IN THE SUPREME COURT OF BRITISH COLUMBIA  
Citation:  
Cardero Coal Ltd. v. Carbon Creek  
Partnership,  
2022 BCSC 253  
Date: 20220217  
Docket: S159680  
Registry: Vancouver  
Between:  
And  
Cardero Coal Ltd.  
Plaintiff/Defendant by Counterclaim  
Carbon Creek Partnership  
Defendant/Plaintiff by Counterclaim  
- and -  
Docket: S160477  
Registry: Vancouver  
Between:  
And  
Peace River Partnership  
Cardero Coal Ltd.  
Plaintiff  
Defendant  
Before: The Honourable Mr. Justice Branch  
Reasons for Judgment  
Counsel for Plaintiff:  
S. Stephens  
Counsel for Defendant:  
P.T. Linder, Q.C.  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Place and Date of Trial:  
Page 2  
Vancouver, B.C.  
October 12-22, 28-29, 2021  
Place and Date of Judgment:  
Vancouver, B.C.  
February 17, 2022  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 3  
Table of Contents  
I. INTRODUCTION ................................................................................................ 5  
II. BACKGROUND ................................................................................................. 5  
The Carbon Creek Coal Deposit ............................................................................ 5  
Project History........................................................................................................ 5  
Utah Mines’ Exploratory Efforts.............................................................................. 6  
The Johnson Application........................................................................................ 6  
The Burns Applications .......................................................................................... 6  
The Coalhunter Approach ...................................................................................... 7  
Coalhunter Seeks Assistance................................................................................. 8  
The Agreements..................................................................................................... 8  
The Project Comes Together ............................................................................... 16  
CDU Takes Control of Coalhunter........................................................................ 18  
2011-2012 Exploration by Cardero....................................................................... 18  
The Coal Price Collapse and its Effect on the Ability to Raise Funds................... 19  
The Failed Sprott Financing ................................................................................. 21  
The Amending Agreement.................................................................................... 21  
June 2013 Meeting............................................................................................... 23  
Kopple Financing.................................................................................................. 23  
October 2013 Meeting.......................................................................................... 23  
November 2013 Discussions................................................................................ 24  
December 2013 Presentation............................................................................... 24  
March 2014 JDS Report....................................................................................... 25  
March 2014 Management Committee Meeting..................................................... 26  
The Surrender and Abandonment........................................................................ 27  
Post-Surrender Fallout ......................................................................................... 28  
Acquisition of Coal Licence Applications from Anglo American ........................... 29  
September 2014 Norwest Report......................................................................... 30  
September 16, 2014 Management Committee Meeting....................................... 30  
October 15, 2014 Telephone Call......................................................................... 31  
Late 2014-Early 2015 Developments ................................................................... 32  
CCP’s July 27, 2015 Letter Enclosing Draft Notices of Default ............................ 32  
Cardero’s August 2015 Notice of Default ............................................................. 33  
Establishment of a Coal Reserve ......................................................................... 34  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 4  
January 2016: CCP Delivers its Notice of Default ................................................ 34  
Mountain Caribou Deferral Area Established ....................................................... 35  
II. EXPERT EVIDENCE........................................................................................ 35  
Pat Akers’ Primary Report.................................................................................... 35  
Robert Farmer and William Wolf’s Reports .......................................................... 37  
Pat Akers’ Reply Report ....................................................................................... 40  
III.  
IV.  
V.  
ISSUES......................................................................................................... 41  
LEGAL PRINCIPLES.................................................................................... 42  
ANALYSIS.................................................................................................... 44  
A. Did Cardero Breach the JVA by Abandoning the Freehold Lease? ................. 44  
1. The Nature of the Alleged Breach................................................................. 44  
2. The Language of the Abandonment Clause ................................................. 45  
3. The Alleged Restriction of the Right to Abandon to the Area of Interest....... 45  
4. The Effect of the Trust Provisions................................................................. 46  
5. The Guidance Provided by the Lease........................................................... 47  
6. The Effect of the Witness Testimony ............................................................ 49  
7. The Duty of Good Faith and the Duties of the Manager Generally ............... 51  
8. The Effect of the Subsequent Increase in the Benchmark Price................... 53  
9. The Lack of a PEA........................................................................................ 53  
10. The Lack of a Viable Path Forward After Abandonment............................. 54  
11. The Failure to Maintain the Lease in Good Standing.................................. 54  
12. Failure to Obtain Management Committee Approval .................................. 55  
13. Other Alleged Breaches by Cardero ........................................................... 56  
13. Conclusion on Cardero’s Alleged Breach of the JVA.................................. 56  
B. Did Cardero Breach the Lease?....................................................................... 56  
C. Did Cardero Breach a Fiduciary Duty? ............................................................ 59  
D. Did CCP Breach the JVA?............................................................................... 60  
E. Notice Issues ................................................................................................... 64  
1. Was Cardero’s Surrender Notice Under the Lease Effective?...................... 64  
2. Was Cardero’s August 24, 2015 Letter Effective Notice under the JVA? ..... 65  
3. Was CCP’s July 27, 2015 Letter Effective Notice under the JVA?................ 67  
4. Is CCP Estopped from Raising Breaches of the JVA or the Lease as a Result  
of its Delay Providing Notice............................................................................. 68  
F. Remedy and Damages..................................................................................... 71  
VI.  
CONCLUSION.............................................................................................. 72  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 5  
I.  
INTRODUCTION  
These two actions seek a determination of the rights of the parties in relation  
[1]  
to a coal mining development project in northern British Columbia (the “Project”).  
[2] Cardero Coal Ltd. (“Cardero”) is the plaintiff in the first action (S159680)  
against Carbon Creek Partnership (“CCP”) (the “JVA action”). Peace River  
Partnership (“PRP”) is the plaintiff in the second action (S160477) brought against  
Cardero (the “Lease Action”). Given the overlap in their ownership and  
representation, CCP and PRP will be referred to collectively as the “Partnerships”.  
[3]  
By order pronounced April 13, 2018, Master Harper ordered that the JVA  
Action and the Lease Action be tried together.  
II.  
BACKGROUND  
The Carbon Creek Coal Deposit  
[4]  
Carbon Creek is approximately 60 kilometers northwest of Chetwynd and 40  
kilometers west of Hudson’s Hope, in the vicinity of Williston Lake. It has long been  
recognized that this area contains substantial coal deposits. A coal deposit was first  
discovered in the early 1900s.  
Project History  
[5]  
In 1924, Senator Patrick Burns obtained certain rights to a landholding in the  
Carbon Creek area as part of an agreement with a debtor of his. In 1956-57, a Burns  
family company exercised an option through which it acquired freehold title to the  
lands and undersurface rights to Crown Granted District Lots 319 to 328 (the  
“Freehold”). Mining on freehold lands enjoys an advantage in that it does not require  
the issuance of a Crown coal licence or lease for exploration or mining.  
[6]  
Pursuant to Quit Claim deeds executed in favour of the Burns Foundation  
Limited in 1971, the original debtors successors did retain a 50% interest in any  
royalties earned from the Freehold.  
       
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 6  
Utah MinesExploratory Efforts  
[7]  
From 1970 to 1981 Utah Construction & Mining Co. (“Utah Mines”) explored  
the Freehold and adjacent Crown lands pursuant to an agreement with certain Burns  
family corporations. Based on its early results, Utah Mines issued a prospectus  
proposing a metallurgical coal development. The prospectus reported the discovery  
of in-place coal reserves of 120 million tonnes (“MT”) from which the company  
projected 67 MT of recoverable reserves. The prospectus also identified the location  
of underground and open pit reserve targets, as well as preliminary mine blocks.  
[8]  
In 1976, Utah Mines issued a revised coal tonnage estimate of 143 MT.  
[9]  
After a period of inactivity, Utah Minescoal licence applications lapsed. Its  
work resulted in 46 boxes of exploration data coming into the Burns family’s  
possession.  
The Johnson Application  
[10] In or around 2004, Alan Johnson filed a coal licence application that also  
purported to cover parts of the Freehold, as well as areas adjacent to it (the  
“Johnson Application”).  
The Burns Applications  
[11] By 2004, the Freehold was controlled by P. Burns Resources Ltd. (Burns).  
[12] In 2005, Burns submitted ten coal licence applications (the Burns  
Applications”) to the B.C. Ministry of Energy and Mines (the “Ministry”). Taken  
together, the Freehold (2,600 hectares or “ha), the additional area covered by the  
Burns Applications (11,310 ha), and the net additional area covered by the Johnson  
Application (3,540 ha) comprised a contiguous parcel of 17,450 ha.  
[13] When filing its applications, Burns discovered the existence of the Johnson  
Application. In response, Burns commenced litigation against Mr. Johnson seeking  
to invalidate the Johnson Application on the basis that it improperly sought to include  
     
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 7  
the Freehold (the “Johnson Litigation”). The existence of the Johnson Litigation  
prevented development of the Project for some time.  
The Coalhunter Approach  
[14] Coalhunter Ltd. was a company controlled by Michael Hunter. I will use both  
“Coalhunter “and “Carderofor this entity, as its name later changed to that of the  
JVA Action plaintiff, Cardero Coal Ltd.  
[15] Michael Hunter has over 20 years experience in the B.C. coal industry,  
including with equipment operations, hiring, budgeting, management of field  
operations, First Nations consultation, and regulatory compliance.  
[16] In about 2010, Mr. Hunter met with Mr. Johnson and discussed whether there  
was a way to resolve the Johnson Litigation so that the Project could move forward.  
Mr. Hunter offered to act on Mr. Johnson’s behalf in trying to resolve the dispute with  
Burns. In March 2010, Coalhunter entered into a letter of intent with Mr. Johnson  
which contemplated Coalhunter receiving an option to acquire the Johnson  
Application.  
[17] Armed with this letter of intent, Mr. Hunter approached Burns, then  
represented by Larry Horan—the Partnerships’ primary witness at trial. Mr. Hunter  
proposed unifying the various interests and claims so that the Project could move  
forward. On or around May 11, 2018, Memoranda of Understanding (“MOUs”) were  
executed between Burns and Coalhunter that would have the effect of ending the  
Johnson Litigation and providing a roadmap to move the Project forward.  
[18] The MOUs provided, inter alia, that Coalhunter would be responsible to make  
the following payments to the Partnerships: $1 million at closing to each of CCP and  
PRP, $2.5 million to each of CCP and PRP by November 15, 2010, and $2.5 million  
to each of CCP and PRP by November 15, 2011.  
[19] As part of implementing the MOUs, Burns had created the separate  
Partnerships in order to accommodate the fact that there was a different group of  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 8  
individuals with an interest in the proceeds of the Freehold as opposed to the other  
Burns properties. However, Burns controlled the day-to-day operations of both  
Partnerships.  
[20] With MOUs now in place, on May 18, 2010, Mr. Hunter executed Coalhunter’s  
option with Mr. Johnson. Under this agreement, Coalhunter acquired the rights to the  
Johnson Application for consideration including a non-refundable deposit of $75,000,  
a first option payment of $275,000, a second payment of $5 million, and the  
provision of certain shares and options in Coalhunter.  
Coalhunter Seeks Assistance  
[21] Coalhunter did not have the funds necessary to meet its immediate financial  
obligations under these various agreements. Consequently, Coalhunter sought out  
financial assistance. Coalhunter made presentations to several investors without  
success. Eventually, Mr. Hunter approached Keith Henderson at the publiclytraded  
company, Cardero Resource Corp. (“CDU”). Coalhunter’s presentation to Mr.  
Henderson included the following assertions:  
a) Production was projected to start in 2012 to 2013, with full production  
estimated for 2014 to 2015.  
b) Development costs and capital expenditures were estimated at $95 million.  
[22] Although Mr. Henderson was of the view that these projections were overly  
optimistic, he believed the deal on offer was too good to pass up. Shortly after the  
presentation, CDU agreed to purchase 49% of Coalhunter’s shares in consideration  
for $3.6 million.  
The Agreements  
[23] With the comfort of financial support from CDU, Mr. Hunter pushed the  
Project forward. Two formal agreements were executed between the newly created  
Partnerships and Coalhunter on June 15, 2010.  
   
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 9  
[24] The first agreement created a joint venture between Coalhunter and CCP (the  
“JVA” for the agreement and the “Joint Venture” for the relationship generally). In  
general terms, Coalhunter agreed to assume 100% of the costs of exploration,  
development, mining, and marketing in return for a 75% interest in the Project.  
Coalhunter would hold any interests of the JVA and would operate as its manager.  
CCP was given shares in Coalhunter, as well as the power to appoint a Coalhunter  
director. The key terms defined in the JVA are as follows:  
“Coal Licenses” is defined as the “coal licences which may be issued by the  
MEMPR pursuant to the Coal Licence Applications, and including any Coal  
Tenures into which the same may be converted, but not including any coal  
licences abandoned pursuant to section 5.10 of this Agreement”.  
“Coal Tenures” is defined as “a coal licence, coal lease or other form of  
tenure to a coal property”.  
“Common Operation” is defined as: “…the performance of Exploration,  
Development and Production on or for the Premises for the Co-Owners as  
tenants in common by the Manager acting under the direction and control of  
the Management Committee to the extent provided by this Agreement.”  
“Laws” is defined to include the Carbon Creek Coal Lease, the common law  
and principles of equity.  
“Losses” is defined as damages, liabilities and legal costs incurred on a  
solicitor and own client basis.  
Premisesis defined as follows:  
the Coal Licence Applications, any Coal Licences once  
issued, any Crown Coal Leases once issued, Coalhunter's  
interest in the Carbon Creek coal lease once granted by the  
Peace River Partnership, any other Coal Tenures issued in  
respect of any of the foregoing, and all lands, leases, interests  
in land and, coal, mines and plants and the production  
therefrom, buildings, machinery equipment, materials,  
supplies, inventories of Production, Products, cash rights'  
Cardero Coal Ltd. v. Carbon Creek Partnership  
powers, privileges, accounts and other property, real or  
Page 10  
personal, movable; immovable, tangible or intangible, of  
whatever nature or kind hereafter acquired and at any time  
held, by or for the Co-Owners as tenants in common under or  
pursuant to this Agreement  
[25] The other relevant terms of the JVA are as follows:  
Pursuant to Article 3.3, any waiver must be in writing.  
Pursuant to Article 4.6, CCP is given 25% carried interest. CCP has a right to  
receive 25% of the net proceeds of production from the Premises but is not  
required to make any contribution towards exploration, development, mining,  
and marketing costs.  
Pursuant to Article 4.8, the parties covenant to make all of their interests in  
each of the coal tenures available exclusively for the purposes of the Joint  
Venture.  
Pursuant to Article 4.9, each Co-Owner has the right to take in kind its  
proportionate share of its interest in coal and coal by-products.  
Pursuant to Articles 4.10-4.12, if and when any” of the Johnson Licenses,  
Coalhunter Licences, or Carbon Creek Partnership Licenses (referred to  
above as the Burns Applications) are issued and transferred to Coalhunter,  
they would form part of the Premises and “shall be held by Coalhunter in trust  
for the benefit of the Carbon Creek Joint Venture for so long as the Carbon  
Creek Joint Venture remains in effect”.  
Pursuant to Article 4.13, similar terms are established for the Freehold  
(referred to in the JVA as the “Carbon Creek Coal Lease”):  
If and when the Carbon Creek Coal Lease is granted to  
Coalhunter, the Carbon Creek Coal Lease shall form part of  
the Premises and the interest of Coalhunter therein shall be  
held by Coalhunter in trust for the benefit of the Carbon Creek  
Joint Venture for so long as the Carbon Creek Joint Venture  
remains in effect.  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 11  
Article 5.2 governs the Co-Owners' Relationship, stating:  
Nothing contained herein shall be deemed to constitute any  
Co Owner, in its capacity as such, the partner, agent or legal  
representative of any other Co Owner, or to create any  
fiduciary relationship between them, for any purpose  
whatsoever.  
Article 5.5 governs the relationship of the Freehold with other the properties,  
stating:  
Except as provided in section 5.6, if the Premises are brought  
into commercial production, the Premises shall not be  
operated as a single operation with other mining properties  
owned by third parties or in which the Manager or a Co-Owner  
has an interest.  
Article 5.6 provides that the Freehold may be operated as a single operation  
with other properties:  
If the Premises are brought into production, the Premises may  
be operated as a single operation with the Peace River  
Partnership Lands.  
Pursuant to Article 5.8, if either party seeks to acquire a property with a larger  
“Area of Interest” outside the current properties, then the other owner will be  
given the right to participate in that additional investment, in which case that  
additional property would become part of the Premises.  
Pursuant to Article 5.10, Cardero has the option to abandon the Project (the  
Abandonment Clause”). This clause states:  
If the Manager wishes to abandon or permit to lapse any of the  
Coal Tenures comprised in the Premises, it may, provided that  
it gives notice of its intention in writing to the Co-Owners and,  
if one or more of the Co-Owners shall so request in writing  
within fourteen (14) days of such notice, transfers such Coal  
Tenures to those Co-Owners as tenants in common in  
accordance with their respective Interests. All costs of such  
transfers shall be home by such Co• Owners, including  
transfer taxes or other taxes payable in respect thereof. Any  
Coal Tenures so abandoned or transferred shall cease to be  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 12  
subject to this Agreement, except with respect to obligations or  
liabilities theretofore accrued.  
Article 5.11 establishes that the Manager of the Project is an independent  
contractor, providing:  
In the conduct of the Common Operation, the Manager shall  
act strictly as an independent contractor and not as an agent  
of the Co-Owners or any of them except as specifically  
authorized in this Agreement.  
Articles 6.1-6.2 establish the Management Committee. The Committee is  
constituted to make decisions required to be made by the Co-Owners with  
respect to the Common Operation, with Coalhunter appointing three of the  
four voting members.  
Pursuant to Article 6.11, Management Committee decisions are binding on all  
parties.  
Pursuant to Article 8.1, Coalhunter is the Manager of the Project.  
Pursuant to Article 8.2, as the Manager, Coalhunter is to conduct the  
Common Operation, and specifically is instructed as follows:  
Subject at all times to the direction and control of the  
Management Committee, the Manager shall conduct the  
Common Operation and do all things necessary or appropriate  
for the proper conduct thereof in accordance with the Work  
Plans and in compliance with all applicable Laws and in a  
sound and miner-like manner in accordance with sound mining  
and engineering practices…  
[…]  
(b)  
Maintenance of Premises in Good Standing Perform  
or cause to be performed all of the obligations of the Co-  
Owners, the performance of which is required in order to  
maintain in good standing all mines, Coal Tenures, surface  
and equipment leases and rights, conditional sales contracts,  
and similar agreements and property rights constituting a part  
of the Premises and shall maintain the Premises free of any  
liens which might otherwise arise as a result of carrying on the  
Common Operation except inchoate liens, liens for payments  
not then due and liens being contested in good faith.  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 13  
Pursuant to Article 11.1, any Co-Owner wishing to withdraw from the  
Common Operation can elect to offer the other Co-Owner its Interest in the  
Joint Venture for $1.00. If the other Co-Owner declines to purchase the  
Interest, “the Agreement shall be deemed terminated”.  
Article 12.1 provides that, upon any default by a Co-Owner in the  
performance of any obligation under the agreement, and the failure to cure  
such default within 30 days, then the defaulting party will be deemed to have  
assigned and conveyed its interest to the other Co-owner and shall be paid  
fair market value for such interest, with the value to be determined by  
arbitration.  
Article 15.1 establishes a force majeure clause, excluding the non-  
performance of certain acts beyond the reasonable control of a party by  
reason of force majeure, but expressly excluded “lack of funds”.  
Article 16.1 provides that the JVA is in effect so long as any two of the original  
parties continue to own any interest or have obligations thereunder.  
Pursuant to Article 19.2, the parties agree to indemnify the other from any  
Lossesincurred as a result of the default of the other.  
Article 21.1 sets out the level of engagement and participation in the  
operation of the Partnership expected of the parties:  
Each party shall promptly do and provide all acts and things  
and shall promptly execute and deliver such deeds, bills of  
sale, assignments, endorsement and instruments and  
evidences of transfer and other documents and shall give such  
further assurances as shall be necessary or appropriate in  
connection with the performance of this Agreement. The  
parties agree to co-operate fully in apply for all necessary  
governmental approvals and permits. Each party shall give to  
the Manager from time to time such powers of attorney and  
other evidences of authority as shall be necessary to enable  
the Manager to perform its duties hereunder.  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 14  
[26] Under the second agreement, Coalhunter was granted an option to enter into  
a coal lease for the Freehold with PRP (the “Coal Lease Option Agreement”). In  
order to maintain its option, Coalhunter was responsible for three payments to PRP  
totalling $6 million. Upon exercising the option, Coalhunter would acquire from PRP  
the sole and exclusive licence and authority to work all mines, seams and beds of  
coal in, on, and under the Freehold. Coalhunter would also be required to pay a 5%  
royalty to PRP on production, with a first minimum annual royalty becoming payable  
starting June 15, 2016. Other key terms of the underlying lease (the “Lease”) are as  
follows:  
Pursuant to Article 1.1 (s), “Losses” is defined as “claims losses, demands,  
judgments, liabilities, expenses, damages, fines, charges and costs (including  
legal costs incurred on a solicitor and own client basis)”.  
Pursuant to Article 2.1, PRP grants Coalhunter the exclusive right to mine  
coal in and under the Freehold.  
Pursuant to Article 2.2, Coalhunter holds the lease for a term of five years,  
expiring on June 15, 2017. The Lease will renew annually so long as  
Coalhunter complied with its terms.  
Pursuant to Article 5.6, Coalhunter has no obligation to mine or work the  
Freehold.  
Article 20.1 stipulates what occurs should Coalhunter fail to perform its  
obligations under the Lease:  
Failure to Perform  
In the event of the occurrence with respect to Coalhunter of  
any one or more of the following:  
(a)  
Coalhunter has failed to obtain on or before June 15,  
2013, all permits and approvals required under  
applicable Laws for the operation of a mine on the  
Lands, provided that if the Peace River Partnership,  
acting reasonably, considers that the failure to obtain  
any permit or approval which has not been obtained by  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 15  
Coalhunter is due to circumstances beyond the control  
of Coalhunter and that Coalhunter has made all  
reasonable efforts to obtain such permit or approval,  
such failure shall not be a termination event unless and  
until any such permit is refused;  
(b)  
(c)  
Coalhunter has failed for whatever reason, whether or  
not beyond Coalhunter's control, to commence  
Commercial Production on the Lands by June 15,  
2017; or  
from and after June 15, 2017, Coalhunter fails to  
achieve Annual Production of at least five hundred  
thousand (500,000) metric tonnes for a period of three  
(3) consecutive years;  
then the Peace River Partnership, without prejudice to any  
other remedy it may have, shall have the right to terminate this  
Lease.  
Article 21.1 provides what will occur in the event of default by any party. This  
clause provides that in the default of the payment of any indebtedness, “and  
the failure of the party to cure any such default in the payment of any monies  
required hereby within thirty (30) days after receipt of written notice”, the other  
party shall “without prejudice to any other remedy it may have… have the  
right to terminate th[e] Lease”.  
Article 23.1 provides Coalhunter with a right to surrender the lands under the  
Lease, stating:  
Notwithstanding anything herein contained, Coalhunter may,  
at any time, upon giving the Peace River Partnership sixty (60)  
days prior written notice thereof determine or surrender all of  
its right, title and interest in all of the Lands or in any legal  
section of the Lands whereupon this Lease shall terminate as  
to the part so surrendered.  
Pursuant to Article 24.1, in the event that the Lease was terminated,  
Coalhunter will remain liable to PRP for any due and unpaidRoyalty or  
Minimum Royalty” amounts “as if such termination had not occurred”.  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 16  
Pursuant to Article 30.1, Coalhunter agrees to indemnify and hold harmless  
PRP from any Losses incurred by PRP as a result of “any breach of this  
Lease by Coalhunter”.  
Article 33.12 governs the relationship of the parties, stating:  
Nothing contained herein, nor the holding of any interest  
acquired hereunder, shall be deemed to constitute Coalhunter  
or the Peace River Partnership, the partner, agent or legal  
representative of the other or to create any fiduciary  
relationship between them for any purpose whatsoever.  
[27] All of the agreements included “entire agreement” clauses.  
[28] With the execution of the agreements, Lawrence Talbot, General Counsel for  
CDU, provided Mr. Horan with bank drafts for the initial two $1 million payments  
required under the Coal Lease Option Agreement and the JVA.  
The Project Comes Together  
[29] The properties subject to the various agreements are set out in the map  
below:  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 17  
[30] In the original of this judgment, the Freehold is outlined in green, the Johnson  
Application licences outside of the Freehold are in red, and the Burns Applications  
are in black. The map does not show the boundary of the Area of Interest, but it  
extends outwards from the outlined areas.  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 18  
CDU Takes Control of Coalhunter  
[31] In the spring of 2011, CDU acquired the balance of Coalhunter’s shares  
through a plan of arrangement and changed the company’s name to Cardero Coal  
Ltd.  
2011-2012 Exploration by Cardero  
[32] Cardero analyzed the Utah Mines information, but found that its usefulness  
was limited, as it was not compliant with National Instrument 43-101 (NI 43-101),  
and thus did not meet the requirements to raise funds through debt or equity.  
[33] On December 6, 2011, Cardero’s consultant, Norwest Corporation  
(“Norwest”), produced a preliminary economic assessment (“PEA”), in accordance  
with NI 43-101, which largely confirmed Utah Mines’ work.  
[34] Over the course of 2011 and 2012, Cardero conducted additional drilling.  
Although never publicly published, these studies expanded the projected resource to  
531 MT measured, and indicated another 215 MT, for a total of 746 MT.  
[35] In late 2012, the Johnson Application was converted into four new coal  
licences.  
[36] On November 6, 2012, Norwest produced a pre-feasibility study (“PFS”) with  
an effective date of September 2012 and which was in accordance with NI 43-101.  
Among other things, the PFS established that:  
a) there were no fatal flaws associated with the Project;  
b) the deposit was understood to be comprised of the most valuable hard coking  
coal (“HCC”) (60%), 34% soft coking coal (“SCC”), and 6% thermal coal;  
c) the projected resource was 468 MT measured and indicated, and 232 MT  
inferred (total of 700 MT);  
d) 62% of the mineable coal was recoverable from the Freehold;  
   
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 19  
e) the required capital costs (excluding the cost of leasing equipment) would be  
$839 million over the life of the mine; and  
f) the total projected net cash flow to Coalhunter, after payback and accounting  
for the carried interest of CCP, was estimated to be roughly $2.1 billion USD  
over the life of any mine.  
[37] I note that the PFS did not incorporate the results of the 2012 drilling.  
[38] Comforted by this information, Coalhunter exercised its option on the  
Freehold by executing the Lease on November 7, 2012.  
[39] On November 8, 2012, CDU reported the key results of the PFS in a press  
release, including the finding that the base case net present value at an 8% discount  
rate for Cardero’s interest was projected to yield a 23.7% internal rate of return  
(“IRR”).  
[40] All things being equal, the next logical step for Cardero should have been to  
complete a full feasibility study. But all things did not remain equal. The unfortunate  
change in the landscape was a dramatic drop in coal prices. No feasibility study was  
ever completed.  
The Coal Price Collapse and its Effect on the Ability to Raise Funds  
[41] When the JVA and Coal Lease Option Agreement were entered into in June  
2010, the key industry benchmark for the price of HCC was approximately $200-  
$220 per tonne. In 2011, this price rose to $220-$330 per tonne. For the purposes of  
the PFS, the potential price was estimated using a low of $165, a base of $200, and  
a high of $217 per tonne. The projected average realized price for coal from Carbon  
Creek, given the assumed split of the types of coal available, was $185 per tonne.  
[42] By the time of the publication of the PFS, the price had fallen to $174 per  
tonne. Prices continued to falter thereafter, which had a serious impact on Cardero’s  
ability to raise funds.  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 20  
[43] Mr. Henderson, the witness with the most experience in mining and marketing  
coal, testified that institutional lenders require an IRR in excess of 20% to consider  
providing project financing for coal mine development. Private equity firms typically  
require an even higher IRR in the range of 30%. The 2011 analysis showed an  
estimated IRR of 29.3%. The 2012 PFS’s base case resulted in an estimated IRR of  
24%. However, if the low case illustrated in the PFS were to materializean  
average price at $143 per tonnethe IRR would fall to 13%, well below what  
investors or lenders would require. Unfortunately, that is precisely what happened.  
[44]  
By mid-2013, the benchmark price for coal fell to $145-$150 per tonne. That  
pricing equated to an average coal price from the Project of only approximately $125  
per tonne. As such, the price of coal was, by that point, significantly below the worst-  
case scenario contemplated in the PFS. Likewise, the price was well below what Mr.  
Henderson testified was necessary to attract investors. The price then continued to  
fall steadily over the subsequent two years. A chart of the downward path of the  
benchmark price through to the end of 2015 follows:  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 21  
[45] Based on these diminished prices, Mr. Henderson foresaw that it would be  
extremely difficult to raise the capital necessary to move the Project forward to full  
production. This is exactly what occurred.  
The Failed Sprott Financing  
[46] Cardero attempted to secure a smaller facility from Sprott Resource Lending  
Corp. (“Sprott”) that, combined with equity funding, would hopefully provide sufficient  
funding to see the Project through its feasibility study stage. However, the potential  
Sprott facility collapsed when CCP declined to make its 25% beneficial interest in the  
Joint Venture’s assets available for Sprott’s security. Without the Sprott funding,  
Cardero was in dire financial circumstances.  
The Amending Agreement  
[47] By this point, it became clear to all of the parties that the June 15, 2013  
deadline in the Lease for receiving the necessary permits would not be met. Mr.  
Hunter and Mr. Horan entered into negotiations to address this issue. Before their  
discussions could be concluded, Mr. Hunter left Cardero’s employ. Thereafter,  
Cardero attempted to negotiate a more wide-ranging set of amendments, but Mr.  
Horan was only willing to agree to the more limited terms discussed with Mr. Hunter.  
[48] Given the approaching June 15, 2013 permitting deadline, Mr. Henderson felt  
that Cardero had no choice but to sign and return the proposed amending  
agreements, notwithstanding that Cardero also viewed the later June 2017  
production deadline, as well as other provisions, as problematic to the development  
of the Project. In an agreement dated May 1, 2013 (the Lease Amending  
Agreement”), the parties replaced the June 15, 2013 permitting deadline with a new  
obligation on the part of Cardero to pay advanced royalties (that would be set off  
against future royalties when production commenced). The required advance royalty  
payments to PRP were as follows:  
a) June 2, 2013: $500,000;  
b) June 2, 2014: $2.5 million;  
   
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 22  
c) June 2, 2015: $2.5 million;  
d) June 2, 2016: $2.5 million;  
e) June 2, 2017: $2.5 million; and  
f) June 2 of each year thereafter: $3.5 million  
(the “Advance Royalty Payments”).  
[49] Cardero was given an election to defer the payment of certain of these  
amounts:  
4.2(e) Peace River Partnership agrees to accept payment of the amount  
due on the following terms and conditions:  
(i) all or any portion of the Advance Royalty due on June 2, 2013,  
such payment may be extended by Cardero Coal by notice in writing  
to Peace River Partnership given not less than 15 days prior to June  
2, 2013, to anytime between June 2, 2013 and June 2, 2014,  
[…]  
(iii) notwithstanding an extension pursuant to clause 4.2(e)(i) or (ii),  
the full amount of the Advance Royalty and all accrued but unpaid  
interest to the date of the occurrence of any default described in  
Section 21.1 shall immediately become due and payable on that  
date…  
[50]  
The JVA was amended by changing the terms of the buy-out provision  
following a default. The provision converted the right of the non-defaulting party to  
buy-out the other’s interest from an obligation to an option (the “JVA Amending  
Agreement”). Mr. Horan testified that he needed this new optional term because he  
realized that a mandatory buy-out might prove prohibitively expensive for the  
Partnerships.  
[51] When he returned the executed amending agreements on May 31, 2013,  
Cardero’s General Counsel, Mr. Talbot, also served notice of Cardero’s election “to  
defer the payment of the CAD 500,000 Advance Royalty Payment due June 2, 2013  
until June 2, 2014, and will therefore commence to pay 6% interest thereon…”.  
Cardero recorded the first Advance Royalty Payment of $500,000 as an “Accounts  
Payable” in its internal accounting records as of June 2, 2013. The interest on the  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 23  
amount was recorded as “interest on Loan” with the notation “$500,000 for one year  
@ 6%.”  
June 2013 Meeting  
[52] In June 2013, Mr. Henderson, now Cardero’s President and CEO, made a  
presentation to the Joint Venture’s Management Committee. The presentation  
outlined the progress Cardero had made to date, but also highlighted the challenges  
created by the deteriorating market conditions. Mr. Henderson reported that market  
feedback with respect to providing financing for the Project was negative. A  
financing consultant advised that mining stock prices were at historic lows and were  
continuing a long descent.  
Kopple Financing  
[53] By mid-to-late 2013, it was becoming clear that the June 2017 production  
deadline in the Lease could also not be met. Further exploration and a feasibility  
study remained to be performed and completed. Various permits, including an  
Environmental Assessment Certificate and a permit under the Mines Act, R.S.B.C.  
1996, c. 293, still had to be obtained.  
[54] Cardero was in a dire cash position by this point, given the inability to obtain  
financing. Staff were let go and most of the senior management team left.  
[55] Cardero did manage to obtain limited interim financing from Luxor Capital  
Group LP (“Luxor”). However, Luxor almost immediately asserted that Cardero was  
in default of the agreement and threatened to enforce its security.  
[56] Cardero was able to obtain replacement financing from Robert Kopple, an  
American venture capitalist. Mr. Kopple’s financial relationship with Cardero began  
in or around August 2013 and continues through to the present.  
October 2013 Meeting  
[57] On October 23, 2013, another Joint Venture Management Committee  
meeting was held. Cardero’s presentation at the meeting emphasized the concerns  
     
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 24  
previously expressed with respect to coal prices. By this point, the average price had  
deteriorated to $126 per tonne. This pricing yielded a projected IRR of only 5.7%—  
well below what financiers required.  
[58] The presentation noted that third parties had already assumed that there  
would be a four-year hiatus in efforts to develop the Project. The presentation also  
noted that, quite apart from trying to time the price forecasts, it would also make  
sense to only bring the mine into production in about 2022 or 2023, given the  
projection that global demand would start to exceed supply at about that time.  
[59] There is some dispute between the parties about whether the possibility of  
splitting the Coal Tenures between the Freehold and the other properties was  
discussed at this meeting or the follow up meetings discussed below. I expect that  
this is an example of each party giving and hearing the same message differently.  
Over this period, Cardero was trying to emphasize that the Project was worth more if  
it was kept together, in the hope that this would convince the Partnerships to make  
concessions in order to keep the Project together in a more economically feasible  
structure. The Partnerships appear to have heard this message as a rosy prediction  
that the Project (as a whole) was still viable, at least in the long run. That said,  
Cardero obviously needed to make decisions and secure financing in the short term.  
This created an obvious tension.  
November 2013 Discussions  
[60] In November 2013, Mr. Horan and Mr. Henderson had a phone call in which  
they discussed the need to push out the production deadline contained in the  
Freehold’s Lease. Given the lack of progress in the discussions on this point,  
Cardero began analyzing what the Project might look like without the Freehold.  
December 2013 Presentation  
[61] Given that Mr. Horan declined to accept the amendments to the agreements  
that Cardero was looking for, Cardero asked to make a presentation to Burnsfull  
board of directors. This meeting took place on December 4, 2013. Mr. Henderson  
   
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 25  
noted that the coal price assumptions in the PFS no longer reflected reality. He  
indicated that the coal market would need to improve in order for Cardero to be able  
to secure project financing. Forecasts were provided that showed that a price  
rebound was not expected until at least 2019. The presentation also noted that,  
given prevailing market prices, the Project had a minimal IRR. Finally, the  
presentation addressed other challenges facing the Project, including increasing  
First Nations opposition.  
[62] Cardero outlined its recommendation to defer production until at least 2023  
and noted the difficulty of securing financing for any project coming online sooner  
than that. In terms of keeping the ball rolling, however, Cardero proposed at least  
preparing a re-stated PFS incorporating data from the 2012 drilling program, as well  
as incorporating mine optimization plans that had been developed. Cardero also  
proposed advancing the coal licence applications and acquiring additional coal  
interests in the vicinity.  
March 2014 JDS Report  
[63] JDS Energy & Mining Inc. (“JDS”) provided Cardero with a report on March 3,  
2014 which analyzed the Project both with and without the Freehold (the “JDS  
Report”). JDS determined that the Freehold and the other Coal Tenures could each  
produce slightly in excess of 39.5 MT of saleable product. It noted that the other  
properties had a significantly greater volume of HCC (46.459 MT versus 25.845 MT)  
and surface mineable HCC (22.823 MT versus 12.594 MT) relative to the Freehold.  
The reported IRR for Cardero’s 75% interest with the tenures kept together, and  
using an 8% discount rate, ranged from 2% to 13%, with associated net present  
values ranging from negative $219 million to $111 million. JDS assessed that if the  
market returned to the PFS’ projected pricing levels, Cardero’s 75% interest in the  
other properties would have an IRR of 31% and a net present value (“NPV”) of $462  
million at an 8% discount rate.It would result in $597 million being paid to CCP on  
account of its interest on an undiscounted basis. However, this particular report was  
not admitted for the truth of its contents given that no expert testified in support of  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 26  
the opinions set out therein. Rather, it was only admitted to help explain the parties’  
subsequent conduct in response to this new information.  
March 2014 Management Committee Meeting  
[64] On March 11, 2014, the parties held another Management Committee  
meeting. Cardero asserted that no investors would support the Project if the  
Freehold stood to be lost due to the terms of the Lease and its approaching, but  
unachievable, June 2017 production deadline. Cardero also advised that it could not  
justify making any Advance Royalty Payments if such payments would effectively be  
wasted. They would be wasted if the Freehold reverted to PRP pursuant to the  
terms of the Lease when the unachievable June 2017 deadline in the Lease was not  
met.  
[65] Mr. Horan requested a letter from Cardero addressing the production  
deadline and Cardero’s proposed moratorium on Advance Royalty Payments.  
Cardero provided a letter on March 13, 2014 stating:  
We have previously discussed the June 15, 2017 deadline for achieving  
commercial production from the Lease lands contained in 20.1(a) of the  
Lease Agreement, and I think it is fair to say that that both Cardero Coal and  
PRP believe that it needs to be moved out at least 5 years in order to make  
the overall Carbon Creek project financeable and to allow the worldwide  
metallurgical coal market to recover. The 2017 date has been, and will  
continue to be, a significant barrier to Cardero Resource raising finance and it  
is frequently raised as an issue by analysts reviewing the Carbon Creek  
project. It is also a barrier to the sale of Carbon Creek as a single asset, if  
that is what the parties, together, chose to do.  
Due to the inability to secure the required financing at current coal prices,  
Cardero Coal is unable to make the June 2, 2014 $500,000 advance royalty  
payment…  
[…]  
Unfortunately, Michael [Hunter] agreed to something that, in today’s coal  
market, is just not financeable.  
[66] Cardero requested a 5-year moratorium on the Advance Royalty Payments.  
Cardero noted that if the requested amendments to the Lease were not accepted,  
then Cardero anticipated having to withdraw from the Lease “with extreme regret  
and as a last resort.”  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 27  
[67] On March 24, 2014, Cardero sent a letter to Mr. Horan confirming the parties’  
agreement that Cardero could deliver a notice of surrender of the Lease as late as  
April 30, 2014. On March 27, 2014, the Partnerships accepted Cardero’s position.  
[68] On April 17, 2014, CDU’s CEO and President, Henrik van Alphen, sent a  
letter to Mr. Horan identifying the benefits of keeping the Coal Tenures together, and  
reiterating the amendments Cardero required in order to allow that to happen.  
Cardero sought to encourage PRP’s agreement to the proposed amendments by  
offering to modify the Advanced Royalty Payments such that they would apply to all  
coal from the Project, rather than just from the Freehold.  
[69] On April 28, 2014, Mr. Horan emailed Cardero with a counter proposal. Mr.  
Horan’s proposal left the June 2, 2013 and 2014 Advance Royalty Payments in  
place, but accepted reductions to $2 million in June 2015, and to $2.5 million  
thereafter. This proposal would still have required payments from Cardero to PRP  
totalling $22 million between June 2014 and June 2022. This was not acceptable to  
Cardero.  
The Surrender and Abandonment  
[70] Given the inability of the parties to agree on terms that would extend the  
Lease’s 2017 deadline, on April 30, 2014, Cardero purported to issue a notice of  
surrender under section 23.1 of the Lease, effective May 30, 2014 (the “Surrender  
Notice”). Cardero also issued a notice of abandonment of the Lease pursuant to  
section 10.5 of the JVA (the “Abandonment Notice”).  
[71] This letter also included a proposal to amend the Lease by extending the  
production deadline to 2022 and reducing the annual Advance Royalty Payments to  
$300,000 until June 2019. PRP did not accept this proposal.  
[72] The abandonment and surrender were not part of that year’s work plan  
prepared by Cardero, and no prior consent was sought from CCP or PRP.  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 28  
Post-Surrender Fallout  
[73] On May 6, 2014, Mr. Horan emailed Mr. van Alphen in connection with their  
verbal discussions wherein Mr. Horan offered to extend the date for commercial  
production to 2022 and to tie the Advance Royalty Payments to the benchmark price  
of hard coking coal for the years 2015-2022. Mr. van Alphen responded on May 15,  
2014, rejecting Mr. Horan’s proposal. Mr. Henderson testified that, notwithstanding  
that Mr. Kopple was prepared to support Cardero, without a moratorium on Advance  
Royalty Payments and an extension of the 2017 deadline for commercial production,  
he could not recommend that Mr. Kopple finance the pending Advance Royalty  
Payments. Mr. Kopple testified that while he had the funds available to finance the  
Advance Royalty Payments if necessary, Mr. Henderson recommended against this.  
[74] On May 21, 2014, Cardero advised Mr. Horan that it had renewed the coal  
licences and paid the associated fees, that it would be preparing assessment reports  
for the remaining Coal Tenures and provided notice that Cardero had applied for a  
coal licence with respect to a small gap in the Joint Venture’s tenures. CCP elected  
to participate in this acquisition pursuant to Article 5.8 of the JVA by letter dated  
June 9, 2014.  
[75] Cardero did not make the Advance Royalty Payment of $500,000 on June 2,  
2014, or thereafter.  
[76] At that time, CDU issued a press release announcing that Cardero had  
withdrawn from the Coal Lease. The release stated that: “In the context of this  
market, the making of the scheduled aggregate $12.5 million in advance royalty  
payments over the coming 5 years was simply not justifiable and not in the best  
interests of Cardero [CDU] shareholders.”  
[77] On June 10, 2014, Mr. Henderson emailed Mr. Horan a proposed letter to the  
Ministry confirming Cardero’s ability to speak for CCP, asking for Mr. Horan’s  
comment. The letter was drafted for Mr. van Alphen’s signature. Mr. Henderson  
testified that he had been informed by Ministry staff that it needed confirmation of  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 29  
Cardero’s authority to deal with the applications, given the uncertainty created by the  
historical Johnson Litigation. Mr. Horan did not respond to Mr. Henderson’s email.  
[78] On June 17, 2014, Mr. Henderson called Mr. Horan to follow up on this issue.  
Mr. Horan replied that CCP would not be cooperating with Cardero because he  
believed the $500,000 of Advance Royalty Payments was owing to PRP and he  
wanted it paid. He said that he would be sending a letter to Mr. Henderson outlining  
his view of Cardero’s obligations on termination of the Lease. Mr. Horan also  
suggested there had been a potential breach of the JVA by Cardero. Finally, Mr.  
Horan said he had concerns with the validity of the Surrender Notice, as well as  
concerns as to whether Cardero had the right to terminate the Coal Lease at all.  
[79] On July 8, 2014, Cardero filed the assessment reports required to maintain  
the Joint Venture’s remaining Coal Tenures in good standing. Cardero also prepared  
and delivered a 2014 work plan. This outlined a plan for completion of the  
assessment reports, completion of a new NI 43-101, efforts to advance pending coal  
licence applications, acquisition of additional coal interests, and further technical  
modelling and planning.  
[80] On July 17, 2014, Mr. Horan sent a letter to Mr. Henderson requesting  
performance of the obligations that arose from Cardero’s surrender. PRP also  
demanded the $500,000 Advance Royalty Payment.  
[81] On July 31, 2014, Cardero confirmed that it had performed its post-surrender  
obligations. Mr. Henderson also noted that Mr. Horan and Mr. van Alphen had  
agreed that the issue of the unpaid royalties would be discussed at the next Joint  
Venture Management Committee meeting in September 2014.  
Acquisition of Coal Licence Applications from Anglo American  
[82] In August 2014, Cardero entered into a contract with a subsidiary of Anglo  
American, plc, to acquire additional coal interests for the Joint Venture. Cardero paid  
$235,000 to acquire the coal licence applications.  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 30  
[83] After receiving notice of this proposed transaction, Mr. Horan requested a  
copy of the agreement to assess whether CCP would elect to participate in the  
acquisition. Mr. Horan confirmed at trial that he understood he only had a right to  
request a copy of this agreement pursuant to the JVA. CCP did not elect to  
participate in these additional acquisitions.  
September 2014 Norwest Report  
[84] On September 12, 2014, Cardero received a new report from Norwest valuing  
the Project without the Freehold. The report estimated a resource of 290 MT  
measured and indicated, and 161 MT inferred.  
September 16, 2014 Management Committee Meeting  
[85] The next Management Committee meeting was scheduled for September 16,  
2014. Cardero delivered notice of its acquisition of the coal licence applications from  
the Anglo American subsidiary and discussed opportunities to potentially acquire  
additional Coal Tenures. Cardero described its ongoing efforts and strategy to  
advance the other coal licence applications. Mr. Henderson again advised Mr. Horan  
that the Ministry had requested CCP’s approval for the advancement of the coal  
licence applications. The Management Committee determined that CCP would  
prepare a letter to the Ministry confirming Cardero’s authority to deal with the coal  
licence applications.  
[86] At the meeting, Mr. Horan requested a letter from Cardero addressing its  
legal position on the $500,000 Advance Royalty Payment.  
[87] The Management Committee also decided the following:  
a) CCP would review the insurance binder and, if acceptable, sign an  
acknowledgement confirming it was accepted as being in compliance with the  
JVA.  
b) CCP would review a proposed amending agreement to modify the Manager’s  
accounting responsibilities and provide comments, if any.  
   
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 31  
c) CCP would review a proposed modified Management Committee resolution  
dealing with the reporting schedule.  
d) The parties would execute a resolution in respect of the 2014 work plan.  
[88] The minutes identified these action items. Mr. Henderson sent Mr. Horan a  
copy of the minutes by email on September 19, 2014. However, aside from signing  
the work plan resolution, Mr. Horan did not act on the other items assigned to CCP.  
The work plan authorized Cardero, as Manager, to “[liaise] with the Assistant Deputy  
Minister and Minerals Titles staff to move certain coal licence Applications (Burns  
Applications’) forward towards issuance of coal licences.”  
October 15, 2014 Telephone Call  
[89] On October 15, 2014, Mr. Henderson and Mr. Horan spoke again. Mr. Horan  
again made it clear that CCP would not be signing anything and would no longer  
cooperate in relation to Joint Venture business until the $500,000 Advance Royalty  
Payment issue was addressed. After the call, Mr. Henderson sent an email summary  
to Mr. Kopple and Mr. van Alphen. Among other things, that email reports that Mr.  
Horan said that he “is not going to sign anything…” and that the JVA “is not  
important to” the Burns Group.  
[90] On cross-examination, Mr. Horan confirmed the sworn statement in  
paragraph 76 of his affidavit dated December 1, 2017 that, in essence, “… it is true  
that on that call I advised [Mr. Henderson] that CCP would not be cooperating with  
Cardero’s plans to manage the joint venture lands…”  
[91] In the Partnerships’ final argument, the Partnerships made the following  
acknowledgement:  
On October 15, 2014, Mr. Horan and Mr. Henderson had a telephone call  
wherein Mr. Horan advised that he would not be signing anything until  
Cardero had dealt with the issue of the payment of the $500,000 Advance  
Royalty payment. Mr. Horan wanted to see Cardero’s legal position in writing  
so that he could provide it to their lawyers and determine whether or not to  
sue Cardero. Mr. Horan believed that CCP, as a silent partner with a Carried  
Interest, had no duty to cooperate or participate in the management of the  
Joint Venture.  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 32  
Late 2014-Early 2015 Developments  
[92] On December 11, 2014, Norwest delivered a report in accordance with NI 43-  
101 reviewing the status of the Joint Venture without the Freehold. The report  
confirmed a coal resource on the remaining tenures of 290 MT measured and  
indicated, and 161 MT inferred.  
[93] On January 30, 2015, Cardero delivered a letter to PRP outlining its position  
in respect of the Advance Royalty Payments. Essentially, Cardero interpreted Article  
4.2(e)(i) of the Lease Amending Agreement as deferring the due date rather than the  
payment date. Given that this due date had not yet passed when the surrender  
occurred, Cardero’s position was that the amount was not payable.  
[94] In March 2015, Mr. Horan invoked the existence of the JVA as the basis to  
obtain a copy of a confidential agreement between Cardero and a firm which owned  
and operated a nearby bulk export marine terminal, Ridley Terminals Inc., from Mr.  
Henderson.  
[95] Mr. Horan testified that CCP formed the view that Cardero had breached the  
JVA by terminating the Lease by at least late March or early April 2015. However,  
CCP did not deliver a notice of default under Article 12.1 of the JVA at that time.  
[96] In May 2015, Cardero filed reports and paid fees necessary to keep the  
remaining Coal Tenures in good standing. Cardero also prepared and circulated a  
new work plan. The work plan referenced Cardero’s intention to still try to advance  
the remaining coal licence applications within the JVA. It also updated CCP on the  
progress of the audit CCP had requested.  
CCP’s July 27, 2015 Letter Enclosing Draft Notices of Default  
[97] On July 27, 2015, a “without prejudice” letter was sent by Mr. Horan to  
Cardero attaching draft letters, including a draft notice of termination of the JVA.  
[98] The draft letters state, inter alia, “[a]s you are aware, Cardero terminated the  
Coal Lease effective May 30, 2014.The letters assert a claim for both the $500,000  
   
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 33  
Advance Royalty Payment and the subsequent $2,000,000 Advance Royalty  
Payment.  
[99] The cover letter concludes:  
We thought you and Mr. Kopp[le] might be interested in discussing these  
matters on a without prejudice basis before we delivered these letters to you.  
Please let us know by Wednesday, July 29, 2015 at 4:00 pm MDT whether  
you are interested in doing so and the proposed date for this meeting (which  
should be within fourteen (14) days of this correspondence). Should we not  
hear from you by that time we will send the attached letters.  
[100] No meeting date was provided by Cardero within the time provided, and CCP  
did not deliver final versions of the draft letters to Cardero.  
Cardero’s August 2015 Notice of Default  
[101] On August 9, 2015, Mr. Henderson sent Mr. Horan a package of materials for  
the Management Committee meeting scheduled for August 12, 2015. Mr. Horan  
advised Mr. Kopple that he did not think Mr. Kopple should attend this meeting,  
given their ongoing dispute, until the two of them had had an opportunity to meet  
and discuss matters.  
[102] On August 24, 2015, Cardero delivered a notice of default to CCP under the  
JVA based on CCP’s alleged failure to:  
a) draft the letter to the Ministry;  
b) review and approve the insurance policy;  
c) review amendments to the JVA to modify the Manager’s accounting  
responsibilities; and  
d) review the minutes of the Management Committee meetings.  
[103] While the letter was marked “Without Prejudice”, it included no settlement  
offer. The letter did go on to suggest that a meeting with Mr. Kopple would be useful.  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 34  
The letter closed by providing notice of the Management Committee meeting  
scheduled for September 3, 2015.  
[104] Cardero then took steps to schedule a Management Committee meeting for  
September 3, 2015. However, since CCP refused to attend, no quorum was  
achieved. The meeting was therefore adjourned and reconvened in Vancouver on  
September 15, 2015. Again, CCP failed to attend. However, pursuant to fallback  
terms in the JVA, quorum was achieved this time even without CCP. The  
Management Committee passed various resolutions in connection with the 2015  
work plan and other outstanding matters. All items of business at the meeting  
passed unanimously, including approval of the insurance policy for the Joint  
Venture, approving amendments to the JVA to modify the Manager’s accounting  
responsibilities, and approving the minutes of the September 16, 2014 Management  
Committee meeting. In relation to the letter to the Ministry, the Minutes note that  
“unless the CCP provided authorization for the Manager to act on their behalf, there  
was in fact nothing that the Manager could do to change that situation”.  
[105] On November 20, 2015, Cardero delivered a notice to CCP indicating that,  
given CCP’s breaches of the JVA, Cardero was making an election under Article  
12.1 of the JVA to acquire CCP’s interest in the Joint Venture. Cardero filed its  
notice of civil claim on the same date. CCP did not accept that there was a valid  
basis for Cardero to acquire its interest.  
Establishment of a Coal Reserve  
[106] On January 8, 2016, the parties learned that the Chief Gold Commissioner  
had established a coal land reserve under s. 21(2) of the Coal Act, S.B.C. 2004, c.  
15, in the area surrounding the Project, including lands covered by a number of the  
remaining Coal Tenures within the JVA.  
January 2016: CCP Delivers its Notice of Default  
[107] On January 18, 2016, CCP finally delivered a formal notice of default to  
Cardero under the JVA. CCP’s notice stated that it “constitutes written notice of  
   
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 35  
default pursuant to Section 12.1(a) of the [JVA].” The default identified in the letter  
was Cardero’s decision to irrevocably surrender its interest and terminate the Lease  
with PRP. CCP filed the JVA Action the same day.  
Mountain Caribou Deferral Area Established  
[108] On May 31, 2019, a provincial Order in Council was issued establishing the  
Mountain Caribou Partnership Coal Licence Deferral Area over a portion of the  
remaining Coal Tenures. This order prohibits coal development within the prescribed  
area.  
[109] There have been no material updates in the development of the Project since  
this last event, as the parties have been focussed on this litigation.  
II.  
EXPERT EVIDENCE  
Pat Akers’ Primary Report  
[110] Pat Akers was presented as an expert witness by Cardero. Mr. Akers has a  
Bachelor of Science in Accounting. He has worked in mining for more than 20 years  
and he has evaluated mine expansions and new mining opportunities. Mr. Akers has  
personal knowledge of this Project, having served as a project manager for Norwest  
in respect of the PFS and the December 2014 Technical Report. Mr. Akers led  
Norwest’s team and organized the work of the engineers and geologists reporting to  
him.  
[111] In his report, Mr. Akers opined on the steps a reasonable and prudent mining  
operator in Cardero’s position would have taken in relation to the Lease and JVA.  
[112] Mr. Akers summarized the difficult situation facing Cardero as follows:  
In valuing a royalty, or in this case, an NPI which is essentially the same  
thing, the economic viability of the underlying mining operation must be  
demonstrated. Without an economically viable mine, there is no net profit,  
hence no net profits interest. As noted previously, the Carbon Creek Coal  
Project was not economically viable based on the coal prices that existed in  
the 2013 through Q2 2016 timeframe. It is clear that the mine could not be  
and was not developed due to the collapse and free fall of metallurgical coal  
prices for three and a half years from 2013 through Q2 2016. Prices fell from  
     
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 36  
about US $225 at the end of 2012 to less than US $100 by the end of 2015.  
Capital was simply not available and even if it was, it would not have been  
prudent to invest those sums of money at that time. As we noted previously,  
during this period, mines were being idled or permanently closed, projects  
were being shelved and coal companies were going bankrupt including  
Peabody, Arch Coal Company, and Alpha Natural Resources. In addition,  
there were other inherent risks associated with the development of the project  
including permitting and First Nations agreements which could have caused  
significant delays in the development schedule.  
[113] Mr. Akers concluded as follows:  
A prudent mining operator would not make an advance royalty payment  
of millions of dollars knowing that it was highly unlikely the production  
requirement could be met which would allow PRP to cancel the Coal  
Lease and keep the advance royalty payments…  
The same is true for the subsequent advance royalty payments due in  
2015, 2016, and 2017. A prudent mining operator would not pay the  
additional advance royalty payments totaling $10.0M when it was highly  
unlikely that the date for initial production could be met. Any prudent  
mining operator in Cardero’s position would have to consider pursuing the  
Joint Venture on the coal licence areas alone.  
In addition, potential investors would not be willing to invest in the project  
without a change in Section 20 of the Coal Lease because it would put  
their investment at significant risk, PRP could cancel the lease at their  
discretion if the June 2017 production date was not met. This created an  
unacceptable risk for any prudent investor.  
Given this difficult situation, it is our opinion that Cardero’s actions were  
consistent with those that would have been taken by a prudent mining  
operator and were in the best interests of the Joint Venture. This is  
because they knew in May 2014 that the advance royalty payment due in  
June 2014 would most likely be forfeited (or at the very least be lost or  
have no value based on the unilateral actions of PRP) because it was  
almost certain that the production deadline of June 2017 could not be  
met. This meant that the lease would be subject to termination even if  
they had made the June 2014 advance royalty payment.  
Based on the information management had at the time, including the JDS  
report and the updated geologic model, and dependent on the outcome of  
the further analysis discussed in the next section of this report, there was  
a significant prospect of a smaller though profitable project on the Coal  
Licence areas.  
[114] In cross-examination, Mr. Akers was asked whether a prudent mining  
operator would pay reduced Advance Royalty Payments in consideration for an  
extension of the production deadline to June 2022. Mr. Akers said that such facts  
would not change the Project’s risk profile, and a prudent mining operator would  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 37  
simply not make material annual payments to maintain the Lease in circumstances  
where the return was so uncertain.  
[115] The Partnerships are critical of Mr. Akers qualifications, given that his  
expertise is in accounting. However, I find that this is precisely the type of individual  
who could properly assess Cardero’s economic decision-making. Cardero, as  
Manager, had to consider the overall economics of the Project, not simply whether  
there was a solid volume of coal in the ground. If the bottom line facing the Project  
meant that the coal could not be sold at a high enough price to overcome its costs  
and expenses, then the Project’s viability would be in question. Such an analysis is  
largely financial, although certainly guided by the underlying technical information.  
[116] The Partnerships are also critical of Mr. Akersreport on the basis that he was  
asked to assume that Cardero sought, but was unable to successfully secure,  
financing for the Joint Venture. I find that this assumption is consistent with the facts  
presented at trial.  
[117] Finally, the Partnerships are critical of the fact that Mr. Akers was asked to  
assume that an extension of the June 2017 production deadline was not available.  
Once again, I find that this assumption fits the evidence. While there was a proposal  
from the Partnerships to extend the deadline, it was on terms that Cardero did not  
accept. The reality on the ground for Cardero, as it made its decision whether or not  
to surrender and abandon, was that the June 2017 deadline was staring down the  
Joint Venture. It was reasonable for Cardero, as Manager, to act on the basis of the  
world as it was, not on how it could have been if the Co-Owners had been able to  
come to terms on an extension. The Manager was bound to do the best it could  
under the existing JVA, not under the terms of a possible amendment.  
Robert Farmer and William Wolf’s Reports  
[118] Robert Farmer and William Wolf from J.T. Boyd Company were jointly  
tendered as experts by the Partnerships. They were qualified as experts in the  
following areas:  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 38  
a) Mr. Farmer, in geologic modeling, resource and reserve estimation,  
underground and surface mine design, production and financial modeling,  
and feasibility of coal mining operation; and  
b) Mr. Wolf, in energy and minerals markets, mine feasibility, economic analysis,  
and valuation of coal mining operations for the purposes of damages  
assessment.  
[119] These experts were asked to assess the effect of abandoning the Freehold,  
and to determine the amount required to put CCP in the position it would have been  
if Cardero had developed a coal mine and put it into commercial production by June  
15, 2017.  
[120] Mr. Farmer concluded that [s]ubject to further review, it is BOYD’s opinion  
that development of an economically feasible mine on the Property without the  
Freehold Lands would have been unlikely.” He opined as follows:  
a) Cardero relinquished those portions of the coal deposit (i.e., the Freehold) for  
which the "location, quantity, grade, geological characteristics and continuity"  
are not substantially based on extrapolation and therefore have higher  
geologic assurance.  
b) Cardero removed over half of the product coal tonnes associated with the  
mine plans presented in the November 2012 PFS. Potential mining  
operations on the remaining portions (i.e., the non-Freehold Lands) would  
likely result in lower annual production rates (and reduced revenues) and/or a  
shorter mine life (reduced payback time).  
c) Cardero sterilized (i.e., made inaccessible or not mineable due to mining  
limitations) those coal resources located at or near the coal interests'  
boundaries.  
d) Cardero surrendered the privately-owned fee simple parcels where mining  
would not have required a coal licence or Crown Coal Lease.  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 39  
e) Cardero lost most of the large contiguous areas of potentially open-pit or  
underground mineable coal, which are more conducive to mining at higher  
productivity rates over longer periods of time.  
f) Cardero segregated the remaining portions of the mine plans presented in the  
November 2012 PFS into smaller isolated pockets with generally poorer  
geologic conditions and limited access that will not support higher productivity  
mining methods and the sustained mine production and operational flexibility  
required to ensure financial success.  
g) Cardero’s decision hindered access to the property, thus adding significant  
costs to any potential operation.  
[121] As such, Mr. Farmer concluded that a positive economic outcome for the  
remaining properties without the Freehold is unlikely.  
[122] Mr. Farmer did not expressly analyze the effect of the June 2017 production  
deadline and the requirement for the Advance Royalty Payments. Mr. Farmer also  
did not consider the depressed coal market at the relevant time, nor did he analyze  
the difficulty in securing project financing, despite his assessment that financing in  
excess of $777 million would be required.  
[123] Mr. Wolf’s work related to the calculation of damages. Mr. Wolf was directed  
how to perform the assessment:  
Please do so based on both the mine plan contemplated under the Norwest  
Cash Flow Model and under the JDS Cash Flow Model, utilizing actual coal  
prices to date, applying a reasonable forecast for future coal prices, and  
discounting future cash flow at an 8% and 10% discount factor.  
[124] Mr. Wolf ran two damages scenarios. Under the earlier Norwest cash flow  
model, he determined that the value of CCP’s 25% carried interest, as of the date of  
trial, using a 10% discount rate, would be $88,803,615 USD. Mr. Wolf then ran the  
same calculation under the later optimized financial model prepared by JDS, which  
yielded a net present value for CCP’s 25% carried interest of $132,878,355 USD.  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 40  
[125] Mr. Wolf also ran a damages calculation associated with the loss of the  
Freehold Lands alone. In doing so, he arrived at a net present value for CCP’s  
carried Interest in the Freehold Lands, at a 10% discount rate, under the Norwest  
model, at $55,324,652 USD, and under the JDS model, at $82,783,215 USD.  
[126] Mr. Wolf assumed that the development and financing risks were  
manageable, including assuming that Cardero was able to prove the feasibility of the  
Project in accordance with NI 43-101, obtain rights of way for power, transportation,  
infrastructure, and road, among other things, successfully complete an  
environmental assessment, overcome any litigation that would ensue, and make all  
necessary transportation and First Nations agreements required. Mr. Wolf performed  
his calculations based on benchmark prices, although Mr. Henderson’s evidence  
was that the quality of the coal at the Project required a discount from the  
benchmark.  
Pat Akers’ Reply Report  
[127] Mr. Akers’ reply report commented on the approach taken by Mr. Wolf as  
follows, inter alia:  
[The] cash flow model developed to support the Income Approach would be  
based on different assumptions regarding price risk and volatility, project  
risks, production risks, availability of capital, capital structure of the entity, the  
cost of capital, and the risk associated with the provisions of Section 20 of the  
Coal Lease agreement. For a project such as this, the valuation model would  
have a much higher discount rate and a different cash flow stream.  
A compounding factor in addition to the risks noted above is demonstrated in  
Tables 1 through 3 of the Boyd report which shows that the simple pay-back  
period for this project using their assumptions is approximately twelve years.  
This means it is twelve years before the initial investment in the property is  
recovered. The longer this period is, the higher risk of the project and  
therefore the higher the discount rate would be. In addition, this long pay-  
back period would deter many investors. While it varies from investor to  
investor, it is our opinion that reasonable pay-back periods range from three  
to six years depending on other risk factors associated with the investment.  
For the reasons noted above, it is our opinion that the assumptions and  
approach used by Boyd in their assessment of estimate of CCP’s damages  
are not valid. In addition, as noted in our report titled “Independent Expert  
Report on the Carbon Creek Property” dated January 9, 2020 it is our opinion  
that CCP did not incur any damages because a net profits interest has no  
value if the underlying mining operation is not economically viable.  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
III. ISSUES  
Page 41  
[128] In the JVA Action, Cardero asserts that CCP breached the JVA by, among  
other things:  
a) failing to comply with decisions of the Joint Venture’s Management  
Committee contrary to Article 6.11;  
b) refusing to make its interest in its Coal Tenures available to the Joint Venture  
contrary to Article 4.8; and  
c) refusing to participate in the Joint Venture at all or cooperate in any of the  
Joint Venture’s business contrary to Article 21.1.  
[129] If any of those defaults are found, Cardero seeks confirmation that it is  
entitled to purchase CCP’s interest in the Joint Venture pursuant to Article 12.1(e) of  
the JVA.  
[130] In its counterclaim in the JVA Action, CCP alleges that it was Cardero that  
breached the JVA by abandoning the Freehold contrary to its obligation to maintain  
the property in trust for the Joint Venture pursuant to Article 4.13.  
[131] Cardero responds by denying any breach, but also alleging that CCP is  
estopped from advancing this argument because it failed to give notice of default  
under the JVA for almost two years. Cardero notes that it expended further funds on  
the Joint Venture during this period.  
[132] In the Lease Action, PRP asserts that, as a result of its breaches of the  
Lease, Cardero should be held liable to PRP for the unpaid Advance Royalty  
Payments of $2.5 million, plus interest. PRP says that Cardero should also be held  
liable for damages sufficient to put the Partnerships in the position they would have  
been in had Cardero performed its obligations and built the mine. CCP also seeks a  
declaration that, given Cardero’s breaches, it should be entitled to acquire Cardero’s  
interest in the remaining Joint Venture lands.  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 42  
[133] Cardero responds that no Advanced Royalty Payment was made because the  
surrender occurred before Advance Royalty Payments first came due on June 2,  
2014. Cardero argues that, given the wording of Article 24.1 of the Lease, no  
Advance Royalty Payment is payable after termination.  
IV.  
LEGAL PRINCIPLES  
[134] This case turns primarily on questions of contractual interpretation. In general,  
Cardero seeks a more “black letter” interpretation of the agreements, whereas the  
Partnerships propose an approach that incorporates a broader consideration of the  
surrounding factual circumstances and the intentions of the parties.  
[135] The tension created by these two approaches was addressed by the  
Supreme Court of Canada in Sattva Capital Corp. v. Creston Moly Corp., 2014 SCC  
53. In this decision, the court described the proper approach as follows:  
[57]  
While the surrounding circumstances will be considered in interpreting  
the terms of a contract, they must never be allowed to overwhelm the words  
of that agreement (Hayes Forest Services, at para. 14; and Hall, at p. 30).  
The goal of examining such evidence is to deepen a decision-maker's  
understanding of the mutual and objective intentions of the parties as  
expressed in the words of the contract. The interpretation of a written  
contractual provision must always be grounded in the text and read in light of  
the entire contract (Hall, at pp. 15 and 30-32). While the surrounding  
circumstances are relied upon in the interpretative process, courts cannot use  
them to deviate from the text such that the court effectively creates a new  
agreement…  
[58] The nature of the evidence that can be relied upon under the rubric of  
"surrounding circumstances" will necessarily vary from case to case. It does,  
however, have its limits. It should consist only of objective evidence of the  
background facts at the time of the execution of the contract (King, at paras.  
66 and 70), that is, knowledge that was or reasonably ought to have been  
within the knowledge of both parties at or before the date of contracting…  
[Emphasis added.]  
[136] The Supreme Court of Canada recently clarified in Corner Brook (City) v.  
Bailey, 2021 SCC 29, that the “knowledge that was or reasonably ought to have  
been within the knowledge of the parties” does not include their subjective  
intentions:  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 43  
[20] This Court set out the current approach to contractual interpretation in  
Sattva. Sattva directs courts to “read the contract as a whole, giving the words  
used their ordinary and grammatical meaning, consistent with the surrounding  
circumstances known to the parties at the time of formation of the contract”:  
para. 47. This Court explained that “[t]he meaning of words is often derived  
from a number of contextual factors, including the purpose of the agreement  
and the nature of the relationship created by the agreement”, but that the  
surrounding circumstances “must never be allowed to overwhelm the words of  
that agreement”: paras. 48 and 57. “While the surrounding circumstances are  
relied upon in the interpretive process, courts cannot use them to deviate from  
the text such that the court effectively creates a new agreement”: para. 57. This  
Court also clarified that the relevant surrounding circumstances “consist only  
of objective evidence of the background facts at the time of the execution of  
the contract . . . , that is, knowledge that was or reasonably ought to have been  
within the knowledge of both parties at or before the date of contracting”: para.  
58.  
[…]  
[25]  
First, the Blackmore Rule does not allow consideration of the  
subjective intention of the parties. While it is not immediately obvious what  
"specially in the contemplation of the parties" means, La Forest J.A. (as he  
then was) held in White v. Central Trust Co. (1984), 54 N.B.R. (2d) 293  
(C.A.), that this does not refer to the subjective intention of the parties, but  
merely permits courts to look to the surrounding circumstances to give  
meaning to the words the parties used. He stated that "[b]y referring to what  
was in the contemplation of the parties, Lord Westbury was, of course, not  
opening the door to adducing evidence of what was actually going on in their  
minds, still less to making inferences about it": para. 33. It is well-established  
that the Blackmore Rule does not allow courts to consider the subjective  
intentions of the parties…  
[137] As the B.C. Court of Appeal explained in 1001790 BC Ltd. v. 0996530 BC  
Ltd., 2021 BCCA 321, surrounding circumstances are considered where there is  
some ambiguity:  
[42]  
What the parties indicated to the outside world is to be determined  
within the four corners of the contract itself. What either party subjectively  
understood or misunderstood is irrelevant in the absence of fraud or  
misrepresentation (see, for instance, Shaw Production Way Holdings Inc v  
Sunvault Energy, Inc, 2018 BCSC 926 at paras 139 et seq, aff’d 2019 BCCA  
72). Where there is some ambiguity in the terms, the court may have regard  
to the surrounding circumstances, but these must never be allowed to  
overwhelm the words of the agreement. The interpretation of a written  
contract “must always be grounded in the text and read in the light of the  
entire contract”: see Sattva at para 57.  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 44  
[138] The existence of an entire agreementclausesuch as was in place here—  
does not undermine the search for objective intent and does not override any need  
to consider the surrounding circumstances or factual matrix evidence: IFP  
Technologies (Canada) Inc. v EnCana Midstream and Marketing, 2017 ABCA 157 at  
para. 124 (“IFP Technologies”). As the court explained in this case:  
[124] The mere existence of an “entire agreement” provision does not mean  
that the words chosen beyond that entire agreement provision admit of one  
interpretation only. The purpose of considering the surrounding  
circumstances is not to add to, contradict or vary the terms of the agreement  
but rather use them as an interpretive aid to determine the meaning of the  
words in dispute. Where parties have concluded an agreement and a court is  
left to sort out the parties’ objective intentions, it cannot be prevented from  
considering the surrounding circumstances by a provision that is itself based  
on the assumption that the agreement is clear when it is not.  
[139] This case also engages a consideration of how agreements that are  
negotiated together should be interpreted. As the court explained in Samson Cree  
Nation v. O’Reilly & Associés, 2014 ABCA 268 at para. 82, “[w]here… the same  
parties make two or more contracts at the same time on the same or related topics,  
the court interprets them together, not in isolation.” Moreover, the contracts “are to  
be interpreted, if possible, to make the parts work harmoniously to achieve the  
overall goal, not to make the parts clash”: Samson Cree Nation at para. 82.  
V.  
ANALYSIS  
A. Did Cardero Breach the JVA by Abandoning the Freehold Lease?  
1. The Nature of the Alleged Breach  
[140] It should be noted that PRP does not argue that Cardero’s decision to  
surrender the Freehold was a breach of the Lease. This was a reasonable  
concession given the clear language of Article 23.1 of the Lease. However, CCP  
argues that Cardero breached the JVA by:  
a) abandoning a property outside the scope of the JVA’s abandonment clause  
Article 5.10;  
b) failing to maintain the Lease in good standing contrary to Article 8.2(b); and  
     
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 45  
c) failing to hold the Lease “in trust for the benefit of the Carbon Creek Joint  
Venture for so long as the Carbon Creek Joint Venture remains in effect”,  
contrary to Article 4.13.  
2. The Language of the Abandonment Clause  
[141] As in any contract case, it is important to start with the words of the  
agreement. Cardero relies on the fact that it had the right under Article 5.10 of the  
JVA to abandon “any of the Coal Tenures comprised in the Premises”.  
[142] The definition of a “Coal Tenure” in the JVA is very broad, being “a coal  
licence, coal lease or other form of tenure to a coal property.” The definition of  
“Premises” under the JVA expressly includes “Coalhunter’s interest in the Carbon  
Creek Coal Lease once granted by the Peace River Partnership”.  
[143] Hence, on the face of the Abandonment Clause alone, the Freehold clearly  
fits within the scope of properties that could be abandoned. However, the  
Partnerships argue that, when viewed within the broader context of the other JVA  
terms, as well as with a consideration of the surrounding circumstances, the  
Abandonment Clause should be interpreted to exclude the Freehold.  
3. The Alleged Restriction of the Right to Abandon to the Area of  
Interest  
[144] The Partnerships rely on the placement of the Abandonment Clause within  
the JVA. In particular, the Partnerships argue that the preceding clauses make it  
clear that the right to abandon was intended to apply only to the Area of Interest,  
relying on the fact that Article 5.8 discusses the acquisition of interests within the  
Area of Interest.  
[145] I find that this argument is flawed for a number of reasons:  
a) There is nothing in Article 5.10 that makes it subject to, or controlled by,  
Article 5.8.  
b) The clause between the two noted articles, Article 5.9, deals with a range of  
properties “deemed to form part of the Premises”, which expressly includes  
   
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 46  
“the interest of Coalhunter in the Carbon Creek Coal Lease, if and when  
granted to Coalhunter by the Peace River Partnership”. Hence, if anything, an  
argument based on clause placement alone would suggest that Article 5.10  
would be controlled more by Article 5.9 than the more distant Article 5.8.  
c) Section 5, in which Article 5.10 is contained, refers broadly to the  
“Relationship of the Parties” and deals with a variety of matters not restricted  
to the Area of Interest. Headings in a contract are part of the language  
chosen by the parties and can inform the interpretation of the provisions that  
follow, provided the wording of the contract is not inconsistent with such an  
interpretation: Neely v. MacDonald, 2014 ONCA 874 at para. 11. See also:  
Yongfeng Holdings Inc. v. Zheng, 2019 BCSC 1534 at para. 104; Meszaros v.  
Hendry, Swinton, McKenzie Insurance Services (Westshore) Inc., 2015  
BCSC 1423 at para. 211.  
d) If anything, the fact that Article 5.8 refers to the “Area of Interest”, but Article  
5.10 makes the choice to use the separate and broader term “Premises”,  
suggests that this distinction mattered.  
4. The Effect of the Trust Provisions  
[146] Next, CCP argues that Article 4.13 of the JVA prohibits abandonment by  
requiring that the Freehold remain in trust. However, Article 4.13 states only that  
Cardero holds “the interest of Coalhunter therein” in trust for the Joint Venture. It  
imposes no obligation on Cardero to maintain its interest in any specific Coal  
Tenure. Rather, where Cardero has a present interest, then that interest is held in  
trust for the Joint Venture.  
[147] Further, interpreting the contract as a whole, it would be a strange thing for  
one clause to negate a right expressly provided by another clause, unless such was  
expressly set out. The JVA’s terms illustrate that its drafters were well aware of the  
usual mechanism for making one clause subject to another (see e.g., Articles 5.4,  
5.5, 5.7, and 5.8). But the authors did not make Article 5.10 subject to Article 4.13.  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 47  
[148] CCP also argues that Article 5.10 could not apply to the Freehold because  
the alleged trust obligation in Article 4.13 is: “obligations or liabilities theretofore  
accrued”, which is expressly excluded from the operation of Article 5.10. However, I  
find that this quoted language from the final sentence of Article 5.10 applies to a  
tenure that has already been abandoned. The identified “obligations or liabilities”  
must be those tied to abandoned property. This sentence cannot have been  
intended to invalidate the initial abandonment itself. This interpretation is consistent  
with the fact that the sentence uses verbs in the past tense (e.g., “abandoned or  
transferred”), signalling that those acts have already taken place when the parties  
carry on to assess the residual and related “obligations and liabilities theretofore  
accrued. In other words, what is maintained is other obligations and liabilities  
related to abandoned property, not the property itself.  
[149] This interpretation does not negate the need for, or the force of, the trust  
language in Articles 4.10-4.13. These provisions were obviously required given that  
certain property interests were going to be held in the name of one party to the Joint  
Venture and not the other. In such circumstances, it makes sense to ensure that the  
other party’s interests are protected in relation to the property held for the Joint  
Venture. Article 5.10 then deals with how property can be removed from the  
properties held by the Joint Venture. Once a property is properly removed, there is  
no purpose to be served by the trust obligations. The removed property then comes  
under the exclusive control of the party who ends up with ownership, here being the  
Partnerships. There is no residual trust obligation controlling either the Partnerships  
or Cardero in relation to abandoned property  
5. The Guidance Provided by the Lease  
[150] The Partnerships argued that the JVA should be read in conjunction with the  
Lease. In their final argument, they state “[i]n June of 2010, PRP, CCP and  
Coalhunter, entered into three intertwined agreements: the JVA, the Coal Lease  
Option Agreement and, ultimately, the Carbon Creek Coal Lease.” As noted above,  
where the same parties make two contracts relating to the same subject matter, the  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 48  
court should interpret them together and, to the extent possible, in a manner which  
allows the two contracts to operate harmoniously.  
[151] In terms of the interaction between the agreements, CCP asserts that [b]y  
design, the surrender of the Coal Lease triggered defaults under the JVA.”.  
[152] I find that it would be very problematic to have an act expressly sanctioned by  
one agreement to constitute a breach of a related agreement. That would be an  
unusual and flawed design rendering harmonious interpretation impossible. I do not  
agree that this is an objectively reasonable interpretation of the agreements when  
read together.  
[153] Article 5.6 of the Lease confirms that there was no obligation on Cardero’s  
part to mine the Freehold. However, many of the Partnershipsarguments make this  
express right not to mine illusory. The Partnerships’ arguments make it difficult to  
see how Cardero could have satisfied its obligations under the JVA without moving  
forward with a mine. Indeed, the Partnerships assert as follows in their final  
argument:  
Once Cardero exercised the option to enter into the Coal Lease, it was  
obligated to meet the deadline for Commercial Production by June 15, 2017.  
This meant that it was committed to build a mine on the Freehold Lands.  
[154] The Partnerships suggest that the only proper option for Cardero, if it no  
longer wanted to proceed with a mine on the Freehold, was to withdraw from the  
JVA completely for $1.00 under Article11.1. However, for the reasons expressed  
above and below, I do not accept that this was the only alternative available to  
Cardero in these circumstances. The JVA contemplates that some, but not all, of the  
Coal Tenures might be kept within the Joint Venture while allowing the abandonment  
of others. A single property abandonment did not require complete withdrawal from  
the JVA.  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 49  
6. The Effect of the Witness Testimony  
[155] Moving out from the written agreements to a broader review of the  
surrounding circumstances, the Partnerships seek to rely on Mr. Horan and Mr.  
Hunter’s testimony. Specifically, the Partnerships rely on:  
a) Mr. Horan and Mr. Hunter’s stated intention in their preparation of the trust  
clauses to ensure that all of the properties, including the Freehold, were kept  
together. They explained that splitting up the lands would concern investors,  
since they were properly and best treated as one deposit and one mine.  
b) Mr. Hunter’s testimony that, if the Lease were ever surrendered, the  
relationship would be broken, Cardero would have to give back the lands to  
Burns, and Cardero would only be entitled to receive fair value.  
c) Mr. Hunter’s testimony that the right to abandon was only put in the  
agreements to allow Coalhunter to avoid having to mine and process inferior  
coal within the Area of Interest.  
[156] There are several problems with these arguments:  
a) They do not reflect the plain meaning of the language of the agreements.  
b) I have not found the presence of an ambiguity that would drive a need to  
consider surrounding circumstances.  
c) The arguments run contrary to the principle that the subjective intentions of  
the parties are not relevant when objectively interpreting a contract: Leemhuis  
v. Kardash Plumbing Ltd., 2020 BCCA 99 at para. 15.  
d) The Partnerships’ interpretation could result in a situation where a Coal  
Tenure could cease to be managed as part of the JVA (given the exercise of  
the Manager’s right to abandon), but the Co-Owner would remain bound to  
hold that same Coal Tenure in trust for the Joint Venture. I agree with  
Cardero that it is illogical to require a Co-Owner to hold a Coal Tenure in trust  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 50  
for the benefit of the Joint Venture in circumstances where that Coal Tenure  
no longer forms part of the Joint Venture.  
e) If it were so vital that the Freehold be and remain part of the Joint Venture,  
why did the negotiating parties allow for:  
i.  
the possibility that it would not be included as part of the Joint  
Venture through the use of the “if and when” language in Article  
4.13, and  
ii.  
the provision of the option in the original Coal Lease Option  
Agreement?  
[157] The partnerships did not just rely on the testimony of witnesses who testified  
at trial, but also on the absence of testimony from certain potential witnesses. CCP  
argued that an adverse inference should be drawn from the fact that Cardero did not  
call Mr. van Alphen or Angus Christie, former Chief Operating Officer of Cardero. Mr.  
Christie authored the JDS Report relied upon by Cardero to justify the surrender of  
the Coal Lease. Mr. Christie was also present at the March 2014 meeting.  
[158] However, as the Court of Appeal explained in Rohl v. British Columbia  
(Superintendent of Motor Vehicles), 2018 BCCA 316, whether to draw an adverse  
inference based on a failure to call a witness is within the discretion of the judge:  
para. 4. I decline to draw such an inference. While the exercise of this discretion  
may be called for where a party fails to call a witness who “in the circumstances  
would be expected to favour the party and the witness would have knowledge of the  
facts in dispute”, the identified witnesses do not warrant such a finding: Rohl at  
para. 1. Cardero was able to advance all of its arguments based on the wording of  
the relevant agreements rather than having to resort to calling further evidence of  
the parties’ intentions. Accordingly, evidence from the above-noted individuals was  
not necessary to advance Cardero’s case, and Cardero should not be punished for  
deciding not to offer their testimony.  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 51  
7. The Duty of Good Faith and the Duties of the Manager Generally  
[159] CCP argues that Cardero violated its duty of good faith in the context of the  
exercise of any discretion it held to abandon, relying on the principles set out in  
Wastech Services Ltd. v. Greater Vancouver Sewerage and Drainage District, 2021  
SCC 7 at paras. 63, 69-71.  
[160] I find no breach of any such duty. Cardero, as Manager, was entitled to  
assess the viability of proceeding with the Freehold. Cardero could assess the  
situation globally. Viewed globally, Cardero reasonably determined that it was going  
to be virtually impossible to secure financing for a project that required that  
production occur within a timeline that any objective observer would understand was  
unrealistic, and where substantial Advance Royalty Payments were coming due. Mr.  
Akers’ report supports this conclusion.  
[161] CCP argued that Cardero, as Manager, could not act exclusively in the  
interests of Cardero. While that may be correct, Cardero was also not obligated to  
disregard the challenges facing the Project as a wholeof which the inability to  
secure additional financing was a large component. This Project was going to  
require hundreds of millions in financing. If the terms of the Lease were standing in  
the way of securing financingwhich the evidence suggests was the case, at least  
in partthen this was a legitimate reason for the Manager to consider whether it  
was wise to hold onto the Freehold.  
[162] Lack of available funds may not have qualified as force majeure, but that  
does not mean that the Manager could not consider economic pressures as a  
reason to exercise its discretion to abandon a particular Coal Tenure. Clearly, a  
decision on abandonment would almost always be made on grounds of financial  
viability. Indeed, it is difficult to understand why the abandonment right would be  
exercised other than by reason of the Manager determining that a particular Coal  
Tenure was no longer a financially beneficial component of the Project.  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 52  
[163] It is true that hard economic times did not excuse the non-performance of the  
JVA, but Cardero was only purporting to exercise a right that was contained within  
the JVA.  
[164] The Partnerships suggest that the decision to abandon was unsupportable,  
as the Project remained economically viable with the Freehold. CCP notes that, in  
the April 17, 2014 letter, Mr. van Alphen indicated that, even with coal prices at the  
lows experienced in early 2014, the NPV of Cardero’s Interest was $200 million USD  
(using an 8% discount rate), and CCP and PRP’s interests would have had a  
combined NPV of $168 million USD. CCP argues that, as part of a Project with a  
global positive NPV of $368 million USD, the Lease was not an uneconomic or a  
“useless” Coal Tenure.  
[165] I find that this argument disregards the economic reality facing such coal  
mining exploration efforts. Like other high-risk endeavours, the hope is that the gains  
on certain projects outstrip the losses on other projects. As such, gains on the  
winners have to be high in order to offset losses on the (more frequent) losers. I  
accept Mr. Henderson’s evidence that, given this reality, a rate of return in the range  
of 20-30% needed to be projected in order to interest financiers. By the time the  
abandonment right was exercised, the reality was that the projected rate of return  
was far below 20-30%. The reported lack of response to Mr. Henderson’s  
fundraising efforts is evidence of that reality. Cardero’s decision is supported by Mr.  
Akersevidence of how a reasonable and prudent miner would act in the  
circumstances.  
[166] It is important to put oneself in the shoes of the Manager at the relevant time.  
The Lease provided that, if Cardero did not achieve production on the Freehold by  
June 2017, PRP would have been entitled to terminate the Lease to the Freehold.  
But it was not possible, or indeed prudent, for the Joint Venture to meet that timeline.  
No agreement could be reached on pushing this date back. Absent such an  
amendment, the Manager had to treat this as a real deadline. However, since the  
deadline was clearly unachievable, any further expenditures in respect of the  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 53  
Freehold stood to be wasted. As Manager, these were all legitimate factors for  
Cardero to consider.  
[167] The Manager was required to act “for the Co-Owners as tenants in common”.  
That did not require the Manager to ignore all necessary inflows and outflows. It did  
not allow the Manager to consider only Cardero’s interests, but nor did it require the  
Manager to consider only CCP’s interest. The Partnerships’ arguments come close  
to a suggestion of the latter: if CCP could still make money if a mine was built, then  
the Manager had to keep the Freehold and build a mine. But that is not the proper  
test to be applied to the Manager’s conduct.  
8. The Effect of the Subsequent Increase in the Benchmark Price  
[168] The Partnerships note that the price of coal started to increase from 2016  
onwards, and that Mr. Akers admitted that the Project would be financeable at the  
present benchmark price. However, Cardero as Manager was dealing with the  
economic reality in 2014. At the time, prices were extremely low, and financing was  
generally unavailable.  
[169] The Partnerships’ argument on this point asks the court to examine the  
Manager’s decision with the benefit of hindsight. If it was known with some certainty  
that the price of coal was going to rebound, as it has done, financiers would  
presumably have been beating down Cardero’s door to fund the Project. But the  
financiers did not know the future, nor did anyone else. Nor should the court assess  
Cardero’s conduct with the benefit of such hindsight.  
9. The Lack of a PEA  
[170] The Partnerships suggest that a prudent mine operator would have  
conducted a PEA on the residual Coal Tenures prior to relinquishing the Freehold.  
However, based on the information before me, I do not see that a PEA would have  
changed the economic reality faced by the Manager. It simply did not make  
economic sense to maintain the Freehold given the terms of the Lease and  
prevailing economic conditions.  
   
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 54  
10. The Lack of a Viable Path Forward After Abandonment  
[171] The Partnerships argue that the Manager’s decision to abandon was  
improper because what remained within the Joint Venture was not viable. They rely  
on Mr. Farmer’s analysis in this respect.  
[172] I disagree. After shedding the deadlines and Advanced Royalty Payments  
obligations associated with the Lease, the Joint Venture still controlled Coal Tenures  
that could eventually have resulted in a viablethough smallerProject, if and  
when coal prices recovered. Although the Ministry’s establishment of protected  
areas in 2016 and 2019 undercut such viability, there is no evidence that the  
intention to protect certain of these lands was known to Cardero when the  
abandonment right was exercised.  
11. The Failure to Maintain the Lease in Good Standing  
[173] The Partnerships argue that Cardero breached the JVA by not keeping the  
Lease in good standing, as required by Article 8.2(b) of the JVA. This clause  
requires the Manager to maintain the Coal Tenures free of any liens and to take the  
necessary steps to maintain them in good standing. I find that it does not impose an  
obligation on the Manager to maintain all Coal Tenures. Again, such an obligation  
would be difficult to rationalize with Article 5.10, which expressly permits  
abandonment. If the obligation to “maintain [the Premises] in good standing” meant  
that Cardero could not abandon properties, then it would largely render the  
Abandonment Clause meaninglessa result that should be avoided: British  
Columbia (Attorney General) v. Malik, 2009 BCCA 202 at para. 32.  
[174] I agree with Cardero that it did not breach of the JVA by failing to make the  
payments necessary to keep the Lease in good standing. The Lease was no longer  
part of the Joint Venture as a result of the surrender. Any Advance Royalty  
Payments were owing under the Lease, not the JVA. The JVA does not provide that  
a breach of the Lease is automatically a breach of the JVA.  
   
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 55  
12. Failure to Obtain Management Committee Approval  
[175] The Partnerships allege that Cardero should have obtained Management  
Committee approval before the abandonment, pursuant to Article 8.2. I disagree. I  
find that the introductory language of Article 8.2 was not intended to suggest that the  
Manager could not make decisions without advanced approval. Rather, the  
Management Committee had discretionary power to direct and control the Manager.  
However, the Management Committee took no steps to exercise this discretion in  
relation to the abandonment. Perhaps CCP could have brought forward a motion to  
the Management Committee preventing the exercise of the abandonment right, but it  
did not do so. The reason for this is obvious, and also has the practical effect of  
undermining the argument: CCP only controlled 25% of the votes on the committee.  
CCP simply could not compel its desired result.  
[176] The Partnerships also argue that the Manager acted inconsistently with  
“laws”, contrary to its obligation under Article 8.2, given that:  
a) “laws” is defined to include the Lease;  
b) Article 31.1 of the Lease prohibits Coalhunter from assigning its interest in  
the Lease without the consent of PRP, which consent may be arbitrarily  
withheld;  
c) as the abandonment clause requires the Manager to offer to transfer the Coal  
Lease as a precondition to abandonment, the Manager required the consent  
of PRP in order to proceed with abandonment; and  
d) Cardero did not seek PRP’s consent, nor would such consent have been  
forthcoming.  
[177] I find that characterizing the abandonment as an “assignment” simply  
because the terms required a Co-Owner to offer its rights in the abandoned property  
to the other is a tortured interpretation. Article 31.1 was clearly intended to apply to a  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 56  
true assignment to another party, not to negate the express internal right to  
surrender and abandon.  
13. Other Alleged Breaches by Cardero  
[178] Although not the focus of submissions at trial, CCP did plead certain other  
miscellaneous breaches of the JVA.  
[179] CCP pleads that Cardero breached the JVA by delegating certain duties as  
Manager through CDU’s plan of arrangement in 2015. However, the JVA did not  
prohibit Cardero from subcontracting functions to CDU. Cardero remained legally  
responsible to make sure that any such obligations were fulfilled. Furthermore, the  
key individuals carrying out its management services did not change.  
[180] Similarly, CCP’s claim that Cardero had no or insufficient staff, expertise, or  
resources, must fail. There was insufficient evidence to support this plea.  
13. Conclusion on Cardero’s Alleged Breach of the JVA  
[181] I find that CCP has not established any breach of the JVA by Cardero.  
B. Did Cardero Breach the Lease?  
[182] As noted, the Partnerships do not allege that the surrender of the Lease itself  
was a breach of the Lease. However, they allege that Cardero breached the Lease  
by failing to pay the Advance Royalty Payments owing.  
[183] Pursuant to the Amending Agreement, the first Advance Royalty Payment of  
$500,000 was due on June 2, 2013 and the second payment of $2 million was due  
on June 2, 2014.  
[184] Pursuant to Article 4.2(3)(i) of the Lease, PRP agreed to “accept payment of  
the amount due on the following terms and conditions”:  
all or any portion of the Advance Royalty due on June 2, 2013, such payment  
may be extended by Cardero Coal by notice in writing to Peace River  
Partnership given not less than 15 days prior to June 2, 2013, to anytime  
between June 2, 2013 and June 2, 2014….  
     
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 57  
[185] The commercial context for these amendments to the Lease was that  
Cardero could not fulfil its obligation to obtain the necessary permits and approvals  
by June 15, 2013, which would otherwise have enabled PRP to terminate the Lease.  
In return for PRP waiving this requirement, Cardero agreed to make the Advance  
Royalty Payments.  
[186] Cardero delivered its Notice of Surrender on April 30, 2014, which purported  
to be effective May 30, 2014. I analyze the effectiveness of this notice below. In this  
section, I assume that notice was effective. With that assumption, the effect of the  
surrender was to terminate the Lease. So what becomes of the promised Advance  
Royalty Payments in this scenario?  
[187] One might have expected this situation to be governed by Article 24.1, which  
provides that, on termination, Cardero remains liable for any Royalty, Minimum  
Royalty, taxes rates and assessments then “due and unpaid with respect to the  
Lands”. However:  
a) Minimum Royaltyis defined as including the payments owing under Article  
4.1. But the Amending Agreement provides for the new Advance Royalty  
Payments through the operation of a new Article 4.2; and  
b) Royaltyis defined by reference to Article 3.1, which refers only to the royalty  
payable on production.  
[188] This suggests to me that there may have been a drafting oversight, in that  
when the amendments were drafted, the parties neglected to tie this new type of  
royalty to the treatment of the other royalty types.  
[189] That said, this possible drafting oversight is of minimal consequence. The  
mere fact that the Advance Royalty Payments were not included in Article 24.1 does  
not mean that PRP was left without a legal remedy for a breach of any obligation to  
pay such royalties. I find that the $500,000 was owing under general contract  
principles of contract, if not pursuant to Article 24.1 specifically.  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 58  
[190] The Lease was terminated on May 31, 2014. I find that this decision did not  
have the effect of negating any accrued or vested rights held by PRP as of that date.  
I agree with PRP that the first $500,000 Advance Royalty Payment was already due  
as of that date. It was just the payment thereof that had been deferred.  
[191] The most reasonable interpretation of the Lease is that obligations that had  
already accrued must be paid. There is a distinction in the Amending Agreement  
between the underlying indebtedness obligation, which is the date on which such  
obligation accrues, and the date by which payment must be made: Videocon Global  
Ltd v. Goldman Sachs International, [2016] EWCA Civ 130 at para. 53. This  
distinction between “due” and “payable” has been recognized in Canadian decisions:  
Canada (Attorney General) v. Reliance Insurance Co. (2008), 40 B.L.R. (4th) 204  
(Ont. Sup. Ct. J.). at para. 33. British Columbia courts have defined “debt” similarly.  
In Coast Capital Savings Credit Union v. British Columbia, 2011 BCCA 20, the court  
held that “debt” includes “a sum of money which is certainly, and at all events,  
payable without regard to the fact whether it be payable now or at a future time”:  
para. 57. Indeed, Cardero’s General Counsel, Mr. Talbot, appears to have  
understood that it was only the “payment” that was being deferred, not the “due”  
date. When he returned the executed Amending Agreement on May 31, 2013, Mr.  
Talbot served notice of Cardero’s election “to defer the payment of the CAD  
$500,000 Advance Royalty Payment due June 2, 2013 until June 2, 2014, and will  
therefore commence to pay 6% interest thereon…” (emphasis added). Cardero  
could not avoid its accrued obligation simply by surrendering the Freehold before the  
extended payment date. Looking to the surrounding circumstances, PRP provided  
the extension to ease Cardero’s cash flow problems, not to give Cardero the power  
to negate its accrued obligations.  
[192] However, this same analysis also drives the necessary conclusion that  
Cardero had no obligation to make the next $2 million Advance Royalty Payment, as  
that obligation was not “due” as of the surrender date of May 31, 2014. Rather, this  
payment only became due on June 1, 2014.  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 59  
[193] PRP argued that the surrender was not effective until it acknowledged the  
surrender by letter dated July 17, 2014. Article 23.1 does not require that PRP  
acknowledge a surrender in order for it to become effective. Rather, the Lease  
simply provides that Cardero may “at any time, upon giving [PRP]… prior written  
notice… surrender all of its right, title and interest” in the identified lands. In my view,  
the plain meaning of this provision is that the only condition necessary to give effect  
to the surrender is notice is given in writing. Were that not the case, the Partnerships  
could have withheld their acknowledgment through to the due dates of future  
Advance Royalty Payments, which would make no sense. Under such an  
interpretation, Cardero’s right to surrender lands under the Lease would only be  
effectively exercisable at the discretion of the Partnerships. In my view, this would  
render Cardero’s right to surrender illusory at best.  
[194] Likewise, I find that the doctrine of repudiation has no purchase here. As  
discussed above and below, the Surrender Notice was effective, so there was no  
repudiation of the Lease by Cardero.  
C. Did Cardero Breach a Fiduciary Duty?  
[195] While this theory was not advanced with any vigour in their final argument,  
fiduciary duty is raised in the Partnerships’ pleadings. So, to the extent that there  
was no breach of the JVA per se, was there at least a breach of a separate fiduciary  
duty obligation? I say not. Article 5.2 of the JVA specifically disclaimed the existence  
of any fiduciary duty as between the Co-Owners, as does Article 33.12 of the Lease.  
Furthermore, Cardero and CCP were sophisticated commercial parties engaged in  
an arm’s length commercial transaction. Rarely do courts impose superadded  
fiduciary duties in this context: Litwin Construction (1973) Ltd. v. Pan (1988), 29  
B.C.L.R. (2d) 88 (C.A.) at 104.  
[196] In addition, Article 5.11 of the JVA confirmed that the Manager was an  
“independent contractor” and not an agent of the joint venturers. Article 8.1  
addressed the duties required of the Manager in detail and imposed obligations to  
take “necessary or appropriate” steps in a “sound and miner like manner.” The  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 60  
standard of care established by the JVA is not a fiduciary standard. There is no  
discussion in the JVA or the Lease of Cardero assuming a duty to act in the best  
interests of the Partnerships: Alberta v. Elder Advocates of Alberta Society, 2011  
SCC 24 at paras. 30-32.  
[197] Given that the parties are sophisticated, arm’s-length entities with relatively  
equal bargaining power and who negotiated their respective rights and  
responsibilities under the JVA, there is no basis to superimpose additional fiduciary  
obligations: Cadbury Schweppes Inc. v. FBI Foods Ltd., [1999] 1 S.C.R. 142 at para.  
30; Canada Southern Petroleum Ltd. v. Amoco Canada Petroleum Co., 2001 ABQB  
803 at paras. 197-214; Litwin Construction (1973) Ltd. at 104; Visagie v. TVX Gold  
Inc. (2000), 187 D.L.R. (4th) 193 (Ont. C.A.) at paras. 25-30.  
[198] It is true that Articles 4.10 through 4.13 of the JVA impose certain trust  
obligations, but I have already concluded above that these limited terms did not  
prevent abandonment.  
[199] Finally, even if Cardero owed fiduciary duties to CCP, abandonment of the  
Lease would not constitute a breach of those duties, particularly given that the Lease  
and the JVA expressly authorized the surrender of the Lease and abandonment of  
any Coal Tenure.  
D. Did CCP Breach the JVA?  
[200] I find that CCP breached the JVA by refusing to provide written confirmation  
of Cardero’s authority to deal with the Ministry in respect of various coal tenures,  
refusing to follow Management Committee decisions, and asserting it would no  
longer cooperate with the Joint Venture operations generally.  
[201] Mr. Horan effectively sought to use CCP’s cooperation under the JVA as  
leverage to help secure the $500,000 Advance Royalty Payment under the Lease.  
However, that was the wrong tool for the job. The fact that Cardero had breached  
the Lease with PRP did not give CCP the right to breach the JVA with Cardero.  
Rather PRP could or should have pursued its remedies under the Lease. In the  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 61  
meantime, there was still an active Joint Venture that needed to be managed in  
relation to the properties beyond the Freehold.  
[202] Put another way, the end of the Lease with PRP did not give CCP the right to  
walk away from its responsibilities under the JVA.  
[203] CCP’s obligations under the JVA may have been limited, but they were real,  
and they were breached.  
[204] Article 21.1 sets out CCP’s obligation to do all things and promptly execute all  
documents as necessary, and specifically obligates CCP to fully cooperate in  
applying for all government approvals and permits. Despite this contractual  
obligation, in October 2014, Mr. Horan advised that CCP would not cooperate or  
sign anything. Specifically, Mr. Horan refused to provide a letter to the Ministry  
authorizing Cardero, as Manager, to deal with government authorities to convert  
pending coal licence applications into coal licences. According to Mr. Henderson’s  
evidence, which I find was credible, this letter was needed to maximize the  
prospects that the licences for drilling would be granted. Only CCP could effectively  
provide the necessary assurance as to CCP’s position. CCP’s failure to cooperate in  
providing this letter was a breach of Article 21.1 of the JVA.  
[205] While it may have been possible for the Manager to secure Ministry approvals  
without the letter from CCP, the evidence suggests it would have been easier with  
CCP’s direct communication. To the extent that CCP suggests that Mr. Henderson’s  
evidence about the request for a CCP letter should be viewed with “extreme  
skepticism”, I reject that suggestion. I accept Mr. Henderson’s evidence. His conduct  
subsequent to that alleged Ministry advice is consistent with such a communication  
having been received from the Ministry. If Mr. Henderson could have sent the letter  
himself, he presumably would have. I cannot find that Mr. Henderson was engaged  
in “three-dimensional chess”, in terms of setting up the potential for a later breach  
allegation against CCP, and for no other purpose. Indeed, any such “set up” would  
have been rendered completely ineffective if Mr. Horan had simply signed his name  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 62  
to the proposed letter. If it was all an effort to entrap CCP in a breach, it was very  
poorly designed, as the scheme would have fallen apart with one stroke of a pen.  
[206] I find that CCP also breached the requirement in Article 6.11(a) that the  
parties abide by decisions of the Management Committee. At the September 2014  
Management Committee meeting, various action items were assigned to CCP.  
However, CCP failed to take steps to address many of the tasks assigned to it. In  
particular, CCP failed to:  
a) review the insurance binder provided and either provide comments or, if  
acceptable, sign an acknowledgement;  
b) review and provide comments on the proposed amending agreement  
concerning Cardero’s accounting responsibilities and, once approved,  
execute the agreed form of amending agreement;  
c) review and provide comments on the proposed form of Management  
Committee resolution dealing with the financial reporting schedule and once  
approved, execute the agreed form of resolution; and  
d) provide a letter acknowledging the potential existence of three core sheds on  
the Freehold and confirm the Joint Venture’s ownership of same.  
[207] I note that CCP refused to attend or participate in any Management  
Committee meetings after September 16, 2014, but CCP had an obligation to “do  
and provide all acts and thingsas shall be necessary or appropriate in connection  
with the performance of this Agreement.” I find that its decision to stop cooperating  
with its Joint Venture partner was a breach of this obligation. It was not “appropriate”  
to hinder the conduct of the Joint Venture through such a complete lack of  
cooperation and engagement.  
[208] CCP failed to cure its defaults within 60 days of receiving Cardero’s August  
24, 2015 notice of default (assuming this notice was effective, which is addressed  
below).  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 63  
[209] CCP says it was not obligated to do any of the things set forth in the notice,  
given that three of the alleged defaults were cured by unanimous vote at the  
subsequent November 2015 Management Committee meeting, and the Manager  
was authorized by CCP to cure the last item pursuant the approved work plan.  
[210] However, I find that the fact that the Management Committee and the  
Manager were simply making the best of a bad situationby trying to keep the Joint  
Venture moving forward notwithstanding CCP’s failure to cooperate. These efforts  
do not negate or cure CCP’s breaches of the JVA. Further, these limited mitigatory  
steps did not change the overarching difficulty that CCP had declared itself unwilling  
to participate in Joint Venture business generally. This changed the fundamental  
character of the relationship.  
[211] CCP took a gamble in attempting to exercise its relatively limited leverage  
under the JVA by refusing to cooperate in order to achieve results it sought under  
the Lease (i.e., immediate payment of the Advance Royalty Payments, or a possible  
unwinding of the surrender). CCP then “doubled down” on this gamble by declining  
to cure its relatively minor breaches once it was put on notice of same. It lost both  
rolls of the dice and must now face the consequences of those losses.  
[212] The fact that CCP’s breaches were relatively minor in the broader context of  
the Project’s development does not change the analysis. Article 12.1 of the JVA  
does not distinguish between major and minor breachesrather it refers to a breach  
of “any obligation”. If there is a breach, the other party has to give notice and provide  
an opportunity to cure before any other rights are triggered. As such, the parties  
effectively managed the prospect of minor breaches by providing for the opportunity  
to cure such breaches. Presumably, in the normal course, once notified of a minor  
breach, the defaulting party would see the wisdom of simply curing the failing rather  
than risking further remedies being sought against it. But that is not what occurred  
here.  
[213] While the operation of Article 12.1 arguably leads to somewhat severe  
outcomes, the parties’ agency in designing the effect of any breach through the  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 64  
terms of the JVA must be respected. Furthermore, it should be noted that the  
otherwise harsh effect of Article 12.1 is muted by the fact that the breaching party is  
still given a right to compensation for their interest in the JVA notwithstanding their  
breach.  
E. Notice Issues  
1. Was Cardero’s Surrender Notice Under the Lease Effective?  
[214] The Partnerships argue that Cardero’s Surrender Notice was ineffective  
because it failed to surrender all of Cardero’s right, title, and interest in all of the  
lands.  
[215] The Partnerships also argue that, in order to be effective, a notice of  
termination must be clear, unambiguous and unconditional. Notices of termination  
under a lease must be strictly construed and effected in strict compliance with their  
provisionsa termination notice which contains conditions is ineffective: Arnold v.  
2261324 Manitoba Ltd., [1995] 1 W.W.R. 305 at paras. 30-36 (Man. C.A.).  
[216] The Partnerships argue that the Surrender Notice was conditional and  
therefore ineffective.  
[217] I do not accept these arguments:  
a) The Surrender Notice covered the entirety of the lands covered by the Lease.  
b) The mere fact that the letter also outlined a path whereby Cardero was  
prepared to agree to new terms under which its valid surrender would no  
longer be operative does not mean that the Surrender Notice was ineffective.  
c) Absent a new agreement between the parties, the Surrender Notice would  
have its intended legal force.  
d) The Lease was always subject to possible amendment by the parties. It had  
been amended on one prior occasion. But on this point, the Partnerships  
declined to agree to new terms sought by Cardero, and vice versa.  
   
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 65  
e) The parties conducted themselves as though the Surrender Notice was  
effective thereafter. For example, in the draft letter attached to their July 27,  
2015 correspondence, the Partnerships state, “[a]s you are aware, Cardero  
terminated the Lease effective May 30, 2014”.  
[218] I find that Cardero’s Surrender Notice was effective.  
2. Was Cardero’s August 24, 2015 Letter Effective Notice under the JVA?  
[219] The Partnerships also assert that Cardero’s August 24, 2015 letter providing  
notice of default under the JVA was ineffective because it was styled as a “without  
prejudice” communication.  
[220] However, where notice is given pursuant to and in compliance with a  
contractual obligation to give notice before taking further steps, the mere presence  
of the words “without prejudice” will not necessarily vitiate the effect of the notice:  
312630 British Columbia Ltd. v. Alta Surety Co. (1995), 10 B.C.L.R. (3d) 84 at paras.  
7-9 (C.A.). The test for settlement privilege requires that:  
a) a litigious dispute must be in existence or within contemplation;  
b) the communication must be made with the express or implied intention that it  
would not be disclosed to the court in the event negotiations failed; and  
c) the purpose of the communication must be to attempt to affect a settlement:  
Cowichan Tribes v. Canada (Attorney General), 2020 BCSC 1507 at para. 74.  
[221] I find that the August 24, 2015 letter is not protected by settlement privilege  
given the absence of a settlement offer. No litigation was pending at this time and, if  
the defaults had been cured, no litigation would have been necessary. Cardero was  
unambiguously enforcing its legal rights without proposing a settlement or  
concession. The following extracts from the letter highlight this point:  
VARIOUS ALLEGATIONS OF BREACH BY CARDERO COAL  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 66  
We continue to believe that none of the issues raised in your correspondence  
of July 27, or in your correspondence of August 12, or in your e-mail of  
August 21, have merit.  
[…]  
It is out view that the termination of the Coal Lease by the Manager was  
carried out in full compliance with both the Coal Lease and the JV  
Agreement, does not otherwise offend the JV Agreement and therefore  
cannot be a breach of the JV Agreement. The question of remedies  
therefor[e] becomes moot. Our position as previously stated continues to be  
the case.  
[…]  
BREACH OF THE JOINT VENTURE BY CARBON CREEK PARTNERSHIP  
We find that we must raise certain breaches of the JV Agreement by Carbon  
Creek Partnership. In this regard we refer to you to section 4.8 and 5.4 of the  
JV Agreement… as well as Section 21.1…  
[…]  
NEXT STEPS  
In accordance with Section 12.1(a) of the JV Agreement, we hereby provide  
notices of a breach to Carbon Creek Partnership and require that such  
defaults be cured on or before October 23, 2015, failing which it is  
acknowledged that Cardero Coal as the non-defaulting partner, shall have the  
right pursuant to 12.1€ of the JV Agreement to acquire the Interest of the  
Carbon Creek Partnership, which Mr. Kopple is very much interested in  
considering.  
[222] The only language that could arguably be read as raising the potential for  
settlement is the following paragraph:  
We continue to be of the view that it would be useful for the parties to meet to  
discuss the Carbon Creek Joint Venture together with Mr. Kopple who is an  
invaluable component to our operation. We agree that it is not in any of the  
parties’ interest to maintain the status quo for the reasons outlined above.  
[223] I do not view this paragraph as undermining the provision of contractual  
notice. Recall that there was a 60-day period for CCP to remedy its defaults. As  
such, there remained a real possibility that the Joint Venture would continue past 60  
days, and it was at least going to subsist for the next 60 days. There is nothing  
inappropriate about encouraging further discussion during this period. Such  
encouragement did not undermine the clear position taken in the first part of the  
letter.  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 67  
[224] Further, even if any part of the notice were somehow subject to settlement  
privilege, which is not the case, that portion may be severed and redacted from the  
portion effecting notice under to Article 12.1(a) of the JVA: Kenton Farm Corp. v. J  
and N Steel Builders Co. (1990), 71 Man. R. (2d) 229 (Q.B.) at para. 5. I find that  
this would be an appropriate case to make such a redaction if required.  
3. Was CCP’s July 27, 2015 Letter Effective Notice under the JVA?  
[225] My analysis of this particular issue is obiter, as I have already concluded that  
there was no breach of the JVA by Cardero for which notice needed to be given. In  
the event that my conclusion on Cardero’s breach of the JVA is wrong, I set out my  
findings on this point in the alternative.  
[226] The notices attached to Mr. Horan’s July 27, 2015 letter were expressly  
identified as “drafts”. Further, the cover letter stated “[w]e thought you and Mr.  
Kopp[le] might be interested in discussing these matters on a without prejudice basis  
before we delivered these letters to you” (emphasis added). Given that the cover  
letter itself treated the drafts as not having yet been “delivered”, it is difficult to see  
how they could be treated as proper notice under the JVA. Mr. Horan confirmed that  
final signed copies of these drafts were never delivered, despite the passing of the  
July 29, 2015 deadline set out in the letter.  
[227] In Pioneer Hi-Bred International, Inc. v. Richardson International Limited,  
2010 MBQB 161 at para. 58, the court stated:  
Notice need be clear and concise as its time period for termination has  
started as of a given letter. Such clarity should leave no doubt in the mind of  
the other party of the possible and expected consequences of non-  
compliance.  
[228] Given the qualified language in the cover letter, it cannot be said that the July  
27, 2015 letter qualified as a “clear and concise” notice that the time period for  
termination had started.  
[229] I find that the first effective notice of CCP’s claim of breach under the JVA  
was its January 18, 2016 letter and the filing of the JVA Action that same day.  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 68  
[230] Cardero argues that CCP’s delay in providing notice under the JVA means  
that CCP is estopped from raising any JVA breaches. It is to that issue I turn next.  
4. Is CCP Estopped from Raising Breaches of the JVA or the Lease as a  
Result of its Delay Providing Notice  
[231] Insofar as this estoppel issue relates to any claim for breach of the JVA by  
Cardero, the following analysis is also obiter. However, it is also arguably material to  
the claim for breach of the Lease.  
[232] In Hongkong Bank of Canada v. Watson (1993), 89 B.C.L.R. (2d) 71 (C.A.),  
the Court of Appeal held that a default notice must be issued within a reasonable  
period of time, which time depends on the circumstances of the case: para. 21. In  
finding that the notice was reasonable in the circumstances of that case, the Court of  
Appeal considered whether the debtor suffered any prejudice by not having prior  
notice of the default. See also: Kingdom Construction Limited v. Regional  
Municipality of Niagara, 2018 ONSC 29 at paras.115-116.  
[233] The principle of estoppel is a flexible concept. Its purpose is to avoid  
unconscionable results. It is based on the principle that when parties to a transaction  
have proceeded on the basis of an underlying assumption on which they have  
conducted their dealings, neither will be allowed to go back on that assumption when  
it would be unfair or unjust to do so: Erickson v. Jones, 2008 BCCA 379 at para. 57.  
[234] Estoppel by convention arises where: (a) the parties’ dealings are based on a  
shared assumption of fact or law; (b) where a party conducts itself in reliance on that  
shared assumption resulting in a change of its position; and (c) it would be unjust or  
unfair to allow one of the parties to resile or depart from the common assumption:  
Ryan v. Moore, 2005 SCC 38 at para. 59.  
[235] Estoppel by representation will be found where:  
a) a representation or conduct amounting to a representation intended to induce  
a course of conduct on the part of a person to whom the representation is  
made;  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 69  
b) an act or omission resulting from the representation, whether actual or by  
conduct, by the person to whom the representation is made; and  
c) there is detriment to such person as a consequence of the act or omission  
Costco Wholesale Canada Inc. v. Cazalet, 2008 BCSC 952 at para. 28.  
[236] For estoppel by misrepresentation to operate, the parties must be of “a like  
mind” at the material time, and this is not so if the nature of the assumption is in  
doubt: Grasshopper Solar Corporation v. Independent Electricity System Operator,  
2020 ONCA 499 at para. 56.  
[237] I find that there is no notice delivery or estoppel problem preventing PRP from  
advancing its claim for Advanced Royalty Payments under the Lease. This was  
simply a demand “in the default of payment”. There is no issue of Cardero being  
deprived of an earlier opportunity to cure. Even if one treats the filing of the Lease  
Action as their first formal demand under the Lease, Cardero nonetheless failed to  
cure within 30 days. Further, there is no indication that Cardero would have cured  
earlier had it been given the opportunity to do so.  
[238] Recall that PRP is not challenging the surrender itself. In relation to the  
Advance Royalty Payments, there is no doubt that Cardero was already well aware  
of PRP’s position on the $500,000.  
[239] In these circumstances, I find that the provision of notice of PRP’s claim  
under the Lease was not so delayed that it cannot be enforced as the result of  
estoppel.  
[240] Turning to CCP’s claim for breach of the JVA, it is understandable why an  
agreement would grant the non-defaulting party some time to issue notice. The non-  
defaulting party’s options in the event of a default may present onerous obligations.  
Accordingly, the non-defaulting party may wish to see how matters develop prior to  
exercising these rights. In this case, for example, it is clear why CCP may have  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 70  
wanted to take some time to see how matters developed after any default occurred  
before electing to move forward with the right to buy-out Cardero’s interest.  
[241] Mr. Horan waited to issue CCP’s notice of default under the JVA because he  
says he was originally unsure as to CCP’s legal right. He also wanted to negotiate  
with Mr. Kopple to see if the Joint Venture could be salvaged. These reasons for  
delay were reasonable and understandable: Le Soleil Hotel & Suites Ltd. v. Le Soleil  
Management Inc., 2009 BCSC 1303 at para. 421.  
[242] Mr. Horan advised Mr. Henderson that he believed Cardero was in default of  
the JVA on June 17, 2014 and October 15, 2014. He also sent draft default notices  
on July 27, 2015. There can be little doubt that Cardero understood that CCP’s  
position was that Cardero was in breach of the JVA prior to January 18, 2016.  
[243] It is difficult to apply the relevant legal test in the absence of a finding of  
specific breaches of the JVA by Cardero against which the test can be applied.  
However, notwithstanding that difficulty, I find that Cardero has not established a  
basis for an estoppel plea against CCP, even assuming any alleged breaches had  
been made out:  
a) Mr. Horan never made a positive statement that could reasonably be  
interpreted as an intention on the part of CCP to not pursue its rights under  
the JVA.  
b) There is no evidence of a shared understanding that CCP would not advance  
a claim under the JVA. Indeed, CCP’s decision to stop cooperating was a  
clear signal that CCP viewed the JVA as having been breached.  
c) There was sufficient evidence as to CCP’s concerns about the JVA, such that  
Cardero could not reasonably assume that no action would be brought.  
d) There is little evidence of Cardero having acted to its detriment based upon  
CCP’s alleged express or implied representation that JVA claims would not  
be pursued. There is no evidence that Cardero would have sought to “un-  
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 71  
surrender the lease” or “un-abandon the Freehold” had CCP sought a remedy  
under the JVA at an earlier date. Cardero never changed its legal position. In  
March 2014, it took the position that it was entitled to surrender the Coal  
Lease, not make the Advance Royalty Payments, and carry on with the Joint  
Venture over the remaining lands. That remained its position from that point  
onward and is still its position today.  
e) The work that was done by Cardero on the Joint Venture during the relevant  
period was not particularly extensive and presumably added value that could  
still be recaptured by Cardero through the Article 12.1 buyout process.  
[244] In these circumstances, there is no unfairness or injustice in allowing the  
Partnerships to continue with its claim for breach of the JVA and Lease.  
[245] The waiver argument would fall for the same reason, but also fails because  
Article 3.3 of the JVA required that any waiver be in writing.  
F. Remedy and Damages  
[246] As a result of Cardero’s breach of the Lease, I find that PRP is entitled to an  
award of $500,000 plus contractual interest. PRP is also entitled to an award for any  
“Losses” incurred as a result of this breach. Subject to my direction on costs below, I  
direct that any necessary residual determination of the amount of such additional  
“Losses” be referred to the Registrar for assessment and certification.  
[247] As a result of CCP’s breaches of the JVA, I confirm that Cardero’s election  
under Article 12.1 was effective, and that it is thus entitled to purchase CCP’s  
remaining interest in the Joint Venture pursuant to process set out in Article 12.1(e)  
of the JVA. Cardero is also entitled to an award for any “Losses” incurred as a result  
of the identified breaches. Again, subject to my direction on costs below, I direct that  
any necessary residual determination of the amount of any such “Losses” be  
referred to the Registrar for assessment and certification.  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 72  
[248] Given my findings above, it is not necessary to determine what remedies  
would have been available to CCP had I found a breach of the JVA by Cardero.  
Absent a finding of specific breaches, it is impossible and impractical to determine  
what damages would have arisen from undetermined breaches.  
[249] Given that I have not found a breach of Cardero’s obligations under the JVA,  
it is also unnecessary to consider:  
a) Cardero’s alternative argument that any breach of its duty as Manager does  
not entitle CCP to invoke the buyout remedy under Article 12.1; or  
b) Cardero’s alternative argument that CCP failed to mitigate its losses.  
VI.  
CONCLUSION  
[250] PRP is entitled to judgment in the Lease Action, as set out above.  
[251] Cardero is entitled to judgment in the JVA Action, as set out above.  
[252] All other claims in both actions are dismissed.  
[253] In relation to costs, if the parties are unable to agree on same within 30 days,  
they may file written submissions on the following schedule:  
a) Cardero’s Submission: written submissions of 20 pages or less may be filed  
within 60 days of this judgment;  
b) Partnerships’ Response: written submissions of 20 pages or less within 30  
days of receipt of the Cardero Submission; and  
c) Cardero’s Reply: written submissions of 5 pages or less within 15 days of  
receipt of the Partnerships’ Response.  
[254] The submissions on costs may include any argument the parties wish to  
make on the proper interaction of the appropriate costs award with each parties’  
 
Cardero Coal Ltd. v. Carbon Creek Partnership  
Page 73  
potential entitlement to solicitor and own client fee “Losses” pursuant to their  
respective breaches of the agreements.  
______________________________________  
The Honourable Mr. Justice Branch  


© 2022 IncJournal is not affiliated with or endorsed by the U.S. Securities and Exchange Commission