                In the Matter of                  :
                                                  :
      PUBLIC SERVICE COMPANY OF OKLAHOMA          :  CERTIFICATE
                                                  :
      CENTRAL AND SOUTH WEST CORPORATION          :       OF
                                                  :
               File No. 70-8711                   :  NOTIFICATION
                                                  :
  (Public Utility Holding Company Act of 1935)    :
- --------------------------------------------------:





      This report is filed under Rule 24 of the Public Utility  Holding  Company
Act of 1935 by Public Service  Company of Oklahoma (PSO) a subsidiary of Central
and South West Corporation  (CSW).  Under HCAR 35-26445 dated December 29, 1995,
it is  required  that PSO  file  semi-annual  reports  providing  the  following
information  with respect to the  activities  related to its  investment in RIKA
Management  Company,  L.L.C.,   Universal  Power  Products,   L.L.C.,  Automated
Substation Development Company,  L.L.C., and RC Training,  L.L.C.  (collectively
referred  to as the  RIKA  Companies):  1) a  description  of all  products  and
services that were developed,  in the process of development or being considered
for development by the RIKA Companies during the period, 2) a description of any
software or ancillary  services provided to PSO by the RIKA Companies during the
period,  3) a statement of any  dividends or interest  paid to PSO, both for the
period and cumulatively, as a result of its debt and equity holdings in the RIKA
Companies, and 4) a statement regarding the nature and consequences of any event
of  default  under  the  development  agreement  occurring  during  the  period,
including any resulting change in the voting interests held by PSO in any of the
RIKA  Companies  and any  exercise  of  control by PSO over the  management  and
affairs of any of the RIKA  Companies.  This report covers the period January 1,
1997 through June 30, 1997.


1) Description of all products and services that were developed,  in the process
of development or being  considered for  development by the RIKA Companies 

                  - The RIKA Companies  continue to develop  new testing modules
                    associated with  "Ultra-test",  its WindowsTM  version relay
                    testing software, released in September 1996.

                  - The  RIKA   Companies  are  Beta  testing   its   substation
                    automation  package.   Currently,  the  RIKA  Companies  are
                    testing at CSW and at a non-affiliated third party site. The
                    substation  package is designed  to provide  remote low cost
                    monitoring to small distribution substations.

                  - The RIKA  Companies  have  completed  the  development of an
                    advanced relay testing training school which began bimonthly
                    operations in May 1997.

                  - The RIKA  Companies  are in  the  process  of  developing  a
                    software database that can be used to integrate the multiple
                    substation/relay  maintenance and testing software  programs
                    available  on the market.  The product  should be  completed
                    before  the end of the  third  quarter  of  1997.  The  RIKA
                    Companies  have begun  marketing  this product to several of
                    its existing customers.


2) Description of any software or ancillary services provided to PSO by the RIKA
Companies

                  - CSW is in the process of  purchasing  the  Ultra-test  relay
                    testing  package  for  each of its four  electric  operating
                    companies,  including PSO. The purchase and  installation of
                    the testing  package  should be  completed  during the third
                    quarter of 1997.

                  - PSO is  currently  Beta  testing the  substation  automation
                    package at one of its  substations.  Test results  should be
                    available  sometime during the third quarter of 1997. If the
                    test results are successful,  CSW could potentially purchase
                    several  of these  packages  for  installation  in its small
                    remote   substations.   The   RIKA   Companies'   substation
                    automation package has better  capabilities at a lower price
                    than other similar systems CSW evaluated.

3) Statement of any  dividends or interest  paid to PSO, both for the period and
cumulatively

                  - Because of the delay in the release of the  current  version
                    of  Ultra-test,  PSO agreed that the RIKA  Companies  should
                    conserve  its  current  cash  reserves.  As a result,  PSO's
                    current semi-annual interest payment was postponed.  None of
                    the  provisions of the agreement  were modified nor were any
                    other considerations given as a result of this decision. The
                    amount of the interest  payment  deferred was $45,874 with a
                    cumulative  amount of  $91,748  postponed  thus far.  During
                    1996,  PSO  received  one  interest  payment  from  the RIKA
                    Companies in the amount of $45,874.

                  - The RIKA  Companies  paid no  dividends  to PSO  during  the
                    reporting period.

4) Statement regarding the nature and consequences of any event of default under
the Development Agreement

                    No events of default occurred during the reporting period.



<PAGE>



                                S I G N A T U R E


        As requested by order of this Commission  pursuant to the Public Utility
Holding Company Act of 1935,  Public Service Company of Oklahoma has duly caused
this report to be signed on its behalf on this 21th day of August 1997.

                                         Public Service Company of Oklahoma

                                         /s/    R. Russell Davis
                                         R. Russell Davis
                                         Controller and Chief
                                         Accounting Officer