NORTHEAST UTILITIES SYSTEM
U-1/A, EX-99.4, 2000-10-20
ELECTRIC SERVICES
Previous: NORTHEAST UTILITIES SYSTEM, U-1/A, EX-99.3, 2000-10-20
Next: OKLAHOMA GAS & ELECTRIC CO, 424B2, 2000-10-20






EXHIBIT D 3.3.2



STATE OF MAINE                                           Docket No. 2000-803
PUBLIC UTILITIES COMMISSION
                                                         October 3, 2000

PUBLIC SERVICE COMPANY OF                                ORDER
NEW HAMPSHIRE, Request For Approval
Of Reorganization


               WELCH, Chairman; NUGENT and DIAMOND, Commissioners

I. SUMMARY

   Pursuant to 35-A M.R.S.A. Section 708, we approve a reorganization that
will occur when Public Service Company of New Hampshire (PSNH) creates a
wholly-owned, limited liability company (referred to herein as SPE). Creation
of SPE is required in connection with the securitization of PSNH's stranded
costs and the issuance of rate reduction bonds, which are integral parts of
the restructuring of the electric industry in New Hampshire.

II. DISCUSSION AND DECISION

   On September 22, 2000, PSNH requested our approval of a reorganization in
which it will create a wholly-owned limited liability company, SPE. This
Commission has previously determined that PSNH is a "public utility" in Maine
subject to the jurisdiction of the Maine Public Utilities Commission because
PSNH owns property in Maine, which is defined as "transmission and
distribution plant" under 35-A M.R.S.A. Section 102(20-A). This primarily
consists of transmission lines. See Public Service Co. of New Hampshire,
Request for Exemption of 35-A M.R.S.A. Section 708(2)(A), Docket No. 2000-46
(Mar. 17, 2000) (listing PSNH's T & D properties in Maine). Under 35-A
M.R.S.A. Section 708, the Commission must approve utility reorganizations. No
reorganization may be approved unless the Commission finds that "the
reorganization is consistent with the interests of the utility's ratepayers
and investor." Also in approving any reorganization, the Commission must
assure that "the ability of the utility to provide safe, reasonable and
adequate service is not impaired." 35-A M.R.S.A. Section 708(2)(A)(4).

   Creation of the SPE subsidiary is an integral part of the electric
industry restructuring that resulted from legislation and a settlement
agreement negotiated by PSNH, the Governor of New Hampshire, various New
Hampshire agencies and the staff of the New Hampshire Public Utilities
Commission. The New Hampshire Public Utilities Commission approved the
settlement and recently issued an order that will allow the reorganization to
take place. Public Service Company of New Hampshire, DE 99-099, Order No.
23,550, Proposed Restructuring Settlement, Order Addressing Financing Issues
(Sept. 8, 2000).

   As noted above, PSNH's contacts with the State of Maine are extremely
limited.  While it owns and operates certain transmission and distribution
plant in Maine, it does not provide retail service to any customers in Maine
nor does it receive any compensation in Maine as a result of the properties
it owns in Maine. Our primary interest is in assuring that PSNH maintains its
T&D plant in Maine in a safe and reasonable manner.

   Because PSNH's contacts are so limited, we believe we can adequately
discharge our responsibilities under section 708 by approving the
reorganization based on the New Hampshire Public Utilities Commission's
approval. We expect that the reorganization will not affect PSNH's ability to
maintain its T&D plan in Maine in a safe and reasonable manner and in
accordance with the National Electric Safety Code, as required by 35-A
M.R.S.A. Section 2305-A(2).

   Accordingly, we approve the reorganization as described in PSNH's request
dated September 22, 2000.


               Dated at Augusta, Maine, this 3rd day of October, 2000.

                                BY ORDER OF THE COMMISSION

                                    Dennis L. Keschl
                                  Administrative Director


COMMISSIONERS VOTING FOR:   Welch
                            Diamond

COMMISSIONER ABSENT:        Nugent



                        NOTICE OF RIGHTS TO REVIEW OR APPEAL

   5 M.R.S.A. Section 9061 requires the Public Utilities Commission to give
each party to an adjudicatory proceeding written notice of the party's rights
to review or appeal of its decision made at the conclusion of the
adjudicatory proceeding. The methods of review or appeal of PUC decisions at
the conclusion of an adjudicatory proceeding are as follows:

1.  Reconsideration of the Commission's Order may be requested under Section
1004 of the Commission's Rules of Practice and Procedure (65-407 C.M.R.110)
within 20 days of the date of the Order by filing a petition with the
Commission stating the grounds upon which reconsideration is sought.

2.  Appeal of a final decision of the Commission may be taken to the Law
Court by filing, within 30 days of the date of the Order, a Notice of Appeal
with the Administrative Director of the Commission, pursuant to 35-A M.R.S.A.
Section 1320(1)-(4) and the Maine Rules of Civil Procedure, Rule 73, et seq.

3.  Additional court review of constitutional issues or issues involving the
justness or reasonableness of rates may be had by the filing of an appeal
with the Law Court, pursuant to 35-A M.R.S.A. Section 1320(5).

Note: The attachment of this Notice to a document does not indicate the
Commission's view that the particular document may be subject to review or
appeal. Similarly, the failure of the Commission to attach a copy of this
Notice to a document does not indicate the Commission's view that the
document is not subject to review or appeal.




© 2022 IncJournal is not affiliated with or endorsed by the U.S. Securities and Exchange Commission