IN THE SUPREME COURT OF BRITISH COLUMBIA  
Citation:  
MDG Contracting Services Inc. v. Mount  
Polley Mining Corporation,  
2022 BCSC 1078  
Date: 20220628  
Docket: S2110069  
Registry: Vancouver  
Between:  
And  
MDG Contracting Services Inc.  
Mount Polley Mining Corporation  
Petitioner  
Respondent  
Before: The Honourable Justice E. McDonald  
Reasons for Judgment  
Counsel for the Petitioner:  
D.G. Volk  
S. John  
Counsel for the Respondent:  
B.J. Greenberg, Q.C.  
O.L. Leung  
Place and Date of Hearing:  
Place and Date of Judgment:  
Vancouver, B.C.  
February 15-16, 2022  
Vancouver, B.C.  
June 28, 2022  
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 2  
Table of Contents  
INTRODUCTION ....................................................................................................... 3  
THE ALLEGED ERRORS ......................................................................................... 4  
ISSUES...................................................................................................................... 5  
FACTUAL BACKGROUND....................................................................................... 5  
The Background in the Award ................................................................................ 5  
The Dispute............................................................................................................ 8  
The Award.............................................................................................................. 9  
ANALYSIS............................................................................................................... 12  
Has MDG met the statutory requirements for granting leave to appeal?.............. 12  
The threshold requirement identification of a question of law ........................ 13  
The failure to find Mount Polley liable to MDG for negligent misrepresentation 16  
The failure to find that Mount Polley breached its good faith contractual duty of  
honest performance.......................................................................................... 21  
Should the Award be set aside because MDG has shown that the Arbitrator  
committed an arbitral error? ................................................................................. 22  
DISPOSITION.......................................................................................................... 26  
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 3  
Introduction  
[1]  
On November 29, 2017, the petitioner, MDG Contracting Services Inc.  
(“MDG”), and the respondent, Mount Polley Mining Corporation (“Mount Polley”),  
entered into a contract for MDG to provide dredging work to remove tailings from an  
area within the Mount Polley Mine (the “Agreement”). The Agreement as a result of  
Mount Polley issuing a request for proposals and MDG responding to the request  
with a proposal.  
[2]  
MDG’s work removing tailings did not go as planned and a dispute arose  
concerning the Agreement. The work required by the Agreement was not  
completed. Mount Polley terminated the Agreement for cause. MDG believes that  
the problems giving rise to the dispute were caused mainly by Mount Polley’s  
negligent representations, coupled with its wrongful failure to disclose relevant  
information to MDG about the nature of the tailings to be dredged.  
[3]  
MDG commenced a notice of civil claim (the “Claim”) alleging that Mount  
Polley breached and wrongfully terminated the Agreement and it made actionable  
misrepresentations regarding the tailings. Mount Polley counterclaimed against  
MDG and alleged that MDG breached the Agreement on numerous grounds,  
including by refusing to complete the work.  
[4]  
MDG also issued a notice of arbitration. The parties agreed to use their  
Supreme Court pleadings as their arbitration pleadings and they appointed  
Mr. Murray Clemens, Q.C., as the sole arbitrator (the “Arbitrator”).  
[5]  
In 2021, the parties attended a lengthy arbitration hearing that they agreed  
would address questions of liability only. That initial hearing resulted in a partial final  
award of the Arbitrator dated October 20, 2021 (the “Award”). The outcome was that  
MDG’s claim alleging liability on the part of Mount Polley was wholly unsuccessful,  
while Mount Polley’s counterclaim against MDG was wholly successful.  
[6]  
In a matter before me, MDG seeks leave to appeal from the Award pursuant  
to s. 31 of the Arbitration Act, R.S.B.C. 1996, c. 55 [Act]. MDG also seeks, pursuant  
 
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 4  
to s. 30 of the Act, to set aside the Award on the basis that the Arbitrator made an  
arbitral error by failing to observe the rules of natural justice (the “Amended  
Petition”).  
The Alleged Errors  
[7]  
In seeking leave to appeal, MDG submits that the Arbitrator erred on  
numerous grounds. The Amended Petition sets out the following alleged errors of  
law:  
i.  
failing to find Mount Polley liable for negligent misrepresentation by  
misapplying the duty of care analysis, misapplying the law regarding when an  
omission may constitute misrepresentation, and, failing to consider the  
element of reliance: Amended Petition, Part 1, para. 1(a);  
ii.  
failing to find Mount Polley liable for negligent misrepresentation by omission  
by failing to consider the elements of MDG’s negligent misrepresentation  
claim: Amended Petition, Part 1, para. 1(b);  
iii.  
failing to find Mount Polley liable for breach of its good faith contractual duty  
of honest performance by misapplying the test for breach of the duty of  
honest performance and failing to consider Mount Polley’s failure to disclose  
material information: Amended Petition, Part 1, para. 1(c);  
iv.  
v.  
failing to consider or misapprehending evidence relevant to MDG’s claims for  
negligent misrepresentation by omission and breach of duty of honest  
performance: Amended Petition, Part 1, para. 1(d);  
in holding that MDG had overbilled Mount Polley and that Mount Polley had  
overpaid for MDG’s dredging services: Amended Petition Part 1, para. 1(e);  
and  
vi.  
in holding MDG liable for negligent misrepresentation by mischaracterizing  
statements made by MDG as actionable misrepresentations: Amended  
Petition, Part 1, para. 1(f).  
 
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 5  
[8] MDG further alleges that the Arbitrator committed arbitral error by failing to  
observe the rules of natural justice with respect to his summary conclusion that MDG  
owed a duty of care to Mount Polley when he failed to set out his chain of reasoning  
to explain how the Arbitrator reached that conclusion”.  
[9]  
Mount Polley opposes MDG’s Amended Petition mainly on the grounds that  
MDG is unable to meet the threshold for leave to appeal. Mount Polley points out  
that MDG lost the arbitration on every factual and legal point that was in issue.  
Issues  
[10] The issues to be addressed are whether MDG meets the requirements of the  
Act for granting leave to appeal from the Award, including whether it appeals “to the  
court on any question of law arising out of the Award” or whether the Award should  
be set aside on the grounds that the Arbitrator erred by failing to observe the rules of  
natural justice.  
[11] For the following reasons, I have determined that MDG’s application must be  
denied.  
Factual Background  
The Background in the Award  
[12] The Award described the background of the parties and the Agreement in the  
following way:  
[1]  
MDG Contracting Services Inc. (“MDG” or the “Claimant”) is a British  
Columbia company with its main place of business in Sparwood, British  
Columbia. MDG did not have prior experience in dredging but planned to  
expand its operational profile to include dredging by hiring Hugo Vergara as  
MDG’s newly appointed Operations Manager – Dredging, to assist MDG in  
responding to the Request for Proposal issued by Mount Polley Mining  
Corporation.  
[2]  
The Respondent, Mount Polley (“Mount Polley” or the “Respondent”)  
is the owner and operator of the Mount Polley gold and copper mine located  
in British Columbia near the towns of Williams Lake and Likely. This dispute  
arose following the breach of a dam associated with the mine’s tailings pond,  
causing a massive escape of tailings and fluid materials in August 2014.  
Following the closing of the tailings pond, the mine continued operations  
using the Springer Pit, then an active open pit mining operation, as a  
     
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 6  
temporary holding facility for tailings while the tailings storage facility (TSF)  
was rebuilt or replaced. The achievement of that goal led to Mount Polley’s  
need to have the tailings removed from the Springer Pit so that the mining  
operations could be resumed, and the remaining ore could be mined and  
milled to extract the copper, gold and silver.  
[3]  
The Agreement was made as of November 29, 2017 between the  
Claimant and the Respondent under which MDG agreed to “…furnish all  
supervision, tools, equipment, labour and materials to perform all work  
necessary to fully complete the work outlined in the Scope of Work (the  
Work) and the other contract documents.”  
[4]  
[5]  
The Scope of Work is defined as:  
4.0 The Scope of Work shall entail dredging up to 3,600,000 m3 of  
tailings from the Springer Pit to the Tailings Storage Facility (TSF), a  
distance of up to 8.0 km. The Contractor is to supply all mechanical  
and electrical components to convey the tailings slurry from the  
Springer Pit to the TSF, except for the pipeline, which shall be of a  
size and rating as specified by the Contractor, and supplied by Owner.  
Pursuant to Article 3 of the Agreement, MDG agreed that it would  
perform the Work during the period commencing no later than March 1, 2018  
with final completion by February 28, 2019.  
[13] Regarding the background to the Agreement, the Arbitrator stated as follows:  
[38]  
The uncontradicted evidence of Don Parsons, the Chief Operating  
Officer of Mount Polley’s corporate parent, was that so long as the tailings  
remained in the Springer Pit it could not be mined and it was critical to Mount  
Polley to carry out active mining operations in the Springer Pit to return the  
mine to economic viability, a fact well known to the Claimant.  
[39]  
Mount Polley issued a Request for Proposal (“RFP”) dated January  
10, 2017 to a number of proponents. MDG was not on the Mount Polley list of  
invited proponents, but upon hearing of the RFP, asked to be and was  
included in the process.  
[40]  
I accept the Respondent’s evidence that it issued a RFP because it  
was not experience [sic] with dredging (as a general contractor might be  
issuing requests for tenders of sub-contractors) and sought proposals from  
experienced dredging companies with technical experience, specialized  
capability and resources who would be in a better position to make their best  
efforts to make a technical and financial proposal to attract the interest of the  
requesting party with the possibility of being chosen to negotiate a contract.  
[41]  
The RFP invited the proponents “to submit your proposal for the  
supply of labour, equipment and materials required for dredging the tailings  
from the Springer Pit...in accordance with requirements” set out in the RFP.  
The deadline for submissions was on or before 2 p.m. February 1, 2017. The  
RFP included the following relevant instructions and guidelines:  
a) A statement that “it is MPMC’s intention to consider the proposals  
submitted pursuant to this process and to negotiate with one, or more  
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 7  
than one, of the Proponents whose proposals MPMC finds  
favourable.”  
b) A statement that “there is no guarantee or representation as to the  
accuracy of the Request for Proposal documents.”  
c) A statement that “MPMC is not obliged to request clarification or  
substantiation of a proposal even if it is apparent additional  
information is required. It is the Proponent’s responsibility to ensure all  
required information is provided to MPMC.”  
d) A statement in the Proposal Submission Guidelines at Part 3 of the  
RFP:  
3.2  
ASSUMPTIONS AND CONSTRAINTS  
a) Provide assumptions made in the development of the  
proposal, specifically relating to any project timelines,  
works, or Services to be provided by the Proponent and  
MPMC not explicitly outlined in this Request for Proposal  
and attached documentation:  
e) A statement concerning pricing as follows:  
3.5  
PRICING  
a) Pricing based on a cubic metre or per tonne basis;  
b) Defined method for measuring payment, as per Section #2  
article 6;  
c) Standby rates and considerations.  
f) A statement in Section 2, Scope of Work, at section 1.1:  
1.1 PREAMBLE  
The Mount Polley Mine is planning to relocate approximately 3.6  
million cubic meters of tailings from the Springer Pit to the tailings  
storage facility (TSF), a distance of 8.0 km. The methodology outlined  
in this Scope of Work is that of a dredging system. The Proponent is  
to supply all mechanical and electrical components to convey the  
tailings slurry from the Springer Pit to the TSF, except for the pipeline,  
which shall be supplied by MPMC based upon the system’s  
requirements. Additionally, all free water reporting to the TSF must be  
pumped back to the Springer Pit.  
g) A statement in the Scope of Work at section 3.0:  
3.0  
SCOPE  
The Scope of Work shall entail dredging up to 3,600,000 cubic meters  
of tailings from the Springer Pit to the TSF.  
h) A statement in section 3.1 “Specifications”:  
3.1  
SPECIFICATIONS  
Total Volume to be removed:  
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 8  
Up to 3.6 million m3 of submerged mine tailings and all water  
required to re-animate and transport it.  
i) A payment provision as follows:  
6.0  
PAYMENT  
Proposals should be structured such that payment is based upon the  
volume or mass of the solids transported. For the purpose of the  
Proposal, solids density is 2.7 tonnes/m3; saturated unit weight of the  
(is-situ) tailings is 1.85 tonnes/m3 (1.35 tonnes/m3 solid; 0.55  
tonnes/m3 water). Tracking Systems are to be provided by the  
Proponent and progress payments shall be made based upon  
Tracking System results, so long as they can be reasonably confirmed  
by MPMC to be accurate.  
At the end of the project, a survey shall be completed by MPMC to  
determine the final tailings geometry. This survey shall be compared  
to the initial geometry, which will be completed prior to the start of the  
Work (a current survey is provided). The volume of solids to be  
removed will be determined and the average, in-situ bulk density will  
be calculated based upon the reported mill tonnage that went into the  
pit. Full payment shall be made less the sum of the progress  
payments. If bid is based upon tonnage, the calculated Bulk Density  
shall be utilized to determine the tonnage of the solid portion.  
j) The Request for Proposal also contained a Schedule of Appendices  
which confirmed that:  
The following documents are enclosed:  
Springer Pit Profile (Sections)  
Tailings Pipe Curve  
Reclaim Pipe Curve  
Mount Polley Area Map  
The Dispute  
[14] The Arbitrator quoted from MDG’s description of the dispute that arose  
between the parties:  
[18]  
In the Notice of Arbitration, MDG, in describing the nature of the  
dispute, made the following statements which are relevant to the matters  
dealt with at the hearing:  
The procurement and Contract documents indicated that the tailings  
which the Claimant was to encounter consisted of very loose tailings  
with a high percentage of water content. The Claimant developed its  
unit price for removal of the tailings on that basis.  
 
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 9  
In early April 2018, the Claimant discovered that the water levels in  
the pit were higher than anticipated, such that “slimes” needed to be  
pumped in order to actually access tailings in the pit which were to be  
dredged. That the Claimant would need to pump slimes and related  
materials was not indicated anywhere in the procurement or Contract  
documents, which documents induced the Claimant to enter into the  
Contract for its original contract price. On April 8, 2018, the Claimant  
put the Respondent on notice of this issue. The Claimant and  
Respondent then negotiated the claims but no settlement was  
reached.  
By June 2018, the Claimant became concerned as it was becoming  
apparent that the composition of the tailings in the Springer Pit was  
not as disclosed and represented to it in the procurement or Contract  
documents. Instead of encountering the slurry-like tailings with a  
high-water content, the Claimant found itself dealing with:  
- tailings with a clay-like composition;  
- larger grain sizes than anticipated; and  
- contamination with rocks having a particle size 6-8 inches in  
diameter.  
The Claimant immediately gave notice of this issue to the  
Respondent, and the Respondent was consistently and repeatedly  
informed of this issue, and related issues, through the Claimant’s  
weekly reporting on the Project.  
[15] The Arbitrator also noted that MDG revised and further refined its claims in  
the Claim. He quoted from the Claim, including paragraphs in which MDG alleged  
actionable misrepresentations by Mount Polley, unpaid amounts owing under the  
Agreement and wrongful termination of the Agreement by Mount Polley.  
[16] The Arbitrator also quoted from the pleadings filed by Mount Polley in respect  
of its counterclaim.  
The Award  
[17] Following the arbitration, the Arbitrator released the Award dismissing MDG’s  
claims for misrepresentation and breach of contract including breach of “good faith  
duty” and for liens under the Builders Lien Act, S.B.C. 1997, c. 45. The Arbitrator  
found MDG liable to Mount Polley in damages for breach of contract due to  
 
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 10  
overbilling, failing to complete the scope of work and misrepresentations contained  
in the response to the RFP. By agreement, the damages are to be assessed in the  
next phase of the arbitration.  
[18] The Arbitrator summarized the material evidence of each witness and he  
made numerous findings throughout the Award. In submissions responding to the  
petition, counsel for Mount Polley provided me with a summary of the Arbitrator’s  
key factual findings.  
[19] As they are described in MDG’s petition, I understand that MDG disputes the  
correctness of some of the Arbitrator’s findings. However, I do not understand that  
MDG disputes that the particular findings identified by counsel for Mount Polley were  
actually made.  
[20] In my view, the following list provided by counsel for Mount Polley accurately  
summarizes the Arbitrator’s main findings:  
a) MDG had no prior experience in dredging (Award, para. 1).  
b) So long as tailings remained in the Springer Pit it could not be mined,  
and the removal of the tailings was essential to returning the Mine to  
economic viability, which was well known to MDG (Award, para. 38).  
c) MDG was unknown to MPMC and was not invited to submit a  
proposal, but became involved after it inserted itself in the RFP  
process. MPMC issued an RFP because it was not experienced with  
dredging and was seeking technical guidance from expert proponents,  
which is the commercial purpose of an RFP, distinct from a tendering  
relationship (Award, paras. 39-40, 226-229).  
d) MDG visited the Mine before responding to the RFP, and was offered  
an opportunity to look at and take samples of the tailings. It declined  
this opportunity, even after it was told “the tailings were very hard to  
deal with”, MDG’s representatives stating “it did not matter to the  
dredges” (Award, paras. 43-45).  
e) MDG did not identify any of the assumptions or conclusions it alleged  
it subjectively drew on the basis of the alleged misrepresentations in  
its response to the RFP, and there was no documentary evidence to  
support Mr. Vergara’s after-the-fact assertions of reliance (Award,  
paras. 51-52).  
f) It was industry practice to state and incorporate such assumptions,  
and each of the other bidders who responded to the RFP did so or  
included other industry standard conditions. MDG did not. (Award,  
paras. 59-61).  
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 11  
g) MDG did not prove the actual characteristics of the tailings, which it  
claimed had been misrepresented to it (Award, para. 53).  
h) The assumptions Mr. Vergara allegedly drew “had no basis in reality”  
(Award, para. 54). Contrary to his ex post facto claims in litigation,  
Mr. Vergara did not take any steps to include the alleged  
“representations” in the Contract (Award, para. 68).  
i) MDG’s proposal delivered in response to the RFP contained the  
representations MPMC sued upon (Award, paras. 56-57). There was  
no controversy these representations were made (Award, para. 259).  
j) While the RFP was not incorporated into the Contract, MDG’s  
proposal and its representations were (Award, paras. 65, 80-82).  
k) MPMC relied upon these representations (Award, para. 145), and if  
MDG had complied with reasonable industry practice it would have  
acted consistently with the representations it had made (Award, para.  
161).  
l) Mr. Vergara, the only individual at MDG who had dredging experience  
of any sort, had no experience dredging a tailings pond at a hard rock  
mining pit (Award, para. 99). Fundamental errors were made by MDG,  
which the Arbitrator found were the sole cause of its alleged  
misfortune (Award, paras. 100-105):  
m) There was no actionable misrepresentation communicated by MPMC  
to MDG (Award, para. 142).  
n) There was no “debate” within MPMC as to the composition of the  
tailings (Award, para. 158).  
o) “[F]or reasons unconnected with any perceived misrepresentation,  
MDG was bound to fail in its performance of this contract because of  
the failure to prepare, follow, or implement a detailed dredging plan,  
use GPS and employ functioning density meters or dredging software  
and technology which is accepted industry practice and failed to meet  
a reasonable standard for a dredging contractor to ‘perform a detailed  
site investigation of their own before bidding on a project. This should  
include a site visit, questions about the material type, and taking their  
own samples to [verify] material conditions before bidding’.” (Award,  
para. 161).  
p) Mr. Vergara and MDG did not actually draw the assumptions they  
claimed were the product of a misrepresentation “until this dispute  
arose”. In other words, they were a post facto invention. (Award, para.  
170).  
q) MPMC did not make the representations pled and advanced by MDG  
- I find as a fact that no representations were made either by direct  
statement or by omission” (Award, para. 204, 208).  
(emphasis added)  
r) On the evidence accepted by the Arbitrator, MPMC could not  
reasonably have foreseen that MDG would rely on the representations  
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 12  
alleged, or that the reliance of MDG would be reasonable in the  
circumstances (Award, para. 207).  
s) “Rather than evidence of negligence, the conduct of [MPMC] in the  
RFP process demonstrates that it exercised reasonable care by  
expressly warning the proponents that ‘there is no guarantee or  
representation as to the accuracy of the Request for Proposal  
documents’, and by inviting them to take samples and conduct their  
own analysis of the materials, an opportunity that Mr. Vergara rejected  
for the reasons described earlier in this award” (Award, para. 210).  
t) MDG did not rely on the misrepresentations alleged to have been  
made by MPMC (Award, para. 213).  
u) If there was reliance, which was not proven, it would not be  
reasonable reliance (Award, para. 219).  
v) As a factual matter, including based on the language of the  
documents in evidence before the Arbitrator, an RFP is not a contract  
or tender (Award, para. 226).  
w) “I found no evidence of bad faith conduct on the part of [MPMC] at all  
in its dealings with MDG, let alone related to its performance of its  
contractual obligations” (Award, para. 249).  
x) “On the evidence”, the Arbitrator found each of the representations  
MPMC sued upon, which MDG admitted it made, were false, and that  
each of the elements of the Queen v. Cognos (JBOA, Tab 30) test  
was satisfied (Award, paras. 259-261),  
Analysis  
[21] I will begin by considering MDG’s request for leave to appeal on the basis that  
it has identified an error of law.  
Has MDG met the statutory requirements for granting leave to appeal?  
[22] The parties agree that the Act, not the current Arbitration Act, S.B.C. 2020, c.  
2, is the governing legislation because the arbitral proceeding at issue was  
commenced on March 13, 2020.  
[23] MDG requires leave from the court to appeal a question of law arising out the  
Award: s. 31(1)(b), Act.  
[24] Subsection 31(2) of the Act provides that the court may grant leave if any of  
the following criteria are established:  
   
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 13  
(a) the importance of the result of the arbitration to the parties justifies the  
intervention of the court and the determination of the point of law may prevent  
a miscarriage of justice,  
(b) the point of law is of importance to some class or body of persons of  
which the applicant is a member, or  
(c) the point of law is of general or public importance.  
[25] In Allard v. The University of British Columbia, 2021 BCSC 60 at paras. 14-15  
[Allard], Justice Douglas discussed the high bar required for leave to appeal  
established in the leading authorities and the intention behind it:  
[14]  
The test for leave to appeal an arbitration award is not easily met:  
Sattva Capital Corp. v. Creston Moly Corp., 2014 SCC 53 at paras. 38-40  
[Sattva]. Courts must show due respect for the parties' decision to arbitrate  
and the commercial arbitral process: TELUS Communications Inc. v.  
Wellman, 2019 SCC 19 at paras. 54-56 [TELUS]. The modern "hands off"  
view is that arbitration is an autonomous, self-contained, and self-sufficient  
process where parties agree to have their disputes resolved by an arbitrator,  
not the courts: TELUS, at para. 56.  
[15]  
The limited jurisdiction of courts to hear arbitral appeals promotes  
efficiency and finality, the central aims of commercial arbitration: Teal Cedar  
Products Ltd. v. British Columbia, 2017 SCC 32 at para. 1 [Teal Cedar]. As  
noted by our Court of Appeal in Boxer Capital Corp. v. JEL Investments Ltd.,  
2015 BCCA 24 at para. 3 [Boxer], commercial arbitration is intended to  
provide a speedy and, in the vast majority of cases, final determination of the  
parties' dispute.  
The threshold requirement identification of a question of law  
[26] In Allard, at paras. 16-17 and 21, Douglas J. summarized the principles that  
apply to determining whether a petitioner has met the threshold requirement for  
leave to appeal of identifying a question of law arising from an arbitration award:  
[16]  
Identifying a question of law for appellate review is a threshold  
requirement for granting leave: Arbitration Act, s. 31(1); Teal Cedar, at para.  
1. This Court has no jurisdiction to review questions of either fact or mixed  
fact and law. Delineating a question of law is particularly important in the  
context of an arbitral review in BC "because it goes beyond the question of  
standard of review to the very jurisdiction of the court to embark on the review  
process": [MSI Methylation Sciences, Inc. v. Quark Venture Inc., 2019 BCCA  
448], at para. 62. A court must grant leave only when questions of law can be  
clearly perceived and delineated: Elk Valley Coal Partnership v. Westshore  
Terminals Ltd., 2008 BCCA 154 at para. 17; Teal Cedar, at para. 45; Sattva,  
at para. 54. Finding that the questions on appeal are not questions of law  
wholly disposes of this Court's jurisdiction to review them: Teal Cedar, at  
para. 42.  
 
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
[17] Legal questions are questions "about what the correct legal test is".  
Page 14  
Factual questions are "about what took place between the parties". Questions  
of mixed fact and law are about whether the facts satisfy the legal test" (i.e.,  
the application of a legal standard to a set of facts): Teal Cedar, at para. 43;  
Sattva, at para. 49; Canada (Director of Investigation and Research) v.  
Southam Inc., [1997] 1 S.C.R. 748 at para. 35 [Southam]; Housen v.  
Nikolaisen, 2002 SCC 33 at paras. 26-27.  
[21]  
Where the legal principle is not readily extricable, the matter remains  
one of "mixed fact and law": Sattva, at paras. 54-55. The leave judge must  
ultimately ensure that the proposed ground of appeal has been properly  
characterised. Only questions of law or extricable questions of law will meet  
the statutory threshold under s. 31(1) of the Act.  
[27] In Hotel Georgia Development Ltd. v. The Owners, Strata Plan EPS849, 2021  
BCSC 1236 at paras. 91-95 [Hotel Georgia], Justice MacNaughton considered an  
application for leave to appeal brought by a petitioner following an arbitration. In  
respect of the threshold question, MacNaughton J. noted as follows:  
[91]  
Questions of mixed fact and law are immune from appeal under s. 31  
of the [Act] because they involve consideration of the factual matrix in which a  
contract was formed.  
[92]  
The Supreme Court of Canada determined, in Sattva at paras. 47 —  
50 and in Teal Cedar at para. 47, that the evolution of the approach to  
contractual interpretation, means that, typically, issues of contractual  
interpretation involve application of legal principles to a set of facts which  
include the particular words of a contract, considered in light of the factual  
matrix.  
[93]  
However, both Sattva and Teal Cedar explained that the application of  
an incorrect legal principle, the failure to consider a required element of a  
legal test, or the failure to consider a relevant factor, may give rise to an  
extricable question of law: Sattva at para. 53 and Teal Cedar at paras. 63 —  
64. If an arbitrator ignores a specific and relevant provision in construing a  
contract, that would be a question of law that would be extricable from a  
finding of mixed fact and law: Sattva at para. 64.  
[94]  
The errors alleged in HGD's petition track this language. However, as  
Sattva warns at paras. 53-55, in seeking leave to appeal, aggrieved parties  
often strain to frame alleged errors as questions of law. Extricable questions  
of law are rare, and reviewing courts should be wary of parties trying to frame  
a question of mixed fact and law as a question of law for the purposes of  
reaching the high threshold for leave to appeal. A similar warning was  
repeated in Teal Cedar at paras. 63-64.  
[95]  
I agree with the Residential Strata's position that the cases establish a  
process to ensure that the threshold question in the [Act]identifying a  
question of law is met first. To dive into the merits of an arbitrator's  
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 15  
contractual analysis, and consider whether the standard of review is  
reasonableness or correctness, is to "put the cart before the horse". The  
analysis must first be characterized as raising a legal question for review:  
Allard v. The University of British Columbia, 2021 BCSC 60 at para. 39, citing  
Teal Cedar at para. 60. To the extent that a review of the evidence is required  
to make the argument that an error of law occurred, the error cannot be said  
to be on the face of the award.  
[28] In Chriscan Enterprises Ltd. v. St. Pierre, 2016 BCCA 442 at para. 29, the  
Court of Appeal held that for purposes of granting leave to appeal from an arbitral  
award, an error of law must be discernable “on the face of the award”:  
[29]  
The scope to appeal arbitral awards is narrow because arbitration is  
intended to be an alternate dispute resolution mechanism rather than one  
more layer of litigation. Thus, an applicant for leave to appeal must identify an  
error of law on the face of the award, the standard of review in the context of  
commercial arbitrations is almost always the deferential standard of  
reasonableness, there is a discretion to deny leave even when an appeal is  
technically permitted by the Act, and the normal 'palpable and overriding  
error' standard does not apply to the arbitrator's factual findings, which are  
"absolute": Sattva, at paras. 75, 85, 92 and 104.  
[29] MDG states that the errors of law in the Award “relate to the law of negligent  
misrepresentation, the law of contractual interpretation and the contractual duties of  
good faith and honest performance”. MDG submits that the Arbitrator’s conclusions  
that Mount Polley was not liable for negligent misrepresentation or breach of  
contractual duty of honest performance and that MDG was liable for negligent  
misrepresentation were “premised on errors of law”.  
[30] To determine whether the Court has jurisdiction to grant leave to appeal, I will  
begin by considering each alleged error to see whether MDG has identified a “clearly  
perceived and delineated” question of law, or, a rare extricable question of law:  
Allard at para. 16; and Hotel Georgia at paras. 93-94. Although MDG has listed six  
individual alleged errors of law, I have considered them in two categories: alleged  
errors relating to MDG’s claim of negligent representation, and alleged errors  
relating to MDG’s claim of breach of the duty of honest performance.  
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 16  
The failure to find Mount Polley liable to MDG for negligent  
misrepresentation  
[31] The parties agree that the Arbitrator correctly identified and set out the  
appropriate test for establishing negligent misrepresentation. The Arbitrator was  
required to determine whether Mount Polley was liable to MDG for negligent  
misrepresentation by way of direct statement, omission, or both.  
[32] The Arbitrator considered MDG’s claim regarding Mount Polley’s alleged  
misrepresentations before concluding that the “alleged misrepresentations, raised in  
argument, are not proven”: Award, para. 204.  
[33] MDG alleges that the Arbitrator erred in law by holding that Mount Polley was  
not liable to MDG for negligent misrepresentation by omission arising from Mount  
Polley’s failure to disclose “all reasonably material in its possession which may have  
had a bearing on MDG’s response to the RFP” and its conduct after the parties  
entered into the Agreement. MDG submits that the Arbitrator erred in law by:  
(a) misapplying the duty of care analysis; (b) misstating and misapplying the law on  
when an omission may constitute a misrepresentation; and (c) failing to consider the  
elements of reliance in respect of MDG’s misrepresentation by omission claim.  
[34] Counsel for Mount Polley submits that since the Arbitrator correctly cited the  
test before finding that MDG had failed to satisfy “any of the five elements of the test  
for actional misrepresentation”, MDG is actually arguing that the Arbitrator ought to  
have reached a different conclusion as he applied the correctly stated legal test to  
the facts. In other words, Mount Polley argues that MDG is essentially raising  
questions of fact or, questions of mixed fact and law, and as such the Court lacks  
jurisdiction to grant leave to appeal.  
[35] In Teal Cedar Products Ltd. v. British Columbia, 2017 SCC 32, at para. 45,  
Justice Gascon warned that courts must, especially when faced with strategic  
drafting designed to frame the issue as a legal question, remain alert to the  
important difference between a party alleging that “a legal test may have been  
altered in the course of its application” (which is an extricable question of law) and a  
 
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 17  
party alleging that “a legal test, which was unaltered, should have, when applied,  
resulted in a different outcome(which is a mixed question of fact and law). The  
significance of that difference is that in the latter circumstance, the threshold for  
leave to appeal will remain unsatisfied.  
[36] MDG submits that had the Arbitrator properly considered the elements [of  
negligent misrepresentation] and the relevant evidence, each the elements would  
have been established …”: Amended Petition, para. 142 [underline added]. MDG’s  
submission confirms the need for vigilance and, in my view, it supports a conclusion  
that MDG is raising a question of mixed fact and law because MDG’s complaint is  
essentially that the unaltered legal test should have, when applied by the Arbitrator,  
resulted in a finding that Mount Polley was liable to MDG for negligent  
misrepresentation.  
[37] First, MDG submits that the Arbitrator failed to properly apply “the duty of care  
analysis necessary to establish the first element of negligent misrepresentation”. In  
MDG’s view the Arbitrator did not consider whether the relationship between the  
parties falls within, or is analogous to, an owner and tenderer relationship which is a  
previously established category.  
[38] Many of the authorities relied on for the proposition that Mount Polley owed  
MDG a duty of care arose in the context of bidding and tendering situations. I was  
directed to no authority stating that a party who issues a RFP owes a duty of care to  
the parties who may receive or respond to it.  
[39] In considering MDG’s contractual claims (which overlap with MDG’s negligent  
misrepresentation claims), the Arbitrator discusses the legal framework surrounding  
RFPs, as compared to a request for tenders. The Arbitrator notes that the  
circumstance of a request for tenders typically creates a contractual relationship  
between the party seeking tenders and the party who answers the request. The  
Arbitrator also considers Guysborough (Municipality) v. Resource Recovery Fund  
Board Inc., 2011 NSSC 15 at paras. 37-38 [Guysborough] where the court  
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 18  
distinguishes the RFP, with its mere “invitation to propose” and “very general  
guidance”, from the creation of the “Contract A” resulting from a tender call.  
[40] After reviewing the law, the Arbitrator concludes that the RFP issued by  
Mount Polley does not form part of the Agreement between Mount Polley and MDG.  
He reaches this conclusion after considering Powder Mountain Resorts Ltd. v. British  
Columbia (1999), 47 C.L.R. (2nd) 32 (BCSC) at para. 72, aff’d 2001 BCCA 619 and  
noting the express instructions to proponents contained in the RFP. It is clear that  
the Arbitrator accepts the statement in Guysborough (at para. 38) that “the RFP  
represented an invitation to propose and nothing more” to conclude that as far as  
MDG and Mount Polley are concerned, there was no intention to create contractual  
relations.  
[41] MDG’s position is that the Arbitrator erred in the applying the duty of care  
analysis by failing to consider whether the relationship between MDG and Mount  
Polley falls within, or is analogous to, an owner and tenderer relationship which is a  
previously established category. More specifically, MDG points to the Arbitrator’s  
failure “to properly apply the body of law recognizing an owner’s obligation to  
disclose all relevant information to proponents” both during an RFP process and  
after the parties entered into the Agreement : Amended Petition, Part 1, para.  
1(a)(i)(1) and (b).  
[42] However, as I noted above, the Award makes clear that the Arbitrator  
considered the differences between requests for proposals versus requests for  
tenders, as well as the factual context that was before him, to conclude that the RFP  
is not part of the Agreement and that Mount Polley owed no duty of care to MDG.  
Although a failure to consider this step in the duty of care analysis could be  
characterized as an extricable question of law, the petitioner has not established an  
error on the face of the Award in this regard.  
[43] Second, MDG says the Arbitrator misstated and misapplied the law on when  
an omission may constitute a misrepresentation.  
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 19  
[44] MDG alleged that Mount Polley made negligent misrepresentations by  
omission when it failed to disclose information, namely certain engineering reports  
and surveys, related to the nature of the tailings listed in the RFP. MDG’s complaint  
regarding the Award is that the Arbitrator “failed to apply all the components of the  
test for negligent misrepresentation, in particular those related to representations by  
omission, and failed to consider certain facts and ignored evidence that was relevant  
to the application of the test”: Amended Petition, para. 90.  
[45] However, it must be kept in mind that the Arbitrator found that Mount Polley  
made no misrepresentations and MDG did not, reasonably or at all, rely on the  
alleged misrepresentations.  
[46] An Arbitrator’s conclusions as to whether misrepresentations were made and  
relied upon are findings of fact: Kaiser v. Schuttler, 1999 ABQB 11 at para. 4;  
McKay Career Training Inc. v. Baker, 2018 SKCA 83 at para. 20.  
[47] In the Award, the Arbitrator considered MDG’s claims of misrepresentation by  
omission and he dismissed the allegations, stating as follows:  
[221] Two allegations of misrepresentation by omission relates to the  
density in the water content of the tailings. The first allegation was that the  
Respondent had a duty to inform the Claimant of the actual density and water  
content of the tailings because numbers stated in the RFP were unreliable.  
[222] The description of density and water content of the tailings in Article  
6.0 of the RFP which I have held are not representations of fact but rather  
representative values to be used only for the purposes of progress payments  
this allegation that those figures were “uncertain” runs contrary to the  
Claimant’s assertion that the Respondent had expressly represented a 1.35  
dry bulk density and a 0.50 water content of the tailings. The allegation that  
the numbers stated in the RFP were unreliable does not stand with my finding  
that no such representation was made and that it would be unreasonable to  
rely on those numbers.  
[223] The second allegation related to two surveys in the possession of the  
Claimant, the results of which directly contradicted the density in the water  
content numbers stated in the RFP, at section 6.0 of the “Scope of Work”  
titled “Payment” which were not disclosed.  
[224] Both allegations of misrepresentation by omission are dismissed on  
the basis that there was nothing stated in the Payment clause 6.0 of the RFP  
which required clarification as that provision, as explained earlier, did not  
convey a representation of fact.  
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 20  
[225] In the result, MDG’s claim for damages in negligent misrepresentation  
is dismissed.  
Award, paras. 221-225  
[48] MDG submits that the Arbitrator focussed excessively on the contents of the  
RFP without considering “the special relationship between owners and bidders that  
is rooted in a fundamental policy in construction law … that owners cannot withhold  
relevant information to bidders.” Again, I was referred to no authority stating that  
“the general principles applying to the standard of care owed to bidders in  
construction projects” apply in the context of a RFP.  
[49] Third, MDG submits that the Arbitrator erred by failing to consider the  
elements of reliance in respect of MDG’s representation by omission claim. MDG  
says that it reasonably relied on “an unstated key assumption of MDG that Mount  
Polley had completed a thorough analysis of the tailings prior to issuing the RFP”  
because Mount Polley was a “tailings expert”.  
[50] The difficulty with MDG’s submission on this point is that it conflicts with  
numerous factual findings made by the Arbitrator, including his conclusion that  
Mount Polley issued the RFP due to its dredging inexperience and because it  
wanted technical guidance from expert proponents: Award, paras. 39-40, 226-229.  
[51] As for MDG’s submission that the Arbitrator failed to consider evidence, the  
Award discusses the evidence of both parties at length, including the expert  
evidence. The Arbitrator sets out his detailed findings regarding the evidence.  
[52] In my view, MDG’s submission that the Arbitrator failed to consider evidence  
is really a complaint that the Arbitrator preferred the evidence of Mount Polley over  
the evidence of MDG for reasons that the Arbitrator explained. This complaint is not  
a basis for granting leave to appeal in the present circumstances.  
[53] I am unable to accept MDG’s submission that it has identified a question of  
law related to the Arbitrator’s holding that Mount Polley was not liable to MDG for  
negligent misrepresentation by omission on any of the specific grounds raised. In  
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 21  
my view, it is clear from a reading of the Award as a whole, that MDG is raising  
questions of fact or mixed fact and law which are not subject to review.  
[54] For the reasons that I have explained, I find that the issues raised by MDG  
essentially come down to” whether the facts satisfy the legal test", or, put another  
way, the application of a legal standard to a set of facts which fails to meet the  
statutory threshold for granting leave to appeal: Hotel Georgia at paras. 89-90. My  
conclusion that MDG is raising only questions of fact or mixed fact and law is, in my  
view, supported by the notable focus in its submissions on the particulars of the  
evidence that was before the Arbitrator.  
The failure to find that Mount Polley breached its good faith contractual  
duty of honest performance  
[55] MDG alleges that when the Arbitrator concluded that Mount Polley had not  
breached its good faith contractual duty of honest performance he erred in law by  
misapplying the legal test and by improperly limiting the scope of the duty of honest  
performance to statements in the RFP documents.  
[56] MDG agrees that the Arbitrator correctly articulates the law in respect of the  
duty of good faith; however, MDG submits that following this correct articulation of  
the law, the Arbitrator “did not include any further discussion of the principles that  
apply”: Amended Petition, para. 147-148.  
[57] A key concern raised by MDG in respect of this issue is the allegation that  
after MDG alerted Mount Polley to the difficulties it was having dredging the tailings,  
Mount Polley continued to withhold relevant information from MDG.  
[58] The Arbitrator was aware of MDG’s allegations that Mount Polley withheld  
information and after considering the evidence presented by the parties, he found  
“no evidence of bad faith on the part of Mount Polley at all in its dealings with MDG,  
let alone related to its performance of its contractual obligations”: Award, para. 249.  
[59] At para. 251, before dismissing MDG’s contractual claims, the Arbitrator  
refers to the relevant authorities and states as follows:  
 
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 22  
[251] As I have noted that the RFP was not included in the Contract  
Documents and accordingly was not incorporated into the contract. Further,  
as the misrepresentations were not incorporated into the contract, it cannot  
be said that Mount Polley failed to correct its misrepresentations, exposing it  
to liability for reach of the contractual duty of good faith identified in Bhasin v.  
Hrynew, 2015 SCC 71, [2014] 3 S.C.R. 494, C.M. Callow Inc. v. Zollinger,  
2020 SCC 45 or Wastech Services Ltd. v. Greater Vancouver Sewage and  
Drainage District, 2021 SCC 7.  
[60] In light of these findings, it is clear that the Arbitrator considered and then  
rejected the allegation raised by MDG that Mount Polley had knowingly misled it for  
the reasons the Arbitrator explained.  
[61] In my view, MDG is once again raising a mixed question of fact and law by,  
essentially, submitting that despite the Arbitrator making a correct statement  
regarding the law, it should have, when properly applied, resulted in a different  
outcome on the issue of whether Mount Polley breached the duty of honest  
performance. As such, the threshold is unmet and leave to appeal is not available.  
Should the Award be set aside because MDG has shown that the  
Arbitrator committed an arbitral error?  
[62] Section 30(1) of the Act provides that an arbitral award may be set aside or  
remitted where the arbitrator commits an arbitral error.  
[63] In this case, MDG alleges an arbitral error in the course of an arbitration due  
to the Arbitrator’s “failure to follow the rules of natural justice”: s. 1 “arbitral error”  
(d), Act. More specifically, MDG describes the arbitral error as the Arbitrators failure  
to set out his chain of reasoning for the conclusion that MDG owed a duty of care to  
Mount Polley.  
[64] In the context of an arbitration, which is a form of private dispute resolution,  
the requirements of natural justice are described by our Court of Appeal in 0927613  
B.C. Ltd. v. 0941187 B.C. Ltd., 2015 BCCA 457 at paras. 59-60, as follows:  
[59]  
Natural justice requirements in arbitration have been broadly stated to  
require the arbitrator to act in good faith (or stated otherwise to be unbiased),  
fairly listen to both sides, and to give a fair opportunity to those who are  
parties to make representations, including to correct or to contradict any  
 
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 23  
relevant statement prejudicial to their view. See Kane v. Board of Governors  
of the University of British Columbia, [1980] 1 S.C.R. 1105 at 1113; and  
Lakeside Colony of Hutterian Brethren v. Hofer, [1992] 3 S.C.R. 165 at 195.  
[60]  
Natural justice will require an arbitrator to act with procedural fairness,  
the requirements of which will depend on the subject-matter of the dispute,  
the circumstances of each case, the nature of the inquiry, and the rules under  
which the parties have agreed to arbitrate their dispute. See Zaleschuk Pubs  
Ltd. v. Barop Construction Ltd. (1992), 68 B.C.L.R. (2d) 340 at para. 47;  
Arbutus Software Inc. v. ACL Services Ltd., 2012 BCSC 1834 at para. 81;  
and Farrar v. Bojan High End Kitchens Inc., 2013 BCSC 1881 at para. 24.  
The duty of fairness is not a “one size fits all” requirement but is molded by  
the circumstances of each case. Its most basic requirement is “simple  
fairness” or “fair play in action”. See Canada (Attorney General) v. Mavi, 2011  
SCC 30 at para. 42; Ridge v. Baldwin, [1962] 1 All E.R. 834 (C.A.) at 850,  
Harman L.J., cited in Kane at 1113.  
[65] Where a party alleges a breach of natural justice in respect of an arbitral  
award, the applicable legal principles were recently set out as follows by  
MacNaughton J. in Hotel Georgia:  
[64]  
On an application to set aside an arbitral award for a breach of natural  
justice, the arbitrator is granted a high degree of deference, and courts  
should not be concerned with the fairness or correctness of the award itself.  
This is because the provisions for setting aside an award “deal with the  
procedural matters, not the legal correctness of the decision”.  
[65]  
As explained in Mungo v. Saverino, [1995] O.J. No. 3021 at paras.  
7273, the courts will endeavour not to second-guess an arbitrator’s  
decision on jurisdiction or procedural fairness grounds.  
[66]  
Justice Dickson, when a member of this Court, outlined the  
requirements of natural justice in the arbitral context, and the recognized  
breaches of natural justice, in Arbutus Software Inc. v. ACL Services Ltd.,  
2012 BCSC 1834 at paras. 8182. Natural justice requires an arbitrator to  
act with procedural fairness and may require processes tailored to meet a  
particular case.  
[67]  
The party alleging a breach of natural justice, in this case, HGD, bears  
the onus of establishing the facts necessary to prove the breach.  
[68] Where an arbitrator considers an approach to an issue that has not  
been raised by either party, natural justice requires the arbitrator to give the  
parties an opportunity to comment on the approach. The fact that a party  
does not make sufficient use, if any, of the opportunity given by the arbitrator  
is not a breach of natural justice and, accordingly, not a basis for setting  
aside an arbitral award.  
[69]  
In this case, the Arbitrator sought submissions on the issue of his  
ability to make a quantum meruit award.  
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
[70] An arbitrator is required to give comprehensible reasons, but such  
Page 24  
reasons need not recite every submission and outline why every submission  
was accepted or rejected.  
[66] In Newfoundland and Labrador Nurses’ Union v. Newfoundland and Labrador  
Treasury Board), 2011 SCC 62 at paras. 14 and 16, Justice Abella noted, in the  
context of judicial review, that the “adequacy” of the reasons is not a stand-alone  
basis for quashing a decision and that reasons need not include all arguments,  
statutory provisions, jurisprudence or explicit findings on each constituent element  
leading to the final conclusion; rather, the issue is whether the reasons enable the  
reviewing court to “understand why the tribunal made its decision and permit it to  
determine whether the conclusion is within the range of acceptable outcomes. At  
para. 17, the Court also noted that the existence of a different interpretation of an  
agreement to the one provided by an arbitrator does not automatically mean the  
decision should be set aside.  
[67] MDG referred me to Economical Mutual Insurance Company v. Intact  
Insurance Company, 2021 BCSC 1772 [Economical Mutual] as support for its  
submission that the Arbitrator provided no reasoning regarding the application of the  
law to the dispute as to whether MDG was liable to Mount Polley for negligent  
misrepresentation, especially in relation to the duty of care analysis.  
[68] In considering whether the principles of natural justice had been complied  
with in Economical Mutual, Justice MacDonald identified the problem with the  
reasons of the arbitrator in the following terms:  
[47]  
Here, the Arbitrator provided no reasoning regarding the application of  
the law to the dispute. He simply reviewed a number of cases and set out the  
principles they stood for. He then stated his conclusion. In reaching his  
conclusion, he did not demonstrate that he applied the legal principles to the  
facts before him. There is no chain of reasoning to explain how the Arbitrator  
made his Decision.  
[48]  
I appreciate that the Arbitrator stated that he reviewed the law as it  
applied to the facts and considered the parties’ submissions. However, there  
is no analysis provided so that the parties or this Court can understand how  
he came to his conclusion. Specifically, it is unclear whether or not he  
considered s. 148.1(9) of the Regulation, a central argument before him. It is  
also unclear whether, since Economical was obliged to provide UMP  
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 25  
coverage pursuant to the BC legislative scheme, Economical “stepped into  
the shoes” of ICBC in doing so. The parties should not have to guess or  
speculate regarding how the Arbitrator came to his Decision.  
[49]  
The Arbitrator’s lack of analysis pertains to a central issue. In my  
view, this renders the reasons inadequate. While the Arbitrator made findings  
of fact and set out the legislative provisions and legal principles, he did not  
apply the legislation and legal tests to the facts before him. By not applying  
the legal tests to the facts when reaching his conclusion, the Arbitrator made  
it impossible for the parties and a reviewing court to understand how and why  
he reached his Decision. Essentially, the Arbitrator detailed the “what” of his  
decision but not the “why”: Conmac Enterprises Ltd. at para. 71.  
[50]  
I find the Arbitrator failed to provide sufficient reasoning in his decision  
and failed to consider all relevant legislation. His reasons do not enable the  
parties and a court on appeal to determine how he reached his conclusion.  
His lack of reasons and failure to address all the primary issues before him  
results in a failure to observe the rules of natural justice: Arbitration Act, s. 1.  
[69] In my view, the Award before me is distinguishable from the award under  
consideration in Economical Mutual. In the present case, the Award contains ample  
detail regarding the Arbitrator’s findings, his consideration of the relevant authorities  
and his reasoning for deciding that MDG was liable to Mount Polley for negligent  
misrepresentation, including with respect to the duty of care element.  
[70] I have reached this conclusion because the Award, for example, sets out in  
para. 40, the Arbitrator’s acceptance of Mount Polley’s evidence that it issued the  
RFP seeking proposals from parties who would be better placed than Mount Polley  
(in terms of technical experience and specialized capability/resources) to make a  
technical and financial proposal for the dredging work.  
[71] I agree with counsel for Mount Polley that as a result of this finding it is  
reasonable to infer that the Arbitrator agreed the whole point of the RFP was to allow  
Mount Polley to obtain and rely on the expertise of proponents who responded to the  
RFP. This is not a situation, as was the case in Economical Mutual, where the  
Award leaves the parties or the court unable to determine how the Arbitrator reached  
his conclusion.  
[72] I am supported in my assessment by the Arbitrator’s ample findings that MDG  
made representations to Mount Polley that it was qualified, experienced and capable  
MDG Contracting Services Inc. v. Mount Polley Mining Corporation  
Page 26  
of doing the work, which he concluded were misrepresentations that Mount Polley  
had relied upon: Award, paras. 145, 259 and 261.  
[73] For the reasons that I have explained, I do not agree with MDG’s allegation  
that Arbitrator committed an arbitral error. As a result, I decline MDG’s request to  
set aside the Award pursuant to s. 30 of the Act.  
Disposition  
[74] The relief sought in paras. 1-3 of part 1 of the Amended Petition is dismissed,  
with costs to the respondent, Mount Polley.  
E. McDonald”  
 


© 2022 IncJournal is not affiliated with or endorsed by the U.S. Securities and Exchange Commission