DECISION  
2022 NSUARB 18  
M10206  
NOVA SCOTIA UTILITY AND REVIEW BOARD  
IN THE MATTER OF the PUBLIC UTILITIES ACT and the MARITIME LINK ACT and  
the MARITIME LINK COST RECOVERY PROCESS REGULATIONS  
- and -  
IN THE MATTER OF AN APPLICATION by NSP MARITIME LINK INCORPORATED for  
final approval of the Maritime Link Project Costs and approval of the 2022 cost  
assessment  
BEFORE:  
Peter W. Gurnham, Q.C., Chair  
Roland A. Deveau, Q.C., Vice Chair  
Steven M. Murphy, MBA, P.Eng., Member  
APPLICANT:  
INTERVENORS:  
NSP MARITIME LINK INCORPORATED  
Colin J. Clarke, Q.C.  
Ian Mondrow, Counsel  
Mary Ellen Greenough, Counsel  
CONSUMER ADVOCATE  
William L. Mahody, Q.C.  
Emily Mason, Counsel  
SMALL BUSINESS ADVOCATE  
E.A. Nelson Blackburn, Q.C.  
Melissa MacAdam, Counsel  
INDUSTRIAL GROUP  
Nancy Rubin, Q.C.  
ALTERNATIVE RESOURCE ENERGY AUTHORITY  
David MacDougall, Counsel  
PORT HAWKESBURY PAPER LP  
James MacDuff, Counsel  
NOVA SCOTIA POWER INCORPORATED  
Eric MacRae, Counsel  
Document: 291318  
- 2 -  
BOARD COUNSEL:  
HEARING DATES:  
S. Bruce Outhouse, Q.C.  
December 6-8, 2021  
FINAL SUBMISSIONS: January 14, 2022  
DECISION DATE:  
DECISION:  
February 9, 2022  
The Board approves NSPML’s application subject to the  
amendments summarized in paragraph 4.  
Document: 291318  
- 3 -  
TABLE OF CONTENTS  
1.0  
2.0  
3.0  
4.0  
5.0  
SUMMARY ........................................................................................................... 5  
BACKGROUND.................................................................................................... 7  
STATUTORY PROVISIONS................................................................................. 9  
ISSUES .............................................................................................................. 10  
ANALYSIS AND FINDINGS ............................................................................... 11  
5.1  
Were the Board’s 2017 conditions for this application met? .................... 11  
Findings ................................................................................................... 14  
What consequences flow from NSPML’s failure to meet those conditions?  
................................................................................................................. 15  
Findings ................................................................................................... 16  
Was it prudent to sign the Acceleration Agreement?............................... 17  
Findings ................................................................................................... 19  
When should the equivalent economic value of NS Block under-deliveries  
be determined?........................................................................................ 26  
Findings ................................................................................................... 29  
Integrity of Submarine Cable ................................................................... 29  
Findings ................................................................................................... 33  
Depreciation Policy and Depreciation Rates............................................ 33  
Findings ................................................................................................... 35  
NSPML’s Overall Project Execution......................................................... 35  
5.7.1 Project Planning, Management, and Governance......................... 36  
Findings ................................................................................................... 39  
5.7.2 Financing Program........................................................................ 39  
Findings ................................................................................................... 41  
5.7.3 Management of the Submarine Cable Program............................ 41  
Findings ................................................................................................... 44  
5.7.4 Management of the Overland Transmission Program................... 45  
Findings ................................................................................................... 50  
5.7.5 Management of the Converter Station and Related Works Program  
........................................................................................... 51  
5.2  
5.3  
5.4  
5.5  
5.6  
5.7  
Findings ................................................................................................... 54  
5.7.6 Management of Completion and Commissioning.......................... 55  
Findings ................................................................................................... 56  
Affiliate Transactions................................................................................ 56  
Findings ................................................................................................... 57  
Accounting or Tax Issues......................................................................... 57  
Findings ................................................................................................... 60  
5.8  
5.9  
5.10 Incentive Executive Compensation.......................................................... 61  
5.10.1 Intervenor Comments.................................................................... 62  
Findings ................................................................................................... 64  
5.11 Sponsorships and Donations................................................................... 65  
Findings ................................................................................................... 68  
5.12 Final Project Capital Costs, including AFUDC ......................................... 70  
Findings ................................................................................................... 75  
5.13 Opening Rate Base ................................................................................. 76  
Document: 291318  
- 4 -  
Findings ................................................................................................... 78  
5.14 2022 Cost Assessment............................................................................ 78  
Findings ................................................................................................... 82  
5.15 Future Reporting Requirements............................................................... 87  
Findings ................................................................................................... 88  
5.16 Adjustment of Rate of Return................................................................... 89  
Findings ................................................................................................... 92  
5.17 Lingan 2 Retirement ................................................................................ 92  
Findings ................................................................................................... 93  
COMPLIANCE FILING ....................................................................................... 94  
6.0  
Document: 291318  
- 5 -  
1.0  
SUMMARY  
NSP Maritime Link Incorporated (NSPML) applied to the Nova Scotia Utility  
[1]  
and Review Board on August 9, 2021, for final approval of the Maritime Link Project Costs.  
The application requests approval of:  
Maritime Link Project Costs of $1.5712 billion and an Allowance for Funds  
Used During Construction (AFUDC) of $208.8 million;  
an opening rate base as at January 1, 2022 for NSPML of $1.7618 billion,  
inclusive of unamortized deferred financing costs incurred as part of the  
Federal Loan Guarantee financing program and net of recoveries to date  
on account of depreciation and amortization;  
a depreciation policy for NSPML and proposed depreciation rates; and  
a 2022 assessment for recovery from NS Power of NSPML’s 2022 revenue  
requirement, including depreciation and return on equity, in the total amount  
of $169.4 million.  
[2]  
The 2022 cost assessment is the amount that will be paid by NS Power and  
recovered from its customers in order to finance the Maritime Link. Pending final approval  
of the application, NSPML requests that the 2021 monthly cost assessment continue on  
an interim basis (i.e., on a level representing a total of $172.2 million per year). This  
amount is currently reflected in NS Power’s rates.  
[3]  
NSPML states that the Maritime Link Project was completed on time and on  
budget. The Maritime Link was placed in-service on January 15, 2018. However, as  
described in earlier Decisions of the Board, the delivery of the NS Block of energy has  
been delayed due to a variety of problems related to the construction and commissioning  
of the Muskrat Falls Generating Station and the Labrador Island Link. However, on  
August 6, 2021, NSPML signed an Acceleration Agreement with Nalcor, which effectively  
commenced the delivery of the NS Block starting August 15, 2021.  
Document: 291318  
 
- 6 -  
[4]  
Having held a hearing and considered all of the evidence and submissions  
in this matter, the Board approves NSPML’s application subject to the following  
amendments:  
a holdback, as more particularly described in paragraph [31] of this Decision,  
beginning April 1, 2022, in the amount of $2 million per month to ensure  
NSPML/NS Power achieve and receive at least 90% of the basic NS Block and  
Supplemental Energy;  
a reduction in operating and maintenance costs for 2022 of $500,000;  
a deduction from project capital costs of $700,000 to reflect a disallowed affiliate  
transaction;  
an adjustment to project capital costs to reflect that NSPML may only recover  
from ratepayers 50% of incentive compensation; and  
an adjustment to project capital costs to reflect that NSPML may only recover  
80% of sponsorship and donations.  
[5]  
The planning and development of the Maritime Link Project was a significant  
endeavor. There have been numerous examples across North America of substantial  
cost overruns and construction delays of energy mega-projects. The completion of the  
Maritime Link Project on time and on budget was a commendable achievement attributed  
to NSPML's actions throughout all phases of the project. While there continue to be  
delivery delays of the NS Block, NS ratepayers will benefit from NSPML's development  
of the Maritime Link Project, including its continuing efforts with Nalcor as they both strive  
to secure an important source of renewable energy for Nova Scotians and our neighbors  
in Newfoundland and Labrador.  
Document: 291318  
- 7 -  
2.0  
BACKGROUND  
NSPML applied to the Board on August 9, 2021, for final approval of the  
[6]  
Maritime Link Project (ML Project) Costs. The application is made pursuant to s. 8 of the  
Maritime Link Cost Recovery Regulations (ML Regulations) and s. 64 of the Public  
Utilities Act for approval of:  
(a)  
the Project’s final capital cost of $1.5712 billion (Project Costs) and AFUDC of  
$208.8 million;  
(b)  
an opening rate base for NSPML, as at January 1, 2022, of $ 1.7618 billion, which:  
(i)  
includes unamortized deferred financing costs of $45.7 million; and  
(ii)  
takes into account amounts previously recovered for depreciation and  
amortization totaling $63.9 million;  
(c)  
(d)  
the proposed depreciation policy for NSPML; and  
a 2022 assessment for recovery from Nova Scotia Power Inc. (NS Power) of  
NSPML’s 2022 revenue requirement in the amount of $169.4 million.  
[Exhibit N-1, p. 5]  
[7]  
With respect to the 2022 cost assessment, NSPML anticipated that this  
proceeding may not be fully completed by the end of 2021 and, accordingly, it requested  
an interim Order continuing 2021 monthly assessment payments from January 1, 2022,  
representing an annual cost assessment of $172.2 million. This would represent a  
temporary continuation of the 2021 cost assessment and is the amount already reflected  
in Nova Scotia Power Incorporated’s (NS Power) rates to its ratepayers under the Board’s  
2020-2022 Base Cost of Fuel (BCF) Decision, 2019 NSUARB 165. This request  
contemplates that the Board will set NSPML’s monthly assessment payments for the  
remainder of 2022 following the issuance of its final Decision and Order, taking these  
interim monthly payments into account. The Board issued an Interim Order on December  
15, 2021, approving the $172.2 million 2022 cost assessment, subject to continuation of  
Document: 291318  
 
- 8 -  
the previously directed $10 million holdback and pending further Order of the Board  
following its disposition of the final cost application.  
[8]  
The Board has repeated in its prior Decisions that it would not consider  
NSPML’s application for approval of final costs of the ML Project until NS ratepayers are  
receiving the NS Block that NSPML had originally promised:  
[153] …The Board is not prepared to hold the Final Assessment hearing until it knows  
that the NS Block is being delivered in accordance with the original bargain. This will  
enable the Board to reserve whatever regulatory options may be available to it in the event  
of further unfortunate news.  
[155] However, the Board is not prepared to approve the final assessment until it is  
confident the ratepayers will get what they bargained for the NS Block, Supplemental  
Energy and Nalcor Market-priced Energy.  
[2017 ML Interim Assessment Decision, 2017 NSUARB 149]  
[9]  
The Maritime Link (ML) was placed in-service on January 15, 2018. As  
described in earlier Decisions of the Board, and in evidence in this proceeding, the  
delivery of the NS Block has been delayed due to a variety of problems related to the  
construction and commissioning of the Muskrat Falls Generating Station (MFGS) and the  
Labrador Island Link (LIL). NSPML asserted in its application that the NS Block started  
on August 15, 2021, as a result of its execution of an Acceleration Agreement with Nalcor  
on August 6, 2021. However, continuing problems with LIL pre-commissioning activities,  
has resulted in continuing delivery delays of the NS Block, including Supplemental  
Energy. NS Power and Nalcor are coordinating forecasts and schedules for the make-  
up of undelivered energy.  
[10]  
Following the filing of Information Requests (IRs) and evidence by various  
parties, the hearing was held from December 6 to 8, 2021, by way of a GoToMeeting  
Document: 291318  
- 9 -  
webinar due to the continuation of the COVID-19 pandemic, with all counsel present in  
the Board’s hearing room, but the witnesses appearing by videoconference.  
3.0  
STATUTORY PROVISIONS  
[11]  
The ML Project is defined under the Maritime Link Act, S.N.S. 2012, c. 9  
(ML Act) as follows:  
2
(c)  
"Maritime Link Project" means the design, construction, operation and  
maintenance of the Maritime Link, together with the related transactions involving the  
delivery of energy, the provision of transmission services over the Maritime Link and the  
enabling of transmission service through the Province, as set out in a term sheet between  
Emera Incorporated and Nalcor Energy dated November 18, 2010; [Emphasis added]  
[12]  
The ML Act provides that the Board has the general supervision of the ML  
Project and of an applicant in respect of the ML Project:  
4
The Review Board has the general supervision of an applicant and the Maritime  
Link Project, and may make all necessary examinations and inquiries and keep itself  
informed as to the compliance by an applicant with the provisions of law and has the right  
to obtain from an applicant all information necessary to enable the Review Board to fulfil  
its duties.  
[13]  
The recovery of a rate, toll, charge or other compensation by an applicant  
(in this case NSPML) from NS Power (and, ultimately, from its ratepayers) is governed by  
ss. 4 and 8 of the ML Regulations:  
Requirement for Review Board approval  
4
(1)  
(2)  
(3)  
To obtain a rate, toll, charge or other compensation for services as  
defined under the Public Utilities Act, an applicant must first obtain an  
approval of the Maritime Link Project under Section 5.  
Once approved under Section 5, an applicant is entitled to recover Project  
costs through a rate, toll, charge or other compensation from Nova Scotia  
Power Incorporated in accordance with Section 8.  
An applicant who makes an application under this Section is not required  
to make a separate application under Section 35 or 35A of the Public  
Utilities Act, but once the Review Board has approved an assessment  
under Section 8, the applicant is subject to Sections 35 and 35A of the  
Public Utilities Act with respect to any new expenditures.  
. . .  
Document: 291318  
 
- 10 -  
Assessment and costing approval  
8
(1)  
Before receiving energy under the Nalcor Transactions, an applicant  
must set an assessment against Nova Scotia Power Incorporated for the  
recovery of the all approved Project costs, and must apply to the Review  
Board for an approval of the assessment under Section 64 of the Public  
Utilities Act.  
(2)  
Nova Scotia Power Incorporated is entitled to recover through its rates any  
assessment approved by the Review Board in respect of the Maritime Link  
Project.  
[14]  
Section 3 of the ML Regulations provides that any applicant is deemed to  
be a public utility:  
Designation as public utility  
3
An applicant is deemed to be a public utility within the meaning of the Public  
Utilities Act and the Public Utilities Act applies to an applicant.  
[15]  
Section 5 of the ML Act sets out the application of the Public Utilities Act,  
R.S.N.S. 1989, c. 380 (PUA):  
5
(1)  
Notwithstanding the regulations, Section 54 of Public Utilities Act does not  
apply with respect to construction of the Maritime Link Project by an applicant in territory  
already served by a public utility of like nature, as that territory exists at the time this Act  
comes into force.  
(2)  
For greater certainty, where an applicant has been made subject to the  
Public Utilities Act by regulation, for the purpose of that Act and in particular Section 64 of  
that Act, the transmission of electricity by the applicant is a service to which Section 64 of  
that Act applies.  
(3)  
Notwithstanding Section 117 of the Public Utilities Act, where there is a  
conflict between this Act or the regulations and the Public Utilities Act or the regulations  
made pursuant to that Act, this Act and the regulations prevail.  
4.0  
ISSUES  
1.  
2.  
3.  
4.  
Were the Board’s 2017 conditions for this application met?  
What consequences flow from NSPML’s failure to meet those conditions?  
Was it prudent to sign the Acceleration Agreement?  
When should the equivalent economic value of NS Block under-deliveries be  
determined?  
Document: 291318  
 
- 11 -  
5.  
Integrity of Submarine Cable.  
6.  
Depreciation policy and depreciation rates.  
NSPML’s overall project management.  
Affiliate transactions.  
7.  
8.  
9.  
Accounting or tax issues.  
10.  
11.  
12.  
13.  
14.  
15.  
16.  
17.  
Incentive Executive Compensation.  
Sponsorships and Donations.  
Final Project Capital Costs, including AFUDC.  
Opening Rate Base.  
2022 Cost Assessment.  
Future reporting requirements.  
Adjustment of Rate of Return.  
Lingan 2 Retirement.  
5.0  
ANALYSIS AND FINDINGS  
5.1  
Were the Board’s 2017 conditions for this application met?  
In the Board’s 2017 ML Interim Assessment Decision [2017 NSUARB 149],  
[16]  
the Board clearly laid out the conditions NSPML had to meet to have the final assessment.  
The Board stated:  
[153] NSPML indicated that it wants to have the Final Assessment hearing during 2018.  
The Board is not prepared to hold the Final Assessment hearing until it knows that the NS  
Block is being delivered in accordance with the original bargain. This will enable the Board  
to reserve whatever regulatory options may be available to it in the event of further  
unfortunate news.  
[155] However, the Board is not prepared to approve the final assessment until it is  
confident the ratepayers will get what they bargained for the NS Block, Supplemental  
Energy and Nalcor Market-priced Energy.  
Document: 291318  
   
- 12 -  
[17]  
The Board reiterated that position in the 2019 ML Interim Assessment  
Decision [2019 NSUARB 156]:  
[60]  
NSPML has characterized the timing for the Board’s approval of the final  
assessment as being linked to the point when the Board “has confidence in the timing of  
commencement of the NS Block, Supplemental Energy and Nalcor Market-priced Energy”.  
To be clear, the Board will not initiate the hearing process into the final assessment of costs  
until the NS Block starts (including the Supplemental Energy) and there is the capacity to  
transact Nalcor Market-priced Energy. That was what has been referenced in earlier  
proceedings as the “original bargain”.  
[61]  
The Board repeats its direction from the 2017 Interim Assessment Decision as to  
the timing of the final assessment hearing:  
[153] …The Board is not prepared to hold the Final Assessment hearing  
until it knows that the NS Block is being delivered in accordance with the  
original bargain. This will enable the Board to reserve whatever regulatory  
options may be available to it in the event of further unfortunate news.  
[155] However, the Board is not prepared to approve the final  
assessment until it is confident the ratepayers will get what they bargained  
for the NS Block, Supplemental Energy and Nalcor Market-priced  
Energy.  
[62]  
Thus, no hearing process into the final assessment matter will be started until the  
NS Block and related components are actually flowing over the Maritime Link.  
[18]  
In his post-hearing submission, the Consumer Advocate set out quite  
succinctly the original bargain:  
c. Meaning of – “what was bargained for”  
NSPML’s 2013 Application (and the Board’s subsequent approval) was based on NS  
ratepayers receiving the NS Block (Base and Supplemental). The attributes of the NS Block  
were referenced in the 2013 ML Application (M05419) Ex M-2 p 33:  
Figure 2-1 Energy Delivery Features  
Document: 291318  
- 13 -  
Another critical representation at the 2013 ML Hearing related to the availability of Nalcor  
market priced energy. Figure 4-4 from NSPML’s Application (Ex M-2 at p. 92):  
Figure 4-4 Weighted Average Electricity Prices Per MWh  
NSPML’s response to UARB IR-37 from the 2013 Application provided the assumptions  
related to Figure 4-4 that IR response has been entered in this proceeding as Ex N-31.  
During this hearing, NSPML confirmed that the anticipated amount of energy to be  
delivered between mid-August 2021 and November 2021 was approximately 692,000  
MWh, consisting of:  
o
o
o
NS Block: 262,000 MWh  
Supplemental Energy (winter only): 48,000 MWh  
Nalcor Market-Priced Energy: 382,000 MWh  
(Transcript, p. 51, line 19 p. 54, line 1)  
[Exhibit N-49, pp. 3-4]  
[19]  
As of the date of the hearing only approximately 19% of the NS Block and  
Supplemental Energy had been delivered for the period commencing August 15 to the  
end of November 2021.  
[20]  
In its submission, NSPML advised that since the hearing, NS Block energy  
flows have improved. This advice was expanded upon in the reply submission but covers  
Document: 291318  
- 14 -  
a time period measured in days not cause for unbridled optimism. That evidence was  
not subject to cross-examination or submitted under oath and is entitled to little weight.  
The Board has noted in the past that NSPML and NS Power have over-promised and  
under-delivered when they describe benefits from the Maritime Link. In the 2017 interim  
assessment hearing, when NSPML was arguing that the Maritime Link was used and  
useful even in the absence of NS Block, NSPML and NS Power stated that energy and  
other benefits in excess of $120 million in 2018 and 2019 were expected. In fact, those  
benefits were less than $5 million per year in each of those years.  
[21]  
One might ask why the Board set these conditions in the 2017 Decision and  
repeated them in every interim assessment since. That turns on the phrase “this will  
enable the Board to reserve whatever regulatory options may be available to it in the  
event of further unfortunate news”.  
[22]  
its regulatory authority to deal with what that “unfortunate news” might turn out to be.  
[23] Had the Board known at the time the hearing was set down that only 19%  
The Board was preserving, for the benefit of ratepayers, the full measure of  
of the energy would flow between August 15 and November 30, 2021, the Board would  
not have agreed to have the hearing at this time.  
Findings  
[24]  
The Board finds that the conditions set in 2017 and repeated in each  
Decision since then for having the final assessment hearing have not been met. The  
Board was placed in the position of convening this hearing in circumstances where the  
hearing should not have taken place until the NS Block was being delivered in accordance  
with the original bargain.  
Document: 291318  
 
- 15 -  
[25]  
That issue is quite separate from whether it was prudent to enter into the  
Acceleration Agreement, which is canvassed below.  
5.2  
What consequences flow from NSPML’s failure to meet those  
conditions?  
[26]  
All of the Intervenors suggest that the Board exercise some regulatory  
mechanism to protect Nova Scotia ratepayers from further risk. The Municipal Utilities  
(MUNIS) suggest a holdback similar to the holdback currently in place would be  
necessary to be meaningful.  
[27]  
The Small Business Advocate also suggests continuation of a holdback with  
the condition that it not be paid to NSPML until under-delivery is made in full and NS  
Power is receiving, on a consistent basis, 90% or more of the promised energy delivery.  
When those conditions are satisfied at some point, a pro-rated amount of the holdback  
should be paid to NSPML, and the balance credited to ratepayers.  
[28]  
The Consumer Advocate argued that the Board’s response should be  
“decisive” due to the fact that NSPML has ignored the direction of the Board. The  
Consumer Advocate recommended a holdback significantly higher than the $10 million  
holdback currently in place.  
[29]  
The Industrial Group stated that while there may be other regulatory tools,  
at a minimum the existing deferral should continue into 2022 until the Board is satisfied  
the original bargain has been reliably fulfilled. This means that the project is  
commissioned and the non-operation of the LIL is no longer a forgivable event. The  
Industrial Group says a form of holdback could be imposed tied to the benefits associated  
with the original bargain to ensure redeliveries are similar in value.  
Document: 291318  
 
- 16 -  
[30]  
As noted in Undertaking U-1, the NS Power estimated cost related to the  
non-delivery of the NS Block from January 1, 2018 to October 31, 2021, is $205.5 million  
in replacement energy costs. However, as make-up power is delivered, that will work to  
the benefit of ratepayers thereby reducing this $205.5 million cost.  
Findings  
[31]  
The Board has determined it is appropriate to continue a form of holdback  
to provide some continued protection to ratepayers. The holdback is as follows: Starting  
April 1, 2022, and in each subsequent month of 2022, NS Power is to holdback $2 million  
from the approved assessment. If in that month NSPML/NS Power achieve and receive  
90% of the basic NS Block and Supplemental Energy, the holdback will be released to  
NSPML in the following month. If 90% of the basic NS Block and Supplemental Energy  
is not achieved, the holdback monies will be used to pay for the cost of any replacement  
energy that may be required as a result of the failure to achieve the 90%, to a maximum  
of $2 million per month. Any portion of the $2 million not utilized to pay for replacement  
cost energy would be paid over to NSPML. This holdback mechanism will continue in  
each and every month during 2022 and then will be reviewed by the Board in January of  
2023.  
[32]  
The fact that today’s customers are paying for the Maritime Link but not  
receiving anything close to the full benefit has caused intergenerational equity concerns.  
This holdback, in some small way, may ameliorate those concerns to the extent an  
imbalance continues. The Board believes this holdback would not jeopardize NSPML’s  
ability to service the federal loan guaranteed debt; however, if circumstances arise where  
that becomes a concern, NSPML should immediately apply to the Board for relief.  
Document: 291318  
 
- 17 -  
[33]  
The holdback in 2022 for January and February, pursuant to the Board’s  
December 2021 Interim Order, may be released to NSPML.  
5.3  
[34]  
Was it prudent to sign the Acceleration Agreement?  
On August 6, 2021, NSPML signed an Acceleration Agreement with Nalcor,  
which effectively commenced the delivery of the NS Block starting August 15, 2021.  
Under the original commercial agreements, the NS Block would not have started until the  
commissioning of the Muskrat Falls Generating Station and the LIL. In its Rebuttal  
Evidence, NSPML outlined the effect of the Acceleration Agreement as follows:  
On August 6, 2021, NSPML secured an agreement with Nalcor Energy (Nalcor) for delivery  
of the NS Block prior to full commissioning of the LIL; the remaining condition precedent  
under the Nalcor agreements for the commencement of delivery. In the result, delivery of  
the NS Block commenced on August 15, 2021. Without the Acceleration Agreement, NS  
customers would still be waiting for the receipt of any NS Block benefits. The effect of the  
Acceleration Agreement has been to secure, and advance, the economic value of the NS  
Block for the benefit of NS customers.  
Pending full commissioning of the LIL there have been, and will continue to be, periods  
when the LIL is derated or out of service. This was anticipated by the parties when the  
Acceleration Agreement was signed and is addressed through the Agreement and ECA’s  
make-up energy provisions which retain for NS customers the total benefit of the NS Block.  
… In any event, the Acceleration Agreement, together with the ECA, ensures, and the  
parties fully agree, that all NS Block energy not delivered to NS from and after August 15,  
2021 has been, and will continue to be, tracked for delivery as soon as reasonably possible.  
… NS Power will schedule such delivery in accord with system requirements and  
capabilities, good utility practice, and maintenance of the economic value of those  
deliveries to NS customers.  
[Exhibit N-22, pp. 10-11]  
[35]  
The Intervenors expressed concerns about NSPML’s execution of the  
Acceleration Agreement. They raised several points in support of their view that it was  
not appropriate to enter into the Acceleration Agreement with Nalcor. One criticism is  
that the delivery of the NS Block continues to be delayed despite the existence of the  
Acceleration Agreement. To the extent this has changed the “original bargain” and there  
continues to be a delay in the NS Block and the make-up of undelivered energy, those  
issues were canvassed earlier in this Decision where the Board applied its regulatory  
Document: 291318  
 
- 18 -  
tools to address the continuing delay. In this part of the Decision, the Board will  
specifically address whether it was reasonable for NSPML to negotiate and enter into the  
Acceleration Agreement.  
[36]  
The Industrial Group submitted:  
Perhaps only time will tell whether the Acceleration Agreement which traded off $18  
million in disputed trenching costs, forgave non-delivery penalties due to the LIL prior to  
commissioning and included O&M costs attributable to Muskrat Falls Plant and the LIL in  
the Joint Operating Agreement calculation from August 15, 2021, notwithstanding only a  
fraction of the promised energy is currently flowing was a good deal. Clearly, it  
fundamentally changed the ECA which was approved by the Board as part of the package  
of agreements.  
Regrettably, there is no contemporaneous economic analysis with sensitivities as to the  
risk of further delays. NSMPL has outlined in its Rebuttal Evidence (Ex. N-22, pp.12-13)  
the benefits it identified with the Acceleration Agreement. As discussed during the  
confidential session, the assumed monetary benefit of avoiding replacement energy for the  
period between August 15 and the (then) forecasted LIL commercial operation date of  
November 27, 2021 has not borne out. [Emphasis added]  
[Exhibit N-50, p. 5]  
[37]  
Further, the MUNIS suggested there is a capacity deficiency for Muskrat  
Falls energy under the Acceleration Agreement in the context of the Board’s recent BUTU  
Decision (M09940) [2021 NSUARB 126]:  
Notable to the Municipal Utilities is that NSPML has, at least to date, made no concession  
that the capacity value of the NS Block has been diminished by the LIL Forgiveable Event  
during the period of its applicability. … NSPI made clear in that proceeding its view on what  
it felt was necessary to constitute capacity. Yet in this proceeding neither NSPI or NSPML  
have conceded that the NS Block is not, while the Acceleration Agreement provisions are  
in place, a viable capacity resource.  
[Exhibit N-46, pp. 31-32]  
[38]  
In response to IRs from the Consumer Advocate to the Board Counsel’s  
consultant, Bates White stated that it was “unaware of any evidence that would suggest  
a date certain by which the entirety of the NS Block would be delivered” [Exhibit N-18, CA  
IR-1]. Further, Bates White opined that the Acceleration Agreement changed the  
definition of “forgivable event” as contained in the original commercial agreement:  
Document: 291318  
- 19 -  
(b) Our opinion is that the revised definition of “Forgivable Event” is materially different  
than the definition contained in the original agreement and approved by the Board  
since it includes the LIL commissioning activities in the definition of Forgivable Event  
and accelerates the commencement date of the NS Block to a date that precedes full  
commissioning of the LIL, which is necessary for delivery of the full NS Block.  
[Exhibit N-18, CA IR-3(b)]  
[39]  
However, in Bates White’s opinion, the Acceleration Agreement obligated  
Nalcor to begin providing the firm, zero emissions NS Block energy to NS Power:  
(a) Bates White’s understanding of the Acceleration Agreement is that it contractually  
obligates Nalcor to commence delivery of the NS Block on a firm basis, consistent with  
the terms of the Energy and Capacity Agreement.  
i.  
“Firm” is consistent with our response to CA IR-2(b). We note, however, that  
because “Forgivable Event” has been revised by the Acceleration Agreement to  
include LIL commissioning activities, there is a material expansion of the universe  
of allowed excuses for underperformance. …  
[Exhibit N-18, CA IR-5(a)]  
[40]  
Bates White defined “firm” as:  
Firm service is the highest priority form of service, meaning it is the last form of service to  
be curtailed, and is considered non-interruptible other than for force majeure events,  
planned maintenance, and emergency events, and when otherwise interrupted, is typically  
subject to penalties.  
[Exhibit N-18, CA IR-2(b)]  
Findings  
[41]  
In the Board’s view, the Intervenors have mischaracterized the impact of  
the Acceleration Agreement. Most of their concerns relate to the delay in the delivery of  
the NS Block. The delay, of course, was not caused by the execution of the Acceleration  
Agreement. The NS Block has already been delayed since 2018. Indeed, NSPML  
entered into negotiations with Nalcor to address the continuing delay in the delivery of the  
NS Block. Earlier in this Decision, the Board applied its regulatory instruments to address  
the impact of the continuing delay upon NS ratepayers. However, the Board considers  
the prudence of the Acceleration Agreement to be a different question.  
Document: 291318  
 
- 20 -  
[42]  
It is important to note that the premise underlying the Agreement is the  
reality that the Muskrat Falls Generating Station and the LIL are now able to  
accommodate the volume of energy comprising the NS Block, including Supplemental  
Energy, as well as the commencement of Nalcor Market-priced Energy starting  
September 1, 2022. In its reply argument, NSPML stated:  
Delivery of the NS Block (at its highest capacity being Supplemental Energy of under  
200 MW) requires less than 25% of the as built capacity of the LIL. The LIL has been  
running above that capacity since August, 2021 (though, as it has turned out, intermittently  
in the initial months following execution of the Acceleration Agreement). The generation  
capacity of MFGS is 824 MW, again well in excess of the capacity requirements of the NS  
Block. The rationale for the Acceleration Agreement was that both facilities were already  
operating above the required NS Block capacity, and neither required final commissioning  
in order to commence NS Block delivery. Both parties agreed with these circumstances,  
which is why they agreed to accelerate NS Block delivery. [Emphasis added]  
[Exhibit N-53, p. 18]  
[43]  
While numerous deliveries of the NS Block after August 15, 2021, have  
continued to be interrupted and delayed, the Acceleration Agreement contains provisions  
that provide several benefits to NS ratepayers, mitigating the full impact of the delayed  
NS Block delivery.  
[44]  
First, the start of the NS Block begins to immediately provide NS Power and  
its customers with energy, mitigating the need for NS Power to secure replacement power  
from other sources at an extra cost under the FAM. Given that the NS Block commenced  
in advance of the 2021-2022 peak winter season, this might enable NS Power to avoid  
relatively higher replacement energy costs this winter. In the absence of the Acceleration  
Agreement, the NS Block would have been delayed until the commissioning of the LIL,  
which was projected at the time to occur no earlier than late November 2021, and possibly  
later. It is now clear that the commissioning date will be later. Moreover, the NS Block  
provides valuable renewable energy which counts towards NS Power’s Renewable  
Document: 291318  
- 21 -  
Electricity Standards requirements and addresses some of the Utility’s GHG  
requirements, with potentially significant financial implications if not satisfied by the end  
of the current compliance period on December 31, 2022. Granted, there have been  
continuing delays in NS Block deliveries, but what has been delivered is provided on  
account of what is currently embedded in customers’ power rates and, as explained  
below, any under-deliveries must be re-scheduled by Nalcor.  
[45]  
Second, as noted above, some of the Intervenors argued that the terms of  
the “original bargain” were relaxed in NSPML’s favour as the term “forgivable event” was  
expanded to include interruptions during LIL pre-commissioning activities under the  
original commercial agreements. However, in such an event, the Energy and Capacity  
Agreement triggers a mechanism which allows Nalcor to provide this energy at a later  
date, or so-called “makeup energy”. This provision serves as a benefit to ratepayers,  
rather than a detriment. The Board finds this is a reasonable commercial provision which  
recognizes that, under the original contractual agreements, the NS Block would not have  
begun to flow over the Maritime Link until the LIL was commissioned. Thus, the  
Acceleration Agreement allows the NS Block to flow during Nalcor’s continuing pre-  
commissioning activities on the LIL. In the Board’s opinion, this appropriately relaxes the  
original contractual term, allowing the deferral of non-deliveries caused by interruptions  
during LIL pre-commissioning activities and requiring the provision of makeup energy.  
The Board concurs with NSPML’s depiction of this component of the Agreement:  
… The “forgivable events” clause of the Acceleration Agreement is a practical and workable  
mechanism to address what the parties to the agreement acknowledged as an obvious  
circumstance to be addressed if NS Block energy was to flow prior to full LIL contractual  
commissioning. This amendment is, in the context of flowing the NS Block during  
continuing commissioning activities, … This provision allowed for pre-LIL commissioning  
delivery of the NS Block, and thus was beneficial for customers. It did not, as the IG  
contends, “forgive non-delivery penalties”, since without the Acceleration Agreement there  
would have been no non-deliveries to forgive. Without the reasonable expanded definition  
Document: 291318  
- 22 -  
of “forgivable event” there would have been no Acceleration Agreement and thus no NS  
Block during the period in question. [Emphasis added]  
[Exhibit N-53, p. 12]  
[46]  
Further, Bates White confirmed that the Acceleration Agreement did not  
change the nature of the energy dispatch requirements. The contractual dispatch of the  
NS Block is still scheduled and managed under Schedule 5 of the Energy and Capacity  
Agreement [see Exhibit N-18, RIR CA IR-2(c) and (d)]. Thus, the delivery of makeup  
energy caused by interruptions related to the LIL commissioning activities are dealt with  
in like fashion to makeup energy resulting from forgivable events as originally  
contemplated. Similarly, the requirement to optimize the energy profile delivered to NS  
Power is also set out in the Acceleration Agreement:  
2.  
Supplemental Energy - Prior to the Final Determination, as such term is defined in  
Schedule 4 of the ECA, the Supplemental Energy shall be deemed to be 240 GWh  
per year and during such period, the parties will work cooperatively to optimize the  
profile of Nova Scotia Block Delivery Schedule including Supplemental Energy  
consistent with the principles set forth in Section 2(d) of Schedule 5 of the ECA.  
[Emphasis added]  
[Exhibit N-2, p. 1]  
[47]  
Third, in support of the provision for makeup energy, the Acceleration  
Agreement, through the operation of the Energy and Capacity Agreement, restricts  
Nalcor’s ability to sell Muskrat Falls energy to any other party where that would impact  
Nalcor’s obligation to deliver the makeup energy to NS Power:  
…The ECA requires that Nalcor provide options for delivery of replacement energy  
promptly upon quantification by NSPML of such energy, and requires suspension of all  
non-firm sales from MFGS and precludes Nalcor from scheduling or entering into  
arrangements for firm or non-firm export sales to the extent that any of which would affect  
Nalcor’s obligation to deliver replacement energy. …  
[Exhibit N-22, p. 17]  
Document: 291318  
- 23 -  
[48]  
This clearly provides an incentive for Nalcor to address any deficiencies in  
the provision of the NS Block to NS Power, which under these contractual terms stand in  
priority to third parties who may be interested in buying Muskrat Falls energy.  
[49]  
Fourth, the Acceleration Agreement secured the availability of Nalcor  
Market-priced Energy by September 1, 2022. Section 4 of the Acceleration Agreement  
provides:  
4.  
Energy Access Agreement - In accordance with Section 2.1(b) of the Energy  
Access Agreement, dated April 13, 2015, Nalcor or its permitted assign shall  
provide the first Nalcor forecast by March 1, 2022, and the first Contract Year shall  
commence on September 1, 2022. [Emphasis added]  
[Exhibit N-2, p. 2]  
[50]  
In the absence of the Acceleration Agreement, the start of the Nalcor  
Market-priced Energy would likely have been delayed to September 2023, at the earliest.  
Mr. Janega of NSPML testified:  
Q.  
(Murphy)…My question is, without the Acceleration Agreement in place, what  
would have been the date for commencement of the ability to purchase market-priced  
energy?  
A.  
(Janega) But for the purpose of your question, Mr. Murphy, the Excess Energy  
Agreement is that specific obligation that I know the UARB Panel, at the time, necessitated  
as a part of the Maritime Link approval back in 2013, and it obligates Nova Scotia Power  
and Nalcor to, through a commercial process, initiate a set of steps whereby Nalcor would  
determine how much energy they have available to sell. Nova Scotia Power would engage  
in a process that’s laid out where they would determine how much they want to procure on  
a forward-looking basis, and Nalcor would then schedule that on a -- on whatever periodic  
basis the two of them agree.  
And that’s a formalized process where it's an annual trigger that they provide a forecast,  
Nova Scotia Power provides a response, and Nalcor then, with NSPI, depending on the  
commercial value of the energy for Nova Scotia customers, would agree to an annual  
volume of energy that they would procure, and a profile.  
... And if it wasn’t for the Acceleration Agreement, that would wait until LIL was fully  
complete, and then essentially, within a year after that, the parties would be required to  
start.  
Q.  
So without the Acceleration Agreement in place, it sounds like that formal process  
could have been delayed a year, I suppose?  
Document: 291318  
- 24 -  
A.  
(Janega) It would likely have been the year after that we would have been talking  
about, 2023 period.  
[Transcript, December 7, 2021, pp. 409-412]  
[51]  
Thus, in addition to commencement of the NS Block (including  
Supplemental Energy), the Acceleration Agreement benefits NS customers by advancing  
the availability of Market-priced Energy by at least one year. Pursuant to the Energy  
Access Agreement (EAA), which was negotiated to meet a condition imposed by the  
Board in its 2013 ML Decision to ensure the ML Project was the lowest cost alternative  
for NS ratepayers, Nalcor Market-priced Energy is contracted differently than other  
Muskrat Falls excess energy.  
[52]  
It is instructive to recall the benefits of the EAA as outlined by Board Counsel  
consultants, Morrison Park, in the Board’s Supplemental ML Decision, 2013 NSUARB  
242:  
[20]  
Both Morrison Park and NSPI highlighted a number of benefits of the EAA which,  
in their view, helped satisfy the Board’s concerns.  
[21]  
Indeed, Morrison Park indicated they do not believe it is a correct characterization  
of the EAA to say it is an energy supply agreement. They said it is, in reality, a contract  
that guarantees access by NSPI to the market, noting that NSPI may not in any particular  
year actually issue an RFP or accept any bids for Nalcor Market-priced Energy, if that is  
not the economic choice. However, the EAA provides NSPI with the benefit of precluding  
Nalcor from contracting power to third parties on a long term basis as Nalcor must forecast  
and bid into annual NSPI solicitations. That provision applies in each year of the term of  
the EAA irrespective of the fact that Nalcor may have satisfied the average 1.2 TWh  
contractual obligation. Morrison Park described that contractual commitment as a series  
of 24 one-way options in favour of NSPI that it can exercise for 24 different consecutive  
years in the future. Morrison Park noted that NSPI has not taken on any additional  
commitments in the EAA.  
[23]  
Morrison Park noted that another beneficial provision of the EAA is that Nalcor  
must disclose its expectations about power availability through the 24 month forecast. Mr.  
Walker noted that when you are transacting with a counterparty, knowing their inventory  
for a 24 month period is an important piece of information that normal market  
counterparties do not have. This would give NSPI an advantage and could lead to better  
energy prices for Nova Scotia ratepayers. …  
[2013 NSUARB 242, paras. 20-23]  
Document: 291318  
- 25 -  
[53]  
The Board is satisfied that the availability of the Market-priced Energy by  
September 1, 2022, provides earlier financial benefits to NS ratepayers by securing the  
full profile of Muskrat Falls energy.  
[54]  
Finally, the Board is mindful that the Acceleration Agreement was the  
subject of negotiation between NSPML and Nalcor, resulting in trade-offs and clarity for  
both sides going forward. NSPML did concede a potential amount of $18 million in  
trenching costs in favour of Nalcor. However, this was a matter of dispute between the  
parties. Like any other negotiation, concluded agreements do provide certainty to the  
parties. Viewed from Nalcor’s perspective, this was undoubtedly an important factor in  
agreeing to commence the NS Block before the LIL commissioning, that being a risk or  
obligation it had to assume. Given the potentially significant financial benefits of starting  
the NS Block now, and avoiding the need for NS ratepayers to incur the burden of  
additional replacement energy costs, the Board considers the trade-off of trenching costs  
to be reasonable and appropriate in comparison. Further, given the relative timing of the  
trenching work after the ML commissioning, the Board also considers the inclusion of  
operating and maintenance (O&M) costs into the Joint Development Agreement to be  
appropriate.  
[55]  
Moreover, despite the MUNISassertions to the contrary, the Board is  
satisfied that the start of the NS Block under the Acceleration Agreement does secure  
firm capacity to NS Power, in that it is the subject of a contractual commitment (which  
also requires the energy to be made up in the event of a forgivable event), which is  
supported by dedicated generation capacity, and is accessed through a firm transmission  
path. The NS Block energy produced at the MFGS and delivered through the LIL and  
Document: 291318  
- 26 -  
Maritime Link is clearly distinguishable from the nature of the New Brunswick energy  
imports canvassed in the BUTU proceeding.  
[56]  
Taking all the above into account, the Board concludes that it was  
reasonable and appropriate for NSPML to negotiate and enter into the Acceleration  
Agreement. The Agreement had the result of moving up the start of the NS Block,  
Supplemental Energy and Nalcor Market-priced Energy, while also helping NS Power to  
avoid the necessity of having to purchase costly replacement energy in the absence of  
the NS Block.  
5.4  
When should the equivalent economic value of NS Block under-  
deliveries be determined?  
[57]  
By definition, as set out in the commercial agreements between Emera and  
Nalcor, the NS Block itself (excluding for the time being Supplemental Energy) is to be  
delivered during NS Power’s peak hours (i.e., 8 am to midnight, seven days per week,  
throughout the year). Further, the five-year Supplemental Energy is to be delivered in the  
winter months (i.e., November to March), seven days per week, in off-peak hours. Since  
NS Power’s system is winter peaking, energy delivered during those months, particularly  
during the peak hours, has the greatest economic value to the Utility.  
[58]  
The requirement to receive the NS Block during peak hours, as well as the  
Supplemental Energy during the winter months, is not coincidental. The economic value  
of those allocations of energy were integral to the Board’s decision that the Maritime Link  
Project was the lowest cost alternative for Nova Scotia customers, when NSPML’s  
original application was considered in 2013.  
[59]  
Any delay in the delivery of the NS Block and the Supplemental Energy  
which results in the re-delivery of such energy later than the winter peaking period (i.e.,  
Document: 291318  
 
- 27 -  
after the month of March) leads to it being delivered at times when NS Power’s system  
generally experiences lower loads, when energy from NS Power’s own generation  
sources and imports can typically be obtained at lower costs than during the winter  
months. Conceivably, the subsequent re-delivery of the NS Block and the Supplemental  
Energy could also result in it being offered when the Utility is unable to use all or part of  
the energy.  
[60]  
Thus, while NSPML has assured the Board and NS Power’s customers that  
any undelivered energy will soon be re-delivered, the question remains how NS Power  
will ensure the energy it receives from Nalcor will have similar economic value to its value  
if it had been delivered when it should have been following August 15, 2021.  
[61]  
While not specifically addressed during the hearing, the Board infers that  
similar considerations to the above also apply to the forecast delivery of Nalcor Market-  
priced Energy.  
[62]  
The quandary created by the delayed delivery of the NS Block and  
Supplemental Energy was highlighted by counsel for the Industrial Group in her  
submissions:  
There is also uncertainty as to the timing of redelivery by Nalcor of the under-delivered  
energy and the complexity of ensuring it is of “similar value”. … [Emphasis added]  
[Exhibit N-50, p. 5]  
[63]  
In questioning by the Board, Mr. Landrigan of NS Power, stated that NS  
Power is working with Nalcor representatives about delivery schedules to ensure that the  
energy will be re-delivered at a time that is economically beneficial to NS Power’s  
ratepayers:  
A.  
So schedules for deliveries and what would -- the difference would be provided on  
a daily basis except for weekends. So there would be a schedule for three days during  
that period.  
Document: 291318  
- 28 -  
So we have, on a handful of occasions, confirmed the exact numbers of the  
undelivered energy so that we have alignment between us and Nalcor in terms of the  
accumulated value, if it's to be redelivered on a one-to-one basis, and so there has been -  
- I guess there's constant communication between the marketing groups in terms of what's  
available to be delivered and then the accumulation of the undelivered amount.  
[Transcript, December 7, 2021, pp. 464-465]  
[64]  
Mr. Landrigan also acknowledged that the review of any such energy  
transactions would fall within the scope of a future FAM Audit:  
Q.  
(MacDougall) … what's the process you're anticipating for showing ratepayers,  
confirming to ratepayers and this Board that for the undelivered energy, specifically created  
by the Acceleration Agreement, that it is of similar value?  
A.  
(Landrigan) I have -- I shouldn't say it this way. I have no doubt it will be a part of  
the FAM audit process, which is the -- which is the proper place for this to be -- in my mind,  
for this to be reviewed.  
[Transcript, December 7, 2021, pp. 520-521]  
[65]  
In questioning by counsel for the Industrial Group, Bates White stated that  
the appropriate forum to review the financial aspects about the re-delivery of previously  
undelivered energy is through the FAM Audit process:  
Q.  
(Rubin) Okay. You said, if it's done right it goes along way to demonstrate that the  
Acceleration Agreement was a prudent decision. Are you suggesting that that needs to  
await a valuation of those product services? Like, is that -- like, to make sure that it's an  
equivalent value, or is this -- or are we looking at a FAM decision?  
A.  
(Musco) Well, I think the venue, you know, I think that's one of the questions, is  
the proper venue for that determination. It's certainly, having conducted -- Bates White  
having conducted the audit in the past, that's something we would look at, absolutely. We'd  
be looking at the administration of that contract consistent with its terms, and we'd be  
looking at the outcomes and the various calculations that support the decision-making  
around that contract. So I think that would be a reasonable place for it to land and to be  
reviewed.  
[Transcript, December 8, 2021, pp. 731-732]  
[66]  
Mr. Musco of Bates White, in his role as FAM Auditor, also identified the  
significance of assessing such transactions with an eye on whether the energy was re-  
delivered at times, and in quantities, which maximize economic benefit for NS Power’s  
ratepayers.  
Document: 291318  
- 29 -  
Findings  
The consequences from any delay in receiving the NS Block prior to, and  
[67]  
following, the Acceleration Agreement, fall upon NSPML and have been dealt with earlier  
in this Decision as directed by the Board.  
[68]  
However, the risks of prudently administering the re-deliveries of this energy  
under the Acceleration Agreement and the Energy and Capacity Agreement is now upon  
NS Power. The Board considers that the FAM Audit process is the appropriate forum to  
review the economic value received by ratepayers from transactions involving the re-  
delivery of the NS Block, Supplemental Energy, and Nalcor Market-priced Energy.  
5.5  
[69]  
Integrity of Submarine Cable  
The submarine cable program for the ML Project involved the design,  
manufacture, transport, installation and protection of a submarine high voltage direct  
current (HVDC) transmission system between Cape Ray, Newfoundland and Labrador,  
and Point Aconi, Nova Scotia. Key elements of the program included:  
Approximately 340 kilometres of +/- 200 kV HVDC submarine cable (two  
submarine cables in total);  
Approximately ten kilometres of land cable;  
Accessories, including terminations, joints and anchoring devices;  
Fiber optic strands in the cable for temperature sensing;  
Telecommunications housed with a separate cable jacket package; and  
Five kilometres of spare HVDC submarine cable and one kilometre of spare  
land cable.  
Document: 291318  
   
- 30 -  
[70]  
NSPML engaged Nexans Norway AS (Nexans) to design, manufacture,  
install and protect the submarine cables. The cables were manufactured using mass  
impregnated (MI) insulation system technology, which is used extensively in HVDC  
projects. During the original design of the cable route, NSPML assessed the risk to the  
cables of external contact by sea ice, ship anchors, and fishing gear. Additional planning  
and preparation work in advance of cable installation included cable routing surveys,  
stakeholder engagement and consideration of environmental requirements and mitigation  
of effects on interested parties such as local lobster, crab and fish harvesters. The cable  
route was later optimized within its established corridor to maximize natural protection  
from external hazards.  
[71]  
To address nearshore wave, storm, ice and rock conditions, as well as the  
greater incidence of marine traffic, NSPML used Horizontal Directional Drilling (HDD) to  
construct micro-tunnels at the cable landfall transition on either side of the Cabot Strait.  
Beyond the HDD exits, the cable was protected from external hazards, as necessary,  
using a combination of trenching and rock cover.  
[72]  
In mid-2018, following cable installation, NSPML retained Xodus Group, an  
international energy consultancy, to undertake a “Cable Integrity Risk Assessment”  
(CIRA). This assessment was completed using as-built survey information provided by  
Nexans to confirm that the subsea cables’ reliability and availability targets had been  
satisfied. Xodus’ work included the creation of a comprehensive probabilistic risk model.  
Xodus, in consultation with other recognized experts in cable protection and ice  
mechanics, concluded that the cables are well protected in their “as built” condition  
(lifetime availability of 97% or greater).  
Document: 291318  
- 31 -  
[73]  
In 2018, NSPML learned that redfish stocks had rebounded much faster  
than scientists had anticipated, and a new redfish fishery had emerged along the cable  
route, including at depths below 400 metres. With this new information, NSPML assessed  
the risk to the cables at these depths and determined it prudent to deploy additional burial  
to ensure the integrity of the deep-water cable spans. Nexans completed this work and  
associated survey activities by late September 2019. The 2019 survey data was provided  
to Xodus to update the CIRA. Xodus subsequently confirmed that the reliability targets  
for the cables continue to be met.  
[74]  
Laurence Trim of Cable Consulting International (CCI) was engaged by  
Board Counsel in this matter to independently assess the integrity of the ML cables, both  
submarine and land components, to ensure they meet contractual design requirements.  
In his written evidence, Exhibit N-10, Mr. Trim stated the following:  
The thermal properties of the cable constructions from the Nexans factories had  
not been verified. As such, he could not confirm that the submarine cable  
systems are operating within their design limits;  
He calculated the energy availability of the ML to be less than the guaranteed  
availability stated in the ML Reliability, Availability and Maintainability (RAM)  
study prepared by ABB and Nexans; and  
Insufficient evidence had been presented by NSPML to support the design life  
requirement for the ML cable systems.  
[75]  
It was clear in Mr. Trim’s evidence that he was not provided with all the  
information he required to complete his review. Consequently, during the hearing on  
December 8, 2021, the parties agreed to adjourn and reconvene on January 7, 2022. In  
Document: 291318  
- 32 -  
the interim period, NSPML agreed to work with Mr. Trim and provide him with the missing  
information needed to complete and update his cable integrity review. Upon NSPML  
providing Mr. Trim with the additional information, he filed his amended written evidence  
[Exhibit N-44] on December 23, 2021. After reviewing Mr. Trim’s amended evidence, the  
parties advised the Board that cross-examination of Mr. Trim was not required. The  
Board, therefore, cancelled the hearing scheduled for January 7, 2022.  
[76]  
Mr. Trim’s updated evidence concluded the following:  
The thermal properties of the cable constructions from the Nexans factories have  
been verified. Therefore, the cable system as designed, and under the  
assumption that all the engineering design parameters adopted are verified as  
being valid for the as installedHVDC land and submarine cable systems,  
should operate within the thermal and electrical stress limits of the cable design.  
Further, given that the ambient sea bottom temperatures below 200m water  
depth remains between 6 to 7oC all year around, the cable in this region should  
remain within the maximum design temperature parameter;  
The energy availability of the ML is in the range 91% to 98% rather than the  
guaranteed ≥ 98% stated in the RAM study, with an optimistic probability of it  
ranging from 95% to 97%. However, Mr. Trim noted that the ability of the ML to  
transmit the NS Block and Supplemental Energy should be largely unaffected by  
system availability. So long as the outage only affects one HVDC cable then the  
link will still be capable of transmitting 250MW of power via the remaining healthy  
cable operating in monopole configuration with a sea return; and  
Document: 291318  
- 33 -  
Test evidence has been presented to support the 50-year design life requirement  
for the Maritime Link cable system.  
[77]  
Mr. Trim also presented three recommendations in his updated evidence:  
NSPML develop a document to describe the thermal characteristics of the ML  
cables using as measured soil thermal resistivity data, appropriate sea bottom  
temperatures (as determined from the 2011 survey and seasonal swing  
information) and distributed temperature sensing (DTS) data;  
NSPML periodically review the cable failure rate and RAM study using the most  
up to date data; and  
For planning purposes, NSPML consider adopting the CIGRE TB815 industry  
failure rate of 0.0029 failures/100 circuit km/year, or 1 failure every 10 years.  
In its final submission, NSPML agreed to implement these recommendations.  
Findings  
[78]  
The Board finds that the as installedML submarine cable system meets  
its contractual design requirements. The Board directs NSPML to implement the  
recommendations presented by Mr. Trim in his updated evidence. In its Compliance  
Filing, NSPML is to provide a schedule for when it intends to implement these  
recommendations.  
5.6  
[79]  
Depreciation Policy and Depreciation Rates  
In previous decisions, the Board directed NSPML to depreciate its rate base  
over a period of 35 years to match the delivery term of the NS Block. The Board approved  
recovery of depreciation to commence in 2020 to enable NSPML to meet Federal Loan  
Guarantee (FLG) principal repayment obligations. For 2020 and 2021 NSPML has  
Document: 291318  
   
- 34 -  
recovered $61.5 million on account of depreciation to meet the FLG requirements and  
pay return on equity to NSPML shareholders. These interim payments have been  
subtracted from capitalization project costs in setting the opening rate base. Gannett  
Fleming conducted a depreciation study on NSPML’s assets.  
[80]  
In its post-hearing brief, NSPML summarized Gannett Fleming’s proposal:  
to distribute the ML Project Costs between two broad asset categories- Electric  
Plant in Service and General Plant and thirteen sub-categories within these two  
broad categories, all as set out in Gannett Fleming’s study and with each  
subcategory being assigned its own depreciation rate;  
to designate an annual depreciation amount based on the assumptions described  
in Gannett Fleming’s report, including the overriding assumption that all assets  
must be fully depreciated at the end of the 35-year duration of the NS Block when  
the ML is to be transferred to Nalcor for $1;  
going forward, to seek determination of depreciation expense on future  
(sustaining) capital investments at the time of approval by the UARB of such  
investments; and  
all subject to periodic revision to depreciation amounts as may be proposed by  
NSPML and determined appropriate by the UARB.  
[Exhibit N-48, pp. 33-34]  
[81]  
[82]  
Gannett Fleming proposed an annual depreciation expense of $56.8 million.  
NSPML further noted that under its currently approved accounting policy  
land costs would normally be excluded from depreciation and recovered when the land  
was sold. However, under the Nalcor commercial agreements, NSPML must transfer  
these assets to Nalcor once the NS Block has been fully delivered in 35 years. NSPML  
seeks to recover these costs through including them in the allowance for depreciation.  
[83]  
Board Counsel consultants Grant Thornton and Bates White both reviewed  
the depreciation evidence. Grant Thornton found the 35-year recovery period to be  
appropriate and otherwise expressed no concerns with respect to the policy. Bates White  
recommended approval of NSPML’s proposed 2022 depreciation expense.  
Document: 291318  
- 35 -  
[84]  
[85]  
No other party commented on depreciation policy.  
Findings  
The Board approves the depreciation policy as summarized above and  
more fully outlined in Section 3.3 of NSPML’s application and detailed in the Gannett  
Fleming depreciation study. The Board also approves, in the unique circumstances of  
this situation, including an allowance for depreciation of land costs in NSPML’s annual  
depreciation.  
5.7  
[86]  
NSPML’s Overall Project Execution  
Over the course of the ML Project, NSPML was confronted with a number  
of significant challenges. These included:  
Default of the project’s main overland transmission line contractor;  
Escalation of disputes with the replacement transmission line contractor;  
A tragic contractor safety incident in which a powerline technician lost his life;  
The failure of a transmission tower anchor and the resultant collapse of a tower;  
Quality control concerns during manufacturing of the subsea cable;  
Buckling of exterior insulated converter station wall panels and their subsequent  
replacement during station construction;  
Several subsea trenching obstacles including a late emergence of a redfish fishery  
necessitating additional cable burial activities once the project was in service;  
Extreme weather conditions and associated scheduling complexities; and  
Competition for skilled and qualified workforce.  
Document: 291318  
   
- 36 -  
NSPML’s response to these challenges, and its overall approach to planning and  
executing the ML Project, are described in Section 2.0 and Schedules 1 through 7 of its  
Application and are discussed in the following sections.  
5.7.1 Project Planning, Management, and Governance  
[87]  
Under the framework of the commercial agreements, Nalcor and NSPML  
formed a joint development committee (JDC) with general oversight of the development  
of the ML Project, including project design, contractual matters, budget and schedule.  
The JDC approved all major contracts including those for converter stations, transmission  
line construction and contractor replacements, and submarine cables. In addition,  
NSPML’s Senior Project Manager reported directly to the JDC on a regular basis to keep  
it fully apprised of the project status.  
[88]  
NSPML’s President and CEO was the Project Owner, and the second level  
of approval after the Senior Project Manager under the project management structure.  
The President and CEO was given the authority to approve contracts and change orders  
up to $2 million in value. Beyond that value, NSPML required the approval of the Project  
Decision Board (for decisions up to $25 million in value) or the Emera Newfoundland and  
Labrador Holdings Inc. (ENLH) Board of Directors (for decisions of more than $25 million  
in value). At the base of the project governance and oversight structure was the Project  
Management Team (PMT). Led by a Senior Project Manager and an Assistant Project  
Manager, the PMT was organized into ten teams, each with its own lead reporting to the  
Senior Project Manager. The PMT included professionals with a combination of  
engineering, construction, utility and project management training and experience.  
Document: 291318  
 
- 37 -  
[89]  
NSPML’s procurement program for all major project contracts involved  
identifying top global and local contractors, an expression of interest and request for  
proposal process, and a protocol for evaluation of contract bids against pre-defined  
criteria through review by NSPML internal subject matter experts and support teams.  
[90]  
Working with external legal experts with international experience in the  
HVDC cable and converter industry, NSPML’s legal and procurement teams developed  
a contract standard that became the starting point for negotiations on all major scopes of  
work. The terms and conditions of this standard were aimed at allocating risk in a manner  
that optimized value and cost certainty and reflected FLG and ML-JDA contractual  
requirements.  
[91]  
NSPML implemented a contract management strategy focused on closely  
monitoring contractor performance to maintain the value contracted for and to defend  
against unwarranted claims. NSPML deployed its specialized teams setup under the  
PMT structure for each major work program, to identify and address project challenges  
and emerging risks, and apply project management practices to minimize schedule  
slippage and scope creep when matters did not go as planned. As part of this effort,  
NSPML developed a project execution risk plan to identify and assess risks to design and  
execution and implement mitigation measures when warranted.  
[92]  
With respect to NSPML’s management of the ML Project, John Reed of  
Concentric, stated:  
The project management and oversight structures functioned exceptionally well,  
responding appropriately to adverse conditions, and resulting in the completion of the ML  
Project on-time and within the approved budget.  
[Exhibit N-1, Schedule 7, Att. 1, p. 5]  
Document: 291318  
- 38 -  
[93]  
Similarly, Patricia Galloway of Pegasus-Global concluded:  
NSPML recognized the size and complexities of the Project and incorporated  
appropriate dispute resolution and change order management clauses in its major  
contracts to minimize the impacts that potential disputes could have on the Project,  
including avoidance of potential litigation costs.  
…the extensive Project planning that the NSPML Project Team performed pre-execution,  
culminating in Decision Gates (DG) 2 and 3, created favorable circumstances for NSPML  
to have a successful execution of the Project. The NSPML Project Team undertook a  
number of risk management initiatives during early planning of the Project including  
independent risk assessments, quarterly risk reviews, program and process reviews, best  
practice research and continued assessments and reviews as the Project progressed.  
These efforts put NSPML in a position to appropriately award and manage the major  
contracts that comprise the bulk of the Project.  
…NSPML fully evaluated and considered the factors typically considered in the selection  
of contract approaches and delivery methodologies…  
… NSPML’s Contract Strategy & Procurement Plan for the Project, Pegasus-Global found  
that it met industry standard practices.  
… NSPML’s contracting risk management strategy for the Project, Pegasus-Global found  
that it met industry standard practices.  
… NSPML’s contract management to be in alignment with industry standards, which  
facilitated the successful execution of the Project, including providing a structure which  
ensured the ability to add resources and expertise as necessary to address the challenges  
which arose during execution in a way that consistently benefited the Project.  
In resolving the commercial disputes on the three primary contracts, NSPML was able to  
reach a resolution with each contractor that protected the Project and allowed for  
successful completion on time and within budget, while also avoiding additional costs that  
would have arisen from not being able to reach a resolution without arbitration and the  
consequent risk of cross-contractor schedule impacts during claim disputes.  
[Exhibit N-1, Schedule 7, Att. 3, pp. 5-6]  
[94]  
Bates White found no instances of red flags indicating NSPML  
mismanagement or poor procurement practices on the ML Project. Bates White also  
found that NSPML followed a clear change order process, and found no related red flags.  
Document: 291318  
- 39 -  
Findings  
Based on the evidence presented in this proceeding, the Board finds that  
[95]  
NSPML established an appropriate governance structure for the ML Project. The Board  
also finds that NSPML effectively managed the project, incorporating appropriate  
planning, procurement, resourcing, contract management, risk management, and dispute  
resolution processes and strategies. The Board, therefore, finds that NSPML prudently  
managed the design and construction of the ML Project.  
5.7.2 Financing Program  
[96]  
The key feature of NSPML’s approach to financing the ML Project was the  
FLG. Working with the Government of Canada and external financial experts, NSPML  
implemented a structure for financing the project which resulted in full substitution of  
Canada’s AAA credit rating for that of NSPML in support of $1.3 billion in ML bonds. In  
effect, project bond investors provided funding for the project based on acceptance of a  
credit rating for NSPML, as the borrower, equal to that of Canada.  
[97]  
The terms of the FLG required a segregation of project finance risk from  
NSPML. To meet this requirement, the structure required the formation of the ML  
Financing Trust (ML Trust), and a separate project company, NSPML. This structure was  
a requirement of Canada, as guarantor, to “ring fence” the ML assets in order to support  
the perfection of security in favour of Canada in support of its guarantee of the project  
borrowing and to provide certainty, clarity, and comfort to the bond investors. In further  
support of Canada’s interest in successful execution of the project, an Independent  
Engineer (IE) was retained to provide oversight on behalf of Canada of construction of  
Document: 291318  
   
- 40 -  
the project. The IE also approved associated construction funding draws from the ML  
Trust funds.  
[98]  
Having secured FLG support for the project, NSPML received approval from  
the Board to finance 70% of the capital cost of the ML Project with a forward bond  
issuance under the FLG. The Board also approved financing of the remaining 30% of the  
capital cost of the project with equity. On April 23, 2014, NSPML implemented an up-  
front borrowing program and $1.3 billion of federally guaranteed bonds were issued with  
a 3.5% coupon rate. The proceeds from these bonds were deposited in the ML Trust.  
Those funds were then invested in structured deposit notes until required to meet  
construction draws throughout the period of construction.  
[99]  
In keeping with the terms of the FLG, NSPML hedged interest rate risk for  
the life of the project by securing all of the necessary FLG debt financing at the beginning  
of the project. NSPML hedged the majority of the Government of Canada benchmark  
rate risk at a simple average rate (i.e., hedging cost) of 3.02%. This short-term hedging  
program ensured that NSPML met the FLG Term Sheet requirement that “a hedging  
program shall be put in place for each Borrower at Financial Close” and provide protection  
against an increase in the underlying benchmark rate between financial close and the  
financing bond issuance. Between the dates the financial hedges were executed in early-  
mid February and the April 23, 2014, issuance of the FLG bonds, the underlying  
Government of Canada rates declined rather than increased. This resulted in a hedging  
cost of approximately $36 million, the bulk of which resulted from the interest rate decline  
from the rate at which the hedge was taken.  
Document: 291318  
- 41 -  
[100]  
As noted elsewhere in this Decision, Cliff Inskip of Polar Star Advisory  
Services, concluded that NSPML's upfront bond financing strategy was not only a very  
prudent financing strategy but also one that very likely provided a net benefit to electricity  
customers in Nova Scotia. He also found that NSPML’s interest rate hedging strategy  
was very defensible and prudent. Grant Thornton also concluded that NSPML’s chosen  
approach to financing construction of the ML was an acceptable means to mitigate project  
risk and was in accordance with the terms of the FLG.  
Findings  
[101]  
The Board finds that NSPML’s combination of an up-front borrowing  
program and hedging instrument was an acceptable financing strategy under the terms  
of the FLG. The Board also finds that the chosen financing strategy was an appropriate  
and prudent means to mitigate project risks, including:  
Availability of financing throughout construction;  
Interest rate volatility; and  
Unknown borrowing costs throughout the life of the project.  
5.7.3 Management of the Submarine Cable Program  
[102]  
The physical components of the ML Project’s submarine cable program  
have been previously described in this Decision. The following sections describe some  
of the challenges that arose during implementation of the program and how NSPML  
addressed these challenges.  
[103]  
NSPML conducted significant planning work to select a two-kilometre wide  
corridor across the Cabot Strait in which to install the submarine cable system. This  
involved cable routing surveys, stakeholder engagement and consideration of  
Document: 291318  
   
- 42 -  
environmental requirements and mitigation of effects on interested parties such as local  
lobster, crab and fish harvesters. Based on this initial work, NSPML, in consultation with  
Nalcor and other stakeholders, also chose a cable protection strategy involving mainly  
burial through trenching to 400m water depth, with supplemental rock installation in areas  
where target burial was unachievable.  
[104]  
In 2011, NSPML and Nalcor formed a core evaluation team to jointly  
manage the procurement process for the submarine cable systems. The team prepared  
criteria and invited top global HVDC submarine cable suppliers to submit Expressions of  
Interest (EOIs) for submarine cable design, supply, and installation. The EOIs received  
were evaluated against key criteria focused on identifying safe, reliable, qualified,  
technically competent, and financially sound candidates. Based on the results of the EOI  
evaluation process, six global HVDC suppliers were approved as bidders and invited to  
participate in the cable contract Request for Proposal (RFP).  
[105]  
NSPML’s procurement and legal teams worked with legal experts in HVDC  
submarine cable projects to prepare contract terms and conditions to govern the work.  
These were appended to the RFP and used as a baseline for contractual negotiations.  
On August 6, 2013, NSPML’s Decision Board approved a recommendation to negotiate  
with two cable proponents: ABB and Nexans. Following an extensive review and  
negotiation process, NSPML decided that Nexans’ manufacturing and vessel supply best  
met NSPML’s commercial and technical needs.  
[106]  
The cable contract was reviewed by NSPML and its counsel as well as  
Nalcor, the IE, and legal counsel for Canada before being approved for execution. The  
contract with Nexans was executed on January 30, 2014. The contract provided for a  
Document: 291318  
- 43 -  
one-time price adjustment mechanism to fix foreign exchange and commodity prices,  
which was exercised on February 7, 2014. After that date, Nexans assumed the risk of  
all commodity and foreign exchange volatility.  
[107]  
To accommodate the length of cable required (two cables, each  
approximately 170 km) for the preferred 2017 installation season, two separate Nexans  
cable manufacturing sites were used, one in Halden, Norway and the other in Futtsu,  
Japan. While the manufacturing process at Halden concluded in March 2017, a defect in  
the lead sheath of the cable being manufactured in Futtsu was discovered in January  
2016. In response, Nexans immediately ceased production at Futtsu and launched an  
investigation into the source and extent of the problem. NSPML worked closely with  
Nexans on the root cause investigation into this issue. The manufacturing issue was  
eventually resolved, with no impact on the cost or schedule for the project.  
[108]  
NSPML continued to refine its cable protection strategy throughout the  
cable manufacturing and construction phase of the Project. In August 2015, Nexans  
performed a bathymetric and sub-bottom profiling survey in the nearshore Point Aconi  
sand channel area. The survey data allowed Nexans to identify positive natural features  
to enhance cable protection, as well as potential seabed obstacles. Nexans used the  
results of its analysis to further optimize the existing cable route and avoid identified  
obstacles and features of concern on the seabed.  
[109]  
Prior to the installation of the submarine cables, a horizontal directional  
drilling (HDD) campaign was completed for the transition facilities where the marine  
cables make landfall. The HDD conduits protect the cable from shoreline and nearshore  
Document: 291318  
- 44 -  
hazards. NSPML undertook the HDD campaign the season prior to cable installation to  
remove the potential risk that a back-to-back drill and installation campaign would create.  
[110]  
During cable installation in 2017, Nexans inadvertently caused one of the  
cables to exceed its minimum bend radius. When investigation revealed that the cable  
had suffered resulting damage, Nexans replaced the damaged section of the cable.  
NSPML recovered all associated costs through its project insurance program.  
[111]  
In 2018, NSPML learned that redfish stocks had rebounded much faster  
than scientists had anticipated, and a new redfish fishery had emerged along the cable  
route, including at depths below 400 metres. Because the submarine cables were surface  
laid over a 59-kilometre section below 400 metre water depth, they would not have been  
physically protected from certain bottom trawling activities associated with the proposed  
redfish fishery. To mitigate the risk of contact to the cables, NSPML retained Nexans to  
trench the cables below 400m water depth. The cost of this additional work was  
approximately $18 million.  
Findings  
[112]  
The Board finds that NSPML’s procurement approach for the submarine  
cable system was appropriate. Further, the Board finds that the one-time price  
adjustment mechanism to fix foreign exchange and commodity prices allowed NSPML to  
effectively mitigate the risk associated with the long lead time and large volumes of  
commodities required to manufacture the cable.  
[113]  
With respect to the cable route selection process, the Board notes that route  
optimization efforts led to increased project costs resulting from a requirement for a longer  
length of cable than originally envisioned. However, as noted in NSPML’s response to  
Document: 291318  
 
- 45 -  
Board IR-29 [Exhibit N-7], optimization of the route provided benefits. These included  
obtaining more favorable positions for HDD exit points, re-routing around poor burial  
areas to allow for cable trenching instead of rock dumping for cable protection, and  
avoidance of pock marks that may have created unwanted free spans in the cables. The  
Board finds that these benefits justified the additional costs of cable route optimization.  
[114]  
submarine cable program.  
5.7.4 Management of the Overland Transmission Program  
The overland transmission program of the ML Project consisted of five lines:  
Overall, the Board finds that NSPML effectively and prudently managed the  
[115]  
two direct current (DC) lines: one in Newfoundland running from Bottom Brook to  
Cape Ray, and one in Nova Scotia running from Point Aconi to Woodbine;  
one alternating current (AC) line in Newfoundland connecting the Bottom Brook  
and Granite Canal substations; and  
two grounding lines at each of the DC transmission facilities.  
In total, the transmission program work involved clearing more than 1,800 hectares of  
land, erecting more than 2,600 steel and wood transmission support structures, and  
stringing 2,000 kilometres of conductor.  
[116]  
To help ensure the success of the overall ML Project, NSPML needed to  
effectively manage the schedule for the transmission line program. Certain lines had to  
be completed at specific times to align with a program of planned outages for testing.  
Failure to meet any component of the transmission line construction schedule, and in turn  
of the testing outage schedule, could have resulted in project delays and extra costs. To  
help mitigate the risk of potential schedule slippage, NSPML:  
Document: 291318  
 
- 46 -  
(a) engaged in advance procurement of long-lead steel towers, foundations, conductor,  
and related materials;  
(b) planned for and completed tree clearing and site preparation activities in advance of  
construction to address the migratory bird construction exclusion period (which  
generally occurs from May to July each year);  
(c) contracted detailed design, engineering, and construction of each of the three  
components of the transmission line program on a consolidated basis; and  
(d) procured field camp accommodations to house and support up to 100 personnel  
involved in the construction of the Newfoundland transmission works and the Granite  
Canal switchyard in the Newfoundland interior, which mitigated the challenges of  
regular travel to this remote location and enhanced the safety and efficiency of the  
work.  
[Exhibit N-1, p. 29]  
[117]  
In developing the transmission line scope of work, NSPML determined that  
combining the scopes for constructing all five transmission lines in a single contract was  
preferred. NSPML believed this would allow one contractor to assume and manage the  
scheduling, integration, and associated risks of a geographically dispersed and multipart  
construction program. NSPML issued an RFP for the transmission program to thirteen  
companies and, in response, received seven proposals. NSPML’s proposal evaluations  
focused on three proponents: Abengoa, Emera Utility Services (EUS), and Valard. The  
price spread among them was significant, with Abengoa’s proposal being lower than the  
next closest bid and within the expected pricing for the works. Further, since 2008,  
Abengoa had been ranked as the largest international transmission and distribution  
contractor in the world by leading trade publications.  
[118]  
Abengoa’s bid for the work met all the requirements in the bid evaluation  
process, and Abengoa had secured a local contractor to support their construction  
execution. As such, NSPML opted to award the transmission line program to Abengoa  
in February 2015. However, NSPML had observed that Abengoa’s share price had been  
subject to significant declines just prior to contract award. As such, NSPML determined  
Document: 291318  
- 47 -  
it prudent to undertake additional due diligence and concluded that the financial risks  
could be managed with Abengoa increasing its letter of credit prior to award, in addition  
to other protections NSPML built into the Abengoa contract.  
[119]  
Abengoa was slow to begin its project execution and did not sufficiently  
organize its workforce to carry out the work required on multiple work fronts. Following  
Abengoa’s pre-insolvency filing in Spain on November 25, 2015, Abengoa began to  
experience global cashflow difficulties, resulting in subcontractors complaining of late  
payment. Eventually, Abengoa failed to meet contract performance expectations, despite  
its assurances to the contrary, and its work quality and schedule began to slip. When it  
became clear that Abengoa could not complete the work to NSPML’s satisfaction and to  
the terms of its contract, NSPML triggered its contractual rights and:  
(a) took assignment of Abengoa’s contract with PowerTel Utilities Contractors Limited  
(PowerTel), Abengoa’s main subcontractor tasked with completing the AC and  
grounding lines;  
(b) called on Abengoa’s letter of credit, recovering $38 million to offset the cost of securing  
a replacement contractor;  
(c) worked closely with the sureties backing Abengoa’s performance bond (Sureties) to  
re-award the DC line work to a replacement contractor, Emera Utility Services Inc.  
(EUS)-Rokstad Joint Venture (ERJV); and  
(d) settled with the Sureties to recover residual losses associated with the need to  
reschedule and re-contract the transmission program.  
[Exhibit N-1, p. 30]  
[120]  
Upon taking assignment of the PowerTel subcontract and issuing a contract  
with ERJV to replace Abengoa, NSPML divided the transmission line work into two work  
scopes, with PowerTel responsible for the AC and grounding lines and ERJV responsible  
for the DC Transmission Lines. NSPML believed that this separation of the work,  
combined with the resulting closer engagement in the work by NSPML’s PMT, would best  
preserve the transmission line work schedule and ensure timely completion of this work  
Document: 291318  
- 48 -  
scope to mesh with the other main work scopes on the overall ML Project. NSPML added  
resources to its PMT so that it could appropriately monitor and manage the work of these  
two contracts, maintain the project schedule, and help ensure cost effective overall project  
completion.  
[121]  
In January 2017, PowerTel experienced a safety incident in which one of its  
powerline technicians lost his life. As a result, NSPML immediately implemented a project  
wide safety stand down that remained in place until all parties concerned, including  
Newfoundland Occupational Health & Safety (NLOHS), the contractor, and NSPML, had  
sufficient information to confirm that work could resume safely. While most contractors  
returned to work in a matter of days, major components of the transmission line work  
experienced a delay of several weeks until the applicable NLOHS stop work orders were  
lifted. In addition, the DC line stringing work in Nova Scotia halted for several weeks until  
the root cause of the incident in Newfoundland could be determined.  
[122]  
Once the stop work orders were lifted, it was clear that PowerTel’s ability to  
achieve the completion date in the contract was at risk. Further, PowerTel had requested  
an equitable adjustment to its contract price, non-resolution of which could have resulted  
in additional schedule delays. As a result, NSPML and PowerTel entered into a  
settlement agreement that secured a path to construction completion. Ultimately  
PowerTel completed the balance of its work on the AC and grounding lines in time for  
testing to take place on schedule. In addition, EUS completed the DC line work in NS by  
May 2017, which, while five weeks behind schedule due to the work stoppage, was still  
in time for all required testing to take place.  
Document: 291318  
- 49 -  
[123]  
The work on the DC line in NL also proved to be challenging. Rokstad  
experienced schedule slippages, and contractual disputes arose between Rokstad and  
NSPML. Rokstad and NSPML continued to advance work while each challenge  
emerged. As the timeline to complete the work on schedule shortened, NSPML increased  
its resources to monitor and assess claims and prepare for potential disputes. Rokstad  
improved its performance in the spring of 2017 and was on track for substantial  
completion of the Newfoundland DC line by July 31, 2017.  
[124]  
Then, in June 2017, a tower on the Newfoundland DC line collapsed and  
NLOHS issued a stop work order. This effectively ceased NL DC transmission work for  
almost three months, putting completion of the project in 2017 at risk. Further  
complicating matters, by mid-October 2017, ERJV’s resources had almost been  
exhausted as a result of its parent company, Carillion PLC, becoming financially  
distressed. To address these challenges, NSPML:  
(a) devoted substantial technical, commercial, and legal resources and, working with  
NLOHS and ERJV, designed and executed a program to inspect all previously installed  
tower anchors in Newfoundland and replace those found to be defective;  
(b) worked with local NL contractors to implement an innovative means they proposed to  
secure the towers while the anchoring systems were tested using techniques which  
had to be developed and proven to satisfy NLOHS; and  
(c) recognizing Rokstad’s financial difficulties (which had been exacerbated by the  
financial deterioration of Rokstad’s parent company, Carillion PLC, in the United  
Kingdom), negotiated an interim settlement utilizing payment milestones to incent  
mechanical completion of the Newfoundland DC line by the end of November 2017, in  
time for scheduled testing, and deferring outstanding commercial disputes for later  
resolution.  
[Exhibit N-1, p. 32]  
In the end, and despite its best efforts, ERJV did not achieve Mechanical Completion in  
NL until December 3, 2017, later than the agreed upon date but in time for the planned  
testing.  
Document: 291318  
- 50 -  
[125]  
In February 2018, NSPML reach a final settlement agreement with ERJV.  
As confirmed by Bates White, the final agreement eliminated all future claims against  
NSPML by the endorsement of the court-appointed monitor overseeing the Carillion  
Canada insolvency process and the approval of the Canadian government pursuant to  
the requirements of the ML Credit Agreement. The settlement also avoided a potential  
lengthy and costly arbitration process and ensured that all undisputed subcontractor and  
supplier accounts were paid.  
Findings  
[126]  
The cost of the transmission line program was approximately $129 million.  
This exceeded the DG3 budget by roughly 40% and required the use of a significant  
amount of the overall ML Project contingency amount. However, the Board finds that the  
transmission line program did, in fact, face significant challenges that had not been  
foreseen. Despite these substantial challenges, NSPML completed the transmission  
work scope in time to avoid cross-contractor delays and initiate commissioning as soon  
as end to end connectivity had been attained, helping to preserve the overall ML Project  
schedule and budget.  
[127]  
With respect to the Abengoa contract, when Abengoa failed to meet  
performance expectations, and when the quality and schedule of Abengoa’s work began  
to slip, NSPML had the contractual tools to actively manage the work and to prepare for  
a possible insolvency. The Board finds that these contractual protections allowed NSPML  
to proactively manage and ultimately terminate and replace Abengoa with no incremental  
cost to customers.  
Document: 291318  
 
- 51 -  
[128]  
Regarding the contract between NSPML and ERJV, the Board notes that  
EUS (a member of ERJV) is an affiliate of Emera. As such, the NSPML procurement  
team engaged in a self-provisioning analysis, as required by NSPML’s Affiliate Code of  
Conduct, prior to deciding to award the work to ERJV. This analysis confirmed that the  
ERJV bid provided the best value. As noted by NSPML in its application, replicating the  
success it had achieved with PowerTel, NSPML negotiated a completion agreement with  
ERJV that gave the best chance possible of completing the work without exposing the  
project to additional risk. The Board agrees.  
[129]  
The Board also finds that the settlement agreements reached between  
NSPML and PowerTel and NSPML and ERJV were appropriate and helped to avoid  
potential future claims against NSPML.  
[130]  
Overall, the Board finds that through deployment of the necessary  
resources and prudent efforts, NSPML was able to overcome the transmission line  
program challenges, maintaining the overall ML Project budget and schedule, and  
avoiding the risk of future claims. The Board, therefore, finds that NSPML effectively and  
prudently managed the transmission line program.  
5.7.5 Management of the Converter Station and Related Works  
Program  
[131]  
NSPML’s converter station and related works program included the  
following elements:  
two 500 MW +/- 200 kV DC Voltage Source Converter (VSC) stations and facilities  
to connect incoming and outgoing conductors;  
HVAC substations at Granite Canal, Bottom Brook, and Woodbine to tie the  
Maritime Link into the existing utility systems;  
Document: 291318  
 
- 52 -  
two transition compounds at Cape Ray and Point Aconi and installation of land  
cable and associated terminations;  
grounding stations at Indian Head and Big Lorraine; and  
telecommunications systems to connect the converter station control systems to  
the energy control centres of NL Hydro and NS Power.  
The converter stations themselves comprised roughly 90% of the total work program.  
[132]  
In 2012, key technical and commercial members of NSPML’s project team  
completed a review of the HVDC converter market globally to assess available  
technologies and identify acceptable vendors from the limited competition in the  
international HVDC market. NSPML’s contract team then developed an RFP for the  
design, supply, and installation of the HVDC converter stations. Three top global HVDC  
converter suppliers were then pre-qualified by NSPML and the related RFP was issued  
in March 2013.  
[133]  
Following submission of proposals from RFP respondents, NSPML  
concluded that ABB Inc. (ABB) offered the best overall value for the converter stations  
work program. ABB’s proposal showed world-class experience with Voltage Source  
Converter (VSC) technology, proposed a suitable work execution strategy, and provided  
an acceptable overall cost. On two occasions during negotiations with ABB, prior to the  
final scope of work being confirmed, NSPML removed certain scope elements from ABB’s  
work plan, including warehouse construction and civil site rock exposure. This required  
that NSPML increase its own resources to manage both reductions. The combined  
scopes removed totaled approximately $48 million. NSPML and ABB executed the final  
contract on June 26, 2014.  
Document: 291318  
- 53 -  
[134]  
In January 2015, ABB notified NSPML that an agreement with its intended  
lead sub-contractor for the civil and installation component of the converter station scope  
in both Nova Scotia and Newfoundland could not be obtained. As an alternative, ABB  
proposed to take direct control over the construction management of this work. Before  
approving this change, NSPML required that ABB demonstrate its readiness to self-  
perform by outlining a comprehensive strategy for such self-performance. ABB  
demonstrated its ability to perform the work to NSPML’s satisfaction. In August 2015,  
ABB mobilized to the Bottom Brook and Woodbine converter sites and its schedule was  
re-baselined to reflect this change.  
[135]  
ABB struggled with the timely completion of its protection and control  
engineering design. NSPML recognized that any delay to this work could impact critical  
outage work to be conducted by and with the utilities in Newfoundland and Nova Scotia  
scheduled for the summer of 2017. Therefore, NSPML continually monitored ABB’s  
progress in completing key interim milestones for this work. ABB completed all protection  
and control design drawings in March 2017, in time for the realigned outage dates  
required by the utilities in Newfoundland and Nova Scotia to allow for the commissioning  
of the ML Project.  
[136]  
In October 2016, ABB encountered problems with the installation of  
insulated exterior wall panels on the converter station buildings, which showed signs of  
buckling shortly after erection. When it became clear that the panels would have to be  
replaced, NSPML and ABB agreed to install temporary hoarding so that work could  
continue on the building interiors through the winter weather. At the same time NSPML  
worked with ABB to identify a suitable replacement panel supplier and validate the quality  
Document: 291318  
- 54 -  
of the replacement panels, and ABB was able to obtain and complete installation of  
exterior panels in April 2017. Under questioning during the hearing, Mr. Janega  
confirmed that all extra contractor construction costs related to replacement of the panels  
were paid directly by ABB with none absorbed by NSPML.  
[137]  
By mid-2017, ABB raised claims for recovery of substantial costs incurred  
to accelerate the work and address quality issues and schedule delays. After evaluation  
of the fairness of ABB’s claims and considering the need for continued performance and  
commitment to schedule, NSPML proposed a settlement agreement designed to resolve  
outstanding claims and change requests and solidify ABB’s resolve to meet the schedule.  
A completion agreement was executed that set December 5, 2017, as the revised date  
for substantial completion. For reasons not entirely within its control, ABB missed the  
revised substantial completion date, and a second round of negotiation with ABB  
followed. A final settlement agreement was subsequently executed between NSPML and  
ABB.  
Findings  
[138]  
The Board finds that NSPML’s efforts related to the panel buckling issue  
allowed the project to avoid a substantial delay with no added contractor construction cost  
incurred by NSPML. Further, the Board finds that the final settlement between NSPML  
and ABB helped to avoid a potentially costly arbitration, secured cost and schedule  
certainty, and required ABB to provide security covering the value of outstanding claims  
with its subcontractors.  
[139]  
Overall, NSPML and ABB completed the converter station work program  
without jeopardizing the project schedule and below the DG3 budget estimate. The Board  
Document: 291318  
 
- 55 -  
finds that NSPML effectively and prudently managed the converter station and related  
works program to an efficient conclusion.  
5.7.6 Management of Completion and Commissioning  
[140]  
NSPML entered the ML Project completion phase in 2017. This phase  
included the process of connecting systems, testing, commissioning and obtaining final  
approvals. Prior to the commissioning phase, all electrical and mechanical terminations  
were tested, and the integrity of the subsea cable and communication networks were  
finalized. Integrated commissioning began in late 2017 and concluded with the first power  
flow across the ML on December 8, 2017. This was followed by the final stage of  
commissioning, which involved performance of multiple “heat runs” and concluded on  
January 14, 2018. Throughout the completion phase, NSPML worked closely with NS  
Power and NL Hydro to plan construction, energization and commissioning activities as  
applicable to ensure that the utilities and operators had the information required to  
perform their respective scopes of work and, when necessary, provide approvals.  
[141]  
On January 15, 2018, ABB declared its work substantially complete and  
NSPML formally transferred control of the assets to NS Power and NL Hydro and released  
the ML for service. After the ML was placed in service, NSPML reduced its project staffing  
levels as needed. NSPML then completed the following activities:  
completion of remaining milestones under the primary contracts;  
obtained legal acceptance by the Government of Canada that “Commissioning”  
requirements under the FLG had been met;  
obtained legal acceptance by Nalcor under the ML-JDA that requirements for  
“Commercial Operation” had been met; and  
Document: 291318  
 
- 56 -  
finalized land rights and survey requirements, completed subsea cable locational  
mapping and coordinates for marine navigational charts and other project  
completion activities necessary to satisfy environmental and stakeholder  
obligations and contractual completeness.  
Findings  
[142]  
The Board finds that NSPML effectively and prudently managed and  
completed the ML Project completion and commissioning phase.  
[143]  
NSPML continues its ML Project close out work related to a number of  
outstanding insurance, warranty, expropriation and contract claims. Section 5.12 of this  
Decision describes Board directives related to this close-out work.  
5.8  
[144]  
Affiliate Transactions  
Transactions with affiliates of NSPML are examined annually through Code  
of Conduct report filings. As noted by NSPML in Exhibit N-1, NSPML incurred a total of  
$3.5 million in office rent costs paid to affiliates from 2013 to the end of 2020 for rent at  
NS Power’s Water Street Headquarters (Water Street) and Emera Place. The space at  
Water Street was initially leased from NS Power and subsequently from Emera, and the  
amount of space varied over time depending on requirements. As part of the original  
approval process for the renovation of the then Water Street Power Plant, Emera leased  
from NS Power a portion of the Water Street space at above market rates.  
[145]  
The Board, in an NS Power Affiliate Code of Conduct proceeding M09706,  
determined appropriate market rates for NS Power to pay Emera for subleasing Water  
Street space. This was as a result of a finding that NS Power was paying in excess of  
market rates. In its direct evidence, NSPML confirmed that the amount it paid Emera is  
Document: 291318  
   
- 57 -  
approximately $700,000 higher than these amounts determined by the Board in matter  
M09706. The details with respect to amounts paid and adjustments made by the Board  
are contained in two letters in the Affiliate Code of Conduct matter, a Board letter dated  
September 28, 2020, and a response from NS Power dated October 9, 2020.  
[146]  
NSPML stated, both in its direct evidence and in response to Board IR-27,  
that the space provided “needed flexibility” through the course of the Maritime Link  
project.  
[147]  
In response to Board questions Mr. Rendall was asked, once the Board  
determined an appropriate rate for Water Street space, what steps NSPML took to  
renegotiate the lease arrangement or obtain a refund. It appears there was no attempt  
to renegotiate the rate or negotiate a refund.  
Findings  
[148]  
Consistent with the direction given to NS Power, the Board disallows the  
$700,000 in above market rates paid by NSPML to affiliates. This amount is to be  
deducted from the final project capital costs.  
5.9  
[149]  
Accounting or Tax Issues  
Grant Thornton’s evidence addressed several key items, including the  
equity thickness which NSPML operated on throughout the construction period, NSPML’s  
deferred income tax regulatory asset, and its depreciation policy.  
[150]  
The equity thickness which NSPML was permitted to operate on throughout  
the construction period was prescribed in the Board’s original 2013 ML Decision:  
To permit NSPML the flexibility it indicates is required, the Board finds it is appropriate to  
permit NSPML the flexibility to earn up to 35% actual equity during Phase 3, the  
construction phase. During Phase 4, the Board permits NSPML the flexibility to deviate  
throughout the year as required. However, during Phase 4, the operating phase, the Board  
Document: 291318  
   
- 58 -  
does not approve any payout of earnings in excess of the approved ROE with a 30% equity  
thickness.  
[2013 NSUARB 154, para. 302]  
[151]  
Grant Thornton addressed this direction in its evidence, stating that in  
reviewing the actual ROE in each of NSPML’s 2018, 2019, and 2020 financial statements,  
it found that all ROE amounts were under the 9% allowed return. Grant Thornton also  
stated that in calculating the Average Regulated Common Equity percentage for a given  
year, the Regulated Capitalization amount is required. They recommended that as the  
determination of Regulated Capitalization is not readily apparent from the regulated  
financial statements, the Board direct NSPML to reconcile the Regulated Capitalization  
amount in the regulated financial statements. Grant Thornton stated that this would allow  
the Board to determine if the calculation of actual Average Regulated Common Equity  
percent is accurate, and within the regulatory limits approved by the Board.  
[152]  
NSPML addressed the issue of Regulated Capitalization in its Rebuttal  
Evidence, submitting a calculation of the amount, reconciled to NSPML’s Regulated  
Balance Sheet, as at December 31, 2020. Grant Thornton agreed that the amounts  
included in the calculation appeared to have been within the regulatory limits approved  
by the Board.  
[153]  
NSPML has amended its income tax returns for the years 2015 to 2019,  
which has increased NSPML’s net loss for income tax purposes in those years. In  
response to Board IR-63(a), NSPML confirmed that it amended the income tax returns  
for those years, increasing NSPML’s non-capital loss carryforward balance; the tax effect  
of which has been recorded as either a regulated or non-regulated deferred tax asset, as  
Document: 291318  
- 59 -  
appropriate. Grant Thornton analyzed NSPML’s deferred income tax regulatory asset  
account balance, along with the customer impact of this account on rate base.  
[154]  
Grant Thornton reviewed NSPML’s responses to various IRs relating to  
these accounts and confirmed the balances of both the deferred income tax regulatory  
asset account, and the related deferred tax liability account. Grant Thornton reiterated  
NSPML’s statement that while these regulated deferred tax assets do contribute to rate  
base, the rate base impact is completely offset by the related deferred tax liabilities.  
[155]  
Grant Thornton also commented on NSPML’s statement in response to  
Board IR-21(c) (M10057), which stated that the increase in non-capital losses has no  
immediate impact as NSPML is not currently taxable and has no cash tax expense. In  
NSPML’s response to that IR, they also stated:  
In the future, when NSPML becomes taxable and the non-capital losses are monetized,  
the income tax benefit of utilizing the non-capital loss carry forward created by the  
amendments will flow to customers and reduce rates otherwise required because the  
losses will reduce NSPML’s cash tax expense at that time.  
Grant Thornton responded to the above-noted concept, stating that in its view, this is a  
prudent and acceptable tax position.  
[156]  
When discussing depreciation, Grant Thornton recommends the completion  
of a depreciation study every five to seven years, with a more frequent study pattern as  
the 35-year recovery period draws closer.  
[157]  
Given the unique circumstance that all NSPML assets must be fully  
depreciated at the end of the 35-year period, when the assets will be transferred to Nalcor  
for $1, NSPML should monitor the ongoing asset situation. If it becomes apparent that  
additions or removals of assets may somehow impact depreciation levels, this can be  
brought forward to the Board for consideration at that time.  
Document: 291318  
- 60 -  
[158]  
Several Board IRs asked NSPML about its proposed depreciation policy  
and rates. Board IR-15 requested information regarding NSPML’s plan for future  
sustaining capital investments. NSPML responded, stating:  
The estimate of the amounts of future sustaining capital needed is under development as  
part of the establishment of the Long Term Asset Management Plan (LTAMP).  
NSPML will adhere to the Public Utilities Act with respect to the filing of capital submissions  
with the UARB for approval. Once the LTAMP has been developed, NSPML will work with  
the UARB and stakeholders to establish a suitable approach that reflects the requirements  
for the Maritime Link and in consideration of existing processes before the Board.  
[Exhibit N-7, pp. 39-40]  
[159]  
The Board notes that the ML Act was enacted to ensure regulatory review  
of the ML Project as the lowest cost alternative and for final approval of ML Project costs.  
Once the present matter is completed the Board's involvement will turn primarily to its  
oversight of Maritime Link asset additions and sustaining capital, and its oversight of O&M  
expenses. Section 35 of the Public Utilities Act would then govern how any additions or  
improvements NSPML makes to its asset system are implemented.  
Findings  
[160]  
throughout the construction period was within the regulatory limits approved by the Board.  
[161] The Board is satisfied that NSPML’s deferred income tax regulatory asset  
The Board is satisfied that the equity thickness which NSPML operated on  
balance fully offsets the related deferred income tax liability and, as such, results in no  
impact to the revenue requirement. The Board directs NSPML to reconcile Regulated  
Capitalization in the ongoing NSPML regulated financial statements as this will allow the  
confirmation that these balances continue to offset one another in future years.  
Document: 291318  
 
- 61 -  
[162]  
The Board notes that all future (sustaining) capital investments are to be  
made through NS Power’s usual means of application, under Section 35 of the Public  
Utilities Act.  
5.10 Incentive Executive Compensation  
[163]  
NSPML paid incentive compensation to its employees during the  
construction phase of the project commencing in 2013 and ending in 2018. NSPML has  
capitalized all compensation costs paid to its project team members during construction  
and completion. On a go-forward basis, following the completion of the construction  
phase, NSPML indicated it intends to follow the compensation rules that apply to NS  
Power under the Public Utilities Act. NSPML argued that as a complex and extended  
project the Maritime Link offered unique staffing challenges and that NSPML needed to  
engage a team of highly qualified professionals with particular expertise. It went on to  
argue it had to do so in a highly competitive labour market with other major projects  
underway competing for specialized resources.  
[164]  
Concentric advised it conducted a prudence review of NSPML’s  
compensation costs including at-risk incentive pay and concluded that the incentives were  
consistent with a competitive labour market for talented professionals in Canada, and the  
need to attract and retain qualified team members. Approximately $13 million of the  
compensation costs included in NSPML’s request falls into categories of costs not  
recovered by NS Power in the normal course of operations pursuant to the provisions of  
the Public Utilities Act, which forbids recovery of incentive compensation of senior officials  
of NS Power. NSPML pointed out that those legislative provisions do not apply to NSPML  
Document: 291318  
 
- 62 -  
and, therefore, the Board can consider recovery of compensation by NSPML as a matter  
of regulatory policy.  
5.10.1 Intervenor Comments  
[165]  
The CA recommended that the legislative provisions that apply to NS Power  
should be deemed to apply to NSPML:  
k. Incentives and Donations  
NSPML’s justification for these items labours under the continued misimpression that the  
Project was exclusively related to the ML itself. As this Board has expressly stated the  
Project related to the delivery of the NS Block and access to market price energy. As the  
Board concluded in its M07718 Decision:  
[80] The Board notes in passing that NSPML asserted Mr. Chernick and  
Synapse were wrong when they claimed that the ML Project (including the  
availability of the NS Block) was not completed as promised. NSPML  
suggested that it had completed what it had undertaken to do, i.e., the  
Maritime Link itself. In the Board’s view, however, the intent was clear and  
unequivocal from the outset. The Maritime Link was built primarily to  
deliver the NS Block generated at Muskrat Falls to Nova Scotia. It is  
important not to lose sight of that fact.  
Measured in that appropriate manner, it simply cannot be said that the project has been  
successful to the extent to justify performance payments to executives, or donations to  
community groups. Such expenditures, while (perhaps) completely appropriate for Emera,  
should not be recovered from ratepayers. As outline above, to the date of the hearing,  
ratepayers have paid $650 million in annual assessments and replacement energy costs  
and received quantified benefits of $17.4 million and 54,000 MWh of power. Such  
performance simply does not warrant the consideration of ratepayer funded incentives and  
donations.  
It is also to be remembered that, but for requirements associated with the Federal Loan  
Guarantee, the ML Project would have been undertaken by NSP. NSPML is a single  
purpose entity created solely to fulfill the requirements of the Federal Loan Guarantee. In  
such circumstances, it is completely appropriate to apply the legislative and regulatory  
restrictions applicable to NSP (respecting compensation) to NSPML.  
[Exhibit N-49, pp. 8-9]  
[166]  
The Industrial Group traced the history of consideration by the Board of  
incentive payments, reviewing the Board’s comments in NSUARB-P-868, from 1996 and  
a 2002 Board Decision [2002 NSUARB 59]. The Board commented in those decisions  
that the issue was not whether a company should have an annual incentive plan but  
Document: 291318  
 
- 63 -  
rather, the extent to which, if at all, the cost of the plan should be recovered from the  
utility’s customers, noting that a plan whose payout is entirely tied to shareholder return  
is of dubious benefit to customers. In the past (prior to the passing of the amendments  
to the Public Utilities Act) the Board ordered a 50/50 sharing of incentive payments  
assuming the level of the payments is justified. The Industrial Group argued that the  
Company has not provided sufficient evidence for the Board to determine the overall  
reasonableness of the compensation. The Industrial Group, in its final brief, stated:  
… However, the information before the Board was largely an expectation the Board would  
blindly accept Mr. Reed’s opinion, without any of the supporting documents and some  
apparent irritation that Intervenors had not sussed out the documents that supported the  
costs claimed.  
(Reed)…We were convinced after going through that document  
production and interview with the HR group that the overall level of  
compensation was appropriate, that the level of incentive compensation  
was responsive to the market, and that it did attract high-quality personnel  
to the project.  
Q. Okay. Thank you for that explanation, Mr. Reed. And I don’t recall  
seeing in the record of this proceeding the information that supports your  
ultimate conclusion, so how is the Board to determine whether the levels  
of compensation, including incentives, are reasonable without those  
records?  
A. (Reed) You have my professional opinion. You have the calculation on  
page 34 that 92 percent of the incentive compensation was tied directly to  
cost of performance on the project and that produced benefits in terms of  
bringing the project in on time, on budget. If additional information -- again,  
this is in my direct evidence filed August 9th. If additional information was  
required or desired, it certainly could have been asked for, including the  
calculation of the 93 percent. But I have gone through with you the process  
that we used.  
The Industrial Group sought additional information in response to undertakings. NSPML  
was asked to produce the information referred to by Concentric Energy regarding NSPML’s  
benchmarking and policies used to set compensation levels, including incentives. That  
response did not yield any documents or records for the Board to consider but simply cut  
and pasted from the transcript. The response also states that compensation is set at the  
50th percentile of the benchmarking distribution but there’s no indication who the  
comparators are.  
[Exhibit N-50, p. 17]  
Document: 291318  
- 64 -  
Findings  
The Board accepts that it was necessary to build incentive compensation  
[167]  
into the compensation package of NSPML in order to attract and retain skilled people.  
The Board also agrees that this no doubt contributed to the fact that the Maritime Link  
was built on time and on budget and there has been no imprudence finding through the  
course of a number of hearings. Mr. Janega, on questioning from the Board, explained  
the steps NSPML took, with the assistance of Emera human resource personnel, to come  
up with the incentive program. NSPML monitored collective agreements, looked at  
compensation packages for marine activities and offshore work, and looked at employees  
seconded from other parts of Emera, to determine the salary and compensation plan that  
was required. He said they constantly targeted the 50th percentile of the market.  
[168]  
So, the real question for the Board is, not whether there should have been  
incentive compensation, but whether ratepayers should bear 100% of the cost of that  
compensation. That question was put by the Board to Mr. Reed who acknowledged that  
the prudency risk of shareholders was effectively managed but argued that the entirety of  
the gain flows to customers in the form of lower base rates than would have been  
achieved if there had been less effective management and supervision.  
[169]  
[170]  
The Board simply does not accept that submission.  
It is clear to the Board that shareholders were the beneficiaries of the  
prudent management of the project by avoidance of the risk of an imprudence finding.  
[171] So these incentives, in the Board’s view, contributed significantly to the  
shareholders avoiding the risk of an imprudence finding. The cost of such a finding would  
be a shareholder cost.  
Document: 291318  
 
- 65 -  
[172]  
Prior to the passing of the provisions of the Public Utilities Act which limited  
incentives to senior officials of NS Power, the Board’s practice had been to split the cost  
50/50 between ratepayers and shareholders. For non-executive employees of NS Power  
that is still the split.  
[173]  
The Board sees no need to depart from that precedent in this situation and  
accordingly 50% of the incentive costs will be borne by shareholders and the final project  
capital cost will be adjusted accordingly.  
5.11 Sponsorships and Donations  
[174]  
In its application to the Board, NSPML is seeking to claim donations and  
sponsorships in the amount of $1,417,520, made during the construction of the Maritime  
Link as project costs. It reasons that establishing and maintaining community trust and  
support was integral to the execution of the Project. In response to Board IR-1 NSPML  
states that:  
Community support was aligned with providing improved communication or access to  
communities, support for Project needs, access to skilled resources or the support for  
development of such resources; all of which benefited the timely completion of the Project.  
[Exhibit N-7, p. 1]  
[175]  
On behalf of the SBA, Mr. Athas recommended a line-by-line review of the  
donations to determine if they could be tied to the project. In the Industrial Group’s IR-2  
to Mr. Athas, he was asked if he still supports this recommendation given the following  
Board comments in the 1993 Rate Hearing (M06144) and the 1996 Rate Hearing  
(M06131):  
In the case of a monopoly utility the customer cannot go to another company if dissatisfied  
with the utility’s spending decisions. Many regulators consider that there is no relationship  
between a utility’s discretionary spending on donations and the level and quality of  
customer service. The spending on donations in effect becomes an involuntary tax on  
customers.  
Document: 291318  
 
- 66 -  
The Board considers that the considerations which persuaded it to disallow the Company’s  
charitable contributions from revenue requirement are equally applicable to sponsorships  
and grants to universities in support of scholarship programs. While these programs may  
enhance the Company’s corporate image, they do not directly benefit customers and the  
customers have no say in the choice of sponsorships. The Board will accordingly reduce  
the Company’s revenue requirement by $227,000. [Emphasis in original]  
[Exhibit N-15, p. 3]  
[176]  
[177]  
Mr. Athas replied:  
… I would agree that if this could not be substantiated to the Board’s satisfaction than such  
donations would be more closely aligned with the corporate image definition in the Board’s  
decision quoted in the question and thus disallowed in terms of cost recovery.  
[Exhibit N-15, p. 3]  
Mr. Athas offered that NSPML is not the same type of entity as NS Power,  
which is a monopoly utility:  
…that as a ‘project-basedentity, recovery of expense items not specifically related to O&M  
or prior to the project being in-service may warrant special considerations regarding  
capitalizing charitable donations.  
[Exhibit N-13, p. 25]  
[178]  
NSPML notes that it is a special purpose entity specifically created to build  
this mega-project. The circumstances under which it was required to operate are  
significantly different in comparison to other NS Power capital projects. Given the size  
and scope of the operations under which this project took place, NSPML submitted it was  
appropriate for it to seek social license with the people in surrounding communities. To  
earn and maintain this social license, NSPML used donations.  
[179]  
Fostering constructive working relationships with Indigenous groups,  
community members, governments and other stakeholders secured trust. NSPML  
offered, in response to CA IR-16:  
NSPML worked to promote open and transparent communication with Indigenous  
communities to accommodate those impacted by the Maritime Link Project in Nova Scotia  
and Newfoundland and Labrador. Building upon respectful and cooperative relationships  
it had already developed with the Mi’kmaq …  
and  
Document: 291318  
- 67 -  
Through these partnerships, NSPML worked collaboratively to create meaningful  
opportunities for Mi’kmaq communities to benefit from the Project, specifically employment  
and business opportunities during the Project supported by the Socioeconomic  
Agreements with the Mi’kmaq in each Province. ...  
[Exhibit N-5, p. 2]  
[180]  
NSPML sought to gain the trust of communities by demonstrating that it was  
a contributor through corporate giving and sponsorships to “…local organizations and  
events in the communities in which it constructed and now operates the Maritime Link”.  
[Exhibit N-5, IR-16, p. 3]  
[181]  
In its Reply Evidence, NSPML indicated that building trust in the local and  
surrounding communities involved participating and/or sponsoring groups and causes  
that are important to the people who live there. NSPML offered that through these  
donations it was able to achieve:  
…improved communication with, and access to and through, communities directly  
impacted by the Project and in which Project needs often competed with local demands for  
services and facilities; …  
… NSPML and its contractors were literally in people’s back yards and in areas that  
communities in Cape Brenton and western and central Newfoundland used for traditional  
heritage, recreation, personal and group activities. …  
[Exhibit N-22, p. 22]  
[182]  
Through supporting educational scholarships and technical training  
programs at local post-secondary institutions and offering job readiness training programs  
to Mi’kmaq Indigenous communities, NSPML could gain trained labour resources in  
addition to community trust.  
[183]  
In its Reply Evidence, NSPML indicated that it had created a committee to  
review requests for contributions and ensure that contributions were aligned with the  
Benefits Agreement, Diversity Plan, Community Investment Plan and Stakeholder  
Document: 291318  
- 68 -  
Engagement Plan. Although NSPML argued that the contributions were made in keeping  
with the principles of the above agreements, it was conceded during the hearing that the  
agreements themselves did not require NSPML to make charitable donations:  
Q.  
(MacAdam) And do those documents require a financial -- or create a financial  
obligation to invest in charitable donations and sponsorships?  
A.  
(Rendell) There isn’t a specific requirement to incur funds, per se.  
[Transcript, December 6, 2021, pp. 140-141]  
[184]  
In the closing submissions of the Industrial Group and the SBA, the  
Intervenors noted that NSPML did not identify the process used to review applications for  
donations and it did not provide a report from NSPML’s committee that reviewed all  
requests for donations in order to demonstrate that the donations were reasonable and  
prudently incurred. The Industrial Group’s post-hearing submission questions the  
connection between several donation recipients and the ML Project.  
Findings  
[185]  
Engagement in the local community is important, especially for a mega-  
project for which these communities will not have a direct benefit but are asked to endure  
the short term intrusion of the construction and tolerate the permanent structures in areas  
used for recreation, personal activities and traditional heritage. Without the support of  
local and Indigenous communities, NSPML contractors and personnel would have  
struggled to access labour, accommodations, restaurants and facilities. It is reasonable  
to use community donations as a tool to build community trust as it supports organizations  
and causes that are important to the people in these communities.  
[186]  
However, the Board considers that some of the contributions and donations  
made by NSPML fall outside the scope of engagement with Indigenous or local  
Document: 291318  
 
- 69 -  
communities, or securing a well-trained and diversified workforce, and appear only  
remotely connected, if at all, to the communities where construction of the Maritime Link  
took place:  
Newfoundland Symphony Orchestra $7,250;  
Junior Achievement Newfoundland $38,700;  
Health Care Foundation $12,750;  
Pinnacle Scopes Inc. $8,161;  
St. John’s International Women’s Film Festival $16,000;  
Eating Disorder Foundation of Newfoundland and Labrador $2,500;  
Big Brothers Big Sisters Eastern Newfoundland and Labrador $12,000;  
Boys & Girls Club St. John’s $2,000;  
Canadian Breast Cancer Foundation $3,585;  
Canadian Cancer Society $9,950;  
Canadian Red Cross $2,500;  
Canadian Women’s Foundation $2,330;  
Iris Kirby House $10,000;  
Dr. H Bliss Murphy Cancer Care Foundation Newfoundland and Labrador $5,000;  
Ceilidh Cup $1,000;  
St. John’s Board of Trade $14,167; and,  
Newfoundland and Labrador Organization $18,000.  
[187]  
There is no doubt that the contributions and the donations have been made  
to worthy causes. However, the burden falls on NSPML to justify adding these donations  
to project costs, for which ratepayers will be asked to pay. To discharge this burden,  
NSPML must show that the donations have been made in support of the project. In order  
to validate the inclusion of these donations in the project’s cost, a review of each donation  
category should have been provided to show that the contribution was connected to local  
organizations and events in the communities in which it constructed the Maritime Link,  
Document: 291318  
- 70 -  
and that the donations contributed to the success of the Project. In cases where the  
connection between the financial contribution and the community, or to the success of the  
Project is not evident on its face, NSPML is required to provide a fulsome explanation for  
the contribution. The Board concludes that without a verification or report upon which to  
determine the relationship of some of the donations to the success of the project itself, or  
to the community which will be impacted by the construction, not all the donations can be  
included in the Project’s cost.  
[188]  
Accordingly, having reviewed the evidence and the submissions on this  
issue, the Board is satisfied that a majority of the contributions made by NSPML were  
reasonable and appropriate. However, as noted above, certain contributions lack a  
sufficient explanation to justify their inclusion in Project costs. The Board finds that  
NSPML may include 80 percent of the contributions and donations in the Project costs,  
representing an amount of $1,134,016.  
5.12 Final Project Capital Costs, including AFUDC  
[189]  
NSPML has requested Board approval of the ML Project’s final capital cost  
in the amount of $1.5712 billion and approval of $208.8 million in AFUDC, pursuant to  
Section 8 of the ML Regulations. These amounts are less than the $1.58 billion maximum  
capital cost and $230 million AFUDC allowance approved by the Board in 2013.  
Nonetheless, as noted in the Board’s 2017 ML Interim Assessment Decision, even though  
the capital cost of the ML Project came within the Board approved budget cap, the project  
cost must still be reviewed for prudence:  
The issue of whether NSPML prudently incurred the costs of constructing the Maritime  
Link (including construction and contract costs, management costs, financing costs, etc.)  
are not the subject of this proceeding and will be canvassed in the final assessment  
proceeding to be held later.  
[2017 NSUARB 149, para. 65]  
Document: 291318  
 
- 71 -  
[190]  
In a NS Power GRA decision, 2005 NSUARB 27, the Board adopted the  
definition of prudence as set out in a decision of the Illinois Commerce Commission as a  
reasonable test to be applied in Nova Scotia. That test was set out at paragraph 84 of  
the Board’s Decision:  
[84]  
… The standard for determining prudency of a utility’s fuel procurement  
practices is well established. As stated by the Illinois Commerce  
Commission, prudence is that standard of care which a reasonable person  
would be expected to exercise under the same circumstances encountered  
by utility management at the time decisions had to be made….Hindsight is  
not applied in assessing prudence….A utility’s decision is prudent if it was  
within the range of decisions reasonable persons might have made. … The  
prudence standard recognizes that reasonable persons can have honest  
differences of opinion without one or the other necessarily being imprudent.  
[2005 NSUARB 27, para. 84]  
The Board went on to say:  
[191]  
[89]  
While the Board recognizes that the definition of imprudence varies somewhat  
among the jurisdictions cited, there are several fundamental principles which are common.  
These include:  
Were the utility’s decisions reasonable in the context of information which was  
known (or should have been known) at the time?  
Did the utility act in a reasonable manner and use a reasonable standard of care  
in its decision-making process?  
The imprudency test should relate to the circumstances at the time in question and  
not to hindsight.  
[2005 NSUARB 27, para. 89]  
[192]  
NSPML has argued that it has sufficiently demonstrated prudence in its  
conduct of the planning, construction and energizing of the ML Project. Schedules 1  
through 6 of NSPML’s application describe the planning and execution processes  
undertaken by NSPML throughout the course of the ML Project. NSPML believes that  
the conduct of these processes was effective and prudent, met or exceeded industry  
norms, and helped to keep the final costs of the ML Project within the Board approved  
Document: 291318  
- 72 -  
total cost envelope. The specifics of these processes are discussed elsewhere in this  
Decision.  
[193]  
NSPML also presented evidence from three external experts related to the  
prudency of ML Project costs. Mr. Reed evaluated NSPML’s conduct on the ML Project  
to determine whether its decisions and actions fell within a reasonable range to establish  
prudence. He focused his evaluation on five elements of NSPML’s internal project  
controls: defined corporate procedures, written project execution plans, involvement of  
key internal stakeholders, reporting and oversight requirements, and corrective action  
mechanisms. Mr. Reed reviewed each of these elements for the following processes:  
project estimating and budgeting, project schedule development and management,  
contract management and administration, internal oversight mechanisms, and external  
oversight mechanisms. In completing his evaluation, Mr. Reed concluded that NSPML  
prudently executed the ML Project:  
… Concentric has found nothing in NSPML’s management of the ML Project that even  
approaches being outside the bounds of reasonable conduct, based on what was known  
or knowable at the time. My experience in working on and reviewing mega projects leads  
me to conclude that NSPML's conduct was superior to industry norms, and its extensive  
preparation and proactive management of the ML Project was the principle contributor to  
the ML Project's overall success - essentially no major changes in engineering or design,  
very effective corrective action, risk management and mitigation of risks that became  
project challenges, almost no rework, effective contract administration and cost controls.  
[Exhibit N-1, Schedule 7, Att. 1, p. 32]  
Mr. Reed, therefore, concludes that NSPML should be permitted to recover the resulting  
costs of the ML Project.  
[194]  
Mr. Inskip assessed the FLG debt financing arrangement and related cost  
for the ML Project. Mr. Inskip’s expert opinion is that NSPML's upfront bond financing  
strategy was not only a very prudent financing strategy but also one that very likely  
provided a net benefit to electricity customers in Nova Scotia. Further, regarding  
Document: 291318  
- 73 -  
NSPML’s short-term hedging program between financial close of the FLG and the  
issuance of bonds by the Maritime Link Financing Trust, Mr. Inskip concluded that it was  
a very defensible and prudent risk management strategy.  
[195]  
Dr. Galloway assessed NSPML’s contracting and risk management  
approach for the ML Project, with particular focus on the three major project contracts:  
the converter station contract, the transmission line contracts, and the submarine cable  
contract. Dr. Galloway’s assessment began with a review of NSPML’s contract  
management strategy, policies and procedures, and project documentation. She also  
conducted interviews with NSPML Project personnel. She then assembled utility and  
transmission industry management standards, which she used to assess NSPML’s  
project management contracting strategy elements, in addition to her own experience and  
expertise. Dr. Galloway concluded that NSPML proactively planned and executed the  
ML Project, including its risk management and management of major contracts, meeting  
expectations of industry best practices and standards.  
[196]  
No party to this proceeding contested the prudence of NSPML’s ML Project  
execution, except for the following three items:  
Project management team incentive compensation;  
Sponsorships and donations; and  
The integrity of the submarine cable system.  
Each of these items are addressed elsewhere in this Decision.  
[197]  
Board counsel consultants, Bates White, completed its own prudency  
review of the ML Project costs. This included a review of NSPML’s approach to  
procurement, contract management, change order management, and other technical  
Document: 291318  
- 74 -  
aspects of capital costs. Bates White’s review focused on the largest costs, the highest  
value contracts and contractors, large value agreements with affiliates, and major events  
that occurred over the course of project development. Bates White’s review found the  
ML Project costs to be reasonable. In addition, Bates White found:  
No instances of red flags indicating NSPML mismanagement or poor procurement  
practices on the ML Project;  
Numerous instances of NSPML prudent decision making in both ML Project  
procurement and contract management; and  
NSPML followed a clear change order process on the ML Project, with no red  
flags observed.  
Bates White also recommended approval of AFUDC in the amount of $208.8 million.  
AFUDC represents the financing costs (return on equity and cost of debt) accumulated  
during design and construction of the ML Project that NSPML is permitted to capitalize.  
[198]  
Grant Thornton was engaged by Board counsel to, amongst other things,  
assess the ML Project financing costs. Grant Thornton noted that NSPML financed 70%  
of the capital cost of the ML Project with a forward bond issue, under the FLG, of  
approximately $1.3 billion. NSPML incurred approximately $50 million of financing costs  
associated with this bond issue, which included roughly $36 million as a forward interest  
hedging settlement. Based on its assessment of this financing arrangement, Grant  
Thornton concluded that NSPML’s chosen approach to financing construction of the ML  
was an acceptable means to mitigate project risk and was in accordance with the terms  
of the FLG. Grant Thornton also found that the related hedging process was completed  
in a timely manner. In addition, Grant Thornton reperformed NSPML’s calculations to  
Document: 291318  
- 75 -  
support the $36 million bond hedging cost and confirmed they agreed, without exception,  
to the underlying supporting documents provided by NSPML. Overall, as it relates to the  
ML Project financing strategy and costs, Grant Thornton determined that NSPML acted  
prudently.  
Findings  
[199]  
The planning and development of the ML Project was a significant  
endeavor. There have been numerous examples across North America of substantial  
cost overruns and construction delays of energy mega-projects. The completion of the  
ML Project on time and on budget was a commendable achievement attributed to  
NSPML's actions throughout all phases of the project. While there continue to be delivery  
delays of the NS Block, NS ratepayers will benefit from NSPML's development of the ML  
Project, including its continuing efforts with Nalcor as they both strive to secure an  
important source of renewable energy for Nova Scotians and our neighbors in  
Newfoundland and Labrador.  
[200]  
Subject to the findings in other sections of this Decision, the Board finds  
that the capital costs associated with the ML Project were prudently incurred. NSPML is  
entitled to recover its prudent and proper costs. As such, the Board approves the  
prudently incurred capital cost of the ML Project. The Board also approves the AFUDC  
incurred on the project. The final amount of the approved ML Project capital cost and  
AFUDC will be confirmed in a Board Order following submission of NSPML’s Compliance  
Filing.  
[201]  
NSPML continues its ML Project close out work related to a number of  
outstanding insurance, warranty, expropriation and contract claims. As noted in Schedule  
Document: 291318  
 
- 76 -  
3 of NSPML’s application, this close out work relates to issues associated with vibration  
dampers, OPGW and OSSH jumpers and splice boxes. NSPML has forecast a project  
cost recovery for these items, which will be credited to the ML Project cost and NSPML’s  
rate base. NSPML is directed to provide a report to the Board once this close out work  
has been completed. This report shall provide a detailed accounting of the final results  
of this work, including any necessary adjustment to the final ML Project capital cost,  
subject to review by the Board.  
5.13 Opening Rate Base  
[202]  
NSPML has requested Board approval of an opening rate base for NSPML,  
as at January 1, 2022, in the amount of $1.761.8 billion. This value was determined as  
shown in the following table:  
[Exhibit N-1, p. 40]  
[203]  
In support of the FLG debt financing program for the ML Project, NSPML  
incurred $50.1 million in deferred financing charges. During construction of the ML, $4.4  
million of the deferred financing charges was charged to AFUDC and is included in the  
Document: 291318  
 
- 77 -  
$208.8 million AFUDC figure included in NSPML’s derivation of its proposed opening rate  
base. This leaves $45.7 million of these charges as of the commercial operation date of  
the ML. Recovery of these charges was deferred in 2018 and 2019, and then commenced  
in 2020 as directed by the Board. At the end of 2021 NSPML recovered a total of $2.4  
million in amortization expenses on account of these deferred financing charges, leaving  
a balance to be added to rate base as at January 1, 2022 of $43.3 million.  
[204]  
As noted previously in this Decision, Bates White expressed no concerns  
with the ML Project capital costs, and recommended approval of $208.8 million in  
AFUDC. Bates White also recommended approval (subject to confirmation by Grant  
Thornton of the cost of NSPML’s hedging program) of $43.3 million in net deferred  
financing charges. Bates White further recommended that the Board approve NSPML’s  
opening rate base amount, subject to any modifications directed by the Board.  
[205]  
Grant Thornton confirmed that under NSPML’s accounting policies, it was  
appropriate for NSPML to defer financing costs, including the forward interest hedge  
settlement cost. Grant Thornton also believes it is appropriate to include the ML Project  
deferred financing costs in rate base, as the costs have been prudently incurred and are  
directly attributable to the successful completion of the project.  
[206]  
Apart from the ML Project capital cost reductions, which are addressed  
elsewhere in this Decision, no parties to this proceeding objected to NSPML’s derivation  
of its proposed opening rate base.  
Document: 291318  
- 78 -  
Findings  
The Board finds that the methodology used to calculate NSPML’s opening  
[207]  
rate base is appropriate. The final amount of NSPML’s opening rate base will be  
confirmed in a Board Order following submission of NSPML’s Compliance Filing.  
5.14 2022 Cost Assessment  
[208]  
In its application, NSPML asked for an annual 2022 assessment of $169.4  
million, broken down as follows:  
[Exhibit N-1, p. 48]  
[209]  
As in prior annual assessments, NSPML proposes to continue the existing  
process of recovery in equal monthly installments, issuing monthly invoices to NS Power.  
Given the likely duration of the current proceeding to consider the ML Project final costs,  
extending into 2022, NSPML requested that the Board provide approval to continue the  
base 2021 monthly assessment payments into 2022 on an interim basis, pending the  
Board’s determination of NSPML’s final 2022 assessment. In its final Decision and Order  
in this proceeding, NSPML proposed that the Board set the monthly assessment  
Document: 291318  
   
- 79 -  
payments for the remainder of 2022, taking into account the interim monthly payments  
such that NSPML recover in 2022 the amount finally approved for the year.  
[210]  
On December 15, 2021, the Board issued an Interim Order approving the  
continuation of the 2021 monthly assessment amounts into 2022, representing an annual  
assessment amount of $172.2 million. As it had done in prior assessments, the Board  
also continued the $10 million holdback and the deferral of recovery by NSPML from NS  
Power of the amounts collected from ratepayers for depreciation and amortization of  
deferred financing charges, until May 1, 2022, and November 1, 2022, when such  
amounts will be required for the respective principal repayment. The Board further  
ordered that the difference between the interim and final 2022 cost assessments will be  
trued-up upon the issuance of its final Order.  
[211]  
One of the issues raised by the Intervenors during this proceeding focused  
on NSPML’s request for O&M costs of $20.9 million in 2022. They submitted that such  
costs had been consistently over-estimated by NSPML in prior years and that they should  
be “trued-up” in this proceeding, in the approximate amount of $7.5 million credited to  
ratepayers.  
[212]  
NSPML provided a summary of annual projected and collected O&M costs  
since the first interim annual assessment approved by the Board for 2018:  
Document: 291318  
- 80 -  
[Exhibit N-8, NSPML (SBA) RIR-8(a)]  
[213]  
John Athas, the SBA’s consultant, expressed concerns with the amount  
requested for the 2022 assessment:  
… NSPML has overestimated O&M costs in each year, totaling $7.5 million. I have a  
concern that the cost of service level review must look into two things. First, will that  
overcollection be credited to NSPI customers? Second, how has NSPML improved its O&M  
estimation process to assure there is no systemic bias toward overestimation?  
… To exacerbate the history of NSPML over-projecting O&M expenses, I am concerned  
there is no reconciliation process in place to refund such over-collections of O&M expenses  
from NSPI. This gives NSPML a financial incentive to over-forecast O&M expenses,  
resulting in NSPML ratepayers over-paying for service from the Maritime Link.  
I believe the NSUARB should require an annual reconciliation process where NSPML files  
a new projection of O&M expenses, which includes true-up for any over-collection or under-  
collection of O&M expenses the previous year. This will protect ratepayers from over-  
projections and also protect NSPML from under-projections and also eliminate NSPML’s  
incentive to over-project O&M expenses. In this Matter, NSPML should refile their 2022  
Assessment to include a reconciliation of O&M expenses over-collected since 2018 in the  
amount of $7.5 million.  
[Exhibit N-13, pp. 15 and 18]  
[214]  
Counsel for the Industrial Group supported Mr. Athas’ recommendation that  
there be a reconciliation of the overestimated O&M expenses totaling $7.5 million since  
2018.  
Document: 291318  
- 81 -  
[215]  
In its Rebuttal Evidence, NSPML opposed the true-up of past forecast  
versus actual O&M expenses. Its consultant, Mr. Reed, of Concentric, in response to Mr.  
Athas’ concerns, stated that providing a credit to ratepayers for the overpayment of O&M  
expenses would constitute retroactive ratemaking and, thus, would be inappropriate:  
Every year, the Company is gaining experience operating and maintaining the ML and  
has pledged to continue efforts to mitigate and contain costs. Furthermore, as Bates White  
noted “it is not uncommon for O&M costs and their estimates to vary over time”. As the  
operation of the assets becomes more established, efficiencies will be gained, and cost  
predictability should be more achievable. Finally, NSPML has decreased its 2022 projected  
O&M by three percent from 2021 projections, which equates to a decrease of  
approximately $600,000 due to organizational improvements to manage costs accordingly.  
I do not agree with that type of retroactive ratemaking for rates that have already been  
collected nor do I believe that this type of a true-up mechanism for projected O&M would  
be appropriate for NSPML. NSPML is realizing efficiencies in its operations every year and  
a true-up mechanism has the potential to remove the incentive for the achievement of these  
costs saving efficiencies which will benefit customers in the future. I see no reason to depart  
from the well-established and very common practice of using projected O&M costs for  
establishing revenue requirement for NSPML.  
[Exhibit N-22, Appendix 1, pp. 7-8]  
[216]  
In her closing submissions, Ms. Rubin submitted that retroactive ratemaking  
does not apply to interim assessments. She cited case authorities, including Bell Canada  
v. Canada (CRTC), [1989] 1 S.C.R. 1722, in support of the proposition that interim orders  
of administrative tribunals can be reviewed or remedied in a final order:  
The Industrial Group submits that by its very nature, a period in which rates were set by  
interim assessment is inherently subject to review and potential remedial action.  
Gonthier, J. writing for a unanimous Supreme Court of Canada in Bell Canada v. Canada  
(CRTC) [1989], found that by virtue of an administrative tribunal’s power to make interim  
orders, the effect, as well as any discrepancy between the interim and final order, may be  
reviewed and remedied by a final order. The Court further found that this power can exist  
in the absence of an explicit provision given it is necessarily implied as a result of a  
tribunal’s power to make interim orders in the first instance. The existence of the CRTC’s  
broad procedural powers with respect to setting rates and a legislative objective to ensure  
rates are at all times just and reasonable, further solidified the Court’s opinion on the  
matter.  
In Bell Canada, 1989, the legislative framework was found to have granted the CRTC broad  
powers in general, but specifically, to make an interim order and reserve further directions  
Document: 291318  
- 82 -  
in advance of an adjourned hearing or further application pursuant to section 60(2) of the  
National Transportation Act.  
In the context of interim orders, courts have also rejected the suggestion that such orders  
are not subject to review and are therefore “final” in nature.  
In Coseka Resources Ltd. v. Saratoga Processing Co. the Alberta Court of Appeal ruled  
that if rates set by an interim order were interpreted as being unavailable for review, it  
would negate the need for legislative provisions providing for such orders. The Alberta  
Court of Appeal ruled that to suggest interim orders are not subject to replacement by final  
order would be to classify interim orders as being final in all but name. …  
[Exhibit N-50, p. 9]  
Findings  
[217]  
Under the ML Act, the Board has all the powers and authority provided to it  
under the Public Utilities Act and the Utility and Review Board Act. The authority for Board  
approval of ML Project costs and expenses, including O&M costs, is contained in the ML  
Regulations:  
Assessment and costing approval  
8
(1)  
Before receiving energy under the Nalcor Transactions, an applicant must  
set an assessment against Nova Scotia Power Incorporated for the recovery of the  
all approved Project costs, and must apply to the Review Board for an approval of  
the assessment under Section 64 of the Public Utilities Act.  
(2)  
Nova Scotia Power Incorporated is entitled to recover through its rates any  
assessment approved by the Review Board in respect of the Maritime Link Project.  
[218]  
The Board notes that there is no reference to interim orders or approvals in  
the ML Act or the ML Regulations.  
[219]  
The Board’s power to issue interim approvals under the Public Utilities Act  
is set out in s. 69:  
Interim approval of schedule  
69 (1) When a public utility has submitted for the approval of the Board a  
schedule of rates, tolls and charges, or a proposed change in any existing schedule of  
rates, tolls and charges, which, in the opinion of the Board, either constitutes a reduction  
in the existing schedule of rates, tolls and charges at the time being paid by the majority of  
the customers of such public utility affected by such change in the class of service to which  
such proposed change applies or which applies only in respect of a service for which no  
rates, tolls or charges have been previously approved, the Board may at any time before  
finally approving or disapproving of such schedule or change, grant an interim approval  
thereof, with or without modification, and thereafter the existing schedule of rates, tolls and  
charges of such public utility as amended by such schedule of charges, interim approval  
Document: 291318  
 
- 83 -  
of which with or without modification, as the case may be, has been so granted by the  
Board, shall be the only lawful rates, tolls and charges of such public utility until the Board  
shall express its final approval or disapproval thereof, with or without modification or  
amendment. [Emphasis added]  
[220]  
In recent years, the Board has considered interim approvals in a few  
instances. The Board considered an application by NS Power for approval of a proposed  
new tariff, the Extra Large Industrial Active Demand Control (ELIADC) Tariff and Rate  
under which Port Hawkesbury Paper LP (PHP) would take electric service (M09420),  
2020 NSUARB 44. NS Power and PHP requested interim approval of the tariff in advance  
of the main hearing on the merits to ensure that it would be in effect for the ensuing  
January 1, 2020. A preliminary hearing was held respecting the interim approval, in which  
NS Power and PHP both confirmed their understanding that the Board could, following  
the hearing on the merits, retroactively adjust the tariff, rate and charges paid by PHP  
effective January 1, 2020. The Board issued an Order on October 8, 2019, under s. 69  
of the Public Utilities Act granting NS Power interim approval for the ELIADC, effective  
January 1, 2020. Following the hearing held February 11-12, 2020, the Board approved  
the ELIADC, but amended the tariff as initially approved, based on a submission by the  
Industrial Group, to provide for the direct referral of a billing or disconnection dispute to  
the Board rather than to the DRO.  
[221]  
The Gas Distribution Act also expressly provides for interim approval by the  
Board. The Board granted interim approval under that Act to Heritage Gas Limited for a  
proposed Customer Retention Program (M07346) 2016 NSUARB 161. Section 21(1A)  
of the Act provides that the Board “may, at any time before finally approving or  
disapproving the schedule or change, grant an interim approval with or without  
conditions”. Heritage Gas applied for approval of a proposed Customer Retention  
Document: 291318  
- 84 -  
Program seeking, among other relief, the suspension of depreciation on its plant-in-  
service and a reduction in the existing Base Energy Charge (BEC) for Rate Class 1  
commercial customers whose annual consumption is at, or above, 500 GJs/year. The  
application was made on an expedited basis due to competitive pricing pressures from  
other energy commodity products, notably from propane. Following a preliminary  
hearing, the Board issued an Order on March 22, 2016, approving the reduced BEC on  
an interim basis (but deferring its decision on other relief requested), and setting the  
matter down for a hearing on the merits. In its final Decision, the Board approved the  
application, but modified a few elements, requiring Heritage Gas to provide the Board,  
the Consumer Advocate and customers with 30 days’ notice prior to a change in BEC  
pricing and prohibiting any BEC increase during the months of December to February in  
any year. The Board also approved the depreciation deferral, but with a lower carrying  
cost, making the approval retroactive with the change in the BEC that was effective on  
March 22, 2016, by virtue of the Interim Order.  
[222]  
Having reviewed the statutory provisions, the cases cited by Ms. Rubin, and  
the submissions, the Board finds that ordering a true-up of the overestimated O&M costs  
of $7.5 million since 2018 would constitute retroactive ratemaking and would not be  
appropriate. Some confusion may have been caused by describing the past annual  
assessments as “interim assessments”. While they were described as interim, the  
assessments were not interim rates or interim assessments in the sense of that term  
canvassed in Bell Canada, or in s. 69 of the Public Utilities Act.  
[223]  
This issue was appropriately addressed in NSPML’s reply argument, with  
which the Board concurs:  
Document: 291318  
- 85 -  
Historically, NSPML’s actual O&M expenditures have been less than forecast and  
approved for inclusion in NSPML’s annual assessments. This is how the incentive  
embedded in conventional forward test year rate making is supposed to work. The IG  
argues, however, that because the 2018 through 2021 assessments set for NSPML by the  
UARB were “interim”, the UARB is at liberty to cast back and “true-up” forecast to actual  
O&M costs. The law relied on by the IG in its argument in respect of an economic  
regulator’s authority to adjust interim rate orders and cost recoveries premised thereon is  
good law. However, it is inapplicable in this case. In the cases cited by the IG, the rate  
decisions in issue were expressly “interim”; i.e. made early in a proceeding pending a final  
decision and expressly on an interim basis, exactly like the interim order made by the UARB  
in this proceeding, and expressly with the expectation of all parties that rates could change  
once deliberations conclude and decisions are made. Setting rates on an “interim” basis in  
this manner precludes retroactive rate adjustments which, but for the interim nature of the  
initial orders, would offend the legal prohibition against retroactive rate making.  
NSPML’s “interim” assessment were not “interim” in the sense in which that term of art is  
used in the cases cited by the IG. NSPML’s 2018 through 2021 assessments were “Interim”  
only in the sense that they were made pending approval of NSPML’s Project Costs  
pursuant to section 8 of the Maritime Link Cost Recovery Process Regulations and  
consequent establishment of NSPML’s opening rate base; i.e. the approvals requested by  
NSPML in this Application. …  
Finally on this point, the IG’s argument that the Board’s jurisdiction and “legislative  
environment” permit review of interim rates also does not apply. Section 69 of the NS Public  
Utilities Act to which the IG refers provides for approval, on an interim basis (i.e. subject to  
final determination) of a proposed change in any existing schedule of rates, tolls and  
charges which constitutes either a reduction to an existing rate, toll or charge, or a rate, toll  
or charge which applies only in respect of a service for which no rates, tolls or charges  
have been previously approved. That is, this legislative provision mandates the Board to  
expeditiously implement an expressly interim rate reduction, or an expressly interim rate  
for a new service, pending its full review and final approval thereof. This is a narrow  
exception to the general legal prohibition on retroactive rate making, and does not create,  
as the IG contends, a “legislative environment” in which the UARB can reopen and  
retroactively adjust its previous rate orders.  
[Exhibit N-53, pp. 36-38]  
[224]  
The Board notes that the ML Act and the ML Regulations make no mention  
of “interim” orders. Unlike the instances noted by Ms. Rubin or the interim rates set by  
the Board in the ELIADC or Heritage Gas’ Customer Retention Program proceedings, no  
part of the annual assessments were identified as being subject to later review or final  
approval. The assessments themselves were approved by the Board to cover costs for  
O&M, depreciation, as well as debt and equity financing costs. These costs were required  
to be assessed and paid by ratepayers to ensure compliance with the FLG. Any  
Document: 291318  
- 86 -  
suggestion that they could be varied subsequently in a final order could potentially have  
jeopardized compliance with the covenants in the FLG.  
[225]  
Notwithstanding the above, NSPML has overestimated O&M expenses  
every year since 2018, without exception. The variances have ranged from a high of $3.2  
million in 2018 to a low of $1.3 million in 2019. Further, NSPML is now entering its fifth  
year with the Maritime Link being in service and is gaining experience in its operation and  
maintenance, including in the control of related costs. Taking these factors into account,  
the Board concludes that NSPML’s total envelope for 2022 O&M costs should be reduced  
by $500,000 and the 2022 assessment adjusted accordingly.  
[226]  
adjustments in this Decision in the amount to be confirmed in the Compliance Filing.  
[227] As noted above, the Board issued an Interim Order on December 15, 2021,  
The Board approves the 2022 assessment as applied for, subject to the  
approving the continuation of the 2021 monthly assessment amounts into 2022, based  
on the annual assessment amount of $172.2 million. As further provided in the Board’s  
Interim Order, the difference between the interim and final 2022 cost assessments will be  
trued-up upon approval by the Board. The Board directs that this true-up and the resulting  
2022 monthly assessment amounts take effect on March 1, 2022. NSPML is to confirm  
these adjustments in its Compliance Filing.  
[228]  
Upon questioning by the Board at the hearing, Mr. Rendell of NSPML  
testified that they were still uncertain about the type of assessment filings in future years.  
NSPML is still considering whether to ask for annual assessments similar to the practice  
to date, or to seek approval of a test year filing that presumably could remain in place for  
a number of years. He indicated that NSPML is still reviewing operational matters,  
Document: 291318  
- 87 -  
including its Long Term Asset Management Plan (LTAMP) and sustaining capital needs.  
The Board notes that the present 2022 assessment is only in effect until year-end.  
NSPML is to manage its regulatory calendar to ensure the Board can address any future  
filing before 2023.  
5.15 Future Reporting Requirements  
[229]  
Throughout the duration of the ML Project, as well as after the Link was  
placed into service, NSPML has been filing quarterly status reports with the Board. In  
addition, in conjunction with the quarterly FAM reports, NS Power has been filing quarterly  
Maritime Link Benefits Reports.  
[230]  
Mr. Musco was asked to provide his views, in an Undertaking, on what  
reporting requirements he would recommend. His response was provided in Undertaking  
U-23 as follows:  
For purposes of this undertaking, I refer to two time periods: (1) the "interim period," which  
is defined as the commencement of the NS Block (as defined by the Acceleration  
Agreement) through the full commissioning of all assets associated with the delivery of the  
NS Block (i.e., Muskrat Falls Generating Station, Labrador Island Link, and associated  
transmission assets), such that the full NS Block (including both the Base Block and  
Supplemental Energy) can be delivered in full, and (2) the period from full commissioning  
of the NS Block through the full term of the Energy and Capacity Agreement.  
For the interim period, I recommend that reporting continue as it has since the beginning  
of 2018, i.e., the energization of the Maritime Link. That is, I recommend that reports be  
filed at least quarterly that show, at minimum, the same level of detail and information as  
already provided in the quarterly Maritime Link Benefits Reports. In addition, I would  
recommend that it be reported for the relevant quarter the (a) amount of Base Block energy  
provided, by month, (b) the amount of Base Block energy, by month, contemplated in the  
2013 NSPML application, (c) the amount of Supplemental Energy provided, by month, (d)  
the amount of Supplemental Energy, by month, contemplated in the 2013 NSPML  
application, and (e) any additional energy received, by month, and categorized by  
capitalized terms as defined in the relevant project agreements (e.g., the Energy and  
Capacity Agreement, or Energy Access Agreement). I also recommend that the reports  
also include any "make up" energy delivered by Nalcor associated with prior under-  
deliveries. For such "make up" energy reporting, I suggest it be provided by month and  
should be specified as to which type of underdelivered energy is being addressed-e.g.,  
Base Block or Supplemental Energy. Last, I recommend that the reports include an up-to-  
date accounting report of all under-deliveries which remain to be provided at the end of the  
relevant quarter, as broken down between Base Block and Supplemental Energy. I  
recommend that this level of reporting continue past the end of the interim period, which,  
again, would be defined by the full commissioning of all assets associated with the delivery  
Document: 291318  
 
- 88 -  
of the NS Block (i.e., Muskrat Falls Generating Station, Labrador Island Link, and  
associated transmission assets), such that the full NS Block (including both the Base Block  
and Supplemental Energy) can be delivered in full. The reporting should continue until  
parties have confidence in the full and sustained delivery of the NS Block. Such a time  
period is necessarily subjective, but six to twelve months seems reasonable from my view.  
It is also my view that the reporting above should focus on the quantities of underdelivered  
and makeup energy. I recognize that NSPI will also likely be focused on the value of both  
the underdelivered and makeup energy quantities, each of which are potentially complex  
determinations that include review and assessment of the energy value, capacity value,  
and environmental attribute value of the underdelivered and makeup energy quantities.  
Assessing these underdelivered quantities and makeup energy for being of similar value  
will be an important process and will likely require an assessment of the timing of the  
deliveries, the system marginal cost, the timing of the missing or makeup capacity value,  
and the impact of the missing or makeup energy on NSPI's environmental compliance and  
associated costs, among other potential relevant data. In my view, this more complex  
exercise is less suited for quarterly or monthly FAM reporting and is better addressed in  
the FAM audit process, where the auditor can review all relevant data to determine if the  
value of the "make up" energy is of similar value to that of the underdelivered quantities.  
Once parties have confidence in the full and sustained delivery of the NS Block, it would  
also appear reasonable to transition further reporting away from the stand-alone, quarterly  
Maritime Link Benefits report to the quarterly FAM reports. The reporting should continue  
to provide data on NS Block power received (both Base and Supplemental, as applicable),  
additional energy (e.g., energy delivered pursuant to the Energy Access Agreement),  
undelivered quantities, "make up" quantities, and cost data. In all cases, the reporting  
should follow the precise terminology and definitions of the relevant agreements, such as  
the Energy and Capacity Agreement and Energy Access Agreement. For example, NSPI  
should distinguish between Block A Undelivered Energy and Block B Undelivered Energy  
in its reporting.  
In addition, and in my view, it would be beneficial to maintain the reporting on the calculated  
benefits of the Maritime Link as is currently being reported in the Maritime Link Benefits  
reports, filed quarterly. I acknowledge that the benefits were linked to the pre-NS Block  
time periods and the associated interim assessments, and once the NS Block begins full  
and sustained delivery, the import of those reported benefits from a ratemaking perspective  
is reduced. Nevertheless, it would seem reasonable to expect that NSPI would continue to  
track those benefits, and that reporting benefits in the quarterly FAM reports would be an  
appropriate forum for reporting those benefits through time.  
[Exhibit N-42, pp. 1-3]  
Findings  
[231]  
It is clear that delivery of the expected energy and capacity via the Maritime  
Link has not materialized. It is also clear that delays continue to be experienced with  
commissioning the LIL. The Board recognizes the importance of tracking and comparing  
actual deliveries against expected deliveries, as well as ensuring that the value of make-  
up deliveries is equal to that expected under the original agreements. Therefore, the  
Document: 291318  
 
- 89 -  
Board finds that NSPML and NS Power need to continue filing quarterly reports until  
otherwise directed by the Board. Any transition away from the stand-alone reports to  
some form of FAM reporting will be addressed at the appropriate time.  
[232]  
In addition to the items identified elsewhere in this Decision by Mr. Trim, the  
Board directs the following, as may be applicable to NSPML and/or NS Power:  
1. Maintain current quarterly Maritime Link reports, supplemented with the  
enhancements identified in the Bates White Undertaking U-23 response regarding  
the interim period. Those reports are also to include summaries focused on the  
quantities and values of makeup energy and capacity, with details being better  
addressed during a FAM audit process. In addition, the reports are to include  
financial data comparing capital and operating expenditures against budgeted  
amounts, reports on the status of MFGS and LIL commissioning, outstanding  
contractual, warranty and insurance claims, final close out punch list matters,  
outstanding expropriations, and outstanding operating agreements yet to be  
finalized.  
2. Maintain current quarterly Maritime Link Benefits reports which also identify costs  
associated with replacement cost of undelivered energy and costs associated with  
extended operation of Lingan 2 and any other thermal resource that was intended  
to be displaced by Muskrat Falls deliveries.  
3. File the annual Independent Engineer O&M Report.  
4. File the annual marine survey report.  
5. File the Long Term Asset Management Plan (LTAMP) once completed.  
6. Report on any forced outages experienced on the assets extending from MFGS to  
Woodbine.  
7. Report on wheel-through energy between Newfoundland and New Brunswick,  
along with the associated OATT revenues.  
5.16 Adjustment of Rate of Return  
[233]  
In its 2013 ML Decision approving NSPML’s original application, the Board  
approved NSPML’s return on equity (ROE) at 9.0% for ratemaking purposes within a  
Document: 291318  
 
- 90 -  
range of 8.75% to 9.25%. The Board also approved a 70:30 debt to equity capital  
structure.  
[234]  
NSPML is a single purpose entity that was created to take advantage of the  
technical requirements of the FLG. But for that requirement, NS Power would have been  
the entity to build the ML Project. The Board concluded:  
[305] In December of 2012 the Board confirmed NSPI’s rate of return on common equity  
at 9.0%. There is no automatic adjustment formula.  
[306] Had NSPI applied to build the ML Project the Board would not have revisited the  
ROE several months after having set it. In the circumstances, the Board finds the rate of  
9.0% is appropriate for NSPML as well.  
[307] NSPI does not have an automatic adjustment formula. There is no substantial  
regulatory lag in this province between the time NSPML might seek a hearing to adjust the  
ROE and the date of the hearing. If NSPML feels at some point, between now and 2017,  
the ROE needs to be adjusted it may apply and it will get a relatively speedy hearing from  
the Board. On the other hand, should the Board or Intervenors determine that the rate  
needs to be adjusted, the same process can be undertaken. The Board finds the inclusion  
of an automatic adjustment formula is not required in these circumstances.  
[2013 NSUARB 154, paras. 305-307]  
[235]  
The review of NSPML’s ROE was not requested by any party until the  
present application. Upon the filing of the application, the Board circulated a Preliminary  
Issues List to the parties for comment. The Small Business Advocate asked that the ROE  
be placed on the Issues List. However, after quoting the above paras. 305 to 307 of the  
2013 ML Decision, NSPML responded as follows:  
Given the Board’s prior determination, we submit that ROE is best and most efficiently  
addressed in an NSPI rate setting application. This approach is consistent with the Board’s  
finding in 2013, promotes regulatory efficiency, and protects against the potential for  
conflicting findings in separate proceedings.  
We respectfully request that “Return of Equity for NSPML” not be added to the Issues List.  
[NSPML Letter, September 2, 2021, pp. 1-2]  
[236]  
On that basis, the Board did not include NSPML’s ROE on the Final Issues  
List. During this hearing, counsel for the Industrial Group cross-examined the NSPML  
witness panel on the issue and Mr. Janega would not commit NSPML to reviewing its  
Document: 291318  
- 91 -  
ROE in NS Power’s next general rate application. He concluded by stating: “…it would  
depend on what’s happening at the time.”  
[237]  
In her closing submissions, Ms. Rubin submitted:  
With respect, it is frustrating to be faced with an anticipated argument that there is  
insufficient evidence - when NSPML argued against inclusion of the issue of ROE so that  
expert evidence could be introduced.  
It is timely to review the ROE considering that the Link is in (and has been) in operations  
phase since 2018 and NSPML expresses confidence that the NS Block will be delivered  
shortly.  
…Additionally, it asks that the issue be placed on the Board’s agenda for determination –  
whether in NSPI’s GRA or in another proceeding.  
[Exhibit N-50, p. 20]  
[238]  
Further, in its closing submissions, the Industrial Group also requested that  
due to the ongoing delay in the delivery of the NS Block, and the impact of the COVID-19  
pandemic, that the Board direct the ROE be set to the lower end of the approved range  
of the ROE: i.e., at 8.75%. Ms. Rubin repeated a similar argument she made the prior  
year:  
… In its submissions (respecting the prior year’s 2021 interim assessment), the Industrial  
Group addressed (a) whether the Board has the power to set the ROE at the lower end of  
the reasonable range, and (b) whether it should do so on the record in that case.  
The Board implicitly accepted that it had the jurisdiction to do so, and was “sympathetic to  
the position put forward by the CA and the Industrial Group” but found there was insufficient  
evidence before the Board upon which the rate of return should be reduced to 8.75% from  
the 9% determined in the 2013 proceeding. It did, however, request that NSPML voluntarily  
reduce its ROE. NSPML declined to do so but made a charitable donation.  
The Industrial Group respectfully requests the Board’s consideration, once again, whether  
the delay itself is sufficient evidence to implement the previous determination on the range  
of reasonable ROE for the 2022 assessment. …  
[Exhibit N-50, pp. 19-20]  
Document: 291318  
- 92 -  
Findings  
The Board concurs with Ms. Rubin that it is appropriate to schedule a review  
[239]  
of NSPML’s ROE. Indeed, the Board found NSPML’s responses to Ms. Rubin’s inquiries  
to be inconsistent with its pre-hearing request to remove ROE from the Issues List in this  
matter. Consistent with its finding in the 2013 ML Decision, and given NSPML’s decision  
not to include a review of the ROE in this proceeding, the Board finds that NSPML’s ROE  
should be as determined in NS Power’s current general rate application (M10431).  
Unless demonstrated otherwise, NSPML’s rate of return shall be that set for NS Power in  
that hearing.  
[240]  
The Board has also considered Ms. Rubin’s submission to make a direction  
on the range of reasonable ROE for the 2022 assessment. She suggested it be fixed at  
the bottom of the range approved by the Board. As outlined earlier in this Decision, the  
Board has applied a combination of regulatory remedies to address the continuing delay  
in the NS Block and uncertainty about the timing of re-deliveries. The Board considers  
that its approach in the matter is sufficient in the present circumstances.  
5.17 Lingan 2 Retirement  
[241]  
In NS Power’s Integrated Resource Plan (IRP), filed in 2020, it was  
indicated that Lingan 2 was assumed to be retired once the NS Block begins to flow as  
its capacity is replaced by the Maritime Link basic NS Block. Lingan 2 does not appear  
in IRP future modelling results. Contrary to the position in the IRP, NSPML, in its rebuttal  
evidence, advised that NS Power’s actual plan for the retirement of this coal unit is that it  
had intended, for operational purposes, to retain all operating coal units in a ready state  
at least for the first year of NS Block delivery. The MUNIS, in their submission, stated:  
Document: 291318  
   
- 93 -  
The Municipal Utilities were full participants in the IRP process and are unaware of any  
comments made during that process, nor is there any evidence in the record of this  
proceeding, of any communication to parties before NSPML’s Rebuttal Evidence, that  
Lingan 2 was not to be retired contemporaneously with the commencement of the NS  
Block. The Municipal Utilities submit that the record of the IRP suggested the contrary  
intent, and certainly the Municipal Utilities were of the understanding that the NS Block was  
to lead to the contemporaneous closure of Lingan 2.  
[Exhibit N-46, p. 17]  
[242]  
The MUNIS argued that if the Board shares the MUNIS’ view that, until this  
proceeding, parties were under the general impression that the NS Block was meant to  
contemporaneously replace the Lingan 2 unit, it is open to the Board to disallow the  
continued costs of operating Lingan 2, until at least the LIL forgivable event clause is no  
longer applicable. They tie this to an argument that ratepayers should not have to pay  
for NS Block capacity so long as the LIL forgivable event provision is in force.  
[243]  
No other party made specific submissions with respect to the Lingan 2.  
Findings  
[244]  
This is not a NS Power proceeding, it is a NSPML proceeding, and from a  
procedural standpoint it would be inappropriate to make a disallowance with respect to  
the operation of Lingan 2 in this proceeding.  
[245]  
In the ordinary course the issue whether Lingan 2 was prudently operated  
would be subject to a FAM Audit, however, the FAM Audit for 2022 will not be completed  
for another two years. That being the case the Board advises NS Power that it will not  
permit recovery of operating costs of Lingan 2 beyond August 15, 2022, without further  
order of the Board. In other words, if NS Power proposes to operate Lingan 2 beyond  
August 15, 2022, it will need to seek specific approval if it wants to recover those operating  
costs.  
Document: 291318  
 
- 94 -  
6.0  
COMPLIANCE FILING  
NSPML is directed to file a Compliance Filing by February 16, 2022, with  
[246]  
comments by Intervenors by February 23, 2022.  
[247]  
An Order will issue accordingly.  
DATED at Halifax, Nova Scotia, this 9th day of February, 2022.  
______________________________  
Peter W. Gurnham  
______________________________  
Roland A. Deveau  
______________________________  
Steven M. Murphy  
Document: 291318  
 


© 2022 IncJournal is not affiliated with or endorsed by the U.S. Securities and Exchange Commission