Court of Queens Bench of Alberta  
Citation: Swanby v Tru-Square Homes Ltd, 2022 ABQB 215  
Date: 20220318  
Docket: 1301 10836  
Registry: Calgary  
Between:  
Craig Swanby and Georgina Swanby  
Plaintiffs  
(Defendants by Counterclaim)  
- and -  
Tru-Square Homes Ltd. and James Frederick Metcalfe  
Defendants  
(Plaintiffs by Counterclaim)  
_______________________________________________________  
Reasons for Decision  
of the  
Honourable Mr. Justice M. David Gates  
_______________________________________________________  
Table of Contents  
I. Introduction and Overview...................................................................................................... 3  
II.  
Facts.................................................................................................................................. 6  
Issues .............................................................................................................................. 12  
Evidence ......................................................................................................................... 13  
III.  
IV.  
A. James Metcalfe ............................................................................................................. 13  
B. The Plaintiff’s Experts.................................................................................................. 14  
1.  
2.  
3.  
David Matthews.................................................................................................... 14  
Dana Bjornson ...................................................................................................... 14  
Cameron Kraychy................................................................................................. 15  
Page: 2  
C. The Defendants’ Expert................................................................................................ 15  
V.  
Analysis .......................................................................................................................... 17  
A. Concurrent Liability in Contract and Tort .................................................................... 17  
B. Liability in Contract...................................................................................................... 18  
1.  
2.  
3.  
The Lock-Up Contract .......................................................................................... 19  
Was the Lock-Up Contract Amended or Varied?................................................. 22  
Breach of Contract ................................................................................................ 29  
C. Liability in Tort............................................................................................................. 30  
D. The Deficiencies ........................................................................................................... 31  
1.  
2.  
3.  
4.  
5.  
6.  
7.  
8.  
9.  
The Foundation..................................................................................................... 32  
The Leaking Windows.......................................................................................... 33  
Bonus Room.......................................................................................................... 40  
The Garage............................................................................................................ 44  
Door Threshold Cut-Outs ..................................................................................... 45  
Interior Electrical .................................................................................................. 46  
Foundation, Framing and Nail Floor Wall Connection ........................................ 47  
Kitchen Floor ........................................................................................................ 49  
Walk-Out Header.................................................................................................. 51  
10. Missing Point Load............................................................................................... 52  
11. Sound Proof Insulation ......................................................................................... 53  
12. Roof....................................................................................................................... 54  
13. Main Attic Insulation ............................................................................................ 58  
14. Deck ...................................................................................................................... 61  
15. Stucco.................................................................................................................... 66  
16. Stone Work ........................................................................................................... 69  
17. Building Envelope, Eaves & Soffits..................................................................... 71  
18. Exterior Decorative Beams................................................................................... 72  
19. Mechanical Room & Plumbing ............................................................................ 73  
20. Other Deficiencies Identified by Bjornson ........................................................... 74  
E. Other Possible Breaches................................................................................................. 74  
1.  
2.  
Metcalfe’s Lack of Involvement in the Project..................................................... 74  
Failure to Keep the Plaintiffs Informed ................................................................ 74  
Page: 3  
F. Application of Liability in Contract ............................................................................... 75  
G. Application of Liability in Tort .................................................................................... 75  
1.  
2.  
3.  
4.  
Inherently Dangerous Work.................................................................................. 76  
Fraud ..................................................................................................................... 78  
Piercing the Corporate Veil .................................................................................. 81  
Inducing Breach of Contract................................................................................. 91  
H. Alberta New Home Warranty Program (“ANHWP”) .................................................. 93  
Damages ......................................................................................................................... 95  
A. Quantification of Damages ........................................................................................... 95  
VI.  
1.  
2.  
3.  
4.  
Contract Price to Lock Up .................................................................................... 98  
Extras and Upgrades ............................................................................................. 99  
Amount Paid to Tru-Square................................................................................ 105  
Amounts Paid to TGC for Remediation Work ................................................... 105  
B. Consequential Damages.............................................................................................. 111  
C. Non-Pecuinary General Damages............................................................................... 113  
D. Punitive Damages ....................................................................................................... 115  
E. Aggravated Damages.................................................................................................... 122  
F. Contributory Negligence .............................................................................................. 123  
G. Mitigation of Damages ............................................................................................... 125  
H. Improvement............................................................................................................... 129  
VII.  
Counterclaim ................................................................................................................ 130  
VIII.  
IX.  
X.  
Conclusion.................................................................................................................... 130  
Costs ............................................................................................................................. 130  
Pre-Judgment Interest................................................................................................... 131  
I. Introduction and Overview  
[1]  
The Plaintiffs, Georgina Swanby (“Ms. Swanby”) and her husband, Craig Swanby (“Mr.  
Swanby”), seek damages from the Defendants, Tru-Square Homes Ltd (“Tru-Square”), and  
James Frederick Metcalfe (“Metcalfe”) relating to the construction of their home west of  
Carstairs, Alberta.  
 
Page: 4  
[2]  
The Plaintiffs filed a Statement of Claim on September 13, 2013 and an Amended  
Statement of Claim on March 12, 2014. In their Amended Statement of Claim, the Plaintiffs  
allege breach of contract and negligence on the part of the Defendants, citing multiple  
construction deficiencies, as well as material breaches of the construction contract and a failure  
to follow the building plans. Further, the Plaintiffs allege that the Defendants failed to meet the  
requirements of the Alberta Building Code (the “Code”) and employed methods and materials  
that were sub-standard so as to render the property uninhabitable.  
[3]  
The Plaintiffs maintain that the Defendantsconstruction deficiencies, and their failure to  
correct these deficiencies, amount to negligence. As such, the Plaintiffs say that the Defendants  
failed to meet the standards of a reasonably competent general contractor and home builder. In  
the alternative, the Plaintiffs contend that the Defendants’ actions constitute a breach of contract.  
[4]  
As more fully discussed below, the Plaintiffs maintain that Tru-Square and Metcalfe are  
legally indistinguishable and invite the Court to pierce the corporate veil.  
[5] Further, the Plaintiffs allege fraud on the part of the Defendants. Specifically, the  
Plaintiffs point to the Defendants’ concealment of construction deficiencies, misrepresentations  
as regards the state of the construction project and diversion of funds from the Plaintiffs’ project  
to another construction project underway at the same time (the West Highlands residence”), as  
amounting to fraud.  
[6]  
With respect to the West Highlands residence, the Plaintiffs seek pre-judgment injunctive  
relief, an order tracing the funds paid by the Plaintiffs to the Defendants, restitution of any funds  
that can be traced, an accounting and a declaration that the Plaintiffs hold an interest in the West  
Highlands residence.  
[7]  
In addition to damages for negligence and, alternatively, breach of contract, the Plaintiffs  
also seek aggravated damages for financial losses and increased costs incurred as a result of the  
actions of the Defendants. The Plaintiffs cite emotional upset, distress and a diminishment in  
their quality of life. Further, the Plaintiffs seek Punitive Damages as a result of the deliberate and  
fraudulent actions of the Defendants.  
[8]  
Finally, the Plaintiffs seek pre-judgment interest pursuant to the Judgment Interest Act,  
RSA 2000, c J-1, and costs on a solicitor-client basis.  
[9] The Defendants filed a Statement of Defence on April 17, 2014 and a Counterclaim on  
April 24, 2014. In their Statement of Defence, they deny any defects in their work and deny that  
they at any time attempted to deceive the Plaintiffs or to hide defects or deficiencies in the  
construction of the residence. The Defendants seek dismissal of the Plaintiffs’ action in its  
entirety, as well as costs. In their Counterclaim, the Defendants allege that they paid a total of  
$879,404.72 to suppliers of goods and services relative to the project. Further, the Defendants  
allege that they are owed not less than $450,000 pursuant to the construction contract for work  
completed. The Defendants state that this $450,000 includes lost profit for work that they were  
not able to complete after they were denied access to the property. They seek costs in relation to  
the Counterclaim.  
[10] The Defendants say that Metcalfe never had a contractual relationship with the Plaintiffs.  
Further, they maintain that the Plaintiffs have failed to establish any legal basis upon which the  
Court can find Metcalfe liable for any alleged negligence on the part of Tru-Square. The  
Defendants maintain that the Plaintiffs cannot prove the four required elements of fraud. They  
Page: 5  
also deny that any funds received from the Plaintiffs were directed to the construction of the  
West Highlands residence.  
[11] The Defendants contend that the work for which they are responsible is covered by the  
Alberta New Home Warranty Program (“ANHWP”) Single Family Residence Warranty  
Certificate that forms part of the contract between the parties. They say that all of their work is  
free of defects or structural defects as defined in the Warranty Certificate. The Defendants also  
maintain that the Plaintiffs are in default of the “Homeowner Obligations” set out in clause 4 of  
the Warranty Certificate. In this regard, the Defendants allege that the Plaintiffs are in breach of  
the Construction Agreement in commencing this action when some of the matters that form part  
of the Plaintiffs’ claim should have been referred to arbitration in accordance with the  
Arbitration Agreement.  
[12] The Defendants further contend that the Plaintiffs failed to mitigate any damages for  
which the Defendants may be liable and contributed to the damage to the residence.  
[13] The Plaintiffs filed a Defence to Counterclaim on June 20, 2014, in which, amongst other  
things, they denied owing $450,000 to the Defendants. The Plaintiffs maintain that the amount  
claimed in the Counterclaim relates to work that was never performed and is based on an invoice  
or invoices issued for the sole purpose of justifying the Counterclaim and set-off claimed by the  
Defendants. The Plaintiffs say that the work performed by the Defendants was deficient and not  
carried out in accordance with the requirements of the contract. Further, the Plaintiffs allege that  
the amount claimed in the Counterclaim represents over - or double-charging insofar as it  
includes invoices issued for progress payments, as well as for payments made directly to  
suppliers and sub-contractors. The Plaintiffs seek dismissal of the Counterclaim and costs on a  
solicitor-client basis.  
[14] Initially, this matter was heard from April 8-18, 2019, the time scheduled for the trial.  
However, significant additional time was required to complete the matter. The trial was  
continued on April 23-25, 2019, May 8-17, 2019, October 15-18, 2019, and November 27-28,  
2019. Instead of the 9 days originally scheduled, 26 days were required.  
[15] The Plaintiffs called seven witnesses, including themselves. Three expert witnesses were  
called to provide opinion evidence in relation to structural engineering, building envelope  
engineering, and the standard of care associated with the construction and remediation of custom  
residential homes.  
[16] The Defendants called nine witnesses, including one expert, Metcalfe and various trades  
who worked on the construction project. They also called a municipal building inspector, a  
representative of a supplier of framing materials, and the Plaintiffsdesigner, Shawn Carm.  
[17] At the conclusion of the evidence and oral argument on November 28, 2019, I reserved  
my decision. On September 30, 2021, counsel for the Plaintiffs supplied a 122-page written  
argument, combining their response argument to the Defendants’ oral submissions delivered on  
November 28, 2019 with the written argument that was to follow their own oral submissions  
delivered on November 27 and 28, 2019. Counsel for the Defendants filed a brief written  
response argument on October 8, 2021.  
[18] The Court wrote to counsel on February 7, 2022, seeking clarification on two matters.  
First, the parties were invited to respond to a question relating to Invoice 118. Second, the parties  
were invited to make further written submissions on the legal relationship, if any, between the  
Page: 6  
parties following the completion of the lock-up contract. The parties submitted further written  
submissions on February 18, 2022 and February 24, 2022, respectively.  
[19] These are my Reasons for Decision.  
II. Facts  
[20] The Plaintiffs have resided in the family home that is the subject of this litigation since  
August 2015. The home is located just west of Carstairs, Alberta. Previously, the Plaintiffs lived  
on Ms. Swanby’s family farm also located in the Carstairs region. The Plaintiffs operate a grain  
farm east of Carstairs.  
[21] Ms. Swanby completed Grade 12 and then qualified and worked as a hairstylist. During  
her career, she has owned, operated, and sold two businesses, a Telus Mobility store and a  
courier company.  
[22] Mr. Swanby is a power engineer, holding a certificate from SAIT obtained in 1991. For  
the past nine years, he has worked out of the country as an oilfields manager. At present, he  
works for Glencore on a 28-day on/28-day off rotation in Chad, Africa. As such, he spends a  
great deal of time outside of Canada. Mr. Swanby has no experience as a structural engineer and  
neither he nor Ms. Swanby has any background or experience in house construction.  
[23] Mr. Swanby gave evidence that he planned to pay for the construction of the residence,  
including the Plaintiffs’ initial mortgage, sometime in 2019, at which point he would terminate  
his overseas work commitments. As a result of the need to finance the remediation work and the  
other associated costs relating to the delayed completion of the project, he testified that he did  
not expect to be able to consider retirement for at least another ten years, approximately 2029.  
[24] The Plaintiffs acquired the land on which the home is built in 2009 or 2010. They were  
looking to move to a new location and searched for land that had either a mountain or coulee  
view. The planned home was to serve as a retirement home that could accommodate a  
wheelchair on an all-purpose ground floor, as well as a home for their then teenaged daughters.  
Their plans included a walk-out basement and multiple windows overlooking the view of the  
coulee. They had known for some time that they would build a home and had collected  
photographs from magazines over the years depicting house ideas that they wished to  
incorporate.  
[25] The Plaintiffs met Shawn Carm (“Carm”) at the Carstairs arena while attending a hockey  
game. They learned that Carm was a designer who had built some large, custom-built homes in  
the past. Carm told them that he “gets to do the pretty stuff,” but did not know how to do the  
other tasks associated with new home construction. The Plaintiffs liked Carm’s ideas.  
[26] Carm provided them with some home design ideas and introduced them in late 2010 to  
Gordon Snell (“Snell”), an architectural draftsman employed by Innographic Design and  
Drafting (“Innographic”). The Plaintiffs provided Snell with a rough sketch they had prepared  
(which no longer exists), together with magazine photographs gathered over the years. They  
discussed with Snell their interest in having stone on the bottom portion of the home’s exterior,  
as well as granite or concrete counter tops in the kitchen and stone around the stove. Snell told  
them that they would require a robust floor in the kitchen area to support these heavy building  
materials. Carm attended the last couple of meetings with Snell and assisted the Plaintiffs with  
 
Page: 7  
their design ideas, including the design of a large exterior deck to be incorporated into the plan,  
as well as interior beams and an interior staircase.  
[27] Snell produced a design for the Plaintiffshome based on the materials and input they  
provided. The drawings that he ultimately prepared for the Plaintiffs addressed this enhanced  
load requirement. Carm provided additional design ideas once the Plaintiffs received the  
drawings. Ms. Swanby recalled that the drawings were completed in mid to late 2010, though it  
could have been later. She identified Exhibit 1-A-1 as the drawings prepared by Snell, the final  
version of which was dated May 8, 2011. A few minor modifications were made to the drawings  
prior to the start of construction, but such modifications related only to the placement of doors.  
Snell told the Plaintiffs that he thought they should employ an Insulated Concrete Form (ICF)  
foundation for their planned home.  
[28] The Plaintiffs had no written agreement with either Carm or Snell for the work that they  
performed.  
[29] Carm proposed that the Plaintiffs engage a builder in Calgary with whom he had worked  
in the past. The Plaintiffs met this builder on two occasions. During their second meeting, the  
Calgary builder provided an oral estimate of approximately $1.4 million to build the home based  
on his review of the Snell drawings.  
[30] Mr. Swanby hoped to find a builder in their local area. In late 2010, the Plaintiffs  
approached Metcalfe to find out if he was interested in building the home. Metcalfe previously  
had built custom homes for Ms. Swanby’s brother, Mr. Swanby’s cousin and friends they knew  
in the area. Metcalfe was also the next-door neighbour of Ms. Swanby’s brother. The Plaintiffs  
were familiar with the Defendantswork as a home builder, having seen Tru-Square signs on  
homes in the Carstairs area. According to the Plaintiffs, Metcalfe had a great reputation in the  
Carstairs region.  
[31] When first contacted by telephone, Metcalfe indicated that he was looking to wind-up his  
construction business and was not really interested in taking on the project. He told them that he  
was about to go to Phoenix for the winter and had plans for a cross-Canada road trip with his  
wife the following year. In the spring of 2011, the Plaintiffs contacted Metcalfe again and asked  
if he would be interested in being their general contractor for the residence. While he was  
hesitant to take on the job due to his upcoming travel plans, he agreed to discuss it with his wife.  
He responded a short time later, indicating that he was possibly interested, but only in terms of  
construction to the lock-up stage given his upcoming holiday plans. Ms. Swanby understood that  
the lock-up stage included pouring the foundation, framing, and installation of doors and  
windows. Following a further meeting with the Plaintiffs, Metcalfe agreed to build the home to  
the lock-up stage.  
[32] Metcalfe was advised from the outset that the home was to be both a family home and the  
Swanbysplanned retirement home. He was shown the Snell drawing that included the interior  
beams, a very large exterior deck, and the requirement for a robust floor construction to support  
the stone and granite features in the kitchen. Metcalfe advised the Plaintiffs that this was the  
largest project he had ever built and that he probably would require a subcontractor to complete  
what he described as the complicated framing for the planned house.  
[33] Metcalfe provided the Plaintiffs with three separate quotes for the job. The initial quote  
was for $500,000 to complete construction to the lock-up stage. The second quote, dated July 6,  
Page: 8  
2011, for a total cost of $578,875.40, including GST, added interior drywall and exterior stucco  
to the contract price: Exhibit 1-C-2.  
[34] The Plaintiffs’ bank required a price quote for the entire cost of building the home,  
including all interior finishing. During an in-person meeting in early August 2011, Metcalfe  
provided a quote for the entire construction project. The written quote (Exhibit 1-C-3) is dated  
August 4, 2011 and totals $1,064,348.00. It sets out specified allowances to cover exterior and  
interior finishes. Metcalfe subsequently provided the Plaintiffs with a document dated August 21,  
2011 (Exhibit 1-C-20) that set out in great detail the projected costs to construct the entire  
residence. After listing a number of items totalling $352,251.00, he added the “part from Tru-  
Square Homes”, $659,510.00, for a total of $1,011,761.00.  
[35] Metcalfe expressed no reservations about his ability to follow the plan and construct the  
home. He told the Plaintiffs that he would fly back from Phoenix periodically to keep a handle  
on the job.  
[36] The parties signed three separate contracts at a sod farm near the location of the  
Plaintiffs’ recreational trailer on August 22, 2011. The meeting lasted approximately 40 minutes,  
during which time there was a discussion regarding Tru-Square’s obligation to meet Code  
requirements and to ensure that all trades on site would have insurance and WCB coverage.  
While the parties signed more than one contract at the time, there is no dispute that the  
agreement reached that day required the Defendants to build to the lock-up stage only, with  
framing to start in late September 2011 and completion to lock-up stage by early 2012.  
[37] The first contract, Exhibit #1-C-5, involved construction of the residence to the lock-up  
stage, including stucco and drywall, in the revised amount of $692,485.50.  
[38] A second contract was signed the same date for a total contract price of $1,011.760.00,  
plus GST of $50,588.00, for a total contract price of $1,062,348.00, Exhibit 1-C-6. That contract  
was for the construction of the residence to completion.  
[39] A third pre-printed form of contract, Exhibit 1-C-4, the ANHWP contract, was brought to  
the meeting by the Plaintiffs. This contract also covered the construction of the entire residence  
at a cost of $1,062,348.00.  
[40] The Plaintiffs obtained a building permit from the county. At the request of the county,  
they also obtained a geotechnical inspection (Exhibit 1-A-3) dated July 2011, prepared by Curtis  
Engineering Associates Ltd of Calgary. The report recommended the use of Type 50, Sulphate  
Resistant Portland Cement for the foundation due to the soil composition. A copy of the report  
was provided to Metcalfe.  
[41] The Plaintiffs retained Quality Dirt Works (“Quality”) to do excavation work and pour a  
concrete pad for a planned future workshop on the property. While James Quartz, the principal  
of Quality, was on site, Ms. Swanby suggested to Metcalfe that Quality undertake the excavation  
work for the property. Metcalfe, who was familiar with Quality’s work, agreed as Quality’s  
equipment was already on site. The Plaintiffs paid Quality’s invoice of $16,803.15 (Exhibit 4) as  
excavation was not part of the contract with Tru-Square.  
[42] As noted above, Snell recommended that the Plaintiffs use an ICF foundation for the  
residence. However, Metcalfe advised that he did not like ICF foundations and would never  
install one. He told the Plaintiffs that if they wanted him to build their home, they would have to  
accept a standard foundation. They agreed, though they told Metcalfe that he was required to  
Page: 9  
otherwise follow Snell’s plan. At one point, the Plaintiffs asked Metcalfe if any new drawings  
would be required in light of the change in foundation. Metcalfe indicated that no further  
drawings would be required and that any necessary adjustments could be made along the way.  
[43] Metcalfe also testified that Ms. Swanby was also opposed to ICF foundations. However,  
this was never put to her in cross examination. Moreover, there is nothing in her evidence to  
suggest that she had any experience with building foundations so as to afford her a basis upon  
which to form an opinion.  
[44] After the foundation was completed, Metcalfe told Ms. Swanby that it was a pretty good  
job and just a little off, but nothing that would affect anything. Later, Metcalfe told her that the  
framing was just a bit off because it was a difficult foundation due to all the jut-outs in the house  
design. He told her that there was nothing to be concerned about as it could be addressed during  
the framing. Ms. Swanby was not concerned by these comments and had full trust in Metcalfe.  
[45] During the framing process, Ms. Swanby spoke to John McEwen, the framer, on a regular  
basis. On one occasion, he told her that the foundation was “off” and that there were some issues  
with the framing. He also told her that Metcalfe was not being particularly helpful, that the  
trusses were not fitting on the foundation and that there was not enough material on site. He  
reported that he had to salvage some of the used cribbing material. According to Ms. Swanby,  
McEwen related that Metcalfe had provided the direction to use whatever material was available  
on site. When she subsequently asked Metcalfe about the issues that McEwen had raised,  
Metcalfe told her that the foundation was not quite square but that this was a common occurrence  
in construction and there were no issues at all in terms of the overall project.  
[46] Metcalfe was on site only occasionally during the framing process and generally not as  
frequently as the Plaintiffs had anticipated. During the summer of 2012, he went on his planned  
cross-Canada road trip. He was also frequently away on camping trips and trips to Saskatchewan.  
According to Ms. Swanby, a number of trips “popped up” and Metcalfe would advise of his  
planned absences. Prior to entering into the contract with the Defendants, the Plaintiffs were  
aware only of the planned cross-Canada road trip.  
[47] The Plaintiffs hired the Defendants to manage the various subtrades. Due to Metcalfe’s  
frequent absences, the project did not proceed as rapidly as expected. When issues arose during  
the construction, the Plaintiffs were left to try to reach Metcalfe to attempt to resolve them.  
[48] According to Ms. Swanby, the construction was progressing slowly and not in  
accordance with the schedule that had previously been provided. At one point, Metcalfe told her  
that some of the delay was on account of poor weather. He also reported that there were some  
issues with the trusses.  
[49] Ms. Swanby described in detail some of the specific problems that arose during the  
construction. Tiles were being installed in one of the bathrooms by Metcalfe’s brother, John.  
Ms. Swanby recalled that she and Carm stopped by the project while the tiling was taking place  
and raised concerns with the way some of the tiles were placed. John Metcalfe responded that he  
was doing the best he could. When the concerns were relayed to Metcalfe several days later, he  
told her that if they were going to be that picky they could find their own tiler. Shortly thereafter  
John Metcalfe’s tools and equipment disappeared from the job site and he never returned to  
finish the job. The Plaintiffs were then forced to go out and hire their own tiler to correct the  
Page: 10  
mistakes and finish the job. According to Ms. Swanby, Metcalfe’s general attitude towards the  
project changed after John Metcalfe walked off the job.  
[50] Metcalfe provided the name of his flooring supplier, Deerfoot Carpet, Ms. Swanby found  
the flooring she liked, but was told that it would be difficult to get due to labour problems in the  
USA. Metcalfe told her that she was going to have to outsource the product herself.  
[51] Metcalfe also advised Ms. Swanby that his supplier would not build the staircase set out  
in the design plans and that she would have to outsource the stairs. As a result, the Plaintiffs had  
to seek out, hire and pay their own tradesperson to rough in the staircase.  
[52] Metcalfe suggested his own painter for the interior painting. Ms. Swanby knew that this  
painter had done a poor job on her brother’s residence. When she suggested another painter,  
Metcalfe threw his hands up in the air and told her to find her own painter.  
[53] At one point, Metcalfe referred the Plaintiffs to his cabinet supplier in Red Deer who  
submitted a quote for the job. Carm suggested that they obtain other quotes from other suppliers.  
He wanted to bid on this part of the project himself as he had his own cabinetry company.  
[54] On May 23, 2013, several weeks prior to the scheduled possession date, Ms. Swanby was  
notified by the flooring subcontractor that water was leaking into the residence through the  
windows. The initial leak was detected in the main floor Great Room, as well as in the Bonus  
Room located over the garage. Ultimately, it was determined that all of the main floor windows  
and many of the second-floor windows leaked.  
[55] Metcalfe was advised of the leaking windows by Ms. Swanby that same day, but he did  
not attend the site to investigate the matter for several days. I accept Ms. Swanby’s evidence that  
when Metcalfe finally attended, he denied any responsibility for the problem. Rather, he blamed  
Carm for the leaking windows, citing his inset or recessed window installment specifications as  
the cause of the problem. Metcalfe refused to assist the Plaintiffs in investigating the cause and  
extent of the window leaks.  
[56] On May 29, 2013, Troy Snyder (“Snyder”), Director of Operations and President of  
Western Form Works, attended the residence at Carm’s request to inspect the leaking windows.  
Snyder had approximately 25 years of experience in residential and commercial construction and  
was, amongst other things, a project manager as well as a ticketed carpenter, log home builder,  
and excavator. Metcalfe was present during this inspection. Snyder subsequently issued a report  
(Exhibit 1-D-5) in which he noted, amongst other things, that the windows had not been installed  
in accordance with the specifications that Carm had previously provided to Metcalfe.  
[57] Snyder noted that it started to rain during the course of his visit and he observed water  
leaking through the soffits. He recommended that the roof be assessed to determine how water  
was getting into the soffit.  
[58] While Snyder had no recollection of the homeowners being present during his inspection,  
I accept Ms. Swanby’s evidence that she was present. I also accept her evidence that Snyder told  
Metcalfe to fix the windows, to which Metcalfe responded, “Not my responsibility”.  
[59] Metcalfe took no action to repair the windows or to offer up any possible solutions to  
remedy the problem in either the short-term or the long-term. Shortly thereafter, the Defendants  
left the construction site and never returned.  
Page: 11  
[60] As more fully described below, the Swanbys began to investigate the installation of the  
leaking windows commencing in July 2013. This led to the investigation of other construction  
deficiencies identified by the engineers and others hired by the Swanbys to assist them in  
uncovering the construction deficiencies and in recommending and executing the required  
demolition and remediation work.  
[61] Around July 17, 2013, Ms. Swanby personally served Metcalfe with a letter listing the  
deficiencies. By the terms of the letter, July 26, 2013, was set as the deadline for Metcalfe to  
address the leaking windows. The Swanbys’ then counsel sent a follow-up letter dated July 30,  
2013 (Exhibit 1-G-11) referring to earlier correspondence from the Defendants, apparently  
seeking access to the property to conduct an inspection. (The Defendantsearlier correspondence  
was not produced at trial.).  
[62] Metcalfe sent an email to Ms. Swanby on July 22, 2013 (Exhibit 1-G-15) outlining the  
mediation/arbitration processes associated with the ANHWP. He expressed his willingness to go  
to non-binding mediation if the Swanbys were prepared to agree. Failing agreement, Metcalfe  
advised that that “final option” would be for him to trigger the arbitration process. Metcalfe  
made no reference in this communication to any intention to address any of the deficiencies  
identified in Ms. Swanby’s July 17, 2013, correspondence.  
[63] Ms. Swanby responded to Metcalfe’s email on July 23, 2013 (Exhibit 1-G-10), advising  
that someone would be hired to repair the damage caused by the leaking windows if Metcalfe  
was not prepared to act. She expressed a willingness to attend mediation after the necessary  
repairs had been completed.  
[64] Ms. Swanby subsequently contacted the ANHWP and learned that the fact that the  
contract amounts owing to Tru-Square had not been paid in full, and that the Plaintiffs did not  
have possession of the home, meant that there was no building warranty in place. Ultimately, no  
mediation or arbitration ever took place.  
[65] Metcalfe’s failure to respond to the substantive concerns raised in their letters led the  
Swanbys to conclude that Tru-Square and Metcalfe had repudiated the contract.  
[66] In July 2013, the Swanbys hired Tamata’s General Contracting & Consulting (TGC),  
an experienced construction and remediation contractor, to begin the investigative and  
demolition work required to determine the nature and scope of the construction deficiencies.  
During his initial examination of the premises, TGC’s principal, Mike Juniper (“Juniper”), found  
water-damaged drywall in every room of the home. Juniper provided a written quote dated  
August 8, 2013, based on his understanding of the scope of work as of that date: Exhibit 1-F-3.  
At the time, he estimated that the total cost would be $19,140. On August 19, 2013, he provided  
a revised quote based on an enhanced scope of work in the amount of $41,701.80. He  
subsequently produced a detailed budget quote dated January 2014 (Exhibit 1-F-9) in which he  
estimated the total cost of all repairs to be $802,597.11. Juniper ultimately produced a detailed  
written report regarding his involvement in this matter: Exhibit 1-F-35. Juniper explained that the  
scope of work greatly expanded as a result of the testing and investigative work undertaken by  
the Plaintiffs and the two engineers hired to oversee the remediation process.  
[67] The Plaintiffs also retained Dana Bjornson (“Bjornson”), a building envelope engineer,  
and David Matthews (“Matthews”), a structural engineer, to assist them in investigating  
Page: 12  
suspected construction deficiencies. Both subsequently were called as expert witnesses during  
the trial.  
[68] As more fully set out below, Matthews concluded that there were numerous building  
Code deficiencies and failures to meet industry best practices in Tru-Square’s construction.  
[69] The Plaintiffs asked Bjornson to examine the condition of the building envelope,  
including if there were any deficiencies or Code deviations. Bjornson found that the building  
envelope was not properly constructed and required remediation. She concluded that there were  
numerous building Code deficiencies and failures to meet industry best practice in Tru-Square’s  
construction of the building envelope.  
[70] Remediation work did not begin until July or August 2014. This work was undertaken by  
Juniper and TGC, working closely with Bjornson and Matthews to correct the various  
deficiencies identified, and to ensure that the remediations were Code-compliant and met the  
custom homebuilding industry’s accepted standards of practice. Juniper’s involvement in the  
remediation process continued until approximately August 2015. The Plaintiffs finally took  
possession of the fully remediated residence in late August or early September 2015, more than  
two years after the initial occupancy date.  
III. Issues  
[71] Numerous issues, both factual and legal, arise in this matter:  
(a) Can the Defendants be concurrently liable in both contract and tort?  
(b) What were the terms of the parties’ contract?  
(c) Was the parties’ contract amended and, if so, what were the amended terms?  
(d) Did Tru-Square and/or Metcalfe have a duty of care to the Plaintiffs?  
(e) What were the deficiencies in the house as constructed?  
(f) Did the Defendants, or either of them, breach the contract with the Plaintiffs?  
(g) Are the Defendants, or either of them, liable to the Plaintiffs in tort?  
i. Was the Defendants’ work inherently dangerous?  
ii. Was Metcalfe’s conduct fraudulent?  
iii. Is it appropriate to pierce the corporate veil in this case?  
iv. Did Metcalfe induce Tru-Square to breach its contract?  
(h) Is the ANHWP’s dispute resolution process applicable?  
(i) What is the appropriate measure of the Plaintiffs’ damages?  
i. Are the Plaintiffs entitled to consequential damages?  
ii. Are the Plaintiffs entitled to non-pecuniary damages?  
iii. Are the Plaintiffs entitled to punitive damages?  
iv. Are the Plaintiffs entitled to aggravated damages?  
v. Was there contributory negligence by the Plaintiffs?  
vi. Did the Plaintiffs appropriately mitigate their damages?  
vii. Have the Plaintiffs benefitted from improvement?  
(j) Are the Defendants entitled to payment under their Counterclaim?  
 
Page: 13  
IV. Evidence  
[72] As will become clear later in these Reasons, my findings on the credibility and reliability  
of the witnesses, both lay and expert, has an impact on my subsequent determinations.  
A. James Metcalfe  
[73] According to the Plaintiffs, the Defendants’ case rests on Metcalfe’s testimony. They  
maintain that Metcalfe was not a credible or reliable witness and that the Court should approach  
his testimony with great caution. Due to his frequent and extended absences from the job site, the  
Plaintiffs say that Metcalfe cannot speak with any authority to the quality of the work of his  
subtrades. His evidence in this regard is entirely self-serving. The Plaintiffs further contend that  
Metcalfe’s failure to produce any contemporaneous notes, documents or photographs tracking  
the progress of the project negatively impacts the reliability of his evidence. In the result, the  
Plaintiffs argue that little or no weight should be given to his evidence.  
[74] In terms of his credibility, the Plaintiffs cite several instances where Metcalfe gave  
inconsistent, even contradictory, evidence during the trial. I would summarize some of these  
instances as follows:  
a) In the Statement of Defence, the Defendants conceded that Metcalfe was the general  
contractor for the project to the lock-up stage. He made the same admission during  
questioning. However, at trial, Metcalfe suggested that Carm was the general  
contractor. Later, in cross-examination, he was insistent that the Swanbys were their  
own general contractors. Further, Metcalfe swore an affidavit on April 18, 2016,  
deposing that he was not the general contractor. Finally, in his response to the Notice  
to Admit Facts, Metcalfe stated he was a “builder” and not a “general contractor”.  
b) In the Agreed Statement of Facts, Exhibit 2A, para 66-67, it was admitted that Tru-  
Square’s insurance coverage during the construction of the Swanby residence was  
held by Metcalfe as a sole proprietor and, further, that the insurance policy was  
cancelled on or about May 13, 2013. Metcalfe testified in chief that the insurance had  
no relevance at all to the construction of the Swanby residence. However, during  
cross-examination, he conceded that he had taken out property and liability insurance  
as a sole proprietor on behalf of Tru-Square Homes, but that the insurance was  
cancelled in May 2013 (Exhibit 35).  
c) In direct examination, Metcalfe testified that he had been up on the roof and inspected  
the work of the roofing subtrade. He stated that the work appeared to be  
unexceptional and in order. In cross-examination, he confirmed that he had been up  
on the roof, but conceded that he never inspected the work.  
d) In his evidence, Metcalfe suggested that the complexity of the interior finishing on  
the residence served as a disincentive to his continued involvement in the project  
beyond the lock-up stage. However, in cross-examination he conceded that the  
complexities associated with the house related to the foundation and the framing, both  
of which were clearly within the scope of his work.  
e) In the Agreed Statement of Facts, Metcalfe admitted that several aspects of his work  
were deficient, but his testimony was to the contrary.  
   
Page: 14  
[75] The Defendants, on the other hand, urge me to accept the evidence of Metcalfe and to  
prefer his evidence over that of the Plaintiffs where there is a conflict.  
[76] I have several concerns with Metcalfe’s evidence generally. First, I agree with the  
Plaintiffs’ contention that Metcalfe’s frequent and extended absences from the job site, and  
indeed Alberta, adversely impact the reliability of his evidence respecting the key events. He was  
not present for almost 50% of the time from the outset of construction to the completion of the  
lock-up stage. His lack of contemporaneous notes, documents, or photographs contributes to my  
concern about the reliability of his evidence relative to events that took place many years ago.  
[77] I also have concerns with Metcalfe’s credibility. I accept the Plaintiffs’ assertion that  
Metcalfe gave conflicting, even contradictory, evidence. As a witness, I found him to be highly  
combative and quick to deflect responsibility for most, if not all, of the extensive deficiencies  
discovered by the Plaintiffs’ experts after Metcalfe abandoned the project. Generally, he was  
unwilling to acknowledge any responsibility for the very serious issues that arose during the  
project. As more fully set out later in these reasons, I reject the evidence of Metcalfe on several  
key matters in dispute. The combined impact of these adverse findings relative to Metcalfe leads  
me to approach the entirety of his evidence with considerable skepticism.  
B. The Plaintiff’s Experts  
[78] The Plaintiffs called three expert witnesses at trial: Bjornson, Matthews, and Cameron  
Kraychy. All of them gave their evidence in a clear, straight-forward manner and were not  
seriously challenged in cross-examination.  
1. David Matthews  
[79] Matthews was qualified by the Court as an expert in structural engineering and qualified  
to give opinion evidence with respect to building code compliance, applicable industry standards  
and best practices relating to the design, construction, and constructional components in custom  
residential home construction in Alberta. His curriculum vitae was marked as Exhibit 11.  
Matthews provided two reports to the Court, an initial report dated April 7, 2017 (Exhibit 12)  
and an Expert Rebuttal Report dated October 30, 2017 (Exhibit 13).  
[80] Matthews is the principal of Madden Matthews Engineering Ltd, with experience in  
structural engineering over a span of 30 years. His expertise is directly applicable to the various  
issues that arose in this litigation. His expert report is the result of extensive examination,  
investigation and on-site testing. He gave detailed and comprehensive evidence that I found to be  
highly credible. I accept his evidence.  
2. Dana Bjornson  
[81] Bjornson is a professional engineer registered with the Association of Professional  
Engineers and Geoscientists of Alberta (APEGA) as well as the Leadership in Energy and  
Environmental Design (LEED) Rating Systems. She is an engineering graduate from the  
University of British Columbia (1994) and holds a Master of Architecture degree from the  
University of Oregon (1999). Her curriculum vitae was marked as Exhibit 15.  
[82] Bjornson has worked in the field of building envelope engineering for over 30 years. She  
has extensive experience in relation to residential and commercial construction projects. She  
serves as a member of the Alberta Building Envelope Council (ABEC) and is the principal of  
     
Page: 15  
her own firm, Optimize Envelope Engineering Ltd. As of the date of her court appearance in this  
matter, she had reviewed over 300 building envelopes in the preceding two years. She has  
previously given expert evidence in the Provincial Court of Alberta.  
[83] The Plaintiffs asked Bjornson to examine the condition of the building envelope,  
including if there were any deficiencies or Code deviations. Bjornson submitted an expert report  
to the Plaintiffs on April 7, 2017, having inspected the site on July 10, September 8, October 18,  
2013, and October 24, 2014: Exhibit 16. Bjornson reviewed the condition of the windows,  
exterior doors, stucco, stone, decks, soffits, interior vapour barrier, interior insulation, drainage  
systems, and roofing. The deck was also flood-tested on July 10, 2013. She provided an Expert  
Rebuttal Report dated September 12, 2017. Her CV was marked as Exhibit 15.  
[84] Bjornson was qualified by the Court as an expert in building envelope engineering and  
permitted to give opinion evidence in the areas of building code compliance, applicable industry  
standards, and best practices relating to the design and construction of building envelopes in  
Alberta custom residential construction. She gave very detailed and comprehensive evidence that  
I found to be highly credible. I accept her evidence without reservation.  
3. Cameron Kraychy  
[85] Cameron Paul Kraychy (“Kraychy”) was qualified by the Court as an expert in the field  
of general contracting in the context of custom home building. He was qualified to give opinion  
evidence on the role of the general contractor and the applicable standard of care in the custom  
home building industry in Alberta, and as regards the remediation of custom homes and  
renovations.  
[86] Kraychy provided an Expert Report dated March 28, 2017 (Exhibit 27) and an Expert  
Rebuttal Report dated September 19, 2017 (Exhibit 28).  
[87] I found Kraychy’s evidence to be of considerable assistance in relation to a number of  
issues. First, he provided the perspective of a seasoned custom home builder on the need to  
engage engineering support relative to structural design, including design changes, as well as  
structural issues arising during construction. Second, he provided important evidence on the role  
of the general contractor on a construction project in terms of overall project oversight and the  
effective management of subtrades. Third, he gave evidence as to the appropriate  
communications strategy to be employed by a general contractor relative to the customer or  
homeowner so as to ensure that they are fully apprised of the progress of the project and, in  
particular, problems or issues arising during the project and the proposed strategy to address such  
matters. Based on his qualifications and experience, I accept Kraychy’s evidence regarding the  
industry standards and best practices applicable to a general contractor working in the custom  
home building field.  
C. The Defendants’ Expert  
[88] The Defendants called Doug Mark Hamman (“Hamman”) and sought to have him  
qualified in the following areas:  
a) The field application of the requirements of the Code;  
b) Field design and construction of structural support systems;  
c) Field design and construction of building envelope systems for construction projects;  
   
Page: 16  
d) Construction project management, including budgeting, scheduling, trades oversight,  
and the inspection of completed work to confirm Code compliance has been met.  
[89] The Plaintiffs urged the Court to find that Hamman was not qualified to give expert  
evidence and to decline to admit his report into evidence. After hearing extensive argument from  
counsel, I qualified Hamman as an expert homebuilder and project manager in the four areas  
proposed by the Defendants. However, I declined to allow him to give expert evidence as an  
engineer in any of those areas. I also note that Hamman was not qualified to give expert evidence  
as either a custom home builder or a remediation expert given his lack of experience in both  
domains. Accordingly, Hamman provided no evidence regarding the standard of care applicable  
to custom residential homebuilding. Subject to these and other limitations more fully set out  
below, Hamman’s Expert Report dated July 17, 2017 was received in evidence (Exhibit 48).  
[90] The Plaintiffs urge the Court to approach Hamman’s evidence with great caution,  
particularly given his alleged cursory examination of the actual construction project and the fact  
that he offered conclusions based on limited visual examination and without the benefit of  
destructive testing or comprehensive investigation. The Plaintiffs argue that Hamman’s evidence  
should be restricted to the determination of Code compliance and structural components in  
residential home construction.  
[91] Hamman’s report was based on three visits of approximately 1.5 hours duration each.  
Given the size of the residence and the nature and number of alleged deficiencies, I am satisfied  
that Hamman’s opportunity to fully inspect the residence was necessarily limited by the time  
constraints. Further, his comments and conclusions were based on his observation of pre-exposed  
areas of the residence. He conducted no independent testing. This stands in sharp contrast to the  
comprehensive investigation undertaken by the Plaintiffs’ experts and Juniper. I would also note  
that Hamman’s report is silent on several deficiencies noted by Bjornson, Matthews and Juniper.  
[92] Of note, Hamman acknowledged the deficiency of the Defendants’ work in quite a  
number of instances. He expressed agreement with many of the conclusions reached by the  
Plaintiffs’ experts.  
[93] I accept the Plaintiffs’ contention that Hamman’s assessment of the individual  
deficiencies was incomplete. A number of the assumptions that form the foundation of some of  
his conclusions are not substantiated by the evidence. This and the other constraints previously  
identified lead me to place very limited weight on Hamman’s evidence. I do not, however, go so  
far as to accept the Plaintiffs’ assertion that the weight to be attributed to Hamman’s evidence is  
credibility-based. In my view, the difficulties with Hamman’s evidence are related to the  
reliability of that evidence, not to his credibility.  
[94] I do not view Hamman’s report as a technical response to the engineering evidence of  
either Matthews or Bjornson or a response to the custom home building expertise of Kraychy. In  
this regard, I accept the Plaintiffs’ caution as regards the treatment of Hamman’s expert  
evidence. As the Plaintiffs properly point out, Hamman’s more limited accepted areas of  
expertise place significant restrictions on his ability to challenge or otherwise undermine the  
opinions and findings of the Plaintiffs’ engineering expert witnesses. In my view, this is the  
natural consequence of the Defendants’ decision not to call engineering experts of their own to  
challenge the Plaintiffs’ experts.  
Page: 17  
[95] Indeed, the Plaintiffs go so far as to suggest that there is essentially no defence to the  
deficiencies aspects of the case. While I accept the general thrust of this argument, it is still  
necessary to consider carefully the evidence of the engineering experts and Kraychy, and all of  
the other evidence in this case, to determine whether the Plaintiffs have satisfied the burden  
resting on them to establish the individual alleged deficiencies. I would simply add that  
Hamman’s reports and trial testimony have been carefully considered in this process.  
[96] The Defendants appear to rely on Hamman’s report as offering to the Court an alternative  
remediation work plan reflected in the budgeting exercises that he undertook. He compared his  
proposed scope of work with a quote that TGC prepared before remediation efforts were  
commenced. The Plaintiffs challenge the weight to be given to Hamman’s comparative  
remediation budgets. They say that Hamman’s budgets are unreliable given that his credibility  
was impugned and his primary conclusions have been found to either be incorrect or  
untrustworthy. As noted above, I do not find that Hamman lacked credibility.  
[97] The law does not require the cheapest or most economical solution to effect remediation,  
but only that reasonable efforts be made in this regard. Cost is only one factor to be taken into  
consideration. The Plaintiffs say that, only three weeks from their anticipated possession date,  
their trust in their contractor had been destroyed. While the Defendants argue that the costs  
incurred were too high, the Plaintiffs respond that there is no evidence that should cause the  
Court to doubt, let alone reject, the investigation results of Bjornson or Matthews, their  
remediation recommendations and, ultimately, Juniper’s charges. This issue is more fully  
explored later in these Reasons in the section dealing with the calculation of damages.  
V. Analysis  
[98] This matter raises numerous legal and factual issues.  
A. Concurrent Liability in Contract and Tort  
[99] The Plaintiffs maintain that a building contractor can be liable concurrently in contract  
and tort unless the terms of the contract clearly and expressly limit or exclude liability in tort.  
They maintain that the contract in this instance is entirely silent on the issue of limiting or  
excluding tort liability. I agree.  
[100] The Plaintiffs rely on Vermillion & District Housing Foundation v Binder Construction  
Limited, 2017 ABQB 365 at paras 123-25, where the Court explained:  
The conduct of a contractor may constitute not only a breach of contract but also  
negligence: Heintzman and Goldsmith, at 7-2. Generally speaking, there is a duty  
of care owed by a contractor to an owner: University of Regina v Pettick (1991),  
90 Sask R 241, 6 CCLT (2d) 1 (CA). What is undertaken by the contract will  
indicate the nature of the relationship that gives rise to the common law duty of  
care, but the nature and scope of the duty of care that is asserted as the foundation  
of the tortious liability does not depend on specific obligations or duties created  
by the express terms of the contract the distinction is between what is to be done  
and how it is to be done: Central & Eastern Trust Co v Rafuse, [1986] 2 SCR 147  
at 204, [1986] SCJ No 52.  
   
Page: 18  
In Fraser-Reid v Droumtsekas, [1980] 1 SCR 720 at 726, [1979] SCJ No 125,  
Dickson J. for the majority stated the relevant question as being: “Did the builder  
act as a competent and careful builder would have acted in what he did or did not  
do?”, citing Batty v Metropolitan Property Realizations Ltd, [1978] 2 All ER 445  
(CA) and Dutton v Bognor Regis United Building Co Ltd, [1972] 1 All ER 462  
(CA).  
An owner may sue a building contractor alternatively or concurrently in contract  
and tort, and a contractor who is negligent in the performance of a contract to  
build is liable in tort to any person suffering resultant injury to person or property,  
unless such liability is limited by the contract: Dominion Chain Co v Eastern  
Construction Co (1976), 12 OR (2d) 201, [1976] OJ No 2104 (CA), aff’d without  
reference to this point [1978] 2 SCR 1346, Dabous v Zuliani (1976), 12 OR (2d)  
230, 1 CPC 48 (CA), Central Trust Co; BG Checo International Ltd. v British  
Columbia Hydro & Power Authority, [1993] 1 SCR 12, [1993] SCJ No 1.  
[101] Briefly stated, the plaintiff in Vermillion advanced claims for breach of contract and  
negligence by a general contractor in the construction of an addition to an existing building. The  
contractor ultimately was found to have breached the contract and to have been negligent for  
failing to exercise reasonable care and skill in ensuring that the construction was undertaken in  
accordance with the accepted standards of a reasonable contractor.  
[102] The Court in Vermillion confirmed at para 179 that in breach of contract, “the wronged  
plaintiff is entitled to be put in as good a position as he would have been in if there had been  
proper performance by the defendant” [citations omitted]. In tort, “[T]he purpose of an award of  
damages...is to put the innocent party back into the position as if the tort had not occurred”  
[citations omitted]: at para 181. With respect to potential concurrent liability in both contract and  
tort, the Court stated at para 183 that “it would seem anomalous to award a different level of  
damages for what is essentially the same wrong on the sole basis of the form of action chosen,  
though particular circumstances or policy may dictate such a course”.  
[103] There is no dispute that Vermillion also stands for the proposition that the contractual  
measure is the preferred approach in cases of concurrent liability in both tort and contract: see  
para 22. Ultimately, I am satisfied that it makes no practical difference whether a case is assessed  
as a tort claim or a contract claim. In both instances, the measure of damages is the same, ie., to  
put the plaintiff back in the position they ought to have enjoyed but for the breach of contract or  
the breach of a duty of care.  
[104] While the overall approach to both liability and damages may be the same under both  
contract and tort, contractual liability is limited to the specific contracting parties, in this case  
Tru-Square, other than in circumstances involving the lifting of the corporate veil. By contrast,  
the Plaintiffs contend that both Tru-Square and Metcalfe can be held liable in tort. The Plaintiffs  
argue that Metcalfe can be found personally liable for negligence, as well as fraud.  
B. Liability in Contract  
[105] To establish liability under contract, the Plaintiffs must prove the existence of an  
enforceable agreement, the breach of an obligation(s) under that agreement and a resulting loss  
that was foreseeable and not too remote.  
 
Page: 19  
1. The Lock-Up Contract  
[106] The parties’ Agreed Statement of Facts includes the following statements relating to the  
three contracts they signed on August 22, 2011:  
a) On August 22, 2011, Tru Square (by Metcalfe) and the Plaintiffs executed an  
Alberta New Home Warranty Program (ANHWP) form of agreement valued  
at $1,062,348.  
b) On August 22, 2011, Tru Square (by Metcalfe) and the Plaintiffs executed two  
additional forms of agreement for construction services valued at $1,062,348  
and $692,485.50, respectively.  
c) Metcalfe typed up and prepared both forms of agreement other than the  
ANWHP agreement.  
[107] All of these contracts were fixed-price contracts and included a four-stage draw payment  
to the Defendants. The first contract (Exhibit 1-C-5) involved construction of the residence to the  
lock-up stage (the Lock-Up Contract”), including stucco and drywall, in the amount of  
$692,485.50. It excluded all interior finishes, any stone, any fireplaces and any exterior services.  
The homeowner was responsible once the drywall was finished. Work performed by others was  
specifically the responsibility of the homeowner.  
[108] The Lock-Up Contract refers to the design prepared by Innographic, but states that “the  
building spec or design of plan drawings may not always be followed as suggested by  
draftsman”. Further, the contract stipulates:  
This contract shall replace the contract that covers the entire home but shall have  
all the warranty on all work done by Tru-Square Homes Ltd. as covered by the  
ANHW program.  
[109] The second, unnumbered paragraph of the Lock-Up Contract stipulates the inclusions and  
exclusions. Included in the contract price of $692,485.50 are the following:  
...foundation (excluding excavation, backfill), framing, windows/doors installed,  
overhead doors installed (allowance of $7000 for 3 doors), shingles, acrylic  
stucco (all built-outs are extra includes $5000 allowance for built-outs in price),  
eavestrough, plumbing, heating, electrical (including pot lights but not rest of  
fixtures), insulation, drywall, concrete finished in basement and garage.  
[110] Excluded from the Lock-Up Contract are the following: “any exterior services (water  
line, septic, power, gas, road, etc.), any fireplaces, any stone, any interior finishes (except  
plumbing, heating and some electrical)”. In another portion of the Lock-Up Contract, the  
owner’s responsibility for all interior finishing after drywall, including false beams, is repeated.  
Later, it stipulates:  
Once the building is completed to the point where the drywall is finished, then the  
home owner takes over the overseeing and responsibility of finishing the home  
except those that are the responsibility of Tru-Square Homes. All interior  
finishing is the responsibility of the homeowner.  
[111] Under the heading “Comments or Specs”, the Lock-Up Contract included a term relating  
to the construction of the foundation:  
 
Page: 20  
Basement has 8” concrete wall, not ICF. Finished ceiling height to be  
approximately 9’1”. Concrete to be 25 MPA (type 50) with two rows of 2 (10  
mm) rebar in the 9 foot wall and 1 row of 2 rebar in 4’ wall. Footing to have 2  
bars in as well. Concrete walls to step down to walkout as grade allows.  
[112] The Lock-Up Contract stipulates that Tru-Square is responsible for ensuring that the  
residence meets building codes and that it will “strive for high quality”. Trades are to have WCB  
coverage or private insurance, while the homeowner is required to have building and liability  
insurance. A four-step payment schedule is set out in the final portion of the contract as follows:  
1. After completion of the foundation- $110,000.00;  
2. Framing complete, including doors/window installed, roof complete, rough in  
plumbing, heating, electrical, insulation and vapour barrier installed, concrete  
basement poured - $350,575.00;  
3. Insulation and drywall complete, heating equipment installed - $130,000,00;  
4. Stucco completed, concrete exterior pads, finals on electrical, heating, plumbing,  
eavestrough and garage doors installed - $101,910.50.  
[113] The second signed contract contemplated construction of the residence to completion for  
a total price of $1,062,348.00. This second contract repeats many of the terms set out in the  
Lock-Up Contract, including that payments are due “after completion of 4 stages as per ANHWP  
contract”.  
[114] While this contract provided details as to the construction of the basement, no reference  
is made to the type of concrete to be used, unlike the Lock-Up Contract. The second contract  
does, however, specify that the basement walls are not ICF. Unlike the Lock-Up Contract, the  
cost of excavation and backfill were not excluded from the second contract.  
[115] The second contract includes allowances for exterior and interior finishes, namely:  
$ 5,000.00  
Stucco build outs (installed)  
$30,000.00  
Stone (installed)  
$ 8,000.00  
Two fireplaces (installed)  
$30,091.00  
Finish material (not including cabinets)  
$15,000.00  
False beams and ceiling timber/beams (installed)  
$ 6,000.00  
Window/door upgrades  
$ 2,000.00  
Interior stair upgrades  
$27,000.00  
Deck covering material with railing (installed)  
$10,000.00  
Appliance allowance  
$33,660.00  
Floor coverings (supply and install main floor)  
$14,735.00  
Floor coverings (supply and install lower level  
$54,710.00  
Cabinets (supply and install)  
Page: 21  
$ 2,736.00  
$ 5,471.00  
$ 3,000.00  
Wall tiles (supply and install)  
Electrical fixtures (does not include pot lights which is part of electrical)  
Steam shower (supply and install)  
[116] Finally, the second contract specifies that trades are required to have WCB coverage or  
private insurance that meets the standards. The homeowner is stated to be responsible to have  
building and liability insurance and is also responsible for the supply of power. Unlike the Lock-  
Up Contract, this contract states that Tru-Square belongs to the ANHWP.  
[117] Metcalfe brought both of these contracts (1-C-5 and 1-C-6) to the meeting. Both are on  
Tru-Square letterhead. The Plaintiffs had never seen the documents before, but reviewed them  
briefly and then signed them.  
[118] The third form of contract, the pre-printed ANHWP contract, was brought to the meeting  
by the Plaintiffs. This contract also covered the construction of the entire residence at a cost of  
$1,062,348.00. Unlike either 1-C-5 or 1-C-6, it specified a completion date of June 30, 2012.  
[119] While this third contract is stated to be between Craig and Georgina Swanby and Tru-  
Square Homes Ltd, it was signed only by Craig Swanby, though both Plaintiffs initialled each  
page of the multi-page document. Of note, some of the blanks are filled in with the following  
information:  
a) Under paragraph (f), the construction section, the following was added: “Custom Plan  
from Innographic Design and Drafting (Gordon Snell) with changes as outlined in  
Part 2 of contract”;  
b) Under paragraph (g), the price of the home was stated to be $1,011,76.00 plus GST of  
$50,588.00, for a total contract price of $1,062,348.00.  
c) Under paragraph (h), the terms of payment were stated as follows:  
(i) 0 deposit;  
(ii) 0 upon the removal or satisfaction of Conditions in paragraph 21;  
(iii) $169,975.68 on completion and inspection of foundation (16%);  
(iv) $350,574.84 upon completion and inspection of ready to drywall (33%);  
(v) $276,210.48 upon completion and inspection of drywall complete, heating  
installed (26%);  
(vi) $265,587.00 being the balance of the total price and interest, if any, on the  
completion and possession of the home, whichever occurs first.  
d) The purchaser was stated to be responsible for utility connections, building permit,  
utility costs, and building/liability insurance (paragraph M);  
e) Completion date was stated to be June 30, 2012, though the builder did not guarantee  
this date in the event of delays for which the builder may not be responsible  
(paragraph N);  
f) Under the heading “warranty” (paragraph S), the contract provided:  
The Builder agrees to provide the Builder Warranty set forth in  
detail in the Warranty Certificate appearing on page 6 of this  
Agreement as the minimum requirement on the part of the Builder.  
Page: 22  
The Builder may provide warranty coverage in addition to the  
minimum required in the said warranty and in such event, the  
additional warranty coverage shall be contained in an addendum in  
writing signed by the Builder and attached to this Agreement.  
Additional coverage is provided solely by the Builder and the  
Program does not warrant the Home beyond the terms, conditions,  
limits and exclusions contained in the Warranty Certificate.  
[120] A Single Family Residence Warranty Certificate was attached to the contract.  
[121] It seems clear that the detailed quote provided by Metcalfe and dated August 21, 2011,  
was in furtherance of the Plaintiffsrequest for information, presumably for their bank, as to the  
total cost to complete the project. Metcalfe’s breakdown confirms that at that point in time, the  
agreement was for him to build to the lock-up or drywall stage only. The document also includes  
a handwritten timeframe for the projected completion of various stages of construction. Of note,  
the timeframe indicated that drywall would be completed by the end of February 2012, with  
work on the interior to commence on March 1, 2012. The document also confirmed that the  
initial quote was for $551,310 and referred to a “new” quote of $659,510, the new quote to  
include exterior stucco, a concrete garage pad, entrance pad and deck pad, soffit, facia,  
eavestrough, ANHWP fees, and other items.  
[122] I am satisfied that at the time of the August 22, 2011 meeting that led to the signing of the  
three contracts, the parties had come to an agreement that the Defendants would construct the  
home to the lock-up stage only. As such, their agreement was that the Lock-Up Contract (1-C-5)  
was to apply. At that time, the Plaintiffs contemplated completing the residence on their own.  
2. Was the Lock-Up Contract Amended or Varied?  
[123] The parties take very different positions on the question of whether there was an  
agreement reached that committed the Defendants either to finish the construction of the  
residence or to complete some aspects beyond the lock-up stage.  
[124] In Hyslip v Macleod Savings & Credit Union Ltd, [1988] 90 AR 141 (QB), the Court  
held that a contract may be varied by agreement. At para 30, the Court stated:  
It may be stated as a general principle that the parties to a concluded agreement  
may by agreement vary the terms of their concluded agreement, and that such  
variation may be by express agreement or may be implied by conduct. An  
agreement varying an existing agreement must in itself amount to a valid contract.  
To effect a variation the parties must be ad idem in the same sense as for the  
formation of a contract, and there must be consideration passing. Where an  
agreement is varied it then operates according to the variation, and the original  
term or terms cannot be set up by one of the parties against the other. A variation  
cannot occur by a unilateral notification by one party to the other, without any  
agreement, but if the variation is made unilaterally by one party and accepted by  
the other party and there is valid consideration passing a variation of the original  
contract can occur.  
[125] According to Metcalfe, the agreement to build to the lock-up stage was the only  
agreement that was ever reached. However, he also says that the total contract consisted of 1-C-  
5, the Lock-Up Contract, as well as portions of 1-C-4, the ANHWP contract relating to warranty  
 
Page: 23  
coverage for the work performed by the Defendants. This ignores the fact that 1-C-4 expressly  
refers to an agreement to construct the entire residence. The Defendants’ reliance on a portion of  
1-C-4 as forming part of their agreement is, in my view, not supported by the evidence. There is  
no evidence before me that the parties ever reached a consensus that a portion of 1-C-4, the full  
construction contract, was to be included as part of their agreement. However, it is not necessary  
for me to resolve this.  
[126] The Defendants say that a plain reading of the terms of the Lock-Up Contract reveals that  
it “replaced” the full contract. As such, they maintain that the Plaintiffs did not have the option  
of making anything other than the Lock-Up Contract the document governing the parties’ legal  
relationship.  
[127] In my view, the plain meaning of the first paragraph of the Lock-Up Contract is that it  
was intended by the parties to replace the full contract. While I accept the Defendants’  
contention that it was not open to the Plaintiffs unilaterally to re-activate the earlier agreement, it  
was certainly open to the parties to reinstate the earlier contract upon a further agreement to this  
effect. Likewise, it was open to the parties to vary the Lock-Up Contract to incorporate some or  
all of the terms of the full house contract.  
a) The Fall 2011 Amendment  
[128] Both Mr. and Ms. Swanby say that, about three-quarters of the way through the framing  
process, they concluded that completion of the residence post lock-up stage was beyond their  
capability. They decided to ask Metcalfe to complete the project. According to Ms. Swanby, she  
had a discussion with Metcalfe while standing close to the doorway of the unfinished kitchen in  
which he agreed to build the residence to completion. She did not recall the exact words that he  
used, but he verbally agreed to complete the construction of the residence. Ms. Swanby  
mentioned to Metcalfe that they already had a signed contract for the completion of the  
residence, but he did not respond. The Plaintiffs maintain that the Defendants thereby committed  
to completing the residence in accordance with the full price contract signed on August 22, 2011  
(Exhibit 1-C-6).  
[129] Metcalfe acknowledges that he did have a conversation with Ms. Swanby at some point  
regarding him taking on the completion of the residence, but disputed he agreed to finish the  
home or to be bound by the full contract, either 1-C-4 or 1-C-6.  
[130] I accept Ms. Swanby’s evidence that she had a discussion with Metcalfe in which he  
agreed to build the residence to completion. I am satisfied that the parties came to an agreement  
in the fall of 2011 to vary the terms of their existing contract. By the terms of this oral  
agreement, the Defendants agreed to complete the construction of the residence. As such, the  
parties agreed to be bound by the terms of the fixed-price, full contract signed on August 22,  
2011, for $1,062,348.00, Exhibit 1-C-6, as constituting an amendment or variation of the Lock-  
Up Contract. Under the terms of the revised contract, Metcalfe remained the general contractor.  
[131] In their written submissions, the Defendants contend that the Plaintiffs abandoned their  
argument that they ever exercised the option to proceed on the full contract. The Defendants say  
that this abandonment took place during counsels’ oral submissions at the conclusion of the  
evidence. I have carefully reviewed the evidence of both Mr. and Ms. Swanby and am satisfied  
that they both testified as to their belief that they reached an agreement with Metcalfe to vary the  
Page: 24  
terms of the Lock-Up Contract so as to incorporate the terms of the full house contract. I accept  
the assertion of counsel for the Plaintiffs that this argument was never abandoned.  
[132] That said, it seems clear that this first variation agreement reached in the fall of 2011 had  
limited practical implications for the progress of the project. At the time, the Defendants were  
still very much engaged in those aspects of the construction of the residence that formed part of  
the Lock-Up Contract. The Plaintiffs maintain that all of the deficiencies claimed in this action  
flow from the Defendantswork to the lock-up stage. As such, the Plaintiffs say that whether or  
not the parties subsequently entered into a new contract for the construction of the entire  
residence is not material to the resolution of this litigation.  
[133] Save for the possible involvement of the stone mason in the leaking windows, I agree  
with the Plaintiffs’ contention in this regard. On the evidence before me, it is clear that the terms  
of the agreement reached between the parties relative to the completion of the project beyond the  
lock-up stage are largely irrelevant to the issue of liability. There is no dispute between the  
parties that virtually all of the deficiencies relied upon by the Plaintiffs in this litigation were  
items covered by the Lock-Up Contract. While the installation of the exterior stone was not part  
of the Lock-Up Contract, its removal was necessitated by the deficient stucco work that clearly  
was covered. This is discussed in greater detail later in these Reasons.  
b) The May 2012 Amendment  
[134] The second amendment alleged by the Plaintiffs is potentially more significant.  
[135] The Plaintiffs assert that the full price contract was varied in May 2012. Ms. Swanby’s  
evidence was that this new agreement was prompted by the Plaintiffs’ escalating concerns about  
the sub-contractors hired by the Defendants to complete the interior work on the residence. As  
noted above, when Ms. Swanby raised concerns with respect to the quality of John Metcalfe’s  
work, he walked off the job, leaving the Plaintiffs to hire their own tile sub-contractor to re-do it.  
Issues also arose with the Defendantspainting sub-contractor and cabinet supplier. Further,  
Metcalfe was unable or unwilling to meet the Plaintiffs’ requests relative to flooring and a  
planned staircase. Finally, Ms. Swanby was growing increasingly frustrated by the delays  
occasioned by Metcalfe’s frequent absences from the job site and his continuing refusal to assist  
in keeping track of the various allowances established for the interior work.  
[136] The full price contract included a list Metcalfe had prepared of allowances to complete  
the interior finishings. Ms. Swanby understood that the full price contract was a fixed price  
contract and that the itemized amounts were Metcalfe’s guidelines as to what could be spent to  
complete the interior. When Metcalfe subsequently refused to provide regular budget updates  
relating to these allowances, Ms. Swanby turned to Carm to assist her in preparing budgets to  
ensure that they knew exactly where they were at relative to each line item. Exhibit 1-I-37 was  
the first budget that she developed with Carm when the required information was not  
forthcoming from Metcalfe. Exhibit 1-I-20 was a later version of this same budget. These  
spreadsheets were created in late 2012 or in early 2013 when bills started to arrive from the  
various interior trades.  
[137] Ms. Swanby testified that she, Metcalfe and Carm met in May 2012 and arrived at a  
verbal agreement under which the Plaintiffs agreed to pay the Defendants either 5% or 10% of  
the cost of work completed by subcontractors, depending on whether the subcontractor was  
identified and hired by the Plaintiffs or by Metcalfe. It was also agreed that Metcalfe would  
Page: 25  
receive and process all of the sub-contractors’ invoices and then seek reimbursement from the  
Plaintiffs. While the terms of this alleged variation were not reduced to writing, Ms. Swanby  
believed that Metcalfe and Tru-Square continued as the general contractor for the project. She  
and Mr. Swanby both testified that they believed it was only fair to provide some compensation  
to the Defendants for their continuing work on, and oversight of, the full price contract even if  
the Plaintiffs hired some of the sub-contractors.  
[138] According to Metcalfe, he was approached by Ms. Swanby and Carm in May 2012, just  
prior to the completion of the drywall, and told that the Swanbys were unable to sell their other  
property and were therefore in a difficult financial situation. Metcalfe asserts Carm asked him if  
he would be willing to pay certain invoices with a 5% or 10% mark-up just to assist the Swanbys  
for a period of time. Metcalfe agreed. Carm set up a schedule on one of the budgets that added  
the 5% or 10% mark-up. Metcalfe says he had no input as to whether he was given 5% or 10%  
for the various trades. He insists that he simply agreed to receive and process the invoices of the  
sub-trades beyond the lock-up stage. The Defendants strongly dispute that Metcalfe retained any  
oversight function for the project beyond the completion of the lock-up stage.  
[139] Carm’s evidence on this point was very limited. He confirmed that a meeting took place  
with Metcalfe and Ms. Swanby in May 2012, during which they reviewed on an item-by-item  
basis the various finishing items and determined whether Metcalfe would receive a mark-up of  
5% or 10%. Carm referred to a budget he prepared dated May 21, 2012, Exhibit 1-I-21, which  
includes various 5% and 10% mark-ups identified as “Jim’s percentage” or “Jim’s mark-up”.  
Carm’s May 15, 2012, budget did not include these mark-ups. A subsequent budget prepared by  
Carm dated January 1, 2013, revealed that Metcalfe’s mark-up was reduced to 5% in certain  
instances where, according to Carm, Metcalfe was unable to provide the trade for the required  
interior work.  
[140] Carm was never questioned about Metcalfe’s version of what took place at this meeting,  
nor was he asked to confirm his alleged initiation of this discussion or his alleged proposal to  
assist the Swanbys through difficult financial circumstances. Metcalfe’s version of events also  
was never put to either Mr. or Ms. Swanby during cross-examination.  
[141] No arguments were advanced at trial regarding the possible application of the so-called  
rule in Browne v Dunn, 6 R 67, 68 (H L 1893), even after the Court invited further written  
submissions on the nature of the legal relationship between the parties, if any, beyond the terms  
of the Lock-Up Contract.  
[142] I accept the evidence of the Plaintiffs. Given the Defendants’ failure to put this key issue  
to the Plaintiffs in cross-examination or to their own witness, Carm, in direct examination, and  
for other reasons discussed below, I place little weight on Metcalfe’s version of events.  
[143] There is no evidence to support Metcalfe’s contention that the cost-plus arrangement  
came about because of financial difficulties experienced by the Plaintiffs when they were unable  
to sell their other home. To the contrary, the evidence indicates that the Plaintiffs had obtained  
full financing from the bank to cover the construction of the entire residence: Exhibit 1-H-22.  
Further, Carm testified that he was unaware of any financial difficulties on the part of the  
Swanbys. While Mr. Swanby gave evidence about financial strain that arose during the  
remediation process that required them to cash in some of their retirement investments, I am  
satisfied that this arose much later than the timeframe relied upon by Metcalfe.  
Page: 26  
[144] The Defendants forcefully assert that they retained no supervisory or oversight  
responsibilities beyond the scope of work set out in the Lock-Up Contract. They advance two  
arguments to support their position that they were not the general contractor and, as such, not  
responsible for the work of the trades involved in the finishing work post lock-up. First, the  
Defendants, relying on Carm’s evidence, maintain that Metcalfe’s only role relative to the trades  
for which he received a 5% mark-up was to simply pay their invoices. According to the  
Defendants, “[I]t is not commercially reasonable that Mr. Metcalfe would not have a role in the  
hiring or supervision of these trades but would be responsible for deficiencies in their work”:  
Defendants’ Response to Additional Reply Submissions of the Plaintiffs, para 12.  
[145] The Defendants called Carm as a witness at trial, which obviously imposed limitations on  
their ability to challenge his evidence. Absent an application under the Canada Evidence Act,  
RSC 1985, c C-5, or the Alberta Evidence Act, RSA 2000, c A-18, or under the common law, to  
have Carm declared an adverse or hostile witness, the Defendants were precluded from cross-  
examining him. No such application was made. The Defendants must accept Carm’s evidence as  
given.  
[146] Carm’s evidence was to the effect that Metcalfe’s responsibilities relative to those trades  
identified by the Plaintiffs, and for which Metcalfe was entitled to a 5% mark-up, were limited to  
the payment of the invoices submitted by that particular trade. However, when questioned as to  
who would be responsible for issues pertaining to the quality of work undertaken by any of the  
so-called 5% trades, Carm offered two responses. First, he suggested that he would be  
answerable to the Plaintiffs if trades associated with his company, C & S Fine Furniture Ltd,  
performed sub-standard or deficient work. Second, he suggested that if another of the 5% trades  
performed substandard work, that trade would be called back to correct the problem. Carm also  
made it very clear that his role on the project did not include any personal responsibility for any  
deficiencies arising from the work of any of the 5% trades. When then asked who would be  
responsible to call back the affected trade to correct the matter, he suggested that anyone from  
the team could make the call.  
[147] I attach very little weight to Carm’s understanding of the chain of responsibility for  
performance issues and deficiencies related to the finishing trades. There is no evidence that  
Carm is legally trained. He was not qualified as an expert witness to give legal opinions. While  
no objection was taken to his responses to hypothetical questions clearly touching on legal  
matters, I do not attribute to this aspect of his evidence the significance advanced by the  
Defendants. In my view, Carm was merely sharing his views as to his personal sense of  
responsibility for trades that he brought to the project either personally or through the Plaintiffs.  
As a practical matter, he believed that trades should be called back to correct sub-standard or  
deficient work. At the same time, he clearly saw very significant limits on his personal  
responsibility insofar as he was quick to point out that he would not bear any personal financial  
responsibility in such circumstances. Moreover, Carm was adamant that he was not the general  
contractor and that this role was played by Metcalfe from the outset of the project until the  
Defendants abandoned it in June 2013. In the result, I am unable to accept Carm’s views as being  
in any way determinative of the underlying issue relating to legal responsibility.  
[148] In my view, Metcalfe’s evidence that the cost-plus variation of May 2012 was a financial  
arrangement only is not credible. It is inconsistent with his continued regular presence on the  
job-site, a presence that would not have been required for someone exercising an invoice  
payment function only. It is also inconsistent with Carm’s time sheets and the various email  
Page: 27  
exchanges between Carm and Metcalfe and others that confirm Metcalfe’s continuing active  
involvement in the project. In rejecting this aspect of Metcalfe’s evidence, I reiterate that  
Metcalfe’s alleged financing arrangement was never put to either Mr. or Ms. Swanby in cross-  
examination. Likewise, it was never put to Carm notwithstanding the key role Metcalfe claimed  
he played in the discussion leading to this new financial arrangement. My rejection of Metcalfe’s  
evidence on this key issue significantly impacts my overall assessment of his credibility as a  
witness in these proceedings.  
[149] The Defendants advance a series of arguments regarding Carm’s role throughout the  
construction project, but most particularly relative to the finishing trades involved in the post  
lock-up phase of the process. Carm identified a number of these trades, including his own  
company, C & S Fine Furniture Ltd, which was involved in furnishing and installing much of the  
interior cabinetry. Several of the other trades, including the stone mason, Lawrence Masonry,  
were identified and hired by the Defendants.  
[150] Carm’s role in this construction project is the subject of significant disagreement between  
the parties. The Defendants suggest that he played a significantly more active role than simply  
the Swanbys’ designer. The Plaintiffs, on the other hand, view the Defendants’ focus on Carm as  
nothing more than an attempt to deflect responsibility for the supervision and oversight of the  
project away from Metcalfe. In my view, the Plaintiffs’ argument finds support in Metcalfe’s  
contradictory evidence regarding his role described earlier in these Reasons.  
[151] Carm was hired by the Plaintiffs as their designer and paid $85 per hour for his work  
throughout his involvement in the project. He was required to keep track of his time. He did not  
have a written contract with the Plaintiffs and there was never a contractual relationship between  
him and the Defendants.  
[152] I am satisfied that Carm’s involvement in the project created some confusion for  
Metcalfe, who testified that he had never worked with a designer before. Metcalfe’s initial email  
communication with Carm on August 27, 2011, days after the parties signed the contracts for the  
construction of the residence, confirms Metcalfe’s uncertainty about the arrangement: Exhibit 1-  
G-23. The final paragraph of the email reads as follows:  
I’m sure the clients appreciate your input into their new home and hopefully we  
can work together as smoothly as possible so that the owners can get the best  
product possible for a reasonable price. I gather this is something neither one has  
done before (work together) so we will need to communicate what is happening  
as the project continues. I will try to remember to keep you informed on the  
progress and schedule but I imagine you will be by regularly to see for yourself  
which will be good as you may pick up something that I may have missed that  
works toward the finished house.  
[153] Carm testified that the Swanbys initially invited him to take on the role of general  
contractor, but he declined on the basis that he lacked the required technical knowledge and  
experience. According to Carm, he was the designer on the project and, as such, his work  
involved design, budgeting and the coordination and scheduling of some of the finishing trades.  
[154] Nonetheless, Carm had significant experience in the design process, as well as in the  
finishing processes that follow the lock-up stage. The Plaintiffs placed great reliance on his input  
Page: 28  
and advice throughout. He acted somewhat as a “go-between” for the Plaintiffs in their dealings  
with Metcalfe throughout the construction project.  
[155] I am satisfied that part of Metcalfe’s confusion regarding Carm’s role flowed from the  
fact that Carm frequently acted as the Plaintiffs’ voice in dealings with Metcalfe and others. This  
confusion was compounded by Metcalfe’s significant time away from the job site when  
circumstances required Carm to step into the breach during these absences to try to keep the  
project rolling. On occasion, when Metcalfe’s travel schedule rendered him difficult or  
impossible to contact, Carm filled some of the oversight vacuum created by Metcalfe’s absences  
from the site, including relaying messages to and from Metcalfe.  
[156] The Defendants cite several examples of circumstances in which Carm is alleged to have  
played a key role in the oversight and supervision of the project, particularly after the lock-up  
stage was reached. For example, the Defendants suggest that Carm’s email to Metcalfe on  
September 19, 2012, makes it clear that he was assuming responsibility for the project with the  
result that Metcalfe and Tru-Square cannot be found to have been responsible for the work of the  
finishing trades.  
[157] Carm’s email (Exhibit 1-I-46) contained a list of fourteen items that he suggested  
required Metcalfe’s attention. The heading at the top of the email is “Items I need you to finish  
before I take over the project”. At the conclusion of that email, Carm asked Metcalfe to sent out  
an email to all of the trades to notify them that “I will be the contact person for the project”. On  
September 22, 2012, Metcalfe sent an email to Carm listing the names and contact information  
for ten of the trades working on the project. The email read as follows:  
Hi Shawn,  
Sorry for the delay but have been extremely busy of late.  
True Blue Plumbing and Heating Jason 540-8230  
Eagle Electric Jim 556-9853  
Amax Exteriors Allan 559-4539 (eavestrough, soffit/fascia)  
Glen Coulter drywaller 507-9840  
Diamond Fireplace 273-0000  
John Lawrence 874-3413 stone  
John 561-1270 tile  
Kory 507-3783 concrete  
Lumberding Exteriors 888-8504 (shingles)  
M+K Stucco (Merlin) 944-1077  
I believe you have any others that I have missed. If not, you can phone my cell (it  
is no extra cost as long as I am in the country) or email but I won’t have access all  
of the time. Any questions phone. The other unfinished items will be delt [sic]  
with on my return.  
[158] Carm sent a further email that same day acknowledging receipt of Metcalfe’s earlier  
message and stating: “[T]hank u when are u leaving and when approximately will u be back?  
Have a great trip.”  
[159] According to Carm, this email exchange took place in the context of Metcalfe’s planned  
absence from the province for a period of three weeks, during which there would be periods of  
time when he could not be reached via cellphone or email.  
Page: 29  
[160] What I take from this email exchange is that Carm was taking over the temporary  
supervision of the project during Metcalfe’s absence. On the evidence before me, it is clear that  
Metcalfe was regularly away from the job site for personal reasons, including pre-planned  
vacations. On occasion, when Metcalfe’s travel schedule rendered him difficult or impossible to  
contact, Carm was required to fill some of the gap created by his absence, including contacting  
the trades directly. In my view, given the oversight vacuum created by Metcalfe’s frequent  
absences from the site, it is not particularly surprising that Carm provided guidance and advice to  
the Plaintiffs at various stages of the construction process. This email exchange was situation-  
specific and involved Carm covering for Metcalfe during an extended absence from the project.  
[161] To the extent that the Defendants are suggesting that this email exchange reflects some  
sort of general transfer of the oversight responsibility for the project from Metcalfe to Carm, I  
am unable to accept this contention. Carm insisted that it never occurred to him that Metcalfe  
was not the general contractor. Further, Carm’s evidence was that he did not instruct any of the  
trades on how to perform their functions. He maintained that he was not paid by the Plaintiffs to  
supervise the trades. I accept his evidence on all of these points. Metcalfe’s role and legal  
responsibilities as general contractor remained unchanged.  
[162] As regards the finishing work that took place following lock-up, Carm’s increased  
oversight role was, in my view, consistent with his role a designer for the project. However, I  
reject any suggestion by the Defendants that Carm was ever the general contractor on the project.  
On the evidence before me, I am satisfied that this was Metcalfe’s role throughout.  
[163] Metcalfe’s contradictory evidence on this point is, as previously stated, troubling. I am  
satisfied that Metcalfe’s failure to properly supervise the project as a result of his personal travel  
commitments, together with his focus on his upcoming retirement, are the principal reasons that  
he failed to note and address the short-cuts and construction deficiencies of the various sub-  
trades that plagued the project to the lock-up stage. While I accept the proposition that it is  
important to consider carefully Carm’s role in some of the key decisions taken during the course  
of construction, I approach Metcalfe’s evidence in this regard with some considerable  
skepticism, particularly his attempts to deflect responsibility to others, notably Carm.  
[164] I am satisfied that Metcalfe and Tru-Square remained the general contractor for the  
project after agreeing to complete the residence on a cost-plus basis.  
3. Breach of Contract  
[165] The Plaintiffs led a substantial quantity of evidence highlighting the various deficiencies  
that were discovered by experts retained following the Defendants’ refusal to address the leaking  
windows and, ultimately, the Defendants’ abandonment of the project. This evidence is set out in  
the various expert reports prepared by Bjornson, Matthews, and Kraychy, as well as the evidence  
of the Plaintiffs’ remediation contractor, Juniper. In response, the Defendants led evidence  
challenging some of the observations and conclusions of the Plaintiffs’ experts and called their  
own expert.  
[166] The Plaintiffs rely on these specific construction deficiencies in support of their  
contention that the Defendants are in breach of contract relative to their construction of the  
Plaintiffs’ residence. I will address those deficiencies in detail later in these Reasons.  
 
Page: 30  
C. Liability in Tort  
[167] The Plaintiffs contend that the Defendants owed a duty of care based on their contractual  
obligation to construct the residence, that they breached that duty of care through the negligent  
performance of their contractual obligations, and that the Plaintiffs suffered damage as a result.  
[168] The Plaintiffs also say that Metcalfe should be held personally liable for the negligent  
construction performance of Tru-Square. Specifically, the Plaintiffs assert that the law provides  
that principal individuals may be held personally liable where the work performed is inherently  
dangerous or where a principal of the defendant contractor induces a breach of contract.  
[169] Metcalfe was aware from his pre-contract discussions with the Plaintiffs that they were  
seeking his assistance in the construction of their dream retirement home. Before entering into  
the agreement, Metcalfe had occasion to review the Swanbys’ architectural plans and, as such,  
was aware of their design specifications. Further, Metcalfe presented himself as a custom home  
builder who had at least some experience in building high quality homes.  
[170] In their written brief, the Plaintiffs suggest that Tru-Square and Metcalfe were under a  
duty of care “to fulfill the contract in the manner expected of a reasonable [sic] competent and  
careful custom home builder, having mind to established industry custom and practice.” In this  
regard, the Plaintiffs cite Vermillion at para 124, wherein the Court, citing Dickson J (as he then  
was) for the majority in Fraser-Reid v Droumtsekas, [1980] 1 SCR 720 at 726, states that the  
relevant question is, “[D]id the builder act as a competent and careful builder would have acted  
in what he did or did not do?”.  
[171] I accept the Plaintiffs’ contention that the scope of the Defendants’ duty of care is  
informed by both the terms of the contract and other general principles. In this instance, the  
terms of the contract specified that the Defendants were to meet Code requirements and to  
“strive for high quality”.  
[172] On the expert evidence before me, I am satisfied that the Code represents only the  
minimum standards required by law. In this regard, the Plaintiffs cite Holtslag v Alberta, 2006  
ABCA 51 at para 35, where Sulyma J (ad hoc) for the Court stated:  
The provisions of the Code are technical requirements relating to minimal health  
and safety standards and the use of safe and adequate building materials (see para.  
10 and excerpt from the Preface to the National Building Code of Canada 1990 in  
Part D above). As the respondent submitted, the Code cannot be said to be a  
textbook on building design. ...The statute establishes a regulatory scheme for  
building products and is intended only as a set of minimum standards for the  
benefit of the public at large.  
[173] The Plaintiffs maintain that the standards applicable to custom home building are higher  
than those prescribed in the Code. Bjornson, Matthews and Kraychy all testified that the Code is  
a set of minimum construction standards. The Defence expert, Hamman, confirmed that a  
reputable construction manager seeks a higher standard then merely meeting the minimum  
requirements in the Code: Evidence of Hamman (Cross), October 15, 2019, at 11:41 a.m.  
[174] In her expert report, Bjornson stated that many of the provisions of the Code either are  
outdated or have been withdrawn by the Standards Association, and that, for this reason, the  
building industry relies on other standards. Her evidence was that the Code’s minimum building  
 
Page: 31  
standards typically lag behind practices and standards generally applicable to the construction of  
custom-build luxury homes: Evidence of Bjornson (Direct) April 22, 2019 (am). As more fully  
discussed later in these Reasons, she expressed the view that in relation to roofing, the Alberta  
Roofing Contractors Association (“ARCA”) Roofing Application Standards Manual is the  
accepted standard for roofing installation purposes, not the Code’s “extremely outdated”  
provisions.  
[175] Kraychy stated that Metcalfe placed undue reliance on the minimum requirements of the  
Code. Given that Metcalfe was hired to build a custom, luxury home, Kraychy maintained that  
the Code’s minimum standards did not reflect the required accepted standard. He provided  
particulars as to some of the attributes and duties of a reasonably competent and careful custom  
home builder, including:  
a) Providing advice and assistance to clients relative to project budgeting;  
b) On-going communication with clients to ensure they are aware of changes,  
problems and delays in construction;  
c) Working with clients to resolve issue or problems arising during the course of  
construction so as to ensure that clients are properly informed of the status of  
the project. In this regard, the custom home builder is required to offer  
solutions to problems or issues that may arise without compromising overall  
building performance;  
d) Oversight of design and shop drawings to ascertain changes, either required or  
made, and consulting engineering professionals as required to ensure  
satisfactory building performance. Changes to the designed structural  
foundation or framing elements require the custom home builder to seek the  
advice and direction of engineering professionals;  
e) Oversight of sub-contractors to ensure work quality.  
Evidence of Kraychy (Direct) April 25, 2019 (10:45 am 12:20 pm).  
[176] As regards to his responsibility for the material and labours supplied by his sub-  
contractors, Metcalfe acknowledged that “My contractors are my responsibility”: Exhibit 29 at  
84:9-12. Hamman described the general contractor’s responsibility for his sub-contractors in the  
following terms: “if I’ve hired trades, they are me”: Evidence of Hamman (Cross), October 18,  
2019, 2:15 p.m.  
[177] As noted above, the Plaintiffs rely on construction deficiencies in support of their  
contention that the Defendants are in breach of contract relative to their construction of the  
Plaintiffs’ residence. The Plaintiffs rely on these same deficiencies as supporting their claim that  
the Defendants breached their duty of care and are, as such, also liable in tort.  
D. The Deficiencies  
[178] Before turning to consider whether or not there was a breach of this contract and, if so,  
whether the Plaintiffs sustained damages as a result of the breach, I would note that the decision  
in Vermillion confirms that there are implied terms in every building contract. At para 122, the  
Court held:  
 
Page: 32  
Unless the contract or the circumstances indicate otherwise, the contract will  
contain an implied term that the work will be done in good and workmanlike  
manner, the workmen employed on the work will possess the ordinary skill of  
those exercising the particular trade, and the materials will be of good quality and  
reasonably fit for the purpose for which they are used: Heintzman and Goldsmith  
at 4-50. In G Ford Homes Ltd v Draft Masonary (York) Co (1983), 43 OR (2d)  
401, 1 DLR (4th) 262 (CA), Cory J., as he then was, observed that a contractor  
undertaking to do work implicitly undertakes that it will be undertaken with care  
and skill and in a workmanlike manner and will be reasonably fit for the purpose  
for which is it required, unless the circumstances of the contract exclude such  
liability.  
[179] As previously stated, the Plaintiffs led a substantial quantity of evidence highlighting the  
various construction deficiencies. I turn now to reviewing that evidence in detail.  
1. The Foundation  
[180] The Plaintiffs contend that the Defendants failed to meet the appropriate standard of care  
as a general contractor in the custom home trade when they failed to engage an engineer  
regarding the change to architectural design drawings relative to the foundation. Specifically, the  
Defendants elected to pour a traditional foundation, rather than the ICF foundation specified in  
the drawings.  
[181] There is no dispute that an ICF foundation consists of the standard 8-inch wide poured  
concrete wall supplemented by rebar reinforced polystyrene forms that remain in place. In a  
traditional foundation, the temporary forms are removed after the concrete has cured.  
[182] I accept Kraychy’s evidence that this change should have been reviewed and approved by  
an engineer to ensure that it did not impact on other structural elements of the construction.  
According to Kraychy, Metcalfe should have obtained the proper engineered drawing for the  
new foundation. Similarly, he needed to make sure that the consulting engineer contacted  
ZyTech to discuss the implications, if any, of using a different type of foundation on the overall  
planned framing structure for the residence. I am satisfied that Metcalfe failed to take any of  
these steps.  
[183] While I note that Metcalfe was insistent that the change in the type of foundation  
employed in this instance had no impact in terms of the dimensions of the perimeter walls, I am  
satisfied that it represented a sufficiently significant deviation from the original plan as to  
warrant expert review. In a November 19, 2012 email to the Plaintiffs, Metcalfe apologized for  
the quality of the framing, noting: “I really appreciate how patient and understanding you have  
been during the building process and am sorry that the framing wasn’t done as well as it should  
have been which has caused us some problems especially in the bathrooms”: Exhibit 1-G-23, p  
83. It is not clear whether or not these framing issues were related to the wall overhang relative  
to the foundation.  
[184] In his written report, Matthews noted the lack of vertical alignment of wood framed walls  
supported on foundation walls at the east elevation of the residence. Specifically, he noted (at p  
5) that “the bottom plate of the stud wall supported at grade level was projecting significantly  
beyond the face of the foundation wall, and vertical support for the wall was compromised”. By  
way of remediation, he noted that the thickness of the concrete foundation wall was increased to  
 
Page: 33  
provide support for the full thickness of the supporting wall (at p 5). He also noted (at p 6) that  
the “substitution for ICF with conventional formwork has potentially significant structural  
impacts”.  
[185] The Defence expert, Hamman, expressed the view that the wall overhang was Code-  
compliant and, as such, acceptable. He recognized, however, that the overhang would have to be  
addressed in subsequent framing steps. Matthews, on the other hand, felt that the as-built  
condition was not satisfactory. He conceded that the situation was Code-compliant, but asserted  
that it did not satisfy industry standards. Both Matthews and Kraychy believed that the change  
from the ICF to traditional foundation was a likely cause of the wall misalignment.  
[186] In my view, the remediation recommended by Matthews was a reasonable response to the  
concern relative to the vertical support available to the wall.  
[187] In final argument, counsel for the Defendants suggested that Juniper’s evidence was to  
the effect that this recommended repair was never actually made. Assuming that to be the case,  
then Juniper obviously did not bill the Swanbys for this work.  
[188] Bjornson also raised issues with respect to waterproofing and damp-proofing relative to  
the foundation. In her report, and confirmed in her rebuttal report, Bjornson observed that  
waterproofing and damp-proofing did not meet s 9.13.2.4.(2) of the Code, which required that  
holes in dampproofed concrete walls be sealed off with cement mortar or damp-proofing  
material. No treatment to the concrete ties at the foundation damp-proofing was observed on the  
SE elevation, contrary to s 9.13.2.4.(2). Bjornson also suggested that best practice is to include a  
drainage mat installed to the foundation perimeter, as per s 9.14.5.1 of the Code.  
[189] The Defendants challenge certain aspects of Bjornson’s evidence in this regard, notably  
her conflicting evidence as to whether or not the absence of a drainage mat amounts to a Code  
violation. The Defendants also question the extent of the absence of damp-proofing observed by  
Bjornson, though I note that the Hamman made no observations in this regard. In accepting the  
evidence of Bjornson on this latter point, I note that there is no evidence that the Plaintiffs took  
any steps to address this issue during the remediation process. Accordingly, it is not strictly  
necessary for me to make any specific findings in this regard.  
2. The Leaking Windows  
[190] Ms. Swanby first became aware of the leaking windows on May 23, 2013. She observed  
water pooling by the great room window on the main floor. Water was also present half-way  
across the 800 square foot Bonus Room above the garage, as well as in the doorway above the  
downstairs bedroom and leaking into the basement. As described earlier in these Reasons,  
Metcalfe was immediately alerted to the situation by Ms. Swanby, but took several days to attend  
the job site. He denied responsibility for the problem and failed to take any steps to assist the  
Plaintiffs in the assessment or remediation of the problem.  
[191] When Snyder attended the residence to inspect the leaking windows, he was provided  
with a copy of recessed window installation detail that Carm had given to Metcalfe as an  
example of this type of installation, Exhibit 1-A-4. He conducted a detailed examination of some  
of the leaking windows. After removing the stone sill, Snyder determined that a lot of the details  
set out in the drawing, Exhibit 1-A-4, had not been followed. Specifically, he referred to the fact  
that there was no weeping rope and no foam rod and sealant. He also determined that some of the  
laps (waterproofing) had not been installed properly. Further, Snyder noted that the metal  
 
Page: 34  
flashing at the bottom of the window was bent upward “a little bit” by the stone sill. He noticed  
that the bottom flashings on other windows were also slightly bent.  
[192] While on site, Metcalfe suggested to Snyder that the impact of the stone sill pushing up  
the metal flashing was the cause of water entering the residence. Snyder disagreed with this  
suggestion, observing that if the window had been properly sealed, the fact that the flashing was  
somewhat bent would not result in water leaking into the residence.  
[193] Snyder subsequently issued a report, Exhibit 1-D-5, in which he concluded:  
Upon inspection of the windows (Master bedroom & Bonus room) we noted that  
the window was not completed as per drawing specifications due to water pooling  
behind the stone Lintel. We did not observe weeping ropes or tubes used to drain  
access water from the windows in question. It is also noted the drip flashing was  
bent on a reverse grade towards the window with no foam rod and sealant  
observed throughout. These issues created the water to pool behind the lentil [sic]  
and break the window wrap therefore allowing water to penetrate the wall.  
[194] In terms of corrective actions, Snyder’s report recommended the following:  
Stone to be removed as needed and lintel lowered to accommodate drip flashings  
installation as per drawing details. (Positive slope, Foam Rod and Sealant).  
After stone (as needed) is removed verify building wrap installation is as per  
drawing details and correct if necessary, before reinstalling stone.  
Weeping ropes/tubes to be installed under lentil [sic] as per drawing details.  
[195] Snyder provided a quote to repair the windows (Exhibit 1-I-22) in the amount of  
$11,530.00, inclusive of GST.  
[196] Water damage was observed by Bjornson at all main floor windows on the rear elevation  
of the residence and below the windows of the Bonus Room above the garage. Bjornson found  
that this water damage was consistent with the Swanbysreports of water leakage. In her report,  
Bjornson noted that there were water stains visible on the floor above the garage, under the  
windows at the back of the house, and in the master bathroom area. In conjunction with her  
investigation, Bjornson conducted flood testing by applying a light spray of water via hose onto  
the exterior of various windows. Flood testing on the second story window above the garage  
showed water entering the window sill at two locations within minutes.  
[197] The Plaintiffs maintain, relying on Bjornson’s expert opinion, that the windows were  
improperly installed by the Defendants, and that this improper installation gave rise to the  
ensuing leaks. The Plaintiffs contend that the window leaks were not the result of deficient or  
problematic design issues, as alleged by the Defendants, but rather the improper installation  
undertaken personally by Metcalfe and the framer. The Plaintiffs point to the fact that Metcalfe  
was personally responsible for the application of the peel-and-stick membrane associated with  
the required creation of a continuous moisture barrier, during the window installation.  
[198] The Defendants advance several different arguments in their denial of any responsibility  
for the leaking windows. First, they suggest that the stone mason, John Lawrence, damaged the  
installed window assembly when installing the sill stones. According to the Defendants,  
Metcalfe’s role was complete by that point in time as the installation of the stone occurred well  
after the lock-up stage had been reached. Second, the Defendants seek to attribute to Carm a  
Page: 35  
good deal of the responsibility for the leaking windows on the basis that he initiated this change  
from the original design and provided the design detail to complete the recessed installation.  
Third, the Defendants say that Metcalfe warned Ms. Swanby and Carm that the recessed  
windows were a bad idea and that he would not provide a warranty that they would not leak.  
According to the Defendants, McEwen also warned Carm about the recessed installation.  
Finally, the Defendants challenge the Plaintiffs’ decision to replace all the windows, rather than  
effecting the repairs proposed by Snyder.  
[199] There is conflicting evidence relating to the installation of recessed, as opposed to flush-  
mount, windows and doors. It is common ground that the original design called for flush-  
mounted windows. I accept Ms. Swanby’s evidence that, following the signing of the contract,  
Carm proposed, and the Swanbys agreed to, a change in the design to recessed installation of the  
windows. Carm provided Metcalfe with a drawing used on a previous project to help explain the  
concept, specifically the framing and installation requirements, as Metcalfe was confused by the  
specifications. Carrm also provided Metcalfe with some photographs illustrating this earlier  
installation, though these photographs are not in evidence. Metcalfe advised Ms. Swanby that he  
had never previously undertaken such an installation and was not sure that it would work. The  
framer, McEwen, was also unfamiliar with this type of window installation and was “leery”  
about this specification.  
[200] Metcalfe’s evidence was that he believed from the outset that the recessed design was a  
mistake. McEwen testified that he told both Metcalfe and Carm that he did not think that the  
recessed windows were a good idea given his belief that they would leak. According to McEwen,  
Carm assured him that he had figured out the recessed installation. Ultimately, McEwen agreed  
to install the recessed windows, but told Metcalfe and Carm that he would not guarantee that the  
windows would not leak. McEwen had no recollection of ever speaking to the Plaintiffs about  
the recessed windows and doors.  
[201] According to Carm, neither Metcalfe nor McEwen ever expressed any concerns to him  
regarding the recessed installation specification. He maintained that Metcalfe or McEwan could  
have easily indicated their reluctance or unwillingness to install the windows in this fashion but  
did not do so. In this regard, I note that Metcalfe refused to undertake the project if the Plaintiffs  
insisted on the use of an ICF foundation as specified in the design drawings. Whatever hesitation  
or reluctance Metcalfe may have had about the recessed installation of the windows, there is no  
dispute that he went ahead and installed the windows in that fashion and subsequently billed the  
Plaintiffs for recessed windows.  
[202] I approach McEwen’s evidence with some caution. His evidence contained repeated  
references to “I would have” or “I would not have” without certainty as to what he actually did in  
this instance. For example, he seemed uncertain as to whether there was a building permit for the  
project. At one point, he indicated that he was not sure, but later gave evidence regarding the  
permit being a one-page document. Overall, he seemed to have a limited recollection of what  
actually took place in this instance.  
[203] I accept Carm’s evidence that Metcalfe was confused by the specification, and that this  
was the reason that he provided a drawing used on an earlier project, together with some  
photographs. Significantly, the drawing Carm provided included disclaimers that the drawing  
was for design purposes only and that the responsibility for proper installation of the windows  
lay with the contractor. Carm also gave evidence that he met with Metcalfe on several occasions  
Page: 36  
to discuss the recessed window installation and, specifically, the special framing requirements to  
accommodate the stone returns around the recessed windows and doors.  
[204] After the windows had been installed, Metcalfe presented Ms. Swanby with the invoice  
covering the window installation and advised her verbally that he would not cover the warranty  
on the windows. In his testimony, Metcalfe conceded that he did not disclaim any warranty on  
the installation of the windows until he issued Invoice 118 on September 1, 2012, well after the  
windows had been installed: Exhibit 1-C-11. The invoice contains the following language:  
Peel and stick, chaulking (sic), extra lumber and personal labor for framing to  
recess doors and windows (does not include extra labor from framer) As this does  
not meet building code warranty is void in regards to any moisture entering  
building (emphasis added).  
[205] Metcalfe’s disclaimer makes no reference to any specific provision of the Code. In cross-  
examination, Metcalfe conceded that he made no investigation to determine whether or not the  
recessed installation was Code compliant or not.  
[206] In my view, Metcalfe’s disclaimer of responsibility for the installation of the recessed  
windows came too late to relieve him and Tru-Square of responsibility for any deficiency arising  
from the installation of the windows. Under the circumstances, Metcalfe should have either  
refused to install the recessed windows, as he refused to utilize the ICF foundation, or sought  
written instructions from the Plaintiffs to proceed with the recessed installation at the Plaintiffs’  
sole risk.  
[207] The Defendants seek to buttress their denial of responsibility for the leaking windows on  
a number of other grounds. First, they point to the fact that the Plaintiffs ultimately elected not to  
reinstall the windows in a recessed configuration given Juniper’s advice that he would not  
warranty windows installed in this fashion. Bjornson also expressed concerns relating to some of  
the details associated with the original plan set out in Exhibit 1-A-4 and recommended to the  
Plaintiffs that they flush-mount the reinstalled windows.  
[208] While Bjornson had reservations about some of the details of the design, she expressed  
the view that it was “not unexecutable.” She also indicated that the recessed windows should  
have had a design detail specifically prepared for this house, saying “It is a difficult design, but it  
can be achieved.”  
[209] I am not persuaded that the after-the-fact views of either Juniper or Bjornson in this  
regard are of any assistance to the Defendants. The fact that the Plaintiffs followed the strong  
recommendation not to reinstall the windows and doors in a recessed fashion during the  
remediation process does not change the fact that Metcalfe installed the windows without ever  
providing a similar strong recommendation.  
[210] The Defendants also rely on the terms of their agreement with the Plaintiffs to construct  
only to the lock-up stage. In particular, the Defendants cite the provision of the contract, Exhibit  
1-C-5, that specifically excluded the exterior stonework. As such, the Defendants say that they  
are not responsible for the work of Lawrence, the stone mason. According to the Defendants,  
Lawrence bent the window flashings while installing the stone sills underneath the windows,  
thereby causing the windows to leak.  
[211] Lawrence was called as a defence witness and gave evidence with respect to the leaking  
windows. He testified that he had no experience installing stone sills where the windows were  
Page: 37  
recessed. He could not recall if he was provided with a copy of Exhibit 1-A-4, the recessed  
window detail that Carm provided to Metcalfe.  
[212] There is no evidence before me as to any specific discussions between Lawrence and  
Metcalfe regarding the special requirements of the recessed window installations. According to  
Carm, Metcalfe was on site frequently during the time that Lawrence was engaged in the  
installation of the stone veneer to the exterior of the residence. As such, Carm assumed that they  
must have had discussions, though Carm claimed that he was not a party to any such discussions.  
[213] Lawrence had some difficulty installing some of the stone stills so that they would fit  
under the windows. Some of the stones had to be made thinner to fit. He also indicated that some  
of the flashings “got pushed up a bit”, but that it was “OK” and he did not feel that it was a big  
issue. In response to the question whether he had any concerns about the windows leaking,  
Lawrence responded (May 14, 2019 (Direct), 11:24 a.m.):  
Q
Did you have any concerns about the window openings  
leaking?  
A
Well, I had never seen a design like that, and to me it’s  
creating a trap, looking at the design.  
Q
A
Q
A
Q
A
What do you mean when you say creating a trap?  
Well it’s creating a spot for water to pool.  
And where would it pool?  
At the sills.  
At the sill where the sill meets the house?  
Yeah.  
[214] Lawrence confirmed his familiarity with weeping ropes and tubes but explained that  
weep holes and ropes are not installed in a closed system like the one he was dealing with at the  
Swanby residence.  
[215] The Code is silent on the installation of windows but requires at section 9.27.1.1 that no  
precipitation penetrate the interior of the building:  
Minimizing and Prevent Ingress and Damage  
1) Except where exterior walls are protected from precipitation or where it can be  
shown that precipitation ingress will not adversely affect occupant health or  
safety, exterior walls shall be designed and constructed to  
a) Minimize the ingress of precipitation into the assembly; and  
b) Prevent the ingress of precipitation into interior space.  
[216] According to Bjornson, the discontinuous moisture membrane and holes around the  
windows allowed water to enter under the window framing and enter the building around the  
Page: 38  
rough opening. Bjornson concluded that the breaks in the moisture barrier below the windows  
caused the leaks and led to the long-term damage to the interior components and the potential for  
fungal growth. I accept her evidence that the deficiencies were related to installation issues and  
not design issues. She maintained that if the windows had been properly installed, “they were not  
likely to leak”: Evidence of Bjornson, Re-Direct, April 24, 2019, 4:29 p.m.  
[217] Notwithstanding that the working drawings for the installation of the windows called for  
the use of sealant, a minimal sill flashing was installed at the base of the windows with an  
inadequate slope and no sealant. Moisture was directed along the window flashing, contrary to s  
9.7.4.2 of the Code, which requires the application of caulking to prevent the entry of water into  
the structure.  
[218] At the base of the windows, a minimal sill flashing was installed with an inadequate slope  
and no sealant, despite sealant use being indicated on the window installation drawings. Moisture  
was directed along the window flashing, contrary to the Code requirements in section 9.7.4.2:  
Caulking Compound  
1) Caulking shall be provided between window frames or trim and the exterior  
siding or masonry in compliance with Subsection 9.27.4.  
9.27.4.1 Required Caulking  
1) Caulking shall be provided where required to prevent the entry of water into  
the structure.  
2) Caulking shall be provided between masonry, siding or stucco and the  
adjacent door and window frames or trim, including sills, unless such  
locations are completely protected from the entry of rain.  
[219] Batt insulation was installed between the window frame and rough opening. While this  
installation did not violate the Code, Bjornson expressed the view that it is inconsistent with best  
practices. As such, she pointed to the 2014 Code at section 9.7.6.1.13: “Windows, doors, and  
skylights shall be sealed to air and vapour barriers.” According to Bjornson, this change to the  
Code represents formal acknowledgement of a best practice. She recommended that spray foam  
be applied consistently to the full depth instead of having a discontinuous barrier.  
[220] Hamman confirmed that the window installation was not Code-compliant. Specifically,  
he found that the rough openings were not properly framed, leading to water being directed into  
the building.  
[221] According to Juniper, all but four or five of the windows had to be replaced. All the main  
floor windows showed signs of leakage. I accept Bjornson’s evidence that the window  
installation did not satisfy Code or industry standards or best practices. Based on the evidence  
before me, it seems clear that several factors contributed to the leaking windows, including:  
a) The windowsrough openings were improperly framed such that the sill stone  
directed water towards the building, rather than away from the structure;  
b) The required peel and stick membrane was not installed properly so as to interrupt the  
continuity of the seal and to direct moisture towards the interior;  
Page: 39  
c) There was no back dam at the interior side of the framing at the rear of the window  
cavity. Sloping the window framing or installing a shim would have met this  
requirement;  
d) The flashings were bent and flat, as opposed to having a 6% minimum slope. There  
were no flashings between the stucco and the stone on the horizontal cladding  
transitions. Similarly, there were no end dams on any of the flashings;  
e) As installed, the windows did not accord with the specifications in the building  
drawings. Specifically, there was no weeping rope and no rain screen fabric installed  
behind the stone veneer. Likewise, there was a mix of foam and batt installation  
around the windows when the drawings called for foam only.  
[222] I am satisfied that the windows were improperly framed and installed by the Defendants  
and their framer, and that this improper installation led to the various leaks. Bjornson and  
Hamman agreed that the rough openings for the windows had been improperly framed.  
Moreover, Metcalfe was fully aware of the special framing requirements associated with the  
recessed installation, including the space required to accommodate the stone returns. Bjornson  
also identified a series of additional installation deficiencies that compounded the framing  
problems.  
[223] I do not accept the Defendants’ contention that the leaking windows were entirely the  
result of Lawrence’s installation of the stone sills that pushed up and bent the previously  
installed metal flashings. Snyder rejected Metcalfe’s assertion that this was the cause of water  
entering the residence. Having carefully considered the detailed evidence adduced at trial on this  
issue, I find that the slightly bent flashings were not a factor contributing to the leaking windows.  
While bent flashings were clearly not a “best practice”, the underlying cause of the window leaks  
was entirely the result of improper installation, including improper framing of the rough  
openings for the windows.  
[224] Regardless of Metcalfe’s role post lock-up, I am satisfied that he had a responsibility to  
take reasonable steps to ensure the integrity of the window installations that clearly formed part  
of the Lock-Up Contract. This responsibility included collaborating with Lawrence on the  
installation of the doors and windows. Metcalfe’s lack of experience with the installation of  
recessed windows and doors should have heightened his diligence in ensuring that Lawrence was  
fully aware, and fully understood, the special requirements for this somewhat unique feature. I  
am satisfied that Metcalfe failed to take these steps.  
[225] Lawrence was one of the Defendants’ trades, hired by the Defendants to complete the  
stonework on the exterior of the residence. I am satisfied that the Defendants were responsible  
for at least this aspect of Lawrence’s work on the project, either as the general contractor or as a  
project coordinator with some oversight responsibilities for the project. I am satisfied that these  
oversight responsibilities at the very least included the obligation to work collaboratively with  
Lawrence on a very complex window installation that had been largely completed under the  
terms of the lock-up contract.  
[226] The Swanbys accepted Bjornson’s advice not to re-install recessed windows. In addition,  
Juniper told Ms. Swanby that he would not warranty the labour on the installation of the new  
windows if the recessed design was retained. He gave evidence that he believed that the design  
of the recessed windows was “poor” and that there were lots of avenues available for the  
Page: 40  
windows to fail. The flush-mount reinstallation involved some additional framing costs, but such  
costs were considerably less than the anticipated costs associated with a recessed re-installation  
and, overall, a less costly repair option.  
[227] Bjornson recommended replacement of the windows. Her inspection of the removed  
windows revealed residual foam and sealant, damaged frames, and broken flanges. She also  
noted that the operation of some of the windows appeared to be difficult. Further, her  
understanding was that the manufacturer’s product warranty was likely voided once the windows  
were removed. She acknowledged that it might be possible to re-use the windows in certain  
circumstances, but that the contractor would have to be confident in accepting responsibility for  
the used product.  
[228] Juniper explained that when a window is removed, it is no longer a “new” window. A re-  
installed window would no longer be covered by the manufacturer’s warranty, though the labour  
would be covered by warranty. Juniper testified that 4 or 5 windows in the home were found to  
have no issue and were never removed or replaced.  
[229] Hamman confirmed that a contractor would warranty the re-installation of windows only  
if it was certain that they were in proper condition. He said his experience suggested that the  
windows could be reinstalled without affecting the manufacturer’s warranty if care is taken not  
to damage them during the removal process. In his written report, Hamman recommended that  
the windows be re-used following the Code method of lapped blueskin. During his testimony, he  
acknowledged that the Code does not refer to such a method, but stated nonetheless that it was  
best practice. He acknowledged that his expert report was in error in this regard.  
[230] Hamman acknowledged that he did not have an opportunity to inspect the windows after  
they had been removed. In cross-examination, he conceded that, to the extent that Bjornson’s  
conclusions regarding the condition of the windows was correct, they would need to be replaced.  
He did not factor window replacement in his suggested remediation budget.  
[231] I am satisfied that the Plaintiffsdecision to replace the windows was reasonable under  
the circumstances. In my view, the level of confidence required for a contractor to re-install and  
provide a warranty for the used windows was missing in this instance. I am also satisfied that the  
manufacturer’s product warranty would have been voided due to damage on removal.  
[232] The Plaintiffs spent approximately $31,000 to replace all of the windows, save for the  
four or five windows that were determined not to require replacement and the decision to  
eliminate one of the windows that had been removed. I am satisfied that this was a reasonable  
expenditure under the circumstances.  
3. Bonus Room  
[233] The Plaintiffs maintain that there were several construction deficiencies relating to the  
Bonus Room, a large room located above the garage.  
a) Roof  
[234] During the course of their investigative work, the Plaintiffs determined that the roof  
trusses in the Bonus Room were cut and not properly connected to the ridge beam. A number of  
trusses were also found to be oriented on their weak axes. Further, the 34-foot long steel I-beam  
was found to lack proper connection to the outside walls.  
 
Page: 41  
[235] In his report (at p 10), Matthews expressed the following concerns with respect to the  
Bonus Room roof:  
a) Lack of connection of steel ridge beam to supports;  
b) Structural inadequacy of support header above windows at east and west walls;  
c) Absence of hangers at trusses at numerous locations;  
d) Non-approved field-modification of trusses by cutting;  
e) Missing nails in hangers;  
f) Lack of fit of trusses evidenced by trussed not fully seated at hangers;  
g) Split wood components due to nailing;  
h) Absence of nails at dimensional lumber components at truss support detail at walls.  
[236] In his evidence, Metcalfe acknowledged that he was personally involved in some of the  
framing in the Bonus Room. He maintained that that there were no cuts or other modifications to  
the trusses supplied by Zytech. He also stated that the I-beam was well secured and that he was  
satisfied that it had been wedged into position in such a fashion that it was not likely to move.  
Further, to the best of his knowledge, Metcalfe believed that the hangers supplied by Zytech had  
been installed. Finally, he challenged one of the photographs presented to him as even being a  
truss, “guessing” that it had been cut during the process of de-construction.  
[237] I accept Matthewsevidence that the roof system in the bonus room was significantly  
compromised as a result of the structural irregularities he noted in his report and related in his  
evidence. Specifically, he testified that good practice requires proper connection of the trusses to  
the ridge beam. Similarly, good practice dictates that truss members should not lie on their weak  
axis and should not be modified on site. In this regard, he observed that the roof is a critical  
structure, the failure of which poses significant safety risks to the occupants of the residence.  
Hamman conceded that the roof in the Bonus Room lacked some connection details and required  
additional blocking.  
[238] According to Matthews’ report (at p 10), “extensive remedial structural work was carried  
out to address the numerous deficiencies observed.” Matthews prepared detailed drawings  
illustrating remediation details, Exhibit 1-A-7, including SK-C, a drawing detailing the required  
Bonus Room truss support, and SK-D, the required Bonus Room truss support cradle.  
b) Floor  
[239] According to Juniper, the Bonus Room floor was missing at least some of the blocking  
between the floor joists stipulated in the Zytech drawings. In addition, Juniper testified that a  
portion of the tongue and groove sub-floor had been cut out in the area near the windows. He  
also observed that there was a floor joist missing.  
[240] Metcalfe and McEwen both testified that blocking was installed but referenced a Zytech  
drawing that indicated blocking was not required. In support of their contention in this regard,  
they produced Exhibit 38, a drawing that appears to be an enlargement of a portion of the  
complete Zytech drawing, Exhibit 1-A-9. Metcalfe’s evidence was that he did not notice that a  
floor joist was missing.  
[241] I accept Juniper’s evidence that the complete Zytech drawing for the Bonus Room  
included a requirement for blocking. The fact that Metcalfe and McEwen included some  
blocking strongly suggests that this was always a structural requirement. No satisfactory  
Page: 42  
explanation was ever provided as to how Exhibit #38 came into existence or that it was actually  
relied upon by the Defendants.  
[242] The recommended remediation involved installation of a new sub-floor, the requisite  
blocking identified in the Zytech drawing (Exhibit 1-I-35, p 18, top photograph) and installation  
of the missing floor joist.  
[243] Under the circumstances, I am satisfied that the remediation work effected by the  
Plaintiffs in this regard was both reasonable and appropriate.  
c) Insulation and Ventilation  
[244] In the vaulted areas of the attic, Bjornson reported that the thickness and installation  
method of insulation blocked the soffits, thus preventing effective cross-ventilation between truss  
cavities. She stated that this amounted to a violation of the Code.  
[245] During his investigation, Juniper removed some of the drywall in the Bonus Room  
ceiling and determined that the insulation batts were touching the plywood roof sheeting such  
that there was no room for air to circulate between the roof and the insulation.  
[246] The roof and attic ventilation requirements are outlined at section 9.19.1.2.(3) and section  
9.25.2.4(6) of the Code:  
9.19.1.2 Vent Requirements  
3) Required vents may be roof type, eave type, gable-end type or any combination  
thereof, and shall be distributed  
a) Uniformly on opposite sides of the building;  
b) With not less than 25% of the required opening located at the top of the  
space, and  
c) With no less than 25% of the required openings located at the bottom of  
the space...  
9.25.2.4 Installation of Loose-Fill Insulation  
6) Where soffit venting is used, measure shall be taken  
a) To prevent loose-fill insulation from blocking the soffit vents and to  
maintain an open path for circulation of air from the vents into the attic or  
roof space, and  
b) To minimize airflow into the insulation near the soffit vents to maintain  
thermal performance of the material.  
[247] According to Bjornson, the ventilation in the Bonus Room was not compliant with the  
Code, in that the insulation prevented proper air flow as it was installed too close to the roof  
sheathing. In addition, there were no continuous ridge vents. Further, the vents were not properly  
connected. Specifically, the Code required two-inch to three-inch spaces between the cavities,  
whereas the as-built state involved only one to one-half inch space between cavities.  
[248] Hamman did not inspect the attic space of the Bonus Room. The Defendants made no  
observations about the ventilation space at the trusses, though they pointed to the fact that there  
was a four-inch space on top of the insulation allowing for ventilation. Nevertheless, Bjornson  
Page: 43  
expressed the view that four-inch spaces in the individual cavities were insufficient for the  
purposes of cross-ventilation.  
[249] At Bjornson’s direction, Juniper installed Styrofoam baffles next to the roof sheeting and  
then insulation batts in order to create sufficient room for air to circulate between the insulation  
and the roof. In order to increase the R factor to R-40, Bjornson also directed Juniper to apply  
spray insulation over the insulating batts. He estimated that spray insulation is approximately  
twice the cost of insulation batts, but noted that there was insufficient room in the cavity to  
accommodate R-40 batt insulation and, further, that no plastic vapour barrier was required when  
using spray insulation.  
[250] I accept the evidence of Bjornson and Juniper as regards these deficiencies and the  
necessary remediation. While the Defendants challenge the need for a building envelope  
engineer to make this type of recommendation, I am satisfied that this fell within the proper  
scope of Bjornson’s very thorough review of the as-built construction of the residence at the time  
of her involvement.  
d) Stairs  
[251] There is a conflict in the evidence as to the as-built condition of the Bonus Room stairs,  
particularly the connection between the stairs and the floor.  
[252] According to Juniper and Matthews, the stairs were not connected to the floor system  
either with bolts or hangers, as required by the Zytech drawings: Exhibit 1-A-2, SWA922.  
Limited finishing materials, including drywall, were holding the stairs in place, together with a  
few nails. Matthews’ evidence was that the stair to floor connection was very deficient and  
presented a risk of detachment or collapse. He noted the lack of fasteners in suggesting that the  
construction represented poor workmanship.  
[253] Metcalfe’s evidence was that McEwen installed the stairs, attaching them at the top, but  
that Metcalfe was personally involved in nailing and screwing every joist to wall studs. McEwen  
pointed to Exhibit #38, which appears to be an enlargement of the Zytech drawings. As in the  
case of the Bonus Room floor blocking, the portion of the drawing containing detailed  
specification notes is missing from the enlarged version.  
[254] McEwen’s evidence was that he “would have screwed” the stairs into the floor system  
and then to the walls and that he was the person who put the screws in: Evidence of McEwen  
(Direct), May 13, 2019, 2:16 p.m. In my view, there are some serious issues with the reliability  
of McEwen’s evidence generally. As previously noted, it was replete with language such as “I  
would have...” or “I wouldn’t have...” without certainty as to what he actually did. I am satisfied  
that, though well-meaning, he had limited recollection of what actually took place. In the result, I  
find that his evidence is not reliable and I attach little weight to it.  
[255] Hamman made no observations as to any defects relative to the stairs. His evidence was  
simply that they appeared to be pinned at both ends and that he conducted no further  
investigation.  
[256] Given the contradictions in the evidence of Metcalfe and McEwen in terms of who  
actually installed the screws alleged to have been employed to connect the stairs to the floor, I  
prefer the evidence of Juniper and Matthews on this point. I am satisfied that the stairs were only  
minimally connected to the rest of the structure and presented a significant risk of collapse.  
Page: 44  
[257] The Plaintiffsremediation, connecting the Bonus Room stairs in accordance with the  
Zytech drawings through the use of bolts, hangers and backers, was both appropriate and  
reasonable under the circumstances: Exhibit 1-F-35, pp 13, 17 (remediated stairs).  
4. The Garage  
[258] The as-built state of the garage raised a number of concerns. First, the division walls  
between the house and the garage were not insulated to prevent the migration of C0-2 gas from  
the garage into the residence. Second, the garage doors had to be re-installed with new springs.  
Third, open heat runs were found buried in the insulation in the ceiling space with no connection  
to registers: Exhibit 1-G-35, p 15, bottom photograph; p 16, bottom photograph. Juniper said he  
had never seen such a configuration before. Fourth, electrical wires that were intended to be  
connected to various exterior electrical outlets were rolled-up and located behind drywall:  
Exhibit 1-G-35, p 20, lower photograph.  
[259] The garage floor was also determined to be off the foundation’s footing and floating  
above it: Exhibit 1-F-35, p 126, bottom photograph; p 127, top photograph. In other words, the  
concrete slab that represented the garage floor was not connected to the footing.  
[260] The Defendants made no submissions, either orally or in writing, relative to this  
particular construction deficiency.  
[261] Metcalfe offered no explanation relative to the insulation of the division walls between  
the garage and the residence or the need to re-install the garage door. With respect to the open  
heat runs, he maintained that this was common practice, relying in part on hearsay statements of  
the heating contractor, who did not give evidence during the trial. Metcalfe’s evidence with  
respect to the electrical wires located behind drywall was to the effect that the wires would have  
been connected during the final walk-through. The electrician, Dueck, testified that he did not  
complete his work on the residence due to unpaid invoices, but that he would normally do a  
walk-through at the end of a job to test circuits and label wires.  
[262] Metcalfe gave evidence that there was gravel located underneath the garage pad, together  
with a Styrofoam floor heating system. He also stated that there were piles located every 8 feet.  
However, he offered no evidence to confirm his assertions regarding the piles or Styrofoam.  
Further, his evidence on this point was never put to Juniper in cross-examination. Hamman’s  
report makes no reference to this alleged deficiency.  
[263] Metcalfe also maintained that the garage doors were not part of the contract as they were  
one of a number of items that were listed as an allowance. However, I note that the final draw  
invoice 137, Exhibit 1-C-17, lists this allowance as a credit.  
[264] Juniper testified that the remediation work in the garage included installing spray foam  
on the walls separating the garage from the main residence, as well as the ceiling, to protect the  
Bonus Room and the living areas from CO-2 gas. I am satisfied that the Plaintiffs’ remediation in  
this regard was appropriate to address the underlying issue.  
[265] I reject Metcalfe’s explanation that the rolled wires concealed behind the drywall would  
have been detected and connected during the final walk-through. Even assuming that to have  
been the case, there would have been costs associated with the necessary disruption and repair to  
the drywall, as well as the cost of connecting the wires to individual outdoor electrical boxes at  
the time of the final walk-through. As such, I am satisfied that the remediation costs were more  
 
Page: 45  
or less the same as would have been incurred under the scenario outlined by Metcalfe. In my  
view, the Plaintiffs acted reasonably in pursuing this course of action.  
[266] I am also satisfied that the Plaintiffs acted reasonably in adding rebar to the garage pad  
and in pouring concrete underneath the slab to connect the pad to its footing, thereby avoiding  
the risk of breaking the concrete pad. To address this issue, Juniper testified that additional  
concrete had to be poured to fill the void and establish a connection between the footing and the  
garage pad.  
5. Door Threshold Cut-Outs  
[267] There is conflicting evidence on the cutting of the sub-floor in the area of the exterior  
door thresholds for the purpose of making space for the installation of stone sills underneath.  
[268] According to Matthews, the floor sheathing at door thresholds on the east elevation of the  
residence, that is at the rear of the residence leading to the deck, had been cut out by a saw. He  
expressed the view that these cut-outs were neither Code-compliant nor acceptable practice. He  
testified that he had never seen this done before. I accept the evidence of both Bjornson and  
Juniper that water entered the basement through these threshold cut-outs and that water damage  
was visible upon removing the drywall in various rooms in the basement. Similarly, daylight was  
visible through the cut-outs. According to Bjornson, the moisture barrier failed at the threshold  
cut-outs: Evidence of Bjornson (Direct) April 17, 2019.  
[269] Juniper gave evidence regarding the as-built condition, depicted in Exhibit 1-G-35, p 24,  
top and bottom photographs. According to him, water was able to enter the basement as a result  
of the discontinuous nature of the sub-flooring. He described the resulting damage to the drywall  
in the rooms in the basement.  
[270] Metcalfe acknowledged that he provided directions to the framer to cut the thresholds and  
that this was not normal practice. He testified that he took directions from Carm on this matter.  
McEwen’s evidence was to the effect that both Metcalfe and Carm provided directions to him to  
cut the thresholds. In this regard, the Defendants rely on two emails Carm sent to Metcalfe.  
[271] On December 22, 2011, Carm sent Metcalfe a short email that read as follows:  
Jim see attached pictures. On the bottom of the doors there is a space for the stone  
to fit in the larger the better but if I only end up with ¾” I will cut the stone to fit.  
Attached to the email are three photographs. Two of the photographs depict windows, not doors,  
while the third photograph shows two sets of double doors. I do not interpret this email as in any  
way providing “instructions” to Metcalfe to cut the thresholds to accommodate the stone  
installation.  
[272] The second email is dated March 13, 2013, two months prior to the Plaintiffs’ discovery  
of the leaking windows. The relevant portion of the email reads as follows:  
...In our final walk through I pointed out that there was missing stone under three  
doors. I was under the impression that he was going to install it before he packed-  
up. He may not have installed it due to the fact the wood needs to be chiseled out  
under the door in order for him to install it like the other doors.  
[273] Carm says he provided no directions to Metcalfe or McEwen on how to ensure that there  
was a minimum ¾” space below the door openings for stone installation. He maintained that he  
 
Page: 46  
provided photographs to Metcalfe to illustrate similar installations. He testified that his only  
involvement in effecting changes to doors or door openings involved a request made to a mason  
to chisel down some wood at a door on the front side of the house. Carm never saw the changes  
made to the exterior door thresholds and was surprised to see photographs depicting the as-built  
details.  
[274] I accept Carm’s evidence on this point, namely that his only involvement in effecting  
changes to door openings involved one of the doors on the front of the house. Even if there was  
some confusion as to which doors that Carm was referring to in his March 13, 2013 email, the  
interpretation advanced by the Defendants is not reasonable given the language employed.  
[275] It is significant, in my view, that Metcalfe was aware that Carm was not an engineer.  
While Carm’s role in the project is the subject of some disagreement between the parties, as  
discussed elsewhere in these Reasons, I am satisfied that his primary role was as designer and  
co-ordinator and that he never had any responsibilities relative to the construction of the building  
structure or the integrity of the building envelope.  
[276] In my view, Metcalfe was responsible for the structural integrity of the building. Even if  
Carm had provided such instructions, a finding that I am not prepared to make in these  
circumstances, Metcalfe, the general contractor, cannot avoid responsibility on the basis that he  
took instructions from a designer on a matter pertaining to a structural and building envelope  
element. I also note that Metcalfe made no efforts to obtain an engineering opinion regarding the  
threshold cut-outs. Finally, Metcalfe had previously refused to install the ICF foundation  
specified in the Innographic drawings and, indeed, advised that Plaintiffs that he would not build  
the home if they insisted on an ICF foundation. Under the circumstances, I reject his contention  
that he directed McEwen to breach the integrity of the building envelope because he had been  
directed by Carm to do so.  
[277] Matthews directed remediation work, namely to cut back more of the floor sheathing in  
order to tie the floor back in and extend it to the foundation. Juniper gave evidence regarding this  
remediation process. All of the doors along the back deck were removed. At Matthews’  
direction, TGC installed Blueskin silicon, flashing and spray foam in conjunction with the repair  
work. Fortunately, all of the doors could be re-used.  
[278] Hamman agreed that it was “absolutely necessary” to replace the cut-out sheathing:  
Evidence of Hamman (Cross) - April 24, 2019, at 4:09 p.m.  
6. Interior Electrical  
[279] During the investigative process, live electrical wires were located in the master bedroom  
taped up behind the drywall. Live wires were also located underneath the jet tub. Further, a plug  
in the mechanical room had been covered with drywall. The investigative process was  
complicated by the fact that the electrical box was not marked. During the remediation, TGC had  
to trace all the electrical lines throughout the residence in order to label the electrical panel.  
[280] As previously indicated, the electrician, Dueck, did not complete his work at the  
residence because of nonpayment of his invoices. He testified that he had no recollection of any  
wiring behind the drywall in the master bedroom, but did not deny any of the deficiencies  
identified by the Plaintiffs in this regard. Rather, he stated that he does not energize wires until  
he has completed his work and, further, that he would have found such wires through testing at  
the time of completion. Dueck also testified that there were no electrical drawings for the project  
 
Page: 47  
and that he would have labelled the main breaker box at completion. Notwithstanding Dueck’s  
evidence that the wires were not energized, the Plaintiffs properly point out that the remediation  
work required electrical power. The electrical system was, accordingly, activated during the  
remediation process, including the live wires in the master bedroom.  
[281] Metcalfe acknowledged the plug in the mechanical room that had been covered by  
drywall. However, he denied that there were hot wires around the jet tub and stated that leaving  
hot wires behind a master bedroom wall is common practice. I do not accept Metcalfe’s evidence  
on this particular issue.  
[282] The question of remediation on this particular matter was straight-forward. By all  
accounts the work was not finished. As such, completing the project necessarily involved the  
completion of the electrical work by TGC in conjunction with its overall remediation work.  
7. Foundation, Framing and Nail Floor Wall Connection  
[283] The Plaintiffs’ concerns under this heading fall into three related categories. The first  
involves the wall off-set from the foundation. The second relates to the use of non-pressure  
treated lumber near grade-level, while the third relates to alleged non-compliance with the  
Code’s nail requirement for wall to floor connections.  
[284] First, the Plaintiffs say that the deck wall overhung the foundation by approximately one  
and one half to two inches. While this was Code-compliant, the Plaintiffs, relying on Matthews’  
opinion, say that it was not satisfactory from a custom home construction standard. Further, the  
Plaintiffs maintain that Metcalfe’s decision not to follow the Zytech drawings calling for an ICF  
foundation in favour of a traditional foundation, changed the width of the foundation walls.  
Despite Metcalfe’s assurances to the Swanbys that the foundation “looked good”, and his  
direction to McEwen to adjust the framing of the walls to account for the fact that the foundation  
was not square, Metcalfe failed to correct the wall off-set from the foundation: Evidence of  
Metcalfe (Cross) May 10, 2019, 10:20 a.m. Furthermore, Metcalfe knew in the fall of 2011 that  
two wall sections were not square.  
[285] Hamman stated that the wall overhang was Code-compliant and therefore acceptable, but  
acknowledged that action would need to be taken to offset the overhanging foundation in  
subsequent framing steps. He also conceded that he had not accounted for occupancy and live  
loading in reaching this conclusion. Matthews, on the other hand, was of the opinion that the risk  
of the wall off-set from the foundation was that the wall could lose the ability to support vertical  
loads, thereby compromising overall stability.  
[286] Kraychy opined that it is common practice to hire a surveyor to set the elevations  
properly in conjunction with pouring a foundation. Further, he indicated that it is customary to  
get engineered drawings for a foundation. He testified that he has never constructed a foundation  
based on architectural design alone.  
[287] Metcalfe failed to engage a surveyor or obtain engineered drawings for the foundation.  
He also failed to consult Zytech or an engineer on the impact of his planned change to the  
foundation. Both Kraychy and Matthews expressed the view that the change from the ICF  
foundation to the non-ICF foundation was a likely cause of the wall misalignment.  
 
Page: 48  
[288] Matthews prepared a repair detail, Exhibit 1-A-7, S-1, to increase the thickness of the  
foundation in this area. While he testified that he believed that this repair was made, Juniper’s  
evidence was that this did not form part of his remediation work on the residence.  
[289] I accept the Defendants’ contention that this alleged deficiency was never actually  
addressed as part of the overall remediation work. Nonetheless, I accept Matthews’ evidence that  
this misalignment of the foundation and the structural framework of the residence may have been  
Code-compliant, but did not meet the expected standards of a custom home builder.  
[290] The second concern related to the use of non-pressure treated wood below 150 mm above  
grade. The Code requires that non-pressure treated lumber and OSB clear grade by a minimum  
of 150 mm. This Code requirement is focused on the permeability of OSB and other types of  
non-pressure treated lumber, particularly when located close to ground level.  
[291] Both Matthews and Hamman expressed the view that this was not Code-compliant, with  
Matthews explaining that there is a long-term moisture concern that underlies this requirement.  
According to Juniper, while investigating the wall leading to the walk-out portion of the  
residence underneath the deck, it was determined that the as-built construction involved the  
placement of OSB next to the foundation and the use of other non-pressure treated lumber for the  
sill plate. This irregularity was observed in approximately three-quarters of the east perimeter  
wall of the residence.  
[292] In framing the residence, McEwen used OSB on top of the wood ladder and also in direct  
contact with the concrete foundation. Metcalfe knew that McEwen installed OSB between the  
top of the foundation and the bottom plate on the underside of the wall. In his evidence, Metcalfe  
acknowledged that he was aware that the as-built OSB detail was not compliant with the Code.  
[293] Hamman testified that he did not believe that the placement of OSB next to the concrete  
foundation was Code-compliant, though he suggested that he was not aware of any specific Code  
reference that prohibited such a practice. He went on to express repeatedly that he did not believe  
that this was good practice, notwithstanding that the foam gasket product used in this instance  
was Code-approved in 2011. In terms of remediation, he recommended removal of the OSB.  
[294] The Defendants point to the evidence of the Building Inspector, Stewart, and of McEwen  
in suggesting that the use of OSB on the foundation wall was common practice at the time.  
McEwen’s evidence was that this was a requirement in Airdrie, though the nature of this so-  
called requirement was never explored.  
[295] I accept Matthews’ evidence that the use of non-treated wood in contact with concrete  
was not compliant with Part IX of the Code. He confirmed this in cross-examination, stating that  
the foam gasket used was not impenetrable to moisture. I also accept his evidence, supported by  
the evidence of Hamman, that this was not a good building practice. In my view, the fact that use  
of this foam gasket may have been common or widespread is not relevant.  
[296] To address these issues, Juniper testified that the lower 18 inches of the exterior sheeting  
had to be removed to permit access to the foundation, the ladder and the sill plate: Exhibit 1-F-  
35, p 46; Exhibit 1-E-5, 0644, 0645, 0646. He replaced the non-Code compliant material with  
pressure-treated lumber, then nailed the wall into the floor to connect and stabilize the  
construction. Overall, Juniper determined that approximately 20 feet of the ladder was not  
constructed using pressure-treated lumber. On Matthews’ recommendation, the Plaintiffs  
replaced the OSB and other non-pressure treated materials along the sill plate with pressure-  
Page: 49  
treated materials. In my view, this was a reasonable course of action from a remediation  
perspective.  
[297] Finally, concern was raised with respect to the main floor bedroom, namely that the  
sheathing did not extend to the floor, the wall-to-floor connection was not present, and there was  
no nailing connection. In Matthews’ opinion, the as-built condition of the wall sheathing, and  
wall-to-floor connection posed a risk to structural integrity. Hamman agreed that the Code’s  
nailing criteria for floor-to-wall connection were not followed.  
[298] McEwen’s evidence was that he did not extend the sheathing because that is accepted  
practice in Alberta. Metcalfe acknowledged that he observed the wall sheathing not connected to  
the floor in one location, but failed to direct McEwen to correct the situation to bring it into  
compliance with the Code.  
[299] I accept the evidence of Matthews and Juniper relative to this construction deficiency. In  
my view, the remediation recommended by Matthews and implemented by Juniper was  
reasonable under the circumstances.  
8. Kitchen Floor  
[300] In his written report, Matthews described the deficiency relating to the kitchen floor in  
the following terms (at para 2.1.1): “[W]alking on the Main Floor structure in selected areas of  
the kitchen resulted in a perceived significant and undesirable vibration response in the floor.  
The vibration performance was excessive from a user perspective in a residence of this  
standard.” As-built, the floor was subject to significant vibration, such that walking across the  
floor caused water bottles to move across kitchen islands.  
[301] The Plaintiffs maintain that the problems that emerged with the kitchen floor were not a  
result of a design issue resting with ZyTech, but a result of Metcalfe’s failure to disclose to  
ZyTech the homeowners’ unique requirements or to consult an engineering professional.  
[302] The Defendants advance a number of arguments with respect to this alleged deficiency,  
as well as to the remediation undertaken by the Plaintiffs. First, they deny that that the Plaintiffs  
brought to their attention the need for a robust floor system. Second, they rely on the term of the  
contract that design plan drawings “may not always be followed as suggested by the draftsman.”  
Third, they challenge the need for the repair detail prepared by Matthews (Exhibit 1-A-7, SKG)  
and, indeed, for the involvement of an engineer in the remediation process.  
[303] The original Innographic design drawings for the residence called for spacing under the  
kitchen floor of 12” on-centre to accommodate the anticipated extra load associated with the  
stone-clad islands that formed part of the house design: Exhibit 1-A-1. The as-built spacing  
under the kitchen floor was 16” on-centre, based on Zytech shop drawings that had not been  
engineer stamped at the time of construction: Exhibit 1-A-2. On the evidence before me, it is  
clear that the Defendants later obtained, and included as part of their document production after  
this litigation had already been commenced, an engineer’s stamp on similar working drawings  
containing the same 16” on-centre spacing.  
[304] In his evidence, Metcalfe confirmed that he had no discussion with an engineer or anyone  
at ZyTech regarding the spacing change in the shop drawings from those set out in the original  
design. He did not take any steps to determine whether the added weight of the stone-clad  
 
Page: 50  
kitchen islands had been considered by ZyTech in producing the shop drawings for the kitchen  
floor support system.  
[305] Matthews stated that the kitchen floor system met the minimum Code requirements for  
strength, but observed that the as-built joist span operated at its functional maximum, namely  
98%. He concluded that the vibration criteria were not addressed and that the as-built condition  
was inappropriate for a home of this standard, specifically as regards the load placed on the  
joists’ span. He referenced unacceptable vibration and deflection of the kitchen floor. He also  
raised concerns regarding the type of joist used as not ideal to address the as-built spacing and  
with respect to the significant number of web-openings cut out of the joists.  
[306] The Plaintiffs rely on Hickey’s Building Supplies Limited v Sheppard, 2014 NLCA 43, a  
case involving the construction of a residence required to be wheelchair accessible. In that case,  
the defendants wanted level transitions from hardwood to ceramic tile flooring materials. In  
constructing the residence, the contractor employed transition strips between flooring materials.  
While the use of such transition strips was compliant with the National Building Code, the strips  
did not produce the level flooring sought by the defendants. In finding for the defendants, Welsh  
JA (dissenting in part) held at paras 19 and 21:  
In this case, the Contractor knew that the National Building Code permitted the  
use of transition strips. The Contractor also knew that the Sheppards particularly  
wanted a level floor, and the reason for that. Clearly, there was a potential for  
conflict between what the Code permitted and what the Sheppards had requested.  
The evidence accepted by the trial judge leads to the conclusion that, while the  
Contractor was aware of this possible conflict, the Sheppards were not. Indeed,  
the Sheppards were relying on the Contractor’s expertise and on the contractual  
obligation in clause 15(b) that the house would be built in a workmanlike manner.  
The trial judge accepted evidence that, without significant expense, a level floor  
between hardwood and ceramic tile could be achieved by the use of appropriate  
underlay.  
...  
In summary, the trial Judge did not err in concluding that the Sheppards had  
contracted for a level floor and that the Contractor could not rely on the National  
Building Code to permit the use of transition strips. In the result, compliance with  
the contract required replacement of the ceramic tile, as well as the hardwood...  
[307] The Plaintiffs maintain that Metcalfe was aware that they required a robust kitchen floor  
given the extensive stonework that was planned for this particular room. As in Hickey’s, the  
Plaintiffs say that the contractor cannot rely on a Code-compliant kitchen floor in the face of  
actual knowledge of the customer’s enhanced requirements.  
[308] I accept Ms. Swanby’s evidence that the Plaintiffs discussed with Metcalfe their very  
specific requirement for a robust kitchen floor to accommodate their plan to incorporate  
significant stone work on the kitchen islands. It is clear to me that this was a design element that  
was important to the Plaintiffs throughout the planning process. The original Innographic  
drawingsincorporation of a re-enforced floor joist system support the Plaintiffs’ contention that  
a strong kitchen floor system was a design element from the outset. Given the importance that  
Page: 51  
this design element played in the Plaintiffs’ overall design, I cannot accept Metcalfe’s evidence  
that he was never told of this requirement.  
[309] Hamman acknowledged that there was a noticeable vibration and bounce in the floor joist  
system and that the as-built state of the floor was deficient from a performance perspective. He  
recommended checking all of the electrical and mechanical cut-outs in the existing joist system,  
as well as the installation of backing plywood and drywall to the underside of the joists. He also  
expressed the view that the criteria for the size and location of cut-outs to accommodate  
electrical and mechanical installations was in accordance with ZyTech instructions. However, he  
acknowledged that these instructions would have accompanied the materials to the construction  
site and had not been produced in this litigation.  
[310] The discrepancy between the kitchen floor joint span spacing in the original design  
drawings and the ZyTech shop drawings should have led Metcalfe to conduct further inquiries.  
The absence of an engineer’s stamp on the ZyTech shop drawings should have also raised a red  
flag for Metcalfe and prompted him to consult an engineer or, at the very least, clarify the  
situation with ZyTech. I accept Kraychy’s evidence that in such circumstances, it was incumbent  
upon Metcalfe to have consulted ZyTech and specifically brought to their attention the  
specifications set out in the architectural drawings and the unique loading requirements for the  
kitchen floor given the Plaintiffsplanned use of significant amounts of stone in the kitchen.  
[311] My findings are significantly influenced by the fact that an engineer-stamped version of  
the shop drawings was subsequently obtained and included in the Defendants’ litigation  
production. In my view, this demonstrates a clear awareness of the significance of having acted  
on the basis of plan drawings that had not been engineer-stamped and that differed in a material  
way from the original design drawings.  
[312] While both the Plaintiffs’ expert and the Defendants’ expert agree that remediation was  
required to address the kitchen floor, there are some notable differences in their recommended  
courses of action. Having carefully considered the underlying circumstances, I am satisfied that  
the remediation action taken by the Plaintiffs was reasonable, namely the strengthening of the  
flooring system through the addition of lumber at the bottom of the joists and the installation of  
blocking.  
[313] In my view, there is no merit to the Defendants’ suggestion that the involvement of  
Matthews, a structural engineer, was somehow excessive in the circumstances. Given my finding  
that a failure to consult an engineer in the first place lay at the heart of this issue, it was  
eminently reasonable for the Plaintiffs to have relied on an engineer in their efforts to resolve the  
problem.  
[314] Matthews prepared an engineered repair detail, Exhibit 1-A-7, SKG, to illustrate the  
required repair. According to Juniper, who executed the required repair, Matthews’ detail  
specified the necessary nail patterns and the required glue. The remediated work is shown in  
photographs incorporated into Juniper’s report at Exhibit 1-F-35, p 58, 59, 60. I am satisfied that  
this was a reasonable approach to the remediation of this construction deficiency.  
9. Walk-Out Header  
[315] McEwen fabricated a header beam for the rear entry-level doors leading to the covered  
area underneath the deck. The header beam was constructed of a single engineered ply-laminated  
veneer lumber (“LVL”) beam that was attached to the interior face of two-plys of dimensional  
 
Page: 52  
lumber: Exhibit 12, p 12, photo #2. McEwen acknowledged that there was no design for the  
beam and he did not consult an engineer before constructing the beam. He expressed the view  
that the header beam was stronger than required as a result of him using LVL. He testified that  
he had used this methodology in other projects.  
[316] Both Matthews and Hamman expressed concerns with the construction of the beam and,  
in particular, the use of different types of woods in combination.  
[317] Metcalfe conceded that he observed some sagging of the beam and it appeared that the  
doorframe was not totally straight. He also acknowledged that he saw a bow over the walkout  
header, but took no steps to determine the cause of the deflection and, further, made no efforts to  
repair the header.  
[318] In his report, Hamman expressed the view that the Code’s span tables allowed a 3-ply  
beam to span the 3.02 meter distance required in this instance. In his subsequent evidence, he  
retracted this opinion once he became aware of the actual make-up of the beam and had an  
opportunity to observe it in place. He stated that he would have consulted a structural engineer in  
such circumstances, in part because the Code’s span tables do not apply to the as-built beam used  
in this instance.  
[319] Matthews expressed the view that the beam was inadequate in terms of the applicable  
Code-loading tables and that the beam’s construction was not good practice. Further, he  
expressed the view that the beam could have collapsed once subject to Code-sanctioned loading.  
He also referred to the potentially serious implications on the building structure if the beam were  
to collapse. In his view, this raised a safety issue.  
[320] Matthews recommended remediation through removal and replacement of the header  
beam. He prepared a repair detail to this effect: Exhibit 1-A-7, SKL. In addition to following this  
recommendation, TGC also removed and reframed the adjacent wall of the structure. The  
remediated header beam is depicted in Juniper’s report, Exhibit 1-F-35, at p 52, bottom  
photograph. The top photograph on the same page shows the repair being effected.  
[321] I am satisfied that the remediation effected by Juniper was reasonable under the  
circumstances.  
10. Missing Point Load  
[322] During the investigative and remediation processes, Matthews examined the building  
structure to confirm that load paths existed within the structure. This investigation revealed that  
there were missing studs and blocking in the main floor joists at the east wall. According to  
Matthews, this situation existed at a small number of different locations on the east wall. In  
particular, he noted one instance where he observed the load from the roof ending at grade and  
not finding a way down to the foundation.  
[323] Matthews testified that there is a requirement that the “structure provide a load path for  
loads to find their way to foundation”: Evidence of Matthews (Chief), April 17, 2019, at 4:10  
p.m.  
[324] Matthews explained that “if the design loads were imposed on the roof, that the posts  
supporting that load, which comes down and lands on top of the floor plate, base plate, bottom  
plate for the wall that is sandwiching the sheathing, I would expect that there would be a high  
likelihood of failure that that post would want to push through the main floor structure.” He  
 
Page: 53  
described this as localized structural failure that would “certainly” pose a safety hazard to  
residents, specifically the possibility of roof collapse: Evidence of Matthews (Chief), April 17,  
2019, at 4:14 p.m.  
[325] Juniper described one example of this problem relative to the kitchen. As depicted in  
Exhibit 1-F-35, photograph 59 (bottom), Juniper assembled three 2 x 6’s next to the doors to the  
basement walk-out to carry the load of the kitchen floor back down to the foundation. No such  
point load existed in this location in the as-built condition. According to Juniper, Matthews  
prepared an engineered repair detail, Exhibit 1-A-7, SKL, to illustrate the required repair.  
[326] Neither Metcalfe nor McEwen offered any evidence on this deficiency. Likewise, the  
Defendants provided no submissions, oral or written, with respect to this issue.  
[327] I accept the evidence of Matthews and Juniper on this issue. I reject the conflicting  
opinion evidence of Hamman given that it was largely based on a visual review of drywall  
surfaces. I am not persuaded that the condition of drywall surfaces provides a proper basis to  
assess the existence of proper load paths.  
[328] In my view, the addition of studs and blocking, as per the recommendation of Matthews,  
was appropriate under the circumstances.  
11. Sound Proof Insulation  
[329] There is conflicting evidence regarding the installation of sound insulation in the  
basement ceiling, specifically under the main area below the ground level Great Room. Metcalfe  
acknowledged that the initial plan included soundproofing. However, he testified that, during a  
conversation with Ms. Swanby and Carm, it was agreed to dispense with this sound insulation  
given the proximity of a stairwell opening and of piping. Carm recalled a discussion involving  
Ms. Swanby, Metcalfe and himself during which Metcalfe raised concerns about the utility of  
soundproofing under the Great Room. However, Carm testified that the decision was taken to  
include insulation for sound proofing purposes above the girls’ basement bedrooms and in the  
main area underneath the Great Room.  
[330] No sound insulation was installed in the basement ceiling, though Juniper testified that  
the as-built condition included some metal sound tracking in the ceiling of the room under the  
Great Room. Juniper also found full sound proof insulation in two basement bedrooms.  
[331] I accept Carm’s evidence that sound proof insulation was to be installed in the ceiling  
under the Great Room. As such, I am satisfied that the Defendants failed to sound-proof this part  
of the basement and did not credit back any amount for sound insulation until October 2013,  
after the lawsuit was initiated. By that time, Metcalfe would have been aware from the contents  
of the Statement of Claim that a claim related to sound insulation was included.  
[332] The Defendants provided no submissions, either during oral argument, or in subsequent  
written argument relative to this deficiency.  
[333] In terms of remediation, the Plaintiffs elected to install QuickRock soundproof drywall  
rather than attempting to place regular sound-proofing insulation between the joists. I accept the  
Plaintiffs’ contention that the cost of QuickRock was greater than the cost of regular insulation,  
but that the use of QuickRock was far less labour intensive and, overall, the cost of the two  
approaches was more or less equal.  
 
Page: 54  
12. Roof  
a) Structure  
[334] Matthews raised a number of concerns relating to the roof-framing, citing non-  
compliance with both the Code and the manufacturer’s recommendations. First, he referred to at  
least three areas where the structural trusses were noted to have broken or removed components:  
Exhibit 1-F-35, pp 84-85 (missing component). The breaks were described as having been  
broken in a brittle manner, as opposed to having been clean-cut by a saw: Exhibit 1-F-35, p 84  
(broken trusses). He explained how the absence of these component parts “radically” negatively  
affects the performance of the truss: Evidence of Matthews (Chief) April 18, 2019, 12:05 p.m.  
According to Matthews, the structural impact of these damaged trusses was critical, the failure  
would lead to a localized collapse of the roof.  
[335] Second, Matthews noted missing hangers and bracing and a missing rafter. Further, he  
observed the absence of connection via hangers and that the rafters were generally toe-nailed. In  
his view, toe-nailing is not good practice. He expressed the view that the impact of missing  
hangers reduces the overall strength of the structure and risks potential failure under Code-  
loading requirements. Finally, Matthews and Juniper both noted that some of the trusses were  
oriented on the flat side, their weaker axis: Exhibit 1-F-35, pp 83, 86.  
[336] Juniper also determined that one of the trusses over the kitchen area was not sitting on a  
supporting beam. During his investigation, he discovered that the intended supporting beam was  
not supported by the wall. Matthews provided Juniper with an engineered repair detail, Exhibit  
1-A-7, SKJ, to effect the necessary repair. A metal bracket was added to connect the beam to the  
wall: Exhibit 1-F-35, p 92, top photograph.  
[337] In his direct evidence, Metcalfe testified that he did not notice any broken or damaged  
trusses. According to McEwen, broken trusses may have arrived on the site, though he was not  
certain whether any broken or unrepaired trusses were left in the roof. He did, however, confirm  
the doubling-up on broken trusses. He also acknowledged one of the Plaintiffs’ photographs that  
revealed one missing truss and member: Evidence of Metcalfe (Direct) May 9, 2019, 11:44  
a.m.; Evidence of McEwen (Direct) May 13, 2019, 3:39 p.m.; 3:51 p.m.; Exhibit 12, p 19,  
photograph 16; May 13, 3019, 3:52 p.m.; Exhibit 12, p 20, photograph 17.  
[338] McEwen also testified that if a member on a truss is broken, the truss is usually repaired  
on site. If a bottom or top cord of a truss is broken, however, the broken truss is not used. He  
indicated that it was his practice to consult ZyTech, the manufacturer of the trusses, for field  
repairs. There is no evidence that ZyTech was consulted regarding any field repairs in this  
construction project.  
[339] Hamman testified that damaged trusses happen from time to time, but they need to be  
repaired in accordance with the directions of the manufacturer. He acknowledged that he would  
not leave a roof in the condition depicted in the photographs of the as-built condition of the roof  
structure: Exhibit #48, p 13; Evidence of Hamman (Cross) October 18, 2019, 3:38 p.m.  
[340] McEwen disagreed with Matthews regarding the requirement for hangers. He testified  
that he installed the bracing in accordance with the plan drawings provided to him. With respect  
to the installation of framing members on the weak axis, McEwen maintained that he had an  
uneven amount of space to work with on either side of the ridge beam and had made adjustments  
 
Page: 55  
so as to avoid the necessity of reframing the roof: Evidence of McEwen (Direct) May 13, 2019,  
3:46 p.m.; Exhibit 12, p 18, photograph 14.  
[341] Hamman agreed that there was a need to improve the support provided by the 2 x 4  
members that were laying on their weak axis. Furthermore, he acknowledged that the framing  
parts of the roof were not strong enough to sustain snow-loading and that his report did not take  
into consideration the impact of actual occupancy of the residence or live-loading.  
[342] The Defendants raise a number of issues with respect to this alleged construction  
deficiency. First, they maintain that there is no reliable evidence as to when the broken trusses  
described by Matthews and Juniper were first noticed. In their written submissions, at para 272,  
they assert that: “Mr. McEwen’s evidence was that there were no broken trusses when he  
completed the project.” In fact, McEwen’s evidence was that he did not believe that there were  
any broken or damaged trusses in the as-built roof when he completed his work on the project.  
[343] To the extent that the evidence of Matthews conflicts with that of Metcalfe, McEwen or  
Hamman, I prefer the evidence of Matthews. I also accept Matthewsevidence regarding the  
repairs that were necessary to remediate these construction deficiencies.  
[344] Based on his assessment of the situation, Matthews recommended that the Plaintiffs  
undertake a de-loading of the trusses to allow the proposed repairs to take place: Exhibit 1-F-35,  
p 90, bottom photograph. This included attaching plywood to strengthen the trusses and the  
replacement of missing truss members. He created an engineered repair details to this effect:  
Exhibit 1-A-7, SKB, SKH, SKK. Further, the recommended repairs involved building up the 2 x  
4 members that were laying on their weak axes to more fully support the structure. In addition,  
hangers and bracing were installed. Finally, a steel plate was installed at the base of the  
supporting beam.  
b) Roofing  
[345] The Code outlines minimum roofing requirements in the following terms:  
9.26.1.1. Purpose of Roofing  
1) Roofs shall be protected with roofing, including flashing, installed to shed rain  
effectively and prevent water due to ice damming from entering the roof.  
9.26.8.2. Starter Strip  
1) A starter strip shall be installed as in Article 9.26.7.2.  
2) Starter strips required in Sentence (1) shall be laid in a continuous band of  
cement not less than 200 mm wide.  
[346] The Plaintiffs identified a series of deficiencies in the roofing installed on the residence.  
Specifically, Bjornson and Juniper raised concerns regarding missing and damaged shingles, the  
use of OSB roof sheathing, the absence of continuous roof underlayment and the use of closed  
versus open valleys on the roof. There also was no proper eaves protection by way of a starter  
strip or extra drip flashing under the shingles.  
[347] Juniper gave evidence regarding the condition of the shingles. He observed that, while  
they appeared to be fine when viewed from the ground, closer inspection revealed cracked and  
split shingles, as well as multiple areas on the roof where shingles were missing: Exhibit 1-F-35,  
Page: 56  
p 117, bottom photograph; p 121, bottom photograph. Bjornson also observed missing and  
broken shingles.  
[348] The Defendants take the position that only a portion of the roof revealed damaged or  
missing shingles. As such, they say that the Plaintiffs should have repaired only the damaged  
sections of the roof and that they have not established a need to replace the entire roof. The  
Defendants rely on the evidence of Shawn Lummerding of Lummerding Exteriors Ltd, the  
roofing contractor who installed the shingles.  
[349] Lummerding testified that he conducted an inspection of the roof back in 2014. He  
acknowledged that he does not have an engineering background and was not personally involved  
in the work on the Swanby residence. As such, he had no personal knowledge of the project at  
the time of completion.  
[350] Lummerding observed concentrated damage to the shingles on 2 or 3 areas of the roof.  
He described this as mechanical damage caused by scaffolding and estimated that there was  
damage to approximately 100 square feet of the roof. He believed that this damage was  
repairable through replacement of the damaged shingles and that such a repair would have no  
impact on the shingle manufacturer’s warranty.  
[351] According to Metcalfe, the stucco contractor set up scaffolding near the front of the  
garage that caused the shingles to crack. He initially testified that he went on the roof to conduct  
an inspection of the shingles, but was challenged during cross-examination based on prior  
inconsistent statements and ultimately acknowledged that he did not inspect the shingles.  
[352] Bjornson recommended that all the shingles be replaced. As described below, she also  
recommended that underlayment be placed on the full field of the roof and that ice and water  
shields be installed in the valleys. She explained that asphalt shingles have a normal life of 40-50  
years. She noted that some of the shingles were observed to be not performing after only one to  
two years.  
[353] Bjornson was asked about the shingle manufacturer’s warranty on their product. She  
explained that the manufacturer guarantees only the product, not the installation. She went on to  
say that, generally speaking, it is not the product that fails, but the installation.  
[354] Concerns were also raised with respect to the use of OSB as the roof sheathing and the  
fact that underlayment had not been installed on the entire surface of the roof. At p 56 of her  
report, Exhibit 16, Bjornson included a photograph that illustrated the absence of underlayment  
where a soffit panel had been removed.  
[355] Bjornson stated that the use of OSB as sheathing and failure to install full underlayment  
were contrary to best practice. She expressed concern about the use of OSB sheathing as roof  
decking as it has a strong tendency to absorb water and not dry. She explained that the roof  
absorbs a lot of moisture during construction and, as such, best practice dictates that OSB not be  
used as roof decking. She went on to explain that her major concern was the lack of continuous  
underlayment, thus depriving the roof of an added layer of protection.  
[356] Lummerding was asked to inspect the roof to determine if underlayment had been  
installed. He checked three or four areas of the roof and confirmed that existence of felt paper in  
each of these areas. While he acknowledged that he did not check the entire roof, he was referred  
to his company’s invoice relating to the Swanby residence and stated that the $854 charge “to  
felt roof” suggested that the underlayment had been applied to the entire roof.  
Page: 57  
[357] As noted above, Bjornson expressed the view in her expert report that the ARCA Roofing  
Application Standards Manual represents the industry standard for the installation of roofing,  
particularly in light of the fact that many of the Code’s roofing provisions are “extremely  
outdated”. In this instance, she maintained that the ARCA standard is the accepted standard for  
roofing installation purposes. She referred to the following underlayment standard set out at  
paragraph 2.5.1:  
2.5.1 Materials  
1. The field of the decking shall be completely covered with a minimum of one (1)  
ply of CSA No. 15 non-perforated asphalt saturated felt prior to application of  
the shingles.  
[358] Bjornson explained that the Code does not specifically require underlayment on the entire  
field of the roof, but stated that it is “very rare” to have a roof that does not have a complete  
underlayment. She agreed that the roof as built met the Code’s minimum requirements, save for  
the damaged shingles. However, she stated that it did not meet best practices.  
[359] Lummerding testified that while he had heard of ARCA and is aware that ARCA issues  
guidelines relating to roofing installation, his company is not a member of ARCA and does not  
follow its guidelines.  
[360] The final area of concern related to the use of closed versus open valleys in the roof.  
Bjornson expressed the view that, though the Code does permit closed valleys, open valleys are  
generally preferred because they better facilitate water management and prevent shingle wear.  
She explained that a closed valley involves the shingles simply meeting in the valley, whereas an  
open valley separates the shingles using a different material, generally a metal flashing. Bjornson  
referred to the ARCA manual touching on this issue:  
2.3.2 Valley Flashing  
.2 Open Valleys must be employed for laminated and interlocking asphalt shingle  
application.  
.3 Where sloping surfaces of shingle roofs intersect to form a valley, the valley  
shall be flashed with a minimum of one (1) ply of 914 mm (36”0 wide self  
adhering modified bituminous membrane centered in the valley.  
[361] Bjornson described the valley flashings in this instance as “quite distressed” and  
“severely distressed and damaged.She did not observe any ice shield on her inspection of the  
roof, though valleys were stated to have been flashed with polyethylene/building paper with  
provision for ice shield.  
[362] Hamman briefly addressed this issue in his report. He acknowledged that the roof valleys  
were distressed and cracking. He went on to state that “[T]he installed roof appeared to be clean  
with straight lines and in my opinion would be subject to the lifetime warranty as provided by  
the manufacturer”: at p 5. In his trial testimony, Hamman conceded that he did not inspect the  
roof. I would simply add that I accept Bjornson’s evidence that Hamman’s observations  
regarding the roof revealing “clean and straight lines” provide no basis for evaluation of the  
roof’s performance.  
[363] In terms of remediation, at the request of Bjornson, Juniper removed all the shingles and  
replaced them over top of a full underlayment. In the process, Juniper replaced all the closed  
Page: 58  
valleys with open valleys. In my view, the Plaintiffs acted reasonably in accepting Bjornson’s  
assessment of the situation and replacing the entire roof.  
13. Main Attic Insulation  
[364] Insulation is required to allow for circulation, not block vents and be of sufficient density  
to preclude settlement. Section 9.25.2.4 of the Code provides as follows:  
1) Except as provided in Sentences (2) to (6), loss-fill insulation shall be used on  
horizontal surfaces only...  
4) Where blown-in insulation is installed in above-ground or below-ground wood-  
frame walls of new buildings,  
a) the density of the installed insulation shall be sufficient to preclude  
settlement,  
b) the insulation shall be installed behind a membrane that will permit visual  
inspection prior to the installation of the interior finish,  
c) the insulation shall be installed in a manner that will not interfere with the  
installation of the interior finish, and  
d) no water shall be added to the insulation, unless it can be shown  
that the added water will not adversely affect other materials in the  
assembly.  
[365] Metcalfe’s evidence was that he personally installed Cellulose insulation, a blown-in  
product, in the main attic of the residence. He expressed the view that this product was denser  
than fiberglass and, as such, the manufacturer’s guidelines indicated that only 10” was required  
to obtain the R-40 value stipulated for this construction project. He acknowledged that Cellulose  
settles 2-3” over time.  
[366] During Questioning in 2015, Metcalfe confirmed that he did not test the depth of the  
insulation after installation. However, in his trial evidence, he expressed confidence that the  
insulation had R-40 value when he left the project. He did not explain the basis for this degree of  
confidence.  
[367] The insulation had already been removed from the attic at the time of Bjornson’s  
inspection of the property. She did, however, offer the opinion that blown-in insulation should  
not block soffits as this is not Code-compliant, and that the thermal value of the insulation must  
be maintained, ie. not compressed.  
[368] At the time Juniper inspected the attic, he found only 6” of blown-in insulation in the  
main attic area covered in mouse feces: Exhibit 1-F-35, p 87, top photograph. He explained that  
he had expected to find about twice that amount of insulation and that 6” was roughly equivalent  
to R-20. Juniper testified that he understood at least 12” was required to achieve the Code  
required R-40 level.  
[369] Hamman did not address the depth of the blown-in insulation in his report. Nevertheless,  
he testified that he would have installed an additional 8” of blown-in insulation in the main attic  
space. He saw no insulation on the exposed soffits but conceded that he inspected only a limited  
number of soffits from outside the house.  
 
Page: 59  
[370] The Defendants produced no product material prepared by the manufacturer of Cellulose.  
Likewise, counsel for the Defendants posed no questions about Cellulose to either Bjornson or  
Juniper. Further, in their written submissions filed at the end of the evidence, the Defendants  
simply suggested that there is “scant evidence of a general lack of insulation” in the areas of the  
house where blown-in insulation was used.  
[371] Given Metcalfe’s evidence that he never tested the depth of the insulation, there is no  
evidence before me that the blown-in insulation ever met the R-40 level specified in the building  
contract. All that is known is that Metcalfe believed that the R-40 level had been attained and  
Juniper’s evidence that he only found 6” of blown-in insulation at the time of his inspection.  
Even if Metcalfe’s belief was correct, it is clear that he failed to account for settlement, as  
required by the Code. In my view, the circumstances required Metcalfe to take positive steps to  
ensure that this contractual requirement for R-40 insulation had been met. He failed to do so.  
[372] The Plaintiffs removed the blown-in Cellulose insulation to effect the required repairs to  
the roof structure and replaced it with 15” of blown-in insulation up to a rating of R-50. The  
original insulation could not be re-used due to the extent of the mouse feces found in the  
material. Under the circumstances, I am satisfied that this was a reasonable approach to the  
remediation of this issue.  
a) Air/Vapour Barrier  
[373] Section 9.25 of the Code outlines the requirements for the air and vapour barrier:  
9.25.3.1 Required Barrier to Air Leakage  
1) Thermally insulated wall, ceiling and floor assemblies shall be constructed so  
as to include an air barrier system that will provide a continuous barrier to air  
leakage  
a) From the interior of the building into wall, floor, attic or roof spaces,  
sufficient to prevent excessive moisture condensation on the room side  
during winter and to ensure comfortable conditions for the occupants.  
9.25.3.3 Continuity of the Air Barrier System  
2) Where the air barrier system consists of flexible sheet material, all joints shall  
be  
a) Sealed, or  
b) Lapped not less than 100 mm and clamped, such as between framing  
members, furring or blocking and rigid panels...  
6) Penetrations of the air barrier system, such as those created by the installation  
of doors, windows, electrical wiring, electrical boxes, piping or ductwork, shall  
be sealed to maintain the integrity of the air barrier system over the entire  
surface.  
9.25.4 Vapour Barriers  
1. Required Barrier to Vapour Diffusion  
Page: 60  
1) Thermally insulated wall, ceiling and floor assemblies shall be constructed with  
a vapour barrier so as to provide a barrier to diffusion of water vapour from the  
interior into wall spaces, floor spaces or attic or roof spaces.  
9.25.4.3 Installation of Vapour Barriers  
1) Vapour barriers shall be installed to protect the entire surfaces of thermally  
insulated wall, ceiling and floor assemblies.  
2) Vapour barriers shall be installed sufficiently close to the warm side of  
insulation to prevent condensation at design conditions.  
[374] I accept Bjornson’s evidence that the building envelope, including the air and vapour  
barrier must be continuous and structurally supported. Hamman agreed with this general  
proposition: Code, s 9.25.3.1, .3, .43.  
[375] According to Bjornson, the air and vapour barrier, typically a single entity in single  
family residences - usually polyethylene sheets - did not meet Code requirements and required  
remediation. She determined that the air and vapour barrier was not continuous on the building  
walls. Specifically, she found that polyethylene sheets were sealed to the window opening  
framing and not the window assembly. While this is common practice, it requires the application  
of foam sealant to create a continuous barrier. In all of the windows that she inspected, Bjornson  
found that the spray foam sealant was not applied in sufficient quantity and was not continuous.  
[376] Bjornson also found that the air and vapour barrier was penetrated as the electrical wiring  
and plumbing entered the barrier without proper sealing. Electrical wires were installed through  
the air and vapour barrier without sealant. Further, she found that overlapping polyethylene  
sheets were not sealed and clamped as required by the Code. Overall, she found that the Code  
requirements had not been met.  
[377] Juniper’s evidence was that none of the pot lights were sealed with either polyethylene or  
blue vapour barrier boxes, as required by standard practice. He also testified that a number of  
plumbing and mechanical holes in the attic were not sealed. The electrician, Dueck, gave  
evidence that he observed water pouring through the pot light installations at one point: Evidence  
of Juniper (Direct) April 12, 2019, (p.m.); Exhibit 1-F-35, p 87 (p 92 remediated); Exhibit  
#29; Evidence of Dueck (Cross) May 14, 2019 (p.m.).  
[378] Hamman was not able to observe the air and vapour barrier at the transition from the  
main floor to the attic because the blown-in insulation was covering the base of the attic. He  
testified that it was not clear to him whether the air and vapour barrier overlapped. He  
acknowledged, however, that if there was no overlap, the air and vapour barrier was deficient.  
He also acknowledged that if water was coming through the pot lights, that indicated that the pot  
lights had not been properly sealed.  
[379] Both Metcalfe and Dueck gave evidence that the brand of pot light installed in the  
Plaintiffs’ residence did not require polyethylene coverings. However, I note that the Defendants  
adduced neither any evidence as to the brand of pot light used nor any information from the  
manufacturer to support their contention. Given the evidence of their own expert regarding the  
absence of a proper seal if water was coming through the pot lights, I am not prepared to accept  
the Defendants’ contention that no polyethylene covering was required.  
Page: 61  
[380] Metcalfe also gave evidence to the effect that plumbing and mechanical holes were  
sealed from below. He produced two undated and unidentified photographs, Exhibit 20 and  
Exhibit 21, depicting plumbing and mechanical holes that appeared to be sealed from below in  
support of his assertion in this regard. I accept Bjornson’s evidence that it is not common  
practice to seal barriers from the underside and that bottom sealant does not produce a  
continuous air seal and, as such, is deficient. She referred to her expert report, Exhibit 16, p 44,  
photograph 8.45 as an example of a breach of the continuous air seal. While she acknowledged  
in cross-examination that it may be possible in some instances to seal plumbing and mechanical  
breaches of the barrier from below, I am not persuaded that this qualifies or otherwise limits her  
overall findings regarding this deficiency. Bjornson’s findings in this regard are not, in my view,  
undermined by that fact that both Metcalfe or Hamman gave evidence that it is common practice  
to seal plumbing, electrical and mechanical holes from below. I am satisfied that this was  
deficient practice that compromised the air and vapour barrier.  
[381] By way of remediation, the Plaintiffs replaced polyethylene around the house, sealed the  
pot lights using blue vapour barrier boxes, and sealed all of the plumbing and mechanical holes  
in the attic with polyethylene: Exhibit 1-F-35, p 92, bottom photograph.  
14. Deck  
a) Connection to House & Blocking  
[382] I accept the evidence of Juniper and Matthews that the as-built condition of the main  
exterior deck did not meet the manufacturer’s requirements, had insufficient connection to the  
main residence and, indeed, was pulling away from the house and sloping downward in one area.  
Hamman inspected the deck on October 3, 2013, at which time part of it had been demolished  
and all of the top decking had been removed. While he did not observe the deck pulling away  
from the house, Hamman acknowledged the risk presented by the deck’s as-built condition to the  
home’s occupants, and noted that “at some point that deck’s coming off the wall”: Evidence of  
Hamman (Cross) October 18, 2019, 3:33 p.m.  
[383] At one point during the construction, Ms. Swanby approached Metcalfe and reported that  
the deck did not appear to be level and, moreover, was pulling away from the residence. Ms.  
Swanby recalled that Metcalfe put a small piece of lumber underneath the stairwell, but took no  
further action.  
[384] Both Juniper and Hamman confirmed that there were no lag bolts fastening the deck to  
the residence. Rather, it was nailed to the house using framing nails, as opposed to galvanized  
nails, screws or pressure treated nails. Both agreed that the wrong sized hangers had been used  
and that the pre-drilled holes in the hangers had not been completely filled in. Likewise, they  
agreed that either there was no blocking or blocking was missing in a majority of spots within  
the deck’s floor system. According to Hamman, the deck not only required blocking, but repair  
to the top surface. He acknowledged that the as-built state of the deck posed a safety hazard,  
particularly relative to the walk-out area located underneath the deck.  
[385] According to McEwen, the deck was constructed without the benefit of any plan for its  
connection to the house. Both Metcalfe and McEwen testified that McEwen used five nails every  
16” to fasten the deck joists to the residence. The Defendants produced two undated and  
otherwise unidentified photographs, Exhibit 1-E-7 (photograph 3 and 4), as confirmation of their  
overall approach to fastening the deck to the residence. These photographs were taken by  
 
Page: 62  
Hamman. While Hamman testified that he was able to observe only 40% of the nailing pattern  
employed to fasten the deck to the residence, he stated that the Code allows for this type of  
nailing pattern.  
[386] While Metcalfe gave evidence that putting nails in all of the holes located on the hangers  
can cause the joists to split, I accept Matthewsevidence regarding the importance of fulfilling  
the manufacturer’s specifications for the installation of hangers: Exhibit 14, Simpson Strong-Tie  
specifications. In particular, Matthews explained that failing to fill all of the holes in the hanger  
alters the design for the deck support, a change that ordinarily would require the support of an  
engineering opinion or change detail. I note that even Hamman concluded that the as-built state  
of the deck showed insufficient connection to the home.  
[387] According to Matthews, the work on dismantling the deck was already underway when  
he first observed it. At that time, he made a series of recommendations for temporary support  
measures to ensure worker safety. He also prepared repair details that were subsequently relied  
upon by Juniper in effecting the required remediation of the deck: Exhibit 1-A-7, SKF. Based on  
his investigation, he concluded that the deck did not meet the manufacturer’s requirements. He  
stated that consultation with an engineer was required in situations where a builder plans or  
intends to deviate from the guidelines established by the manufacturer. There is no evidence to  
suggest that Metcalfe ever sought such advice or direction from an engineer prior to installing  
the deck in the manner described above. Indeed, the evidence of McEwen was that there was no  
plan for the deck’s connection to the residence.  
[388] The Defendants rely on the fact that the as-built construction of the deck was passed by  
the building inspector, James Stewart. For the reasons that follow, I am unable to accede to this  
argument. In my view, Stewart’s inspection reports and trial evidence do not offer any  
meaningful validation or approval of the as-built construction of the deck.  
[389] Stewart inspected the Swanby residence on September 15, 2011, and again on March 1,  
2012. His one-page inspection reports, Exhibit 1-D-3 and 1-D-4, contain very cursory hand-  
written notes detailing the scope of his inspections. Given the passage of time, Stewart had very  
little, if any, recollection of either inspection. Rather, he relied on his usual practices and on his  
limited notes made at the time. Stewart acknowledged that he is not an engineer by training and  
that his work experience is as a journeyman bricklayer. He agreed with the suggestion put to him  
in cross-examination that his inspections are preliminary or cursory and that he is looking for  
blatantly obvious deficiencies only. Further, he agreed with the suggestion that he does not  
undertake an assessment of the quality of the work that he is reviewing and, indeed, that he is not  
qualified to do so. Finally, he agreed that his inspection does not purport to report that no other  
construction deficiencies were present.  
[390] Stewart’s September 2011 inspection was restricted to the foundation. His report  
indicates that he was on-site for one half hour only. With respect to his subsequent inspection, he  
acknowledged that the report refers to him having been on-site for one hour. However, he  
conceded that this would include his travel time from the last inspection conducted prior to  
attending the Swanby residence. During his time on site, he would have taken a look at the  
framing of the roof and flooring systems, the ventilation system, checked the point loads on each  
floor of the structure, checked the windows and checked the support posts in the basement.  
[391] With one exception, Stewart’s hand-written notes on the report simply direct that  
specified work is to be completed in accordance with building plans and specifications and in  
Page: 63  
compliance with the Code. The notes make no mention of any problem or deficiency. The only  
specific item referred to relates to the deck, directing “Install hangers on rear deck treated joists  
at ribbon plate.Stewart could not recall how the deck joists were connected to the rest of the  
structure, though he believed that they may have been toe-nailed at the time. Stewart assumed  
that he had no other concerns about the connection since he made no other notes.  
[392] Given the size of the Swanby’s residence and the fact that the entire process was  
conducted in less than one hour, I find that Stewart’s inspection on March 1, 2013 was cursory at  
best. He could not recall if any of the drywall was in place or if there was an I-beam under the  
deck. Given his direction regarding the installation of hangers, it seems clear that the installation  
of the deck was not complete at the time of his inspection. Under the circumstances, I attach  
virtually no weight to the fact that Stewart ticked off a box indicating that there were no  
observed deficiencies at the time of inspection when assessing the final as-built construction of  
the deck. The Defendants’ reliance on this inspection is, in my view, misplaced.  
[393] I am satisfied on the evidence before me that there were very serious issues with the as-  
built connection of the deck to the rest of the building structure. I accept Hamman’s evidence  
that the deck was so inadequately connected that it was only a question of time before it would  
separate from the adjoining wall. I also accept Matthewsconclusion set out at page 8 of his  
report that:  
The construction of the deck displayed a poor quality of workmanship, inattention  
to details, and a lack of compliance with the ABC [Alberta Building Code]. The  
observed deficiencies, also including .1 above, in the deck structure could pose a  
significant safety risk to building occupants.  
[394] In terms of remediation, it is noteworthy that both Matthews and Hamman made similar  
recommendations. Hamman suggested that proper fasteners be used to attach the deck joists to  
the rim board. He also proposed adding blocking to the deck in accordance with the requirements  
of the Code. Matthews, on the other hand, recommended enhancing the deck beam connection  
and repair to the rim board. The Plaintiffs opted to repair the rim board and joist connections and  
to install blocking and hangers. According to Juniper, after a significant portion of the deck was  
dismantled, approximately 50% of the original deck material was salvaged and re-used during  
the remediation process.  
b) I-Beam  
[395] McEwen, Juniper and Matthews all testified that the steel I-beam supporting the deck  
rested on, but was not attached to, two 2 x 6 posts. Rather, it was held in place by gravity.  
Further, the beam rested on only a portion of a laminated beam. The laminated beam consisted of  
four 2 x 6’s laminated together. One end of the I-beam rested on slightly more than half of the  
laminated beam only. The other end rested on three quarters of the beam only: Exhibit 1-F-35, p  
96, top photograph.  
[396] McEwen testified that he bolted the I-beam to the underside of the deck: Exhibit 1-E-7,  
photograph 7. He testified that he received no drawings regarding the installation of the beam  
and simply installed it based on his experience in installing similar beams. He acknowledged that  
he never brought the lack of an installation detail to Metcalfe’s attention and conceded that he  
has no recollection as to how the beam was attached to the laminated beam.  
Page: 64  
[397] McEwen’s evidence regarding the bolt he installed to connect the beam to the deck was  
seriously undermined by Juniper’s evidence that the I-beam was not connected to either the deck  
or the supporting posts but was simply sandwiched in-between. As part of the remediation  
process, Juniper testified that he bolted the I-beam to a 2 x 8 that ran the length of the beam into  
which the deck structure was then nailed. Juniper was never presented with Exhibit 1-E-7, the  
photograph identified by McEwen. I prefer the evidence of Juniper in this regard.  
[398] Metcalfe said he inspected the I-beam before it was encased and prior to installing the  
final deck surface. He was not, however, able to observe how the I-beam was actually connected  
to the supporting posts. He acknowledged that he had never previously worked with an I-beam in  
the construction of a deck. Notwithstanding his lack of experience in this regard, Metcalfe failed  
to seek advice or assistance as to the adequacy of the deck construction.  
[399] Matthews expressed the view that that I-beam support and connections were not Code  
compliant or consistent with good practice. Hamman did not review the as-built condition of the  
deck and his report is silent on the connection between the I-beam and the supporting posts. He  
did, however, acknowledge in his evidence that the as-built condition violated the Code.  
[400] By way of remediation, the Plaintiffs elected to have TGC build a cradle for the I-beam  
that was Code compliant. Matthews prepared an engineered report detail in this regard: Exhibit  
1-A-7, SKF. In addition, TGC fastened the beam to the supporting posts that were rebuilt to  
prevent the beam from shifting. In my view, this was a reasonable approach to the remediation of  
the deficiencies identified relative to the I-beam supporting the deck. Exhibit 1-F-35, p 98,  
bottom photograph, depicts the fully-cradled beam after the remediation had been completed.  
c) Waterproofing  
[401] The Defendants were required to waterproof the deck to protect the covered space  
underneath it from rain. On the evidence before me, I am satisfied that water leaked through  
approximately 80% of the deck’s surface. Metcalfe conceded that the drainage system that he  
personally installed was inadequate, though in his evidence he stated that he did not guarantee to  
“keep water out”: Evidence of Metcalfe (Direct) – May 9, 2019, 11:58 a.m. Invoice 118 issued  
on September 1, 2012, stipulated that the drainage system was “not guaranteed to drain all  
water: Exhibit 1-C-11. Similarly, in an August 7, 2012 email to the Plaintiffs, Metcalfe advised  
that: “[P]lease note that great effort is made to drain all water but that is not guaranteed...”;  
Exhibit 1-G-23, p 71.  
[402] Hamman agreed that waterproofing the deck was appropriate remediation under the  
circumstances. As more fully discussed below, he did not, however, include this in his  
calculation of the budget for his alternate remediation work plan.  
[403] I am satisfied that the as-built state of the deck did not provide any real water protection  
for the space underneath. I am not persuaded that Metcalfe’s disclaimer, even if valid, was  
sufficient to encompass the almost complete failure of the drainage system he installed.  
[404] In terms of remediation, the Plaintiffs addressed the situation by treating the deck as a  
roof system with drain holes membraned for water to pass into drains. The top decking was  
replaced by cedar boards at less than half the cost of the composite decking initially employed by  
the Defendants: Exhibit 1-F-35, p 113, bottom photograph.  
Page: 65  
d) Piles  
[405] According to Matthews and Juniper, the most southerly concrete pile supporting the deck  
was less than 4 feet deep and rested on disturbed soil. Hamman agreed that this concrete pile  
required repair in that it was settling in disturbed soil and causing the deck to move. A second  
concrete pile in the same general area was, according to Matthews, resting on concrete overpour  
of the supporting pile and not anchored to the actual pile. Juniper testified that this was an area of  
the deck that sloped. Hamman offered no evidence relative to this particular deficiency: Exhibit  
1-F-35, p 101.  
[406] Metcalfe personally poured the concrete piles for the deck. The piles were required to be  
a minimum of 4’ in depth and resting on undisturbed soil. Metcalfe testified that, as built, the  
piles met the depth requirement. However, he also suggested that soil erosion removed the top  
level of the dirt. Further, he explained that he had repeatedly advised Ms. Swanby of the  
requirement for a retraining wall to address the soil erosion issue.  
[407] Given Metcalfe’s awareness of the erosion problem, the onus was on him to address this  
apparently unexpected development. As the general contractor, he was under an obligation to  
ensure that every aspect of the construction was Code-compliant and in accordance with best  
practices. The Defendants have produced no document to confirm that this concern was ever  
formally brought to the attention of the Plaintiffs. In my view, this would have been the  
appropriate course of action under the circumstances. I also note that the Defendants failed to  
cross-examine Ms. Swanby on this point. In the result, I reject Metcalfe’s attempt to deflect  
responsibility for this deficiency.  
[408] The posts resting on the concrete piles were also required to be centered. McEwen  
testified that he pinned each post to the piles by drilling a hole into the centre of the pile and  
drilling rebar into the hole. Based on my review of Exhibit 1-F-35, p 100, bottom photograph,  
and the other evidence before me relative to this issue, including the evidence of Hamman, I am  
unable to accept McEwen’s evidence in this regard.  
[409] Matthews prepared an engineered repair detail, Exhibit 1-A-7, SKA, to address this issue.  
According to Juniper, this entire portion of the deck had to be removed and replaced. TGC reset  
one of the posts so that it rested properly on the concrete pile. With respect to the post resting on  
disturbed soil, TGC excavated the surrounding soil to reach undisturbed ground. However,  
during the course of the excavation, a very large boulder was encountered. Rebar and a concrete  
footing were employed to support this deck pile in relation to this boulder. I am satisfied that the  
Plaintiffs employed reasonable measure to remediate these construction deficiencies. The top  
photograph on page 103 of Exhibit 1-F-35 depicts the work in progress relative to the pile  
determined to rest on disturbed soil.  
e) Columns  
[410] According to Juniper, the stone-clad deck columns were completely finished when he  
arrived on the worksite. At Matthews’ request, the bottom 24 inches of stone was removed from  
the columns in order to investigate the connection of the structural posts inside the columns to  
the ground. Mould and water damage was found on the revealed sheeting, Exhibit 1-F-35, top  
photograph.  
Page: 66  
[411] Bjornson determined that the deck columns had been fabricated from non-pressure  
treated material, though the deck posts within the columns were constructed from pressure-  
treated material. She concluded that the improper use of OSB, improper lath installation, and the  
risk of de-bonding required the removal of all of the stone from the columns. Hamman agreed  
that some of the columns were located too close to the ground for the type of material originally  
selected.  
[412] Bjornson also opined that the mason had installed the metal lath vertically on the deck  
columns, contrary to both good practice and the manufacturers requirements.  
[413] The Defendants seek to deflect responsibility for this building deficiency by pointing to  
the stone mason’s apparent lack of concern with the use of non-pressure treated materials in the  
construction of the columns. In my view, there is no merit to this argument. Metcalfe and Tru-  
Square were responsible for ensuring that their construction was Code-compliant and in  
accordance with generally accepted building standards applicable to custom home building. The  
Defendants’ work on this aspect of the construction project failed to meet these standards. The  
fact that the stone mason, Lawrence, elected to complete his portion of the required work on this  
element of the project in no way excuses or justifies the Defendants’ actions. In my view, it is  
simply not relevant.  
[414] TGC removed the stone and framing from the deck columns, re-framed them and sheeted  
them with treated studs and ½” blue board sheeting, a pressure-treated and bug-resistant product.  
A new moisture barrier and metal lath were then added before re-installing the stone over the  
scratch and brown coats. This remediation work is depicted in progress in Exhibit 1-F-35, p 104-  
05.  
[415] In conjunction with the repair work undertaken on the deck columns, two small retaining  
or pony walls were installed adjacent to the remediated piles described above. During the  
remediation work, it was determined that during rain, the sloped earth leading to the final grade  
at the rear of the residence was sliding down the slope and creating mud pools on the surface of  
the walk-out area. In order to address this issue, two small retaining walls were built, one of  
which is depicted in the bottom photograph of page 114 of Exhibit 1-F-35.  
[416] I am satisfied that this was appropriate remediation under the circumstances.  
15. Stucco  
[417] As originally designed, the exterior of the residence was to be finished using a  
combination of stone veneer and stucco. Some exterior features, including the fireplace chimney  
and the deck columns were to be clad entirely in stone, while the upper portion of the residence  
was, with some exceptions, to be clad in stucco.  
[418] Metcalfe gave evidence that the final coat of acrylic stucco had not yet been applied in  
May 2013, when the Plaintiffs discovered that the windows leaked and the Defendants  
discontinued work on the project. He indicated that the second coat of stucco normally would be  
applied approximately one month after the application of the scratch coat.  
[419] According to the Code, the stucco on the residence had to comply with specified  
thickness, cladding-continuity, and clearance-from-grade requirements. The stucco requirements  
are outlined in Section 9.28.6.6(2) of the Code:  
9.28.1.4 Clearance over Ground Level  
 
Page: 67  
1) Stucco shall not be less than 200 mm above finished ground level except when  
it is applied over concrete or masonry.  
9.28.6.3 First Coat  
1) The first coat shall not be less than 6 mm thick, measured from the face of the  
lath or masonry, fully embedding the lath.  
2) The surface of the first coat shall be scored to provide a key with the second  
coat.  
9.28.6.4 Second Coat  
1) The second coat shall not be less than 6 mm thick.  
2) The surface of the second coat shall be lightly roughened to provide a key with  
the finish coat if the finish coat is other than stone dash.  
9.26.6.6 The second coat shall be continuous across the entire surface of the first  
coat and have no gaps or voids.  
[420] According to Bjornson, the stucco on the Swanby residence had extensive map cracking  
on all elevations. Cracks extended as far as the entire depth of the stucco scratch coat and brown  
coat and could be easily removed. These deep and extensive cracks could permit water to  
penetrate through in bulk in breach of Code section 9.28.6.  
[421] In her examination of the exterior finish of the residence, Bjornson identified several  
issues with respect to the stucco. First, she noted that it was not sufficiently clear of grade around  
the rear patio under the deck. While final grade was not present at the time of Bjornson’s work  
on the residence, the concern was that the stucco would end up too close to grade in other areas  
of the house. She noted that a special solution must be devised in accordance with Part 5 of the  
Code in order to install stucco close to grade: Exhibit 16, p. 38, photo 8.34.  
[422] Bjornson described the map-cracking on the as-built residence as amongst the ten worst  
cases she had ever reviewed, including 300 installations in the two years immediately preceding  
her trial evidence. She described the map-cracking as “extensive” and noted that the stucco was  
easily removed. She also observed dark spots at the corners of the house, particularly in the  
vicinity of the garage. She noted that the stucco was adequately thick in most areas on the  
residence. Save for the rear patio area, and that it was of sufficient hardness: Evidence of  
Bjornson, (Direct) April 22, 2019, p.m.; (Cross) April 24, 2019, at 3:11 & 3:20 p.m.; Exhibit  
16, p 39, photo 8.63.  
[423] The Defendants advance a number of arguments challenging the Plaintiffs’ decision to  
remove all of the stucco on the residence. First, they rely on Hamman’s evidence that map  
cracking is common and that he did not note any cracks exceeding 1/8” in depth. He also did not  
find any Code violations relative to the stucco. Second, the Defendants appear to challenge  
Bjornson’s evidence regarding the extent and severity of the stucco cracking, arguing that she  
tested only one area of the residence and, further, that she was not able to identify the specific  
cause of the map-cracking. Third, they appear to rely on information provided to Ms. Swanby by  
an unidentified stucco contractor, who informed her that the stucco cracking was the result of it  
having sat too long in an unsealed state. Finally, they challenge Bjornson’s reliance on the  
presence of house-wrap under the stucco as a reason to remove all of the stucco.  
Page: 68  
[424] Hamman confirmed the map-cracking, but expressed the opinion that the first two coats  
and the wire mesh were well-bonded to the wall. At the time of his site inspection on October 3,  
2013, he did not observe any weak or falling areas.  
[425] Hamman made a series of recommendations that appear to contradict his overall  
conclusion that there were no issues with the stucco. First, he suggested the removal and  
recoating of those areas where the brown coat was weak or failing. He also recommended  
patching larger cracks with glass fibre tape prior to the application of the acrylic colour coat. As  
such, he recommended the application of glass fibre tape to the entire surface as part of the final  
colour coat.  
[426] Bjornson rejected Hamman’s proposed remediation. In her view, glass fibre tape is only  
appropriate to address telegraphing and very minor cracking. In her view, the map cracking in  
this instance was both too thick and too extensive. Further, she raised the concern that the  
extensive cracking evident in this situation would come through the final acrylic colour coat.  
Hamman acknowledged he could not be certain that his recommended use of glass fibre tape  
would prevent telegraphing in this instance.  
[427] I accept the Defendants’ contention that Bjornson conducted destructive testing in only  
one area of the residence. In her expert report, Exhibit 16, p 40, photo 9.37, shows the beginning  
of the destructive testing in a two-foot area at the front of the house. The photograph shows an  
area in the centre where the stucco has been removed. According to Bjornson, the rest of the  
stucco in this area located between two stone sections was ultimately removed by hand. I am  
satisfied that Bjornson conducted other testing in reaching her conclusions regarding the wide-  
spread nature of the map cracking and, more significantly, the depth of these cracks. In  
particular, she described observing Juniper easily remove stucco from other areas of the house  
with the light tap of a hammer.  
[428] In cross-examination, Bjornson clearly rejected the suggestion put to her by counsel for  
the Defendants that prolonged exposure to the elements is a factor in the incidence of map  
cracking. I accept Bjornson’s evidence in this regard. I also accept her evidence that map  
cracking is generally caused by the stucco drying too quickly on account of warm outside  
temperatures, or the drying stucco not being sufficiently hydrated. Given that she was not present  
when the scratch and brown coats were applied, it obviously was not possible for her to  
determine the precise cause of the map cracking in this instance. I am not persuaded that this in  
any way undermines the weight to be placed on her findings and conclusions.  
[429] In her evidence, Bjornson described the presence of Tyvek house-wrap under the scratch  
coat. She explained that the concern is that the scratch coat will bond with the backside of the  
wrap, thereby compromising the separate plane of protection afforded by the house-wrap.  
According to Bjornson, it is common practice to either double up the house-wrap before  
applying the scratch coat or not use house-wrap at all. While she did not observe any actual  
bonding in this instance, she maintained that the concern remains that it may occur over time.  
[430] While the Defendants appear to challenge Bjornson’s evidence regarding the presence of  
Tyvek house-wrap in this instance, I note that this was not a point that was raised with her in  
cross-examination. In my view, there is no merit to the Defendants’ challenge. I would also note  
that Hamman agreed in cross-examination that the stucco would need to be removed if it had  
been improperly installed over Tyvek.  
Page: 69  
[431] Bjornson recommended total removal of the stucco based on several factors, including  
the extensive map-cracking, concerns relating to the stucco bonding to the house wrap, the grade  
issues, and the problematic door and window installation. She rejection the option of partial  
removal of the stucco because of her concerns about the extent of the map cracking and the  
possibility of bonding to the house wrap. She also noted that it is very rare to do a partial  
removal of stucco to effect this kind of repair. In her view, only total removal could ensure  
second barrier continuance.  
[432] Based on Bjornson’s recommendation, the Plaintiffs elected to remove the stucco. In  
addition, TGC removed the building envelope down to the sheathing, then reinstalled the house  
wrap and stone. Rather than re-installing stucco, the Plaintiffs elected to install Hardie Board. I  
accept Juniper’s evidence that the use of Hardie Board was less costly in the circumstances than  
reinstallation of stucco.  
16. Stone Work  
[433] There is considerable discrepancy in the parties’ evidence about the application of the  
exterior stone veneer to certain portions of the residence, as well as the preparation of those  
surfaces prior to the application of the stone. In addition, the Defendants take the position that  
the supply and installation of the stone was specifically excluded from the contract with the  
Plaintiffs and, as such, they bear no responsibility for any deficiencies that may have arisen  
relative to the installation of the stone.  
[434] The stone mason, Lawrence, testified that the stone was installed directly over the stucco  
brown coat that was applied to the entire exterior prior to his arrival on site. He stated that the  
mortar base was “whatever the stucco guy used”, and then explained that he could tell by the  
colour that it was a Portland lime mix. He confirmed that he used a Type S mortar to apply the  
stone to the building. Lawrence maintained that he had no concerns about applying the stone to  
the surface as it existed when he arrived on site: Evidence of Lawrence, (Direct), May 14, 2019  
(a.m.).  
[435] According to Metcalfe, the stucco scratch coat was done at Carm’s direction. He  
maintained that it was against best practices for stucco workers to do the preparation work for  
masons. Hamman agreed with Metcalfe’s view that this was not good practice. Nevertheless,  
Metcalfe directed that the stucco scratch coat be applied to the entire residence.  
[436] Carm denied telling Metcalfe to have the stucco trades prepare the residence for the  
masons. Rather, he testified that he discussed with Metcalfe the implications on the overall  
project arising from delay in the shipment of the stone from India. These discussions went back  
and forth around the possibility of completing the house wrap on the exterior of the residence  
and the application of the scratch coats of stucco to the entire residence to allow work to  
continue on the interior finishing while waiting for the stone to arrive. Carm maintained that he  
has no knowledge as to the normal sequencing of stucco and masonry work. He was adamant  
that he left this decision to Metcalfe, the general contractor.  
[437] Carm also testified that he never provided instructions to the stucco contractor to apply  
the scratch coat to the entire residence. He insisted that he was not paid by the Plaintiffs to  
supervise the trades and that he did not instruct any of the trades on how to perform their  
functions. He testified that Metcalfe was the general contractor.  
 
Page: 70  
[438] I accept Carm’s evidence and find that Metcalfe, as the general contractor, directed that  
the scratch coat to be applied to the entire residence. I do not accept Metcalfe’s contention that  
he was in any way “directed” to do this by Carm.  
[439] I am satisfied that the stone mason, John Lawrence, did not prepare the house for the  
application of the stone finish other than the deck columns. The moisture barrier, metal lath,  
scratch coat and brown coat, had already been applied prior to Lawrence starting work. In his  
evidence, he expressed the view that this is not common or typical practice.  
[440] Bjornson expressed the view that the application of stone over the stucco brown coat is  
not standard practice and is not Code-compliant as it does not allow for an adequate bond.  
Bjornson explained that stone and stucco are different cementitious products and, as such,  
require different mortar bases. Stone is a heavier material and requires Type-S mortar, while  
stucco requires Type-N mortar. Further, she noted that the K2 Stone Nature Veneer used in this  
instance specified in the installation guidelines that Type S mortar be used for installation.  
[441] Bjornson reported that the thin stone veneer had a high probability of failure as a result of  
the bonding issue. According to Juniper, the stone was not properly bonded to the walls and  
came away by tapping with a rubber mallet. He explained that stone removal is ordinarily a very  
labour-intensive process. Bjornson recommended that the stone be removed and replaced due to  
the deficiencies.  
[442] While Hamman’s evidence was that the stone appeared to be well-bonded to the walls, he  
also stated that he had no issues with Bjornson’s observations to the contrary. I prefer the  
evidence of Juniper and Bjornson in this regard.  
[443] In terms of other deficiencies in the stone installation, Bjornson also identified loosely  
bonded stone sills at the exterior doors on the patio. At the same time, she observed horizontal  
mortar joints that had been left fully exposed to degradation from pooled moisture. Further, she  
noted that mortar joints at stone sills were insecure and could be easily removed.  
[444] Another issue involved the metal starter angle strip used to support and frame the actual  
stone veneer. As built, the installed angle strips were attached using 2” screws. Upon  
investigation, however, it was determined that many of the metal angle strips were not secure as  
the screws were not sufficiently long to penetrate into the studs.  
[445] During the investigation, it was determined that some of the stone had, in fact, been  
properly installed. In the result, Bjornson and Juniper ultimately removed approximately 75% of  
the stone that had been installed previously.  
[446] The stone veneer requirements in the Code are outlined at section 10.5.1.  
10.5.1 Thin Veneers secured individually by mortar adhesion  
Thin veneers secured individually by mortar adhesion shall  
a) be supported by structural backing;  
b) have all of their joints filled with mortar that meets the requirements of  
CSA A179; and  
c) be secured to the structural backing by  
Page: 71  
(i) galvanized metal lath over structural backing other than  
masonry or concrete, in accordance with the material,  
specification, application, and fastening requirements for stucco  
lath in Part 9 of the National Building Code of Canada;  
(ii) a 6 mm scratch coat of Type M, S, or N cement plaster directly  
over masonry or concrete, or over metal lath where the structural  
backing is other than masonry or concrete; or  
(iii) a 20 mm mortar bed of Type M, S, or N cement plaster applied  
over the cured scratch coat and a bond coat of Type M, S, or N  
cement plaster applied to the back of the veneer units and set into  
the mortar bed.  
[447] In terms of remediation, Bjornson recommended that the stone be removed to repair the  
underlying stucco. Hamman agreed that if the stucco was improperly installed, then the stone  
would have to be removed in order to remediate the stucco. Bjornson also recommended  
replacement of the stone but accepted that the actual remediation undertaken in this instance  
involved cleaning and re-installation of the stone initially installed. She expressed the view that  
this was appropriate if the salvaged stones were in good condition. TGC was able to clean and  
re-use most of the original stone.  
[448] I am satisfied that the wrong mortar base was applied to the residence in those locations  
that were to be finished with the natural stone veneer product. At Metcalfe’s direction, the stucco  
scratch coats were applied to the entire residence. The stucco scratch coat and brown coat were  
not the correct base for the stone installation, leading to inadequate bonding of the stone pieces  
to the residence exterior as described by Bjornson and Juniper.  
[449] Moreover, as described in the previous section of these Reasons, the stucco application  
was so seriously deficient as to require its complete removal. Combined with the stone to stucco  
bonding issues, I am satisfied that it was necessary to remove all the stone to address the  
deficiencies associated with the underlying stucco. Since the stucco was clearly part of the  
Defendants’ responsibilities under the contract, I find that the removal of the stone was a  
necessary element of the remediation process for which the Defendants were responsible.  
17. Building Envelope, Eaves & Soffits  
[450] In her report and her trial evidence, Bjornson concluded that the building envelope was  
not properly constructed and required remediation. She found numerous Code deficiencies and  
failures to meet industry best practices.  
[451] In her report, Bjornson explained that the moisture barrier provides the secondary layer of  
protection for a building. The Code requires this secondary plane of protection in section 9.27.3:  
9.27.3. Second Plane of Protection  
9.27.3.1 Elements of the Second Plane of Protection (See Appendix A)  
1) The second plane of protection shall consist of a drainage plane having an  
appropriate inner boundary and flashing to dissipate rainwater to the exterior.  
[452] Based on her extensive examination of the as-built construction of the residence,  
Bjornson expressed the view that the moisture barrier was discontinuous and, therefore, not  
 
Page: 72  
Code-compliant. She noted that only a portion of the moisture barrier was visible at the time of  
her review, though she indicated that additional areas were revealed during the investigative and  
remediation processes. Due to the visible interior water leakage throughout the residence, she  
concluded that the moisture barrier clearly had not provided the continuous protection envelope  
required by the Code.  
[453] She also observed that the house wrap did not extend past the soffit line and that the top  
edge of the moisture barrier was susceptible to wind driven rain through the soffits’ perforated  
material. Further issues with the discontinuity of the moisture barrier were also observed in  
relation to the rear patio doors leading to the deck area. Water testing resulted in leakage below  
the deck area and into the interior of the bar area below the deck. Water stains were observed on  
the drywall in this area of the residence, indicating previous leakages.  
[454] As a result of testing conducted on the roof, Bjornson determined that water was coming  
out of the soffits and running down the exterior walls. She noted that the flashing was not  
installed in accordance with best practice to protect the eaves under the shingles. Specifically,  
she noted that there was insufficient flashing or drip edge behind the eavestroughs and fascia.  
She concluded that the roofing installation was not Code-compliant regarding eaves protection  
and drip flashing.  
[455] Other witnesses noted that the eaves and soffits leaked. Juniper testified that he observed  
water coming out of the soffits and running down the exterior walls. He noted that there was no  
flashing present to prevent water from running down the walls. He referred to p 118 of his report,  
top photograph, Exhibit 1-F-35, as depicting the work they were required to do to install flashing  
on most of the roof.  
[456] Metcalfe asserted that a drip edge and Tyvek house wrap were installed, but  
acknowledged during questioning that he was aware there were issues with leaking soffits.  
[457] In his report, Hamman expressed the view that the moisture barrier had been properly  
installed. However, in cross-examination, he acknowledged that his conclusion was based on  
information provided to him regarding the soffit installer’s usual methods of installing house  
wrap to the soffit line. He also relied on a series of construction progress photographs that were  
not identified during the trial. In the result, I place little weight on his opinion and prefer  
Juniper’s evidence on this point.  
[458] Bjornson recommended removal and replacement of the entire moisture barrier. TGC  
replaced the entire building envelope, all eavestroughs, most soffits and fascia, and installed a  
drip and break edge over the entire house. I am satisfied that this was an appropriate approach to  
the remediation of the issues.  
18. Exterior Decorative Beams  
[459] The Defendants undertook an “extra” in terms of installing false beams in the gables over  
the front entrance. A second decorative beam was to be installed in one of the gables at the back  
of the home. McEwen confirmed that he assisted Metcalfe in installing these decorative beams.  
The Defendants billed for this work.  
[460] According to Juniper, the decorative beam at the front of the residence was not properly  
connected to the structure. He determined that this beam was only tacked to the soffit with nails,  
rather than being properly anchored and bolted to the exterior structure. He testified that he was  
 
Page: 73  
able to pull the beams away from the exterior structure easily by hand. He indicated that the  
second decorative beam at the back of the house had been properly installed.  
[461] In terms of remediation, a replacement beam has not yet been ordered or installed.  
19. Mechanical Room & Plumbing  
[462] Juniper described a floor joist in the mechanical room that had been cut to accommodate  
the plumbing for a toilet in the room above. According to him, this was inconsistent with the  
ZyTech shop drawing that called for an adjustment to the flooring to avoid cutting through the  
floor joist: Exhibit 1-A-2. Neither Metcalfe nor McEwen offered any explanation for this  
deviation from the shop drawing.  
[463] Matthews issued an engineered repair detail regarding the cut out of this truss that  
involved stiffening a three-foot section of the truss: Exhibit 1-A-7, SKI. TGC effected this repair  
in conjunction with the remediation process. Juniper was also required to add blocking and nail  
hangers to the floor system in the mechanical room.  
[464] According to Juniper, the original boiler system that was installed in the residence was  
inadequate to service the entire house, including the in-floor heating systems installed throughout  
the residence. He testified that the pressure tank was too small for the intended purpose given the  
number of zones in the residence that required service. Neither Metcalfe nor McEwen offered  
any evidence on this point.  
[465] As part of the remediation process, TCG upgraded the boiler system to meet the needs of  
a house of that size by increasing the size of the pressure tank and installing a pressure regulator:  
Exhibit 1-F-35, p 136.  
[466] Juniper also gave evidence regarding a series of repairs or upgrades required in relation to  
the electrical system in the residence. First, he described the considerable work that was required  
to properly mark the main electrical box located in the mechanical room. He explained that this  
is a step that is usually completed near the end of the construction process. In this instance, the  
electrical box had not been marked by the original electrician prior to him abandoning the job  
site. TGC was, accordingly, required to pull back substantial electrical wiring and to determine  
the function of each wire to allow for the proper labelling of the electrical box and the  
connection of wires to the appropriate electrical box or outlet: Exhibit 1-F-35, p 138, top  
photograph.  
[467] In effecting this remediation, TGC was able to re-use approximately 85% of the  
plumbing and electrical materials. However, Juniper described this as a great deal of work:  
Evidence of Juniper, April 12, 2019, p.m.  
[468] Further, Juniper explained that a second electrical box was located adjacent to the  
principal electrical box. During the remediation work, it was determined that the wire going into  
the sub-panel was under-rated and had to be upgraded.  
[469] Finally, while tracing electrical lines to mark the electrical panel, an electrical outlet was  
discovered behind a completed plywood wall in the mechanical room: Exhibit 1-F-35, p 135.  
This was also addressed during the remediation process.  
 
Page: 74  
20. Other Deficiencies Identified by Bjornson  
[470] Bjornson’s expert report raised questions regarding several other aspects of the  
construction of the home. It is not, however, necessary for me to deal with these specific matters  
since there is no evidence that the Plaintiffs took any steps to address any of these issues during  
the remediation process.  
E. Other Possible Breaches  
1. Metcalfe’s Lack of Involvement in the Project  
[471] The Plaintiffs raise several concerns relating to Metcalfe’s role as their general contractor  
during the course of the construction project and, in particular, his lack of oversight of the  
various trades hired to perform different aspects of the work.  
[472] In his testimony, Metcalfe acknowledged that a general contractor must be present on the  
work site to oversee the work of the sub-trades. He also conceded that he had been away from  
Alberta on personal business for a period of 8 to 9 months during the approximately 19 months  
that he was involved in this project. The Plaintiffs point to the lack of progress reports and the  
absence of any contemporaneous photographs taken by Metcalfe as one of the shortcomings  
flowing from his extended absences.  
[473] As more fully set out later in these Reasons, I am satisfied that Metcalfe’s frequent and  
extended absences from Alberta left him in a state that he lacked proper knowledge of the details  
of the work undertaken by trades acting under his supervision. I find that most if not all of the  
construction deficiencies ultimately identified by the Plaintiffs’ experts related to matters that  
were largely unknown to Metcalfe. This lack of up-to-date knowledge also was a contributing  
factor in Metcalfe’s failure to engage expert assistance in relation to a number of issues that  
arose during construction.  
[474] I accept the Plaintiffs’ submissions that Metcalfe’s extended absences from the job site  
severely impacted his ability to properly monitor and supervise the work of his sub-trades.  
Combined with what I find to be his general lack of engagement in this project, Metcalfe was left  
in a situation where he lacked essential information about the various issues that arose during  
construction. Metcalfe’s general lack of knowledge about the project was manifested in a number  
of ways, including the communication deficiencies that lie at the heart of the Plaintiffs’ concerns  
discussed in the next section  
[475] Based on the expert evidence of both Kraychy and the Defendants’ expert, Hamman, I  
am satisfied that Metcalfe consistently failed to meet the standards expected of an experienced  
custom home builder in terms of his knowledge and involvement in this project.  
2. Failure to Keep the Plaintiffs Informed  
[476] The Plaintiffs maintain that the Defendants failed to keep them properly informed of  
important developments during the construction project, notably deficiencies and other problems  
that arose. The Plaintiffs refer to Kraychy’s evidence regarding a software program he employs  
to keep customers up to date on necessary changes to the plan and the associated cost  
implications. He testified that sharing this information with customers on an on-going basis  
       
Page: 75  
allows them to be aware of the amount of the various allowances that are available, as well as to  
keep track of the overall cost of the project.  
[477] Both Ms. Swanby and Carm gave evidence that Metcalfe was reluctant or unable to  
provide detailed financial information relating to the various allowances. Carm commenced a  
budgeting process to assist the Plaintiffs with this aspect of project management, particularly in  
relation to the interior work.  
[478] The Plaintiffs maintain that Metcalfe failed to meet the requisite standard of care in  
communicating openly and transparently with his clients once he knew deficiencies had been  
identified. They assert that he was reckless in his failure to disclose and to confirm that other  
aspects of the work were adequate. Hamman confirmed in cross-examination that, faced with  
sub-trade deficiencies, he would take steps to review all of the other work undertaken by that  
particular trade to confirm that it had been properly executed.  
[479] Earlier in these Reasons, I referred to the important evidence of Kraychy, the Plaintiffs’  
expert called to give opinion evidence in relation to a number of issues touching on custom  
home-building. I accepted Kraychy’s evidence regarding the importance of effective, on-going  
communication between a general contractor and his or her customers. He explained the need for  
a general contractor to keep the customer fully apprised of the progress of the project and  
actively engaged in the resolution of issues or problems arising during construction. I am  
satisfied that there was a serious communication deficiency in this instance on the part of  
Metcalfe. Unfortunately, Metcalfe’s poor communication with the Plaintiffs gave rise to an  
erosion and, ultimately, a breakdown, in the Swanby’s confidence in him.  
F. Application of Liability in Contract  
[480] As already noted, the Plaintiffs rely on the deficiencies enumerated above in support of  
their contention that the Defendants are in breach of contract.  
[481] I find that the construction deficiencies enumerated above amply demonstrate that Tru-  
Square breached its contract with the Plaintiffs. Contrary to their agreement, numerous aspects of  
the construction failed to meet Code standards, let alone the higher standard advocated by the  
Plaintiffs and their experts. Further, Tru-Square failed to provide proper supervision of the  
subcontractors.  
[482] The difficulty for the Plaintiffs is that their contract, whatever its terms, was with Tru-  
Square only, not with Metcalfe. Therefore, no contractual remedy is available as against  
Metcalfe. To impose liability on him personally, the Plaintiffs must establish that they are  
entitled to such a remedy in tort.  
G. Application of Liability in Tort  
[483] The Plaintiffs say that the construction was deficient from a Code perspective in a  
number of areas. Moreover, citing Ryan v Victoria, [1999] 1 SCR 201, the Plaintiffs say that  
even if there was compliance with the Code, that does not absolve the Defendants from  
negligence. At para 29, the Court in Ryan held:  
Legislative standards are relevant to the common law standard of care, but the two  
are not necessarily coextensive. The fact that the statute prescribes or prohibits  
certain activities may constitute evidence of reasonable conduct in a given  
   
Page: 76  
situation, but it does not extinguish the underlying obligation of reasonableness.  
See Saskatchewan Wheat Pool v Canada, [1983] 1 SCR 205. Thus, a statutory  
breach does not automatically give rise to civil liability; it is merely some  
evidence of negligence. See, e.g. Stewart v Pettie, [1995] 1 SCR 131 at para 36,  
and Saskatchewan Wheat Pool, at p. 225. By the same token, mere compliance  
with the statute does not, in the end of itself, preclude a finding of civil liability.  
See Linden, supra, at p. 219. Statutory standards can, however, be highly relevant  
to the assessment of reasonable conduct in a particular case, and in fact may  
render reasonable an act or omission which would otherwise appear to be  
negligent. This allows courts to consider the legislative framework in which  
people and companies must operate, while at the same time recognizing that one  
cannot avoid the underlying obligation of reasonable care simply by discharging  
statutory duties.  
[484] Further, the Plaintiffs rely on the evidence of Kraychy and the other experts regarding the  
applicable standard of care. In particular, they point to the good workmanlike standard implied in  
every building contract, the need to communicate effectively with homeowners, the requirement  
to disclose deficiencies and to take appropriate steps to rectify such deficiencies, and generally to  
ensure that the homeowners’ objectives are satisfied.  
[485] I accept the Plaintiffs’ suggestion that the observations, opinions and recommendations of  
their experts are largely unchallenged by the Defendants. Indeed, Hamman did not seriously  
challenge any of the findings or conclusions of either Bjornson or Matthews. In some instances,  
Hamman agreed with the Plaintiffs’ experts that the original construction was deficient.  
[486] The Plaintiffs assert that the deficiencies described above establish that the applicable  
standard of care was not met in this instance and that Tru-Square is liable in negligence.  
Moreover, the Plaintiffs contend that Metcalfe may be held personally liable for that negligence.  
They arrive at this conclusion via a number of different routes.  
1. Inherently Dangerous Work  
[487] First, the Plaintiffs say that Metcalfe should be held personally liable for Tru-Square’s  
negligent construction because the work performed was inherently dangerous. They point to  
several examples:  
a) The bonus room stairs were not properly connected;  
b) Unsecured steel I-beams in the Bonus room and the back deck;  
c) The deck was not properly connected to the main structure;  
d) One of the deck’s concrete piles was resting on disturbed soil and not of sufficient  
depth;  
e) Live wires were located behind the drywall in the garage and in the bedroom, as well  
as under the jet tub in the master ensuite bathroom. All of these wires were, to  
Metcalfe’s knowledge, energized without any final review by an electrician or any  
warning provided to the Plaintiffs;  
f) Threshold cut outs directed by Metcalfe undermined the structural integrity of the  
residence and exposed the structure to serious water damage; and  
g) Broken roof trusses were not repaired prior to being installed in the residence.  
 
Page: 77  
[488] The Defendants argue the Plaintiffs have failed to establish that any of the work actually  
performed by Metcalfe resulted in damage and that the decided cases on this point do not cover  
the risk of physical damage, only the actual occurrence of such damage. Further, they assert that  
the Plaintiffs have failed to establish the probability of risk of physical injury flowing from the  
Defendants’ negligence.  
[489] The Defendants rely on the Court of Appeal’s comments in Vargo v Hughes 2013 ABCA  
96 at para 43:  
In our view, the trial judge had a sufficient basis to conclude that the threat of roof  
collapse meant the house was dangerous. His conclusion was not palpably wrong.  
He had before him expert evidence that if a sufficient snow load came onto the  
roof tresses, there was a “good chance” they might collapse. This meets the  
“reasonable likelihoodstandard required by Winnipeg Condo.  
[490] The Defendants challenge the Plaintiffs’ contention that either the deck or the Bonus  
Room staircase was inherently dangerous. With respect to the deck, they maintain that the  
Plaintiffs’ reliance on a statement attributed to Matthews by Ms. Swanby was not confirmed in  
his actual trial evidence. In any event, the Defendants say that Matthews never observed the as-  
built deck and, as such, his words to Ms. Swanby predicting its ultimate collapse, without more,  
are insufficient to conclude that the deck construction was inherently dangerous.  
[491] I am satisfied that there was reliable evidence regarding the inadequacy of the decks  
connection to the main residence. Both Matthews and Juniper gave evidence about this and even  
the Defendants’ expert, Hamman, acknowledged the risk posed by the as-built condition of the  
deck, noting “at some point, that deck’s coming off the wall.”  
[492] In my view, the as-built condition of the deck posed a significant risk to users of the deck  
and the outdoor space accessed from the basement directly beneath the deck. I am satisfied that  
the deck construction was inherently dangerous.  
[493] The Defendants also challenge the Plaintiffscontention regarding the hazardous nature  
of the Bonus Room staircase’s connection to the house frame. They rely on the evidence of  
Metcalfe and McEwen regarding their personal involvement in this process. I prefer the evidence  
of Matthews given what I find to be the contradiction in the evidence of Metcalfe and McEwen  
on this point. As outlined elsewhere in these reasons, I also have serious reservations about the  
reliability of Metcalfe’s evidence generally.  
[494] In my view, the as-built condition of the Bonus Room staircase posed a significant risk to  
the various trades who may have had occasion to use it during the course of construction. In  
addition, the Plaintiffs and others using the staircase in the future would also have been exposed  
to a significant risk of collapse given the inadequacy of its connection to the rest of the building  
structure.  
[495] I am satisfied that my findings do not require proof of actual injury to persons or of actual  
collapse. The investigative work conducted by the Plaintiffs’ experts brought the danger to the  
Plaintiffsattention prior to occupancy, thereby averting a likely accident once the deck and  
staircase were subjected to normal use.  
[496] I note that the Court of Appeal stated this in Vargo at paras 26 and 27:  
Page: 78  
The main policy justification given by the Supreme Court in Winnipeg Condo for  
allowing the subsequent owner of a negligently constructed building to recover  
the cost of repairing defects which present a real and substantial danger was to  
encourage that subsequent owner to take preventative steps before physical  
damage to persons or property resulted. If a plaintiff can show a reasonable  
likelihood of a real and substantial danger to the building’s occupants, there is no  
point in making the owner wait until the risk of injury manifests itself before  
attending to the repair of the dangerous defect. ...  
And, once it has been established that sufficient harm is reasonably likely to occur  
within the useful life of the building, what, if anything, is gained by imposing an  
imminence requirement on the harm? ...  
[497] To be sure, Vargo dealt with the question of whether a negligent builder could be liable  
to a subsequent owner of the building. In my view, however, it would be nonsensical to allow a  
claim by a subsequent owner but bar recovery by the party who engaged the negligent builder.  
[498] Accordingly, I find that the Defendants’ negligent construction of the residence created a  
real and substantial danger to its occupants that permits recovery.  
[499] The remaining difficulty, however, is that there was no reference in Vargo to the builder  
operating through a corporation. Therefore, it is not clear to me that Vargo permits the Plaintiffs  
to recover from Metcalfe personally, as opposed to from Tru-Square.  
2. Fraud  
[500] The Plaintiffs advance two arguments in support of their position that Metcalfe’s conduct  
was not only negligent, but fraudulent. First, they say that Metcalfe “pacified” them into  
believing that their dream home would be realized notwithstanding the existence of substantial  
and dangerous construction deficiencies. They argue that his concealment of these deficiencies  
amounts to fraud. Second, the Plaintiffs say that Metcalfe had Tru-Square send them invoices for  
goods and services that were not provided.  
[501] The Plaintiffs rely on the test for fraud set out in Bruno Appliances and Furniture Inc v  
Hryniak, 2014 SCC 8 at para 21:  
From this jurisprudential history, I summarize the following four elements of the  
tort of civil fraud: (1) a false representation made by the defendant; (2) some level  
of knowledge of the falsehood of the representation on the part of the defendant  
(whether through knowledge or recklessness); (3) the false representation caused  
the plaintiff to act; and (4) the plaintiff’s actions resulted in a loss.  
[502] The Plaintiffs maintain that Metcalfe knowingly concealed construction deficiencies  
within his actual knowledge or was reckless or wilfully blind to deficiencies he should have  
known about through the exercise of reasonable diligence in his role as general contractor. They  
particularize these undisclosed deficiencies as follows:  
a) Failure to engage a qualified surveyor to mark and peg the foundation  
notwithstanding that the cost of same was included in the contract;  
b) Failure to engage an engineer or obtain engineered drawings relative to Metcalfe’s  
decision to shift from an ICF foundation to a traditional foundation;  
 
Page: 79  
c) Failure to disclose that the foundation was off-set;  
d) Failure to remedy the off-set foundation. Rather, Metcalfe told the framer to frame  
the residence square off the foundation;  
e) Metcalfe was aware that OSB and untreated lumber was improperly used at grade in  
contravention of the Code;  
f) Directing or permitting the framer to cut away floor sheathing at numerous door  
threshold without first obtaining engineering advice on the positional impact on the  
structural integrity of the building;  
g) Failure to disclose the lack of proper connection of the staircase leading to the Bonus  
Room above the garage;  
h) Permitting the steel I-beam relating to the deck to be encased notwithstanding that it  
was improperly supported. In this regard, Metcalfe failed to consult the Code to  
obtain guidance as regards the minimum requirements;  
i) Permitting the most southerly pile supporting the deck to rest on disturbed soil and at  
a non-Code compliant depth;  
j) Failure to disclose the existence of window leaks in the Bonus Room prior to the  
Plaintiffs discovery of generalized window leaks in May 2013;  
k) Failure to address leaking pot lights notwithstanding advice from the electrician that  
water was observed to gush through the openings in the seal. Further, Metcalfe  
personally installed blow-in insulation in the attic around these same unsealed pot  
lights;  
l) Failure to install sound insulation in the main basement ceiling area despite an  
agreement with the Plaintiffs in this regard.  
[503] The Plaintiffs assert that Metcalfe told Ms. Swanby the foundation “looked good”  
notwithstanding that it was off-set or not square and that he failed to address the issue or to  
consult an engineer. Further, Ms. Swanby testified that she had a conversation with McEwen in  
which he reported that Metcalfe had told him not to disclose any framing problems to the  
Plaintiffs.  
[504] The Defendants assert that a November 19, 2012 email from Metcalfe to Mr. Swanby  
“disclosed problems and concerns”. They also challenge Ms. Swanby’s evidence about the  
alleged conversation with McEwen. Metcalfe denied having ever made such a statement to  
McEwen. As well, the Defendants assert that McEwen denied ever having had such a  
conversation with either Metcalfe or Ms. Swanby.  
[505] I reject the Defendants’ argument that the November 19, 2012 email actually disclosed  
problems and concerns. Rather, as discussed elsewhere in these Reasons, it set out a description  
and attempted explanation for a series of cost over-runs associated with the project. In my view,  
it says nothing about problems or concerns with the construction.  
[506] Further, I accept Ms. Swanby’s testimony about the conversation with McEwen. Having  
carefully reviewed his evidence, I conclude the McEwen did not deny the alleged conversation;  
his denial pertained to something else.  
Page: 80  
[507] In considering whether Metcalfe’s conduct amounted to fraud, I have found instructive  
these comments from the Court of Appeal in Motkoski Holdings Ltd v Yellowhead (County),  
2010 ABCA 72 at paras 57 58:  
The legal definition of fraud is well established... There are two branches to it.  
Both branches are built on a finding that a false or inaccurate statement was made.  
Under the first branch, fraud is established if the defendant “knew” that the  
statement was false, and made it with the knowledge or intention that the plaintiff  
would rely on it.  
Under the second branch, it is sufficient if the defendant did not actually know the  
statement was false, so long as the statement was made recklessly. “Recklessly”  
in this context means that the statement was made “without caring whether it was  
true or false”. “Recklessly” does not just mean the statement was made with “very  
great negligence”, nor that it was made in a highly risky context, such that the  
probability of someone relying on the statement to their detriment was enhanced.  
As Lord Herschell said in Derry v. Peek at p. 375, “making a false statement  
through want of care falls far short of, and is a very different thing from, fraud,  
and the same may be said of a false representation honestly believed though on  
insufficient grounds”. Under neither branch of the test is it sufficient that the  
defendant “should have known” the truth, or should have been more careful and  
made further inquiries; actual knowledge or actual indifference to the truth is  
required.  
[508] The Plaintiffscivil fraud claim is based on Metcalfe’s alleged concealment of  
construction deficiencies that were within his actual knowledge or that he should have been  
aware of through the exercise of reasonable diligence as a general contractor. Other than  
Metcalfe’s statement to Ms. Swanby that the foundation “looked good”, the Plaintiffs’ argument  
is founded on concealment or failure to disclose, as opposed to actual false or negligent  
representations.  
[509] Having in mind the above comments from Motkoski, I am not satisfied that Metcalfe’s  
failure to disclose the construction deficiencies is sufficient to constitute fraud. Metcalfe’s  
frequent and extended absences from the construction site resulted, in my view, in his being  
largely unaware of how the construction was proceeding. While he was certainly negligent in his  
oversight of the project and in his dealings with the Plaintiffs, I consider his actions to be more in  
the nature of deflection or “want of care” than active concealment. Therefore, I am not prepared  
to find that his conduct amounted to fraud.  
[510] In a similar vein, I accept the Defendants’ argument that Metcalfe did not make verbal  
representations to the Plaintiffs prior to the signing of the construction contracts regarding his  
status as a “luxury custom home builder”. I do not interpret the Plaintiffs’ argument in this  
regard to suggest that he did. Rather, the Plaintiffs say that they relied on the fact that Tru-Square  
was a well-known builder in the area and they were personally aware that Tru-Square had been  
the contractor for building custom homes for Ms. Swanby’s brother and a neighbour. Further, the  
Swanbys had, through signage, seen evidence of Tru-Square’s work in the area. Through this  
body of work, the Plaintiffs say that Tru-Square held itself out to be an experienced custom  
home builder.  
Page: 81  
[511] With respect to their allegation of civil fraud on the basis of billing for work not  
completed, the Plaintiffs refer to several instances in which they say Metcalfe invoiced them for  
goods and services that were not provided. As discussed later in these Reasons, I have found that  
a number of these invoices are properly payable by the Plaintiffs.  
[512] In my view, this is not the Plaintiffsstrongest argument. While I accept that there is  
some evidence of anomalies in Tru-Square’s invoices, I am not satisfied that the Plaintiffs have  
established fraud on this basis. Under the circumstances, given the relatively modest amount of  
money involved, I am not prepared to infer that the Defendants had knowledge of the false  
statements that form the basis of the Plaintiffs’ claim in this regard. Rather, I am inclined to the  
view that these were careless, even negligent, mistakes or oversights on the part of the  
Defendants that will need to be addressed in dealing with damages.  
[513] In light of all of the foregoing, I am not prepared to find that Metcalfe’s conduct was  
fraudulent, though I will say that I consider this case very close to the line.  
3. Piercing the Corporate Veil  
[514] Finally, the Plaintiffs suggest that there is authority for personal liability to be imposed  
for non-dangerous defects in relation to individuals associated with closely held corporations.  
The Defendants take the position that any acts of negligence occurred while Metcalfe was  
engaged in the business of Tru-Square and therefore cannot be visited upon him personally.  
a) The Law  
[515] As far back as the seminal case of Kosmopoulos v Constitution Insurance co of Canada,  
[1987] 1 SCR 2, the Supreme Court noted at para 12 that “The law on when a court may  
disregard this principle by lifting the corporate veiland regarding the company as a mere  
agentor puppetof its controlling shareholder or parent corporation follows no consistent  
principle.” The Court added:  
The best that can be said is that the "separate entities" principle is not enforced  
when it would yield a result "too flagrantly opposed to justice, convenience or the  
interests of the Revenue": L.C.B. Gower, Modern Company Law (4th ed. 1979) at  
p. 112.  
[516] The rationale underlying this inconsistency was discussed at some length by Slatter JA in  
Hall v Stewart, 2019 ABCA 98 at paras 11-13:  
The widespread recognition of the corporation as a separate legal person, coupled  
with limited liability of those associated with the corporation, was one of the most  
important legal-economic developments of the 19th century. The corporate legal  
entity allowed the conglomeration of small amounts of capital into large pools of  
capital needed for complex enterprises. It allowed those with managerial expertise  
to exploit those sums, and those with cash but no expertise to put their assets to  
work. A modern corporation can own property, engage in business, and sue and  
be sued in its own name. A key feature of corporations is that the shareholders are  
not personally liable for the debts and obligations of the corporation.  
The recognition of a separate corporate personality, and the resulting limited  
liability, is not a loophole or a technicality; it is an essential tool of social and  
 
Page: 82  
economic policy. There are, however, some situations where personal liability  
remains, notwithstanding the concept of a separate legal personality and limited  
liability. While the corporation is seen as a valuable economic and social tool, it is  
recognized that it is a tool that can be misused. One area of potential personal  
liability is when officers and employees of a corporation cause damage by a  
tortious act. When will an employee or director be held personally liable,  
notwithstanding that they only acted on behalf of the corporation?  
Finding representatives of corporations personally liable for torts engages  
competing policy objectives. One policy objective of the law of torts is the  
compensation of injured persons. A competing policy objective of corporate law  
is the limitation of personal liability for corporate acts.  
[517] The difficulty in balancing these competing policy objectives manifests as a lack of  
coherence in the courts’ approach to piercing the corporate veil. Over time, various attempts  
have been made to bring some structure to this analysis. This was aptly expressed by Antonio JA  
in Aubin v Petrone, 2020 ABCA 13 at paras 21-22:  
The corporate veil is not impenetrable. The law provides for instances when the  
veil may be “pierced” or “lifted”. Such instances are rare and difficult to  
categorize, as the Supreme Court of Canada recognized in the seminal case of  
[Kosmopoulos]…  
Recognizing the variety of unpredictable situations in which it may be appropriate  
to life the corporate veil, Kosmopoulos reserves to the courts a residuum of ability  
to act to prevent injustice when necessary. However, the courts have been  
appropriately leery of interpreting Kosmopoulos as free rein to trench on the  
principle of corporate separateness. Some have tried to set out criteria or factors to  
govern the determination of when the corporate veil should be lifted.  
[518] Fundamentally, the courts have focused on two factual issues: the extent to which the  
corporation was controlled by its parent or principal and the nature and egregiousness of the  
alleged wrongdoing.  
[519] In Tirecraft Group Inc (Receiver of) v High Park Holdings ULC, 2010 ABQB 653,  
Justice Yamauchi provided a very thorough review of the law to that point, beginning with  
Kosmopoulos. He referred to two Ontario decisions: Transamerica Life Insurance Co of  
Canada v Canada Life Assurance Co (1996), 28 OR (3d) 423 (ONGD) and Clarkson Co Ltd v  
Zhelka (1967), 64 DLR (2d) 457 (ONHC).  
[520] The Court in Transamerica had refused to pierce the corporate veil, applying this test as  
set out at paras 22-23:  
As just indicated, the courts will disregard the separate legal personality of a  
corporate entity where it is completely dominated and controlled and being used  
as a shield for fraudulent or improper conduct. The first element, “complete  
control”, requires more than ownership. It must be shown that there is complete  
domination and that the subsidiary company does not, in fact, function  
independently…  
The second element relates to the nature of the conduct: is there “conduct akin to  
fraud that would otherwise unjustly deprive claimants of their rights?”  
Page: 83  
[521] The Court in Zhelka also had declined to pierce the corporate veil, though it found at  
para 86 that the case before it was “close to the line” after applying this test set out at paras 83-  
84:  
If a company is formed for the express purpose of doing a wrongful or unlawful  
act, or, if when formed, those in control expressly direct a wrongful thing to be  
done, the individuals as well as the company are responsible to those to whom  
liability is legally owed.  
In such cases, or where the company is the mere agent of a controlling corporator,  
it may be said that the company is a sham, cloak or alter ego, but otherwise it  
should not be so termed.  
[522] Justice Yamauchi then enumerated several factors the courts have found significant in  
determining whether a corporation is a “sham, cloak or alter ego”:  
(a) the shareholder treats itself and the corporation interchangeably;  
(b) the corporation is merely created to deflect monies from their proper usage;  
(c) the shareholder intermingles the corporation’s affairs with its own, such that  
the shareholder fails to recognize the corporation’s separate identity;  
(d) the shareholder treats corporate property as though it belongs to the  
shareholders without regard for the interests of those dealing with the  
corporation;  
(e) whether the corporation is independent from its shareholders;  
(f) whether the corporation has its own assets, skills or employees; and  
(g) whether the corporation has its own bank accounts, books or records.  
[523] Justice Yamauchi recognized that these indicia of control, in and of themselves, are not  
sufficient to justify piercing the corporate veil. Rather, he noted at para 25 that “It is only when  
the promoter uses the corporate structure as a cloak, sham or alter ego in such a way as to  
perform a wrongful, unlawful, fraudulent or improper act that causes third parties to suffer, will a  
court pierce the corporate veil.” (Emphasis added.)  
[524] Elbow River Marketing Limited Partnership v Canada Clean Fuels Inc, 2012 ABCA  
328, a decision delivered by Picard JA from the bench, involved a consideration of whether to  
pierce the corporate veil between two closely related corporations. Citing Transamerica, the  
Court of Appeal held at para 16 that “Canadian courts will pierce the corporate veil only when a  
corporation has been completely dominated and controlled and used as a shield for fraudulent or  
improper conduct.” The Court of Appeal did not review the factors set out in Tirecraft, but  
concluded that it was inappropriate to summarily dismiss the corporate veil issue and ordered  
that it proceed to trial.  
[525] In Spartek Systems Inc v Brown, 2014 ABQB 526, Justice Ross cited both Elbow River  
and Tirecraft and concluded that piercing the corporate veil was appropriate in that case. She  
stated as follows at para 282:  
The circumstances in which 113 was formed demonstrate that Brown did not  
distinguish between his own affairs and 113’s, and that 113 has no independent  
Page: 84  
existence apart from Brown. Brown transferred his own shares in Spartek to 113,  
and directed 113 to transfer those shares to Spartek and to receive payment for  
them. The evidence was that 113 had no objective and pursued no activity other  
than receiving payments under the Share Sale Agreement for Brown’s tax  
planning purposes. 113 was a mere alter ego of Brown.  
[526] Justice Ross went on at paras 283-285 to find that there was wrongful conduct:  
A wrongful act that justifies the lifting of a corporate veil does not have to amount  
to fraud. Courts have described circumstances where the corporate veil can be  
lifted as “improper conduct”, “wrongful conduct” or “conduct akin to fraud”:  
Tirecraft at paras 16 and 19.  
In this case, both Brown and 113, as Vendors under the Share Sale Agreement,  
had joint obligations under the Confidentiality, Non-Solicitation and Non-  
Competition Agreement. Brown went on to breach those obligations and to  
conspire with the other Defendants. It is true, as Brown argues, that Brown was  
not directing or acting on behalf of 113 when he breached his contractual  
obligations and entered into the conspiracy. But that is because 113’s sole purpose  
and activity, as determined by Brown, was the receipt of monies pursuant to the  
Share Sale Agreement.  
If the corporate veil is not pierced, 113 may receive the benefit of full payment  
under the Share Sale Agreement while avoiding any responsibility for Brown’s  
breach of the joint obligations under the Confidentiality, Non-Solicitation and  
Non-Competition Agreement. This may result in serious inconvenience and/or  
loss to Spartek, in the enforcement of its judgment against Brown. To permit  
Brown’s alter ego to improperly benefit and potentially permit Brown to escape  
from his obligations would be a result that should not be condoned by this Court.  
[527] The Plaintiffs cited two decisions in which personal liability attached to individual  
principals of corporations responsible for non-dangerous construction deficiencies. In 1469753  
Alberta Ltd v Luxen, 2015 ABQB 282, Pentelechuk J (as she then was) imposed personal  
liability, but the decision turned on the absence of any written estimate or contract for the  
plumbing and heating services supplied by the plaintiff and on the defendantslegitimate  
assumption that they were dealing with a sole proprietor. The Court found a breach of s 10(8) of  
the Business Corporations Act, RSA 2000, c B-9, requiring a corporation to set out its name in  
all contracts, invoices, negotiable instruments and orders for goods or services. I would simply  
add that in Luxen, the principal operating the plaintiff corporation did not perform any of the  
plumbing or heating work that gave rise to the defendants’ successful counterclaim founded in  
both contract and tort.  
[528] In Koltai v Hauser, 2017 BCSC 1675, the Court, relying on Transamerica, concluded  
that it was appropriate to pierce the corporate veil and find Hauser personally liable for breach of  
contract relating to renovations undertaken by his corporation. While the written contract was  
between the plaintiff and the corporation, Brown J found that the construction was so deficient as  
to amount to fraud. Further, she found that the defendant had either misappropriated or not  
properly accounted for the funds advanced by the plaintiff.  
Page: 85  
[529] In AVAC Ltd v Ceapro Inc, 2018 ABQB 44 at para 70, Justice Jones took an approach  
similar to that in Elbow River:  
I am satisfied, based on the foregoing discussion, that CTI was “completely  
dominated” by Ceapro Inc. The question is whether there is a wrongful act in this  
case sufficient to justify piercing the corporate veil. …  
[530] However, Justice Jones went on at paras 71-73 to note the need for caution in considering  
the issue of wrongful act:  
There is no suggestion that the formation of CTI or the plan to operate the  
Ceaprove business through it was in any way fraudulent. As discussed above, this  
was done for the legitimate purpose of isolating potential liability arising from the  
production of a product for human consumption. Moreover, it is clear from the  
evidence that AVAC was aware at all times that CTI was the contracting entity  
under the Ceaprove Agreements. The only wrongful act here is the breach of the  
Ceaprove Agreements.  
This case is distinguishable on its facts from Spartek. In that case, both Brown  
and 113 were parties to the contract, but only Brown was in breach and the  
question was whether the non-breaching party should be held liable. In this case,  
the only party to the Ceaprove Agreements is CTI. Ceapro is neither in breach of  
the Ceaprove Agreements nor a party to them.  
The type of wrongful act which justifies ignoring the separate corporate identity  
of CTI must be something more than CTI’s non-compliance with the Ceaprove  
Agreements. Were I to pierce the corporate veil in these circumstances, I would  
be disregarding the need for a wrongful act and relying solely on the extent of  
control of CTI by Ceapro Inc. That would be tantamount to concluding that the  
corporate veil may be pierced in any situation in which a subsidiary is closely  
associated with its parent.  
[531] In Aubin, Antonio JA considered the application of the corporate veil in the family law  
context and made reference to Transamerica at paras 23-24:  
In [Transamerica], the Ontario Superior Court General Division held that the  
separate identities of a parent company and its subsidiary can be disregarded if (i)  
there is complete control of the subsidiary, such that the subsidiary is the “mere  
puppet” of the parent corporation; and (ii) the subsidiary was incorporated for a  
fraudulent or improper purpose or used by the parent as a shell for improper  
activity.  
The two-part Transamerica test has found general application, though it has  
sometimes been stated in different terms. For instance, in Arsenault v Arsenault  
(1998), 38 RFL (4th) 175 at para 24, the test was stated in three parts:  
1. The individual exercises complete control of finances, policy, and business  
practices of the company.  
2. That control must have been used by the individual to commit a fraud or wrong  
that would unjustly deprive a claimant of his or her rights.  
3. The misconduct must be the reason for the third party’s injury or loss.  
Page: 86  
[532] Antonio JA found that the test is applicable in the family law context, citing the “leading  
authority” in Wildman v Wildman (2006), 82 OR (3d) 401 (CA) and commenting as follows at  
paras 33, 34 and 36:  
Echoing the Transamerica test, the [Wildman] court at para 25 framed the central  
question as whether it is possible to disregard the separate legal personality of a  
corporation when it is in an individual’s complete control and is being used as a  
shield for fraudulent and improper conduct. The court concluded that the answer  
is “a resounding ‘Yes’”.  
…”[T]he law must be vigilant to ensure that permissible corporate arrangements  
do not work an injustice in the realm of family law”: Wildman at paras 41 and 49.  
Though some authorities have spoken of a relaxed test for veil-lifting in the  
family law context, it seems that generally a remedy has been awarded on a pure  
version of the test. Perhaps the added factor, if there is one, is the recognition that  
obligations imposed by family law are on equal footing with other legal  
obligations and deserve fair balancing where interests compete. It is also  
appropriate to recognize, as the trial judge did, that “in the family law context, the  
creditor spouse cannot choose whether to deal with the corporation the way a  
commercial creditor can. The assets of the family unit are tied to the  
corporation”…  
[533] Justice Antonio reiterated that piercing the corporate veil is by no means automatic,  
saying at paras 40 and 59:  
Attribution of corporate income to a payor parent is not automatic; it requires  
inquiry and balancing against legitimate business requirements. As stated in  
[Goett v Goett, 2013 ABCA 216] at para 13:  
When the corporate veil is lifted in a commercial context, certain  
factors are considered: for example, whether the individual  
exercises complete control of finances, policy, and business  
practices of the company, whether the control has been used by the  
individual to commit a fraud or wrong that would unjustly deprive  
a claimant of his or her rights, and whether the misconduct (for  
example the transfer [of a corporation previously owned by the  
payor for the purpose of avoiding child support obligations]) is the  
reason for the loss. These factors are also relevant, although not  
applied as stringently, in the family context.  
At risk of oversimplification, protection of shareholders is the reason for the  
corporate veil. It is therefore obvious that the presence of other shareholders is an  
important factor to be considered in deciding whether to lift it. It will also be  
relevant to consider the nature of the company (for example, family business  
versus publicly traded corporation), the reasonable expectations of the  
shareholders about how the company will be used by its principals, whether the  
shareholders are bona fide purchasers for value, and any other relevant factors.  
Page: 87  
[534] Nevertheless, while acknowledging that piercing the corporate veil is not the rule, Justice  
Antonio held at para 68 that it is not restricted to “exceptional” circumstances:  
…the repeated jurisprudential references to lifting the veil in rare and exceptional  
cases should be understood as an expectation, not a requirement. The courts  
expect that lifting the veil will rarely be justified because they expect corporations  
and their directing minds to deal fairly and in accordance with their legal  
obligations, and because the necessary balancing of interests means that a remedy  
will not automatically flow. But a claimant who asks that a corporate veil be lifted  
is not required to establish that his or her case is rare and exceptional.  
Circumstances that cause unjust deprivation but are “far from unusual”, as the  
court found in Arsenault at para 22, deserve redress. The law should not shelter  
wrongdoers because their type of wrongdoing is too commonplace.  
[535] In brief written reasons in Zerbin v Vrbanek, 2021 ABCA 317, the Court of Appeal  
upheld the trial judge’s decision to pierce the corporate veil and find the appellant Vrbanek  
personally liable for overcharging for project management services related to the construction of  
two homes for the respondents. The trial judge found that “the facts invoke fraud, deceit or  
dishonesty”, rendering Vrbanek personally liable. At para 18, the Court of Appeal referred to the  
two factors discussed above:  
Although not strenuously argued at the appeal hearing, the appellants in their  
factum challenge the trial judge’s decision to piece the corporate veil and find  
both DN and Mr. Vrbanek jointly and severally liable for damages. Courts will  
pierce the corporate veil only when a corporation has been “completely  
dominated and controlled and used as a shield for fraudulent or improper  
conduct”: [Elbow River].  
[536] In contrast to this two-factor test, Slatter JA articulated a somewhat different approach in  
Hall at para 16 (all citations omitted):  
The law on when personal liability will attach to corporate actors is not clear. The  
case law was surveyed in the concurring reasons in Rocky Mountain Slate at  
paras. 75ff. A number of relevant factors have been identified by the courts:  
(a) Whether the negligent act was committed while engaged in the business of the  
corporation, and whether the negligence of the employee was contemporaneous  
with that of the corporation...  
(b) Whether the individual was pursuing any personal interest beyond the corporate  
interest…  
(c) Whether the director or corporate representative owed a separate and distinct  
duty of care towards the injured party…  
(d) That the conduct was “in the best interests of the company”;  
(e) Whether the plaintiff voluntarily dealt with the limited liability corporation, or  
had the corporate relationship “imposed” on it…  
(f) The expectations of the parties… Was it reasonable for the plaintiff to think that  
the individuals involved would be personally responsible for any damage that  
resulted? In the area of negligent misrepresentation, this factor takes on a  
Page: 88  
particular importance: was it reasonable for the plaintiff to rely on the  
representation coming from the individual, rather than the corporation? …  
(g) Whether the tort was “independent”. The cases sometimes say that the  
employee or individual is liable for his or her “independent” torts, implying that  
there are some torts which are so closely identified with corporate activity that  
they are not fairly categorized as “individual torts” as well…  
(h) The case law clearly recognizes the exception in Said v Butt…, specifically  
respecting claims of inducing breach of contract, without identifying whether it  
is a narrow or wide exception, nor the principles upon which it is based;  
(i) The nature of the tort, and particularly whether it was an intentional tort…  
(j) Whether the damage was physical or economic… This partly relates to  
accessibility to insurance, which is more common for physical damage…  
These factors can be seen as being part of a generalized concern about the effect  
that individual liability can have on the viability of corporate structures and their  
efficacy. While it is undesirable to decide on a case-by-case basis if a corporate  
actor is personally liable in tort, a comprehensive and integrated test remains  
elusive…  
[537] I find it difficult to reconcile the Hall/Rocky Mountain Slate approach with that in the  
cases earlier discussed. Even today, Wilson J’s lament in Kosmopoulos holds true: the case law  
“follows no consistent principle”. To the extent that it can be said that any unifying theme  
emerges, it is that the question of whether to pierce the corporate veil continues to confront the  
court with the need to do justice by balancing competing and conflicting principles.  
Notwithstanding Slatter JA’s concern expressed above about deciding personal liability on a  
case-by-case basis, the determination in each case will be specific to its own context and  
circumstances.  
[538] The comments of Justice Yamauchi at para 23 of Tirecraft are apt:  
When one parses through the various tests and criteria courts have established to  
determine whether they will pierce the corporate veil, they all come down to the  
“persuasive argument” that Justice Wilson provided us in Kosmopoulos at para.  
13, where she said:  
13 There is a persuasive argument that “those who have chosen the  
benefits of incorporation must bear the corresponding burdens, so  
that if the veil is to be lifted at all that should only be done in the  
interests of third parties who would otherwise suffer as a result of  
that choice”: Gower, supra, at p. 138…  
b) Application  
[539] The Defendants take the position that there is no basis in this case to justify piercing the  
corporate veil. They argue that Tru-Square was not “a mere shell set up to carry out a deliberate  
plan to deceive and defraud the Swanbys.Further, the Defendants contend that Metcalfe acted  
in good faith throughout and that the Plaintiffs have not established any dishonest act,  
recklessness or wilful blindness on his part to justify piercing the corporate shell.  
Page: 89  
[540] I accept the Defendants’ argument that Tru-Square was not a mere shell incorporated for  
the purpose of carrying out a wrongful act. The evidence is clear that it operated as a successful,  
legitimate homebuilding business for some time prior to the events in question. Nevetheless, I  
am satisfied that in the circumstances of this case, several of the factors enumerated in Tirecraft  
are applicable. Metcalfe treated himself and Tru-Square interchangeably and intermingled the  
corporation’s affairs with his own. The Plaintiffs assert that he did not distinguish between Tru-  
Square and himself in his dealings with them. In his evidence, Metcalfe admitted that he and his  
wife mingled their personal money with Tru-Square’s. I find, therefore, that Metcalfe treated  
Tru-Square as his alter ego.  
[541] This, of course, is not sufficient by itself. As discussed above, Justice Jones found in  
Ceapro that, notwithstanding that the parent corporation had complete control over the  
subsidiary, the only wrongful act was the breach of contract by the subsidiary. Since the parties  
were all on an equal footing, and it was known to all concerned that the subsidiary was the  
contracting entity, lifting the corporate veil was not justified.  
[542] To warrant piercing the corporate veil and attaching personal liability to Metcalfe, the  
Plaintiffs must show that Metcalfe used his control over Tru-Square to commit a wrong that  
would unjustly deprive them of their rights in such a way as to work an injustice.  
[543] The Court in Koltai found at para 30 that the failure to complete the renovations properly  
was “so extreme as to amount to fraud.” I am not prepared to go that far in this case. However, I  
agree with Justice Ross’ conclusion in Spartek that it is not necessary for me to do so. As she  
indicated at para 283, the corporate veil may be pierced in cases where there is sufficient  
improper or wrongful conduct. Similarly, Justice Yamauchi stated at para 25 of Tirecraft that the  
veil may be pierced where there is a “wrongful, unlawful, fraudulent or improper act that causes  
third parties to suffer” (emphasis added).  
[544] In my view, the combination of the sheer number of construction deficiencies, their  
pervasive nature affecting many aspects of the residence, the physical danger posed by some of  
these deficiencies, Metcalfe’s ultimate abandonment of the project rises to a level that warrants  
looking through the corporate shield. I find that this case is distinguishable from Ceapro and is  
more akin to Spartek. In these circumstances, permitting Metcalfe to escape liability by shielding  
himself behind Tru-Square would unjustly deprive the Plaintiffs of their rights.  
[545] I am bolstered in my decision by two additional factors. In Hall, the Court of Appeal held  
at para 23 that the “deciding factor” was that the claim was in respect of personal injury:  
The deciding factor in this case, however, is the nature of the damage: personal  
injury. A number of the cases where individual liability has been found for  
corporate torts concern physical damage or personal injury [citations omitted].  
There is clearly a “duty of care” to avoid injuring one’s co-workers, and no  
residual policy considerations to exclude liability: Rocky Mountain Slate at paras.  
127-8 Anyone who agrees to install a staircase clearly owes a duty of care to  
those who are likely to use that staircase. Although the respondent’s tort was not  
at all “independent” of the corporation DWS Construction, the modern  
corporation was not designed to be a method of providing immunity to corporate  
actors for this sort of loss. There are strong public policy reasons to ensure that  
physically injured plaintiffs are compensated. Claims for pure economic loss raise  
different issues.  
Page: 90  
[546] In this case, there has been no personal injury. The Plaintiffs, however, cite the Court of  
Appeal’s statement in Vargo at para 32:  
If the plaintiff establishes at the time of the suit a reasonable likelihood of a defect  
causing real and substantial danger to the building’s occupants and the danger is  
reasonably likely to occur within the useful life of the building, the time frame  
within which the harm is likely to occur may be irrelevant.  
[547] I agree with the Plaintiffs that personal liability should attach to Metcalfe in these  
circumstances. Arguably, physical damage already has occurred in the sense that the house has  
been improperly constructed. Moreover, certain aspects of the defective construction,  
particularly the unconnected deck and bonus room staircase, presented as a real and substantial  
danger of personal injury at some point.  
[548] In Hall, the Court of Appeal also found it significant that the individual defendant could  
have, but had not, obtained insurance coverage. The Court stated at para 19:  
The competing policy objectives of tort law and corporate law must be reconciled  
in context. One important factor is the ready availability of insurance for property  
damage and personal injury. One obvious source of personal injury insurance is  
the workers’ compensation system itself. However, even if a corporation does not  
elect to purchase director’s insurance within the workers’ compensation system,  
general commercial liability insurance coverage is widely available for personal  
injury and property damage. In assessing whether a corporate representative  
should be exposed to personal liability for corporate torts, it must be  
acknowledged that the underlying risk can readily be managed and diverted  
through the purchase of appropriate insurance. Balanced against this factor is the  
reality that mere employees (unlike directors like the respondent) have little  
control over corporate decisions to insure. Whether the respondent actually  
purchased commercial general liability insurance is not the point; the point is that  
such insurance was available to him, and if he did not purchase it he must have  
elected to assume the underlying risk himself. He could not, by his decision, seek  
to pass the risk of recovery of personal injury damages onto injured claimants like  
the appellants.  
[549] Metcalfe’s evidence was that he had commercial general liability insurance in his own  
name as a sole proprietor. On the evidence before me, I find that he cancelled that insurance as  
soon as the windows leaked and a substantial amount of water leaked into the interior of the  
residence. As outlined above, a dispute arose between the parties shortly thereafter in the face of  
Metcalfe’s refusal to take steps to remediate the problem, culminating in his walking off the job.  
As set out in the Agreed Statement of Facts, he also cancelled his WCB coverage at more or less  
the same time. The above statement from the Court of Appeal indicates to me that Metcalfe’s  
failure to maintain insurance coverage should be visited upon him rather than the Plaintiffs.  
[550] Taking all of the foregoing into account, I am of the view that it is appropriate to lift the  
corporate veil in this case.  
Page: 91  
4. Inducing Breach of Contract  
[551] The Plaintiffs argue that Metcalfe is personally liable in tort for inducing Tru-Square to  
breach its contract with them by walking off the job in the face of identified deficiencies rather  
than addressing those deficiencies.  
[552] The test for inducing of a breach of contract is set out in Brae Centre Ltd v 1044807  
Alberta Ltd, 2008 ABCA 397. Citing Klar, Tort Law, 3d ed. (Toronto: Thomson Canada  
Limited, 2003), at pp 610-620, the Court set out the six required elements at para 19:  
a) the existence of a contract;  
b) the defendant intended to cause a breach of contract;  
c) knowledge by the defendant of the contract;  
d) the defendant’s conduct induced the breach;  
e) damage;  
f) lack of justification for the defendant’s conduct.  
[553] The application of this tort is more difficult in situations like the one in this case. In  
concurring reasons in 698828 Alberta Ltd v Elite Homes (1998) Ltd, 2020 ABCA 154, Slatter  
JA referred at paras 115 and 116 to what he called the “corporate variation” of the tort:  
This appeal, however, involves the “corporate variation” of the tort where there  
are only two parties involved. A has a contract with B. B is a corporation, and B  
breaches its contract through the acts, decisions, or inaction of its officers or  
management. A then attempts to sue the officers or management of B for inducing  
breach of contract, as if they personally were in the position of C in the three-  
party tort. ...  
The corporate variation of the tort has always been viewed with caution by the  
courts. Corporations can only act through their human agents, and any distinction  
between a corporation and its officers is prima facie artificial. The knowledge and  
intention of one are the knowledge and intention of the other. It does not make  
sense to speak of a contracting party inducing itself to breach its own contract. A  
modified approach to the corporate variation of the tort is necessary, because  
turning a breach of contract by a corporation into personal liability in tort of its  
officers undermines the legal concept of the corporation as a separate legal  
person.  
[554] The tort is said to be inapplicable where the director of the corporation is acting bona  
fide in the best interests of the corporation. The Court of Appeal confirmed this at para 23 of  
Brae:  
Based on one or both of these rationales, there is general agreement in the case  
law that a director acting bona fide within the scope of his authority and in the  
best interests of the company will not be personally liable in tort for inducing  
breach of contract by the company: Said v Butt. Something more must be proven  
to establish personal liability.  
[555] In applying the six-part test in the case of a “corporate variation”, the courts must take  
account of the fact that corporations can act only through their human agents. Fruman JA  
explained this in 369413 Alberta Ltd v Pocklington, 2000 ABCA 307 at para 65:  
 
Page: 92  
Although justification is a defence to the tort, the burden is fairly placed on the  
plaintiff to prove the director was not acting in the best interests of the  
corporation, and therefore stepped out from under the protective umbrella of the  
director’s corporate duties. If a director wishes the plaintiff to prove more, in my  
view, the director must demonstrate that some legitimate interest of the  
corporation could have been served by the conduct. This information is well  
within the director’s knowledge and a requirement to demonstrate it on a prima  
facie basis, rather than to prove it on a balance of probabilities, does not unduly  
open the company’s business to third party scrutiny.  
[556] The Defendants assert that the Plaintiffs’ Amended Statement of Claim makes no claim  
for damages on the basis of Metcalfe inducing a breach of contract by Tru-Square and, in any  
event, that no evidence was led that Metcalfe intended to cause the breach.  
[557] The Plaintiffs argue that the required intent is established where the consequences of the  
inducing party’s actions are reasonably foreseeable or where that party acted recklessly or was  
wilfully blind to the likelihood of breach. The Plaintiffs contend that Metcalfe actively induced  
the breach by permitting the deficient work to occur or was reckless in his oversight of that work  
and ought to have been aware that a breach of the contract was likely to occur. Further, the  
Plaintiffs point to Metcalfe’s decision to abandon the project in July 2013.  
[558] Clearly in these circumstances, the “corporate variation” of the test for inducing breach of  
contract must be applied. Accordingly, as indicated in Brae, “something more” is required  
beyond the six elements of the test. Slatter JA discussed this requirement in Elite at paras 127  
and 129:  
What is needed is some indication that the officers and management of the  
corporation, in causing the breach by the corporation B, stepped outside their role  
as officers and managers. The corporate variation of the tort is only made out  
when the officers and managers do not honestly believe they are acting in the best  
interests of the corporation, or they advance some personal interest divorced from  
that of the corporation. It is only at that point that the “intention” of B can be split,  
so that there is once again a separate intention of B to breach, and an intention of  
C to induce the breach.  
...  
On the other hand, a contracting party could consciously decide to breach the  
contract. That is an option open to a contracting party, as long as it is prepared to  
pay the damages that result, because specific performance is rarely awarded for  
breach of contract. Sometimes a contracting party may conclude that breach is a  
less expensive option than performance...  
[559] I am not satisfied that the necessary “something more” is made out in this case. There is  
no evidence before me to establish that Metcalfe was acting to advance some personal interest  
divorced from that of Tru-Square. Indeed, given my finding above that Metcalfe treated himself  
and Tru-Square interchangeably, it is not clear to me how such a separate interest could be  
established.  
[560] Therefore, I reject the Plaintiffs’ claim against Metcalfe for inducing breach of contract.  
Page: 93  
H. Alberta New Home Warranty Program (“ANHWP”)  
[561] Both contracts signed by the parties on August 22, 2011, referred to the ANHWP,  
incorporating it by reference. A third “fill-in-the-blank” ANHWP contract for the construction of  
the entire residence was signed at the same time.  
[562] At the time in question, the ANHWP was not mandatory for new homes. If parties opted  
to participate, the Program had three components. It provided deposit protection, builder  
performance protectionand a warranty. Under the builder performance protection, if a builder  
failed to complete construction of a home, the Program would arrange for completion of the  
home, up to a total cost of $50,000. Under the warranty, if a builder failed to construct a home to  
Code standards, the Program would ensure that defects were repaired or remedied, up to a total  
cost of $100,000.  
[563] At issue in this action is whether the Program’s dispute resolution process was  
mandatory. Under the Homeowner Obligations clauses of the warranty, homeowners were  
obligated to give the builder notice of any defects immediately, or not later than one year from  
their possession date. The builder was then required to remedy the defect. If a dispute arose,  
homeowners were required to provide written notice to the Program. This would engage the  
Program’s Conciliation Procedure, which provided that the Program’s decision regarding the  
defects would be binding, subject to arbitration that either party could invoke. In that case,  
arbitration pursuant to the provisions of the Arbitration Act, RSA 2000, c A-43, would be final  
and binding on all parties.  
[564] The builder performance protection conditions were similar. Purchasers were obligated to  
claim against the Program within certain timeframes. Subject to enumerated limits and  
exclusions, the Program would assist the homeowner in remedying the construction issue(s). Any  
dispute arising about the builder performance protection would be settled in binding arbitration.  
[565] Although the Plaintiffs identified numerous issues with their newly constructed home,  
neither party invoked the Program’s Conciliation Procedure. The Defendants contend that the  
Plaintiffs should have done so instead of commencing litigation.  
[566] I note that the parties did exchange correspondence in July 2013, some two months after  
the Plaintiffs discovered that the windows leaked. On July 22, 2013, Metcalfe sent an email to  
Ms. Swanby (Exhibit 1-G-15) outlining the ANHWP’s mediation/arbitration processes and  
expressing his willingness to go to non-binding mediation if the Swanbys were prepared to  
agree. Failing agreement, Metcalfe advised that the “final option” would be for him to trigger the  
arbitration process. Metcalfe made no reference in this communication to any intention to effect  
repairs to the residence. It does not appear that the Plaintiffs responded to Metcalfe’s suggestion  
or that Metcalfe took any follow-up action. According to Ms. Swanby, she approached the  
ANHWP, but learned that the Program’s pre-conditions had not been met.  
[567] In their Statement of Defence, the Defendants allege that the Plaintiffs are in default of  
both the warranty certificate and the builder performance protection, for failing to invoke the  
Program’s dispute resolution process once they discovered that the windows leaked. Likewise,  
the Defendants suggest that all of the other alleged deficiencies should have been referred to the  
ANHWP. Further, the Defendants contend that the Plaintiffs did not exhaust their remedies  
under the contract, which itself explicitly required the parties to settle any related disputes  
through binding arbitration in accordance with the Program’s arbitration rules.  
 
Page: 94  
[568] The Plaintiffs, on the other hand, reject the notion that there were obliged to have  
recourse to the ANHWP in lieu of proceeding to litigation. They maintain that the ANHWP was  
not the proper vehicle to resolve this dispute as it could not have resolved all the claims  
advanced in this action. They point out that the ANHWP’s monetary limits fall well below their  
alleged damages. The Plaintiffs also assert that by the time the ANHWP remedies became  
available to them under the mandated timeline, the remediation had been completed.  
[569] The Plaintiffs also take the position that the ANHWP’s dispute resolution process was  
optional. I disagree. The parties’ contract explicitly incorporated the Program with all of its terms  
and conditions, notably its mandatory dispute resolution process.  
[570] The relevant provisions of the Arbitration Act include:  
6. No court may intervene in matters governed by this Act, except for the  
following purposes as provided by this Act:  
(c) to prevent manifestly unfair or unequal treatment of a party to an  
arbitration agreement;  
Stay  
7(1) If a party to an arbitration agreement commences a proceeding in a court in  
respect of a matter in dispute to be submitted to arbitration under the agreement,  
the court shall, on the application of another party to the arbitration agreement,  
stay the proceeding. [Emphasis added.]  
(2) The court may refuse to stay the proceeding in only the following cases:  
(d) the application to stay the proceeding was brought with undue  
delay;  
(5) The court may stay the proceeding with respect to the matters in dispute dealt  
with in the arbitration agreement and allow the proceeding to continue with  
respect to other matters if it finds that  
(a) the agreement deals with only some of the matters in dispute in  
respect of which the proceeding was commenced, and  
(b) it is reasonable to separate the matters in dispute dealt with in the  
agreement from the other matters.  
[571] Given their position and my finding that the ANHWP’s arbitration process was  
mandatory before litigation could be commenced, I would have expected the Defendants to have  
sought a stay of proceedings in accordance with s 7(1) of the Arbitration Act some time ago.  
Such a stay would have been mandatory unless the Plaintiffs had been able to bring themselves  
within one of the exceptions found in s 6(c). However, no such application has ever been  
brought.  
[572] While the Defendants appear to place considerable significance on the Plaintiffs’ failure  
to seek the assistance of the ANHWP, they fail to identify what consequence should flow from  
that failure. The Defendants raise the Plaintiffs’ alleged non-compliance with the ANHWP’s  
dispute resolution process, but seek no form of relief.  
Page: 95  
[573] In oral submissions, Defendants’ counsel conceded that the ANHWP’s dispute resolution  
process would have addressed only “some of the peripheral claims for damages”. I agree. Given  
the nature of the Plaintiffsclaims, the aspects covered by the arbitration clause cannot  
reasonably be separated from the others. If the parties had arbitrated, they likely would also have  
had to litigate. These proceedings would have overlapped, with the “real danger that there  
[would] be contrary findings of fact and law.”: New Era Nutrition Inc v Balance Bar Co, 2004  
ABCA 280 at para 44. In New Era, the Court of Appeal found, at para 3, that s 6(c) of the  
Arbitration Act could be used to refuse to stay proceedings in circumstances where overlapping  
matters could not reasonably be separated.  
[574] While it is not necessary for me to decide this issue, I am doubtful that the Defendants  
would have been successful if they had sought a stay the proceedings at this late date. First, I  
believe that the Plaintiffs would have a strong argument that s 6(c) applies in these circumstances  
given the breadth of their claim and the total damages sought. There is also the issue of undue  
delay. Section 7(2)(d) of the Arbitration Act provides an incentive for parties intending to rely on  
a mandatory arbitration agreement to bring such an application in a timely fashion when faced  
with court action.  
[575] While undue delay is assessed on a case-by-case basis, I am satisfied that this matter  
reaches the threshold required under s 7(2)(d). The Plaintiffs and Defendants have been engaged  
in this action for over six years. In other cases, less time has been found to constitute undue  
delay: Millennial Construction Ltd v 1021120 Alberta Ltd, 2005 ABQB 533 at para 15. Both  
parties were aware of a dispute, yet neither engaged the ANHWP’s dispute resolution process.  
Considerable time, energy, and financial resources have gone into this litigation. The Plaintiffs  
have reasonably relied on the Defendants’ participation. Further, they were led to believe,  
through the Defendants’ actions, that there would be no insistence on the arbitration clauses in  
the contract: Faith v Quadrant Construction Ltd, 2019 ABQB 151 at para 49. It is now too late  
for the Defendants to suggest that litigation is not the appropriate forum for resolution and to  
maintain that arbitration was required.  
[576] While both parties expressed some willingness to participate in arbitration and/or  
mediation, neither party engaged the ANHWP and no mediation or arbitration ever took place.  
The parties are equally to blame for this.  
[577] For the foregoing reasons, I am of the view that the ANHWP mediation and arbitration  
provisions have no application in this instance.  
VI. Damages  
A. Quantification of Damages  
[578] The Plaintiffs, relying on Vermillion, suggest that the most common approach to the  
assessment of damages in construction cases is to focus on the contract measure of damages even  
in situations involving concurrent liability in both contract and tort.  
[579] The Plaintiffs rely on the decision of the Supreme Court in Penvidic Contracting Co v  
International Nickel Co of Canada Ltd, [1976] 1 SCR 267, as support for the proposition that  
courts are not required to employ mathematical accuracy in determining damages when dealing  
with evidence of deficiencies.  
   
Page: 96  
[580] In my view, Penvidic stands for a somewhat different principle but, nonetheless, one that  
has some application in this case. Penvidic was an action for breach of a contract to lay railway  
track and the required sub-ballast on top of the graded track bed. The contractor was forced to  
revise its entire method of construction when a required rail connection to be used for the  
movement of equipment was not constructed until well after work had commenced on the track  
in issue. In response to these unanticipated circumstances, the contractor was forced to employ  
alternate and more costly means to fulfill the contractual obligations. The contractor then sought  
additional compensation. The trial judge awarded $.25 per ton for extra ballasting, as well as an  
amount for additional costs for moving the ballast. The trial judge accepted the evidence of an  
experienced railway builder, who described as “reasonable” this method of estimating the  
contractor’s additional cost. On appeal to the Court of Appeal, this amount was disallowed.  
[581] On a further appeal to the Supreme Court, the trial judge’s damage award relative to this  
item was restored. At para 24, Spence J held:  
I can see no objection whatsoever to the learned trial judge using the method  
suggested by the plaintiff of assessing damages in the form of additional  
compensation per ton rather than attempting to reach it by ascertaining items of  
expense from records which, by the very nature of the contract, had to be  
fragmentary and probably mere estimations. In doing so, he had the testimony of  
MacIlroy, an experienced railroad builder, whom the learned trial judge found to  
be an honest and a satisfactory witness...  
[582] The Supreme Court also referred to its own earlier decision in Wood v Grand Valley  
Railway Company (1915), 51 SCR 283, in which Davies J held at p. 289:  
It was clearly impossible under the facts of that case to estimate with anything  
approaching to mathematical accuracy the damages sustained by the plaintiffs, but  
it seems to me to be clearly laid down there by the learned judges that such an  
impossibility cannot “relieve the wrongdoer of the necessity of paying damages  
for his breach of contract” and that on the other hand the tribunal to estimate them  
whether jury or judge must under such circumstances do “the best it can” and its  
conclusion will not be set aside even if the amount of the verdict is a matter of  
guess work. [emphasis in original]  
[583] What I take from the decision in Penvidic is courts are required to do the best they can in  
circumstances where the assessment of damages proves to be difficult. In Martin v Goldfarb  
(1998), 41 OR (3d) 161 (CA), leave to appeal to SCC refused [1999] 1 SCR x, Finlayson JA  
considered Penvidic and other decisions before concluding (at para 75):  
Having considered the above cases and others, notably Williamson v Stephenson  
(1903), 33 S.C.R. 323 and [Penvidic, citations omitted], I have concluded that it is  
a well established principle that where damages in a particular case are by their  
inherent nature difficult to assess, the court must do the best it can in the  
circumstances. That is not to say, however, that a litigant is relieved of his or her  
duty to prove the facts upon which the damages are estimated. The distinction  
drawn in the various authorities, as I see it, is that where the assessment is  
difficult because of the nature of the damage proved, the difficulty of assessment  
is no ground for refusing substantial damages even to the point of resorting to  
Page: 97  
guess work. However, where the absence of evidence makes it impossible to  
assess damages, the litigant is entitled to nominal damages at best.  
[584] Similarly, in Extreme Venture Partners Fund 1 LP v Varma, 2021 ONCA 853, the  
Court held at para 53:  
The jurisprudence recognizes that trial judges are not held to a standard of  
perfection in making damage awards. Appellate courts will not interfere with  
reasonable damage awards where they have an evidentiary basis, as damages  
cannot always be calculated with mathematical precision. Sometimes the trial  
judge must do the best they can in the circumstances...  
[585] Renke J reached a similar conclusion in Mitchell v Pytel, 2021 ABQB 403, in which he  
noted at para 386 that “difficulty in assessing damages does not relieve the court from doing the  
‘best it can’”.  
[586] Finally, I would refer to the decision of Wittmann ACJ (as he then was) in Viper  
Concrete 2000 Inc v Agon Developments Ltd, 2009 ABQB 91, in which he held at para 53,  
citing Penvidic and other authorities including S.M Waddams in The Law of Damages, looseleaf  
(Toronto: Canada Law Book, 2008): “The onus is on the plaintiff to prove its damages on a  
reasonable preponderance of credible evidence (See: 100 Main Street East Ltd. v W.B. Sullivan  
Construction Ltd. (1978), 20 O.R. (2d) 401 (C.A.) at p. 422). The damages need not, however be  
proven with mathematical accuracy”.  
[587] The Plaintiffs ask me to accept the methodology employed by Juniper in this instance and  
to accept his explanation that he and his work crew were involved in multiple activities at the  
same time. As such, the investigation, including any necessary destruction, and repair work on  
any given item was not carried out on a straight-line basis with remediation proceeding  
sequentially on an item-by-item basis. Rather, the practical realities of the situation involved  
moving from one item to another as time and circumstances permitted. In the result, the invoices  
submitted to the Plaintiffs were based on non-itemized time sheets.  
[588] Under the unique circumstances of this case, I am prepared to accept that Juniper’s  
methodology was reasonable. I acknowledge that this methodology would render difficult, if not  
impossible, the task of attempting to extricate the cost of work relative to damage for which the  
Defendants were not responsible. However, I am satisfied that this is only a hypothetical problem  
in these particular circumstances, save for one relatively minor exception discussed below. I find  
that all the applicable invoices relate to remediation work for which the Defendants are  
responsible. The one exception relates to remediation work associated with damages caused by a  
fluid leak from the refrigerator. As more fully explained later in these Reasons, I am satisfied  
that the Defendants are not responsible for any of the damage related to the refrigerator leak.  
Juniper’s invoices contain sufficient detail to allow me to deduct the amounts billed for this  
work.  
[589] I am also satisfied that Juniper employed a system that ensured that time records for work  
or improvements or to other, unrelated projects for the Swanbys, were kept separate and apart  
from the time records and invoicing processes associated with the remediation of this particular  
residence.  
[590] The Plaintiffs maintain that “the appropriate measure of damages in contract is the cost of  
performance, including consequential expenses resulting from the breach of contract, in addition  
Page: 98  
to punitive and general, non-pecuniary damages and pre-judgment interest”: Plaintiff’s Brief,  
para 227.  
[591] The Plaintiffs’ damage calculations focus on breach of contract and, as such, on the cost  
of performance. This calculates the amount paid under the contract and the cost to remediate and  
complete the work. According to the Plaintiffs, this approach will account for the amounts  
claimed by the Defendants in their counterclaim as owing to them under the contract.  
[592] The Defendants, on the other hand, have filed a counter claim for what they allege to be  
unpaid invoices owed by the Plaintiffs. Likewise, they dispute other amounts included by the  
Plaintiffs, including aggravated and punitive damages, as well as the amount claimed for  
remediation work and consequential damages.  
[593] The remediation work, including the destruction of the as-built construction on an as-  
required basis, was undertaken by Juniper and his company, TGC. According to Juniper, six of  
his employees were involved in the remediation process on a daily basis. Juniper’s November  
2015 report, Exhibit 1-F-35, sets out the work that he performed on the Swanby residence. His  
various invoices for this work are found at the back of this report. These costs are broken down  
in terms of demolition costs and rebuild costs, as well as costs relating to labour, material, and  
rentals.  
[594] The attached invoices do not include all the TGC invoices submitted to the Plaintiffs,  
specifically invoices that were not part of the original scope of work in the parties’ contract,  
TGC invoices associated with extras or add-ons requested by the Plaintiffs, or work undertaken  
at the Plaintiffs’ East Carstairs home and shop, are not included in Juniper’s written report  
[595] Photographs depicting the as-built, demolished state, and remediated state are found  
throughout his report and in various other exhibits.  
[596] The Plaintiffs seek damages in the sum of $427,941.61, calculated on the following basis:  
a) Contract price to Lock-Up, plus;  
b) Extras and Upgrades; plus;  
c) Amounts Paid to Third Parties, less;  
d) Amounts paid to Tru-Square; less  
e) Amounts Paid to TGC for remediation work, less;  
f) Consequential costs includes costs paid to consultants and double utility  
payments on two houses, plus;  
g) Aggravated Damages, plus;  
h) Punitive Damages.  
[597] I am satisfied that the Plaintiffs proposed approach to the calculation of damages is  
appropriate and fully accounts for the Defendants’ challenge to some of the amounts claimed, as  
well as the Defendants’ Counterclaim.  
1. Contract Price to Lock Up  
[598] There is no dispute regarding the lock-up cost of constructing the residence. This amount  
was set out in Exhibit 1-C-5, $692,485.50. In accordance with the terms of the Lock-Up contract,  
Tru-Square issued four invoices reflecting the four “draws” contemplated by the agreement. The  
final “draw” Invoice 137 remains unpaid.  
 
Page: 99  
Invoice #  
Amount  
$110,000.00  
Exhibit #  
1-C-7  
Invoice 106 (September 30, 2011)  
Invoice 112 (February 5, 2012)  
Invoice 117 (June 16, 2012)  
Invoice 137 (September 27, 2013)  
Total Billed  
$350,575.00  
$130,000.00  
$ 86,619.35  
$677,194.35  
$590,575.00  
$ 86,619.35  
I-C-9  
I-C-10  
I-C-17  
Total Paid  
Total Unpaid  
2. Extras and Upgrades  
[599] Both parties rely on Re Chittick and Taylor (1954), 12 WWR (NS) 653, as setting out the  
principles relating to the determination of whether work performed constitutes an “extra”. At p  
654-655, Egbert J set out four “rules” that apply in such circumstances:  
Rule 1. An item specifically provided for in the contract is not an “extra.”  
Rule 2. When the plaintiff supplied material of a better quality than the minimum  
quality necessary for the fulfillment of the contract, without any instructions,  
express or implied, from the defendant to do so, he is not entitled to charge the  
extra costs as an “extra.”  
Rule 3. When the plaintiff did work or supplied materials not called for by the  
contract (plans or specifications) without instructions, express or implied, from  
the defendant, or the consent of the defendant, he is not entitled to charge this  
addition work or materials as an “extra.”  
Rule 4. When the plaintiff did work or supplied materials not called for by the  
contract on the instructions, express or implied, of the defendant, he is entitled to  
charge for additional work or materials as an “extra.”  
What amounted to instructions from the defendant is dependent on the  
circumstances relating to each item. If the defendant, without giving definite  
instructions, knew the plaintiff was doing extra work or supplying extra materials  
and stood by and approved of what was being done and encouraged the plaintiff  
to do it, that, in my opinion, amounts to an implied instruction to the plaintiff, and  
the defendant is liable.  
[600] Tru-Square issued a series of invoices (#111, #118, #124, #125, #129, #133, #136 and  
#135) relating to extra work provided in conjunction with the Lock-Up contract. These invoices  
total $91,134.92, of which $34,678.28 remains outstanding. According to the Plaintiffs, all of  
these amounts, a total of $107,751.11, including GST, were part of the lock-up contract and, as  
such, not properly characterized as “extras.” According to the Plaintiffs, the total contract price  
 
Page: 100  
consists of the Lock-Up contract value, plus the six disputed invoices noted above, a total of  
$1,124,939.25, including GST.  
Invoice #  
Amount  
Exhibit #  
1-C-8  
Invoice 111 (February 12, 2012)  
Invoice 118 (September 1, 2012)  
Invoice 124 (January 4, 2013)  
Invoice 125 (January 5, 2013)  
Invoice 129 (June 18, 2013)  
Invoice 133 (August 20, 2013)  
Invoice 136 (September 27, 2013)  
Invoice 135 (September 29, 2013)  
Total Billed  
$ 16,632.55  
$ 39,824.09  
$ 10,472.70  
$ 2,287.95  
$ 18,246.57  
$ 19,541.97  
745.28  
I-C-11  
I-C-12  
I-C-13  
I-C-14  
I-C-15  
I-C-16  
I-C-18  
$
$324,702.64  
$432,453.75  
$ 69,217.29  
$363,236.46  
Total Paid (#111,#118,#124,#125)  
Total Unpaid  
[601] The Plaintiffs concede that Invoice #135 covering millwork, flooring and stone should be  
added to the amount owing to the Defendants. Invoice #135 is dated September 27, 2013, and  
consists entirely of payments made by Tru-Square to third parties, including C&S Fine Furniture  
Ltd (Carm’s company); Rock Tops Inc; Lawrence Masonry; Creative Interiors; and Dominion  
North. It also includes Tru-Square’s 5% or 10% markup, a total of $15,327.50. The total invoice  
is for $324,702.64. This invoice was never paid.  
[602] The Plaintiffs also concede that Invoice #118 includes “extras” that should be added to  
the amount owing to the Defendants.  
[603] However, the Plaintiffs dispute five of the items invoiced by the Defendants as “extras.”  
For the reasons that follow, I find that some of the disputed items were either requested or  
approved by the Plaintiffs and, as such, are properly included as “extras.”  
[604] First, the Plaintiffs refer to Invoice #111, and a charge of $16,632.55 for alleged upgrades  
to windows and doors. The Plaintiffs maintain that windows and doors were part of the contract  
and that Metcalfe never explained this particular invoice or sought their agreement to an  
additional cost. Moreover, the Plaintiffs maintain that Metcalfe provided no explanation or  
justification for this “extra” during his testimony at trial. In the result, the Plaintiffs say that the  
Defendants are not entitled to pass on these additional costs by way of “extra.” Invoice #111 was  
paid by the Plaintiffs on April 11, 2012.  
Page: 101  
[605] The Defendants advance a number of arguments challenging the Plaintiffs’ assertions  
regarding these alleged “extras.” First, the Defendants point to the fact that the Plaintiffs  
promptly paid Invoice #111 without question or objection. The invoice, Exhibit 1-I-8, clearly  
stated: “UPGRADE WINDOW/DOOR PACKAGE (LUX) Original quoted price 46,531 New  
price 62,371.52”. The original contract, Exhibit 1-C-5, had called for “Windows from Lux – to  
have triple pane low-e (recommended).”  
[606] The Defendants also point to the fact that Carm prepared a budget in May 2012, Exhibit  
1-I-21, that incorporated a list of “extras or upgrades” prepared by Metcalfe and dated May 19,  
2012, Exhibit 1-I-31. In cross-examination, Ms. Swanby acknowledged that she did not bring  
any concerns to either Metcalfe or Carm relative to this list. It is noteworthy that the list includes  
the window upgrade package. Metcalfe’s evidence was that he was asked by either Ms. Swanby  
or Carm to complete this list of estimated extras and upgrades for budgeting purposes.  
[607] I accept Metcalfe’s evidence that, upon request, he produced the May 19, 2012, list of  
extras and upgrades. Given that Ms. Swanby was aware of the list and raised no concern with  
either Metcalfe or Carm regarding these additional expenditures, combined with the prompt  
payment of this invoice without question, I am satisfied that the Plaintiffs approved this  
expenditure. The request to produce this list, as well as the Plaintiffs’ silence in circumstances  
that called out for comment on their part if they disputed any listed upgrade, support my finding  
that the Plaintiffs are liable for the cost of this extra. In my view, it is too late for the Plaintiffs to  
now suggest that they did not approve this additional cost.  
[608] Second, the Plaintiffs dispute a charge of $2,048.28 as set out in Invoice #125, Exhibit 1-  
C-13, stated to relate to plywood installed for the subfloor in tiled areas, plywood to frame  
bathtub surrounds, and the cost to install a temporary two-piece bathroom for the subtrades. The  
Plaintiffs maintain that these items are part of the original contract and that there was never any  
agreement to add either of these items as “extras”. Invoice #125 was paid by the Plaintiffs.  
[609] The Defendants resist the characterization of the items set forth in this invoice as  
“extras”. As such, they say that this was interior work that was specifically excluded from the  
contract.  
[610] Unlike the window upgrade, there is no evidence before me that this particular  
expenditure was the subject of any discussion between the parties. I find that the items set forth  
in this invoice are not properly characterized as “extras”. In my view, the lock-up contract  
obligated the Defendants to build to the point where the drywall had been completed. In my  
view, the framing of bathtub surrounds, the installation of sub-flooring to support eventual tile  
installations and framing within the shower and sauna units were all part of the lock-up contract.  
The Plaintiffs are, accordingly, liable for $228 of this invoice related to a stairway at the garage  
entrance, but no more. Given that this invoice was paid, the Plaintiffs are entitled to a credit of  
$2,059.95  
[611] Third, the Plaintiffs also dispute the cost of removing the temporary two-piece bathroom  
set out in Invoice #136, Exhibit 1-C-16. According to the Plaintiffs, the Defendants did not  
discuss or obtain their approval for this additional cost. Invoice #136 was never paid by the  
Plaintiffs.  
[612] Invoice #136 is in the amount of $745.28 and involved the removal of a temporary two-  
piece bathroom. While it seems clear that Tru-Square paid the sub-contractor, there is  
Page: 102  
insufficient evidence before me to make a finding that the Plaintiffs approved this particular  
item, either expressly or impliedly. Rather, the only evidence before me is that the Plaintiffs did  
not approve this item. Under the circumstances, I accept the Plaintiffs’ contention that this was  
an unapproved “extra” the costs of which the Defendants are not entitled to pass on to the  
Plaintiffs.  
[613] Fourth, the Plaintiff disputes the $17,025.95 amount billed for plumbing upgrades and  
extras, as well as for the replacement cost of a window broken by one of the subtrades. These  
items are set forth in Invoice #129, Exhibit 1-C-14. The Plaintiffs maintain that these items are  
covered by the original contract and were not approved as “extras”. Invoice #129 was never paid  
by the Plaintiffs.  
[614] There are two separate invoices that are dated June 18, 2013, and identified as “Invoice  
129”. One is in the amount of $1,630.38, while the second is in the amount of $18,246.57. The  
second invoice of this same date includes an item not present in the first invoice, specifically, the  
sum of $15,824.95 for plumbing extras and upgrades. I am satisfied that the proper amount of  
this invoice is $18,246.57.  
[615] The amount of $390.24 is attributed to the cost of replacing the broken window. The  
Plaintiffs challenge their responsibility to cover the cost of a window broken by one of the  
Defendants’ subtrades. Likewise, they challenge what they describe as unexplained and  
unspecified plumbing extras and upgrades.  
[616] The Defendants seek to support the validity of this invoice on the basis that the Swanbys  
never denied that this work was necessary or that it was completed. In my view, this is flawed  
logic on the part of the Defendants. Whether the work was necessary and/or completed does not  
address the real question as to whether the work and materials were covered by the original  
contract and, if not, whether these items were added with the express or implied approval of the  
Plaintiffs.  
[617] I am satisfied that the replacement of the broken window was not included in the contract  
that existed between the parties. I find that the Plaintiffs never agreed, either expressly or by  
necessary implication, to cover the replacement cost of the window damaged on site by one of  
the Defendants’ subtrades. In my view, the statement on the invoice that “Shawn was in charge”  
at the time the window was broken does not assist the Defendants’ position in this regard.  
[618] The matter of plumbing upgrades and extras raises different considerations. Prior to the  
parties signing the contracts for the construction of the residence, Metcalfe provided the  
Plaintiffs with a breakdown of the cost of constructing the entire residence beyond the lock-up  
stage: Exhibit 1-C-20. Ms. Swanby believed that the itemized break-down set out in this  
document represented the basis upon which Metcalfe determined the cost to complete the  
residence, virtually the same cost set out in the second contract signed on August 22, 2011:  
Exhibit 1-C-6. This included amounts of $3,000, $3500, and $5000 for a steam shower, shower  
door(s) and plumbing upgrades, respectively. These were items for which Tru-Square was not  
responsible as part of the Lock-Up contract. In her evidence, Ms. Swanby testified that she did  
not know what the amount for plumbing upgrades entailed as Metcalfe never provided her with  
any information as to what would be included as basic plumbing covered by the contract and  
what would be considered an upgrade. Likewise, despite repeated requests, Metcalfe failed to  
provide Ms. Swanby or Carm with a list of available allowances for the various interior finishing  
elements of the residence.  
Page: 103  
[619] As previously discussed, Metcalfe prepared a document dated May 19, 2012, in which he  
listed a breakdown of the construction costs associated with the Lock-up Contract, as well as a  
list of extras and or upgrades again relating to the Lock-Up Contract: Exhibit 1-I-31. The May  
2012, budget prepared by Carm, Exhibit 1-I-21, included a list of actual and anticipated upgrades  
based on the May 19, 2012, Metcalfe document, including the sum of $20,725 for “plumbing  
upgrades above original fixture list”. Again, as previously discussed, Ms. Swanby conceded  
during cross-examination that these documents were presented to her at some point and she  
failed to raise any concerns with Metcalfe regarding any of the items on the list.  
[620] Generally speaking, the onus is on the contractor to ensure that the customer either  
requested or approved the “extra”. In this instance, I find that the Plaintiffs were aware from the  
outset of their discussions with Metcalfe that the base price set out in the initial quote, Exhibit 1-  
C-2, as well as in the Lock-Up contract, I-C-5, covered basic fixtures only. Both documents  
contemplated that customer preferences would be accommodated as “extras”. As of May 19,  
2012, the Plaintiffs were also aware from Metcalfe’s list of extras and upgrades that he estimated  
a cost of $20,725 for plumbing fixture upgrades. This same number was carried forward into  
Carm’s May 21, 2012, detailed budget prepared for the Plaintiffs. Given this knowledge, I am  
satisfied that the Plaintiffs were well aware that their selection of plumbing fixtures over and  
above basic fixtures would result in an “extra” for which they would be financially responsible.  
[621] For the foregoing reasons, I find that the plumbing extras of $15,824.95, is properly  
characterized as an “extra” for which the Plaintiffs are responsible. However, the replacement of  
the broken window, $390.24, is not “extras” for which the Defendants can seek compensation  
from the Plaintiffs. The other items on the invoice totaling $1,162.50 are properly characterized  
as “extras” for which the Plaintiffs are responsible.  
[622] Finally, the Plaintiffs refer to Invoice #133. Exhibit 1-C-15, that lists a charge of $16,274  
for “Electrical as per detail supplied by Eagle Electric”. An explanatory note states that Tru-  
Square has “paid some of extras so check (sic) needs to be made out to Tru-Square Homes.” In  
his direct examination, Metcalfe testified that everything listed on this invoice related to “extras”  
that were not part of the original contract.  
[623] There is no dispute that Tru-Square never paid Eagle Electric the $10,500 then owing at  
the time Dueck walked off the job prior to completion of the electrical work. Dueck testified that  
he left the job site on account of the non-payment of his account. Metcalfe’s evidence on this  
point was that he intends to pay Eagle Electric once he receives payment from the Plaintiffs. This  
amount is, accordingly, included in his counterclaim. Metcalfe described these extras as light  
fixtures but provided no details in his trial evidence.  
[624] Of this amount, the Plaintiffs say that $10,000 was never paid by Tru-Square or by them.  
The Plaintiffs maintain that this contractor has never made a claim for this unpaid work.  
According to the Plaintiffs, the remaining $3,400 covers work that was never actually done.  
Accordingly, the Plaintiffs contend that these amounts are not owing to the Defendants and are  
not recoverable as “extras.” Invoice #133 was never paid by the Plaintiffs.  
[625] Counsel have not directed me to any evidence that demonstrates that the Plaintiffs ever  
approved any of these electrical “extras”. The Plaintiffs take the position that they did not. The  
evidence of Dueck and his invoice, Exhibit 7, certainly suggest that all of this work was  
completed. As noted above, Metcalfe was clear that at all of the amounts covered in Invoice  
#133 involved “extras”.  
Page: 104  
[626] In my view, it was incumbent upon Metcalfe and Tru-Square to lead some evidence to  
show that the Plaintiffs either requested these “extras” or that they approved them. In the  
absence, of such evidence I am not prepared to find that these are “extras” for which the  
Defendants are entitled to be compensated, even assuming that Eagle Electric continues to have a  
viable claim against the Defendants for this unpaid work. I would simply add that the $710 item  
for the rough in of the vacu-flow is not disputed by the Plaintiffs as constituting an extra.  
[627] Finally, the Plaintiffs say that Tru-Square was credited a sum of $2,560 for work on the  
front deck that was never actually performed by the concrete subcontractor. The Plaintiffs  
maintain that this amount was never credited to them and, as such, should be deducted from the  
counterclaim.  
[628] Exhibit 4 is an invoice dated September 12, 2011, issued by Kutney Concrete  
Foundations to Tru-Square Construction (sic). The invoice includes a charge of $18,563 for  
labour supplied to crib and place the foundation of the residence as per the plan and previous  
quote. The invoice also includes a credit for $2,560, described as “front deck credit”. Tru-  
Square’s May 2, 2012, invoice to the Plaintiffs, Exhibit 1-C-9, covers the second draw of the  
parties’ contract and includes the cost of pouring the basement floor.  
[629] The Defendants say that there is no evidence that any of the work that was to have been  
undertaken by Kutney was not completed. Unfortunately, Metcalfe was never cross-examined as  
to why this credit was issued. I agree with the Defendants that it would not be appropriate in  
such circumstances to simply assume that this was work that was required under the terms of the  
contract. There is simply no evidence that this was essential concrete work that formed part of  
the parties’ fixed-price contract.  
[630] If Tru-Square was able to fulfill its’ obligations under that contract at a cost that was  
somewhat less than it may have anticipated, this does not result in a credit to the home owners.  
The converse is also true in that if the cost of the foundation, for example, had greatly exceeded  
what Tru-Square had anticipated, this so-called additional cost could not have been passed on to  
the home owners as an “extra”. In a fixed price contract situation, the contractor bears both the  
“benefit” and the “burden” of shifting costs.  
[631] In this instance, Kutney would appear to have completed the concrete work at a cost to  
Tru-Square that was less than the bid amount. The identification of a credit on Kutney’s invoice  
suggests that Tru-Square had already paid the full amount specified in the bid and was now  
receiving a credit for work that was not required. In the context of a fixed price contract, this  
scenario results in some “gain” to the general contractor, but does not lead to a credit back to the  
homeowners.  
[632] I would summarize my findings relative to the various contested upgrades and extras set  
out in Invoice #111, #118, #124, #125, #129, #133 and #136 as follows:  
Invoice  
#111  
$16,632.55 to be added as an “extra” to the contract price;  
Invoice  
#118  
$39,824.09 to be added as an “extra” to the contract price;  
Page: 105  
Invoice  
#125  
$228.00  
to be added as an “extra” to the contract price;  
Invoice  
#136  
No items to be added as an “extra” to the contract  
price;  
Invoice  
#129  
$16,987.45 to be added as an “extra” to the contract price;  
Invoice  
#133  
$710.00  
to be added as an “extra” to the contract price.  
TOTAL  
$74,382.09  
[633] Taking all these amounts that have been determined to be “extras”, I would add  
$74,382.09 to the total contract price (contract price plus Invoice #135) for a total contract value  
of $1,091,570.23.  
3. Amount Paid to Tru-Square  
[634] As set out at paragraph 246 of the Agreed Statement of Facts, Exhibit 2, the parties agree  
that the Plaintiffs paid a total of $659,792.29 to Tru-Square, leaving an outstanding balance  
owing to Tru-Square of $431,777.94 by the Plaintiffs.  
4. Amounts Paid to TGC for Remediation Work  
[635] The Plaintiff say that they paid a total of $1,431,892.41 to obtain what they had  
contracted for with the Defendants. Of this amount, as indicated above, they paid a total of  
$659,792.29 to the Defendants and the remaining $772,100.20 that was paid for remediation  
work and completion costs. According to the Plaintiffs, this amount breaks down as follows:  
Demolition work by TGC  
$84,543.21  
$606,816.56  
$25,338.70  
$4,693.50  
$6,516.22  
$31,316.81  
$5,139.86  
$3,615.62  
$3,835.76  
Remediation work by TGC  
TGC work completed after Nov/15  
C & S Fine Furniture Ltd  
Tile Subcontractor and replacement  
Replace improperly installed windows  
Replace Exterior Stone  
Plumbing Material for SubTrade  
Burst waterline replacement flooring  
   
Page: 106  
Burst waterline remove line  
$133.88  
Moving costs fridge (waterline burst)  
$150.00  
Total  
$772,100.12  
[636] The first three items in the above list were apparently paid to TGC a total of  
$716,698.47. However, as set out below, Juniper gave evidence that TGC submitted a total of 19  
invoices totalling $769,543.24 to the Plaintiffs, all of which were paid. The difference between  
these two amounts - $52,844.77 has never been explained. In view of the fact that the Plaintiffs  
written submissions clearly state that they are seeking $772,100.12, of which $716,698.47 was  
paid to TGC, this is the amount that I will factor into the assessment of damages.  
[637] The remediation work to address the various construction deficiencies was carried out by  
TGC, a general contracting firm run by Mike Juniper. In addition to the remediation work carried  
out relative to this residence, TGC also did work for the Plaintiffs in relation to their other home  
and a shed located on the same property as the Tru-Square built home. I accept the evidence of  
both Juniper and Ms. Swanby that TGC’s work on the shed and the Plaintiffs’ other home was  
billed separately from the remediation work on the Tru-Square built home.  
[638] TGC submitted a series of invoices to the Plaintiffs for the labour, materials, and rentals  
that were used in the remediation process. A total of 19 invoices relating to this project were  
submitted and paid by the Plaintiffs. The invoices have a common format in that they include  
charges for site management; consulting; skilled labour billed out at an hourly rate; general  
labour billed out at an hourly rate; materials; and tool rentals. A number of the invoices have  
supporting time sheets of the TGC workers involved in this remediation project, though these  
time sheets were not included in the invoices sent to the Plaintiffs.  
Invoice#  
4
Date  
Sub-Total  
$25,467.43  
GST  
Total  
Exhibit#  
19/08/13  
04/11/13  
21/01/14  
08/08/14  
08/22/14  
10/01/14  
10/23/14  
11/18/14  
12/17/14  
01/12/15  
02/01/15  
02/20/15  
03/19/15  
04/06/15  
$1,273.37  
$26,740.80 1-F-4  
$3,053.06 1F7  
$2,063.25 1-F-8  
10  
$3,053.06  
$2,063.25  
14  
26  
$18,350.96  
$19,834.16  
$9,402.65  
$917.55  
$19,268.51 1-F-12  
$20,825.87 1-F-13  
$9,872.79 1-F-14  
$16,726.50 1-F-15  
$24,113.18 1-F-18  
$28,653.10 1-F-19  
$27,351.10 1-F-21  
$46,887.80 1-F-22  
$15,673.56 1-F-23  
$78,050.12 1-F-24*  
$40,286.68 1-F-26  
28  
$991.71  
32  
$470.14  
34  
$15,930.00  
$22,964.93  
$27,288.66  
$26,048.67  
$44,655.04  
$14,927.19  
$796.50  
37  
$1,148.25  
$1,364.44  
$1,302.43  
$2,232.76  
$746.37  
42  
43  
45  
47  
48  
52  
$38,368.26  
$1,918.42  
Page: 107  
Invoice#  
Date  
Sub-Total  
$51,759.60  
GST  
Total  
Exhibit#  
53  
54  
04/28/15  
05/13/15  
06/10/15  
07/01/15  
07/24/15  
08/26/15  
09/27/15  
10/28/15  
03/04/16  
$2,587.98  
$3,052.51  
$1,951.66  
$2,998.43  
$1,873.70  
$4,115.27  
$1,054.39  
$682.17  
$54,347.58 1-F-27  
$64,102.71 1-F-28  
$40,984.94 1-F-29  
$62,967.02 1-F-30  
$39,347.63 1-F-31  
$86,420.80 1-F-32  
$22,142.13 1-F-33  
$14,325.41 1-F-34  
$25,338.70 1-F-37  
$769,543.24  
$61,050.20  
$30,033.28  
$59,968.59  
$37,473.93  
$82,305.53  
$21,087.74  
$13,643.24  
$24,132.10  
56  
58  
61  
65  
66  
72  
79  
$1,206.60  
TOTAL  
*The TGC invoice dated March 19, 2015, in the amount of $78,050.12 consists of  
the following items:  
a) TGC labour [$2,952.50], materials [$6,657.61], electrical services [$3,112.73], and  
plumbing [$5,746.13] TOTAL: $18,468.97;  
b) Infinity Plumbing and Heating Ltd - $5,223.75 [including GST of $248.75];  
c) Rock-It Concrete Ltd - $2,104.20 [including GST of $100.20];  
d) Rock-It Concrete Ltd - $567 [including GST of $27];  
e) BTB Drywall Ltd - $16,748.76 [including GST of $797.56];  
f) JMV Inc [labour] - $2,829.75 [including GST of $134.75];  
g) Liberty Roofing Inc - $57,555 plus GST of $2877.75 Total: $60,432.75.  
1732964 Alberta Ltd  
Invoice#  
10  
9
11  
13  
Date  
Sub-Total  
$1600.00  
$1600.00  
$1125.00  
$1800.00  
GST  
Total  
Exhibit #  
1-F-16  
1-F-16  
1-F-16  
1-F-16  
28/10/14  
28/10/14  
28/10/14  
12/12/14  
$80.00  
$80.00  
$56.25  
$90.00  
$1680.00  
$1680.00  
$1181.25  
$1890.00  
Ken Nordenfelt Contracting  
Invoice# Date  
Sub-Total  
$3240.00  
$3240.00  
$2565.00  
$2880.00  
GST  
Total  
Exhibit #  
1-F-16  
1-F-16  
1-F-16  
1-F-16  
$162.00  
$162.00  
$128.00  
$144.00  
$3402.00  
$3633.00*  
$2693.00  
$3024.00  
*Includes $231.00 for galvanized nails  
Rock-It Concrete Ltd  
Invoice#  
Date  
Sub-Total  
GST  
Total  
Exhibit #  
931  
25/11/14  
$3480.00  
$174.00  
$3,654.00  
1-F-16  
[639] In several instances, the TGC engaged sub-contractors to assist with the remediation  
work. These costs were passed on and paid directly by the Plaintiffs.  
Page: 108  
[640] Exhibit 1-F-4 represents two copies of the same invoice and totals $26,740.80. This  
invoice was partially paid by the Plaintiffs, though shows an outstanding balance of $2,021.28.  
[641] Attached to Juniper’s final report, undated Exhibit 1-F-35, a cost break-down to date is  
provided at pages 140-143. In this cost break-down, Juniper refers to the demolition expenses  
(Invoices 4, 10, 14, 26, 28, 32, 34, 37, 42, 47, 52, and 53) which total $84,543.21. A second chart  
sets out the costs associated with rebuild expenses (Invoices 4, 10, 26, 28, 32, 34, 37, 42, 43, 45,  
47, 48, 52, 53, 54, 56, 58, 61, 65, and 72) which total $606,816,56. These two amounts total  
$691,359.77.  
[642] The cost break-down also refers to the fact that there were several aspects of the house  
that were not completed. These incomplete items are listed as including:  
a) Carpet not installed in bedrooms and Bonus Room;  
b) Final coat of paint in most rooms;  
c) Interior doors needed to be sprayed and installed with hardware;  
d) A number of electrical and plumbing items needed to be finished (lights, fan, panels,  
steam shower etc);  
e) Cabinetry not complete;  
f) Eaves and Downspouts not complete;  
g) Bar counter tops and finals in this area;  
h) Final coat of stucco required;  
i) Tops on both the front and back pillars not finished;  
j) Garage doors not trimmed or water-sealed.  
[643] In his report, Juniper estimated that it would cost $50,000-$60,000 to complete these  
items. While it is not entirely clear on the evidence before me, it would appear that TGC  
completed all this work as part of the remediation process and billed the Plaintiffs accordingly.  
[644] The Defendants advance several arguments in support of their contention that it is not  
possible to calculate accurately the quantum of damages owing to the Plaintiffs in this instance.  
[645] First, the Defendants say that the invoices are not detailed and that there are no reliable  
supporting records for the invoices submitted by Juniper to the Plaintiffs. According to the  
Defendants, Juniper’s timesheets do not provide a reliable indicator of the time spent on a  
particular deficiency by any specific worker. In particular, the Defendants raise concerns with  
respect to the fact that the invoices do not permit a determination as to how much was spent on  
structural repairs as opposed to building envelope repairs.  
[646] The Defendants also say that the timesheets provide no explanation as to why skilled  
labour may have been required in some instances and not others and combines labour costs of the  
TGC employees and independent sub-contractors. The Defendants also raise concerns with the  
fact that Juniper testified that he only had hand-written notes as to what deductions he made  
relative to other, unrelated work being performed for the Plaintiffs. The Defendants point out that  
not all of the invoices are fully supported by accompanying time sheets.  
Page: 109  
[647] Second, the Defendants say that it is not possible to associate the budgeted figures with  
the invoices that were issued. In this regard, the Defendants say that Juniper had not been  
provided with any work program at the time that he prepared the budget for his remediation work  
and, further, that he had no recollection of receiving the Remediation Scope document prepared  
by Matthews in October 2013.  
[648] Third, the Defendants suggest that there is no way to isolate the costs associated with the  
damages resulting from a leak in the refrigerator ice-maker line.  
[649] Fifth, the Defendants challenge the remediation costs claimed by the Plaintiffs on the  
basis that this work was not subject to any competitive process.  
[650] Sixth, the Defendants say that there is no evidentiary basis to conclude that Juniper’s total  
charges represent a reasonable cost to complete the required remediation work. In this regard, the  
Defendants challenge the evidence of Kraychy regarding the reasonableness of these costs.  
[651] The Defendants advance one further argument relating to the difficulty of identifying the  
costs associated with the removal of all the exterior stone from the residence. The Defendants  
raise this concern on the assumption that the removal of the stone was not a remediation cost  
properly attributed to the Defendants given that the application of the stone fell outside of the  
parties’ contract. As more fully explained earlier in these reasons, I am satisfied that the removal  
of the stone was required in this instance to remove the underlying stucco due to extensive  
cracking and so that the stone could be re-installed with a proper bonding material.  
[652] I do not accept the Defendants’ contention that the only basis upon which to assess the  
reasonableness of the Plaintiffs’ remediation expenditures lies in what is alleged to be the  
unsubstantiated dollar figures of the TGC invoices. First of all, Juniper gave extensive evidence  
during the trial. He was examined in chief for a full day and subject to a further full day of cross-  
examination. He provided at least three written quotes to the Plaintiffs as his knowledge and  
understanding of the scope of the work evolved through the on-going investigative work. His  
January 2014 quote, Exhibit 1-F-9, contains a 23-page overview of the scope of work required to  
remediate the residence. It is broken down into categories defined by the type of required  
remediation work or affected area of the home. Estimated repair costs were provided for each  
category. Of note, the total estimated cost of remediation was $802,597.11, just over $32,000  
more than the actual cost of $769,543.24 paid to Juniper by the Plaintiffs. The difference  
between the projected cost and the actual cost was approximately 4%.  
[653] Juniper’s final report is 143 pages long, including numerous photographs, that show the  
as-built condition of the residence, repairs being effected, and the remediated state. Juniper’s  
evidence must also be considered together with the trial evidence and expert reports prepared by  
Bjornson and Matthews, the two engineers hired by the Plaintiffs, as well as the expert report of  
the Defence expert, Mr. Hamman. The extensive collection of photographs that are in evidence,  
together with Matthews’ engineered repair details, Exhibit 1-A-7, are all part of the  
comprehensive body of evidence that reveals the full extent of the remediation work required to  
complete the residence.  
[654] I have carefully considered the other arguments advanced by the Defendants challenging  
both the adequacy and reliability of the Plaintiffs’ damages claim. In the absence of any authority  
suggesting otherwise, I am not prepared to find that the Plaintiffs were under any obligation to  
submit this remediation work to any form of competitive process prior to engaging Snyder,  
Page: 110  
Matthews, Bjornson and Juniper. Likewise, I do not attach any real significance to the fact that  
Juniper’s final budget for the remediation does not appear to be closely related to a work  
program developed by either Matthews or Bjornson based on their investigative findings and  
associated recommendations. As previously indicated, one of the most significant challenges  
posed by this project lay in the fact that the investigation of one identified deficiency revealed  
other unanticipated deficiencies. This state of affairs significantly undermined the planning part  
of the process in so far as the plan was in a seemingly continuous state of evolution.  
[655] This is not a situation where the Defendants could legitimately claim that the work of the  
remediation team was unfocused, disorganized or lacking coordination. Quite the contrary, based  
on the evidence before me, I am satisfied that the key members of the remediation team,  
Matthews, Bjornson and Juniper, worked together very effectively under very challenging  
circumstances. I would simply add that the importance of planning must always be balanced  
against the pressing need that existed in this situation to complete the construction of this  
residence.  
[656] The Defendants also raise concerns with respect to the adequacy of the time sheets  
provided by the various workers involved in the remediation exercise. There is, in my view,  
some merit to the Defendants’ suggestion that the various invoices and timesheets do not  
perfectly align, and that there are some obvious gaps in the records supporting the invoices.  
Ideally, each invoice would have been broken down by work activity and fully supported by time  
records that reflected how much time any given worker spent on a specific task. Information  
gathered and recorded in this fashion would have provided a clear indication of which work had  
been performed by skilled versus unskilled workers and by Juniper’s employees versus  
independent contractors.  
[657] Unfortunately, this information is not available in this instance. Rather, itemized invoices  
are partially supported by time sheets prepared by individual workers, though some of the  
invoices are missing some of the supporting time sheets. In the result, some gaps are revealed in  
trying to determine with certainty what workers performed work on specific activities over a  
specific period of time. Juniper did, however, provide a reasonable explanation for at least some  
of these gaps.  
[658] The gaps in TGC’s records that support the invoices for the work performed do not cause  
me to doubt the overall reliability of this evidence. I found Juniper to be a highly credible  
witness who went to great lengths during the course of this nearly two days on the witness stand  
to assist the Court and the parties to fully understand the nature and extent of the work that he  
undertook in this instance. I am satisfied that he employed a reasonable, albeit imperfect, system  
to gather together the required information to substantiate his client billings. Having heard his  
evidence and reviewed the extensive materials that he produced in documenting his involvement  
in this project, I have confidence in the overall reliability of the billing processes employed in  
this instance.  
[659] With respect to the damages resulting from the leak in the refrigerator, I accept the  
underlying contention that these are not damages attributable to the Defendants. Juniper was the  
only witness who addressed the leaking refrigerator, its underlying cause, and the ensuing  
damage. He testified that the leak was not related to the water line leading to the appliance.  
Rather, the leak was internal to the refrigerator, though he was unable to identify the precise  
source of the leak. He also testified that the resulting damage was not covered by the Plaintiffs’  
Page: 111  
insurance, and that the repairs undertaken to the hardwood flooring, the basement wall in the  
room underneath the kitchen, and the replacement of a water-damaged roll of cork flooring that  
was being stored in the basement, was included in the invoices he submitted to the Plaintiffs.  
[660] Juniper was unaware when the appliance had been installed or who was involved in the  
installation process. There is no other evidence on this point, including any evidence regarding  
any manufacturer’s warranty that may have been applicable under the circumstances. Given  
Juniper’s evidence regarding the nature of the leak, namely that it was internal to the appliance, I  
am satisfied that this damage is not properly attributed to the Defendants. There is no evidence  
that the Defendants had any role in the installation of the refrigerator, let alone any responsibility  
for its internal operation. While it is unfortunate that neither the Plaintiffs’ insurers nor the  
appliance manufacturer was willing to cover the cost of repairing the resulting damage, I am  
satisfied that this was not a cost for which the Defendants should be held responsible.  
[661] Juniper testified that it was necessary to patch the kitchen floor with left-over flooring  
material, repair the drywall and repaint in certain areas. I would reduce the Plaintiffs’  
remediation claim by $500 to account for the repair to the drywall and the necessary repainting  
and would disallow the various items included in TGC’s account in this regard.  
[662] I find that the Plaintiffs are entitled to recover total remediation costs of $772,100.12, less  
the costs associated with the damages occasioned by the refrigerator leak, $4,119.64, and less  
$500 to cover the drywall repair and repainting, for a total remediation cost of $767,480.48.  
From this amount, I would deduct the amount the Plaintiffs owe the Defendants under the  
construction contract, a total of $431,777.94. In the result, the Defendants are required to pay to  
the Plaintiffs the sum of $335,702.54.  
B. Consequential Damages  
[663] Relying on Vermillion at para 180, and Heintzman on Canadian Building Contracts, 5th  
ed., Carswell, Toronto, at para 9-50, the Plaintiffs say that they are entitled to consequential  
damages in the amount of $68,632.12, including the costs of hiring consultants to assist them in  
remediating and completing the residence. Specifically, the Plaintiffs claim the following  
amounts:  
$525  
a) Western Form Works (Troy Snyder leaking  
windows  
$3,024  
b) Optimize Engineering (Dana Bjornson)  
$36,456  
c) Madden Matthews Engineering  
[664] The Plaintiffs also say that they are entitled to be compensated for other consequential  
losses occasioned in this instance. The Plaintiffs, citing Chitty on Contracts, Vol 2, at 37-214,  
say that they are entitled to consequential losses which would have been in the reasonable  
contemplation of the parties if they had thought about the issue. Chitty on Contracts describes  
consequential loss in the following terms:  
In construction projects, defects in the works will often have a wider impact upon  
the employer’s existing operations and production process. Such losses will rarely  
be said to arise naturally according to the usual course of things and, accordingly,  
consequential losses will usually fall under to (sic) the second limb of Hadley v  
 
Page: 112  
Baxendale, that is, damage which, in the reasonable contemplation of both parties  
at the time of making the contract would, had they thought about it, have had a  
very substantial degree of probability.  
[665] This very issue was also addressed in Vermillion. At paras 263-65, the Court included  
profession fees incurred by the claimant to investigate and then remediate the defect that was  
discovered in that instance. At para 264, the Court held:  
I have found that Vermillion acted reasonably in the circumstances in retaining  
Williams to conduct an investigation into the cause of the Defect and in  
undertaking remedial work as required on the Project. This is particularly so given  
the total lack of input from the Defendants from approximately mid-2006 onward.  
While Vermillion is a sophisticated entity in the business of providing health  
services, it is not sophisticated in the areas of design and construction of facilities  
such as the Project. It was entirely reasonable for it to seek the assistance of a  
professional firm such as Williams to investigate and address the problems  
encountered with the Project.  
[666] The Defendants do not seriously challenge the Plaintiffs need for professional assistance  
in this instance. While the Defence expert, Hamman, appeared to suggest that some of the  
identified construction deficiencies did not require the involvement of professional engineers, his  
evidence focused largely on his conclusions that less costly options were available to address  
many of the identified deficiencies. In any event, I am satisfied that the Plaintiffs’ prompt  
decision to seek the assistance of experts was reasonable under the circumstances. Given  
Metcalfe’s unwillingness to offer any assistance, let alone accept any responsibility, for the  
leaking windows, it was eminently reasonable, indeed highly prudent, for the Plaintiffs to reach  
out for high level guidance and advice. I find that the Plaintiffs’ decision to engage Snyder,  
Bjornson and Matthews gave rise to expenses that properly fall under the heading of  
consequential damages.  
[667] According to the Plaintiffs, Metcalfe was aware that they intended to sell their former  
residence in Carstairs. He was also aware that the anticipated completion of the new residence  
was June 2012. The Plaintiffs maintain that costs arising from their delayed occupancy of the  
new residence on account of remediation work was reasonably foreseeable. They claim a total of  
$28,527.24, covering the period of approximately May 2013 until August 2015:  
Waste bin rental during demolition/remediation  
Burn pit (waste disposal)  
$1,281.12  
$882.00  
Utilities during demolition/remediation  
Gas at new residence  
$6,704.57  
$3,780.13  
$3,527.63  
$7,681.80  
Tax Assessment on new residence (not land)  
Equipment rental for demolition/remediation  
Replacement door handles (disappeared from site)  
$986.95  
Page: 113  
Lost interest  
$3,683.04  
[668] With respect to the claim for lost interest, the Plaintiffs made 27 mortgage payments  
between April 2013 and July 2013 [sic] at $4,958.20, totaling $133,871.40. The Plaintiffs claim a  
total of $3,683.04 in interest for the premature use of these funds that could otherwise have  
earned interest or investment proceeds.  
[669] The Defendants challenge the characterization of all the above items as consequential  
costs in these circumstances. According to the Defendants, these damages were not foreseeable  
given the length of time that it took to commence and complete the remediation of the residence.  
The Defendants cite no authority for the proposition that there is any recognized connection  
between foreseeability and the time that it takes the aggrieved party to address the damage  
caused by the other party. In my view, there is no merit to the Defendant’s contention in this  
regard.  
[670] I would, however, deduct the cost of the replacement door handles. While this is a  
relatively minor item, this was not a foreseeable loss and, as such, is not recoverable as  
consequential damages.  
[671] The Defendants also challenge a portion of Matthews’ November 2, 2015, invoice to the  
Plaintiffs, Exhibit 1-H-32, namely an expenditure of $20,215.00 plus GST for 14  
repair/remediation sketches produced at the request of Juniper. According to the Defendants,  
some of these sketches were not used or completed. No details are provided as to which sketches  
were either not used or completed.  
[672] During his testimony, Juniper specifically referred to at least 10 of the 14 sketches  
provided by Matthews. He explained that he relied on these sketches to effect the repairs and or  
remediation recommended by Matthews. In his evidence, Matthews also referred in some detail  
to many of these same sketches. In the absence of any particulars as to which sketches were not  
used or completed, I am not prepared to accept the Defendants’ submission in this regard. In my  
view, the sketches were a reasonable, indeed essential, part of the more complex tasks involved  
in the remediation process.  
[673] In conclusion, I would award a total of $67,545.29 in consequential damages.  
[674] Before turning to consider other potential heads of damages, I find that the Defendants  
are liable to the Plaintiffs in the amount of $403,247.83.  
C. Non-Pecuinary General Damages  
[675] The Plaintiffs seek non-pecuniary general damages of $50,000. Relying on the decision  
in Hickey’s Building Supplies Ltd v Sheppard, 2014 NLCA 43, the Plaintiffs say that this  
contract was a ‘peace of mind’ contract that was intended to bring about psychological benefit to  
them as their dream retirement home and a place to spend time with their then teenaged  
daughters. The Plaintiffs maintain that the breach of contract brought about mental distress that  
was within the reasonable contemplation of the contracting parties sufficient to justify  
compensation. In further support of their claim for damages in this regard, the Plaintiffs point to  
the fact that Mr. Swanby’s plan to retire from his overseas job in 2019, once he had paid for the  
cost of building the home, had to be postponed such that he now expects to have to work outside  
of the country for an additional 10 years.  
 
Page: 114  
[676] As the Defendants properly point out, the Plaintiffs did not seek non-pecuniary general  
damages in their various pleadings and have made no application to amend their claim. If the  
Plaintiffs are permitted to advance their claim for general non-pecuniary damages, the  
Defendants say that the Plaintiffs have failed to advance sufficient evidence to justify the  
awarding of such damages.  
[677] The Defendants maintain that there is no basis to conclude that the Plaintiffs suffered  
from anything beyond the normal frustrations of litigants pursuing a claim for breach of contract.  
There is no evidence that either of the Plaintiffs suffered any additional distress, or that they  
required counselling or other medical intervention. Further the Defendants point out that the  
Plaintiffs were experiencing other stresses in their life at the time as well, including the  
inordinate delay in the commencement and completion of the remediation work, a matter that  
was outside the control of Metcalfe and could not have been anticipated by him at the time the  
contract was signed on August 22, 2011.  
[678] In Hickey’s, a majority of the Newfoundland and Labrador Court of Appeal upheld the  
trial judge’s decision to award $15,000 in general, non-pecuniary damages. In that instance, the  
Sheppards contracted with Hickey for the construction of a new home. The builder was aware  
that the new home to be constructed had to accommodate Ms. Sheppard’s wheelchair and her  
mobility issues and, as such, required level floors. The residence, as constructed, included the  
use of transition strip between ceramic tile and hardwood flooring given the difference in  
thickness between the two materials.  
[679] Writing for the majority, Hoegg JA provided an extensive review of the law relating to  
the awarding of general, non-pecuniary damages for mental distress in breach of contract cases.  
Starting with the decision of McLachlin CJC and Abella J in Fidler v Sun Life Assurance Co,  
2006 SCC 30, Hoegg JA traced the evolution of this head of damages in both the United  
Kingdom and Canada.  
[680] In Fiddler, the Supreme Court found that mental distress may be an appropriate head of  
damage “where such damages were in the reasonable contemplation of the parties at the time the  
contract was made”: at para 44. The Court went on to explain at para 45-47:  
It does not follow, however, that all mental distress associated with a breach of  
contract is compensable. In normal commercial contracts, the likelihood of a  
breach of contract causing mental distress is not ordinarily within the reasonable  
contemplation of the parties. It is not unusual that a breach of contract will leave  
the wronged party feeling frustrated or angry. The law does not award damages  
for such incidental frustration. The matter is otherwise, however, when the parties  
enter into a contract, an object of which is to secure a particular psychological  
benefit...The basic principles of contract damages do not cease to operate merely  
because what is promised is an intangible, like mental security.  
This conclusion is supported by policy considerations that have led the law to  
eschew damages for mental suffering in commercial contracts. As discussed  
above, this reluctance rests on two policy considerations the minimal nature of  
the mental suffering and the fact that in commercial matters, mental suffering on  
breach is “not in the contemplation of the parties as part of the business risk of the  
transaction”: McGregor on Damages, at p. 63. Neither applies to contracts where  
Page: 115  
promised mental security or satisfaction is part of the risk for which the parties  
contracted.  
This does not obviate the requirement that a plaintiff prove his or her loss. The  
court must be satisfied that: (1) that an object of the contract was to secure a  
psychological benefit that brings mental distress upon breach within the  
reasonable contemplation of the parties; and (2) that the degree of mental  
suffering caused by the breach was of a degree sufficient to warrant  
compensation...  
[681] The Court concluded that the “peace of mind” class of cases “should not be viewed as an  
exception to the general rule of the non-availability of damages for mental distress in contract  
law, but rather as an application of the reasonable contemplation or foreseeability principle that  
applies generally to determine the availability of damages for breach of contract”: at para 49.  
[682] Subsequently, in Mustapha v Mulligan of Canada Ltd, 2008 SCC 27, McLachlin CJC  
considered the awarding of non-pecuniary general damages in the context of a plaintiff who  
found a fly in an unopened bottle of drinking water. Chief Justice McLachlin found that the  
damages in that instance were too remote to be compensable, explaining (at para 16) that “the  
law of tort imposes an obligation to compensate for harm done on the basis of reasonable  
foresight, not as insurance”. She went on (at para 17) to explain that “[O]nce a plaintiff  
establishes the foreseeability that a mental injury would occur in a person of ordinary fortitude,  
by contrast, the defendant must take the plaintiff as it finds him for the purpose of damage”. Of  
relevance to the within matter, McLachlin CJC went on to add that in contract law if:  
the defendant had actual knowledge of the plaintiff’s particular sensibilities; the  
ordinary fortitude requirement need not be applied strictly. If the evidence  
demonstrates that the defendant knew that the plaintiff was of less than ordinary  
fortitude, the plaintiff’s injury may have been reasonably foreseeable to the  
defendant...  
[683] I accept the Defendants’ contention that the Plaintiffs have failed to meet either of the  
requirements set out in Fidler. First, Metcalfe’s general awareness that the residence was  
intended as the Swanby’s retirement residence does not rise to the level that it can be said the  
parties reasonably contemplated mental distress flowing to the Plaintiffs beyond normal  
frustration and anger upon a breach of the contract to build that residence. Likewise, I am not  
persuaded by the fact that Metcalfe was aware that the residence was planned as a family home  
for the Swanbys and their children would give rise to mental distress beyond incidental  
frustration if there was a breach. I agree with the Defendants that the circumstances in this  
instance were not comparable to the circumstances of the disabled plaintiff impacted in Hickey’s.  
[684] As regards the second requirement set out in Fidler, I note that the Plaintiffs have not  
adduced any evidence from, for example, a mental health professional to substantiate that the  
breach of contract in this instance produced a significant impact that involved something more  
than “the ordinary annoyances, anxieties and fears” associated with the breach of an agreement:  
Mustapha at para 9.  
D. Punitive Damages  
[685] In their Statement of Claim and Amended Statement of Claim, the Plaintiffs sought both  
aggravated damages and punitive damages. While it seems clear that aggravated and punitive  
 
Page: 116  
damages will frequently cover the same conduct, the decided cases make it plain that they serve  
different purposes.  
[686] McIntyre J provided a helpful explanation of the nature of these two heads of damages in  
Vorvis v ICBC, [1989] 1 SCR 1085 at p 1098:  
… Punitive damages, as the name would indicate, are designed to punish. In this,  
they constitute an exception to the general common law rule the damages are  
designed to compensate the injured, not to punish the wrongdoer. Aggravated  
damages will frequently cover conduct which could also be the subject of punitive  
damages, but the role of aggravated damages remains compensatory. The  
distinction is clearly set out in Waddams, The Law of Damages (2nd ed. 1983) at  
p. 562, para 979, in these words:  
An exception exists to the general rule that damages are  
compensatory. This is the case of an award made for the purpose,  
not of compensating the plaintiff, but of punishing the defendant.  
Such awards have been called exemplary, vindicative, penal,  
punitive, aggravated and retributory, but the expressions in  
common modern use to describe damages going beyond  
compensatory are exemplary and punitive damages. “Exemplary”  
was preferred by the House of Lords in Cassell & Co. Ltd. v  
Broome, but ‘punitive’ has also been used in many Canadian  
courts including the Supreme Court of Canada in H.L.Weiss  
Forwarding Ltd. v Omnus. The expression ‘aggravated damages’,  
though it has sometimes been used interchangeably with punitive  
or exemplary damages, has more frequently in recent times been  
contrasted with exemplary damages. In this contrasting sense,  
aggravated damages describes an award that aims at compensation,  
but takes full account of the intangible injuries, such as distress and  
humiliation, that may have been caused by the defendants insulting  
behaviour. The expressions vindictive, penal and retributory have  
dropped out of common use.  
[687] The Plaintiffs seek punitive damages in the range of $75,000 to address what they  
describe as the high-handed, malicious and reprehensible conduct of the Defendants in this  
instance. According to the Plaintiffs, the Defendants’ actions ought to attract the Court’s outrage.  
[688] The Plaintiffs cite and rely on the Supreme Court’s decision in Whiten v Pilot Insurance  
Co, 2002 SCC 18, as authority for the proposition that punitive damages are generally  
appropriate where a defendant’s misconduct is high-handed, malicious, arbitrary, or highly  
reprehensible. The conduct in question must depart from the ordinary standards of decent  
behavior to be recoverable: at paras 94-95. They also rely on a series of other cases, including  
Keays v Honda Canada Inc., 2008 SCC 39, Leclair v Leclair, 2019 ABQB 594, Sturrock v  
Ancona Petroleum Ltd (1990), 75 Alta LR (2nd) 216 (QB), and HL Weiss Forwarding Ltd v  
Omnus, [1976] 1 SCR 776.  
[689] In this instance, the Plaintiffs say that the Defendants concealed known deficiencies,  
including breaches of the Code and dangerous work. The Plaintiffs also refer to Metcalfe’s  
complete disregard for the careful review of Tru-Square’s scope of work that was required under  
Page: 117  
the circumstances. Further, the Plaintiffs refer to Metcalfe’s failure to offer any assistance to  
rectify the deficient work while, at the same time, filing a counterclaim for damages that  
Metcalfe knew Tru-Square was not entitled to receive. Finally, the Plaintiffs say that Metcalfe  
induced a breach of contract on the part of Tru-Square. According to the Plaintiffs, the combined  
effect of these factors reveals egregious conduct on the part of the Defendants that warrants an  
award of punitive damages.  
[690] In support of their claim for punitive damages in their Amended Statement of Claim, the  
Plaintiffs cited construction deficiencies, as well as the diversion of payments provided by the  
Plaintiffs to the construction of the Metcalfe’s West Highlands residence, a residence that was  
under construction at the same time as the Swanby residence. The Plaintiffs further allege that  
materials they paid for in relation to the construction of their home were used in the construction  
of the West Highlands residence. Based on these allegations, the Plaintiffs claim a beneficial  
interest in the West Highlands residence and seek a finding that the remaining proceeds from the  
sale of the West Highlands residence are subject to a remedial constructive trust.  
[691] While the pleadings filed by the Plaintiffs make a series of allegations relative to the  
West Highlands residence, there is simply insufficient evidence to allow me to make any  
findings in this regard. My consideration of the Plaintiffs’ claim for punitive damages does not,  
accordingly, take this unproven allegation into account.  
[692] The Defendants, on the other hand, seek to distinguish the within matter from what the  
Defendants say are far more serious circumstances in the cases cited by the Plaintiffs. In sum, the  
Defendants say that Metcalfe’s conduct falls far short of the type of conduct attracting punitive  
damages. The Defendants rely on the decision of Germain J in Field v Krisco, 2004 ABQB 391,  
in which the Court declined to award punitive damages.  
[693] The Defendants point to the complete absence of evidence that Metcalfe intended to harm  
the Swanbys in terms of them suffering any damage or loss. Rather, the Defendants underscore  
the fact that the relationship between the parties was generally without difficulty prior to the  
discovery of leaking windows on May 23, 2013. Thereafter, the Defendants say that Metcalfe  
continued to pay invoices submitted by the various trades in accordance with the parties’ revised  
agreement, notwithstanding the breakdown in the relationship. Metcalfe also provided a credit at  
the time of the final accounting when it was clear that his involvement in the project was over.  
[694] The Defendants also say that there is no evidence that Metcalfe ever lied to the Swanbys,  
notwithstanding Ms. Swanby’s unconfirmed allegation that McEwen told her that he had been  
asked by Metcalfe to conceal deficiencies in the framing of the residence.  
[695] Finally, the Defendants contend that the fact that the Plaintiffs refused to consider making  
use of the mediation services of the ANHWP should disentitle them to aggravated damages.  
There is no evidence that the Plaintiffs made any real effort to avail themselves of any relief that  
may have been available through that program.  
[696] The Supreme Court’s decision in Whiten involved a jury decision in a case where the  
plaintiff’s insurance company refused to pay a claim under a fire insurance policy. The insurance  
company forced an eight-week trial based on an allegation of arson notwithstanding the fact that  
the insurance company’s own expert acknowledged that there was no evidence whatsoever of  
arson. The jury awarded compensatory damages and punitive damages of $1 million. A majority  
Page: 118  
of the Ontario Court of Appeal reduced the punitive damages award to $100,000. On a further  
appeal to the Supreme Court, the jury award was restored.  
[697] Binnie J, for the majority, provided a comprehensive summary of the principles  
applicable to the awarding of punitive damages at para 94:  
To this end, not only should the pleadings of punitive damages be more rigorous  
in the future than in the past (see para.87 above), but it would be helpful if the  
trial judge’s charge to the jury included words to convey an understanding of the  
following points, even at the risk of some repetition for emphasis. (1) Punitive  
damages are very much the exception rather than the rule, (2) imposed only if  
there has been high-handed, malicious, arbitrary or highly reprehensible  
misconduct that departs to a marked degree from ordinary standards of decent  
behaviour. (3) Where they are awarded, punitive damages should be assessed in  
an amount reasonably proportionate to such factors as the harm caused, the degree  
of the misconduct, the relative vulnerability of the plaintiff and any advantage or  
profit gained by the defendant, (4) having regard to any other fines or penalties  
suffered by the defendant for the misconduct in question. (5) Punitive damages  
are generally given only where the misconduct would otherwise be unpunished or  
where other penalties are or are likely to be inadequate to achieve the objectives  
of retribution, deterrence and denunciation. (6) Their purpose is not to  
compensate the plaintiff, but (7) to give a defendant his or her just desert  
(retribution), to deter the defendant and others from similar misconduct in the  
future (deterrence), and to mark the community’s collective condemnation  
(denunciation) of what has happened. (8) Punitive damages are awarded only  
where compensatory damages, which to some extent are punitive, are insufficient  
to accomplish these objectives, and (9) they are given in an amount that is no  
greater than necessary to rationally accomplish their purpose. (10) While  
normally the state would be the recipient of any fine or penalty for misconduct,  
the plaintiff will keep punitive damages as a “windfall” in addition to  
compensatory damages. (11) Judges and juries in our system have usually found  
that moderate awards of punitive damages, which inevitably carry a stigma in the  
broader community, are generally sufficient.  
[698] The Supreme Court confirmed its decision in Whiten in Keays. At para 62 of Keays,  
Bastarache J, for the majority, noted that Whiten had settled the question of whether or not  
punitive damages require an actionable wrong. He stated:  
In Vorvis, McIntyre J., for the majority, held that punitive damages are  
recoverable provided the defendant’s conduct said to give rise to the claim is itself  
“an actionable wrong”. This position stood until 2002 when my colleague Binnie  
J., writing for the majority, dealt comprehensively with the issue of punitive  
damages in the context of the Whiten case. He specified that an “actionable  
wrong” within the Vorvis rule does not require an independent tort and that a  
breach of the contractual duty of good faith can qualify as an independent wrong.  
Binnie J. concluded, at para. 82 that “[a]n independent actional wrong is required,  
but it can be found in breach of a distinct and separate contractual provision or  
other duty such as a fiduciary obligation.”  
Page: 119  
[699] In Hill v Church of Scientology of Toronto, [1995] 2 SCR 1130, the Supreme Court  
discussed the type of conduct required to support an award of punitive damages. At p 1208, the  
Court held:  
Punitive damages may be awarded in situations where the defendant’s misconduct  
is so malicious, oppressive and high-handed that it offends the court’s sense of  
decency. Punitive damages bear no relation to what the plaintiff should receive by  
way of compensation. Their aim is not to compensate the plaintiff, but rather to  
punish the defendant. It is the means by which the jury or judge expresses its  
outrage at the egregious conduct of the defendant. They are in the nature of a fine  
which is meant to act as a deterrent to the defendant and to others from acting in  
this manner. It is important to emphasize that punitive damages should only be  
awarded in those circumstances where the combined award of general and  
aggravated damages would be insufficient to achieve the goal of punishment and  
deterrence.  
[700] The decision of Mason J in Herman v Graves, 1998 ABQB 471, also provides a  
comprehensive and helpful review of the law regarding the awarding of punitive or exemplary  
damages. At para 44, he explained that:  
Punishment is the primary purpose of an award of exemplary, or punitive,  
damages. Deterrence is also a purpose. An award of punitive damages follows  
when the conduct of the defendant is so egregious that the damages that should be  
awarded go beyond mere compensation of the plaintiff. Whether exemplary  
damages should be awarded is focused on the defendant. Such an award serves to  
deter not only the defendant but also others from committing such acts.  
[701] The Plaintiffs point to five factors which they say support the awarding of punitive  
damages in this instance:  
a) Breaching the contractual obligation to act in good faith;  
b) Concealing or attempting to cover up misconduct;  
c) Benefiting from fraudulent acts;  
d) Awareness that their conduct was wrong; and  
e) Inducing a breach of contract.  
[702] In terms of the appropriate quantum of damages under this head of damages, the  
Plaintiffs point to the awarding of $20,000 in punitive damages in Walker; $25,000 in Sturrock;  
$10,000 in Weiss; and $70,000 in LeClair, as informing the appropriate measure of punitive  
damages in this instance.  
[703] I am not persuaded that this is a proper case for awarding punitive damages. While I am  
dismayed by what I would characterize as Metcalfe’s casual and careless conduct in discharging  
his important responsibilities to the Plaintiffs in the construction of their retirement home, I am  
not persuaded that this conduct rises to the level described in the various cases referenced above.  
[704] The decision in Whiten makes it clear that punitive damages should only be awarded in  
exceptional cases where it is necessary to punish the offending behavior. The descriptors used in  
Whiten include “high-handed”, “malicious”, and “arbitrary or highly reprehensible conduct”.  
The decision in Hill includes similar language, but also “oppressive” and “offends the court’s  
Page: 120  
sense of decency.” Given that punitive damages focus on deterrence, as opposed to  
compensation, I take Whiten to signal the need for judicial restraint.  
[705] The Plaintiffs’ allegations with respect to Metcalfe’s conduct are serious. I share the view  
that his frequent absences from the job site rendered him an ineffective supervisor of a large  
project involving multiple sub-contractors. It seems clear that he was not engaged in the overall  
coordination and oversight of the construction anywhere near to the extent dictated by the  
circumstances. I further find that his refusal to offer any form of assistance, or to accept any  
responsibility for the leaking windows, reflects very poorly on his professionalism. On a human  
level, it demonstrated a somewhat shocking lack of compassion for the plight of his clients. His  
stubborn refusal to come to the aid of the Plaintiffs when the completion of their home was  
within sight is hardly a high-water mark at the end of a long career in custom home building.  
[706] I accept the Plaintiffs contention that Metcalfe concealed some known deficiencies.  
Specifically, I accept Ms. Swanby’s evidence regarding her conversation with McEwen in which  
the framer reported that Metcalfe had told him not to tell the Plaintiffs about the framing of the  
residence being off. Earlier in these reasons, I also made findings regarding Metcalfe’s  
knowledge of other deficiencies that he failed to address or bring to the attention of the Plaintiffs.  
I refer specifically to the following:  
a) Metcalfe’s awareness that McEwen used non-pressure treated lumber next to the  
foundation. Metcalfe was aware that this was a Code violation, yet failed to address  
the matter or bring the issue to the attention of the Plaintiffs;  
b) Metcalfe’s awareness that the sheathing in the main floor bedroom did not extend to  
the floor and, as such, represented a Code violation. Metcalfe failed to direct McEwen  
to correct the issue or bring the issue to the attention of the Plaintiffs;  
c) Metcalfe’s awareness that he observed some sagging of the header beam for the rear  
entry-level doors. Metcalfe failed to determine the cause of the deflection or to  
correct the situation. He also failed to bring the issue to the attention of the Plaintiffs;  
d) Metcalfe’s awareness that the deck drainage system was inadequate. He failed to  
disclose the scope of this issue with the Plaintiffs other than through his subsequent  
disclaimer of responsibility for a drainage system that was 100% effective;  
e) Metcalfe’s awareness of a soil erosion issue at the rear of the residence that he  
believed was responsible for at least one of the deck piles being less than 4 feet deep.  
I do not accept his evidence that he brought to Ms. Swanby’s attention the need to  
construct a retaining wall to address this soil erosion issue;  
f) Metcalfe’s awareness that the soffits leaked. Metcalfe failed to determine the cause of  
the problem or to address the issues. He also failed to bring the matter to the attention  
of the Plaintiffs.  
[707] I do not accept the Plaintiffs’ contention that Metcalfe in any way concealed any  
problems relating to the foundation. As McEwen stated in his evidence, the fact that a two-to-  
three-foot section of the exterior wall overhung the foundation by two inches was “very  
obvious”. On the evidence, the Plaintiffs asked questions about this situation and received  
assurances from Metcalfe, and possibly McEwen, that this situation could be addressed during  
the balance of the construction process.  
Page: 121  
[708] I am very suspicious that Metcalfe was also aware of, but concealed from the Plaintiffs,  
the leaking windows. However, I am not satisfied that this was the case and, as such, I am not  
prepared to make such a finding in these circumstances.  
[709] I am, however, satisfied that Metcalfe was largely unaware of most, if not all, of the other  
deficiencies that were ultimately revealed through the work of Bjornson, Matthews and Juniper.  
As a result of his frequent absences and his overall distracted state, I find that Metcalfe was  
simply not engaged in the details of the project other than on a somewhat selective basis. While  
the evidence points to the fact that he was personally involved in a number of specific tasks  
during the project, it seems clear that he placed significant reliance on his trades to complete  
their work without the benefit of his oversight. He also relied on Carm, inappropriately in my  
view, to help fill the leadership vacuum that he created.  
[710] It is important to distinguish between concealment and a lack of awareness. Metcalfe  
should, of course, have been aware of many of the deficiencies that were ultimately revealed.  
However, I am satisfied that he was not. His lack of awareness in circumstances in which he  
clearly should have been aware obviously has legal consequences. However, lack of awareness  
cannot be equated with concealment in these circumstances.  
[711] While I am very troubled by Metcalfe’s request to McEwen not to inform the Plaintiffs  
about the framing issues, I find that this comment, as well as the other instances referred to  
above that do involve concealment, must be viewed in context. As previously indicated, I find  
that Metcalfe was distracted, even disinterested in this construction project. He was at the end of  
a long career in housebuilding and initially turned down the job. While none of this undermines  
my other findings regarding breach of contract and negligence, it informs my characterization of  
Metcalfe’s conduct.  
[712] The Plaintiffs also contend that Metcalfe induced Tru-Square’s breach of contract and  
that this is a factor to be considered in determining whether to award punitive damages. As  
outlined earlier in these reasons, relying on the decision of Slatter JA in Elite Homes, I do not  
believe that this allegation has been established in these circumstances  
[713] Finally, the Plaintiffs rely on the fact that the Defendants’ decision to pursue a Counter  
Claim in this instance, allegedly with full knowledge that there was no legitimate basis for this  
claim. In my view, there is no merit to this argument. Indeed, the damage calculation set out  
earlier in these reasons reveals my acceptance of the Defendants’ contention that they are owed a  
substantial sum of money by the Plaintiffs under the terms of the contract.  
[714] What seems clear to me from this most unfortunate situation is that Metcalfe really did  
not want to undertake this project given his forthcoming planned retirement. He took on the  
construction of the Swanby residence with some reluctance and in the seriously mistaken belief  
that he could manage the project from a distance while he pursued his other planned activities.  
He did not provide proper supervision to the trades that were involved in the construction  
project. As a consequence, he was largely unaware of the quality of the work that was  
undertaken by the trades in circumstances that clearly called for his active involvement and  
oversight. He was, after all, the general contractor, a role that required him to ensure that all  
those involved under his supervision met the standards expected of a custom homebuilder.  
[715] Overall, I strongly disapprove of Metcalfe’s overall execution of his role as the general  
contractor of this construction project. However reluctant he may have been to take on this role,  
Page: 122  
once he accepted the work, he had a duty to ensure that it was carried out in a competent fashion  
and in accordance with the standards associated with a custom homebuilder. He clearly failed to  
meet this standard.  
[716] I accept the Defendants’ contention that Metcalfe never intended to harm the Plaintiffs. In  
these circumstances, I am not prepared to find any malice or bad motive in any of the many  
shortcomings that are fairly attributed to him.  
[717] For the foregoing reasons, I decline to award punitive damages in this case. In my view,  
the conduct of the Defendants, particularly Metcalfe, does not rise to the level of behavior that  
warrants an award of punitive damages.  
E. Aggravated Damages  
[718] In their pleadings, the Plaintiffs also advance a claim for aggravated damages. At para 36  
of their Amended Statement of Claim, they state:  
The conduct of the Defendants as described in the Statement of Claim has caused  
the Plaintiffs to suffer emotional upset and mental distress. It has interfered with  
their family life and work and recreational activities, and diminished their quality  
of life. The Plaintiffs have incurred financial losses and increased costs as a result  
of the breach of contract. The Plaintiffs are entitled to aggravated damages.  
[719] In Elkow v Sana, 2020 ABCA 350, the Court of Appeal addressed the matter of  
aggravated damages in the context of an action brought for defamation. At para 16, the Court,  
citing Hill v Church of Scientology of Toronto, [1995] 2 SCR 1130, confirmed that “[G]eneral  
damages and aggravated damages are compensatory, and are intended to address the harm  
suffered by the plaintiff. Punitive damages are designed to punish the defendants and deter  
defamatory conduct.” The Court elaborated (at para 30) as follows:  
Aggravated damages are a second category of compensatory damages. The award  
of general damages is intended to compensate the plaintiff for the injury to her  
reputation, and for other injuries she suffered. Aggravated damages, in order to be  
justified, must represent some greater injury to the plaintiff, not captured by the  
award of general damages. They are justified “where the defendants conduct has  
been particularly high-handed or oppressive, thereby increasing the plaintiff’s  
humiliation and anxiety arising from the libelous statement”, or  
Where the defendant is guilty of insulting or oppressive conduct  
which increases the mental distress – – the humiliation,  
indignation, anxiety, grief, fear and the like – – suffered by the  
plaintiff as a result of being defamed, the plaintiff may be entitled  
to what has come to be known as “aggravated damages”.  
Hill at para 188, quoting Walker v CFTO Ltd. (1987), 1987 CanLII 126 (ON  
CA), 59 OR (2d) 104 at p 111 (CA), emphasis added.  
[720] Similarly, in Vorvis, McIntyre J emphasized that “[A]ggravated damages are  
compensatory in nature and may only be awarded for that purpose”: at p 1086.  
 
Page: 123  
[721] The Plaintiffs provided no oral or written submissions dealing with the applicability of  
aggravated damages in this instance. Rather, the thrust of their submissions focused on punitive  
damages.  
[722] In my view, this is not a situation where it would be appropriate to award aggravated  
damages to the Plaintiffs.  
F. Contributory Negligence  
[723] If the Defendants are found liable for any damages resulting from the leaking windows,  
they maintain that a significant portion of the damages must be allocated to the Plaintiffs.  
According to the Defendants, the Plaintiffs failed to heed the caution provided to them by  
Metcalfe and McEwen, either directly or indirectly through Carm, their designer. According to  
the Defendants, the validity of this caution was confirmed by Bjornson, Juniper, McEwen and  
Lawrence.  
[724] The Defendants plead and rely on the Contributory Negligence Act, RSA 2000, c C-27,  
which directs apportionment of liability for damage or loss caused by two or more persons.  
Section 1(1) of the Act provides as follows:  
When by fault of 2 or more persons damage is caused to one or more of them, the  
liability to make good the damage or loss is in proportion to the degree in which  
each person was at fault but if, having regard to all the circumstances of the case,  
it is not possible to establish different degrees of fault, the liability shall be  
apportioned equally.  
[725] The Plaintiffs, on the other hand, maintain that Metcalfe and Tru-Square are entirely  
responsible for the defective installation of the windows and liable for all remediation costs  
associated with this aspect of the project.  
[726] The Defendants maintain that the recessed windows were not contemplated in the  
contract and came about because of a change proposed by Carm and subsequently approved by  
the Plaintiffs. Further in his Invoice #118 (C-11), Metcalfe confirmed his earlier caution that any  
warranty with respect to the windows was voided. The Defendants say that Metcalfe and Tru-  
Square cannot be found liable for the leaking windows or for any of the resulting damage  
sustained, including the significant costs associated with the demolition work and the installation  
of new windows. They point out that Carm, who was hired by the Swanbys, designed the  
recessed window openings.  
[727] The Defendants rely on Intrawest Corp v Hart, 2002 BCSC 234, at para 47, wherein  
Melnick J, quoting Glanville Williams, states as follows:  
Cases where one party has been found “contributorily negligent” for the breach of  
contract of another are rare. That it is an available defence, however, was  
suggested by Glanville Williams in his 1951 text, Joint Torts and Contributory  
Negligence, at p 214:  
Usually the defendant in an action for damages for breach of  
contract cannot successfully set up the plaintiff’s contributory  
negligence, for the reason that the plaintiff is usually entitled to  
assume that the defendant will act carefully in carrying out his  
undertaking. Culpable carelessness is not usually to be ascribed to  
 
Page: 124  
the plaintiff merely because he has omitted to take precautions  
against breach. Thus, it seems that a railway passenger (at least in  
the absence of a warning notice) is entitled to assume that the  
carriage door has a secure fastening, on that assumption to lean  
against it.  
But there are cases where the plaintiff may be part author of his  
own damage, and where in consequence the defendant ought to be  
relieved of responsibility in whole or in part. If a passenger in a  
railway carriage knows that the door is defective and yet leans  
upon it and falls out, it is difficult to see why the defence of  
contributory negligence should not be available, and this whether  
the action be framed in contract or tort. So also if, although he does  
not know it to be defective, he leans very heavily upon it.  
[728] In Linden, Canadian Tort Law, 7th ed, Butterworths, the author deals with the operation  
of apportionment legislation, namely the various provincial contributory negligence statutes. At  
p 474, he states:  
Apportionment will be employed when the fault of two persons combine to cause  
a loss, that is, when there is concurrent negligence of two individuals. There is no  
apportionment between a negligent and a non-negligent cause. The Canadian  
practice is to look at the “causative conduct in terms of relative or comparative  
blameworthiness or culpability”. It has recently been repeated that the job of the  
court in apportioning damages is to “assess the respective blameworthiness”, not  
the “extent to which the loss may be said to have been caused by the conduct of  
each.”  
[729] The referenced passages contained in this extract from Linden are from the Supreme  
Court’s decision in Athey v Leonati, [1996] 3 SCR 458.  
[730] In this instance, the Defendant rely on the Plaintiffsdecision to proceed with the  
recessed windows notwithstanding the caution that Ms. Swanby is alleged to have received from  
Metcalfe and McEwen and, indirectly, via Carm. I have serious reservations as to whether such  
conduct, even if established, would be sufficient to establish the degree of fault, causative  
conduct or culpable carelessness required to attribute some portion of the responsibility for the  
resulting damage to the Plaintiffs. I would note that the Court in Hart found contributory  
negligence on the part of the plaintiffs based on non-disclosure of a prior expert report  
commissioned by the plaintiffs and, more generally, the non-disclosure of the extent of the ice  
damming problem impacting the condominium. In other words, the court found some degree of  
fault on the part of the plaintiffs that justified imposing on them some degree of blameworthiness  
for the losses sustained.  
[731] It is, however, unnecessary for me to decide this issue in view of my earlier findings  
regarding the timeliness and effect of Metcalfe’s purported disclaimer of responsibility after he  
installed the recessed windows.  
[732] In the result, I find that the Defendants have failed to establish that the Plaintiffs were  
contributorily negligent for the damages sustained as a result of the leaking windows.  
Page: 125  
G. Mitigation of Damages  
[733] The Defendants maintain that the Plaintiffs failed to mitigate their damages in this  
instance by not making a claim through the ANHWP, not proceeding with the remediation work  
in a timely fashion, not obtaining competitive quotes for the remediation work, and not requiring  
a detailed plan from Juniper for the execution of the detailed scope of work recommended by  
Matthews and Bjornson. According to the Defendants, the Plaintiffs had the funding to proceed  
promptly with the remediation work given that they did not pay Tru Square the balance of the  
budgeted amount for the construction of the residence.  
[734] The Plaintiffs maintain, contrary to the assertions of the Defendant, that the steps they  
took to mitigate their damages by addressing the issues with the initial exterior stone-cladding  
were appropriate under all of the circumstance. They rely on Winnipeg Condominium Corp No  
36 v Bird Construction Co, [1955] 1 SCR 85, as well as the decision of Master Prowse in the  
instant matter wherein he denied summary dismissal of the personal claims against Metcalfe:  
Swanby v Tru-Square Homes Ltd, 2016 ABQB 731.  
[735] The Plaintiffs acknowledge that they were required to take reasonable steps to mitigate  
the losses caused by the actions of the Defendants. They also acknowledge that they have the  
burden of establishing that they acted reasonably in the expenditure of funds to effect  
remediation in this instance.  
[736] The issue of mitigation was addressed in Vermillion. Citing British Westinghouse  
Electric & Manufacturing Co v Underground Electric Railways Co of London, [1912] AC 673  
(HL), the Court held at para 184:  
In that case, Viscount Haldane held that the fundamental basis of damage  
assessment, being compensation for pecuniary loss naturally flowing from the  
breach, is qualified by the second basis, whereby the plaintiff is required to take  
all reasonable steps to mitigate the loss consequential on the breach. Waddams  
[The Law of Damages] further states at 15.290:  
Often the plaintiff incurs expenses in attempting to mitigate loss. If  
the mitigation is successful and a larger loss is avoided by  
expenditure of a lesser sum, the plaintiff is entitled to recover the  
lesser sum. The plaintiff will in such a case have reduced the loss  
(to the amount of the lesser sum) but will not have avoided all loss.  
It follows that if the plaintiff incurs expense in a reasonable but  
unsuccessful attempt to mitigate, the defendant will be liable for  
the expense even though, in the result, liability is greater than it  
would have been if the plaintiff had done nothing...[citations  
omitted].  
[737] Vermillion also refers to the Court of Appeal’s decision in Nu-West Homes Ltd v  
Thunderbird Petroleum Ltd, [1975] 59 DLR (3d) 292 (SC App Div), in which Moir JA  
addressed the required conduct of an aggrieved party in seeking to mitigate itsloss. He stated, at  
p 308:  
In my view, one should be careful not to weigh in too fine a set of balances the  
conduct of the aggrieved party. The wrongdoer is entitled to expect the aggrieved  
party to act reasonably. He is not entitled to have him act perfectly. In my view  
 
Page: 126  
the proper test to be applied is that set out by Lord McMillan in Banco de  
Portugal v Waterlow & Sons Ltd, [1932] AC 452 at p 506, where he states:  
Where the sufferer from a breach of contract finds himself in  
consequence of that breach placed in a position of embarrassment a  
measure which he may be driven to adopt in order to extricate  
himself ought not to be weighed in nice scales at the incidence of  
the party whose breach of contract has occasion to difficulty. It is  
often easy after an emergency has passed to criticize the steps  
which have been taken to meet it, but such criticism does not come  
well from those who have themselves created the emergency. The  
law is satisfied if the party placed in a difficult situation by reason  
of the breach of a duty owed to him has acted reasonably in the  
adoption of remedial measures, and he will not be held disentitled  
to recover the cost of such measures merely because the party in  
breach can suggest that other measures less burdensome to him  
might have been taken.  
[738] Vermillion, citing the decision of Laskin CJC in Michaels v Red Deer College, [1976] 2  
SCR 324, confirms that a wrongdoer bears the onus of establishing that the aggrieved party has  
not taken reasonable steps to mitigate damages. In Michaels, Chief Justice Laskin explained the  
so-called “duty to mitigate” in the following terms at p 330-31:  
… The parameters of loss are governed by legal principle. The primary ruling in  
breach of contract cases, that a wronged plaintiff is entitled to be put in as good a  
position as he would have been in if there had been proper performance by the  
defendant, is subject to the qualification that the defendant cannot be called upon  
to pay for avoidable losses which would result in an increase in the quantum of  
damages payable to the plaintiff. The reference in the case law to a “duty” to  
mitigate should be understood in this sense.  
In short, a wronged plaintiff is entitled to recover damages for the losses he has  
suffered but the extent of those losses may depend on whether he is taken  
reasonable steps to avoid their unreasonable accumulation.  
[739] The Plaintiffs maintain that they acted reasonably in their response to the leaking  
windows and in the ensuing investigation and ultimate remediation of the construction  
deficiencies that were revealed. Further, they say that they should not be disentitled to their  
reasonable costs on the basis of the Defendants’ assertion that less costly means may have been  
available.  
[740] I am satisfied that the Plaintiffs acted reasonably in quickly retaining Snyder to  
investigate the cause of the leaking windows as a first step in addressing the underlying problem.  
Likewise, I find that retaining Juniper and then a building envelope engineer, Bjornson, were  
necessary steps in the Plaintiffs’ investigation of the scope of the construction deficiencies that  
would need to be addressed. Bjornson, in turn, recommended that the Swanbys hire a structural  
engineer to further investigate deficiencies that she identified during the course of her review.  
This led to the hiring of Matthews, one of four names provided to the Swanbys. Given the  
Defendants’ refusal to address the leaking windows and, indeed, their abandonment of the  
project, I find that the Plaintiffs required professional guidance and advice in conducting the  
Page: 127  
required examination of the construction of their home. As such, I accept the Plaintiffs’  
contention that Bjornson and Matthews were critical to the overall investigative and remediation  
requirements relative to the Swanbys home.  
[741] The Defendants elected not to retain an expert with the necessary qualifications to  
challenge or contest any of the expert opinions offered by the Plaintiffs’ engineers, Bjornson and  
Matthews. Whether this was a decision taken for tactical or other reasons is unclear. Regardless,  
it left the evidence of Bjornson and Matthews largely unchallenged. Given Hamman’s lack of  
qualifications even remotely approximating those of either Bjornson or Matthews, he was not in  
a position to be able to attack any of their opinion evidence falling within their respective areas  
of expertise.  
[742] The Defendants do not question the need for the Plaintiffs to engage a contractor to assist  
the consulting engineers with the investigation of construction deficiencies and then to effect the  
recommended remediation required under the circumstances. Rather, they question the Plaintiffs’  
failure to initiate a competitive process before hiring the various experts and Juniper. They also  
question Juniper’s work method, notably his alleged failure to develop and follow a  
comprehensive work plan based on the recommendations of Bjornson and Matthews.  
[743] The Defendants’ expressions of concern relating to the Plaintiffs’ “process” in terms of  
citing the absence of a competitive process and a comprehensive work plan seem to be somewhat  
at odds with their other concerns relating to the Plaintiffs’ alleged delay in completing the  
investigative and remediation processes. It seems clear that both additional steps would have  
required additional time and would doubtless have delayed the entire process.  
[744] As previously indicated, I find no merit in the Defendants’ assertion that some form of  
competitive process was required before the Plaintiffs proceeded with the remediation work. In  
terms of the work plan, I am satisfied that a careful review of the various price quotes that  
Juniper provided to the Plaintiffs include an evolving understanding of the scope of the work  
required to correct the various construction deficiencies. These written quotes are dated August  
8, 2013, Exhibit 1-F-3; October 22, 2013 (Proposed Remediation Scope), Exhibit 1-F-6; January  
21, 2014, Exhibit 1-F-9; March 23, 2015 (Progress Report), Exhibit 1-F-25. In my view, these  
documents provide a clear picture of Juniper’s proposed scope of work relative to this property.  
[745] In raising a concern relative to the alleged lack of a formal work plan, the Defendants fail  
to articulate any underlying basis for such a concern. As such, the Defendants fail to identify  
how the absence of such a work plan impacts the reasonableness of the Plaintiffs’ conduct as  
regards mitigation of damages. In the absence of some evidence that the conduct or execution of  
Juniper’s work was adversely impacted by the absence of a formal work plan, I am not prepared  
to attach much weight to this submission on the part of the Defendants. I would simply add that  
the reasonableness and necessity of the various steps taken by Juniper during the remediation  
process were not successfully challenged during cross-examination.  
[746] In any event, I accept that the Plaintiffs acted reasonably in retaining Juniper and TGC to  
undertake this work. Juniper had significant related construction experience, including  
experience in remediation work. Further, both Bjornson and Matthews supported his  
involvement in the project. Both engineers provided Juniper with direction and guidance  
throughout the investigative and repair processes.  
Page: 128  
[747] In reaching my conclusions in this regard, I take into consideration the evidence of  
Kraychy regarding the prevailing circumstances in the construction industry at the time. Kraychy  
described the required remediation work as “messy” and that the industry was very busy at the  
time these events were unfolding. He went so far as to suggest that he would have not bid on this  
work given the ready availability of easier work on new construction projects.  
[748] There is no dispute that the Plaintiffs were scheduled to take possession of their home in  
May or June of 2013. In fact, they took possession in August 2015, a delay of approximately 27  
months.  
[749] The Defendants allege that the Plaintiffs did not pursue the remediation process in a  
timely fashion, suggesting that the failure to pay Tru-Square’s outstanding invoices would have  
left the Swanbys with the available resources to execute any required remediation process at an  
earlier date. Of note, the Defendants offer no timeline that they suggest would have been  
reasonable, save for Hamman’s “schedule” that contemplated the completion of the remediation  
work over the span of 3-4 months.  
[750] The Plaintiffs strongly resist this contention, suggesting that the scope of the remediation  
work was a shifting target, continuing to expand as they worked their way through the  
investigative stage of the process. New issues were continually emerging that required attention.  
Further, the Plaintiffs suggest that the time expended was eminently reasonable given the scope  
and magnitude of the task that confronted them. As regards the Hamman “schedule”, the  
Plaintiffs say that it lacks any air of reality in a real-world setting. I agree.  
[751] I am satisfied that Hamman never produced an actual work “schedule”. Rather he  
estimated the number of hours that would be required to complete the remediation work. He  
acknowledged that this was an estimate of man-hours only and did not account for how those  
hours would need to be scheduled over real time. In my view, Hamman’s notional “schedule” is  
of very limited, if any, assistance in addressing the issue of timeliness. First, the “schedule” does  
not account for the impact of weather conditions, notably Alberta’s typical winter temperatures.  
Likewise, it does not account for the time requirements associated with obtaining permits and  
scheduling building inspections. Further, the sequencing of tasks would not have been a straight-  
line exercise in that some tasks would have required the completion of other tasks before they  
could proceed. Further, this “schedule” did not account for the time requirements associated with  
the investigation of suspected construction deficiencies, notably through dismantling and testing  
otherwise completed building components.  
[752] I accept the Plaintiffs’ explanation that the remediation exercise was a complex process  
that involved the destruction of existing “finished” construction, the examination and assessment  
of identified deficiencies, the acquisition of replacement items, and the actual reconstruction of  
the affected component. The impact of weather, the need to schedule tradespeople, inspectors,  
and site visits by the Defendants, as well as the requirement to sequence the work in an orderly  
fashion, all took time. Likewise, the Swanbys faced cash-flow issues as a result of the need to  
hire and pay experts and lawyers, finance remediation work, and cover the costs of maintaining  
two homes over an extended period of time.  
[753] I also accept Juniper’s evidence that this was not the only project that they were working  
on at the time. TGC’s work on this project had to be juggled with work on another large custom  
build home in Linden, as well as remediation work on two flooded homes in High River. TGC  
was also involved in remediating foundation damage to the Swanby’s other home in Carstairs.  
Page: 129  
[754] While 27 months may appear at first blush to be an inordinate amount of time, I am  
satisfied that the Plaintiffs pursued this process aggressively from the outset. As previously  
discussed, Ms. Swanby discovered that the windows were leaking on May 23, 2013. Snyder  
visited the site to conduct an investigation shortly thereafter on May 29, 2013. Juniper and TGC  
were hired in July or August 2013. Bjornson was retained and made her first visit to the site on  
July 10, 2013, at which time she conducted flood testing on some of the leaking windows.  
Matthews made his first visit to the residence in September 2013.  
[755] All of the key members of the Plaintiffs’ response team were in place by September  
2013, some 4 months after the discovery of the leaking windows. Actual remediation work  
commenced in July or August 2014. In my view, the Plaintiffs acted promptly, even swiftly,  
once they became aware of the leaking windows. The remaining portion of the approximately 27  
months until the Plaintiffs took possession of the home was simply the time required to complete  
a complex, multi-stage process involving multiple participants.  
[756] Having carefully considered all of the surrounding circumstances, I find that the  
Defendants have failed to convince me that the Plaintiffs did not prosecute this remediation plan  
in a timely fashion.  
H. Improvement  
[757] The Defendants maintain that some amount should be deduced from any damages  
awarded to the Plaintiffs on account of the principle of improvement. The Defendants advance  
several arguments in this regard. First, it is alleged that the evidence of Juniper, the person  
responsible for the remediation work, lacked detail to determine the difference between what Tru  
Square had been hired to build, and the house that was ultimately completed by Juniper.  
[758] The Defendants specifically point to the fact that the kitchen floor designed by Matthews  
(and built by Juniper) represents a significant improvement over the floor that was contracted to  
be built by Tru-Square.  
[759] Further, according to the Defendants, Juniper gave evidence that it was cheaper to install  
Hardie Board as opposed to redoing the stucco that had been removed from the exterior of the  
residence. The Defendants maintain that this has not been proven due to the lack of detail in  
Juniper’s invoices. Further, the Defendants point to the fact that Hamman testified that Hardie  
board is generally 30% more expensive than stucco.  
[760] Finally, the Defendants suggest that the reframing of the window and door opening  
represented an improvement over the original recessed opening.  
[761] I am not persuaded that there is any merit to the Defendants’ arguments relating to  
improvements alleged to have been made to the residence ultimately completed by Juniper, as  
opposed to the residence the Defendants were hired to build. First, I reject the Defendants’  
contention that they were unable to determine whether there were differences between the home  
contracted for and the home ultimately delivered to the Plaintiffs. Through the litigation process,  
culminating in a 29-day trial, the Defendants had ample opportunity through document  
production, questioning, the exchange and review of numerous expert reports, site inspections,  
and the examination of the Plaintiffs’ witnesses produced at trial, to fully ascertain the state of  
the residence as ultimately remediated. Furthermore, I do not accept the suggestion that the  
evidence of Juniper lacked the level of detail required to permit the Defendants to complete this  
assessment.  
 
Page: 130  
[762] The Defendants’ suggestions that the kitchen floor and the reframing of the window and  
door openings somehow resulted in an overall improvement are lacking in specifics. As regards  
the kitchen floor, I am satisfied that the remediated kitchen floor was “improved” only in the  
sense that the construction deficiencies were addressed. As discussed earlier in these reasons, the  
Defendants failed to install the robust floor system set out in the Innographic design drawings to  
accommodate the extra load requirements of the kitchen design. In my view, correcting this  
construction deficiency to give the Plaintiffs what they had contracted for from the outset, did  
not result in any “improvement”.  
[763] With respect to the use of Hardie Board instead of stucco, there was conflicting evidence  
as between Juniper and Hamman. I prefer the evidence of Juniper that, in this instance, it was  
cheaper to install the Hardie Board than to reapply the stucco to the exterior of the residence.  
[764] Finally, as regards the alleged “improvement” with the reframing of the window and door  
openings to a flush mounting, as opposed to a recessed mounting, the Defendants did not lead  
any evidence that one form of installation represents an “improvementover the other.  
[765] To conclude, I am not persuaded that any deduction should be made to the damage award  
otherwise applicable on account of “improvement”.  
VII. Counterclaim  
[766] The Defendants’ Counterclaim is based on the unpaid invoices they submitted to the  
Plaintiffs relative to the construction of the residence, including the fourth and final contract  
payments, invoices relating to “extras” and upgrades, and invoices paid to third parties on behalf  
of the Plaintiffs. A number of these invoices also include a series of credits from the Defendants  
to the Plaintiffs.  
[767] I am satisfied that the entirety of the Defendants’ counterclaim has been considered and  
addressed in my earlier damage calculation.  
VIII.  
Conclusion  
[768] For the foregoing reasons, I find the Defendant Tru-Square Homes Ltd. breached the  
contract with the Plaintiffs dated August 22, 2011, and as varied in the fall of 2011, and again in  
May 2012. I also find the Defendants jointly and severally liable in tort for breach of the duty of  
care owed to the Plaintiffs in the construction of the Plaintiffs’ residence.  
[769] The Plaintiffs are entitled to damages in the sum of $403,247.83.  
IX. Costs  
[770] The Plaintiffs are entitled to their costs, including the recovery of disbursements for  
expert fees in accordance with Rule 10.41(2)(e), and a second counsel fee in accordance with  
11(2) and (4) of Schedule C of the Rules of Court. If the parties are unable to reach an agreement  
as to the quantum of costs, they may appear before the Review Officer to seek a ruling on the  
Plaintiffs’ Bill of Costs.  
     
Page: 131  
X. Pre-Judgment Interest  
[771] The Plaintiffs seek pre-judgment interest on the damages awarded in this instance from  
the date of the causes of action. According to the Plaintiffs, the cause of action arose on  
September 30, 2011, the date of the first invoice submitted by the Defendants upon completion  
of the foundation.  
[772] In my view, the Plaintiffs are entitled to pre-judgment interest from the date that Ms.  
Swanby discovered, and brought to Metcalfe’s attention, the leaking windows. This date was  
May 23, 2013.  
Heard on April 8-18, 2019, and continued April 23-25, 2019, May 8-17, 2019, October 15-18,  
2019, and November 27-28, 2019.  
Dated at the City of Calgary, Alberta this 18th day of March, 2022.  
M. David Gates  
J.C.Q.B.A.  
Appearances:  
C. Babiuk & B. Frenken  
for the Plaintiffs (Defendants by Counterclaim)  
M. Keyes & K. Lavery  
For the Defendants (Plaintiffs by Counterclaim)  
 


© 2022 IncJournal is not affiliated with or endorsed by the U.S. Securities and Exchange Commission