MCN CORP
U-1/A, 1996-02-08
NATURAL GAS DISTRIBUTION
Previous: DEVON ENERGY CORP /OK/, S-3, 1996-02-08
Next: SCUDDER STEVENS & CLARK INC, SC 13G/A, 1996-02-08



                         File No. 70-8731

                          UNITED STATES
                SECURITIES AND EXCHANGE COMMISSION
                      Washington, D.C. 20549



                  PRE-EFFECTIVE AMENDMENT NO. 1

                                TO

                             FORM U-1

                   APPLICATION AND DECLARATION

                            UNDER THE

            PUBLIC UTILITY HOLDING COMPANY ACT OF 1935




                         MCN CORPORATION
                       500 Griswold Street
                     Detroit, Michigan 48226

           (Name of companies filing this statement and
             address of principal executive offices)


                               None

             (Name of top registered holding company
              parent of each applicant or declarant)


                     Daniel L. Schiffer, Esq.
                 Vice President, General Counsel
                          and Secretary
                         MCN Corporation
                       500 Griswold Street
                     Detroit, Michigan 48226

             (Name and address of agent for service)


          The Commission is requested to mail copies of
            all orders, notices and communications to:

                      William S. Lamb, Esq.
              LeBoeuf, Lamb, Greene & MacRae, L.L.P.
                       125 West 55th Street
                  New York, New York 10019-4513



          Pursuant to Section 9(a)(2) and 10 of the Public

Utility Holding Company Act of 1935 (the "Act"), MCN Corporation,

a Michigan corporation ("MCN") hereby requests that the

Securities and Exchange Commission (the "Commission") authorize

the acquisition (the "Acquisition"), as described herein, of a 1%

general partnership interest in Southern Missouri Gas Company,

L.P., a Missouri limited partnership (the "Partnership"), which

will construct, own and operate a gas pipeline and distribution

system (the "System") in southern Missouri that is currently

under construction and owned by Tartan Energy Company of

Missouri, L.C., a Missouri limited liability company ("TEC"). 

Prior to the consummation of the Acquisition, ownership of the

System will be transferred to the Partnership, as described

below.    

          MCN is currently a public utility holding company

exempt from all provisions of the Act except Section 9(a)(2)

under Section 3(a)(1) pursuant to Rule 2.  MCN owns all of the

issued and outstanding common stock of two public utility

companies as defined under the Act:  Michigan Consolidated Gas

Company ("MichCon") and Citizens Gas Fuel Company ("Citizens"),

both of which are organized and operate virtually exclusively in

the state of Michigan.  MCN believes that following the

consummation of the Acquisition and the commercial operation of

the Partnership, it will continue to be a public utility holding

company entitled to an exemption under Section 3(a)(1) of the Act

because the Partnership, which when it begins commercial

operation will be a public utility subsidiary of MCN organized

and operating exclusively in Missouri, will not account for a

material part of MCN's income<F1> and thus, MCN and each

public utility subsidiary from which it derives a material part

of its income will continue to be organized and operating

predominantly in the state of Michigan.  

____________________

<F1> Specifically, under current plans, in its first full year of
     commercial operation (1997), MCN's share of Partnership
     revenue will account for 0.18% of MCN's consolidated
     revenues, which according to current projections, will be
     the highest such percentage reached, and it is projected
     that in 1998, that percentage will decrease to approximately
     0.17%.  Although the term "material part of its income" is
     not defined in the Act, in many instances, holding companies
     with out-of-state utility subsidiaries accounting for an
     equivalent amount of revenues have been permitted to claim
     an exemption under Section 3(a)(1).  For example, in In re
     Yankee Atomic Electric Co., 36 S.E.C. 552 (1948), the
     Commission granted an exemption under Section 3(a)(1) in a
     case where 2% of the holding company's revenues were derived
     from an out-of-state utility subsidiary.  Indeed, the amount
     of income generated by the Partnership and contributed to
     MCN will be well within the traditional parameters of the
     term materiality as discussed in Commission precedent.  See
     e.g., Commonwealth Edison, 28 S.E.C. 172 (1948) (holding
     that utility subsidiary accounting for between 2.7% and 3.3%
     of system revenues is not providing a material part of
     income); Wisconsin Electric Power Company, 28 S.E.C. 909
     (1948) (holding utility subsidiary accounting for 10.31% of
     income and doing substantial business out-of-state is
     material and not predominantly intra-state).


Item 1         DESCRIPTION OF PROPOSED TRANSACTION

               A.   Description of MCN

               MCN was organized in 1988 and is the holding

company for (i) MichCon, a gas utility company as defined under

the Act engaged in the distribution, transmission and storage of

natural gas to approximately 1.1 million customers in Michigan;

(ii) Citizens, a gas utility as defined under the Act and was

acquired by MCN in 1990, is engaged in the distribution of

natural gas in the city of Adrian, Michigan, and (iii) MCN

Investment Corporation, a subsidiary holding company for

nonutility businesses.  As mentioned above, MCN is exempt from

all provisions of the Act except Section 9(a)(2) under Rule

3(a)(1) because both MCN and its material public utility

subsidiaries are organized and conduct virtually all of their

operations in the same state (Michigan).  See, Form U-3A-2,

"Statement by a Holding Company Claiming Exemption under Rule 2

from the Provisions of the Public Utility Holding Company Act of

1935," dated February 24, 1995, filed by MCN and incorporated

herein by reference.  MCN's common stock is publicly traded on

the New York Stock Exchange.  MCN's principal executive office of

located at 500  Griswold Street, Detroit, Michigan  58226.

               B.   Existing Utility Operations

          As mentioned above, MichCon is engaged in the

distribution, transmission and storage of natural gas to

approximately 1.1 million customers in Michigan and Citizens is

engaged in the distribution of natural gas in to the City of

Adrian, Michigan.  MichCon and Citizens provide retail gas

distribution services primarily to residential and small volume

commercial customers and MichCon provides transportation services

to large volume commercial and industrial customers.  MichCon

also provides intrastate transportation services to other gas

utilities, gas marketers and producers.  In the fiscal year ended

December 31, 1994, MCN reported consolidated revenues of

approximately $1,545.8 million, of which amount MichCon's

revenues accounted for $1,111.7 million or 71.9% and Citizens

revenues were $14.4 million or 0.9%.

          Approximately 46% of MichCon's gas supply originates in

the Midcontinent and Southern basins, 40% in Michigan, 10% in

Canada and 4% from other sources.  Similarly, approximately 55%

of Citizen's gas supply originates in the Midcontinent and

Southern basins, 35% in Michigan and 10% in Canada.  MichCon and

Citizens take gas from the Midcontinent and Southern basins

through the ANR and Panhandle pipelines pursuant to firm and

interruptible contracts with these pipelines.

          MichCon is subject to regulation by the Michigan Public

Service Commission (the "Michigan PSC") with regard to rates and

other corporate matters and Citizens is subject to regulation by

the City of Adrian, Michigan with respect to its rates and by the

Michigan PSC with regard to other corporate matters.

               C.   Description of the Proposed Transaction

          MCN has entered into an agreement (the "Formation

Agreement") containing the terms on which MCN intends to acquire

a 1% general partnership interest and a 46.5% limited partnership

interest in the Partnership.  The remaining interests in the

Partnership will be owned as follows:  1% general partnership and

4% limited partnership interest owned by Tartan Management

Company of Missouri, L.C. or its successor ("Tartan") and 47.5%

limited partnership interest owned by Torch Energy Marketing,

Inc. or its successor ("Torch").  Torch, a Delaware corporation,

is a wholly owned subsidiary of Torch Energy Advisors

Incorporated ("TEAI"), which in turn is a wholly owned subsidiary

of United Investors Management, Inc. which is owned by Torchmark

Corporation.  Torchmark Corporation has publicly announced its

intended disposition of TEAI to a newly formed investor group

that includes TEAI management and United Investors Management,

Inc.  The limited liability company interests in Tartan will be

held by three individuals (the "Individuals").  Tartan will also

serve as operator of the System in accordance with the terms and

conditions set forth in the Construction and Management Agreement

attached hereto as Exhibit B-3.

          The terms of the Partnership Agreement among MCN,

Tartan and Torch will provide that the limited partners will take

no part in the management or control of the Partnership's

business and the general partners will have exclusive management

and control of the business of the Partnership in accordance with

the provisions of the Missouri Uniform Limited Partnership Act. 

The Partnership Agreement will also provide that the general

partners will have the exclusive right, without any requirement

of prior consultation with the limited partners, to do all things

that, in their sole and reasonable judgment, are necessary,

proper or desirable to carry out their duties and

responsibilities as general partners.  The prior approval of a

majority in interest of the limited partners will be required

only for certain major events materially affecting the business

of the Partnership.  These events will include, but will not

necessarily be limited to, (i) the sale, exchange, lease,

mortgage, or other disposition of 25% or more of the fair market

value of the business or assets of the Partnership, or the merger

or consolidation with another entity; (ii) incurring or prepaying

indebtedness (or providing guaranties of another entity's

indebtedness) other than in the ordinary course of business or,

if in the ordinary course of business, in an amount in excess of

$1,000,000; (iii) admitting any additional limited or general

partner or adjustment in a partners percentage ownership;

(iv) dissolving or liquidating the Partnership or appointing a

liquidating partner other than the general partners;

(v) commencing a voluntary, or admitting a material allegation in

an involuntary, proceeding in bankruptcy in the name of the

Partnership; (vi) entering into or effecting a material amendment

of any gas purchase agreement, any firm gas transportation

contract, any negotiated third-party gas sales contract in excess

of $10,000 or certain contracts with third parties in excess of

$100,000 per year; (vii) making any capital expenditure in excess

of $500,000; (viii) materially amending any material government

permit or materially amending any material filing with any

governmental body, or seeking any governmental action other than

is ordinarily required in the ordinary conduct of business; (ix)

making a determination with respect to the disposition of

insurance proceeds in excess of $500,000 or the repair or

rebuilding of the facilities in the event of substantial damage

or destruction; (x) settling a dispute or litigation involving

the Partnership that would materially adversely affect the

Partnership or require payment by the Partnership of more than

$1,000,000; (xi) engaging in any transaction with the general

partner or partners or an affiliate of either general partner

except where such transaction is effectuated on terms no less

favorable to the Partnership in a modified arm's-length

transaction with an unaffiliated entity; (xii) adopting and

operating under an annual budget that includes an increase of 10%

for any category of expenses over the amount included in the

prior year's budget, or an aggregate increase of 5% or

(xiii) modifying the annual budget to result in an increase of

10% for any category of expenses or an aggregate of 5%.  In

addition, the Partnership Agreement will require the limited

partners to vote for the removal of either Tartan or MCN as a

general partner for cause and that Tartan or MCN may be removed

upon the affirmative vote of 66 rds of the interests of the

limited partners.<F2>   On September 25, 1995, Torch

submitted a no-action request letter to the Division request that

the Division state it will not recommend enforcement action under

the Act upon Torch's acquisition of a 47.5% limited partner

interest in the Partnership.

____________________

<F2> "Cause" will be defined in the Partnership Agreement to
     include, but will not be limited to, (i) the failure of a
     general partner to timely make a required capital
     contribution; (ii) the failure of a general partner to
     obtain the approval of a majority in interest of the limited
     partners before undertaking those actions which require the
     approval of the limited partners; (iii) the commencement of
     bankruptcy or insolvency proceedings by or against a general
     partner or certain of its affiliates; (iv) a general
     partner's breach of any provision of the Partnership
     Agreement which has a material adverse effect on the
     construction, operation or maintenance of the operations of
     the Partnership or on the limited partners' equity
     investment in the Partnership; (v) a general partner's gross
     negligence, fraud or breach of its fiduciary duties pursuant
     to the Partnership Agreement; or (vi) in the case of Tartan,
     a 45% or greater change in its stock ownership.


          The Partnership will initially distribute gas to the

residents of approximately fifteen communities in Greene,

Webster, Wright, Howell, Douglas and Texas counties, Missouri,

all of which are located in south-central Missouri.  Currently,

the System is being constructed by TEC which also holds fifteen

local franchises for providing service issued by the Missouri

Public Service Commission (the "MPSC").  These licenses were

initially held by a predecessor of TEC, Tartan Energy Company

L.C., an Oklahoma limited liability company, which was merged

with and into TEC in accordance with the order of the MPSC dated

September 29, 1995 and attached hereto as Exhibit D-2.  When

fully developed and serving the fifteen franchised communities,

the System will have over 300 miles of trunk pipeline and

distribution piping, serving over 10,000 customers.  The

Partnership will operate exclusively in the state of Missouri and

once the System is operational, will be subject to MPSC

regulation with regard to rates and other corporate matters.

          The MPSC has already approved TEC's application for the

first three years of expenditures for developing the system

(estimated to be $39 million at the time of the application) to

serve approximately 9,000 customers in ten of the franchised

communities and construction for the first seven communities

began in March 1995 (the "Phase One Construction").  Attached as

Exhibit D-4 is a copy of this order, which was initially issued

to TEC's predecessor (the "MPSC April Order").  The MPSC has

recently approved construction of the system for an additional

five communities and the Partnership intends to begin

construction to these five additional communities plus one of the

original ten communities, which should be completed in late 1996

("Phase Two Construction").  As the result of planned highway

construction, the Partnership is unable to predict when

construction to the final two communities will take place ("Final

Construction").  Attached as Exhibit D-5 is a copy of this recent

order (the "MPSC September Order").  The Phase One Construction,

the Phase Two Construction and the Final Construction are

referred to here in collectively as the "Construction Phase". 

The cost of the Phase One Construction is currently estimated to

be $35 million and it is estimated that the cost of the Phase Two

Construction will be approximately $8 million, which additional

amount has been taken into account by the MPSC in the MPSC

September Order.  Effective upon the consummation of the

transactions described below, the terms of the MPSC April Order

and the MPSC September Order will be applicable to the

Partnership.  

          Pursuant to the MPSC April Order, the maximum financing

for the construction of the project to the original ten

communities will be $24 million (plus interest during

construction).  The financing may be with recourse to the System

only.  The MPSC April Order and the MPSC September Order both

require that the Partnership maintain a 40% equity level and thus

approximately $17.2 million of project funding ($16 million

pursuant to the MPSC April Order and $1.2 million pursuant to the

MPSC September Order) must be in the form of equity contributions

from the project partners.  In accordance with the MPSC April

Order, the project partners must make an equity contribution for

at least the initial $8 million in project funding, which may be

followed by the expenditure of up to $24 million in debt

financing, with construction finally being completed with at

least $7 million in equity funds.  The MPSC September Order

permits additional debt financing for the additional

construction.

          Currently, Torch has $1.4 million outstanding in loans

to TEC for project development costs and MCN has $6.6 million

outstanding in loans to TEC for construction equity.  These loans

were secured by a pledge of 98.5% of Tartan's and certain of the

Individuals' interests in TEC.  Tartan and such Individuals have

subsequently transferred the 98.5% interest in TEC subject to the

pledge to Tartan Limited Partnership of Missouri (the "Interim

Entity").  Tartan is the general partner of the Interim Entity

and certain of the Individuals are the limited partners.  The

Interim Entity has assumed TEC's debt to Torch and MCN.

          In order to transfer the assets of the System as well

as the franchises held by TEC to the Partnership to establish the

initial ownership structure for the Partnership and pursuant to
                    
the terms of the Formation Agreement, the following transactions

will take place:  MCN and Torch will contribute $8 million to the

Interim Entity in consideration of the subsequent distribution of

the general and limited partnership interests of the Partnership. 

The $8 million will be used by Interim Entity to repay the loans

from Torch and MCN.  The Interim Entity will cause the

Partnership to be formed.  The Partnership will issue 98.5% of

its limited and general partnership interests to the Interim

Entity and 1.5% of its limited partnership interest to certain of

the Individuals.  The Individuals will contribute their interest

in the Interim Entity to Tartan.  The Interim Entity will

distribute the Partnership's limited partnership interest and

general partnership interests to Tartan (1% general and 4%

limited), MCN (1% general and 46.5% limited) and Torch (46%

limited) and the Individuals will sell their 1.5% limited

partnership interest in the Partnership to Torch.  The Interim

Entity subsequently will be dissolved, leaving the Partnership as

the surviving entity owning the System and whose interests are

owned by MCN, Torch and Tartan.

          Torch and MCN will equalize their equity contributions

to the Partnership to $8 million each in apportioning equity by

the end of 1996.  As a result, the Partnership will have received

$16 million in equity contributions from Torch and MCN.  In order

to maintain the 40% equity level of the Partnership, MCN and

Torch may contribute an additional $600,000 each toward the Phase

Two Construction costs.  No determination has been made as to the

source of any additional equity required for Final Construction,

if it occurs.  In order to facilitate the initial debt financing

of the Partnership, MCN has agreed to provide credit support to

the Partnership during the Construction Phase.  Specifically, MCN

has agreed to cause the Partnership to maintain a positive net

worth and has agreed to provide the Partnership with funds

(either as equity or a loan) if the Partnership is unable to make

timely payments under its credit facility.  Finally, Tartan has

contributed its interest in the Missouri franchises to the

Partnership as consideration for its general partnership

interest.

          The merger of TEC into the Partnership is subject to

the approval of the MPSC.  Although formal approval of the

Acquisition by the Michigan PSC is not required under Michigan

law, the staff of the Michigan PSC has stated that it does not

object to the Acquisition by MCN as set forth in the letter from

the staff of Michigan PSC attached as Exhibit D-1.

          The timetable for the construction of the System is

currently estimated as follows: Phase One Construction from May

1995 to June 1996 and Phase Two Construction from March 1996 to

December 1996.  The System began commercial operation in six

communities in December 1995.  No current plans to expand the

System beyond the fifteen franchised communities exist and any

such expansion, and the financing therefore, would require the

approval of the MPSC.

          The natural gas supply for the System will be sourced

via the Williams Natural Gas Company ("Williams") pipeline, with

whom a ten year Transportation Service Agreement for firm

transportation has been negotiated.  Williams has agreed to

construct, at its sole cost and expense, a pipeline lateral, tap

and measurement/regulation facilities in order to deliver gas to

the System.

          MCN's current budget and projections for the next ten

years indicate that MCN's aggregate 47.5% share of the capital

expenditures of the Partnership will amount to approximately $6

million in 1996 (from the initial equity contribution of MCN),

less than $400,000 in 1997 and around $120,000 per year for the

following eight years (which amounts the parties intend to be

taken from the profits of the Partnership and not additional

equity contributions).  Moreover, MCN's share of the assets of

the Partnership are not projected to exceed $20 million at any

time in this period.  For purposes of their internal analysis,

MCN and Torch have estimated the projected revenues and net

income for the Partnership as follows:

          ($ million)              1996      1997      1998
          Revenue                  $3.9      $6.9      $6.8
          Net Operating Income      2.0       2.0       2.8

MCN currently has approximately $2 billion in assets on a

consolidated basis and in excess of $1 billion in utility assets.

          It should be noted that Tartan has filed a Form U-3A-2

with the Commission to claim an exemption from all provisions of

the Act (except section 9(a)(2)) under Section 3(a)(1).


Item 2    FEES, COMMISSIONS AND EXPENSES

          The fees, commissions and expenses of MCN expected to

be paid or incurred, directly or indirectly, in connection with

the transactions described above are estimated as follows:

     Commission filing fee
     relating to Application
     on Form U-1  . . . . . . . . . . . . . . . . . . . .  $2,000

     Legal Fees . . . . . . . . . . . . . . . . . . . . .  50,000

     Miscellaneous  . . . . . . . . . . . . . . . . . . . . 5,000

               Total  . . . . . . . . . . . . . . . . . .  57,000


Item 3    APPLICABLE STATUTORY PROVISIONS

          The following sections of the Act are directly or

indirectly applicable to the proposed transaction:  Sections

9(a)(2) and 10.

          Section 9(a)(2) makes it unlawful, without approval of

the Commission under Section 10, "for any person ... to acquire,

directly or indirectly, any security of any public utility

company, if such person is an affiliate ... of such company and

of any other public utility or holding company, or will by virtue

of such acquisition become such an affiliate."  Because MCN

presently is an affiliate of two public utility companies,

MichCon and Citizens, and by virtue of the proposed transaction

will also become an affiliate of the Partnership, Section 9(a)(2)

requires approval by the Commission of the proposed transaction

under Section 10.  MCN believes that the proposed transaction

meets the requirements of Sections 9(a)(2) and 10.

               A.   Section 10(b)(1)

          Section 10(b)(1) provides that, if the requirements of

Section 10(f) are satisfied, the Commission shall approve an

acquisition unless:

               (1) such acquisition will tend towards
          interlocking relations or the concentration
          of control of public utility companies, of a
          kind or to an extent detrimental to the
          public interest or the interest of investors
          or consumers.

Section 10(b)(1) requires a finding that control is "of a kind or

to an extent detrimental to the public interest or the interest

of investors or consumers."  The framers of the Act sought

through Section 10(b)(1) to avoid "an excess of concentration and

bigness" while preserving the "opportunities for economies of

scale, the elimination of duplicative facilities and activities,

the sharing of production capacity and reserves and generally

more efficient operations" afforded by certain combinations. 

American Electric Power Co., Inc., 46 S.E.C. 1299, 1309 (1978). 

The acquisition of a 1% general partner interest, even coupled

with a 46.5% limited partner interest the latter of which does

not convey control for purposes of the Act, in the small

distribution system of the Partnership by MCN will not create an

"excess of concentration and bigness," but, as discussed in more

detail below, will afford the Partnership the opportunity to

achieve the economies of scale and efficiencies, particularly in

the areas of management expertise and gas supply, that the Act's

framers intended to preserve for the benefit of investors and

consumers.

               B.   Section 10(b)(2)

          Section 10(b)(2) provides that the Acquisition should

be approved unless the price paid:

          is not reasonable or does not bear a fair
          relation to the sums invested in or the
          coming capacity of the utility assets to be
          acquired or the utility assets underlying the
          securities to be acquired.

MCN will make a capital contribution of up to $8.4 million for

its 47.5% aggregate interest in the Partnership.  The other

partners will make capital contributions of various intangible

property (i.e., the franchises) as well as a total of $8.4

million for an aggregate 52.5% in interests.  As previously

noted, these financing arrangements have been essentially

mandated by the MPSC and any permanent financing will require

additional approval.  The staff of the Michigan PSC does not

object to the arrangement.  The MPSC can continue to monitor the

Partnership's expenditures through its ratemaking proceedings and

the Michigan PSC, as well as the City of Adrian in the case of

Citizens, can monitor MCN through ratemaking and other

proceedings designed to protect MichCon's and Citizen's

customers.  In addition, each partner's contribution is to be

used to finance the construction and start up of the system and

effectively amounts to a purchase made at cost.  Overall, the

fact that the amount of the equity contributions to be made have

been either approved or not objected to by these state

commissions, these arrangements were negotiated among the

partners on an arm's length basis and, as discussed below, the

investment constitutes a small portion of MCN's overall capital

expenditures, all lead to the conclusion that the price to be

paid by MCN is fair and does not warrant any of the negative

findings that call for disapproval under Section 10(b)(2).

               C.   Section 10(b)(3)

          Section 10(b)(3) directs approval of the acquisition

unless the Commission finds that:

          (3) such acquisition will unduly complicate
          the capital structure of the holding-company
          system of the applicant ... or will be
          detrimental to ... the proper functioning of
          such holding-company system.

Section 10(c)(1) provides that the Commission not approve an

acquisition that "is detrimental to the carrying out of the

provisions of section 11."  Together they relate to the corporate

simplification standards of Section 11(b)(2), which require that

each registered holding company take the necessary steps

          to ensure that the corporate or continued
          existence of any company in the holding-
          company system does not unduly or
          unnecessarily complicate the structure ... of
          such holding-company system.

The intent of these requirements is to assure the financial

soundness of the holding-company system, with a proper balance of

debt and equity.  No such complexities will result from the

acquisition.

          The following table shows the capitalization of MCN at

December 31, 1994:

         Capitalization of MCN - as of December 31, 1994
          (in thousands of dollars, except percentages)

                                         Amount      Percentage

  Long term debt, including capital
    lease obligations . . . . . . .     $685,519         53%

  Redeemable Cumulative Preferred
    Securities of Subsidiaries  . .      102,618          8 
  Common shareholders equity  . . .      511,495         39 

                             Total:   $1,299,632        100%

MCN's investment in the Partnership will take the form of a

straightforward capital contribution which will not complicate or

indeed, involve MCN's capital structure.  

               D.   Section 10(c)(1) and 10(c)(2)

          Section 10(c) provides for two distinct findings with

respect to a proposed acquisition, and both are related to the

standards prescribed in Section 11(b).  Section 10(c)(1) requires

that the proposed acquisition not be "detrimental to the carrying

out of the provisions of Section 11."  As discussed below,

Section 11 of the Act relates to the simplification of holding

company systems, which was one of the major purposes behind the

passage of the Act.  Section 11(b)(1) discusses two main elements

to this simplification:  reform of the corporate structure of

utility holding companies and confining the properties and

business of the companies within holding company systems to an

"integrated public utility system."

          Section 10(c)(2) is a more specialized provision.  It

requires that an acquisition not be approved unless the

Commission finds that:

          [S]uch acquisition will serve the public
          interest by tending towards the economical
          and efficient development of an integrated
          public-utility system.

Section 2(a)(29)(B) defines an "integrated public utility system"

as applied to gas utility companies as:

          [A] system consisting of one or more gas
          utility companies which are so located and
          related that substantial economies may be
          effectuated by being operated as a single
          coordinated system confined in its operation
          to a single area or region, in one or more
          States, not so large as to impair
          (considering the state of the art and the
          area or region affected) the advantages of
          localized management, efficient operation,
          and the effectiveness of regulation: 
          Provided, that gas utility companies deriving
          natural gas from a common source of supply
          may be deemed to be included in a single area
          or region.

The acquisition of an interest in the Partnership by MCN will

meet the standard set forth in Section 2(a)(29)(B) and,

therefore, will satisfy the requirements of Sections 10(c)(1) and

(2) and should be approved by the Commission.  First, both the

Commission's limited precedent and current technological

realities point to the conclusion that, with the Partnership

included, MCN's gas utility system will operate as a coordinated

system confined in its operation to a single area or region

because they will derive natural gas from a common source of

supply.  None of the Act, the Commission's orders and rulings or

the Commission's staff's no-action letters provide a definition

as to what constitutes a "common source of supply." 

Nevertheless, the Commission has not traditionally required that

the pipeline facilities of an integrated system be

interconnected,<F3> has looked to such issues as from whom

the distribution companies within the system receive much,

although not all, of their gas supply,<F4> and has considered

both purchases of gas from a common pipeline<F5> as well as

from different pipeline's when the gas originates from the same

gas field.<F6>  Since the time of most of these decisions, the

state of the art in the industry has developed to allow efficient

operation of systems whose gas supplies derive from many sources.


____________________

<F3> See In the Matter of Pennzoil Company, HCAR No. 15963 (1968)
     (finding an integrated system where facilities both
     connected with an unaffiliated transmission company but not
     each other).  See also, American Natural Gas Company, HCAR
     15620 (1966) ("it is clear the integrated or coordinated
     operations of a gas system under the Act may exist in the
     absence of such interconnection").

<F4> See e.g., In the Matter of Philadelphia Company and Standard
     Power and Light Company, HCAR No. 8242 (1948) ("most of the
     gas used by these companies in their operations is obtained
     from common sources of supply"); Consolidated Natural Gas
     Company, HCAR No. 25040 (1990) (finding integrated system
     where each company derived natural gas from two transmission
     companies, although one such company also received gas from
     other sources).  

<F5> In the Matter of the North American Company, HCAR No. 10320
     (1950) (finding Panhandle Eastern pipeline to be a common
     source of supply).

<F6> See In the Matter of Central Power Company and Northwestern
     Public Service Company, HCAR 2471 (1941), in which the
     Commission declared an integrated system to exist where two
     entities purchase from different pipeline companies since
     "both pipelines rule out of the Otis field, side by side,
     and are interconnected at various points in their
     transmission system; and that they are within two miles of
     each other at Kearney."     


          Following the Acquisition, MCN's gas utility company

subsidiaries will derive some of their gas from a common source

of supply as defined in Section 2(a)(29)(B).  As previously

mentioned, MichCon receives approximately 46% of its gas supply

from the Midcontinent and Southern basins through the ANR and

Panhandle pipelines.  The Partnership will take gas from the

Williams pipeline, which is interconnected with the ANR and

Panhandle pipelines.  It is currently anticipated that the

Partnership's gas purchasing needs may be met in part by the same

MCN subsidiary that provides gas to Citizens.<F7>  In the

past two years, MichCon and Citizens have obtained their gas

supply from the same gas field in numerous instances and both

companies transport substantial portions of their gas supply

through the Panhandle and ANR pipelines.  Although gas purchases

for the Partnership will be made on an economic basis and not

with the main goal of ensuring a common source of supply, given

economies of scale and the past practice by the same purchasers,

it can be expected that the Partnership, Citizens and MichCon

will purchase gas from the same fields and that much of their gas

will travel thorough the same pipelines even if it is not from

the same field.  As noted above, both purchases from a common

pipeline as well as from a common gas field have been found to

satisfy to "common source of supply" requirement of Section

2(a)(29)(B) of the Act.

____________________

<F7> Although MichCon and Citizens do exchange information on the
     subject, MichCon's and Citizens' gas purchasing operations
     are basically separate from each other.  


          In addition, MCN's ownership of an interest in the

Partnership will be beneficial to the management and operations

of the Partnership's system.  MCN's management, through MichCon

and Citizens, is highly trained and experienced in providing gas

distribution services and will bring its technological, customer

service and regulatory expertise to the Partnership, and can pass

on that expertise to Tartan, the local operator of the

Partnership project.  In addition, MCN's access to gas supplies

could prove useful to the Partnership, and complements the

financial strength MCN brings to the Partnership's operations.

          While final arrangements are not yet in place, it is

anticipated that MCN will provide the Partnership with assistance

and expertise relating to the efficient operation of gas utility

companies.  At the moment, MCN has agreed to provide engineering,

consulting (gas purchasing, planning and coordination) as well as

billing services to the Partnership at cost.  At this point, no

specific estimate of the magnitude of the savings for the

Partnership that will result from this arrangement is possible,

but we believe the tangible benefits to the Partnership will be

substantial and additional intangible benefits will result from

access to MCN's management's expertise.  Similarly, by increasing

the purchasing power of MCN, who will provide such services to

the System, the addition of the system to MCN's existing system

will create a stronger combined system able to capture economies

of sale in purchasing activities.


Item 4    REGULATORY APPROVALS

          No federal commission, other than this Commission has

jurisdiction over the Acquisition as described herein.  As

discussed above, the MPSC has approved the financing arrangements

for the System and the merger of TEC's predecessor with and into

TEC.  Application to the MPSC for approval of the merger which

will result in ownership of the System and the related franchises

and certificates being transferred to the Partnership will be

made.  In addition, the Partnership will hold a number of

franchises issued by local authorities allowing it to provide

service in those areas.  No other state regulatory commission has

jurisdiction over the transactions for which approval is sought

herein, although the staff of the only other state commission

where any public utility companies involved in the transaction

are located has indicated that it does not object to the

transaction.


Item 5    PROCEDURE

          MCN hereby requests that there be no hearing on this

Application and that the Commission issue its order as soon as

practicable after the filing hereof.  The Commission is

respectfully requested to issue and publish the requisite notice

under Rule 23 with respect to the filing of this Application not

later than February 16, 1996, such notice to specify a date not

later than March 12, 1996, by which comments may be entered and a

date not later than March 15, 1996, as the date after which an

order of the Commission granting and permitting the Application

to become effective may be entered by the Commission.  A form of

Notice if filed herewith as Exhibit G-1.

          Without prejudice to its right to modify the same if a

hearing should be ordered on this Application, MCN hereby makes

the following specifications required by paragraph (b) of Item 5

of Form U-1:

          1.   There should not be a recommended decision by a

               hearing officer or any other responsible officer

               of the Commission.

          2.   The Division of Investment Management may assist

               in the preparation of the Commission's decision

               and/or order.

          3.   There should not be a 30-day waiting period

               between issuance of the Commission's order and the

               date on which the order is to become effective.

          It is requested that the Commission send copies of all

communications to MCN as follows:

          Daniel L. Schiffer, Esq.
          Vice President, General Counsel 
           and Secretary
          MCN Corporation
          500 Griswold Street
          Detroit, MI  48226

          with concurrent copies to:

          William S. Lamb, Esq.
          LeBoeuf, Lamb, Greene & MacRae, L.L.P.
          125 West 55th Street
          New York, NY  10019-4513


Item 6    EXHIBITS AND FINANCIAL STATEMENTS

          a)   Exhibits

          B-1  Form of Partnership Agreement (previously filed).

          B-2  Formation Agreement (previously filed).

          B-3  Construction and Operation Agreement (previously
               filed).

          C-1  Form U-3A-2 of MCN (Incorporated herein by
               reference to Form U-3A-2 filed by MCN on February
               24, 1995 (File No. 69-352).

          D-1  Letter from the staff of the State of Michigan
               Public Service Commission dated September 18, 1995
               (previously filed).

          D-2  Order of the Missouri Public Service Commission,
               dated September 29, 1995 (previously filed).

          D-3  Order of the Missouri Public Service Commission,
               dated September 16, 1995 (previously filed).

          D-4  Order of the Missouri Public Service Commission,
               dated April 15, 1995 (previously filed).

          D-5  Order of the Missouri Public Service Commission,
               dated September 13, 1995.

          F-1  Opinion of Counsel.

          F-2  "Past Tense" Opinion of Counsel (to be filed by
               amendment).

          G-1  Proposed Form of Public Notice (previously filed).

          b)   Financial Statements

          1.1  Balance Sheet   MCN (consolidated), as of
               September 30, 1995 (Incorporated herein by
               reference to Form 10-Q filed by MCN on November 7,
               1995).

          1.2  Statement of Income and Retained Earnings   MCN
               (consolidated), for the six months ended September
               30, 1995 (Incorporated herein by reference to Form
               10-Q filed by MCN on November 7, 1995).


Item 7    INFORMATION AS TO ENVIRONMENTAL EFFECTS

          None of the matters that are the subject of this

application and declaration involve a "major federal action" nor

do they "significantly affect the quality of the human

environment" as those terms are used in section 102(2)(C) of the

National Environmental Policy Act.  The transaction that is the

subject of this application will not result in changes in the

operation of the company that will have an impact on the

environment.  MCN is not aware of any federal agency that has

prepared or is preparing an environmental impact statement with

respect to the transactions that are the subject of this

application.

                            SIGNATURE

          Pursuant to the requirements of the Public Utility

Holding Company Act of 1935, the undersigned company has duly

caused this application and declaration to be signed on its

behalf by the undersigned thereunto duly authorized.

                              MCN CORPORATION


                              By: 
                                   Daniel L. Schiffer
                                   Vice President, General
                                   Counsel and Secretary


Date: February 8, 1996

                                   February 8, 1996



Securities and Exchange Commission
450 Fifth Street, N.W.
Washington, DC  20549

Gentlemen:

          This opinion is furnished to the Securities and
Exchange Commission (the "Commission") in connection with the
filing with the Commission of the Application/Declaration on
Form U-1 (File 70-8731) of MCN Corporation (the "Company") under
the Public Utility Holding Company Act of 1935 (the
"Application").  The Application requests that the Commission
issue an order authorizing the acquisition (the "Acquisition") by
the Company of a 1% general partnership interest in Southern
Missouri Gas Company, L.P., which will be a gas utility company
organized and operating in the state of Missouri.

          I have acted as counsel for the Company and in
connection with this opinion I have examined originals or copies
certified or otherwise identified to my satisfaction of:

          (1)  the charter documents and by-laws of the Company,
     as amended to date;

          (2)  minutes of meetings of the Company's shareholders
     and directors, as kept in its minute books; 

          (3)  the Agreement of Limited Partnership of Southern
     Missouri Gas Company, L.P.; and 

          (3)  the documents and agreements pertaining to the
     Acquisition and such other certificates, documents and
     papers as I deemed necessary or appropriate for the purpose
     of rendering this opinion.

          In such examination, I have assumed the genuineness of
all signatures, the authenticity of all documents submitted to me
as originals and the conformity to the original documents of all
documents submitted to me as copies.  As to any facts material to
my opinion, I have, when relevant facts were not independently
established, relied upon the aforesaid agreements, instruments,
certificates and documents.  In addition, I have examined such
questions of law as I have considered necessary or appropriate
for the purpose of rendering this opinion.

          Based on the foregoing, and subject to the final
paragraph hereof, I am of the opinion that when the Commission
has taken the action requested in the Application:

     (1)  All state laws applicable to the Acquisition have been
          complied with;

     (2)  The Company is a corporation validly organized, duly 
          existing and in good standing in the State of Michigan;

     (3)  The Company may legally acquire the partnership
          interests of Southern Missouri Gas Company, L.P.; and

     (4)  The consummation of the Acquisition will not violate
          the legal rights of the holders of any securities
          issued by the Company.

          I hereby consent to the use of this opinion as an
exhibit to the Application.

          I am not, in this opinion, opining on laws other than
the laws of the State of Michigan and the federal laws of the
United States.


                              Very truly yours,

                              /s/
                              Daniel L. Schiffer


<TABLE> <S> <C>

<ARTICLE> 5
<RESTATED> 
<MULTIPLIER> 1,000
       
<S>                             <C>
<PERIOD-TYPE>                   9-MOS
<FISCAL-YEAR-END>                          DEC-31-1995
<PERIOD-END>                               SEP-30-1995
<CASH>                                          16,825
<SECURITIES>                                         0
<RECEIVABLES>                                  170,700
<ALLOWANCES>                                    13,325
<INVENTORY>                                    154,987
<CURRENT-ASSETS>                               407,884
<PP&E>                                       2,928,136
<DEPRECIATION>                               1,196,535
<TOTAL-ASSETS>                               2,364,525
<CURRENT-LIABILITIES>                          439,308
<BONDS>                                        811,546
<COMMON>                                           662
                          100,000
                                          0
<OTHER-SE>                                     634,357
<TOTAL-LIABILITY-AND-EQUITY>                 2,364,525
<SALES>                                              0
<TOTAL-REVENUES>                             1,044,287
<CGS>                                                0
<TOTAL-COSTS>                                  925,950
<OTHER-EXPENSES>                                 1,605
<LOSS-PROVISION>                                 8,727
<INTEREST-EXPENSE>                              40,724
<INCOME-PRETAX>                                 75,389
<INCOME-TAX>                                    20,114
<INCOME-CONTINUING>                             55,275
<DISCONTINUED>                                       0
<EXTRAORDINARY>                                      0
<CHANGES>                                            0
<NET-INCOME>                                    55,275
<EPS-PRIMARY>                                      .86
<EPS-DILUTED>                                        0
        

</TABLE>

                        STATE OF MISSOURI
                    PUBLIC SERVICE COMMISSION
                          JEFFERSON CITY


                                        September 13, 1995



CASE NO:  GA-95-349

James M. Fischer, Attorney at Law,
101 West McCarty Street
Suite 215
Jefferson City, MO  65101



          Enclosed find certified copy of ORDER in the above-
numbered case(s).


                                   Sincerely,


                                   David L. Rauch
                                   Executive Secretary




Uncertified Copy:

Office of the Public Counsel, P.O. Box 7800, Jefferson City, MO
65102
Tom M. Taylor, President, Missouri Southern Gas Company, 8801
South
  Yale, Suite 385, Tulsa, OK 74137
Pat Odom, 223 West Center, Rogersville, MO 65742
Mary Jane Burr, P.O. Box 65, Fordland, MO 65652
Rhonda Coatney, P.O. Box 100, Norwood, MO 65717
Greg Fox, 516 South Division, Seymour, MO 65746
Jimmy Crisp, P.O. Box 301, Seymour, MO 65746
Linda Wrinkles, 106 North Mill, Rogersville, MO 65742
Bill Elgie, Rt. 1 Carpenter Street, Fordland, MO 65652
Regina Harper, 526 N. Eagle, Norwood, MO 65717
Roger McCormack, P.O. Box 261, Seymour, MO 65746
Dennis Cody, Rt. 3, Box 3102, Seymour, MO 65646
To the county commission of Greene, Wright and Webster County.
To the mayor of Rogersville, Fordland, *Diggins, Norwood and
Seymour.


*    not incorporated


                                                STATE OF MISSOURI
                                        PUBLIC SERVICE COMMISSION

                               At a Session of the Public Service
                                    Commission held at its office
                                    in Jefferson City on the 13th
                                          day of September, 1995.


In the matter of the application of Tartan )
Energy Company, L.C., d/b/a Southern       )
Missouri Gas Company, L.C., for            )
certificate of convenience and necessity   )
authorizing it to construct, install, own, )
operate, control, manage and maintain gas  ) 
facilities and to render gas service in    ) CASE NO. GA-95-349
and to residents of certain areas of       )
Greene, Wright and Webster Counties,       )
including the incorporated municipalities  )
of Rogersville, Fordland, Diggins, Norwood )
and Seymour, Missouri.                     )
                                           )


     ORDER GRANTING CERTIFICATE OF CONVENIENCE AND NECESSITY

          On May 9, 1995, Tartan Energy Company, L.C., d/b/a

Southern Missouri Gas Company, L.C. (Tartan), filed an

application pursuant to Section 393.170, RSMo 1986 and 4 CSR 240-

2.060 for a certificate of convenience and necessity authorizing

it to construct, install, own, operate, control, manage, and

maintain gas facilities, and to render gas service in and to

residents of certain areas of Greene, Wright and Webster

Counties, including the incorporated municipalities of

Rogersville, Fordland, Diggins, Norwood and Seymour, Missouri. 

The application included a number of exhibits designed to comply

with 4 CSR 240-2.060, and indicated that other exhibits would be

late-filed when they became available.  On May 31, 1995, the

Commission issued an Order and Notice, giving notice of Tartan's

application and setting an intervention deadline of June 15,

1995.  No applications for intervention were received by the

Commission.

          Tartan explains in its application that the

incorporated cities of Rogersville, Fordland, Diggins, Norwood

and Seymour, Missouri would be served by city gate facilities and

distribution systems connected to Tartan's trunkline, while the

unincorporated portions of the proposed certificated areas would

be served via farm taps and short segments of distribution

pipeline connected to Tartan's trunkline.  Tartan notes that the

five municipalities for which a certificate of convenience and

necessity is now sought were considered "probable additional

cities" in the feasibility study previously submitted by Tartan

in Case No. GA-95-127.<F1>  A new feasibility study was filed

in this case as late-filed Exhibit 3.  In addition, Tartan filed

as Exhibit 4 the franchises and certified election results for

the municipalities of Rogersville, Fordland, Norwood and Seymour,

Missouri.  The ratification election for the municipality of

Diggins was late-filed as a supplement to Exhibit 4 on August 23,

1995.

____________________

<F1> Tartan was previously granted a conditional certificate of
     convenience and necessity to construct a trunkline and
     provide service in various municipalities and unincorporated
     areas in the vicinity of the areas for which a new
     certificate of convenience and necessity is sought.  See
     Tartan, Case No. GA-94-127, Report and Order, issued
     September 16, 1994.  This conditional certificate was made
     effective as a certificate of convenience and necessity in
     an Order Approving Tariffs And Authorizing The Commencement
     Of Construction Of Gas Facilities, issued April 14, 1995. 
     The Commission later issued an Order Granting Certificate of
     Convenience And Necessity For Mountain View, Missouri, And
     Authorizing Construction And Distribution Facilities In
     Mountain View, Missouri, And In Texas And Wright Counties,
     issued May 19, 1995, which extended the certificate to
     include a municipality which had not yet ratified its
     franchise at the time of the original Report and Order.


          Tartan states that no other public utility is currently

providing natural gas service in the proposed service area, but

similar unregulated utility service is available in the area

through propane gas distributors.  Tartan asserts that the

granting of its application is required by the public convenience

and necessity because it will make available to the residents of

the proposed service area a new, efficient and economical form of

energy, which will enhance the economic development of the area

and thus aid in attracting new businesses to the area.  Tartan

maintains that the regulatory issues related to this project were

thoroughly reviewed by the Commission in Case No. GA-94-127,

including the public interest considerations, rate issues,

financial and management issues, safety issues, and gas supply

issues.  The additional projected load for the five

municipalities for which a certificate is currently sought is

approximately 144,000 Mcfs per year, which represents

approximately 8 percent of the projected load in the service area

approved in Case No. GA-94-127.  In addition, at least one

industrial customer, with facilities in multiple locations

through Tartan's existing service area, seeks to convert all of

its facilities at or near the same time, including some

facilities in a municipality which is the subject of this

application.  Furthermore, Tartan notes its construction activity

for the facilities approved in Case No. GA-94-127 will span the

1995 and 1996 construction seasons, and that the proposed

facilities which would be built to service the areas for which a

certificate is sought in the present case can be built most cost

effectively by being integrated completely into the on-going

construction activity that presently is surrounding and alongside

the proposed additional service areas.

          No party to this proceeding has requested a hearing,

therefore pursuant to State ex rel. Rex Deffendorfer Enterprises,

Inc. v. Public Service Commission, 776 S.W.2d 494, (Mo. App.

1989), the Commission determines that no hearing is necessary in

this case.  The Commission will base its decision on the verified

application filed by Tartan, and the attachments thereto,

including late-filed exhibits, and the recommendation of the

Staff of the Commission (Staff).

          Tartan is a limited liability company duly organized

and existing under the laws of the State of Oklahoma, with its

principal place of business located at 8801 South Yale, Suite

385, Tulsa, Oklahoma 74137, and does business in the State of

Missouri as Southern Missouri Gas Company, L.C.  It also is a gas

corporation and public utility as defined in Section 386.020,

RSMo 1994, and is subject to the jurisdiction of the Commission

pursuant to Chapters 286 and 393 of the Missouri Revised

Statutes.

          On August 2, 1995, Staff filed a memorandum containing

its recommendation regarding Tartan's application.  Staff states

that each of the five cities involved in Tartan's application are

adjacent to the planned route of the Company's trunkline, and are

surrounded by the Company's currently approved service area. 

Overall voter approval in four of the five cities has been

approximately 81 percent, with voter ratification pending in

Diggins.<F2>  In addition, Staff states that in response to

local interest, Tartan is seeking Commission approval to service

customers via farm taps in unincorporated areas located along

approximately seven miles of its trunkline located in Greene

County.  Staff indicates that according to Tartan, no franchise

is required from Greene County, but right-of-way petitions will
                    
____________________

<F2> As previously indicated, the result of the ratification
     election for the municipality of Diggins was late-filed as a
     supplement to Exhibit 4 on August 23, 1995.


be filed as needed for access to county right-of-ways. 

Additionally, Staff notes that the distribution systems for each

of the five cities are to be designed, constructed, operated and

maintained to the same specifications and criteria as the systems

in the other cities for which service has already been approved. 

Likewise, Tartan is proposing to serve customers in the requested

service area at the same rates, terms and conditions as were

approved in Case No. GA-94-127, including the provision of up to

$200 per customer for conversion costs, one-half of which is to

be included in rate base.

          Staff states that it recommends Commission approval of

Tartan's application, even though it has some concerns regarding

the financial feasibility of the natural gas certificate request. 

Staff's support is made in view of the current competition from

propane and a local desire for natural gas service.  However,

Staff's support is contingent upon several factors specifically

related to the Company's last certificate case in Case No. GA-94-

127.  Essentially Staff's recommendation is contingent upon the

conditions previously contained in the Stipulation and Agreement

approved in Case No. GA 94-127 being applied to the certificate

in this case as well.  These conditions include the continued use

of the stipulated volumes and tariffed rate amounts, compliance

with the equity financing and capital ratio provisions as

originally approved, and the continued commitment of the Company

to file a rate case within two year of commencement of service in

West Plains, Missouri.  Staff adds that the Company has requested

expedited approval of the application so that the new

construction projects can be efficiently integrated into the on-

going construction activity presently surrounding the five

cities, and that Staff has no objection to this.  Staff therefore

recommends the following:

          1)   That the Commission grant the requested
               certificate of convenience and necessity for the
               proposed service area, including, upon receipt of
               evidence of voter ratification, the municipality
               of Diggins, Missouri;

          2)   That the Commission order Tartan to comply with
               all the conditions previously outlined in the
               Stipulation and Agreement approved in Case No. GA-
               94-127;

          3)   That the Commission order Tartan to file tariff
               sheets to reflect the inclusion of the above
               incorporated and unincorporated service areas in
               its service area descriptions; and

          4)   That the Commission order that the certificate of
               convenience and necessity become effective
               simultaneously with the effective date of the
               tariffs to be filed and approved.


          The Commission has reviewed Tartan's application and

the attachments thereto, as well as Staff's recommendations, and

finds that Tartan's application to provide natural gas service in

the proposed service area is necessary and convenient for the

public service, and is in the public interest.  Tartan has

provided sufficient indication of the need for natural gas

service in the proposed service area.  In addition, Tartan's

qualification to provide the proposed service were adequately

reviewed in Case No. GA-94-127.  There are no new facts or

unusual circumstances which would indicate a need for further

review of Tartan's qualifications.  Likewise, Tartan's financial

ability to provide the proposed service and the economic

feasibility of its original proposal were also addressed in

Case No. GA-94-127.  There the Commission found that Tartan's

original proposal, as modified by the Nonunanimous Stipulation

and Agreement entered into between Tartan, Staff, and the Office

of the Public Counsel, represented a viable project.  Similarly,

the Commission finds that Tartan's current proposal represents a

logical and an anticipated extension of its original proposal in

Case No. GA-94-127.  The Commission is of the opinion that the

additional sales volume which may be anticipated from the

provision of service to the five municipalities, the one

industrial customer specifically referred to, and the anticipated

farm taps will assist in the economic viability of the overall

project.  The Commission also finds that the introduction of

natural gas into the proposed service area may assist in the

economic expansion of the area.  Furthermore the issuance of a

certificate at this time which extends Tartan's current service

area to contiguous areas will allow the gas facilities needed to

provide service to the newly certificated area to be included in

Tartan's overall construction plans, thus helping to minimize the

construction cost for the new gas facilities.

          Just as the Commission views Tartan's current proposed

service area as an extension of its proposal in Case No. GA-94-

127, so the Commission shares Staff's concern about the financial

feasibility of this segment of the overall project.  Under

Section 393.170, RSMo 1994, the Commission has authority to

impose such condition or conditions as it may deem reasonable and

necessary in granting permission and approval for the

construction of gas plant and the exercise of a franchise

relating thereto.  The Commission finds that the conditions

suggested by Staff are reasonable and should be adopted in this

case.  Thus the Commission will grant the requested certificate

of convenience and necessity subject to the conditions contained

in the Nonunanimous Stipulation and Agreement entered into and

approved in Case No. GA-94-127, including, but not limited to,

the booking of one-half of the cost of Tartan's conversion

incentive program below-the-line for ratemaking purposes,

Tartan's continued use of the stipulated volumes and tariffed

rate amounts, its continued compliance with the equity financing

and capital ratio provisions, and its continued commitment to

file a rate case within two years of the commencement of service

in West Plains, Missouri.

          IT IS THEREFORE ORDERED:

          1.  That Tartan Energy Company, L.C. d/b/a Southern

Missouri Gas Company, L.C., by and is hereby granted a

certificate of convenience and necessity authorizing it to

construct, install, own, operate, control, manage, and maintain

gas facilities and to render gas service in and to the residents

of certain areas of Greene, Wright, and Webster Counties,

including the incorporated municipalities of Rogersville,

Fordland, Diggins, Norwood and Seymour, Missouri.  Said

certificate shall be in conformity with Attachment 1 attached

hereto and incorporated herein by reference, which describes the

service area by county, range, township and section, and

Attachment 2, attached hereto and incorporated herein by

reference, which is a map which generally depicts the service

area.

          2.   That the variance from Commission's promotional

practices rule previously granted to Tartan Energy Company, L.C.

d/b/a Southern Missouri Gas Company, L.C., in the Commission's

Report and Order issued on September 16, 1994 in Case No. GA-94-

127, be and is hereby extended to the service area referenced in

Ordered Paragraph 1 above.

          3.   That Tartan Energy Company, L.C., d/b/a Southern

Missouri Gas Company, L.C., be and is hereby authorized to

account for one-half of the allowed $200 maximum per customer

conversion incentive program costs above-the-line, and include

those costs in rate base, as set forth in the Commission's Report

and Order issued on September 16, 1994 in Case No. GA-94-127.

          4.   That the conditions contained in the Non-unanimous

Stipulation and Agreement approved in the Commission's Report and

Order issued on September 16, 1994 in Case No. GA-94-127 shall be

applied to the certificate of convenience and necessity issued in

this Order, including, but not limited to, the continued use by

Tartan Energy Company, L.C., d/b/a Southern Missouri Gas Company,

L.C., of the stipulated volumes and tariffed rate amounts,

continued compliance with the equity financing and capital ratio

provisions, and continued commitment to file a rate case within

two (2) years of the commencement of service in West Plains,

Missouri.

          5.   That Tartan Energy Company, L.C., d/b/a Southern

Missouri Gas Company, L.C. be and is hereby authorized to file

tariff sheets to reflect the inclusion of the above incorporated

and unincorporated certificated service areas in its service area

description.

          6.   That the certificate of convenience and necessity

referenced in Ordered Paragraph 1 above shall become effective

simultaneously with the effective date of the tariffs required to

be filed and approved pursuant to Ordered Paragraph 5 above.

          7.   That the Commission makes no finding as to the

prudence or ratemaking treatment to be given any costs or

expenses incurred as the result of the granting of this

certificate of convenience and necessity, except those costs and

expenses dealt with specifically in the Nonunanimous Stipulation

and Agreement approved in the Report and Order issued on

September 16, 1994 in Case No. GA-94-127, and reserves the right

to make any disposition of the remainder of those costs and

expenses which it deems reasonable, in any future ratemaking

proceeding.

          8.   That this Order shall become effective on

September 26, 1995.


                                   BY THE COMMISSION



                                   David L. Rauch
                                   Executive Secretary


(S E A L)


McClure, Kincheloe, Crumpton,
and Drainer, CC., Concur.
Mueller, Chm., Absent.



© 2022 IncJournal is not affiliated with or endorsed by the U.S. Securities and Exchange Commission