Page: 97
a view to "prepar[ing] [him] for the questions that will be asked for
clarification";
(
(
f)
on February 8, 2011, Sheegl and Armik exchanged calls wherein Armik
gave Sheegl ”the approximate numbers so you have it in advance of the
meeting"; Armik reported to Richard that Sheegl just wanted the CAJV to
"
take over this project to bring it home". The Phase 1 contract was
awarded to the CAJV two days later;
g)
on February 17, 2011, Sheegl told Armik that he would get approval for
$126 million but that he wanted "2+2 for sam and phil". On July 20, Sheegl
was delegated the authority to award the GMP contract. Two days later,
Armik's company Mountain paid Sheegl's company FSS $200,000. The
GMP contract, which was signed by Sheegl as CAO, was awarded to Caspian
in the amount of $137.1 million on November 18, 2011. Despite the
size of the contract, no competitive bids were ever sought and indeed,
the City never sought tenders from any other contractors;
(
h)
on March 19, 2011, after Armik expressed concerns about AECOM, Sheegl
requested a meeting with theCity legal department "as I think wemay have
an out”, a phrase which Sheegl acknowledged meant a way to get out of
the AECOM contract;
(
(
i)
j)
on May 1, 2011, Sheegl directed that there be a ''full stop on payments [to
AECOM] until we meet with them";
on May 4, 2011, after Armik expressed concerns about the City's project
director Aziz, Sheegl promised to get a contract for Armik's handpicked
consultant Abouzeid. In February 2012, Sheegl as CAO awarded a single•
source contract to Abouzeid's company Dunmore - the contract was
backdated to June 1, 2011. At one point, on June 29, 2011, Sheegl
threatened to use his authority as CAO to terminate Aziz's employment.
By September 2011, Aziz had been forced out of his role as City Project
Manager;
(
k)
l)
on June 23, 2011, after Armik requested it, Sheegl contacted the City's
legal department to "ensure everything is in order" with respect to the
assignment of the Phase 1 contract to Caspian alone. As requested by
Armik to Sheegl on June 6, the assignment agreement, signed by Sheegl
as CAO, ultimately included a clause whereby the City released Akman
Construction from the obligations under its bond;
(
(
on July 5, 2011, Sheegl requested through Armik that Abouzeid, the City's
new Project Manager, make a recommendation to the City of $150 million.
He did so. Ultimately, the City increased its budget from $127.167 million
to $155 million on July 20, 2011;
m) on September 30, 2011, after Armik told Sheegl to put AECOM on notice
and let him install a different design team and, indeed, went so far as to