perhaps the furthest they have gone in that direction
is in Chaplin v. Hicks, [1911] 2 K.B. 786. In that
case the plaintiff, owing, as was found by the jury, to
a breach by the defendant of his contract, had lost the
chance of being selected by him out of fifty young
ladies as one of twelve to whom, if selected, he had
promised to give engagements as actresses for a
stated period and at stated wages, and the action was
brought to recover damages for the breach of the
contract, and the damages were assessed by the jury
at £100. The defendant contended that the damages
were too remote and that they were unassessable.
The first contention was rejected by the Court as not
arguable, and with regard to the second it was held
that 'where it is clear that there has been actual loss
resulting from the breach of contract, which it is
difficult to estimate in money, it is for the jury to do
their best to estimate; it is not necessary that there
should be an absolute measure of damages in each
case:' per Fletcher Moulton, L.J., at p. 795."
When Wood v. Grand Valley R. Co., supra, reached the Supreme
Court of Canada, judgment was given by Davies, J., and was
reported in 1915 CanLII 574 (SCC), 22 D.L.R. 614, 51 S.C.R.
283, 25 C.R.C. 117, where the learned Justice said at p. 618
D.L.R., p. 289 S.C.R.:
"It was clearly impossible under the facts of that
case to estimate with anything approaching to
mathematical accuracy the damages sustained by
the plaintiffs, but it seems to me to be clearly laid
down there by the learned Judges that such an
impossibility cannot 'relieve the wrongdoer of the
necessity of paying damages for his breach of
contract' and that on the other hand the tribunal to
estimate them whether jury or Judge must under
such circumstances do 'the best it can' and its
conclusion will not be set aside even if 'the amount
of the verdict is a matter of guess work.'"
I can see no objection whatsoever to the learned trial Judge
using the method suggested by the plaintiff of assessing the
damages in the form of additional compensation per ton rather
than attempting to reach it by ascertaining items of expense
from records which, by the very nature of the contract, had to
be fragmentary and probably mere estimations.
210