF AVOIDED COST PRICING. Each of
the Company's SO4 Agreements provides for both capacity payments and energy
payments for a term of between 20 and 30 years. During the first ten years of
the term of each SO4 Agreement, energy payments are based on a pre-set
schedule. Thereafter, while the basis for the capacity payment remains the
same, the required energy payment is SCE's then-current published avoided
cost of energy ("Avoided Cost of Energy"), as determined by the California
Public Utility Commission ("CPUC"). The initial ten-year period expires in
August 1997 for the Company's Navy I Project, March 1999 for its BLM Project
and January 2000 for its Navy II Project. Such ten-year period expires in
1996 with respect to one of Magma's Salton Sea Known Geothermal Resource Area
Projects (as hereinafter described), in 1999 for three of its Salton Sea
Known Geothermal Resource Area Projects and in 2000 for the remaining two
Salton Sea Known Geothermal Resource Area Projects that operate under SO4
Agreements.

   Estimates of SCE's future Avoided Cost of Energy vary substantially in any
given year. The Company cannot predict the likely level of Avoided Cost of
Energy prices under its SO4 Agreements with SCE at the expiration of the
fixed-price periods. SCE's Avoided Cost of Energy as determined by the CPUC
is currently substantially below the current energy prices under the
Company's respective SO4 Agreements and is expected to remain so. For
example, for September 1994, the time period-weighted average of SCE's
Avoided Cost of Energy was 2.2cents per kWh, compared to the time
period-weighted average September 1994 selling prices for energy of
approximately 10.9cents and 10.6cents per kWh, for the Company and Magma,
respectively. Thus, the revenues generated by each of the Company's
facilities operating under SO4 Agreements are likely to decline significantly
after the expiration of the fixed-price period.

                               10

<PAGE>

         
<PAGE>

   
   SUBSTANTIAL LEVERAGE. Following completion of the Magma Acquisition, the
Company will continue to be substantially leveraged. As of September 30,
1994, the Company's total consolidated indebtedness was $775.5 million, its
total consolidated assets were $1,087.1 million and its total stockholders'
equity was $179.7 million. As of such date, on a pro forma basis, after
giving effect to the completion of the Magma Acquisition, the Offering and
the Direct Sale, the Company's total consolidated indebtedness was $1,476.9
million, its total consolidated assets were $2,255.9 million and its total
stockholders' equity was $455.3 million. The Company's substantial level of
debt presents the risk that the Company might not generate sufficient cash to
service the Company's indebtedness or that its leveraged capital structure
could limit its ability to finance the acquisition and development of
additional projects, to compete effectively or to operate successfully under
adverse economic conditions. See "BUSINESS--Description of Projects,"
"CAPITALIZATION" and "PRO FORMA UNAUDITED CONDENSED COMBINED FINANCIAL DATA."
    

   CERTAIN RISKS OF THE MAGMA ACQUISITION. As a result of the Magma
Acquisition, the Company's total assets, total liabilities and total
resources will each approximately double. Such rapid expansion could divert
the resources and management of the Company and will require the integration
of Magma's operations with those of the Company. There can be no assurance
that the Company will be successful in managing such growth or that it will
be able to achieve any of the anticipated benefits of the Magma Acquisition.

   IMPACT OF ENVIRONMENTAL AND OTHER REGULATIONS. The Company is subject to a
number of environmental laws and regulations affecting many aspects of its
present and future operations, including the disposal of various forms of
waste, the construction or permitting of new facilities and the drilling and
operation of new wells. Such laws and regulations generally require the
Company to obtain and comply with a wide variety of licenses, permits and
other approvals. The Company also remains subject to a varied and complex
body of regulations that both public officials and private individuals may
seek to enforce. There can be no assurance that existing regulations will not
be revised or that new regulations will not be adopted or become applicable
to the Company which could have an adverse impact on its operations. The
implementation of regulatory changes imposing more comprehensive or stringent
requirements on the Company, which would result in increased compliance
costs, could have a material adverse effect on the Company's results of
operations. In addition, regulatory compliance for the construction of new
facilities is a costly and time-consuming process, and intricate and rapidly
changing environmental regulations may require major expenditures for
permitting and create the risk of expensive delays or material impairment of
project value if projects cannot function as planned due to changing
regulatory requirements or local opposition.

   SHARES OF COMMON STOCK ELIGIBLE FOR FUTURE SALE. Pursuant to the Company's
Amended and Restated 1986 Stock Option Plan (the "1986 Plan"), as of
September 30, 1994, the Company had outstanding various options to its
officers, directors and employees for the purchase of 3,371,075 shares of
Common Stock, of which all of the shares of Common Stock issuable upon
exercise of said options have been registered pursuant to registration
statements on Form S-8, and, as and when fully vested, are available for
immediate resale. Also as of September 30, 1994, there were additional
options outstanding to purchase 6,064,154 shares of Common Stock, 5,789,163
of which were granted to PKS. As of September 30, 1994, PKS has demand and
piggyback registration rights with respect to approximately 8,971,912 shares
of Common Stock (and any shares of Common Stock subsequently held by PKS,
including without limitation, any shares of Common Stock purchased in the
Direct Sale), all options to purchase shares of Common Stock (and the shares
issuable upon the exercise of such options) and 3,393,197 shares of Common
Stock issuable upon conversion of the 1,247 shares of the Series C Preferred
Stock held by PKS (or upon conversion of the Company's Exchangeable
Subordinated Debentures if issued upon the exchange of the Series C Preferred
Stock). In addition, 3,393,197 shares of Common Stock and 4,444,444 shares of
Common Stock have been reserved for issuance pursuant to the conversion of
the 1,247 shares of Series C Preferred Stock held by PKS and the Debentures,
respectively. Sales of substantial amounts of Common Stock or the
availability of Common Stock for sale, could have an adverse impact on the
market price of the Common Stock and on the Company's ability to raise
additional capital through the sale of Common Stock.

                               11

<PAGE>

         
<PAGE>

                               USE OF PROCEEDS

   
   The net proceeds (before expenses) to the Company of the Offering are
estimated to be approximately $250.2 million (approximately $287.7 million if
the over-allotment option is exercised in full). The proceeds to the Company
of the Direct Sale are estimated to be approximately $25.5 million.
Approximately $957.4 million will be required to complete the Magma
Acquisition. The net proceeds of the Offering and the proceeds of the Direct
Sale (approximately $275.7 million in the aggregate, assuming no exercise of
the over-allotment option), together with borrowings of $500 million under
the Merger Facilities described herein and general corporate funds of the
Company in the amount of approximately $181.7 million, will be used by the
Company to acquire the Remaining Magma Shares, to repay certain bank
borrowings incurred in connection with the Magma Tender Offer (the "Tender
Facility") and to pay fees and expenses related to the Magma Acquisition and
the Offering and Direct Sale. See "THE MAGMA ACQUISITION--Financing."
    

   Pursuant to the terms of the Merger Agreement, the Company has the right
to acquire the Remaining Magma Shares either for a combination of cash and
shares of Common Stock valued at approximately $39.00 per share of Magma
Common Stock or pursuant to the All-Cash Option. The Company presently
intends to acquire the Remaining Magma Shares pursuant to the All-Cash
Option. The closing of the Offering will occur concurrently with, and is
conditioned upon, the closing of the Merger pursuant to the All-Cash Option.
Any closing of the Direct Sale will occur concurrently with and is
conditioned upon the closing of the Offering.

                      MARKET PRICES OF THE COMMON STOCK

   The Common Stock is listed for quotation on the NYSE under the symbol
"CE". The following table sets forth the high and low last reported sale
prices of the Common Stock on the NYSE Composite Tape for the fiscal quarters
indicated.

<TABLE>
<CAPTION>
                                         HIGH      LOW
                                      --------  --------
<S>                                   <C>       <C>
Fiscal Year Ended December 31, 1993
 First Quarter ...................... $21.50    $16.50
 Second Quarter .....................  20.13     17.25
 Third Quarter ......................  18.38     16.00
 Fourth Quarter .....................  20.13     18.13
Fiscal Year Ended December 31, 1994
 First Quarter ...................... $19.25    $17.13
 Second Quarter .....................  18.13     16.00
 Third Quarter ......................  17.75     16.00
 Fourth Quarter .....................  17.13     15.25
   
Fiscal Year Ended December 31, 1995
 First Quarter (through February 15)  $18.88    $15.75
</TABLE>

   On February 15, 1995, the last reported sale price of the Common Stock on
the NYSE Composite Tape was $17.88.
    

                               12

<PAGE>

         
<PAGE>

                                CAPITALIZATION

   
   The following table sets forth the consolidated capitalizations of the
Company and Magma at September 30, 1994 and as adjusted to reflect borrowings
of $500 million under the Merger Facilities, consummation of the Magma
Acquisition and completion of the Offering and the Direct Sale at a price of
$17.00 per share of Common Stock, and the application of the proceeds (net
proceeds in the case of the Offering) therefrom. The following table should
be read in conjunction with the other pro forma financial information
contained in this Prospectus and the respective consolidated financial
statements and notes thereto of the Company and Magma incorporated by
reference herein.

<TABLE>
<CAPTION>
                                                                            PRO FORMA     PRO FORMA
                                                THE COMPANY     MAGMA      ADJUSTMENTS    COMBINED
                                               ------------  ----------  -------------  -----------
                                                      (IN THOUSANDS, EXCEPT PER SHARE AMOUNTS)
<S>                                            <C>           <C>         <C>            <C>
INDEBTEDNESS:
Construction loans ........................... $   21,079    $     --    $      --      $    21,079
Project loans ................................    233,080     188,969           --          422,049
Senior discount notes ........................    421,375          --           --          421,375
Convertible subordinated debenture ...........    100,000          --           --          100,000
Other long term liabilities ..................         --      12,354      500,000          512,354
                                               ------------  ----------  -------------  -----------
Total indebtedness ...........................    775,534     201,323      500,000        1,476,857
Redeemable preferred stock ...................     62,350          --            -           62,350
STOCKHOLDERS' EQUITY:
Preferred stock--Series A of no par value;
 authorized 2,000 shares .....................         --          --           --              --
Common stock of $0.0675 par value; authorized
 60,000 shares; outstanding 32,230
 shares--actual; 48,900 shares--pro forma
 combined (1) ................................      2,407          --          894            3,301
Magma common stock of $0.10 par value;
 authorized 30,000 shares; 24,043 issued  ....         --       2,401       (2,401)             --
Additional paid-in capital ...................    100,000     142,765       72,478          315,243
Unrealized gain from marketable securities  ..         --        (677)         677              --
Retained earnings ............................    136,769     250,797     (250,797)         136,769
Less treasury stock--3,420 shares at cost  ...    (59,516)         --       59,516              --
                                               ------------  ----------  -------------  -----------
Total stockholders' equity ...................    179,660     395,286     (119,633)         455,313
                                               ------------  ----------  -------------  -----------
Total capitalization ......................... $1,017,544    $596,609    $ 380,367       $1,994,520
                                               ============  ==========  =============  ===========
</TABLE>
    
- ---------------
   (1) On February 10, 1995, the stockholders of the Company approved a
       proposal to increase the number of authorized shares of Common Stock to
       80,000,000 shares. Issued shares (actual and as adjusted) do not
       include (i) 9,435,229 shares of Common Stock reserved for issuance upon
       the exercise of presently outstanding stock options, (ii) 4,444,444
       shares of Common Stock issuable upon the conversion of the Debentures
       and (iii) 3,393,197 shares of Common Stock issuable upon conversion of
       the 1,247 issued and outstanding shares of Series C Preferred Stock.

         See "PRO FORMA UNAUDITED CONDENSED COMBINED FINANCIAL DATA."

                               13

<PAGE>

         
<PAGE>

                            THE MAGMA ACQUISITION

   The Company is acquiring all of the outstanding equity interest in Magma
in a two-step transaction according to the terms of the Merger Agreement. On
January 10, 1995, the Company acquired approximately 51% of the outstanding
shares of Magma Common Stock in the Magma Tender Offer and the Company
expects that it will complete the Magma Acquisition by acquiring the
Remaining Magma Shares through the Merger. Magma is engaged in independent
geothermal power operations and development activities similar to those of
the Company. Upon the effective time of the Merger, each outstanding share of
Magma Common Stock (other than shares of Magma Common Stock held by the
Company, CE Sub or any other direct or indirect subsidiary of the Company and
shares of Magma Common Stock held in the treasury of Magma) will be converted
into the right to receive, at the Company's election, either cash or a
combination of cash and Common Stock. If the Company elects to pay the Merger
consideration with a combination of cash and Common Stock, the consideration
paid by the Company in the Magma Tender Offer and the Merger will consist, on
a blended basis, of $28.50 per share of Magma Common Stock in cash and $10.50
per share of Magma Common Stock in market value of Common Stock, based on the
Average Closing Price; provided, however, that for purposes of calculating
the Average Closing Price, if the Average Closing Price exceeds $18.73, the
Average Closing Price shall be deemed to be $18.73, and if the Average
Closing Price is less than $14.27, the Average Closing Price shall be deemed
to be $14.27. If the Company elects to pay the All-Cash Option, the blended
consideration paid by the Company in the Magma Tender Offer and the Merger
would be $38.75 per share of Magma Common Stock. The Company currently
intends to pay the Merger consideration solely in cash, funded in significant
part with the net proceeds of the Offering and the proceeds of the Direct
Sale, but such intention is subject to change if (i) the proposed
underwriters for the Offering determine that they cannot or will not proceed
with the Offering upon terms reasonably satisfactory to the Company, or (ii)
market conditions would require the issuance of a greater number of shares of
Common Stock in order to fund the Merger pursuant to the All-Cash Option than
would be required to be issued in the Merger with a combination of cash and
Common Stock consideration. If the Company changes its intention and does not
elect the All-Cash Option, it will promptly withdraw the Registration
Statement. The Company currently intends to elect the All-Cash Option at the
time the Price to Public and PKS for the Offering and the Direct Sale is
determined. The closing of the Offering will occur concurrently with, and is
conditioned upon, the closing of the Merger pursuant to the All-Cash Option.

CONDITIONS OF THE MERGER

   Consummation of the Merger remains subject to certain conditions,
including (i) the approval and adoption of the Merger and the Merger
Agreement by the requisite vote of Magma's stockholders, which approval and
adoption can be effected by the Company without the affirmative action of any
other Magma stockholder; (ii) the approval of the Company's stockholders of
the issuance of Common Stock in order to provide a portion of the
consideration for the Merger (if a combination of cash and shares of Common
Stock were used to acquire the Remaining Magma Shares); and (iii) that there
shall not be in effect (a) any judgment, decree or order issued by any
Federal, state or local court of competent jurisdiction, or (b) any statute,
rule or regulation enacted or promulgated by any Federal, state, local or
legislative, administrative or regulatory body of competent jurisdiction,
that in either of cases (a) or (b) prohibits the consummation of the Merger
or makes such consummation illegal. The waiting period under the
Hart-Scott-Rodino Antitrust Improvements Act of 1976, as amended, has
expired.

FINANCING

   A total of approximately $957 million will be required to complete the
Magma Acquisition. Pursuant to the Merger Facilities, Credit Suisse will
provide, on specified terms and subject to customary conditions, up to $500
million in secured bank financing. Such funds, together with the net proceeds
of the Offering, the proceeds of the Direct Sale and general corporate funds
of the Company, will be sufficient to complete the Magma Acquisition.

   The Merger Facilities are expected to be comprised of (i) a six year term
loan ("Term Loan A") in a principal amount of up to the difference between
$500 million and the principal amount of Term Loan

                               14

<PAGE>

         
<PAGE>

   
B and C (as defined below), expected to be amortized in semi-annual payments,
(ii) a seven year term loan ("Term Loan B") in a principal amount to be not
less than $75 million, expected to be amortized in semi-annual payments in
the seventh year of such Term Loan and (iii) an eight year term loan ("Term
Loan C") in a principal amount to be not less than $75 million, expected to
be amortized in semi-annual payments in the eighth year of such Term Loan.
Loans under the Merger Facilities will be made to the Company on a
non-recourse basis, and the Company will lend the proceeds of such loans to
Magma in exchange for a secured term note of Magma (the "Magma Note"). The
loans under the Merger Facilities are to be amortized from payments received
by the Company from Magma on the Magma Note which will be amortized from
internally generated funds of Magma. Loans under the Merger Facilities will
be secured by an assignment and pledge by the Company of the Magma Note and
100% of the capital stock of Magma. The Magma Note will be secured by an
assignment of certain unencumbered assets of Magma.

   Interest on loans under the Merger Facilities is expected to be payable at
spreads of 2.50% above LIBOR (adjusted for reserves) or 1.50% above the Base
Rate for Term Loan A, and 3.50% above LIBOR (adjusted for reserves) or 2.50%
above the Base Rate for Term Loans B and C. The Company may elect to have
loans bear interest based on either LIBOR or the Base Rate (as defined in the
Merger Facilities).
    

   The Merger Facilities will contain affirmative and negative covenants
customary for similar non-recourse credit facilities. Such covenants will
include a negative pledge of all stock and unencumbered assets of Magma; a
limitation on guaranties by Magma; a limitation on mergers and sales of
assets by Magma; a limitation on investments in other persons by Magma; a
prohibition on dividends and other payments by Magma to the Company unless
the proceeds are used to pay down the Merger Facilities; a prohibition on the
sale of ownership interests in Magma; a limitation on the incurrence of
additional debt by Magma; a requirement that the Company deliver each fiscal
quarter a certificate as to the absence of material adverse changes in the
Company or Magma which could reasonably be expected to materially affect the
ability of the Company to repay the Merger Facilities or the ability of the
lenders to realize on the collateral for the Merger Facilities; and a
restriction on a change in the nature of the business of the Company and
Magma.

   The Merger Facilities will also contain financial covenants and customary
events of default, including events of default based on breaches of certain
representations, warranties and covenants; cross defaults with respect to
certain debt of the Company and Magma; bankruptcy and similar events; the
failure to pay one or more final judgments aggregating more than a specified
threshold to be agreed upon; the failure to make a payment with respect to
the Merger Facilities when due; and the failure of the pledge agreement with
respect to the capital stock of Magma and the Magma Note to be in full force
and effect.

   Credit Suisse's commitment to provide the Merger Facilities is subject to
certain customary conditions, including without limitation (i) capital
investment in CE Sub in an amount and form satisfactory to Credit Suisse and
(ii) the absence of certain material adverse changes.

                               15

<PAGE>

         
<PAGE>

                                   BUSINESS
THE COMPANY

   California Energy Company, Inc. was founded in 1971 to develop geothermal
power production facilities. The Company is primarily engaged in the
exploration for, and development and operation of, environmentally
responsible independent power production facilities worldwide utilizing
geothermal resources or other energy sources, such as hydroelectric, natural
gas, oil and coal.

   Following completion of the Magma Acquisition, the Company will be the
largest independent geothermal power producer in the world (on the basis of
the Company's estimate of the aggregate MW of electric generating capacity in
operation and under construction). The Company will have an aggregate net
ownership interest of 354 MW of electric generating capacity in power
production facilities in the United States having an aggregate net capacity
of 571 MW. All of these facilities will be managed and operated by the
Company and are principally located in Southern California. In addition to
the electricity sales revenue earned from its net ownership position in such
facilities, the Company receives significant fee and royalty income from
operating such plants and managing the production from the geothermal
resource for such facilities. The Company will have an aggregate net
ownership interest of 409 MW of electric generating capacity in three
geothermal power projects in the Philippines, having an aggregate net
capacity of 500 MW, which projects are financed and under construction. The
Company is also developing eight additional projects with executed or awarded
power sales contracts in the Philippines, Indonesia and the United States.
The Company will have an approximate net ownership interest of 935 MW in
these development projects representing an aggregate net capacity of 1,589 MW
of additional potential electric generating capacity.

   PKS is an approximate 44% stockholder of the Company (on a fully diluted
basis). PKS is a large employee-owned construction, mining and
telecommunications company with approximately $2.2 billion in revenues in
1993. PKS is one of the largest construction companies in North America and
has been in the construction business since 1884. Since the initial PKS
investment in the Company in 1991 (which at that time represented
approximately 25% of the Common Stock on a fully diluted basis), a new
management team has been installed and the Company's net income has increased
from $12.0 million for the 12-month period ended December 31, 1990 to $29.4
million for the nine-month period ended September 30, 1994. PKS has indicated
an intention to acquire 1,500,000 of the shares of Common Stock being offered
in the Direct Sale at the Price to Public and PKS set forth on the cover of
this Prospectus, subject to receipt and review by PKS of a final Prospectus
and conditioned upon the closing of the Offering. Assuming PKS purchases such
shares, following the completion of the Offering and the Direct Sale, PKS
will be an approximate 33.8% stockholder of the Company (on a fully diluted
basis). Any closing of the Direct Sale will occur concurrently with and is
conditioned upon the closing of the Offering.

REASONS FOR THE MAGMA ACQUISITION

   The Company believes that Magma is an excellent strategic fit and that the
acquisition of Magma will create significant benefits, including:

 O EXPANSION AND ENHANCEMENT OF DEVELOPMENT EFFORTS

   Development of new opportunities, particularly internationally, is a key
component of the Company's strategy. Since 1990, the Company and Magma have
each pursued international development opportunities primarily in Southeast
Asia. By pursuing additional development opportunities rather than competing
with Magma for the same opportunities, the Company expects to expand its
development efforts to cover additional projects and thereby more effectively
capitalize on the numerous opportunities in the growing international
independent power market.

   Furthermore, the Company will have available to it technology of both
companies. The Company owns production technology compatible with the
relatively low mineral content of its wells at the Coso Project, and Magma
owns technology compatible with the high levels of mineral precipitates found
in the

                               16

<PAGE>

         
<PAGE>

geothermal resource at the Salton Sea Projects. The Company expects that
access to these technologies will enable it to compete for new power
development projects from geothermal reservoirs encompassing a wide range of
geothermal resource characteristics.

 O BENEFITS OF INCREASED SIZE

   The Company believes that size is an important factor in determining the
success of an independent power producer. This view is based on the Company's
belief that potential customers consider both the price of power and the
provider's capacity to fulfill its obligations as primary factors in the
selection of power suppliers. The expanded size and capabilities of the
combined companies is expected to further enhance the Company's reputation
and credibility with sovereign governments and state utility customers and
therefore enhance its ability to successfully compete for new projects.
Following the Magma Acquisition, the Company will have over $2 billion of
total assets and an aggregate net ownership interest of 1,698 MW in projects
in operation, under construction or in development, which projects have an
aggregate net generating capacity of 2,770 MW. The Company also believes that
the combination with Magma will create the opportunity to reduce the
Company's average cost per kWh by expanding its asset base, without
materially expanding its cost structure. This will allow the Company to be
more price competitive with other geothermal power producers and traditional
fossil fuel power plants, which the Company believes will be its primary
competition in the future.

 O OPPORTUNITIES FOR OPERATIONAL AND ADMINISTRATIVE COST SAVINGS

   Based in part on its experience in restructuring the operations of the
Company since 1991, management of the Company believes that it can achieve
meaningful cost savings upon the combination of Magma and the Company.
Through the implementation of the Company's existing organizational
structure, management policies and cost controls, the Company presently
expects that the cost of duplicate functions will be substantially eliminated
and that the productivity of its combined operating and administrative staff
will be significantly increased.

 O DIVERSIFICATION IN SOURCES OF REVENUE AND OPERATIONS

   The combination of the Company's and Magma's operations will increase the
Company's sources of revenue and increase the number of operating sites
(including projects under construction) from eight to 16. The Company
believes that the resulting diversification in sources of revenue and
operations can be expected to reduce the risk profile of the Company, thereby
enhancing its overall credit position and improving its access to capital in
relation to competitors with more concentrated sources of revenue and
operations.

GEOTHERMAL ENERGY

   Geothermal energy is a clean, renewable and generally sustainable energy
source that releases significantly lower levels of emissions than result from
energy generation based on the burning of fossil fuels. Geothermal energy is
derived from the natural heat of the earth when water comes sufficiently
close to hot molten rock to heat the water to temperatures of 400 degrees
Fahrenheit or more. The heated water then ascends naturally toward the
surface of the earth where it can be extracted by drilling geothermal wells.
The energy necessary to operate a geothermal power plant is typically
obtained from several such wells which are drilled using established
technology similar to that employed in the oil and gas industry.

                               17

<PAGE>

         
<PAGE>


                              GEOTHERMAL ENERGY

 #############################################################################

                                 IMAGE OMITTED:

                   [Schematic representing Geothermal Energy]

             (SEE ALSO "APPENDIX FOR GRAPHICS AND IMAGE MATERIAL"
                     AFTER BACK COVER PAGE OF PROSPECTUS.)

 #############################################################################


   Geothermal production wells are normally located within approximately one
to two miles of the power plant as geothermal fluids cannot be transported
economically over longer distances. From the well heads, the heated fluid
flows through pipelines to a series of separators where it is separated into
water, brine and steam. The steam is passed through a turbine which drives a
generator to generate electricity. Once the steam has passed through the
turbine, it is then cooled and condensed back into water which, along with
any brine, is returned to the geothermal reservoir via injection wells.
Geothermal plants in the United States are eligible to be qualifying
facilities ("QFs") under the Public Utility Regulatory Policies Act of 1978
("PURPA"), which provides for certain beneficial Federal regulatory
treatment. The geothermal reservoir is a renewable source of energy if
natural ground water sources and re-injection of extracted geothermal fluids
are adequate over the long term to replenish the geothermal reservoir after
the withdrawal of geothermal fluids.

   The generation of electric power from geothermal resources has certain
advantages when compared to other methods of electric power generation.
Geothermal energy facilities generate significantly less emissions than
fossil fuel power plants. Geothermal energy facilities typically have higher
capital costs but tend to have significantly lower variable costs than fossil
fuel based power plants. The utilization of geothermal power is preferred by
certain governments so as to minimize the import, or maximize the export, of
hydrocarbons. Geothermal power facilities also enjoy certain tax benefits in
the United States.

                               18

<PAGE>

         
<PAGE>

GEOTHERMAL RESOURCE--"RING OF FIRE"

   Geothermal energy is most prevalent where the different sections or plates
of the Earth's crust meet. Productive geothermal resources are found
throughout the Pacific Rim (the so-called "Ring of Fire"), including the
western United States, Latin America, Hawaii, Indonesia, the Philippines,
Malaysia and New Zealand. These areas are experiencing high rates of
population growth and increased demand for new electric generating capacity.

                    AREAS OF POTENTIAL GEOTHERMAL ACTIVITY

 #############################################################################

                                 IMAGE OMITTED:

        [Schematic representing Areas of Potential Geothermal Activity]

             (SEE ALSO "APPENDIX FOR GRAPHICS AND IMAGE MATERIAL"
                     AFTER BACK COVER PAGE OF PROSPECTUS.)

 #############################################################################


THE GLOBAL POWER MARKET

   The opportunity for independent power generation has expanded from a
United States market consisting of cogeneration and small power production
projects to a global competitive market for power generation. Many foreign
countries have initiated restructuring policies after the advent of the
independent power market in the United States.

   In the United States, the independent power industry expanded rapidly in
the 1980's, facilitated by the enactment of PURPA. PURPA was enacted to
encourage the production of electricity by non-utility companies as well as
to lessen reliance on imported fuels. According to the Utility Data
Institute, independent power producers were responsible for about 30,000 MW,
or 50%, of the U.S. electric generation capacity which has been placed in
service since 1988.

   As the size of the United States independent power market has increased,
available domestic power capacity and competition in the industry have also
significantly increased. Over the past decade, obtaining a power sales
contract from a U.S. utility has generally become increasingly difficult,
expensive and competitive. Many states now require power sales contracts to
be awarded through competitive bidding, which both increases the cost of
obtaining such contracts and decreases the chances of obtaining such
contracts as bids significantly outnumber awards in most competitive
solicitations. The federal Energy Policy Act of 1992 is expected to further
increase domestic competition. As a result of this increased

                               19

<PAGE>

         
<PAGE>

competition, it may be difficult to obtain a power sales agreement for a
proposed project in the United States, and the terms and conditions of any
such contract may be less favorable than those in prior agreements.

   Large amounts of new electric power generating capacity are required in
developing countries. The movement toward privatization in some developing
countries has created significant new markets outside the United States. In
1990, the World Bank estimated that developing countries will need
approximately 380,000 MW of new power generating capacity through the end of
the decade. The need for such rapid expansion has caused many countries to
select private power development as their only practical alternative and to
restructure their legislative and regulatory systems to facilitate such
development. The Company believes that this significant need for power has
created strong local support for private power projects in many foreign
countries and increased the availability of attractive long-term power
contracts. The Company intends to take advantage of opportunities in these
new markets and to develop, construct and acquire power generation projects
outside the United States.

STRATEGY

   Domestically, the Company is focusing on market opportunities in which it
believes it has relative competitive advantages due to its geotechnical,
project management and operating expertise. In addition, the Company expects
to continue diversification into other environmentally responsible sources of
energy primarily through selected acquisitions of partially developed or
existing power generating projects and contracts.

   The Company presently believes that the international independent power
market holds the majority of new opportunities for financially attractive
private power development in the next several years, in large part because
the demand for new generating capacity is growing more rapidly in emerging
nations than in the United States. In developing its international strategy,
the Company pursues development opportunities in countries which it believes
have an acceptable risk profile and where the Company's geothermal resource
development and operating experience, project development expertise or
strategic relationship with PKS or local partners are expected to provide it
with a competitive advantage. Subsequent to the Magma Acquisition, the
Company will have financed and have under construction three projects
representing an aggregate of 409 MW of net ownership of electric generating
capacity in the Philippines. In addition, the Company is currently pursuing a
number of other electric power project opportunities in countries including
the Philippines and Indonesia. These countries are ideally suited for the
Company to develop, finance and operate power projects successfully because
of their excellent population demographics, extensive geothermal resources
and stated commitments to the development of private power programs. The
Company's development efforts include both so-called "greenfield" development
as well as the acquisition of or participation in the joint venture
development of projects which are under development or already operating. In
greenfield development, the Company attempts to negotiate power sales
contracts for new generation capacity or engages in competitive bids in
response to government agency or utility requests for proposals for new
capacity.

   In pursuing its international strategy, the Company intends to own a
significant equity interest in, and to operate, the projects it develops or
acquires. In order to compete more effectively internationally, the Company's
strategy is to attempt to diversify its project portfolio, extend its future
equity funding capacity through joint ventures and utilize fixed-price,
turnkey construction contracts with contractors experienced in the
construction of power plants or other infrastructure facilities. The Company
also believes that it is important in foreign transactions to work with local
partners who are knowledgeable concerning local culture, politics and
commercial practices and who provide a visible local presence and local
project representation.

   With respect to emerging market projects, the Company's policy is to
attempt to minimize currency risks, including the devaluation of local
currencies versus the U.S. dollar, as well as the risk of availability of
hard currency convertibility. To date, all of the Company's executed power
contracts contain provisions which index the Company's returns to U.S.
dollars or provide for the payment of capacity payments in U.S. dollars. To
the extent possible, the Company attempts to secure "political risk"
insurance from the Overseas Private Insurance Corporation ("OPIC") or similar
multilateral agencies to limit its risk in

                               20

<PAGE>

         
<PAGE>

emerging market countries. In addition, the Company endeavors to involve the
World Bank, export credit agencies or multilateral funding sources in its
international project financings. The Company believes multilateral lending
agencies and foreign source financing and political risk insurance are
available for certain international private power projects, particularly
those utilizing indigenous fuel sources in renewable or otherwise
environmentally responsible generating facilities. The Company believes that
the involvement of these institutions will enhance an international project's
position in emerging market countries.

   The Company has an international joint venture agreement with PKS which
the Company believes enhances the Company's capabilities in foreign power
markets. The joint venture agreement is limited to international activities
and provides that if both the Company and PKS agree to participate in a
project, they will share all development costs equally. Each of the Company
and PKS will provide 50% of the equity required for financing a project
developed by the joint venture and the Company will operate and manage such
project. The agreement creates a joint development structure under which, on
a project by project basis, the Company will be the development manager,
managing partner and/or project operator, an equal equity participant with
PKS and a preferred participant in the construction consortium and PKS will
be an equal equity participant and the preferred turnkey construction
contractor. The joint venture agreement may be terminated by either party on
15 days written notice, provided that such termination cannot affect the
pre-existing contractual obligations of either party.

   In order to augment its technical capabilities, in 1993 the Company
acquired The Ben Holt Co. ("BHCO"), a California based engineering firm with
over 25 years of geothermal experience, specializing in feasibility studies,
process design, detailed engineering, procurement, construction and operation
of geothermal power plants, gathering systems and related facilities.

THE PROJECTS

   Upon completion of the Magma Acquisition, the Company will have net
ownership interests of an aggregate of (i) 354 MW in 13 projects in operation
representing an aggregate net capacity of 571 MW of electric generating
capacity, (ii) 409 MW in three projects under construction representing an
aggregate net capacity of 500 MW of electric generating capacity and (iii)
935 MW in eight projects in development stages with signed power sale
agreements or under award representing an aggregate net capacity of 1,589 MW
of electric generating capacity. The following table sets out the Company's
various projects in operation, under construction and in the latter stages of
development pursuant to signed power sales agreements or awarded mandates in
each case subsequent to the Magma Acquisition.

                               21

<PAGE>

         
<PAGE>


                            INTERNATIONAL PROJECTS

PROJECTS UNDER CONSTRUCTION
<TABLE>
<CAPTION>
                             FACILITY    FACILITY       NET                      PROJECTED
                              GROSS        NET       OWNERSHIP                   COMMERCIAL
                             CAPACITY    CAPACITY    INTEREST                    OPERATION      CONTRACT     CONTRACT     POWER
PROJECT                     (IN MW)(1)  (IN MW)(2)    (IN MW)      LOCATION         DATE      EXPIRATION(3)    TYPE    PURCHASER(4)
- -------------------------  ----------  ----------  -----------  -------------  ------------  -------------  ---------- ------------
<S>                        <C>         <C>         <C>          <C>            <C>           <C>            <C>         <C>
Upper Mahiao ............. 128         119         119          Leyte, the          1996          CO+10     Build, Own, PNOC- EDC
                                                                Philippines                                   Transfer  (GOP)(5)

Mahanagdong(6) ........... 180         165          74          Leyte, the          1997          CO+10     Build, Own, PNOC- EDC
                                                                Philippines                                   Transfer  (GOP)(5)

Malitbog-Phase I and II  . 231         216         216          Leyte, the       1996-1997        CO+10     Build, Own, PNOC- EDC
                           ---         ---         ---          Philippines                                   Transfer  (GOP)(5)

Total Under Construction   539         500         409
                           ---         ---         ---
</TABLE>

PROJECTS WITH SIGNED POWER SALES CONTRACTS OR AWARDED DEVELOPMENT RIGHTS

<TABLE>
<CAPTION>
                                         FACILITY
                             FACILITY      NET           NET                       PROJECTED
                              GROSS      CAPACITY     OWNERSHIP                    COMMERCIAL
                             CAPACITY      (IN        INTEREST                     OPERATION     CONTRACT   CONTRACT      POWER
PROJECT                     (IN MW)(7) (IN MW)(2)(7) (IN MW)(7)    LOCATION          DATE       EXPIRATION    TYPE     PURCHASER(4)
- --------------------------  ---------- ------------- ----------  -------------    ----------    ----------  --------   -----------
<S>                            <C>         <C>         <C>        <C>               <C>             <C>     <C>            <C>
Dieng(6) ....................   400         400         188        Central Java,     1997-1999       CO+30  Build, Own,     PLN
                                                                   Indonesia                                Transfer       (GOI)

Patuha(6) ...................   400         400         140        Western Java,     1997-1999       CO+30  Build, Own,     PLN
                                                                   Indonesia                                Transfer       (GOI)

Casecnan(8) .................   140         140          98        Luzon, the           1998         CO+20  Build, Own,     NIA
                                                                   Philippines                              Transfer       (GOP)(5)

Bali(8)(9) ..................   350         350         210        Bali,             1998-1999       CO+30  Build, Own,     PLN
                                                                   Indonesia                                Transfer       (GOI)

Alto Peak ...................    70          70          70        Leyte, the           1997         CO+10  Build, Own,     PNOC-
                              -----       -----       -----        Philippines                              Transfer        EDC
                                                                                                                           (GOP)(5)
Total Contracted/ Awarded     1,360       1,360         706
                              -----       -----       -----
Total International Projects  1,899       1,860       1,115
                              -----       -----       -----
<FN>
- ---------------
   (1) Actual MW may vary depending on operating and reservoir conditions and
       plant design. Facility Gross Capacity (in MW) for projects under
       construction represents gross electric output of the facility prior to
       subtraction of the parasitic load. Parasitic load is electrical output
       used by the facility and not made available for sale to utilities or
       other outside purchasers. Facility Gross Capacity (in MW) does not
       necessarily reflect electric output available for sale to utilities or
       other purchasers.
   (2) Facility Net Capacity (in MW) represents Facility Gross Capacity (in
       MW) less parasitic load.
   (3) Commercial Operation (CO).
   (4) Philippine National Oil Company-Energy Development Company (PNOC-EDC);
       Government of the Philippines (GOP); P.T. PLN (Persero) (PLN);
       Government of Indonesia (GOI); and Philippine National Irrigation
       Administration (NIA).
   (5) Government of the Philippines undertaking supports PNOC-EDC's and
       NIA's respective obligations.
   (6) PKS has elected to exercise its ownership option pursuant to its joint
       venture agreement with the Company.
   (7) Actual MW may vary depending on operating and reservoir conditions and
       final plant design. Facility Gross Capacity (in MW) for awarded
       projects equals maximum sales amount. Significant contingencies exist
       in respect of awards, including without limitation, the need to obtain
       financing, permits and licenses, and the completion of construction.
   (8) PKS has not indicated whether it intends to exercise its ownership
       option pursuant to its joint venture agreement with the Company and
       such net ownership interest remains subject to the PKS option. The
       Casecnan Project is a combined hydroelectric and irrigation project and
       will also sell water to NIA.
   (9) Geothermal resource development rights have been awarded and the power
       sales contract is subject to negotiation.
</TABLE>

                               22

<PAGE>

         
<PAGE>


                              DOMESTIC PROJECTS

PROJECTS IN OPERATION

<TABLE>
<CAPTION>
                                    FACILITY
                        FACILITY      NET          NET
                         GROSS      CAPACITY    OWNERSHIP                        DATE OF
                        CAPACITY      (IN       INTEREST                        COMMERCIAL    CONTRACT     CONTRACT      POWER
PROJECT(1)             (IN MW)(2)  MW)(3)(4)     (IN MW)        LOCATION        OPERATION    EXPIRATION      TYPE     PURCHASER(5)
- ---------------        ----------  ---------    ---------       --------        ----------   ----------    --------   ------------
<S>                   <C>         <C>            <C>         <C>                 <C>          <C>           <C>          <C>
Navy I ..............  96          88             41          China Lake, CA      8/1987       8/2011        SO4          SCE
BLM .................  96          88             42          China Lake, CA      3/1989       3/2019        SO4          SCE
Navy II .............  96          88             44          China Lake, CA      1/1990       1/2010        SO4          SCE
Vulcan ..............  41          34             17          Imperial Valley, CA 2/1986       2/2016        SO4          SCE
Hoch (Del Ranch)  ...  46          38             19          Imperial Valley, CA 1/1989      12/2018        SO4          SCE
Elmore ..............  46          38             19          Imperial Valley, CA 1/1989      12/2018        SO4          SCE
Leathers ............  46          38             19          Imperial Valley, CA 1/1990      12/2019        SO4          SCE
Salton Sea I ........  11           8              8          Imperial Valley, CA 7/1987       6/2017     Negotiated      SCE
Salton Sea II .......  20          18             18          Imperial Valley, CA 4/1990       4/2020        SO4          SCE
Salton Sea III ......  54          50             50          Imperial Valley, CA 2/1989       2/2019        SO4          SCE
Yuma ................  55          50             50          Yuma, AZ            5/1994       5/2024     Negotiated     SDG&E
Roosevelt Hot
 Springs ............  25          23             17          Milford, UT         5/1984       1/2021   Gathered Steam    UP&L
Desert Peak .........  10          10             10          Desert Peak, NV    12/1985      12/1995     Negotiated      SPPC
                      ----        ----           ----
Total in Operation    642         571            354
                      ----        ----           ----

</TABLE>

PROJECTS WITH SIGNED POWER SALES CONTRACTS OR AWARDED DEVELOPMENT RIGHTS

<TABLE>
<CAPTION>
                                    FACILITY
                        FACILITY      NET          NET                          PROJECTED
                         GROSS      CAPACITY    OWNERSHIP                       COMMERCIAL
                        CAPACITY      (IN       INTEREST                        OPERATION     CONTRACT     CONTRACT      POWER
PROJECT                (IN MW)(6)  MW)(3)(6)     (IN MW)        LOCATION          DATE       EXPIRATION      TYPE     PURCHASER(5)
- ---------------        ----------  ---------    ---------       --------        ----------   ----------    --------   ------------
<S>                     <C>         <C>          <C>        <C>                   <C>          <C>           <C>         <C>
BRPU(7) ..........       163         163          163        Imperial Valley, CA   TBD          TBD           FSO4        SCE
Fish Lake(8) .....        36          36           36        Imperial Valley, CA   1996         CO+30      Negotiated     SCE
Newberry .........        30          30           30        Bend, OR              1997         CO+50      Negotiated   BPA/EWEB
                       -----       -----        -----
Total Contracted/
 Awarded                 229         229          229
                       -----       -----        -----
Total Domestic
 Projects                871         800          583
                       -----       -----        -----
Total Projects         2,770       2,660        1,698
                       =====       =====        =====
<FN>
- ---------------
   (1) In addition to the electricity sales revenue earned from its net
       ownership position in such facilities, the Company receives significant
       fee and royalty income from operating such plants and managing the
       production from the geothermal resource for such facilities.
   (2) Actual MW may vary depending on operating and reservoir conditions and
       plant design. Facility Gross Capacity (in MW) for projects in operation
       represents gross electric output of the facility prior to subtraction
       of the parasitic load. Parasitic load is electrical output used by the
       facility and not made available for sale to utilities or other outside
       purchasers. Facility Gross Capacity (in MW) does not necessarily
       reflect electric output available for sale to utilities or other
       purchasers.
   (3) Facility Net Capacity (in MW) represents Facility Gross Capacity (in
       MW) less parasitic load.
   (4) With respect to the Vulcan, Hoch (Del Ranch), Elmore, Leathers, Salton
       Sea II and Salton Sea III Projects, this represents contract nameplate.
   (5) Southern California Edison Company (SCE); San Diego Gas & Electric
       Company (SDG&E); Utah Power & Light Company (UP&L); Sierra Pacific
       Power Company (SPPC); Bonneville Power Authority (BPA); and Eugene
       Water and Electric Board (EWEB).
   (6) Actual MW may vary depending on operating and reservoir conditions and
       final plant design. Facility Gross Capacity (in MW) for awarded
       projects equals maximum sales amount. Significant contingencies exist
       in respect of awards, including without limitation, the need to obtain
       financing, permits and licenses, and the completion of construction.
   (7) SCE is contesting the BRPU award; accordingly, no power sales contract
       is currently signed.
   (8) Combined Fish Lake and Salton Sea Expansion.
</TABLE>

                               23

<PAGE>

         
<PAGE>

   The following summary project descriptions are qualified in their entirety
by reference to the Company's 1993 10-K and the Magma 1993 10-K and the other
documents incorporated herein by reference.

                            INTERNATIONAL PROJECTS
PROJECTS IN CONSTRUCTION

   THE PHILIPPINES. The Company believes that increasing industrialization, a
rising standard of living and an expanding power distribution network has
significantly increased demand for electrical power in the Philippines.
According to the 1993 Power Development Program of the National Power
Corporation of the Philippines ("NAPOCOR"), demand for electricity exceeds
supply. NAPOCOR has also reported that its ability to sustain desired levels
of electric production from existing facilities has been limited due to
frequent breakdowns in many of its older electric generating plants. As a
result, the Philippines has experienced severe power outages, with Manila
suffering significant daily brownouts during much of 1993 and periodic
brownouts during 1994. Although the occurrence of brownouts has been recently
reduced, NAPOCOR has said that it still anticipates significant energy
shortages in the future.

   In 1993, the Philippine Congress, pursuant to Republic Act 7648, granted
President Ramos emergency powers to remedy the Philippine energy crisis,
including authority to (i) exempt power projects from public bidding
requirements, (ii) increase power rates and (iii) reorganize NAPOCOR. Until
1987, NAPOCOR had a monopoly on power generation and transmission in the
Philippines. In 1987, then President Aquino issued Executive Order No. 215,
which granted private companies the right to develop certain power generation
projects, such as those using indigenous energy sources, on a
"build-operate-transfer" or "build-transfer" basis. In 1990, the Philippine
Congress enacted Republic Act No. 6957, which authorized private development
of priority infra-structure projects on a "build-operate-transfer" and a
"build-transfer" basis. In addition, under that Act, such power projects were
made eligible for certain tax benefits, including exemption from Philippine
national income taxes for at least six years and exemption from, or
reimbursement for, customs duties and value added taxes on capital equipment
to be incorporated into such projects. In 1994, certain amendments to
Republic Act No. 6957 were approved by the Philippine Congress and signed
into law (R.A. 7718). Among other things, such amendments provide for the
financing of "unsolicited proposals" on a "build-operate-transfer" basis.

   In an effort to remedy the shortfall of electricity, the Philippines,
NAPOCOR and the Philippine National Oil Company-Energy Development Company
("PNOC-EDC") continue to jointly solicit bids for private power projects.
Among private power projects selected through this solicitation process were
the Upper Mahiao (the "Upper Mahiao Project"), Mahanagdong (the "Mahanagdong
Project"), Malitbog (the "Malitbog Project") and Alto Peak (the "Alto Peak
Project") geothermal power projects, as described below. Geothermal power has
been identified as a preferred alternative by the Philippine Government due
to the domestic availability and the minimal environmental effects of
geothermal power in comparison to other forms of power production. PNOC-EDC,
which is responsible for developing the Philippines' domestic energy sources,
has been successful in the exploration and development of geothermal
resources.

   The Company and Magma have financed and commenced construction of the
Upper Mahiao, Mahanagdong and Malitbog Projects, which have an aggregate net
capacity of 500 MW, of which the Company's aggregate net ownership interest
is 409 MW subsequent to the Magma Acquisition.

                               24

<PAGE>

         
<PAGE>


                            MAP OF THE PHILIPPINES

 #############################################################################

                                IMAGE OMITTED:

                [Schematic representing Map of The Philippines]

             (SEE ALSO "APPENDIX FOR GRAPHICS AND IMAGE MATERIAL"
                    AFTER BACK COVER PAGE OF PROSPECTUS.)

 #############################################################################

   Upper Mahiao. The Company has closed the financing and commenced
construction of the Upper Mahiao Project, a 128 gross MW geothermal project
to be located in the Greater Tongonan area of the island of Leyte in the
Philippines. The Upper Mahiao Project will be built, owned and operated by CE
Cebu Geothermal Power Company, Inc. ("CE Cebu"), a Philippine corporation
that is approximately 100% indirectly owned by the Company. It will sell 100%
of its capacity on a "take-or-pay" basis (described below) to PNOC-EDC, which
will in turn sell the power to NAPOCOR for distribution to the island of
Cebu, located about 40 miles west of Leyte.

   The Upper Mahiao Project will have a total project cost of approximately
$218 million, including interest during construction, project contingency
costs and a debt service reserve fund. A consortium of international banks
has committed to provide approximately $162 million in a project-financed
construction loan, supported by political risk insurance from the
Export-Import Bank of the United States ("ExIm Bank"). The largest portion of
the term loan for the project will also be provided by ExIm Bank. The
Company's equity contribution to the Upper Mahiao Project is $56 million.
Subject to the pledge of the project company's stock to the lenders, the
Company has arranged for political risk insurance of its equity investment
through OPIC. The financing is collateralized by all the assets of the
project.

   The Upper Mahiao Project is being constructed by Ormat, Inc. ("Ormat") and
its affiliates pursuant to supply and construction contracts (collectively,
the "Upper Mahiao EPC"), which, taken together, provide for the construction
of the plant on a fixed-price, date-certain, turnkey basis. Ormat is an
international manufacturer and construction contractor that builds binary
geothermal turbines. It has provided its equipment to several geothermal
power projects throughout the United States, the Philippines and
internationally. The Upper Mahiao EPC provides liquidated damage protection
of up to

                               25

<PAGE>

         
<PAGE>

30% of the Upper Mahiao EPC price. Ormat's performance under the Upper Mahiao
EPC is backed by a completion guaranty of Ormat, by letters of credit, and by
a limited guaranty of Ormat Industries, Ltd., an Israeli corporation and the
parent of Ormat, in each case for the benefit of the project lenders.

   Under the terms of an energy conversion agreement, executed on September
6, 1993 (the "Upper Mahiao ECA"), CE Cebu will build, own and operate the
Upper Mahiao Project during the approximately two-year construction period
and the ten-year cooperation period, after which ownership will be
transferred to PNOC-EDC at no cost.

   The Upper Mahiao Project will be located on land provided by PNOC-EDC at
no cost. It will take geothermal steam and fluid, also provided by PNOC-EDC
at no cost, and convert its thermal energy into electrical energy to be sold
to PNOC-EDC on a "take-or-pay" basis. Specifically, PNOC-EDC will be
obligated to pay for the electric capacity that is nominated each year by CE
Cebu, irrespective of whether PNOC-EDC is willing or able to accept delivery
of such capacity. PNOC-EDC will pay to CE Cebu a fee (the "Capacity Fee")
based on the plant capacity nominated to PNOC-EDC in any year (which, at the
plant's design capacity, is approximately 95% of total contract revenues) and
a fee (the "Energy Fee") based on the electricity actually delivered to
PNOC-EDC (approximately 5% of total contract revenues). The Capacity Fee
serves to recover the capital costs of the project, to recover fixed
operating costs and to cover return on investment. The Energy Fee is designed
to cover all variable operating and maintenance costs of the power plant.
Payments under the Upper Mahiao ECA will be denominated in U.S. dollars, or
computed in U.S. dollars and paid in Philippine pesos at the then-current
exchange rate, except for the Energy Fee, which will be used to pay
Philippine peso-denominated expenses. The convertibility of Philippine peso
receipts into U.S. dollars is insured by OPIC. Significant portions of the
Capacity Fee and Energy Fee will be indexed to U.S. and Philippine inflation
rates, respectively. PNOC-EDC's payment requirements, and its other
obligations under the Upper Mahiao ECA, are supported by the Government of
the Philippines through a performance undertaking.

   The payment of the Capacity Fee is not excused if PNOC-EDC fails to
deliver or remove the steam or fluids or fails to provide the transmission
facilities, even if its failure was caused by a force majeure event. In
addition, PNOC-EDC must continue to make Capacity Fee payments if there is a
force majeure event (e.g., war, nationalization, etc.) that affects the
operation of the Upper Mahiao Project and that is within the reasonable
control of PNOC-EDC or the government of the Philippines or any agency or
authority thereof. If CE Cebu fails to meet certain construction milestones
or the power plant fails to achieve 70% of its design capacity by the date
that is 120 days after the scheduled completion date (as that date may be
extended for force majeure and other reasons under the Upper Mahiao ECA), the
Upper Mahiao Project may, under certain circumstances, be deemed "abandoned,"
in which case the Upper Mahiao Project must be transferred to PNOC-EDC at no
cost, subject to any liens existing thereon.

   PNOC-EDC is obligated to purchase CE Cebu's interest in the facility under
certain circumstances, including (i) extended outages resulting from the
failure of PNOC-EDC to provide the required geothermal fluid, (ii) certain
material changes in policies or laws which adversely affect CE Cebu's
interest in the project, (iii) transmission failure, (iv) failure of PNOC-EDC
to make timely payments of amounts due under the Upper Mahiao ECA, (v)
privatization of PNOC-EDC or NAPOCOR, and (vi) certain other events. Prior to
completion of the Upper Mahiao Project, the buy-out price will be equal to
all costs incurred through the date of the buy-out, including all Upper
Mahiao Project debt, plus an additional rate of return on equity of ten
percent per annum. In a post-completion buy-out, the price will be the net
present value (at a discount rate based on the last published Commercial
Interest Reference Rate of the Organization for Economic Cooperation and
Development) of the total remaining amount of Capacity Fees over the
remaining term of the Upper Mahiao ECA.

   Mahanagdong. The Company has also closed the financing and commenced
construction of the Mahanagdong Project, a 180 gross MW geothermal project,
which will also be located on the island of Leyte. The Mahanagdong Project
will be built, owned and operated by CE Luzon Geothermal Power Company, Inc.
("CE Luzon"), a Philippine corporation that during construction is indirectly
owned 50% by the Company and 50% by PKS. Up to a 10% financial interest in CE
Luzon may be sold at completion

                               26

<PAGE>

         
<PAGE>

to another industrial company at the option of such company. The Mahanagdong
Project will sell 100% of its capacity on a similar basis as described above
for the Upper Mahiao Project to PNOC-EDC, which will in turn sell the power
to NAPOCOR for distribution to the island of Luzon.

   Mahanagdong has a total project cost of approximately $320 million,
including interest during construction, project contingency costs and a debt
service reserve fund. The capital structure consists of a project financing
construction and term loan of approximately $240 million provided by OPIC,
ExIm Bank and a consortium of international banks, and approximately $80
million in equity contributions. Political risk insurance from ExIm Bank has
been obtained for the commercial lenders. The Company's equity investment for
the Mahanagdong Project will be approximately $40 million. Subject to the
pledge of the project company's stock to the lenders, the Company has
arranged for political risk insurance on its equity investment through OPIC.
The financing is collateralized by all the assets of the project.

   The Mahanagdong Project is being constructed by a consortium (the "EPC
Consortium") of Kiewit Construction Group, Inc. ("KCG") and BHCO pursuant to
fixed-price, date-certain, turnkey supply and construction contracts
(collectively, the "Mahanagdong EPC"). The obligations of the EPC Consortium
under the Mahanagdong EPC are supported by a guaranty of KCG at an aggregate
amount equal to approximately 50% of the Mahanagdong EPC price. The
Mahanagdong EPC provides for maximum liability for liquidated damages of up
to $100.5 million and total liability of up to $201 million. KCG, a wholly
owned subsidiary of PKS, is the lead member of the EPC Consortium, with an
80% interest. KCG performs construction services for a wide range of public
and private customers in the U.S. and internationally. Construction projects
undertaken by KCG during 1993 included transportation projects, including
highways, bridges, airports and railroads, power facilities, buildings and
sewer and waste disposal systems, and water supply systems, utility
facilities, dams and reservoirs. KCG accounts for 80% of PKS's revenues,
contributing $1.7 billion in revenues in 1993. KCG has an extensive
background in power plant construction.

   BHCO will provide design and engineering services for the EPC Consortium,
holding a 20% interest. The Company has provided a guaranty of BHCO's
obligations under the Mahanagdong EPC Contract.

   The terms of an energy conversion agreement (the "Mahanagdong ECA"),
executed on September 18, 1993, are substantially similar to those of the
Upper Mahiao ECA. The Mahanagdong ECA provides for an approximately
three-year construction period and a ten-year cooperation period. At the end
of the cooperation period, the facility will be transferred to PNOC-EDC at no
cost. All of PNOC-EDC's obligations under the Mahanagdong ECA are supported
by the Government of the Philippines through a performance undertaking. The
capacity fees are expected to be approximately 97% of total revenues at the
design capacity levels and the energy fees are expected to be approximately
3% of such total revenues.

   Malitbog. In December 1994, Magma closed the financing and commenced
construction of the Malitbog Project, a 231 gross MW geothermal project,
which will also be located on the island of Leyte. The Malitbog Project will
be built, owned and operated by Visayas Geothermal Power Company ("VGPC"), a
Philippine general partnership that is wholly owned, indirectly, by Magma.
VGPC will sell 100% of its capacity on substantially the same basis as
described above for the Upper Mahiao Project to PNOC-EDC, which will in turn
sell the power to NAPOCOR.

   The Malitbog Project has a total project cost of approximately $280
million, including interest during construction and project contingency
costs. A consortium of international banks and OPIC have provided a total of
$210 million of construction and term loan facilities, the $135 million
international bank portion of which is supported by political risk insurance
from OPIC. Magma's equity contribution to VGPC was $70 million. Magma's
equity participation is covered by political risk insurance from OPIC.

   The Malitbog Project will be constructed by Sumitomo Corporation
("Sumitomo") pursuant to a fixed-price, date-certain, turnkey supply and
construction contract (the "Malitbog EPC"). The Malitbog EPC provides that
certain liquidated damages will be paid by Sumitomo for failure to meet
certain scheduled performance test dates, including the payment of any
liquidated damages or penalties required to be paid by VGPC to PNOC-EDC under
an energy conversion agreement (the "Malitbog ECA")

                               27

<PAGE>

         
<PAGE>

(subject to limitations on the total amount of liquidated damages payable by
Sumitomo). The Malitbog EPC also provides for the payment of certain
liquidated damages on a per unit basis if upon completion of the facility
tests do not demonstrate such unit's ability to operate at a net generating
capacity of at least 74.1 MW. The liquidated damages for each generating unit
are capped at 13 1/3 % of the total Malitbog EPC price. Pursuant to a
reimbursement undertaking, Magma has agreed to reimburse Sumitomo for draws,
if any, by PNOC-EDC on the construction bond provided by Sumitomo on behalf
of Magma in excess of the liquidated damage amounts provided in the Malitbog
EPC.

   Sumitomo is one of the principal trading and investment companies in
Japan, and has built power plants around the world, often on a turnkey basis.
As of October 20, 1994, Sumitomo had a credit rating of "Aa3" from Moody's
Investors Service, Inc. ("Moody's"). The Malitbog EPC requires Sumitomo to
provide engineering, procurement, construction, start-up and testing services
with respect to the facility.

   Construction of the facility has begun, with commercial operation of unit
1 scheduled to commence in July 1996, and commercial operation of unit 2 and
unit 3 scheduled to commence in July 1997.

   The terms of the Malitbog ECA, executed on September 10, 1993, are
substantially similar to those of the Upper Mahiao ECA. The Malitbog ECA
provides for a two-phase construction period, of three identical 77 gross MW.
The cooperation period is ten years from the completion of unit 3. At the end
of the cooperation period, the facility will be transferred to PNOC-EDC at no
cost. All of PNOC-EDC's obligations under the Malitbog ECA are supported by
the Government of the Philippines through a performance undertaking. The
capacity fees are 100% of total revenues and there is no energy fee.

PROJECTS IN DEVELOPMENT

   Casecnan. In November 1994, the Company signed a "Project Agreement" with
the Philippine National Irrigation Administration ("NIA") to develop an
estimated $320 million combined irrigation and hydroelectric power generation
project (the "Casecnan Multipurpose Project"). Such Project will deliver
excess water from the Casecnan and Denip (Cagayan) watershed in Northern
Luzon to the Pampanga watershed and the Pantabangan Reservoir for irrigation
use in the Central Luzon Valley. The Casecnan Multipurpose Project, which has
satisfied the requirements for an unsolicited proposal under the amended BOT
law, will also provide 140 MW of net electric generation capacity to the
Luzon grid.

   The project agreement is structured as a build, operate and transfer
agreement under which NIA will supply the water for the Project and provides
for a 20-year cooperation period with significant "take-or-pay" obligations
for water and electricity. At the end of the 20-year cooperation period, the
Casecnan Multipurpose Project will be transferred to NIA at no cost. The
Company anticipates commencing construction in 1995.

   Completion of such Project remains subject to a number of significant
uncertainties, including arranging financing, obtaining certain required
permits and licenses and completing construction, none of which can be
assured.

   Alto Peak. The Alto Peak Project is a smaller geothermal project in the
same general area of Leyte as the Upper Mahiao, Mahanagdong and Malitbog
Projects. Magma and PNOC-EDC have executed a 70 MW net Energy Conversion
Agreement, dated May 7, 1994. The general terms and conditions are similar to
the Malitbog ECA. However, the plant design has not been initiated as
PNOC-EDC has not finalized the steam conditions (pressure, composition and
ph), as PNOC-EDC is still drilling and testing the geothermal wells that will
supply steam to such project. Consequently, Magma has not commenced financing
arrangements for the Alto Peak Project.

   INDONESIA.  Indonesia, which has the world's fourth largest population,
has experienced rapid growth in electricity demand. The Company believes that
load growth has exceeded 13% since 1980. Furthermore, the Company believes
that rapid expansion in industrial growth has created a backlog of
unconnected industrial users in excess of 4,000 MW. In its sixth five-year
plan, the Indonesian government has called for the addition of 12,000 MW of
additional generating capacity by 1999. The long range plan calls for an
additional 15,000 MW to be added by the year 2004. The plans call for
approximately 75% of this capacity to be added by independent power
producers. Although Indonesia is a member of OPEC

                               28

<PAGE>

         
<PAGE>

and is also the world's largest exporter of liquified natural gas, the
Government of Indonesia has announced that it wishes to maintain sufficient
amounts of oil for export, which will require a shift to coal fired
generation and the use of other energy sources, such as geothermal.

   It is estimated that Indonesia has sufficient geothermal steam potential
to generate 16,000 MW, centered in the Java and Sumatra areas (the two most
populous of the 13,000 islands in Indonesia). To date, less than 150 MW of
geothermal facilities have been commissioned, as the Government of Indonesia
was not encouraging the development of geothermal energy.

   The Indonesian state-owned utility, has recently been converted to a
limited liability company, P.T. PLN (Persero) ("PLN"), as a first step toward
the privatization of its two largest generating subsidiaries. The main
objective of Indonesia's electric energy policy has been to secure a
continuity of supply at reasonable rates for households (more than 50% of
which have been reported to have no power) and to minimize the utilization of
hydrocarbons. Rural electrification will remain an important component of the
energy policy as PLN is targeting the addition of 2 million customers a year.

   Indonesia is rated "Baa3" by Moody's and "BBB-" by Standard & Poor's
Ratings Group ("S&P"). The Company believes that Indonesia represents an
attractive development opportunity, as it combines growing power needs with
ample geothermal resources and creditworthy contract parties.

                  MAP OF INDONESIA AND NEIGHBORING COUNTRIES

 #############################################################################

                                IMAGE OMITTED:

      [Schematic representing Map of Indonesia and Neighboring Countries]

             (SEE ALSO "APPENDIX FOR GRAPHICS AND IMAGE MATERIAL"
                    AFTER BACK COVER PAGE OF PROSPECTUS.)

 #############################################################################


                               29

<PAGE>

         
<PAGE>

   The following is a summary description of certain information concerning
the Company's projects in Indonesia. Since these projects are still in
development, however, there can be no assurance that this information will
not change materially over time. In addition, there can be no assurance that
development efforts on any particular project, or the Company's efforts
generally, will be successful.

   Dieng. On December 2, 1994, a subsidiary of the Company executed a joint
operation contract (the "Dieng JOC") for the development of the geothermal
steam field and geothermal power facilities at the Dieng geothermal field,
located in Central Java (the "Dieng Project") with Perusahaan Pertambangan
Minyak Dan Gas Bumi Negara ("Pertamina"), the Indonesian national oil
company, and executed a "take-or-pay" energy sales contract (the "Dieng ESC")
with both Pertamina and PLN, the Indonesian national electric utility.

   A subsidiary of the Company has entered into a joint development agreement
with P.T. Himpurna Enersindo Abadi ("P.T. HEA"), its Indonesian partner,
which is a subsidiary of Himpurna, an association of Indonesian military
veterans, whereby the Company and P.T. HEA have agreed to work together on an
exclusive basis to develop the Dieng Project (the "Dieng Joint Venture"). The
Dieng Joint Venture is structured with subsidiaries of the Company having a
minimum 47% interest, subsidiaries of PKS having the option to take a 47%
interest and P.T. HEA having a 6% interest in the Dieng Project.

   Pursuant to the Dieng JOC and ESC, Pertamina will grant to the Dieng Joint
Venture the geothermal field and the wells and other facilities presently
located thereon and the Dieng Joint Venture will build, own and operate power
production units with an aggregate capacity of up to 400 MW. The Dieng Joint
Venture will accept the field operation responsibility for developing and
supplying the geothermal steam and fluids required to operate the plants. The
Dieng JOC is structured as a build own transfer agreement and will expire
(subject to extension by mutual agreement) on the date which is the later of
(i) 42 years following effectiveness of the Dieng JOC and (ii) 30 years
following the date of commencement of commercial generation of the final unit
completed. Upon the expiration of the proposed Dieng JOC, all facilities will
be transferred to Pertamina at no cost. The Dieng Joint Venture is required
to pay Pertamina a production allowance equal to three percent of the Dieng
Joint Venture's net operating income from the Dieng Project, plus a further
amount based upon the negotiated value of existing Pertamina geothermal
production facilities that the Company expects will be made available by
Pertamina.

   Pursuant to the Dieng ESC, PLN agreed to purchase and pay for all of the
Project's capacity and energy output on a "take or pay" basis regardless of
PLN's ability to accept such energy made available from the Dieng Project for
a term equal to that of the Dieng JOC. The price paid for electricity
includes a base energy price per kWh multiplied by the number of kWhs the
plants deliver or are "capable of delivering," whichever is greater. Energy
price payments are also subject to adjustment for inflation. PLN will also
pay a capacity payment based on plant capacity. All such payments are payable
in U.S. dollars.

   The Company presently intends to begin well testing by the second quarter
of 1995 and to commence construction of an initial 55 MW unit in the 4th
quarter of 1995, and then to proceed on a modular basis with construction of
three additional units to follow shortly thereafter, resulting in an
aggregate first phase net capacity at this site of 220 MW. The Company
estimates that the total project cost of these units will be approximately
$450 million. The next phase is expected to expand the total capacity to 400
MW. The cost of the full Dieng Project is estimated to approximate $1
billion. The Company anticipates a consortium consisting of KCG and BHCO will
submit a proposal for the design and construction of the Dieng Project, and
that the Company, through a subsidiary, will be responsible for operating and
managing the Dieng Project.

   The Dieng field has been explored domestically for over 20 years and BHCO
has been active in the area for more than five years. Pertamina has drilled a
total of 27 wells to date. The Company has a significant amount of data,
which it believes to be reliable as to the production capacity of the field.
However, a number of significant steps, both financial and operational, must
be completed before the Dieng Project can proceed further. These steps, none
of which can be assured, include obtaining required regulatory permits and
approvals, completing the well testing, entering into a construction
agreement and other project contracts, and arranging financing.

                               30

<PAGE>

         
<PAGE>

   Patuha. The Company is also developing a geothermal power plant with
respect to the Patuha geothermal field in Java, Indonesia (the "Patuha
Project"). The Company has entered into a joint venture (the "Patuha Joint
Venture") for Patuha with P.T. Enerindo Supra Abadi ("P.T. ESA"), an
Indonesian company. P.T. ESA is an affiliate of the Bukaka Group, which has
extensive experience in general construction, fabrication and electrical
transmission construction in Indonesia. In exchange for project development
services, P.T. ESA will receive a 10% equity interest in the Patuha Project
with an option to acquire an additional 20% interest for cash upon the
satisfaction of certain conditions. Subject to the exercise of that option,
subsidiaries of the Company will have a 45% interest and subsidiaries of PKS
will have the option to take a 45% interest in the Patuha Project.

   On December 2, 1994, the Patuha Joint Venture executed both a joint
operation contract and an energy sales contract, each of which currently
contains terms substantially similar to those described above for the Dieng
Project. The Patuha Joint Venture intends to proceed on a modular basis
similar to the Dieng Project, with an aggregate capacity of up to 400 MW. The
Company estimates that the total cost will be approximately $1 billion. The
Company presently intends to begin well testing and further exploration in
the fourth quarter of 1995 with construction of the first unit expected to
begin by 1996.

   The Patuha Project remains subject to a number of significant
uncertainties, as described above in connection with the Dieng Project, and
there can be no assurance that the Patuha Project will proceed or reach
commercial operation.

   Bali.  The Company and PT Panutan Group, an Indonesian consortium of
energy, oil, gas and mining companies, have formed a joint venture to pursue
the development of geothermal resources in Bali (the "Bali Project") and to
obtain a power sales contract from PLN.

   The Company presently intends to develop the Bali Project and other
possible projects in Indonesia using a structure similar to that contemplated
for the Dieng Project.

   The Bali Project remains subject to a number of significant uncertainties,
as described above for the Dieng Project, and there can be no assurance that
the Company will pursue the Bali Project or that it will proceed or reach
commercial operation.

                               31

<PAGE>

         
<PAGE>

                              DOMESTIC PROJECTS

                       MAP OF THE WESTERN UNITED STATES

 #############################################################################

                                IMAGE OMITTED:

           [Schematic representing Map of the Western United States]

             (SEE ALSO "APPENDIX FOR GRAPHICS AND IMAGE MATERIAL"
                    AFTER BACK COVER PAGE OF PROSPECTUS.)

 #############################################################################


PROJECTS IN OPERATION

   The Coso Project. In 1979, the Company entered into a 30-year contract
(the "Navy Contract") with the United States Department of the Navy (the
"Navy") to develop geothermal power facilities located on approximately 5,000
acres of the Naval Air Weapons Station at China Lake, California (150 miles
northeast of Los Angeles). In 1985, the Company entered into a 30-year lease
(the "BLM Lease") with the United States Bureau of Land Management ("BLM")
for approximately 19,000 acres of land adjacent to the land covered by the
Navy Contract. The Navy Contract and the BLM Lease provide for certain
royalty payments as a percentage of gross revenue and certain other formulas.
The Company formed three joint ventures (the "Coso Joint Ventures") with one
primary joint venture partner, Caithness Corporation ("Caithness"), to
develop and construct the three facilities which comprise the Navy I project
(the "Navy I Project"), the BLM project (the "BLM Project") and the Navy II
project (the "Navy II Project") (collectively the "Coso Project").

   The Coso Joint Ventures are as follows: (i) Coso Finance Partners, which
owns the Navy I Project (the "Navy I Partnership"), (ii) Coso Energy
Developers, which owns the BLM Project (the "BLM Partnership") and (iii) Coso
Power Developers, which owns the Navy II Project (the "Navy II Partnership"
and, together with the Navy I Partnership and the BLM Partnership, the "Coso
Partner-

                               32

<PAGE>

         
<PAGE>

ships"). The Company holds ownership interests of approximately 46% in the
Navy I Partnership; approximately 48% in the BLM Partnership, after payout to
the Company and Caithness; and 50% in the Navy II Partnership. The Company
consolidates its respective share of the operating results of the Coso
Partnerships into its financial statements. In addition, the Company
indirectly holds rights to certain cash flows from its partners in the BLM
Project, and, to a lesser extent, the Navy I Project and Navy II Project.
Each of the Coso Joint Ventures is managed by a management committee which
consists of two representatives from the Company and two representatives from
the Company's partners. The Company operates the Coso Project, for which it
receives fees from the Coso Partnerships.

   The Coso Project sells all electricity generated by the respective plants
pursuant to three long-term SO4 Agreements between the Navy I Partnership,
the BLM Partnership, and the Navy II Partnership, respectively, and SCE.
These SO4 Agreements provide for capacity payments, capacity bonus payments
and energy payments. SCE makes fixed annual capacity payments to the Coso
Partnerships, and to the extent that capacity factors exceed certain
benchmarks is required to make capacity bonus payments. The price for
capacity and capacity bonus payments is fixed for the life of the SO4
Agreements. Energy is sold at increasing fixed rates for the first ten years
of each contract and thereafter at SCE's Avoided Cost of Energy. The fixed
price periods of the SO4 Agreements extend until August 1997, March 1999 and
January 2000 for each of the Navy I, BLM and Navy II Partnerships,
respectively, at rates ranging from 11.0cents per kWh in 1994 to 14.6cents
per kWh in 2000. The Company's share of the revenues received by the Coso
Partnerships for 1993 and the first nine months of 1994 was $124.7 million
and $105.2 million, respectively.

   The physical facilities used for geothermal energy production are
substantially the same at the Navy I, BLM and Navy II Projects.

   The Navy I Project. The geothermal resource for the Navy I Project
currently is produced from approximately 32 wells. The Navy I Project
consists of three turbine generators, each with approximately 32 MW of
electrical generating capacity. The Navy I Project has an aggregate gross
electrical generating capacity of approximately 96 MW. Based on an assumed
net capacity of 80 MW, the Navy I Project operated at an average operating
capacity factor of 99.8% in 1992, 111.2% in 1993 and 114.6% in the first nine
months of 1994.

   The BLM Project. The BLM Project's geothermal resource currently is
produced from approximately 20 wells. The BLM Project consists of three
turbine generators. Two of these turbine generators are located at the BLM
East site in a dual flash system, each with a nameplate capacity of 29 MW;
and one is located at the BLM West site in a single flash system, with a
nameplate capacity of 29 MW. The BLM Project has an aggregate gross
electrical generating capacity of approximately 96 MW. Based on an assumed
capacity of 80 MW, the BLM Project operated at an average operating capacity
factor of 87.2% in 1992, 98.1% in 1993, and 98.5% in the first nine months of
1994.

   The Navy II Project.  The geothermal resource for the Navy II Project
currently is produced from approximately 25 wells. The Navy II Project
consists of three individual turbine generators, each with approximately 32
MW of electrical generating capacity. The Navy II Project has an aggregate
gross electrical capacity of approximately 96 MW. Based on an assumed net
capacity of 80 MW, the Navy II Project operated at an average operating
capacity factor of 98.1% in 1992, 102.6% in 1993, and 103.5% in the first
nine months of 1994.

   In December 1992, the Coso Joint Ventures refinanced the existing bank
debt on the Coso Project with the proceeds of the sale of approximately $560
million in non-recourse senior secured notes (the "Notes") in a private
placement pursuant to Rule 144A under the Securities Act. The Notes were
issued by Coso Funding Corp. ("Coso Funding"), a corporation owned by the
Coso Joint Ventures and formed exclusively for the purpose of issuing the
Notes. Coso Funding lent the Coso Joint Ventures substantially all of the net
proceeds of the sale of the Notes. At the time of their issuance, the Notes
were rated "Baa3" by Moody's, "BBB-" by S&P and "BBB" by Duff & Phelps Credit
Rating Co., all investment grade ratings. The outstanding balance of the
Notes on September 30, 1994 was $483.5 million with a remaining average life
of 3.5 years, and the average interest rate on the Notes for the nine months
ending on the same date was 8.07%. The obligations of each Coso Partnership
under the loans from Coso Funding are

                               33

<PAGE>

         
<PAGE>

non-recourse to the Company. Coso Funding may look solely to each Coso
Partnership's pledged assets for satisfaction of such Coso Partnership's
loan. In addition, the loans are cross-collateralized by certain support
loans only to the extent of the other Coso Joint Ventures' available cash
flow and, under certain circumstances, the debt service reserve funds, and
not as to other assets.

   Salton Sea Known Geothermal Resource Area Projects. Magma acquired three
geothermal power plants which comprise the Salton Sea I project (the "Salton
Sea I Project"), the Salton Sea II project (the "Salton Sea II Project") and
the Salton Sea III project (the "Salton Sea III Project") (collectively, the
"Salton Sea Projects") and all related wellfield, land and other related
assets in March 1993 from Union Oil Company of California. Each of the
Vulcan, Hoch (Del Ranch), Elmore and Leathers projects (the "Vulcan Project,"
the "Hoch (Del Ranch) Project," the "Elmore Project" and the "Leathers
Project," respectively, and collectively, the "Partnership Projects") is
owned by an equal partnership (the "Vulcan Partnership," the "Del Ranch
Parthership," the "Elmore Partnership" and the "Leathers Partnership,"
respectively, and collectively, the "Partnerships") between Magma and a
subsidiary of Mission Energy, a wholly owned subsidiary of SCE. In the case
of the Vulcan Project, the Vulcan Partnership owns certain geothermal
resources supplying the Vulcan Project plant. In the case of the other three
Partnership Project plants, Magma owns the geothermal resources and receives
royalty payments from the Del Ranch, Elmore and Leathers Partnerships. In the
first nine months of 1994, such royalties together with the royalties from
the East Mesa Plant and Mammoth Plants (as defined below) totaled $15.1
million. Magma's share of the aggregate electricity revenues received by the
Salton Sea Projects and the Partnerships for the first nine months of 1994
was $124.1 million. In each case, a subsidiary of Magma is the managing
general partner, and Magma consolidates one-half of the operating results of
each Partnership Project plant into its financial statements. A subsidiary of
Magma operates each of the Salton Sea Project plants and the Partnership
Project plants.

   The Salton Sea Projects operated at a combined contract nameplate factor
(excluding scheduled maintenance hours) of 94.1% in the nine months ended
December 31, 1993 and 90.8% in the first nine months of 1994. The Partnership
Projects operated at a combined contract nameplate factor of 100.7% in 1993
and 105.0% in the first nine months in 1994.

   Vulcan. The Vulcan Project sells electricity to SCE under a 30-year SO4
Agreement that commenced on February 10, 1986. The Vulcan Project has a
contract capacity and contract nameplate of 29.5 MW and 34 MW, respectively.
Under the SO4 Agreement, SCE is obligated to pay the Vulcan Project a
capacity payment, a capacity bonus payment and an energy payment.

   The price for contract capacity payments is fixed for the life of such SO4
Agreement. The as-available capacity price is based on a payment schedule as
approved by the CPUC from time to time. The contract energy payment increases
each year for the first ten years, which period expires on February 9, 1996.
Thereafter, the energy payments will be based on SCE's Avoided Cost of
Energy. The energy payment per kWh is 10.9cents for 1994, 11.8cents for 1995
and 12.6cents for 1996. The Vulcan Project is unleveraged.

   Hoch (Del Ranch). The Hoch (Del Ranch) Project sells electricity to SCE
under a 30-year SO4 Agreement that commenced on January 1, 1989. The contract
capacity and contract nameplate are 34 MW and 38 MW, respectively. The
provisions of such SO4 Agreement are substantially the same as the SO4
Agreement with respect to the Vulcan Project.

   The price for contract capacity payment is fixed for the life of the SO4
Agreement. The energy payments per kWh for the first ten-year period, which
expires on December 31, 1998, are fixed at rates ranging from 10.9cents for
1994 to 14.6cents for 1998. Thereafter, the energy payments will be based on
SCE's Avoided Cost of Energy.

   The Del Ranch Partnership entered into a $66 million secured credit
facility with commercial banks in March 1988. The final maturity date of the
term loans is September 15, 2001. The secured credit agreement was amended to
allow for the issuance of commercial paper and medium-term notes supported by
a letter of credit as an alternative to borrowing directly from the banks.

                               34

<PAGE>

         
<PAGE>

   Elmore. The Elmore Project sells electricity to SCE under a 30-year SO4
Agreement that commenced on January 1, 1989. The contract capacity and
contract nameplate are 34 MW and 38 MW, respectively. The provisions of such
SO4 Agreement are substantially the same as the SO4 Agreement with respect to
the Vulcan Project.

   The price for contract capacity payments is fixed for the life of the SO4
Agreement. The energy payments per kWh for the first ten-year period, which
expires on December 31, 1998, are fixed at rates ranging from 10.9cents in
1994 to 14.6cents in 1998. Thereafter, the energy payments will be based on
SCE's Avoided Cost of Energy.

   The Elmore Partnership entered into a $66 million secured credit facility
with commercial banks in March 1988. The final maturity date of the term
loans is September 15, 2001. The secured credit agreement was amended and
restated on April 18, 1990 to allow for the issuance of commercial paper and
medium-term notes supported by a letter of credit as an alternative to
borrowing directly from the banks.

   Leathers. The Leathers Project sells electricity to SCE pursuant to a
30-year SO4 Agreement that commenced on January 1, 1990. The contract
capacity and contract nameplate are 34 MW and 38 MW, respectively. The
provisions of such SO4 Agreement are substantially the same as the SO4
Agreement with respect to the Vulcan Project.

   The price for contract capacity payments is fixed for the life of the SO4
Agreement. The energy payments per kWh for the first ten-year period, which
expires on December 31, 1999, are fixed at rates ranging from 10.9cents in
1994 to 15.6cents in 1999. Thereafter, the energy payments are based on SCE's
Avoided Cost of Energy.

   The Leathers Partnership entered into an $82 million secured credit
facility with commercial banks in March 1988. The final maturity date of the
term loans is September 15, 2002. The secured credit agreement was amended to
allow for the issuance of commercial paper and medium-term notes supported by
a letter of credit as an alternative to borrowing directly from the banks.

   Salton Sea I Project. The Salton Sea I Project sells electricity to SCE
pursuant to a 30-year negotiated power purchase agreement, as amended (the
"Salton Sea I PPA"), which provides for capacity and energy payments. The
initial contract capacity and contract nameplate are each 10 MW. The Salton
Sea I Project may add subsequent increments of contract capacity (subject to
notification requirements) the sum of which may not exceed 20 MW (the "Salton
Sea I Project Expansion"). See "--Projects in Development-Fish Lake/Salton
Sea I Expansion."

   The capacity payment is based on the firm capacity price which is
currently $123.61/kW-year. The contract capacity payment adjusts quarterly
based on a basket of energy indices for the term of the Salton Sea I PPA. The
energy payment is calculated using a Base Price (defined as the initial value
of the energy payment (4.701cents per kWh for the second quarter of 1992)),
which is subject to quarterly adjustments based on a basket of indices. The
time period weighted average energy payment for Unit 1 was 4.8cents per kWh
during 1993. As the Salton Sea I PPA is not an SO4 Agreement, the energy
payments do not revert to SCE's Avoided Cost of Energy.

   Salton Sea II Project. The Salton Sea II Project sells electricity to SCE
pursuant to a 30-year modified SO4 Agreement that commenced on April 15,
1990. The contract capacity and contract nameplate are 15MW and 18 MW,
respectively. The contract requires SCE to make capacity payments, capacity
bonus payments and energy payments. The price for contract capacity and
contract capacity bonus payments is fixed for the life of the modified SO4
Agreement. The energy payments for the first ten-year period, which period
expires on April 4, 2000, are levelized at a time period weighted average of
10.6cents per kWh. Thereafter, the monthly energy payments will be SCE's
Avoided Cost of Energy. For the period April 1, 1994 through March 31, 2004,
SCE is entitled to receive, at no cost, 5% of all energy delivered in excess
of 80% of contract capacity.

                               35

<PAGE>

         
<PAGE>

   Salton Sea III Project. The Salton Sea III Project sells electricity to
SCE pursuant to a 30-year modified SO4 Agreement. The contract capacity is
47.5 MW and the contract nameplate is 50 MW. The SO4 Agreement requires SCE
to make capacity payments, capacity bonus payments and energy payments for
the life of the SO4 Agreement. The price for contract capacity payments is
fixed. The energy payments for the first ten-year period, which period
expires on February 13, 1999, are levelized at a time period weighted average
of 9.8cents per kWh. Thereafter, the monthly energy payments will be SCE's
Avoided Cost of Energy.

   The partnerships that own the Salton Sea Projects (the "Salton Sea
Partnerships") are parties to a secured credit facility with commercial
banks. The agreement provides for a $130 million term loan broken into two
tranches, (i) tranche A (covers Units 1 and 2) in the original principal
amount of $37 million with a final maturity date of March 15, 2000 and (ii)
tranche B (covers Unit 3) in the original principal amount of $93 million
with a final maturity date of January 31, 1999. In addition, the agreement
provides for a renewable working capital loan in the aggregate principal
amount of $5 million with an initial maturity date of February 27, 1995.

   Yuma. During 1992, the Company acquired a development stage 50 MW natural
gas-fired cogeneration project in Yuma, Arizona (the "Yuma Project"). The
Yuma Project is designed to be a QF under PURPA and to provide 50 MW of
electricity to San Diego Gas & Electric Company ("SDG&E") under an existing
30-year power purchase contract. The electricity is sold at SDG&E's Avoided
Cost of Energy. The power is wheeled to SDG&E over transmission lines
constructed and owned by Arizona Public Service Company ("APS"). An agreement
for interconnection and a firm transmission service agreement have been
executed between APS and the Yuma Project entity and have been accepted for
filing by the Federal Energy Regulatory Commission ("FERC").

   The Yuma Project commenced commercial operation in May 1994. The project
entity has executed steam sales contracts with an adjacent industrial entity
to act as its thermal host in order to maintain its status as a QF, which is
a requirement of its SDG&E contract. Since the industrial entity has the
right under its contract to terminate the agreement upon one year's notice if
a change in its technology eliminates its need for steam, and in any case to
terminate the agreement at any time upon three years notice, there can be no
assurance that the Yuma Project will maintain its status as a QF. However, if
the industrial entity terminates the agreement, the Company anticipates that
it will be able to locate an alternative thermal host in order to maintain
its status as a QF or build a greenhouse at the site for which the Company
believes it would obtain QF status. A natural gas supply and transportation
agreement has been executed with Southwest Gas Corporation, terminable under
certain circumstances by the Company and Southwest Gas Corporation. The Yuma
Project is unleveraged other than intercompany debt.

   Roosevelt Hot Springs. The Company operates and owns an approximately 70%
interest in a 25MW geothermal steam field which supplies geothermal steam to
a power plant owned by Utah Power & Light Company ("UP&L") located on the
Roosevelt Hot Springs property under a 30-year steam sales contract. The
Company obtained approximately $20.3 million of cash under a pre-sale
agreement with UP&L whereby UP&L paid in advance for the steam produced by
the steam field. The Company must make certain penalty payments to UP&L if
the steam produced does not meet certain quantity and quality requirements.

   Desert Peak. The Company is the owner and operator of a 10 MW geothermal
plant at Desert Peak, Nevada that is currently selling electricity to Sierra
Pacific Power Company under a power sales contract that expires December 31,
1995 and that may be extended on a year-to-year basis as agreed by the
parties. The price for electricity under this contract is 6.3cents per kWh,
comprising an energy payment of 1.8cents per kWh (which is adjustable
pursuant to an inflation-based index) and a capacity payment of 4.5cents per
kWh. The Company is currently negotiating the terms of an extension to this
contract.

   Mammoth Plants. Magma receives royalty revenues from a 10 MW and a 12 MW
contract nameplate geothermal power plant (the "First Mammoth Plant" and the
"Second Mammoth Plant", respectively, and referred to herein, collectively,
as the "Mammoth Plants") at Mammoth Lakes, California. Electricity from the
Mammoth Plants is sold to SCE under two long-term power purchase agreements.
The First Mammoth Plant and the Second Mammoth Plant began commercial
operation in

                               36

<PAGE>

         
<PAGE>

1985 and 1991, respectively. Magma leases both property and geothermal
resources to support the Mammoth Plants in return for certain base royalty
and bonus royalty payments. For the First Mammoth Plant and the Second
Mammoth Plant, the base royalty is 12.5% and 12%, respectively, of gross
electricity sales revenues. The bonus royalty for the Mammoth Plants is 50%
of the excess of annual gross electricity sales revenues over an annual
revenue standard based on the Mammoth Plants operating at 85% of contract
capacity.

   The East Mesa Plant. Magma also receives royalty revenues from a 37 MW
contract nameplate geothermal power plant (with two units) at East Mesa in
Imperial Valley, California (the "East Mesa Plant"). Electricity from the
plant is sold to SCE pursuant to two SO4 Agreements formerly held by Magma,
and Magma is entitled to receive a senior payment of 4% of gross electricity
sales revenues and a junior payment of 10% of gross electricity sales
revenues. To date, such junior payment has not been received. Since 1992,
Magma recognized the accrued junior payments as royalty income.

PROJECTS IN DEVELOPMENT

   The BRPU Process. Magma is seeking new long-term final standard offer no.
4 power purchase agreements in southern California through the bidding
process adopted by the CPUC under its 1992 Biennial Resource Plan Update
("BRPU"). In its 1992 BRPU, the CPUC cited the need for an additional 9,600
MW of power production through 1999 among California's three investor-owned
utilities, SCE, SDG&E and Pacific Gas and Electric Company (collectively, the
"IOUs"). Of this amount, 275 MW was set aside for bidding by independent
power producers (such as Magma) utilizing renewable resources. Pursuant to an
order of the CPUC dated June 22, 1994 (confirmed on December 21, 1994), Magma
was awarded 163 MW for sale to SCE and SDG&E, with in-service dates in 1997
and 1998. However, the IOUs may continue to challenge the order and there can
be no assurance that power sales contracts will be executed or that any such
projects will be completed.

   Fish Lake/Salton Sea I Expansion. The Salton Sea I Project has an option
to supply an additional 20 MW of power to SCE under the Salton Sea I PPA.
Magma, through its wholly-owned subsidiary, Fish Lake Power Company, acquired
in 1992 a modified ISO4 power purchase agreement (the "Fish Lake ISO4") to
supply electric power to SCE from a 16 MW geothermal power plant proposed to
be built at Fish Lake in Esmeralda County, Nevada (the "Fish Lake Project").

   The Fish Lake ISO4 is a 30-year contract providing for a contract capacity
of 14 MW and a contract nameplate of 16 MW. The contract capacity payment
under the Fish Lake ISO4 is levelized in the contract for the full 30-year
term of the contract at $180 per kW-year. The capacity portion (plus bonus
capacity) of such revenues is levelized at approximately 2.5cents per kWh for
30 years (assuming a 90% nameplate capacity factor). The energy payment
thereunder is fixed for the first ten years starting at 10.2cents per kWh in
1996 and escalates at an average annual rate of 3.9%. For years 11 through
15, such energy payment is set at SCE's Avoided Cost of Energy, plus an
additional specified amount which decreases each year. For the last 15 years
of the Fish Lake ISO4, the energy payment will be based on SCE's Avoided Cost
of Energy.

   On November 29, 1994, SCE filed an application with the CPUC seeking
approval for the proposed restructuring of (i) the Salton Sea I PPA and (ii)
the Fish Lake ISO4, whereby the Fish Lake Project would not be developed at
its present site in Nevada's Fish Lake Valley and instead would be developed
under an amended and restated 30-year power purchase agreement (the "Amended
PPA") in conjunction with the Salton Sea I PPA.

   If approved, the Amended PPA will consolidate the Salton Sea I Project
Expansion with the Fish Lake Project. The Amended PPA also would reduce the
price for contract capacity payments to $158/kW-year and would alter the
energy payment schedule to commence in 1996 at 8.8cents per kWh.

   Newberry. Under a Bonneville Power Administration ("BPA") geothermal pilot
program, the Company is developing a 30 MW net geothermal project within the
Newberry known geothermal resource area of Deschutes County, Oregon (the
"Newberry Project"). Pursuant to two power sales contracts executed in
September 1994, after the final environmental impact statement for the
Newberry Project was issued, the Company has agreed to sell 20 MW to BPA and
10 MW to Eugene Water and

                               37

<PAGE>

         
<PAGE>

Electric Board ("EWEB") from the Newberry Project. In addition, BPA and EWEB
together have an option to purchase up to an additional 100 MW of production
from the Newberry Project under certain circumstances. In a public-private
development effort, the Company is responsible for development, permitting,
financing, construction and operation of the project (which will be 100%
owned by the Company), while EWEB will cooperate in the development efforts
by providing assistance with government and community affairs and sharing in
the development costs (up to 30%). The Newberry Project is currently expected
to commence commercial operation in 1997. The power sales contracts provide
that under certain circumstances the contracts may be utilized at an
alternative location. Completion of the Newberry Project is subject to a
number of significant uncertainties and cannot be assured.

                               38

<PAGE>

         
<PAGE>

                          CERTAIN TAX CONSIDERATIONS

   The following is a discussion, based upon present law, of certain U.S.
federal income and estate tax consequences to U.S. Holders and Non-U.S.
Holders of owning and disposing of shares of Common Stock. The term "U.S.
Holder" means a citizen (and, under certain circumstances, a former citizen)
or resident of the United States, a corporation, partnership or other entity
created or organized in or under the laws of the United States or any
political subdivision thereof, or an estate or trust the income of which is
subject to U.S. federal income taxation, regardless of its source, and the
term "Non-U.S. Holder" means any person who is not a U.S. Holder.

   This discussion does not deal with all aspects of U.S. federal income and
estate taxation that may be relevant to holders of the shares of Common Stock
and does not deal with tax consequences arising under the laws of any
foreign, state or local jurisdiction. This discussion assumes that each
holder holds the shares of Common Stock as capital assets and that any
amounts received by a Non-U.S. Holder with respect to the shares of Common
Stock are not effectively connected with the conduct by such Non-U.S. Holder
of a trade or business in the United States. Each prospective holder is
advised to consult its own tax adviser with respect to current and possible
future tax consequences of acquiring, holding and disposing of the shares of
Common Stock.

U.S. HOLDERS

   Disposition of Shares of Common Stock. In general, the U.S. Holder of the
shares of Common Stock will recognize capital gain or loss upon the sale or
other disposition of shares of Common Stock measured by the difference
between the amount realized and the U.S. Holder's tax basis in the shares of
Common Stock. The gain or loss on such disposition of shares of Common Stock
will be long-term capital gain or loss if the shares of Common Stock have
been held for more than one year at the time of such disposition.

   Dividends. Distributions on shares of Common Stock will constitute
dividends for U.S. federal income tax purposes to the extent of current or
accumulated earnings and profits of the Company as determined under U.S.
federal income tax principles. Such dividends will be subject to U.S. federal
income taxation in the hands of U.S. Holders of shares of Common Stock under
rules generally applicable to dividends received from U.S. corporations. For
example, such dividends paid to U.S. Holders that are U.S. corporations may
qualify for the 70% dividends-received deduction permitted by Section 243 of
the Internal Revenue Code of 1986 (the "Code"). Individuals, partnerships,
trusts, and certain corporations, including certain foreign corporations, are
not entitled to the dividends-received deduction.

NON-U.S. HOLDERS

   Gain on Disposition of Shares of Common Stock. A Non-U.S. Holder will not
be subject to U.S. federal income tax by withholding or otherwise on any gain
realized upon the disposition of shares of Common Stock unless (i) in the
case of a Non-U.S. Holder who is an individual, such Non-U.S. Holder is
present in the U.S. for a period or periods aggregating 183 days or more
during the taxable year of the disposition but is still not a resident of the
U.S. and either (a) the Non-U.S. Holder has a "tax home" (within the meaning
of the Code) in the U.S. (unless such gain is attributable to a fixed place
of business in a foreign country maintained by such individual and has been;
subject to foreign tax of at least 10%) or (b) the gain is attributable to an
office or other fixed place of business maintained by the Non-U.S. Holder in
the U.S., or (ii) the Company is or has been a "United States real property
holding corporation" for U.S. federal income tax purposes at any time within
the shorter of the five-year period ending on the date of such disposition or
such Non-U.S. Holder's holding period, and no treaty exception is applicable,
and either (a) at any point in time during such period the Non-U.S. Holder
has held, directly or indirectly, more than 5% of the Common Stock or (b) the
Common Stock is not "regularly traded" on an established securities market in
the U.S., within the meaning of Temporary Treasury Regulation Section
1.897-9T(d). If clause (ii) is applicable, a withholding tax will apply
(generally at a rate of 10% of the gross proceeds of any such sale or other
disposition). Any amount withheld pursuant to these rules will be creditable
against such Non-U.S. Holder's U.S. federal income tax liability and may
entitle such Non-U.S. Holder to a refund upon furnishing the required
information to the Internal Revenue Service.

                               39

<PAGE>

         
<PAGE>

   Dividends. Generally, any distribution on shares of Common Stock to a
Non-U.S. Holder will be subject to U.S. federal income tax withholding at a
rate of 30% of the amount of the distribution, or at a lesser applicable
treaty rate. Under current Treasury regulations, dividends paid to an address
in a foreign country are presumed to be paid to a resident of such country
for purposes of determining the applicability of a treaty rate unless the
Company has definite knowledge that such presumption is not warranted or an
applicable tax treaty requires some other method for determining a Non-U.S.
Holder's residence.

   To the extent, if any, that a distribution to a Non-U.S. Holder is treated
as a tax-free return of capital or as a capital gain (see "U.S.
Holders--Dividends" above), the Company nevertheless intends to withhold U.S.
federal income tax at the 30% or lesser applicable treaty rate. In such
event, the Non-U.S. Holder is entitled to apply for a refund of such withheld
amounts by filing Form 1040NR or Form 1120F with the Internal Revenue
Service. To the extent that the distribution is treated as a capital gain,
however, it will be subject to the same rules as applicable to gains realized
on the disposition of Common Stock (see "Gains on Disposition of Shares of
Common Stock"), and therefore a refund may not be granted.

   Estate Tax. Shares of Common Stock held at the time of death (or
previously transferred subject to certain retained rights or powers) by an
individual holder, who at such time was not a citizen or resident of the
U.S., will be subject to U.S. federal estate tax, except as otherwise
provided by an applicable estate tax treaty.

INFORMATION REPORTING AND BACKUP WITHHOLDING

   In addition to the withholding rules described above, interest, dividends,
distributions, and payments of proceeds from the disposition by certain
non-corporate holders of shares of Common Stock may be subject to backup
withholding at a rate of 31%. Such a U.S. Holder generally will be subject to
backup withholding at a rate of 31% unless the recipient of such payment
supplies an accurate taxpayer identification number, as well as certain other
information, or otherwise establishes, in the manner prescribed by law, an
exemption from backup withholding. Any amount withheld under backup
withholding is allowable as a credit against the U.S. Holder's federal income
tax, upon furnishing the required information.

   Under temporary and proposed U.S. Treasury regulations, backup withholding
will not apply to dividends paid on shares of Common Stock to a Non-U.S.
Holder. Generally, the payor of the dividends may rely on the payee's address
outside the U.S. in determining that such payee is a Non-U.S. Holder. The
Company must report annually to the Internal Revenue Service and to each
Non-U.S. Holder the amounts of dividends paid to, and the tax withheld with
respect to, each Non-U.S. Holder. These information reporting requirements
apply regardless of whether withholding was reduced by an applicable tax
treaty. Copies of these information returns may also be made available under
the provisions of a specific treaty or agreement to the tax authorities in
the country in which the Non-U.S. Holder resides. The payment of the proceeds
of the disposition of shares of Common Stock to or through the U.S. office of
a broker will be subject to information reporting and backup withholding at a
rate of 31% unless the owner certifies its status as a Non-U.S. Holder under
penalties of perjury or otherwise establishes an exemption. The proceeds of
the disposition by a Non-U.S. Holder of shares of Common Stock to or through
a foreign office of a broker will not be subject to backup withholding.
However, if such broker is a U.S. person, a controlled foreign corporation
for U.S. tax purposes, or a foreign person 50% or more of whose gross income
from all sources for a specified three-year period is from activities that
are effectively connected with a U.S. trade or business, information
reporting will apply unless such broker has documentary evidence in its files
of the owner's status as a Non-U.S. Holder and has no actual knowledge to the
contrary.

   Holders should consult their tax advisors regarding the application of
information reporting and backup withholding in their particular situation
and the availability of an exemption therefrom, and the procedures for
obtaining any such exemption.

                               40


<PAGE>

         

<PAGE>

   
                                 UNDERWRITING

   Under the terms and subject to the conditions contained in the
Underwriting Agreement, dated February 15, 1995 (the "U.S. Underwriting
Agreement"), the Underwriters named below (the "U.S. Underwriters"), for whom
CS First Boston Corporation, Bear, Stearns & Co. Inc., Donaldson, Lufkin &
Jenrette Securities Corporation, C.J. Lawrence/Deutsche Bank Securities
Corporation and Lehman Brothers Inc., are acting as representatives (the
"Representatives"), have severally but not jointly agreed to purchase from
the Company the following respective numbers of U.S. Shares:

<TABLE>
<CAPTION>
                                                        NUMBER OF
    UNDERWRITERS                                         SHARES
   --------------                                      -----------
<S>                                                   <C>
CS First Boston Corporation .........................  2,611,500
Bear, Stearns & Co. Inc. ............................  2,611,500
Donaldson, Lufkin & Jenrette Securities Corporation    2,611,500
C.J. Lawrence/Deutsche Bank Securities Corporation  .    435,250
Lehman Brothers Inc. ................................    435,250
George K. Baum & Company ............................    117,500
Alex. Brown & Sons Incorporated .....................    235,000
The Buckingham Research Group Incorporated  .........    117,500
The Chapman Company .................................    117,500
Crowell, Weedon & Co. ...............................    117,500
Dain Bosworth Incorporated ..........................    117,500
Dresdner Securities (USA) Inc. ......................    235,000
First Analysis Securities Corporation ...............    235,000
Goldman, Sachs & Co. ................................    235,000
Invemed Associates, Inc. ............................    235,000
Kirkpatrick, Pettis, Smith, Polian Inc. .............    117,500
Laidlaw Equities Inc. ...............................    117,500
WR Lazard, Laidlaw & Mead Inc. ......................    117,500
McDonald & Company Securities, Inc. .................    117,500
Merrill Lynch, Pierce, Fenner & Smith Incorporated  .    235,000
J.P. Morgan Securities Inc. .........................    235,000
Morgan Stanley & Co. Incorporated ...................    235,000
NatWest Securities Limited ..........................    235,000
Neuberger & Berman ..................................    117,500
RBC Dominion Securities Corporation .................    235,000
Robertson, Stephens & Company, L.P. .................    235,000
Salomon Brothers Inc ................................    235,000
SBC Capital Markets Inc. ............................    235,000
UBS Securities Inc. .................................    235,000
                                                      -----------
  Total ............................................. 13,170,000
                                                      ===========
    
</TABLE>

   The U.S. Underwriting Agreement provides that the obligations of the U.S.
Underwriters are subject to certain conditions precedent and that the U.S.
Underwriters will be obligated to purchase all the U.S. Shares if any are
purchased.

   The U.S. Underwriting Agreement provides that, in the event of a default
by a U.S. Underwriter, in certain circumstances the purchase commitments of
non-defaulting U.S. Underwriters may be increased or the U.S. Underwriting
Agreement may be terminated.

   The Company has entered into a Subscription Agreement (the "Subscription
Agreement") with the Managers of the International Offering (the "Managers")
providing for the concurrent offer and sale of the International Shares
outside the United States. The closing of the U.S. Offering and the closing
of the International Offering are each conditional on the other.

   The Company has granted to the U.S. Underwriters and the Managers an
option, exercisable by CS First Boston Corporation, expiring at the close of
business on the 30th day after the date of this Prospectus, to purchase up to
2,275,000 additional shares at the public offering price, less the
underwriting discounts and commissions, all as set forth on the cover page of
this Prospectus. Such option may be exercised only to cover over-allotments
in the sale of the Shares offered hereby. To the extent that this option to
purchase is exercised, each U.S. Underwriter and each Manager will become
obligated, subject

                               41

<PAGE>

         
<PAGE>

to certain conditions, to purchase approximately the same percentage of
additional shares being sold to the U.S. Underwriters and the Managers as the
number of U.S. Shares set forth next to such U.S. Underwriter's name in the
preceding table bears to the total number of U.S. Shares in such table and as
the number set forth next to such Manager's name in the corresponding table
in the Prospectus relating to the International Offering bears to the total
number of International Shares in such table.

   
   The Company has been advised by the Representatives that the U.S.
Underwriters propose to offer the U.S. Shares in the United States and Canada
to the public initially at the public offering price set forth on the cover
page of this Prospectus and, through the Representatives, to certain dealers
at such price less a concession of $.30 per share, and the U.S. Underwriters
and such dealers may allow a discount of $.10 per share on sales to certain
other dealers. After the initial public offering, the public offering price
and concession and discount to dealers may be changed by the U.S.
Underwriters. Gleacher & Co., Inc. ("Gleacher") has provided financial
advisory services to the Company in connection with the Magma Acquisition and
the Offering including, with respect to the Offering, participation in the
selection of the underwriters and the negotiation of the underwriting
documents. In addition, Gleacher has advised the Company regarding the
pricing of the Offering and related marketing issues. Gleacher may
participate as a dealer in the sale of the Shares in the Offering. In
addition to its fees for advisory services rendered in connection with the
Magma Acquisition and any selling commissions to which it may be entitled in
the Offering, Gleacher received a $100,000 fee from the Company upon the
filing of the Registration Statement with the Commission, will receive out of
the gross underwriting discounts and commissions (as set forth on the cover
page of this Prospectus) a fee in the amount of 20% of the underwriting fee
and will receive from the Company an incentive fee upon the closing of the
Offering (not to exceed $1,500,000) tied to a formula relating to the Price
to Public and PKS (as set forth on the cover page of this Prospectus).
    

   The public offering price, the aggregate underwriting discounts and
commissions per share and per share concession and discount to dealers for
the U.S. Offering and the concurrent International Offering will be
identical. Pursuant to an Agreement between the U.S. Underwriters and
Managers (the "Intersyndicate Agreement") relating to the Offering, changes
in the public offering price, concession and discount to dealers will be made
only upon the mutual agreement of CS First Boston Corporation, as
representative of the U.S. Underwriters, and CS First Boston Limited
("CSFBL"), on behalf of the Managers.

   Pursuant to the Intersyndicate Agreement, each of the U.S. Underwriters
has agreed that, as part of the distribution of the U.S. Shares and subject
to certain exceptions, it has not offered or sold, and will not offer or
sell, directly or indirectly, any shares of Common Stock or distribute any
prospectus relating to the Common Stock to any person outside the United
States or Canada or to any other dealer who does not so agree. Each of the
Managers has agreed or will agree that, as part of the distribution of the
International Shares and subject to certain exceptions, it has not offered or
sold, and will not offer or sell, directly or indirectly, any shares of
Common Stock or distribute any prospectus relating to the Common Stock in the
United States or Canada or to any other dealer who does not so agree. The
foregoing limitations do not apply to stabilization transactions or to
transactions between the U.S. Underwriters and the Managers pursuant to the
Intersyndicate Agreement. As used herein, "United States" means the United
States of America (including the States and the District of Columbia), its
territories, possessions and other areas subject to its jurisdiction,
"Canada" means Canada, its provinces, its territories, possessions and other
areas subject to its jurisdiction, and an offer or sale shall be in the
United States or Canada (i) any individual resident in the United States or
Canada or (ii) any corporation, partnership, pension, profit-sharing or other
trust or other entity (including any such entity acting as an investment
adviser with discretionary authority) whose office most directly involved
with the purchase is located in the United States or Canada.

   Pursuant to the Intersyndicate Agreement, sales may be made between the
U.S. Underwriters and the Managers of such number of shares of Common Stock
as may be mutually agreed upon. The price of any shares so sold will be the
public offering price, less such amount as may be mutually agreed upon by CS
First Boston Corporation, as representative of the U.S. Underwriters and
CSFBL, on behalf of the Managers, but not exceeding the selling concession
applicable to such shares. To the extent there are sales between the U.S.
Underwriters and the Managers pursuant to the Intersyndicate Agreement, the
number of shares of Common Stock initially available for sale by the U.S.
Underwriters or by the managers may be more or less than the amount appearing
on the cover page of the Prospectus. Neither the U.S. Underwriters nor the
Managers are obligated to purchase from the other any unsold shares of Common
Stock.

                               42

<PAGE>

         
<PAGE>

   This Prospectus may be used by underwriters and dealers in connection with
sales of International Shares to persons located in the United States, to the
extent such sales are permitted by the contractual limitations on sales
described above.

   The Company and its officers and directors have agreed that they will not
offer, sell, contract to sell, pledge or otherwise dispose of, directly or
indirectly, or file with the Securities and Exchange Commission a
registration statement under the Securities Act relating to, any additional
shares of its Common Stock without the prior written consent of CS First
Boston Corporation for a period of 90 days after the date of this Prospectus,
except issuances pursuant to the exercise of employee stock options
outstanding on the date hereof or pursuant to the conversion of the Company's
Debentures or its Series C Preferred Stock.

   The Company has agreed to indemnify the U.S. Underwriters and the Managers
against certain liabilities, including civil liabilities under the Securities
Act, or to contribute to payments that the U.S. Underwriters and the Managers
may be required to make in respect thereof.

   Each of Bear, Stearns & Co. Inc., Donaldson Lufkin & Jenrette Securities
Corporation and Lehman Brothers Inc. were underwriters of the Company's
$529,640,000 senior discount notes offering in March 1994.

   Lehman Brothers Inc. has provided financial advisory services to the
Company in connection with the Magma Acquisition.

   Credit Suisse, an affiliate of CS First Boston Corporation, has provided
certain credit facilities and commercial banking services to the Company and
its subsidiaries from time to time and is the agent bank in connection with
the Tender Facility and the Merger Facilities. The Company is currently
indebted to Credit Suisse in the amount of $245.6 million under the Tender
Facility. Such loan is secured by a pledge to Credit Suisse of the 12,600,000
shares of Magma Common Stock owned by CE Sub. The Company is currently in
compliance with the terms and conditions contained in the Tender Facility.
Certain of the net proceeds of the Offering may be deemed to be used to repay
some portion of the Tender Facility. Accordingly, the Offering is being made
in accordance with the requirements of Section 44(c)(8) of Article III of the
Rules of Fair Practice of the National Association of Securities Dealers,
Inc. The decision of CS First Boston to underwrite the Offering was made
independently of Credit Suisse, which had no involvement in determining
whether or when to underwrite the Offering or the terms of the Offering. CS
First Boston will not receive any benefit from the Offering other than its
respective portion of the gross underwriting discounts and commissions as set
forth on the cover page of this Prospectus.

   1,500,000 shares of Common Stock being offered pursuant to this Prospectus
are expected to be purchased by PKS from the Company in the Direct Sale at a
price equal to the Price to Public and PKS set forth on the cover of this
Prospectus. PKS has indicated an intention to acquire such shares, subject to
receipt and review by PKS of a final Prospectus and conditioned upon the
closing of the Offering.

                         NOTICE TO CANADIAN RESIDENTS
RESALE RESTRICTIONS

   The distribution of the Common Stock in Canada is being made only on a
private placement basis exempt from the requirement that the Company prepare
and file a prospectus with the securities regulatory authorities in each
province where trades of the Common Stock are effected. Accordingly, any
resale of the Common Stock in Canada must be made in accordance with
applicable securities laws which will vary depending on the relevant
jurisdiction, and which may require resales to be made in accordance with
available statutory exemptions or pursuant to a discretionary exemption
granted by the applicable Canadian securities regulatory authority.
Purchasers are advised to seek legal advice prior to any resale of the Common
Stock.

REPRESENTATIONS OF PURCHASERS

   Each purchaser of the Common Stock in Canada who receives a purchase
confirmation will be deemed to represent to the Company and the dealer from
whom such purchase confirmation is received that (i) such purchaser is
entitled under applicable provincial securities laws to purchase such Common
Stock without the benefit of a prospectus qualified under such securities
laws, (ii) where required by law, that such purchaser is purchasing as
principal and not as agent, and (iii) such purchaser has reviewed the text
above under "Resale Restrictions".

                               43

<PAGE>

         
<PAGE>

RIGHTS OF ACTION AND ENFORCEMENT

   The securities being offered are those of a foreign issuer and Ontario
purchasers will not receive the contractual right of action prescribed by
section 32 of the Regulation under the Securities Act (Ontario). As a result,
Ontario purchasers must rely on other remedies that may be available,
including common law rights of action for damages or recission or rights of
action under the civil liability provisions of the U.S. federal securities
laws.

   All of the Company's directors and officers as well as the experts named
herein may be located outside of Canada and, as a result, it may not be
possible for Ontario purchasers to effect service of process within Canada
upon the Company or such persons. All or a substantial portion of the assets
of the Company and such persons may be located outside of Canada and, as a
result, it may not be possible to satisfy a judgment against the Company or
such persons in Canada or to enforce a judgment obtained in Canadian courts
against such Company or persons outside of Canada.

NOTICE TO BRITISH COLUMBIA RESIDENTS

   A purchaser of the Common Stock to whom the Securities Act (British
Columbia) applies is advised that such purchaser is required to file with the
British Columbia Securities Commission a report within ten days of the sale
of any Common Stock acquired by such purchaser pursuant to this offering.
Such report must be in the form attached to British Columbia Securities
Commission Blanket Order BOR #88/5, a copy of which may be obtained from the
Company. Only one such report must be filed in respect of Common Stock
acquired on the same date and under the same prospectus exemption.

                                LEGAL MATTERS

   Certain legal matters with respect to the validity of the securities
offered hereby will be passed upon for the Company by Willkie Farr &
Gallagher, One Citicorp Center, 153 East 53rd Street, New York, New York
10022. Chadbourne & Parke, 30 Rockefeller Plaza, New York, New York 10112,
will pass on certain legal matters for the U.S. Underwriters and the Managers
in connection with the Offering.

                                   EXPERTS

   The financial statements and the related financial statement schedules of
the Company and its subsidiaries incorporated in this Prospectus by reference
to the Company's 1993 10-K have been audited by Deloitte & Touche,
independent auditors, as stated in their reports (which reports express an
unqualified opinion and include an explanatory paragraph referring to the
Company's adoption effective January 1, 1993, of Statement of Financial
Accounting Standards No. 109, "Accounting for Income Taxes") which are
incorporated herein by reference, and have been so incorporated in reliance
upon the reports of such firm given upon their authority as experts in
accounting and auditing.

   With respect to the unaudited interim financial information for the
periods ended March 31, 1993 and 1994, June 30, 1993 and 1994, and September
30, 1993 and 1994, incorporated herein by reference, Deloitte & Touche LLP
have applied limited procedures in accordance with professional standards for
a review of such information. However, as stated in their reports included in
the Company's Quarterly Reports on Form 10-Q for the quarters ended March 31,
1994, June 30, 1994 and September 30, 1994 and incorporated by reference
herein, they did not audit and they do not express an opinion on that interim
financial information. Accordingly, the degree of reliance on their reports
on such information should be restricted in light of the limited nature of
the review procedures applied. Deloitte & Touche LLP are not subject to the
liability provisions of Section 11 of the Securities Act for their reports on
the unaudited interim financial information because those reports are not
"reports" or a "part" of a registration statement prepared or certified by an
accountant within the meaning of Sections 7 and 11 of the Act.

   The consolidated balance sheets of Magma and subsidiaries as of December
31, 1993 and 1992 and the related consolidated statements of operations,
changes in stockholders' equity, and cash flows for each of the three years
in the period ended December 31, 1993 and the Statement of Net Assets
Acquired as of March 31, 1993 and the Historical Summaries of Gross Revenues
and Direct Operating Expenses for each of the three years in the period ended
December 31, 1992 of the Imperial Valley Geothermal Interests, incorporated
by reference in this Prospectus have been incorporated herein in reliance on
the reports of Coopers & Lybrand, independent accountants, given on the
authority of that firm as experts in accounting and auditing.

                               44

<PAGE>

         
<PAGE>

        INDEX TO PRO FORMA UNAUDITED CONDENSED COMBINED FINANCIAL DATA

<TABLE>
<CAPTION>
                                                                                     PAGE
                                                                                    ------
<S>                                                                                  <C>
Pro Forma Unaudited Condensed Combined Balance Sheet of the Company and Magma
 As of September 30, 1994 .......................................................     P-3
Pro Forma Unaudited Condensed Combined Statements of Earnings of the Company and
 Magma For the Year Ended December 31, 1993 and the Nine Months Ended September
 30, 1994 .......................................................................     P-4
Notes to Pro Forma Unaudited Condensed Combined Financial Data of the Company
 and Magma ......................................................................     P-5
</TABLE>

                               P-1

<PAGE>

         
<PAGE>

             PRO FORMA UNAUDITED CONDENSED COMBINED FINANCIAL DATA

   The following Pro Forma Unaudited Condensed Combined Balance Sheet as of
September 30, 1994 and the Pro Forma Unaudited Condensed Combined Statements
of Earnings for the year ended December 31, 1993 and the nine months ended
September 30, 1994 combine the historical consolidated balance sheets of the
Company and Magma as if the acquisition had been effected on September 30,
1994 and the historical statements of income as if the acquisition had been
effected at the beginning of each of the periods presented pursuant to the
All-Cash Option. The acquisition is recorded under the purchase method of
accounting, after giving effect to the pro forma adjustments and assumptions
described in the accompanying notes. Under this method of accounting, which
is in accordance with generally accepted accounting principles, assets and
liabilities of Magma are adjusted to the estimated fair value and combined
with the recorded values of the assets and liabilities of the Company. This
pro forma combined financial data should be read in conjunction with the
financial data appearing in, and are qualified in their entirety by, the
consolidated financial statements, including the notes thereto, of the
Company and Magma, included in the documents incorporated by reference
herein.

   The Company has not completed reviewing Magma's records in order to make
its determination of the fair value of Magma's assets and liabilities. The
fair value adjustments reflected in the accompanying pro forma condensed
combined financial data reflect, among other things, estimates of fair value
made by the Company based on market quotations and assumptions it believes to
be reasonable. Accordingly, the final pro forma condensed combined amounts
may be different from those set forth herein.

   It should be noted, however, that the actual fair values will be
determined on the basis of the financial condition of Magma at the time the
Magma shares are purchased.

   The pro forma combined financial data are intended for information
purposes only and are not intended to present the results that would have
actually occurred if the acquisition had been in effect on the assumed dates
and for the assumed periods, and are not necessarily indicative of the
results that may be obtained in the future.

                               P-2

<PAGE>

         
<PAGE>

             PRO FORMA UNAUDITED CONDENSED COMBINED BALANCE SHEET
                            THE COMPANY AND MAGMA
                           AS OF SEPTEMBER 30, 1994
                                (In thousands)
   
<TABLE>
<CAPTION>
                                                                          PRO FORMA      PRO FORMA
                                              THE COMPANY     MAGMA      ADJUSTMENTS      COMBINED
                                            -------------  ----------  --------------  ------------
<S>                                         <C>            <C>         <C>             <C>
ASSETS
Cash and short-term investments ........... $  316,349     $  5,111    $(181,713)(5C)  $  139,747
Marketable securities .....................         --       43,609           --           43,609
Joint venture cash and short-term
 investments ..............................     27,088       25,478           --           52,566
Restricted cash and short-term investments     127,380           --           --          127,380
Accounts receivable--trade and other  .....     33,901       54,204           --           88,105
Prepaid expenses and other assets  ........         --       10,423           --           10,423
Due from joint ventures ...................      1,639           --           --            1,639
Property and plant, net ...................    522,268      395,560      340,000 (5B)   1,257,828
Equipment, net ............................      4,699           --           --            4,699
Notes receivable--joint venture ...........     12,255           --           --           12,255
Other investments .........................     11,517       41,245           --           52,762
Power purchase contracts ..................         --       21,313       60,000 (5B)      81,313
Deferred charges and other assets  ........     29,968       24,480        6,948 (5B,5C)   61,396
Goodwill ..................................         --        8,999      313,132 (5B)     322,131
                                            -------------  ----------  --------------  ------------
  Total assets ............................ $1,087,064     $630,422    $ 538,367       $2,255,853
                                            =============  ==========  ==============  ============
LIABILITIES AND STOCKHOLDERS' EQUITY
LIABILITIES
Accounts payable .......................... $    1,021     $  7,832    $      --       $    8,853
Other accrued liabilities .................     23,357        3,605           --           26,962
Income taxes payable ......................        587           --           --              587
Construction loans ........................     21,079           --           --           21,079
Project loans .............................    233,080      188,969           --          422,049
Senior discount notes .....................    421,375           --           --          421,375
Convertible subordinated debenture  .......    100,000           --           --          100,000
Deferred income taxes .....................     24,774       22,376      158,000 (5B)     205,150
Other long-term liabilities ...............         --       12,354      500,000 (5C)     512,354
                                            -------------  ----------  --------------  ------------
  Total liabilities .......................    825,273      235,136      658,000        1,718,409
Deferred income ...........................     19,781           --           --           19,781
Redeemable preferred stock ................     62,350           --           --           62,350

STOCKHOLDERS' EQUITY
Common stock ..............................      2,407        2,401       (1,507)(5A)       3,301
Additional paid-in capital ................    100,000      142,765       72,478 (5A)     315,243
Unrealized gain from marketable securities          --         (677)         677 (5A)          --
Retained earnings .........................    136,769      250,797     (250,797)(5A)     136,769
Treasury stock ............................    (59,516)          --       59,516 (5A)          --
                                            -------------  ----------  --------------  ------------
  Total stockholders' equity ..............    179,660      395,286     (119,633)         455,313
                                            -------------  ----------  --------------  ------------
   Total liabilities and stockholders'
     equity ............................... $1,087,064     $630,422    $ 538,367       $2,255,853
                                            =============  ==========  ==============  ============
</TABLE>
    
    The accompanying notes to the pro forma unaudited condensed combined
           financial data are an integral part of these statements.

                               P-3

<PAGE>

         
<PAGE>

         PRO FORMA UNAUDITED CONDENSED COMBINED STATEMENTS OF EARNINGS
                            THE COMPANY AND MAGMA
        FOR THE YEAR ENDED DECEMBER 31, 1993 AND THE NINE MONTHS ENDED
                              SEPTEMBER 30, 1994
                    (In thousands, except per share data)

<TABLE>
<CAPTION>
                                               YEAR ENDED DECEMBER 31, 1993                NINE MONTHS ENDED SEPTEMBER 30, 1994
                                    -------------------------------------------------  -------------------------------------------
                                                              PRO FORMA                                        PRO FORMA
                                        THE                   ADJUSTMENT    PRO FORMA      THE                ADJUSTMENT  PRO FORMA
                                      COMPANY      MAGMA        (5 D)       COMBINED     COMPANY      MAGMA        (5 D)   COMBINED
                                    ----------  ----------  ------------  -----------  ----------  ----------  ------------ -------
<S>                                 <C>         <C>         <C>           <C>          <C>         <C>         <C>           <C>
REVENUES
Sales of electricity and steam  ... $132,059    $137,882    $     --      $269,941     $117,208    $124,086    $     --    $241,294
Royalties .........................       --      19,629          --        19,629           --      15,062          --      15,062
Interest and other income .........   17,194       4,195      (9,086)       12,303       21,980       3,866      (6,814)     19,032
Management services ...............       --       5,432          --         5,432           --       3,090          --       3,090
                                    ----------  ----------  ------------  -----------  ----------  ----------  ------------ -------
  Total revenue ...................  149,253     167,138      (9,086)      307,305      139,188     146,104      (6,814)    278,478
                                    ----------  ----------  ------------  -----------  ----------  ----------  ------------ -------
COSTS AND EXPENSES ................
Plant operations ..................   25,362      49,493          --        74,855       23,887      41,208          --      65,095
General and administrative ........   13,158      10,943          --        24,101        9,536       9,602          --      19,138
Royalties .........................    8,274          --          --         8,274        7,898          --          --       7,898
Depreciation and amortization  ....   17,812      21,692      18,103        57,607       15,439      17,737      13,577      46,753
Other non-plant costs .............       --         471           _           471            _         380          --         380
Interest expense ..................   30,205       9,626      45,875        85,706       44,480       9,262      34,406      88,148
Less interest capitalized .........   (6,816)         --          --        (6,816)      (7,518)         --          --     (7,518)
                                    ----------  ----------  ------------  -----------  ----------  ----------  ------------  ------
  Total costs and expenses ........   87,995      92,225      63,978       244,198       93,722      78,189      47,983     219,894
                                    ----------  ----------  ------------  -----------  ----------  ----------  ------------ -------
Income before income taxes ........   61,258      74,913     (73,064)       63,107       45,466      67,915     (54,797)     58,584
Provision for income taxes ........   18,184      22,778     (25,824)       15,138       14,067      21,072     (19,368)     15,771
                                    ----------  ----------  ------------  -----------  ----------  ----------  ------------  ------
Income from continuing operations     43,074      52,135     (47,240)       47,969       31,399      46,843     (35,429)     42,813
Preferred dividends ...............    4,630          --          --         4,630        3,711          --          --       3,711
                                    ----------  ----------  ------------  -----------  ----------  ----------  ------------  ------
Income available to common
 stockholders ..................... $ 38,444    $ 52,135    $(47,240)     $ 43,339     $ 27,688    $ 46,843    $(35,429)    $39,102
                                    ==========  ==========  ============  ===========  ==========  ==========  ============ =======
INCOME PER COMMON AND COMMON
 EQUIVALENT SHARE
Assuming no dilution ..............    $1.00       $2.17                      $0.79       $0.77       $1.95                   $0.74
                                    ==========  ==========                ===========  ==========  ==========               =======
Assuming full dilution ............    $1.00       $2.17                      $0.78       $0.76       $1.95                   $0.72
                                    ==========  ==========                ===========  ==========  ==========               =======
Weighted average common shares
 outstanding ......................   38,485      24,063                     55,155      36,174      24,017                  52,844
                                    ==========  ==========                ===========  ==========  ==========               =======
</TABLE>

The accompanying notes to the pro forma unaudited condensed combined
       financial data are an integral part of these statements.

                               P-4

<PAGE>

         
<PAGE>

        NOTES TO PRO FORMA UNAUDITED CONDENSED COMBINED FINANCIAL DATA
                            THE COMPANY AND MAGMA
                            (Tables in thousands)

   The Magma Acquisition will be accounted for as a purchase. The resulting
adjustments are based on the historical consolidated financial statements of
the Company and Magma. The final adjustments will be based upon the net
proceeds to the Company from the sale of the shares of Common Stock in the
Offering and the Direct Sale and the fair market value of the assets of Magma
at or near the effective time of the Merger.

   The pro forma unaudited condensed combined financial data are based on the
following assumptions:

   1. The Magma Acquisition occurred on September 30, 1994 for balance sheet
purposes and at the beginning of the periods presented for statements of
earnings purposes.

   
   2. 15,170,000 shares of Common Stock will be sold in the Offering at a
price sufficient to provide net proceeds of approximately $16.49 per Share to
the Company and 1,500,000 shares of Common Stock will be sold in the Direct
Sale at a price sufficient to provide proceeds of $17.00 per share to the
Company, the sum of which will be used to fund a significant portion of the
purchase price under the Merger. The Company's treasury stock will be
canceled.
    

   3. 23,843,000 Magma shares outstanding as of September 30, 1994 will be
purchased for cash in an amount of $483,600,000 as to 12,400,000 Magma shares
and cash in an amount of $440,266,000 as to 11,443,000 Magma shares.

   4. Outstanding Magma options will be retired for approximately $8,500,000
in cash.

   5. The pro forma adjustments to reflect the effect of the transaction are
as follows:

       A. The adjustments reflect the elimination of Magma's equity accounts,
    the sale of the shares of Common Stock pursuant to the Offering and the
    Direct Sale, and the cancellation of the Company's treasury stock.

       B. The adjustments which have been made to the net assets of Magma and
    the Company to give effect to the Magma Acquisition follow:

<TABLE>
<CAPTION>
<S>                                                   <C>         <C>
Cash consideration plus estimated direct costs to be
 incurred in consummating the Magma Acquisition  ....             $ 936,366
Cost of retiring outstanding Magma options  .........                 8,500
Cost of 200,000 Magma shares owned by the Company
 prior to the Merger ................................                 5,552
Net assets of Magma ................................. $395,286
Adjustment to eliminate goodwill of Magma  ..........   (8,999)    (386,287)
                                                      ----------  -----------
Excess of purchase price over carrying value of net
 assets acquired ....................................               564,131
Allocated to:
 Property and plant .................................              (340,000)
 Power purchase contracts ...........................               (60,000)
 Deferred income taxes on allocated costs  ..........               158,000
                                                                  -----------
Goodwill ............................................             $ 322,131
                                                                  ===========
</TABLE>

                               P-5

<PAGE>

         
<PAGE>

        NOTES TO PRO FORMA UNAUDITED CONDENSED COMBINED FINANCIAL DATA
                      THE COMPANY AND MAGMA--(CONTINUED)

        C. The cash which the Company will be required to pay in order to
    effect the Magma Acquisition has been provided for in the pro forma
    adjustments as follows:
   
<TABLE>
<CAPTION>
<S>                                             <C>
Reduce cash on hand ........................... $181,713
Proceeds from the Offering and the Direct Sale   275,653
Increase long-term debt .......................  500,000
                                                ----------
Total sources of cash ......................... $957,366
                                                ==========
Payments to Magma common stockholders  ........ $923,866
Payments to Magma stock option holders  .......    8,500
Other direct acquisition costs ................   12,500
Financing costs ...............................   12,500
                                                ----------
Total uses of cash ............................ $957,366
                                                ==========
</TABLE>
    
       D. The pro forma adjustments to the pro forma condensed combined
    statements of earnings are as follows:

       i. Record amortization of the excess of purchase price over net assets
    acquired over a 40-year period, eliminate the amortization of goodwill
    from the historical operating results of Magma and provide depreciation
    expense on costs allocated to property and plant. The Company's policy is
    to provide depreciation and amortization expense beginning upon the
    commencement of energy production over the estimated remaining useful life
    of plant and equipment or the contract period for costs applicable to
    power sales and development contracts. Costs of $150 million have been
    allocated to power sales and development contracts and plant for which
    energy production is not expected to commence until 1996 or later.
    Accordingly, revenues, period operating costs and amortization of future
    costs to be incurred in the completion of such facilities together with
    amortization of this allocation of acquisition costs are not included in
    the pro forma combined statements of earnings.

   
       ii. Increase interest expense relating to amortization of deferred
    financing costs over ten years and cash used to finance the Magma
    Acquisition, utilizing an 8.925 percent annual interest rate assumption
    applied to additional borrowings and a 5 percent annual interest rate
    assumption applicable to the reduction of cash on hand.
    

       iii. Change income tax expense as a result of pro forma adjustments
    which affect taxable income.

   The pro forma income per common and common share equivalent has been
determined on the basis of weighted average shares which have been adjusted
to include the number of shares of Common Stock sold pursuant to the Offering
and the Direct Sale.

                               P-6


<PAGE>

         

<PAGE>

 #############################################################################

                                IMAGES OMITTED:

                               [Photographs of:
                          (a) Navy I Facility at the
                                 Coso Project;
                           (b) One of the Salton Sea
                                   Projects]

             (SEE ALSO "APPENDIX FOR GRAPHICS AND IMAGE MATERIAL"
                     AFTER BACK COVER PAGE OF PROSPECTUS.)

 #############################################################################




<PAGE>

         


<PAGE>

   NO DEALER, SALESPERSON OR OTHER PERSON HAS BEEN AUTHORIZED TO GIVE ANY
INFORMATION OR TO MAKE ANY REPRESENTATION NOT CONTAINED IN THIS PROSPECTUS
AND, IF GIVEN OR MADE, SUCH INFORMATION OR REPRESENTATION MUST NOT BE RELIED
UPON AS HAVING BEEN AUTHORIZED BY THE COMPANY OR ANY U.S. UNDERWRITER. THIS
PROSPECTUS DOES NOT CONSTITUTE AN OFFER TO SELL OR A SOLICITATION OF AN OFFER
TO BUY ANY OF THE SECURITIES OFFERED HEREBY IN ANY JURISDICTION TO ANY PERSON
TO WHOM IT IS UNLAWFUL TO MAKE SUCH OFFER IN SUCH JURISDICTION. NEITHER THE
DELIVERY OF THIS PROSPECTUS NOR ANY SALE MADE HEREUNDER SHALL, UNDER ANY
CIRCUMSTANCES, CREATE ANY IMPLICATION THAT THE INFORMATION HEREIN IS CORRECT
AS OF ANY TIME SUBSEQUENT TO THE DATE HEREOF OR THAT THERE HAS BEEN NO CHANGE
IN THE AFFAIRS OF THE COMPANY SINCE SUCH DATE.

                                ----------------

                              TABLE OF CONTENTS
<TABLE>
<CAPTION>
                                               PAGE
                                            --------
<S>                                           <C>
Available Information .....................    3
Incorporation of Documents by Reference  ..    4
Prospectus Summary ........................    5
Risk Factors ..............................    9
Use of Proceeds ...........................    12
Market Prices of the Common Stock  ........    12
Capitalization ............................    13
The Magma Acquisition .....................    14
Business ..................................    16
Certain Tax Considerations ................    39
Underwriting ..............................    41
Notice to Canadian Residents ..............    43
Legal Matters .............................    44
Experts ...................................    44
Index to Pro Forma Unaudited Condensed
 Combined Financial Data ..................   P-1
</TABLE>

                          [CALIFORNIA ENERGY LOGO]

                       California Energy Company, Inc.

                              16,670,000 Shares
                                 Common Stock
                             ($0.0675 par value)

                                  PROSPECTUS

                               CS First Boston
                           Bear, Stearns & Co. Inc.
                         Donaldson, Lufkin & Jenrette
                            Securities Corporation
                         C.J. Lawrence/Deutsche Bank
                            Securities Corporation
                               Lehman Brothers


<PAGE>

         


                APPENDIX FOR GRAPHIC AND IMAGE MATERIAL

        Graphics or images which cannot be reproduced in the ASCII format
required for EDGAR have been omitted from the pages of the preceding document as
listed below. Pursuant to Rule 304 of Regulation S-T, the substantive
information contained in these graphics or images is conveyed in tabular and/or
narrative form:


Page in
Typeset Copy                  Description
- ------------                  -----------
Inside front cover of
US Prospectus                   California Energy Company, Inc.'s
                                Planned Project Development; Development
                                and Capacity Implementation Schedule;
                                Chart listing facilities with MW capacity; Map
                                [Datapoints/tables are provided in place of the
                                graphics inside the front cover of this EDGAR
                                file, as necessary, to disclose material
                                content of said graphics.]

18                              Schematic representing Geothermal Energy

19                              Map depicting areas of Potential Geothermal
                                Activity

25                              Map of the Republic of the
                                Philippines with Project locations

29                              Map of Indonesia and Neighboring
                                Countries with Project locations

32                              Map of the Western United States
                                with Project locations

Inside back cover of
US Prospectus                   Photographs of (a) Navy I Facility at the
                                Coso Project; (b) One of the Salton Sea
                                Projects




<PAGE>

         

<PAGE>

                                 [Alternate Page For International Prospectus]

                                              Filed Pursuant to Rule 424(b)(1)
                                                Registration File No.: 33-57191


   
    
                              16,670,000 Shares
[LOGO]                 California Energy Company, Inc.
                                 Common Stock
                             ($0.0675 par value)
                                ----------------
   
All the 16,670,000 shares of Common Stock (the "Common Stock") of California
Energy Company, Inc. (the "Company") offered hereby are being sold by the
Company. Of the 16,670,000 shares of Common Stock being offered, 2,000,000
shares are initially being offered outside the United States and Canada (the
"International Shares") by the Managers (the "International Offering") and
13,170,000 shares are initially being concurrently offered in the United States
and Canada (the "U.S. Shares" and, together with the International Shares, the
"Shares") by the U.S. Underwriters (the "U.S. Offering" and, together with the
International Offering, the "Offering"). The offering price and underwriting
discounts and commissions of the International Offering and the U.S. Offering
are identical. 1,500,000 shares of Common Stock being offered pursuant to this
Prospectus are expected to be purchased by Peter Kiewit Sons', Inc. ("PKS"),
directly from the Company, at a price equal to the Price to Public and PKS set
forth below. PKS has indicated an intention to acquire such shares (the "Direct
Sale"), subject to receipt and review by PKS of a final Prospectus and
conditioned upon the closing of the Offering.
    
The net proceeds of the Offering and the proceeds of the Direct Sale, together
with borrowings of up to $500 million under bank credit facilities and general
corporate funds of the Company, will be used to complete the Magma Acquisition
(as hereinafter defined). The closing of the Offering will occur concurrently
with, and is conditioned upon, the closing of the Magma Acquisition pursuant to
the All-Cash Option (as hereinafter defined).
   
The Common Stock of the Company is listed on the New York Stock Exchange
under the symbol "CE". On February 15, 1995, the last reported sale price of
the Common Stock on the New York Stock Exchange Composite Tape was $17 7/8 per
share.
    
                                ----------------
FOR A DISCUSSION OF CERTAIN FACTORS THAT SHOULD BE CONSIDERED IN CONNECTION
         WITH AN INVESTMENT IN THE COMMON STOCK, SEE "RISK FACTORS".
                                ----------------
THESE SECURITIES HAVE NOT BEEN APPROVED OR DISAPPROVED BY THE SECURITIES AND
    EXCHANGE COMMISSION OR ANY STATE SECURITIES COMMISSION NOR HAS THE
       SECURITIES AND EXCHANGE COMMISSION OR ANY STATE SECURITIES
           COMMISSION PASSED UPON THE ACCURACY OR ADEQUACY OF THIS
              PROSPECTUS. ANY REPRESENTATION TO THE CONTRARY IS
                             A CRIMINAL OFFENSE.
   
<TABLE>
<CAPTION>
                                            UNDERWRITING
                              PRICE TO      DISCOUNTS AND    PROCEEDS TO
                            PUBLIC AND PKS  COMMISSIONS(1)    COMPANY(2)
                            --------------  --------------  -------------
<S>                        <C>              <C>            <C>
Per Share  ..............      $17.00           $.51           $16.49
Total (3)  ..............   $283,390,000     $7,736,700     $275,653,300
<FN>
   (1) No Underwriting Discounts and Commissions are to be paid in connection
       with the Direct Sale to PKS.
   (2) Before deduction of expenses payable by the Company estimated at
       $2,132,810. Per Share Proceeds to Company reflect per share proceeds
       from the Offering, but not from the Direct Sale.
   (3) The Company has granted the Managers and the U.S. Underwriters an
       option, exercisable by CS First Boston Corporation for 30 days from the
       date of this Prospectus to purchase a maximum of 2,275,000 additional
       shares to cover over-allotments. If the option is exercised in full,
       the total Price to Public and PKS will be $322,065,000, Underwriting
       Discounts and Commissions will be $8,896,950 and Proceeds to Company
       will be $313,168,050.
</TABLE>
                                ----------------
   The International Shares are offered by the several Managers when, as and
if issued by the Company, delivered to and accepted by the Managers and
subject to their right to reject orders in whole or in part. It is expected
that the International Shares will be ready for delivery on or about February
24, 1995.

                               CS First Boston
Bear, Stearns International Limited               Donaldson, Lufkin & Jenrette
                                                     Securities Corporation
Deutsche Bank                                                  Lehman Brothers
Aktiengesellschaft

              The date of this Prospectus is February 16, 1995.
    

<PAGE>

         
<PAGE>
                                 [Alternate Page For International Prospectus]

   NO DEALER, SALESPERSON OR OTHER PERSON HAS BEEN AUTHORIZED TO GIVE ANY
INFORMATION OR TO MAKE ANY REPRESENTATION NOT CONTAINED IN THIS PROSPECTUS
AND, IF GIVEN OR MADE, SUCH INFORMATION OR REPRESENTATION MUST NOT BE RELIED
UPON AS HAVING BEEN AUTHORIZED BY THE COMPANY OR ANY MANAGER. THIS PROSPECTUS
DOES NOT CONSTITUTE AN OFFER TO SELL OR A SOLICITATION OF AN OFFER TO BUY ANY
OF THE SECURITIES OFFERED HEREBY IN ANY JURISDICTION TO ANY PERSON TO WHOM IT
IS UNLAWFUL TO MAKE SUCH OFFER IN SUCH JURISDICTION. NEITHER THE DELIVERY OF
THIS PROSPECTUS NOR ANY SALE MADE HEREUNDER SHALL, UNDER ANY CIRCUMSTANCES,
CREATE ANY IMPLICATION THAT THE INFORMATION HEREIN IS CORRECT AS OF ANY TIME
SUBSEQUENT TO THE DATE HEREOF OR THAT THERE HAS BEEN NO CHANGE IN THE AFFAIRS
OF THE COMPANY SINCE SUCH DATE.

   In this Prospectus, references to "dollars" and "$" are to United States
dollars.

   IN CONNECTION WITH THE OFFERING, CS FIRST BOSTON CORPORATION ON BEHALF OF
THE U.S. UNDERWRITERS AND THE MANAGERS MAY OVER-ALLOT OR EFFECT TRANSACTIONS
WHICH STABILIZE OR MAINTAIN THE MARKET PRICE OF THE COMMON STOCK AT A LEVEL
ABOVE THAT WHICH MIGHT OTHERWISE PREVAIL IN THE OPEN MARKET. SUCH
TRANSACTIONS MAY BE EFFECTED ON THE NEW YORK STOCK EXCHANGE, THE PACIFIC
STOCK EXCHANGE, THE LONDON STOCK EXCHANGE OR OTHERWISE. SUCH STABILIZING, IF
COMMENCED, MAY BE DISCONTINUED AT ANY TIME.

   DURING THE OFFERING, CERTAIN PERSONS AFFILIATED WITH PERSONS PARTICIPATING
IN THE DISTRIBUTION MAY ENGAGE IN TRANSACTIONS FOR THEIR OWN ACCOUNTS OR FOR
THE ACCOUNTS OF OTHERS IN THE COMMON STOCK PURSUANT TO EXEMPTIONS FROM RULES
10b-6, 10b-7, AND 10b-8 UNDER THE EXCHANGE ACT.

                              TABLE OF CONTENTS
<TABLE>
<CAPTION>
                                          PAGE
                                        --------
<S>                                       <C>
Available Information ................     3
Incorporation of Documents by
 Reference ...........................     4
Prospectus Summary ...................     5
Risk Factors .........................     9
Use of Proceeds ......................     12
Market Prices of the Common Stock  ...     12
Capitalization .......................     13
The Magma Acquisition ................     14
Business .............................     16
Certain Tax Considerations ...........     39
Subscription and Sale ................     41
Legal Matters ........................     43
Experts ..............................     43
Index to Pro Forma Unaudited
 Condensed Combined Financial Data  ..    P-1
</TABLE>
                            AVAILABLE INFORMATION

   California Energy Company, Inc. (the "Company") and Magma Power Company
("Magma") are each subject to the informational requirements of the
Securities Exchange Act of 1934, as amended (the "Exchange Act"), and, in
accordance therewith, each files reports, proxy statements and other
information with the Securities and Exchange Commission (the "Commission").
Such reports, proxy statements and other information filed by the Company or
Magma with the Commission pursuant to the informational requirements of the
Exchange Act may be inspected and copied at the public reference facilities
maintained by the Commission at Room 1024, 450 Fifth Street, N.W.,
Washington, D.C. 20549 and at the following Regional Offices of the
Commission: Midwest Regional Office, Citicorp Center, 500 West Madison
Street, Suite 1400, Chicago, Illinois 60661; and New York Regional Office,
14th Floor, Seven World Trade Center, New York, New York 10048. Copies of
such materials can be obtained at prescribed rates from the Public Reference
Section of the Commission at Judiciary Plaza, 450 Fifth Street, N.W.,
Washington, D.C. 20549. In addition, material filed by the Company can be
inspected at the offices of the New York Stock Exchange, Inc. ("NYSE"), 20
Broad Street, New York, New York 10005, on which the shares of common stock,
par value $.0675 per share (the "Common Stock") of the Company, are listed,
at the offices of the Pacific Stock Exchange at 301 Pine Street, San
Francisco, California 94104 and 233 South Beaudry Avenue, Los Angeles,
California 90012 and at the offices of the London Stock Exchange at
International Stock Exchange, Throgmorton Street, EC2N 1HP, London, England.
Material filed by Magma can be inspected at the offices of the National
Association of Securities Dealers, Inc., 1735 K Street, N.W., Washington,
D.C. 20006.

   The Company has filed with the Commission a Registration Statement on Form
S-3 (the "Registration Statement," which term shall include all amendments,
exhibits and schedules thereto) under the
                                3

<PAGE>

         
<PAGE>

                                 [Alternate Page For International Prospectus]

Securities Act of 1933, as amended (the "Securities Act"), with respect to
the shares of Common Stock offered pursuant to the Offering (the "Shares")
and the Direct Sale. This Prospectus does not contain all of the information
set forth in the Registration Statement, certain parts of which have been
omitted in accordance with the rules and regulations of the Commission. For
further information with respect to the Company and the Shares, reference is
made to the Registration Statement, including the exhibits and schedules
filed as a part thereof and otherwise incorporated therein. Statements made
in this Prospectus as to the contents of any contract, agreement or other
document referred to are not necessarily complete. With respect to each such
contract, agreement or other document filed as an exhibit to the Registration
Statement, reference is made to such exhibit for a more complete description
of the matter involved and each such statement shall be deemed qualified in
its entirety by such reference. Copies of the Registration Statement and the
exhibits thereto may be inspected, without charge, at the offices of the
Commission, or obtained at prescribed rates from the Public Reference Section
of the Commission at the address set forth above.

                   INCORPORATION OF DOCUMENTS BY REFERENCE

   The Company and Magma hereby incorporate by reference into this Prospectus
the following documents previously filed with the Commission pursuant to the
Exchange Act:

   1. The Company's Annual Report on Form 10-K for the fiscal year ended
December 31, 1993 (the "Company's 1993 10-K").

   2. The Company's Quarterly Reports on Form 10-Q for the quarters ended
March 31, 1994, June 30, 1994 and September 30, 1994.

   3. The Company's Current Reports on Form 8-K dated March 7, 1994, March
28, 1994, April 11, 1994, May 6, 1994, June 8, 1994, August 16, 1994,
September 22, 1994, September 30, 1994, October 6, 1994, October 26, 1994,
November 22, 1994, December 6, 1994, December 9, 1994, January 11, 1995,
January 27, 1995 and February 13, 1995.

   4. The Company's description of the Common Stock contained in the
Company's Registration Statement on Form 8-A, dated July 28, 1993, pursuant
to Section 12 of the Exchange Act.

   5. Magma's Annual Report on Form 10-K for the fiscal year ended December
31, 1993 (the "Magma 1993 10-K").

   6. Magma's Quarterly Reports on Form 10-Q for the quarters ended March 31,
1994, June 30, 1994 and September 30, 1994.

   7. Magma's Current Reports on Form 8-K dated March 31, 1993, as amended,
October 7, 1994, December 9, 1994 and January 11, 1995.

   In addition, all reports and other documents filed by the Company or Magma
pursuant to Section 13(a), 13(c), 14 or 15(d) of the Exchange Act subsequent
to the date hereof and prior to the termination of the Offering hereby shall
be deemed to be incorporated by reference herein and to be a part hereof from
the date of filing of such reports and documents. Any statement contained in
a document incorporated or deemed to be incorporated by reference herein
shall be deemed to be modified or superseded for purposes of this Prospectus
to the extent that a statement contained herein, or in any other subsequently
filed document that also is incorporated or deemed to be incorporated by
reference herein, modifies or supersedes such statement. Any such statement
so modified or superseded shall not be deemed, except as so modified or
superseded, to constitute a part of this Prospectus.

   The Company hereby undertakes to provide without charge to each person,
including any beneficial owner, to whom this Prospectus is delivered, upon
written or oral request from such person, a copy of any and all of the
documents incorporated by reference in this Prospectus (other than exhibits
to such documents unless such exhibits are specifically incorporated by
reference into the documents that this Prospectus incorporates). Written or
oral requests for such copies should be directed to California Energy
Company, Inc., 10831 Old Mill Road, Omaha, Nebraska 68154, Attention:
Secretary (telephone no. (402) 330-8900).

                                4

<PAGE>

         
<PAGE>

                                 [Alternate Page For International Prospectus]

                            SUBSCRIPTION AND SALE

   
   The institutions named below (the "Managers") have, pursuant to a
Subscription Agreement dated February 15, 1995 (the "Subscription
Agreement"), severally and not jointly, agreed with the Company to subscribe
and pay for the following respective numbers of International Shares as set
forth opposite their names:

<TABLE>
<CAPTION>
                                                           NUMBER OF
MANAGER                                               INTERNATIONAL SHARES
- -------                                               --------------------
<S>                                                        <C>
CS First Boston Limited ............................        485,000
Bear, Stearns International Limited ................        485,000
Donaldson, Lufkin & Jenrette Securities Corporation         485,000
Deutsche Bank Aktiengesellschaft ...................        100,000
Lehman Brothers International (Europe) .............        100,000
ABN AMRO Bank N.V. .................................         57,500
Credit Lyonnais Securities .........................         57,500
Robert Fleming & Co. Limited .......................         57,500
Oakes, Fitzwilliams & Co. Limited ..................         57,500
Swiss Bank Corporation .............................         57,500
UBS Limited ........................................         57,500
                                                     --------------------
  Total ............................................      2,000,000
                                                     ====================
</TABLE>

    
   The Subscription Agreement provides that the obligations of the Managers
are such that, subject to certain conditions precedent, the Managers will be
obligated to purchase all the International Shares if any are purchased. The
Subscription Agreement provides that, in the event of a default by a Manager,
in certain circumstances the purchase commitments of the non-defaulting
managers may be increased or the Subscription Agreement may be terminated.

   The Company has entered into an Underwriting Agreement (the "Underwriting
Agreement") with the U.S. Underwriters of the U.S. Offering (the "U.S.
Underwriters") providing for the concurrent offer and sale of the U.S. Shares
in the United States and Canada. The closing of the U.S. Offering is a
condition to the closing of the International Offering and vice versa.

   The Company has granted to the Managers and the U.S. Underwriters an
option, exercisable by CS First Boston Corporation, expiring at the close of
business on the 30th day after the date of this Prospectus to purchase up to
2,275,000 additional shares at the public offering price, less the
underwriting discounts and commissions, all as set forth on the cover page of
this Prospectus. Such option may be exercised only to cover overallotments in
the sale of the Shares offered hereby. To the extent that this option to
purchase is exercised, each Manager and each U.S. Underwriter will become
obligated, subject to certain conditions, to purchase approximately the same
percentage of additional shares being sold to the Managers and the U.S.
Underwriters as the number of International Shares set forth next to such
Manager's name in the preceding table bears to the total number of
International Shares in such table and as the number set forth next to such
U.S. Underwriter's name in the corresponding table in the Prospectus relating
to the U.S. Offering bears to the total number of U.S. Shares in such table.

   
   The Company has been advised by CS First Boston Limited, on behalf of the
Managers, that the Managers propose to offer the International Shares outside
the United States and Canada initially at the public offering price set forth
on the cover page of this Prospectus and, through the Managers, to certain
dealers at such price less a commission of $.30 per share and that the
Managers may reallow a commission of $.10 per share on sales to certain other
dealers. After the initial public offering, the public offering price and
commission and reallowance may be changed. Gleacher & Co., Inc. ("Gleacher")
has provided financial advisory services to the Company in connection with
the Magma Acquisition and the Offering including, with respect to the
Offering, participation in the selection of the underwriters and the
negotiation of the underwriting documents. In addition, Gleacher has advised
the Company regarding the pricing of the Offering and related marketing
issues. Gleacher may also participate as a dealer in the sale

    
                               41

<PAGE>

         
<PAGE>

                                 [Alternate Page For International Prospectus]

of the Shares in the Offering. In addition to its fees for advisory services
rendered in connection with the Magma Acquisition and any selling commissions
to which it may be entitled in the Offering, Gleacher received a $100,000 fee
from the Company upon the filing of the Registration Statement with the
Commission, will receive out of the gross underwriting discounts and
commissions (as set forth on the cover page of this Prospectus) a fee in the
amount of 20% of the underwriting fee and will receive from the Company an
incentive fee upon the closing of the Offering (not to exceed $1,500,000)
tied to a formula relating to the Price to Public and PKS (as set forth on
the cover page of this Prospectus).

   The offering price and the aggregate underwriting discounts and
commissions per share and per share commission and re-allowance to dealers
for the International Offerings and the concurrent U.S. Offering will be
identical. Pursuant to an Agreement between the U.S. Underwriters and
Managers (the "Intersyndicate Agreement") relating to the Common Stock
Offering, changes in the offering price, the aggregate underwriting discounts
and commissions per share and per share commission and re-allowance to
dealers will be made only upon the mutual agreement of CS First Boston
Limited, on behalf of the Managers, and CS First Boston Corporation, on
behalf of the U.S. Underwriters.

   Pursuant to the Intersyndicate Agreement, each of the Managers has agreed
that, as part of the distribution of International Shares and subject to
certain exceptions, it has not offered or sold, and will not offer to sell,
directly or indirectly, any shares of Common Stock or distribute any
prospectus relating to the Common Stock in the United States or Canada or to
any other dealer who does not so agree. Each of the U.S. Underwriters has
agreed that, as part of the distribution of the U.S. Shares an subject to
certain exceptions, it has not offered or sold and will not offer or sell,
directly or indirectly, any shares of Common Stock or distribute any
prospectus relating to the Common Stock to any person outside the United
States and Canada or to any dealer who does not so agree. The foregoing
limitations do not apply to stabilization transactions or to transactions
between the Managers and the U.S. Underwriters pursuant to the Intersyndicate
Agreement. As used herein, "United States" means the United States of America
(including the States and the District of Columbia), its territories,
possessions and other areas subject to its jurisdiction, "Canada" means
Canada, its provinces, territories, possessions and other areas subject to
its jurisdiction, and an offer or sale shall be in the United States or
Canada it is made to (i) any individual resident in the United States or
Canada or (ii) any corporation, partnership, pension, profit-sharing or other
trust or other entity (including any such entity acting as an investment
adviser with discretionary authority) whose office most directly involved
with the purchase is located in the United States or Canada.

   Pursuant to the Intersyndicate Agreement, sales may be made between the
Managers and the U.S. Underwriters of such number of shares of Common Stock
as may be mutually agreed upon. The price of any shares so sold will be the
public offering price less such amount agreed upon by CS First Boston
Limited, on behalf of the Managers, and CS First Boston Corporation, as
representative of the U.S. Underwriters, but not exceeding the selling
concession applicable to such shares. To the extent there are sales between
the Managers and the U.S. Underwriters pursuant to the Intersyndicate
Agreement, the number of shares of Common Stock initially available for sale
by the Managers or by the U.S. Underwriters may be more or less than the
amount appearing on the cover page of this Prospectus. Neither the Managers
nor the U.S. Underwriters are obligated to purchase from the other any unsold
shares of Common Stock.

   Each of the Managers and the U.S. Underwriters severally represents and
agrees that (1) it has not offered or sold, and will not offer or sell, in
the United Kingdom, by means of any document, any shares of Common Stock
other than to persons whose ordinary business it is to buy or sell shares or
debentures, whether as a principal or agent, or in circumstances which do not
constitute an offer to the public within the meaning of the Companies Act
1985, (2) it has complied and will comply with all applicable provisions of
the Financial Services Act of 1986 with respect to anything done by it in
relation to any shares of Common Stock in, from or otherwise involving the
United Kingdom, and (3) it has only issued or passed on and will only issue
or pass on to any person in the United Kingdom any document received by it in
connection with the issue of any shares of Common Stock if the person is of a
kind described in Article

                               42

<PAGE>

         
<PAGE>

                                 [Alternate Page For International Prospectus]

9(3) of the Financial Services Act 1986 (Investment Advertisements)
(Exemptions) Order 1988 (as amended by Article 6(c) of the Financial Services
Act of 1986 (Investment Advertisements) Order 1992) or is a person to whom
the document may otherwise lawfully be issued or passed on.

   The Company and its officers and directors agreed that they will not
offer, sell, contract to sell, pledge or otherwise dispose of, directly or
indirectly, or file with the Securities and Exchange Commission a
registration statement under the Securities Act relating to, any additional
shares of its Common Stock or securities convertible or exchangeable into or
exercisable for any shares of its Common Stock without the prior written
consent of CS First Boston Corporation for a period of 90 days after the date
of this Prospectus, except issuances pursuant to the exercise of employee
stock options outstanding on the date hereof or pursuant to the conversion of
the Company's Debentures or its Series C Preferred Stock.

   The Company has agreed to indemnify the Managers and the U.S. Underwriters
against certain liabilities or to contribute to payments that the Managers
and the U.S. Underwriters may be required to make in respect thereof.

   Each of Bear, Stearns & Co., Inc., Donaldson Lufkin & Jenrette Securities
Corporation and Lehman Brothers Inc. were underwriters of the Company's
$529,640,000 senior discount notes offering in March 1994.

   Lehman Brothers Inc. has provided financial advisory services to the
Company in connection with the Magma Acquisition.

   Credit Suisse, an affiliate of CS First Boston, has provided certain
credit facilities and commercial banking services to the Company and its
subsidiaries from time to time and is the agent bank in connection with the
Tender Facility and the Merger Facilities. The Company is currently indebted
to Credit Suisse in the amount of $245.6 million under the Tender Facility.
Such loan is secured by a pledge to Credit Suisse of the 12,600,000 shares of
Magma Common Stock owned by CE Sub. The Company is currently in compliance
with the terms and conditions contained in the Tender Facility. Certain of
the net proceeds of the Offering may be deemed to be used to repay some
portion of the Tender Facility. Accordingly, the Offering is being made in
accordance with the requirements of Section 44(c) (8) of Article III of the
Rules of Fair Practice of the National Association of Securities Dealers,
Inc. The decision of CS First Boston to underwrite the Offering was made
independently of Credit Suisse, which had no involvement in determining
whether or when to underwrite the Offering or the terms of the Offering. CS
First Boston will not receive any benefit from the Offering other than its
respective portion of the gross underwriting discounts and commissions as set
forth on the cover page of this Prospectus.

   1,500,000 shares of Common Stock being offered pursuant to this Prospectus
are expected to be purchased by PKS from the Company in the Direct Sale at a
price equal to the Price to Public and PKS set forth on the cover of this
Prospectus. PKS has indicated an intention to acquire such shares, subject to
receipt and review by PKS of a final Prospectus and conditioned upon the
closing of the Offering.

                                LEGAL MATTERS

   Certain legal matters with respect to the validity of the securities
offered hereby will be passed upon for the Company by Willkie Farr &
Gallagher, One Citicorp Center, 153 East 53rd Street, New York, New York
10022. Chadbourne & Parke, 30 Rockefeller Plaza, New York, New York 10112,
will pass on certain legal matters for the U.S. Underwriters and the Managers
in connection with the Offering.

                                   EXPERTS

   The financial statements and the related financial statement schedules of
the Company and its subsidiaries incorporated in this Prospectus by reference
to the Company's 1993 10-K have been audited by Deloitte & Touche,
independent auditors, as stated in their reports (which reports express an
unqualified opinion and include an explanatory paragraph referring to the
Company's adoption effective January 1, 1993, of Statement of Financial
Accounting Standards No. 109, "Accounting for Income

                               43

<PAGE>

         
<PAGE>

                                 [Alternate Page For International Prospectus]

Taxes") which are incorporated herein by reference, and have been so
incorporated in reliance upon the reports of such firm given upon their
authority as experts in accounting and auditing.

   With respect to the unaudited interim financial information for the
periods ended March 31, 1993 and 1994, June 30, 1993 and 1994, and September
30, 1993 and 1994, incorporated herein by reference, Deloitte & Touche LLP
have applied limited procedures in accordance with professional standards for
a review of such information. However, as stated in their reports included in
the Company's Quarterly Reports on Form 10-Q for the quarters ended March 31,
1994, June 30, 1994 and September 30, 1994 and incorporated by reference
herein, they did not audit and they do not express an opinion on that interim
financial information. Accordingly, the degree of reliance on their reports
on such information should be restricted in light of the limited nature of
the review procedures applied. Deloitte & Touche LLP are not subject to the
liability provisions of Section 11 of the Securities Act for their reports on
the unaudited interim financial information because those reports are not
"reports" or a "part" of a registration statement prepared or certified by an
accountant within the meaning of Sections 7 and 11 of the Act.

   The consolidated balance sheets of Magma and subsidiaries as of December
31, 1993 and 1992 and the related consolidated statements of operations,
changes in stockholders' equity, and cash flows for each of the three years
in the period ended December 31, 1993 and the Statement of Net Assets
Acquired as of March 31, 1993 and the Historical Summaries of Gross Revenues
and Direct Operating Expenses for each of the three years in the period ended
December 31, 1992 of the Imperial Valley Geothermal Interests, incorporated
by reference in this Prospectus have been incorporated herein in reliance on
the reports of Coopers & Lybrand, independent accountants, given on the
authority of that firm as experts in accounting and auditing.

                               44


<PAGE>

         



                APPENDIX FOR GRAPHIC AND IMAGE MATERIAL

        Graphics or images which cannot be reproduced in the ASCII format
required for EDGAR have been omitted from the pages of the preceding document as
listed below. Pursuant to Rule 304 of Regulation S-T, the substantive
information contained in these graphics or images is conveyed in tabular and/or
narrative form:


Page in
Typeset Copy                  Description
- ------------                  -----------
Inside front cover of
International Prospectus        California Energy Company, Inc.'s Planned
                                Project Development; Development and Capacity
                                Implementation Schedule; Chart listing
                                facilities with MW capacity; Map
                                [Datapoints/tables are provided in place of the
                                graphics inside the front cover of this EDGAR
                                file, as necessary, to disclose material
                                content of said graphics.]

18                              Schematic representing Geothermal Energy

19                              Map depicting areas of Potential Geothermal
                                Activity

25                              Map of the Republic of the
                                Philippines with Project locations

29                              Map of Indonesia and Neighboring
                                Countries with Project locations

32                              Map of the Western United States
                                with Project locations

Inside back cover of
International Prospectus        Photographs of (a) Navy I Facility at the