COURT OF APPEAL FOR BRITISH COLUMBIA  
Citation:  
Thurlow & Alberni Project Ltd. v. The  
Owners, Strata Plan VR 2213,  
2022 BCCA 257  
Date: 20220725  
Dockets: CA47534; CA47535  
Docket: CA47534  
Between:  
Thurlow & Alberni Project Ltd.  
Appellant/  
Respondent on Cross Appeal  
(Respondent)  
And  
And  
The Owners, Strata Plan VR 2213  
Respondent/  
Appellant on Cross Appeal  
(Petitioner)  
James Jamieson and Gillian Jamieson  
Respondents  
(Respondents)  
- and -  
Docket: CA47535  
Between:  
James Jamieson and Gillian Jamieson  
Appellants/  
Respondents on Cross Appeal  
(Respondents)  
And  
The Owners, Strata Plan VR 2213  
Respondent/  
Appellant on Cross Appeal  
(Petitioner)  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 2  
Before:  
The Honourable Mr. Justice Willcock  
The Honourable Justice Dickson  
The Honourable Mr. Justice Marchand  
On appeal from: An order of the Supreme Court of British Columbia, dated  
May 12, 2021 (The Owners, Strata Plan VR 2213 (Re), 2021 BCSC 905,  
Vancouver Docket S198769).  
Counsel for the Appellant/Respondent on  
cross appeal in CA47534, Thurlow & Alberni  
Project Ltd.:  
S.A. Griffin  
D. Siracusa  
Counsel for the Respondent/Appellant on  
cross appeal in CA47534 and  
Respondent/Appellant on cross appeal in  
CA47535, The Owners, Strata Plan  
VR 2213:  
A.K. Aggarwal  
K.A. McGoldrick  
The Respondent in CA47534 and  
Appellant/Respondent on cross appeal in  
CA47535, James Jamieson, appearing in  
person:  
J. Jamieson  
Place and Date of Hearing:  
Place and Date of Judgment:  
Vancouver, British Columbia  
April 56, 2022  
Vancouver, British Columbia  
July 25, 2022  
Written Reasons by:  
The Honourable Mr. Justice Willcock  
Concurred in by:  
The Honourable Justice Dickson  
The Honourable Mr. Justice Marchand  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Summary:  
Page 3  
This appeal arises from the dismissal of a petition by the respondent, the Owners,  
Strata Plan VR 2213 (the Strata Corporation), seeking an order pursuant to  
s. 173(2) of the Strata Property Act, S.B.C. 1998, c. 43, that a special resolution  
calling for the imposition of a special levy be approved. The special levy was passed  
by a simple majority and is intended to raise funds to repair the building envelope.  
The appellant, Thurlow & Alberni Project Ltd. (“Thurlow”), submits the judge erred in  
addressing its defences by ordering it to pay its share of any special levy for any  
future repairs, despite dismissing the petition. The Strata Corporation cross appeals,  
arguing that the judge erred in applying the wrong test in interpreting s. 173(2) of the  
Act and misapprehending the evidence with respect to the necessity of the repairs.  
The Jamiesons appeal the dismissal of their application for documents on the  
grounds the application should not have been dismissed with the petition. Held: Both  
appeals allowed, cross appeal allowed. The order requiring Thurlow to pay its pro  
rata share of any special levy for future repairs of common property was made on  
the court’s own motion and without the benefit of argument from counsel. Regarding  
the cross appeal, the judge erred in requiring the risk to be imminent and requiring  
the repairs to be the minimum necessary to address the risk. The judge also  
misapprehended the expert evidence, which showed the building envelope was  
obsolete and needed to be replaced. Because the appeal is allowed from the  
dismissal of the petition and remitted for consideration of the trial court, the  
Jamiesons’ appeal is allowed and remitted as well.  
Paragraph  
Table of Contents  
Range  
INTRODUCTION: THE ISSUES ON APPEAL  
REASONS OF THE CHAMBERS JUDGE  
THE THURLOW APPEAL  
[1] - [13]  
[14] - [29]  
[30] - [44]  
[45] - [123]  
[46] - [69]  
[46] - [49]  
[50] - [53]  
THE STRATA CORPORATION CROSS APPEAL  
Argument  
Repair Necessary to Ensure Safety: the Applicable Test  
Misapprehension or Failure to Consider Evidence of Safety  
Concerns  
Consideration of an Irrelevant Factor  
[54] - [56]  
[57] - [60]  
Repair Necessary to Prevent Significant Loss or Damage:  
the Applicable Test  
Evidentiary Errors  
[61] - [69]  
[70] - [117]  
[70] - [70]  
[71] - [92]  
Discussion and Analysis  
Standard of Review  
Statutory Interpretation of s. 173  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 4  
Unauthorized Expenditures  
Special Levies  
[72] - [75]  
[76] - [92]  
Application of the Law to the Case  
Work Necessary to Ensure Safety  
Work Necessary to Prevent Loss or Damage  
[93] - [117]  
[95] - [101]  
[102] - [117]  
[118] - [123]  
[124] - [126]  
[127] - [130]  
Relief  
THE JAMIESONS’ APPEAL  
SUMMARY AND CONCLUSION  
Reasons for Judgment of the Honourable Mr. Justice Willcock:  
Introduction: the Issues on Appeal  
[1]  
The appellants in CA47534 are the Owners of Strata Plan VR 2213 (the  
“Strata Corporation”), a 21-storey high-rise building known as The Carlyle”, located  
at 1060 Alberni Street, Vancouver (the Building”). The Building consists of 146  
residential units in an 18-storey tower, and one commercial unit occupying the first  
three floors of the Building. The Strata Corporation is divided into two sections, a  
commercial section and residential section.  
[2]  
The Building is enveloped by an exterior insulation and finish system (EIFS),  
installed at the time of its construction in 1988, with an estimated life expectancy  
of 30 years. Beginning in or about 2018, the Strata Corporation began to note  
deficiencies in the EIFS, leading it to obtain reports from consultants and, ultimately,  
make a motion to approve a special resolution at its 2019 annual general meeting.  
The resolution called for the imposition of a special levy of $5,327,969 for the  
purpose of repairing the east and west elevations of the EIFS on the tower. The  
resolution failed to achieve the 3/4 of the votes needed for it to pass. There were 97  
votes in favour, 83.46 opposed and eight abstentions. The largest opposition to the  
resolution came from the commercial section, owned by the respondent Thurlow,  
holding 31.6% of the Strata Corporation votes.  
[3]  
The Strata Corporation then filed a petition seeking an order pursuant to  
s. 173(2) of the Strata Property Act, S.B.C. 1998, c. 43 [Act] that the special  
 
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 5  
resolution be approved, and authorizing the Strata Corporation to proceed as if it  
had been passed under s. 108(2) of the Act.  
[4]  
Section 108 provides:  
(1) The strata corporation may raise money from the owners by means of a  
special levy.  
(2) The strata corporation must calculate each strata lot's share of a special  
levy  
a) in accordance with section 99, 100 or 195, in which case  
the levy must be approved by a resolution passed by a  
3/4 vote at an annual or special general meeting, or  
(b) in another way that establishes a fair division of expenses  
for that particular levy, in which case the levy must be  
approved by a resolution passed by a unanimous vote at  
an annual or special general meeting.  
(3) The resolution to approve a special levy must set out all of the following:  
(a) the purpose of the levy;  
(b) the total amount of the levy;  
(c) the method used to determine each strata lot's share of  
the levy;  
(d) the amount of each strata lot's share of the levy;  
(e) the date by which the levy is to be paid or, if the levy is  
payable in instalments, the dates by which the instalments  
are to be paid.  
[5]  
Section 173, the provision relied upon by the Strata Corporation in this case,  
provides:  
(2) If, under section 108(2)(a),  
(a) a resolution is proposed to approve a special levy to raise  
money for the maintenance or repair of common property  
or common assets that is necessary to ensure safety or to  
prevent significant loss or damage, whether physical or  
otherwise, and  
(b) the number of votes cast in favour of the resolution is  
more than 1/2 of the votes cast on the resolution but less  
than the 3/4 vote required under section 108 (2) (a),  
the strata corporation may apply to the Supreme Court, on such notice as the  
court may require, for an order under subsection (4) of this section.  
...  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 6  
(4) On an application under subsection (2), the court may make an order  
approving the resolution and, in that event, the strata corporation may  
proceed as if the resolution had been passed under section 108(2)(a).  
[Emphasis added.]  
[6]  
Thurlow opposed the petition, alleging it had entered into an agreement with  
the Strata Corporation (the “Cost Allocation Agreement”) pursuant to which it  
renovated the part of the Building occupied by the commercial section (including its  
exterior envelope) without contribution from the residential section’s owners, and did  
so on the understanding that the residential section would fund the replacement of  
the exterior envelope of the residential tower without contribution from Thurlow. It  
argued the residential section owners are barred by contract or, in the alternative,  
are estopped from claiming contribution from the commercial section toward the cost  
of the repairs of the tower’s envelope. In addition, Thurlow pleaded and relied upon  
s. 195 of the Act, which provides:  
Expenses of section  
195 Subject to section 100 and the regulations, expenses of the strata  
corporation that relate solely to the strata lots in a section are shared by  
the owners of strata lots in the section and each strata lot's share of a  
contribution to the operating fund and contingency reserve fund is  
calculated as follows:  
unit entitlement of strata lot  
x
total contribution  
total unit entitlement of all strata lots in section  
[7]  
Thurlow further argued that the 2019 annual general meeting was affected by  
procedural irregularities and, last, that the proceedings commenced by petition were  
not properly authorized by the Strata Corporation.  
[8]  
Thurlow applied for an order that there be a trial of the proceeding, for an  
order that certain documents be produced, and for an interim injunction restraining  
the Strata Corporation from funding the legal proceedings initiated by the petition.  
[9]  
The appellants in CA47535, residential unit owners James and Gillian  
Jamieson, sought an order for the production of further and other documents by the  
Strata Corporation.  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 7  
[10] The petition came on for hearing on May 12, 2021. The following orders were  
made, for reasons indexed at 2021 BCSC 905:  
a) the petition was dismissed;  
b) the application of the respondents for trial of the proceeding was dismissed;  
c) the Strata Corporation was ordered to produce documents relating to legal  
expenses incurred in this litigation, but the balance of the document  
production applications (including the Jamiesonsapplication) was dismissed;  
d) the application for an interim injunction restraining the Strata Corporation from  
funding the proceedings was dismissed; and  
e) para. 6 of the order provided:  
Thurlow & Alberni Projects Ltd. is ordered to pay its share of any special levy  
for any future repairs and maintenance of the common property of the  
Building, including the exterior of the residential tower, in accordance with its  
unit entitlement, subject to further court order or the agreement of the Strata  
Corporation and owners as authorized in the Strata Property Act.  
[11] Thurlow contends that, having dismissed the petition, the judge erred in  
addressing Thurlow’s defences. It says the judge erred as a matter of law in failing to  
find that s. 195 of the Strata Property Act required that the cost of the repair or  
replacement of the EIFS be borne by the residential section alone, and further erred  
by granting what amounts to a mandatory quia timet injunction (in para. 6 of the  
entered order) which no party sought, and without affording the parties a hearing in  
relation to that relief.  
[12] The Jamiesons appeal the dismissal of their application for documents on the  
grounds that the application should not have been dismissed with the petition.  
[13] The Strata Corporation cross appeals, seeking an order setting aside the  
dismissal of the petition and an order from this Court allowing the petition or, in the  
alternative, remitting the petition to the trial court for hearing. The Strata Corporation  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 8  
says the chambers judge erred in applying the wrong test in interpreting the phrases  
“ensure safety” and “significant loss or damage” in s. 173(2):  
a) by applying a more stringent standard than that called for by the legislation;  
b) by considering irrelevant factors in holding that the repairs were not  
necessary; and  
c) by misapprehending the evidence with respect to the necessity of the repairs.  
Reasons of the Chambers Judge  
[14] At the hearing of the petition, Thurlow took the position that a building  
envelope condition assessment (“BECA”) and the opinion evidence in affidavits  
sworn by its principal author, Mr. Hoy, relied upon by the Strata Corporation, did not  
meet the requirements for admissibility in R. 11-6 of the Supreme Court Civil Rules.  
The chambers judge held that she would consider Mr. Hoy’s opinions because they  
formed the basis on which the Strata Corporation acted: at para. 130.  
Parenthetically, I note that Thurlow’s expert opinion evidence suffered from the  
same defects as that adduced by the Strata Corporationneither strictly complied  
with the requirements of R. 11-6.  
[15] Turning to the merits, the judge first addressed the question whether the  
repairs and maintenance sought were objectively necessary to ensure safety. There  
was evidence the entry of water into the Building had caused mould to develop in  
some interior locations. The judge found that the evidence did not support the  
conclusion that the mould was realand not trifling: at para. 135. She held that the  
evidence supported the conclusion that some limited units might have some  
elevated mould spores but there was not a systemic problem that posed a safety risk  
throughout the Building: at para. 136.  
 
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 9  
[16] She then considered the evidence that there was a risk that portions of the  
EIFS would fall off the Building, concluding that there was some risk of failure in  
certain locations but that risk did not justify full remediation of the EIFS:  
[138] It is clear that since the Updated BECA Report in July 2019 to  
present, a period of twenty-one months, there have been no falling panels.  
The evidence that the panels are at a risk of falling off is not supported by the  
totality of the engineering evidence. None of the experts emphasize any  
imminent risk of panels falling. The suggestion is that it is a potential risk at  
some point in the future. I am not prepared to find that a full remediation of  
the east elevation of the Building is necessary to ensure safety. I accept there  
is some risk of failure in the southern end of the east elevation of the Building.  
This is the one area the engineers agree needs to have work completed, and  
the Strata Corporation should address it, but it does not justify approving the  
entire s. 173 Petition.  
[17] The question whether the EIFS repairs were necessary to prevent significant  
loss or damage was considered by weighing the competing expert reports. The  
Strata Corporation’s consultant, Mr. Hoy, described the EIFS as obsolete and  
recommended full replacement of the building enclosure to a new rainscreen  
system, including the windows and patio doorson the east and west elevations of  
the Building. He acknowledged that some targeted repairs could extend the life of  
the EIFS, but not by more than ten years. However, this approach, in his view, would  
result in “a prolonged construction period and potentially a more costly approach.”  
[18] The judge noted that Thurlow’s expert, Mr. Narciso, was of the opinion further  
investigation was needed to assess what repairs are necessary for safety and to  
prevent significant loss or damage: at para. 144. The judge concluded:  
[147] The evidence does not currently support that the type of remediation  
requested in the special levy is necessary. Necessity has yet to be  
determined since I accept that the proper investigations have not yet been  
carried out.  
[148] The petitioner cited several cases in support of the s. 173 Petition.  
The evidence in the cases cited was far more substantial and indicated a  
greater risk of significant loss or damage than the evidence before me ...  
[19] She noted that a strata corporation can rely on s. 173(2) in support of a  
resolution aimed at avoiding a loss that may arise if money is wasted by performing  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 10  
temporary repairs rather than remedying a significant underlying problem: at  
para. 149. However, she concluded:  
[151] The evidence before me does not support that targeted repairs would  
be a waste of money by the owners. The EIFS will have to be replaced with a  
different system since it is, according to Mr. Hoy, obsolete. In contrast,  
Mr. Narciso states that the EIFS is a system designed to deflect, absorb, and  
desorb water away from the Building. These conflicting opinions are difficult  
to reconcile.  
[20] She also accepted that s. 173(2) can be relied upon in support of a resolution  
intended to effect repairs promptly so as to avoid the loss arising from increased  
costs if remediation is deferred. She acknowledged there is a risk of increased costs  
if there is a delay in effecting a full remediation, but appears to have concluded that  
the evidence did not establish that a full remediation will be required. She held:  
[153] There was no evidence before me that the costs for a full remediation  
would increase with time. I do accept there is a risk of increased costs if a full  
remediation is necessary but it is not clear on the evidence before me that a  
full remediation is required.  
[21] She then characterized the issue before her as whether to exercise a  
discretion to require owners to spend money on repairs, rather than a discretion to  
permit the majority to effect repairs without the support of 3/4 of the votes cast in  
support of the resolution:  
[154] The evidence before me does not support that I should exercise my  
discretion and require the owners to spend in excess of $5.3 million on the  
repairs. As such, the s. 173 Petition is dismissed.  
[22] Having dismissed the petition, it was unnecessary to address the  
respondent’s application to move the petition to the trial list, or the application for the  
production of documents (other than those related to legal fees incurred in the  
proceedings).  
[23] It was also unnecessary to consider Thurlow’s position that it could not be  
required to contribute to the special levy to fund the repair or replacement of the  
EIFS. As I have noted, Thurlow contended the Cost Allocation Agreement barred the  
Strata Corporation from requiring Thurlow to pay for work on the residential tower;  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 11  
or, in the alternative, that the residential section was estopped from claiming  
contribution from the commercial section. Further, it had pleaded s. 195 of the Act as  
a defence to the claim that it could properly be required to contribute to the special  
levy.  
[24] The judge nevertheless addressed the s. 195 argument, holding that s. 195  
applies only to limited common property, the exterior envelope of the tower is not  
limited common property, and Thurlow’s argument had no merit: at para. 169. While  
she set out her reasoning for that construction of s. 195, neither the analysis she  
employed nor the conclusion that s. 195 applies to limited common property had  
been urged upon her by counsel.  
[25] The chambers judge engaged in a limited weighing of Thurlow’s claim that the  
Cost Allocation Agreement barred the Strata Corporation from seeking contribution  
to the EIFS repair from Thurlow. On the evidence before her, she was unable to  
resolve that question, holding that whether there was such an agreement and, if so,  
what effect it had would “likely be determined in a further judicial proceeding: at  
para. 219. Despite this, she held, at para. 219:  
... However, until the existence of that agreement has been judicially  
considered I am of the view that Thurlow is legally obligated to pay for any  
special levy authorized either by a 3/4 vote resolution or in accordance with a  
s. 173 determination subject to any further court order.  
[26] That conclusion was made part of the order described at para. 250 of the  
reasons for judgment as follows:  
[250] A summary of the orders made is:  
1. The s. 173 petition is dismissed.  
6. Thurlow & Alberni Projects Ltd. is ordered to pay its share of any  
special levy for any future repairs and maintenance of the  
common property of the Building, including the exterior of the  
residential tower, in accordance with its unit entitlement, subject  
to further court order or the agreement of the Strata Corporation  
and owners as authorized in the Strata Property Act.  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 12  
[27] The judge did not expressly set out the basis for making an interim order  
before addressing Thurlow’s claims, except her observation that the unresolved  
issues with respect to Thurlow’s obligation to contribute to a special levy could  
postpone even urgent repairs to the exterior of the tower. She wrote: “That type of  
delay cannot be condoned since it will potentially put at risk the safety of the Building  
and cause significant loss and damage to the owners: at para. 195.  
[28] The judge was also unable to resolve the question whether the course of  
conduct of the parties in relation to the renovation of the commercial section gave  
rise to an estoppel that barred the Strata Corporation from requiring Thurlow to  
contribute to a special levy. That argument would also “have to wait for further  
judicial commentary”: at para. 220.  
[29] Finally, the chambers judge dealt with Thurlow’s application for particulars  
and documents related to the legal expense incurred in these proceedings, and its  
claim for an injunction, holding that the legal accounts and the amount paid in legal  
fees respecting the s. 173 petition should be provided to all owners.  
The Thurlow Appeal  
[30] Thurlow’s appeal hinges upon the fact that the chambers judge was unable to  
address its claims that the Cost Allocation Agreement or, in the alternative, estoppel,  
precludes the Strata Corporation from requiring it to contribute a pro rata share of  
the special levy. That being the case, Thurlow says, the chambers judge should not  
have made any order with respect to its obligation to pay a special levy to effect  
future repairs of the common property in accordance with its unit entitlement. For the  
following reasons, I agree.  
[31] The order in question was not sought by the Strata Corporation. It was made  
by the judge on her own motion. A court should not act on its own motion in the  
absence of extraordinary circumstances. As this Court noted in Jensen v. Ross,  
2014 BCCA 173:  
[24]  
Civil litigation is an adversarial process. The judge is the referee.  
Judges must leave it to the parties to determine the court processes that they  
 
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 13  
wish to engage to resolve a proceeding. Absent extraordinary circumstances  
such as those facing Chief Justice McEachern when picketers threatened to  
shut down the courthouse (Re British Columbia Government Employees  
Union et al. and Attorney General of British Columbia et al. (1982), 2 D.L.R.  
(4th) 705; aff’d (1985) 20 D.L.R (4th) 399; aff’d [1988] 2 S.C.R. 214), judges  
should not act on their own motion. To do so compromises their role of  
impartial arbitrator.  
[32] There are no extraordinary circumstances such as might justify an order on  
the court’s own motion in this case. No interim repairs or measures other than that  
proposed by the resolution were before the court.  
[33] The order requiring Thurlow to pay its pro rata share of any special levy for  
future repairs of common property is affected by error that may have arisen because  
it was made on the court’s own motion, and because the chambers judge did not  
have the advantage of the thorough submissions we have heard on how s. 195  
should be interpreted.  
[34] First, the order restricts Thurlow’s rights before adjudication of the merits of its  
defences. As Thurlow submits, the order bears the hallmarks of a quia timet order,  
one made to restrain wrongful acts that are threatened or imminent but have not yet  
commenced. The order was not made in the limited circumstances in which such an  
order may be justified. As McLachlin J.A. (as she was) noted in Canwest Pac. T.V.  
Inc. v. 147250 Can. Ltd. (1987), 14 B.C.L.R. (2d) 104 at 108109 (C.A.):  
In Aetna Fin. Services Ltd v. Feigelman, [[1985], 1 S.C.R. 2], the Supreme  
Court of Canada reviewed the principles governing the granting of orders  
prior to trial which are not confined to procedural matters, but which have the  
effect of altering the parties’ rights over their property in the pre-trial period. ...  
At p. 166, Estey J., for the court, distinguished between interlocutory  
applications of a procedural nature and those which affect the parties’  
substantive rights, stating:  
As a general proposition, it can be fairly stated that in the scheme of  
litigation in this country, orders other than purely procedural ones are  
difficult to obtain from the court prior to trial.  
After referring to the need of the applicant to show irreparable harm if the  
order sought does not go, he went on to state:  
A second and much higher hurdle facing the litigant seeking the  
exceptional order is the simple proposition that in our jurisprudence,  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 14  
execution cannot be obtained prior to judgment and judgment cannot  
be recovered before trial. Execution in this sense includes judicial  
orders impounding assets or otherwise restricting the rights of the  
defendant without a trial.  
These passages make it plain that the essential distinction is not between  
Mareva orders and other types of interlocutory orders, but between  
interlocutory orders of a procedural nature and interlocutory orders which  
restrict a party’s substantive rights before trial. The broad concept of  
execution as that word is used in Aetna extends to any order abrogating the  
defendant’s rights prior to trial. Such orders, apart from certain exceptions,  
will not be granted.  
[Underline emphasis added; italic emphasis original]  
[35] None of the exceptions described in Aetna are present in this case and for  
that reason, in my opinion, the order should not have been made.  
[36] Second, the only adjudication of the defences available to Thurlow was the  
judge’s conclusion that s. 195 of the Act had no application in this case and that  
there was, therefore, no statutory bar to the Strata Corporation seeking contribution  
to its expenses from Thurlow. Unfortunately, that distinct question of statutory  
interpretation was addressed without the benefit of the argument we have heard.  
[37] The chambers judge held that the meaning of s. 195 is clarified by s. 11.2 of  
the Regulations: at para. 172. It is unclear how reading s. 195 together with the  
regulation cited by the judge leads to the conclusion that s. 195 relates only to  
limited common property.  
[38] Section 195 sets out a manner in which expenses that relate solely to the  
strata lots in a section are to be borne. Such expenses generally are shared by the  
owners of strata lots in the section. Section 11.2 of the Regulations modifies that  
general cost sharing regime by providing a formula for cost sharing where a  
contribution to a strata corporation’s operating fund relates to and benefits only  
limited common property or only specific types of strata lots in a section. It reads as  
follows:  
11.2 (1) For the purposes of section 195 of the Act, but subject to a  
resolution under section 100 of the Act, if a contribution to the  
operating fund relates to and benefits only limited common property  
for the exclusive use of strata lots in a section, the contribution is  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 15  
shared only by owners of the strata lots entitled to use the limited  
common property, and each strata lot's share of that contribution is  
to be calculated in accordance with the following formula and not in  
accordance with the formula set out in section 195 of the Act:  
unit entitlement of strata lot in section  
x
contribution to operating fund  
total unit entitlement of all strata lots in section whose  
owners are entitled to use the limited common  
property to which the contribution relates  
(2) For the purposes of section 195 of the Act, but subject to a  
resolution under section 100 of the Act, if a contribution to the  
operating fund relates to and benefits only one type of strata lot in a  
section, and that type is identified as a type of strata lot in the  
bylaws of the section, the contribution is shared only by owners of  
strata lots of that type, and each strata lot's share of that  
contribution is to be calculated in accordance with the following  
formula and not in accordance with the formula set out in section  
195 of the Act:  
unit entitlement of strata lot in section  
x
contribution to operating fund  
total unit entitlement of all strata lots in section  
of the type to which the contribution relates  
(3) Subject to a resolution under section 100 or 108 (2) (b) of the Act, if  
a strata lot's share of a contribution to the operating fund is  
calculated in accordance with subsection (1) or (2), each strata lot's  
share of the total contribution to the contingency reserve fund or a  
special levy is to be calculated using the following formula:  
unit entitlement of strata lot in section  
total unit entitlement of all strata lots in section  
x
total contribution to contingency  
reserve fund or special levy  
[Emphasis added.]  
[39] Before us, Thurlow argues s. 195 of the Act and s. 11.2 of the Regulations,  
just like s. 99 of the Act and s. 6.4 of the Regulations, set out a general cost  
allocation rule and a formula for modifying the general rule where only certain  
owners benefit from the expenditure. Section 99 sets out the generally applicable  
obligation to contribute to operating funds and contingency reserves:  
99 (1) Subject to section 100, owners must contribute to the strata  
corporation their strata lots' shares of the total contributions budgeted for  
the operating fund and contingency reserve fund by means of strata fees  
calculated in accordance with this section and the regulations.  
(2)Subject to the regulations, the strata fees for a strata lot's share of the  
contribution to the operating fund and contingency reserve fund are  
calculated as follows:  
unit entitlement of strata lot  
x
total contribution  
total unit entitlement of all strata lots  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 16  
Section 6.4 of the Regulations modifies that obligation to account for expenses  
related to limited common property or specific types of strata units, an exception to  
the general rule:  
6.4 (1) For the purposes of section 99 of the Act, but subject to a  
resolution under section 100 of the Act, if a contribution to the  
operating fund relates to and benefits only limited common  
property, the contribution is shared only by owners of the strata lots  
entitled to use the limited common property, and each strata lot's  
share of that contribution is to be calculated in accordance with the  
following formula and not in accordance with the formula set out in  
section 99 (2) of the Act:  
unit entitlement of strata lot  
x
contribution to operating fund  
total unit entitlement of all strata lots whose  
owners are entitled to use the limited common  
property to which the contribution relates  
(2) For the purposes of section 99 of the Act, but subject to a  
resolution under section 100 of the Act, if a contribution to the  
operating fund relates to and benefits only one type of strata lot,  
and that type is identified as a type of strata lot in the bylaws of the  
strata corporation, the contribution is shared only by owners of  
strata lots of that type, and each strata lot's share of that  
contribution is to be calculated in accordance with the following  
formula and not in accordance with the formula set out in section  
99 (2) of the Act:  
unit entitlement of strata lot  
x
contribution to operating fund  
total unit entitlement of all strata lots  
of the type to which the contribution relates  
(3) Subject to a resolution under section 100 or 108 (2) (b) of the Act, if  
a strata lot's share of a contribution to the operating fund is  
calculated in accordance with subsection (1) or (2), each strata lot's  
share of the total contribution to the contingency reserve fund or a  
special levy is to be calculated using the following formula:  
unit entitlement of strata lot  
total unit entitlement of all strata lots  
x
total contribution to contingency  
reserve fund or special levy  
[Emphasis added.]  
[40] I agree with Thurlow that these provisions establish comparable schemes.  
Just as s. 99 describes a general rule for sharing the burden of contributions to the  
operating fund and contingency reserve fund, and s. 6.4 of the Regulations modifies  
the rule to account for contributions to funds that benefit only limited common  
property, s. 195 describes a rule for cost sharing between sections, and s. 11.2 of  
the Regulations modifies the rule where the expenditure benefits only certain owners  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 17  
in a section. Specific provisions in the Regulations govern cost sharing where  
expenditures benefit only limited common property, but the general provisions in the  
Act are not limited to common property. Counsel did not draw s. 99 of the Act and  
s. 6.4 of the Regulations to the attention of the chambers judge because no counsel  
argued that s. 195 applies only to limited common property. Nor did counsel address  
the jurisprudence relied upon by the chambers judge in support of her conclusion  
that s. 195 relates only to limited common property. In my view, the applicability of  
s. 195 was not adequately addressed.  
[41] If, as appears likely, the cost sharing formula set out in s. 195 applies to  
expenses that relate to all common property, its applicability in a particular case will  
hinge upon whether it can be shown that the expense in issue relates only to the  
strata lots in one section. Having dismissed the petition, the judge made an order  
with respect to Thurlow’s obligation to share the cost of “any special levy for any  
future repairs and maintenance of the common property of the Building, including the  
exterior of the residential tower” without regard to whether such levies might be  
made to pay expenses that relate to strata lots in only one section: at para. 250. In  
my opinion, no order should have been made with respect to Thurlow’s obligation to  
contribute to undefined future expenses.  
[42] I would not accede to the Strata Corporation’s argument that the judge’s  
interpretation of s. 195 is not appealable because it is not an order. Nor would I  
accede to its submission that “the judge’s statement that Thurlow remained legally  
obligated to pay its unit entitlement share was not an order’”.  
[43] The finding that Thurlow is obliged to pay its unit entitlement share of “any  
future repairs of the common property of the Building” is incorporated as para. 6 of  
the entered order. Despite that fact, the Strata Corporation says it is powerless to  
impose a special levy without Thurlow’s consent or a court order, and the impugned  
order is “subject to further court order or the agreement of the Strata Corporation  
and owners”. So, the Strata Corporation argues, the order will not have any effect  
before the matter comes before a court. The order, however, must be considered to  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 18  
have been intended to have some effect. While its effect in unclear, it is problematic.  
I would allow the appeal and set aside the order requiring Thurlow to pay its share of  
any special levy for any future repairs and maintenance of the common property of  
the Building in accordance with its unit entitlement.  
[44] I would do so, in part, because the judge’s interpretation of s. 195 of the Act  
was not founded upon consideration of the argument the parties might have made if  
the issue had been raised by the parties. The declaratory order should not stand as  
a dubious precedent.  
The Strata Corporation Cross Appeal  
[45] The Strata Corporation says the judge erred by:  
a) applying the wrong test in respect of the meanings of “ensure safety” and  
“significant loss or damage” in s. 173(2) by applying a more stringent  
standard;  
b) considering an irrelevant factorthe fact that no panels had fallen off the  
Buildingin holding that the repairs were not necessary for safety; and  
c) erroneously assessing the evidence, by  
i.  
ignoring evidence of the safety risk due to corroded fasteners;  
ii.  
misapprehending Mr. Narciso’s evidence regarding the EIFS  
and the conflict with Mr. Hoy’s opinion regarding whether it was  
obsolete and required full replacement;  
iii.  
iv.  
misapprehending the evidence that there was commonality  
between the engineering professionals that further  
investigations were required; and  
ignoring evidence of the increased cost of remediation of the  
EIFS over time, and that targeted repairs would be a waste of  
money.  
 
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 19  
Argument  
Repair Necessary to Ensure Safety: the Applicable Test  
[46] The Strata Corporation submits that in considering whether the repairs were  
necessary to ensure safety, the judge erred in focusing on imminence of the risk. It  
says there is nothing to suggest there must be an imminent risk of a potential safety  
issue in order to approve a special levy.  
[47] The Strata Corporation says there clearly is a safety risk. It adduced evidence  
that although there were no areas other than the southeast section with panels that  
had noticeably detached, other locations on the east wall had “the same conditions  
of compromised gypsum sheathing that have the same potential for panel  
separation, wall cladding collapse and falling object hazard”.  
[48] Further, it argues it was incorrect for the trial judge to say that none of the  
experts “emphasize any imminent risk of panels falling”: at para. 138. Mr. Hoy had  
reported that the panel adjacent to unit 410 and other panels on this east wall  
section were “at imminent risk for further cladding detachment and full collapse”, and  
Mr. Narciso did not dispute there was a risk of panels falling in that area.  
[49] Thurlow does not suggest that s. 173 is only intended to address repairs that  
are immediately necessary. It disputes the suggestion that the judge focused on the  
imminence of risk. It says she concluded that the proposed repairs were not  
necessary to ensure safety, not that the repairs were not immediately necessary.  
That is apparent in her conclusion that there was not a safety risk due to the  
existence of mould in the Building (at para. 136), and that “[t]he evidence that the  
panels are at a risk of falling off is not supported by the totality of the engineering  
evidence”: at para. 138. It says the finding that the proposed repairs were not  
necessary is a finding of fact unaffected by palpable error.  
Misapprehension or Failure to Consider Evidence of Safety Concerns  
[50] The Strata Corporation submits that the judge erred in ignoring the evidence  
of risk posed by corroded fasteners. The evidence was that there was systemic  
     
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 20  
corrosion of the fasteners supporting the attachment of both the window frames and  
the metal guardrails, and that “[f]ailure of the fastener could result in the detachment  
of the guardrail and window from the building”. Its expert evidence was that the “full  
assessment of the fasteners at both the window and guardrail locations is essential  
and should be completed within the next one (1) year to determine the level of risk”.  
[51] The Strata Corporation says this was as equally a high-priority issue as the  
repairs the judge found to require immediate attention, yet it is not mentioned in the  
judgment. Corrosion was apparent and confirmation of its presence did not depend  
on moisture readings, internal observations, or core openings.  
[52] In response, Thurlow says a judge is not required to refer to every item of  
evidence considered or to detail the way each item was assessed. Reasons are  
sufficient if they are responsive to the case’s live issues and the parties’ key  
arguments: R v. Walker, 2008 SCC 34 at para. 20. It says the failure to mention  
fasteners is not a critical omission.  
[53] Further, it argues, the expert opinion was that the fasteners should be  
assessed so that risk could be determined. Thurlow says the recommendation of a  
full assessment of the corroded fasteners is consistent with the conclusion that  
further investigation is required to assess safety risks, and with the dismissal of the  
petition.  
Consideration of an Irrelevant Factor  
[54] The judge placed some weight upon the fact that in the 21-month period  
between the preparation of the BECA report and the hearing of the petition, there  
had been no falling panels: at para. 138. The Strata Corporation contends that  
considering the fact that no panels had fallen was impermissible ex post facto  
reasoning and was an irrelevant factor. The question was whether there was a risk  
to safety at the time of the hearing, not whether the risk about which the Strata  
Corporation had been warned two years earlier had in fact materialized.  
 
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 21  
[55] Thurlow says the fact that not one panel had fallen in the interval referred to  
was relevant, and the judge did not say it was determinative. Her conclusions were  
reached expressly on the basis of “the totality of the engineering evidence”: at  
para. 138.  
[56] In my view, there is no merit in this ground of appeal and it may be dealt with  
summarily. Surely if panels had fallen off the Building after the passage of the  
resolution by a majority of votes and before the hearing of the petition, that would be  
considered to be highly relevant. The fact there had been no dramatic failure was  
equally of some evidentiary value. The Strata Corporation points to no error in  
principle in the consideration of this evidence.  
Repair Necessary to Prevent Significant Loss or Damage: the Applicable  
Test  
[57] The Strata Corporation says that while the judge correctly set out the  
meaning of “significant loss or damage” as referring to loss or damage that is  
“extensive or important enough to merit attention” she did not apply that standard  
when assessing the necessity of the proposed repair. Rather, it contends, she  
concluded that the repair in this case was not comparable to cases where a “greater  
risk of significant loss or damage” had been established by the petitioners: at  
para. 148. It says this approach was erroneous and resulted in the application of the  
wrong test: the only question was whether the test in s. 173 was met, not whether  
the damage was less severe than in other cases.  
[58] The Strata Corporation submits that the judge failed to grapple with whether  
the damage sought to be avoided by the repairs was “significant enough to merit  
attention”, and applied a more stringent standard.  
[59] Thurlow says the judge applied the proper test in the following passage:  
[145] The only common agreement is that some targeted repairs to the  
south-east elevation of the Building are necessary to fix the EIFS. Otherwise,  
the engineering evidence before me raises a significant dispute as to the  
recommendations made.  
...  
 
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 22  
[147] The evidence does not currently support that the type of remediation  
requested in the special levy is necessary. Necessity has yet to be  
determined since I accept that the proper investigations have not yet been  
carried out.  
[60] Thurlow argues the judge had proper regard to the cases, and was entitled to  
consider what evidence was found to satisfy the s. 173(2) test and support the  
exercise of the court’s discretion, and how they were different from the evidence  
before her. The Strata Corporation was found not to have done sufficient  
investigations and, Thurlow submits:  
... it was not proportionate. Instead of addressing the specific and immediate  
building envelope issues, which is largely restricted to the need to re-caulk  
and paint and the south east corner which was the subject of Mr. Jamieson’s  
“targeted resolution”, it stubbornly sought a very expensive, wide-scale repair  
of the entire east side, top to bottom of the 21-storey building. …  
[Footnote citations omitted.]  
Evidentiary Errors  
[61] Finally, the Strata Corporation alleges that the judge misapprehended the  
expert evidence.  
[62] It says the judge erroneously considered there to be conflicting opinions with  
respect to whether the EIFS was obsolete and needed to be replaced. Thurlow’s  
consultant Mr. Narciso expressed the opinion that “the EIFS is a system designed to  
deflect, absorb, and desorb water away from the Building”. The Strata Corporation  
says the trial judge mistakenly regarded that as an opinion that the system was not  
obsolete. The depreciation report, which Mr. Narcisco reviewed, noted that the EIFS  
had a typical service life of 30 years and was due for renewal in 2020.  
[63] Further, the Strata Corporation says the judge mistakenly considered that the  
Strata Corporation’s expert opinion evidence supported her conclusion that further  
investigations were required. It says it is a misapprehension of the BECA report to  
say that the “plan is that Williams [Engineering] would conduct further investigations  
in order to determine what work has to be performed”, or that Williams Engineering  
(Mr. Hoy) believed further investigations were necessary: at para. 146. Mr. Hoy  
 
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 23  
specifically stated that, in his view, the methods of investigation were sufficient, and,  
in particular, he disagreed with Mr. Narciso that additional core openings were  
necessary.  
[64] Finally, the Strata Corporation says the judge erred in ignoring evidence of  
the increased cost of remediation of the EIFS over time, and that targeted repairs  
would be a waste of money. Although she recognized these were factors she could  
take into account within the meaning of the word “otherwise” in s. 173(2), she stated  
there was no evidence that the cost of remediation would increase with time, and  
that while she accepted there was a risk of increased costs if a full remediation is  
necessary, she was of the view that it was not clear on the evidence that this was  
required. It says Mr. Narciso did not disagree that a full remediation was necessary;  
rather, he opined that it could not be concluded that it was necessary at the present  
time.  
[65] The Strata Corporation says targeted repairs will only defer “a necessary full  
wall cladding assembly replacement”, and, in order to be successful, the program of  
targeted repairs would need to be “demanding”, including a detailed building  
envelope condition assessment every two to three years, and repairs as necessary.  
The Strata Corporation says the owners would spend more money for this  
“demanding” targeted program and a new rainscreen system once those repairs no  
longer prevented water ingress, as compared to the new system alone.  
[66] The Strata Corporation says there was evidence (in the BECA report) that the  
cost for priorities 1 and 2 (replacement of the EIFS envelope on the east façade and  
part of the west façade), if completed in 18 months, would be $4.66 million, as  
compared to $5.324 million if completed in stages over 4.3 years. That is some  
measure of the extent to which delay will increase costs. It says that here, as in The  
Owners, Strata Plan VIS114 v. John Doe, 2015 BCSC 13 [Strata Plan VIS114], it  
would be “a waste of money to continue to pay for spot repairs that do not address  
the root causes of the harm experienced”: at para. 107.  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 24  
[67] Thurlow says nothing turns on whether the judge misapprehended  
Mr. Narcisco’s evidence with respect to obsolescence of the EIFS. The judge  
properly understood the substance of Mr. Narciso’s evidence as to the need for  
further investigation, which the judge accepted. It says the judge did not ignore or  
misapprehend evidence of increased cost of remediation of the EIFS over time or  
that targeted repairs would be a waste of money. Her view of the evidence simply  
differed from the Strata Corporation’s view, as reflected in the judgment at  
paras. 147155 cited above.  
[68] Mr. Narciso’s evidence was: “[I]n terms of proper sequencing, it is important  
to undertake further investigations which will then inform what work, if any, might be  
actually required. Otherwise both inefficient and unnecessary work, and  
unnecessary expense, may be incurred.”  
[69] Thurlow notes that the judge specifically distinguished Strata Plan VIS114. It  
says that in Strata Plan VIS114, the court found that the exercise of the court’s  
discretion was appropriate. In the case at bar, on the evidence, the court expressly  
determined it was not.  
Discussion and Analysis  
Standard of Review  
[70] There is no dispute with respect to the applicable standard of review. The  
assessment of the strength of the Strata Corporation’s petition required the  
chambers judge to exercise her discretion. The orders made attract a deferential  
standard of review. We cannot interfere in the exercise of that discretion unless we  
are satisfied that the chambers judge reached a conclusion which cannot reasonably  
be supported, either because of an error in principle or a palpable and overriding  
error. Thurlow says this is a fact-intensive case and the judge, after considering the  
evidence, concluded that it did not support a finding that the proposed remediation  
was necessary.  
   
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Statutory Interpretation of s. 173  
Page 25  
[71] Section 173 must be read in light of the whole scheme established by the  
Strata Property Act. The Act provides that expenditures by a Strata Corporation will  
ordinarily be approved in a budget or by resolution at a general meeting or special  
meeting of the corporation. Section 96 provides for expenditures from the  
contingency reserve fund. Certain ordinary and recurring expenditures from that fund  
must be approved by a resolution passed by a majority; other expenditures require  
a 3/4 vote. Section 97 provides that expenditures from the operating fund must be  
approved by a resolution passed by a 3/4 vote at an annual or special general  
meeting, or authorized in the corporation’s budget.  
Unauthorized Expenditures  
[72] Section 98 provides for an exception to those rules. It sheds some light on  
how s. 173 should be interpreted. It provides:  
98 (1)  
If a proposed expenditure has not been put forward for approval in  
the budget or at an annual or special general meeting, the strata  
corporation may only make the expenditure in accordance with this  
section.  
(3) The expenditure may be made out of the operating fund or  
contingency reserve fund if there are reasonable grounds to believe  
that an immediate expenditure is necessary to ensure safety or  
prevent significant loss or damage, whether physical or otherwise.  
(3.1) For the purposes of subsection (3), the prevention of significant  
loss includes, without limitation, the obtaining and maintaining by  
the strata corporation of insurance that is required under section  
149 or 150 or the strata corporation's bylaws.  
(5) Any expenditure under subsection (3) must not exceed the  
minimum amount needed to ensure safety or prevent significant  
loss or damage.  
[73] This provision, like s. 173, provides for expenditures that are necessary to  
ensure safety or prevent significant loss or damage. Section 98(3.1) by including,  
without limitation, the obtaining of insurance as an expense to prevent loss,  
   
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 26  
suggests that such losses are defined liberally, to include losses that are uncertain  
but foreseeable and not necessarily imminent.  
[74] The fact that the power to make unapproved expenditures may only be  
exercised where there are reasonable grounds to believe that an immediate  
expenditure is necessary suggests that without this express provision the power to  
make unauthorized expenditures might otherwise not have been so limited.  
[75] The express limitation on the corporation’s authority to make unapproved  
expenditures to those that are the minimum amount needed to ensure safety or  
prevent significant loss or damage suggests that the authority would not be so  
limited in the absence of s. 98(5). In other words, unless limited by s. 98(5), the  
corporation would have authority to use the operating fund or contingency reserve  
fund to undertake such work as it considered to be reasonably necessary to ensure  
safety or prevent significant loss or damage, which might be more than the minimum  
amount of work.  
Special Levies  
[76] The provision for a special levy cited above, s. 108, regulates the imposition  
of levies and the expenditure of funds raised by levy. It does not restrict the Strata  
Corporation’s right to impose a special levy or the purposes for which a levy may be  
imposed or spent, in any way.  
[77] The brake on the imposition of special levies is the requirement that they be  
approved by a 3/4 vote or, in the alternative, by a majority and court approval  
pursuant to s. 173.  
[78] Section 173 was enacted by a 2009 amendment to the Act, in force on  
December 12, 2013 (B.C. Reg 263/2013). Prior to its enactment, the inability of a  
strata corporation to maintain and repair common property was addressed by  
application pursuant to s. 165 of the Act, which permits the court to order the strata  
corporation to perform a duty it is required to perform under the Act, the bylaws or  
the rules, and to make any other orders the court considers necessary to give effect  
 
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 27  
to such an order. The approach taken to applications under this provision may be  
instructive. In general, for obvious reasons, judges have not been inclined to second  
guess recommendations to repair structures or to become directly involved in the  
timing or sequencing of repair.  
[79] In Enefer v. The Owners, Strata Plan LMS 1564, 2005 BCSC 1866, Taylor J.  
considered an application by an owner for an order authorizing a strata council to  
raise $850,000 by a levy to fund a major rehabilitation project. One respondent  
opposed the order sought, taking issue with certain of the expenses for which the  
levy was to be imposed. The court held that it was “not for this Court in essence to  
make orders … that restricts or limits the ability of council to perform its functions”: at  
para. 52.  
[80] In Browne et al. v. The Owners, Strata Plan 582, 2007 BCSC 206, Ralph J.  
heard a petition brought by unit owners for an order compelling the repair of the  
strata’s building envelope, and the authorization to issue a special assessment to  
the owners to enable the repair. There was an issue with respect to the appropriate  
scope of the necessary repair. The court recognized the strata corporation’s  
obligations to make repairs, but was not inclined to specify which repair option  
should be chosen by the strata corporation. A special levy was authorized which  
would permit the corporation to raise the funds necessary to perform both the  
immediate and medium-term work recommended by consultants. Justice Ralph  
noted that the evidence before him was that there was more than one option open to  
the strata corporation in responding to the damage: at para. 30. He adopted the  
view, expressed in Sterloff v. Plan No. VR 2613 (1994), 38 R.P.R. (2d) 102  
(B.C.S.C.), that the court should not interfere with a strata corporation’s discretion as  
to how it managed its repair and maintenance obligations, provided it acted in the  
best interests of all the owners: at para. 30.  
[81] He held, at para. 30: “the strata corporation is entitled to determine which  
actions to take in order to meet its statutory obligation” and:  
[31]  
I am satisfied that there must be an order under section 165 of  
the Strata Property Act that the strata corporation perform its statutory  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 28  
obligation to repair the building envelope. In performing its obligation the  
strata corporation must have regard to the observations and  
recommendations contained in [the expert’s] reports.  
[34]  
It is necessary to consider whether the court in directing the strata  
corporation to proceed should authorize and empower the strata corporation  
to issue a special assessment to the owners to a monetary limit. The strata  
corporation has opposed such an order on the ground that the petition linked  
the amount of $1,803,000 to the MH estimate of the cost of carrying out the  
work described as immediateand as medium term.  
[35]  
In my view, it is open to the court to authorize and empower the strata  
corporation to issue a special assessment to an amount "not exceeding"  
$1,803,000 without restricting the corporation's authority to determine a repair  
program that will accomplish its statutory obligation. There will therefore be  
an order that to finance the building repair work the corporation is authorized  
to issue a special assessment to the owners, based on their respective unit  
entitlement, not exceeding $1,803,000 and payable in such manner as the  
strata council may decide.  
[Emphasis added.]  
[82] Section 173 gave strata corporations an additional tool to enable them to  
discharge their statutory obligations. It was comprehensively addressed by  
Fitzpatrick J. in Strata Plan VIS114. She noted that the section was enacted by way  
of the Strata Property Amendment Act, 2009, and that Hansard for September 24,  
2009 records the following description of the relevant amendment by the Honourable  
Rich Coleman (then Minister of Housing):  
[T]his bill enhances consumer protection. It gives owners, former owners  
and potential purchasers greater rights to access additional information. It  
ensures that special levies can't be mingled with other strata funds and are  
only invested in appropriate, insured accounts. It allows the courts to break a  
deadlock when the strata can't quite get a three-quarter vote needed to make  
a crucial repair via a special levy.  
[Emphasis added by Fitzpatrick J.]  
British Columbia, Legislative Assembly, Official Report of the Debates  
(Hansard), 39th Parl., 1st Sess., Vol. 3, No. 5 (24 September 2009) at 1635  
(Hon. Rich Coleman).  
[83] Justice Fitzpatrick rejected the submission that the court should only exercise  
its discretion under s. 173(2) where the engineering evidence clearly establishes that  
the repairs are immediately necessary to ensure safety or prevent significant loss or  
damage: at para. 53. She considered that argument to be a conflation of the  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 29  
requirements under s. 173(2) with the “almost identical” wording of s. 98(3) of the  
Act: at para. 55. She noted that the authority to make unauthorized expenditures  
under s. 98 was constrained by the requirement that the expenditure not exceed the  
minimum amount needed to ensure safety or prevent significant loss or damage: at  
para. 56. The argument that the discretion under s. 173 should be similarly  
constrained was rejected. She held:  
[58]  
In my view, it is illogical to analogize the situation addressed in  
s. 173(2) with that addressed in s. 98. In the first place, as argued by the  
strata corporation, s. 98 deals with unauthorized expenditures whereas  
s. 173(2) addresses a situation where a clear majority vote has been  
received, but not the special majority vote. Accordingly, the premise is that  
the expenditures have been considered by the owners but the special  
majority vote was not obtained to proceed. In addition, s. 98 is clearly  
intended to address urgent situations given the reference to the immediacy of  
the expenditures being necessary. This is confirmed by reference to the  
requirement in s. 98(5) that only the minimum amount need be spent. No  
such limits are imposed or limiting language used in s. 173(2).  
[59]  
Accordingly, under s. 173(2), the requirement is only whether the  
repairs and maintenance are necessaryto ensure safety or prevent loss  
and damage.  
[84] In summary, Fitzpatrick J. described the appropriate considerations governing  
the exercise of the discretion as follows:  
[135] Section 173(2) is a new tool available to strata corporations to seek  
court intervention in appropriate circumstances. I would not, however, expect  
that court intervention would be appropriate simply because there is a  
dispute. Clearly, the test under s. 173(2) must be met before the court's  
discretion can be exercised. Importantly, there must be issues of safety or in  
the event of loss or damage, that loss or damage must be significant”.  
Further, the court's discretion is only to be exercised in appropriate  
circumstances and in accordance with the overall objectives in the Act.  
[Emphasis added.]  
[85] Section 165 empowers the court to make orders necessary to permit a strata  
corporation to discharge its statutory obligation to maintain the strata’s property.  
When it has been invoked, as we have seen, the courts have approached the  
management decisions of strata corporations with deference. As Ralph J. observed  
in Browne: “the strata corporation is entitled to determine which actions to take in  
order to meet its statutory obligation”: at para. 30.  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 30  
[86] The same is true, in my view, when s. 173(2) is invoked. Before an  
application for court approval can be brought, the Strata Corporation must have  
proposed a resolution to approve a special levy. The levy must be intended to raise  
money for the maintenance or repair of common property, or common assets the  
Strata Corporation considers to be necessary to ensure safety or to prevent  
significant loss or damage. The Act requires the resolution to specify, among other  
particulars, the purpose of the levy; its total amount; and the date by which the levy  
is to be paid or, if the levy is payable in instalments, the dates by which the  
instalments are to be paid: at s. 108(3). Because the Act gives the court the power to  
approve a special resolution, rather than the power to draft the resolution, it leaves in  
the hands of the Strata Corporation the responsibility for formulation of the resolution  
and discretion to determine the timing and scope of repairs. It would be unworkable  
to leave such matters in the hands of the courts.  
[87] For that reason, in my view, Fitzpatrick J. was correct in Strata Plan VIS114,  
to conclude, after citing Weir v. Owners, Strata Plan NW 17, 2010 BCSC 784, and  
Browne, that the starting point for the analysis should be deference to the decision  
made by the strata council, approved by the majority of owners: at para. 68.  
Deferring to the strata corporation in that case, she concluded that after a full  
consideration of the matter, the strata corporation has concluded, I think reasonably,  
that the time to proceed is now: at para. 71.  
[88] A similar approach was taken by Pearlman J. in The Owners, Strata Plan  
LMS 1383, 2015 BCSC 1816, where he concluded that the strata corporation was  
entitled to rely on the professional advice it had received (and agreed himself that  
the repair proposed was necessary):  
[58]  
In my view, giving s. 173(2) its plain meaning and taking into account  
the purpose of s. 173, which is to provide the means for strata corporations in  
appropriate cases to be able to proceed with necessary repairs and  
maintenance to common property in circumstances where they obtain  
majority support but not a three-quarter vote, I find that the appropriate test of  
what constitutes significantdamage or loss is whether the damage or loss is  
extensive or important enough to merit attention.  
[59]  
The strata corporation has relied on the advice it has received from  
the engineers. It is entitled to do so. Bearing in mind all of the engineering  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 31  
evidence, including the evidence of Levelton, I find that the repairs and  
maintenance proposed by the strata corporation through the resolution are  
repairs and maintenance necessary to prevent significant loss or damage to  
the common property.  
[89] In The Owners, Strata Plan NW 1815 v. Aradi, 2016 BCSC 105, the  
respondent, opposing court approval of a proposed resolution, argued that because  
the language contained in s. 173(a) and (b) “empowers a court to order mandatory  
or prohibitory relief of an injunctive nature, a test similar to that which must be met  
to obtain injunctive relief should be employed. Justice W.J. Harris rejected that  
submission, and instead adopted Fitzpatrick J.’s description of the discretion to  
make an order pursuant to s. 173 in appropriate circumstances and in accordance  
with the overall objectives in the Act: at para. 57, citing Strata Plan VIS114 at  
para. 135. She wrote:  
[60]  
I conclude from these authorities that the court has a broad discretion  
under s. 173 of the Act. The exercise of its authority is to be guided by a  
consideration of the scheme of the legislation, its overall objectives, and the  
circumstances giving rise to the application. The interests of the strata  
corporation must be balanced against the interests of the owner or other  
person against whom the order is sought, within this legislative context.  
[90] In Santos v. The Owners, Strata Plan LMS 1509, 2016 BCSC 1775,  
Morellato J. considered applications to appoint an administrator of a dysfunctional  
strata corporation and to approve a special levy to permit repairs to be effected. She  
held:  
[56]  
It is noteworthy that both s. 165 and s. 174 are remedial in effect and  
are situated within Part 10 of the Act, which deals with Legal Proceedings  
and Dispute Resolution. Both provisions provide the Court with a  
discretionary power to provide remedies on an application to the Court.  
These sections provide distinctive remedies to address different disputes  
affecting a strata corporation. In this case, appointing an administrator to  
remedy executive dysfunction while also issuing a special levy to remedy  
legislative deadlock would give effect to the remedial purpose of these  
provisions and would, in my view, be in the best interests of the strata  
corporation. In reading the Act as a whole, it is clear that these are not  
mutually exclusive remedies and that there is nothing to prohibit this Court  
from ordering these remedies concurrently.  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 32  
[91] She held that the enactment of s. 173 did not preclude the court from making  
the orders that might formerly have been made pursuant to s. 165, even where less  
than a bare majority of owners approved the proposed expenditure. She concluded:  
[59]  
While I agree that s. 173(2) provides an additional remedy to owners  
who are seeking approval of a levy in circumstances were a 3/4 vote is  
defeated but where a bare majority approves the levy, I do not accept that  
that the enactment of this provision circumscribes the authority and the  
discretion of this Court to issue a special levy in the proper circumstances,  
even if less than a bare majority of owners approve the levy. Put  
differently, the broad remedial powers of the Court under the Act have been  
expanded rather than constrained by the enactment of s. 173(2).  
[92] I agree with the conclusions of Fitzpatrick, Pearlman and Morellato JJ. The  
provision in question is remedial. It should be read purposively with a view toward  
permitting strata corporations to discharge their statutory obligation to maintain and  
repair the strata property. It permits the court to authorize special levies to effect  
repairs that are necessary, but does not require that the repairs be immediately  
necessary or that the proposed repair be the minimum necessary to address the  
problem. It should be read in a manner that permits the Strata Corporation to  
determine the timing and method of repair. The Act requires the Strata Corporation  
to maintain and repair its common property. Section 173, seen in that context, is not  
intended to place the court in the position of overseeing or managing repairs but,  
rather, to afford a tool to break a deadlock and permit a simple majority to resolve to  
effect necessary repairs. It would be contrary to the remedial intention of the  
provisions to require the court to intensively analyse the scope of the work the strata  
corporation proposes to do. Doing so will only increase costs to owners and fail to  
address the deadlock the legislature clearly intended to resolve.  
Application of the Law to the Case  
[93] The chambers judge noted the Strata Corporation has the onus of proving on  
a balance of probabilities that the repairs are necessary to ensure safety or to  
prevent significant loss or damage, physical or otherwise, and that “significant loss  
or damage” is that which is considered to be “extensive or important enough to merit  
attention”: at paras. 113114. It is correct that in order to invoke the court’s authority  
 
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 33  
to make an order under s. 173(2), the Strata Corporation must establish the work  
proposed is necessary. It is not, however, necessary for the Strata Corporation to  
establish that the work must be done immediately, that there is an imminent risk to  
persons or property or that the work proposed is the minimum necessary to address  
the identified risk.  
[94] In my view, the judge erred in assessing the necessity of the proposed work  
to ensure safety and prevent damage by seeking to determine whether the work was  
necessary to address an immediate safety risk and no more than presently  
necessary to ensure safety or prevent damage.  
Work Necessary to Ensure Safety  
[95] Dealing with the evidence of mould, the judge concluded that there was  
equivocal evidence of the presence of elevated levels of mould and the extent of the  
mould problem. There was insufficient evidence that a safety risk was posed by the  
presence of mould. She concluded: “it is not a systemic problem throughout the  
Building”: at para. 136. That conclusion cannot be said to be erroneous. It turns on  
the judge’s assessment of the evidence, to which we must defer, and does not  
reflect the application of an erroneous test.  
[96] Dealing with the evidence of deterioration of the EIFS and the risk of portions  
of the Building falling and endangering pedestrians or residents” (at para. 137), she  
concluded [t]he evidence that the panels are at a risk of falling off is not supported  
by the totality of the engineering evidence: at para. 138.  
[97] That conclusion, however, is difficult to reconcile with the findings that  
immediately follow:  
[138] ... The suggestion is that it is a potential risk at some point in the  
future. I am not prepared to find that a full remediation of the east elevation of  
the Building is necessary to ensure safety. I accept there is some risk of  
failure in the southern end of the east elevation of the Building. This is the  
one area the engineers agree needs to have work completed, and the Strata  
Corporation should address it, but it does not justify approving the entire  
s. 173 Petition.  
[Emphasis added.]  
 
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 34  
[98] Taken as a whole, these findings suggest that the judge found that there is a  
risk portions of the Building’s exterior cladding will fall off as a result of its  
deteriorationclearly a safety riskbut that the risk does not yet require the  
extensive work proposed by the Strata Corporation. For that reason, she was not  
prepared to approve the “entire s. 173 Petition”. In part, that conclusion appears to  
have been founded upon the view that the entire risk the Strata Corporation sought  
to address was not imminent, and that which was imminent might be addressed by  
less extensive work than proposed.  
[99] In my view, once it was determined that the deterioration gave rise to a safety  
risk, it was an error to consider whether the repair the Strata Corporation sought to  
conduct was immediately necessary or whether it was the minimum work necessary  
to address the deterioration that gave rise to what was clearly identified as a safety  
risk. If the evidence established the existence of a safety risk, and that one  
reasonable way to deal with that risk was to do work as extensive as that proposed  
by the Strata Corporation, then the threshold for making a s. 173(2) order was  
overcome.  
[100] That being the case, the judge should have considered factors going to the  
exercise of her discretion to approve the special resolution, including:  
a) whether the Strata Corporation acted in good faith;  
b) whether there were procedural irregularities in the manner in which the  
resolution was proposed and passed by a majority of the votes cast at its  
special or annual general meeting;  
c) whether the Strata Corporation acted reasonably on the strength of  
professional advice in seeking to impose the special levy; and  
d) whether court approval of the resolution would unfairly prejudice the owners  
in the minority.  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 35  
[101] The judge did not engage in that exercise, having concluded that all of the  
proposed work was not imminently required to address the identified safety risk.  
Work Necessary to Prevent Loss or Damage  
[102] Section 173(2)(a) provides that a special levy must be “to prevent significant  
loss or damage, whether physical or otherwise”. I will first address the evidence  
regarding physical loss or damage, and then turn to economic loss arising from the  
potential for increased costs if the remediation is delayed.  
[103] Mr. Hoy identified multiple areas where repair was necessary to avoid  
damage due to deterioration of the EIFS and water entering the Building. These  
formed the basis for, among others, the following recommendations:  
a) that the EIFS wall areas on the east elevation of the building (facing  
Burrard St.) be replaced within a year, from top to bottom, with a new  
rainscreen wall assembly system, starting with the south-east wall  
section that had already separated, to prevent further damage,  
potential for wall cladding collapse, and falling object hazard;  
b) that the EIFS wall areas on the south-east elevation of the building  
(the corner facing Burrard and Robson Sts.) be replaced within three  
years with a new rainscreen wall assembly system,  
c) that the EIFS wall areas at the west elevation (facing Thurlow St.)  
north of the balcony be replaced with new rainscreen wall assembly  
system within three years due to compromised gypsum sheathing and  
potential for panel separation, wall cladding collapse and falling object  
hazard.  
[104] Mr. Hoy was confident that there had been sufficient investigation to establish  
that the proposed work on the east and west elevations of the Building was  
necessary. He deposed:  
6.  
Appropriate and reasonable best practice testing/examination  
protocols were used to assess the Strata Corporation's building enclosure  
(the EIFS). Every building envelope is unique, and the methodology used to  
assess a building envelope will change based on local factors. In this case,  
the following factors were considered when determining the appropriate  
assessment methodology for the EIFS: the age of the EIFS, the original  
exterior cladding assembly design, the fact that the EIFS' cladding was  
designed as a face-sealed system, the EIFS' maintenance history, the failure  
history of this type of system in the greater Vancouver area, and the  
requirements of the local authority having jurisdiction over the EIFS'  
remediation. With the aforementioned factors in mind, the methodology used  
 
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 36  
to assess the EIFS, including the number of core openings undertaken, was  
determined to be sufficient in the circumstances.  
13.  
In the context of typical building envelope remedial work, the repair  
scope is developed with a best practice design approach, sound building  
envelope construction methodology, and the requirements of the authority  
having jurisdiction. For the City of Vancouver, for example, when replacing a  
segment of wall, it must adhere to current best practices and new rainscreen  
technology. These standards apply to the Strata Corporation. To meet that  
criteria, it is generally accepted that the wall area to be repaired include up to  
a change-of-plane, and/or stack. It would also be impractical to only replace  
one segment of an elevation, as this would be visually evident and would  
likely be rejected by the local planning authorities due to alteration of the  
building appearance. For efficacy, a single exploratory opening may be  
adequate to conclude the fate of a wall segment, wall plane or elevation, and  
whether the wall system is deemed suitable for the local environment. In this  
case, a single exploratory opening was deemed to be adequate and effective  
to conclude the fate of the wall segment.  
[105] Mr. Narcisco, on the other hand, was of the view that the investigation  
conducted by and for Mr. Hoy was superficial, and did not adequately address the  
extent to which moisture penetration had caused panel separation and a risk of  
collapse. He conceded that there was evidence of some significant damage that  
required at least targeted repairs, but questioned the extent of the required repairs.  
In his first affidavit he states:  
16.  
Based on the BECA Report, we believe there is currently enough  
information to conclude that the southern end of the east elevation of the  
building where the EIFS is sagging is damaged and requires targeted repair.  
[106] However, he says:  
13. [T]he Building has an EIFS system. The EIFS system is designed to  
deflect, absorb and desorb water away from the building. In other words, it is  
expected to get wet. The presence of moisture alone, which is what the  
impedance scanner [the testing device relied upon by Mr. Hoy] detects, is  
insufficient to conclude that there is moisture-relateddamage. What is critical  
is the condition of the materials behind the cladding, which requires  
destructive testing to explore.  
[107] In addressing the question whether targeted repairs would suffice in this  
instance, the judge appears to have proceeded on the basis that it was not  
established that the EIFS was “obsolete” and would inevitably have to be replaced at  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 37  
the end of its expected lifespan. For ease of reference, I repeat here passages from  
her reasons I have cited above. She wrote:  
[151] The evidence before me does not support that targeted repairs would  
be a waste of money by the owners. The EIFS will have to be replaced with a  
different system since it is, according to Mr. Hoy, obsolete. In contrast,  
Mr. Narciso states that the EIFS is a system designed to deflect, absorb, and  
desorb water away from the Building. These conflicting opinions are difficult  
to reconcile.  
[152] The Depreciation Report estimated the EIFS life expectancy was until  
2020. It is not clear how much longer after that date will it remain serviceable.  
However, the Strata Corporation is in the process of obtaining an updated  
depreciation report as required by the Act. Hopefully this will provide further  
information for the owners to consider when deciding what repairs are  
necessary and should be undertaken.  
[Emphasis added.]  
[108] This analysis indicates that the judge was not satisfied that the EIFS envelope  
on the east and west elevations of the Building will have to be replaced, and that she  
was of the view that the evidence of Mr. Hoy and Mr. Narcisco conflicted and was  
“difficult to reconcile”. With respect, these views do not appear to be consistent with  
the evidence.  
[109] In his October 2016 depreciation report, Mr. Narcisco produced life cycle  
renewal cost tables based on predicted replacement dates, assuming reasonable  
and ongoing maintenance was being performed. The building envelope was  
described in that report as an EIFS system installed in 1988 with a typical service life  
of 30 years, an effective age of 25 years, a remaining service life of 5 years and a  
“planned renewal date” of 2020. The report included the following notes:  
Description: The Exterior Insulation Finish System (EIFS) consists of an  
acrylic coating applied to reinforcing mesh, attached to rigid insulation and a  
sheathing material. The cladding system does not feature a drainage cavity  
behind the outer water shedding surface and is considered a face-sealed”  
assembly. This type of assembly has limited capacity to drain any moisture  
that becomes trapped in the wall assembly.  
Condition: The EIFS cladding is generally in serviceable condition. The EIFS  
assembly was observed to have deteriorated acrylic coating in some  
locations exposing the insulation, cracks in the acrylic coating and organic  
growth and algae staining. Evidence of EIFS repairs was noted in a two  
locations on the south and east elevations. Moisture ingress was reported at  
penthouse unit 8 end unit 402 near the windows on the north and north west  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 38  
elevation, respectively. Failing sealant and EIFS at the transition between the  
tower roof membrane and the building wall above penthouse unit 8 provide  
moisture with a direct path to enter the wall assembly and is likely the cause  
of leaking at the unit.  
Short-Term Action Required: Perform further review and repairs to address  
leakage at the EIFS/window transition at unit 1704 and monitor vent locations  
at residential balconies for moisture ingress.  
Comments: An allowance for targeted repairs or an engineering assessment  
of the cladding system has been included prior to full scale renewal. It should  
be noted that premature failure of EIFS wall cladding has been observed in  
the pacific northwest. The Strata should regularly review the EIFS cladding  
and complete repairs as required to maintain the integrity of the water  
shedding surface in an effort to mitigate potential water penetration issues.  
[Emphasis added.]  
[110] Mr. Hoy’s updated BECA report of July 2016 included the following  
observations:  
The exterior cladding system is obsolete and notequipped lo effectively  
preventwater ingress and drainage without implementation of a successful  
and demanding maintenance and renewal program. There are five main  
categories of concern (list by priority):  
1. The EIFS wall assembly backed by gypsum sheathing and  
steel stud framing;  
2. The EIFS wall assembly at the balconies and wall interfacing  
(including guard fastening);  
3. The window system, including window fastening;  
4. Pool area;  
5. The balcony drainage system.  
Face-seal EIFS, as installed on the building, has proven to be ineffective at  
providing long term moisture protection of the underlying building envelope  
components without diligent monitoring and maintenance of the sealant  
joints, connections, and acrylic finish. A more suitable system for our coastal  
climate, that is subject to high annual rainfall and driving rain, is a wall  
assembly incorporating a rainscreen system with more durablematerials.  
Utilizing a rainscreen system will help the management of any water ingress  
and mitigate damage by using pressure equalization and promoting the  
principles of drainageand drying and deflection. Exterior insulation willhave to  
be included to match the original intent for exterior thermal value.  
[Emphasis added.]  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 39  
[111] Mr. Narcisco took issue with the extent of the damage that had already been  
sustained as a result of water penetration and with Mr. Hoy’s description of the work  
now required but, as we have seen, his depreciation report expressed the view that  
the EIFS would reach the end of its expected lifespan in 2020 and that it would then  
require renewal. He described the inherent deficiency of EIFS systems when he  
noted that [t]he cladding system does not feature a drainage cavity behind the  
outer water shedding surface and the assembly has limited capacity to drain any  
moisture that becomes trapped within it.Mr. Narciso also discusses targeted  
repairs as measures to be taken pending full scale renewal, and he notes that  
premature failure of EIFS systems has been observed in the pacific northwest.  
[112] The appellant says these opinions were not in conflict and there ought to  
have been no difficulty reconciling them. I agree. Both experts agreed that there is  
existing damage at the southern end of the east elevation of the building.  
Mr. Narcisco did not dispute the evidence that the EIFS is obsolete. There was no  
doubt that it is at the end of its anticipated lifespan and will require replacement.  
[113] The judge’s conclusion (at para. 153) that it was not clear on the evidence  
before her “that a full remediation is required” must either have been based upon a  
misapprehension of that aspect of Mr. Narcisco’s evidence, or have been intended  
to say that there was no evidence that a full remediation is immediately required.  
[114] The judge also recognized that the threshold in s. 173(2) of establishing that  
maintenance or repair of common property is necessary to “prevent significant loss  
or damage, whether physical or otherwise”, can be met by establishing that the  
repair proposed by a strata corporation is necessary to avoid potentially greater  
repair costs in the future, though she did not find that threshold was met in this case:  
[149] Case authorities have interpreted the word “otherwise” in s. 173(2)(a)  
of the Act to include loss of value to the units, potential for waste of money if  
only targeted repairs are done, and the potential for increased costs when the  
remediation does take place.  
[150] There was no evidence before me to support any loss of value of the  
residential units in the Building.  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 40  
[151] The evidence before me does not support that targeted repairs would  
be a waste of money by the owners. The EIFS will have to be replaced with a  
different system since it is, according to Mr. Hoy, obsolete. In contrast,  
Mr. Narciso states that the EIFS is a system designed to deflect, absorb, and  
desorb water away from the Building. These conflicting opinions are difficult  
to reconcile.  
[152] The Depreciation Report estimated the EIFS life expectancy was until  
2020. It is not clear how much longer after that date will it remain serviceable.  
However, the Strata Corporation is in the process of obtaining an updated  
depreciation report as required by the Act. Hopefully this will provide further  
information for the owners to consider when deciding what repairs are  
necessary and should be undertaken.  
[153] There was no evidence before me that the costs for a full remediation  
would increase with time. I do accept there is a risk of increased costs if a full  
remediation is necessary but it is not clear on the evidence before me that a  
full remediation is required.  
As stated previously, in my view, the judge misapprehended the evidence in  
concluding the experts conflicted in whether the EIFS was “obsolete” and would  
inevitably have to be replaced at the end of its expected lifespan.  
[115] I would not accede to Thurlow’s argument that nothing turns on whether the  
judge misapprehended Mr. Narcisco’s evidence with respect to obsolescence of the  
EIFS because she properly understood the substance of Mr. Narciso’s evidence as  
to the need for further investigation. The necessity and value of investigation must  
be weighed in light of the probability that full remediation will be required. Further  
investigation to determine the extent of the needed temporary repairs may itself be a  
wasted expense if full scale renewal is inevitable. The call for further investigation is  
closely tied to the question whether full scale renewal is inevitable and will be  
necessary soon. Misapprehension of the evidence in that regard undermines the  
conclusion that further investigation is called for before approval of the Strata  
Corporation’s resolution to effect repairs.  
[116] For that reason, in my view, the judge’s conclusion that the Strata Corporation  
has not established that the planned repairs are necessary to avoid economic loss is  
flawed. I would set her order dismissing the petition aside.  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 41  
[117] Further, the trial judge’s conclusion that further investigation was necessary  
reflected her view that she had to be satisfied that the proposed work was necessary  
to address an imminent threat of damage and was the least expensive means to do  
so. In my opinion, those choices, if reasonably made by the Strata Corporation  
acting in good faith on the strength of professional advice and in a manner that is not  
unfairly prejudicial to the minority owners, are for the Strata Corporation.  
Relief  
[118] It is, of course, open to us to make or give any order that could have been  
made or given by the chambers judge, including an order pursuant to s. 173(4)  
approving the resolution, permitting the Strata Corporation to proceed as if the  
resolution had been passed under s. 108(2)(a).  
[119] In my view, however, there are several reasons why we should not do so.  
[120] First, a resolution must describe the obligation of strata lot owners to  
contribute to the levy imposed and, as I have noted, Thurlow’s liability has not been  
settled and the resolution does not set out a method of determining that question on  
an interim or final basis (nor have we been asked to do so).  
[121] Second, there are factors going to the exercise of the discretion to grant the  
order that have not been addressed by the trial court, and I am of the view that a  
court of first instance should first address all such considerations.  
[122] Last, almost three years have passed since consideration of the resolution  
and, in my view, the trial court should reconsider the petition, on such evidence as it  
considers appropriate to receive, to ensure that the court does not endorse a  
resolution that has been overtaken by events.  
[123] I would remit the petition to the trial court for reconsideration.  
The Jamiesons’ Appeal  
[124] The Jamiesonsappeal may be dealt with summarily. They argue that the  
Strata Property Act requires the Strata Corporation to maintain certain classes of  
   
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 42  
documents and to provide them to owners on request. They sought documents that,  
in their view, related to the order sought by the Strata Corporation in the proceedings  
commenced by petition. There was no freestanding application for those documents.  
When the petition was dismissed, the chambers judge dismissed the Jamiesons’  
application as moot. The judge held:  
[161] The Applications seek extensive document production. Since I have  
dismissed the s. 173 Petition, I will not comment on anyof the applicationsfor  
production of documents, except where I discuss the legal fees incurred by  
the Strata Corporation later in these reasons.  
[162] I will add the following comments for the benefit of the parties.  
Document production is strongly guided by the pleadings and governed by  
the Supreme Court Civil Rules. If an action is brought under s. 164 of the Act,  
that action would determine the parameters of the document production.  
Section 169 of the Act provides direction on what information and documents  
are producible.  
[125] The Jamiesons appeal, arguing that the trial judge erred in law by not  
considering and ruling on the application for documents which was based on a  
statutory right. In reply, the Strata Corporation says the judge committed no error in  
declining to address the application. Because she dismissed the petition, the  
applications were certainly moot. The Strata Corporation says it is open to the  
Jamiesons to seek production of documents pursuant to the provisions of the Act in  
separate proceedings, other than those that were commenced by the Strata  
Corporation for an order approving a special resolution.  
[126] In my view, the Strata Corporation is correct to say that the chambers judge,  
having dismissed the petition, could dismiss the application for production of  
documents in those proceedings. However, because I would allow the appeal from  
the dismissal of the petition and remit the petition for consideration to the trial court,  
it follows that I would also allow the Jamiesonsappeal from the dismissal of their  
applications and remit those applications for consideration with the petition.  
Thurlow & Alberni Project Ltd. v. The Owners, Strata Plan VR 2213  
Page 43  
Summary and Conclusion  
[127] I would allow the Thurlow appeal and set aside para. 6 of the order on the  
basis that the judge erred in law in making an order affecting Thurlow’s rights without  
adjudication upon the merits of its argument.  
[128] I would allow the Strata Corporation’s appeal, set aside the dismissal of the  
petition, and remit the petition to the trial court for reconsideration on the basis that  
the judge erred in law in the application of the test that must be met to obtain an  
order pursuant to s. 173(2) of the Strata Property Act, and for consideration of the  
amount of the levy; the liability of Thurlow to pay the levy; the method used to  
determine each strata lot's share of the levy; the amount of each strata lot's share of  
the levy; and the date by which the levy is to be paid or, if the levy is payable in  
instalments, the dates by which the instalments are to be paid.  
[129] I would allow the Jamiesonsappeal and remit their applications for  
consideration by the trial court.  
[130] I would give the parties leave to make written submissions as to costs if they  
cannot agree on an order reflecting their respective successes.  
The Honourable Mr. Justice Willcock”  
I agree:  
The Honourable Justice Dickson”  
I agree:  
The Honourable Mr. Justice Marchand”  
 


© 2022 IncJournal is not affiliated with or endorsed by the U.S. Securities and Exchange Commission