Centura Building Systems (2013) Ltd. v. 601 Main Partnership
Page 25
[80] Change Orders #6r2 ($1,782), #7 ($172), #8r1 ($822), #9 ($162), #18r1
($383), #33 ($1,653), and #51 ($4,762) were the subject of site instructions. The
defendants ultimately conceded that Centura is owed a total of $9,736 with respect
to those, before consideration of any deficiencies. The only issue with respect to
these concerned #6r2. Mr. King expressed the view that Centura was entitled to the
full amount of that Change Order ($11,136) but Centura’s evidence was that the
work was only 16% complete at the time the Contract was terminated. In the
circumstances, I have attributed a value of $1,782 to Change Order #6r2 (16% of
$11,136).
[81] Change Orders #12r2 (-$11,293), #14r1 ($7,116), #15r1 ($1,616), #16r1
($787), #20r1 ($11,403), #21r1 ($484), #23r1 ($890), #24r1 ($3,550), #35 ($303),
#37 ($2,187), #39 ($1,416), #40 ($1,786), #41r1 ($1,355), and #50 ($3,262) were
the subject of extra work conformation forms approved by Mr. Brezovski on site. The
defendants ultimately conceded that Centura is owed a total of $24,862 with respect
to those, before consideration of any deficiencies.
[82] Change Orders #27r2 ($19,960), #28r1 ($3,843), #29r1 ($993), #31r1
($2,864), and #34r1 ($1,367) were the subject of contemporaneous email
exchanges. The defendants ultimately conceded that Centura is owed a total of
$29,027 with respect to those, before consideration of any deficiencies.
[83] The Change Orders in dispute are #10r1, #13r2, #17r2, #19r2, #22r2, #25r2,
#26r1, #30r1, #36, #38, #42, #43, #44, #45, #46, #47, #48, #49, #52, #53, and #54.
[84] Change Order #10r1 concerned the replacement of hollow steel framing with
regular steel framing. The amount claimed is $4,967. An extra work confirmation
form was prepared by Centura and contemporaneously approved by Mr. Brezovski.
There is no dispute that the work was done. Mr. King opined that there was too
much time spent on the work and he valued it at only $2,607. However,
Mr. Brezovski testified that when he signed the extra work confirmation form he
considered the number of hours quoted to be appropriate. Mr. Brezovski was the
Icon representative with the most direct involvement in the work on the Project as it