Page: 103
[619] As previously discussed, Metcalfe prepared a document dated May 19, 2012, in which he
listed a breakdown of the construction costs associated with the Lock-up Contract, as well as a
list of extras and or upgrades again relating to the Lock-Up Contract: Exhibit 1-I-31. The May
2012, budget prepared by Carm, Exhibit 1-I-21, included a list of actual and anticipated upgrades
based on the May 19, 2012, Metcalfe document, including the sum of $20,725 for “plumbing
upgrades above original fixture list”. Again, as previously discussed, Ms. Swanby conceded
during cross-examination that these documents were presented to her at some point and she
failed to raise any concerns with Metcalfe regarding any of the items on the list.
[620] Generally speaking, the onus is on the contractor to ensure that the customer either
requested or approved the “extra”. In this instance, I find that the Plaintiffs were aware from the
outset of their discussions with Metcalfe that the base price set out in the initial quote, Exhibit 1-
C-2, as well as in the Lock-Up contract, I-C-5, covered basic fixtures only. Both documents
contemplated that customer preferences would be accommodated as “extras”. As of May 19,
2012, the Plaintiffs were also aware from Metcalfe’s list of extras and upgrades that he estimated
a cost of $20,725 for plumbing fixture upgrades. This same number was carried forward into
Carm’s May 21, 2012, detailed budget prepared for the Plaintiffs. Given this knowledge, I am
satisfied that the Plaintiffs were well aware that their selection of plumbing fixtures over and
above basic fixtures would result in an “extra” for which they would be financially responsible.
[621] For the foregoing reasons, I find that the plumbing extras of $15,824.95, is properly
characterized as an “extra” for which the Plaintiffs are responsible. However, the replacement of
the broken window, $390.24, is not “extras” for which the Defendants can seek compensation
from the Plaintiffs. The other items on the invoice totaling $1,162.50 are properly characterized
as “extras” for which the Plaintiffs are responsible.
[622] Finally, the Plaintiffs refer to Invoice #133. Exhibit 1-C-15, that lists a charge of $16,274
for “Electrical as per detail supplied by Eagle Electric”. An explanatory note states that Tru-
Square has “paid some of extras so check (sic) needs to be made out to Tru-Square Homes.” In
his direct examination, Metcalfe testified that everything listed on this invoice related to “extras”
that were not part of the original contract.
[623] There is no dispute that Tru-Square never paid Eagle Electric the $10,500 then owing at
the time Dueck walked off the job prior to completion of the electrical work. Dueck testified that
he left the job site on account of the non-payment of his account. Metcalfe’s evidence on this
point was that he intends to pay Eagle Electric once he receives payment from the Plaintiffs. This
amount is, accordingly, included in his counterclaim. Metcalfe described these extras as light
fixtures but provided no details in his trial evidence.
[624] Of this amount, the Plaintiffs say that $10,000 was never paid by Tru-Square or by them.
The Plaintiffs maintain that this contractor has never made a claim for this unpaid work.
According to the Plaintiffs, the remaining $3,400 covers work that was never actually done.
Accordingly, the Plaintiffs contend that these amounts are not owing to the Defendants and are
not recoverable as “extras.” Invoice #133 was never paid by the Plaintiffs.
[625] Counsel have not directed me to any evidence that demonstrates that the Plaintiffs ever
approved any of these electrical “extras”. The Plaintiffs take the position that they did not. The
evidence of Dueck and his invoice, Exhibit 7, certainly suggest that all of this work was
completed. As noted above, Metcalfe was clear that at all of the amounts covered in Invoice
#133 involved “extras”.