                               CERTIFICATE OF NOTIFICATION

                                       Filed by

                        SOUTHERN ELECTRIC GENERATING COMPANY 
                          SOUTHERN ELECTRIC RAILROAD COMPANY

          Pursuant to Order of the Securities and Exchange Commission dated
          January 13, 1993 (HCAR No. 35-25734) in the matter of File No.
          70-7911.

               Southern Electric Generating Company ("SEGCO") and Southern
          Electric Railroad Company hereby certify to said Commission,
          pursuant to Rule 24 and the above-referenced Order, as follows:

               SEGCO has decided to proceed with a project for the benefit
          of Plant Gaston (the "Plant"), a five-unit coal fired generating
          facility, four units of which are owned by SEGCO and one unit of
          which is owned by Alabama Power Company.  The project consists of
          the construction of a turnout from the existing line of CSX
          Transportation, Inc. ("CSX")  to the existing line owned by
          SEGCO.  The existing connection allows CSX to access the SEGCO
          rail line from a westerly direction; the new turnout will enable
          CSX to deliver coal from sources located west of the Plant.  The
          project will thus provide increased rail competition and savings,
          as currently CSX may enter the Plant from the west only by
          travelling past the SEGCO railroad for several miles and
          repositioning locomotives for entry from an easterly direction,
          all resulting in inefficient operation and increased rates.

               SEGCO currently estimates that the project will result in
          cost savings to SEGCO of approximately $235,000 on a present
          value basis over the period 1995 through February, 2002 in excess
          of the estimated cost of construction.  This present value fuel
          cost savings was calculated based upon forecasted prices for new
          coal supplies to be delivered to the Plant and reflects the rates
          quoted by CSX.

          Dated  November 28, 1994

                                   SOUTHERN ELECTRIC GENERATING COMPANY


                                   By   Wayne Boston                   
                                        Wayne Boston
                                        Assistant Secretary


                                   SOUTHERN ELECTRIC RAILROAD COMPANY


                                   By   Wayne Boston                   
                                        Wayne Boston
                                        Assistant Secretary<PAGE>