BROKEN HILL PROPRIETARY CO LTD
6-K, 2000-08-09
STEEL WORKS, BLAST FURNACES & ROLLING MILLS (COKE OVENS)
Previous: REDWOOD MORTGAGE INVESTORS VI, 10-Q, EX-27, 2000-08-09
Next: NATIONAL SECURITIES CORP/WA/, SC 13D/A, 2000-08-09

BHP

News Release


Release Time  IMMEDIATE
Date                   24 July 2000
Number         74/00

THE BROKEN HILL PROPRIETARY COMPANY LIMITED
QUARTERLY REPORT ON EXPLORATION AND DEVELOPMENT

April 2000-June 2000

 

This report covers exploration and development activities for the quarter ended June 30, 2000.

Unless otherwise stated, BHP’s interest in the projects referred to in this report is 100%.

 

DEVELOPMENT PROJECTS

The following projects are in various stages of construction and/or development:



MINERALS

Escondida Phase IV Expansion, Chile (BHP 57.5% interest)

The current engineering and procurement phase for the proposed 110 000 tonnes per day sulfide concentrator reached 88% completion during the quarter. The joint venture partners continued to evaluate the final feasibility study and the project will be presented for approval in the coming months.

HBI Joint Venture, Iron Ore, Venezuela (BHP 50% interest)

Production from two trains on Module 1 commenced on May 29 and commissioning is in progress. Early results relating to performance and briquette quality are encouraging.

Mechanical construction on Module 2 is complete and electrical and instrumentation installation is underway. Commissioning is scheduled to commence late in the first quarter of next fiscal year.

The construction project's lost time frequency rate stands at 0.82.

San Juan Underground, New Mexico, USA (BHP 100% interest)

Evaluation of the proposed San Juan Underground coal mine continued during the quarter. Work continued on the completion of the feasibility study including technical peer review, geotechnical and ventilation studies plus third party reviews of safety, health and environmental issues. Submission of the project for development approval will be dependent on successful negotiation of an agreement with the San Juan Generating Station owners and completion of the project feasibility study.

 

PETROLEUM

Typhoon, Gulf of Mexico (BHP 50% interest, non-operated)

The Typhoon development, consisting of the subsea completion and tieback of the four existing appraisal wells to a mini tension leg platform (TLP), is being developed jointly by Chevron (50%, operator) and BHP (50%). Peak production of 40 000 bopd and 60 mmscfd (gross) is expected, with first production scheduled for third quarter 2001.

Construction began in April and May on the Typhoon mini TLP hull and topsides at McDermott’s yard in Morgan City, Louisiana, for installation second quarter 2001. Work progressed on the fabrication of the four subsea production wellheads that will be installed as part of the well completion activities beginning in September 2000.

Oil and gas export transportation contracts were signed by both partners and Coastal Corporation to provide infrastructure that will tie-in to existing shelf export networks.

Griffin, Australia (BHP 45% interest, operated)

Over the period the Scindian 3 infill well was drilled and penetrated a 26 metre oil column. The well was tested at 6370stb/d. The Griffin 8 infill well encountered a larger than predicted oil column of 63 metres and was tested in excess of 8000stb/d although the true potential was not realised because of equipment limitations on the rig. The importance of the Griffin 8 result suggests the presence of larger than previously estimated in-place and recoverable volumes. These results will be evaluated in combination with further data collection to reassess the potential of the Griffin Field and the need for further development and/or drilling. Additional reserves are expected to be booked in FY2001.

In June a Diving Support Vessel was mobilised to the field to complete the subsea tie back of these wells and at the end of the period work was nearly complete with both wells expected to be in production by mid July. Additional infill and exploration prospects in the Griffin permit and other nearby permit areas are under evaluation and additional drilling and/or development proposals are likely to be made in FY2001.

Keith, North Sea (BHP 31.83% interest, operated)

During this period the Keith Project achieved two major milestones with the successful completion of the tie-in work at the Bruce Phase II Subsea Manifold in preparation for the pipeline bundle installation in August, and the installation of the Christmas tree overtrawlable structure at the Keith well location.

Other activities have focussed on the fabrication of the bundle at Halliburton’s Subsea site at Wick in the North of Scotland, and the manufacture of the Christmas tree at Kvaerner’s works in Aberdeen. The bundle is on schedule to be launched on 4-5 August. The Christmas tree is due to have completed all of its System Integration Testing and Stack-up Testing by the end of July in readiness for the mobilisation of the John Shaw drilling rig at the end of August or early September 2000. The project is within budget and first oil is projected between mid-October and early November depending on the arrival of the John Shaw.

Zamzama Extended Well Test, Pakistan (BHP 38.5% post commerciality equity, operated)

In 1998 BHP discovered the Zamzama gas field on the Dadu Concession, Sindh Province, with the successful exploration well Zamzama-1/ST1. An appraisal program comprising 2D/3D seismic and an appraisal well was completed in 1999.

In February 1999 BHP obtained approval from the Government of Pakistan to carry out an Extended Well Test (EWT). In April 2000 BHP and its Joint Venture partners executed a gas sales and purchasing agreement with Sui Southern Gas Company Ltd for the supply of up to 70 MMscfd of gas for 21 months. The EWT project, at a capital cost of US$8.8 million (BHP share), is a precursor to the field development. Execution is under way with first gas planned for April 2001.

On 31 May 2000 BHP submitted to the Pakistan authorities the Notice of Commercial Discovery, an Application for a Development and Production Lease and the preliminary Development Plan for the Zamzama gas discovery. BHP is continuing the aggressive market capture activities and subject to timing and the volume of market capture it envisages a two phased development.

ROD Integrated Oil Field Development, Algeria (BHP 17.3% interest. Joint operating entity comprising SONATRACH/BHP /AGIP)

During the quarter BHP announced the development of the Rhourde Oulad Djemma (ROD) 300 million barrel (gross) integrated oil field development in the Berkine Basin of Algeria.

BHP’s partners in the US$500 million development are the Algerian State oil company SONATRACH and AGIP Algeria Exploration BV (the Algerian operating company of ENI SpA). A total of five fields will be developed - ROD, SFNE, RERN, BSF and RDB - all of which are located in Blocks 401a/402a. A Unitisation Agreement has been put in place to give joint operatorship and commercial arrangements for the development, giving BHP approximately 17 per cent of overall project reserves. After grossing for Algerian taxes, BHP’s net share is around 60 million barrels of the proven and probable hydrocarbon reserves.

The fields will be developed via a new dedicated processing train which will be built at AGIP and SONATRACH’s existing BRN production facility on Block 403. From there, oil will be exported via the established pipeline infrastructure to terminals located on the Algerian coast. The associated gas will be reinjected underground. BHP’s share of the US$500 million investment cost will be around US$190 million.

First production from the fields is scheduled for the first half of 2003, with a gross peak production rate of 80 000 barrels per day. The development and operations will be conducted by joint operating entities comprising BHP, AGIP and SONATRACH.

Ohanet Development, Algeria (BHP 60% interest. Joint operating entity comprising SONATRACH/BHP)

On 3 July BHP announced that it had signed a Risk Service Contract (RSC) with SONATRACH, the Algerian national oil company for the development of four gas/condensate reservoirs in the Ohanet region of Algeria. The participants in the venture are BHP 60%, Japan Ohanet Oil & Gas Co Ltd, 30% and Petrofac Resources (Ohanet) LLC, 10%.

The total cost of developing the Ohanet reservoirs will be around US$1.0 billion (BHP share US$618 million). In return the participants will be entitled to recover their investment - together with an agreed fixed profit consideration - over a target eight year period from the start of production. The Ohanet fields are estimated to contain total proven and probable reserves exceeding 3.4 trillion cubic feet of pipeline quality gas, 107 million barrels of condensate and 116 million barrels of LPG. The structure of the RSC means that BHP’s reserves entitlement fluctuates with movements in hydrocarbon prices and the company expects to book proved reserves in the range of 55 million to 75 million barrels of oil equivalent.

First production is scheduled for October 2003 and peak liquids production will be around 58 000 barrels per day. BHP’s revenue is taken from its share of condensate and LPG produced.

 

EXPLORATION

The Discovery Group of BHP Minerals carries out worldwide grass-roots exploration for all BHP's minerals businesses. During the quarter, a process of re-organisation, to align the Discovery Group with the BHP Minerals portfolio management model, was completed.

The Discovery Group is also responsible for exploration and development work related to existing mines.

 

MINERALS

Copper Projects

Agua Rica, Argentina (BHP 70% interest)

The joint venture is continuing to evaluate development options for the project that may reduce capital and operating costs. Activity at the field site was limited to environmental monitoring and tenement management.

Escondida Norte, Chile (BHP 57.5% interest)

Geological and metallurgical studies continued during the quarter. Attention was focused on mineralogical modelling, trace metal distribution studies and clay mineral studies. A detailed structural evaluation of the deposit and the sidewall sampling of the decline were completed.

Geotechnical drill holes and a restricted close spaced (50m) in-fill program are planned to commence in July. Database compilation of all data since the Phase 2 resource model (1998) is underway.

An environmental team is preparing the bidding documents for the Environmental Impact Study.

Tintaya Oxide Project, Peru

During the quarter, work continued on updating the feasibility study and on other engineering activities. Estimates are being reviewed and completion of a final feasibility study is expected during the next quarter.

Subject to approval, construction of the Oxide Project will take approximately 15 months. Annual production is expected to peak at 34 000 metric tonnes of Grade 'A' cathode at a direct cash cost of less than 40 cents per pound.

Tintaya Antapaccay Project, Peru

The drilling program to further evaluate the potential of the project, which started in January, was completed during the quarter. Drilling on the project now totals 79 500 metres. Metallurgical test-work indicates that all ore types respond well to flotation and concentration. Assessment of development options, based on a project with a stand-alone concentrator processing between 30 000 to 60 000 tonnes per day of ore, is continuing.

 

Coal Projects

 

Revision of Queensland Coal Resources & Reserves

BHP Queensland Coal has completed a major review of Coal Resources and Reserves for the mines it operates in Queensland on behalf of the Central Queensland Coal Associates (CQCA) Joint Venture, Gregory Joint Venture and BHP Mitsui Coal Pty Ltd.

The various joint ventures are made up as follows:

CQCA joint venture

- BHP (52.1%)
- QCT Resources Limited Group (32.37%)
- Mitsubishi Development Pty Ltd (15.53%).

Gregory Joint Venture

- BHP (64.14%),
- QCT Resources Limited Group (32.37%)
- Mitsubishi Development Pty Ltd (3.49%)

BHP Mitsui Coal Pty Ltd

- BHP (80%),
- Mitsui and Co. Ltd. (Japan) (13.3%)
- Mitsui and Co. Ltd. (Australia) (6.7%)
 

The process for estimating coal reserves and resources for the mines managed by BHP Queensland Coal complies with the standards mandated in the JORC Code (1999 Edition of Australasian Code for Reporting of Minerals Resources and Ore Reserves).

The estimates represent the first major review of resources and reserves for the mines since May 1997.

The 1999 resources and reserves estimates for undeveloped deposits are re-stated, since more recent exploration and mine planning studies have not been conducted. Deposit models for all mines have been re-generated and in some cases the deposit geology has been re-interpreted.

A more rigorous interpretation of the Measured, Indicated and Inferred resource confidence levels and the definition of the term "reasonable prospects of eventual economic extraction" have, in some cases, resulted in a movement of coal to lower confidence levels or a reduction in the resource base. Significant increases in the estimates of the reserve base are due to a change in the method of determining the economic cut-off, which is now based on a breakeven analysis (current average coal prices less FOB cash costs and sustaining capital).

In the past various forms of cut-off were applied, including depth and strip ratio. The only underground reserves quoted are for Crinum. Given that the feasibility studies for underground development at Goonyella and Saraji have not been completed, it has not been possible to include underground reserves for these projects at this time.

Marketable Coal Reserves and Total Coal Resources for the mines and undeveloped deposits managed by BHP Queensland Coal at 30 June 2000, compared to the previous 31 May 1999 estimates, are shown in the following tables:

 
Marketable Coal Reserves (Million Tonnes)
 
June 2000
May 1999
 
Total
BHP Share
Total
BHP Share
Reserves at mines        
CQCA JV (52.1 % BHP)        
Goonyella
606.2
315.8
136.7
71.2
Peak Downs
564.0
293.8
239.5
124.8
Saraji
116.9
60.9
126.5
65.9
Norwich Park
48.7
25.4
74.3
38.7
Blackwater
250.6
130.6
162.9
84.9
Sub-total
1586.4
826.5
739.9
385.5
         
GREGORY JV (64.14 % BHP)        
Gregory
16.9
10.8
24.2
15.5
Crinum
61.1
39.2
69.4
44.5
Sub-total
78.0
50.0
93.6
60.0
         
BHP Mitsui (80 % BHP)        
Riverside
13.8
11.0
14.3
11.4
South Walker Ck
66.2
53.0
78.0
62.4
Sub-total
80.0
64.0
92.3
73.8
         
Total reserves at mines
1744.4
940.5
925.8
519.4
         
Undeveloped reserves        
CQCA JV (52.1 % BHP)      
 
Daunia
47.1
24.5
47.1
24.5
         
BHP Mitsui (80 % BHP)      
 
Poitrel/Winchester
71.4
57.1
71.4
57.1
Nebo West
15.9
12.7
15.9
12.7
Sub-total
87.3
69.8
87.3
69.8
   
 
 
 
Total undeveloped reserves
134.4
94.4
134.4
94.4
Total reserves
1878.8
1034.9
1060.2
613.7

 
 Total Coal Resources (Million Tonnes)*
 
 June 2000
May 1999 
 
Measured
Indicated
Inferred
Total
BHP Share
Total
BHP Share
               
Resources at mines              
CQCA JV (52.1 % BHP)              
Goonyella
1396
278
14
1689
880
1943
1012
Peak Downs
1366
362
224
1951
1016
1441
751
Saraji
464
88
9
561
292
717
374
Norwich Park
407
124
39
569
297
561
292
Blackwater
491
253
272
1016
529
1078
562
Sub-total
4124
1105
557
5786
3014
5740
2991
               
GREGORY JV (64.14 % BHP)              
Gregory Crinum
218
29
2
249
159
279
179
               
BHP Mitsui (80 % BHP)              
Riverside
27
   
27
21
26
20
South Walker Ck
80
45
353
478
382
410
328
Sub-total
107
45
353
504
403
435
348
               
Total resources at mines
4449
1178
912
6539
3577
6284
3408
               
Undeveloped resources              
CQCA JV (52.1 % BHP)              
Red Hill
90
406
306
801
417
167
87
Daunia
165
39
 
204
106
204
106
Peak Downs East  
668
104
772
402
175
91
Sub-total
255
1113
410
1777
926
546
284
               
GREGORY JV (64.14 % BHP)              
Liskeard
13
   
13
8
13
8
               
BHP Mitsui (80 % BHP)              
Wards Well
331
289
 
620
496
817
654
Lancewood  
225
 
225
180
78
62
Bee Creek
77
54
 
131
105
131
105
Nebo West  
178
 
178
142
178
142
Poitrel/Winchester
310
15
4
328
262
328
262
Sub-total
717
760
4
1482
1185
1531
1225
   
 
 
 
 
 
 
Total undeveloped resources
985
1873
414
3271
2119
2090
1517
Total resources
5434
3051
1326
9810
5696
8373
4926
 * Total coal resources shown are inclusive of coal reserves

The relevant competent persons are Douglas L. J. Dunn and Brian W. Cox,

Goonyella Mine, Queensland (BHP 52.1% interest)

Exploratory mining of a three-heading Adit in the Middle Seam down-dip from the Goonyella highwall continued. Results so far have generally corroborated the interpretations made from surface drilling and seismic surveys. At the end of June a total of 8 759 metres of development had been completed out of a projected total of 13 079 metres.

Small scale faulting has delayed development and led to a budget overrun of about 10%. It is now expected the adit will be completed in December, two months behind schedule. Feasibility studies for a proposed longwall mine are on going.

Saraji Mine, Queensland (BHP 52.1% interest)

Exploration activities for the Saraji longwall pre-feasibility study continued. Two-dimensional seismic surveying completed during the quarter confirmed the relative lack of geological structures, which could (if present) negatively impact on any development.

Illawarra Coal, Dendrobium Project

Evaluation of potential mine design layouts and estimation of the capital investment that may be required continued during the quarter. Further geological work, engineering studies and environmental work are required to improve confidence levels before any decision can be made.

 

Iron Ore Projects

Revision of Pilbara Iron Ore Resources and Reserves

BHP Iron Ore has completed a major review of the Mineral Resources and Ore Reserves for its Western Australia Pilbara iron ore interests.

BHP Iron Ore manages several joint ventures in the region:

Mt Newman Joint Venture

- BHP Minerals Pty Ltd 85%
- Mitsui Itochu Iron Pty Ltd 10%
- CI Minerals Australia Pty Ltd 5%

Mt Goldsworthy Mining Associates

- BHP Minerals Pty Ltd 85%
- Mitsui Itochu Iron Pty Ltd 8%
- CI Minerals Australia Pty Ltd 7%

Yandi Joint Venture - BHP Minerals Pty Ltd 85%

- Mitsui Itochu Iron Pty Ltd 8%
- CI Minerals Australia Pty Ltd 7%

BHP/Renison Joint Venture

- BHP Australia Coal Pty Ltd 77%
- Renison Ltd 23%

BHP Iron Ore also manages the Jimblebar operation which is 100% owned by BHP Minerals Pty Ltd.

There is a significant increase in the Ore Reserves over those reported previously, and Mineral Resources are reported for the first time.

This new reporting is due to a change in reporting practice; past practice was to only report Ore Reserves for operating mines and BHP approved developments. The BHP June 2000 Annual Report will bring all of BHP’s Minerals Resource and Ore Reserve reporting into line with standards outlined in the updated JORC Code (1999 Edition of Australasian Code for Reporting of Mineral Resources and Ore Reserves).

Minerals Resources and Ore Reserves for the BHP’s Pilbara Ore interests as at end June 2000 are shown the following tables:

 

Ore Reserves for Pilbara Iron Ore  
 

as at end June 2000

Proved Ore Reserve

as at end June 2000

Probable Ore Reserve

as at end June 2000

Total Ore Reserves

Compared

with 1999
Area Ore Type

Tonnes
(millions)

Grade Tonnes
(millions)
Grade Tonnes
(million)
Grade Tonnes
(millions)
Grade
     
Fe %
P %
 
Fe %
P %
 
Fe %
P %
 
Fe %
Mt Newman JV B loP HG
479
65.0
0.05
165
65.3
0.05
644
65.1
0.05
   
(BHP 85% interest) B loP LG
214
58.5
0.08
78
58.2
0.09
292
58.4
0.08
   
  B hiP HG
134
63.0
0.12
6
61.5
0.12
141
62.9
0.12
   
  B hiP LG
61
59.7
0.12
     
61
59.7
0.12
   
  M loP HG
81
62.3
0.07
     
81
62.3
0.07
   
  M loP LG
12
59.1
0.06
     
12
59.1
0.06
   
Total
 
981
 
 
249
   
1230
 
 
695
63.4
         
 
     
 
     
Jimblebar B loP HG
111
63.3
0.06
39
63.2
0.06
150
63.3
0.06
   
(BHP 100% Interest) B loP LG
57
59.6
0.07
18
59.4
0.07
75
59.6
0.07
   
  B hiP HG
11
63.3
0.11
3
63.3
0.11
15
63.3
0.11
   
  B hiP LG
11
60.2
0.11
3
60.2
0.11
14
60.2
0.11
   
Total
 
191
 
 
63
 
254
 
 
52
62.1
         
 
 
 
 
     
Mt. Goldsworthy JV Y loP HG
18
65.8
0.03
1
64.7
0.04
20
65.7
0.03
   
(BHP 85% Interest) Y loP LG
4
58.2
0.04
1
58.9
0.05
5
58.3
0.04
   
  Yc loP HG
0
63.9
0.04
-
-
-
0
63.9
0.04
   
  Yc loP LG
6
59.2
0.04
-
-
-
6
59.2
0.04
   
  Yd loP H
2
63.4
0.06
-
-
-
2
63.4
0.06
   
  Yd loP LG
4
61.0
0.07
-
-
-
4
61.0
0.07
   
  M loP HG
128
63.4
0.06
23
63.4
0.06
151
63.4
0.06
   
  M loP LG
32
58.6
0.07
6
58.6
0.07
38
58.6
0.07
   
Total
 
196
   
31
   
226
   
39
62.4
     
 
 
 
         
 
 
Yandi JV C loP HG
658
58.4
0.05
159
58.2
0.04
817
58.4
0.05
198
58.4
(BHP 85% Interest)                        
 

Relevant Competent Person is P. Schultz. Totals have been rounded.

 
Total Mineral Resources for Pilbara Iron Ore
   
as at end June 2000 in 100% terms 
   
Measures
Resources
Indicated
Resources
Inferred Resources
Total Resources
Deposit type Tonnes
(millions
Grade
Tonnes
(millions)
 Grade
Tonnes
(millions)
 Grade
Tonnes
(millions)
  Grade
     
%Fe
%P
 
%Fe
%P
 
%Fe
%P
 
%Fe
%P
                           
Newman JV B loP HG 
819
63.1 
0.07
315
63.0 
0.08
5
60.0 
0.06
1,138
63.1 
0.07
(BHP 85% Interest) B loP LG
8
61.7
0.05
13
57.0
0.07
-
-
-
21
58.8
0.06
  B hiP HG
125
63.2
0.11
29
62.4
0.14
42
62.2
0.12
196
62.8
0.12
  B hiP LG
21
61.6
0.10
-
-
-
52
56.8
0.13
73
58.2
0.12
  M loP HG
231
61.1
0.07
25
61.5
0.06
364
61.9
0.07
620
61.6
0.07
  M loP LG
31
57.6
0.05
18
57.1
0.06
266
55.6
0.09
315
55.9
0.08
  D loP HG
-
-
-
11
58.8
0.05
1
61.1
0.03
12
59.0
0.05
Subtotal
 
1,235
 
 
410
 
 
731
   
2376
   
   
 
 
 
 
   
 
   
 
   
Jimblebar B loP HG
279
61.5
0.07
105
61.3
0.08
-
-
-
385
61.4
0.07
(BHP 100% Interest) B loP LG
45
58.4
0.08
-
-
-
-
-
-
45
58.4
0.08
  B hiP HG
-
-
-
7
62.9
0.11
668
62.0
0.13
675
62.0
0.13
  B hiP LG
-
-
-
-
-
-
76
57.6
0.11
76
57.6
0.11
  D loP HG
-
-
-
10
60.1
0.08
7
55.6
0.06
17
58.2
0.07
Subtotal
324
 
123
   
752
 
 
1,199
   
         
 
   
 
         
Goldsworthy JV Y loP HG
32
65.0
0.04
9
62.5
0.04
-
-
-
42
64.5
0.04
(BHP 85% Interest) Yc loP LG
-
-
-
31
58.5
0.06
2
54.2
0.04
33
58.3
0.06
  Yd loP HG
15
61.0
0.09
-
-
-
-
-
-
15
61.0
0.09
  D loP HG
22
58.5
0.07
19
58.5
0.06
5
57.6
0.06
45
58.4
0.07
  B loP LG
-
-
-
27
63.5
0.04
-
-
-
27
63.5
0.04
  B hiP HG
-
-
-
99
62.2
0.15
-
-
-
99
62.2
0.15
  B hiP LG
-
-
-
66
57.8
0.13
-
-
-
66
57.8
0.13
  M loP HG
151
62.8
0.06
131
61.9
0.06
510
61.3
0.06
793
61.7
0.06
  M loP LG
30
58.7
0.06
32
53.8
0.05
35
56.0
0.05
97
56.1
0.06
Subtotal
 
250
   
415
   
552
   
1,216
   
   
 
 
                   
BHP/Renison JV B hiP HG
-
-
-
49
61.1
0.15
67
62.0
0.16
116
61.6
0.16
(BHP 77% Interest) B hiP LG
-
-
-
33
57.5
0.14
18
58.4
0.17
51
57.8
0.15
  M loP HG
-
-
-
29
62.6
0.06
45
63.0
0.07
75
62.8
0.07
  M loP LG
-
-
-
22
57.6
0.05
21
57.5
0.05
43
57.6
0.05
Subtotal
     
 
133
   
151
 
 
284
   
         
 
               
Yandi JV C loP HG
955
58.0
0.04
288
57.5
0.04
234
57.3
0.04
1,477
57.8
0.04
(BHP 85% Interest)                          

Total Mineral Resources are inclusive of Ore Reserves

Relevant Competent Persons are M.Kneeshaw, P.Waters and D.Podmore. Totals have been rounded

 

Iron Ore Type Legend

Brockman ore

B

Yarrie lode ore

Y

High grade ore - see notes

HG

Marra Mamba ore

M

Yarrie crustal ore

Yc

Low grade ore - see notes

LG

Channel Iron Deposits

C

Yarrie detrital ore

Yd

Low phosphorus ore (< 0.1%P)

loP

Detrital ore (lump product)

D

 

 

 

High phosphorus ore (> 0.1%P)

hiP

Explanatory notes to Tables:

          Grades

- Grades listed refer to in-situ (head grade) raw iron (Fe) and phosphorus (P) percentages (%) of the various ore types available within the BHPIO resource portfolio. Ore is defined as high or low phosphorus (P) viz + / - 0.1% P levels.
- High-grade ore is defined at +60%Fe, except for Channel Iron (+54%Fe) and Detrital Ores (+56%Fe). Low-grade ore is defined at ~54-60%Fe.
- The low P Brockman ores represent a core blending source which enables the overall blend of Brockman ores to meet market requirements of max ~ 0.08%P. The balance of high P Brockman ores does not meet current market specifications.
- Detrital ore grade is estimated lump product grade (+6mm) and not the in situ grade, except for the Yarrie Y10 (Yd) deposit, where in situ grade is reported.

Ore Types

- Brockman ores have a martite-(hematite)-goethite mineralogy and are hosted within the Proterozoic Brockman Iron Formation.
- Marra Mamba ores have a martite-(ochreous)-goethite mineralogy and are hosted within the Archaean Marra Mamba Iron Formation.
- Channel Iron Deposits (or pisolites) have a goethite-hematite mineralogy and occur within Tertiary age palaeochannels.
Yarrie lode ores have a martite-hematite mineralogy and are hosted within the Archaean age Nimingarra Iron Formation in the Yarrie area.
- Yarrie crustal ore is low grade, near surface hematitic ore occurring on the Nimingarra Iron Formation in the Yarrie area. This is normally fed to a beneficiation plant for up grading.
- Yarrie detrital ore is a Proterozoic conglomerate hematite ore occurring in the Eel Creek Formation in the Yarrie area. This is normally fed to a beneficiation plant for up grading, but may also be used as direct high grade feed.

Mining Area C, Iron Ore, Western Australia (BHP 85% interest)

Negotiations with registered groups under the Native Title Act Section 29 notice proceeded during the quarter and agreement has been reached with one group pertinent to an infrastructure title. Negotiations are also proceeding to obtain agreements that would allow the mining lease to be issued.

A decision regarding a preferred railway route is still pending.

Other Projects

Ekati Diamonds, Canada (BHP 51% interest)

On-site processing of the Wolverine, Zach, Cougar and Lynx kimberlite samples commenced during the quarter. Sample tonnage estimates were completed for the reverse circulation drill hole samples (35 cm diameter) collected in early 2000. The estimates shown below are based upon hole volumes (from calliper data), lithology logs and dry bulk densities.

Pipe Name

No. Holes

Kimberlite Intersected

Estimated Dry Tonnes

Wolverine

3

628m

130

Zach

1

252m

58

Cougar

2

408.5m

78

Lynx

5

849m

169

 

Exploration core drilling during the quarter intersected four additional kimberlite pipes bringing the total number of confirmed kimberlite occurrences to 125. Three of the discoveries are located within the core zone and one of the discoveries is within the buffer zone claims. None of the new occurrences yielded significant microdiamond results.

Chagai Copper, Pakistan (BHP 75% interest)

On 28 April Mincor Resources NL signed a six month Option Agreement with BHP Minerals which, if exercised, will allow Mincor to enter into an Exploration Alliance with BHP to explore and develop the copper potential of the Chagai Hills region of Pakistan. This Alliance will include the Chagai JV between BHP Minerals and the Government of Balochistan and has received all necessary government approvals.

Gag Island Nickel, Indonesia (BHP 75% interest)

Although announced after the end of the quarter, the following materially relevant information about the Gag Island Nickel Project was released on July 12:

"The Broken Hill Proprietary Company Ltd (BHP) today announced that it had reached agreement with Falconbridge Limited on the formation of a Joint Venture which may lead to development of the Gag nickel laterite project in Indonesia.

The basis of the agreement is that Falconbridge would spend US$75 million to earn a 37.5 per cent interest in the Gag Island nickel project. It is expected the investment would primarily be directed towards completing a Gag Island project feasibility study, to be managed by Falconbridge, over the next 2 years.

A number of substantial matters need to be resolved before the Joint Venture can become effective including:

Following completion of the Falconbridge earn-in, shareholders in the project would be BHP 37.5 per cent, Falconbridge 37.5 per cent and P.T. Aneka Tambang 25 per cent. Currently BHP holds a 75 per cent interest in the project and the remaining 25 per cent stake is held by P.T. Aneka Tambang.

The Gag Island nickel project is located in Republic of Indonesia. The current resource estimate which contains both oxide and silicate laterite zones is tabled below. At this stage there is no commitment to proceed with the project beyond the feasibility study.

Gag Island Mineral Resource Estimate
Resource Class Tonnage* (Mt dry) Nickel Grade Cobalt Grade
Measured 12 million 1.33% 0.09%
Indicated 93 million 1.46% 0.07%
Inferred 135 million 1.3% 0.09%
Total Resource 240 million 1.35% 0.08%
* -The Relevant Competent Person is A. Bailey, totals have been rounded

The Gag Island nickel project is consistent with BHP’s strategy of adding material growth opportunities and further diversifying its minerals asset portfolio. The agreement with Falconbridge delivers on BHP’s stated intention to seek an experienced nickel partner to assist in developing the project."

Exco Alliance, Mt Isa Australia

Drilling to evaluate new targets in the project area has commenced. No further comment will be made in future reports unless there are developments which are materially significant to BHP. Ongoing results of Exco’s work are released by Exco in regular reports to the Stock Exchange and may be found summarised on their web-site (www.exco.com.au)

Falcon Airborne Gravity Gradiometer Technology.

The deployment of BHP's proprietary airborne gravity gradiometer technology (called "Falcon") is proceeding and results from the two aircraft in Australia and North America continue to be very encouraging.

PETROLEUM

Wells drilled during the quarter or in the process of drilling as at June 30, 2000.

WELL

LOCATION

BHP EQUITY

STATUS

Argus-1

AC/P30, Browse Basin, Australia

66.66% Operator

Drilling ahead

Aripo-1

Block 2(c), Northeast coast Trinidad

45% Operator

Gas discovery; Temporarily suspended.

Atlantis-2

Green Canyon Block 743, Gulf of Mexico

44%, BHP well-operator

The well has encountered a significant oil zone in Miocene (M7) sands with net pay in excess of 300 feet. Drilling ahead through additional prospective zones.

RAR-1 bis

Block 401a/402a,

Algeria

45%, Operator

Operations concluded.

Viper-1

Grand Isle Block 106, Gulf of Mexico

40% Operator

Plugged and abandoned at a total depth of 19,204 feet

 

 

EXPENDITURE

Information related to exploration expenditure will be included in the BHP FY2000 Profit Report, released 27 July 2000.

 

COMPETENCE AND RESPONSIBILITY

The following statements apply in respect of the information in this report that relates to any stated Mineral Resources or Ore Reserves.

 

 

For information contact:

Media Relations:

Mandy Frostick – Manager Media Relations
(BH) (61 3) 9609 4157
(AH) (61 3) 9687 6651
Mobile (61) 0419 546 245
Email: [email protected]

Investor Relations:

Robert Porter – Vice President Investor Relations
(BH) (61 3) 9609 3540
Mobile (61) 0419 587 456
Email: [email protected]

Candy Ramsey
BHP Investor Relations Houston
Tel: (713) 961-8640
Email: [email protected]

 

 



© 2022 IncJournal is not affiliated with or endorsed by the U.S. Securities and Exchange Commission