Date of Release: October 30, 1995  
NO. C902032  
VANCOUVER REGISTRY  
IN THE SUPREME COURT OF BRITISH COLUMBIA  
BETWEEN:  
AND:  
THE FOUNDATION COMPANY OF CANADA LTD.  
PLAINTIFF/DEFENDANT  
BY COUNTERCLAIM  
UNITED GRAIN GROWERS LIMITED  
DEFENDANT/PLAINTIFF  
BY COUNTERCLAIM  
AND:  
AND:  
CHOUKALOS WOODBURN MCKENZIE MARANDA LTD.  
DEFENDANT  
BUHLER (CANADA) INC. and  
CROSSTOWN METAL INDUSTRIES LTD.  
THIRD PARTIES  
NO. C911710  
VANCOUVER REGISTRY  
IN THE SUPREME COURT OF BRITISH COLUMBIA  
BETWEEN:  
CROSSTOWN INDUSTRIES LTD.  
PLAINTIFF  
AND:  
AND:  
FOUNDATION COMPANY OF CANADA LTD.  
DEFENDANT  
UNITED GRAIN GROWERS LIMITED AND CHOUKALOS WOODBURN  
MCKENZIE MARANDA LTD  
THIRD PARTIES  
- 2 -  
John S. Logan  
Counsel for Foundation:  
Charles F. Willms,  
Katherine A. Arnold  
Counsel for United Grain Growers:  
Murray A. Clemens Q.C.,  
Henning W. Wiebach,  
Rupert M. Shore  
Counsel for Choukalos:  
Counsel for Crosstown:  
Place and Date of Hearing:  
Kerry A. Short,  
Karen L. Martin  
Stuart B. Hankinson,  
James R. White  
Vancouver, B.C.  
Sept. 7, 1993 -  
February 4, 1995  
132 trial days.  
REASONS FOR JUDGMENT  
OF  
THE HONOURABLE MR. JUSTICE BRENNER  
- 3 -  
I N D E X  
PAGE  
5
INTRODUCTION  
NATURE OF THE CLAIMS  
NATURE OF THE EVIDENCE  
THE GRAIN TERMINAL  
THE PROJECT  
9
13  
17  
20  
21  
23  
24  
25  
39  
40  
61  
PERSONNEL  
CHRONOLOGY  
HISTORY OF THE TENDER  
THE TENDER PERIOD  
THE PRIME CONTRACT  
PRESELECTED EQUIPMENT - DELIVERY RESPONSIBILITY  
PROJECT DELAY - FCC ALLEGATIONS  
PROJECT DELAY - CMI ALLEGATIONS  
117  
PROJECT DELAY - UGG AND CWMM ALLEGATIONS  
CONCLUSION ON PROJECT DELAY CAUSATION  
FCC NEGLIGENT MISREPRESENTATION CLAIM  
FCC BREACH OF CONTRACT CLAIM  
141  
159  
163  
173  
177  
EXTENSION OF CONTRACT TIME  
NOTICE OF CLAIM BY FCC, CMI AND UGG  
FCC DAMAGES - DELAY  
179  
213  
217  
FCC EXTRAS  
CMI ACCELERATION CLAIM  
CMI PRODUCTIVITY LOSS CLAIM  
263  
276  
- 4 -  
CMI EXTRAS  
292  
DEFICIENCY PROGRAM  
330  
331  
CMI OVERHEAD AND PROFIT  
INTEREST  
332  
334  
JUDGMENT SUMMARY  
- 5 -  
INTRODUCTION  
1.  
These actions follow a major renovation in 1989 at the  
United Grain Growers Limited ("UGG") grain terminal on the  
Vancouver inner harbour (the "Terminal"). Foundation Company of  
Canada Ltd. ("FCC") was the General Contractor, UGG was the Owner  
and CWMM including its subconsultant P. J. Campbell & Associates  
Ltd ("CWMM") was the engineer retained by UGG. No cross claims  
are advanced between UGG and CWMM. Although UGG's position at  
trial was that its vicarious responsibility for any acts or  
omissions of CWMM is limited to the discharge by CWMM of its  
duties under the prime contract, UGG does not assert any extra-  
contractual conduct by CWMM and hence UGG is vicariously  
responsible for any acts or omissions of its engineer CWMM.  
2.  
Crosstown Metal Industries Ltd. ("CMI") was the sheetmetal  
subcontractor of FCC responsible for the fabrication and  
installation of dust control ducting and spouting. Spouting is  
made by joining rectangular sections of sheetmetal together in  
runs which convey grain by gravity flow down through the various  
levels, equipment and storage bins in the grain terminal. Gates,  
which act as valves, are installed in spouting runs and are  
opened and closed to control the flow of grain.  
3.  
On February 10, 1989 UGG accepted FCC's tender and awarded  
it the $16 million stipulated price contract. FCC awarded the  
- 6 -  
spouting subcontract of $2.86 million to CMI on February 14 (all  
dates in 1989 unless otherwise noted). On site construction was  
scheduled to start March 6 when UGG shut down its operations at  
the Terminal, and continue until Substantial Performance by  
August 31. In the result, CWMM certified Substantial Performance  
as of December 29. To be determined is the responsibility and  
recoverable damages, if any, arising from that delay, as well as  
the entitlement of FCC and CMI to extras.  
4.  
CMI says it was prevented from installing its spouting as  
planned because of delays in site preparation and in the delivery  
and installation of equipment to which it was required to connect  
spouting runs. CMI also says when it tried to install its  
spouting, interferences with other components in the terminal, or  
the terminal itself caused by CWMM design errors required CMI to  
modify the spouting so it would fit. CMI seeks damages for  
productivity losses, acceleration costs and unpaid extras in the  
amount of $1,746,601 plus contractual interest of $1,152,620  
calculated to the date of argument in February 1995. While CMI  
advances its claims through FCC in contract, most of its  
allegations are referable to the acts or omissions of UGG and  
CWMM, for which FCC claims indemnity.  
5.  
FCC advances against UGG either directly or through CWMM  
allegations for breach of contract and negligent  
misrepresentation as well as alternative claims in quantum meruit  
- 7 -  
or for restitution. FCC says these contractual breaches or  
negligent misrepresentations consisted of:  
(i) the late design completion and delivery of as well  
as defects in owner pre-selected equipment;  
(ii) the late completion of a new  
administration building being  
constructed for UGG by another  
contractor;  
(iii)the fact that the design of the Project  
was not complete at the time of tender  
and changed after the close of tender;  
(iv) the inability of FCC to obtain access to  
UGG's dock to install two dock  
progressors;  
(v) the significant number of Change Orders  
added to FCC's contract; and  
(vi) the delay in the computer programming by  
CWMM.  
6.  
FCC's claim in this action also includes such of the unpaid  
Change Orders or extras claimed by CMI found to be Change Orders  
under the Prime Contract, together with its 5% markup. It seeks  
judgment against UGG and CWMM for $2,236,002 including interest,  
as well as indemnity in respect of the CMI claim. FCC advances  
no claims for acceleration, overtime costs or productivity  
- 8 -  
losses. It says its damages are its costs in having to continue  
on the job site past the original substantial performance date of  
August 31 to the actual date declared by CWMM of December 29.  
7.  
UGG and CWMM say that FCC and CMI have failed to prove:  
(1) that any of the events of which they complain either  
individually or collectively caused any delay to FCC or CMI  
in prosecution of their work on the project or on their  
ability to achieve substantial performance by August 31;  
(2) that any of the alleged causes of delay were the fault of  
UGG or CWMM;  
(3) that FCC and/or CMI gave sufficient notice of delay or  
request for extension of time under the contract.  
8.  
The defendants say that FCC and CMI failed to complete the  
contract on time because of their own inexperience or  
incompetence and they are solely responsible for any losses which  
flow from the manner in which the work was carried out or the  
late completion. They point to delay caused by FCC's demolition  
contractor Johnny Walker, gates supplied for FCC by IECO, the low  
levels of manpower utilised by FCC and CMI in the early stages of  
the project, CMI's decision to fabricate complete spouting runs  
from CWMM construction drawings without prior shop drawing  
approval and without first field measuring which they say was  
required by the contracts to ensure that the runs would fit  
without interferences and CMI's decision to use 2 piece instead  
- 9 -  
of 4 piece spouting which is less rigid and more amenable to  
adjustment during installation.  
9.  
UGG counterclaims against FCC for its economic losses of  
some $5 million caused by the contractor's 4 month delay in  
achieving substantial performance, for which FCC seeks indemnity  
from CMI.  
10.  
At the opening of the trial, the quantification of the  
counterclaim and the third party proceedings against CMI were  
severed. CWMM's third party claim against one of the equipment  
manufacturers Buhler (Canada) Ltd. was discontinued with costs  
reserved. Both the FCC and CMI actions were heard together.  
11.  
To be decided is:  
1.  
Liability and damages in CMI's action against FCC  
including the liability of UGG and CWMM to contribute  
to or indemnify FCC for any damages which may be  
awarded to CMI;  
2.  
3.  
Liability and damages in FCC's action against UGG and  
CWMM;  
Liability in UGG's counterclaim against FCC.  
NATURE OF THE CLAIMS  
12.  
In this case FCC alleges it suffered damages because the  
acts or omissions of CWMM or UGG prevented it, despite all of its  
- 10 -  
efforts in mitigation, to achieve substantial performance under  
the contract by August 31. No analysis was done by either  
plaintiff in an attempt to quantify each delay period said to  
have been caused by each respective act or omission alleged  
against the defendants. That is to say no ordinary or expert  
evidence was tendered linking a specific defendant error to a  
quantified delay period.  
13.  
Rather the plaintiffs rely on the evidence in the documents  
created at the time together with the testimony of witnesses to  
show the causal link between the defendants' failings and the  
project delay. They assert that if I conclude that the  
plaintiffs' original plans of work were achievable, and if I also  
conclude that no act or omission of the plaintiffs caused any  
delay, then I must conclude that the late completion was caused  
by the failings of the defendants which did not allow FCC and CMI  
an "unimpeded run at the work".  
14.  
CMI emphasizes what it says was CWMM's failure to address  
the following problems that it says hampered its work on this  
project:  
(a) The late release of necessary design data;  
(b) The late delivery of equipment which was to be  
installed by others;  
- 11 -  
(c) "Interferences", where the spouting could not be  
constructed as dimensioned by CWMM because it would  
have conflicted with other spouting, or equipment, or  
the building itself; and  
(d) Changes in the scope of CMI's work.  
15.  
16.  
In CMI's case, this can be assessed only by reviewing how  
CMI intended to execute its work, by reviewing the reasonableness  
of its bid, and reviewing each claim to determine why the claim  
arose and how much it cost CMI.  
CWMM contends that many aspects of this project did not  
proceed as and when originally anticipated by various parties  
during the tender period. The witnesses with experience in  
retrofit industrial projects testified that unanticipated  
problems frequently occur in this type of project. However, in  
CWMM's submission, the two critical issues in both actions are:  
what were the effective causes of the delay in the completion of  
the project, and where does legal responsibility lie for those  
causes of delay?  
17.  
I concur with that submission and conclude that as a  
starting point I must answer the following questions regarding  
the plaintiffs' allegations against the defendants:  
- 12 -  
1.  
2.  
Were any one or more of the alleged acts or omissions  
of UGG or CWMM an effective cause of the delay to the  
progress of the work?  
If the answer is yes, was that work on the critical  
path such that that delay caused loss or damage in the  
forms asserted by FCC and CMI?  
3.  
4.  
If the answer to 1 & 2 is yes, were there any  
concurrent delays not caused by the defendants?  
If there were any such concurrent delays, is that a  
complete defence to the plaintiffs' delay claims or is  
it appropriate to apportion fault amongst the parties?  
18.  
The defendants say the plaintiffs claims for damages for  
late completion fail for want of proof. They contend that while I  
heard a long litany of complaints during the trial about the  
matters said to have delayed the plaintiffs in their work, there  
is little or no evidence showing that these complaints were,  
either individually or taken together, the effective cause of the  
plaintiffs failing to complete the work by August 31. In CWMM's  
words, "these complaints can be properly summarized as one  
'cause' after another without 'effect'". It says there has been  
a complete failure to establish on a balance of probabilities  
that any of the alleged breaches, or acts of negligence or  
misrepresentations of CWMM caused a delay, or loss to FCC or  
CMI."  
- 13 -  
19.  
In my view these questions can only be answered by an  
analysis of the evidence to determine whether any of the  
defendant's acts or omissions alleged by the plaintiffs were in  
fact the effective cause of delay or loss to FCC or CMI as they  
contend. I propose to conduct this review chronologically in the  
context of the specific factual allegations and to make  
appropriate findings of fact. In doing so I shall be considering  
whether I am able on the evidence to conclude what the effective  
cause or causes of delay were on this project. If I conclude I  
am able to do that, I shall then consider liability for those  
effective causes under the specific heads advanced by FCC and  
CMI. This will necessarily include an analysis of the terms of  
the contract and subcontract to see if the requisite notice was  
given as well as other provisions said by the defendants to  
constitute a complete or partial defence to the plaintiffs'  
claims. If I conclude that the plaintiffs can succeed, I shall  
assess the recoverable damages for the delay. I shall then turn  
to a consideration of the more specific claims of CMI for  
acceleration, overtime, lost productivity and for the extras  
claimed by both FCC and CMI.  
NATURE OF THE EVIDENCE  
20.  
Because of the nature of the claims, much of the trial  
testimony consisted of the employees of the parties reviewing  
events on the project chronologically. Much of the documentary  
- 14 -  
evidence consisted of notes made at the time by many of the  
participants.  
21.  
FCC kept minutes at the weekly site meetings which started  
February 21. The meetings were attended by all parties as well  
as other subcontractors. The minutes were typed after the  
meeting and circulated to all attendees prior to the start of the  
next week's meeting. The site minutes contained standard  
language inviting recipients to advise if they took issue with  
the accuracy of the minutes. On at least one occasion CMI did so  
and the minutes were revised.  
22.  
The defence witnesses testified that these minutes were not  
objective and tended to reflect the interests of FCC. However  
they lodged no formal objection at the time. Since these minutes  
were kept by the employees of FCC they do have the potential to  
be self serving and selective in the details they record.  
However, because of the absence of any written objections from  
the defendants at the time to the content of the minutes, I  
consider the minutes to be a generally accurate record of the  
proceedings at those meetings, subject to the general proviso  
that they were maintained by FCC and hence have the potential to  
reflect its interests. These minutes can be accorded  
considerable weight when the events recorded can be corroborated  
by notes made at the time by one or more of an adverse party's  
employees.  
- 15 -  
23.  
24.  
Van Dyke of UGG was probably the most prolific note-taker  
and his practice was to record during the meetings both what was  
said at meetings and who said it. He afterwards added to his  
notes what he recalled saying at the meetings.  
Other contemporaneous records were kept in the form of  
internal reports generated by the parties for their own use such  
as the Daily Site Reports prepared each day by Don Steel, FCC's  
site superintendent from February 28 until he left the project  
August 24 and the daily reports kept by CWMM.  
25.  
Generally there was considerable consistency between the  
notes kept by the parties, particularly in the earlier part of  
the project and before the course of the job strained relations  
between the parties. Where notes about a contentious issue from  
witnesses for both sides are generally consistent, I have not  
hesitated to accept them as accurate, and to be preferred to the  
trial testimony of witnesses who were trying to recall what  
occurred at meetings or what their notes meant after the passage  
of some five years.  
26.  
Another feature of this trial was the relative absence of  
expert evidence. I heard from only two expert witnesses: John  
Dawson-Edwards who testified in support of the CMI productivity  
loss claim and Gordon Adams who gave brief expert evidence for  
CWMM on the procedures followed by spouting contractors. These  
- 16 -  
took a total of five days of trial time. The balance of the 127  
days of trial evidence came from ordinary witnesses as to what  
occurred on the project.  
27.  
The defendants take issue with the failure of FCC and CMI to  
call evidence to show how the alleged acts or omissions of the  
defendants caused the plaintiffs to be delayed in the prosecution  
of their work. CWMM says the plaintiffs should have led evidence  
in the form of expert time and motion analyses to show the  
precise nature and extent of the delays alleged. It relies on  
Pacific Coast Construction Co. Ltd. et al v Greater Vancouver  
Regional Hospital District et al (1986) 23 C.L.R. 35 in which  
Wallace J said at p. 55:  
To reach any proper conclusion as to the costs from the  
delay one would be required to analyze the contractor's  
progress and to determine to what extent the different  
causative factors, such as contractor caused delays,  
unavoidable delays and owner-caused delay contributed  
to the overall delay experienced by the contractor. It  
would also be necessary to evaluate the validity of the  
contractor's original contract schedule and the  
"reasonable contractor" schedule.  
28.  
What Wallace J says is: (1) that a plaintiff contractor in  
a delay claim must establish a causal link between an owner  
caused event and resultant contractor delay; and (2) a plaintiff  
contractor must establish that its original contract schedule was  
reasonable, i.e.--that it did not underbid by artificially  
compressing its time estimate to get the contract. However I do  
not take Wallace J's decision on the summary judgment application  
- 17 -  
in Pacific Coast to mean that a plaintiff contractor is obliged  
to lead expert evidence in support of these requirements.  
29.  
While such evidence might make the task of a trial judge  
easier, I am of the view that the evidence of the people who  
actually did the job can be the more compelling. In addition, it  
is not realistic to expect parties to a construction project to  
start keeping detailed records for the purpose of litigation from  
the outset of the project. The evidence to which I accord the  
greatest weight is that brought about prior to the development of  
conflict on the job and before the parties started creating a  
record in anticipation of the subsequent litigation. I am not  
convinced that receiving the opinions of experts who engage in  
post facto analysis is necessarily more helpful than hearing the  
evidence of the people who worked on the job each day and who are  
able, particularly with the assistance of their notes made at the  
time, to explain what was happening.  
30.  
Of course, the party with the legal burden of proof is still  
obliged to make out its case. A failure to do so must result in  
a dismissal of the claim. Even if the party discharges its  
burden of proof and establishes liability, the quality of that  
proof may make it difficult or impossible for the court to award  
the full measure of damages sought. The consequence of that is  
that damages will be awarded in an amount that can be supported  
by the evidence that has been adduced, rather than the damages  
- 18 -  
that might have been recovered had evidence in appropriate detail  
been maintained by the parties and available to the court.  
THE TERMINAL  
31.  
UGG receives grain into the Terminal by railcar and cleans,  
stores, and ultimately loads it onto ships for delivery to its  
customers through an east and a west berth at a dock owned by the  
Vancouver Port Corporation and leased to UGG. The Terminal was  
originally constructed in 1923 and has undergone numerous  
renovations and additions. It has a multi-level section in the  
middle called the workhouse, attached to which are annexes  
running to the north and south containing bins in which grain is  
stored. Also attached to the west side of the workhouse is the  
track shed into which arriving railcars containing grain are  
moved and the contents of the cars emptied into hoppers.  
32.  
Moving down from the top floor, the workhouse contains a  
garner floor, scale floor, distributing floor, bin floor,  
cleaning floor and basement. Conveyors extend horizontally out  
from the bin floor of the workhouse the length of the annexes so  
grain can be moved into the storage bins. Similarly, there are  
conveyors running along the bottom of the bins in the annexes  
used to transfer grain out of the bins.  
33.  
After each arriving car load of grain is dumped and weighed,  
it moves to the top floor of the workhouse through a vertical  
- 19 -  
receiving leg and into garners on the garner floor for drying.  
The grain then moves down through scales on the scale floor,  
through the distribution and bin floors to the cleaning floor in  
the workhouse. At this point the grain is cleaned with small  
seeds, wild oats and broken wheat being separated and directed  
into by-products storage. The clean grain is then again moved  
vertically through the clean grain leg to the top floor, after  
which it passes down through a garner and onto conveyors on the  
bin floor for distribution to the assigned bin in the north or  
south annex for storage.  
34.  
When required for shipment the grain is drawn down from the  
bin onto the basement conveyors and moved to the shipping leg.  
It again travels vertically up the shipping leg to the top floor,  
after which it passes through another garner and scale located on  
the garner and scale floors respectively. It then moves down  
into a shipping bin from which it travels out to the dock via  
shipping conveyors and is loaded onto a waiting ship. Within the  
terminal, the grain is moved upwards using conveyors called  
"legs", horizontally with conveyors and downwards through the  
spouting.  
35.  
Spouting must be designed, manufactured and installed with  
care. Because the grain depends on gravity and because the object  
is to move the greatest volume of grain at the highest possible  
speed and because the direction of spouting runs frequently  
- 20 -  
changes in order to avoid other spouting or structures, it is  
important to minimize sharp changes in direction along the length  
of a spouting run. Such changes cause increased abrasive wear on  
the inside of the spout where the running grain contacts the  
inside of the spout and they can cause grain to accumulate and  
jam the spout. Diamond or twist fittings are used in spouting  
runs where directional changes are required. These are used to  
ensure that maximum grain flow can be maintained through the  
directional changes in the spouting runs. Where the running  
grain contacts the inside of the spouting runs, steel plate  
liners are used to absorb the wear. Liners are periodically  
inspected and replaced as they are worn by the grain flow.  
THE PROJECT  
36.  
This project was intended to increase the terminal's  
capacity to clean grain so UGG could process its share of the  
West Coast grain allocation. To achieve this, two major changes  
were involved: first, new machinery, spouting, dust collection  
and electrical equipment was installed in almost all areas of the  
Terminal, except for the Oilseed Plant and Barley System upgraded  
earlier, and second, a new computer system was installed which  
was intended to put all of the new machinery in the Terminal  
under a new centralized automatic control from a new  
Administration Building.  
- 21 -  
37.  
While this project was underway, the Vancouver Port  
Corporation ("VPC") dock leased to UGG was being upgraded with  
UGG's concurrence under a separate contract between VPC and JJM  
Construction. While FCC played no part in the dock upgrade, it  
was required to install two progressors on the dock. These  
progressors shunt railcars in and out of the track shed where  
grain is unloaded. JJM was a non-union contractor which caused  
conflict with the union forces of FCC.  
38.  
Also while the project was underway, UGG contracted with PCL  
Construction Ltd for a new administration building. FCC had to  
complete tie-ins for grain sampling and install a new centralized  
automatic control in the new administration building. FCC says  
delays by PCL in constructing the building delayed its work. It  
also says substantial performance under the contract was  
impossible until the automatic control was operational.  
PERSONNEL  
CMI  
Randy Popowich - CMI project co-ordinator and CMI principal  
(referred to as "Popowich")  
Howard Popowich - CMI site general foreman (referred to as  
"H. Popowich")  
Gary Todd - CMI Burnaby shop foreman  
Hank Rupert - CMI detailer on site  
Tom Adams - CMI "A" foreman  
- 22 -  
Mark Hiatt - CMI "B" foreman  
John Dawson-Edwards - CMI expert witness re: CMI  
productivity losses  
FCC  
Ted Skodje - Senior Vice-President Western Canada  
John Derhousen - Estimator, mechanical portion of FCC tender  
Ray Marquis - project manager  
Don Steel - site superintendent to August 24, 1989  
Brent Hawkins - site engineer  
John Whitaker - project engineer, prepared FCC schedules  
throughout project - was not available to testify at trial,  
but was examined for discovery. In this judgment references  
to his evidence are references to discovery evidence read in  
at trial.  
Johnny Walker - FCC's demolition subcontractor  
UGG  
Gerry Moore - General Manager, executive vice-president and  
COO of UGG  
Murdoch McKay - Manager of Western Canada Terminal  
Operations  
Clarence Van Dyke - project and systems manager - UGG site  
representative during the project  
Wayne Pope - Manager of Vancouver Terminal Operations  
- 23 -  
CWMM  
Bill Choukalos - President  
Bob Rhodes - CWMM site representative from March 13, 1989  
until April 1990 when he joined UGG  
George Somogyi - mechanical/design engineer  
Gary Van Druten - draftsman/technician/designer  
Herb Hoffman - site representative  
Don Foote - quantity surveyor  
P.J. CAMPBELL & ASSOCIATES LTD.(CWMM sub-consultant)  
John Campbell - project engineer  
David Atwell - mechanical engineer, site supervisor  
BUHLER (CANADA) LTD  
Erwin Notter - manager, materials handling  
HAMMOND ASSOCIATES  
Mark Hammond - electrical engineer, subconsultant to CWMM  
VANCOUVER PORT CORPORATION  
Peter Smith  
CHRONOLOGY  
December 18, 1988 - initial closing date for tenders  
- 24 -  
January 13/89  
-
CMI bids $3,208,876 for spouting and  
dust collection to all general  
contractors  
January 17  
February 10  
-
-
FCC bids $16,484,737 for project  
UGG issues Letter of Intent awarding  
contract to FCC  
February 14  
March 6  
-
FCC issues Letter of Intent to CMI - CMI  
bid reduced to $2,864,228  
Project commencement, grain terminal  
shutdown  
-
March 29  
May 16  
-
-
-
-
-
prime contract signed  
CMI - FCC subcontract signed  
Planned CMI work completion  
Revised Substantial Performance date  
CMI advances claim of $1,478,175.00 to  
FCC  
August 11  
August 31  
November 10  
November 21  
-
FCC submits CMI's November 10 claim,  
together with its own claim for  
compensation, to UGG with a copy to  
CWMM.  
December 29/89 -  
CWMM  
awards FCC  
Substantia  
l
completion  
on project  
- 25 -  
HISTORY OF THE TENDER  
39.  
In May 1987, CWMM prepared a Preliminary Report for Terminal  
No. 3 Improvements which contemplated a phased construction  
program allowing Terminal improvements to be done without  
shutting the Terminal down. An alternative to phased  
construction was to shut the Terminal down for the 40 week  
estimated construction period. The Report also noted an  
estimated Project cost of $9.5 million, which was later updated  
in May of 1988 to $10.6 million. This estimate did not include  
any changes in the bin floor conveyors.  
40.  
At the time UGG was considering upgrading the Terminal it  
was also discussing with VPC the problems it was having with the  
dock. In 1987 a vessel damaged the west berth of the UGG dock  
and put the west berth out of commission for two months. UGG  
continued to ship using the east berth during this period. In  
October of 1987 CWMM, on behalf of UGG, made the first formal  
application to VPC to install two dock progressors. Choukalos  
described these progressors as "an integral part of the terminal  
improvements". The progressors shunt rail cars out onto the dock  
and then into the track shed for unloading.  
41.  
Subsequently, a number of improvements mentioned in the  
Preliminary Report were done by others including an upgrade of  
the Barley System by Spantek.  
- 26 -  
42.  
In September 1988 UGG decided to add the bin floor conveyor  
upgrade to the scope of the work and to build the new  
administration building. The minutes of a special design review  
meeting of September 28, 1988 note that CWMM had prepared  
preliminary layouts for the bin floor conveyors, and that "this  
administration building is a critical delivery item - must be far  
enough along in construction completion to accept new electrical  
and control room functions".  
43.  
At this time UGG decided that these three significant  
changes to its operation in Vancouver, the Terminal improvements,  
the new Administration Building and the dock upgrade, would best  
be carried out while the Terminal was shut down.  
THE TENDER PERIOD  
(a) THE TENDER  
44.  
On November 17, 1988 tender documents were sent to the pre-  
qualified contractors including FCC. The Instructions to Bidders  
included the following provisions:  
Section 1 - INSTRUCTIONS TO BIDDERS  
1.  
SCOPE OF WORK  
1.1 GENERAL  
1.1.1  
Furnish all labour, equipment,  
supervision, tools and miscellaneous  
materials to complete the mechanical,  
electrical and structural work including  
track work to the full intent of the  
drawings and specifications.  
- 27 -  
The scope of this work includes the  
supply of all equipment, including pre-  
selected equipment appendixed. U.G.G.  
has prepaid some of the referenced  
suppliers of pre-selected equipment.  
The details of prepayments are listed  
and will be accounted for on the Tender  
Form.  
Test all mechanical and electrical  
equipment in accordance with the  
specification....  
1.1.3  
The work shall include but not be  
limited to the following areas:  
a)  
b)  
c)  
d)  
e)  
f)  
Trackwork and Receiving  
Primary Wheat Cleaning  
Distribution  
Bucket Elevator Upgrades  
Primary Wheat Reclaim  
Bin Floor Conveyors and Scale 3  
Spouting  
Miscellaneous work in North Annex  
New Panel Room and offices,  
equipment rooms in Administration  
Building....  
g)  
h)  
1.5 Purchase and Installation of Pre-selected  
Equipment  
1.5.1  
The Owner has pre-tendered and selected  
equipment to be used for this project  
and has issued Letters of Intent to the  
successful tenderers. Copies of the  
Letters of Intent are appendixed.  
1.5.2  
The Contractor shall issue a purchase  
order to the manufacturers of the pre-  
selected equipment for the prices and  
conditions detailed in the Letters of  
Intent. The Contractor shall arrange  
for delivery, receive, store, install  
and warranty the pre-selected equipment.  
1.5.3  
The cleaning equipment has been  
purchased fully assembled. If the  
Contractor finds that he must dismantle  
and reassemble the equipment for  
installation, he shall arrange with the  
manufacturer for whatever is required to  
maintain the manufacturer's warranty.  
- 28 -  
The Contractor shall include in his bid  
the costs of any dismantling and re-  
assembly.  
1.5.4  
The bucket elevators will come in  
components for site assembly including  
the buckets which must be bolted to the  
belts. Pulleys will be mounted on  
shafts along with bearings and low speed  
coupling half. If required to  
disassemble the pulley assemblies for  
installation it will be the Contractors  
responsibility to reassemble. Drive  
base will be shipped complete with all  
drive components as shown....  
12. SCHEDULING OF WORK  
12.1 Speed and sequence of construction is of the  
essence. Plant shutdown is scheduled to begin  
March 6, 1989. The plant must be fully  
commissioned and handed over to UGG on or before  
July 31, 1989...  
45.  
46.  
On November 28, 1988 the tender date was extended to January  
6 and on December 21, 1988 it was further extended to January 17.  
The Terminal shutdown date of March 6 remained unchanged.  
On November 23, 1988 Campbell faxed Van Dyke requesting  
advice of "all equipment that you want to keep - reference  
demolition and removal", and noting "we would like to advise  
contractors this info in Monday's addendum". UGG did not respond  
until after the contract was awarded. FCC subcontracted the  
demolition work to Johnny Walker and UGG afterwards decided to  
keep certain equipment that both FCC and Walker assumed would be  
his. He billed FCC for this equipment, which FCC in turn claims  
from UGG.  
- 29 -  
(b) CMI'S WORK PLAN  
47.  
In the weeks leading up to the tender, CMI developed its  
plan for the project. It contemplated fabrication at its shop in  
Burnaby and its related companies in Calgary and Spruce Grove,  
Alberta. CMI advised tendering contractors of its plan by  
letters of December 5, 1988 and January 4. The "work outline"  
enclosed with the January 4 letter described CMI's plan for the  
mobilization, prefabrication of product, installation, and  
availability of steel. The December 5, 1988 proposal explained  
that:  
"Fabrication would begin as soon as an approval could  
be received on any drawing submissions. We would  
utilize all three company facilities to increase  
fabrication output."  
"All shops would then ship their fabricated product to one  
coating facility ... in the Lower Mainland... This area  
would also act as our marshalling yard. Inspection of any  
product or coating application could be made the consultants  
or owner at this location."  
"When an area becomes available, the preparation of the  
fabrication drawings and pre-fabricating of products ...  
will allow us the flexibility required to complete the many  
different areas with short notice."  
"Manpower will not be a problem at this company, we  
presently have an active waiting list of key site personnel  
for engagement."  
48.  
Popowich described the plan for preparing and submitting  
shop drawings, having those shop drawings returned with the  
designer's comments, and the production process thereafter. When  
prepared, the shop drawings were to be submitted through FCC to  
CWMM who would review the drawings and return them, generally  
- 30 -  
either marked "review completed", "make corrections as noted", or  
"resubmit". This process of submissions and the review process  
actually started on March 8.  
49.  
50.  
Following CWMM review, the shop drawing and computer disk of  
the drawing were to be reviewed by Fagrie to determine whether  
any special fittings required manual detailing. If so, he would  
prepare custom drawings.  
The next step in the process was the preparation of cutting  
sheets. These sheets were a translation of the three dimensional  
spouting details on the shop drawings into two dimensional shapes  
to be cut from steel plate. This information was stored on  
floppy disks. When the shop foreman was ready to cut the steel  
shapes, he would download the cutting information from the floppy  
disk to the computerized cutting table. The sheet steel was then  
laid on the cutting table and the shapes cut by the computer  
guided cutting torch. Once the steel was cut, drilling or  
punching holes for bolted connections, or folding the sheet to  
form the final shape of the spout would occur. The final step of  
the fabrication stage was the attachment of angle brackets,  
welding joints, attaching liners and assembly of lids. The  
assembled spout would then be ready for painting and shipping to  
site.  
- 31 -  
51.  
CMI's plan was contingent on an adequate supply of sheet  
metal workers in Vancouver for the field installation. While  
there was an adequate supply in the spring when CMI planned to  
start field installation, the delays in the project meant that  
when CMI went to ramp up its field forces in the summer of 1989,  
it found a shortage of labour.  
(c) CMI'S PLANNED SEQUENCE OF CONSTRUCTION  
52.  
CMI's January 4 letter to the invited general contractors  
included some preliminary schedule information. The bin floor  
conveyer spouting was the first element CMI planned to finish, by  
June 15. The balance of the spouting was planned to be complete  
by July 15.  
53.  
FCC's February 20 "tender schedule" (actually prepared after  
the award had been received) shows the installation of dust  
control ducting in March, gates during the last week of March and  
spouting beginning April 3. It also indicates equipment  
deliveries of such equipment as drag conveyors, primary wheat  
cleaners and wheat reclaim equipment, to which CMI was obliged to  
connect its spouting runs.  
54.  
After receiving FCC's tender schedule, CMI faxed its  
detailed spouting and dust control schedule to FCC on March 27.  
CMI planned to start work in the primary wheat cleaning area:  
installation of feed pots and hoppers was to have begun  
- 32 -  
immediately, with spouting to follow in a logical sequence. The  
spouting for the north annex was to be installed through the  
month of April and south annex spouting was to be installed  
beginning late in April and completing in early July. Other  
areas of the work were similarly detailed as to CMI's intended  
sequence of construction.  
55.  
The intended sequence of construction in this case was of  
considerable significance. Many of the areas into which spouting  
had to be installed were extremely congested and hence it was of  
critical importance that CMI be able to proceed with its field  
installation sequence as planned.  
(e) THE ACCURACY OF THE CMI ESTIMATE  
56.  
On January 13, CMI submitted its tender to all bidding  
general contractors, offering to perform the spouting and dust  
collection work for $3,208,876. The takeoff of material  
quantities for the estimate was prepared by David Harrish, the  
senior industrial estimator for CMI's Spruce Grove affiliate.  
Popowich then prepared CMI's bid price on the basis of CMI's  
experience and on trade information authored by American sheet  
metal expert Victor  
Ottaviano. Popowich's analysis of the productivity factors were  
based on Mr. Ottaviano's suggested labour factors for "black  
iron".  
- 33 -  
57.  
58.  
59.  
On January 16 Popowich wrote to Marquis advising of a  
deduction of $125,000.00 from the original total lump sum amount.  
Although this was ostensibly because FCC was going to provide  
overhead cranage, the defendants say that CMI had carried only  
$22,000 in its original bid for this item. In addition CMI  
reduced its gate installation price to $22,000. The defendants  
say that by so doing CMI effectively underbid this job.  
Popowich testified that although he suggested at the time  
that the $125,000.00 related to cranage, in fact the only cranage  
that CMI had in its bid was $22,000.00, which was eventually  
carried into its final tender price to FCC. In my view CMI's  
reduction of its tender to $3,083,876.00 was a reasonable  
response to Popowich's increased familiarity with the project and  
its requirements.  
As a precondition to its lost productivity claim, CMI must  
establish the reasonableness of its estimate. A comparison of  
CMI's original estimate with the bids of its competitors Bisco  
and Irvco is instructive. After adjusting for differences in the  
scope of work tendered, Bisco's tendered price was approximately  
1% lower than CMI's price. Irvco's price was approximately 6%  
higher. This narrow differential suggests that either all of the  
bidding spouting subcontractors formulated unrealistic plans for  
the work, or, as is more likely, CMI's plan was realistically  
planned and priced. I find the latter to be more probable.  
- 34 -  
60.  
Further support for the CMI bid and the consequent  
reasonableness of its plan of work can be found in a comparison  
between its take-off and CWMM's earlier June 1988 take-off.  
Since the CWMM take-offs were done prior to any addenda, the  
comparison is to the original CMI take-off figures.  
CWMM  
TAKE-OFF  
CMI  
TAKE-OFF  
%
DIFFERENCE  
Reclaim  
27,223 lb.  
27,336 lb  
(Exh. 13,  
doc. 3556)  
(Exh. 119, p2)  
<1%  
3.5%  
6%  
Wheat Cleaning  
Distribution  
99,924 lb  
(Exh. 120,p2)  
96,429 lb  
(Exh. 13,  
doc. 3583)  
99,848 lb  
(Exh. 121,p2)  
93,546 lb  
(Exh. 13,  
doc. 3583)  
61.  
It is significant that CWMM's estimated unit cost for all  
areas was identical at $4.50/lb. From a further comparison of  
unit prices, it can be seen that CWMM added a 7% "mark-up" before  
bringing the costs forward to its summary sheet of January 16.  
The total calculated in that summary was then increased by  
approximately 16% for escalation and other factors. Applying this  
to the $4.50 unit cost gives an adjusted unit price of $5.60/lb.  
62.  
This figure is almost identical to CMI's overall tendered  
unit price for spouting. CMI's January 24 "final sheet" and the 7  
back-up sheets to it show the following figures:  
- 35 -  
$1,632,333 estimated spouting costs from p.1-5;  
411,112 lb. estimated spouting weight from p.1-5;  
$359,918 mobilization costs: approximately 18% of other  
costs  
20% profit  
63.  
64.  
CMI's unit price derived from these figures is $5.62/lb.  
Based on the foregoing, I conclude that CMI's bid for the work  
was reasonable.  
(f) FIELD MEASUREMENT  
CMI's plan which it communicated to FCC and CWMM before  
FCC's tender was accepted February 10, showed significant pre-  
fabrication of spouting. That is the spouting was to be  
fabricated in sections and the liners installed prior to delivery  
to the site. CMI's intention was to pre-fabricate runs of  
spouting off-site based on CWMM's construction drawings leaving  
the last or at least one section of spouting in the run to be  
measured on site and custom finished at the time of installation  
when the all of the spouting segments in each run were joined  
together. CMI says inaccuracies in the drawings caused it to  
encounter interferences when it went to install the spouting  
runs. This in turn generated much extra work in fabricating  
replacement fittings to accommodate these interferences.  
65.  
The defendants say CMI was obliged under the contract to  
"field measure" or use a fabrication procedure to ensure that the  
- 36 -  
spouting could be installed without interferences. I deal with  
the responsibility for field measurement in the "Project Delay"  
section of the judgment.  
(g) PRE-SELECTED EQUIPMENT  
66.  
On or about January 9, Addendum number 4 added the rest of  
the Letters of Intent to the preselected (or, as referred to by  
FCC "pre-purchased") equipment suppliers. By this date the  
tender documents included Letters of Intent of various dates  
issued to 12 equipment suppliers by CWMM. The equipment  
suppliers were companies who were to supply specific equipment  
selected by and fabricated to CWMM's specifications for  
installation in the Terminal. The 12 equipment suppliers were  
selected by CWMM on UGG's behalf prior to the close of tenders on  
February 10 by which date UGG had made payments to Buhler, Carter  
Day, Motion Control, Ebco, Western Scale and Transcontinental  
Engineered Products. The letters of intent had a projected  
delivery date to the site of mid-March. Van Dyke testified as to  
UGG's intention:  
Well the plan of UGG was that we have all the equipment  
that took a long time to manufacture be made and be  
ready prior to when the contractor was going to need  
it.  
67.  
To achieve this, it is clear from the evidence of Van Dyke  
and Campbell that UGG and CWMM intended that all of the equipment  
be designed and manufactured so as to be available to be  
delivered to the Terminal in or about March 1989 at the latest.  
- 37 -  
68.  
I conclude that prior to the close of tenders on February  
10, FCC and CMI understood the owner's intention and both  
contractors believed that all of the preselected equipment would  
be available so it could be delivered to the Terminal in or about  
mid-March. FCC and CMI were entitled to rely and did in fact  
rely on the accuracy of the tender documents, including the  
Letters of Intent to the equipment suppliers. As Campbell said in  
discovery, "when a delivery date is set out in a letter of intent  
in a tender package as a matter of practice in the construction  
industry it is assumed by the tendering contractor that the date  
has been agreed to by the recipient of the letter". I find that  
FCC and CMI relied on the dates shown in the letters of intent in  
formulating their bids and planning their work on the project and  
that such reliance was reasonable and justified.  
69.  
A common provision in the Letters of Intent also required  
the equipment suppliers to submit certified or "shop" drawings to  
CWMM within 10 or sometimes 14 days of the Letter of Intent. The  
shop drawings which passed back and forth between CWMM and the  
equipment suppliers were significant since generally an equipment  
manufacturer waits for a fully reviewed shop drawing from the  
engineer before completing fabrication of the equipment.  
Cardinal Construction v. Corporation of the City of Brockville  
(1984), 4 C.L.R. 149 (Ont. H.Ct.), states the effect of tender  
documents at p. 170:  
- 38 -  
...Given the general principle that a bidder is  
entitled and expected to rely on the tender documents  
as conveying the best information the engineer can  
give, it is not good enough in my opinion to provide  
information that is misleading incomplete or inaccurate  
with the intention that the more experienced or  
knowledgeable bidder will ferret out the problems from  
"clues". The information should be clear and  
intelligible to all bidders and in this case it was  
not.  
70.  
CWMM omitted material information concerning the equipment  
from the tender documents. In the months prior to the issuance  
of the tender documents, CWMM and UGG received quotes from the  
various proposed equipment suppliers. These quotations, except  
for the quote from Klockner-Moeller, were neither included in the  
tender documents nor disclosed to any of the tendering  
contractors. This became a significant omission because many of  
the equipment suppliers never agreed to deliver equipment by mid-  
March as set out in the letters of intent. Had at least the  
quotations from these suppliers been communicated to bidders such  
as FCC and CMI, they would have realized prior to tendering that  
much of the equipment was not going to be delivered by mid-March  
as shown in the letters of intent. Instead only the letters of  
intent were included in the Tender package and in my view, they  
were inaccurate representations to tendering contractors of  
agreements between UGG and the equipment suppliers to manufacture  
and supply the equipment in accordance with the Letters of Intent  
both as to dates for supply of shop drawings and delivery.  
- 39 -  
71.  
On or about January 16 Campbell did his own tender estimate  
to compare with the tenders as they came in. He noted that with  
respect to the scope of the Project, the addition of the bin  
floor drag conveyors being supplied by Buhler had increased the  
scope of the Project by approximately 30%. After the Buhler  
conveyors were delivered, FCC had to install and align them and  
then CMI had to connect gates and spouting. Accordingly the  
timely delivery of this equipment became an essential ingredient  
of the ability of FCC and CMI to complete their work as  
originally scheduled.  
72.  
On January 17 FCC submitted its tender in the amount of  
$16,484,737.00. Following discussions between January 17 and  
February 9 and an exchange of correspondence and credits for  
further payments, the tender price was reduced to $15,959,072.00.  
One significant change was a $135,000.00 credit given by FCC to  
UGG to extend the completion date from July 31 to August 31,  
1989.  
73.  
By January 23 Popowich had reworked his estimate to assist  
him in negotiations with the tendering contractors for the  
spouting subcontract. He changed CMI's bid from being based on  
field installation of 12 hour day shifts, 4 on, 4 off, to a 5 day  
shift. Popowich says the 5 day shifts were based on 7-1/2 hour  
days. The other parties contend that CMI's revised estimate was  
based on 9 hour days. Popowich was extensively cross-examined on  
- 40 -  
this point and I accept his evidence that with the one month  
extension of the contract completion to August 31 his final  
estimate of $2,883,876.00 was based on 7-1/2 hour days. This  
price, subject to a number of additions and deletions, eventually  
formed the basis for the Subcontract price between FCC and CMI.  
74.  
75.  
On January 31 Campbell sent a fax to Van Dyke with a copy  
of the CMI pre-qualification which outlined CMI's intention to  
prefabricate a large part of the spouting.  
On February 8 Marquis advised Popowich that as of that date  
FCC was estimating installation of the distributors for May 8 -  
May 22, the primary wheat cleaners for April 17 - April 24, and  
the drag conveyors April 17 - May 7.  
76.  
On February 10 UGG accepted FCC's tender and awarded the  
Project to FCC. Subsequently minor amendments were agreed to  
between FCC and UGG respecting, inter alia, charge out rates for  
extra work.  
THE PRIME CONTRACT  
77.  
The prime contract was dated March 29, 1989 and provided,  
inter alia, that FCC would:  
"(c) commence the Work by the 10th day of February  
1989 and attain Substantial Performance of  
the Work, as certified by the Consultant, by  
the 31st day of August 1989."  
- 41 -  
78.  
It provided in General Condition ("GC") 1 that:  
"Substantial performance of the work is as defined in  
the lien legislation applicable to the Place of the  
Work. If such legislation is not in force or does not  
contain such definition, Substantial Performance of the  
Work shall have been reached when the Work is ready for  
or is being used for the purpose intended and is so  
certified by the Consultant."  
79.  
80.  
81.  
82.  
Supplementary General Condition ("SGC") 13 added the  
following:  
"Substantial performance is further defined, with  
respect to conveyors, only when product flow has been  
achieved and to design or maximum capacity."  
Specification 15A.4.6 provided:  
15A.4.6  
Commissioning  
Equipment commissioning is not defined  
complete until product has run through  
the system at design or maximum load.  
This was a lump sum contract with a requirement for  
substantial performance as defined.  
PRESELECTED EQUIPMENT DELIVERY DELAY - RESPONSIBILITY  
(a) Introduction  
Much of the preselected equipment was delivered later than  
the mid-March date set out in the letters of intent. However  
under the terms of the prime contract, UGG purported to transfer  
the responsibility for the equipment, including its timely  
delivery, to FCC.  
- 42 -  
83.  
This was custom equipment being fabricated to the  
specifications of CWMM. The manufacturers were required to  
submit shop drawings to CWMM for its approval prior to  
fabrication. CWMM issued letters of intent to 12 suppliers,  
copies of which were included in the tender documents. The basic  
format of the Letters of Intent was similar. Each letter began:  
"On behalf of United Grain Growers (U.G.G.) we confirm  
that U.G.G. intends to purchase, through their  
contractor,..."  
(emphasis added)  
84.  
The purchase price in the Letters of Intent were "FOB UGG  
Vancouver, B.C.".  
The Letters of Intent said:  
"The contractor, upon being appointed by UGG, will be  
required:  
-
-
to purchase this equipment in accordance with  
your quotation and this Letter of Intent.  
to assume the year warranty on this  
equipment.  
-
-
-
to arrange with you for delivery.  
to receive the equipment.  
to store and to install the equipment".  
(emphasis added)  
85.  
Certainly prior to February 10, the letters of intent were  
individual contracts between UGG and the respective equipment  
suppliers for the supply of equipment insofar as they committed  
UGG to pay for the equipment whether or not the Project proceeded  
and, if the Project did proceed, irrespective of who the general  
contractor would be. In respect of half of the equipment  
- 43 -  
suppliers, payments were made by UGG directly to the supplier  
prior to the award of the Prime Contract to FCC on February 10.  
86.  
CWMM and UGG say that the intent of the "Instructions to  
Bidders" was that the general contractor, upon award of the  
construction contract, was to assume direct contractual  
responsibility for the pre-selected equipment. They point to the  
instructions which provided:  
1.5 Purchase and Installation of Pre-Selected  
Equipment  
1.5.1  
the Owner has pre-tendered and  
selected equipment to be used for this  
project and has issued Letters of Intent to  
the successful tenderers. Copies of the  
Letters of Intent are appendixed.  
1.5.2 the Contractor shall issue purchase  
orders to the manufacturers of the pre-  
selected equipment for the prices and  
conditions detailed in the Letters of Intent.  
The Contractor shall arrange for delivery,  
receive, store and install and warranty the  
pre-selected equipment." (emphasis added)  
87.  
Did CWMM and UGG succeed in shifting responsibility as they  
contend? To answer this question the letters of intent, the  
Prime Contract and the conduct of the parties during the course  
of the Project must be considered.  
(b) THE LETTERS OF INTENT  
88.  
Each Letter confirmed "that UGG intends to purchase, through  
their contractor..." certain equipment. "Through" means "by the  
agency of". (See Black's Law Dictionary, 6th Edition, Definition  
- 44 -  
of "through"; Rye and Eyre v. Inland Revenue Commissioners,  
[1935] A.C. 274, at pp. 278-279 (H.L.)). That language creates  
at least the prospect that in respect of the purchase of the  
equipment, FCC was acting not as a principal but as UGG's agent.  
As Hammond testified with respect to Klockner Moeller, the  
Letter of Intent "tells Klockner Moeller that basically no matter  
what UGG will pay Klockner Moeller for the motor control  
centres".  
89.  
The letters of intent were representations or guarantees to  
the suppliers that ultimately UGG would ensure they were paid for  
the equipment. If UGG had decided not to proceed with the  
project, they were nonetheless guaranteeing payment.  
(c) THE LANGUAGE OF THE CONTRACT  
90.  
The obligation of FCC is set out in 1.5.2 in the  
Instructions to Bidders quoted above. Although this requires the  
contractor to issue its own purchase order, nowhere in that  
section does it provide that the contractor shall purchase the  
equipment and resell it to UGG. In fact, Instruction to Bidder,  
1.5.3 says:  
"the cleaning equipment has been purchased fully  
assembled".  
(emphasis added)  
- 45 -  
91.  
The contractor was also obliged to issue a purchase order  
"for the prices and conditions in the letters of intent". The  
contractor had no right to vary any of those terms previously  
committed by UGG. In addition, the instructions did not impose  
an obligation on the contractor to ensure or guarantee "timely"  
delivery. Alternatively, the instructions contained no language  
which would have alerted a contractor or put it on notice that  
the proposed delivery dates in the letters of intent issued by  
UGG were not to be relied upon or were to be verified by the  
contractor prior to tender.  
92.  
This provision did not require FCC to step into CWMM's shoes  
after February 10 with respect to the continuing design or  
fabrication of the equipment. There was no intention that FCC  
take over any of the design or fabrication responsibility for the  
equipment. That always remained with CWMM. FCC was only  
obligated to "arrange delivery" under the contract.  
93.  
Clearly, had the design and fabrication of the pre-selected  
equipment occurred on what was doubtless the originally intended  
timeline so that it would have been available for delivery by  
mid-March, the task of finalizing the design and indeed much of  
the fabrication would have been completed when the contract was  
awarded to FCC on February 10. However because this did not  
occur, it is difficult to see how FCC can be fixed with the  
responsibility for the fact that the equipment was late-  
- 46 -  
delivered. In my view, had the parties intended to fix FCC with  
this obligation, clearer contractual language ought to have been  
used. That language ought to have included at least a warning  
that bidding contractors were not to rely on the mid-March dates  
in the letters of intent and were to conduct their own  
independent investigations prior to tender.  
94.  
I conclude that the obligation to issue a purchase  
order for "the prices and conditions detailed in the Letters of  
Intent" when considered in conjunction with the language of each  
Letter of Intent and Instruction to Bidder 1.5.3 indicates that  
the intention of the contract was that the purchaser of the  
preselected equipment was at all times to be UGG, and in respect  
of that purchase FCC was acting as UGG's agent in issuing the  
purchase orders. This is consistent with the fact that the  
equipment was selected, designed and manufactured to the approval  
of CWMM and UGG.  
95.  
In addition, FCC did not, at any time, have any property in  
the equipment. The delivery of the equipment was FOB site. The  
method of delivery and the risk in the property was completely  
with the equipment supplier until delivery to site. After  
delivery, the equipment became the property of UGG. The FCC  
warranty only commenced after substantial performance was  
achieved. UGG says that the payment of a markup to FCC on the  
equipment purchased meant that FCC purchased the equipment as  
principal and resold it to UGG and that FCC was thereby  
- 47 -  
responsible for the late delivery. I do not agree with that  
submission. FCC was to warranty the equipment after substantial  
performance and the markup was likely the appropriate  
consideration for FCC's agreeing to assume that responsibility.  
96.  
UGG also says that FCC signed the formal contract on March  
28 with full knowledge that most of the equipment would be  
delivered later than mid-March. While this is true this  
submission misinterprets the legal effect of the letter of intent  
awarding the contract to FCC on February 10. The parties entered  
into a binding contract February 10 when FCC's bid was formally  
accepted by UGG. This is supported by Campbell who testified that  
the effect of a letter of intent in this context is that a  
binding contract is entered into upon issuance. It is clear that  
all of the parties acted on the basis of letters of intent and  
not the formal contracts. While FCC learned shortly after  
February 10 that there would be some delivery delays, it also  
believed that it could still achieve substantial performance by  
August 31 by utilizing the float time built into its schedule.  
97.  
CWMM continued to be responsible for the completion of the  
design of the equipment and the approval of submitted shop  
drawings after February 10. In my view, it would not be a  
consistent interpretation of the contract documents to conclude  
that FCC, which had no input into this continuing design process,  
- 48 -  
was nonetheless responsible for the timely delivery of equipment  
when it had no control over the design or fabrication.  
(d) COURSE OF CONDUCT - PRESELECTED EQUIPMENT  
98.  
Alternatively, if the terms of the Prime Contract relating  
to the pre-purchase equipment are ambiguous, reference can be  
made to parol evidence to determine the intention of the parties.  
Throughout the course of the Project, FCC took the position that  
its only obligation with respect to the preselected equipment  
suppliers was to arrange for delivery and install the equipment  
once it reached the site. FCC made it clear that it had no  
responsibility for the design or manufacture of the equipment or  
expediting the equipment.  
99.  
While UGG and CWMM complained between themselves about FCC's  
failure to expedite the equipment, they took steps to expedite  
the delivery of equipment by Bisco, Ebco, Concise,  
Transcontinental Engineered Products, Hansen, Buhler, Klockner  
Moeller, Nord-Sen and General Railway. These expediting steps  
included making cash payments to suppliers, approving necessary  
change orders, choosing enamel paint for track instead of epoxy,  
authorizing the shipment of equipment without shop testing,  
authorizing shipment of equipment by air freight and writing  
letters directly to the suppliers. While these steps may be  
characterized as merely assisting FCC in the discharge of what  
CWMM and UGG viewed as FCC's obligations, I consider that they  
- 49 -  
can more properly be viewed as conduct consistent with a  
continuing obligation recognized by CWMM and UGG to ensure that  
the equipment was delivered, if not in accordance with the  
scheduling represented to bidders at the outset, then as soon  
thereafter as that could be accomplished. If they were merely  
assisting FCC in discharging its contractual obligation, I would  
have expected UGG and CWMM to have been advising FCC throughout  
of their expediting efforts. In fact the contrary occurred; FCC  
was not so advised.  
100.  
In my view, CWMM continued to act after February 10 in a  
manner inconsistent with a complete transfer of responsibility  
for the equipment to FCC. On February 14, Campbell wrote to  
Carter day in Winnipeg questioning the reliability of a supplier  
they proposed to use. If FCC had assumed responsibility for that  
equipment, one would have expected Campbell to have at least  
copied FCC with the letter. He did not. The evidence at trial  
showed many such instances of CWMM and or UGG dealing with the  
equipment suppliers without advising FCC and in my view, this  
conduct is consistent with an interpretation that the contract  
imposed an obligation on FCC to purchase the equipment as UGG's  
agent and not as an independent principal and that UGG continued  
to be responsible for the timely delivery of the equipment.  
101.  
With respect to the parties course of conduct for the pre-  
selected equipment I summarize my findings as follows:  
- 50 -  
1.  
CWMM and UGG represented to bidders including FCC and  
CMI that the equipment would be delivered to the site  
approximately mid-March;  
2.  
3.  
FCC and CMI relied on that representation in preparing  
their tenders and plans to do their work;  
CWMM and UGG knew as of February 10 that much of the  
equipment would not be available for delivery by mid-  
March, but nonetheless never advised FCC or CMI prior  
to February 10;  
4.  
CWMM and UGG retained the responsibility for the design  
and timely delivery of the equipment after February 10.  
102.  
103.  
104.  
This, in my view, is consistent with a plain reading of the  
contract by which UGG was the effective purchaser of the  
equipment under the letters of intent.  
Further support for this interpretation is also found by  
examining the conduct of the parties with respect to the  
individual items of equipment.  
The Rail Car Progressors were manufactured by Motion  
Controls Inc. before the Terminal was shut down.  
Two  
progressors were installed on the dock and one progressor was  
installed on the UGG property. The progressors were installed to  
automatically advance railcars as part of the receiving function  
of the Terminal. The Letter of Intent provided a purchase price  
- 51 -  
of $314,636.83 of which $228,458.68 was paid to Motion Controls  
prior to February 10 and by February 20, the railcar progressors  
were in storage in Vancouver.  
105.  
The Rail Car Retarders were manufactured by General Railway  
Signal of Canada. The Rail Car Retarders function to stop the  
railcars after shunting. The Letter of Intent provided for a  
purchase price of $175,953.57. UGG issued a purchase order to  
General Railway directly in that amount to become the importer of  
record.  
106.  
In September 1988, General Railway advised that "delivery  
could be completed within (120) one hundred and twenty days of  
receipt of a Letter of Intent". There were three letters to  
General Railway dated September 30, October 5 and October 27,  
1988. The October 27, 1988 letter said "latest date for receipt  
of equipment is February 18, 1989". On January 13 Somogyi wrote  
to General Railway advising that "no equipment shall be shipped  
before drawings etc. are reviewed by us." This equipment was  
delivered May 4 after UGG had issued a purchase order direct to  
General Railway on April 7.  
107.  
The Rail Car Gate Opener was manufactured by Concise  
Technik. This is a machine that travels on a rail beside the  
railcars and opens the railcars to allow grain to flow into the  
- 52 -  
hopper pits in the Track shed. The Letter of Intent provided for  
a purchase price of $61,692.00.  
108.  
Concise's quote of December 14, 1988 provided for delivery  
"11 - 13 weeks". The revised quotation dated January 6 also  
provided delivery "11 - 13 weeks". The Letter of Intent dated  
January 9 provided "projected shipping date March, 1989". Eleven  
to 13 weeks from January 9 was between March 27 and April 10.  
While the Letter of Intent required drawings within "ten (10)  
working days after receipt of" the Letter of Intent, drawings  
were submitted by Concise between March 6 and May 30. The final  
shop drawings for Concise were checked and returned by CWMM on  
June 6. The track arrived on site June 7 and the car opener  
arrived on site in August. It had to be modified to fit a new  
panel and became operational in the fall of 1989.  
109.  
The Receiving Bulkweigher was manufactured by Western Scale  
Ltd.  
The Bulkweigher is located in the Trackshed and weighs  
grain being received while the grain is flowing through it. It  
requires government certification prior to use. The Letter of  
Intent dated September 1, 1987 provided for a purchase price of  
$84,200.00 of which $60,000.00 had been paid by UGG to Western  
Scale by February 10.  
110.  
The Receiving Bulkweigher was complete as of February 20 but  
there were delays in UGG and CWMM getting the bulkweigher  
- 53 -  
certified so that grain could be received over it. Complicating  
factors included changes to the software package in the fall of  
1989 relating to the bulkweigher and changes in the  
communications between the bulkweigher and the terminal  
computers.  
111.  
The Primary Wheat Cleaners, the Wheat Reclaim Equipment and  
the Reclaim Jack-Legs were manufactured by Carter Day Ltd. The  
Wheat Cleaners are used to clean wheat after it is received into  
the Terminal. The Wheat Reclaim Equipment and Reclaim Jack Legs  
are used as a part of the process to make use of dockage and  
other material cleaned from the wheat by the Primary Wheat  
Cleaner. The Primary Wheat Cleaners are located on the Cleaner  
Deck in the workhouse. The Wheat Reclaim Equipment and Wheat  
Reclaim Jack-Legs are located in the Wheat Reclaim area in the  
upper Workhouse. The Letter of Intent provided for a purchase  
price of $1,140,922.48 of which $250,635.00 had been paid by UGG  
to Carter Day prior to February 10.  
112.  
The equipment listed in the Letters of Intent dated  
September 23, 1987 and November 2, 1988 was stored at Annacis as  
of February 20, 1989. With respect to the Wheat Reclaim  
Equipment listed in the Letter of Intent dated January 6, 1989,  
on December 6, 1988 delivery was quoted to be "10 weeks from  
receipt of approved drawings, with the exception of the elevator  
belting. Quoted delivery on the belting is 12 - 14 weeks". This  
- 54 -  
Letter of Intent stated "projected shipping date early March of  
1989". Twelve to fourteen weeks from January 6 was between March  
31 and April 14, 1989. The first Carter Day shop drawings were  
submitted to CWMM on January 26. The final shop drawings were  
returned to Carter Day as being checked on March 1. The  
equipment arrived on site between the middle and end of April,  
1989.  
113.  
The Dual and Single Distributors were manufactured by Ebco  
Industries Ltd. Distributors are turnhead machines which direct  
grain coming into the machine from one or more spouts into other  
spouts leading away from the distributor. D-1 is located in the  
Workhouse on the Distribution Floor, D-2 is located in the  
Workhouse on the Scale Floor, TH-1, TH-2 and TH-3 are located in  
the Workhouse on the Bin Floor. The Letter of Intent dated  
November 16, 1988 provided for a purchase price of $354,000.00 of  
which $53,099.96 had been paid by UGG to Ebco by February 10.  
114.  
Ebco's quote dated November 10, 1988 which referred to  
delivery "March 15, 1989 or earlier" also stated "all other  
conditions are as per our original quotations # 1817 and # 1815".  
Quotation # 1815 said "delivery would be approximately 12 - 14  
weeks from receipt of approved shop drawings". Quotation # 1817  
provided "delivery would be approximately 10 - 12 weeks from  
receipt of approved shop drawings". The Letter of Intent did not  
- 55 -  
contain a delivery date. However, the tender specifications  
provided for a delivery date of mid January, 1989.  
115.  
Ebco accepted the Letter of Intent on November 18, 1988 with  
an amendment not included with the tender documents. On February  
6, Ebco wrote to CWMM advising that they "may be unable to meet  
the March 15, 1989 delivery deadline". The letter concluded "may  
we rely on you to inform the parties of this situation". UGG and  
CWMM did not so inform FCC. The Ebco distributors were delivered  
by May 30 without motors. The motors were delivered in August,  
1989. The last Ebco shop drawings were returned "checked" by  
CWMM on February 8. Ten to twelve weeks from this date was  
between April 19 and May 3.  
116.  
The Bucket Elevator Components were manufactured by  
Transcontinental Engineered Products Ltd. and the Bucket Elevator  
Drives by Hansen Transmissions Ltd. The bucket elevators are  
used to elevate grain from the lower levels of the Terminal to  
the upper levels of the Terminal. L-1, L-2, L-3, L 4/5, L 8/9  
and L 11/12 are located in the Workhouse and L-28 is in the  
Trackshed. The Transcontinental Letter of Intent dated November  
15, 1988 provided for a purchase price of $594,322.82 of which  
$91,783.78 had been paid by UGG to Transcontinental by February  
10. The Hansen Letter of Intent dated October 4, 1988 provided  
for a purchase price of $293,620.00.  
- 56 -  
117.  
On October 12, 1988 Transcontinental provided its quote to  
CWMM and said: "based on the Letter of Intent within the next 7  
to 10 days, delivery of components should be completed by mid to  
late February". The Letter of Intent dated November 15, 1988  
provided "delivery required: March 15, 1989 or earlier". It  
also required that drawings be submitted to CWMM "before  
fabrication". Drawings were submitted between November 23, 1988  
and May 15, 1989. The last drawing returned to Transcontinental  
was checked by CWMM on May 19. The Bucket Elevator Components  
were delivered to site mid May to beginning of June, with  
miscellaneous equipment in July, and replacement buckets for the  
defective buckets not delivered until the end of July. The  
original buckets ordered for the elevators were defective and had  
to be replaced.  
118.  
The Letter of Intent to Hansen dated October 4, 1988 said  
"this equipment is to be delivered to UGG Vancouver latest week  
of February 20, 1989." Hansen wrote to CWMM on October 31, 1988  
taking exception to the Letter of Intent. An addendum to the  
Letter of Intent was issued on November 25, 1988, but was not  
included in the tender package. The addendum provided "both the  
purchase specification and the Letter of Intent are applicable to  
the additional equipment supply, including the date of delivery".  
Hansen wrote back to CWMM again on November 30, 1988 taking  
exception to the Letter of Intent. The Hansen drives were  
delivered May 17. The Letter of Intent required submission of  
- 57 -  
certified drawings within "ten (10) working days after the date"  
of the Letter of Intent. Drawings were submitted by Hansen on  
January 18. The final Hansen check on drawings was returned by  
CWMM March 15.  
119.  
Although the tender documents called for screw conveyors in  
certain areas of the Terminal, eventually Bisco manufactured drag  
conveyors were ordered and installed. Conveyors STB-3,STB-3A,  
TBS-1, TBS-2, TBS-3, SBS-1, SBS-1A, SBS-1,2R, SBS-2, SBS-3, and  
SBS-3A are located in the Workhouse in the Basement. Conveyors  
RFC-1, RFC-2, RFC-3 and RFC-4 are located in the Wheat Reclaim  
area of the Workhouse on the Bin Floor. Conveyors RFC-5 and RFC-  
6 are located in the Wheat Reclaim and Scale Three area of the  
Workhouse on the Bin Floor. The Letter of Intent dated January 9  
provided for a purchase price of $179,988.00.  
120.  
On December 7, 1988 Bisco quoted for screw conveyors with a  
proposed shipping date "10 - 12 weeks upon receipt of a Letter of  
Intent". On January 5 Bisco supplied its quote for 6 drag  
conveyors, proposed shipping "10 - 12 weeks upon receipt of a  
Letter of Intent". On January 9 Bisco quoted for 17 drag  
conveyors with no change in the delivery date. Ten to twelve  
weeks from this date was between March 20 and April 3, 1989. The  
Letter of Intent provided "projected shipping date mid March of  
1989". In subsequent correspondence of January 12 and 13 Bisco  
took exception to the Letter of Intent and did not sign it. The  
- 58 -  
Letter of Intent provided that drawings were to be submitted to  
CWMM "within ten (10) working days". However, the drawings were  
submitted by Bisco between February 6 and March 8, 1989.  
The  
final shop drawings were checked by CWMM and returned to Bisco  
March 29. Their drag conveyors were delivered at the end of  
April.  
121.  
Other drag conveyors were manufactured by Buhler-Miag and  
supplied through its Canadian company Buhler Canada Ltd.  
Conveyors DC-101 and DC-103 were located with the head end of  
each conveyor in the Workhouse on the Bin Floor and the tail end  
of each conveyor on the roof of the North Annex. Conveyors DC-  
102 and DC-104 are located in the North Annex on the Bin Floor.  
Conveyors DC-105, DC-106, DC-107, and DC-110 are located on the  
Bin Floor in the South Annex. Conveyor DC-109 has its head end  
on the Bin Floor in the Workhouse and tail end on the Bin Floor  
in the South Annex. Conveyor DC-201 is located in the Workhouse  
on the Distribution Floor. Conveyors BD-2 and BD-2A are located  
in the Workhouse in the Basement. The relative significance of  
the Buhler equipment on this project can be seen from the amount  
of the purchase price in the January 9 letter of intent of  
$1,946,764.20, of which UGG had paid $183,657.00 by February 10.  
122.  
In November 1988, Notter of Buhler had attended in Vancouver  
to solicit the drag conveyor contract with UGG. At that time he  
told Campbell there would be difficulties with March/April  
- 59 -  
delivery. On December 9, 1988 Buhler submitted its quote for the  
drag conveyors. The quote contained the following with respect  
to delivery:  
"Delivery of equipment would be approximately 4 - 5  
months after receipt of written order and settlement of  
all technical details, ie. 3 months after receipt of  
approved layout drawings. Based on receiving the  
Letter of Intent on or before December 16, 1988 layout  
drawings submitted and approved week of January 16,  
1989, fabrication to commence immediately with shipping  
to start the 2nd half of March, 1989 with final  
shipment 2nd half of May, 1989. This preliminary  
schedule to be discussed. Bar chart will be submitted  
2 - 3 days after receipt of Letter of Intent".  
123.  
124.  
The quote also provided that 10% of the total contract price  
would be due with the Letter of Intent or order, whichever came  
first.  
On January 9 CWMM sent its Letter of Intent to Buhler which  
provided "projected shipping date mid March of 1989". This did  
not conform to Buhler's quote and Buhler rejected it. On January  
14 Notter sent a fax to Campbell requesting 10% of the contract  
which was due according to the Buhler quote and enclosing a  
preliminary project schedule as promised in the Buhler quote  
which showed Buhler delivery going into July, 1989. If the  
parties intended the successful contractor to assume  
responsibility for the timely delivery of this equipment,  
communications of this nature ought to have been disclosed to the  
bidders before the contract award February 10.  
- 60 -  
125.  
Although Campbell intended to try to improve the proposed  
Buhler delivery schedule after receiving the January 14 fax, the  
discrepancy between the mid-March date represented to bidders and  
the January 14 schedule was highly material. Campbell estimated  
that the work associated with the Buhler bin floor conveyors  
comprised approximately 30% of the project. Given the amount of  
work that the Buhler equipment represented on the project, had  
UGG intended to transfer the responsibility for the timeliness of  
the Buhler equipment delivery to FCC on February 10, I would have  
expected an immediate communication to FCC as the successful  
bidder on February 10 or very shortly thereafter respecting the  
true state of affairs. This never occurred. FCC only started to  
learn of this after February 10 when Whitaker contacted the  
equipment suppliers and put together his first Pre Purchase  
Vendor schedule. The January 14 fax from Buhler was never  
disclosed to FCC. Skodje of FCC testified that if the January 14  
fax been disclosed, FCC would have suggested a change to the  
completion commitment of the Project.  
126.  
The January 9 Letter of Intent required drawings to be  
submitted to CWMM within "ten (10) working days after receipt of  
the" Letter of Intent. Buhler submitted drawings between  
February 7 and April 12. Somogyi testified that representatives  
of Buhler were supposed to come out during the month of January,  
1989 to discuss drawings with CWMM. This did not occur. FCC was  
unaware of this before the contract was awarded February 10.  
- 61 -  
Representatives of Buhler did come out to visit CWMM during the  
first part of February, 1989 to discuss layout drawings. The  
layout drawings were finalized, checked and returned by CWMM by  
May 19. Buhler drag conveyors were delivered between mid May and  
July 20, with inspection gears delivered in August.  
127.  
128.  
Klockner-Moeller supplied the motor control centres. The  
motor control centres control the various equipment motors and  
pneumatic gates in the Terminal. The Letter of Intent dated  
December 13, 1988 provided for a purchase price of $70,850.40.  
The Klockner Moeller Letter of Intent provided for a  
projected shipping date "March of 198[9]". Hammond did issue the  
marked up shop drawings for approval February 22 by which time  
not all shop drawings had been completed. The equipment arrived  
on site between the end of April and June 19.  
129.  
Although there are no specifications in the Prime Contract,  
a Letter of Intent dated January 9 was issued to Nord-Sen  
Industries to manufacture new gates for existing conveyors in the  
Terminal. These gates open and close pneumatically to allow  
grain to fall into spouting or bins. The Nord-Sen Gates were for  
modified existing drag conveyors B-1, B-2 and DC-2. All of these  
conveyors are located on the Bin Floor in the South Annex. The  
Letter of Intent provided for a purchase price of $192,920.00.  
- 62 -  
130.  
The Nord-Sen Letter of Intent provided for "projected  
shipping date mid March of 1989". The letter was signed by Nord-  
Sen on January 24. The letter required certified drawings  
"within ten (10) working days". Nord-Sen submitted drawings  
between January 7 and April 4. Subsequently, Nord-Sen was asked  
to manufacture the same type of gate as Buhler. The Nord-Sen  
drawings were not finalized until the Buhler gate drawings had  
been finalized. CWMM transmitted the drawings for DC 2 on May 1  
and the end gates for conveyors B1 and B2 on May 8. Nord-Sen  
could not start manufacturing until these drawings had been  
received. The Nord-Sen gates were not completely shipped to the  
site until the mid to the end of July. The last of the Nord-Sen  
gates arrived at site on August 2. Repairs were carried out on  
the gates between August and October.  
CONCLUSION  
131.  
I conclude that whether the terms of the Prime Contract are  
taken on their own or in conjunction with the parties' conduct,  
the result is the same. FCC had no obligation and assumed no  
obligation under the Prime Contract to expedite the design or the  
manufacture of the preselected equipment. FCC purchased the  
equipment only as agent for UGG and at no time did FCC assume or  
have any obligation in respect of the equipment other than to  
arrange for delivery and take delivery once the equipment had  
been manufactured. FCC was obliged to take delivery and install  
- 63 -  
the equipment, but defects in the equipment were at UGG's risk  
until after substantial performance when FCC's one year warranty  
became effective. Accordingly I find that UGG and CWMM remained  
responsible for the timely completion of the design and  
manufacture of the preselected equipment, as well as its  
availability for timely delivery to the site.  
PROJECT DELAY  
(a) INTRODUCTION  
132.  
133.  
I now consider the factors said by the parties to have  
delayed the progress of the work. For each, I consider whether  
the evidence can support a finding that the factor alleged was in  
fact an effective cause of delay.  
It is to be noted that FCC says it is not advancing a  
"delay" claim. It says it is not suing to have the contract time  
extended. Rather FCC's claim is for damages for the contract  
breaches and/or the negligent misrepresentations of UGG and CWMM.  
The damages for which FCC claims entitlement are its costs  
incurred in being forced to stay on the project until substantial  
performance was declared by CWMM on December 29. FCC does not  
advance any impact or productivity loss claim for the  
dislocations to its original plan of work that the acts or  
omissions of UGG and CWMM are said to have caused. CMI similarly  
does not advance a delay claim, but rather a claim against FCC  
- 64 -  
for breaches of the subcontract, for most of which FCC in turn  
claims indemnity from UGG and CWMM.  
134.  
The defendants say that FCC and CMI have failed to prove how  
many days of delay were sustained by reason of the alleged  
breaches of contract or negligence, whether those breaches are  
examined individually or taken collectively. This requirement  
would of course apply if FCC were seeking a contract extension.  
135.  
However in this case FCC and CMI advance claims for damages.  
Accordingly they must demonstrate on a balance of probabilities  
that the matters complained of delayed or disrupted them in their  
work and caused losses, in FCC's case measured by its extra time  
spent on site. If FCC succeeds in its proof, then, subject to  
the contractual defenses advanced by UGG and CWMM, it is entitled  
to recover the damages that flow from the contractual breaches or  
negligence. CMI is similarly entitled with respect to its  
claims.  
136.  
In its very detailed analysis in final argument CWMM traced  
the history of the project in support of its contention that FCC  
and CMI have failed in their proof. CWMM set out the timing of  
the delivery to site of the preselected equipment and its  
subsequent installation. Where there is a time gap between these  
events, it submits that is proof that the late delivery of the  
equipment could not have delayed the contractors' work on site  
- 65 -  
and it says that FCC and CMI have failed to prove that the  
alleged acts or omissions delayed them in their work. If this is  
so, there can be no recovery on this portion of their claims  
since ultimately, to succeed, FCC and CMI must establish that the  
defendants' acts or omissions complained of were the proximate  
cause of the losses they say they sustained, in FCC's case in the  
form of being onsite for an extra 4 months, and in CMI's case in  
acceleration costs, productivity losses and its additional  
overhead costs.  
137.  
However, in my view, CWMM's analysis is overly simplistic  
insofar as it presupposes that a contractor would be waiting at  
the site with forces at the ready to immediately install  
equipment as delivered. This ignores reality. There may be many  
good reasons why equipment is not installed upon arrival. In his  
evidence Steel testified that a contractor tries to "smooth out"  
the work so as to avoid as much as possible variations in work  
load from week to week. As an example he says a contractor will  
not crew up one week to rush through work and then be left the  
following week with much less to do and hence with its forces  
either under utilized or laid off. In my view that is the  
weakness in the submission that a time gap between equipment  
delivery and installation means that the equipment deliveries did  
not cause a delay.  
- 66 -  
138.  
In argument counsel for CWMM said that FCC has not provided  
any explanation as to why work was not done when it was planned  
or why the changes to its plan through the course of the project  
delayed it past August 31. CWMM put this question: Has FCC  
proved that it suffered loss or damage flowing from the alleged  
breaches of contract? While conceding that where loss or damage  
flows from a breach the court is required to quantify the loss as  
best it can, CWMM says FCC has not proved any loss. It further  
says that FCC asks the court to assume it suffered a loss by  
reason of its late completion instead of satisfying the burden  
upon it of proving the required causal link between the alleged  
acts or omissions and the late completion.  
139.  
However one of the critical points in this project was the  
date by which all work on the project was on the critical path.  
That is to say when all of FCC's float time was used up and when  
the delay of any part of the work would necessarily and in spite  
of FCC's efforts in mitigation, delay substantial performance  
past August 31.  
140.  
Campbell expressed his view of the status of the project in  
a June 28 fax to Maxi-Lift with respect to some defective  
buckets in which he said:  
"On June 19 we advised the general contractor to stop  
work on the bucket installation. This project is  
running 2 x 9 hour shifts per day and we are on a crash  
schedule to be fully commissioned by September 1/89."  
- 67 -  
141.  
On discovery, Campbell confirmed that by crash schedule he  
meant that all work on the project was on the critical path. So  
it was Campbell's view by June 28 that any delay to any part of  
the work from that time forward would necessarily delay the  
August 31 substantial performance date.  
142.  
However, it is also clear that simply proving that events  
occurred later than scheduled does not constitute proof that the  
events caused delay. Post hoc does not necessarily mean propter  
hoc. I accordingly propose to consider all of the "delaying"  
factors alleged by the parties to see if FCC and CMI have  
discharged the burden of proof upon them of proving the necessary  
causal link which the law requires before holding that a party is  
entitled to recover damages in negligence or breach of contract.  
(b) FCC ALLEGED DELAY FACTORS  
(i) PRE-SELECTED EQUIPMENT  
143.  
FCC did not learn that much of the pre-selected equipment  
was going to be delivered later than the mid-March date in the  
letters of intent until after it was awarded the contract on  
February 10. After that date Whitaker contacted the equipment  
suppliers and obtained their estimated delivery dates. On  
February 20 he prepared the first of a number of schedules  
showing anticipated delivery dates for the equipment. This was  
tabled at the first site meeting on February 21. The defendants  
- 68 -  
say that FCC cannot complain about the equipment as a causal  
delay factor because it learned what might be termed the true  
state of affairs by the end of February and certainly before it  
signed the prime contract on March 29.  
144.  
It is clear that FCC and CMI changed or adapted their plans  
of work to accommodate the changes in equipment delivery. It is  
therefore necessary to consider the evidence as to whether FCC or  
CMI were actually delayed in the progress of their work by the  
equipment deliveries.  
145.  
The evidence of FCC and CMI is consistent. In the records  
made at the time and in their trial testimony, the plaintiffs'  
witnesses identified equipment delays as causing delays to their  
work. Steel's daily site reports show a consistent recording of  
the impact the late equipment was having on the progress of the  
job. Whitaker's construction schedule tabled at the September 7  
site meeting shows his calculation of the impact of the late  
equipment deliveries. However in my view any doubt as to the  
impact of the late delivery of equipment can be resolved by the  
evidence of CWMM and UGG.  
146.  
On May 16 at a secondary meeting following the regular site  
meeting attended by representatives of FCC, UGG and CWMM, Buhler  
was discussed in detail. At that meeting the President of UGG,  
Moore, expressed his view that Buhler had "lowballed" its tender  
- 69 -  
in order to get the job and was now holding the job up for  
ransom. Moore also pointed out that the "issue" was Buhler.  
Derhouson advised those at the meeting that the float in the  
contract at the back end had now been used up. Moore advised the  
meeting that UGG took the contract with Buhler on honourable  
intentions and would fight it out with Buhler in the courts and  
the newspapers. According to Moore, Buhler's request for an  
additional $75,000 to accelerate was not the issue, it was the  
principle. If UGG paid one supplier then all suppliers would try  
it.  
147.  
On the same day Campbell sent a 14 page fax of the  
background on Buhler to Van Dyke. One document entitled "Buhler  
Saga" confirms that Buhler's quote was based on a Letter of  
Intent dated December 16, 1988 and layout drawings January 16,  
1989 which would lead to shipping in the second half of March and  
final shipping second half of May, 1989. It also confirms that  
UGG received the January 14 fax showing the later deliveries.  
148.  
On May 19 Pope recorded in his notes a discussion between  
Moore, Eigenmann and Notter. Pope's notes refer to a discussion  
of the Buhler schedule and state that the schedule "indicated  
that 'drags' seemed to be the only area to jeopardize our  
completion schedule of September 1, 1989". The notes also  
confirm that Buhler advised Moore that the best Buhler could do  
would be the end of July, and that Moore advised Eigenmann and  
- 70 -  
Notter that every day UGG was out of business it was $140,00.00  
to $150,000.00 loss of revenue, which was "very severe". Moore  
also advised Buhler that the end of July was "no good".  
149.  
On or after July 27 in an undated note regarding Buhler, Van  
Dyke wrote:  
"Talk to Murdoch about deducting job delay costs from  
FCC re BM[Buhler] deduct from $75,000.00 O.T. payment.  
There will be charges from FCC.  
BM did not complete their contract before shipping:  
(1)(a)(1) 36 limit switches and brackets left  
off  
(2) They relaxed tolerances to improve  
time, i.e. deliberate substandard  
fabrication on 48-1/8" opening.  
(3) No match marking of gates to  
openings."  
150.  
On July 28 Van Dyke also made a list of items that he wanted  
to discuss. In this list he stated:  
"Anticipate "extension of contract" wanted by FCC due  
to "hold" on pulling chain and interference due to BM  
problems due to the gate problem tolerances. Also  
expect "delay of job" charges from FCC. They are going  
to try everything to extend their completion date. Don  
Steel always alludes to "going to really affect  
schedule". Expect fax from Ray by Tues. Suggest BM be  
made responsible for these charges."  
Van Dyke's notes suggest that Buhler:  
"relaxed the tolerances on openings...deliberate  
substandard fabrication to ensure delivery...no match  
marking of gates to openings as required by contract"  
- 71 -  
The notes also indicate Van Dyke's comment:  
"respond to commissioning schedule. Blatant about  
being behind."  
151.  
While Van Dyke did not realize when he made this note that  
the failure of Buhler to matchmark the gates to the openings as  
required was by agreement between Buhler and CWMM reached in  
April without FCC's knowledge, it nonetheless demonstrates his  
view at the time of the effect on the project scheduling of the  
timing of the Buhler deliveries and the state of the Buhler  
equipment when it was delivered.  
152.  
Most significantly, on August 24, in a report to his client,  
Campbell identified the late delivery of equipment as one of the  
facts relevant to FCC's inability to attain substantial  
performance by August 31. In that letter to Pope, he confirmed  
his verbal advice that the contract with FCC would not complete  
by August 31. He set out the most optimistic estimate for  
completion of spouting and gates to be mid to end of October.  
Campbell projected electrical control, instrumentation work into  
November not including "an apparent impasse with respect to  
completing work on the dock progressors". He then listed as some  
relevant facts: late delivery of owner preselected equipment, and  
that the manhour projections by FCC based on the contract were  
not being met.  
- 72 -  
153.  
154.  
155.  
At trial in cross examination Campbell was asked if he had  
reviewed documents during the course of the project to ascertain  
if FCC had been delayed in part due to late equipment deliveries.  
His response was that FCC was not so delayed. After a followup  
question, he asked which documents were being referred to by  
counsel. He was then referred to his discovery evidence where he  
said that he had reviewed documents to ascertain whether the late  
equipment deliveries had delayed FCC. On discovery he then said  
he couldn't remember if he had reached any conclusions after  
conducting that document review.  
I found Campbell's trial testimony on this point  
unsatisfactory. In his evidence he appeared to me to be trying  
to justify a conclusion reached somewhat later in the fall after  
the relations between the parties had soured considerably and  
when he was doubtless attempting to bolster the position of CWMM  
and UGG. No explanation was offered as to why the conclusion he  
stated in his August 24 letter was not accurate. I find that  
when he wrote the August 24 letter to his client, Campbell  
believed that the equipment delays were a relevant factor in the  
failure of FCC to achieve substantial performance by August 31.  
On his discovery, Van Dyke testified that he knew in August  
1989 that the late delivery of the equipment as well as the  
changes to the drag conveyors had the effect of delaying CMI in  
its work.  
- 73 -  
156.  
After the regular site meeting on September 7, MacKay, Pope,  
Graham, Van Dyke, Campbell, Skodje, Derhouson, Marquis and  
Whitaker met to deal with the equipment delivery impact. At this  
meeting an impact schedule prepared by Whitaker and showing  
completion in late December, 1989, early January, 1990 was put  
forward and discussed. In this schedule Whitaker demonstrated  
the impact of the delay in the delivery of the preselected  
equipment on FCC's progress on the project. Van Dyke testified  
that he understood that FCC's position was that the late delivery  
of the preselected equipment was the fault or the blame or the  
responsibility of either CWMM or UGG.  
157.  
On October 5 a meeting took place at UGG's office attended  
by MacKay, Pope, Van Dyke, Campbell, Nicholls, Skodje, Marquis  
and Whitaker. At that meeting documents were presented to UGG  
and discussed including Whitaker's final Pre-Purchase Vendors  
List, the tender schedule, and a separate sheet for each of the  
equipment suppliers showing tender delivery versus actual  
delivery. A schedule comparison between the tender schedule and  
the equipment delivery impact, was also provided, based on 45  
hours per week per shift and based on 37½ hours per week per  
shift (i.e.-- if no more premium time was worked). The schedule  
showed actual installation of mechanical equipment extending to  
September 11, electrical installation projected to extend to the  
end of December, spouting installation projected to extend to the  
- 74 -  
end of October, dust control projected to extend to the end of  
November, pneumatics installation and hydraulics projected to  
extend to the end of November, with testing, start-up and  
commissioning extending to the end of December. No one from UGG  
or CWMM disputed any of the information presented by FCC in any  
of these documents at the meeting, or in writing afterwards.  
158.  
Van Dyke's notes record Skodje advising those attending that  
FCC "would like to demonstrate to you how and why time was lost  
and circumstances that brought it about". Whitaker then gave out  
a package of "back up documents". What followed was a discussion  
concerning the impact of the delivery of the equipment. In that  
discussion Skodje pointed out that everything appeared to come  
later than portrayed in the Letters of Intent. Van Dyke records  
him saying "If knew this why was this not portrayed in tender  
call. All expected people to deliver on time.  
No vehicle in L  
of Is to permit FCC to...commitment UGG made on 'unknown  
contractor' - let him believe that dates would be adhered to".  
Skodje was clearly referring to FCC's reliance on the delivery  
dates in the Letters of Intent in bidding the project.  
159.  
In my view the foregoing demonstrates that by August, 1989,  
Campbell and Van Dyke had concluded that the delays in delivery  
of the preselected equipment delayed FCC and CMI in the progress  
of their work and that substantial performance would, as a  
consequence, occur later than August 31. Their assessments are  
- 75 -  
consistent with the evidence of FCC and CMI and I conclude that  
FCC has established the requisite causal link between the late  
delivery of the preselected equipment and the delays it  
encountered in carrying out its work which resulted in work on  
the project continuing past August 31.  
(ii) ADMINISTRATION BUILDING  
160.  
The new administration building was constructed by PCL  
independent of the FCC contract. However, FCC was obliged under  
its contract to install tie-ins to the new building so grain  
could flow to the sampling rooms of the Canadian Grain Commission  
and UGG in the building as well as installing the new controls in  
the control room. FCC contends that it was unable to complete  
this work on time because the administration building was  
finished late.  
161.  
On April 14 PCL forwarded its schedule for the construction  
of the Administration Building to Campbell who noted on the  
schedule that PCL would be "out of control room & control room  
100% complete before August 7". FCC required access to the  
control room after PCL was finished to do its work under the  
Prime Contract. On April 15, at a meeting attended by Van Dyke  
and Campbell, it was confirmed with PCL that the control room  
must be complete by July 24. Additionally, the minutes of the  
meeting note that the control room console details were to be  
finalized as soon as possible.  
- 76 -  
162.  
On May 3, at the Administration Coordination Meeting no. 1,  
the meeting notes indicate that pipe bridge drawings and  
specifications were required in order to tender the pipe bridge  
work, that the basic penthouse was scheduled to be complete to  
the point where FCC could commence installing piping by July 10  
and that approval of the control room layout was required from  
UGG in order to complete the work by July 24.  
163.  
The minutes of the June 15 site meeting record FCC  
requesting whether CWMM or UGG have any preferred start up  
procedures. The minutes also record that CWMM requested that any  
new or added work be assessed "with regards to schedule  
deadlines, prior to work being done".  
164.  
Also at that meeting a new schedule prepared by Whitaker  
showing construction completion by September 4 and commissioning  
by September 11 was turned over to all present. That FCC  
schedule was contingent on a number of matters being completed by  
certain dates as set out in the minutes as follows:  
"16.003.17  
The schedule was turned over to all  
present, with the following  
clarifications; subjects:  
A)  
That all B.M. chains  
are shipped by June  
19/89.  
B)  
That all remaining  
B.M. equipment is  
- 77 -  
shipped by July  
7/89.  
C)  
D)  
E)  
F)  
That Nordsen meet  
their 3 shipping  
dates. First load  
June 25/89, second  
July 5/89, last  
July 15/89.  
That we are allowed  
to begin our tie-ins  
to the office  
control room and  
sampling room on or  
before July 17/89.  
That we are able to  
begin work on the  
dock progressors and  
north end loop on or  
before July 17,  
1989.  
That all "Holds" on  
drawings are removed  
prior to June 30/89.  
FCC and their subtrades are  
requested to review and advise  
of any holds that they feel  
are existing."  
(emphasis added)  
165.  
166.  
The urgent nature of the foregoing items is consistent with  
Campbell's view in his June 28 fax to Maxi-Lift referred to above  
in which he stated that by then the project was on a "crash  
schedule".  
The site minutes of June 22 record UGG's response that to  
the best of its knowledge the office building would be ready for  
tie-ins by July 17.  
- 78 -  
167.  
On June 28 the Administration Building Coordination Meeting  
#3 minutes noted that the revised pipe bridge drawings were not  
issued as yet, and that furniture would be required on site  
August 21 with staff "to commence start-up in building in mid  
August." The minutes noted a letter from PCL dated June 27 which  
was attached to the minutes and provided for penthouse erection  
occurring the week of July 10, pipe bridge erection the week of  
July 10 and completion of the control room July 28. The letter  
also referred to UGG staff commencing a start-up in the building  
including training sessions stating that the building would be  
available September 1, but no air conditioning until September  
29.  
168.  
The minutes of the July 19 Administration Building  
Coordination Meeting #4 noted a prediction that FCC could  
commence work in the building on July 31, that the interim  
turnover date for the building was still the first week of  
September, and that air balancing for the building would not be  
completed until the end of September.  
169.  
On August 16 the minutes of the Administration Building  
Coordination Meeting #5 record potential delivery of the air  
conditioning units in October or November, the anticipated  
turnover date for the building was September 15, the building  
must be ready to commence the start-up of grain movement by not  
later than September 15 and UGG's request that the annunciator  
- 79 -  
panel for the entire complex be located in the administration  
building, which would require a fire alarm panel change.  
170.  
Also on September 5 Ryan of PCL wrote to Campden with  
respect to the administration building advising of delivery of  
air conditioning units in October and requesting information with  
respect to the annunciator panel for the fire alarm to be  
installed in the administration building.  
171.  
Additionally, on September 7 at the Administration  
Coordination Meeting #6, the minutes note that the date of  
substantial performance of the Administration Building was  
scheduled for October 2 and that it was anticipated that 57  
people would be occupying the building after this date. The  
annunciator panel is referred to as not having been finalized,  
the air conditioning units were due to be installed by October  
17, and sprinkler tests and verification was required for the  
occupancy permit. The minutes also note that "no further  
meetings are scheduled unless required to resolve the issue of  
the Occupancy Permit,....".  
172.  
On September 12 representatives of UGG met with  
representatives of CWMM to discuss the electrical and engineering  
status.  
Van Dyke's notes record that Campbell had a "concern re  
control philosophy. No control devices yet installed. Need  
realistic indication of where [at]". He also noted that a report  
was needed with respect to "dock time completion". Van Dyke's  
- 80 -  
notes make it clear that there were many outstanding electrical  
and engineering items, including those relating to the Canadian  
Grain Commission, the PLC and computer programming, and the  
preparation of an operations manual and control philosophy which  
were slated to be ready by September 21. Also, in response to  
the question "when R & S complete" it was noted "maybe end of  
October to run grain - still need more time to get into  
production".  
Hammond testified that at no time did he think  
Ricketts-Sewell was not diligently prosecuting its portion of the  
work under the contract.  
173.  
At a September 19 meeting Van Dyke noted:  
"owner late delivery  
-
Samples and changes to sampler system was  
completely designed  
-
Drag conveyor section designs were  
late..."  
174.  
On October 13 Campbell sent a memo to Van Dyke confirming a  
telephone conversation they had that morning in which Campbell  
records "chase Campden and PCL to complete return sample hopper  
installation so that FCC and PCL get out of the office  
administration before the end of the week".  
175.  
On November 2 Campden issued the certificate of substantial  
performance for the administration building. On the same day PCL  
returned its signed contract to UGG. The PCL contract provided  
- 81 -  
for substantial completion of the Administration Building by  
October 20, 1989. FCC was never advised of this date. The  
Administration Building was needed for the operation of the  
Terminal and was required to comply with safety standards and  
Labour Canada Codes.  
176.  
177.  
On January 4, 1990 the City of Vancouver granted an  
occupancy permit for the Administration Building. The permit  
certified that the Administration Building "may now be occupied  
in accordance with the approved occupancy herein described".  
From the foregoing it will be seen that the original date  
for substantial completion of PCL's work on the administration  
building was August 7. It is clear that PCL's schedule slipped  
steadily through the summer of 1989 with the result that  
substantial completion was not granted until November 2. This  
delay of necessity delayed FCC in carrying out the work it was  
required to do under its contract with UGG. Until PCL finished  
the control room, FCC could not complete its work in that area.  
PCL's original schedule was to be out of the control room with  
the room 100% complete by August 7. On June 15 FCC stated at the  
site meeting that the schedule it was tabling that day showing a  
completion date of September 4 was conditional on FCC being  
allowed into the control and sampling rooms to begin their tie-  
ins by no later than July 17. This did not occur. As early as  
- 82 -  
June 27 PCL was predicting a completion date of July 28 for the  
control room.  
178.  
It is clear that FCC had to follow PCL in the administration  
building. There is also no evidence that construction of the  
administration building was slowed by CWMM because FCC was  
running late on other contract work. Had PCL's work been  
deliberately delayed by CWMM because FCC was going to finish  
later than August 31 because of other concurrent delay events the  
fault of FCC, that would sever any causal link between the late  
completion of the administration building and FCC's losses.  
However that did not occur. The evidence is that PCL finished at  
the end of October instead of August 7, and hence I conclude that  
the late completion of the administration building prevented FCC  
from completing its contract work in that building until well  
into November.  
(iii) STATE OF PROJECT DESIGN - VOLUME AND TIMING OF DRAWING  
DELIVERIES  
179.  
FCC and CMI say that CWMM had not completed the design of  
the project to the extent to which the law says a tendering  
contractor on a lump sum bid is entitled to rely. Earlier I  
dealt with the impact of the late delivery of the preselected  
equipment which the plaintiffs say was caused at least in part by  
CWMM design delays. In this section I deal with FCC's contention  
that the overall design of the project was late and that the  
- 83 -  
number and timing of the drawings eventually released by CWMM  
delayed FCC and CMI in their prosecution of the work.  
180.  
In Ex 92 FCC summarizes these drawings and sketches and  
their release dates. While this chronology affords some support  
for FCC's case, those facts by themselves do not establish that  
the timing of the drawing releases delayed the work. It is  
necessary to review the evidence in order to make an assessment  
as to whether the release of drawings through the course of the  
project were an effective cause of delay. In considering this  
evidence it must be borne in mind that this was a complex refit  
project, that all parties understood this at the outset and that  
a certain number of drawing revisions were to be expected as work  
proceeded. However that being said, the owner still had an  
obligation to ensure that the state of design was sufficiently  
finalized prior to tender on this lump sum project so that the  
progress of the contractors work would not be unreasonably  
impacted.  
181.  
The difficulties experienced with drawing deliveries and the  
reasons therefore were related at trial by Steel who testified  
that when he expressed his view to Campbell that "the plant just  
wasn't there yet, the design wasn't there", Campbell told him  
that "they had wished that they had had more time with the design  
also, that they felt it went to tender a little earlier than what  
it should have."  
- 84 -  
182.  
In my view Steel's evidence as to what Campbell told him  
illustrates what was at the root of one of the significant  
problems on this job. The design was not sufficiently advanced  
when the project went to tender to allow it to be built in the  
time allotted. This caused the equipment to be ready later than  
planned and it also caused the engineer to be faced with the task  
of having to continue designing as the project was being carried  
out.  
183.  
184.  
At the first site meeting on February 21 FCC sought  
clarification concerning the release of "holds" on the bin floor  
drawings. CWMM promised release of the holds would be  
forthcoming.  
On March 2, Whitaker wrote to Campbell concerning holds on  
drawings, an item appearing frequently in subsequent site minutes  
and other documents. At the site meeting of March 2 the minutes  
record that FCC required release of bin floor drawings which were  
on hold:  
"Upon review of the revised schedule  
overview, it was noted that certain delivery  
dates required to meet previous planning  
schedule may not be met.  
Therefore, discussions regarding approach to  
improvements brought forward certain  
suggestions as follows:  
A)  
Drawings on hold must be released  
on basis of current information  
(see 1.008).  
- 85 -  
185.  
These drawings included the bin floor drawings. Popowich  
testified that CWMM's failure to provide those construction  
drawings "meant that we couldn't proceed with the detailed shop  
drawings and consequently a fabrication of -- -- our work related  
to the particular construction drawing".  
186.  
187.  
At the site meeting of March 7 the minutes record FCC's view  
that the hold on the bin floor drawings was becoming critical and  
the drawings should be released. FCC again asked that drawings  
be released in their current state by CWMM.  
On March 8 CMI wrote to FCC to notify them that their  
Edmonton affiliate had halted manufacturing spouts for the bin  
floor conveyors:  
"As previously discussed, the present hold on the  
Construction Drawings and in particular the Bin Floor  
Conveyors #5542 is forcing us to halt manufacturing  
from our Spruce Grove facility.  
If this matter continues long term delivery problems could  
result."  
188.  
At the site meeting of March 14 the minutes record CWMM's  
advice that they were still working on the structural drawings  
FCC had said was required the week before. The issue of gates  
was again raised; CWMM was asked to complete the gate schedules  
on the drawings. With respect to changes on the construction  
drawings, the minutes note:  
- 86 -  
"FCC enquired as to procedure for dealing with the  
changes on the construction drawings (From Tender set).  
CWMM advised that we are to proceed with the work in  
accordance with the "latest" issue for construction  
drawings and that they will issue a change order to  
cover.  
FCC requested all trades to price the changes as soon  
as possible to finalize differences."  
189.  
The site minutes of March 21 note that the question of  
missing information not shown on drawings and the issue of  
proceeding with changes before receipt of a change order were  
raised again. Also appended to the minutes was a list of eight  
construction drawings that were either not issued as of March 16  
or which had been held.  
190.  
On March 23 Marquis wrote to Campbell passing along CMI's  
letter of the same date advising that they had been delayed  
approximately two weeks due to drawing delays. Popowich  
testified that CMI "needed the drawing to confirm the location of  
the modified conveyor in the north annex."  
191.  
At the April 4 site meeting CWMM advised that it was  
redesigning the brackets for the Bisco drag conveyors. At the  
same meeting, FCC reported five to six drawings still on hold  
with some drawings not issued for construction. Steel testified  
that the drawings listed were important to completing the work.  
- 87 -  
192.  
On April 7 Campbell advised Marquis that CWMM was revising  
the tail end of DC 105 and to hold all spouting relating to DC  
105. He also advised FCC to hold details 1/102 and 2/102 on  
drawing 5542-S102. This drawing detailed the intermediate bin  
floor drag conveyor supports. The April 11 site minutes also  
note five drawings still not issued or on hold and record a  
request by CWMM for FCC to look into alternative methods of  
hanging the bin floor conveyors. This request related to the  
hold that was put on the bin floor conveyor drawing on April 7 by  
Campbell.  
193.  
At the site meeting of April 18 the minutes note that  
information had been received with respect to the brackets  
required to hang the Bisco drag conveyors. The minutes also note  
that there were still four drawings on hold. FCC requested a  
"CCN [contemplated change notice] for the change in conveyor  
length because of the impact it would have on other trades for  
new gates, pneumatics, controls, etc". At the April 18 site  
meeting FCC produced sketches for consideration for the conveyor  
hangers that had been put on hold by Campbell on April 7. A  
change was also requested to be confirmed by CWMM for the  
addendum to the Hansen Letter of Intent that was missing from the  
tender package.  
- 88 -  
194.  
195.  
Steel's April 20 Daily Report notes that FCC had repeated a  
request for design answers, and further noted that it appeared  
that CWMM could not keep up.  
At the April 25 site meeting the sketches and method of  
structural connections with respect to the bin floor conveyor  
hangers that had been proposed by FCC at the previous meeting  
were agreed, and CWMM "advised concurrence by Buhler". FCC  
requested further information with respect to the additional  
length of Buhler conveyor and noted that the information is  
required "ASAP". The minutes also record in item 10.014 that FCC  
requested approval of AI shop drawings, which had been submitted  
several weeks before.  
196.  
197.  
On April 29 Campbell advised Marquis by fax to put a hold on  
a spouting line on drawing 5326-M156.  
The May 2 minutes note that drawings were still on hold,  
that CWMM would not allow alternate suppliers for idlers for  
conveyor C2, and that work on DC 105 respecting the CWMM memo of  
April 7 had been held up for two weeks.  
198.  
On May 2 Popowich sent a fax to Harrish in Edmonton which  
said:  
"CWMM had to revise the standard spout gate  
to look something like the attached sketch.  
IECO have requested that we give them a price  
- 89 -  
to supply and install these sections as they  
are unable to complete this work."  
199.  
On May 4 CMI gave notice to FCC that CMI was being prevented  
from crewing up on the project due to several occurrences of  
delayed information, delayed decision making and delayed supplies  
of equipment for the upper workhouse, the workhouse and the bin  
floor annex. On May 6 Whitaker faxed Campbell requesting  
information on the conveyor supports to come for conveyors DC 101  
and DC 103.  
200.  
The May 9 site minutes also record that CWMM had eliminated  
two of the four drawings still on hold. FCC advised CWMM and UGG  
that crews would be increased as more equipment arrived, and that  
a second shift would be initiated once the day shift had reached  
its maximum capacity.  
201.  
202.  
In an FIR dated May 10 FCC requested support details for  
conveyor DC109. FCC's sketch of support details was approved on  
May 18.  
On May 12 CMI wrote to FCC and listed eight spouting  
drawings which they had not yet received for construction. On  
May 15 CMI issued RFC [Request for Clarification] 17 listing  
spouting details that were on hold. These drawings were needed  
to enable CMI to mark holes in the concrete floors in the north  
- 90 -  
and south annexes that FCC were required to cut to allow spouting  
to pass through.  
203.  
204.  
The minutes of May 16 record another request for information  
on the supports for conveyors DC 101 and 103 which was required  
by FCC. The minutes of May 23 record FCC's request for conveyor  
head support drawings for DC 101, 103, 105, 106 and 107.  
The relevant portion of the June 15 site minutes recorded:  
"16.003.17  
The schedule was turned  
over to all present, with  
the following  
clarifications; subjects:  
...  
F)  
That all "Holds" on  
drawings are removed  
prior to June 30/89.  
FCC and their subtrades are  
requested to review and advise  
of any holds that they feel  
are existing."  
205.  
As noted earlier, the schedule turned over on June 15 showed  
construction being completed by September 4 and commissioning  
being completed by September 11. In my view, a review of the  
documents authored by Van Dyke and Pope show that all present at  
the meeting understood that the schedule that was being handed  
out on that day was premised on the conditions set out in A  
through F being met. This did not occur.  
- 91 -  
206.  
On June 15 Whitaker sent a fax to Campbell listing drawings  
for FCC's subcontractors that were still at CWMM awaiting review.  
On June 27 Campbell advised the CWMM site representatives that  
there would be revisions on the head end of DC 110 issued on the  
next day. Additionally, Transcontinental sent a fax directly to  
Campbell with respect to the problem being encountered with the  
maxi-lift buckets which did not fit properly on the leg belts.  
207.  
By the end of July most of the drawing holds had been  
released. However some drawing holds resulted in extra work. On  
August 26 Campbell sent a fax to Van Dyke advising that the C5-C9  
drawings would be finished by the end of August. The drawings  
related to a change to conveyor C5-C9 which eventually led to a  
change order.  
208.  
209.  
On September 5 Weingand wrote to Koga advising of the change  
for belt alignment switches. These switches were to be changed,  
arising out of the direction given at the August 31 site meeting.  
The minutes of the site meeting of September 7 record sample  
belt alignment switches being turned over to FCC. These switches  
serve a safety function relating to the belt conveyors. The  
minutes record that the earliest delivery for the north annex bin  
bottom gates I/O rack was September 11, and that the trackshed  
panel would not arrive on site for a week. The minutes also  
record a target of moving grain on September 25.  
- 92 -  
210.  
On September 21 Derhouson confirmed that FCC would undertake  
modifications to C5 and C9 as shown on drawings issued on  
September 19 on a time and material basis with "completion by  
October 20/89". This fax was formally incorporated into Change  
Order 119.  
211.  
Van Dyke testified that he would not have ordered the C5 and  
C9 work if he thought it would take longer than October 23  
because that was FCC's then scheduled date for completion of the  
work. This estimated completion date was consistent with Van  
Dyke's own estimate in his report to MacKay.  
212.  
This illustrates one of the critical issues in assessing the  
delay allegations. To the extent that any FCC acts or omissions  
had caused the completion to be delayed to October 23 at the time  
UGG ordered the C5 and C9 work, then clearly the ordering of that  
work did not cause that period of project delay. Even if other  
UGG or CWMM acts or omissions had already caused project delay to  
October 23, then the fact that this specific item was carried out  
when it was does not necessarily mean it was a cause of delay.  
For FCC's case, it was only such if it, standing alone, caused  
substantial performance to be achieved later than it otherwise  
would have been. Van Dyke's evidence indicates that he was alive  
to this issue at the time and that is why he says he would not  
have ordered the work if he thought it would take longer than  
FCC's then scheduled substantial completion date.  
- 93 -  
213.  
214.  
215.  
CMI read in portions of Whitaker's discovery evidence at  
trial as follows:  
A.  
Probably one of the most obvious examples [of late  
design information] would be the spouting and conveyor  
layout in the north and south annexes.  
...  
Q.  
A.  
How did that impact upon the activities of FCC?  
It meant that shop drawings for conveyor supports  
could not proceed and shop drawings and  
fabrication of the spouting could not proceed."  
As the Project proceeded, Whitaker prepared an analysis of  
the drawing revisions that had occurred. In his evidence at  
discovery he stated:  
Q.  
A.  
Now as a result of the review that you conducted  
of the drawings, Mr. Whitaker, did you reach any  
conclusions with respect to the changes in those  
drawings?  
There was an unusually large number of drawings  
issued late or revised late.  
Whitaker gave further discovery evidence relating to certain  
of the mechanical drawings as follows:  
Q.  
A.  
When you say "lateness", what do you mean by that?  
Well, an example is on the third page, drawings  
5325, M-201 to M-205, these are spouting detail  
drawings, revised on the 30th of May, 1989.  
I'm sorry, where are you?  
The third page. Given that shop drawings have to  
be prepared by the spouting fabricator, reviewed  
by the engineer, the spouting pieces fabricated  
and installed, in my view May the 30th is too late  
for a project that was to be completed by the end  
of August.  
Q.  
A.  
On the next page, drawing 5325, M-401 was revised  
on October 26, 1989. This was after the intended  
completion date for the project. There are  
- 94 -  
several other drawings which were revised in  
October...  
216.  
Steel testified to the length and effect of the delay in  
receiving the final support details for the basement conveyors.  
He stated that he requested the details on June 8 and that they  
were not finally received until 18 days later:  
Q
A
Now, what difficulty was that causing you as of  
June 8th?  
Will, it's pretty obvious once against without the  
support details for conveyors you're not going to  
hang the conveyors and if you can't get the  
conveyors up Crosstown is not going to be able to  
get on with their field measurements and do the  
spouting and ducting.  
Q
And how long did it take to get an answer to that  
particular request? You might refer to Mr.  
Whitaker's summary for a quick answer to  
that.  
A
Q
A
Okay. Are you insinuating that I'm slow?  
No.  
Well, there was -- do you want the number of days  
or  
--  
Q
A
Q
A
Q
Yes. Did you get the answer in one lump?  
No, we didn't. We got it piecemeal.  
Okay. And how long did it take?  
Total duration looks like 18 days to me.  
Do you recall having any discussions with anyone  
from CWMM or UGG as to either why these were late  
the time or with respect to what problems you were  
having with these or was it simply done by memo?  
Oh, I think, you know, in all fairness we did  
speak to Bob on the site and we were advised that  
they were going to make some changes to the  
at  
or  
A
conveyors in the base. They were going to switch  
from screw conveyors I believe to drag conveyors  
something of this nature so they were going to  
re-design it.  
Q
Did this work put Crosstown behind at all, do you  
know?  
Well, sure.  
A
- 95 -  
217.  
Steel gave the following evidence of the effect of FIR 98 on  
CMI:  
Q
A
Would you refer to FIR number 98 please. That's  
regarding a gate interfering with a leg. Would  
you explain what information you required and why  
just in your own words?  
I believe that this is a gate that actually is  
going to be installed by Crosstown in their  
operation, and it was going to interfere with one of  
the legs on the scale floor.  
Q
A
Q
A
Q
A
Q
Okay so what you were looking for?  
Some instruction as to what we should do about it.  
Okay. The memo is June 28, correct?  
Yes.  
When did you get a response?  
July the 7th.  
Okay. Do you know why it took nine days to  
respond?  
A
No, I have no idea but I can tell you this, that  
it certainly stopped Crosstown from carrying  
on with  
that work and they couldn't afford to stop.  
Now, why do you say that they couldn't afford to  
stop?  
Well, now that the equipment is finally come and  
we have a -- a good supply of tradesmen to  
it we were putting the stuff in fast and  
and* just and they had a lot of work to  
all of a sudden this equipment was here  
Q
A
install  
fewer rust  
do now that  
and being  
installed. Now it was up to them and the  
electricians and the control people to  
this job. So you know, they didn't need  
that's for sure or any hold-ups.  
complete  
any stops  
218.  
Notter complained that CWMM continuously changed the design  
of the Buhler equipment, often in an incomplete way, and were  
slow at returning shop drawings, but recognized no schedule  
impacts as a result. At a May 3 meeting with CWMM, Notter said  
"Stop changing and then we can finalize and say that's the final  
delivery".  
- 96 -  
219.  
In my view, the evidence demonstrates that the number of  
drawings prepared by CWMM during the course of the project and  
the timing of their delivery to the contractors delayed them in  
the prosecution of their work. A contractor on a lump sum  
project is entitled to expect that the project design has been  
substantially completed at the time of tender. While a certain  
number of changes are to be expected during the course of a refit  
project such as this, the number of drawing revisions and the  
delay in providing these to the contractors caused FCC to attain  
substantial performance after August 31 and it delayed CMI in its  
work.  
(iv) DOCK PROGRESSORS  
220.  
On March 17 UGG confirmed by letter that it had "asked the  
Vancouver Port Corporation to upgrade the jetty at the terminal  
as part of construction works that VPC is undertaking to repair  
the jetty". At the time MacKay knew that if the upgrade contract  
was awarded it would be awarded to JJM, a non-union contractor.  
The letter also said:  
"We [UGG] understand that VPC can proceed to award the  
contract for construction of the repair and upgrade  
project based on UGG's agreement and consent to the  
matters referred to in this letter."  
221.  
UGG also confirmed its agreement that construction of the  
west berth could carry forward to September 15 and construction  
of the east berth could carry forward to November 15.  
- 97 -  
222.  
The site minutes of April 25 record at item 10.007:  
"10.007  
It is to be noted that all FCC related  
personnel are totally off the dock area.  
CWMM asked FCC to advise of the latest date  
they require to complete their work in this  
area.  
A - FCC ask that it be recorded that any delay or  
interruption in this area has an adverse  
affect on their completion.  
B - It is to be noted that there is certain  
electrical work to be done at the north end  
of the dock.  
C - FCC request a copy of the dock work  
plans/specifications and schedule."  
223.  
On May 15 Bomback sent a fax to Campbell requesting  
instructions with respect to the Concise equipment. On the same  
day Campbell provided information to Marquis about the  
availability of the dock for installation of the dock  
progressors. The dock progressors could not be installed on the  
date suggested by Campbell because the dock did not become  
available.  
224.  
The site minutes of May 16 recorded under item 13.001:  
"13.001  
The potential problem of non-union versus  
union for dock installation was raised.  
A)  
The area for secondary  
progressors will be available  
to FCC July 3, 1989.  
- 98 -  
B)  
C)  
Electrical I.O. Loops should  
now be postponed until after  
dock work is complete.  
Concerns regarding  
demarcations of north end  
boundary were discussed and it  
is hoped that as the dock work  
progresses, the installation  
of progressors, etc., will  
follow the dates as those  
areas are turned over."  
225.  
226.  
The dock progressor work was not completed until November.  
The site meeting minutes of June 8 record that FCC advised  
UGG and CWMM that the dock progressor work should "begin July  
17/89 to meet the completion date". Additionally, the meeting  
notes record "FCC advised that they will prepare a schedule  
update for next week based on the advice of earlier delivery  
dates for all BM conveyor components".  
227.  
228.  
The Whitaker schedule turned over by FCC at the June 15 site  
meeting was subject to:  
E)  
That we are able to begin work on the dock  
progressors and north end loop on or before July  
17, 1989.  
In MacKay's June 20 report to the UGG Board of Directors he  
noted that the secondary car progressors on the dock would "not  
be installed until July when JJM is finished working on this area  
of the dock". MacKay also noted that discussions with the union  
with respect to reducing staff were going very slowly. The  
- 99 -  
report also notes that the west berth was scheduled to be  
completed by September 15 and the east berth by November 15.  
229.  
230.  
On June 22 at a meeting after the site meeting, Skodje  
advised that FCC wanted to withdraw from the dock work concerning  
the two dock progressors because of union problems caused by  
JJM's dock upgrade work.  
On July 5 Rhodes forwarded to Campbell the documentation  
reflecting the walkout on site, indicating that on Thursday, June  
29 most tradesmen on the Project decided to exercise their non-  
affiliation clauses not to work alongside non-union workers on  
the dock and walked off the job. They did not return to work  
until late in the day on July 4.  
231.  
Van Dyke's notes of the meeting following the site meeting  
on July 6 indicate "CWMM put together new contract for FCC with  
C.O. for deletion of [the dock] progressors".  
On July 7 Mr. Skodje wrote to Campbell stating as follows:  
"In accordance with the requirements of Item 6, Page 2  
- 6, Section 2, "Form of Tender" and "GC4 Delays", page  
11, Section 3, "Contractor Agreement Between Owner and  
Contractor" we notify you of the possibility of a claim  
due to labour disruptions which commenced on site  
approximately June 30, 1989."  
232.  
Both CWMM and UGG knew at this time that FCC had been  
delayed by the labour disruption on site. JJM was working on the  
dock upgrade contract (consented to and approved by UGG) and FCC  
- 100 -  
employees exercised their non-affiliation rights and refused to  
work alongside non-union employees.  
233.  
On July 13 Campbell sent a fax to Atwell requesting the  
official cancellation of the change order deleting the dock  
progressors from the Prime Contract. Van Dyke cancelled the  
change order. This cancellation was not done at FCC's request  
and had the effect of adding the two progressors back into the  
work under the Prime Contract.  
234.  
235.  
On July 14 there was a meeting respecting the dock work  
attended by representatives of VPC, JJM, CWMM, UGG and Acres, but  
not by FCC. At that meeting Tuttle of VPC said "can't guarantee  
allowing FCC to work on dock unless he gets time extension".  
The minutes of the site meeting of August 24 record that FCC  
had completed all work for the progressors on the dock to the  
extent possible in the previous weekend, and that UGG had  
expressed their concern regarding the schedule and completion  
with all parties to continue maximum efforts to meet deadlines.  
236.  
In his August 24 letter to Pope, Campbell projected  
electrical control, instrumentation work into November not  
including "an apparent impasse with respect to completing work on  
the dock progressors". The August 24 site minutes also record  
FCC being requested to proceed with the progressor installation  
on the docks Wednesday, November 1 as UGG advised JJM would be  
- 101 -  
off the dock. Ricketts-Sewell stated that the fire alarm would  
be operational by the following Monday.  
237.  
After November 1 the minutes of the site meetings were  
prepared by Hawkins. The minutes of the site meeting of November  
2 record that all sampling systems had been checked out, while  
the three panels added by the CGC were still coming there were  
further requirements of the CGC, the additional belt alignment  
switches had been completed, and FCC would begin the preparatory  
work the next day for the installation of the dock progressors  
"assuming that JJM will be off the upper deck".  
238.  
On December 6 MacKay and Van Dyke met with Smith and  
Birkland of the VPC. They were advised that by Christmas the  
west berth could be done, but that the east berth may take an  
additional four to five months. The VPC explained they had no  
problem terminating JJM's contract since there was a standard  
termination clause in the contract. It was then suggested or  
decided that the work on the east berth would be delayed until  
the dredging for the east berth could be done, so that one berth  
would be lost only once for six months instead of for twelve  
months. MacKay's notes record "UGG should also mention that hold  
off east berth - get JJM off berth therefore not a problem with  
non-union/union shop. We have concern over working relationship  
- longshore - grain handlers - etc.". MacKay explained in  
evidence that this was a reference to the fact that no one knew  
- 102 -  
whether or not the Grainworkers Union or the Longshoremens' Union  
would work while JJM was on the dock. The best thing to do,  
according to MacKay, would be to get JJM off the dock before  
doing any shipping.  
239.  
FCC was delayed in installing the dock progressors because  
its union work force refused to work at a common site with JJM's  
non-union forces. It is clear that FCC was unable to install the  
two progressors on the dock until JJM's work was completed and  
they were off the dock. However Van Dyke testified that the dock  
work was delayed or at least it was not completed earlier because  
FCC was already late in completing its work under the contract.  
He says UGG could have had the dock work completed earlier. I  
accept that evidence and conclude that while the dock may have  
delayed FCC, such delay was concurrent to the delay already  
caused.  
(v) VOLUME OF CHANGE ORDERS OR EXTRA WORK  
240.  
As outlined in the "FCC EXTRAS" section, the parties elected  
not to follow the provisions of GC 11 and 12 in the prime  
contract respecting extra work. These stipulated that upon the  
ordering of extra work, the contractor was to advise in the event  
that the extra would result in an extension of the contract time.  
If so, the owner would then have the option to proceed with the  
extra or cancel it and have it done later or by another  
- 103 -  
contractor. FCC says that because the contract provisions were  
mutually waived, it did not have to so notify UGG. UGG contends  
it was entitled to order extra work and to be advised by FCC if  
such extras would delay substantial performance. UGG says that  
if the extra was going to delay the completion, it wanted the  
option of cancelling the work or having it done later or by  
another contractor. At no time on this project did FCC ever  
advise that ordered extra work was going to delay substantial  
performance.  
241.  
242.  
On March 20 Campbell forwarded proposed change order  
material to Marquis, which did not comply with GC 11 and GC 12 of  
the Prime Contract. This type of material was used during the  
balance of the Project.  
The April 18 site minutes note that information had been  
received with respect to the brackets required to hang the Bisco  
drag conveyors. The minutes also note that there were still four  
drawings on hold. FCC requested a "CCN (Contemplated Change  
Notice) for the change in conveyor length because of the impact  
it would have on other trades for new gates, pneumatics,  
controls, etc".  
243.  
At the April 18 site meeting FCC produced sketches for  
consideration for the conveyor hangers that had been put on hold  
by Campbell on April 7. A change was also requested to be  
- 104 -  
confirmed by CWMM for the addendum to the Hansen Letter of Intent  
that was missing from the tender package.  
244.  
On August 8 Campbell sent a fax to the CWMM site  
representatives with respect to metering gates for six gates.  
This work was to allow UGG to control the extent to which the  
gates opened, rather than having the gates in a fully open or a  
fully closed position as the only alternatives. This requirement  
was first noted on July 31.  
245.  
On August 9 CWMM issued memo 300 directing the metering work  
on the six gates to proceed on a time and material basis. FCC  
says that when work was directed on a time and material basis  
Campbell intended that FCC would have a reasonable time within  
which to complete the work. At no time did CWMM say to FCC that  
FCC took an unreasonable period of time to complete this work.  
However a reasonable time to complete the work is not the same  
thing as an agreement to extend the contract time.  
246.  
FCC's response to this memo is as close as FCC ever came to  
giving specific notice of extra-caused delay. Marquis wrote on  
the memo "we will review and advise as to any effect on the  
schedule". No further advice was given to CWMM or UGG. On  
August 15 FCC advised CWMM that this extra could not be completed  
for at least four weeks due to equipment deliveries. Van Dyke  
acknowledged in evidence that from subsequent site meetings and  
- 105 -  
copies of documents from CWMM, UGG had the same information on  
delivery of the valves as did CWMM and FCC.  
247.  
This illustrates the difficulty with assessing the impact of  
the extras. FCC told CWMM August 15 that the extra would take at  
least 4 weeks, well past the August 31 completion date. However  
by August 15 it was clear that substantial performance was not  
going to be achieved by August 31. Hence telling CWMM August 15  
that the extra work would take at least 4 weeks was not a  
communication that the extra would cause a delay in substantial  
performance.  
248.  
Also on August 10 CWMM discovered that many of the motors on  
site did not have thermistors. This led to an extra directed on  
a time and materials basis to FCC to install thermistors in the  
motors. Several motors, weighing 5-600 pounds each had already  
been installed and needed to be removed. Van Dyke initially  
understood the thermistors were an insurance requirement for  
operation of the plant.  
249.  
The site minutes of August 17 record that the schedule could  
not be maintained with the additional work without overtime. FCC  
was targeting the first week of September to remove the overhead  
crane. Hammond advised that they had received the first modicon  
control card and Ricketts-Sewell advised that the I/O rack for  
the basement gate extra would not arrive on site until September  
- 106 -  
"after which it will take 3 weeks to complete the installation".  
Ricketts-Sewell also advised that "the South Annex will follow".  
All parties were apprised of the delay problems with respect to  
the basement gates extra at this meeting.  
250.  
On August 21 Van Dyke and Campbell discussed Van Dyke's  
feeling that FCC would not complete until December 1. They  
discussed whether the Celtek extra could be done outside the  
Prime Contract without affecting it. They discussed the  
number of man-hours they thought FCC had worked on the Project  
(based upon a conservative estimate provided by Atwell) compared  
to the number of man-hours they thought UGG was entitled to based  
on their interpretation of page 2-5 of the Prime Contract. Van  
Dyke also noted the dock delay as well. In his notes dated August  
22 Van Dyke recorded a conversation with Campbell regarding  
thermistors "were they not spec'd, what happened?". On August 23  
Campbell sent a fax to Weingand with further solenoid  
clarifications advising Weingand "this is not the end".  
251.  
On August 24 Weingand advised Koga of Ricketts-Sewell of  
significant changes to the basement gate work caused by Modicon's  
inability to deliver 32 bit cards and a change to 16 bit cards.  
This work was eventually done on a time and materials basis under  
a change order.  
252.  
On August 26 Campbell sent a fax to Van Dyke advising that  
the C5-C9 drawings would be finished by the end of August. The  
- 107 -  
drawings related to a change to conveyor C5-C9 which eventually  
lead to a change order.  
253.  
On August 28 Somogyi sent a fax to the site office with the  
additional work required with respect to the manifold diverter  
valves. The largest part of this additional work was to supply  
solenoids for all double valves. The time estimate for delivery  
was four weeks after receipt of order. These solenoids were  
necessary because the default position of the solenoids was the  
closed position. In case of a power failure, if both gates on a  
double valve gate were to close they would damage the gates. It  
was therefore necessary to add solenoids to each of the double  
valve gates. This work was required before substantial  
performance of the Work could be achieved.  
254.  
At the end of the site meeting on August 31 Marquis handed  
out three pages of the FCC's concerns. These concerns  
transmitted to all at the meeting, included many extras which  
were causing delays, many questions which needed to be answered  
in order to finalize the project, and noted:  
"Additional work - both RS and CMI have problems doing  
within current schedule & need to do on overtime  
basis...both CMI & RS should be authorized to work  
overtime on contract work."  
255.  
Subsequently, Hammond did from time to time authorize  
Ricketts-Sewell to work overtime on original Contract Price work  
- 108 -  
and on Change Order work. No such authorization was forthcoming  
from Campbell for CMI or FCC. However while FCC advised the  
extras were causing delays, it at no time gave notice of time  
extension.  
256.  
On September 13 Weingand sent a fax to Atwell regarding  
changes to the basement gates. A memo was sent to FCC directing  
that the further changes take place stating "these changes have  
been discussed with your electrical subcontractor and do not  
represent a delay to the work". Marquis crossed out the words  
"and do not represent a delay to the work" and returned the memo  
to CWMM because any additional work at that stage of the game  
would have delayed the Work. What Marquis did not do was to  
advise that the extra would cause substantial performance to be  
delayed and request a time extension to the contract. If extra  
work was going to delay substantial performance the contract  
required FCC to notify UGG if it wanted a time extension.  
Although the parties waived the contractual formalities for  
ordering extra work, I conclude that the requirement that the  
contractor provide notice if an ordered extra was going to delay  
substantial performance was never so waived.  
257.  
On September 21 Derhouson confirmed that FCC would undertake  
modifications to C5 and C9 as shown on drawings issued on  
September 19 on a time and material basis with "completion by  
- 109 -  
October 20/89". This fax was formally incorporated into Change  
Order 119.  
258.  
On September 27 Marquis advised Campbell of the extent of  
the additional work for the diverter gates. Hammond noted on the  
memo that the terminations should all be finished by October 13.  
This was extra work. On the same day Weingand noted the final  
layouts were sent for the receiving and shipping panels for the  
Canadian Grain Commission to meet their requirements.  
259.  
260.  
On October 19 Van Dyke authorized Hammond to direct  
Ricketts-Sewell to continue with overtime on terminal lighting  
and repairs to motor control centre 12A, to ensure that lights  
and fire sensors were in place for start up.  
On October 30 Campbell directed Bisco to install chain  
casings for conveyors B1 and B2 and UGG issued a purchase order  
November 1. These chain casings were required before conveyors  
B1 and B2 could operate at production capacity. The purchase  
order to BISCO was not a Change Order to the Prime Contract.  
261.  
On November 7 Weingand developed a lengthy list of further  
Modbus II parts which were required. The parts were ordered  
under a change order to the Prime Contract and were installed  
between Nov 13 and Nov 18. The Modbus II was required to operate  
the PLC.  
- 110 -  
262.  
On November 14 Weingand recorded a telephone conversation  
with Van Dyke regarding a change order to the Western Scale  
delivery which would be handled as a new purchase order directly  
between UGG and Western Scale. The equipment ordered was  
required for the communication between the scale computers (in  
the old control room) and the terminals, printers etc. (in the  
administration building), and for the direct scale to Modicon  
communication.  
263.  
The minutes of the site meeting of December 14 note that  
scale 1 was to be certified on that day, Ricketts-Sewell would  
finish the extra work in the scale 3 area the next day and were  
waiting "testing by HA", a partial deficiency list had been  
received on Tuesday, and security was to become UGG's  
responsibility starting Sunday at midnight, December 17. The  
minutes also note that CWMM advised "UGG to take over lock-out of  
MCC's after Friday, December 15, 1989".  
264.  
One difficulty in assessing the impact of the extras on  
substantial performance is that FCC never advised CWMM or UGG  
that a specific extra, if carried out, would result in a  
corresponding project delay. If the ordered extras were going to  
delay FCC, I would have expected it to have notified CWMM and /or  
UGG. In addition, most of the extras were ordered later in the  
project. For these reasons I am unable to conclude that FCC has  
established that the ordered extras delayed it in its work beyond  
- 111 -  
the delays caused by the factors to which I have already  
referred.  
(vi) COMPUTER PROGRAMMING  
265.  
On June 5 Hammond transmitted drawings to Western Systems,  
including the drawings for the PLC I/O module and closure  
layouts. Weingand said in his accompanying note with respect to  
the changes that were made "I hope this hasn't caused too much  
extra work or confusion".  
266.  
On July 24 Weingand of Hammond sent a fax to Western Systems  
with a copy to Koga of Ricketts-Sewell dealing with inter alia  
delivery of modules and enclosures for the Basement Gate extra.  
In the fax he said:  
"We understand that the B806 modules are long delivery.  
Please do not delay delivery of these enclosures  
because you don't have these modules. If delivery of  
enclosures is delayed it will set the whole job behind,  
therefore modules will have to be installed on site."  
267.  
268.  
This fax was not sent to FCC.  
On July 31 Campbell sent a fax to Weingand stating, inter  
alia:  
"3. SVG 05, 02, 11, 12 and SVS01 all require  
metering gates.  
4. Any control philosophy info ? for me".  
- 112 -  
269.  
The site minutes of August 17 record Hammond advising that  
they had received the first modicon control card and Ricketts-  
Sewell advising that the I/O rack for the basement gate extra  
would not arrive on site until September "after which it will  
take 3 weeks to complete the installation". Ricketts-Sewell also  
advised that "the South Annex will follow".  
270.  
On September 12 representatives of UGG met with  
representatives of CWMM to discuss the electrical and engineering  
status. Van Dyke's notes record that Campbell had a "concern re  
control philosophy. No control devices yet installed. Need  
realistic indication of where [at]". He also noted that a report  
was needed with respect to "dock time completion". Van Dyke's  
notes make it clear that there were many outstanding electrical  
and engineering items, including those relating to the Canadian  
Grain Commission, the PLC and computer programming, and the  
preparation of an operations manual and control philosophy which  
were slated to be ready by September 21. Also, in response to  
the question "when R & S complete" it was noted "maybe end of  
October to run grain - still need more time to get into  
production". Hammond gave evidence that at no time did he think  
Ricketts-Sewell was not diligently prosecuting its portion of the  
work under the contract.  
271.  
The minutes of the site meeting on September 14 record a  
further three weeks for the installation of the thermistors with  
- 113 -  
CSA approval required when installed, actual delivery of the  
north annex bin bottom gates I/O racks for September 13 with the  
south annex racks perhaps coming Tuesday or Wednesday of the  
following week, and that the trackshed panel would arrive on site  
on that day but probably would not be installed until October 9.  
272.  
On September 15 Van Dyke prepared a detailed report on all  
areas of the Terminal for MacKay. According to Van Dyke's notes  
he did not estimate the completion of any of the mechanical  
installations to take longer than three to four weeks. However,  
he did advise MacKay that he could not see the west berth being  
finished until November or December, that the new engine would  
likely not arrive until mid October and that electrical  
completion was scheduled for the end of October. He also noted  
that with respect to the north and south annex basements that  
very little work had been done on the bin gate opening system and  
that Van Dyke was "unsure of the status of equipment at this  
time".  
273.  
274.  
On September 18 Campbell sent a fax to Hammond re changes to  
the gate opener cab that had to be completed before the gate  
opener would accept the panel that was to be installed in it.  
The gate opener needed the panel in order to operate.  
The site minutes of October 5 record that installation of  
thermistors would take place in the next week, the progressor  
- 114 -  
cylinders would be sent out for check out, the wiring for the  
north annex basement gates would be complete on October 5, the  
tie-in and termination of plant systems into the administration  
building was targeted for October 16, the PLC terminations would  
be completed in the north annex, the work in the south annex was  
targeted for completion by October 23, and Ricketts-Sewell was  
experiencing problems with the lighting circuits.  
275.  
On October 17 Hammond sent a fax to Campbell with a copy to  
Van Dyke suggesting that the proposed grain run for October 18 be  
cancelled. The reasons Hammond gave were as follows:  
"(a)(2)1. The fire alarm system is not fully  
operational. There are 2 major splices to be  
made where conduit was removed to clear  
spouting. Once repaired (later this week  
apparently) the system must be tested by  
Systematic along with the annunciator in the  
panel room. I suspect that running grain  
without adequate fire protection would have  
dire insurance consequences.  
2.  
The workhouse would become "hot" after  
the run. It appears there is at least 3  
eeks worth of concentrated hot work  
still to be done.  
3.  
4.  
Electrical rooms must be sealed and  
pressurized. Also all open electrical  
boxes and equipment must be sealed.  
For process purposes, the proposed grain  
run has no commissioning benefit. The  
equipment sequencing can not be checked  
until entire systems are available. My  
first choice would be to have systems  
dry-run under control from the PLC once  
all wiring checks are done. After this,  
- 115 -  
grain can be run to observe performance  
under load."  
276.  
The fire alarm reference was a reference to a Change Order.  
The hot work in the workhouse was a reference, as the meeting  
minutes of October 12 recorded, to primarily Change Orders rather  
than originally tendered contract work. The reference to  
"process purposes" was a reference to the fact that because the  
PLC was not fully programmed to run from the computer there was  
no commissioning benefit as far as Hammond was concerned.  
277.  
On October 19 the site minutes record that the thermistor  
extra would be completed in the next week and north annex testing  
had caused Hammond some problems but should be sorted out by the  
next week. It was also reported that the tie-in to the  
administration building should start in a few days and would take  
three days, but that CWMM had not yet heard of the date of  
deliveries of the revised grain commission panels. Hammond  
advised that minimum requirements were not yet completed prior to  
running grain and that he would prepare a list for review, would  
identify minimum lighting required and repiping prior to a grain  
run, and that it was targeted to run the sampling systems with  
the PLC on Monday, October 23. The minutes also record that  
additional belt alignment switches were now required and that  
there were tolerance problems with the wipers for the Nord-Sen  
gates.  
- 116 -  
278.  
279.  
On October 19 Van Dyke authorized Hammond to direct  
Ricketts-Sewell to continue with overtime on terminal lighting  
and repairs to motor control centre 12A, to ensure that lights  
and fire sensors were in place for start up.  
At a meeting of October 23, FCC confirmed that A - K in the  
start up memo had been done, the exceptions being "F" and "I".  
"F" was an exception relating to belt alignment switches and it  
was confirmed at the meeting that the belt alignment switches  
could be installed before or after grain flow. The only  
outstanding item for start up in accordance with Hammond's memo,  
as of October 23 were opening and closing the gates, some of  
which were still being rewired with new solenoids.  
280.  
The minutes of the site meeting of October 26 record that  
the thermistors were inspected and that in respect of testing,  
cleaner deck and basements were complete, north annex drags and  
gates would be done the next day, and the remaining workhouse  
would be done by the following Monday. The minutes also record  
lighting requirements for the grain run being identified on an  
ongoing basis, and that the three panels added by the Canadian  
Grain Commission would arrive in 2 weeks. The minutes also  
record "upon the comment that substantial completion of the main  
contract be established, it was suggested that this would happen  
after grain was introduced. Further review will be made".  
- 117 -  
281.  
Van Dyke's notes of the October 26 meeting record that when  
Marquis asked Skodje to call for substantial completion, Skodje  
said "we haven't done our work until grain runs through the  
system. Feel done by Friday then ask for substantial completion.  
Workhouse "'hot' by next week". This was a reference to FCC's  
view that once the workhouse was hot and some grain had been run  
FCC would have substantially performed its obligations under the  
Prime Contract.  
282.  
After November 1 the minutes of the site meetings were  
prepared by Hawkins. The minutes of the site meeting of November  
2 record that all sampling systems have been checked out, while  
the three panels added by the CGC were still coming there were  
further requirements of the CGC and the additional belt alignment  
switches had been completed. Item 37.001 records:  
"37.001  
Continuation of item 32.004 - Testing:  
HA gave verbal report of  
current checkouts  
-
-
-
-
-
-
-
Wheat reclaim done  
Legs all complete except 10 & 28  
All drag conveyor have been bumped  
Distributors are ready  
All gates on cleaner deck have been adjusted  
Adjustment required on gate limit switches  
Encountering some wiring problems for the  
dust control systems."  
283.  
On November 14 Weingand recorded a telephone conversation  
with Van Dyke regarding a change order to the Western Scale  
- 118 -  
delivery which would be handled as a new purchase order directly  
between UGG and Western Scale. The equipment ordered was  
required for the communication between the scale computers (in  
the old control room) and the terminals, printers etc. (in the  
administration building), and for the direct scale to Modicon  
communication.  
284.  
285.  
On November 20 Weingand made a further list of missing I/O  
modules related to the Modicon supply.  
On December 11 Van Dyke took notes at a meeting with MacKay.  
Van Dyke's notes state, inter alia, "Gerry Moore asking what's  
going on - directors want to know...MM - find out 'where at' and  
'when' done - wants to unload cars on Wed if scales certified by  
Tues - wants day shift crew in place and in position to run  
grain". The also notes indicate that Van Dyke "expressed concern  
re: 'starting up too soon' and not being under PLC control -  
trying to operate manually will cause too many problems and slow  
down the total automatic process from coming into effect". The  
note ends with MacKay requesting a meeting with Hammond,  
Campbell, Graham and Van Dyke to "see where programming is at".  
286.  
On December 20 Campbell, Van Dyke, Hammond, Pope, Graham and  
MacKay met to discuss programming. Hammond advised of the items  
that were still outstanding including the following comment with  
respect to the shipping system, "programming is done - will  
- 119 -  
commence working on this area Jan 2, 1990 - right now we can run  
belts and open bins - we have to verify all the bins are  
operationally functional and we have to meter the gates - we have  
to check and certify the scales - then have to check from scale  
to vessel".  
287.  
On December 21 Van Dyke's notes record "ship scales and 3  
shipper - not yet certified", "Need written Operational &  
Procedure manuals info on inter-locks - fire alarms systems -  
etc.", "Shipping: problems re: metering new gates - may be  
potential future problems....", "UGG - perhaps open/close  
basement gates on MT bins and when running" and "Damage to  
hydraulic power pak by JJM - lights etc."  
On December 21 Van Dyke made a note entitled "discussion with  
PJC". In the note Van Dyke says:  
"Deficiencies for substantial completion.  
1.  
Basement gates have not yet been tested and  
shipments under auto control cannot be made.  
(consultant still to check performance  
parameters)".  
288.  
At trial Van Dyke said that this would not be a deficiency  
for substantial completion, although he thought that it was in  
December, 1989.  
- 120 -  
289.  
On February 1, 1990 UGG shipped grain for the first time  
since 1989. The shipment was from the west berth. In respect of  
the shipment Pope told Wilson of the Vancouver Province that  
"United Grain Growers shut down its elevator in March, 1989  
expecting a five month closure. But the conversion to  
centralized computer control was much longer".  
290.  
On March 13, 1990 MacKay forwarded his quarterly report to  
the Board of Directors. He advised inter alia:  
"The UGG Vancouver terminal starting unloading cars the  
week of December 18...the handling agreement with SWP  
ceased as of December 1 (excluding canola)"....During  
January and February the terminal staff were kept busy  
getting the 2 receiving scales, 2 shipping scales and  
the truck loading scale approved by the Canadian Grain  
Commission. The 2 shipping scales and 2 receiving  
scales had been approved, but the CGC has some concerns  
about the bulk weigh receiver scale. UGG and Western  
Scale spent a lot of time during January and February  
working on the bulk weigher in order to erase the  
concerns of the CGC weighing staff. As in most new  
systems one must learn how to walk before you run and  
this project is no different. The employees are  
learning the new system and at the same time we are  
debugging the computer program which runs the terminal  
operations. This is an ongoing process and can be very  
frustrating for all concerned - management, employees,  
engineers, and directors. There has been some  
improvement and it is encouraging to see some  
consistency developing as of the end of February".  
291.  
Because the programming delays occurred relatively late in  
the project I cannot conclude that these events delayed  
substantial performance longer than it had already been delayed  
by other events earlier in time. So to the extent that computer  
- 121 -  
programming delayed substantial completion, I find that those  
delays were concurrent.  
DELAY ALLEGATIONS - CMI  
(a) INTRODUCTION  
292.  
I now turn to the factors said by CMI to have delayed it in  
its work under the subcontract with FCC. Many of these factors  
such as drawing delays echo FCC allegations. Other factors such  
as equipment delays contain allegations at least in part directed  
at acts or omissions of FCC as well as UGG and CWMM. Finally,  
CMI's allegations with respect to demolition delays and the IECO  
gates are directed solely at FCC.  
293.  
Most of CMI's work on this project consisted of spouting  
that was to be connected to equipment that was in fact delayed.  
Since CMI's spouting could not be connected to this equipment  
until after the equipment had been installed in its final  
location, delays to the delivery and installation of equipment  
became delays to CMI.  
294.  
CMI summarizes its delay case with reference to the  
installation of the south annex drag conveyors. It points out  
that no critical path analysis was undertaken by the parties to  
this litigation to enable a detailed analysis to be made as to  
why the project schedule was not achieved. However, it says the  
critical path of its work was extremely simple. It involved one  
- 122 -  
final "milestone" and one "work item", namely: the South Annex  
drag conveyors. Relying on Rhodes October 18 Daily Report which  
is the first reference to CMI installation work in the south  
annex, CMI says the last South Annex drag conveyors were made  
available to CMI for installation of spouting on or shortly  
before that date. CMI substantially completed its work on the  
South Annex spouts - and the project - by the end of November:  
somewhat more than one month later. CMI says if the six week  
period it took to install the south annex spouting is reasonable,  
then whatever may have happened in other areas of the plant, it  
could not have completed its work before November, 1989.  
295.  
In its March 27 Schedule, CMI planned to begin the south  
annex spouting on April 24, and complete it by July 10. The bin  
floor spouting in the north and south annexes was a significant  
work item. It represented 30% of CMI's originally tendered scope  
of work.  
296.  
Some other factors that delayed CMI were canvassed with  
Marquis in cross-examination. He agreed that:  
(a) the demolition work had been delayed, and CMI's work  
had to follow completion of the demolition work;  
(b) holds had been placed on the design drawings throughout  
the period March - June 1989;  
- 123 -  
(c) there had been delays in the delivery of the IECO gates  
to which CMI spouting had to be connected and the  
installation of IECO gates was essential to CMI's  
performance of its contract;  
(d) CMI had difficulties in both the basement and cleaner  
decks as a result of interferences;  
(e) CMI had not been able to field measure because of a  
number of factors, and he agreed that FCC supported CMI  
on this issue;  
(f) there had been late delivery of some of the pre-  
selected vendors' equipment;  
(g) when the drag conveyors were delivered there had been  
tolerance problems with the gates attached to them;  
(h) CMI had been asked to work substantial overtime from  
July 26 to October 12 to accomplish extra work and to  
maintain the "contract schedule".  
297. Of all the witnesses at the trial, other than CMI's witnesses,  
Steel had the most frequent and direct contact with CMI's effort  
and progress on a daily basis. He testified that CMI was delayed  
from the beginning by factors beyond its control in many areas of  
- 124 -  
the project. I further take from his evidence that in his  
opinion CMI took reasonable steps in mitigation.  
298.  
He responded as follows with respect to the April 5 Daily  
Report:  
Q
Would you refer to your daily job report for April  
5th, please. And would you describe where  
Crosstown was in its work?  
A
Well, my note to myself here is Crosstown  
materials are starting to roll in now.  
Q
A
That's halfway down the page?  
Yes. And they will be increasing the installation  
crews next week.  
Q
A
Okay. Was it your perception as of April 5th that  
Crosstown was holding up the work?  
No. Not -- not for the equipment they had, no,  
certainly not.  
299.  
When asked about the May 2 site meeting item 11.014 he said:  
Q
A
Okay. Do you recall anyone from Crosstown stating  
that Crosstown was being held up in some areas?  
Well, there was more than some areas, John. I  
mean obviously without gates, without conveyors  
there is all kinds of areas that are being held  
up.  
Q
A
But can you recall anybody saying that at the  
meeting?  
Yes. It was brought out when this was -- when  
this was thrown out at the minutes we and  
also stated they were being held up in  
Crosstown  
areas --  
Q
A
You can recall that specifically?  
Yes, I do, yeah.  
300.  
301.  
Popowich noted on his copy of the minutes that 11 gates  
arrived the next day, May 3.  
Regarding the May 4 Daily Report Steel said:  
Q
Look at the last paragraph. It says:  
- 125 -  
"Meeting held with Crosstown today. They will  
be crewing up next week. Problem with the turn  
head drive motor relocation has apparently been  
sorted out by CWMM today. This equipment will now  
be approximately three weeks behind schedule in  
arriving."  
Let's start from the beginning with the notation  
about "Crosstown crewing up next week". Why was  
Crosstown going to be crewing up next week?  
Well, with the arrival of -- anticipated arrival  
of the turn heads and various equipment they are  
anxious to put people on the site and get on with  
their work.  
A
302.  
Referring to the May 10 Daily Report Steel said:  
Q
At that time, May 10th, was Crosstown behind in  
its spouting given the equipment that had arrived?  
In the cleaner deck or on the entire site?  
Let's start with the cleaner deck?  
A
Q
A
Q
A
No. Not in my opinion they weren't, no.  
What about the entire site?  
No. Every time a piece of equipment came in on  
that site they were on it. I mean as soon as we  
as soon as we got it installed or hung or whatever  
we had to do to it.  
--  
303.  
Referring to the May 25 Daily Report he said:  
Q
Okay. Now, as of that date May 25, do you recall  
whether you felt that Crosstown was still able to  
keep up with the incoming equipment? Well, yeah,  
they were doing fine at that particular time. As  
I think earlier we already said said that they  
were increasing by five and by five and so we all  
felt we were on top of what was happening.  
304.  
In chief referring to the July 12 Daily Report Steel said:  
Q
Would you refer to your July 12th daily report,  
please. Starting with the first paragraph, do you  
see that?  
A
Q
Yes.  
It is says, "after several meetings with Crosstown  
with us expressing our concerns as their ability  
to maintain the schedule, they have now decided to  
- 126 -  
work the crews 11 hour days. This will help but  
we  
definitely need to have a second shift. They have  
promised to address the problem."  
Can you remember having several meetings with  
Crosstown and expressing concerns as to  
Crosstown's ability to maintain the schedule?  
A
Q
Yes, I do.  
Can you remember anything about who said what at  
those meetings?  
A
Yes, I can. This is, you know, this trade as I've  
mentioned before has been pushed into the critical  
path on this job. He is now performing work that  
he should have done a long time ago. As we talked  
about earlier if we had of got support steel four  
or five or drawings cleared for support steel four  
or five weeks earlier and had we got conveyors  
four or five weeks earlier, we would have finished  
the installation four or five weeks earlier, so  
hence Crosstown would have been on these conveyors  
four or five weeks earlier and they would have had  
an easier time with the labourer situation. The  
problem with pulp mills and grain elevators is  
this differentbreed of people. And they move from  
place to place. They like to come home and spend  
summer months and stuff with their kids and they  
want to be sure they are going to work through the  
winter and as soon as they have had a little play  
time with their kids and families they take off.  
When they see the job is coming to the end they  
like to look for work that's going to keep them  
going for the rest of the year and that's the  
fact. Hence it was becoming very difficult for  
these people to get additional tradesmen from the  
hall, Ray and I checked this out many times and  
there was nobody available in the hall. They were  
offered people on permits, these are unqualified  
people which would have been in my opinion  
disaster even to have on the site. They tried to  
get people from Alberta and the union would not  
allow them to bring them into the area. They were  
in a tough position here.  
305.  
Testifying with respect to the August 17 Daily Report Steel  
said:  
Q
A
Were you satisfied at the time that Crosstown was  
doing all it could to get men?  
Absolutely.  
- 127 -  
Q
A
Could you see that Crosstown and Ricketts-Sewell  
were falling behind at that time?  
No. I don't think that's a fair statement. How  
can you fall behind when you've just been given  
something to do.  
306.  
307.  
308.  
The foregoing illustrates the cumulative effect that the  
late equipment delivery had on CMI's plan of work. The CMI  
component of the project work was significant and it could not be  
carried out until others had performed, specifically with respect  
to the equipment and drawings.  
(b) DEMOLITION  
Marquis testified that CMI had to follow behind the  
demolition being carried out by FCC's subcontractor Johnny Walker  
in most instances, and that "there had been difficulties in terms  
of Johnny Walker demolition finishing its work as quickly as  
scheduled." But Steel testified that these delays were  
overshadowed by equipment delays. This was also true for CMI.  
Steel said that as of March 14, the cleaner deck equipment  
was the only equipment available, so that was where the focus  
occurred to complete demolition. However, he said that FCC did  
not deem the cleaner deck to be on the critical path, so FCC  
believed there was no point in accelerating the demolition. This  
may have been accurate, but there is little doubt that demolition  
delays generated a great deal of attention and concern. The site  
minutes of April 4 at items 2.008.4, 2.008.6 and 2.008.7 record  
that Johnny Walker's crew "are not staying ahead".  
- 128 -  
309.  
While FCC says the demolition delay only resulted in its  
float time of 3 weeks being used up, I am not satisfied that I  
can reject the demolition delays as a causal factor in delaying  
the work on the project. While clearly of much less significance  
than the equipment delivery delays, the demolition delays  
nevertheless had an impact on the progress of the work and to  
that extent I conclude on balance that some responsibility must  
attach to FCC. Based on the records made at the time I conclude  
that the demolition delays likely delayed the progress of CMI's  
work.  
(c) IECO GATES - DESIGN  
310.  
I have earlier dealt with the issue of general drawing  
delays. I now turn to drawing delays respecting the IECO gates.  
IECO was to supply 108 gates to FCC under a materials supply  
contract and hence responsibility for IECO's performance rests  
with FCC. These gates were to be installed in the middle of  
spouting runs, and therefore the spouting below the IECO gates  
could not be installed until the gates were in place.  
311.  
On March 1 CMI delivered to FCC a list of their gate  
availability requirements in order of priority. The site minutes  
of March 2 record questions that IECO directed to FCC and CWMM:  
"2.004 - IECO has requested that info required to clear up  
design/fabrication details be pursued `Right Away'. Also  
the final agreed count & type. IECO are requested to  
- 129 -  
prepare an outline suggesting how to deal with this. CWMM  
advised that they are pursuing on a priority basis."  
312.  
These minutes confirm that it was not only the design  
information that was late; as at March 2, the number and type of  
the IECO gates were unresolved. The design details, however,  
were to be pursued "right away".  
313.  
314.  
The site minutes of March 28 show that item 2.004 - in  
respect of the IECO gates - was still a major concern:  
"2.004.6  
This information was given to IECO in a  
subsequent meeting today."  
The site minutes of March 14 record the progress of CMI's  
attempts to obtain IECO shop drawings, which were needed to  
detail the spouting to be connected to them, since the site  
meeting of February 21 recorded:  
"1.010  
Crosstown have requested shop drawings from IECO.  
...  
1.010.2  
1.010.3  
1.010.4  
It was agreed that they would exchange details as  
available with copies of transmittals to FCC.  
FCC requested confirmation that this was  
occurring.  
FCC reiterated that this is of paramount  
importance - NOW."  
315.  
The level of concern with the IECO schedule performance is  
also reflected by entries in Steel's daily reports:  
- 130 -  
March 16 - "little is being done on our job by IECO."  
March 22 - "this firm (IECO) seems to be waffling on all  
their commitments."  
316.  
On April 25 CMI wrote to FCC stating that they needed IECO  
shop drawings and were unable to detail related spouting without  
them. IECO responded to CMI on April 26. They were waiting for  
CWMM's clarification on 12 non-standard inlets, and would "be  
unable to provide the shop drawings noted in your April 25 letter  
to FCC until this is resolved and new dwgs completed".  
317.  
While FCC and IECO were delayed in part due to CWMM's delay  
in furnishing design information, FCC must bear a share of the  
responsibility for the delay in the provision of the IECO shop  
drawings to CMI.  
(d) SHOP DRAWING REVIEW  
318.  
As discussed earlier, the release of many of the "issued for  
construction" drawings was delayed. As a result of these delays,  
the CMI shop drawing preparation process was delayed, the review  
by CWMM of the shop drawings of many of the equipment suppliers  
was also delayed, and this caused "ripple effect" delays to CMI.  
319.  
Ultimately CMI elected to fabricate without having CWMM  
approve its shop drawings. Whitaker gave discovery evidence as  
follows:  
- 131 -  
Q
A
The fourth complaint that you had identified,  
sir, was the late return of shop drawings.  
Can you explain to me what that complaint was  
all about and what effect that would have on  
FCC's operations?  
Well, the instance I'm thinking of involved  
Crosstown. They had submitted shop drawings  
for spouting and had not had them returned  
after several weeks.  
Why was it important to have the shop  
drawings returned?  
So that fabrication of the spouting could  
proceed.  
Q
A
***  
Q
A
What was the explanation given as to why it  
was taking so long to return the shop  
drawings, if you can recall?  
When the consultants were questioned on it  
they replied that they were waiting for a  
general arrangement drawing to show how these  
detailed drawings fit into the scheme of the  
structure.  
Who was to prepare the general arrangement  
drawing?  
Crosstown. They requested that Crosstown  
provide a general drawing.  
Before you had complained to the consultant  
regarding the late return of shop drawings in  
this instance were you aware that C.W.M.M. or  
Mr. Campbell had requested a general  
arrangement drawing from Crosstown?  
No.  
Did Crosstown indicate to you, sir, that they  
were aware that Mr. Campbell was waiting for  
such a general arrangement drawing?  
No.  
Q
A
Q
A
Q
A
320.  
Campbell explained the cause of the delayed review process  
in the following portion of his evidence in chief:  
Q
A
Did you have an expectation at the time of what  
turn-around time you expected the various people  
to turn the shop drawings around in?  
Oh, it's a difficult question to answer. We, you  
know, I could see one week or two weeks at the  
- 132 -  
most at what always occurs on a job, this job or  
any other job like this is that all the shop  
drawings have to, the award and they go out to the  
general contractor send, you know, his structural  
steel, everything all out, the hoppers and the  
steel for the reclaim, everything they send it all  
out together and all the shop drawings arrive on  
your desk at the same time and it's impractical to  
sort of upgrade youforces just to take care of a  
temporary, you know,peak on the bell as it were,  
but you'd like to see them turned around as fast  
as possible. And if they get anything over two  
weeks or so you start to get a little concerned  
but in the case with FCC -- and this did occur  
about the 1st of April we got scads and scads of  
drawings and we got drawings on the big receiving  
hoppers and on the structural steel for the  
reclaim and what not and so we asked FCC for  
priorities on this stuff and we worked to their  
prior reports and tried to get them south as soon  
as we do.  
321.  
Campbell's difficulty was that in early April CWMM was  
inundated with, in his words, "scads and scads of drawings". The  
necessary time to review these shop drawings dictated some delay  
in approving them and returning them to the parties for  
fabrication.  
322.  
That this was not Campbell's original intention is  
demonstrated by his evidence in cross-examination as follows:  
Q
A
So in your evidence in direct when you mentioned  
the scads and scads of drawings that you received  
on April 1st, including the big receiving hoppers  
and the structural steel, the original plan was  
that you wouldn't be doing those scads and scads  
of drawings at the same time that you were  
reviewing the re-selected equipment suppliers's  
shop drawings, correct?  
I think I can answer yes to that.  
- 133 -  
(e) PRESELECTED EQUIPMENT  
323.  
As documented in the April 25 site minutes delays to the  
project schedule had become a major concern of all project  
participants by that date. Many references can be seen in these  
minutes, particularly at page 2, to meetings with Buhler to  
discuss additional costs, the possibility of allowing some  
spouting to be installed before conveyers were in place, and the  
fact that drawings not yet been received from CWMM. A  
significant comment can be found at paragraph 4.012.10 of these  
minutes: "total schedule still under review due to conveyer  
deliveries."  
324.  
325.  
Steel testified that equipment deliveries were the "driving  
power" behind the delayed project completion.  
Whitaker testified on discovery as follows:  
Q
A
All right. Go ahead.  
The bucket elevator components are  
late two-four and a half months.  
Basement conveyors, one and a half  
months late. South annex drag  
conveyors, four to four and a half  
months late. Drag conveyors in the  
work house were from two to four  
months late, with some items being  
five months late. The items that  
were five months late would affect  
FCC's installation but not  
Crosstown. Receiving bulk ware was  
on time. Reclaim jack-legs were  
two months late. Those are the  
items on the list that would be --  
would have tie-ins to Crosstown's  
spouting and ducting.  
326.  
Spouting was installed in the grain terminal to connect the  
various pieces of equipment. CMI could not commence its work in  
a logical sequence until the equipment at the top of the run had  
- 134 -  
been installed, and could not complete its work until both of the  
pieces of equipment connected by the spouting run had been  
installed in their final locations.  
327.  
In his discovery Skodje described a meeting that was held on  
August 31 at the Cannery Restaurant, attended by FCC, UGG and  
CWMM representatives. He described FCC's views of CMI's problems  
at that time: "They all of a sudden had a large(r) volume of  
work than they had ever been led to anticipate because now we  
have got all the material finally ... all at once."  
(f) BASEMENT DRAG CONVEYORS  
328.  
329.  
A specific example of late design and resultant delays to  
CMI was caused by the change in some of the basement conveyers  
from screw to drag conveyers.  
This was a major change in design. Both the location of the  
conveyors and the nature of the support steel was changed to  
accommodate the new design. The support steel design was  
finalized so late that the actual conveyers had to be assembled  
and hung in their approximate locations on temporary supports to  
await support steel. CMI could not attach spouting to these drag  
conveyers until the conveyors were in their final locations. Tom  
Adams testified as to the problems caused by the delay in  
designing the support steel:  
Q
What do you recall of the placement of machines  
and conveyors on the UGG project, sir?  
- 135 -  
A
On the cleaner floor I believe the machines were  
placed according to the prints. The basement we  
had a major problem with the small drag conveyors.  
In one instance which we couldn't do any field  
measuring or prefab indication on spouts down into  
the drags, excuse me, because of the structural  
steel supports not being designed in time,  
therefore, everything was hanging on either slings  
or on tirfor cables. And until those units are  
tied in solid you are basically wasting hours  
trying to pre-measure them. That was a  
major headache for us in the basement. It took  
much longer I felt than it should have, though the  
steel Should have all been pre-drawn by the engin  
eersb  
efore  
we  
even  
came  
throu  
gh  
the  
door.  
330.  
331.  
Steel described the 18 day delay in receiving a complete  
response to FCC's June 8 FIR 52 seeking support details for the  
basement drags. This also delayed CMI in awaiting installation  
so that they could measure up these conveyors.  
After the basement drag conveyors had been set temporarily  
in their approximate locations, CMI was instructed by FCC to  
proceed with the spouting work in that area. Later, because the  
drag conveyors were not in their position of final placement at  
the time CMI did the spouting work, CMI was required to realign  
the spouting and add 1" to 3" spout fillers, as required. The  
problems with the basement drags was a combination of design  
delays and installation problems. At his discovery Rhodes said:  
- 136 -  
Q
A
How many drag conveyors are there  
in the basement?  
About eight, maybe ten.  
Q
A
Were a lot of them delayed or just a couple?  
No, a lot of them moved. I may  
have missed a few, there's eight or  
ten, something like that.  
Were they all sort of in a state of flux?  
Quite a few of them were.  
Q
A
332.  
333.  
Hoffman testified that "All of them were out of alignment".  
Rhodes gave further evidence on this point as follows:  
Q
A
Do you remember what caused them to be delayed?  
One thing was that they originally were going to  
be screw conveyors and then it was decided to use  
drag conveyors instead and so there were design  
changes. The drives on the drag conveyors weren't  
the same as the screw conveyors and they had to be  
allowed for. So even when they were being  
installed they didn't go in exactly as with the  
same center lines as the screw conveyors.  
Would that fact have essentially again invalidated  
the field measurement in that area as far as  
connection to those pieces of equipment?  
Where the screw conveyor center line  
Q
A
and elevation stayed the same but longitudinally  
moved a couple of inches it wouldn't have mattered  
there, but in some cases the elevation center  
slope, and everything changed a little bit  
that case it invalidated your field  
it  
lines,  
and in  
measurements,  
was the  
fitting  
the  
yes. The biggest problem in that area  
conveyor-to-conveyor spout as far as not  
because a lot of these conveyors carry on to  
next one and to another one and when you started  
moving those around it made a big difference in  
interconnecting spouts.  
Q
A
So it would [not] have been useful for Crosstown  
to have measured or done nothing down there to  
field measure before everything was set?  
As far as I can remember they did the measuring  
after they were set, especially for the  
interconnecting spouting from  
conveyor-to-conveyor.  
- 137 -  
Q
A
Did that delay their ability to  
install the spouting in that area?  
You obviously can't install it  
until you have measure it in that  
case.  
334.  
Hoffman testified as follows:  
Q
All right. And then did you have  
any discussions with Crosstown  
representatives about the  
alignment of the basement drags?  
Yes, I did.  
Who were those discussions with and what were  
those discussions?  
I talked with Tom and Howard and some of their  
foremen, and I tried to make it clear to them  
that the drag conveyors were not straight.  
When you say you tried to make it clear to them,  
do you recall what you said to them?  
Don't put the spouts on. The drag conveyors  
aren't straight.  
Do you recall what response you got?  
We have to do something. FCC says they're  
done.  
Now, is this more than one conversation?  
Yes, it is.  
A
Q
A
Q
A
Q
A
Q
A
335.  
336.  
Hoffman gave further evidence as follows:  
Q
A
Mr. Hoffman, do you recall, with respect to the  
basement drag conveyors, when the alignment with  
the piano wire was actually done?  
I believe it was early in September.  
No claim was submitted and no evidence led by CMI on this  
item because CMI thought at the time that the problems originated  
entirely with Steel's crews. Out of respect for Steel, CMI  
absorbed these costs. However it is nonetheless clear that this  
alignment problem was the responsibility of FCC to the extent  
- 138 -  
that its failure to properly align before spouting was installed  
delayed the progress of CMI's work.  
(g) IECO GATES - DELIVERY  
337.  
338.  
CMI was not only delayed as a result of the delay in design  
information for the 108 IECO gates, but it was also delayed by  
the late delivery of the gates themselves.  
On March 1 CMI delivered to FCC a list of its gate  
requirements, in order of priority. The site minutes of March 2  
record that the design details would be pursued "right away". On  
March 7 CMI wrote to FCC attaching an updated list of the IECO  
gates and setting out the dates on which the gates would be  
required. These dates were not met. Delays to the availability  
of the gates ranged from 2 to 45 days in duration.  
339.  
Popowich testified that the March 7 letter was prepared to  
advise FCC of the dates and sequence in which CMI would require  
the IECO gates in order that CMI could comply with FCC's timelime  
schedule:  
Q
A
What was the purpose of preparing this attached  
document on March 7th?  
It was to give specific dates that the gates were  
required by CMI for IECO to fabricate by.  
Yes. Why did you give dates?  
Q
A
They had a -- there was substantial number of  
gates  
that they had to manufacture. We had given them a  
priority one listing the order followed with  
priority  
2 completing the order or the balance of the  
gates.  
- 139 -  
This letter now starts stipulating which gates are  
required by what particular time and so on and so  
forth down the list.  
Q
A
And how would you use this information regarding  
the  
date it was required in terms of your work?  
Well, we would -- we had scheduled our work  
accordingly or according to the FCC baseline  
schedule  
and --  
The Time-Line schedule?  
The Time-Line schedule. And in order for us to  
meet those dates we required that IECO  
with the gates in this sequence and by  
Q
A
provide us  
these dates.  
Q
Did IECO in fact provide you with the gates in  
that sequence and on those dates?  
No. ...  
A
340.  
At the May 9 site meeting Skodje said the schedule had  
slipped 3 weeks to that time, but that "it was not because of  
Buhler but all of the suppliers, and pointed out particularly  
IECO".  
341.  
On May 25 CMI wrote to FCC informing them that a recently  
received schedule of deliveries for IECO gates was "totally  
unacceptable", and that spouting for these gates was on the job  
site and could not be installed until the gates had arrived.  
Popowich testified:  
Q
Now, on the basis of that, Mr. Popowich, did you  
write a letter to Mr. Marquis on the 25th?  
Yes, I did.  
A
Q
And you say in your first paragraph: "As  
mentioned in the above memo the proposed delivery  
date of June 16th for certain gates" which I won't  
note "is totally unacceptable. Spouting for these  
gates is on job site and cannot be installed until  
- 140 -  
the gates arrive." Stopping there. Was that a  
true statement that spouting was on-site?  
Yes.  
A
Q
Why couldn't the spouting be installed until the  
gates arrived?  
A
Again many of the gates were an integral part of  
the spouting run and without the gate the spouts  
just couldn't be installed.  
You say -- and the next paragraph: "This matter  
has become so serious that it is not only  
Q
preventing us from crewing up but forcing us to  
juggle our present crews around the delivery dates."  
What does crewing up mean, sir?  
A
Well, around that time we were adding about five  
tradesmen a week to get up to peak crew and  
without these gates being there it was affecting our  
crew up position.  
Q
Why were you adding five trades men a week at this  
point in the project, May 25th?  
A
Well, we had, you know, intended to crew up  
earlier on the project, but being because of  
deliv  
ery,  
late  
deliv  
eries  
of  
vario  
us  
piece  
s of  
equip  
ment  
our  
crew  
up  
came  
much  
later  
and  
we  
were  
hopin  
g to  
get  
that  
crew  
up at  
a
fairl  
y
quick  
pays  
- 141 -  
(pace  
) or  
fairl  
y
subst  
antia  
l
pays(  
pace)  
at about May the 25th. I believe we were a  
attempting to add five tradesmen a week until we  
got up to, I believe, around 40 on-site tradesmen.  
Why 40?  
Well, that, I believe at that particular time was  
our projected peak crew.  
Q
A
Q
A
You say forcing us to juggle our present crews  
around the delivery dates. Why would that be?  
Well, again, without gates being there and us  
having the spouts there, then we couldn't install  
certain runs of spouts because there were no  
gates.  
drags  
Q
A
Next paragraph you say "I cannot sympathize with  
IECO's problem any further. It is now costing us  
money and project scheduling delays." What money  
was it costing you?  
Well, again, we are getting back to a matter of,  
you know, stop and go and productivity loss and  
unfortunately there were not other areas of the  
plant that we could go. There were no Buhler  
or no Nord-Sen or Buhler gates. I don't  
believe the  
distributors at that  
particular time were in place, so because of  
that we were being forced to work on the  
cleaner deck and when equipment wasn't there  
we couldn't -- we had no place to juggle the  
crews. There was no place to go.  
342.  
The issue of delivery dates had still not been resolved by  
June 13 when CMI sent a fax to FCC stating that "all spouting for  
garner number 5 is on site, we are still missing gate DVC - 053  
(sic) which is "preventing us from installing spouting.....this  
is getting to be very serious to keep a crew working in upper  
work house."  
- 142 -  
343.  
FCC says that while the IECO gates may have been delivered  
late from its sub-contractor, that late delivery was not an  
effective cause of delay. It says the effect of the late IECO  
gates was overshadowed by the other delay factors such as the  
pre-selected equipment and design drawings. However, based on  
the evidence at the time, I conclude that the late delivery of  
the IECO gates caused CMI's work on the project to be delayed.  
(h) BUHLER DRAG CONVEYORS AND GATES  
344.  
CMI's March 27 schedule shows installation of spouting to  
the Buhler drags in the annexes between April 3 and July 10.  
Skodje confirmed the effect of the late delivered Buhler  
equipment at his discovery as follows:  
Q.  
Did you believe, in May of 1989, that the  
failure to deliver this type of equipment and  
materials - I'm suggesting in particular the  
Buhler drag conveyors - that it was going to  
impact upon your subcontractors like  
Crosstown?  
A.  
Q.  
It was going to impact on us.  
In turn, would that impact upon your  
subcontractors?  
A.  
Quite likely.  
345.  
346.  
Based on the entry in the FCC Daily report of July 18:  
"expecting last truck tomorrow", it appears that the last Buhler  
drag conveyors did not arrive on site until after that date.  
Steel also recorded that CWMM had informed him of the Buhler  
gate tolerance problem. The resulting hold on conveyors B1 and  
- 143 -  
B2, documented in CWMM's July 25 letter to FCC continued for CMI  
until mid-October, when spouting installation was resumed.  
Campbell gave the following evidence with respect to the spouting  
that was attached to those gates in his examination in chief:  
Q
If you turn to July 25th in Exhibit 78 -- I'm  
sorry, 105 B. You should find there a letter from  
yourself to Mr. Marquis. And in that letter you  
say, "with regard to the above conveyors please  
proceed as follows pull the top chains only until  
the gates and gate plates can be rectified. Do  
not pull the bottom chains." Can you explain what  
that means and why you gave that instruction?  
Well, you can appreciate in order to even check  
A
these gate plate tolerances you have to get inside  
the  
conve  
yor  
with  
the  
botto  
m
chain  
pulle  
d it  
would  
be  
almos  
t
impos  
sible  
to  
crawl  
up  
and  
down  
the  
conve  
yor  
as it  
were.  
Q
Did you give any instructions, Mr. Campbell, with  
respect to spouting from these conveyors relating  
to the tolerance problem?  
A
Q
Not do I recall.  
Could spouting be placed on these conveyors when  
the tolerance problem was unresolved?  
A
Well, I guess, my lord, it could be but then you  
- 144 -  
could appreciate the spouting would be attached to  
the gate and if the gate had to be jigged around a  
bit or moved or adjusted or whatever, then you'd be  
dragging the spout with it. It would be an awful  
lot more work.  
347.  
348.  
As described above, CMI was not able to install spouting to  
these conveyors until mid-October.  
(i) LABOUR SHORTAGE  
CMI's December 5, 1988 proposal explained that "Manpower  
will not be a problem at this company, we presently have an  
active waiting list of key site personnel for engagement."  
Steel described conversations with CMI, which illustrated the  
good supply of labour early in the job, as follows:  
A
The electricians didn't feel they had a problem  
and nor did Crosstown.  
Q
A
This was at the beginning of the job?  
Yes. It was going to hit them right at the time  
they told us.  
Q
A
Q
A
Who told you that?  
Randy and Howard Popowich.  
Told you what and when?  
On the first days in the site in the trailer when  
[CMI] were doing their shop drawings that it was a  
per(fect) time for them. They were in between  
and it was just a perfect time for staff, for  
people, the whole ball of wax. That's the  
reason they were so anxious to get on the  
site and why they were the first people  
there, I guess.  
jobs  
349.  
By May 2 FCC had concluded there was no need to crew up to  
their expected peak manpower, nor to institute a second shift,  
since nothing would be gained by so doing. Skodje gave evidence  
- 145 -  
of this in cross-examination referring to the May 2 site minutes  
11.015, as follows:  
Q
Were you aware that as of that time there was  
equipment to be installed and it was sitting  
waiting for installation and Mr. Van Dyke was  
the position with FCC that a second crew  
could be  
taking  
now  
used to start installing equipment which had  
arrived but was not yet being installed?  
Mr. Van Dyke was not the contractor. There was  
some pieces of equipment there, the majority had  
been brought to our attention that it was late and  
therefore there was no need to exercise a second  
shift whatsoever and you'll follow that all the  
equipment went in on a timely basis when it  
A
arrived without a second shift. If the material is  
not there, we can't install it and we're not  
obliged to have forces there waiting.  
350.  
351.  
On May 4 CMI wrote to FCC and listed certain factors that  
were preventing CMI from crewing up. Steel testified that as of  
May 25 CMI "were doing fine at that particular time" in terms of  
manpower.  
But by July the available supply of sheet metal workers had  
diminished. In reference to his July 12 and 21 daily reports,  
Steel testified that it was becoming very difficult at that time  
for CMI to get additional tradesmen from the union hall. He said  
that he and Marquis checked for themselves many times and found  
that "there was nobody available in the hall." CMI formally  
notified FCC of this in its letter of July 21.  
- 146 -  
352.  
CMI was still attempting to crew up in July, whereas its  
original schedule anticipated completion by then. In addition,  
CMI accelerated the work to mitigate earlier and ongoing delays,  
which caused it to need larger crews than originally planned.  
All of this took place at a time when there was a shortage  
of qualified tradesmen, which had not existed in March through  
May when CMI had originally planned to crew up.  
353.  
CMI says that the labour problems they experienced, any  
resultant delays to completion of the project, and their  
increased labour costs of premium time, would not have occurred  
but for delays which were beyond CMI's control. Its costs  
incurred form the basis of its claims to recover overtime  
premiums, extended overheads, and lost productivity.  
354.  
I conclude that CMI was hindered by the shortage of labour  
by the time it increased its forces. But for the project delay,  
CMI would have been able to obtain the necessary manpower had it  
been able to ramp up its forces earlier in the spring as  
originally planned.  
PROJECT DELAY - CWMM AND UGG  
(a) FCC HOURS  
- 147 -  
355.  
In his August 24 letter to Pope identifying the factors  
causing completion past August 31, Campbell stated that FCC had  
failed to meet the manhour projections in its tender. However  
his calculation was done by taking 150 men per day multiplied by  
9 hours per day multiplied by the number of days between March 6,  
1989 and August 24, 1989 (which was 108 days). Campbell  
acknowledged in cross-examination that FCC had no contractual  
obligation to have that manpower on site.  
He also had no  
explanation as to why he did not refer in the letter to the  
reference to additional work and extra time in the site meeting  
minutes or in the memo from Marquis. I accept Steel's evidence  
that FCC staffed at levels that "smoothed out" variations from  
week to week in the available work. I conclude there is no  
evidence to support the contention that FCC understaffing delayed  
the project.  
(b) FCC EXPERTISE  
356.  
UGG and CWMM say that some of the FCC personnel identified  
in its tender did not in fact work on the project. However FCC  
was entitled to substitute personnel and there is no evidence  
that its personnel who worked on this project lacked competence.  
I have earlier made findings with respect to the specific FCC  
acts or omissions that contributed to the project delay.  
However, I do reject the broader contention advanced by the  
defendants that the project was delayed because FCC failed to  
- 148 -  
provide either all of the senior personnel listed in its tender  
or that the senior personnel who were supplied lacked competence.  
(c) CMI EXPERTISE, PERSONNEL AND RESOURCES  
357.  
CWMM and UGG say that CMI's personnel lacked the necessary  
expertise or experience to take on this complex refit project.  
They say the spouting fabrication and installation with its  
complexity and time constraints required more than one  
subcontractor. However, based on the evidence of the CMI  
witnesses, I am satisfied that it had the necessary experience to  
take on this project at the time it tendered. No expert evidence  
was tendered contra.  
(d) CMI - 2 VS 4 PIECE SPOUTING AND WELDED FLANGES  
358.  
CWMM and UGG say that CMI erred in its decision to use the  
more rigid two piece spouting instead of the more flexible four  
piece spouting, as well as in using welded flanges which further  
precluded adjustments in the field at the time of installation.  
However, CMI made it clear to the parties before the tender was  
awarded that it planned to use two piece spouting. Had the CWMM  
construction drawings been more accurate, the two piece would  
have been a more efficient mode.  
359.  
However I do accept the defendant's contention with respect  
to the welded flanges, and find that, in part, the delay CMI  
- 149 -  
experienced in its work was aggravated by its decision to weld  
the flanges prior to installation.  
(e) FIELD MEASUREMENT  
360.  
UGG and CWMM say that despite the clear obligation to field  
measure placed upon CMI under the Prime Contract and the notice  
it was given to comply with this term, CMI chose to fabricate  
without field measurement and that this was a principal cause of  
CMI delay. This requires a consideration as to whether the field  
measurement procedure used by CMI complied with the requirements  
in the prime contract. All parties agree that the failure of  
much of the prefabricated spouting to fit without interference  
when installed delayed CMI.  
361.  
In its argument UGG characterized this as a principal cause  
in these words:  
Despite the clear obligation to field measure which was  
placed upon Crosstown under the Prime Contract, and the  
clear and unequivocal notice he was given that he was  
to comply with this term, Crosstown chose to fabricate  
without field measurement. It submitted shop drawings  
without first having 'determined and verified all field  
dimensions.' In doing so it breached its contract.  
362.  
CWMM echoed this in its submission:  
The main cause of CMI's problems, apart from  
underbidding the job, was its failure to comply with  
Division 15 - Mechanical Systems Section 15B  
-
Spouting. This has been quoted above and was commonly  
referred to in evidence as the field measuring and  
field fit specification. Gordon Adams gave expert  
evidence, adopted by CMI to a large extent in its case,  
- 150 -  
as to the trade practice to be followed in complying  
with that specification, and as to the plan Bisco had  
formulated if this job had been awarded to it. Mr.  
Rhodes gave similar evidence regarding Carter Day's  
plan for compliance with that specification.  
363.  
364.  
CMI and FCC say that CMI was entitled to fabricate from the  
CWMM construction drawings and that the specification required  
that only the last piece of spouting in a run was required to be  
field measured and "cut to suit" or field fitted at installation.  
In my view, the real issue is which party had the obligation  
to verify the design to detect interferences prior to fabrication  
and to rectify discrepancies.  
365.  
The CMI Subcontract provided:  
All work shall be done in a proper and workmanlike  
manner and in accordance with the requirements within  
such documents as drawings, specifications,  
instructions, instructions to bidders, general  
conditions and supplementary general conditions, issued  
before the date of submission of Sub-Contractor bids to  
the Prime Contractor or as modified herein), [sic] and  
this Sub-Contract Agreement including the Sub-Contract  
Conditions (and Appendix" A") forming part hereof.  
(Page 2(a)).  
The provisions of the Prime contract insofar as they are  
applicable are incorporated by reference into this  
Agreement. (Paragraph 15, Appendix A.)  
366.  
Specification 15B.1 of the Prime Contract states:  
"15B.1  
SCOPE  
- 151 -  
15B.1.1  
15B.1.2  
This specification covers the  
general requirements for the  
design, fabrication and  
installation of new spouting.  
The Contractor shall check all  
spouting drawing dimensions in the  
field before fabrication and  
installation of all spouting. Any  
field modifications to spouting  
shall be solely the responsibility  
of the Contractor.  
15B.1.3  
15B.1.4  
Submit shop drawings to the  
Engineer for review prior to  
assembly of gates, elbows and all  
other items except for straight  
spouting.  
Support angles, straps and bracing  
required to adequately position and  
support the spouting shall be  
determined from an examination of  
site and shall be furnished and  
installed by the Contractor.  
15B.1.5  
Under certain circumstances some  
existing spouts, scheduled for  
removal from present systems, may  
be reused. Wherever feasible when  
existing spouting has been removed  
and sizes are compatible with new  
spouting specified, the removed  
spouting has been removed and sizes  
are compatible with new spouting  
specified, the removed spouting may  
be reused. Lined or plain spouting  
may be used for vertical spouts.  
Sloping spouting must have new  
liners installed for re-use.  
Reinstalled spouting will have to  
be repainted."  
367.  
GC34 deals with shop drawings. Two provisions read as  
follows:  
"34.2  
The Contractor shall arrange for the  
preparation of clearly identified shop  
- 152 -  
drawings as called for by the Contract  
Documents or as the Consultant may  
reasonably request.  
34.3  
Prior to the submission to the  
Consultant the Contractor shall review  
all shop drawings. By this review the  
Contractor represents that he has  
determined and verified all field  
measurements ..."  
368.  
The stamp placed upon shop drawings by the Consultant  
states:  
"Reviewed for conformance with general design concept.  
Contractor still responsible for errors or omissions  
and for meeting requirements of contract documents."  
369.  
The following issues must be considered:  
1.  
On a true construction, did 15B.1.2 require the  
last piece of spouting in every run to be field  
measured or field fitted or did it require the  
entire spouting run to be so measured?  
2.  
3.  
If 15B.1.2 is ambiguous and reference to parol  
evidence is required to construe the provision,  
what does that evidence demonstrate?  
In the alternative, if the provision has the  
meaning argued by CWMM and UGG, was CMI's  
- 153 -  
fabrication method a reasonable compliance with  
15B.1.2 in the circumstances?  
1.  
True Construction of 15B.1.2  
370.  
In Edgeworth Construction, McLachlin, J. said at p. 221:  
...In the scheme of things, it makes good practical and  
economic sense to place the responsibility for the  
adequacy of the design on the shoulders of the  
designing engineering firm, assuming reasonable  
reliance and barring disclaimers.  
(emphasis added)  
371.  
On UGG and CWMM's construction of 15B.1.2, the "adequacy of  
the design" of the spouting would be shifted from the shoulders  
of the engineer to the shoulders of CMI. In my view, the section  
is not an "adequate disclaimer" of engineering responsibility in  
respect of the spouting drawings.  
372.  
The principle of construction, taken from B G Checo is that  
the Prime Contract is to be construed as a whole.  
The Prime Contract provides in Section 1.6, as follows:  
"1.6 Supply and Install...  
1.6.2 Spouting and valves and all distribution  
pots, garner bottom, complete, in accordance with  
the drawings and specifications...".  
(emphasis added)  
373.  
18.1 of the Instructions to Bidders provides:  
"18.1  
The Contractor shall be responsible  
for as built drawings for  
- 154 -  
Contractor initiated changes to  
mechanical and structural work and  
shall keep 1 (one) set of prints,  
including revision drawings, in the  
job site office."  
(emphasis added)  
374.  
375.  
In the Form of Tender, paragraph 1 begins:  
"Having carefully examined the tender drawings...the  
undersigned offers to complete the work as set down  
therein'...".  
GC 1.9 provides:  
"1.9 Drawings...furnished by the Consultant are  
and shall remain his property with the  
exception of the signed contract sets  
belonging to each party to this Contract.  
Such documents...are to be used only with  
respect to the Work and are not to used on  
other work. Such documents...are not to  
be... revised in any manner without the  
written authorization of the Consultant."  
(emphasis added)  
GC 25.3 provides:  
376.  
"25.3  
The Contractor shall have the sole  
responsibility for the design,  
...of temporary structural and  
other temporary facilities and the  
design...of construction methods  
required in their use."  
(emphasis added)  
377.  
GC 34.3 provides:  
"34.3 Prior to submission to the  
Consultant the Contractor shall  
review all shop drawings. By this  
review the Contractor represents  
that he has determined and verified  
all field measurements,..."  
- 155 -  
378.  
Pursuant to 15B.1.3 CMI was obligated to "submit shop  
drawings to the Engineer for review prior to assembly of gates,  
elbows and all other items except for straight spouting".  
(emphasis added)  
379.  
380.  
15B which deals with spouting is to be contrasted with 15C  
which deals with dust control ductwork.  
for design in 15C.2.  
15C explicitly provides  
In my view, 15B.1.2 required CMI to field check the  
dimensions of its spouting before installation. The section did  
not require CMI to field check all building measurements before  
fabrication of spouting, nor to ferret out design errors made by  
CWMM in drawing spouting which conflicted with other spouting,  
other pieces of equipment, or parts of the building. CMI was  
responsible for "field modifications" if it did not "check all  
spouting drawing dimensions in the field" before fabrication.  
CMI was responsible for problems that could be corrected in the  
field. There is nothing in 15B.1.2 that contemplated that CMI  
would be liable if additional pieces of spouting had to be  
fabricated in order to allow the spouting to avoid other  
spouting, machinery or parts of the building or to rectify CWMM's  
design errors. A review of construction drawings shows  
measurements related to work points. A particular spouting run  
could contain a number of twists and turns which included elbows,  
specially fabricated pieces and straight sections. If it were  
- 156 -  
the intent of UGG to shift the obligation for verification of the  
validity of the spouting run design to FCC or CMI, the shop  
drawing requirement in 15B.1.3 would have included a requirement  
for shop drawings for straight spouting as well in order to  
determine the length of a particular run. The Prime Contract  
would have required the submission of shop drawings for complete  
spouting runs, rather than elbows or transition pieces.  
381.  
Further support for this construction can be found in GC  
34.3, where the verification of field measurements by FCC was  
restricted to shop drawings and did not include verifying the  
field measurements of CWMM in its design drawings. Since CMI was  
not obliged to submit shop drawings for complete spouting runs,  
FCC was not obligated to verify field measurements for complete  
spouting runs.  
382.  
383.  
If the interpretation argued by UGG and CWMM is correct, the  
specification would have required CMI to check and verify the  
field measurements of CWMM on its construction drawings and  
revise those drawings contrary to GC 1.9.  
In my view, when the other provisions of the Prime Contract  
are considered, the Prime Contract did not oblige CMI (or FCC) to  
field measure the Terminal. There is no language in the Prime  
Contract that shifts the design obligation for the spouting to  
- 157 -  
CMI. 15C, with respect to dust control, specifically imposes the  
design obligation on CMI, 15B does not.  
384.  
On a true construction of 15B.1.2 the specification  
contemplates field measuring or field checking the last piece in  
any run. It does not require field checking the total length of a  
run, nor does it require CMI or Foundation to field measure the  
Terminal to locate design errors made by CWMM in its depiction of  
the location of parts of the building, equipment or spouting runs  
which are designed so as to collide with each other.  
2. Parol Evidence  
385.  
There was considerable evidence led by the parties with  
respect to the meaning of 15B.1.2. The rule on the admissibility  
of subsequent conduct evidence was stated in Canadian National  
Railways v. Canadian Pacific Limited, [1979] 1 W.W.R. 358  
(B.C.C.A.); aff'd [1979] 6 W.W.R. 96 (S.C.C.). Lambert, J.A.  
(Seaton, J.A. concurring) said at page 372 - 373:  
"In Canada the rule with respect to subsequent conduct  
is that, if, after considering the agreement itself,  
including the particular words used in their immediate  
context and in the context of the agreement as a whole,  
there remain two reasonable alternative  
interpretations, then certain additional evidence may  
be both admitted and taken to have legal relevance if  
that additional evidence will help to determine which  
of the two reasonable alternative interpretations is  
the correct one. It certainly makes no difference to  
the law in this respect if the continuing existence of  
two reasonable alternative interpretations after an  
- 158 -  
examination of the agreement as a whole is described as  
doubt or as ambiguity or as uncertainty or as  
difficulty of construction.  
The types of extrinsic evidence that will be admitted,  
if they meet the test of relevance and are not excluded  
by other evidentiary tests, include evidence of the  
facts leading up to the making of the agreement,  
evidence of the circumstances as they exist at the time  
the agreement is made and, in Canada, evidence of  
subsequent conduct of the parties to the agreement.  
However, to say that these types of evidence become  
admissible where two reasonable interpretations exist  
is not to say that the evidence, if tendered, must be  
given weight. In the case of evidence of subsequent  
conduct, the evidence is likely to be most cogent where  
the parties to the agreement are individuals, the acts  
considered are the acts of both parties, the acts can  
relate only to the agreement, the acts are intentional  
and the acts are consistent only with one of the  
alternative interpretations. Where the parties to the  
agreement are corporations and the acts are the acts of  
employees of the corporations, then evidence of  
subsequent conduct is much less likely to carry weight.  
In no case is it necessary that weight be given to  
evidence of subsequent conduct. In some cases it may  
be most misleading to do so, and it is to this danger  
that allusions are made throughout the recent English  
cases, particularly L. Schuler AG v. Wickman Machine  
Tool Sales Ltd., supra, and James Miller & Partners  
Ltd. v. Whitworth Street Estates (Manchester) Ltd.,  
supra. In England the risks have been considered  
sufficiently grave that the possibility of illumination  
from the use of subsequent conduct has been ruled out.  
In Canada they have not, but those risks must be  
carefully assessed in each individual case before  
determining to give weight to subsequent conduct."  
386.  
387.  
At page 377, Craig, J.A. said:  
"The law of Canada does permit subsequent conduct to be  
used as an aid in construing a contract if, but only  
if, the contract is ambiguous in some respect."  
In B.C. Hydro and Power Authority v. Cominco Ltd. (1989), 34  
B.C.L.R. (2d) 60 (C.A.), the Court said at page 74:  
- 159 -  
"The third issue raised by Hydro concerns the  
admissibility of the evidence concerning the subsequent  
conduct of the parties. The law is clear that in  
Canada evidence of post-contractual conduct can be  
considered in the event of an ambiguity in the  
contract."  
388.  
Much of CWMM's evidence concerning the construction of  
15B.1.2 is that the specification obliges CMI to "field measure".  
However, while the evidence of Rhodes and Gordon Adams about the  
meaning of "field measure" on other projects is evidence of  
practice or custom, it is of limited assistance to a construction  
of 15B.1.2, the contractual language in this case. Most  
importantly, it does  
not constitute evidence of the conduct of  
the parties to the Prime Contract in this case.  
389.  
Both Rhodes and Gordon Adams gave evidence that as soon as  
they were awarded the contract they would have begun field  
measurements. However, 15B.1.2 must require checking  
construction drawing dimensions in the field, not the tender  
drawings. CMI was not obligated to build to the tender drawings,  
it was obligated to build to the construction drawings. Tom  
Adams gave evidence which I accept that CMI could not comply with  
Section 15B.1.2 prior to the issuance of the construction  
drawings.  
- 160 -  
390.  
Campbell explained in his discovery why CWMM did not field  
measure but merely used UGG's old drawings as the tender  
drawings:  
"So you check and you use old drawings as much as  
possible and, of course, when this engineering was done  
all the existing equipment was all over the floor. You  
have to appreciate that. Then when all the existing  
equipment is removed you have a nice clean area to work  
with. You can line up your conveyors, measure all your  
distances and check all the dimensions that are on the  
engineering drawings before you put them on shop  
drawings and fabricate. It's the process that takes  
place."  
391.  
Campbell agreed in his examination for discovery:  
"The most accurate way to check spouting drawing  
dimensions in the field before fabrication is to check  
the drawing dimensions after the equipment has been  
installed."  
392.  
393.  
When 15B.1.2 was drafted it was contemplated "the equipment  
would be installed before the spouting drawing dimensions in the  
field were checked".  
On the evidence of Campbell, the construction of 15B.1.2  
proposed by Rhodes and Gordon Adams, if admissible, cannot be  
supported. To field measure as they proposed was impossible. It  
is not necessary to wade through the conflicting evidence at  
trial concerning the definition of field measurement to conclude  
that the definition advanced by CWMM and UGG of field measurement  
could not be what was contemplated by 15B.1.2.  
- 161 -  
394.  
When I consider the admissible evidence, I conclude that the  
meaning to be given to 15B.1.2 is that proposed by, and adopted  
by CMI during the course of construction.  
Hoffman, who  
supervised CMI's work during the Project, said:  
"...when we're talking about field measuring, we  
anticipated field measuring at least one piece in every  
spout run."  
395.  
Van Druten, who reviewed CMI's shop drawings, explained that  
he marked on a CMI shop drawing that the subcontractor should  
field measure a piece because "this was in effect the last piece  
in a run before it hit the diamond head and changed direction".  
Van Druten said that field measure and field check meant the same  
thing. Van Druten said:  
"I told him [John Derhouson] that that's impossible.  
You always have to have one section in the spout that  
you make longer and trim it in the field or measure it  
exactly in field and fabricate it. But you always have  
to have some piece of spout that you use for the final  
connection."  
396.  
397.  
Other witnesses gave the same or similar evidence, as to  
their conduct on the Project, that is field measure means field  
measure the last piece in any particular run.  
I prefer the evidence of Derhouson, Popowich, Tom Adams,  
Hoffman, Van Druten and Campbell on his examination for discovery  
- 162 -  
to the evidence of Campbell at trial. In my view, 15B.1.2 did  
not require CMI to field measure the Terminal.  
3. CMI Reasonably Complied With 15B.1.2  
398.  
Alternatively, if Clause 15B.1.2 is construed to have  
required CMI to field measure beyond the last piece in each  
spouting run, CWMM and UGG, by their conduct, rendered it  
impossible for CMI to comply with 15B.1.2 and CMI's attempted  
compliance was a reasonable response to the equipment delivery  
and drawing delays.  
399.  
As stated above, the provision can only relate to  
construction drawings. As Tom Adams said in cross-examination:  
"We didn't receive the construction drawings until  
well, almost into March, I believe. So unless you have  
your construction drawings you can't assume the tender  
drawings are going to be close. They were for only  
reference for bidding, I believe was the purpose for  
those."  
400.  
The spouting drawings for the Primary Wheat Reclaim area  
were issued for construction on February 17, but of the seven  
drawings, five drawings had holds which were not removed until  
May 30. The spouting drawings for the Primary Wheat Cleaning  
were issued for construction on February 17. One drawing was  
revised on March 30, two drawings had holds removed on May 19.  
Further revisions were made to one drawing on May 31 and on June  
- 163 -  
5. The spouting drawings for the Distribution area were issued  
for construction on February 16. Eight drawings were revised on  
April 24. A further drawing was revised on May 18. Two drawings  
which were revised for the first time on April 24 were revised  
again on May 18 and June 5 respectively. Spouting drawings for  
the Bin Floor were issued for construction for the first time  
between March 13 and March 15. Four drawings were revised on  
April 14. A further drawing was revised on June 28.  
401.  
Construction drawings had holds placed on them which  
affected the spouting relating to the drawing. In the Wheat  
Reclaim area five general arrangement drawings had holds placed  
on them. The holds affected associated spouting and "field  
measuring". In the Primary Wheat Cleaning area one general  
arrangement drawing had a hold placed on it which would affect  
associated spouting and "field measurements". In the Bin Floor  
area, holds were placed on slide gate layouts and structural  
drawings for the conveyors, all of which affected associated  
spouting and "field measurements".  
402.  
Many witnesses gave evidence concerning the difficulty with  
field measuring without the preselected equipment in place.  
Campbell admitted that the most accurate way to check  
measurements in the field is with the equipment in place. Some  
witnesses gave evidence that it was possible to field measure  
without the preselected equipment being in place so long as you  
- 164 -  
had the certified prints for the equipment. Other witnesses went  
so far as to suggest that you could field measure without the  
equipment or the certified prints so long as the engineer  
confirmed that the drawings were accurate. However, one thing is  
clear. Field measurements in respect of spouting which would  
connect to any of the preselected equipment before the equipment  
was delivered and before the certified prints were produced  
required reliance on the engineering drawings and their accuracy.  
403.  
In the circumstances, CMI's decision to rely on the CWMM  
drawings and to field measure the last piece was the best that  
CMI could be expected to do to comply with 15B.1.2. I find that  
the steps CMI took were reasonable. It would have been  
unreasonable to wait until the preselected equipment was  
delivered. It would have been unreasonable to wait until CWMM  
and the equipment suppliers had resolved design issues so that  
certified prints could be issued. It would have been  
unreasonable to fabricate in any way other than the way in which  
CMI did.  
404.  
I conclude that 15B.1.2 did not require CMI or FCC to field  
measure the Terminal. There is no disclaimer in 15B.1.2  
suggesting that it would be unreasonable for CMI to rely on the  
accuracy of CWMM's drawings. On its true construction, 15B.1.2  
required CMI to field measure the last piece in any spouting run  
and made CMI responsible for any field modifications if they did  
- 165 -  
not do so. The parol evidence confirms this construction of  
15B.1.2. Even if the construction of 15B.1.2 is that proposed by  
CWMM and UGG, in the circumstances CMI reasonably complied with  
the provision.  
CONCLUSIONS ON PROJECT DELAY  
405.  
CWMM says that the plaintiffs have failed to provide an  
explanation as to why the work was not done when planned. It puts  
the question: Has FCC proved that it suffered loss or damage? It  
concedes that where damage flows from a breach of contract, but  
quantification cannot be established, then the court must  
nonetheless do the best it can. It says that it was FCC's task  
to show that the matters complained of had an impact on the  
course of the work. It says to prove this FCC should have called  
Whitaker who did the scheduling; it should have called evidence  
of the specific effects of each identified specific breach. If a  
cumulative effect is contended as in this case, FCC should have  
led evidence in specific time periods of the cumulative effects  
of the beaches. While CWMM says this is often done by an expert  
witness, it says FCC could have accomplished this by calling FCC  
witnesses to testify using the FCC schedule and identifying the  
delay factors in a particular time period and the effect of these  
factors on the August 31 completion date.  
- 166 -  
406.  
However in my view FCC has proved that the proximate cause  
of the progress of its work on this project being delayed past  
August 31 was at least in part caused by the acts or omissions of  
UGG and CWMM. The most serious cause of delay was the late  
availability of the preselected equipment. I have earlier  
reviewed the discrepancy between the mid-March date for  
deliveries of the preselected equipment represented to the  
tenderers and the actual knowledge of CWMM and UGG at the time  
the contract was awarded February 10. Equally instructive is the  
difference between the delivery information that FCC had received  
from the equipment suppliers by March 10, one month after it had  
been awarded the contract, and the actual deliveries, which is  
shown in the following table taken from FCC's reply argument:  
Prepurchase  
Equipment  
Supplier  
Delivery Information  
as of  
Actual Delivery  
March 10, 1989  
Carter Day  
Wheat Reclaim  
Equipment  
End March (1  
Screenerator 1  
March)  
Mid April except  
Thresher End April  
Misc. items - Mid May  
Ebco Distributors Motors 19 May/89  
Rest 07 Apr/89  
[Single distributors]  
12 May except Motors.  
[Dual distributor]  
30 May except motors  
Only 1 motor of 6 end  
of July, 3 on 14 Aug,  
14, 2 on 22 Sept  
Shop test with  
temporary motors  
end March  
General Railway  
Retarders  
15 Mar/89 Ready to  
ship awaiting P.O.  
04 May/89  
Transcontinental  
Motors=to Hansen  
15 May to 07 Jun/89,  
New buckets 31 Jul/89  
Bucket Components Shafts= 20 Mar  
Buckets=07 Apr  
Steel=7 Apr  
- 167 -  
Hansen  
20 Mar/89 P.O.  
17 May/89  
01 May/89  
Bucket Elevator  
Drives  
needed prior to  
shipping  
Bisco Conveyors  
Nord-sen Gates  
12 May/89  
30 Apr/89  
13 July to 01 Aug/89  
Repairs by 03 Aug/89  
Buhler Conveyors  
End May End June  
03 Apr/89  
15 May to 20 Jul/89,  
(except 2 insp. gears,  
1 solenoid 14 Aug  
Repairs by 28 Aug  
Concise Car  
Opener  
Track 07 Jun/89  
Opener 01 Aug/89  
Carter-Day  
20 May/89  
30 Apr/89  
08 May/89 Except  
Belting 21 Jun/89  
Reclaim Jack-legs  
Klockner-Moeller  
Motor Control  
Centres  
02 May to 19 Jun/89  
407.  
In my view this clearly illustrates what Campbell was  
speaking of in his August 24 letter to UGG in which he identified  
late equipment deliveries as a factor in the failure to achieve  
substantial performance by August 31. In addition, FCC could not  
complete its contract work until the administration building was  
available. This did not occur until November.  
408.  
Hence I conclude that by reason of the delays in the  
delivery of the preselected equipment and drawings and the  
completion of the administration building, FCC has shown that it  
was delayed past August 31 in achieving substantial performance.  
- 168 -  
Although the other factors I have referred to such as the dock,  
computer programing and extras likely also delayed FCC, I cannot  
conclude that these were other than concurrent. Accordingly I  
find that FCC has established that it was delayed by the acts or  
omissions of CWMM and/or UGG for a period of 3 months past the  
August 31 completion date.  
409.  
The preselected equipment and drawing deliveries also  
delayed CMI in its work. In addition, I have also found that FCC  
contributed to the delays experienced by CMI by reason of the  
demolition, the IECO gates and the basement drag conveyors. When  
assessing the extent to which FCC is entitled to indemnity from  
CWMM and UGG in respect of the CMI claims, it is necessary to  
make a finding of comparative fault between the parties. As  
between CWMM and UGG and FCC, I would apportion the  
responsibility for the delays for which CMI is entitled to  
compensation at 75% CWMM and UGG and 25% FCC.  
410.  
While I have found that CMI's decision to use welded flanges  
delayed it in its work, that decision did not materially delay  
substantial performance.  
FCC NEGLIGENT MISREPRESENTATION CLAIM  
(a) CONTRACTUAL EXCLUSION?  
411.  
The law respecting the negligent misrepresentations of an  
engineer or owner in a contractual setting was recently discussed  
- 169 -  
by the Supreme Court of Canada in BG Checo v. B.C. Hydro, [1993]  
1 S.C.R. 12 and Edgeworth Construction Ltd. v. N.D. Lea &  
Associates Ltd., [1993] 3 S.C.R. 206.  
412.  
In both cases the Supreme Court of Canada held that  
notwithstanding the existence of a contract between a contractor  
and an owner, an action lay in tort against an engineer for its  
conduct in the design stage and during the course of  
construction. The Court held that an engineering firm could owe  
a duty of care in tort to a contractor. In BG Checo the  
contractor was entitled to sue the owner, who was also the  
engineer, both in contract and in tort. In Edgeworth the  
contractor was entitled to sue the engineer in tort, where the  
engineer prepared the tender documents but did not play any part  
in the administration of the contract.  
413.  
In BG Checo at p 26 the majority stated in dealing with the  
principal of concurrency in tort and contract:  
In our view, the general rule emerging from this Court's  
decision in Central Trust Co. v. Rafuse [1986] 2 S.C.R. 147,  
is that where a given wrong prima facie supports an action  
in contract and in tort, the party may sue in either or  
both, except where the contract indicates that the parties  
intended to limit or negative the right to sue in tort.  
This limitation on the general rule of concurrency arises  
because it is always open to parties to limit or waive the  
duties which the common law would impose on them for  
negligence. This principle is of great importance in  
preserving a sphere of individual liberty and commercial  
flexibility. Thus if a person wishes to engage in a  
dangerous sport, the person may stipulate in advance that he  
or she waives any right of action gainst the person who  
operates the sport facility: Dyck v. Manitoba Snow-mobile  
- 170 -  
Association Inc. [1985] 1 S.C.R. 589. Similarly, if two  
business firms agree that a particular risk should lie on a  
party who would not ordinarily bear that risk at common law,  
they may do so. So a plaintiff may sue either in contract  
or in tort, subject to any limit the parties themselves have  
placed on that right by their contract. (Emphasis added).  
The mere fact that the parties have dealt with a matter  
expressly in their contract does not mean that they intended  
to exclude the right to sue in tort. It all depends on how  
they have dealt with it."  
(Emphasis added)  
414.  
415.  
416.  
After B.G. Checo and prior decisions dealing with  
concurrency, it is clear that the right to sue in tort is not  
taken away by the existence of a contract between the parties.  
It is only taken away to the extent that the language of the  
contract limits the scope of the tort duty or waives the right to  
sue in tort.  
In the case at bar, the definition of "contract" in the  
prime contract deals with the exclusion of the right to sue for  
pre-contractual representations. It states, in part:  
"The Contract ... represents the entire agreement  
between the parties. The Contract supersedes all prior  
negotiations, representations or agreements, either  
written or oral, including the bidding documents."  
Is this language sufficient to bar a claim by FCC for the  
negligent representations it says were made by CWMM on UGG's  
behalf?  
- 171 -  
417.  
UGG relies on Carman Const. Co. v. CPR [1982] 136 D.L.R.  
(3rd) 193 (S.C.C.) where the court held (at p.203) that a similar  
clause operated to discharge any duty of care owed by the owner  
to the contractor for pre-contractual representations. However  
in Carmen the disclaimer clause stated:  
"It is hereby declared and agreed by the  
contractor...that the Contractor does not rely upon any  
information given or statement made to him in relation  
to the work by the company."  
418.  
In the case at bar the language does not expressly limit the  
tort duty or waive the right to sue in tort. Given the principle  
in B.G. Checo, a statement that a contract represents the "entire  
agreement" would at the highest only preclude a cause of action  
in breach of contract and not tort. Similarly, the words by  
which the contract is stated to supercede "all prior  
negotiations, representations or agreements" would operate, in my  
view, to bar only a contractual cause of action based on such  
pre- or extra- contractual representations.  
419.  
Unlike Carmen, the contract in this case does not contain  
what might be termed a statement of "non-reliance". In my view  
the case at bar is more analagous with BG Checo where the  
argument that the "disclaimer clauses" in the contract barred a  
tort claim was rejected.  
420.  
The contractual language prepared by UGG is also ambiguous.  
The definition of contract is said to be the entire agreement and  
- 172 -  
it purports to supercede preceding events including the "bidding  
documents". Yet as in BG Checo, the bidding documents in this  
case were incorporated into the prime contract. Two things  
follow from this: first, to the extent that the tender documents  
were so incorporated, FCC is able to advance a breach of contract  
claim for inaccuracies in the tender documents; and second, by  
so incorporating the tender documents, the parties must be taken  
to have attached considerable importance to the accuracy of the  
tender documents and UGG and CWMM must have reasonably expected  
FCC to rely upon the accuracy of statements contained in the  
tender documents.  
421.  
This being the case, it seems to me that the parties  
recognized the importance of the tender documents and any  
exclusion of representations in the tender documents could only  
be accomplished by clear language. There is certainly no "non-  
reliance" language as found in Carmen.  
422.  
The policy reasons for the high threshold that the courts  
will require a contracting party to meet before nullifying a duty  
in tort is found in Edgeworth Construction, where McLachlin, J.  
stated at pp. 214 to 215 as follows:  
"The facts alleged in this case meet this  
test, leaving the contract between the  
contractor and the province to one side. The  
engineers undertook to provide information  
(the tender package) for use by a definable  
- 173 -  
group of persons with whom it did not have  
any contractual relationship. The purpose of  
supplying the information was to allow  
tenderers to prepare a price to be submitted.  
The engineers knew this. The plaintiff  
contractor was one of the tenderers. It  
relied on the information prepared by the  
engineers in preparing its bid. Its reliance  
upon the engineers' work was reasonable. It  
alleges it suffered a loss as a consequence.  
These facts establish a prima facie cause of  
action against the engineering firm."  
423.  
And stated at pp. 220 to 222 as follows:  
"The proposition that the only correct way to  
bring a claim for design defects is by suing  
the owner in contract, who then may claim  
over against the design professional, is  
similarly suspect. The result, in a case  
such as this, would be that the contractor  
would not be able to claim against anyone for  
design defects. Since the province as owner  
has excluded its responsibility for design  
defects under the contract, the contractor  
could not recover against it. So there would  
be no claim over. Moreover, the notion that  
there is only one right way to proceed - in  
contract - undercuts the philosophy expressed  
by this Court in cases such as Central Trust  
Co. v. Rafuse, [1986] 2 S.C.R. 147, and BG  
Checo International Ltd. v. British Columbia  
Hydro and Power Authority, supra that  
plaintiffs may sue concurrently in contract  
and tort, provided the contract does not  
negate the imposition of a duty of care in  
tort.  
One important policy consideration weighs  
against the engineering firm. If the  
engineering firm is correct, then contractors  
bidding on construction contracts will be  
obliged to do their own engineering. In the  
typically short period allowed for the filing  
of tenders - in this case about two weeks -  
the contractor would be obliged, at the very  
least, to conduct a thorough professional  
review of the accuracy of the engineering  
design and information, work which in this  
case took over two years. The task would be  
difficult, if not impossible. Moreover, each  
- 174 -  
tendering contractor would be obliged to hire  
its own engineers and repeat a process  
already undertaken by the owner. The result  
would be that the engineering for the job  
would be done not just once, by the engineers  
hired by the owner, but a number of times.  
This duplication of effort would doubtless be  
reflected in higher bid prices, and  
ultimately a greater cost to the public which  
ultimately bears the cost of road  
construction. From an economic point of  
view, it makes more sense for one engineering  
firm to do the engineering work, which the  
contractors in turn are entitled to rely on,  
absent disclaimers or limitations on the part  
of the firm. In fact, the short tender  
period suggests that in reality this is the  
way the process works; contractors who wish  
to bid have no choice but to rely on the  
design and documents prepared by the  
engineering firm. It is on this basis that  
they submit their bids and on this basis that  
the successful bidder enters into the  
contract. The fact that the contractor may  
agree to exempt the party inviting tenders  
from liability for the design process does  
not suggest that it thereby should be taken  
to have exempted the engineering firm. In  
the scheme of things, it makes good practical  
and economic sense to place the  
responsibility for the adequacy of the design  
on the shoulders of the designing engineering  
firm, assuming reasonable reliance and  
barring disclaimers. The risk of liability  
to compensate third parties for design error  
will be reflected in the cost of the  
engineers' services to the owner inviting  
tenders. But that is a much better result  
than requiring the owner to pay not only the  
engineering firm which it retains, but  
indirectly, the additional engineers which  
all tendering parties would otherwise be  
required to retain."  
(emphasis added)  
424.  
This reasoning is apposite here. The engineering in this  
case started in 1987. It was a large and complex project. It  
would have been impractical if not impossible for tendering  
- 175 -  
contractors to do independant engineering to verify the adequacy  
or completeness of CWMM's work at the time of tender.  
425.  
426.  
UGG says that the contractual language bars a tort claim  
against UGG. It says further that it would be an anomalous  
result if such a bar operated to the benefit of UGG but failed to  
protect CWMM, which was acting as UGG's agent.  
In my view this submission fails to take into account the  
reasoning of the Supreme Court of Canada in Edgeworth and the  
other authorities referred to. These cases stand for the  
proposition that an engineer in appropriate circumstances owes an  
independant duty to a tendering contractor to ensure the accuracy  
of bidding documents intended to be relied on by the contractor.  
If an engineer is to be shielded from such liability by the terms  
of either the bidding documents or a construction contract  
subsequently entered into, clear and unambiguous language must be  
found in the contract. Not only must there be explicit language  
limiting the tort duty or waiving the right to sue in tort  
between the contracting parties, the owner and contractor, but  
that language must also clearly include and extend to the  
engineer. This would give a contractor a clear choice between  
doing its own engineering before bidding or alternatively having  
a clear and unambiguous understanding that any bid would be  
submitted in reliance on the owner's engineering on a non-  
recourse basis. Absent such language in a large project of this  
- 176 -  
nature, I conclude that the parties must have intended tendering  
contractors to rely on the accuracy of the bidding documents. I  
also conclude that the terms of the prime contract do not not bar  
FCC from advancing a claim in negligent misrepresentation against  
either UGG or CWMM based on alleged errors or omissions in the  
bidding documents.  
(b)MISREPRESENTATIONS ALLEGED BY FCC  
427.  
Some basic principles concerning negligent misrepresentation  
were set out in Queen v. Cognos Inc., [1993] 1 S.C.R. 87. At p.  
125 Iacobucci, J. said:  
A duty of care with respect to representations made  
during pre-contractual negotiations is over and above a  
duty to be honest in making those representations. It  
requires not just that the representor be truthful and  
honest in his or her representations. It also requires  
that the representor exercise such reasonable care as  
the circumstances require to ensure that the  
representations made are accurate and not misleading.  
Although the representor's subjective belief in the  
accuracy of the representations and his moral  
blameworthiness, or lack thereof, are highly relevant  
when considering whether or not a misrepresentation was  
fraudulently made, they serve little, if any, purpose  
in an inquiry into negligence. As noted above, the  
applicable standard of care is that of the objective  
reasonable person. The representor's belief in the  
truth of his or her representations is irrelevant to  
that standard of care. The position adopted by the  
Court of Appeal seems to absolve those who make  
negligent  
misrepresentations from liability if they believe that  
their representations are true. Such a position would  
virtually eliminate liability for negligent  
misrepresentation as liability would result only where  
there is actual knowledge that the representation made  
- 177 -  
is not true; the basis of fraudulent  
misrepresentation".  
(emphasis added)  
428.  
FCC contends that the representations made by CWMM and UGG  
in supplying the tender documents were continuing representations  
and that there is nothing in the Prime Contract which negates a  
continuing duty of care. It points to two significant  
representations made in the Letters of Intent which it says were,  
in most cases, inaccurate or misleading. First, the Letters of  
Intent contained references to estimated or projected delivery  
dates of the preselected equipment and it says CWMM and UGG knew  
or ought to have known that the equipment would not be available  
for delivery by that date. Second, the Letters of Intent  
contained representations as to the status of the shop drawings,  
completion of which were essential for the manufacture of the  
equipment. FCC says UGG and CWMM knew or ought to have known  
that these representations were inaccurate or misleading but did  
not advise FCC or take steps to ensure the representations were  
accurate and not misleading.  
429.  
Clearly, FCC relied on the tender documents in tendering the  
Project: after the Prime Contract award on February 10, it made  
written commitments to the major subcontractors CMI and Ricketts-  
Sewell on February 14 and it made commitments to all of the  
preselected equipment suppliers on February 17. Over the next  
months FCC learned that some of the material information  
- 178 -  
contained in the tender documents, particularly the Letters of  
Intent, was inaccurate or misleading.  
430.  
The equipment delivery dates of "approximately mid-March"  
were not accurate. At the time the contract was awarded on  
February 10, the state of equipment design and procurement was  
such that certain of the suppliers were clearly not going to be  
able to deliver equipment by or close to the approximate mid-  
March date. After the contract was awarded, Buhler advised  
Whitaker that its delivery dates would be mid May and mid June.  
This was significant since the work in the bin floor area in  
which the Buhler equipment was to be installed represented  
approximately 30% of the contract work.  
431.  
In his evidence Skodje said that if he had known of the  
status of the Buhler deliveries before tender that: "We'd of  
suggested that the completion commitments be rearranged. This  
didn't coincide with the planned schedule." Skodje said in  
respect of the February 6 Ebco letter, that had he known of the  
Ebco letter before the tender was accepted on February 10: "We'd  
of had to reneg on executing it. This again impacts on the  
schedule completion." In cross-examination Skodje confirmed that  
the following answer from his discovery was true:  
"If between February 17th and March 1st Mr.  
Campbell was cognizant of the fact that we  
weren't going to get components until May, we  
would have changed our whole approach. We  
- 179 -  
would have attempted to mitigate everyone's  
costs with them. Instead we were required to  
forge on full bore".  
432.  
433.  
FCC developed its tender schedule in reliance on the tender  
documents, including the Letters of Intent which reliance was  
reasonable.  
Based on the findings of fact I have made with respect to  
the pre-selected equipment and the Letters of Intent, I conclude  
that the representations made by CWMM and UGG in the Letters of  
Intent were inaccurate or misleading, they were relied on by FCC  
and CMI and that such was known or ought to have been known to  
UGG and CWMM prior to the close of tenders. Accordingly, they  
are liable to FCC for negligent misrepresentation.  
FCC'S BREACH OF CONTRACT CLAIM  
434.  
After the award of the Prime Contract on February 10 FCC  
took steps to mobilize on site. One of the first steps that  
needed to be taken in accordance with the Letters of Intent was  
to send purchase orders to the various preselected equipment  
suppliers and then to arrange for the delivery of the preselected  
equipment. After repeated requests, some, but not all of the  
equipment files in the possession of CWMM were turned over to FCC  
by March 23. Purchase orders were issued to the various  
preselected equipment suppliers commencing March 20 and carrying  
on until April 21. At  
- 180 -  
the site meeting of March 28 FCC advised CWMM and UGG that the  
delay in turning over these files to FCC had affected the  
schedule.  
435.  
After FCC's tender had been accepted by UGG on February 10,  
FCC was advised by some of the preselected equipment suppliers  
that their delivery might be later than that set out in the  
Letters of Intent. That information was passed along to UGG and  
CWMM by way of Whitaker's PrePurchase Vendors Lists. UGG and  
CWMM were also aware of this through their direct dealings with  
the equipment suppliers.  
436.  
Many of the equipment suppliers did not manufacture the  
equipment on or before the delivery dates set out in the Letters  
of Intent. I have found that the late delivery of the equipment  
delayed FCC in the performance of the Work. The Letters of  
Intent were incorporated into the Prime Contract.  
437.  
In BG Checo Iacobucci, J. (Sopinka, J. concurring)  
discussed the effect of incorporation of tender documents into  
the contract in issue in that case and said at p. 81:  
"...Checo bases its claim for negligent  
misrepresentation on the alleged  
representation made in clause 6.01.03 of the  
tender documents. Clause 6.01.03 of the  
tender documents was incorporated verbatim as  
an express term (also numbered 6.01.03) of  
the contract between Hydro and Checo after  
Hydro accepted Checo's tender. On Checo's  
interpretation of clause 6.01.03 of the  
- 181 -  
tender documents, it is a representation as  
to the state of the right-of-way. If clause  
6.01.03 of the tender documents is such a  
representation (and I am of the opinion that  
it is, as I will discuss below), then clause  
6.01.03 of the contract is an express  
warranty as to the state of right-of-way."  
438.  
439.  
Although Iacobucci, J. dissented on the issue of concurrent  
liability in tort and contract, the majority of the court also  
found liability against B.C. Hydro for breach of contract. (BG  
Checo at pp. 21, 25).  
CWMM had responsibility for the design of the preselected  
equipment. The design was changed on a number of occasions for a  
number of equipment suppliers. These design changes delayed the  
manufacture of some of the equipment, most notably, the Nord-Sen  
gates and the Buhler drag conveyors and gates. CWMM sent out its  
employees to the manufacturing plants of most of the equipment  
suppliers to observe the manufacturing and testing of the  
equipment. In some cases the CWMM employees made suggestions to  
or reached agreement with, the equipment suppliers on steps that  
could be taken to expedite the manufacture and availability for  
delivery of the equipment.  
440.  
FCC played no part in the design or manufacture of the  
preselected equipment. Neither CWMM nor UGG expected that the  
design or manufacture would have anything to do with FCC. After  
the design had been completed and the equipment was manufactured,  
FCC arranged for the delivery of the equipment. In arranging for  
- 182 -  
that delivery I conclude that FCC moved as expeditiously as it  
could. I note that FCC did not warrant that the equipment would  
meet the specifications set out in the Prime Contract. FCC's  
assumption of the equipment suppliers' warranty on the equipment  
did not commence until the date of Substantial Performance. Thus  
CWMM or UGG were solely responsible for and controlled the design  
and manufacture, and hence, I conclude the availability for  
delivery of or defects in the preselected equipment prior to that  
date.  
441.  
FCC says the representations which were made in the Letters  
of Intent were carried forward into the Prime Contract becoming  
an express warranty by UGG as to the state of the design,  
manufacture and availability for delivery of the preselected  
equipment. However UGG says that as at the date of tender and up  
to the date of contract award the dates in the letters of intent  
were in the future and were stated as "approximately mid-March".  
However in my view there was, at the time of tender, if not an  
express warranty, at the very least an implied warranty carried  
into the prime contract that the state of the preselected  
equipment as to design and procurement was such that a tendering  
contractor could rely on the fact that the equipment would be  
available on either the dates stipulated or sufficiently soon  
thereafter so that the delivery would not materially delay the  
contractor in the progress of its work. This warranty was  
- 183 -  
breached and FCC is entitled to succeed in its breach of contract  
claim against UGG.  
442.  
On this project FCC was entitled to expect that the work to  
be performed by other UGG contractors would not delay FCC in its  
contract work. On a lump sum tendered project it must be that  
the owner warrants, either expressly or by implication, that the  
contractor will have a clear and unimpeded run at the work. In  
this case I have found that PCL's delay in completing the  
administration building and the late delivery of the preselected  
equipment and drawing delays were responsible for delaying FCC in  
the completion of its contract work until the end of November.  
Such a delay constituted a breach by UGG of the contractual term  
to which I have referred.  
EXTENSION OF CONTRACT TIME  
443.  
In this case neither FCC nor CMI ever formally applied for  
an extension of contract time (with the exception FCC's  
application following the short labour disruption over the July 1  
long weekend). FCC says that CWMM in its capacity as an  
independant arbiter under the contract had a duty to extend the  
contract time in view of the acts or omissions of CWWMM and UGG  
which delayed FCC and CMI in completing their work. CWMM and UGG  
say it was incumbent on the contractors to apply for an extension  
of time, and having failed to do so, they are liable for their  
- 184 -  
respective failures to complete the work so substantial  
performance could have been declared by August 31.  
444.  
I do not accept either submission. This project was marked,  
particularly in its latter stages by some surprising  
communications failures. As the August 31 deadline approached  
and went by, CWMM continued to order extra work which FCC  
accepted, as well as continuing its work under the original  
contract. Yet at no time did FCC ever request an extension of the  
contract time.  
445.  
In my view FCC cannot now argue that the contract time ought  
to have been extended by CWMM in the absence of any request from  
FCC. While FCC is entitled to advance a claim for damages  
flowing from the defendants' negligent misrepresentations or  
contract breaches as outlined above, I cannot conclude that the  
failure of CWMM to extend the contract time, in the absence of a  
specific request from the contractor, was a breach by UGG of the  
contract.  
446.  
In my view of the contractual language in this case, it was  
incumbent upon FCC to initiate a request for a contract extension  
should it be desired. It was not the responsibility of the  
engineer when the project had been apparently delayed, to  
unilaterally issue such a time extension in the absence of a  
specific request from the contractor. In the circumstances of  
- 185 -  
this case, I conclude that even if the delay was caused by the  
owner or engineer, it was nonetheless incumbent on the contractor  
to seek an extension of time. This FCC failed to do. Hence to  
the extent that the delay in achieving substantial performance  
was caused by acts or ommisions of FCC, it comes under a  
liability to UGG for UGG's counterclaim, subject to the notice  
provisions of the contract.  
NOTICE OF CLAIMS BY FCC, CMI AND UGG  
447.  
There are two provisions in the Prime Contract which are  
relevant to the claims of FCC and UGG. There are two mirror  
provisions of the Subcontract which are relevant to the claims of  
CMI. First, written notice of claim must be given by FCC under  
GC 4.4 of the Prime Contract or by CMI under Clause 19 of the  
Subcontract before FCC or CMI is entitled to extensions of time  
under the Prime Contract or Subcontract, respectively. Second,  
written claims of damage caused by the wrongful act or neglect of  
FCC or UGG must be made "within reasonable time after the first  
observance" by FCC or UGG under GC 22.2 of the Prime Contract or  
by CMI under Clause 8 of the Subcontract before FCC, UGG or CMI  
are entitled to claim damages for breach of contract.  
448.  
GC 4.4 and GC 22.2 of the Prime Contract are different  
provisions and are mutually exclusive.  
Clause 19 and Clause 8  
of the Subcontract are different provisions and are mutually  
exclusive. GC 4 and Clause 19 deal with extensions of contract  
- 186 -  
time and reimbursement for delay costs and not the more general  
topic of notice of claims for damage which is dealt with in GC 22  
and Clause 8.  
449.  
In this case FCC characterizes its claim not as a delay  
claim, but rather as a claim for damages for breach of contract  
and/or misrepresentation. CMI also advances a damages claim and  
not a claim for delay or for an extension of the subcontract.  
FCC never gave formal notice of claim under GC4.4 for an  
extension of contract time during the course of the project (with  
the exception of the time lost during the work stoppage on the  
July 1 long weekend). Similarly, CMI never so applied under the  
subcontract. Was such notice a precondition in order for FCC and  
CMI to be able to advance their respective breach of contract  
claims?  
NOTICE FOR EXTENSION OF TIME  
GC 4.1 provides:  
450.  
If the Contractor is delayed in the performance of the  
Work by an act or omission of the Owner, Consultant,  
Other Contractor, or anyone employed or engaged by them  
directly or indirectly, contrary to the provisions of  
the Contract Documents, then the Contract Time shall be  
extended for such reasonable time as the Consultant may  
decide in consultation with the Contractor. The  
Contractor shall be reimbursed by the Owner for  
reasonable costs incurred by the Contractor as the  
result of such delay.  
GC 4.3 provides:  
- 187 -  
If the Contractor is delayed in the performance of the Work  
by labour disputes, strikes, lock-outs (including lock-outs  
decreed or recommended for its members by a recognized  
contractors' association, of which the Contractor is a  
member or to which the Contractor is otherwise bound), ...  
or, without limit to any of the foregoing, by a cause beyond  
the Contractor's control, then the Contract Time shall be  
extended for such reasonable time as the Consultant may  
decide in consultation with the Contractor, but in no case  
shall the extension of time be less than the time lost as  
the result of the event causing the delay, unless such  
shorter extension be agreed to by the Contractor. The  
Contractor shall not be entitled to payment for costs  
incurred as the result of such delays unless such delays are  
the result of actions by the Owner.  
GC 4.4 provides:  
No extension shall be made for delay unless written  
notice of claim is given to the Consultant not later  
than fourteen (14) days after the commencement of  
delay, providing however, than in the case of a  
continuing cause of delay only one notice of claim  
shall be necessary.  
(emphasis added)  
451.  
Clause 19 of the Subcontract provides, inter alia:  
"CLAUSE 19 - DELAYS AND EXTENSION OF TIME  
If the Sub-Contractor is delayed in the  
completion of the work by any act or neglect  
of the Owner, Consultant, Prime Contractor or  
any other Sub-Contractor of the Prime  
Contractor or any employee of any of them or  
by changes ordered in the work, then the time  
of completion shall be extended to compensate  
for such delays unless a longer or shorter  
period of extension is established by mutual  
agreement. If the Sub-Contractor is delayed  
in completion of the work by labour disputes,  
strikes, lock-outs (including lock-outs  
decreed or recommended by a recognized  
contractors' association for its members of  
which the Sub-Contractor is a member), fire,  
unusual delay by common carriers or  
unavoidable casualties or, without limit to  
- 188 -  
any of the foregoing, by any cause of any  
kind whatsoever beyond the Sub-Contractor's  
control, then the time of completion shall be  
foregoing, by any cause of any kind  
whatsoever beyond the Sub-Contractor's  
control, then the time of completion shall be  
extended to compensate for such delay unless  
a longer or shorter period of extension is  
established by mutual agreement.  
No such extension shall be made for delay  
unless written notice of claim is given to  
the Prime Contractor within five (5) working  
days of its commencement provided, however,  
that in the case of a continuing cause of  
delay only one claim shall be necessary...  
(emphasis added)  
452.  
Provisions virtually identical to GC 4 were interpreted by  
Wallace J in Pacific Coast Construction Co. Ltd. et al v. Greater  
Vancouver Regional Hospital District et al (1986), 23 C.L.R. 35  
(B.C.S.C.) At p. 54 he said this:  
"In my view GC 9.6 [4.4] only bars a  
contractor's right to an extension of the  
Contract. It does not refer to the  
obligation of the Hospital District to  
reimburse the contractor for any costs  
incurred by it as a result of the owner-  
caused delay as provided in GC 9.1 [4.1]".  
453.  
On this interpretation a failure to give notice under GC 4.4  
of the Prime Contract or Clause 19 of the Subcontract does not  
bar a claim for damages by FCC or CMI under GC 4.1, provided of  
course the more general time requirements of GC 22 and clause 8  
have been complied with. UGG and CWMM say the plaintiffs'  
failure to give GC 4.1 notice is a bar to the recovery of their  
- 189 -  
delay claims. However, because GC 4 and GC 22 are mutually  
exclusive, even if the plaintiffs failed to give GC 4 notice,  
that is no bar to a claim under GC 22 for "...damage...because of  
any wrongful act or neglect of the other party" provided the  
requisite GC 22 notice was given. That notice is less stringent  
than the 14 day time limit set out in GC 4. Under GC 22 notice  
must be given "within a reasonable time after the first  
observance of such damage".  
454.  
Of course a contractor's failure to give CG 4.1 notice will  
result in it being held to the original completion date and its  
failure to complete on time will, if no application for a time  
extension has been sought and received, expose the contractor to  
liability to the owner for the late completion.  
455.  
Neither CG 4.1 nor CG 22 nor the corresponding subcontract  
provision specify the form of the written notice that must be  
provided. Under GC 4.4 FCC must provide written notice of claim  
of delay not later than 14 days after the commencement of delay.  
In the case of a continuing cause of delay, FCC is only required  
to give written notice of claim of delay once. There is no  
requirement in GC 4.4 for any particular form of notice of claim  
nor any requirement that FCC quantify the duration of or cost of  
delay in the notice of claim.  
- 190 -  
456.  
Because the contracts are silent as to the form of written  
notice to be provided, the issue on notice is not the format that  
any notice might have followed. Rather the issue is: Did FCC  
communicate to CWMM and UGG with sufficient particularity so that  
they either understood or ought to have understood that FCC and  
CMI through FCC were advancing claims for the reimbursement of  
the reasonable costs incurred by them as the result of owner or  
engineer caused delay.  
457.  
However if notice under GC 4.1 was required, in my view the  
documents in this case are replete with evidence of written  
notice being provided by both FCC and CMI with respect to the  
delays they said they were experiencing to their work as the  
project proceeded.  
(a)Incomplete or Changed Design  
458.  
Beginning in late February the number of holds on the bin  
floor drawings began to delay the performance of the Work by CMI.  
From the outset, CWMM and UGG were made aware of the delay caused  
by the holds on the bin floor drawings at site meetings and  
through letters. At the site meeting of February 21 the minutes  
record that FCC sought clarification concerning the release of  
holds on the bin floor drawings which CWMM promised would be  
forthcoming.  
- 191 -  
459.  
At the site meeting of March 2 the minutes record that FCC  
required the release of bin floor drawings which were on hold.  
The minutes also record that FCC was told by CWMM the situation  
was "temporary" and was "currently being dealt with". At the  
site meeting of March 7 the minutes record that the holds on the  
bin floor drawings were becoming critical and the drawings should  
be released. FCC requested that the drawings be released in  
their current state by CWMM.  
460.  
On March 9 Marquis forwarded to CWMM CMI's letter of March 8  
advising that production in Spruce Grove had been halted due to  
the hold on the construction drawings for the bin floor  
conveyors. On Campbell's copy of the letter he wrote "is this  
still a problem?". On March 23 Marquis wrote to Campbell passing  
along CMI's letter of the same date advising that CMI had been  
delayed approximately two weeks due to drawing delays.  
Subsequent minutes continued to highlight design deficiency  
problems.  
461.  
The minutes of the June 15 site meeting record that FCC  
turned over a new schedule that showed construction being  
completed by September 4 and commissioning being completed by  
September 11. The new schedule was conditional upon a number of  
factors including:  
- 192 -  
That all "Holds" on drawings are removed  
prior to June 30, 1989.  
462.  
463.  
In my view this provided clear written notice to CWMM and  
UGG that FCC would not be able to meet the schedule if all holds  
on drawings were not removed prior to June 30.  
The implications of drawing holds were clearly understood by  
UGG and CWMM. In his evidence, Van Dyke confirmed that when a  
hold is placed on a drawing, it means that a contractor is not to  
do the work shown on that drawing. Van Dyke said that one of the  
reasons holds were put on drawings on this Project was because  
part of the drawing was being re-designed. Campbell testified,  
"hold" means "if they're working on it don't do any work on it  
until we transmit that clarification or change to them". At the  
early stages of the Project, there were drawings on hold which  
Van Dyke knew affected CMI's work.  
464.  
All holds on drawings were not removed prior to June 30.  
Furthermore, revisions were made and some new drawings were  
issued for construction for the first time after June 30. At  
least 20 drawings were still on hold after June 30, including  
drawings related to B1 and B2 conveyors and the other drag  
conveyor supports.  
- 193 -  
465.  
At least 23 CWMM Drawings were revised or issued for  
construction for the first time after June 30. Some 126  
Miscellaneous Drawings and Sketches were issued for construction  
for the first time after June 30. At least 159 Electrical  
Drawings and Schematics were revised or issued for construction  
for the first time after June 30.  
466.  
467.  
I conclude that timely notice was given regarding incomplete  
or changed design delays.  
(b)Preselected Equipment  
Whitaker regularly updated and distributed his Prepurchase  
Vendor Lists. These lists gave UGG and CWMM notice of the exact  
stage of any particular aspect of the preselected equipment. As  
noted above, by the middle of May FCC was no longer able to  
rearrange its scheduled performance of the Work to ensure that it  
could be completed by August 31. As soon as Whitaker had  
prepared a new schedule, taking into account the new information  
from Nordsen and Buhler in May, the schedule was given to UGG  
along with a subsequent letter dated May 23 from Skodje providing  
a written notice of claim respecting the preselected equipment.  
468.  
On March 14 the site minutes record:  
4.012  
Construction Schedule.  
-
The overall construction schedule has  
been posted on the meeting room wall.  
- 194 -  
-
An update will be made before month end  
for all to review. A copy will be sent  
to all parties.  
ALL/NOTE  
ALL/NOTE  
Note that all parties are expected and required  
to follow or advise of any concerns.  
469.  
FCC's construction and commissioning schedules from May 23  
on showed completion of the Work after August 31. Not only were  
UGG and CWMM aware of the estimated delay impact at any given  
time, they were aware of the cause of delay alleged by FCC. The  
schedules and other documents given to UGG and CWMM on September  
7 and October 5 demonstrated the overall impact of the delays in  
delivery of the preselected equipment and of defects in the  
equipment. In my view FCC gave timely notice of preselected  
equipment delay.  
(c)Administration Building  
470.  
A critical part of the Work included tie-ins between the  
Terminal and the Administration Building. By the delivery of the  
minutes of the meeting of June 15 and the schedule handed out at  
the time, FCC gave notice to CWMM and UGG that unless the  
Administration Building was available by July 17 the June  
schedule would not be met. The Administration Building was not  
available by July 17. Subsequently, numerous references were  
made in the site minutes to the problems with completing the work  
into the Administration Building. In my view, the June 15  
minutes constituted a written notice of claim in respect of the  
Administration Building.  
- 195 -  
471.  
In my view both Campbell and Van Dyke believed, apparently  
from at least July, that FCC would not meet the completion date  
under the Prime Contract. FCC provided ample written notices to  
CWMM and UGG respecting the causes, according to FCC, of the  
delays.  
472.  
473.  
FCC timely advised CWMM and UGG of the delay problems it was  
encountering, and the fact that FCC attributed those problems to  
UGG and CWMM.  
Campbell recognized what he called a "paper war" developing  
at the end of April. Van Dyke acknowledged that as of July 28 he  
"anticipate[d] extension of contract wanted by FCC due to hold on  
pulling chain and interferences due to BM problems, also expect  
delay of job charges from FCC".  
474.  
In my view FCC complied with CG 4.4 to the extent that it is  
not barred from advancing a claim under the contract for the  
reimbursement of its costs incurred as a result of owner caused  
delay.  
NOTICE OF CLAIM OF DAMAGE  
475.  
Under GC 22.2 both FCC and UGG have an obligation to provide  
a claim in writing to the other party "within a reasonable time"  
of the first observance of such damage caused by the other party.  
- 196 -  
The onus rests with the party bringing a claim to show that the  
party liable has breached the contract, and further to show, that  
written claims have been provided under GC 22.2.  
476.  
GC 22.2, or a similar provision, was considered by the  
British Columbia Court of Appeal in First City Development Corp.  
Ltd. et al v. Stevenson Construction Co. Ltd. (1985), 14 C.L.R.  
250 (B.C.C.A.), leave to appeal refused October 19, 1985, [1985]  
2 S.C.R. xii, and in Doyle Construction Co. v. Carling O'Keefe  
Breweries of Canada Ltd. (1988), 27 B.C.L.R. (2d) 89.  
477.  
In First City Development Corp. the owner sued the  
contractor for damages caused by the delay of the contractor.  
Article 36 of the contract in issue in that case was in material  
respects the same as GC 22.1 and GC 22.2. Hutcheon, J.A. said,  
in respect of Article 36:  
"
I approach the construction of art. 36  
with the proposition established by the  
decided cases in mind: if a party to a  
building contract is to be deprived of a  
cause of action, this is only to be done by  
clear words. Two citations are sufficient.  
In Hancock v. B.W. Brazier (Anerley) Ltd.,  
[1966] 2 All E.R. 901, [1966] 1 W.L.R. 1330  
(C.A.), the English Court of Appeal held that  
an article such as art. 17 was not clear  
enough in meaning to take away from the owner  
the right to sue in respect of structural  
defects which were not discoverable within  
six months.  
The Ontario Court of Appeal, in Simpsons Ltd.  
v. Pigott Construction Co. (1973), 1 O.R.  
(2d) 257, 40 D.L.R. (3d) 47 (C.A.), held that  
- 197 -  
neither art. 17 nor art. 32 were sufficiently  
clear to excuse the builder from liability in  
an action brought within the statutory  
limitation period. Article 17 provided for  
corrections after final payment and art. 32  
resembled art. 36 in the present case except  
that claims were to be made not later than  
the time of final payment.  
The only limitation clearly stated in art. 36  
is that by the words "not later than the time  
of final certificate". I then turn to art.  
27 for the meaning of "the time of final  
certificate". For the owner the time is the  
issue of the final certificate; for the  
contractor the time is the acceptance of the  
final certificate. When that time has  
passed, all known claims are barred save  
those excluded by art. 27. There is a  
responsibility placed upon each party by art.  
36 to give notice of a claim in writing  
within a reasonable time but, in my opinion,  
the failure to do so does not create a bar to  
the making of a claim. The clear words that  
are required to create that bar are not  
present in art. 36.  
The injunction to the parties in art. 36 is  
of a kind similar to that to the contractor  
in art. A-6: "The Contractor shall...make  
such investigations as to the supply of  
materials...as may be reasonably required...  
and shall make such estimates as may be  
reasonably required...."  
The respondents filed a cross-appeal from the  
paragraph of the formal order appealed from  
adjudging that art. 36 applies to claims for  
pure economic loss arising from breach of  
contract by the contractor. Since I consider  
that art. 36 by itself, and in so far as it  
requires written notice to be given within a  
reasonable time, is not a clause of time  
limitation for the bringing of an action, I  
do not find it necessary to examine the  
merits of the cross-appeal.  
478.  
In First City, the trial Judge had found that:  
- 198 -  
"...the defendant was well aware that  
completion of the contract was delayed. It  
had every reason to believe that a claim  
would be advanced....  
The defendant does not say that its officers  
were mislead. It does not say either that  
the defendant acted to its detriment on any  
representation or indeed expectation  
initiated by the plaintiff that no claim  
would be made. Had that been the case, the  
defendant might have been able to raise the  
defence of estoppel.  
I say that the timing of the claim of the  
plaintiffs is reasonable because the delay,  
if any, and the timing thereof has not  
prejudiced the defendant in the least".  
First City Development Corporation Ltd. et al. v. Stevenson  
Construction Co. Ltd. (1984), 8 C.L.R. 125 (B.C.S.C.), at p. 127.  
479.  
480.  
The First City case was considered by the British Columbia  
Court of Appeal in Doyle when construing contractual provisions  
virtually identical to GC 22 of the Prime Contract.  
Craig, J.A. focused on the issue of prejudice raised in  
First City Developments and said at p. 103:  
"...I think that the judgment of this court  
in the First City case can not justify the  
contractor ignoring the express conditions of  
G.C. 22.2. The meaning of G.C. 22.2 is  
obvious and comes patently within the "clear  
words" principle.  
To hold that a contractor is not barred from  
presenting a claim unless he gives notice of  
the claim within a reasonable time would  
render G.C. 22.1 and G.C. 22.2 nugatory. The  
trial judge was correct in relying on the  
- 199 -  
extract from Hudson to which I have referred  
in holding that reasonable notice in the  
circumstances was a condition precedent to a  
claim by the plaintiff.  
(emphasis added)  
481.  
482.  
The focus for the Court of Appeal consideration in Doyle was  
the exception created in First City Development. That is, was  
there prejudice by the failure to give notice.  
Whether or not a party has suffered any prejudice is  
determined in light of the purpose for requiring notice.  
Locke, J.A. in Doyle stated at p. 111,  
What is a reasonable time must surely be  
determined by reference to all relevant  
circumstances... The provision for notice is  
useless unless it gives some particulars to  
the owner as to what the complaint is. It  
must surely also be given in enough time so  
that he may take the guarding measures  
pointed out in Corpex if he so desires. An  
early notice also leaves the owner free to  
negotiate either under this provision or  
under any other provision of the contract  
which may assist in the resolution of the  
problem. From the standpoint of the  
contractor, he may not, of course, know  
precisely what the monetary effect of  
accumulation of delays might bring about, but  
an early notification of his concern will  
also enable him to get himself into a  
negotiating position as to the method of  
solution of the problem, and to raise his  
concerns under the contract...  
The purpose of the notice is to give the  
owner an opportunity of considering his  
position and perhaps taking corrective  
- 200 -  
measures, and he is prejudiced by not being  
able to do it".  
483.  
Craig, J.A., (Macdonald, J.A. concurring) at p. 96, adopted  
the statement of the law set out in Hudson's:  
"Building and engineering contracts  
frequently contain provisions requiring a  
contractor to give notice within a reasonable  
time of events occurring which he considers  
may entitle him to claim additional payment  
under the terms of the contract. Since the  
purpose of such provisions is to enable the  
employer to consider the position and its  
financial consequences, and by cancelling or  
authorizing a variation, for example, he may  
be in a position to reduce his possible  
financial commitment if the claim is  
justified, and since special attention to  
contemporary records may be essential either  
to refute or regulate the amount of the claim  
with precision, there is no doubt that in  
most cases the court will be ready to  
interpret these obligations of the contractor  
as conditions precedent to a claim and  
failure to give the notice may deprive the  
contractor of all remedy".  
(emphasis added)  
484.  
Doyle and First City Development Corp. demonstrate that  
the form of notice is not important. What is important is the  
substance of the notice. Whether or not the substance of the  
notice is sufficient must be determined in light of the purpose  
for giving notice. Proof of notice is a pre-condition to  
recovery by FCC or CMI of their claims or by UGG of its  
counterclaim. As Macdonald, J.A. said in Doyle at p.105:  
- 201 -  
"For the reasons given by Mr. Justice Craig,  
I hold that failure to give reasonable notice  
in the circumstances of this case was a  
condition precedent to the claim of the  
contractor".  
(emphasis added)  
485.  
In W.A. Stevenson Construction (Western) Limited v. Metro  
Canada Limited (1987), 27 C.L.R. 113 (B.C.S.C.), Locke, J.,  
examined what the purpose of notice was in that case. He said at  
p. 182:  
A reading of the minutes is very revealing:  
they were obviously regarded by everyone as a  
method of formally communicating their  
concerns to the other party. Reading them is  
rather discouraging: in almost parrot-like  
fashion entries, the contractor's concerns  
regarding access to the side, structures,  
utilities both under and above ground, and  
topics such as strikes or weather, appear  
with monotonous regularity seemingly from  
beginning to end...On consideration of all  
the minutes and the letters, I find that all  
claims in this action are covered.  
486.  
487.  
Interestingly, Locke, J. considered the trial judgment in  
Doyle in coming to this conclusion. He later sat on the panel  
which dismissed the appeal from the trial judgment in Doyle.  
In Doyle, Locke, J.A. considered whether the trial judge's  
conclusion that site meeting minutes did not provide adequate  
notice of a claim for damages was palpably wrong. He began by  
discussing the purpose of notice. He then discussed whether the  
- 202 -  
particular site meeting minutes in that case disclosed enough  
information to satisfy the purpose of giving notice. On the  
particular facts, Locke, J.A. said:  
"
The grumblings of this contractor,  
recorded though they may be in site minutes,  
display no intention to claim until December  
1983. Even then, no claim was actually  
advanced, but intent was indicated. But no  
details were given: an owner would be hard  
put to know exactly what it is to meet, and  
hence what it is to do".  
In this case, on each item for which FCC alleges delay, CWMM and  
UGG knew exactly what they had to meet and hence what to do.  
488.  
Doyle is authority for the proposition that the form of  
notice is not governing. Rather, the issue is whether the notice  
contains enough information to satisfy the purpose test. In my  
view, FCC did provide to UGG sufficient notice within a  
reasonable time to satisfy the purpose test and it complied with  
GC 22..  
489.  
On May 23 FCC advised UGG and CWMM of the delay impact of  
the Buhler deliveries, and UGG took corrective action based on  
that advice. As he said in cross-examination, Campbell  
understood from this May 23 letter that FCC was saying if it  
incurred additional construction and overhead costs because of  
the matters set out in the letter, FCC was going to claim them.  
- 203 -  
490.  
On June 15 FCC advised UGG and CWMM of problems that the  
delay in the delivery of the Buhler equipment and the Nord-Sen  
equipment were causing, gave notice of the problems that the  
holds on the drawings were causing, gave notice of the problems  
that the delay in the completion of the Administration Building  
were causing, and gave notice of the problem respecting the  
installation of the dock progressors.  
491.  
On July 7 notice by letter was given to UGG and CWMM  
respecting a labour shut-down due to the dock progressors. This  
was in addition to earlier notices provided in the minutes of  
April 25 meeting and May 16 minutes.  
492.  
493.  
On August 10 a detailed list of areas holding up Ricketts-  
Sewell in the performance of its work was provided to UGG and  
CWMM.  
At the August 31 site meeting further explicit details were  
given to UGG and CWMM concerning the delay to FCC and its causes.  
On September 7 FCC, at a meeting with UGG and CWMM, explained in  
some detail the anticipated costs to UGG of finishing late and  
provided a cost/benefit analysis to UGG by outlining the benefits  
to UGG if UGG paid for the acceleration of the work.  
494.  
On September 14 FCC wrote to CWMM and provided further  
analysis as follows:  
- 204 -  
"Further to the site meeting of September 7, 1989,  
attached is a copy of the material that was tabled for  
discussion at that time. It is meant to illustrate the  
schedule slippage between the anticipated delivery date  
of major components and the actual date that the  
components were received. It also illustrates the  
compounded cost effects that the various scenarios  
would have on the overall project.  
These costs represent the effect of acceleration  
through August and September and do not reflect cost  
impacts as a result of delays.  
As expressed we are looking for cost reimbursement for  
the additional costs that are the result of  
accelerating the program in order to meet the earliest  
possible completion date.  
We trust that you find the attached in order and that  
we may resolve this issue as expeditiously as  
possible."  
495.  
Discussions concerning FCC and CMI's delay and impact cost  
claims continued throughout the fall of 1989. On October 5 more  
detail was provided to UGG and CWMM concerning the causes of  
delay to FCC and the potential extension of time required. On  
November 21 FCC delivered to UGG and CWMM, CMI's delay claim and  
FCC's estimated delay quantum to the end of November.  
496.  
Perhaps even more importantly, FCC delivered meeting  
minutes, construction and commissioning schedules and updated  
Prepurchase Vendor lists to UGG and CWMM on a regular basis,  
keeping both CWMM and UGG completely apprised of the status of  
the work, prospective completion dates including commissioning,  
and causes of delay.  
- 205 -  
497.  
The primary cause for the initial delay was the delay in the  
design and manufacture of the preselected equipment which  
prevented FCC from arranging timely delivery of the equipment.  
CWMM and UGG were fully aware of the status of the design and the  
manufacture of that equipment and understood the effect of the  
delay in delivery on the installation of the equipment.  
498.  
In my view FCC provided written notice compliant with the  
contract and it is accordingly entitled to recover its provable  
damages representing its reasonable costs incurred as the result  
of the delays as provided in GC 22.  
NOTICE OF DELAY BY CMI  
499.  
Equipment delays were identified as a concern by CMI at an  
early stage in the project. On February 27 Popowich wrote to  
Marquis enclosing a "points list" pertaining to FCC's tender  
schedule. The points list notes that the "present schedule" for  
installation of the distributors would not allow CMI sufficient  
time to fabricate and install spouting before July 31, 1989.  
500.  
Several further examples of notices of delay given by CMI to  
FCC, UGG and CWMM have been referred to above, under the topics  
of specific delays. Three examples are repeated below:  
- 206 -  
501.  
502.  
503.  
504.  
On March 8 and March 12, CMI notified FCC that holds that  
had been placed on design information had begun to delay CMI's  
progress.  
On March 23 CMI again wrote to FCC, notifying FCC that its  
fabrication of bin floor spouting had been delayed by two weeks  
due to delays in the release of design information.  
CMI also issued 91 RFC's, many of which, such as RFC 24 and  
RFC 89 for example, identified potential or actual delays,  
generally due to the lack of design information.  
In my view, CMI's notices of delay to FCC coupled with the  
delivery of its formal claim on November 11 fulfilled the  
requirements of Clause 19 its Subcontract. The notices were  
timely given in writing and were specific to the particular  
causes of delay being encountered. FCC passed on these notices  
to CWMM and UGG.  
NOTICE BY UGG OF ITS COUNTERCLAIM  
505.  
UGG gave written notice of its counterclaim January 30,  
1990. As MacKay and Van Dyke testified, this letter was the  
first "formal notice of a claim for damages that was given to  
FCC".  
- 207 -  
506.  
507.  
However as early as September 13, 1989, the defendants were  
considering not only the CMI overtime claims forwarded to them by  
FCC but also the economic loss that UGG was going to suffer  
because of the later than planned completion.  
On September 13 a meeting was held attended by  
representatives of CWMM and UGG to discuss the FCC and CMI  
claims. MacKay, Choukalos, Campbell, Van Dyke and Pope attended  
the meeting. Prior to the meeting Campbell prepared a document  
as a "response to 'proposed' claim against United Grain Growers  
for delay in completion". The note contained three options which  
were discussed at the meeting. The first option was to listen to  
FCC and advise FCC that UGG would have to consider the facts and  
adjourn and meet again. The second option was to listen to FCC's  
proposal and discuss with them whether there was a real impact of  
late delivery. The third option was to listen to FCC and to tell  
them that they were late because of their own problems. The  
notes recorded:  
"At present, FCC have a reprieve due to the  
dock work progress. On the given day that  
the dock is ready and UGG is able to ship -  
UGG will pursue liquidated damages charges  
against FCC".  
508.  
The reference was to the dock work being done by JJM, which  
was not completed to a point where shipping could take place  
until the end of January, 1990.  
- 208 -  
509.  
At the beginning of his notes of the same meeting, Van Dyke  
wrote:  
"Discuss response to FCC re contract  
schedules. What UGG position - see no  
possibility for September 30 completion -  
dubious Oct 31 want to know UGG's  
position/approach- discussed options (PJC and  
info)."  
The options referred to in Van Dyke's memo were those contained  
in the typed notes prepared by Campbell.  
510.  
At the September 13 meeting Choukalos asked if there was a  
strategy or policy and MacKay replied that the number one policy  
was to get the project done. He said "will admit some  
prepurchasers late, but can't feel lateness impacts on CMI and R  
& S". MacKay testified that he had not done any study on the  
impact at this time, nor had anyone else. At the same meeting  
Campbell suggested obtaining a legal opinion, apparently with  
respect to FCC's contract obligations concerning the letters of  
intent. One complainant concerning FCC and its conduct during  
the course of the meeting was Choukalos, who had very little to  
do with the Project on a day to day basis and who attended only  
one site meeting. However Choukalos nonetheless advised the  
attendees at the meeting, correctly in my view, that they "must  
tell Skodje he has not fullfilled his obligations and has not met  
his obligations and has misled us with his schedules". Choukalos  
gave evidence that he felt a letter should be sent to FCC to put  
- 209 -  
the owners opinion of where they stood in writing, so all parties  
would know.  
511.  
On September 19 during a meeting entitled "discussion at  
Bill's Wed aft." Van Dyke noted "owner to write serious letter to  
FCC"... "Contractually - normally should indicate lack of  
progress and how FCC intends to bring job back on schedule". Van  
Dyke also noted, "Skodje not feeling uncomfortable - no one  
'swing' at him - need advice as to how firm UGG position is". In  
my view, these were references to the strategy adopted by UGG at  
the time not to tell FCC its real opinion concerning the delay  
and not to give any notice under the Prime Contract. Van Dyke  
also wrote  
"owner late delivery  
-Samples and changes to sampler system was  
completely designed  
-Drag conveyor section designs were late..."  
512.  
On a number of occasions at that meeting Choukalos and  
Campbell suggested that UGG should get legal advice as to their  
position concerning the FCC and CMI claims. The notes record a  
discussion of the various options set out by Campbell and in  
particular "question as to what we do tomorrow give example or  
stall or what". At the conclusion of the meeting after Campbell  
suggested a combination of option 1 and option 3, MacKay set out  
the "strategy of 'no response'". On the evidence that strategy  
of no response was adopted and continued until January 31, 1990,  
- 210 -  
one month after CWMM had declared substantial performance and the  
time when the work on the dock was completed and when UGG was in  
a position to start shipping.  
513.  
On October 5 a meeting took place at UGG's office attended  
by MacKay, Pope, Van Dyke, Campbell, Nicholls, Skodje, Marquis  
and Whitaker. At that meeting documents were presented to UGG  
and discussed including Whitaker's final Pre-Purchase Vendors  
List, the tender schedule, and a separate sheet for each of the  
prepurchased equipment suppliers showing tender delivery versus  
actual delivery. A schedule comparison between the tender  
schedule and the equipment delivery impact, was also provided,  
based on 45 hours per week per shift and based on 37½ hours per  
week per shift (i.e. if no more premium time was worked). The  
schedule showed actual installation of mechanical equipment  
extending to September 11, electrical installation projected to  
extend to the end of December, spouting installation projected to  
extend to the end of October, dust control projected to extend to  
the end of November, pneumatics installation and hydraulics  
projected to extend to the end of November, with testing start-up  
and commissioning extending to the end of December.  
514.  
There are two sets of notes of the meeting of October 5. Van  
Dyke made notes at the time and MacKay made notes at a later  
date. In respect of any differences between the notes, Van  
Dyke's are to be preferred, since he made them at the time.  
- 211 -  
MacKay apparently made his notes sometime in January, 1990 or  
later. At that meeting MacKay confirmed, as Van Dyke noted,  
"Same as we have discussed in past Ted - just want project done.  
Have never intended to jeopardize project so haven't gone to  
finger pointing - so no letter - jeopardizes project". Just  
before MacKay said this Pope said "UGG's basic stance is we  
recognize project simply as LATE".  
515.  
Van Dyke's notes record Skodje advising those attending that  
FCC "would like to demonstrate to you how and why time was lost  
and circumstances that brought it about". Whitaker then gave out  
a package of "back up documents". What followed was a discussion  
concerning the impact of the delivery of the equipment. In that  
discussion Skodje pointed out that everything appeared to come  
later than portrayed in the Letters of Intent. Van Dyke records  
him saying "If knew this why was this not portrayed in tender  
call. All expected people to deliver on time. No vehicle in L  
of Is to permit FCC to...commitment UGG made on 'unknown  
contractor' - let him believe that dates would be adhered to".  
This was a reference to FCC's reliance on the delivery dates in  
the Letters of Intent in bidding the project.  
516.  
There was then a discussion about the shop drawing problems  
and CMI's reaction to the late equipment deliveries followed by a  
discussion about extras. A discussion followed about what would  
happen with respect to the CMI overtime program and a discussion  
- 212 -  
of the three letters Skodje had received from Popowich for  
overtime. In discussing CMI, Pope is noted as saying "UGG's  
situation still is we're not convinced - If Randy stops working  
O.T. then UGG will react".  
517.  
There was then a discussion about the promise made by MacKay  
to Skodje at the Cannery meeting of August 31 (which Skodje  
passed along to Popowich) where MacKay said that he would see  
that CMI did not get hurt. Then there was a discussion about the  
impact on CMI and MacKay "asked again if all documents given out  
re late deliveries have a total impact on CMI". Campbell then  
referred to the dates he thought the workhouse and north annex  
drags were delivered. The dates he mentioned were not correct.  
Skodje said to all at the meeting: "read L of I - doesn't say  
expedite". This was a reference to FCC's consistent position  
throughout the course of the Project that nothing in the Prime  
Contract required FCC to expedite the delivery of the preselected  
equipment and that expediting the delivery of the preselected  
equipment was the responsibility of UGG or CWMM.  
518.  
Then a caucus took place where the FCC representatives met  
separately from CWMM and UGG representatives. After that, the  
meeting resumed with Skodje advising "need to do something with  
Randy". Skodje suggested that CMI be given $300,000.00 by UGG,  
one half at that time and one half when CMI was finished on  
October 23, 1989. Skodje said about CMI: "figure if works O.T.  
- 213 -  
will be 20,000 hours behind". Van Dyke then "asked how others  
hours have been".  
519.  
There was further discussion about drawings and extras and  
then Pope said "no deep thought as to what Randy deserves. Not  
convinced UGG has part to play in Randy's problem. Makes it hard  
for us to understand why we have to play a part". Pope did not  
deny any responsibility on the part of UGG but appears to have  
taken the position that if FCC convinced him that UGG should pay  
then UGG would. MacKay confirmed in his evidence there was no  
resolution at this meeting. Nicholls then noted that FCC did not  
feel obligated to pay. Pope wanted to know why. Nicholls said it  
was not up to FCC, that UGG should talk to Campbell, saying to  
Campbell "maybe you have some responsibility why he's [CMI]  
late". Campbell's response was that FCC "had control of what  
Randy did on site".  
520.  
Nicholls then observed "does not feel that FCC is  
responsible for lateness of CMI". Skodje observed "CMI has  
contributed to his demise". Pope "expressed concern re  
management of project". MacKay then said "goal is to get project  
done - anticipate some "bloodletting" - not UGG's intention".  
At this point the meeting ended.  
521.  
At no point during the October 5 meeting did UGG give any  
indication of an intention to advance a claim against FCC.  
- 214 -  
Another meeting was held amongst the same participants October 6  
to which Popowich was invited. Again, at this meeting, UGG gave  
no indication of an intent to claim against FCC or CMI.  
522.  
On December 6 Choukalos, Campbell, MacKay and Van Dyke met  
to discuss claims submitted by FCC and CMI. MacKay asked  
Choukalos what he thought and Choukalos said "start claiming for  
damages due to delays". He suggested that they should get legal  
advice and "start fighting back". Choukalos also said "you  
haven't fought back...time to let them know not going to take it  
anymore". Campbell said "put in counterclaim for liquidated  
damages...then will sit up and take notice". He also "gave brief  
scenario of present situation with CMI/FCC - you have to decide  
if going to pursue it...if start...then go to win the battle".  
Van Dyke "explained discussion re pre-negotiation with  
FCC...discussed cards 32/16 cables for Modicon". Choukalos  
suggested "respond to FCC letter only to acknowledge receipt  
speak to lawyer to get advice before respond to Skodje".  
Campbell said "need to respond to every single requirement - only  
document that counts is the contract + specifications - legal  
document that FCC signed says completion on August 31/89". Van  
Dyke then explained the situation of VPC and JJM, which related  
to the fact that the dock wasn't ready for shipping at that time.  
MacKay then asked about the status of the project and asked "when  
meet Lawyer...Thursday/Friday a.m.". MacKay then instructed  
- 215 -  
Campbell to "start responding to FCC/CMI presentation". However,  
no such response followed.  
523.  
On December 11 Skodje wrote to Pope, with a copy to MacKay  
and Campbell, stating as follows:  
"It has been in excess of two weeks since we  
submitted the Crosstown Metal Industries  
claim and the Foundation Company of Canada  
Limited claim and we have yet to receive any  
indication of a speedy reply. We would  
hereby request that a meeting be convened at  
your earliest convenience in order that we  
may discuss in detail your position regarding  
this claim. Should you not be desirous of  
such a meeting, we would request, as per the  
terms of the Contract, that you inform us of  
your nominee in order that we may pursue  
resolution of this outstanding claim through  
arbitration".  
No nominee was ever put forward by UGG.  
524.  
Also on December 14 Pope wrote to Skodje, with copies of the  
letter to MacKay, Campbell and Van Dyke, and said:  
"We are in receipt of your letter dated  
December 11, 1989 requesting a meeting to  
address the issue of claim submitted by  
Foundation of Canada Ltd. and Crosstown Metal  
Industries. This letter is to inform you  
that United Grain Growers Limited is  
presently reviewing the content of this  
claim, in depth, with a view to establishing  
our response and position. A meeting to  
further discuss this claim will be convened  
in due course".  
- 216 -  
525.  
526.  
On the evidence, UGG was in fact not reviewing the claim in  
depth and there was no meeting to further discuss the claim.  
This letter appears to have been written as part of MacKay's  
strategy of "no response", which was developed in September.  
UGG finally gave notice on January 31, 1990 when Pope wrote  
to Skodje in response to the claims of FCC and CMI. Pope advised  
in the letter "we have no alternative but to advise you that the  
claim cannot be considered except to the extent that we are  
prepared to complete the negotiations with respect to any and all  
outstanding Change Orders". The letter went on to say:  
"As you are aware, your contract with us was  
to be substantially completed by August 31,  
1989. Substantial completion was not  
documented until December 29, 1989. No claim  
has been made to extend the contract period.  
The fact that this project was not completed  
by the date required by the terms of the  
contract has resulted in our company  
suffering considerable damages. Such  
damages, we can assure you, are far greater  
than the claim presented. We are presently  
calculating our claim in this regard".  
527.  
This was the first claim in writing by UGG that it had  
suffered any damage because of an alleged wrongful act or neglect  
of FCC.  
Skodje says if the letter had been sent in September  
1989, FCC would have completed the work that was remaining,  
ceased taking on any extra work and got off the site as quickly  
as it could.  
The dock was ready for shipping at the time this  
letter was sent and the first shipment took place the next day.  
In my view, this letter constituted the last step in MacKay's  
- 217 -  
strategy of "no response", which began in September, 1989. The  
strategy included, as the typed minutes of the September 13  
meeting note: "on the given day that the dock is ready and UGG  
is able to ship - UGG will pursue damages charges against  
Foundation". In my view this is in fact what occurred.  
528.  
This is not a case of oversight or omission. In September  
UGG made a decision to adopt a policy of "no response" to the CMI  
overtime claims and this posture continued unchanged through the  
fall even after it received the formal CMI and FCC claims in  
November. The motive was clear: it did not want CMI or FCC to  
leave the site. While this policy may have been open to UGG with  
respect to the FCC and CMI claims, it was clearly not open to it  
in respect of its own claim. GC 22 required written notice within  
a reasonable time. By electing to remain silent through the fall  
of 1989 until January 31, 1990, UGG prejudiced FCC by denying to  
FCC the opportunity to mitigate the UGG claim.  
529.  
In September UGG and CWMM considered advising FCC of a UGG  
claim for damages for delay but decided not to do so. One reason  
why UGG took no steps to notify FCC of any claim against it, or  
to refrain from ordering the substantial number of Change Orders  
that were ordered in the fall of 1989, might have been that UGG  
knew in September that its west berth would not be ready for  
shipping until (as UGG thought at the time) at least the middle  
of November.  
- 218 -  
530.  
Consonant with Doyle, FCC not only gave ample notice to UGG  
and CWMM of delays, FCC also provided information to UGG of the  
costs of delay times throughout the Project, thereby complying  
with GC 22 of the Prime Contract. Conversely, UGG provided no  
timely notice of claim to FCC. Skodge testified that if such a  
written claim had been given within a reasonable time after  
August 31 FCC would have refused any further extra work on the  
Project, would have completed its work as quickly as possible and  
left the job site. In September, in McKay's words, UGG just  
wanted to get the job done and it was perhaps a fear that FCC  
would refuse any additional extra work and simply finish the  
contract work and leave the site that drove UGG's decision not to  
give FCC notice of claim until January 30, 1990. However, in any  
event of the reason, by delaying until this date, UGG's failure  
to give notice prejudiced FCC.  
531.  
In fact through the fall, far from giving an indication that  
it would be advancing a counterclaim, UGG only told FCC that its  
claim and CMI's claim would be fairly and equitably considered.  
FCC was given no claim in writing for damages by UGG until one  
month after substantial completion, and was thereby prevented  
from taking mitigating steps or guarding measures to complete  
their work faster than they did and hence to minimise the quantum  
of UGG's claim. In my view, while FCC complied with GC 22, UGG  
did not.  
- 219 -  
532.  
UGG says that GC 22 has no application to its claim because  
the words in GC 22 refer to a property claim and not a claim for  
economic loss. It points to the subrogation provisions in the  
clause in support of this contention. However this language was  
interpreted in Doyle to encompass a contractor's claim for  
acceleration costs which was clearly a claim for economic losses  
and not physical property damage. I know of no reason why this  
language would not equally apply to a contractor's economic loss  
claim.  
533.  
In my view support for this conclusion can be found in the  
policy reasons underlying the judicial interpretation of the  
meaning of this GC 22 language: the parties to a construction  
contract are required to provide reasonable notice of acts or  
omissions of the other party for which compensation will be  
sought. Reasonable notice in the context of an ongoing  
construction project means notice which will afford the alleged  
offending party to take guarding measures in mitigation of the  
potential claim. In this case UGG denied FCC that opportunity.  
I conclude on the evidence that UGG made a deliberate decision in  
the early fall of 1989 not to so notify FCC. This is not a case  
of omission; rather it is a case where the owner made a  
deliberate decision not to put the contractor on notice until 5  
months after the substantial performance date had passed and  
until after the contractor had virtually completed its work on  
the project. This is, in my view, the precise conduct which the  
- 220 -  
courts in Doyle etc. have said runs directly contrary to the  
intent of contract language such as is found in GC 22.  
534.  
In reaching this conclusion I am also mindful of the  
following test as set out in Doyle (B.C.C.A. (1988) 27 B.C.L.R.  
(2d) 89 at 110:  
In view of the fact that the giving of a notice bars a  
remedy, the Courts have almost uniformly construed these  
clauses strictly. For instance, in this Court, First City  
Development Corp. v. Stevenson Construction Co. (1985),  
14  
C.L.R. 250, said [page 253]:  
"I approach the construction ... with the  
proposition established by the decided cases in  
mind, if a party to a building contract is to be  
deprived of a cause of action, this is only to be  
done by clear words."  
535.  
However, in my view the language of GC 22 is clear and is  
matched by the equally clear conduct of UGG. UGG elected not to  
comply with the contractual language it chose to insert into the  
contract it wrote. By failing to do so, it is barred from  
advancing its counterclaim.  
FCC DAMAGES - DELAY  
(a)DAMAGES IN TORT  
536.  
In respect of its tort claim, FCC is entitled to be  
compensated for all foreseeable losses, direct or indirect, as a  
result of the defendants' negligent misrepresentations. As  
LaForest and McLachlin JJ. said in B.G. Checo, at pp. 41-42:  
- 221 -  
"In tort, Checo is entitled to be  
compensated for all reasonably foreseeable  
loss caused by the tort. The Court of Appeal  
was of the view that Checo, had it known the  
true facts (i.e., had the tort not been  
committed) would have increased its bid by an  
amount equal to the cost of the extra work  
made necessary by the improperly cleared  
worksite plus profit and overhead. Such loss  
was not too remote, being reasonably  
foreseeable. But to compensate only for the  
direct costs of clearing is to suggest that  
the only tort was the failure to clear. The  
real fault is that Hydro misrepresented the  
situation and Checo may have relied on that  
representation in performing its other  
obligations under the contract. For example,  
having to devote its resources to that extra  
work might have prevented Checo from meeting  
its original schedule, thereby resulting in  
Checo incurring acceleration costs in order  
to meet the contract completion date. Such  
costs would also arguably be reasonably  
foreseeable. In our view, the matter should  
be referred back to the trial division for  
determination of whether any such indirect  
losses were the foreseeable results of the  
misrepresentation."  
537.  
538.  
FCC claims $822,439.00 as damages for negligent  
misrepresentation. This includes profit which, on this Project,  
was initially intended to be approximately 7.3% of the original  
Contract Price.  
The method used by FCC to calculate its damages is  
appropriate. It is similar to the approach adopted in BG Checo  
International Ltd. v. British Columbia Hydro and Power Authority  
(No.2) (1994), 109 D.L.R. (4th) 1 (B.C.S.C.) to calculate damages  
- 222 -  
on the damages reassessment. In respect of that reassessment,  
Cohen, J. said at pp. 8-9:  
"(2) Exhibit 5C, Checo's revised statement of  
claims for its direct and indirect losses,  
sets out Checo's damages calculated in  
accordance with the provisions of clause 4.21  
of the contract, the "Extra Work" clause.  
(These calculations include a 15% markup for  
overhead and profit.) This formula was  
accepted by me at trial. Hydro argued that  
the Supreme Court of Canada rejected this  
method of quantifying Checo's damages and  
contended that, in the case of Checo's direct  
losses, these losses were in fact, according  
to Hydro's approach, about 70% of the sums  
claimed by applying clause 4.21. I disagree  
with Hydro's position. On the contrary, the  
Court of Appeal and the Supreme Court of  
Canada accepted Checo's approach as a  
reasonable method for quantifying its claims.  
While it is correct that the Supreme Court of  
Canada, in dealing with Checo's claim for  
breach of contract, rejected the notion of a  
profit to Checo on the cost of clearing the  
right-of-way, nevertheless the court,  
referring specifically to cl. 4, which  
provides, inter alia, that the percentage fee  
of 15 percent shall be an allowance for  
overhead and profit, found that Checo may  
still be entitled to a portion of the 15%  
overhead".  
539.  
The use of the agreed Change Order charges with respect to  
labour is appropriate since there is no express provision in the  
Prime Contract dealing with quantification of this kind of cost.  
Campbell acknowledged in cross-examination that when CWMM wanted  
the work to be performed faster than it had been contracted to be  
performed, a change order would be appropriate for owner  
responsible delays.  
- 223 -  
540.  
541.  
As the Supreme Court of Canada stated in BG Checo, at p. 37,  
FCC is entitled to be "put in the position it would have been in  
had the misrepresentation not been made".  
FCC's damages calculations were essentially unchallenged in  
cross-examination. The calculations are based on actual hours  
expended. The calculations deduct paid and claimed Change Order  
work and back order work along with superintendent's time in  
accordance with the agreed charge out rates for Change Order  
Work. The rate used is a journeyman rate at $44.35 per hour for  
all hours, including foremen and general foremen. UGG is given  
credit for the payments made in respect of original Contract  
Price work after August 31, 1989. FCC was reasonably entitled to  
expect it would not be on the Project after August 31 except for  
correcting deficiencies which work is included in the original  
Contract Price work. To put FCC in the position it would have  
been in but for misrepresentation, it is entitled to compensation  
for its costs incurred during the three months of the delay  
period which I have found was caused by the acts or omissions of  
UGG and CWMM. Accordingly FCC is entitled to recover its costs  
for the 3 month period in the amount of $616,829. In accordance  
with the Interest section of this judgment, FCC will also recover  
interest in accordance with the Prime Contract at 10% per annum,  
calculated monthly.  
(b)DAMAGES IN CONTRACT  
- 224 -  
542.  
In respect of its contract claim, FCC is entitled "to be put  
in the position it would have been in had the contract been  
performed as agreed". (BG Checo v. B.C. Hydro at p.37)  
This means that FCC is entitled to be put in the position it  
would have been had the preselected equipment been delivered on  
time and not been defective, had the Adminstration Building been  
completed on time and had the design been done on time. No party  
has led evidence that the Prime Contract would have been  
impossible to complete by August 31, 1989 had there been no  
breaches of contract by UGG or CWMM.  
543.  
In this case, FCC attempted to mitigate the effects of delay  
and took certain steps to reorganize its work schedule. Neither  
CWMM nor UGG have pleaded a failure to mitigate nor attempted to  
prove a failure to mitigate. FCC is therefore entitled, as  
damages for breach of contract, the three months of costs  
incurred after August 31 minus the appropriate reductions.  
544.  
545.  
FCC's claim for delay is calculated as if a Change Order  
were ordered under the Prime Contract for the period after August  
31, 1989. Campbell testified that this is the mechanism he  
contemplated would be invoked for GC 4.1.  
Calculated as a Change Order under the Prime Contract, FCC's  
delay claim for the 4 month period after August 31, excluding  
CMI's pass through claim and excluding interest, is $822,439.00.  
- 225 -  
Based on my conclusion that FCC has proved that three months of  
that delay are attributable to CWMM and UGG, I assess its damages  
for breach of contract at $616,829.  
546.  
Since the payments for Change Orders would be monthly in  
arrears, payments by UGG for these damages should have been made  
under the Prime Contract commencing October, 1989. FCC is also  
entitled to contractual interest from December 1, 1989 to the  
date of judgment at 10% calculated monthly.  
FCC EXTRAS  
547.  
FCC claims against UGG or, alternatively, CWMM for unpaid  
Change Orders in the amount of $519,606.57, summarized as  
follows:  
C22/C25 Conveyors  
Conveyor Supports  
Gates  
$73,852.45  
$88,077.97  
$121,607.55  
$97,755.00  
$40,768.55  
$42,547.61  
$51,484.65  
$ 3,512.79  
$519,606.57  
Civil Group  
Conduit  
Dock Progressors  
Equipment Salvage  
Miscellaneous  
TOTAL  
FCC also claims interest of 10% per annum, calculated monthly, on  
the unpaid balance.  
(a) WAIVER OF CONTRACT PROVISIONS  
- 226 -  
548.  
Under the Contract, UGG, without invalidating the Contract,  
could make changes in the Work. These changes could take the  
form of additions to, or deletions from, the Work. In the case  
of additions, FCC was entitled to extra compensation, as allowed  
by the terms of the Contract. In the case of deletions, UGG was  
entitled to a credit as allowed by the terms of the Contract.  
549.  
GC 11 and GC 12 of the Contract deal with "Changes in the  
Work" and "Valuation and Certification of Changes in the Work".  
They read:  
GC 11 CHANGES IN THE WORK  
11.1 Except as provided in GC 12 - VALUATION AND  
CERTIFICATION OF CHANGES IN THE WORK, PARAGRAPH  
12.4:  
(a) the Owner, through the Consultant, without  
invalidating the Contract, may make Changes in the  
Work with the Contract Price and Contract Time  
being adjusted accordingly by written order, and  
(b) no Changes in the Work shall be proceed with  
without a written order signed by the Owner and no  
claim for a change in the Contract Price or change  
in the Contract Time shall be valid unless so  
ordered and at the same time valued or agreed to  
be valued as provided in GC 12 - VALUATION AND  
CERTIFICATION OF CHANGES IN THE WORK.  
GC 12 VALUATION AND CERTIFICATION OF CHANGES IN THE  
WORK  
12.1 The value of a change shall be determined in one or  
more of the following methods:  
(a) by estimate and acceptance in a lump sum;  
(b) by unit prices set out in the Contract or  
subsequently agreed upon;  
- 227 -  
(c) by cost and a fixed or percentage fee.  
12.2 When a change in the Work is proposed or required the  
Contractor shall present to the Consultant for his  
approval his claim for a change in the Contract Price  
and change in the Contract Time with appropriate  
documentation in a form acceptable to the Consultant.  
The Consultant will satisfy himself as to the  
correctness of such claim and, when approved by the  
Owner, a change order shall be issued to the Contractor  
amending the Contract Price and Contract Time as  
appropriate. The value of work performed in the change  
shall be included for payment with the regular  
certificates for payment.  
12.3 In the case of changes in the Work to be paid for under  
methods (b) and (c) of paragraph 12.1, the form of  
presentation of costs and methods of measurement shall  
be agreed to by the Consultant and Contractor before  
proceeding with the change. The Contractor shall keep  
accurate records, as agreed upon, of quantities or  
costs and present an account of the cost of the change  
in the Work, together with vouchers where applicable.  
12.4 If the method of valuation, measurement, change in  
Contract Price and change in Contract Time cannot be  
promptly agreed upon and the change is required to be  
proceeded with then the Consultant in the first  
instance will determine the method of valuation,  
measurement, the changes in Contract Price and Contract  
Time subject to final determination in the manner set  
out in GC 7 - DISPUTES. In this case the Consultant  
will, with the consent of the Owner, issue a written  
authorization for the change setting out the method of  
valuation and if by lump sum his valuation of the  
change in Contract Price and Contract Time.  
12.5 In the case of a dispute in the valuation of a change  
authorization in the Work and pending final  
determination of such value, the Consultant will  
certify the value of work performed in accordance with  
his own valuation of the change and include the amount  
with the regular certificates for payment. The  
Contractor shall keep accurate records of quantities of  
such work.  
12.6 It is intended in all matters referred to above that  
both the Consultant and Contractor shall act promptly.  
- 228 -  
550.  
551.  
In this case it was agreed by the parties that in order to  
complete the work as quickly as possible, the procedure set out  
in GC 11 would not be followed before work was proceeded with.  
The site minutes record examples of this decision not to  
strictly comply with certain of the contract provisions regarding  
extras. At Site Meeting #4, held March 14 the changes between  
the "tender" set of drawings and "issued for construction" set of  
drawings were discussed. Marquis minuted this discussion as  
follows:  
4.007  
FCC enquired as to procedure for dealing with the  
changes on the construction drawings (From Tender  
set).  
CWMM advised that we are to proceed with the work  
in accordance with the "latest" issue for  
construction drawings and that they will issue a  
change order to cover.  
FCC requested all trades to price the changes as  
soon as possible to finalize differences.  
552.  
At Site Meeting #6, held March 28 there were further  
discussions in relation to changes to the work. Marquis minuted  
this discussion as follows:  
6.011  
FCC requested that specific instructions "To  
proceed with the Change" or "Price First" be given  
when CCN's or field instructions are issued.  
- 229 -  
553.  
At Site Meeting #7, held April 4 there were further  
discussions in relation to changes in the Work. Marquis minuted  
this discussion as follows:  
7.012  
Procedure for changes  
CWMM advised that for the time being they will continue  
to issue memos on a daily basis to deal with field  
changes.  
Detailed drawings requiring changes will be issued with  
CCN with instructions to price first or to proceed with  
the changes and price later.  
554.  
Van Dyke gave evidence with respect to how extra work done  
on a time and material basis was ordered and dealt with. Extra  
work under the Contract started from a memorandum to FCC from  
Campbell. FCC would then assign a 90,000 number to the work. A  
claim with attached supporting documents would then be submitted  
by FCC. When there was no agreed price, the process would be to  
carry out work on a time and materials basis (cost and a fixed  
percentage fee according to G.C. 12.1(c)). Van Dyke also  
testified that if work was done on a lump sum basis, a quote was  
sought and approved prior to the work being undertaken.  
555.  
UGG contends that nothing in the discussions at the site  
meetings or in the subsequent minutes constituted a general  
waiver on the part of UGG of the provisions of GC 11 and GC 12.  
Article A-5(b) reads:  
- 230 -  
"No action or failure to act by the Owner, Consultant  
or Contractor shall constitute a waiver of any right or  
duty afforded any of them under the Contract, nor shall  
any such action or failure to act constitute an  
approval of or acquiescence in any breach thereunder,  
except as may be specifically agreed in writing."  
556.  
557.  
Under GC 12, FCC was responsible for presenting CWMM with  
its claim for a change in Contract Price and change in Contract  
Time with appropriate documentation in a form acceptable to CWMM.  
However in practice, Change Order work was requested  
during the Project in a variety of ways. UGG recognized Change  
Order work and paid FCC and its Subcontractors for work that  
resulted from changes to the drawings or specifications and work  
that was directed verbally by CWMM or UGG, by CWMM memo or fax,  
and by sketches issued by CWMM.  
558.  
Whenever FCC was instructed to proceed with work it  
considered to be Change Order work, a 90,000 number was assigned  
to the work for record keeping purposes. FCC or its  
subcontractors often requested CWMM site representatives to sign  
time sheets to acknowledge that the time recorded was spent on  
the work in question. When he noted the time sheets, Rhodes  
satisfied himself that the time had been worked on that day, and  
that the time recorded was reasonable. Hoffman also satisfied  
himself the correct number of hours had been apportioned to the  
right work before signing time sheets.  
- 231 -  
559.  
The documents FCC submitted to CWMM in support of its  
requests for payment of Change Order work included a cover sheet  
referencing the 90,000 number assigned to the work, summarizing  
the labour, equipment and materials, and attaching material  
invoices and time records for work done by FCC or its Sub-  
contractors on the work in support of the claim. These records  
were generally made in the ordinary course of business by FCC  
employees shortly after the time was spent or the material was  
invoiced. These records were reviewed by CWMM, then forwarded to  
UGG and would form the basis of each Change Order. FCC was paid  
on the basis of these records.  
(b) FCC RECORDS  
560.  
UGG contends that many of the records submitted by FCC in  
support of requests for payment of Change Order work are not  
business records within the meaning of Section 48 of the Evidence  
Act, and as such, cannot be offered in proof of the time and  
materials claimed.  
561.  
FCC says it was within the knowledge or observation of and  
the duty of the foremen to code timesheets to identify the hours  
spent and material supplied for Change Order work. It was also  
within the knowledge or observation of the material and equipment  
suppliers to prepare invoices of the equipment and materials  
supplied. It was the duty of Hawkins and other FCC employees to  
assemble what Hawkins referred to as "extra work orders" which  
- 232 -  
were summaries of the hours spent by the workers and foremen and  
the particular pieces of equipment involved. These summaries  
were signed by the Project Manager and forwarded to CWMM as  
requests for payment of Change Order work.  
562.  
563.  
It is clear that the records submitted by FCC in support of  
their claims for Change Order work were made in the ordinary  
course of business and formed the basis upon which FCC was paid  
for Change Order work. Are they admissible as business records?  
In Emil Anderson Mr. Justice MacDonald ruled that in the  
absence of evidence to the contrary, the statements of fact in  
Extra Work Orders ("EWO") including the headings or descriptions  
thereon were evidence the work was done, the equipment worked and  
the materials used in relation to the reference or description on  
the particular EWO, and sufficient to entitle the Plaintiff to  
judgment thereon. MacDonald J. noted that the EWO's which  
claimed payment for labour costs were little more than summaries  
of or extracts from the daily reports of foremen. FCC says Emil  
Anderson is authority for the proposition that FCC's request for  
Change Order work payment are business records pursuant to  
Section 48 of the Evidence Act.  
564.  
The test for the admissibility of business records has been  
recently discussed by the Court of Appeal in Olynyk v. Yeo  
(1988), 33 B.C.L.R. (2d) 247 (C.A.) where the court addressed the  
- 233 -  
ambit of s.48 of the Evidence Act. Olynyk was a case relating to  
the applicability of s. 48 to a doctor's records.  
565.  
The Court of Appeal in Olynyk made some general comments  
about s.48 of the Evidence Act. After citing s.48 in its  
entirety, Southin, J.A. wrote, at p. 253:  
"...I am of the opinion that...this section is directed  
toward recording "facts" occurring in the ordinary  
course of (the business of the maker of the document)  
and required to be recorded..."  
She continued at p. 254:  
"...The words "to record in that document a statement  
of fact" mean, in our opinion, that the fact occurred  
within the observation of someone who has a duty  
himself to record it or to communicate it to someone  
else as part of the usual and ordinary course of  
business."  
Finally, Southin, J. A. wrote, at p. 255:  
"...(Section 48) does not make everything in a document  
admissible just because the document is one which for  
some purposes falls within the section."  
566.  
Olynyk was referred to in Hunt v. Westbank Irrigation  
District (1991), 59 B.C.L.R. (2d) 215 (S.C.). The Plaintiff in  
Hunt was a commercial grape grower whose property was located in  
Westbank, British Columbia. During a drought, Westbank briefly  
cut off the Plaintiff's water source. The Plaintiff claimed that  
he suffered a loss as a result of the water having been shut off.  
The Defendant sought to introduce a document generated by the  
British Columbia Grape Board entitled "Grape Summary Sheets"  
- 234 -  
which, on its face, showed that no other grape grower in the area  
had suffered a loss comparable to that alleged by the Plaintiff.  
567.  
Mr. Justice Oliver held that these documents were not  
admissible pursuant to s. 48 of the Evidence Act. He wrote,  
after reviewing aspects of the document which rendered them  
unreliable for the purpose tendered wrote, at p. 223:  
"...The records do not show if the "facts" recorded  
were within the observation of the maker of the  
statement or within the observation of any person whose  
observation it is part of the usual and ordinary course  
of business of the maker to record.  
In the circumstances, to admit these records for the  
truth of their contents would be to admit unreliable  
hearsay. Section 48 is intended to make admissible  
reliable business records admissible and not intended  
to make any hearsay evidence of third parties  
admissible: "Olynyk".  
568.  
In my view the nature of the documents that were at issue in  
Olynk and Hunt distinguish those cases from the case at bar.  
In Olynyk, the evidence sought to be introduced from the medical  
record was not a record of the results of an examination or  
similar 'observable fact' but was a note made on admission of the  
patient regarding history of a previous fall. Because of the  
lack of evidence as to the source of information regarding the  
previous fall (the evidence was it may have come from the  
Plaintiff/patient, the ambulance attendant, or almost anyone  
else) the trial judge instructed the jury not to consider  
- 235 -  
evidence of the previous fall. The Court of Appeal stated at  
page 254.  
"The words "to record in that document a statement of  
the fact" mean, in our opinion, that the fact occurred  
within the observation of someone who has a duty  
himself to record it or to communicate it to someone  
else to record as part of the usual and ordinary course  
of business."  
...  
"There was no duty on whoever provided the information  
as to the cause of the fall to make or cause to be  
recorded that fact."  
569.  
In Hunt the court decided a Grape Summary Sheet should not  
be admitted pursuant to s. 48 of the Evidence Act because it was  
not prepared by the grape board in its ordinary course of  
business and was unreliable. At p. 223 Oliver J said:  
"These records are not made by the grape board. They are not  
signed by the producer, winery or the grape board  
representative. They do not show the size of the vineyard  
or any other information that would indicate when the  
information was recorded or the source of the information  
other than the name of the grower. The records do not show  
if the "facts" recorded were within the observation of the  
maker of the statement or within the observation of any  
person whose observation it is part of the usual and  
ordinary course of business of the maker to record."  
570.  
In my view the documents relied upon by FCC in support of  
its unpaid Change Order work are, for the most part, admissible  
as business records. They were prepared by FCC in its ordinary  
course of business and provided to the defendants at the time the  
extras claims were submitted. While some of the documents were  
- 236 -  
not prepared by FCC, they were prepared by FCC's subcontractors  
in the ordinary course of their business and submitted with the  
appropriate extras claims for review by CWMM and UGG. In my  
view, this class of document is admissible under s. 48 of the  
Evidence Act  
(c) FCC EXTRAS  
571.  
There is no issue as to FCC's charge out rates for Change  
Order work and its 5% fee for all materials and subcontractor's  
invoices. When FCC's claims for Change Order work were approved,  
FCC was notified by letter so that it could invoice for the work  
in the current month's progress claim.  
572.  
Throughout the Project it was understood by FCC and its  
Subcontractors that they were required to do the work directed by  
CWMM, keep records of all time and materials and wait to resolve  
any disputes regarding whether the work was Change Order work and  
the quantification of Change Order work when there was more time  
to assess these issues. When FCC was directed by CWMM to do  
work, even if FCC considered it to be Change Order work and CWMM  
or UGG initially did not agree, FCC was obligated to do the  
work.  
UGG says and I agree that it is not required to compensate FCC  
for "losses" incurred by FCC as a result of FCC:  
- 237 -  
(a) failing to provide an adequate sum in its tender to  
undertake various portions of the Work required under  
the Contract;  
(b) letting subcontracts which were inconsistent with the  
Prime Contract; or  
(c) deviating from, or allowing its subcontractors to  
deviate from, the provisions of the Prime Contract.  
573.  
Compensation under GC 11 and GC 12 is not available to  
compensate FCC for a bad bargain, or for "losses" incurred while  
undertaking "risks" which FCC assumed in prosecuting the Work.  
The onus is on FCC, in relation to all claims for extra work, to  
prove:  
(a) that the alleged extra work claimed for is not within  
the Contract; and  
(b) the time spent, and materials utilized, to perform the  
extra work.  
574.  
In addition, it must show that it has complied with the  
terms of the Prime Contract so as to entitle it to compensation  
for extra work.  
- 238 -  
(d)C-22/C-25 CONVEYORS  
575.  
C-22 and C-25 were belt conveyers in the South Annex of the  
UGG terminal. The Contract between UGG and FCC contained the  
following provisions relating to C-22 and C-25:  
a)  
i)  
Instructions to Bidders:  
1.1.9: Belt Conveyors:  
Work to include but not limited to:  
(a) All work with respect to providing a complete new  
system throughout both the North and South Annex.  
ii) 1.2.8: Removal of Equipment Annex, Bin Floors:  
(a) All belt conveyer systems in North and South Annex  
to be removed with exception of C-25 and C-22 and  
C-27 and C-28. C-27, C-28 to be modified as  
called for in Scope of Work. The head and tail  
sections of C-22 and C-25 will be modified, the  
balance of these two conveyors are to be removed.  
iii) 1.3.4: Relocation and Modification of Existing  
Equipment:  
Extensive work will be done to modify Bin Floor  
Belt Conveyor C-25 and C-22. Refer to Scope of  
Work, Bin Floor Conveyors.  
(b) Specifications:  
BELT CONVEYORS:  
Scope:  
15I.1.1.:  
This specification covers the general requirements for  
the work on belt conveyor upgrades in the Workhouse for  
Bin Floor conveyors C-27 and C-28 and South Annex belts  
C-22 and C-25.  
Equipment:  
ii) 15I.2.1  
- 239 -  
Reuse existing pulleys, bearings, shafts on belts. Re-  
lag, with 3/8" vulcanized logging, head pulley on C-22  
and C-25.  
iii) 15I.2.3.  
Belt C-22 drive to be adjusted by replacing sprocket  
drive and chain. Motor to remain as is.  
Belt C-25 motor to remain as is but gear reducer to be  
replaced.  
iv) 15I.2.3:  
Now automatic gravity type take-up to be installed for  
belt C-25.  
Existing screw take-up to be revised for belt C-22.  
v)  
15I.2.4.  
Idlers to be CEMA III, 5" diameter, 3/4" shaft roller  
bearing, off-set, equal length 45 degree, 35 degree and  
25 degree, as specified in the drawings. One side  
lubrication.  
Stands with slotted holes for adjustment. Bearings  
anti-friction type and dust proof transition and  
framing idlers where indicated on the drawings.  
vi) 15I.2.7:  
Transfer point for C-25 to C-22 to be modified as  
called for on drawings. C-22 Belt Loader/DC110 drag  
chain conveyer loader. Two way valve to be automated.  
576.  
577.  
In addition, the drawings in the tender package showed that  
C-22 and C-25 were part of the "system" of conveying in the South  
Annex.  
Campbell described at trial the original plan for C-22 and  
C-25. It was intended that the two conveyors were to be  
demolished and replaced with new conveyors, save and except as  
outlined in the Contract. Prior to the close of tenders, Campbell  
took the bidding contractors on a walk through of the UGG  
- 240 -  
terminal. While Campbell could not specifically recall what he  
told these contractors on the tour with respect to the work  
required on C-22 and C-25 he testified that "it was one of the  
stopping points on the orientation tour for all the general  
contractors".  
578.  
FCC did not provide in its bid for the construction of new  
mid-sections of C-22 and C-25. After FCC had been awarded the  
Contract, C-25 was extended, and C-22 was deleted in its  
entirety. FCC is entitled to compensation for extra work  
required to extend C-25.  
579.  
580.  
UGG is entitled to a credit for the deletion of C-22. FCC  
unilaterally reduced its last progress claim by $16,115.00 as a  
result of C-22 having been deleted. UGG takes the position that  
there was an "additional credit due".  
The dispute on this claim can be summarized as follows:  
(a) was FCC required, as part of the Work under the  
Contract, to construct a new Conveyor C-22, and if so,  
what is a reasonable credit for its deletion?  
(b) what extra compensation is FCC entitled to for extra  
work in relation to C-25?  
- 241 -  
581.  
UGG intended that the successful contractor would install  
whole new conveyors C-22 and C-25. The Instructions to Bidders  
outlined that, other than the head and tail sections, C-22 and C-  
25 conveyors were to be removed. Further, FCC were required to  
complete a new system of bin floor conveying throughout the ...  
South Annex.  
582.  
Derhousen gave evidence at trial that he recognized when  
preparing the tender for C-22 and C-25 that there was a conflict  
within the tender package with respect to the Work required of  
the Contractor on these conveyors. He went on to say that when  
preparing his portion of the FCC bid, he elected to rely on the  
drawings and the first sentence of 1.2.8 providing that all belt  
conveyor systems were to be removed with the exception of C22 and  
C25. He sought no clarification from Campbell or anyone else  
with respect to the conflict he observed. As a result, FCC bid on  
the assumption that minimal work was required on these conveyors.  
FCC carried $74,500 in its tender for all work on the 6 belt  
conveyors (C1, C2, C25, C22, C27 and C28).  
Paragraph 11.2 of the Instructions to Bidders (which form part of  
the Contract) reads:  
"The bidder shall not claim at any time after  
submission of his tender that there was any  
misunderstanding in regard to the requirements of and  
conditions imposed by the tender documents."  
583.  
Paragraph 11.3 of the Instructions to Bidders reads:  
- 242 -  
"The bidder shall ensure that his tender price allows  
for all materials, equipment and supplies forming a  
part of the permanent work being new, unused and  
originally coming from the supplier to the owner."  
Exceptions to this were re-usable spouting and refurbished air  
cylinders and hoses.  
584.  
In my view the purpose of the foregoing bidding instruction  
was to foreclose precisely the event which occurred with respect  
to the work on C22 and C25. Derhousen ought to have clarified  
what he described as the conflict in the tender documents as  
required by the Instructions to Bidders. He failed to do this  
and having regard to the clear provisions of the contract, UGG  
was entitled to expect that FCC's bid included the replacement of  
C22 and C25.  
585.  
However after the prime contract was awarded, the middle  
section of C25 was changed. The length of C25 as shown in the  
tender drawings was changed when the construction drawings were  
issued. To the extent that this entailed extra work, FCC is  
entitled to compensation.  
586.  
FCC broke its claim into a number of discrete parts.  
a)  
FCC 90012 (Replace C-25 drive pulley with C-  
23) Hawkins was directed to this claim in his  
evidence. Although he was unable to give  
evidence as to whether it had been paid or  
- 243 -  
not, I am prepared to allow FCC's claim for  
$52.38 based on FCC's records.  
b)  
FCC 90265 (Additional Idlers for C-25) These  
idlers were incorporated into the mid-section  
of C-25. Specification 15I.2.4 provided for  
new idlers and stands. Campbell gave  
evidence that the overall length of the  
conveyor was the same length as shown on the  
construction drawings.  
In my view, this is contract work and FCC is not entitled to  
compensation for the work.  
c)  
90508A (Miscellaneous & Structural Steel  
Drawing Changes)  
587.  
This claim is for additional steel required to fabricate the  
middle section of C-25. In my view, this was contract work, and  
hence FCC is not entitled to compensation for the work. In  
addition this matter was settled at the meeting to discuss  
structural steel extra work which took place on November 11.  
Three separate structural steel extra claims were discussed at  
this meeting: one for construction of drag conveyors  
($72,876.72), one for drives, etc. ($66,126.18), and another for  
this work ($37,450.38).  
- 244 -  
588.  
Skodje was asked on discovery whether he remembered this  
meeting. After that meeting a change order (#132) was issued to  
FCC for $72,876.72. It was suggested to Skodje on discovery that  
in exchange for FCC accepting that amount FCC was not going to  
proceed to claim the other two amounts, that they would be  
settled and taken off the table; he answered "It could be". At  
trial, Skodje confirmed the truth of that answer.  
589.  
Campbell gave evidence that all three claims were settled by  
a payment of $72,876.72. He recalled someone at the meeting  
asking if Skodje wanted the 72¢ and Skodje saying that he did --  
if he was only getting 1/2 of what he came after, he wanted the  
72¢. Atwell testified that he recalled Campbell reviewing with  
FCC the drawings, and that it was his firm impression that the  
steel extras were settled.  
d)  
90545 (C-25 Modifications - Take up and Shorten)  
Hawkins gave evidence that he saw the FIR at  
Tab 90545 of Exhibit 98. He recalled seeing CWMM  
memo 342. Hawkins could not recall whether there  
was any dispute as to whether the time and  
materials outlined on the October 1 work order  
were performed or utilized. However based on FCC's  
records, it is entitled to $1,277.53 for this  
extra.  
- 245 -  
e)  
f)  
90558 (Remove section of stringer on C-25)  
Hawkins gave evidence that a stringer had to  
be removed and I would allow FCC $1,098.43  
for this extra.  
90570 (Raise stringers head end of C-25) Hawkins  
was asked to give evidence with respect to this  
claim. He was not in Canada during the time that  
this work was done. He gave no evidence that this  
was extra work, while Campbell testified that this  
was not extra work. It is not allowed.  
CREDIT FOR DELETION OF C22  
590.  
UGG challenges the credit of $16,115 provided by FCC for the  
deletion of C22. FCC calculated this credit based on the amount  
FCC carried in its tender for the work to be done to C22, less  
the cost of work relating to the deletion and removal of C22  
which is summarized as follows:  
90006  
90050  
90110  
Elimination of C22  
Remove drive & base/old C22  
Remove tail pulley C22 (90006,90050)  
$2,884.42  
568.27  
1,025.26  
$4,477.95  
591.  
Derhouson gave evidence that the credit for the deletion of  
C22 should be between $8,000.00 and 10,000.00. FCC contends  
that its $16,115.00 for the deletion of C22 was generous and  
accepted by UGG insofar as it was deducted from the final  
- 246 -  
progress payment. UGG says the unilateral reduction of $16,115  
given by FCC for deletion of C-22 is insufficient.  
592.  
At trial Derhousen estimated the installation cost of these  
conveyors at $400 - $500 a foot. Campbell gave evidence that he  
may have used a similar sum in his estimate. Drawing 5542-M30  
shows that C-22 was 222 feet 3 inches long. On this basis, using  
the most conservative figure offered by Derhousen, deletion of  
the conveyor portion of the work would amount to $88,900.  
593.  
594.  
There was associated deletion of concrete spouting at the  
end.  
Campbell gave evidence that a reasonable credit for this  
work was at least $20,000. UGG says that the total credit owing  
to UGG for deletion of C-22 is therefore $108,900.  
However, in my view, the most accurate basis for this credit  
is the calculation based on the amount FCC carried in its tender  
for the work to be done to C22. While the estimates provided by  
Campbell and Derhousen at trial must be considered, they are not  
as reliable as FCC's actual tender amount. The credit is allowed  
at the figure of $16,115 already provided to UGG.  
595.  
The C-22 and C-25 claim is accordingly allowed as follows:  
Replace C-25 drive pulley  
C-25 modifications  
$52.38  
$1,277.53  
$1,098.43  
Remove section of stringer on C-25  
- 247 -  
Raise stringer head end of C-25  
$1,396.22  
TOTAL: $3,824.56  
(e)CONVEYOR SUPPORTS  
596.  
FCC tendered only on support steel that was shown on the  
tender drawings. The drawings showed hangers coming from the  
concrete beams on the ceiling down to the conveyor with some  
lateral bracing. Supports required for the ends of the conveyors  
were not indicated on the drawings. FCC bid on intermediate  
supports only. Was it correct?  
597.  
The initial specifications did not require the General  
Contractor to provide conveyor supports. The manufacturers of  
drag conveyors were to provide head and tail supports. In  
December, 1988 Addendum #2 was sent to all bidding contractors.  
It amended the specifications relating to drag conveyor supports  
by adding "All drag conveyor supports to be supplied and  
installed by General Contractor."  
598.  
FCC says it interpreted this provision in Addendum #2 as  
being limited to "intermediate supports". I do not accept this  
submission. The Purchase Specification for Drag Conveyors was  
included in the initial tender package. It stated that the drag  
conveyor manufacturer was to provide head and tail supports for  
the drag conveyors. Intermediate Sections of the drag conveyors  
were dealt with at page 3 of the Purchase Specification. The  
- 248 -  
drag conveyor manufacturer was not required to provide immediate  
supports.  
599.  
Instruction to Bidders, s.1.1.1 noted that the Contractors  
were obliged to "furnish all labour, equipment supervision, tools  
and miscellaneous materials to complete the mechanical,  
electrical and structural work including trackwork to the full  
intent of the drawings and specifications".  
600.  
Intermediate supports were required in order to make the  
drag conveyors functional. Prior to Addendum #2 being issued,  
the contactor was required to provide all intermediate drag  
conveyor supports. Addendum #2 was then issued, outlining that  
"All drag conveyor supports must be supplied and installed by  
General Contractor". In my view it was not reasonable to apply  
this only to intermediate supports. The General Contractor was  
already required, by the terms of the tender package, to provide  
"all intermediate drag conveyor supports".  
601.  
It must be assumed that an Addendum to a tender package is  
meaningful. Addendums are not made to repeat matters already in  
the initial tender package. The Addendum to specification 15K  
was clear. It expanded the contractor's responsibility to the  
providing of all conveyor supports.  
- 249 -  
602.  
The drawings contained typical conveyor supports. While  
some of the conveyor supports were not finally detailed at the  
time of tender, the typical supports provided information which  
would have enabled FCC to build an allowance for conveyor  
supports into its bid.  
603.  
Finally, in my view, the claim for additional steel for  
conveyor support (90508B) was settled at the meeting between UGG,  
CWMM and FCC held on November 11 in the boardroom of UGG's  
Administration Building and referred to earlier.  
(f)GATES  
604.  
605.  
FCC included only the 87 gates shown in the gate schedules  
and qualified its January 17, 1989 tender as follows:  
"2. Our tender includes only those pneumatic valves or  
gates as listed on the mechanical tender drawings  
schedules."  
From the evidence regarding the IECO and Bisco estimates of  
the number of gates and the discussion at site meetings, I  
conclude that no one was certain how many gates were to be  
included in the Project.  
606.  
Hoffman gave evidence that when Bisco was preparing its  
tender for the Project, he carefully reviewed all of the drawings  
to count the gates. The Bisco tender specified only 104 gates.  
- 250 -  
Campbell was aware that FCC had qualified their tender although  
he could not recall the specific number of 87 but since the  
number '87' was noted in his own handwriting on his draft letter,  
he says that Skodje probably advised him that FCC only carried 87  
gates in its tender.  
607.  
At the first site meeting on February 21 IECO questioned the  
number of gates required by the drawings. IECO produced a  
summary of the number of gates for the engineer to check. On  
February 22 Campbell produced a summary showing 110 gates. He  
later changed that count to 115 gates. At the March 1 site  
meeting, IECO requested that the question of the number of gates  
be resolved right away, including the question of the final count  
for the gates and the types of gates. CWMM advised that they  
would pursue the matter on a priority basis.  
608.  
On May 23 FCC sent Addendum #1 to its purchase order to IECO  
adding another 22 gates for a cost of $91,891.90. FCC coded this  
cost under #90083 and on October 1 FCC submitted its request for  
payment of these additional gates plus its 5% fee to CWMM in the  
amount of $96,496.50. On June 19 FCC issued a purchase order to  
Bisco for the supply of four additional gates and a gate DV109  
(excluding PST.) FCC coded the cost of the four gates (excluding  
DV109) under #90083. On July 19 FCC submitted a request for  
payment of the four additional gates purchased plus PST and FCCs  
- 251 -  
5% fee in the amount of $16,728.39. On August 3 FCC received  
Bisco's invoice for all five gates.  
609.  
FCC coded the work for the supply of gate DV109 and the  
spout for gate DV109 under #90206. On July 18 FCC submitted its  
request for payment of the supply of gate DV109 plus FCCs 5% fee  
in the amount of $4925.03. On August 31 Bisco invoiced FCC for  
the supply of the spout to gate DV109. On September 9 FCC  
forwarded its request for payment of this supply plus its 5% fee,  
in the amount of $3,467.64.  
610.  
611.  
It is clear that these additional gates were not included in  
FCC's tender. The amount of FCC's claim is calculated on the  
basis of the actual cost of the gates to FCC (as evidenced by the  
purchase orders to Bisco and IECO) plus FCC's 5% fee.  
However is FCC entitled to this as an extra? It is clear  
that there were communications between the parties after tender  
and before the contract was awarded on the topic of the number of  
gates. There were no gate schedules produced and hence the  
contractor had to rely on a number count taken off the drawings.  
In its tender, FCC wrote that its bid "includes only those  
pneumatic valves or gates are listed on the mechanical tender  
drawings schedules.  
- 252 -  
612.  
Derhousen spoke with Campbell after FCC's bid had been  
received by UGG and Campbell informed him that there were more  
gates on the drawings than those accounted for in FCC's bid. A  
meeting was convened between Skodje and Campbell to resolve the  
issue of the number of gates in the Work.  
613.  
614.  
Campbell informed Skodje that there were no gate schedules.  
The two of them reviewed the tender drawings and Campbell pointed  
out valves to Skodje. Skodje confirmed that they were included  
in FCC's tender.  
The letter dated March 22 from Campbell to Pope of UGG  
contained the following passage:  
"There were no valve schedules produced on the  
engineers bid documents, FCC have confirmed that they  
have included all pneumatic electric and pneumatic  
gates shown on the drawings and/or called for on the  
specifications. The total number of new two way valves  
and single slide gates included in this contract are 50  
and 65 respectfully. Additional work on existing  
valves is clearly defined in the electrical portion of  
the documents."  
This letter was sent in draft by Campbell to Skodje prior to the  
contract being signed.  
615.  
Skodje admitted in cross-examination that he confirmed to  
Campbell that FCC had included all of the pneumatic electric and  
hydraulic gates shown on the drawings and/or called for in the  
specifications, as outlined in the March 22 letter. However it  
- 253 -  
is apparent that Campbell, at the time, had considerable sympathy  
for FCC on this claim. He testified that it was always his  
intention "at the end of the day to support FCC on this claim for  
extra gates". UGG contends that late notice was given in respect  
of this claim contrary to GC 12. In my view Campbell was alive  
to this issue from the time it arose and his conclusion to  
support FCC was, in all the circumstances reasonable. While it  
is true that had the other outstanding matters between the  
parties been resolved amicably that FCC would not have advanced  
this claim, I do not think that the timeliness of the claim  
submission is a bar to recovery because Campbell was alive to the  
issue. That being the case, the owner suffered no prejudice and  
FCC is accordingly entitled to recover $121,607.55 for this  
extra.  
(g) CIVIL  
1. Additional Concrete Work  
FCC claims $49,762.00 for additional concrete work on equipment  
bases and pads that were either not shown on the tender drawings  
or were substantially revised in size and shape by CWMM. CWMM  
and UGG agree this is Change Order work and the only issue is  
quantification.  
616.  
The claim is based on a material takeoff using rates  
provided in a handbook for formwork labour hours. Although he  
was not present when this work was done, Hawkins testified that  
- 254 -  
this work was relatively expensive because it had to be done at  
the top of the workhouse in an area difficult to access. It was  
expensive to get the material there and the work had to be done  
in very tight quarters. FCC initially claimed $49,762.00 for this  
work. In a meeting with CWMM and UGG, probably because a  
substantial portion of the work had to be done under the  
contract, FCC offered to compromise the claim at $21,191 but the  
offer was refused.  
617.  
Hawkins did not do the calculation of the amount being  
claimed by FCC for this extra. He did say that he "believed"  
that a handbook for "formwork labour hours" was used in the  
calculation.  
No evidence was put forward by Hawkins as to why the "handbook"  
would apply to the work for which extra compensation was claimed.  
The difficulty with quantifying this claim is that the materials  
in support contain few, if any particulars as to how it was  
calculated.  
618.  
619.  
It is likely that Whitaker did the calculation of this  
claim. He did not give evidence at trial. There were no FCC  
time sheets in support of the claim. No evidence was put before  
the Court as to how long it took to do this work or the cost of  
the materials..  
Campbell did a take off of the material. He estimated that  
3.3-3.5 cubic yards of concrete were added. He acknowledged it  
- 255 -  
was expensive work, and estimated that cost would be $500 - $1000  
a cubic yard. In my view Campbell's takeoff is unduly  
conservative having regard to the likely difficulty in carrying  
out this work at the top of the workhhouse in confined  
surroundings. I would allow $15,000 for this claim.  
2. Extra Cutting and Coring  
Based on the tender drawings, FCC estimated a floor slab  
thickness of 6" from the drawings and did spot checks during the  
tender period to confirm the estimated 6" thickness. Campbell  
gave evidence that when CWMM did its estimate they measured  
openings in the floor to establish slab thickness and they also  
estimated a 6" thickness.  
620.  
In some areas the floor slabs were considerably thicker than  
the 6" estimated, as shown on Adriatic's invoices and summarized  
in Whitaker's February 26, 1990 memo, resulting in a substantial  
increase in the cost for cutting and coring openings for  
equipment, spouting, etc. FCC claims $45,186.00 for the  
additional cutting and coring cost. This claim has been  
calculated using the invoices sent by Adriatic for the cutting  
and coring work to calculate the portion of the work that exceeds  
the thickness estimated on the basis of the tender documents.  
- 256 -  
621.  
UGG objects to the admissibility of the Adriatic invoices as  
business records. However, in my view, FCC has a more  
fundamental problem with this extra claim. GC12 requires a  
Contractor to act promptly in making claims for additional  
compensation. This obligation is imposed so that the owner has  
an opportunity to verify the extra work claims being made by its  
Contractors. These claims were made in December, 1989, months  
after the work was undertaken. This delay deprived UGG of any  
verification opportunity. The claim is not allowed.  
3. South Annex 3" Topping  
In the South Annex, there was an additional three-inch topping  
which resulted in Change Order work to cut and core holes.  
Campbell gave evidence that the three inch topping was not shown  
on the drawings and it would have been difficult without coring  
holes, to find out that in fact there was a three inch topping.  
Rhodes gave evidence that he extensively reviewed all of the  
drawings at the beginning of the Project and continued to check  
them on almost a daily basis while employed by CWMM. Rhodes did  
not expect to find a three inch topping in the south annex.  
622.  
Atwell also gave evidence that it would not be possible for  
FCC to have anticipated the additional thickness of concrete when  
preparing its tender. Atwell's October 17 letter noted that a  
change order was pending for cutting the "additional thickness of  
concrete" in relation to another claim coded under #90344.  
- 257 -  
623.  
The Change Order work required to do the additional cutting  
and coring as a result of the three inch topping was calculated  
by Hawkins. He measured the holes which were cut in the South  
Annex. Using a 3" factor on each hole, he came up with the  
number of "foot inches" which were allegedly cored as a result of  
the existence of a 3" topping. He then multiplied the number of  
"foot inches" by .079 hours per foot inch (.069 hours/foot inch  
for cutting based on a "means book" and .010 for "productivity  
loss"). To this was added 15% for "foremen's hours", and  
equipment of $10.00/hour. The cutting and coring was actually  
done by FCC's subcontractor, Adriatic Cutting and Coring. At  
trial Hawkins effectively tried to recreate what it cost FCC to  
have Adriatic core the holes.  
624.  
However, Adriatic was paid by the foot inch and arguably  
there can be no productivity loss when payment is made on a "unit  
basis". There is also no indication that Adriatic charged a  
"premium" for this additional work. Neither is there any  
indication as to whether foremen's hours were charged separately  
by Adriatic. Hawkins gave no evidence as to the source of this  
number. Similarly, there is no evidence as to why $10.00 per  
hour should be added for equipment. When asked where he got  
$10.00/hour for equipment, Hawkins testified "I can't say right  
now off the top of my head. I mean I don't have any specific  
recollection". Finally, there is no indication that the work was  
- 258 -  
done on premium time. It is therefore not appropriate to use  
$44.75/hour for workers, and $47.52 for foremen.  
625.  
UGG says that if Hawkins "means book" reference is accepted,  
the claim is limited to $1,762.65. It will be allowed in that  
amount.  
(h)CONDUIT  
1. Removal of redundant conduit  
The electrical drawings contain notes that redundant conduit is  
to be removed. Although the redundant conduit appears in the  
drawing legend as a dotted line, there were no references to  
redundant conduit on the tender drawings and it was expected by  
CWMM the bidders would make a reasonable allowance for the  
removal of redundant conduit.  
626.  
The Instructions to Bidders required bidders to make an  
allowance of 240 man hours for relocation of conduit and required  
the successful contractor to track the time actually spent on  
relocation of conduit during the Project. Hammond gave evidence  
that it would have been reasonable to allocate 450 man hours or  
about $20,000.00 in the tender for removal of redundant conduit  
and that he discussed this with Van Dyke.  
627.  
FCC included conduit removal in its demolition bid, and  
planned to have Johnny Walker remove redundant conduit. During  
post-tender negotiations, in a letter dated January 27, FCC  
- 259 -  
proposed a credit of $13,995.00 for the deletion of the conduit  
removal. The credit was not accepted by UGG.  
628.  
The conduit to be removed was to be identified by Hammond on  
a walk through of the project. At the May 2 weekly site meeting  
it was noted that Hammond had just begun to identify the  
redundant conduit for removal. Hammond continued to identify  
redundant conduit to the end of October 1989.  
629.  
On May 25 CWMM issued memo #051 directing FCC to remove  
redundant electrical conduit at the basement west wall L-2 spout.  
FCC coded this work under #90097A. UGG issued Change Order #71  
for some of Ricketts-Sewell's work removing this conduit, coded  
under 90097. FCC sent a request for payment, dated May 24 in the  
amount of $2,328.38 to CWMM for the work coded under #90097A. On  
March 12, 1990 Whitaker sent a fax to Atwell attaching the May 24  
request for payment and supporting documents requesting that it  
be 'added to the redundant conduit discussion group.' On October  
30 CWMM sent memo #594 to FCC attaching a memo from Hammond  
Engineering regarding the removal of redundant conduit directing  
FCC to remove the redundant conduit as outlined in the memo. FCC  
coded this work under #90655.  
630.  
CWMM and UGG were both aware FCC budgeted $13,995 for the  
removal of redundant conduit based on removal by Johnny Walker.  
The actual cost of removing the conduit exceeded this budget.  
Time spent removing redundant conduit was coded under #90655, and  
- 260 -  
the $13,995 allowance in FCC's tender for removal of redundant  
conduit was subtracted from the actual cost of the removal for a  
remaining claim of $26,694.64. Hammond agreed that if a  
contractor spent  
more than a reasonable allowance for the removal of redundant  
conduit, that it would be the basis for a claim for a Change  
Order.  
631.  
The difficulty here was that the identification of the  
conduit to be removed did not take place at the start of the  
project as contemplated by FCC, when it planned to have its  
demolition contractor do the removal. Identification of the  
redundant conduit started instead in May and continued to  
October. This was clearly contrary to the expectation of the  
parties and I would allow this extra at $26,694.64.  
2. Relocate Conduit at B2  
On July 12 FCC sent FIR #112 to CWMM advising that the support  
steel for B-2 was in conflict with the new electrical conduit  
rack. On July 20 CWMM issued memo #221 to FCC requesting that  
FCC relocate the conduit. Hawkins gave evidence that this  
conduit had to be relocated to accommodate the installation of  
one of the conveyors.  
632.  
Ricketts-Sewell invoiced FCC $21,552.00 for this Change  
Order work in relocating the conduit on September 12. On  
September 12 FCC issued a request for payment to CWMM for this  
- 261 -  
portion of the work. On October 23 UGG issued Change Order #89  
to FCC for this portion of the work (including FCC's 5% fee) and  
on November 6 FCC paid Ricketts-Sewell.  
633.  
634.  
On September 19 Ricketts-Sewell invoiced an additional  
$11,186.21 for this work to FCC. On September 21, 1989 FCC  
issued a request for payment of this invoice plus FCCs 5% fee to  
CWMM. UGG has not paid FCC for this portion of the work.  
UGG says that some of the work done by Ricketts-Sewell was  
to repair damage done to the conduit rack by FCC's ironworkers;  
Hawkins testified that this damage occurred after the rack was  
relocated. Clearly, UGG is not obliged to pay for damage done by  
FCC forces which is FCC's responsibility under GC 21.  
635.  
Hawkins was unable to say whether the hours underlying this  
claim related to relocation of the conduit rack in issue, or  
rectification of damage. Hence there is some question as to how  
much of the invoice in dispute represents work in connection with  
the relocation and how much represents the cost of repairing FCC  
inflicted damage. From a review of the documents, I conclude that  
the $21,552 item which has been paid was likely for the  
relocation and the $11,186.21 item was likely for the repairs. It  
is not allowed.  
- 262 -  
3. Celtek Sensor Conduit  
Ricketts-Sewell were instructed by Hammond Engineering to  
relocate the conduit for the new Celtek sensors along the  
ceiling. FCC says that no route was specified for this conduit.  
It was installed along the floor. It was re-routed as a result  
of a direction by CWMM. Hawkins had no knowledge of this  
particular claim for additional compensation. No other FCC  
witness had any evidence with respect to this extra claim.  
636.  
Specification 16B.2.7 reads:  
"Conduits shall be routed along building lines  
generally as shown. Conduit shall not be run over  
equipment or between spouting where possible or in such  
a way that may be hazardous to personnel, or provide an  
obstruction. Conduit routes which may be questionable  
shall be referred to the Engineer for a decision."  
Hammond testified that the routing for this conduit was not an  
approved routing and he was not consulted prior to the  
installation. He says that this conduit was run down spouting  
and across the floor to the location of the sensor. He rejected  
it on the grounds that it did not comply with the specifications.  
In my view FCC's initial installation contravened the  
specifications and it is not entitled to this extra.  
(h)DOCK PROGRESSORS  
637.  
Two progressors were required to be installed on the dock.  
In order to avoid a conflict with JJM's non-union workers and  
- 263 -  
FCC's union workers, it was agreed that FCC would work on  
weekends to try to install the progressors in August.  
the time constraints involved in working only weekends, it was  
also agreed that plywood templates would be used for setting the  
progressors. CWMM and UGG agreed that the premium time portion  
of this work and the time and materials required to fabricate the  
templates would be Change Order work.  
Due to  
638.  
On July 21 CWMM sent memo #232 requesting FCC proceed with  
'fabrication of the templates....on a time and materials basis.'  
FCC prepared the templates and began installing the progressors  
as instructed, on weekends in August. Time and materials were  
coded under FCC #90271 and requests for payment were submitted in  
August and September. On October 18 at the request of UGG and  
CWMM, FCC re-calculated this claim so that it included only the  
premium portion of the weekend work (and not the underlying  
straight time) and re-submitted a Change Order request to CWMM  
for the amount of work to that date.  
639.  
On November 6 and 7 FCC returned to work on the dock  
installing the progressors. FCC submitted a Change Order request  
for this portion of the work on November 8. On December 12  
Hawkins re-calculated the claim and faxed it to Atwell so that it  
could be discussed at a meeting in December. The calculation  
prepared by Hawkins included the November time, but only the  
premium time portion of the hours worked and the materials to  
- 264 -  
fabricate the templates. Hawkins calculated the claim to be  
$42,547.61.  
In March 1990 Mr. Whitaker sent a fax to Van Dyke, offering a  
reduction in the dock progressor claim to $39,998.90 by  
recalculating some of the labour rates and charging for only 40  
sheets of plywood although 50 were purchased. Whitaker's offer  
was not accepted by UGG.  
640.  
UGG agrees that FCC is entitled to be compensated for this  
extra. Hawkins gave evidence that some review was made of the  
amount being claimed by FCC. On the basis of Whitaker's  
calculation and the submission of FCC's counsel the claim is  
allowed at $39,998.90.  
(i)SALVAGE  
The Prime Contract specified that certain equipment  
would remain the property of UGG after demolition. The  
Prime Contract provided in section 2B.1 of the  
Specifications that:  
Note:  
i)  
Unless otherwise stated, all items removed,  
must be disposed of off the UGG property by  
the Contractor, in a legal manner.  
(emphasis added)  
641.  
UGG says this provision deals with disposal of items  
removed; it does not give the contractor title to all goods  
- 265 -  
removed. At the pre-award meetings, CWMM and UGG asked each  
tendering contractor whether they would be re-using any of the  
equipment specified for removal. Campbell gave evidence that  
this question was asked to determine whether the tendering  
contractors were going to salvage any of the equipment that they  
were taking out and re-use it in the Project. At the pre-award  
meeting on January 20 FCC advised UGG and CWMM that they were not  
planning on re-using or salvaging any of the equipment for re-use  
in the Terminal. At this meeting Derhouson asked whether UGG  
wished to keep any of the equipment. Van Dyke said no, if UGG  
personnel were given the option of keeping certain equipment,  
none of the equipment would ever leave the site.  
642.  
On February 21 Johnny Walker provided a quote to FCC  
for the demolition work which was subject to the following terms  
and conditions:  
Item no. 7  
Demolition Work.  
All salvageable material at the  
time of this tender to become the  
property of the successful bidder.  
FCC's subcontract with Johnny Walker, under "Article 1 - Work to  
be Done" referred specifically to the February 21 quotation.  
Walker understood that Johnny Walker was contractually required  
to remove all of the equipment off the property and after it was  
removed it became the property of Johnny Walker.  
- 266 -  
643.  
644.  
645.  
The March 2 site meeting minutes record:  
2.003  
A further review of owner retaining existing  
equipment was brought forward.  
A)  
B)  
FCC advised that the bid was based on certain  
salvage value of items was considered at tender  
time and through wrap-up negotiations.  
FCC requested a list for clarification from the  
client as to those items now being considered as  
'keepers', for evaluation.  
On March 6 FCC faxed UGG's list of 'keepers' to Johnny  
Walker which dismantled and removed the listed equipment and  
stored it for UGG on site. On June 6 Johnny Walker invoiced FCC  
for $49,033.00 for the salvaged goods kept by UGG, attaching an  
itemized list. Walker gave evidence of how the value of the  
equipment was calculated.  
In my view the language of the contract and the conduct  
of the parties was consistent with title to all salvaged items  
not specifically identified by UGG for retention becoming the  
property of the contractor. UGG was not entitled to retain  
equipment, other than that which was specified in the Prime  
Contract, without compensating FCC, in this case for the amount  
claimed by Johnny Walker in the amount of $51,484.65.  
(k)MISCELLANEOUS  
1. Metering Gates  
646.  
On August 9 CWMM sent memo #300 to FCC ordering the  
conversion of six gates to metering on a "Time and Materials"  
- 267 -  
basis. CWMM's August 8 fax to the site office noted that the  
work represented a "change in the work". FCC coded this work  
under #90344 and submitted requests for payment to CWMM in  
September and October. On October 30 FCC received an additional  
invoice from Westburn for freight costs associated with materials  
that had been provided for this work and invoiced by Westburn  
earlier. On November 9 FCC submitted a request for payment of  
the extra freight charge to CWMM. On November 13 UGG issued  
change order #109 for FCC's requests for payment that had been  
submitted in September and October. The November claim in the  
amount of $34.09 remains unpaid. UGG says FCC has failed to  
prove that this $34.09 invoice was in fact connected to the  
shipping of the six metering gates.  
647.  
Hawkins was the only FCC witness to give evidence on  
this extra. When asked in direct examination, whether he could  
tell what the Westburne invoice was for, he candidly answered "It  
appears to be an invoice for some materials from Westburne. I  
mean I can't specifically say what exactly the item was". When  
asked whether he knew if the invoice related to the conversion of  
the six gates to monitoring, Hawkins replied "I can't say for  
sure". Given the relative size of this claim in the context of  
this case, these answers were not surprising.  
- 268 -  
648.  
In my view the documents establish that this claim is  
likely connected to the shipping cost of the six metering gates  
and I allow it at $34.09.  
2. Dust Shed  
649.  
650.  
In its argument UGG admits liability for the principal  
amount of this claim in the amount of $439.34.  
3. Bulkweigher Valves  
On October 3, 1989 CWMM directed FCC by memo #476 to  
reconnect the compressed air supply to the UGG shop "A.S.A.P.".  
Marquis noted on the memo that this would be Change Order work  
and to "advise if you would like us to proceed on this EWO on a T  
& M basis".  
On November 27 FCC advised CWMM by FIR #262 that  
there was a significant amount of water in the plant's compressed  
air system that was "obviously effecting the operation of  
equipment such as the gates". Campbell gave evidence that  
bulkweigher solenoids had been damaged by the water in UGG's  
compressed air system. On January 12, 1990, CWMM sent memo #683  
to FCC directing repair of two damaged bulkweigher solenoids. On  
March 9, 1990 Western Scale invoiced FCC for this work and on  
March 30, 1990 FCC sent a request for payment for the amount of  
the invoice plus FCC's 5% fee for a total of $957.28 to CWMM.  
- 269 -  
651.  
UGG says that during construction FCC used its own  
compression system and that water got into the pneumatic lines.  
When FCC reconnected the UGG compressor water in the lines went  
directly to the scale and did some damage to the solenoids. UGG  
says that testing the hydraulic control systems was FCC's  
responsibility. Specification 15M.1 reads, in part:  
Testing of hydraulic control system and flow control  
valve initial settings shall be the responsibility of  
the general contractor through the hydraulic control  
contractor.  
652.  
Damage caused by FCC during the testing process is  
FCC's responsibility. However the damage in this case was caused  
not by the testing of FCC installed equipment, but rather the  
water which had accumulated in the UGG compressed air lines. In  
the circumstances, had CWMM expected FCC to bear the cost of the  
solenoid replacement, it should have done other than just issue a  
change order. This claim is allowed at $957.28.  
4. Additional Painting  
653.  
On February 28, 1990, Velvet Painting invoiced FCC for  
extra painting on the Project. A portion of the invoice, in the  
amount of $1,302.00 was for Change Order work to paint the entire  
side of the rail shed which had been coded under FCC #90749.  
Campbell acknowledged that the tender package did not call for  
painting the entire side of the rail shed.  
- 270 -  
654.  
Another portion of Velvet Painting's February 28, 1990  
invoice, in the amount of $591.00 was for Change Order work to  
paint the car haul sheaves and the cleanouts in the basement.  
This work was coded under FCC #90751. Campbell was asked on his  
examination for discovery whether this additional painting was  
done and why no payment had been made for it. His response, in a  
letter from counsel, was that the painting had been done but no  
payment had been made because of the late arrival of the claim.  
655.  
On May 18, 1990 FCC submitted two requests for payments  
to CWMM for the amounts invoiced by Velvet Painting and FCC's 5%  
fee. The first request was for $1,367.10 for the work coded  
under #90749. The second request was for $620.55 for the work  
coded under #90708. This claim is allowed.  
(k) FCC EXTRAS - SUMMARY  
C22/C25 Conveyors  
Conveyor supports  
Gates  
$ 3,825  
NIL  
$121,608  
$ 16,763  
$ 26,695  
$ 39,999  
$ 51,485  
$ 3,418  
Civil group  
Conduit  
Dock progressors  
Salvage  
Miscellaneous  
- 271 -  
656.  
FCC will recover $263,793 from UGG for its extras  
claims.  
In accordance with the interest section of this judgment, FCC is  
entitled to contractual interest at 10% calculated monthly  
commencing 30 days after it invoiced CWMM for the extras I have  
allowed.  
CMI ACCELERATION CLAIM  
LIABILITY  
657.  
CMI says that FCC instructed it to accelerate its work,  
and that FCC undertook to pay CMI for the costs of that  
acceleration program. FCC says it only agreed to seek  
reimbursement from UGG, that it never agreed to pay these costs  
and it never, expressly or constructively directed CMI to incur  
these costs.  
658.  
The law on express or constructive acceleration was  
discussed by this Court and the Court of Appeal in Emil Anderson.  
What is clear from a consideration of that case is that an  
obligation to pay costs for a direction to accelerate requires an  
express direction in writing signed by the owner or contractor  
directing the acceleration. Was there such an express direction  
in this case?  
JULY 21-AUGUST 10 PERIOD  
- 272 -  
659.  
On July 21 CMI advised FCC that it was accelerating its  
work, at an estimated cost of $25,650.00, in order to recover  
lost schedule time. This acceleration occurred in response to  
numerous prior delays and repeated verbal requests from Campbell  
to accelerate. CMI also accelerated its work in an effort to  
mitigate the increased costs that it was incurring as a result of  
the delays caused by others. However, there was no express  
written direction to accelerate from FCC or CWMM. Hence it is  
not recoverable as an acceleration expense except to the extent  
it was a reasonable response to the delays that CMI had  
experienced, which would permit recovery as an impact or  
mitigation cost.  
PERIOD AFTER AUGUST 10  
660.  
On August 11 CMI wrote to FCC to confirm that it would  
work overtime until August 31 at an estimated cost of $100,548.  
This letter also confirmed a discussion that had taken place that  
morning between Popowich and Skodje in which this overtime  
program had been discussed. Popowich attached to his file copy  
of the August 11 letter, notes that had been handwritten by  
Skodje, also dated August 11 in which Skodje calculated an  
overtime cost of approximately $86,226, using a different crew  
size and total hours. Popowich and Skodje have contrasting  
versions as to what was agreed at that meeting.  
- 273 -  
Popowich described the events surrounding the signing  
of that document in his examination in chief as follows:  
A
We discussed the overtime or proposed overtime  
program from August 12th through August 31 based  
on  
48 men in the field and 24 men in the shop. We  
had a  
subsequent meeting of that day whereby we agreed  
to  
work 40 men in the field and 24 men in the shop  
with  
some changes in the weekend work, as well. So the  
total agreed premium time was $86,226.  
And who did you agree with that with -- who did  
you  
Q
agree that with?  
A
Q
A
Mr. Skodje.  
Yes.  
And the breakdown goes 15 hours equals three weeks  
times five days, 25 and a half hours equals three  
Saturdays of eight and a half hours.  
Yes. And whose handwriting is that in?  
That was Mr. Skodje's.  
Q
A
Q
And then there is a reference "work schedule  
August  
11 to 31 inclusive."  
A
Q
A
Q
A
That's correct.  
And whose is that?  
That was his handwriting, as well.  
Yes.  
And we had both agreed on the document and signed  
the  
bottom right-hand corner.  
...  
Q
Well, what was said at the points in time when you  
and Mr. Skodje signed the document in the lower  
right-hand corner, sir?  
A
Well, he simply said: Let me sign this document  
in  
case I drop dead or something like that.  
...  
Q
What was your intention in signing this document,  
Mr.  
Popowich?  
A
Well, my intention was that it become an agreement  
to  
- 274 -  
perform the work as we had discussed.  
When my friend rose with his objection you said it  
was a substantial amount of money. You were in  
the  
Q
A
middle of your answer. Can you tell his Lordship  
about that?  
Again, it is a substantial amount of money being  
$86,226. It's premium time which we figured was  
compensable based on the fact that the equipment  
was  
late and we wanted to get the project back on  
schedule. Premium time had been aloud in our  
original tender and it was credited to extend the  
schedule.  
661.  
662.  
Skodje says that his handwritten note on August 11 was  
a commitment he extracted from CMI to work certain crew sizes;  
it was not a commitment from FCC to pay the extra costs shown on  
that document.  
This conflict can be resolved by considering the August  
11 letter FCC wrote to CWMM, which was not copied to CMI. In that  
letter, FCC enclosed CMI's July 21 and August 10 letters and  
stated that FCC had "committed to this undertaking". In my view  
a plain reading of that letter leads to the inference that what  
FCC was telling CWMM was that FCC had committed to pay CMI for  
the premium time which totalled at that time some $126,000. If  
Skodje's commitment was not to CMI's acceleration program but  
rather was to only the cost to FCC of supporting it, I would have  
expected his letter to contain some reference to FCC's forces;  
it does not. I accept Skodje's evidence that FCC had every  
intention of claiming this cost from UGG. This was why he wrote  
promptly to CWMM to advise of this. I also accept that CMI  
- 275 -  
probably understood that FCC would attempt to obtain  
reimbursement from the owner. However that does not alter the  
fact that, on the evidence, Skodje's handwritten note of August  
11 represents a written authorization of the overtime program  
proposed and agreed to by CMI.  
663.  
On September 1 CMI wrote to FCC and confirmed that it  
would continue to work overtime until September 25 at an  
estimated cost of $207,752. On September 2 CMI wrote to FCC with  
a clarification of the price of the overtime program, reducing  
the total cost to $185,603.  
664.  
665.  
On September 4 Popowich noted in his handwritten  
memorandum of his conversation with Skodje that the costs of  
acceleration had been agreed with Skodje in the amount of  
$142,800.  
On September 5 FCC wrote to CWMM indicating that "They  
(CMI) fully intend to be reimbursed for their costs". No copy  
was sent to CMI. Again if FCC was merely acting as a conduit of  
this claim to the owner, I would have expected FCC to have  
notified CMI that its claim had been forwarded to CWMM for  
consideration. By not so advising CMI, FCC allowed CMI to  
continue the overtime program in good faith and in the belief  
that its claim would be honoured. If it did not believe this to  
be the case FCC should have told CMI.  
- 276 -  
666.  
On September 7 representatives of FCC, CWMM and UGG met  
to discuss CMI's acceleration program. CMI was not notified of  
this meeting and no resolution was reached on the costs of the  
acceleration program as between FCC and UGG. On September 14 FCC  
again wrote to CWMM to seek "reimbursement" for the costs of the  
acceleration program. No copy of this request was sent to CMI.  
667.  
On September 21 CMI wrote to FCC confirming FCC's  
instructions to further extend the overtime program from  
September 25 to October 5 at a cost of $90,433. On the same day  
Campbell wrote to Skodje denying the owner's responsibility for  
payment of the CMI overtime premium. FCC did not pass this on to  
CMI. Again, FCC's conduct is not consistent with a party that  
merely agreed to forward the overtime claim for consideration. I  
conclude that was happening was that FCC had committed to the CMI  
program and was doing its best to secure reimbursement for itself  
from the owner.  
668.  
Van Dyke gave the following evidence in chief in  
reference to the notes of a meeting held on October 5:  
Q
A
And then a note for Ted it says "after lunch  
we discussed with CMI ... chose not to go through  
litigation, so made commitment."  
meeting  
Do you remember what that note reflects, what  
discussion that note reflects?  
That he had made a commitment to CMI that the  
overtime would be paid.  
669.  
On October 10 CMI wrote to FCC and stated as follows:  
- 277 -  
"Further to our meeting of Friday, a.m., October 6, 1989,  
and our subsequent telephone conversation at 3:00 p.m. of  
the same day, we wish to confirm your instructions received  
as follows:  
1.  
It was agreed that the owners will pay all  
premium time incurred by this company since  
the notification date of July 21, 1989. This  
payment will be made upon audit of CMI's  
actual payroll records by others.  
2.  
We are further instructed to carry on this  
premium time program until the project is  
complete or we receive further notifications  
of same to cease.  
Your acknowledgment of these instructions would be  
appreciated."  
670.  
Popowich described the events and discussions leading  
up to that letter, in his evidence in chief:  
Q
All right. Now, just with that background,  
Mr. Popowich has just indicated, my lord, that the  
thanksgiving long weekend was in fact October 7th,  
sat, 8th, Sunday, ninth, Monday. Can I ask you to  
turn to the document which is found behind the tab  
for October 10 this, sir.  
Now, this is a one page letter that you wrote  
to Mr. Skodje on or about that date?  
That's correct.  
A
Q
A
Q
And did you in fact send this to Mr. Skodje?  
Yes.  
There is a reference, again, to a fax stamp, and  
whose initials are in the fax stamp?  
That's mine.  
A
Q
Yes. All right now in this letter you say  
"further  
our  
to our meeting of Friday a.m. October 6th, 1989,  
subsequent telephone conversation at 3:00 p.m. Of  
the same day, we wish to confirm your instructions  
received as follows." Now tell his lordship  
what the circumstances were of the October 6th  
meeting what happened there? You went through  
Mr. Van dykes' notes. Tell his lordship what you  
did?  
A
Again, I was asked to be present during the  
morning  
- 278 -  
session of the October 6th meeting, which I did.  
The primary issue that was being dealt with was  
the  
overtime issue. After the meeting, I went back to  
the jobsite.  
So your evidence of yesterday was that the October  
6th meeting was at Foundation's offices in  
Q
Burnaby?  
that's  
A
Q
That's correct.  
Yes and you say you went back to the jobsite  
the UGG terminal?  
A
Q
A
That's correct.  
Go ahead?  
And at about three o'clock that afternoon, I  
called  
Mr. Skodje to see how they made out during the  
afternoon session of the meeting. We had to --  
Where were you when you made your telephone call?  
On the jobsite.  
Q
A
Q
A
Yes?  
We had to schedule our crews come Tuesday morning,  
which is October the 10th.  
Q
And did you have a telephone conversation with  
Mr. Skodje on that day?  
A
Q
A
Yes, I did.  
And what do you recall of that conversation?  
Well, my recollection is as written in the letter,  
item number 1 and item number two of October 10th,  
1989.  
Q
All right. Those two items say "it was agreed  
that  
21,  
the owners will pay all premium time incurred by  
this company since the notification date of July  
1989. This payment will be made upon audit of  
Crosstown's actual payroll records by others.  
Two,  
we are further instructed to carry on this premium  
time programme until the project is complete or we  
receive further notification of same to cease."  
Now who hold you that?  
A
Q
A
Q
Mr. Skodje.  
In the telephone conversation?  
That's correct.  
Was Mr. Skodje still in the October 6th meeting  
when  
or  
you talked to him at 3:00 p.m. On that day?  
A
I never asked him, but it didn't appear to be --  
he didn't appear to be.  
- 279 -  
Q
A
All right. Now, what does "will be made upon  
audit  
of Crosstown's actual payroll records by others"  
mean?  
Well, the scheduled overtime programme extended  
for  
a couple of months plus, and it was my belief that  
when payment of the overtime was to be made  
finally,  
that an audit of our records would probably have  
been the most likely way to quantify the  
outstanding  
overtime. And that was a suggestion that I had  
brought up at the morning session, and it was a  
discussion that we had at 3:00 p.m. On that  
afternoon.  
671.  
By October 10 CMI had incurred several hundred thousand  
dollars in overtime premium costs, which had been authorized  
orally and in writing by Skodje. However, on October 12 Skodje  
wrote to CMI advising that:  
"There has never been the implication that the owner  
will pay the total premium time incurred by your  
company." He concluded his letter by saying that "I  
trust that the foregoing clears up any misunderstanding  
that may have previously existed."  
CMI consequently ended its premium time program.  
672.  
FCC says that under the Subcontract CMI was to proceed  
with "Two Shifts, 5 days per week, as project requires in order  
to meet a Substantial Completion date of August 11, 1989" and  
that there is nothing in this language entitling CMI to any  
overtime worked during the "Two Shifts, 5 days per week".  
Because of this FCC says that CMI's choice in implementing an  
overtime program instead of two full shifts throughout the  
- 280 -  
Terminal is not a contractual claim that can succeed against FCC  
under the Subcontract. It contends that CMI elected to institute  
the overtime program rather than two regular time shifts in order  
to attract sufficient manpower to the job.  
673.  
However on August 11 FCC expressly agreed to pay the  
CMI acceleration program as evidenced by Skodje's hand written  
notes. While the program no doubt assisted CMI in attracting and  
keeping manpower on the site, CMI's manpower difficulty was  
caused by the project delays: the surfeit of sheet metalworkers  
when CMI originally planned to do its work had disappeared by the  
summer of 1989.  
674.  
Accordingly CMI is entitled to recover the impact  
portion of its overtime claim for the period prior to August 10  
and its provable overtime claim for the period after August 10  
from FCC.  
QUANTUM  
675.  
CMI calculates its overtime claim from its records.  
These show its personnel worked 7713 hours of field overtime plus  
2921 hours of shop overtime. If the 350 overtime hours included  
in various extra work claims are deducted from those totals, the  
balance of 10,284 reimburseable overtime hours at the premium  
rate of $24.59 per hour comes to $252,833.  
- 281 -  
676.  
The appropriate base week is the first issue to be  
considered when quantifying CMI's reimburseable overtime hours.  
This requires a determination of the hours that CMI would have  
worked, if it had not suffered the various breaches of the  
subcontract which forced it to work more overtime hours.  
677.  
The original July 31 substantial completion date was  
extended by UGG to August 31 in return for a reduced price.  
Although CMI originally planned to work seven, twelve hour days  
in the field, and re-calculated the project estimate January 23  
and 24 based on five, nine hour days, the extension of the  
schedule made these extended hours unnecessary, in CMI's  
estimation. I accept Popowich's evidence on this point and find  
that this enabled CMI to give FCC a $200,000 reduction in the  
subcontract price.  
678.  
In his January 23 and 24 re-calculation, Popowich used  
$33.25 per hour, reflecting five, nine hour days in the field and  
$30.64 per hour, reflecting two regular shifts plus a small  
amount of overtime in the shop. The $200,000 reduction was based  
on elimination of all labour costs beyond $28.50 per hour in both  
the shop and the field, as follows: 28,657 field hours x 4.75 =  
$136,120, and 24,076 shop hours x 2.14 = $51,522, both rounded  
up, to $140,000 and $60,000, respectively. These amounts were  
noted on the January 24 final sheet.  
- 282 -  
679.  
CMI's March 19 Job Cost Detail Report reflects CMI's  
revised labour budget at that time. All hourly labour was  
budgeted at the straight time rate of $28.50: 10,500 shop hours  
costing $299,250, and 24,333 field hours costing $693,490. An  
amount of $115,581 which had been included in field labour  
overtime was set aside as a contingency fund under the category  
"Field Supervision Overtime", for casual overtime and unexpected  
costs. CMI says this reflects prudent budgeting, not planned  
overtime.  
680.  
681.  
After adjustments, CMI's plan and budget called for no  
scheduled overtime.  
The subcontract as executed specifies "two shifts, five  
days per week, as project requires in order to meet a substantial  
completion date of August 11, 1989." It does not specify how  
long those shifts are to be, nor in view of the equipment and  
other delays was it possible, in any event, for CMI to finish by  
August 11.  
682.  
683.  
The ultimate issue therefore becomes whether CMI could  
have completed the project on schedule without overtime, if it  
had not been delayed and its work disrupted.  
On January 24 CMI estimated 24,076 shop and 28,657  
field hours on this contract. If one considers the field labour,  
- 283 -  
28,657 hours over the course of the 22 week duration of CMI's  
subcontract schedule, March 6 to August 11 this gives 1303  
manhours per week. On 37.5 hour weeks, this would would mean an  
average site manpower of 35 people. FCC's daily reports support  
this estimate; its records show CMI had 34 people or more on  
site beginning July 6, notwithstanding the evidence of a shortage  
of labour during this period.  
684.  
However, it is appropriate when assessing the quantum  
of this claim to consider CMI's decision to use welded flanges.  
I have earlier found that was a factor in delaying CIM's work and  
hence in part may have contributed to the overtime worked.  
685.  
686.  
In the productivity section I refer to the significant  
overrun in CMI metal purchased. An allowance must be made for  
the extra shop hours because of this factor.  
While I conclude that CML would have been able to  
complete its contract on time without substantial scheduled  
overtime, if it had not been delayed, after making appropriate  
allowances for the foregoing items I would assess the quantum of  
CMI's recoverable acceleration claim at $185,000.  
687.  
The next issue is the extent to which FCC is entitled  
to be indemnified by UGG. To the extent that the CMI  
- 284 -  
acceleration was a reasonable response to delays caused by UGG  
and CWMM, those costs are recoverable impact costs. In its  
submissions FCC supports CMI's acceleration claim to the extent  
that such acceleration occurred on weekends and outside the 5 day  
week on which CMI based its tender. FCC calculates the field  
portion of the weekend overtime at approximately $85,000 and says  
that represents the total of the impact expense suffered by CMI  
and proved at trial.  
688.  
Overtime, if caused by delay, is an appropriate impact  
cost according to the judgment of the Supreme Court of Canada in  
B.G. Checo. However overtime directed by the prime contractor is  
not payable by the owner in the absence of an agreement, express  
or implied, to do so. On its evidence, FCC never obtained the  
agreement of CWMM or UGG to the CMI acceleration program.  
Therefore FCC cannot succeed in a claim for indemnification  
except to the extent that CMI's acceleration program can be  
characterized as an impact cost caused by the acts or omissions  
of CWMM or UGG.  
689.  
In my view and notwithstanding the submissions of FCC I  
consider that CMI's net acceleration claim can be accurately  
characterized as an impact claim. UGG recognized this when Pope  
stated to Skodje at the Cannery meeting that UGG would see to it  
that CMI "did not get hurt". CMI will therefore recover $185,000  
- 285 -  
from FCC. In my view FCC is entitled to indemnity of 75% of this  
amount or $138,750 from UGG and CWMM.  
CMI PRODUCTIVITY LOSS CLAIM  
690.  
Relying on the analysis of its expert witness John  
Dawson-Edwards, CMI advances a claim for lost productivity in the  
amount of $741,977. Dawson-Edwards' analysis was not done by  
taking CMI's original estimate and plan of work and comparing it  
to the actual time expended on the job. His analysis for CMI's  
field work consisted of locating a base line of relatively  
undisrupted work in the wheat reclaim area, determining the  
labour productivity in that area, and then applying that labour  
productivity to other areas where delay impacts were said to be  
caused by the various factors described in his report: extended  
overtime, stacking of trades, and "stop and go" work disruptions  
caused by interferences. The loss of productivity was then  
determined by calculating the difference between the labour  
productivity in the base line area and the impacted areas.  
691.  
He testified that various adjustments were necessary to  
ensure that he was comparing "apples with apples" - such as the  
elimination of overtime impacts from the base line area, the  
elimination of costs already reimbursed or reimbursable as  
- 286 -  
ordinary extra work, and also taking into account the effects of  
a learning curve.  
692.  
The principle of productivity loss is easy to describe  
but difficult to quantify. Derhousen addressed the principle in  
cross-examination as follows:  
Q
Now, I want to talk to you just generally, sir, about  
your experience in the construction industry and this  
morning we touched briefly upon -- we touched briefly  
on what you described as a composite work force when  
you were talking about a number of trades working in  
the basement area of this particular project. You  
recall I referred to it as stacking of trades and you  
said, no, you are more familiar with the phrase  
composite work force?  
A
Q
Seemingly the two terms are the same.  
Yes. And you will recall that at the end of  
our discussion there you said that in some  
circumstances in those cases you would have a loss of  
productivity?  
A
Q
Where there's -- where there is a large amount, a  
large  
number of workers in a small area, this is  
natural that you are going to have loss of  
productivity.  
All right. I want to ask you about a couple of other  
phenomenon in the construction industry and just have  
you tell me whether or not it's your opinion based on  
your experience that would be a loss of productivity.  
Now, what about circumstances, sir, where crews of a  
particular trade work scheduled over time over an  
extended period of time, say many weeks. Would you  
from your experience that in fact there is a loss of  
productivity that occurs?  
agree  
A Yes, there would be.  
Q What about circumstances, sir, where on any  
construction  
project an interference occurs, say, for example,  
a crew  
of work men are working in a particular area and  
of some issue beyond their control they are forced to  
down tools and to go and move to another area, perhaps  
the same sub area of the project but to another area.  
Are you familiar with the concept of what is called  
and go in the construction industry?  
because  
in  
stop  
A I know what the term means, yes.  
Q Yes. Would you agree with me, sir, that if there  
are  
repeated occasions of what I've called stop and go  
- 287 -  
that there would be a loss of productivity?  
A It would effect the productivity.  
693.  
Skodje similarly testified in cross-examination:  
Q -- B. It's the overtime premium, and you identify  
your views on a productivity loss due to extended  
overtime?  
A Yes.  
Q What was your opinion in November 1989?  
A The percentage?  
Q Yes.  
A Twenty percent.  
Q Twenty percent. And that was your honestly held  
opinion at that time?  
A Yes.  
Q Now, Mr. Popowich deals with the issue, as you're  
quite correct in saying, the issue of productivity in  
several other subissues. Referring back to the  
table  
of contents, he refers to stop and go, stacking of  
trades, unavailability of skilled manpower. Do  
you see those items?  
A Yes.  
Q And you expressed an opinion on each of those to  
the owner as well?  
A Yes.  
Q And in November of 1989 did you, in fact, believe  
that Mr. Popowich's company had suffered losses as  
a
result of stop and go?  
A To some extent. That's what I say here.  
Q Yes. And did you believe that Mr. Popowich's company  
had suffered losses as a result of stacking of  
trades?  
A Once again, to a revised extent.  
Q Yes. And did you believe that he had suffered  
losses as a result of an unavailability of skilled  
manpower?  
A To some degree.  
Q I see. And then Mr. Popowich made references to  
the  
- 288 -  
extended duration of the project and the fact that  
he  
had to have his services and his site trailer and  
so  
on on site for a longer period than originally  
planned and he claimed some cost for that. Did you  
have an opinion with respect to their validity?  
A Yes.  
Q And that was?  
A That it was valid.  
Q Yes? And then he had a claim for financing  
because  
he was on the project longer, and did you believe  
that he had a valid claim for that?  
A We suggested an amendment.  
Q Yes. But you believed that he did have a claim  
for  
financing?  
A An adjusted one, yes.  
...  
Q And you passed all that information along to the  
owner?  
A Yes.  
694.  
Stacking of trades occurs when the addition of more and  
more manpower to a project reaches a point of diminishing  
returns, beyond which productivity suffers a decline. When Steel  
was asked in chief: "couldn't you put more men in the cleaner  
deck?" He replied: "Not unless you wanted to play cards. I  
mean there is only so much room, you know, for people". CMI's  
witnesses testified and Skodje agreed that productivity did  
indeed suffer on this project, particularly in areas like the  
cleaner deck and the basement.  
695.  
The work disruptions or "stop and go's" can be seen  
from the 91 CMI "Requests for Clarification". Steel testified  
- 289 -  
that the lack of crucial information often brought work to an  
immediate halt in the affected area. This typically arose when  
the crew attempted to install a component, but found that the  
component either would not fit, or was inaccurate in some other  
way. Popowich testified that when such an interference  
occurred, the crew was brought to a standstill. In order to  
carry on with the work, the crew needed direction as to how to  
overcome the problem. If the required information was not  
immediately forthcoming, as it generally was not, CMI's crews had  
to shift to other work, if possible. Popowich, Todd and Steel  
testified that it often took several hours, or even days, to  
receive an answer to these RFC's and questions, and to reorganize  
the crews. As one example, Steel testified that on June 28 he  
sent FIR #98 to CWMM requesting instructions as to what to do  
about the fact that a gate that was to be installed by CMI would  
interfere with one of the legs on the scale floor. CWMM took 9  
days to respond to that request. When asked whether he knew why  
it took so long to respond, Steel said:  
"I have no idea, but I can tell you this,  
that it certainly stopped Crosstown from  
carrying on with that work and they couldn't  
afford to stop."  
696.  
Of course CMI does not contend that it lost 9 days as a  
result; its forces did not sit for 9 days doing nothing while  
awaiting a response. However it is illustrative of the principle  
- 290 -  
that such an interference would necessarily result in some lost  
productivity.  
697.  
In another example, Steel testified that on August 1 a  
spout could not be installed as drawn because it interfered with  
conveyor C25. The CWMM response followed in 7 days. As to the  
effect of this, Steel stated:  
"So we are talking about critical path trade  
here and it's taken seven days to tell the  
fellow this and he's the guy that's under the  
gun to get the job finished."  
698.  
When Popowich reviewed the RFC's in detail at trial, he  
gave evidence as to the number and scope of these disruptions. A  
number of these requests for information caused the work in  
question to be suspended for several days. The first disruption  
CMI encountered on April 4 caused a delay in the specific work  
involved that lasted 10 days. Several others lasted somewhat  
longer.  
699.  
In addition to the RFC process, on June 14 CMI  
implemented a process of fabricating priority or "emergency"  
fittings in its shop. This arose from the increasing frequency  
of the need for these emergency fittings as interferences were  
encountered during field installation. By the conclusion of the  
project, CMI had fabricated over 300 priority fittings.  
- 291 -  
Rhodes testified in chief as follows:  
Q
Whenever Crosstown ran into a problem where they  
required clarification in order to proceed with  
their spouting activities, did you make any  
observation as to whether or not that particular  
crew stopped work, continued work, moved  
elsewhere?  
A
Both situations. Sometimes the -- sometimes they  
had to stop the work, sometimes they had to do  
what was required to correct the situation and  
sometimes they -- like I say, they had to stop  
the work and do something else while they were  
waiting for those pieces to arrive. If it was  
something that hadn't been caught aheod of time,  
something that came up while the crew was working  
on it, both things happened.  
700.  
Steel gave evidence about the effects of the frequent  
design information requests, and the delayed responses received  
from CWMM:  
Q
A
What affect was that having on your job?  
Well, it was very detrimental. You know, I think  
you have to know that it's important in  
to build up a momentum. It's really  
build up enthusiasm and speed and when you  
do something right away there is a  
construction  
important to  
start to  
question you  
you lose the  
can't do it, you have to stop,  
momentum, you lose the morale. Things are -- it  
isn't good for a contractor.  
701.  
Steel said this about interferences when he was asked  
what happened when a CMI crew arrived with a spout that didn't  
fit:  
Q
A
And could it stop that crew for a number of hours?  
Certainly it would stop them for a number of  
hours,  
possibly cause the relocation of the crew to  
- 292 -  
elsewhere.  
702.  
Steel gave evidence about design discrepancies which  
forced him to pull crews from an item of work:  
Q
A
Did you have problems like that daily or weekly or  
monthly, how often?  
All of the above.  
703.  
704.  
Steel gave further evidence in chief:  
Q
Does doing the work out of your preferred sequence  
generally have any impact on the completion time  
or  
your productivity?  
Yes, it would.  
A
Todd described how a priority was handled on arrival at  
the CMI Burnaby shop, how a priority was inserted into the flow  
of the work, and the disruption that this caused to the flow. In  
his evidence he estimated the effect of such an event: it could  
disrupt 3 men for a day, sometimes up to 45 manhours. He said  
that sometimes priorities had to leap-frog one another.  
705.  
At trial Dawson-Edwards, Skodje and Derhousen testified  
that scheduled overtime and weekend work causes a loss of  
productivity. CMI did not delay in seeking reimbursement for the  
cost of this lost productivity: when it wrote to FCC on  
September 1 and September 21 it requested reimbursement of the  
overtime premiums. The factor used at that time by CMI for its  
loss of productivity was 28%.  
- 293 -  
706.  
FCC agreed that CMI incurred losses of productivity due  
to the extended hours worked by CMI personnel on this project;  
Skodje testified that it was his opinion in November 1989 that  
the appropriate factor to quantify that loss was 20%.  
DAWSON-EDWARDS REPORT  
707.  
Dawson-Edwards' report states that a calculation of  
productivity losses is most accurate where the analysis is based  
on a comparison of data generated on the actual project in  
question. In other words, this is the best "yard stick" by which  
to judge productivity losses. By this method, the difficulties  
that can arise in selecting the most appropriate study or work  
"model" to use as a "yard stick" are avoided.  
708.  
Such an analysis however depends on adequate data being  
available and on the existence within that data of an appropriate  
base line sample. Dawson-Edwards selected the wheat reclaim area  
as such a baseline. It was relatively free of design problems,  
work delays, interferences and other problems found on this  
project. In his report he calculated the total cost to CMI of  
productivity losses on the project at $741,977.  
709.  
However, in my view, there are a number of factors  
which call into question the assumptions used by Dawson-Edwards  
in his report.  
- 294 -  
710.  
711.  
712.  
His underlying assumption was that CMI could have  
completed its work within the hours allocated in its estimate.  
The resulting overexpenditure of hours was attributed solely to  
the fault of others. He conceded at trial that his task was to  
find the "causes" for this overexpenditure and that he could not  
objectively determine how many hours were lost by each of the  
causes he identified. In addition to relying on the field  
productivity achieved in the wheat reclaim, he used the  
productivity from CMI's Alberta facilities as the basis for his  
shop productivity comparison.  
The work in the wheat reclaim was considerably  
different than the work elsewhere in the project. The wheat  
reclaim area was constructed using 4 piece spouting while 2 piece  
spouting was used in the remainder of the project. Although it  
requires more field assembly time, 4 piece spouting is more  
flexible and hence somewhat more forgiving. Small, on-site  
adjustments can easily be made in the field. It is physically  
less demanding since the pieces are smaller. Much of the  
spouting in the wheat reclaim was pre-existing spouting, which  
was reused.  
The wheat reclaim area was less congested than other  
areas (excluding the bin floors). The wheat reclaim area did not  
require substantial scaffolding or heavy temporary supports. The  
wheat reclaim spouting was installed with a smaller crew with few  
- 295 -  
other trades present. It was generally smaller in cross section  
than spouting elsewhere in the terminal. Significantly, in the  
wheat reclaim area, CMI was able to confirm actual dimensions  
prior to installation. Finally, the wheat reclaim area contained  
a relatively small proportion of the gates which Crosstown agreed  
to install.  
713.  
While Dawson-Edwards contends that the lighter weight  
of the wheat reclaim spouting offsets the apparent advantages to  
CMI in using it as a baseline, I consider that the many  
differences outlined above make unreliable the use of the wheat  
reclaim as an appropriate baseline underpinning CMI's field  
productivity loss.  
714.  
Dawson-Edwards contends that CMI experienced an overrun  
in the Burnaby shop totalling 9,756 hours (revised upwards at  
trial to 10,698 hours). He concedes that "no reports or figures  
exist to be able to calculate the changes in shop productivity  
over time." At CMI's suggestion he reviewed the productivity of  
the Alberta companies "to provide some insight into the accuracy  
of its estimating techniques." He found that the Alberta  
companies met their fabrication estimates. He concluded at pp.  
75-79:  
"... As a result, Crosstown claims the difference  
between the estimated shop hours and the actual shop  
hours as the effect of the priority fabrications and  
- 296 -  
scheduled overtime on the overall Burnaby shop  
productivity."  
715.  
However there was a large discrepancy between CMI's  
estimate and the records of actual metal used in its Burnaby  
facility. The February 15, 1991 Job Cost Detail Report shows an  
actual cost of $226,041 against a budgeted figure of $122,826.  
Rather than attributing the extra hours to the effect of the  
priority fabrications and scheduled overtime, UGG says the  
following may account for many of the extra fabrication hours:  
(a) the fabrication estimate was based on "net" as opposed to  
"gross" weights: that may account for over 2,500 hours in the  
Burnaby facility;  
(b) CMI allowed only .05 hrs/lb. for fabrication of twist  
fittings: that may account for 750 hours;  
(c) the necessity to use continuous seam welds required 1,000  
extra hours;  
(d) CMI grossly underestimated its materials.  
716.  
Other hours may be accounted for by the fact CMI  
fabricated some of the special fittings for the dust collection  
system, that some 400 hours of remedial work, which foremen are  
reluctant to record, are recorded on the time cards, and that all  
of the priority work was fabricated in the Burnaby shop.  
717.  
In my view the shop productivity achieved by the  
Alberta companies is a questionable guide to the productivity  
- 297 -  
that should have or would have been achieved in Burnaby. CMI  
subcontracted out the ducting with which it was familiar and  
which is not comparable to spouting. It also chose to contract  
out the bin floor spouting, which Howard Popowich characterized  
as "simple, straight spouting" consisting of "large, heavy  
pieces" and having no twist fittings or elbows to speak of. That  
exercise left the more complex fabrication work for CMI's Burnaby  
shop. While it made good sense to have this complex work carried  
out locally, the significant differences in fabrication  
complexity make it difficult to measure what the Burnaby shop  
would have achieved by using the Alberta results.  
718.  
719.  
This evidence leads me to conclude that while the many  
priority fittings required did impact on CMI's Burnaby shop  
productivity, CMI has not proven that the unexplained overrun in  
material was all caused by the priority fabrications.  
Productivity loss claims in construction cases have  
been rejected in a number of recent cases for want of proof. An  
opinion of Dawson-Edwards was rejected for lack of causation by  
Gibbs J. in Derco Industries v. Grimwood (1986), 20 C.L.R. 174 at  
191:  
"... I am not convinced by the case put forward by  
Grimwood. The project was plagued by delay-causing  
events from start to finish. Notwithstanding the  
valiant tracing attempts by Mr. Dawson-Edwards, in my  
opinion, taking into account the `ripple' effects,  
- 298 -  
there has not been established a causal chain which  
translates a particular delay into a specific number of  
extra hours or days required for completion."  
720.  
A claim for loss of productivity in connection with an  
acceleration claim was also rejected by MacDonald J. for lack of  
probative evidence in Emil Anderson Construction Co. v. British  
Columbia Railway Co. (1988), 28 C.L.R. 90 at p. 132 (B.C.S.C.):  
"I should add, for the benefit of the parties and a  
higher Court, that had this claim [acceleration] been  
allowed I would have rejected the claim for loss of  
productivity (4.5.7) on the ground that the  
calculations which support it may be quite well founded  
and correct, but cannot be considered in a vacuum. It  
is any increase in the loss of productivity between 24  
and 8 and 6 and 1 which is the question. In the  
absence of a comparison of productivity between those  
two types of work schedules on a given project, an  
award of $156,721.47 under this head would in my view  
be much too speculative."  
721.  
Macdonald J's language illustrates the difficult nature  
of this type of claim. As opposed to an extras or an  
acceleration claim, a productivity claim is a claim for the  
marginal cost increases suffered by a contractor because of the  
faults of others. It is a claim that must be calculated by  
comparing what might have been or what productivity might have  
been achieved with what in fact occurred. The judicial  
disinclination to award damages for lost productivity is no doubt  
founded on the inherent unreliability of this type of analysis.  
- 299 -  
722.  
For the reasons set out above I am unwilling to accept  
Dawson-Edwards loss calculation. In my view a productivity loss  
claim should be supported to the fullest extent possible by  
evidence as to what was occurring as the job progressed. If  
employees sit idle because materials do not arrive or, on  
arrival, do not fit, the loss of time can be documented. If  
employees are forced to move to another area, the time lost in  
that exercise can also be recorded. If the pace at which  
employees complete their tasks is reduced because of extended  
overtime hours, that as well can be noted by supervisors at the  
time. No such evidence was led by CMI.  
723.  
I return to what I said at the outset of this section  
of the judgment: productivity loss claims are simple in  
principle but difficult in application. To the extent that CMI  
failed to keep the necessary evidence at the time of the impact  
of the factors which it says caused it to lose productivity, it  
must bear the consequences of such lack of proof.  
724.  
However to the extent there is evidence that  
establishes that the acts or omissions of the other parties were  
the proximate cause of a CMI productivity loss, I must assess  
that loss as best I can on that evidence. In respect of damages,  
the Court of Appeal said in Begusic v. Clark Wilson & Co, at pp.  
286 and 290:  
- 300 -  
725.  
The fundamental rule, as is often described,  
is stated in many cases but none more clearly  
than by Lord Blackburn in Livingstone v.  
Rawyards Coal Co. (1850), 5 App. Cas. 25  
(H.L.), a tort case, where it was stated at  
p. 39 that:  
...where any injury is to be compensated by  
damages, in settling the sum of money to be  
given for reparation of damages you should as  
nearly as possible get at the sum of money  
which will put the party who has been  
injured, or who has suffered, in the same  
position as he would have been in if he had  
not sustained the wrong for which he is now  
getting his compensation or reparation.  
...  
The assessment of damages is not a  
precise science; it is not even a  
calculation. Having seen the difficulties  
experienced by the learned trial judge, we  
are in the position described by Megaw L.J.  
in Dodd Properties (Kent) Ltd. v. Canterbury  
City Council, [1980] 1 W.W.R. 433, [1980] 1  
All E.R. at 934 (C.A.), where he said:  
In any case of doubt, it is desirable  
that the judge, having decided provisionally  
as to the amount of damages, should, before  
finally deciding, consider whether the amount  
conforms with the requirement of Lord  
Blackburn's fundamental principle. If it  
appears not to conform, the judge should  
examine the question again to see whether the  
particular case falls within one of the  
exceptions of which Lord Blackburn gave  
examples, or whether he is obliged by some  
binding authority to arrive at a result which  
is inconsistent with the fundamental  
principle."  
726.  
In this case, I must make an award that will "as nearly  
as possible" put CMI into the position it would have been in but  
for the acts or omissions of the other parties. In so doing I  
- 301 -  
must consider the evidence that is available in support of this  
claim.  
In this case there is evidence that CMI was impacted by the  
factors which it identified. The interferences and resulting  
"stop and goes" necessarily reduced CMI's productivity. Not all  
of these were caused by the other parties; some were caused by  
the errors of CMI's forces. After allowing for such CMI induced  
causes, I assess CMI's loss caused by the faults of the other  
parties at an average of 8 manhours per disruption and would  
allow $145,696 for this item.  
727.  
728.  
729.  
Skodje's estimate in November 1989 of CMI's  
productivity reduction caused by the extended overtime was in the  
order of 20%. I would accordingly allow 20% of the allowed  
acceleration claim of $245,233 or $49,046.  
CMI's loss due to stacking of trades and the  
unavailability of skilled manpower is, in my view, virtually  
impossible to quantify in the absence of supporting evidence.  
These items are disallowed.  
Based on Todd's evidence I accept that the requirement  
to fabricate priority fittings did disrupt CMI's Burnaby shop  
work and cause a productivity loss. After discounting for the  
uncertainties outlined above with respect to the shop portion of  
- 302 -  
this claim I would assess CMI's loss at an average of 10 manhours  
per priority or $85,380.  
730.  
731.  
In the result I assess CMI's recoverable damages due to  
productivity losses from FCC at $280,122; FCC is entitled to  
indemnity from UGG and CWMM of $210,091.  
CMI EXTRAS  
CMI claims a total of $497,899.00 for the cost of extra  
work.  
These extra work claims can be categorized as follows:  
Design Changes  
$177,615.00  
Scope of Work  
$194,917.00  
Interferences  
$ 77,118.00  
Deficiency Program  
$ 47,613.00  
Miscellaneous Extra  
$
636.00  
TOTAL EXTRAS  
$497,899.00  
THE PROCEDURE REGARDING EXTRA WORK  
The following are the relevant contractual provisions:  
732.  
CMI's Subcontract, Article III(e)(i) Payment of Changes:  
"(i) The Prime Contractor may at any time by written  
order to the subcontractor make changes in, additions  
to, and omissions from the work ... and the Sub-  
Contractor shall promptly proceed with the performance  
of this Sub-Contract Agreement as so changed. ... Any  
increase or decrease in this Sub-Contract price  
resulting from such changes in or additions to the work  
- 303 -  
shall be agreed upon in writing by the parties hereto  
and the valuation of such changes shall be determined  
in accordance with one of the following methods or any  
combination of same:  
1. In accordance with the Prime Contract. ...  
General Condition 14:  
"No work or changes in the specifications or other  
contract documents or work extra to that originally  
contracted for shall be undertaken or commenced without  
prior written authority from the Prime Contractor".  
733.  
I have earlier set out the provisions of GC 12 in the  
prime contract which deals with valuation and certification of  
changes in the contract work in the FCC extras portion of the  
judgment. As also set out earlier this procedure was not  
followed as set out in the April 4 site minutes which recorded at  
Item 7.012:  
"Procedures for changes: CWMM advised that for the  
time being they will continue to issue memos on a daily  
basis to deal with field changes. Detailed drawings  
requiring changes will be issued with CCN [Contemplated  
Change Notice] with instructions to price first or to  
proceed with the changes and price later."  
734.  
This direction never changed. Each of the parties  
chose not to comply with the requirements of their respective  
contracts regarding changes to the work. Because of the number  
and frequency of changes to the work and the schedule, the  
parties adopted the procedure set out in Item 7.012 above which  
was to proceed with the extra work as instructed, without regard  
to whether it was a "change", immediately on receiving  
- 304 -  
instructions to do so. The resolution of whether the work  
ordered was a change or not and the valuation of that change, was  
left for later resolution. On this project that became  
problematic.  
735.  
Steel's April 7 Daily Report notes that "We (FCC)  
recommended to CMI that they submit all changes in the form of a  
quotation between the tender drawings and the construction  
drawings so we could process them and keep the consultant aware  
of the cost changes that he is making". CMI complied with this  
request.  
736.  
737.  
Campbell gave evidence at his discovery that the formal  
extra work procedure was not followed "to save time" and that "it  
did happen" that the parties did not follow the formal extra work  
procedure.  
FCC says that CMI's unpaid Change Orders, save for the  
"A" versus "M" drawing issue which will be discussed below, are  
all pass through Change Order claims since all of the work was  
directed by CWMM and not FCC. However where FCC directed "extra"  
work, such extras are recoverable under the subcontract  
regardless of whether they are extras under the prime contract.  
738.  
There are 3 general issues to be considered with  
respect to CMI's extras claims:  
- 305 -  
1. Can CMI recover the cost of bin floor spouting extras  
fabricated by CMI's Edmonton affiliate?  
2. Material cost  
3. Labour rate  
EDMONTON FABRICATION COSTS  
739.  
The bin floor spouting including extras were fabricated  
by CMI's Edmonton affiliate. Popowich testified that no money  
was owed by CMI to its Edmonton affiliate. In re-examination,  
CMI's counsel attempted to lead evidence that money was in fact  
owed. I ruled that CMI could not, at that stage in the trial,  
amend its claim to include monies said to be owed to its Edmonton  
affiliate because throughout the pretrial discovery process CMI  
had refused to answer any questions related to CMI's Edmonton or  
Calgary affiliates on the basis that those companies were not  
parties to this action.  
740.  
However, in my view, CMI is entitled to recover a  
reasonable price for this work. The ultimate issue with respect  
to claims for the extra fabrication work performed in Edmonton is  
the reasonable price for the work not its cost. Considering the  
change provisions of the prime contract, the changes were ordered  
by CWMM either under GC 11 or under the modified procedure set  
out in the April 4 minutes.  
- 306 -  
741.  
CG 12 contemplates 3 methods of valuing extras. In this  
case the changes were not ordered to be valued under GC 12.1(c),  
"by cost and a fixed or percentage fee". Thus their value could  
only have been intended to be determined under 12.1(a) or (b).  
There are no unit prices set out in the contract, so the  
valuation must have been intended to be by 12.1(a) "estimate and  
acceptance in a lump sum" or 12.1(b) "by unit  
prices...subsequently agreed upon". Neither of these provisions  
refers to costs; both refer to negotiated prices.  
742.  
Because UGG chose not to comply with the contract and  
failed to have CWMM value the changes according to the contract,  
the "value" of such changes were not paid during the course of  
the work. Also as a consequence, CMI was not obliged to comply  
with CG 12.5 and "keep accurate records of quantities and costs  
of such work". No dispute of the nature referred to in CG 12.5  
arose until after the Edmonton fabrication work had been  
completed.  
743.  
UGG chose to deviate from the contract terms for the  
ordering of extras. Because of time constraints and the number  
of changes that decision was understandable. However, having  
given up the right to have the extras valued in accordance with  
CG 12.1(c), UGG cannot now argue that the extras should be valued  
on a "cost" approach which it chose to give up in the early  
stages of the project.  
- 307 -  
744.  
The real issue is whether the CMI extras should be  
valued on the basis of the CMI quotations submitted at the time  
which were to form the basis of a negotiated settlement or on a  
cost basis using the CMI tender calculations as argued by UGG and  
FCC. Using the CMI quotations could produce an assessment based  
upon figures which might not have been accepted as presented had  
the other parties negotiated a settlement at the time. However,  
because that did not occur, CMI is not to be penalized for any  
lack of supporting evidence. Similarly, a cost approach cannot  
be the basis since the defendants elected not to follow the  
contract's provisions which allowed this form of assessment.  
745.  
In my view, the intention of the parties at the time of  
the April 4 site meeting was that changes were to be proceeded  
with on the assumption that reasonable prices would be  
negotiated. CMI's position throughout was that $6.70 per pound  
was a reasonable price for new spouting. There was no admissible  
evidence tendered contra. Hence I find that CMI is entitled to  
compensation for the bin floor extra spouting on that basis.  
MATERIAL COST  
746.  
CMI priced its metal cost at 55 cents per pound. A  
series of 6 handwritten documents were put to Howard Popowich  
during his cross-examination which appear to contain tallies of  
steel quantities and prices paid to a number of steel suppliers.  
- 308 -  
If the amount of steel shown is divided by the total price shown,  
the per pound cost figure is 30 cents.  
747.  
Howard Popowich did not recognize the handwriting on  
these documents, nor the documents at all. In his words: "I  
could have flipped through it but it doesn't mean anything to  
me".  
I do not know what these documents are or what they  
represent. I do not accept FCC's characterization that they are  
business records. I am unable to conclude from these documents  
that CMI in fact paid 30 cents per pound for steel.  
748.  
I observe once again that had UGG wished to have extras  
priced on a cost basis, it could have elected to follow the  
provisions of CG 12.1(c). It didn't and hence the extras must be  
valued on a "reasonable price" basis. In 1989, CMI prepared its  
takeoffs for its extra work claims showing a material cost of 55  
cents per pound. A number of its extras claims calculated on that  
basis were accepted and paid. If any of the other parties wished  
to take issue with the reasonableness of that figure, they should  
have done so at the time.  
LABOUR RATES  
749.  
FCC says CMI is not entitled to recover more than  
$44.14 per hour for labour in the field inclusive of overhead and  
profit and $41.00 for time and materials work. On June 19 CMI  
agreed in a letter to FCC that its rate for force account work  
- 309 -  
would be $41.00 per hour, which was the same rate that FCC had  
agreed to charge UGG for its forces. However, CMI's letter also  
said: "As further agreed all lump sum quotations will remain at  
the rate of $44.14 per hour".  
750.  
In lump sum quotations submitted on the project, CMI  
used a field labour rate of $42.56 which reflects the 9 hour days  
being worked, exclusive of profit and overhead. Shop labour was  
charged at $45.00 per hour. To the labour and material was added  
10% for overhead and to that total a further 10% for profit.  
751.  
It is clear that when it submitted its extras claims  
CMI anticipated that there could be a element of negotiation on  
the labour rate. That was illustrated by an answer Popowich gave  
at trial to FCC's counsel: when asked about the $42.56 rate and  
why $41.00 wasn't used, Popowich replied that if he could get the  
claims settled he would gladly reduce his claim to $41.00.  
752.  
Another factor I must consider is that there is a  
degree of overlap between the CMI extra claims with the hourly  
rates calculated on a composite basis reflecting the 11/2 hours  
of overtime per day being worked and the CMI overtime claim dealt  
with separately in these reasons. CMI says that if it is found  
to be entitled to extras for which it has claimed overtime  
amounts, its overtime claim should be reduced accordingly. I  
- 310 -  
have chosen to make this adjustment by subtracting the overtime  
component included in the claimed extras.  
753.  
754.  
755.  
In its argument UGG seeks to have applied an "addition  
formula" for reimbursing CMI which is based on its arrangement  
with FCC for extras. It says 30 cents per pound should be  
allowed for material, $2.00 per pound on painting and hauling and  
a labour rate of $44.35 per hour to fabricate and install the  
materials with hours calculated in the same manner as CMI's  
tender.  
However there is no basis in the contract or  
subcontract or the evidence for such a calculation. The prime  
contract provides that FCC is entitled to a 5% fee on all  
materials and subcontractors. It does not provide that  
subcontractors would be paid any particular rate, that they would  
not be paid for expendables, nor that they would not be paid for  
their overhead and profit.  
In this case CMI provided quotations at the time for  
each item of extra work. It intended these to form the basis of  
negotiations with UGG as to reimbursement to CMI for the cost of  
performing the extra work. In some cases these quotations were  
accepted, including quotations submitted in the same format as  
quotations which have not been accepted. In many cases CMI never  
received a response.  
- 311 -  
756.  
I do not know what the parties would have negotiated at  
the time had the other parties elected to bargain with CMI and  
had they reviewed the CMI takeoffs and other supporting claim  
documents. While CMI may well have been willing to reduce its  
labour rates had such negotiations occurred, I cannot now  
determine what rates the parties likely would have settled on.  
Any rate I might select at this stage would be speculation. In  
my view the consequences of failing to negotiate this issue at  
the time must be borne by the parties that chose not to follow  
such a course. Accordingly I do not propose to attempt to select  
labour rates that might have been agreed had they been pursued  
through timely negotiations. In the circumstances I cannot  
conclude that the labour rates used by CMI were unreasonable.  
CMI EXTRAS  
757.  
CMI's extras claims can be classified under the  
following categories:  
a)  
b)  
c)  
d)  
Design Changes  
Scope of Work  
Interferences  
Miscellaneous  
DESIGN CHANGES: $177,615  
This section refers to CMI extra work claims #9, #19, #32, #40,  
#45, #97. These extra work claims arose primarily from design  
changes between the tender drawings and the "issued for  
- 312 -  
construction" drawings with the exception of the design changes  
in CMI 32 & 97 which were not made on revised construction  
drawings, but were instructed by CWMM representatives.  
758.  
These are generally claims that "pass-through" FCC to  
the owner. An exception to this is in respect of two items  
claimed under CMI 9, namely spouts that were shown on "A" series  
drawings, but not on "M" series drawings. These cannot be passed  
through to UGG for the reasons in the "Scope of Work" section  
which follows.  
759.  
CMI 9 (FCC 90455) $145,846: Numerous Drawings  
This claim refers to revised spouting in the receiving, wheat  
cleaning, distribution and bin floor areas. CMI's quotations for  
this extra work are found in its's letters of May 12 and October  
21. Considerable negotiation took place with respect to this  
extra work claim. In its October 21 letter, sent after an  
October 17 meeting to discuss extras, CMI reduced its May 12  
claim by some $4,100.  
760.  
CWMM and UGG set out in the Scott Schedule their  
positions on each of CMI's claims. In some cases, liability for  
these claims and their value has been admitted by UGG and/or  
CWMM. In other cases, UGG and CWMM continue to dispute the value  
or quantity of the claims, while admitting liability. In yet  
further cases, UGG and CWMM dispute liability, quantities and  
- 313 -  
values. I have categorized those different levels of acceptance  
when dealing below with the specific items of each claim. Unless  
otherwise noted, these admissions were made in the Scott  
Schedule. Liability is admitted by UGG and/or CWMM for all but  
the last category, for which CMI claims $25,655.  
ADMITTED, BUT UNPAID: $3,297  
Liability for the cost of changes that arose with respect to  
these drawings has been admitted by UGG and/or CWMM.  
Drawing No.  
CMI Quotation:  
5326-M153-RO:  
5326-M150-RO:  
$812 for 15 s.f. concrete liner (Aug. 11/94)  
$6,669 (Aug. 11/94)  
5326-M151-RO: -$6,669 (Aug. 11/94)  
5326-M156-RO:  
5542-M108-R2:  
$1,159 for 22 s.f. concrete liner (Aug. 11/94)  
$1,326 for 26 s.f. concrete liner  
These extras are allowed at $3,297.  
VALUE ONLY DISPUTED: $83,925  
761.  
The work represented by the following drawings required  
the addition of spouting (15,280 lb. at $6.70 = $102,376), and  
the value of the additions remains in issue:  
Drawing No.  
CMI Quotation:  
5326-M104-RO: 750 lbs. ($5,025.00)  
5326-M111-RO: 330 lbs. ($2,211.00)  
5326-M119-RO: 200 lbs. ($1,340.00)  
5542-A108-R2: 14,000 lbs. ($93,800.00)  
The above were calculated using $6.70 per pound. UGG says  
Popowich's reconstruction at his June 23, 1990 discovery  
- 314 -  
demonstrates that this figure cannot be used for both spouting  
and liner. However, in his October 16 letter to FCC, Popowich  
calculated $6.70 per pound based on CMI's original tender price.  
As stated above, CMI is entitled to recover fair compensation for  
the value of spouting supplied by its Edmonton affiliate and  
hence these claims are allowed.  
762.  
The work represented by the following drawings required  
the deletion of spouting components (14,528 lb. at -$1.27 = -  
$18,451), and the amount of the credit remains in issue:  
Drawing No.  
CMI Quotation:  
5542-A108-R2: 1,379 lb. gusset supports  
5542-A108-R2: 4,206 lb. angle flanges  
5542-A108-R2: 7,773 lb. side liners  
5542-A106-R0: 1,224 lb. angle supports  
763.  
764.  
These quotations were originally made on May 12 on the  
basis of lump sum estimates. The unit prices were quoted on  
October 21 at the request of CWMM, at $6.70/lb for added spouting  
and $1.27 for deleted spouting components.  
UGG and CWMM say that $6.70 is too high for added  
spouting, and, particularly if the $6.70 figure is used, that  
$1.27 is too low for deleted spouting. Clearly if additions and  
deletions occur early in a project when little or no work has  
been done on the items, a compelling argument can be advanced  
that the figures should be closer together. However, when  
additions and deletions are ordered during the course of a  
- 315 -  
project, appropriate allowances for additions and deletions will  
depend on how much work has been done by the contractor prior to  
the change. If all of the work has been done and the material  
cannot be used elsewhere on the project, presumably the  
contractor will not be able to offer any credit. In my view,  
there is no evidence which would allow me to conclude that the  
figures proposed by CMI are unrealistic and hence I accept them.  
In addition, the deleted work referred to above was not  
"spouting", but in fact various components of spouting -  
primarily liners - and the revised liner design was much more  
difficult to install than the earlier design. Where complete  
"spouting" was deleted, as under CMI 19 for example, CMI offered  
a $3.24/lb. credit.  
QUANTITY AND VALUE DISPUTED: $29,318  
765.  
The value of the work arising out of revisions to the  
work represented on the drawings set out below was in issue as to  
quantity and quantum.  
Drawing No:  
CMI Quotation:  
5326-M158-RO: D2 to DC103: 279 lbs. sm, 112 lbs. plate =  
$2,175.00  
5326-M158-RO: D2 to DC101: 393 lbs. sm, 432 lbs. plate =  
$6,484.00  
5326-M164-RO: 1,676 lbs. spout, 408 lbs. sm, liner, 1,074 lbs.  
plate liner = $20,659.00  
766.  
These items were quoted at lump sum prices on May 12  
based on Harrish's takeoffs. There is no issue as to the total  
- 316 -  
weight of 4,374 lb. The claim is allowed at $29,318 using the  
overall unit price of $6.70.  
LIABILITY, QUANTITY AND VALUE DISPUTED: $25,655  
The value of the work arising out of revisions to the  
work represented on the drawings set out was at issue as to  
liability, quantity and quantum.  
767.  
Drawing No:  
CMI Quotation:  
5326-M154-RO: 94 s.f. concrete liner added = $4,809.00  
($51.16/s.f.)  
5326-M159-RO: 90 s.f. concrete liner added = $4,630.00  
($51.44/s.f.)  
Although it took the position that the above was "contract work"  
CWMM did not introduce any evidence to support that position.  
The claims are allowed at $4,809 and $4,630.  
Drawing No:  
CMI Quotation:  
5326-M160-RO: 163 lbs. spout, 48 lb. sm liner, 71 lbs. plate  
liner = $1,622.00 ($5.75/lb.)  
768.  
In his October 17 letter to Marquis, Atwell documents  
CMI's agreement at a meeting that day to cancel this claim. It  
is disallowed.  
- 317 -  
CMI Quotation:  
Drawing No:  
5326-M156-RO: D2 to DC201: 1,112 lbs. sm, 405 lbs. plate =  
$9,943 ($6.55/lb.)  
5326-A120-RO: 600 lbs. sm, 500 lbs. plate = $8,302 ($7.55/lb.)  
769.  
This work was shown on the "A" and not the "M"  
drawings. Because of my findings below, these extra claims are  
recoverable from FCC, but FCC is not entitled to indemnity from  
UGG.  
CMI 19 (FCC 90442) $4,601: Drawings 5326-M152 & 5326-M153  
Drawing No:  
5326-M152:  
5326-M153:  
CMI Quotation:  
462 lbs. deleted at $3.24 = ($1,497)  
1134 lb. added and 224 lb. deleted, agreed to net  
these out by weight, giving 910 lbs. added at  
$6.70 = $6,097  
770.  
771.  
For the reasons set out above, the net claim is allowed  
at $4,600.  
CMI 32 (FCC 90141) $9,187: DC103 Tail Section  
This extra work required 840 lbs. of spouting, 240 lbs.  
of sheet metal liner, 366 lbs. of plate liner, for a total cost  
of $9,187.00. This was a diamond fitting that was required for  
connection to DVG-114. It was ordered by Hoffman June 5. The  
work was performed on Aug. 18. It is allowed.  
- 318 -  
CMI 40 (FCC 90441) $9,289: Drawings 5325-M201, 205,  
207, 5326-M163  
Drawing No:  
CMI Quotation:  
5325-M201-R1:  
70 lbs. sm, 26 lbs. plate = $658  
5325-M205-R1: 495 lbs. sm, 247 lbs. plate = $5,017  
5325-M207-R1:  
5326-M163-R2: 163 lbs. sm, 195 lbs. plate = $2,367  
97 lbs. sm, 82 lbs. plate = $1,247  
772.  
At issue on this extra is the accuracy of the CMI  
takeoff. Foote of CWMM did independant takeoffs which Campbell  
says were offered to CMI. However Foote did not testify at  
trial, while CMI's takeoff and estimate were prepared by Harrish  
and Popowich who did testify. Accordingly, I accept CMI's  
calculation and allow this extra as presented at $9,289.  
CMI 45 (FCC 90447) $6,295: Drawings 5524-M104, Add/Delete Spouts  
Drawing No:  
5524-M104  
CMI Quotation:  
Delete spouts 31 and 35: no credit since already  
on site. Installation offset against 57 and 58.  
Added spouts 57 and 58: 1,023 lbs. sm, 969 lbs.  
plate = $6,295 ($3.16/lb.) for supply only:  
installation offset against installation of 31 and  
35.  
5542-M104  
773.  
Popowich described the work which involved the deletion  
of two spouts on site and the addition of one spout on this extra  
work.  
- 319 -  
774.  
In response to the question: "If a set of spouts were  
manufactured and then became redundant and two other spouts were  
added would it reduce the credit you would expect?", Campbell  
agreed, in cross-examination that "it doesn't sound  
unreasonable". This is allowed at $6,295.  
CMI 97 (FCC 90493) $2,397: BD2A to Leg D  
CMI added a transition spout and an additional boot inlet to BD2A  
to Leg D. This opened the throat to allow grain flow. The work  
was performed on August 28 and 31. A Daily Extra Work Record was  
signed by Marquis and Rhodes. While UGG agrees this is an extra,  
it says the small tool charge and overtime is not compensible.  
However CMI is claiming for rented equipment, not small tools.  
After deducting the overtime worked August 31, this claim is  
allowed at $2,150.  
DESIGN CHANGES - SUMMARY  
In this category CMI is entitled to recover extras of $167,169,  
to be paid $148,924 by UGG and $18,245 by FCC.  
SCOPE OF WORK: $194,917; "A" VS "M" DRAWINGS ISSUE  
CMI's extra work claims #67, #82, #91, #96 and #136, and part of  
#9, all relate to increases in the scope of its work. CMI claims  
#17 and #50 relate to deletions in contract work.  
"A" DRAWINGS VS "M" DRAWINGS  
- 320 -  
CMI says that the scope of the work that it was required to  
perform under its subcontract was based on the list of drawings  
that was included with its tender submission to FCC. It says its  
scope of work was as shown on the mechanical ("M") drawings, but  
not on the general arrangement ("A") drawings. CMI quoted only on  
the work shown in the "M" drawings, but not the "A" drawings. The  
prime contract required FCC to fabricate and install all spouting  
shown on the "M" and "A" drawings. CMI did this work and claims  
compensation for the fabrication and installation of the  
additional spouting on the "A" drawings.  
775.  
CMI's January 13 tender submission offered "to perform  
all work described in the attached pre-bid tender submission".  
The attached submission defined, in a list of drawings and notes,  
the "work" that CMI was to perform. The submission listed only  
"M" series drawings. CMI says that its scope of work was defined  
by the mechanical drawings that were listed in its January 13  
tender when that offer was accepted on February 14 by FCC's  
Letter of Intent to CMI "in accordance with CMI's quotation  
...... and subsequent discussions". No discussions subsequent to  
CMI's quotation led to any drawings being added to CMI's work.  
776.  
Bisco also included lists of drawings in its bid in the  
same way that CMI did, although Bisco's list included various "A"  
drawings. CMI says that it should have been obvious to FCC when  
it received and reviewed these two tender submissions, that there  
- 321 -  
was a difference in the scope of work being priced by these two  
subcontractors.  
777.  
778.  
John Derhousen testified as to the practice that FCC  
followed in comparing the bids of the subcontractors. He also  
testified that a spouting contractor would takeoff the spouting  
shown on the "M" drawings but not the "A" drawings.  
After several exchanges of correspondence regarding the  
form of the subcontract agreement, CMI returned the executed  
subcontract on May 8 with certain revisions. Popowich indicated  
those drawings upon which CMI had based its tender, by placing  
his initials beside each drawing on the drawing list attached as  
Exhibit "B" to the subcontract. He also changed the revision  
letters, as appropriate, to reflect the version of the drawing  
upon which CMI based its price. Skodje responded to the changes  
made by Popowich in a letter dated May 11, 1989. In regard to  
drawings, this letter noted only that "we concur with your  
drawing revisions".  
FCC points to the explicit provisions of the subcontract which  
provide:  
"Article 1 - Work to be Done...  
(a) All Dust Collecting Ductwork, Spouting, &  
Installation of Valves & Gates all as per Plans  
- 322 -  
and Specifications. Including Addenda 1, 2, 3, &  
4".  
779.  
780.  
FCC says that all of the spouting required for the  
Project was included in the Plans and Specifications which CMI  
possessed at the time that it tendered.  
However, CMI specifically tendered on the "M" drawings  
only. What is apparent is that FCC failed to notice that CMI's  
tender was limited to the "M" drawings. Given Derhousen's  
evidence that a spouting contractor would not normally takeoff  
spouting shown on general arrangement drawings, I conclude that  
CMI is entitled to recover this category of extra from FCC.  
CMI 82 (FCC 90446) $125,434: 5542-A103-RB Spouting  
CMI added spouts DC 101 to DC 102 and DC 103 to DC 104. This  
spouting was shown at the time of tender only on drawing 5542-  
A103-RB, and was related to drag conveyors DC-101-102 and DC-103-  
104. This claim involves 11,175 lbs. of sheet metal spouting,  
1,648 lbs. sheet metal liner and 6,032 lbs. plate liner, for a  
quoted price of $125,434 (overall, 18,855 lb @ $6.65).  
781.  
In addition to CMI 82, CMI claims $8,302 and $9,943  
under CMI 9 for spouts that were shown at the time of tender on  
drawings 5326-A120 and 5326-A113 (later detailed on 5326-M156-  
R0), but not shown on any "M" drawings (earlier dealt with under  
- 323 -  
the design change section). These amounts were included earlier  
at CMI 9, but the questions of liability are identical to that  
under CMI 82. For the reasons above, FCC is responsible to CMI  
for this claim.  
782.  
However, FCC seeks indemnity on the basis that Drawing  
5542-A103 was ambiguous, that this ambiguity was drawn to CWMM's  
attention during the tender period, and that CWMM failed to issue  
a written addendum to all bidders to resolve the point in  
question. Derhousen also testified that the inclusion by CWMM in  
the general arrangement drawings of spouting which would normally  
be shown on mechanical drawings "went away from the norm" and was  
"one of these sneakers that was pulled on us". However, at the  
least because of the Bisco bid, I conclude that FCC should have  
been alive to this issue. In addition a revision "B" to the  
drawing was issued during the tender period. Hence I conclude  
that FCC is not entitled to pass this claim through to UGG.  
CMI 17 (FCC 90100) -$1,846: 5542-M108 Deleted Spout  
CMI deleted one gate and concrete lined spouting beneath the bin  
floor slab, which was to feed bin 298. The deletions were  
ordered by Hoffman on May 18. CMI's May 19 letter to FCC  
calculated the following credits:  
502 lbs. spouting at $2.11 = $1,059.00.  
620 plate liner at $1.27 per pound = $787.40  
- 324 -  
783.  
CMI's quote was for the section above the floor,  
detailed on 5542-M108-R2, and not the concrete lined section  
below the floor. CMI's October 4 letter to FCC confirmed that  
CMI had assumed the concrete-lined section below the floor, as  
shown on 5542-A106-R2, was pre-existing. However, in addition,  
the sections above and below the floor did not appear on any "M"  
series tender drawing, and thus were never included in CMI's  
scope of work.  
784.  
Campbell testified that the concrete lined spout to Bin  
298 was relatively expensive. He estimated at trial the cost at  
approximately $500 per lineal foot. He said he expected a total  
credit of some $20,000 for the deletion of this work. UGG says  
there is no evidence that CMI had taken any steps to fabricate  
this spouting prior to the deletion and hence it should receive a  
credit of $5,567 for the spouting deletion.  
785.  
786.  
I would allow UGG a credit of $2,000 for the spouting  
and $6,000 for the concrete spouting. Because of the sections  
that did not appear on the "M" drawings, CMI will bear the $2,000  
credit and FCC the $6,000 credit.  
CMI 50 (FCC 90323) -$2,454: DC-6 to Bin 17 Deleted  
Spout  
The deleted spout was shown only on the "A" drawings.  
CMI offered a credit before realizing the work was not within its  
original scope of work and that it had not included any value in  
its original price for the work. CWMM refused to accept the  
- 325 -  
credit offered and ordered CMI to proceed with work. CMI  
subsequently noted that the spout was not shown on "M" drawings,  
stopped the work and cancelled the credit.  
CMI Quotation:  
Delete 508 lbs. at $3.24 = $1,645.00  
13 sf concrete liner at $62.20 per sf = $809.00  
787.  
FCC purported to accept CMI's credit in the amount of  
$2,454.00, and deducted the amount from payments to CMI in 1994.  
Because this credit was rejected by CWMM and because the work was  
on the "A" and not the "M" drawings, FCC must pay this amount to  
CMI.  
788.  
CMI 67 (FCC 90341) $20,021: Leg 6 & 7 Spouting  
CMI installed spouting from Leg 6 and 7. This was ordered by  
Rhodes on August 2. The work was shown to pre-exist on the "A"  
drawings. It did in fact exist and was not shown on the "M"  
drawings. It appears that the spouting was removed by the  
demolition contractor.  
CMI Quotation:  
1,369 lbs. spouting, 246 lbs. sm liner, 1,431 lbs.  
plate liner = $20,021.00  
789.  
Marquis testified that FCC's demolition contractor  
removed spouting by mistake and Steel also gave evidence about  
the removal of spouting.  
- 326 -  
790.  
Rhodes admitted in cross-examination that these spouts  
were shown in a lighter line than the rest, and that it was a  
grey area as to whether the "A" drawing 5326-A121 showed these  
spouts as existing or not. He said: "In most drawings spouting  
was in light lines to show pre-existing".  
791.  
Van Dyke testified that this spouting was removed by  
Johnny Walker and that it was replaced by CMI. His evidence on  
this point was as follows:  
A
Q
I recall the spouting coming from 6 and 7 to the  
two augers on the top floor, yes.  
Do you recall it being removed during the  
demolition phase?  
A
Q.  
Yes.  
Do you recall it being removed by the demolition  
contractor Johnny Walker?  
If you are going to say did I see it happen, no.  
It was I believe part of his responsibility to do  
that demolition work.  
A
Q
A
All right. You knew that it was removed by  
Foundation or its subcontractors?  
That's correct.  
792.  
FCC says based on the documents that this extra was  
cancelled by CMI. Howver, in my view at most the documents show  
that FCC and UGG might have thought this. Popowich adamantly  
denied this at trial and I accept his evidence. This claim will  
be allowed at $20,021 and since the spouting was mistakenly  
removed by Johhny Walker, FCC shall pay this claim.  
- 327 -  
793.  
CMI 91 (FCC 90408) $2,475 Replace Bin 241/242 Feed Box  
CMI replaced the bin 241/242 feed box which was thrown out in  
error by FCC's demolition contractor Johnny Walker. It is  
recoverable against FCC.  
CMI 96 (FCC 90460) $3,929: Feed Box at DC 1  
CMI installed a new feed box in the tail end of DC 1.  
CMI Quotation:  
192 lbs. 10 sheet metal, 98 lb. angle, 300 lbs. plate =  
$3,929.00 (overall, $6.66/lb.)  
794.  
795.  
Rhodes gave evidence at discovery that, based on time  
and materials spent, CMI's original estimate was reasonable. It  
is allowed.  
CMI 136 (FCC 90597) $21,930: 4488 Rotary Cleaner Spouts  
CMI supplied and installed spouting for the 4488 RDI rotary  
cleaner, as instructed in CWMM memo 519 of October 11. This  
spouting was not shown on either the "A" or "M" drawings, but was  
shown on to be existing on a flow sheet drawing. The  
Specifications, Instructions to Bidders 1.2.5, states "remove all  
existing spouting with exception of that from 4488 rotary  
cleaner". Notwithstanding this, the spouting was removed during  
the course of the Project. On May 5 Rhodes issued Memo #30  
instructing the removal of spouting from the 4488 RDI Rotary  
Cleaner. CMI removed the spouts and then put them in again at  
the direction of CWMM in Memo #519 dated October 11. CMI's Daily  
- 328 -  
Extra Work Records for October 12 to 20 total $21,930 for this  
work. CMI is entitled to this extra.  
796.  
CMI 133 (FCC 90565) $6,221: IECO Gate Inlet  
Modifications  
This claim item was originally identified  
as an "interference", but is more appropriately included as a  
scope change, since it did not involve work originally included  
in CMI's scope. CMI modified 6 inlet spouts, which were supplied  
by IECO as standard inlets, but which needed new entry points.  
797.  
CMI gave notice in RFC 89, dated October 2, that extra  
costs and delay would result from this problem. FCC informed  
CWMM in FIR 241 that the gates required modification. CWMM's  
memo 477 instructed FCC to modify the gates and this instruction  
was forwarded to CMI by FCC. CMI performed the work and  
submitted DEWR's, which were signed by Rhodes who acknowledged  
that the time was spent. It is recoverable by CMI. IECO was  
FCC's contractor and hence the costs for these modifications  
occasioned by IECO's failure to properly fabricate must be borne  
by FCC.  
798.  
CMI 6 (FCC 90088) $14,907: IECO Gate Inlets  
This work is closely related to CMI 133. CMI supplied and mounted  
12 non-standard twist elbow inlet spouts with liners to meet the  
necessary gate spout installation for IECO. In its May 4 letter  
- 329 -  
to IECO, copied to Marquis, CMI quoted $28,620 for the 12 spouts.  
CMI did the work, but it was not within its contract scope.  
799.  
FCC sought reimbursement for this work from UGG,  
alleging that it was extra to its contract. CMI pursued payment  
through FCC with FCC's cooperation as a normal extra. On March  
11, 1990, FCC accepted $9,000 from UGG for this extra. On  
February 14, 1994, FCC paid CMI $13,713 and it paid CMI the  
interest accrued on that amount on August 24, 1994. CMI seeks  
the balance of $14,907, plus interest.  
800.  
FCC says CMI's recourse is against IECO, with whom CMI  
contracted for this work. It says CMI has advanced no cost basis  
for this claim other than its May 4 letter to IECO. It says CMI  
can point to no direction from FCC to fabricate the inlets. I do  
not accept these submissions. Marquis was copied with the May 4  
letter. FCC took no objection to the CMI pricing at the time.  
Afterwards, CMI's claim was advanced by FCC as a normal extra.  
FCC elected to settle with both IECO and UGG without informing or  
consulting with CMI. FCC is liable to CMI for the balance of  
this extra.  
SCOPE OF WORK - SUMMARY  
801.  
CMI is entitled to recover $192,917 from FCC; UGG is  
entitled to a credit from FCC of $10,454.  
- 330 -  
INTERFERENCES: $77,118  
802.  
803.  
Interferences which were encountered when CMI went to  
install its spouting caused extra work. I have earlier rejected  
the submissions of CWMM and UGG that specification 15B.1.2  
absolves them of responsibility for these interferences.  
CMI 13 (FCC 90552) $2,059: Transition Spout at L5 and  
C9  
CMI added one transition spout with liners on 4 sides, to rectify  
an interference at L5 and C9. Spouting as drawn on 5326-M121  
interfered with leg casing of L5.  
CMI Quotation:  
804.  
805.  
107 lbs. spout plus 193 lbs. liner = $2,059.00  
This claim is allowed.  
CMI 14 (FCC 90096) $4,691: Spout Moved to Avoid  
Stairway  
CMI relocated spouts on the cleaner deck, bin  
22 to leg 7, to avoid interference with a new stairway. As drawn  
on 5326-M123, the spouting would have overlapped a new stairway.  
UGG admits this is an extra and it is allowed.  
806.  
CMI 24 (FCC 90182) $1,799: Added Fittings Bin 32 to Leg  
6.  
- 331 -  
As designed, the spout from bin 32 to Leg 6 interfered with  
aspiration hood R2B. CMI identified the problem, devised a  
solution in consultation with Rhodes, and submitted it through  
FCC on June 12. The sketch added 2 diamond heads and 1 twist  
fitting. The work was ordered by CWMM, in its memo of June 14  
which solicited a lump sum quotation, if CMI thought it to be an  
extra. CMI submitted a quotation on June 16.  
CMI Quotation:  
807.  
808.  
168 lbs. sm plus 102 lbs. plate = $1,799.00.  
Rhodes testified at discovery that the dust control  
hoods were not shown correctly on the Carter-Day drawings and  
that a spouting contractor couldn't have picked that up. This  
claim is allowed.  
809.  
CMI 27 (FCC 90551) $2,207: Feed Pot Discharge  
Modifications  
CMI modified spouting feed pots to Rotary R1A, R2A, R3A because  
the gate cylinders were hitting the bottom of the pots. This  
modification was ordered by Rhodes on June 2. The work was  
performed on September 6.  
CMI Quotation:  
50 hours at $44.14 = $2,207.00  
- 332 -  
810.  
811.  
Rhodes confirmed in cross-examination at trial that  
this work was not part of the spouting subcontract. It is  
allowed.  
CMI 37 (FCC 90128) $3,437: Modify Spouts at Bin 31 &  
Bin 42  
This claim is made with respect to an interference where the  
spouting from Bin 31 to R2A was narrowed at the point of  
interference with the spout from Bin 42 to C2B. Two twist  
transitions and a spout were added. The work was ordered by  
Rhodes on June 1 and it was performed on September 8.  
CMI Quotation:  
812.  
813.  
266 lbs. spout plus 67 lbs. sm liner plus 148 lbs.  
plate liner = $2,334.00; 25 field hours at $44.14 =  
$1,103.00  
Rhodes in chief testified this work could have been  
"found", but not avoided, by field measuring. It is recoverable.  
814.  
CMI 58 (FCC 90249) $16,399: DVG 113 Modifications  
CMI reworked spout DVG 113 due to interference between leg 3  
casing and channel support for air cylinder on gate. The  
modification was ordered by Rhodes on July 7.  
CMI Quotation:  
- 333 -  
815.  
816.  
1,434 lbs. spout, 462 lbs. sm liner, 578 lbs. plate  
liner = $16,399.00  
This claim is recoverable.  
CMI 63 (FCC 90289) $2,141: Fan C4 Relocated to Clear  
Spout  
CMI relocated fan C4 to clear garner #12 spout. This work was  
ordered by Hoffman on July 20 and was performed on Oct. 22.  
CMI Quotation:  
817.  
818.  
Materials $2,517.00 plus installation 40 hours @ $44.14  
= $1,765.00.  
FCC compromised this claim with UGG at 50% of the  
amount claimed by CMI, under C.O. 188, and received payment of  
$2,141 with their January 31, 1990 progress claim. FCC paid  
$2,141 to CMI on February 15, 1994. FCC admits it owes the  
balance of $2,141 to CMI.  
819.  
CMI 72 (FCC 90361) $4,704: Added Spouting DVD 21/DVD 22  
This claim is made with respect to the spout between gate DVD 21  
and DVD 22, which interfered with a conduit rack. Spouting was  
added on the orders of Rhodes on August 10.  
CMI Quotation:  
820.  
496 lbs. spouting, 224 lbs. plate = $4,704.00  
- 334 -  
821.  
822.  
UGG concedes that there was some extra work involved,  
but says CMI failed to calculate the weight of a spout deleted.  
However Popowich testified that this extra was calculated on the  
net weights and it is allowed.  
CMI 75 (FCC 90344) $10,943: Bin Spouts - 3" Topping  
South Annex Bin spouts had to be cut down to fit due to 3"  
topping on the floor which was not shown on CWMM's drawings.  
This work was ordered by Hoffman Aug. 4. The work was performed  
on Aug. 17, 18, 21 - 24, 26, and 27. An adjustable flange on  
each spout allowed for slight floor fluctuations, but not for  
variations of this magnitude. Rhodes gave evidence at his  
discovery that CWMM took the measurements from as-built drawings  
which did not show the topping.  
823.  
In my view CMI's decision to use the adjustable flanges  
was reasonable and would have allowed for the type of variation  
in floor elevation to be expected in a structure such as the  
south annex which was constructed in stages at various times over  
its life. However the extra 3 inch topping not shown on the CWMM  
drawings renders this a compensible extra to CMI.  
824.  
CMI 76 (FCC 90343) $1,315: Transition to Bin 272  
CMI added a transition piece due to interference at bin 272 with  
the original spouting. This work was ordered by Hoffman on  
August 4. The take-up was not originally scheduled to be in this  
- 335 -  
position. The work was not requested until a diverter valve to  
bin 272 had been installed.  
CMI Quotation:  
825.  
826.  
100 lb. spout plus 95 lb. plate liner = $1,315.00  
Bob Rhodes testified on discovery that the take-up was  
not originally scheduled to be in that place. He also stated  
that, if he had been the contractor, he would have sought  
compensation for this extra. UGG concedes this is legitimate  
extra work and is recoverable by CMI.  
827.  
CMI 80 (FCC 90377) $1,497: Diamond Heads at D2 Turnhead  
Diamond head fittings were required due to interference  
between D2 to battery turnhead #2 and D2 to turnhead #1. This  
work was ordered by Rhodes on Aug. 14 and is recoverable.  
CMI Quotation:  
828.  
829.  
136 lbs. spout, 38 lbs. sm liner; plate liner =  
$1,497.00  
CMI 86 (FCC 90413) $88: Mark out Hopper  
CMI marked out a hopper so that FCC could cut the corner to allow  
the spout to pass through. This work was ordered by Rhodes on  
Aug. 24. The work was performed Sept 5.  
CMI Quotation:  
830.  
2 field hours at $44.14  
- 336 -  
UGG admits this claim.  
831.  
CMI 88 (FCC 90411) $14,414: Hopper Extension at R2A  
A hopper extension was required from rotary R2A so that  
a spout would clear the underside of a floor box beam. This  
required extensive field modifications, which were ordered by R.  
Rhodes on August 25 & 30. The work was performed between August  
28 and September 7. This work is shown on DEWRs for August 28  
through September 17 at $41.00 per hour and $72.28 per overtime  
hour.  
832.  
Rhodes testified at discovery on that if he were the  
contractor, he would expect to be compensated for this work,  
which involved changes in design to spouts that had already been  
fabricated. The existing design did not accommodate the existing  
work.  
UGG says the claim must be reduced as follows:  
(a) premium portion of the hours must be taken out.  
There is no provision in the Contract to allow  
extra work to be done in premium time. In  
addition, this work is being claimed elsewhere  
(Crosstown overtime claim). The reduction is  
$2,252.16.  
- 337 -  
(b) small tools are not compensable under the  
Contract. The charges for the welder are not  
compensable. The reduction is $469.27.  
In my view the welder rental is compensible, but the overtime  
should be taken out of this claim. It is allowed at $12,162.  
833.  
CMI 89 (FCC 90410) $176: Reroute Ducting from DC 103  
This extra work required the rerouting of ducting from  
DC 103, which interfered with the ability to cut the hole for the  
spouting run. This work was ordered by Rhodes on August 25.  
The FCC portion of this extra has been paid to FCC; UGG admits  
liability and quantum of this claim.  
834.  
CMI 93 (FCC 90507) $4,478: DC 2 to C 28 Modifications  
CMI modified spout DC 2 to C 28 to clear gate DVD-12.  
Three twist fittings were added. Rhodes and Adams reviewed this  
spout. In his August 29 memo Rhodes advised that "it would  
appear that if the fittings as supplied are re-arranged the spout  
will fit".  
CMI tried, but failed, to rearrange the fittings to  
clear gate DVD-12. CMI then proceeded with the work without  
further instruction from Rhodes. It is not compensible.  
835.  
CMI 101 (FCC 90404) $353: Bin 300 to Bin 320 Spout  
CMI removed and retained a barley systems spout between bin 300  
and bin 320, which interfered with the discharge spouting from DC  
103, all as instructed by CWMM memo 348, dated August 23.  
- 338 -  
CMI Quotation:  
836.  
837.  
8 hours at $44.14  
This extra is recoverable.  
CMI 103 (FCC 90393) $1,522: Diamond Head, DC 109  
CMI added diamond head fittings to barley leg to DC 109 to clear  
existing dust control equipment. This was ordered by Rhodes on  
August 18. CMI had to change work points, dimensional data and  
design.  
CMI Quotation:  
838.  
839.  
128 lbs. 12 ga., 36 lbs. 10 ga., 62 lbs. plate =  
$1,522.00  
This extra is allowed.  
CMI 108 (FCC 90532) $665: Twist Fitting, Spout No. 33  
CMI added a left hand twist to enable the discharge spout from  
no. 33 to clear screenings. The only matter in dispute is the  
weight of the twist fittings. This work was ordered by Rhodes on  
September 25. The work was performed on October 1.  
CMI Quotation:  
840.  
50 lbs. 12 ga., 20 lbs. 10 ga., 29 lbs. plate = $665.00  
This claim is allowed.  
- 339 -  
841.  
CMI 114 (FCC 90553) $1,917: Raise Bin Floor Ductwork  
CMI raised the bin floor ductwork to provide additional  
head room. This work was ordered by Rhodes on September 21. The  
work was performed on October 1. The ductwork was originally  
installed pursuant to the elevation shown on the drawings, and  
had to be changed. However Rhodes testified that CMI should not  
have proceeded with the installation and that Adams knew it would  
not be acceptable. I accept UGG's submission that when a  
contractor does work which it knows is unacceptable, the Owner  
should not have to pay to rectify the deficiency. This claim is  
not allowed.  
842.  
CMI 119 (FCC 90555) $795: Spouting from RSB Machine  
CMI dismantled, field fabricated and re-assembled spouting due to  
an interference with spouting from RSB machine. This was ordered  
by Rhodes on September 30.  
CMI Quotation:  
843.  
844.  
18 field hours @$ 44.14 = $795.24  
This extra is allowed.  
CMI 137 (FCC 90568) $307: Barley Spout to Bin 340  
CMI removed and reinstalled barley spout to bin 340 with 1 foot  
vertical drop below ceiling, to avoid interference with DC 103.  
This was ordered by Hoffman in CWMM memo 520 dated October 12.  
UGG admits this extra.  
- 340 -  
845.  
CMI 138 (FCC 90602) $1,211: Reroute Dust Pickups  
CMI rerouted dust pick-ups from bin 23 and 24 so that the duct  
work would clear the access doors to these bins. This work was  
ordered by Rhodes on October 16. CMI performed work on openings  
that had been pre-approved. The DEWR for September 8 in the  
amount of $1,211.62, was signed by Rhodes. The overtime portion  
of this claim must be subtracted and the extra will be allowed at  
$1086.  
INTERFERENCES - SUMMARY  
846.  
847.  
CMI is entitled to recover $68,258 payable $66,117 by  
UGG and $2,141 by FCC.  
OTHER EXTRAS  
CMI 151/90724 $636: Repair Plugged Chute, C1 to L1  
CMI repaired this chute, plugged during plant orientation when  
one of the drag conveyors failed, resulting in grain back-up.  
Work was performed on December 12 and 13. Daily Extra Work  
Records were signed by Rhodes. However this damage occurred  
during the commissioning process and before substantial  
performance had been declared. It is therefore for FCC's  
account.  
CMI EXTRAS - SUMMARY OF CMI RECOVERIES  
Design Changes: $167,169, payable $148,924 by UGG;  
$18,245 by FCC  
848.  
- 341 -  
Scope of Work: $192,917 payable by FCC; FCC owes credit of  
$10,454 to UGG  
Interferences: $68,258 payable $66,117 by UGG; $2,141 by FCC  
Other: $636 payable by FCC  
CMI is entitled to recover $428,980 from FCC. After allowing for  
the amounts payable by UGG and the $10,454 credit owed by FCC to  
UGG, FCC is entitled to be indemnified by UGG in the amount of  
$204,587.  
DEFICIENCY PROGRAM: $47,613  
849.  
CMI claims the amount of $47,613 for the cost of the  
labour incurred by CMI (1673 hours @ 28.46 = $47,613) in  
returning to the site to act upon the list of deficiencies. I do  
not propose to review the evidence in this matter in detail other  
than to note that CWMM's calculation that 87% of the installed  
liners were defective was thoroughly discredited in the evidence  
at trial. Similarly discredited was CWMM's attempt to disavow its  
agreement to pay CMI for its work in connection with the  
deficiency programme to the extent that no deficiencies were in  
fact found after "suspect" spouting was opened and the liners  
examined. This claim is allowed.  
OVERHEAD AND PROFIT  
850.  
Extended On-Site Overhead Costs ($28,880)  
- 342 -  
CMI claims the following monthly amounts:  
3.2 months from August 12 to November 15, for site trailers  
($750), phone, fax and consumables ($300), rented equipment  
($1,500), insurance ($875), and supervision ($5,600).  
851.  
In order to recover damages for the costs of its  
overhead beyond August 11, CMI must demonstrate that it could  
have completed the project by the August 11 subcontract  
completion date, absent compensable delays and disruptions. In  
view of my findings above I conclude that CMI is entitled to  
compensation for its extended on-site overhead costs in the  
amount of $28,880.  
Head Office Overhead & Profit ($224,980)  
852.  
CMI claims a mark-up of 21% to be applied to the totals  
claimed above, less the extra claims to which mark-ups were added  
at the time of submission. CMI's original January 13 quotation  
included 25% "mark-ups" on the various estimated costs. CMI's  
January 24 "Final Sheet" included an allowance for "profit" of  
20% of the various estimated costs.  
853.  
In order to recover an amount under this head of  
damages, CMI must show that it could have achieved the mark-ups  
included in its estimates. I have dealt with this under the  
productivity section. CMI says that, but for compensable delays  
and disruptions to its work, it would have carried out its work  
- 343 -  
for an amount equal to or less than its estimated costs, earning  
profits in excess of the 20% estimated and budgeted for on  
January 24.  
854.  
855.  
Since overhead and profit are included in the unit  
prices and rates quoted for CMI's extra work claims, including in  
the rates in the extended overhead amounts, the appropriate rate  
must not be applied to those amounts.  
I would allow CMI 20% for head office overhead and  
profit on the amounts I have assessed for its acceleration,  
productivity, deficiency, and extended on-site overhead cost  
claims. I calculate this at $108,323.  
INTEREST  
856.  
The Subcontract, at page 4, Article III (g) "Interest  
on Overdue Payments" states:  
"(i) Where the Prime Contractor has received a progress or  
holdback payment including an amount due and payable to the  
Sub-Contractor and fails to make payment in accordance with  
the payment provisions contained in [the subcontract], the  
overdue amount shall bear interest at the rate of 2% per  
annum over the prime rate being charged by Toronto Dominion,  
being a Canadian Chartered Bank."  
"(ii)  
Where the contract between the Owner and the Prime  
Contractor includes provision for interest in overdue  
payments and where there is a consequent payment due to  
the Sub-Contractor, the Sub-Contractor shall receive  
his pro rata share of such interest payment received by  
the Prime Contractor."  
- 344 -  
The Prime Contract, at section 3, page 3, Article A-4 Payment,  
(c) states:  
"If the Owner fails to make payments to the Contractor as  
they become due under the terms of this Contract or in an  
award by arbitration or court, interest of ten percent (10%)  
per annum on such unpaid amounts shall also become due and  
payable until payment. Such interest shall be calculated and  
added to any unpaid amounts monthly."  
857.  
CMI and FCC say that they are entitled to contractual  
interest at 10% compounded monthly calculated starting 30 days  
from when the amounts found to be due in this judgment should  
have been paid. CWMM and UGG say that there is a distinction in  
Article A-4 between amounts due under the terms of the contract  
and any amounts that might be awarded by an arbitrator or judge.  
They contend that in the latter case contractual interest does  
not start to accrue until after such an award. They say that in  
the former case, contractual interest would only apply to amounts  
certified for payment under the contract by the engineer, but not  
paid.  
858.  
The difficulty with the defendants' interpretation is  
that, if correct, an owner could avoid contractual interest from  
the time the work was done until after an eventual arbitration or  
court award by the simple expedient of having its engineer refuse  
to certify monies owed. I do not accept that this is the correct  
interpretation to be applied to Article A-4.  
- 345 -  
859.  
In my view, Article A-4 entitles FCC and CMI to  
contractual interest from 30 days after the monies ought to have  
been paid as found by the court. If the parties are unable to  
agree on the amounts owing they are at liberty to apply.  
JUDGMENT SUMMARY  
860.  
1. Responsibility for the 4 month delay in substantial  
performance is assessed 75% to UGG and CWMM and 25% to FCC.  
2. UGG and CWMM are liable to FCC for negligent  
misrepresentation; UGG is liable for breach of contract; FCC is  
liable to CMI for breach of contract, with partial indemnity over  
against UGG and CWMM.  
3. FCC and CMI complied with the notice provisions of  
the contract; UGG failed to so comply and its counterclaim is  
dismissed.  
4. FCC is entitled to damages of $616,829 representing  
75% of its overhead costs for the delay period; extras of  
$263,793 and its 5% markup on the CMI extras payable by UGG in  
the amount of $10,203.  
5. CMI damages recoverable against FCC with partial  
indemnity over against UGG and CWMM are as follows:  
(a) Acceleration - $185,000 of which FCC is entitled to recover  
indemnity of $138,750;  
(b) Productivity loss - $280,122 of which FCC is entitled to  
recover indemnity of 75% or $210,091;  
- 346 -  
(c) CMI extras - $428,980 of which FCC is entitled to recover  
indemnity from UGG of $204,587;  
(d) Deficiency program - $47,613 of which FCC is entitled to full  
indemnity;  
(e) Extended overhead - $28,880 of which FCC is entitled to  
recover indemnity of 75% or $21,660;  
(f) Head office overhead and profit - $108,323 of which FCC is  
entitled to recover indemnity of 75% or $81,242.  
6. FCC and CM1 are entitled to recover contractual  
interest on the foregoing amounts.  
864.  
I wish to thank counsel for their very able  
assistance throughout this trial as well as for their extensive  
written arguments which were an invaluable aid in the preparation  
of these reasons. At the request of all parties, the issue of  
costs is reserved and counsel may contact the Trial Registry to  
arrange a date to speak to that issue.  
"D. Brenner J."  
Dated this 27th day of October, A.D. 1995  
Vancouver, B. C.  