Date: 20220726  
Docket: T-538-19  
Citation: 2022 FC 1109  
Ottawa, Ontario, July 26, 2022  
PRESENT: The Honourable Mr. Justice Pamel  
BETWEEN:  
GCT CANADA LIMITED PARTNERSHIP  
Applicant  
and  
VANCOUVER FRASER PORT  
AUTHORITY and  
ATTORNEY GENERAL OF CANADA  
Respondent  
JUDGMENT AND REASONS  
Contents  
I. Overview................................................................................................................................ 3  
II. The parties.............................................................................................................................. 5  
III. History of Deltaport terminal expansion prior to the proposed DP4 project......................... 7  
IV. The RBT2 and DP4 projects................................................................................................ 10  
V. The March and September 2019 decisions and the institution of the present proceedings . 21  
VI. Procedural history................................................................................................................ 30  
VII. Legislative framework ......................................................................................................... 36  
Page: 2  
VIII. Issues.................................................................................................................................... 38  
IX. Standard of review............................................................................................................... 39  
X. Analysis................................................................................................................................ 39  
A. Preliminary matter: Is the application for judicial review moot and premature? .......... 39  
B. Did the VFPA breach the principles of natural justice and procedural fairness by  
rendering a decision tainted by bias and by breaching GCT’s legitimate expectations  
regarding the review of its PPE?.................................................................................... 43  
(1) Has the VFPA demonstrated impermissible bias by closing its mind to the DP4  
project?..................................................................................................................... 54  
(a) Were the March and September 2019 decisions, the manner in which they were  
made and the statements made therein, reflective of an actual bias or even a  
reasonable apprehension of bias on the part of the VFPA?............................... 55  
(i) Stated rationale........................................................................................... 56  
1. The notion of prohibition....................................................................... 56  
2. The competition concerns...................................................................... 65  
(ii) The tactical way that the March and September 2019 decisions were  
orchestrated ................................................................................................ 77  
1. The role of the VFPA’s previous law firm in the decision-making  
process and the paucity of the tribunal record ....................................... 77  
2. The current law firm and the tactical attempt to game the system ........ 84  
3. Deliberate avoidance of transparency by the VFPA in an effort to  
immunize itself from the bias allegation................................................ 90  
4. Efforts to undermine DP4 to third-party stakeholders......................... 100  
(iii) The declaration of preference for RBT2 without a proper evidence-based  
assessment ................................................................................................ 114  
(b) Failure to respect policy of separation of proponent and regulatory functions 116  
(c) Are the VFPA decision makers biased as a result of any financial interest in the  
development of the RBT2 project?.................................................................. 119  
(d) Contradictions in the VFPA’s positions as evidence of bias ........................... 123  
(e) Final thoughts on the bias issue ....................................................................... 125  
(2) Has the VFPA breached GCT’s legitimate expectations? ..................................... 131  
C. Mootness and prematurity............................................................................................ 149  
D. Does this Court have the jurisdiction to grant the relief sought by GCT?................... 150  
XI. Conclusion ......................................................................................................................... 151  
ANNEX....................................................................................................................................... 154  
Page: 3  
Overview  
[1]  
The Canada Marine Act, SC 1998, c 10 [CMA], invests port authorities with the power to  
manage the marine transportation of goods and people, as well as related and necessary services,  
within their ports, the whole as may be permitted under their letters patent and otherwise  
provided for under the CMA and its regulations. The Vancouver Fraser Port Authority [VFPA] is  
one such port authority. As operator of the Port of Vancouver, the VFPA is responsible for,  
amongst other things, the long-term commercial advancement of the port, undertaking  
commercially and environmentally sustainable development plans consistent with the purpose of  
the CMA, and following through on those development plans in line with its strategic goals. It  
can operate the port facilities itself, or act as landlord and lease port property to commercial  
operators.  
[2]  
Global Container Terminals Canada Limited Partnership [GCT] is one such commercial  
operator, and operates two container terminals within the jurisdiction of the Port of Vancouver,  
one of which is at Roberts Bank in Delta, British Columbia [GCT Deltaport], by way of lease  
with the VFPA; GCT is the tenant. By way of judicial review, GCT challenges two decisions of  
the VFPA, the first by which the VFPA refused in March 2019 to formally process GCT’s  
preliminary project enquiry [PPE] for the further expansion of GCT Deltaport [DP4 project]  
through the VFPA’s Project and Environmental Review Process [PER Process], and the second,  
a few months later, by which the VFPA purportedly rescinded in September 2019 its earlier  
decision and advised GCT that the port authority would assess the DP4 project proposal through  
its PER Process, but on the understanding that the VFPA’s preferred project for achieving  
capacity expansion at Roberts Bank continued to be a different project [RBT2 project], which  
 
Page: 4  
was being developed by the VFPA and which was at that time further advanced and undergoing  
environmental impact assessment; the VFPA advised GCT that its review of the DP4 project  
would be conducted having regard to, amongst other things, the status of the RBT2 project in  
meeting the anticipated increased shipping demands of the Port of Vancouver.  
[3]  
GCT claims that the VFPA has, through its conduct, demonstrated an incurable failure to  
act as an impartial decision maker under its statutory mandate set out in the CMA to consider the  
DP4 project, and that its executives closed their mind to the DP4 project without even assessing  
it under the port authority’s very own regulatory decision-making process, thus exhibiting actual  
bias against the project when the VFPA issued its decision to GCT in March 2019. The second  
decision in September 2019 purportedly reversing the earlier decision and confirming that the  
VFPA would assess the DP4 project under the PER Process was, according to GCT, an  
acknowledgment of such bias and a tactical attempt by the same executives to cover up the  
reversible error in the VFPA’s earlier decision. GCT now seeks to set aside both decisions, and  
on account of what it claims to be actual bias on the part of the VFPA’s executives which  
purportedly taints the entire review process, GCT is asking this Court to order an alternative  
assessment processtantamount to an order for mandamuscompelling the Minister of  
Transport [Minister], or his delegate, such as Transport Canada, to step in and oversee the review  
process for the DP4 project and, as clarified by GCT during the hearing, to actually conduct  
certain components of the review process given the lack of process at the VFPA to address any  
of the issues of concern to GCT, in particular the VFPA’s purported bias. In addition, GCT seeks  
a series of declarations confirming the existence of such bias.  
Page: 5  
I am not persuaded by GCT that there is any evidence that the VFPA executives were  
[4]  
actually bias against the DP4 project or that what GCT claims to be the indicia of such bias is in  
any way evidence of a reasonable apprehension of bias on the part of the VFPA executives.  
Consequently, and as a result of subsequent changes to the governing legislation which affect the  
environmental assessment process to which the DP4 project would be subject, as well as the  
VFPA’s eventual decision to actually proceed with a review of the DP4 project under its PER  
Process, I am dismissing GCT’s application as the issues between the parties have become moot.  
[5]  
I should also state at the outset that, as pleaded, these proceedings were not meant to be,  
and were not argued before me as, a trial on the governance model and the quality of governance  
of port authorities under the CMA, and of the VFPA in particular. The principal issue before me  
was whether the VFPA breached its obligation of procedural fairness by issuing a biased  
decision by refusing to process GCT’s application for DP4 or because it failed to respect GCT’s  
legitimate expectations in relation to the VFPA’s own process for regulatory review of large-  
scale projects within the Port of Vancouver. I leave the issue of optimization of proper and  
modern port authority governance in the hands of Transport Canada as part of its Ports  
Modernization Review commenced in 2018.  
The parties  
[6]  
GCT is an affiliate of GCT Global Container Terminals Inc. and is jointly owned by  
affiliates of the Ontario Teachers’ Pension Plan Board, British Columbia Investment  
Management Corporation and Australian-based IFM Investors. In addition to GCT Deltaport,  
GCT operates three other terminals in North America: GCT Vanterm, which is also within the  
 
Page: 6  
Port of Vancouver; GCT Bayonne in New Jersey; and GCT New York situated on Staten Island,  
New York.  
[7]  
The VFPA is a Canadian port authority established through letters patent dated  
December 22, 2007, issued by the Minister under the authority of section 8 of the CMA and is  
the result of the amalgamation of the Vancouver Port Authority, the Fraser River Port Authority  
and the North Fraser Port Authority; supplementary letters patent have been issued since 2007  
dealing with specific matters such as acquisitions or dispositions of land. The VFPA is  
responsible for the management of federal port lands and waters within its jurisdiction in the Port  
of Vancouver. Its mandate under the CMA includes acting as both proponent and regulator with  
respect to land and project development under its authority. There is no issue between the parties  
that the VFPA’s jurisdiction includes the area within which the development of the RBT2 and  
DP4 projects is intended to be undertaken.  
[8]  
Section 28 of the CMA authorizes the VFPA to operate the port, without any statutory  
requirement that it do so through an independent terminal operator. Companies seeking to  
undertake activity within the Port of Vancouver, including the leasing of port land and the  
activities inherent in building and operating marine terminals, require the authorization of the  
VFPA (section 23 of the Port Authorities Operations Regulations, SOR/2000-55 [Regulations]).  
There is no issue between the parties that the VFPA has the authority to develop the RBT2  
project on its own or that GCT must seek VFPA authorization to undertake the DP4 project, save  
that the VFPA has asserted that it has traditionally acted as the proponent of large-scale projects  
involving the reclaiming of land.  
Page: 7  
[9]  
As regards GCT Deltaport, the VFPA acts as landlord in a leasehold concession pursuant  
to lease and berth corridor agreements with GCT, under which GCT has tenancy obligations  
including, amongst other things, the payment of rent and obligations in relation to repair and  
maintenance, permitted use, compliance with laws, and landlord re-entry rights.  
[10] The Attorney General of Canada [AGC] is named as a respondent because GCT seeks, as  
a possible remedy, that the Minister or another delegate of the Crown oversee the review and  
assessment process for the DP4 project.  
History of Deltaport terminal expansion prior to the proposed DP4 project  
[11] GCT Deltaport is today a 210-acre, 2.4 million TEU (twenty-foot equivalent unit)  
container terminal located in the outer harbour of Roberts Bank, constructed on pods of  
reclaimed land built on the southern end of a man-made causeway running over a shallow bank  
and connecting the terminal to the British Columbia lower mainland at Delta. It first began  
operating as a container terminal in 1997. In 2002, the predecessor to the VFPA (which I will  
refer to simply as the VFPA) embarked on a port expansion strategy in answer to the expected  
growth of trans-Pacific container shipping, which included, at the time, the development of two  
separate container terminal projects at Roberts Bank: the first being the Deltaport Third Berth  
Project [DP3], which was to consist of adding a third berth to the existing terminal, and the  
second being what was described at the time as the Terminal 2 Project [T2], which was a  
precursor to RBT2. DP3 would be an extension of the existing Deltaport terminal on its northern  
side, landward into shallower waters, and running along the eastern side of the causeway. The T2  
project was to be developed along both the eastern and western sides of the causeway and also  
 
Page: 8  
leading north into shallower waters (E1 and W3 options), but included, in addition, a separate  
extension of the terminal to the southwest, and away from the causeway into deeper waters (W1  
and W2 options). Assessment and review of the projects was to be undertaken, and on  
February 24, 2003, the VFPA, as proponent of the projects, submitted separate letters of intent  
for the projects to the British Columbia Environmental Assessment Office so as to initiate a pre-  
application review; meetings with federal and provincial regulators to discuss the two projects  
took place on March 11, 2003.  
[12] As one of the agencies responsible for approving the projects, the Department of  
Fisheries and Oceans [DFO] reviewed the proposed projects: two letters were sent to the VFPA,  
the first by DFO on April 1, 2003, and the second by the Minister of Fisheries and Oceans on  
July 29, 2003 [2003 DFO letters]. The 2003 DFO letters expressed concerns regarding  
development and the reclaiming of additional land along the eastern side of the causeway on  
account of the “critical value of the fish habitat in the area”. As regards the DP3 project, DFO  
stated that it “will not consider issuing a Fisheries Act Section 35(2) authorization for the  
destruction of this critical fish habitat”. As regards the T2 project, DFO expressed similar  
concerns regarding the proposed expansion into shallower waters, both on the eastern and  
western side of the causeway, and thus confirmed that it would not authorize the development as  
proposed. Just as importantly, DFO suggested that the port authority, as proponent of the  
terminal expansion projects, focus its efforts on proposals that had less of a damaging impact on  
the environment, and confirmed that it would be willing to work with the port authority on the  
development of the separate area of T2 which extended beyond the edge of the causeway to the  
southwestseemingly an area to the south of where the W1 and W2 options for T2 were being  
Page: 9  
proposed—“[a]s these options are in deeper water, where construction would likely have less  
impact on the Estuary’s fish habitat”.  
[13] The 2003 DFO letters, amongst other things, caused the VFPA to reassess the projects.  
Eventually, a scaled down version of the DP3 project (about 30% less land mass on its north side  
so as to reduce its overall footprint on the landward side and thus accommodate DFO concerns)  
would move forward; on February 2, 2006, the VFPA advised the British Columbia  
Environmental Assessment Office that it was withdrawing its letter of intent to initiate a pre-  
application review request for T2 for the time being. From the point of view of the VFPA, the T2  
project was thereby placed “on hold” pending further discussions with various stakeholders,  
including consultations with First Nations in the area, to address the outstanding environmental  
and community issues that had been identified during previous discussions. T2 would remain as  
a possible consideration for future expansion after the completion of DP3.  
[14] DFO and Environment Canada jointly published a comprehensive study in July 2006 on  
the revised DP3 project, acknowledging that the reduced footprint minimized the potential  
effects on existing fish and fish habitat. The footprint-reduced DP3 project received final  
approval on December 8, 2006; the project was completed and became operational in January  
2010, increasing the GCT Deltaport terminal’s capacity by 600,000 TEUs per year.  
[15] In October 2015, the VFPA issued a permit allowing GCT to undertake the Deltaport  
Terminal, Road and Rail Improvement Project: a series of improvements at GCT Deltaport,  
mostly involving upgrades to the existing road and rail infrastructure at the container terminal  
Page: 10  
and causeway, resulting in a further increase in container capacity of 600,000 TEUs per year,  
thereby bringing the terminal’s total capacity to 2.4 million TEUs per year, where it stands today.  
The RBT2 and DP4 projects  
[16] As a commercial enterprise, the VFPA must undertake long-term planning to  
accommodate the evolving needs of the industry and the Port of Vancouver. In 2010, the VFPA  
established the Container Capacity Improvement Program [CCIP] as part of its long-term  
strategy to meeting the increasing demand for container terminal capacity at the Port of  
Vancouver; the options that the CCIP was to consider included increasing the capacity and  
efficiency of existing terminals, possibly converting existing underutilized terminals to handle  
container traffic, and building new terminals as may be required.  
[17] With the DP3 project becoming operational in January 2010, the VFPA turned its mind  
back to the possible development of a new terminal at Roberts Bank, and in September 2013,  
engaged the environmental assessment process when it submitted to the Canadian Environmental  
Assessment Agency its project description for the approval of an updated version of the T2  
project (the RBT2 project), in preference to further development in the area to the north of DP3  
previously identified as problematic for development; the RBT2 project entailed constructing a  
new marine terminal area in the waters off Roberts Bank, extending into deeper waters to the  
southwest of the causeway, and to the west of GCT Deltaport, thus avoiding development and  
the reclaiming of land to the northlandward sidein shallower waters, which was one of the  
problematic aspects identified by DFO in 2003 with the initial T2 project. The RBT2 project  
would provide up to three additional berths and add an estimated additional 2.4 million TEU  
 
Page: 11  
capacity to the Port of Vancouver. In January 2014, the Minister of the Environment (now the  
Minister of Environment and Climate Change) referred the environmental assessment of the  
proposed RBT2 project to a independent review panel [Review Panel] in accordance with section  
38 of the then in force Canadian Environmental Assessment Act, SC 2012, c 19, s 52 [CEAA]. In  
fact, the VFPA’s Land Use Plan adopted in October 2014 specifically provides for the  
development of RBT2.  
[18] In the meantime, GCT was also moving forward with its expansion plans, and in 2014,  
began plans to further extend GCT Deltaport to add an additional 2 million TEUs of annual  
capacity [DP4 project]. DP4 would be built within VFPA-managed federal lands and water and  
within Tsawwassen First Nation water lots, and part of the project dredging would extend past  
VFPA-controlled lands into VFPA navigational jurisdictions and provincial seabed. The  
extension and necessary reclaiming of land would be contiguous to the existing terminal to the  
northlandward sideof GCT Deltaport, into shallower waters and to the east of the causeway,  
i.e., in the area of the E1 option for T2 which was identified as problematic for development in  
2003 by DFO at the time.  
[19] On March 27, 2015, the VFPA submitted its Environmental Impact Statement [EIS] for  
the RBT2 project, which included an alternatives assessment, for federal review. Eventually, the  
Review Panel determined that the EIS was sufficient and that the matter may proceed to public  
hearings on the project; public hearings on the RBT2 project would take place in May and June  
2019. At the same time, GCT’s PowerPoint presentation of its proposed expansion project along  
with the preliminary assessment of the DP4 project by VFPA management, in particular, the  
Page: 12  
financial and environmental considerations were discussed during a March 31, 2015, meeting of  
the VFPA board of directors.  
[20] As part of the planning process for RBT2, the VFPA undertook a procurement process to  
identify and select a commercial operator for the new RBT2 container terminal; GCT applied in  
June 2015 to become the terminal operator for RBT2, along with continuing to be the operator of  
the adjacent Deltaport terminal, but was not successful.  
[21] Informal discussions continued between GCT and the VFPA through 2016 when the  
parties began to discuss the DP4 project in detail, and on January 13, 2017, GCT made its first  
formal presentation of the proposed DP4 project to the VFPA. Within a few months of the  
meeting, the VFPA retained Hemmera Envirochem Inc. [Hemmera] to review regulatory  
changes, advances in scientific understanding and changes to DFO policies since the 2003 DFO  
letters, when DFO refused to authorize development of the area now being proposed for the DP4  
project, and to consider the likelihood of DFO approving further expansion along the east side of  
the causeway to the landward side of the existing GCT Deltaport terminal. GCT agreed to pay  
half of the cost for the review.  
[22] In November 2017, Hemmera delivered its report to the VFPA [Hemmera Report],  
which, although not squarely addressing the issue of whether the 2003 DFO letters constituted a  
prohibition of development in the area at the time, set out a series of sequenced activities (eight  
tasks) to be undertaken for any proponent looking to pursue future port infrastructure  
development on the east side of the causeway, landward of GCT Deltaport, in possible answer to  
Page: 13  
the concerns expressed by DFO in 2003. GCT argues that I should read the Hemmera Report as  
confirming that the 2003 DFO letters did not constitute a prohibition against development of the  
area now proposed for DP4. However, the Hemmera Report made it clear that Hemmera “draws  
no conclusions related to the potential likelihood of attaining approvals and authorizations for  
project(s) along the East Causeway of Deltaport.”  
[23] On December 8, 2017, GCT and the VFPA held a meeting during which GCT presented  
its views on the marketplace and existing competition amongst container terminal operators—  
issues of concern to the VFPAand reiterated its intention to develop the DP4 project. In  
parallel to the discussions it was having with GCT regarding the DP4 project, the VFPA was  
moving forward with the development of RBT2.  
[24] On December 6, 2017, the VFPA sent a briefing note to the then federal Minister of  
Public Services and Procurementalso the member of Parliament for the riding of Delta at the  
time [December 2017 Briefing Note]espousing the benefits of the RBT2 project and the need  
for its development, and in particular outlining concerns with market concentration within the  
Port of Vancouver, with emphasis on avoiding dominance by any one single terminal operator  
within the port. I understand from the record and representations of GCT before me that GCT’s  
two terminals (GCT Vanterm and GCT Deltaport) together serviced around 78% of the container  
traffic within the Port of Vancouver at that time.  
[25] In line with its procurement process to identify and select an operator for the RBT2  
container terminal, the VFPA stated in the December 2017 Briefing Note that, consistent with  
Page: 14  
the approach of maintaining healthy competition within the port, “no concessions or agreements  
will be granted for the Roberts Bank Terminal 2 [RBT2] Project that would result in an operator  
having more than 60 per cent of the container handling capacity within the Port of Vancouver.”  
The VFPA continued by stating that “[o]ngoing control by a single operator of more than 60 per  
cent of the container capacity within the Port of Vancouver has proven to be detrimental to  
customers of the gateway.” The briefing note went on to explain that any existing container  
terminal operator which sought to also operate RBT2 would have to demonstrate that, amongst  
other things, “its total container handling capacity within the Port of Vancouver would not  
exceed 60 per cent of the total available capacity.” The selection process seems to be ongoing  
from what I understand, at least as of the time of the hearing before me.  
[26] The record includes similar briefing notes prepared by the VFPA in preparation for  
meetings with the then federal Minister of Transport and the British Columbia Minister of  
Transportation and Infrastructure in January and February 2018 to discuss and promote the need  
for the development of the RBT2 project. As regards the federal Minister of Transport in  
particular, the issues included that the VFPA’s borrowing limits under its letters patent would  
have to be increased in order to finance the RBT2 project. In discussing alternatives to the  
project, the briefing notes made it clear that the VFPA “concluded that the Roberts Bank  
Terminal 2 Project is the only viable option to ensure that the Port of Vancouver can efficiently  
handle growing trade in containers when it is required in the mid-2020s, and there are no other  
suitable alternatives that can reliably meet the need for additional capacity for the long-term”  
[emphasis added]. Specifically as regards the proposed DP4 project, the VFPA stated:  
No other proponent proposal has been formally submitted to the  
port authority or government, though we are aware one is  
Page: 15  
contemplated by GCT, albeit in the area of Roberts Bank already  
dismissed by the Minister of Fisheries in 2003. If a proposal were  
to be submitted, it would likely take at least nine years for  
approval, based on the experience of the Terminal 2 proposal to  
date, as it would likely be reviewed by a federal panel.  
[Emphasis added.]  
[27] There is no issue between the parties that both RBT2 and DP4 are not required  
concurrently by the Port of Vancouver in order to meet short-and medium-term increases in  
demand for container space. On February 2, 2018, the VFPA sent a letter to GCT [February 2,  
2018 letter] aiming to “provide clarity and transparency in respect of VFPA’s approach” in its  
consideration of what was expected to be a permitting application for the DP4 project. After  
stating that it has, over several decades, “given extensive consideration to expansion of port  
facilities on either side of the causeway, and the decision to proceed with T2 was made having  
regard to this prior analysis (including environmental concerns associated with further  
development on the east side)”, the VFPA stated the following in relation to how it would  
consider any application by GCT for the development of DP4:  
Specifically, GCT is at liberty to propose a project and apply to  
have it reviewed under VFPA’s project and environmental review  
process. For a project of the nature contemplated by GCT, and  
having regard to the history of environmental issues associated  
with the eastern side of the causeway, any proponent of such a  
project should expect significant environmental assessment  
requirements. We would encourage GCT to speak with an  
independent environmental consultant familiar with VFPA’s  
process and environmental assessment of similar projects to obtain  
a realistic understanding of the time that would take, the amount of  
information required, the cost of doing so and the likelihood of the  
environmental issues being amenable to sufficient mitigation at the  
end of the day.  
It is also important that we be clear that, even if the previously  
identified environmental issues associated with such a project  
proved to be mitigable to some extent, those impacts would have to  
Page: 16  
be considered in a cumulative context with T2. Further, given the  
multifaceted role of VFPA as discussed above, we believe it would  
be entirely appropriate and indeed incumbent upon VFPA to also  
consider the impacts of a DP4 project on the overall port  
operations. VFPA would also consider the issue of timing,  
recognizing the very significant lead times required for such  
projects, and the looming need for more near term capacity in the  
Port of Vancouver.  
[Emphasis added. The VFPA’s reference to T2 is actually to the  
new RBT2 project.]  
[28] The VFPA’s concerns regarding container terminal market concentration within the Port  
of Vancouver and the perceived lengthy and difficult road ahead for DP4 to gain environmental  
approval were again expressed in the VFPA executive’s briefing note on the status of the RBT2  
project prepared for the board of directors meeting of March 21, 2018. The VFPA’s campaign to  
develop RBT2and according to GCT, a campaign to undermine the DP4 projectcontinued  
throughout April and May 2018 with letters to the then federal Minister of Transport on April 27,  
2018, and to the then federal Minister of International Trade on May 5, 2018; both letters  
provided an update on the status of the RBT2 project and also comments on the reasoning for  
preferring RBT2 over DP4. The VFPA stated:  
We are aware of one other potential container terminal expansion  
project that has been discussed by an existing container terminal  
operator in the Vancouver gateway. Its proposed location is not a  
new idea, having first been mooted as a possible location for  
Terminal 2 over 15 years ago. It is, however, a highly sensitive  
location that the Minister of Fisheries stated unequivocally in 2003  
would not be permitted. With that direction, we sought to avoid  
development in the area referred to by the minister to preserve the  
fragile inter-tidal marine aquatic ecosystems that exist there.  
Terminal 2 would introduce a new container terminal operator to  
the West Coast of Canada, respecting the principles of choice and  
commercial competition. We believe this will benefit the Canadian  
economy by ensuring three strong independent container terminal  
Page: 17  
operators are in place to serve Canada’s needs and provide a  
competitive market place.  
[Emphasis added.]  
[29] In a May 11, 2018, email entitled “2003 letter ruling out terminal development adjacent  
to current Deltaport terminal”, the VFPA sent a copy of the July 29, 2003 DFO letter to a  
government official. In particular, the email stated:  
Further to our brief discussion about the idea GCT have been  
raising around an extension of Deltaport, we looked into this at the  
start of the RBT2 process and did not pursue it as it was explicitly  
ruled out by the Liberal Minister of Fisheries Robert Thibault in  
2003 (letter attached options 2 & 3 are in the location GCT  
suggests).  
Even if this could be overturned, which would be a challenge to  
say the least, it would be impossible to permit and develop a  
facility to be ready anywhere near in time to meet demand. It  
would almost certainly be a longer process than RBT2 and we’ve  
been working on permitting RBT2 (in the deeper location referred  
to in the letter) for 7 years already and it will likely be another  
9 years to get through permitting, construction and commissioning.  
[Emphasis added.]  
[30] In October 2018, the VFPA published on its website an “Overview and Rationale” setting  
out the benefit of the RBT2 project and outlining the status of the project and the work that had  
been undertaken to date for the project as regards consultation with stakeholders, including First  
Nations communities, an environmental impact review, its terminal operator procurement  
process, and the actual building of the project. In the section on possible alternatives to the  
project, the VFPA stated that the expansion of the existing GCT Deltaport facility through the  
DP4 project was “not an option for two main reasons”: first, DFO had prohibited any further  
land reclamation inland from Deltaport because of environmental sensitivity and, second, the  
Page: 18  
VFPA wished to prevent one terminal operator from controlling a significant majority of the  
market for container terminal services.  
[31] On October 5, 2018, GCT delivered a further presentation to the VFPA in support of the  
DP4 project, during which a tour of the terminal and an overview of the proposed expansion was  
provided; present at the presentation was the majority of the VFPA’s board of directors as well  
as the VFPA’s senior executives. However, the issues of the environmental challenges to the  
development of DP4 in the area that proved problematic in 2003 and of terminal operator market  
dominance within the Port of Vancouver continued to play on the mind of the VFPAthe record  
before me includes a series of email exchanges dated between October 3 and 15, 2018 between  
the VFPA and outside consultants retained to review and prepare a report on the issue of market  
dominance within ports around the world, as well internal emails within the VFPA regarding a  
review of the Hemmera Report and its conclusions at the time.  
[32] At the request of GCT, on January 24, 2019, GCT and the VFPA held a pre-PPE meeting  
as part of the first procedural requirement for review of capital projects under the VFPA’s PER  
Process. The agenda for the meeting included a discussion on where engagement of the parties  
stood on the issue of DP4 as well as the status of the preliminary work undertaken by GCT in  
line with the three-phase/eight-task process outlined in the Hemmera Report for the advancement  
of future projects along the east side of the causewayit would seem that GCT had completed  
Phase 1 of the eight phases recommended by Hemmera, being the pre-feasibility study. At the  
conclusion of that meeting, the VFPA suggested that a further pre-PPE meeting would be  
required. The next day, GCT asked for further clarity regarding such further meeting and  
Page: 19  
although hesitant as to whether it was even necessary, requested that any further pre-PPE  
meeting take place before the end of the week of February 4, 2019, otherwise GCT was to be  
“filing the PPE in accordance with all VFPA’s posted guidelines.” The VFPA proposed February  
13, 2019, for the next meeting, but as the date was outside GCT’s proposed window, on February  
5, 2019, GCT formally submitted its PPE for the DP4 project to the VFPA for review in  
accordance with its PER Process.  
[33] GCT’s PPE was received and distributed internally amongst VFPA management. It  
would seem that the PER Process for the DP4 project was to begin, as internal VFPA emails  
state that “staff will be doing an internal review over the comings days/weeks, and no doubt a  
number of initial meetings with GCT will be required.” In fact, on February 7, 2019, the VFPA  
confirmed to GCT receipt of its PPE and advised that VFPA staff “will undertake a review of the  
submission to better understand the project and determine if our submission criteria has been  
satisfied in order to continue processing. Once this is done, staff will either confirm our February  
13 meeting with you or will reschedule a meeting should further information and engagement be  
necessary to process your submission.” The proposed meeting for February 13, 2019, with GCT  
was eventually deferred at the suggestion of the VFPA on February 11, 2019, as its staff had not  
completed their review of the information submitted by GCT; as confirmed during the cross-  
examination of Mr. Peter Xotta, Vice-President, Planning and Operations for the VFPA, nor had  
a project lead for the GCT’s proposal been appointed at that time.  
[34] The affidavit of Mr. Xotta, filed in August 2021 in replacement of the initial affidavit of  
Mr. Yeomans who was no longer able to be cross-examined, indicates that he participated in  
Page: 20  
several discussions with other members of the VFPA executive regarding the PPE, and in  
particular, the port authority’s pending decision whether to accept the PPEalthough it had  
indicated to GCT that it was to undertake a review of the submission so as to better understand  
itso as to advance “VFPA’s statutory decision-making process under the [CMA]”. The VFPA  
executives met on February 13, 2019 (it seems as though all members of the seven-person  
executive team were in attendance, including Mr. Xotta), with a decision being reached by  
consensus which was eventually to be communicated to GCT on March 1, 2019. In his cross-  
examination, Mr. Xotta confirmed that there were no documents that reflected the discussions  
and decision made by the executives at the time, other than the formal decision that was to be  
sent to GCT on March 1, 2019. In the meantime, exchanges continued between the parties during  
the last two weeks of February 2019, with GCT looking for a status report and the VFPA  
responding only that “senior management is considering the GCT request and the submission  
materials …”. However, in response to a media request in relation to GCT’s proposed expansion  
project, on February 26, 2019, the VFPA advised that it was:  
reviewing GCT’s submission that was posted on the independent  
review panel registry, and don’t have any specific comments at this  
time.  
However, what is important is that the Roberts Bank Terminal 2  
Project is the only project on the West Coast that is currently in the  
review process and that could potentially meet the need for  
container terminal capacity when Canada needs it by the late  
2020s.  
Should GCT decide to proceed with the Deltaport expansion, they  
would need many years to do all the planning and environmental  
work to enter into the federal review process, followed by the  
environmental review which has taken already four years for the  
RBT2 Project and then by construction. This would make it very  
difficult for GCT to meet demand that is just a few years away.  
Page: 21  
The March and September 2019 decisions and the institution of the present proceedings  
[35] On March 1, 2019 (the letter is incorrectly dated February 29, 2019), the VFPA sent a  
letter to GCT, reflecting the decision reached by the VFPA executives on February 13, 2019,  
stating: “we will not be processing your [PPE] through our [PER Process] at this time”  
(emphasis added) [March 2019 decision]. In its letter, the VFPA noted that DP4 would involve a  
footprint expansion extending onto the same environmentally sensitive area on which the DFO  
expressed concerns in 2003 as involving “unacceptable impacts to critical fish habitat”. The  
March 2019 decision continued by stating:  
It was very clear that the reduced footprint was a significant factor  
in the assessment and ultimate recommendation for approval of the  
DP3 Project by DFO and Environment Canada, and that the  
originally proposed footprint of 80 acres would not have been  
acceptable.  
It is notable that your proposed DP4 Project would involve a  
footprint expansion of 56 hectares (138 acres), extending into and  
well beyond the footprint on the very same intertidal habitat which  
was specifically protected by the reduced footprint of the DP3  
Project to address the opposition of DFO to impacts on what they  
regarded as critical intertidal habitat.  
[Emphasis added.]  
[36] In addition, and underscoring the same two reasons stated in its 2018 “Overview and  
Rationale” document, i.e., the 2003 DFO letters and market concentration within the port, the  
VFPA stated that the RBT2 project was its preferred project for expansion of capacity at Roberts  
Bank:  
As you are aware, the VFPA plans for container capacity  
expansion at Roberts Bank have included additional expansion on  
the west side of the terminal, in deeper water, as encouraged by the  
Minister of Fisheries and Oceans in 2003.  
 
Page: 22  
The RBT2 Project is our preferred project for achieving the  
expansion of capacity to meet projected increases in demand.  
You must understand that your DP4 proposal, even if it is able to  
receive the necessary environmental and regulatory approvals,  
could only be considered as subsequent and incremental to the  
RBT2 Project. We note that your proposed development timeline  
would conflict with the implementation of RBT2 capacity. Taking  
all of the above factors into consideration, we will not be  
processing your Enquiry through our project and environmental  
review process at this time. We would be prepared to review  
development plans for Deltaport with GCT at a point when we can  
more accurately project the need for incremental capacity beyond  
RBT2.  
[Emphasis added.]  
[37] On March 4, 2019, GCT expressed disagreement with the VFPA’s decision not to  
process the PPE through the port authority’s PER Process at that time, confirmed that it was  
nonetheless continuing to advance its environmental and engineering studies, and requested port  
authorization to access the causeway to undertake the necessary environmental studies.  
[38] The record before me also contains a draft of a letter dated March 25, 2019, from the  
VFPA to the then Deputy Minister of Fisheries and Oceans [March 25, 2019 draft] seeking  
“clarification from Fisheries and Oceans Canada (DFO) on earlier direction regarding terminal  
expansion at Roberts Bank, B.C.” and advising that it had “recently had an inquiry from a  
proponent interested in expanding a Roberts Bank port terminal by reclaiming lands east of the  
existing terminals … .” In the draft, the VFPA was requesting “confirmation from DFO that its  
earlier direction still stands, and that no terminal expansion on the east side of the causeway will  
Page: 23  
be permitted.” For some reason, the draft letter was never sent, however, in response to what is  
expressed to be a public relations campaign undertaken by GCT to promote the DP4 project as  
an alternative to RBT2, the record before me includes an internal VFPA document entitled  
“Issues Management Plan”, also dated March 25, 2019 [Issues Management Plan], that provides  
speaking points for the VFPA to address the DP4 project and to further promote the RBT2  
project.  
[39] On March 28, 2019, GCT served and filed the present notice of application for judicial  
reviewat the time limited to the March 2019 decision; GCT also filed a second application for  
judicial review of the Review Panel’s decision to proceed with public hearings for RBT2  
(T-537-19); however, that application has been stayed.  
[40] On March 29, 2019, the VFPA sent a briefing note to the Prime Minister’s office  
following up on discussions that took place earlier in the week meant to address public concerns  
and opposition to the RBT2 project, and address the port authority’s response to those concerns.  
The briefing note provided, inter alia, that the “location of the proposed terminal was guided in  
large part by direction from the minister of fisheries who advised in 2003 that only expansion  
options beyond the existing Deltaport terminal in deeper water should be considered, since  
Fisheries Act permits for options in highly sensitive habitat closer to the shore would not be  
granted.” In reference to the DP4 project, the VFPA mentioned that the “port authority evaluated  
the same area suggested for DP4 as one of several location options for the RBT2 Project, but  
rejected it because Fisheries and Oceans Canada advised no Fisheries Act permits would be  
issued for projects in that area due to it being sensitive inter-tidal waters.”  
Page: 24  
[41] On April 10, 2019, the VFPA met with the Prime Minister’s office. The follow-up emails  
included a series of PowerPoint presentations and reports. The briefing note entitled “Concerns  
and opposition” was updated on April 3, 2019, and although it did not mention the DP4 project  
directly, it stated the following in the section on alternate options:  
Should another project be proposed, we expect it would take at  
least 15 to 20 years before the project could be built and  
operational, similar to the length of time it will ultimately have  
taken for the RBT2 Project. Therefore, any other project could not  
be ready to meet demand when needed by mid-2020s, but could  
possibly provide capacity for continually-growing demand by the  
late 2030s.  
[42] In May and June 2019, the Review Panel under the CEAA held public hearings on RBT2  
and received submissions from a number of stakeholders, including GCT. During the Review  
Panel hearings, representatives of DFO testified that the 2003 DFO letters were not meant to be a  
blanket prohibition on future development of the area now being proposed for DP4, but only  
addressed the proposed projects as they stood at that time. As stated during the Review Panel  
hearings by DFO: “each project is weighed and based on the application received, the current  
legislation and the current policies. So in future, should a project come in, DFO will review the  
application and make a decision based on the information that’s presented to us.” As part of its  
review process, the Review Panel considered whether the VFPA had carried out appropriate  
assessments on alternatives to RBT2; during the hearings, GCT participated and argued, inter  
alia, that the Review Panel should reject RBT2 in favour of DP4. In the end, the Review Panel  
concluded that the VFPA had undertaken an appropriate assessment of alternatives to RBT2, and  
submitted its final report to the Minister of Environment and Climate Change about nine months  
later, on March 27, 2020. As of the hearing before me, final approval for the RBT2 project was  
still pending.  
Page: 25  
[43] In the meantime, on August 28, 2019, the CEAA was repealed and replaced with the  
Impact Assessment Act, SC 2019, c 28, s 1 [IAA], as a result of which DP4 would now be a  
“Designated Project” under the IAA so that it may have to undergo a federal environmental  
assessment process prior to review by the VFPA under its PER Process; the PER Process  
nonetheless remains a necessary step in project approval, but with the enactment of the IAA, the  
VFPA’s PER Process Application Guide [Guide] provided that the port authority may rely on the  
results of the federal impact assessment where the assessment meets the VFPA’s standards and  
requirements. That said, the IAA precludes the VFPA from making any decision on DP4 unless  
and until the Impact Assessment Agency [Agency] gives its approval, approval which may never  
be given if in fact the Agency rejects DP4. On the assumption that DP4 does pass Agency  
approval, however, final say on the approval of projects within the Port of Vancouver remains  
with the VFPA, with necessary permitting having to eventually pass through the PER Process.  
Consequently, notwithstanding the new impact review process under the IAA, the VFPA remains  
an active player in the approval process for DP4.  
[44] Although I discuss this further below, on September 6, 2019, this Court issued an Order  
disqualifying the VFPA’s legal counsel on the basis of a conflict of interest. According to the  
affidavit of Mr. Xotta, shortly after retaining new counsel, on September 23, 2019, the VFPA  
executives met by telephone to consider the implications of the said Order and the earlier March  
2019 decision. Following further discussion amongst the VFPA executives, the VFPA informed  
GCT [September 2019 decision] that, after further consideration regarding the PPE for the  
proposed DP4 project, the VFPA was rescinding its March 2019 decision. The VFPA stated:  
Having regard to all relevant information available to the Port  
(including some which became available to us through the review  
Page: 26  
panel process) we are hereby rescinding our [March 2019 decision]  
and will proceed with receiving GCT’s Preliminary Project  
Enquiry. Port staff will be in touch with your staff shortly on this  
matter to discuss the timing of the Port’s process relative to the  
impact assessment process DP4 would be required to undergo,  
pursuant to the recently enacted Impact Assessment Act and  
supporting regulations.  
[Emphasis added.]  
[45] Although advising that it was prepared to review the proposed DP4 project, the VFPA  
reiterated its concerns:  
In making this decision I wish to note that, as we made clear in the  
review panel hearings, the Port still believes (based on prior  
assessments of the area) there are considerable risks with the  
proposed DP4 project as it relates to fish habitat. However, in the  
circumstances, we are no longer of the view that they are of such a  
nature that any consideration of DP4 is not an option. Instead, we  
are open to considering GCT submissions (and responses to any  
related questions or concerns) as part of a federal impact  
assessment of DP4 and our PER process.  
Similarly, in respect of the competitiveness and control question,  
we remain of the view that this is a significant issue one that we  
have consistently made GCT aware of for some years now  
(including in our commercial agreements and through the terminal  
operator RFQ process). We continue to consider it potentially  
problematic for the proposed DP4 project, but we are prepared to  
further consider that issue through the information and analysis  
that will be undertaken through the federal impact assessment of  
DP4 and our PER process.  
[Emphasis added.]  
[46] In the end, the VFPA again addressed the issue of the GCT’s concerns over bias in the  
review process:  
With respect to your stated concerns about “bias” on the part of the  
Port given its different roles, the Port considers these multiple roles  
mandated by the Canada Marine Act and related regulations and  
Page: 27  
thus an integral and appropriate aspect of the Port’s mandate.  
Further, to the extent you may hold any residual concerns in this  
regard, we note that before any decisions would be made by the  
Port, the DP4 project would be subject to assessment under the  
Impact Assessment Act, and that process would materially inform  
the Port PER process.  
Ultimately, and having said all the above, I wish to reiterate the  
position noted in my [March 2019 decision] that, even if the DP4  
project is able to satisfactorily address the above noted issues, the  
Port would ultimately make a decision on the project having regard  
to all relevant factors including effective and efficient port  
operations (as we are mandated). This wold include, but is not  
limited to, the status of the RBT2 project in terms of meeting  
anticipated increased shipping demands.  
[Emphasis added.]  
[47] GCT responded to the VFPA on September 27, 2019, advising that it was of the view that  
its PPE would not receive fair consideration under the Port of Vancouver’s PER Process. In any  
event, GCT advised the VFPA that it was mindful of the new legislation and that the DP4 project  
is considered thereunder as a Designated Projectmeaning that any VFPA permitting decisions  
relating to the project could not be made until it favourably completed an impact assessment  
under the IAAand accordingly, “GCT’s view is that it is not necessary to immediately engage  
in the VFPA’s permitting process” [emphasis added]. As asserted before me by GCT, had GCT  
resubmitted its PPE as invited to do by the VFPA, the PPE would likely have had to be amended  
slightly to reflect the change in legislative structure in place with the repeal of the CEAA and the  
enactment of the IAA; however, GCT declined to participate in a process which it felt was  
simply being reopened to it by the VFPA for tactical reasons.  
[48] The VFPA replied to GCT on October 2, 2019, advising that the impact assessment under  
the IAA would be undertaken by an independent external agency and “[a] permitting decision by  
Page: 28  
the port authority would only be necessary if the project received approval under the [IAA], and  
any resulting report/federal decision would necessarily and substantially inform [the VFPA’s]  
permitting process.” The VFPA also asked GCT to confirm whether it was still asserting that the  
VFPA would be in a situation of bias at the time it may be called upon to make a permitting  
decision in the future, and, if so, to provide submissions on the matter for consideration so that if  
the concerns are considered valid, the VFPA could consider “what steps need to be taken to  
address those issues well before a decision is required” [October 2, 2019 letter].  
[49] On October 8, 2019, GCT replied to the October 2, 2019 letter to advise that it  
recognized the effects of the new legislative regime on DP4 and that it was still asserting that the  
VFPA is in a situation of bias. GCT did not provide further submissions on the issue of the  
VFPA’s purported bias, but advised simply that it would continue with the judicial review  
application as filed.  
[50] Since then, the parties have continued to move forward with their respective proposals.  
As stated, the Review Panel under the CEAA submitted its final report on RBT2 to the Minister  
of Environment and Climate Change on March 27, 2020. Having to determine, amongst other  
things, whether the VFPA properly conducted an assessment of alternative means for carrying  
out RBT2, the Review Panel concluded that the VFPA reasonably eliminated the E1 and W3  
options, and although the regulatory context had changed since 2003, the VFPA had reason to  
believe that “the potential for environmental effects on critical fish habitat in the intertidal area  
had not changed, and the destruction of that critical habitat would potentially not be permitted by  
Page: 29  
DFO”. In concluding that the VFPA’s assessment of alternative means of carrying out RBT2 was  
appropriate, the Review Panel stated the following:  
The Panel cannot ignore the fact that sensitive fish habitat has been  
identified on the east side of the causeway and building E1 would  
destroy that habitat which may or may not be fully mitigable. The  
Panel recognizes that the [VFPA] had continued conversations  
with DFO after 2003 and they never altered their position. After  
considering all arguments presented by GCT the Panel submits that  
GCT is proposing a competing Project, which the Panel has no  
mandate to review. The Panel has however, assessed alternative  
locations of [RBT2], including E1.  
[Emphasis added.]  
[51] As stated, although not identical to E1, construction of DP4 is being proposed in the area  
where E1 was to be built, an area which was identified by DFO as problematic for development  
in 2003. In May 2020, the VFPA sent about 30 letters to various First Nations communities  
adjacent to the Roberts Bank facility and thus interested in port development in the area [May  
2020 letters], purportedly to answer questions arising from information being disseminated by  
GCT, in which the VFPA asserted, amongst other things, the following:  
i.  
The VFPA has decided to pursue the RBT2 project,  
having considered other options including expansion in  
the area being proposed for DP4;  
ii. The DP4 project was rejected by the VFPA for reasons  
which included environmental and competition concerns;  
iii. The Review Panel under the CEAA has concluded that  
the VFPA’s assessment of alternative means of carrying  
out RBT2 was adequate and has supported the VFPA’s  
conclusion to locate the proposed new terminal in deeper  
waters; and  
iv. The VFPA has no plans to pursue development of DP4,  
and GCT does not have the ability to pursue an expansion  
of its existing facility without VFPA approval.  
Page: 30  
[52] For its part, and as part of the first step in the impact assessment process under the IAA,  
GCT submitted an initial project description for the DP4 project to the Agency in September  
2020, with the intention of filing a detailed project description in the fall of 2021.  
Procedural history  
[53] As stated, on March 28, 2019, GCT served and filed its notice of application for judicial  
review of the March 2019 decision; since then, the proceedings have been at times somewhat  
spirited. As stated earlier, on September 6, 2019, Mr. Justice Pentney granted GCT’s motion  
disqualifying the VFPA’s counsel from acting in relation to the present application for judicial  
review (2019 FC 1147), compelling the VFPA to retain new counsel.  
[54] In addition, with the enactment of the IAA on August 28, 2019, rendering the DP4  
project a Designated Project and the issuance of the September 2019 decision, amongst other  
things, GCT sought to amend its notice of application to include the September 2019 decision  
along with the March 2019 decision as the decisions for which judicial review was being sought;  
GCT also sought permission to file supplemental affidavits in support of such amendments.  
[55] The VFPA and the AGC in turn filed motions seeking to strike GCT’s underlying claim.  
The VFPA first argued that the rescission of the March 2019 decision by way of the September  
2019 decision rendered GCT’s application moot, as GCT is no longer prevented from accessing  
the PER Process given that the VFPA specifically advised GCT that it was ready to proceed with  
reviewing GCT’s PPE in the September 2019 decision, and that it was GCT that refused to  
engage the PER Process; with no application in the pipeline for the VFPA to review, there was  
 
Page: 31  
no longer a live issue between the parties and no reason for the Court to exercise its discretion to  
hear a matter that had become strictly hypothetical. In addition, the VFPA sought to strike as  
premature GCT’s requests seeking a declaration, amongst other things, that the VFPA cannot  
conduct a fair and impartial process because of actual bias, as the GCT had refused the invitation  
to first put the bias issue before the VFPA, thus not exhausting the required administrative route  
and denying the VFPA the opportunity to respond to the issue so as to provide a record for the  
Court to review. The port authority also sought to strike the application as a whole, given that the  
Court, it was argued, lacks jurisdiction to order the oversight remedy being requested by GCT  
and the Minister lacks the authority to oversee the VFPA in its assessment process.  
[56] On March 9, 2020, Prothonotary Furlanetto, as she then was, who was acting Case  
Management Judge, allowed the various motions in part: GCT was permitted to amend its notice  
of application on the grounds that the inclusion of the September 2019 decision “is not an  
intention to raise judicial review of an additional decision but rather to indicate a continuing type  
of activity that it asserts supports the allegation of bias” (2020 FC 348). In addition, and although  
Prothonotary Furlanetto allowed the VFPA’s motions to strike certain aspects of the relief sought  
by GCT, she nonetheless dismissed the request to strike other aspects which related to mootness  
and prematurity connected to the bias issue; under the test set out in Borowski v Canada  
(Attorney General), [1989] 1 SCR 342 [Borowski], the Prothonotary considered that the  
allegations of underlying bias with respect to the March 2019 decision remained a live issue even  
though the March 2019 decision may itself have been rescinded by the September 2019 decision.  
Prothonotary Furlanetto explained that although there was a change in the legislative regime, the  
“VFPA’s authority over GCT in respect of the DP4 Project is ongoing. The VFPA exercises  
Page: 32  
power over the DP4 Project under the PER Process and the authority granted to it under the  
[CMA]. While a change in the environmental regime has been effected by the implementation of  
the IAA, there is no change in the gatekeeper role of VFPA in the process”. Citing Michel v  
Adams Lake Indian Band Community Panel, 2017 FC 835, Prothonotary Furlanetto determined  
that ““[e]ven where a decision is alleged to be moot, the bias underlying the decision may remain  
a live issue that can be determined by the Court at its discretion”. As to the prematurity  
argument, the Prothonotary found that such a defence could not arise from the VFPA’s own  
making in rescinding its March 2019 decision when the live issuethe purported bias of the  
VFPAwas tethered to that decision. The Prothonotary, however, made it clear that her decision  
was not intended to be a pronouncement of findings with respect to the merits of the case, but  
was limited strictly to the issues raised in the motions before her.  
[57] On September 11, 2020, GCT filed its amended notice of application for judicial review  
with respect of both the March 2019 decision and September 2019 decisionscollectively  
referred to as the March and September 2019 decisions, seeking the following relief:  
(a) An Order in the nature of certiorari quashing the Decision and  
directing that the Minister of Transport (Canada) or an appropriate  
delegate of Her Majesty the Queen other than the VFPA, as  
determined by this Honourable Court (the “Minister”), oversee the  
assessment and permitting activities for the DP4 Project which are  
under the jurisdiction of the VFPA pursuant to the Canada Marine  
Act, S.C. 1998, c.10 (the “Act”), the Port Authorities Operations  
Regulations, SOR/2000-55 enacted under the Act, or such other  
process as this Honourable Court determines is appropriate;  
(b) Declarations that:  
(i) the March 1st Decision was made pursuant to the  
VFPA’s actual improper bias;  
Page: 33  
(ii) the September 23rd Decision, purportedly rescinding  
the March 1st Decision, was made pursuant to improper  
motives, and the VFPA’s actual improper bias;  
(iii) In the alternative, and if necessary, that the VFPA  
created an inescapable situational bias such that, where  
VFPA remains the decision maker, GCT has no possible  
opportunity of advancing DP4 before an unbiased decision  
maker;  
(c) deleted;  
(d) An Order directing independent oversight of the VFPA’s  
administrative, permitting and other powers with respect to the  
DP4 Project in relation to:  
(i) access for conducting studies, collecting data, and other  
works and activities related to the impact assessment and  
permitting processes of DP4;  
(ii) leasing;  
(iii) dredging;  
(iv) construction;  
(v) transportation activities;  
(vi) undertaking offsetting measures; and  
(vii) other activities and powers of the VFPA and its  
subsidiaries, including those related to port operations,  
pursuant to the VFPA’s letters patent.  
(e) A Declaration that the VFPA made the Decision relying upon  
extraneous and inappropriate considerations resulting from its own  
actual bias, thereby exceeding its jurisdiction under the Act. The  
VFPA relied upon its own immediate commercial interest in the  
Decision and its desire to protect and enhance its own competing  
project to fund and build a second terminal at Roberts Bank (the  
RBT2 Project”) – considerations incompatible with its role as a  
federal board, commission or other tribunal;  
(f) A Declaration that the VFPA has not conducted, and cannot  
conduct, a fair and impartial process under the Act and its own  
Project and Environmental Review Process (the “PER Process”),  
and in accordance with the principles of natural justice and  
procedural fairness due to its actual bias;  
Page: 34  
(g) A Declaration that the lands affected by the DP4 Project are not  
all within the jurisdiction of the VFPA and remain under the  
jurisdiction of the Minister of Transport (Canada), or such other  
delegate of Her Majesty the Queen as determined by this  
Honourable Court;  
(h) deleted;  
(i) An Order assigning a case management judge or prothonotary  
pursuant to Rule 383 of the Federal Courts Rules, SOR/98-106;  
(j) An Order expediting the hearing of this Application;  
(k) The Costs of this Application; and  
(l) Such other relief as counsel may advise and this Court deems  
just.  
[58] As stated earlier, by requesting that this Court direct the Minister, by way of an order in  
mandamus, to oversee the assessment and permitting activities for the DP4 project, GCT is  
seeking an alternative assessment process where Transport Canada oversees certain aspects of  
the VFPA’s review of the DP4 project and also conducts certain components of the review  
process itself. During the hearing, GCT explained that if I were to find bias on the part of the  
VFPAwhich GCT contends means having a closed mind and a refusal to make a fair and  
rational decision based on objective considerations, and instead making a decision based on  
predeterminations on the part of the VFPAthe parties, with the assistance of the Court, would  
have to sketch out the exact process that will eventually have to be undertaken during the  
assessment process of the DP4 project. GCT’s assertion, rightly or wrongly, that it was open to  
this Court to fashion a remedy of this kind under the circumstances is supported, it argues, by the  
decision of Madam Justice Sharlow, as she then was, in Pushpanathan v Canada (Minister of  
Citizenship and Immigration ), [1999] 4 FC 465. I should also mention that during the hearing,  
Page: 35  
GCT confirmed that it was no longer pursuing the declaration sought at paragraph 2(g) of the  
amended notice of application for judicial review.  
[59] The VFPA appealed the Order of Prothonotary Furlanetto, strictly on the mootness and  
prematurity issues. On November 17, 2020, Mr. Justice Phelan dismissed the appeal, finding that  
the Prothonotary did not commit a palpable and overriding error in her decision (2020 FC 1062).  
The VFPA appealed Justice Phelan’s decision, on the prematurity issue alone, to the Federal  
Court of Appeal [FCA] which, on September 17, 2021, dismissed the appeal (2021 FCA 183) on  
the grounds that it saw no palpable or overriding error in the decision of Justice Phelan. The FCA  
also made it clear that its decision was not meant to tie the hands of the judge hearing the matter  
on the merits, in the determination of the issues before me.  
[60] In addition, following the disclosure under section 317 of the Federal Courts Rules,  
SOR/98-106 [Rules], GCT filed a motion seeking further disclosure of the record, primarily on  
the basis of the bias allegation. On October 15, 2020, Mr. Justice Pentney dismissed GCT’s  
motion seeking an order for leave to cross-examine a senior official of the VFPA in advance of  
the hearing of its motion pursuant to subsection 318(2) of the Rules (2020 FC 970), and on June  
17, 2021, Justice Pentney granted in part the motion to compel disclosure (2021 FC 624).  
[61] That is where matters stood at the commencement of the hearing.  
Page: 36  
Legislative framework  
[62] I have set out in the annex to my decision the relevant statutory and regulatory  
provisions.  
[63] By virtue of the enactment in 1998 of the CMA, Parliament relinquished the legislative  
means of the federal government to direct or control the actions of port authorities through the  
requirement under the Financial Administration Act, RSC 1985, c F-11, that they submit  
corporate plans to the Governor in Council. The purpose of enacting the CMA was to consolidate  
and simplify maritime regulations, reduce red tape, and shorten the time for commercial  
decision-making for, amongst other federal entities, port authorities; the overall goal was to  
make Canada’s maritime sector more competitive (British Columbia (Attorney General) v  
Lafarge Canada Inc, 2007 SCC 23, [2007] 2 SCR 86 at paras 44 and 45).  
[64] As seen from section 4 of the CMA, the legislative framework is designed to ensure that,  
in particular, port authorities are managed in a commercially sound and decentralized manner,  
for the most part free from the control of the Minister of Transport. The core commercial focus  
of the CMA is reflected in its legislative history, with the result that the VFPA is autonomous  
and financially sustainable. In fact, one of the conditions for the Minister to issue letters patent  
incorporating a port authority is that the Minister is satisfied that the port “is, and is likely to  
remain, financially self-sufficient” (CMA s 8(1)(a)).  
[65] In the present case, the nature of the CMA is commercialin fact, it is interesting that  
subsection 2(2) of the CMA looks to the Canada Business Corporations Act for greater certainty  
 
Page: 37  
in the interpretation of words and expressions used in the CMAwith its purpose being to, inter  
alia, “provide a high degree of autonomy for local and regional management … and be  
responsive to local needs and priorities” as well as to “manage the marine infrastructure and  
services in a commercial manner that encourages, and takes into account, input from users and  
the community in which a port or harbour is located(CMA ss 4(e) and (f)).  
[66] The VFPA’s power to authorize certain activities within the Port of Vancouver derives  
from section 28 of the CMA, which specifically authorizes a port authority to “operate” its port  
and, subject to the letters patent, to engage in port activities set out in subsection 28(2) of the  
CMA. There is no issue that GCT requires the authorization of the VFPA to proceed with DP4.  
Moreover, the Regulations do not establish the procedures that must be undertaken for an  
applicant to have its project reviewed by the port authority. Rather, the VFPA is empowered to  
set up its own procedures for project assessment and review. Its letters patent provide the  
following: “To operate the port, the [VFPA] may undertake the port activities referred to in  
paragraph 28(2)(a) of the [CMA]” which may include the “development, application,  
enforcement and amendment of rules, orders, bylaws, practices or procedures and issuance and  
administration of authorizations respecting use, occupancy or operation of the port” [emphasis  
added].  
[67] A port authority is managed by a board of directors who “shall have generally  
acknowledged and accepted stature within the transportation industry or the business  
community” (CMA ss 15(1) and (2), and 20). The directors have to “act honestly and in good  
faith with a view to the best interests of the port authority” (CMA s 22(1)(a)). The VFPA’s Code  
Page: 38  
of Conduct (Schedule E to its Letters Patent Certificate of Amalgamation of Port Authorities  
(Department of Transport), PC 2007-1885, art 5.1) [Code of Conduct], governs the conduct of  
the directors of the VFPA. However, neither the CMA, nor the Regulations, nor the letters patent  
prescribe who, within the VFPA, must make a decision to authorize the building of a new project  
(Communities and Coal Society v Canada (Attorney General), 2018 FC 35 at paras 45-46  
[Communities and Coal Society]; Carltona Ltd v Commissioners of Works and Others, [1943] 2  
All ER 560).  
[68] Prior to the introduction of the IAA, the VFPA had environmental assessment powers  
under section 67 of CEAA. With the coming into force of the IAA, the VFPA, as a “federal  
authority”, can only exercise its authorization powers in accordance with the IAA, and as  
mentioned, section 8 of the IAA prohibits the VFPA from acting with respect to a project  
proposal until a project is approved under the IAA process. In addition, and quite apart from  
approvals under the now repealed CEAA or the new IAA and under a myriad of other federal  
legislation and from the Tsawwassen First Nation for activities on their lands or water lots,  
authority from DFO would be required under the Fisheries Act, RSC 1985, c F-14, in respect of  
projects which may affect fish habitat.  
Issues  
[69] The present application raises three issues:  
1.  
Is the present application moot or premature given the rescission of the March  
2019 decision and the repeal of the CEAA in favour of the IAA?  
 
Page: 39  
2.  
3.  
Did the VFPA breach the principles of natural justice and procedural fairness by  
rendering a decision tainted by impermissible bias?  
Does this Court have the jurisdiction to grant the relief sought by GCT?  
Standard of review  
[70] As regards the second issue, questions of procedural fairness are not decided according to  
any particular standard of review; deference has no room in the analysis, and the Court must be  
fully and independently satisfied that procedural fairness has been met and that the decision-  
making process was fair, having regard to all of the circumstances (Canadian Pacific Railway  
Company v Canada (Attorney General), 2018 FCA 69 at para 54 [Canadian Pacific Railway  
Company]; Angara v Canada (Citizenship and Immigration), 2021 FC 376 at para 23 [Angara]).  
Analysis  
A.  
Preliminary matter: Is the application for judicial review moot and premature?  
[71] The VFPA takes up before me the issues argued before Prothonotary Furlanetto during its  
earlier motion to strike and raises mootness and prematurity as preliminary issues. The port  
authority argues that the September 2019 decision rescinded the March 2019 decision and that  
whether flawed or not, the March 2019 decision no longer prevents GCT from submitting its  
PPE for DP4. Consequently, there is no need for an order in the nature of certiorari as the  
September 2019 decision already quashed the March 2019 decision. The matter is therefore moot  
as there is no practical effect of the relief sought by GCT.  
     
Page: 40  
[72] The VFPA also argues that the present application is premature for two reasons; first, and  
although invited to do so, GCT refused to make submissions on bias to the VFPA and is  
therefore now barred from raising the issue on judicial review. In addition, the VFPA argues that  
as the GCT failed to re-engage the PER Process after the September 2019 decision, it does not  
have an active application before the VFPA for a permitting decision, and with the repeal of the  
CEAA and the enactment of the IAA, the VFPA’s authority to exercise any powers or perform  
any duties or functions is curtailed.  
[73] Putting aside the issue of res judicata raised by GCT, I must agree with Prothonotary  
Furlanetto (2020 FC 348) and with Mr. Justice Phelan (2020 FC 1062), who maintained the  
Prothonotary’s decision in refusing to strike GCT’s application: after considering the test set out  
in Borowski on the issue of mootness, both Prothonotary Furlanetto and Justice Phelan  
determined that the issue of purported bias permeates the entire debate between the parties as  
well as their continued relationship in respect of the DP4 project. Mr. Justice Phelan summarized  
the bias concerns of GCT in this way: “how can [GCT] receive a fair and unbiased consideration  
of its own project in the face of VFPA’s clear preference for its own project?” The fact that the  
VFPA may have rescinded its March 2019 decision does not make the bias concerns of GCT go  
away, even with the change in legislative landscape.  
[74] GCT continues to argue that the VFPA cannot shake the bias shown with the March 2019  
decision by making a tactical decision to “rescind” it with the September 2019 decision. In  
addition, this is not, as was the case in 0769449 BC Ltd (Kimberly Transport) v Vancouver  
Fraser (Port Authority), 2016 FC 645, and Kozel v Canada (Citizenship and Immigration),  
Page: 41  
2015 FC 593, cited by the VFPA, a situation whereby the change in the legislation transferred  
the power to grant licences to access the Port of Vancouver’s premises from the VFPA to another  
administrative body, or a case where the change in the statute resulted in the termination of an  
applicant’s legal status. In this case, the statutory change did not transfer any responsibility  
relating to permitting from the VFPA to another administrative body; the VFPA still needs to  
conduct its review of DP4 under its PER Process with permitting authority regarding the tasks  
inherent in the actual construction and operations of the project, although admittedly now only  
following review under the IAA. In other words, regardless of the newly enacted IAA, GCT  
eventually still required port authority approval to pursue the project. Accordingly, deciding not  
to accept the PPE under the PER Process goes to the heart of GCT’s bias claim. Moreover, the  
claim of prematurity arises from the purported rescission of the March 2019 decision; however,  
if GCT’s bias concerns are valid, such a finding would certainly influence any determination as  
to whether the VFPA manipulated the prematurity doctrine with its September 2019 decision to  
shield itself from judicial review, and thus “game the system”.  
[75] With respect to the issue of exhaustion and the argument that GCT circumvented the  
VFPA’s primary jurisdiction by not raising the bias issue first with the VFPA (Chopra v Canada  
(Attorney General), 2013 FC 644 at para 66; Lin v Canada (Public Safety and Emergency  
Preparedness), 2021 FCA 81 at para 6 [Lin]), I accept the general principle of non-interference  
with ongoing administrative processes subject only to exceptional circumstances, and I accept  
that concerns regarding procedural fairness or bias are not exceptional circumstances allowing  
parties to bypass an administrative process as long as that process allows the issues to be raised  
and an effective remedy to be granted (Canada (Border Services Agency) v CB Powell Limited,  
Page: 42  
2010 FCA 61 at para 33 [CB Powell Limited]). However, as was the case with Prothonotary  
Furlanetto, I have not been convinced that there existed an adequate route or process for the  
VFPA, as a non-adjudicative tribunal saddled with commercial and operational responsibility for  
running the Port of Vancouver, to have considered its own bias, and that informal  
correspondence was simply inadequate as a procedure under the circumstances.  
[76] I also accept that what was before Prothonotary Furlanetto was a motion where the  
threshold for striking a notice of application is higher (David Bull Laboratories (Canada) Inc v  
Pharmacia Inc (CA), [1995] 1 FC 588 at 600)the test for which the VFPA simply did not  
meetand thus the prism through which I should review the issues of mootness and prematurity  
is different. However, the fundamental problem remains the same, i.e., GCT’s concerns over bias  
have a direct impact upon how these two issues are to be assessed.  
[77] Under the circumstances, what remains is very much a live issue between the parties, and  
as stated by Prothonotary Furlanetto, “[t]he facts set out in the application raise issues as to the  
ability of the port authority to discharge its statutory duty and provide unbiased oversight and as  
to its accountability if it cannot do so. These allegations will persist until they are evaluated by  
the Court.” I agree, and the situation that existed before Prothonotary Furlanetto and Justice  
Phelanas well as the FCA, although only the issue of prematurity was raised on appeal—  
remains today, and as stated by Justice Phelan, it would be wasteful to compel GCT to file a  
fresh PPE containing the same basic request for project approval “only to end up in the same  
position as at present”; the issue of bias must be addressed.  
Page: 43  
B.  
Did the VFPA breach the principles of natural justice and procedural fairness by  
rendering a decision tainted by bias and by breaching GCT’s legitimate expectations  
regarding the review of its PPE?  
[78] There is no doubt that ““[a]ll administrative bodies, no matter what their function, owe a  
duty of fairness to the regulated parties whose interest they must determine” (Newfoundland  
Telephone Co v Newfoundland (Board of Commissioners of Public Utilities), [1992] 1 SCR 623  
at 636 [Newfoundland Telephone]).  
[79] The Court’s assessment of the content of procedural fairness should be guided by the five  
non-exhaustive contextual factors set out by the Supreme Court in Baker v Canada (Minister of  
Citizenship and Immigration), [1999] 2 SCR 817 [Baker] (Angara at para 23). As stated by  
Justice L’Heureux-Dubé, the concept of procedural fairness is flexible and variable as there is no  
set rule for what requirements will be applicable in any given case; there are several factors in  
the spectrum analysis which are relevant in determining the content of the common law duty of  
procedural fairness in a given set of circumstances (Baker at paras 21 and 22). Although not  
exhaustive, such factors include (Baker at paras 23 to 28):  
i.  
the nature of the decision being made and the process  
followed in making it;  
ii.  
iii.  
the nature of the statutory scheme and the terms of the  
statute pursuant to which the body operates;  
the importance of the decision to the individual or  
individuals affectedthe more important the decision is to  
the lives of those affected and the greater its impact on that  
person or those persons, the more stringent the procedural  
protections that will be mandated;  
iv.  
the legitimate expectations of the person challenging the  
decision;  
 
Page: 44  
v.  
the choices of procedure made by the agency itself,  
particularly when the statute leaves to the decision maker  
the ability to choose its own procedures.  
[80] In addition, the common law has long recognized that bias on the part of an  
administrative decision maker erodes any sense of procedural fairness, which in turn negatively  
affects the duty of fairness which applies to all administrative bodies. In Newfoundland  
Telephone, the Supreme Court of Canada set out the issue as follows at page 636:  
Although the duty of fairness applies to all administrative bodies, the  
extent of that duty will depend upon the nature and the function of  
the particular tribunal. See Martineau v. Matsqui  
Institution Disciplinary Board, [1980] 1 S.C.R. 602. The duty to act  
fairly includes the duty to provide procedural fairness to the  
parties. That simply cannot exist if an adjudicator is biased. It is, of  
course, impossible to determine the precise state of mind of an  
adjudicator who has made an administrative board decision. As a  
result, the courts have taken the position that an unbiased  
appearance is, in itself, an essential component of procedural  
fairness. To ensure fairness the conduct of members of  
administrative tribunals has been measured against a standard of  
reasonable apprehension of bias. The test is whether a reasonably  
informed bystander could reasonably perceive bias on the part of  
an adjudicator.  
[Emphasis added.]  
[81] The need for a spectrum or content analysis to establish the scope of the duty of  
procedural fairness was also outlined in Newfoundland Telephone, where Justice Cory stated:  
It can be seen that there is a great diversity of administrative  
boards. Those that are primarily adjudicative in their functions will  
be expected to comply with the standard applicable to courts. That  
is to say that the conduct of the members of the Board should be  
such that there could be no reasonable apprehension of bias with  
regard to their decision. At the other end of the scale are boards  
with popularly elected members such as those dealing with  
planning and development whose members are municipal  
councillors. With those boards, the standard will be much more  
Page: 45  
lenient. In order to disqualify the members a challenging party  
must establish that there has been a pre-judgment of the matter to  
such an extent that any representations to the contrary would be  
futile. Administrative boards that deal with matters of policy will  
be closely comparable to the boards composed of municipal  
councillors. For those boards, a strict application of a reasonable  
apprehension of bias as a test might undermine the very role which  
has been entrusted to them by the legislature.  
[Emphasis added.]  
[82] In Old St Boniface Residents Assn Inc v Winnipeg (City), [1990] 3 SCR 1170 [Old St  
Boniface], the Supreme Court stated that “[t]he rules which require a tribunal to maintain an  
open mind and to be free of bias, actual or perceived, are part of the audi alteram partem  
principle which applies to decision-makers” (Old St Boniface at p 1190). In addition, Justice  
Sopinka set out the standard for the determination of whether a closed mind exists at page 1197:  
In my opinion, the test that is consistent with the functions of a  
municipal councillor and enables him or her to carry out the  
political and legislative duties entrusted to the councillor is one  
which requires that the objectors or supporters be heard by  
members of Council who are capable of being persuaded. The  
Legislature could not have intended to have a hearing before a  
body who has already made a decision which is irreversible. The  
party alleging disqualifying bias must establish that there is a  
prejudgment of the matter, in fact, to the extent that any  
representations at variance with the view, which has been adopted,  
would be futile. Statements by individual members of Council  
while they may very well give rise to an appearance of bias will  
not satisfy the test unless the court concludes that they are the  
expression of a final opinion on the matter, which cannot be  
dislodged. In this regard it is important to keep in mind that  
support in favour of a measure before a committee and a vote in  
favour will not constitute disqualifying bias in the absence of some  
indication that the position taken is incapable of change. The  
contrary conclusion would result in the disqualification of a  
majority of Council in respect of all matters that are decided at  
public meetings at which objectors are entitled to be heard.  
[Emphasis added.]  
Page: 46  
[83] In other words, in line with the spectrum analysis relating to the content of the scope of  
procedural fairness, a certain level of pre-judgment of decision makers is to be expected in  
certain circumstances, as long as it does not equate to intransigencea closing of the mind to the  
point of no longer being able to be otherwise persuaded.  
[84] In Yukon Francophone School Board, Education Area #23 v Yukon (Attorney General),  
2015 SCC 25 [Yukon Francophone School Board], the Supreme Court of Canada noted that the  
objective of the reasonable apprehension of bias test “is to ensure not only the reality, but the  
appearance of a fair adjudicative process” and that the issue of bias is thus “inextricably linked to  
the need for impartiality” (at para 22). In particular, as regards the judiciary, suspicions,  
speculations or the possibilities of bias is not enough. The test for a reasonable apprehension of  
bias requires a “real likelihood or probability of bias” (Yukon Francophone School Board at para  
25, citing Arsenault-Cameron v Prince Edward Island, [1999] 3 SCR 851).  
[85] That said, and as instructed in Baker, one must also look to the statutory scheme which is  
the source of the decision maker’s legitimacy in determining the content of the duty of fairness  
owed when a particular administrative decision is made (Baker at para 24). Thus, in assessing the  
issue of bias, courts must also take into account the particular process at hand:  
In administrative law the question is not simply whether an  
administrative decision-maker has a bias. It is also whether any  
bias which the decision-maker has is authorized by law. This is an  
important distinction to make. To fail to take this into account will  
result in improper pigeon holing of administrative processes where  
individual administrative schemes are judged according to general  
standards rather than the standards appropriate to the particular  
process at hand.  
[Emphasis added.]  
Page: 47  
(Robert W. MaCaulay & James L.H. Sprague, Hearings Before  
Administrative Tribunals, 5th ed (Toronto: Thomson Reuteurs.  
2016) at p 39-5 39-6.)  
[86] As stated by the Supreme Court of Canada in Ocean Port Hotel Ltd v British Columbia  
(General Manager, Liquor Control and Licensing Branch), 2001 SCC 52 at paras 20, 22 and 42  
[Ocean Port Hotel]:  
[20] … It is well established that, absent constitutional constraints,  
the degree of independence required of a particular government  
decision maker or tribunal is determined by its enabling statute. It  
is the legislature or Parliament that determines the degree of  
independence required of tribunal members. The statute must be  
construed as a whole to determine the degree of independence the  
legislature intended.  
[22] However, like all principles of natural justice, the degree of  
independence required of tribunal members may be ousted by  
express statutory language or necessary implication. …  
[42] Further, absent constitutional constraints, it is always open to  
the legislature to authorize an overlapping of functions that would  
otherwise contravene the rule against bias. …  
[Emphasis added.]  
[87] Given the parameters of the CMA, I find that in its regulatory, decision-making role, the  
VFPA falls, as set out in Newfoundland Telephone, [a]t the other end of the scale” where “the  
standard [for procedural fairness] will be much more lenient” and where in order to challenge a  
decision for reasons of bias, GCT must establish “that there has been a pre-judgment of the  
matter to such an extent that any representations to the contrary would be futile” (Newfoundland  
Telephone at p 638; Old St Boniface at p 1197).  
Page: 48  
[88] That said, Parliament can authorize an overlapping of functions that would otherwise run  
afoul of the rule against bias at common law. As stated by the Supreme Court in Brosseau v  
Alberta Securities Commission, [1989] 1 SCR 301 at page 310 [Brosseau]:  
Administrative tribunals are created for a variety of reasons and to  
respond to a variety of needs. In establishing such tribunals, the  
legislator is free to choose the structure of the administrative  
body. The legislator will determine, among other things, its  
composition and the particular degrees of formality required in its  
operation. In some cases, the legislator will determine that it is  
desirable, in achieving the ends of the statute, to allow for an  
overlap of functions which in normal judicial proceedings would  
be kept separate. In assessing the activities of administrative  
tribunals, the courts must be sensitive to the nature of the body  
created by the legislator. If a certain degree of overlapping of  
functions is authorized by statute, then, to the extent that it is  
authorized, it will not generally be subject to the doctrine of  
“reasonable apprehension of bias” per se.  
[Emphasis added.]  
[89] GCT asserts that the matter under the present application for judicial review is not one  
regarding any permissible structural bias by virtue of the VFPA’s overlapping statutory roles—to  
which, it argues, the decision in Ocean Port Hotel would applybut rather one of actual bias,  
where the decision maker has a closed mind and a direct interest in the matter in the way in  
which it dealt with the DP4 project. GCT argues that the VFPA’s “dogged pursuit of its  
competing project” has undermined its ability to objectively evaluate the DP4 project. In short,  
GCT asserts that the VFPA, as landlord, regulator and proponent, has closed its mind and cannot  
fairly review the DP4 project and that therefore any review of its project cannot continue under  
the existing structure on the grounds of actual bias, or at least a reasonable apprehension of bias.  
Page: 49  
[90] The AGC made no submissions on the issue of bias. Regarding the issue of possible  
structural bias, the VFPA argues that nothing in the CMA, the letters patent or the governing  
regulations obliges the VFPA to have regulated activities within the Port of Vancouver carried  
out by third-party operators or to defer to third-party operators the long-term operational and  
management objectives set by the VFPA. It asserts that the decision-making structure in place is  
determined by the governing legislation and consequently, absent constitutional constraints, it  
was open to Parliament to authorize an overlapping of functions that would otherwise contravene  
the rule against bias. Accordingly, argues the VFPA, even where the plurality of functions  
prescribed to a port authority under the CMA “would otherwise offend the rule against bias, it  
may well be that this structure was authorized by the [CMA] at the relevant time” (Ocean Port  
Hotel at paras 42 and 43) and that therefore the relevant statutory scheme of the CMA ousts the  
common law duty of procedural fairness in this case (Ocean Port Hotel at paras 20, 22 and 42;  
Democracy Watch v Canada (Attorney General), 2018 FC 1290 at paras 5, 128).  
[91] I agree with the VFPA on the structural bias issue. GCT defines bias as meaning a closed  
mind and a refusal to make a fair and rational decision based on objective evidence-based  
considerations, and instead making a decision based on predeterminations on the part of the  
VFPA. However, similar to the case in Old St Boniface, where there are, as here, statutorily  
created overlapping functions of the decision maker, including both a commercial and regulatory  
role, I would think that it is to be expected that “some degree of pre-judgment is inherent” in the  
decision-making process (Old St Boniface at p 1196). Throughout its submissions before me, GCT  
skilfully tried to tiptoe around the 6-ton elephant in the room, to wit, that the VFPA has been set  
up as a commercially driven, financially sustainable, non-adjudicative decision maker, and it  
Page: 50  
never properly addressed at what point on the spectrum analysis of procedural fairness did the  
VFPA, in its conduct or failings, cross the Rubicon from permissible, structural bias to the  
domain of impermissible bias; GCT only asserted that the indicia of bias it claimed to highlight  
were evidence of actual bias.  
[92] The legislative scheme created by Parliament explicitly tasks the VFPA with overlapping  
functions: the VFPA is the commercial operator of the Port of Vancouver, a functioning,  
operational port authority focused on running the Port of Vancouver in accordance with the port  
activities as set out in section 28 of the CMA by managing, occupying and holding port property.  
At the same time, the VFPA acts as a regulator tasked, inter alia, with developing a land use plan  
that may regulate the use of the property it manages, holds and occupies, and with authorizing  
certain activities within the port (subsections 28(1), 44(2), and 44(6) and sections 45 and 48 of  
the CMA; sections 20 to 28 of the Regulations; article 3.2 of the letters patent). The  
determination of the level of impartiality that is expected of the decision maker is rooted in the  
statute that created it, and in the case of the CMA, it is a balance struck by Parliament as between  
competing interests: on the one hand, what is normally expected of a completely independent  
adjudicative decision maker, and on the other, the unbridled independence required in decision-  
making and commitment to long-term strategic planning so as develop and run a commercially  
sustainable port operation. The VFPA is free either to operate the terminals within the port itself  
or to lease the property to third-party commercial operators such as GCT. In short, by enacting  
the CMA legislative scheme, Parliament chose to vest the VFPA with all these roles, roles which  
cannot be parsed into separate silos.  
Page: 51  
[93] Accordingly, I am mindful that throughout the decision-making process, a certain level of  
pre-judgment is to be expected from the VFPA executives, who are primarily business-minded  
individuals tasked with making decisions in the exercise of long-term and ongoing  
developmental planning for the Port of Vancouver—such “bias” would be structural, and a  
consequence of the VFPA’s plurality of operational and statutory functions; I should mention  
that GCT never truly took issue with what may be some level of permitted structural bias on the  
part of the VFPA executives, and I will consider GCT’s arguments of actual bias through this  
prism.  
[94] I should also mention that the VFPA has the discretion to refuse to authorize activities  
that are inconsistent with its long-term development plans and, in its reasonable opinion, the  
commercial interests of the Port of Vancouver. GCT argues that the full economic risk of RBT2  
resides for the moment with the VFPA. That may be true, however, although RBT2 is being  
developed by the VFPA as project proponent, which is normally the case for large new  
infrastructure development projects, the evidence suggests that it is the intention of the VFPA to  
find, through an ongoing request for proposal (RFP) process, a third-party commercial tenant for  
RBT2 to operate the new terminal, and in fact, as mentioned, GCT had applied to be the terminal  
operator for RBT2. I do not accept GCT’s argument before me that the fact that the full  
economic risk for RBT2 presently rests with the VFPA goes to the issue of its bias. It may be  
that under optimal circumstances, one would expect to have an operator, a lease and some  
operational structure already in place in advance of construction; however, the process to secure  
a third-party commercial operator for RBT2 continues for the VFPA, and I see nothing to  
suggest that one may not be found prior to the start of construction on RBT2, even assuming that  
Page: 52  
confirmation by that time of a third-party terminal operator being in place is even necessary. In  
any event, there is no indication that, throughout its dealings with GCT in relation to the DP4  
project, the VFPA acted in any capacity that was not otherwise permitted under the governing  
legislation or its letters patent. Even if it can be argued that the overlapping functional structure  
under the CMA creates a reasonable apprehension of bias when port authorities are undertaking  
their regulatory role, it was open to Parliament to set up port authorities as it did under the CMA.  
[95] That said, the Supreme Court in Brosseau did not close the door to a finding of actual  
bias where there is a plurality of functions undertaken by the decision maker; in other words, a  
statutorily-created overlapping structure is not a hall pass for actual bias. The fact that Parliament  
has created an overlapping structure which, itself, may support independence and the existence  
of some level of structural bias on the part of the decision maker does not shield the statutory  
decision maker from a finding of impermissible bias in its decision-making process. I use the  
expression “impermissible bias” because I recognize that the CMA, by creating overlapping  
roles for port authoritieswhere they are mandated to commercially run their ports in a  
financially sustainable fashion, act as proponents on major work projects, and manage external  
communication and outreach with stakeholderscan only be interpreted as tolerating a lesser  
degree of impartiality in its regulatory function as compared with a traditional, adjudicative  
decision maker whose role it is to act as arbiter between two competing positions. As stated by  
the Supreme Court in Ocean Port Hotel, “the degree of independence required of a particular  
government decision maker or tribunal is determined by its enabling statute”, which “must be  
construed as a whole to determine the degree of independence the legislature intended(Ocean  
Port Hotel at para 20). GCT is not arguing otherwise, but states simply that the VFPA was  
Page: 53  
actually biasedacting even below any permissible lower degree of independence or  
permissible bias that Parliament may have permitted with the enactment of the CMA.  
[96] GCT argues that the VFPA never considered its PPE, which was submitted on  
February 5, 2019, because the VFPA, as a conflicted regulator, let its penchant for its own  
project cloud and displace its regulatory obligations. In a case of overlapping functions such as  
the powers vested in the VFPA by the CMA, I suspect that the port authority will always be  
somehow conflicted to a certain extent when performing its regulatory role given that it performs  
such a role with the baggage of also being the port operator, including having to consider its  
long-term plans for port development. I would think that this is what the parties refer to as  
structural bias, i.e., the displacement of the common law principles of procedural fairness that  
have been created by statute and permitted under Brosseau. However, what was stated by the  
Supreme Court in Brosseau was that where a decision maker is undertaking overlapping  
functions to the extent that they are authorized under statute, it will not generally be subject to  
the doctrine of reasonable apprehension of bias per se. It seems to me therefore that legislative  
construct alone will not in all cases shield a decision maker from a finding of actual,  
impermissible bias when undertaking overlapping functions. In other words, although the VFPA  
is a regulator with an acceptable preference, it cannot allow that preference to cloud and displace  
its regulatory obligations, in particular the need for respect for a degree of natural justice and  
procedural fairness called for under the circumstances.  
[97] It therefore becomes necessary to consider the indicia which GCT asserts demonstrates  
actual, impermissible bias, or at the very least is evidence of a reasonable apprehension of bias in  
Page: 54  
the decision-making process apart from the structural allowances, on the part of the VFPA. GCT  
argues that the indicia of bias on the part of the VFPA is clear and that in any event, the VFPA  
otherwise breached the principles of natural justice and procedural fairness by refusing to act in  
accordance with GCT’s legitimate expectations in not processing its PPE in accordance with the  
PER Process and the Guide. The VFPA takes issue with what GCT calls the indicia of bias,  
asserting that such “indicia” pointed to by GCT do not in any way establish, or even suggest,  
bias on its part.  
(1)  
Has the VFPA demonstrated impermissible bias by closing its mind to the DP4  
project?  
[98] As summarized by Mr. Justice Pentney in his Order of June 17, 2021, “the core of GCT’s  
Amended Notice of Application for Judicial Review is its claim that VFPA’s actual bias against  
GCT is evident from the decision letters regarding both the refusal to consider its project  
proposal in March 2019, as well as the subsequent rescission in September 2019.” In particular,  
GCT sets out a series of primary facts which, it argues, are elements which demonstrate the  
VFPA’s actual bias, as well as the desire to stonewall and undermine any objective consideration  
of DP4 culminating in the March 2019 decision, and that such bias renders void everything  
thereafter which the VFPA may have done in an attempt to right the ship, in particular, by  
issuing the September 2019 decision.  
[99] The elements of actual bias raised by GCT are, it argues, reflected in the March and  
September 2019 decisions themselves, the manner in which those decisions were orchestrated,  
and the declared preference of RBT2 over DP4 by the VFPA. I will deal with GCT’s arguments  
in relation to each of the identified indicia of bias on the part of the VFPA.  
 
Page: 55  
(a)  
Were the March and September 2019 decisions, the manner in which they  
were made and the statements made therein, reflective of an actual bias or  
even a reasonable apprehension of bias on the part of the VFPA?  
[100] From a timing perspective, there is no evidence that GCT considered the VFPA to be  
biased against the DP4 project prior to the March 2019 decision. Before me, GCT conceded that  
the closest the evidence came on that issue was to be found in the cross-examination of  
Mr. Doron Grosman, President and CEO of GCT, where Mr. Grosman stated that GCT was  
aware that a “myriad of factors” would have to be considered by the VFPA upon receipt of the  
PPE.  
[101] In the March 2019 decisionwhat GCT calls the initial declaration of biasthe VFPA  
set out the context and history of container terminal expansion in the Port of Vancouver, and in  
particular at Deltaport, and the fact that RBT2 has been in the planning stages since 2013. The  
port authority underscored that it plans for additional capacity to be built on the west side of the  
existing terminal, in deeper waters, as it was encouraged to do by DFO in 2003, and noted that  
the updated project rationale for RBT2, filed in 2018, emphasized that (1) DFO prohibited  
further land reclamation inland from Deltaport, and (2) healthy competition within the port  
would be encouraged. As to the earlier environmental studies, the VFPA reiterated that one of  
the driving factors in the eventual recommendation of DP3, which became operational in 2010,  
was the reduced footprint of the project, which minimized the potential effects on existing fish  
and wildlife habitat. Accordingly, the VFPA confirmed that its preferred project for capacity  
expansion to meet increased demand was RBT2. Although the VFPA decided not to proceed  
with reviewing GCT’s PPE for DP4 at that time, in particular, because the proposed development  
 
Page: 56  
timeline for DP4 would conflict with the implementation of RBT2 capacity, it did not shut the  
door to future consideration of DP4 as a subsequent and incremental project.  
[102] GCT submits that the VFPA’s stated rationale for the March 2019 decision is baseless as  
it relies on what GCT calls a mischaracterization by the VFPA of the 2003 DFO letters and on  
vaguely framed competition concerns. The essence of GCT’s argument is that such stated  
rationale, the tactical way the decisions were orchestrated and the fact that the VFPA stated that  
RBT2 was its preferred project without first conducting a formal review of DP4 can only lead to  
a conclusion that the VFPA was biased in its decision-making process in relation to DP4. I will  
now deal with each of those issues.  
(i)  
Stated rationale  
[103] GCT argues that the statements contained in the March 2019 decision in support of the  
decision to refuse to even consider the PPE, in particular regarding the effect of the 2003 DFO  
letters and regarding its competition concerns, demonstrate both a closed mind to exercising  
objective statutory decision-making regarding DP4 and an intention to mischaracterize and  
embellish facts to justify the VFPA’s closed mind.  
1.  
The notion of prohibition  
[104] As a first rationale, the March 2019 decision provides the following:  
At Roberts Bank, expanding the existing Deltaport container  
terminal is not an option for two main reasons. First, [DFO] has  
prohibited further land reclamation inland from Deltaport, due to  
environmental sensitivity. The graphic below shows how further  
   
Page: 57  
expansion at Deltaport would have to be built almost entirely in the  
sensitive intertidal habitat within the inter-causeway area.  
[Emphasis added.]  
[105] As regards the 2003 DFO letters, GCT argues that the VFPA knew that the claim that it  
posted on the updated Project Rationale for the RBT2 project and that it outlined in the March  
2019 decision that DFO had prohibited land reclamation inland of Deltaportthe proposed area  
for the DP4 projectwas simply not true and that such a claim is further evidence of its bias  
against DP4. To understand GCT’s position, a little context is needed.  
[106] As mentioned earlier, the VFPA-sponsored T2 project was put on hold in 2006 in favour  
of the scaled down version of the DP3 project, which was completed; however, the project  
eventually to become RBT2 remained as a possible consideration for future expansion after the  
completion of DP3. With the DP3 project becoming operational in January 2010, the VFPA  
turned its mind back to the development of a new terminal at Roberts Bankpreferring to  
develop in deeper waters, to the west of the causeway, as recommended by DFO in 2003. Having  
moved the project forward sufficiently, the VFPA entered the review process for RBT2 in 2013  
and proceeded to file its EIS for federal review in March 2015.  
[107] Around the same time, GCT began discussing the development of DP4 with the port  
authority. Given the VFPA’s role as project proponent for RBT2 and its concurrent role as  
regulatory gatekeeper for the DP4 project, the requirement to ensure transparency and objectivity  
for DP4 was directed by the VFPA’s board of directors during a board meeting held on  
March 31, 2015, at which the VFPA executives were also in attendance. Following a PowerPoint  
Page: 58  
presentation of GCT’s proposed expansion at Deltaport given by the one of the VFPA executives  
to the VFPA board of directors, as well as a summary of the VFPA management’s preliminary  
assessment of GCT’s proposal, the board noted that it was critical that GCT’s proposal be  
evaluated by the VFPA with “an open mind”—echoing the requirements of the PER Process and  
the port authority’s statutory obligations.  
[108] In January 2017, GCT made a detailed presentation to the VFPA of the proposed DP4  
project, including the business case for moving its project forward rather than RBT2 because,  
according to GCT, the DP4 project is the most competitive, cost-effective way to address  
growing container demand on the West Coast of Canada. It seems clear that at this point, GCT  
saw the RBT2 project moving forward, with the prospect of a new terminal operator eating into  
the existing share of the container market at the Port of Vancouver. Following the presentation,  
the VFPA raised various environmental issues, in particular those addressed in the 2003 DFO  
letters, which would make DP4 a challenge to be approved. The matter culminated in the port  
authority retaining Hemmera, as outlined earlier. The non-disclosure agreement between GCT  
and the VFPA in relation to the Hemmera Report, which was delivered in November 2017,  
expired in May 2019, allowing GCT to present that report to the Review Panel set up under the  
CEAA for the purpose of reviewing RBT2. As stated, although the Hemmera Report does not  
squarely address the issue of whether the 2003 DFO letters constituted a prohibition of  
development in the area at the time, the reportwith the hindsight of the regulatory changes and  
advances in scientific understanding over the previous 14 yearsdid manage to set out eight  
mitigating factors to consider should a proponent seek to develop the area of the proposed DP4  
project; in fact, the completion of DP3 is testament to the fact that development east of the  
Page: 59  
causeway, to the landward side, is possible with, as was the case with DP3, mitigating steps  
taken to address environmental concerns, including building in offsets for lost fish and wildlife  
habitat to the satisfaction of regulators, and building a smaller footprint than initially proposed.  
However, we should also keep in mind that the Hemmera Report also made it clear that it “draws  
no conclusion related to the potential likelihood of attaining approvals and authorizations for  
project(s) along the East Causeway of Deltaport.”  
[109] With the Hemmera Report in hand, as stated earlier, with the February 2, 2018 letter, the  
VFPA wrote to GCT confirming the terminal operator’s right to apply to have DP4 reviewed  
under the PER Process and stated that, however, “having regard to the history of environmental  
issues associated with the eastern side of the causeway, any proponent of such a project should  
expect significant environmental assessment requirements. … [and that] even if the previously  
identified environmental issues associated with such a project proved to be mitigable to some  
extent, those impacts would have to be considered in a cumulative context with [RBT2].” The  
VFPA went on to state that “given the multifaceted role of VFPA as discussed above, we believe  
it would be entirely appropriate and indeed incumbent upon VFPA to also consider the impacts  
of a DP4 project on the overall port operations. VFPA would also consider the issue of timing,  
recognizing the very significant lead times required for such projects, and the looming need for  
more near term capacity in the Port of Vancouver.” (Emphasis added).  
[110] GCT states that the upshot of the February 2, 2018 letter is that the VFPA is confirming  
that it will consider the project if GCT wishes to propose it, given the concerns expressed, and  
also that there will be environmental assessments that the parties will have to work through in  
Page: 60  
order to get to an evidence-based objective conclusion about the environmental impacts. In  
addition, GCT reads the letter as indicating that it is incumbent on the VFPA to consider DP4 in  
connection with the impact on the overall port operationswhich I take to include how the  
VFPA sees port development and operations moving forward and the policy decisions made by  
the port authority in relation theretoand that due process will be followed and objective  
considerations will be made in coming to a final decision on whether DP4 moves forward.  
[111] It seems to me that the February 2, 2018 letter was tantamount to a pre-emptive  
procedural fairness letter, meant to make clear the concerns of the port authority if called upon to  
act in its regulatory capacity should GCT trigger the PER ProcessI deal with this issue further  
belowand provide GCT with some insight on the considerations the port authority would deem  
important in the assessment of DP4. GCT states that I am reading too much into the letter, that  
the Review Panel hearings had not yet commenced and that whether or not RBT2 would ever see  
the light of day was still an open question. That may be so, and I accept that RBT2 was not at  
that point a fait accompli, but the fact remains that the VFPA entered the environmental  
assessment process with RBT2 in September 2013 and had already submitted its EIS regarding  
the RBT2 project for federal review in March 2015, about three years earlier; GCT was still in  
the planning stages for DP4. I think that it is safe to say that when the VFPA mentioned that DP4  
would need to be looked at in the context of overall port operations and that the issue of timing  
would also need to be taken into consideration (recognizing the very significant lead times  
required for such projects and the looming need for more near-term capacity in the port), the fact  
that RBT2 was already well ahead of DP4 in the regulatory pipeline should have been expected  
to be an important element in the eventual assessment decision of the port authority.  
Page: 61  
[112] A year later, on February 5, 2019, GCT formally submitted its PPE through the PER  
Process portal, which was met with the March 2019 decision, which GCT argues is an  
unequivocal declaration of a closed mind and actual bias as it was made clear that the motivation  
behind refusing to allow DP4 into the regulatory gate and therefore precluding it from any  
objective consideration on the merits, is that RBT2 is the VFPA’s preferred project. With the  
March 2019 decision, GCT argues that the VFPA is cross-contaminating its two competing roles,  
the first as a proponent for a project, and the second as the regulator, and as stated earlier,  
although it may have properly reached the decision at some point that RBT2 was to be the  
preferred project, it was necessary that such a decision be reached only after a fair, independent,  
objective, evidence-based decision-making process was undertaken so that such a decision could  
be made on its merits. From GCT’s perspective, any decision by the VFPA that its preferred  
project was to be RBT2 was arrived at through an opaque decisionmaking process without  
justification or transparency, and thus, an indicium of impermissible bias.  
[113] GCT points to the Hemmera Report as well as to confirmation from the DFO witnesses  
themselves during the Review Panel hearings to argue that the 2003 DFO letters were not meant  
to constitute a prohibition against future development of the area proposed for DP4. GCT adds  
that, in fact, the VFPA was actually aware that no prohibition existed and GCT points to the  
speaking notes of Duncan Wilson, Vice-President of Environment, Community and Government  
Affairs [Mr. Wilson’s speaking notes], prepared with the view of reporting on the status of the  
RBT2 project during a meeting of the VFPA board on March 21, 2018. In addressing the issue of  
support and opposition to RBT2, Mr. Wilson’s speaking notes show what Mr. Wilson called  
“one minor, but important, change to my section.” The passage reads as follows:  
Page: 62  
GCT has conducted a quieter, more focused campaign against  
RBT2, since RBT2 would create additional competition for them.  
They have repeatedly claimed that further expansion of Deltaport  
(i.e. DP4) could provide required capacity in a more economic and  
environmentally friendly manner. And as we have mentioned,  
GCT’s proposal is likely unapprovable from an environmental  
perspective, results in comsolidation [sic] of market control and  
has not entered any regulatory process.  
[Emphasis added.]  
[114] I have underlined the reference to the VFPA’s concern over the concentration of market  
share and the fact that DP4 had not ever entered the regulatory process at that time, issues that I  
will come back to later. For now, in the amended version of Mr. Wilson’s speaking notes, the  
words likely unapprovable from an environmental perspectivewere changed to located in an  
area that has been rejected by DFO in the past (high value shallow-intertidal habitat). GCT  
argues that not only did Mr. Wilson avoid the use of the word “prohibited” in the first draft  
(choosing simply to say that DP4 was “likely unapprovable”), but he also shifted further away  
form the concept of prohibition in the amended draft, electing to say only that the location was in  
an area “rejected by DFO in the past”. This, says GCT, is clear confirmation of the mindset of  
the VFPA executive, and when the VFPA echoed the statement in its March 2019 decision that  
development in the area of the proposed DP4 project was “prohibited”, the port authority knew it  
to be an untruth, thereby revealing its impermissible bias against DP4.  
[115] I accept that the use of the word “prohibition” outlined in the March 2019 decision is  
confusing. However, I am not convinced that the term was used by the VFPA in bad faith so as  
to mislead GCT into thinking that such a prohibition existed. I may have thought otherwise if  
GCT had not had a copy of the Hemmera Report in hand, but it did, and the VFPA knew that it  
Page: 63  
did. Consequently, this is not a case where the VFPA tried to mislead GCT with information  
only the VFPA had in hand; GCT was able to come to its own independent conclusions as to  
what the report said or did not say about the intent of the 2003 DFO letters. What is clear is that  
the Hemmera Report does not squarely address whether the 2003 DFO letters constitute a  
prohibition against development in the area proposed for DP4GCT itself conceded before me  
that one must read into the report that the experts consider that the 2003 DFO letters do not  
constitute such a prohibition. Also, I think it important to point out that confirmation from DFO  
that the 2003 DFO letters did not constitute a prohibition against future development in the area  
was only obtained in testimony during the Review Panel hearings in May and June 2019.  
[116] GCT also points to the March 25, 2019 draft, and although the letter was never sent, GCT  
argues that the port authority seemed to be asking a leading question so as to extract from DFO  
an ex post facto justification for its claim that DFO prohibited further development of the area  
where DP4 is now proposed. The March 25, 2019 draft provides:  
The [VFPA] has recently had an inquiry from a proponent  
interested in expanding a Roberts Bank port terminal by reclaiming  
land east of the existing terminals as shown below:  
The port authority is of the opinion that no further terminal  
expansion can be done in the area indicated, as directed by DFO to  
the port authority in the 1970s and in 2003. However, the  
proponent has stated that changes to both the existing Fisheries Act  
and proposed amendments (Bill C-68) have made the earlier  
direction obsolete.  
In a letter dated April 1, 2003 (enclosed), the [VFPA] was advised  
by [DFO] that: DFO will not be involved in any review of the  
Delta Port proposal as the only option proposed for that project  
results in the destruction of critical fish habitat on the east side of  
the causeway … .  
Page: 64  
In a letter dated on or about July 29, 2003 (enclosed), the then  
minister of fisheries wrote “DFO staff has clearly identified the  
unacceptable impacts to critical fish habitat that would occur … .  
Therefore, the port authority requests confirmation from DFO that  
its earlier direction still stands, and that no terminal expansion on  
the east side of the causeway will be permitted.  
[117] Certainly the March 25, 2019 draft may reasonably be read along the lines of GCT’s  
interpretation, but it may also reasonably be read as an honest reflection of how the VFPA had  
understood the 2003 DFO letters, and given GCT’s push-back and assertion “that changes to  
both the existing Fisheries Act and proposed amendments (Bill C-68) have made the earlier  
direction obsolete”, the VFPA was seeking to know whether its initial assessment of the 2003  
DFO letters was correct. In fact, during his cross-examination, Mr. Xotta confirmed as much,  
testifying that the assertion that the 2003 DFO letters constituted a “prohibition” against  
development in the area of the proposed DP4 project was something “that VFPA believed to be  
accurate at that time”. No specific reason was given as to why the letter was never sent other  
than Mr. Xotta, on cross-examination, saying that the decision not to send the letter was taken  
“around the time other things were unfolding and, for whatever reason, [VFPA executives]  
determined that it would not be advisable to send this letter.” GCT suggests that the March 25,  
2019 draft was not sent because a few days later, GCT instituted the present application for  
judicial review and the VFPA simply did not want to know the answer. That said, I find that  
GCT also did not seriously press Mr. Xotta during cross-examination to ascertain the reason for  
the letter not having been sent; maybe GCT did not want to know the answer either. The game of  
cat and mouse continues!  
Page: 65  
[118] In any event, I am not prepared to imply bad faith on the part of the VFPA, and I rather  
chalk up what was confirmed afterwards by DFO as being an imprecise use of the word  
“prohibit” to a misunderstanding on its part. I note that after receiving the March 2019 decision,  
GCT, rather than pointing out to the VFPA what would seem to be an error in the VFPA’s  
characterization of the 2003 DFO letters, instituted the present judicial review application, as  
was its right; in addition, DFO testimony during the Review Panel hearings confirming that no  
such prohibition was intended in the 2003 DFO letters was a factor mentioned by the VFPA in  
the September 2019 decision in deciding to rescind the March 2019 decision.  
2.  
The competition concerns  
[119] As a second rationale, the March 2019 decision provides the following:  
Second, expanding Deltaport would mean one terminal operator  
would control a significant majority of the market for container  
terminal services. Healthy competition is necessary to ensure users  
continue to pay reasonable rates for reliable service. For this  
reason, the [VFPA] is committed to fostering an appropriate level  
of competition within the Port of Vancouver. This competitive  
environment is especially relevant for Canadian exporters who rely  
on the Vancouver gateway.  
[Emphasis added.]  
[120] In the December 2017 Briefing Note, the VFPA highlighted the need for market  
competition within the Port of Vancouver, and stated:  
It is of utmost importance to the [VFPA] that fair and appropriate  
competition be promoted and maintained among container terminal  
operators within the Port of Vancouver and that any dominance  
over container handling operations be avoided. Ongoing control by  
a single operator of more than 60 per cent of the container capacity  
within the Port of Vancouver has proven to be detrimental to  
customers of the gateway. This view was confirmed by market  
 
Page: 66  
sounding and reflects the Competition Bureau’s position that looks  
negatively on existing incumbents expanding to control markets.  
Allowing the new terminal to be run by one of the two existing  
operators without relinquishing some facilities would create a  
near-monopoly in container terminal services of as much as  
80 per cent, which would be unhealthy for the supply chain  
marketplace. Typically, major ports around the world operate with  
at least three competitive container terminals, which we agree is  
best for Canada’s trade competitiveness.  
Consistent with this approach, no concessions or agreements will  
be granted for the [RBT2] Project that would result in an operator  
having more than 60 per cent of the container handling capacity  
within the Port of Vancouver. For this reason, the operators of  
RBT2 and Deltaport will necessarily be entirely independent from  
each other.  
Existing Port of Vancouver container terminal operators were not  
precluded from participating in the terminal operator procurement  
process [for RBT2], but were required to clearly demonstrate, to  
the satisfaction of the port authority, the manner in which the  
participant would ensure fair competition would be maintained and  
confirm that its total container handling capacity within the Port of  
Vancouver would not exceed 60 per cent of the total available  
capacity.  
[Emphasis added.]  
[121] GCT admits being aware of the VFPA’s competition concerns as far back as 2017.  
According to GCT, in the lead-up to the January 2019 pre-PPE meeting for DP4, there was an  
ongoing dialogue regarding the development of the project, and GCT was trying to bring the  
VFPA over to its way of thinking. This ongoing dialogue, in particular as it regarded the issue of  
market concentration, prompted GCT, on December 8, 2017, to make a presentation to the  
VFPA, which included GCT’s perspective on how competition should be measured and assessed  
and in which GCT asserted that looking at the issue of competition from its perspective, DP4 is  
actually good for consumers; as expressed by GCT before me, GCT educated the VFPA on  
Page: 67  
understanding the Herfindahl-Hirschman Index [the HHI], described as a commonly accepted  
measure of market concentration and competition. The VFPA’s concerns over market  
concentration were also expressed by its executive to the VFPA board in March 2018, as seen  
from Mr. Wilson’s speaking notes.  
[122] As to having undertaken its own analysis of the competitive factors at play, on cross-  
examination, Mr. Xotta indicated that from time to time, the VFPA would undertake an analysis  
of the container market, including expertise on pricing, demand and forecasting, and that such  
material was filed as part of the port authority’s RBT2 application under the CEAA; however,  
Mr. Xotta conceded that as part of the record before the Court on the present application for  
judicial review, there is no pricing analysis or report undertaken by an outside expert on  
competition matters. Mr. Xotta also testified that the CMA imposes an obligation on port  
authorities to consider the interests of the port in its commercial operations, and from time to  
time, the port authority would have disagreements with tenants on various issues, including the  
degree of market share the tenant should have going forward. However, Mr. Xotta conceded that  
there was no formal written competition policy applicable at the time the March 2019 decision  
was made setting out the extent of market share that would be appropriate for a single terminal  
operator within the Port of Vancouver.  
[123] In addition to there being no evidence before the Court of any analysis which could have  
informed the VFPA’s assertions or rationale regarding its competition concerns, GCT adds that  
rather than seeking outside professional advice regarding the impact that DP4 would have on  
competition, the VFPA had undertaken an in-house study using what the GCT characterizes as a  
Page: 68  
purpose-built tool to undermine DP4, but with a result that actually disproves the VFPA’s  
hypothesis that DP4 would lessen competition.  
[124] GCT claims that following the presentation on December 8, 2017, the VFPA tried to  
devise a competition case against DP4 that was not based upon a bona fide policy consideration.  
GCT claims rather that the port authority actually tried to create an analysis to support the  
VFPA’s predetermined view—which GCT asserts is evidence of biasthat allowing GCT to  
build DP4 would result in unacceptable market concentration in the container terminal space at  
the Port of Vancouver. GCT points to an internal VFPA email sent two days following the  
December 8, 2017, meeting with GCT whereby Mr. Victor Pang sent a message to Mr. Robin  
Silvester, President and Chief Executive Officer of the VFPA, stating that he looked into the  
HHI, noting that the HHI was being used by the U.S. Department of Justice to assess anti-  
competition in merger and acquisition transactions, and indicating as follows: “We’ll run the  
math as you suggested. But it looks like this framework (and the way DoJ interprets it) is a pretty  
strong tool for us!” [Emphasis added].  
[125] GCT queries what “is a pretty strong tool for us” actually means, in particular  
considering the email sent the next day from Mr. Pang to the VFPA’s finance staff asking them  
to undertake a review of the HHI; after setting out the basis of what the HHI was, Mr. Pang  
stated in his email: “Looks like this can be a really good tool for us to communicate market  
concentration on the container sector.” Mr. Pang then asks that the HHI be run using various  
scenarios envisaging different scopes of the market (from more local ones involving only the  
Canadian West Coast at one end, to the entire west coast of North America on the other) as well  
Page: 69  
as different capacity scenarios, including existing capacity, capacity with the proposed Vanterm  
expansion, DP4 constructionwhether or not GCT divests itself first of Vanterm or the VFPA  
exercises its right of cancellation of its terminal leaseand the construction of RBT2. Then,  
after setting out the different matrices and scenarios to run the HHI, Mr. Pang added: “Research  
on HHI applicability-the point here is to build a case for us to talk to GCT and/or officials about  
the need to increase competition in the container sector, using HHI as a tool.” [Emphasis added].  
[126] Mr. Pang mentioned that he wanted to know, amongst other things, whether Canadian  
agencies use this metric, whether the HHI has been used in situations “similar to GCT’s market  
position and what it means to expand Vanterm and build DP4”, and whether there were any  
examples “where HHI was used as an important factor to halt or place conditions on  
M&A/projects/expansion”. As a final comment, Mr. Pang stated:  
Part of GCT’s argument is that we should use a broader definition  
of market to include PNW [the ports in the Pacific Northwest] and  
LA/LB [the ports of Los Angeles and Long Beach, California].  
Even if the shipping lines indeed think about the market as up and  
down the west coast, I would argue there are specific competitive  
concerns that need to be addressed at the national and local level.  
And the customers in this market are not just the shipping lines,  
but BCO, not to mention other stakeholders. Antitrust issues are  
also often looked at both at global and national level. It would be  
good if we can find examples where HHI was assessed both  
nationally/locally and internationally, and where the agency/court  
specifically mentioned that the national/local view is  
important/paramount.  
[Emphasis added.]  
[127] GCT reads the message of Mr. Pang as giving direction on how to build a competition  
case against DP4. I can see where one might read Mr. Pang’s message in that way, but there is  
also another reasonable way to read his messages. It seems to me that, given the importance of  
Page: 70  
maintaining healthy competition within the Port of Vancouver, Mr. Pang was looking to run  
different scenarios through the HHI and to come up with a series of results in line with those  
scenarios. The actual evidence is that, during his cross-examination, Mr. Xotta indicated that  
GCT was using the HHI “as a basis to advance the position that the market share concerns that  
VFPA has had for some time were unfounded. And so that discussion led to, [Mr. Xotta  
believed], the response or analysis undertaken within VFPA.”  
[128] Clearly, the VFPA was not aware of the HHI as a tool to measure market concentration—  
and to that extent was educated by GCT on the subject. However, given GCT’s own bias in  
favour of DP4a legitimate and understandable bias of any purely commercial proponent  
looking to safeguard its own project and commercial interestsit seems to me that it was  
incumbent upon the port authority to look into this matrix and run the series of scenarios so as to  
better understand how market concentration would be affected; looking for the parts of the  
matrix that GCT may not wish to share with the VFPA in its promotion of DP4 is fair game as  
regards the port authority. I can certainly understand that using GCT’s methodology—looking at  
concentration over a larger area, say the entire west coast of North Americamay diminish the  
relative weight of more localized market concentration than if the area of analysis was only, say,  
the Port of Vancouver. However, in the end, both the VFPA and GCT are using the same matrix,  
the results will be what they will be, and the discussion will continue.  
[129] Turning now to the actual results of the VFPA’s analysis of the various scenarios  
prepared in March 2018 using the HHI, GCT interprets the results as indicating that whatever  
area of the marketplace is adoptedwhether just the Port of Vancouver, or Western Canada, or  
Page: 71  
Western Canada plus the Pacific Northwest, or the entire west coast of North Americathe  
development of DP4 does not create increased market share for GCT. That may be true, but that  
is, it seems to me, beside the point. At the present time, operating both Vanterm and Deltaport,  
GCT controls 78% of the Port of Vancouver container market share, with Centerm (the other  
container terminal operator at the Port of Vancouver) having 22% of the market. The building of  
DP4 will not change those numbersCenterm will continue to have its 22% share of the existing  
market, and GCT will continue to have its 78% share. With the building of DP4, and assuming  
that GCT concurrently divests itself of Vantermalthough before me GCT did not commit to  
doing soits market share based on present container volumes drops to 64% when the  
assessment is based only on the Port of Vancouver, being the narrowest view of the marketplace  
area as stated in the March 2019 decision; market share for GCT drops even further, to 47%,  
even without it having to divest itself of Vanterm, if RBT2 is built and the concession to operate  
the terminal is given to a third operator.  
[130] However, there is a difference between existing market share and eventual terminal  
capacity. From what I can tell, the HHI statistics do not account for future growth in the  
container traffic market or the fact that GCT will have, with the building of DP4, the additional  
terminal capacity to absorb the expected future increase in total traffic; with total container  
volume expected to increase, the proportion of total containers handled by Centerm, assuming  
full capacity is reached at that terminal, will continue to drop, meaning that that proportion will  
continue to increase for GCT until it reaches full capacity with DP4 having come on stream. That  
may be why the VFPA stated in its December 2017 Briefing Note that a near 80% concentration  
of market share within the Port of Vancouver represents an unhealthy situation for the supply  
Page: 72  
chain marketplace and that no concessions or agreements will be granted for RBT2 that would  
result in an operator having more than 60% of the container handling capacity within the Port of  
Vancouver.  
[131] GCT has not argued that the results of the HHI analysis in the Court record are indicative  
of any bias against DP4, nor does it endorse or adopt any of the calculations or methodology in  
that chart. Rather, GCT simply states that the chart provides a window into what the VFPA was  
thinking at the time and argues only that the results of the analysis do not support the VFPA’s  
assertion that its nearly 80% of market concentration will continue if DP4 is built. I do not read  
the statistics in the way that GCT is proposingthe concern of the VFPA has been how to  
handle future growth and the expected increase in container traffic at the Port of Vancouver.  
Rightly or wrongly, I can certainly understand the concern of the VFPA that with the building of  
DP4 and with no divesting by GCT of Vanterm, more containers are likely to flow to the area of  
available capacity, meaning more and more to a GCT-controlled terminal.  
[132] Moreover, I do not agree as GCT asserts before me that in the March 2019 decision, the  
VFPA improperly limited the scope of the marketplace for the assessment of market  
concentration to only the Port of Vancouver, thus undertaking what GCT argued before me to be  
a “constrained view” of the marketplace; GCT argues that when shippers are selecting where to  
ship to or where to ship from along the West Coast, their geographic range is not limited to the  
Port of Vancouver. I agree; goods destined to or from Canada often have a U.S. West Coast port  
of loading or discharge, with the remaining leg of the transit being either by truck or rail  
carriage. However, that again misses the point. The VFPA is not operating along the entire West  
Page: 73  
Coast; it is concerned with market concentration, and logistics and supply chain management and  
efficiencies, in the Port of Vancouver. I cannot see how diluting the results of a study on market  
concentration by expanding the area of analysis is of any assistance to the Port of Vancouver, but  
then again, as I am not here to assess the merits of the arguments on market concentration, I  
leave that issue to the marketing specialists. Suffice it to say that, putting aside the issue of  
procedural fairness, which I will deal with below, I see Mr. Pang as someone who, in his emails,  
was exhibiting the excitement of having found a new tool to do his job, beyond any particular  
projectdeclaring it to be “a pretty strong tool for us” even before any analysis was undertaken  
as regards DP4and as specifically regards DP4, as a healthy skeptic looking to find the counter  
argument to what GCT is pushing, to wit, the idea that the scope of the marketplace for  
competition assessment is not simply the Port of Vancouver or even the Canadian West Coast,  
but rather the market for container traffic all along the west coast of North America, and that, in  
any event, the building of DP4 will not increase its market share at the Port of Vancouver.  
[133] There is nothing to suggest that the VFPA would not have then shared its findings with  
GCT, thus enhancing the dialogue on market concentration. I do not agree with GCT’s assertion  
that Mr. Pang was seeking a results-oriented tool to undermine DP4 on competition grounds, nor  
am I convinced that the results of the analysis actually contradict the VFPA’s rationale regarding  
its competition concerns. Given that the parties seem to be viewing the starting point of any  
competition analysis from different positions, I see nothing sinister in Mr. Pang’s emails.  
[134] I also do not accept GCT’s assertion that the rationale articulated by the VFPA in the  
March 2019 decision to the effect that DP4 would reduce the number of terminal operators is  
Page: 74  
false. That is not what was stated in the March 2019 decision; that decision simply stated that  
“expanding Deltaport would mean one terminal operator would control a significant majority of  
the market for container terminal services.” Even if, with present volumes, the construction of  
DP4 would not necessarily increase GCT’s present market share in the Port of Vancouver, it  
seems to me that the issue has more to do with controlling capacity so as to absorb future growth.  
[135] To add more fuel to the proverbial fire, GCT further argues that if the VFPA truly had a  
concern, as it claims in the March 2019 decision, with one terminal operator controlling a  
significant majority of the market for terminal services in Vancouver, why then subsequently, in  
March 2020, did the VFPA approve the purchase by DP Worlda global port and terminal  
operator which operates Centerm at the Port of Vancouverof Fraser Surrey Docks from the  
Macquarie Group, thus reducing the number of terminal operators in the port from three (GCT,  
DP World and Macquarie) to two. As GCT rhetorically posed the question, I rhetorically put it to  
GCT that maybe it was because the VFPA expected the coming on stream of RBT2, with a  
different operator, to create enough of a safeguard to competition; or quite simply, maybe it was  
the fact that Fraser Surrey Docks is a multi-purpose terminal. GCT states that there is no  
evidence in the record as to the reason why, yet insists that whatever the reason, the purchase  
renders the VFPA’s concerns with one terminal operator controlling a significant majority of the  
market for terminal services in Vancouver as nothing but a fallacya further indicium of a  
closed mind. The trouble that I have with GCT’s assertions is that what GCT is doing is making  
certain observations and insisting that there is only one way to interpret them. I disagree. There  
could be a myriad of reasons why the VFPA allowed one operator to take over operations at  
another terminal and while those reasons may not be in the tribunal record, I fail so see why they  
Page: 75  
should be; the sale of Fraser Surrey Docks is not the issue in dispute in this case. In the end,  
insinuations are not reality, and asserting them does not make it so.  
[136] Coming back then to the March 2019 decision, GCT states that any concerns of market  
concentration expressed in the December 2017 Briefing Note are beside the point and that the  
issue is what was considered by the port authority at the time of the March 2019 decision when,  
just two months earlier, GCT had agreed to amend its Lease and Berth Corridor Agreement  
[Vanterm Lease amendment] with the VFPA, which purportedly addressed the port authority’s  
market concentration concerns. The trouble that I have with that argument is that, when pressed  
by the Court, GCT also made it clear that it did not concede any right on the part of the VFPA to  
contractually compel GCT to divest itself of its operations at Vanterm under the circumstances  
set out in the Vanterm Lease amendment. In other words, GCT is setting up a proposition, but  
failing to concede the premise upon which it lies. In any event, GCT argues that examining the  
VFPA’s rationale for its competition concerns in 2017, before Mr. Pang embarked on his  
competition analysis and before the Vanterm Lease amendment, is of limited assistance when we  
compare it with the tribunal record, which is supposedly contemporaneous with the March 2019  
decision and which contains no documents to assess the rationale of the VFPA at the time the  
decision to shut the door on DP4 was made. I cannot agree. The argument of GCT may have  
been tenable if the decision maker was a more traditional, adjudicative tribunal. However, here,  
in the context of the running of a port authority, GCT cannot ask the VFPA to limit its decision-  
making to a snapshot in time and to disregard corporate history and the well-documented stated  
ongoing concerns regarding market concentration. Simply because a specific study on the issue  
is not in the tribunal record or was not before the VFPA executives at the time that they  
Page: 76  
expressed their concerns over market concentration in the March 2019 decision does not  
invalidate the concern, which had, by then, been longstanding. We are dealing with business  
people running what the CMA mandates to be a commercially-driven operation, and the DP4  
project had been a work-in-progress for some time; if concerns are not fully addressed, they  
remain concerns going forward and do not stop being concerns just because they are not  
documented every day. GCT has not convinced me that either the HHI analysis or the Vanterm  
Lease amendment, especially with it having refused to concede the purported right of the VFPA  
to compel GCT to divest its interests in Vanterm under appropriate circumstances as part of that  
amendment, should have reasonably caused the VFPA to no longer have the competition  
concerns expressed in the December 2017 Briefing Note when the time came to issue the March  
2019 decision.  
[137] GCT argues that the VFPA, by not assessing its competition concerns on any evidence-  
based objective basis and by not having undertaken any analysis to ascertain whether further  
consolidation of terminal operators at the Port of Vancouver would have a bearing on pricing to  
consumers, or do anything to jeopardize Canada’s competitiveness, which is part and parcel of  
its mandate under the CMA, closed its mind to considering the issue, thus exhibiting another  
indicium of bias. I do not agree. As I indicate further on, the failure to have the issue tested  
within a proper regulatory setting constituted a breach of procedural fairness. It may well be, as  
argued by GCT, that there is insufficient support for the port authority’s long-held competition  
concerns; however, that would go to the reasonableness of the decision; as GCT’s counsel put it  
to Mr. Xotta during his cross-examination, the competition discussion is a question of judgment  
and opinion, and reasonable people can differ on that issue.  
Page: 77  
[138] On the whole, I have not been convinced that the expression by the VFPA of concerns  
over market concentration as part of the rationale for the March 2019 decision was vaguely  
framed and unjustifiable, and even less so an indicium of bias against the DP4 project.  
(ii)  
The tactical way that the March and September 2019 decisions  
were orchestrated  
[139] In addition to the stated rationale of the March and September 2019 decisions, GCT  
asserts that the tactical way that the decisions were orchestrated also leads to a conclusion that  
the VFPA was biased in its decision-making process in relation to DP4; it cites further indicia of  
the VFPA’s closed mind, which I deal with below.  
1.  
The role of the VFPA’s previous law firm in the decision-  
making process and the paucity of the tribunal record  
[140] GCT asserts that the refusal to even consider DP4 on any objective, evidence-based basis  
was directed by the VFPA’s previous law firm, which was legally precluded from advising the  
VFPA on matters related to GCT because of a disqualifying conflict of interest, as subsequently  
found by Justice Pentney in September 2019. It argues that there is no agenda item note and no  
circulated material, in particular, nothing as regards competition concerns or environmental  
imperatives in the tribunal record as reflecting the decision-making process. In fact, GCT argues  
that the March 2019 decision continues to be clouded in mystery with respect to how the  
decision was made, what documents were considered, what input was provided and by whom,  
and what was rejected.  
   
Page: 78  
[141] The record shows that the decision not to consider GCT’s PPE was made at a meeting of  
the VFPA executives on February 13, 2019. GCT asserts that the VFPA, rather than showing its  
cards in order to demonstrate what it says now was a legitimate and authorized regulatory  
decision, instead went to great lengths to avoid appropriate production of the tribunal record. On  
the issue of the lack of documentation in the tribunal record, GCT argues that ultimately, and  
rather than depicting when, how, by whom and why the decisions regarding DP4 were made,  
other than documentation covered by solicitor-client privilege, the tribunal record is completely  
empty of any documentation which would allow for an understanding of the VFPA’s decision-  
making. GCT continues by stating that the solicitor-client privilege in question is either privilege  
belonging to a client in connection with legal counsel who were acting in a legally impermissible  
conflict of interest in March of 2019, or privilege attaching to litigation counsel for the purpose  
of defeating the present application for judicial review, as opposed to a bona fide consideration  
of DP4 on its merits.  
[142] The evidence of Mr. Xotta regarding the lead-up to the March 2019 decision is as  
follows:  
I participated in several discussions with other members of the  
VFPA executive regarding GCT’s PPE, and in particular, VFPA’s  
pending decision whether to accept the PPE and advance VFPA’s  
statutory decision-making process under the [CMA]. VFPA  
executive met on February 13, 2019 and a decision was reached by  
consensus among the executive members. Based on that  
discussion, I issued [the March 2019 decision]. The rationale for  
the decision set out in [the March 2019 decision] reflects the  
reasoning applied by the executive in its discussions.  
[143] GCT states that I should not have to speculate as to what went through the minds of the  
executives during their deliberations culminating in the decision not to move forward with the  
Page: 79  
assessment of GCT’s PPE, and that the hush created by the lack of any evidence of any analysis,  
report or summary of any discussions leading to the March 2019 decision was deafening. In my  
experience, however, it is not.  
[144] In a commercial setting where business people often make decisions by walking into  
other people’s offices and sitting in the chair in front of their desks to discuss a project that has  
been front and centre as part of their daily business lives, the paucity of a written record of the  
precise moment of the decision-making process is not unusual. It is important that we keep in  
mind that the nature of the decision to be made, to wit, whether or not to even process the PPE  
application. Since 2017, there had already been a number discussions, presentations, and  
exchanges between GCT and the VFPA regarding DP4, including the February 2, 2018 letter to  
GCT, whereby the VFPA specifically addressed its concerns and advised GCT how it intended  
to review its application for DP4 under the PER Process when it came time to do so.  
[145] I accept that the VFPA may have failed to live up to its commitment to review the PPE,  
an issue that I deal with when speaking to the issue of GCT’s legitimate expectations; however,  
the point here is that the VFPA executives had convened to decide on how to deal with GCT’s  
application, and whether to consider it through the PER Process. I do not find it unusual that for  
such purpose, we do not find in the tribunal record, as GCT insists we should, documents such  
as: documents scheduling meetings, circulated material, an agenda, expert reports regarding  
market saturation and competition as well as environmental issues, minutes to describe who  
chaired the discussion, who participated in the discussion, who may have spoken in opposition,  
how long the meeting took, who drafted the March and September 2019 decisions, the  
Page: 80  
amendments to any possible drafts of the decisions, or documents as may be required by the  
Guide that demonstrate that subject-matter experts conducted a review and considered the PPE  
on its merits.  
[146] The fact is that the PPE was not considered on its merits and the reason for the meeting of  
the VFPA’s executives was to determine whether to even consider the PPE on its merits and  
allow it to pass through the pipeline of the PER Process. Under the circumstances, I do not find it  
unusual that for the purposes of the discussion and the nature of the decision that was to be  
made, none of the documents that one may expect to find following a complete review of GCT’s  
application under the PER Process were in hand, and that all that may have existed are  
documents exchanged with the VFPA’s lawyers given the sensitivity and importance of the  
decision to both parties.  
[147] It seems to me that what may be causing GCT’s consternation with what it claims is the  
paucity of the tribunal record is its failure to appreciate that the VFPA executives have been  
living the DP4 project, by that point, for around five years. I find that GCT is missing the mark  
by continuously pounding the table on account of the little documentation that was in the actual  
hands of the VFPA executives when they sat to discuss what the port authority was to do with  
GCT’s application for DP4; it would not be unexpected if the executives felt that they did not  
need to review the file because the history of the project and their continued, unresolved  
concerns and assessments of the project were committed to memory. That is not to say that the  
VFPA did not owe a duty of procedural fairness to GCT once it filed its PPE through the PER  
Process portal; in fact the port authority did, and I discuss this issue further below. However, the  
Page: 81  
issue here is that GCT is asking me to find the fact that there were no documents before the  
VFPA executives on February 13, 2019, went beyond rendering the March 2019 decision  
unreasonable, andf was actually an indicium of a closed mind on the part of the VFPA equating  
to impermissible bias. That I will not do as I do not agree with GCT’s underlying premise that in  
a business context, and considering the reason for the meeting and the nature of the decision to  
be made at that stage of the regulatory process that was engaged, I should have expected to find  
such a fulsome tribunal record. Suspicions, speculations or the possibilities of bias is not enough.  
The test for a reasonable apprehension of bias requires a “real likelihood or probability of bias”  
(Yukon Francophone School Board at para 25, citing Arsenault-Cameron v Prince Edward  
Island, [1999] 3 SCR 851).  
[148] In addition, the meeting of February 13, 2019, was not a board meeting, and I have not  
been shown any requirement as part of the VFPA’s internal procedures requiring that when the  
executive team is assembled to make a decision on a very specific issue of which the members  
are aware, a documentary footprint of such a meeting should be kept. The failure to do so may in  
fact render the ultimate decision unreasonable, but escalating such a possible failure to the level  
of being an indicium of bias is untenable in the present case. It seems to me that this issue is a  
tempest in a teapot. Port authorities are commercial operations, with commercial people running  
a commercial establishment, precisely in the way that Parliament intended them to be when  
setting them up under the CMA. I have not been convinced that the criteria for documenting the  
decision-making process in a business environment is the same as in the context of regulatory  
adjudicative boards or tribunals. GCT argues before me that the Court, in judicial review, must  
be able to see the decision-making of the decision maker. Here, the tribunal record contains  
Page: 82  
about 710 documents outlining the history of the RBT2 and DP4 projects leading up to the  
March 2019 and September 2019 decisions. Under the circumstances, the decisions of the VFPA  
were properly reflected in the March and September 2019 decisions.  
[149] Ultimately, I am not convinced that, under the circumstances, the failure to memorialize  
the deliberations that took place during the meeting of February 13, 2019, which resulted in the  
March and February 2019 decisions, or the fact that there were no documents before the  
executive members other than advice from counsel, are in any way a indicia of bias leading to a  
breach of procedural fairness. There is plenty of room in this scenario for the underlying  
considerations for the decision not to proceed with the review of GCT’s PPE to have nothing to  
do with impermissible bias or any underhanded behaviour on the part of the port authority; there  
is not even a reasonable apprehension of bias as far as I can tell.  
[150] Moreover, it would not be unusual for the VFPA to have sought legal advice in relation  
to a decision which was clearly controversial in the eyes of GCT, and a claim of solicitor-client  
privilege in this context would be expected. In any event, GCT’s motion for disclosure of the  
documents on which solicitor-client privilege was invoked was dismissed by Mr. Justice Pentney  
in his Order dated June 17, 2021. Mr. Justice Pentney was not prepared to override the privilege  
associated with communications with counsel, but quite rightly stated that “if VFPA cannot  
defend its decisions as reasonable based on the record it has (and/or will) disclose, the decisions  
will be quashed. If those decisions could be defended based on something over which solicitor-  
client privilege is claimed or which was otherwise not disclosed, then VFPA has only itself to  
blame, in the sense that it could have constructed a decision-making process that would have  
Page: 83  
allowed it to disclose a better record.” I agree with Mr. Justice Pentney, that the issue is one of  
reasonableness of the merits of the decision. However, here, GCT’s argument is that the claim of  
privilege was somehow concocted to purposely avoid disclosure and that such conduct is an  
indicium of impermissible bias leading to a breach of procedural fairness. I disagree with GCT;  
there was a legitimate claim of privilege invoked by VFPA, and claiming malicious intent on the  
part of the VFPA does not make it so.  
[151] Also, as regards the involvement of the VFPA’s previous counsel, the privilege log filed  
by the VFPA shows that on February 6, 2019, the VFPA sent an email to its legal counsel  
regarding GCT’s PPE, as well as indications of a draft response from counsel to both GCT and to  
the Review Panel regarding GCT’s submission, and eventually a legal opinion on the issues.  
GCT argued in essence that there was a breach of the separation between the regulatory and  
proponent side of the VFPA’s previous law firm and that the partner who had been assisting the  
VFPA on the proponent side for advancing RBT2 through the regulatory process was now giving  
advice to the VFPA on the regulatory side on whether the VFPA could legitimately refuse to  
process GCT’s PPE.  
[152] I am not quite sure what to make of GCT’s submission on this issue; it is not suggesting  
that the VFPA should not have retained legal counsel, nor is it actually saying that legal counsel  
advised the VFPA not to have any documents in hand when it made its decision so as to not  
create a tribunal record. Innuendo alone is not convincing, even assuming that I knew of what I  
should have been convinced. I have no reason to doubt that the VFPA’s previous counsel put  
themselves in a conflict of interest, and in the end, on September 6, 2019, Mr. Justice Pentney  
Page: 84  
made them pay the price, thus compelling the VFPA to retain new counsel. The fact that the  
VFPA’s previous counsel put themselves in conflict of interest is unfortunate; however, I do not  
know what more to make of that fact; in the end, they were removed.  
2.  
The current law firm and the tactical attempt to game the  
system  
[153] GCT argues that in the midst of the present proceedings, and immediately after new  
counsel was retained by the VFPA, in an attempt to transform the March 2019 decision somehow  
into an interim or interlocutory decision after the fact and thereby immunize its bias from judicial  
scrutiny, the September 2019 decision was issued. GCT claims that this rescission decision was  
an attempt to “game the system”, drafted by litigators in order to procure the foundation for a  
mootness and prematurity argument, and was thus, and in and of itself, proof of the bias; just like  
the March 2019 decision, the September 2019 decision was not based on any objective or bona  
fide consideration of the merits of DP4, but instead was just a litigation tactic fashioned  
exclusively by legal counsel. In any event, argues GCT, there would still be no assurance that  
GCT “would get a fair shake” if it was to re-engage the PER Process without further safeguards  
as it was invited to do with the September 2019 decision.  
[154] GCT again points to the privilege log that was filed by the VFPA showing, in particular,  
that on September 13, 2019, the VFPA’s current counsel gave preliminary legal advice regarding  
the present judicial review application and that Mr. Stewartwho is supposedly on the  
proponent side for the VFPA as regards RBT2was copied on a message which related to the  
VFPA exercising its regulatory role regarding the DP4 project. On the same day, additional  
preliminary advice was provided regarding GCT’s PPE and the port authority’s previous  
 
Page: 85  
counsel. The matter becomes problematic, argues GCT, when the privilege log shows that on  
September 20, 2019, Mr. Stewart is directly involved with the port authority’s new and current  
counsel in drafting what will eventually become the September 2019 decision. GCT claims that  
it is clear from the privilege log that this is a process directed by the VFPA’s current counsel,  
specifically in relation to the judicial review application, and that Mr. Stewart is at the epicentre  
of it. GCT states that, accordingly, the September 2019 decision is not a freely made, bona fide  
regulatory decision based on evidence or any policy considerations, but rather purely a litigation  
tactic, driven by litigation counsel and the VFPA executive who was primarily responsible for  
RBT2, and has nothing to do with DP4 on its merits.  
[155] Again, I cannot go where GCT is asking me to go on this issue; GCT’s argument is pure  
conjecture. First, there is nothing wrong with the VFPA seeking, retaining and following the  
advice of outside counsel. Second, the whole point of the September 2019 decision is that it was  
a recognition that there were problems with the March 2019 decision, in particular, the VFPA’s  
understanding regarding the effect of the 2003 DFO letters; had there been no issues with the  
first decision, there may never have been a rescission decision.  
[156] GCT further points to the September 2019 decisionin particular where the VFPA states  
that although it continues to believe there to be considerable risks posed to fish habitat by DP4,  
the port authority was no longer of the view that such risks are of such a nature that any  
consideration of DP4 is not an optionas an excuse for not doing what the VFPA should have  
done back in March, and that the bias that existed in March cannot now be rectified. I have not  
been persuaded by GCT. The March 2019 decision raised the prospect of risk to fish habitat from  
Page: 86  
development in the area of the proposed DP4 project, as expressed in the 2003 DFO letters, as a  
concern militating against moving forward with a review of DP4. With the Review Panel  
hearings and, in particular, I must think, the testimony of DFO during those hearings that the  
2003 DFO letters were not meant to be a prohibition against any development of the area in the  
future, I see nothing untoward in the VFPA setting aside the issue of risk to fish habitat as a  
prohibitive factor, pending the assessment process for DP4.  
[157] GCT raises the same argument with the manner in which the VFPA treated the issue of  
maintaining competitiveness within the port in the September 2019 decision; the VFPA made it  
clear that although the question of competitiveness/capacity control remained a serious issue to  
be considered in review of DP4, the VFPA was nonetheless prepared to no longer treat that  
question as a gating issue militating against assessing the project, and was prepared to “further  
consider that issue through the information and analysis that will be undertaken though the  
federal impact assessment of DP4 and our PER process”. GCT argues that the bias is patent in  
the VFPA having done what it did in March with refusing to even process its PPE, and that the  
VFPA was no longer in any position to deal with the review process in an unbiased fashion.  
[158] Again, I have not been persuaded and must reject what I find to be GCT’s bald assertion  
of improper purpose in the VFPA having rescinded the March 2019 decision. The evidence of  
Mr. Xotta on cross-examination is as follow:  
On September 23, 2019, shortly after retaining McMillan LLP, the  
VFPA executive met by telephone to consider the implications of  
the Federal Court ruling [I take it regarding Mr. Justice Pentney’s  
decision to disqualify the VFPA’s previous counsel] and the VFPA  
position set out in [the March 2019 decision]. Following a further  
discussion among VFPA executive members, on behalf of VFPA  
Page: 87  
CEO Robin Silvester issued [the September 2019 decision] to  
GCT, rescinding [the March 2019 decision]. The rationale for the  
decision set out in that letter reflects the reasoning applied by  
VFPA executive in the September 23, 2019 meeting.  
[159] It is clear to me from the September 2019 decision that events subsequent to the March  
2019 decision which could legitimately inform the decision-making process did just that, and  
caused the VFPA to rethink its position regarding the review of DP4. In the September 2019  
decision, the VFPA indicated that it further considered the concerns of GCT as expressed during  
the Review Panel hearings on RBT2 as well as in the judicial review applicationwhich  
included GCT’s claim of impermissible bias. The landscape had changed between the March  
2019 decision and the September 2019 decision: hearings took place before the Review Panel  
under the CEAA and the enactment of the IAA shifted the heavy lifting of environmental  
assessment of “designated projects” from the VFPA to the Agency.  
[160] It was also likely that a change of solicitorsupon which GCT looks with a cloud of  
suspicionbrought forth a fresh perspective on the appropriateness of proceeding with the PER  
Process, which the VFPA had not only set up, but which, in this case, had already been engaged  
before a stop was put on the process by the port authority. In addition, as admitted by the VFPA  
in the September 2019 decision, the filing of the application for judicial review also had a hand  
in the decision to rescind the March 2019 decision. I am simply not persuaded to go as far as  
GCT wishes to take me and find that the September 2019 decision was a tactical decision to  
shield the VFPA from judicial review rather than, just as likely, the result of a series of  
developments having the effect of focusing the minds of business people whose attention is more  
normally focused on commercial port operations. From a simple reading of both the March and  
Page: 88  
September 2019 decisions, it seems to me that the VFPA is not an impetuous or petulant decision  
maker that stubbornly sticks to its decision in the face of changing circumstances which would  
reasonably call for reconsideration of what clearly was an important decision for GCT. I have not  
been persuaded to read the March and September 2019 decisions as evidence of a closed mind  
beyond a simple level of pre-judgment on the part of the VFPA executives, which may be  
expected under the circumstances, and certainly not pre-judgment of the matter to such an extent  
that any representations to the contrary would be futile (Newfoundland Telephone; Old St  
Bonifac at p 1197).  
[161] GCT also asks that I contrast the September 2019 decision with one of the May 2020  
letters sent by the VFPA to various First Nations communitiesin particular the May 25, 2020  
letter sent to the Malahat Nation [Malahat Nation letter], where the VFPA asserts that the option  
to proceed with DP4 “was rejected by the port authority for a number or reasons, including  
environmental concerns with further development at that location, competition concerns and  
anticipated trade needs.” The letter goes on to make clear that the VFPA has no plans to pursue  
DP4, that GCT requires port authority approval to pursue the project, that GCT was not at that  
time engaging the port authority in relation to DP4, and that nothing required the VFPA to  
ensure that GCT was the only container terminal at Roberts Bank. GCT asserts that these  
statements are evidence of the VFPA’s closed mind and that the message being conveyed in the  
letter is that DP4 “is not on” and GCT cannot do anything without the port authority’s approval;  
this is all independent evidence, says GCT, of the VFPA closing its mind to the PER Process.  
Page: 89  
[162] I am not convinced. The letter must be read in context. GCT had engaged in what one  
may describe as a public relations campaign in favour of the DP4 projectas far as I am  
concerned, fair game in the promotion of its commercial interests. The letter sent to the Malahat  
Nation by the VFPA includes the following introductory paragraph:  
Over the last number of weeks we have received several comments  
and questions from Indigenous groups related to information that  
appears to have been provided by [GCT]. We are writing to you  
today to respond to requests for further information about the  
status of the RBT2 project relative to the GCT claims about a  
project it has said it is proposing. In this regard, I am pleased to  
share the following with you.  
[163] Clearly, the Malahat Nation letter, as with the remainder of the May 2020 letters sent by  
the VFPA to other First Nations communities, was meant to address questions which arose on  
account of information disseminated by GCT in support of DP4. I can hardly fault the VFPA in  
looking to clarify the status of the two projects in answer to stakeholder questions, nor do I see in  
the May 25, 2020 letter any sign of a closed mind creating impermissible bias. GCT has not  
argued that any of the statements made by the VFPA in that letter were incorrect. Rather, it  
seems to me that the VFPA had moved on given that GCT had refused to re-engage the PER  
Process. A port authority cannot be expected to suspend its development plans waiting for a  
particular proponent to engage its review process, which GCT refused to do following the  
September 2019 decision. The positions of the parties were clearly set out in the exchanges of  
the previous September and October; those positions had consequences for both parties. Nor can  
the prospect of an application for judicial review create a situation whereby the port authority is  
put in a state of suspended animation; life moves on, and GCT cannot expect the judicial process  
to act as a brake on the continuation of the VFPA’s development plans pending the outcome of  
the judicial proceedings, and where such plans are not halted, claim that the VFPA has somehow  
Page: 90  
closed its mind in a manner that renders it biased. In a way, whenever we move on in life, we are  
somehow closing our mind to what may have been, but that cannot be equated to bias towards  
what could have been.  
[164] On the whole, I am not convinced of any attempt by the VFPA to “game the system”.  
3.  
Deliberate avoidance of transparency by the VFPA in an  
effort to immunize itself from the bias allegation  
[165] GCT argues that it has been forced to embark on a repeated effort to extract a proper  
tribunal record from the VFPA; between what it claims to be glaring omissions from the tribunal  
record, which shows that the VFPA predetermined its rejection of DP4 even before any  
application was submitted, and the scope of the questions that were the subject of improper  
refusals during the cross-examination of the VFPAwhere GCT was trying to elicit  
explanations for such omissions so that they could be understood and reviewed by the Court—  
GCT claims that the VFPA’s approach to the tribunal record compounds its bias and that there is  
clear evidence which demonstrates the VFPA’s effort to immunize itself from the bias allegation.  
Again, some context is required.  
[166] Following the dismissal by Prothonotary Furlanetto of the VFPA’s motion to strike the  
judicial review on the basis of mootness and prematurity, GCT made a Rule 317 request for  
production of the tribunal record on March 12, 2020the initial Rule 317 request included in the  
application for judicial review was struck by the Prothonotary, about a year after the  
institution of the present application for judicial review and five days prior to the issuance of this  
Court’s first Practice Direction and Order (COVID-19). This matter was heavily case managed,  
 
Page: 91  
and following a series of case management conferences dealing with, inter alia, scheduling  
issues, on September 9, 2020, the VFPA produced a tribunal record consisting of about  
478 documents. GCT considered disclosure by the VFPA to be inadequate and brought a motion  
under Rule 318(2) for further disclosure, which was granted by Mr. Justice Pentney on June 17,  
2021 [June 17, 2021 Order]; Mr. Justice Pentney found, inter alia, the VFPA’s disclosure of  
board materials to be incomplete and found as troubling the fact that no material was provided  
for the entire 2019 year given that the decisions being challenged were made during that year. As  
a result, Mr. Justice Pentney ordered the VFPA to disclose certain specifically identified  
documents and to identify a senior official to supervise a review of its document holdings and to  
search for certain other categories of documents for disclosure.  
[167] With cross-examinations on the merits of the present application set to begin in mid-  
August 2021, the VFPA produced another 100 documents at the end of July 2021. The VFPA  
concurrently prepared an affidavit from Mark Gustafson, its General Counsel and Corporate  
Secretary, outlining the manner in which he supervised and instructed the collection of  
documents in response to the June 17, 2021 Order; amongst other things, Mr. Gustafson stated in  
his affidavit that certain requested documents did not exist. GCT’s informal request to cross-  
examine Mr. Gustafson on his affidavit was allowed by Mr. Justice Pentney on August 25, 2021  
[August 25, 2021 Order], in particular on the efforts that had been undertaken to produce  
documents. Mr. Justice Pentney commented on the unusual situation of the parties, to wit, that  
the VFPA is both the decision maker and a full party to the proceeding, and that more  
commonly, the decision maker is not a party to the judicial review proceeding and provides its  
Page: 92  
Rule 317 disclosure as a matter of course, typically based on a clear record that is essentially the  
evidence that was presented before it by the parties.  
[168] A few hours before the cross-examination of Mr. Gustafson was set to begin on  
September 3, 2021, the VFPA announced that additional documents within the scope of the June  
17, 2021 Order were discovered; an additional 100 documents were produced by the VFPA, but  
only later in the afternoon of September 3, 2021, after the cross-examination of Mr. Gustafson.  
Finally, as confirmed by GCT, another 10 documents were disclosed a week later.  
[169] GCT argues that such a chronology is hardly the conduct of a statutory decision maker  
attempting to provide transparency into a bona fide evidence-based decision, and as a result of  
such conduct, the VFPA cannot point to anything in the record, other than the privilege log or  
bald assurances, to refute the bias allegation or to defend the motivations behind the March and  
September 2019 decisions. The paucity of the record also provides the Court with no ability,  
argues GCT, to test the motivations behind such decisions, and results in restricting GCT’s  
ability to test its bias allegation during its cross-examination of the port authority. GCT cites  
Dunsmuir v New Brunswick, 2008 SCC 9, [2008] 1 SCR 190; Slansky v Canada (Attorney  
General), 2013 FCA 199, [2015] 1 FCR 81; and Lukács v Canada (Transportation Agency),  
2016 FCA 103, for the proposition that in order for the Court to fulfill its supervisory function in  
judicial review, it must have access to the records underlying the decision which is being  
reviewed and that an inadequate evidentiary record could immunize the decision maker from  
being reviewed on certain grounds.  
Page: 93  
[170] As regards the cross-examination of Mr. Gustafson, GCT listed a series of undertakings  
that it sought as to certain documents, for example, an agenda of the board meeting or minutes of  
that board meeting, which were not produced because the questions were met with an objection  
by VFPA counsel and an undertaking was taken under advisement; the undertakings were  
eventually refused on the grounds that the questions fell outside the scope of the August 25, 2021  
Order. As a further example of the VFPA refusing production, GCT specifically points to the  
failure on the part of the VFPA to produce the email responses and questions posed by the board  
members (including the collated list of board questions, of which there were as many as 39) in  
advance of the March 21, 2018 board meeting, which purportedly went into the preparation of  
Mr. Wilson’s speaking notes in advance of that board meeting. Again, it seems from the  
undertakings chart that the request was taken under advisement and eventually refused on the  
grounds that the question was outside the scope of the August 25, 2021 Order. As the hearing on  
the merits was soon approaching, dealing with the refusals was left to me.  
[171] GCT argues that its requests for further production which were made during the  
cross-examination of Mr. Gustafson and which were ultimately refused by the VFPA were  
specifically authorized by Mr. Justice Pentney in his August 25, 2021 Order, which states at  
paragraphs 26 to 28:  
[26] As described above, the record’s adequacy is tightly  
connected to GCT’s underlying complaint in this case: VFPN’s  
concurrent roles as both the decision-maker and a party to the  
dispute. It is likely that the record’s adequacy will continue to be a  
live issue between the parties, and the hearing judge may be asked  
to either make a ruling or take this into account in reaching a  
decision on the merits. Either way, the hearing judge will benefit  
from a full understanding of the disclosure made, and  
Mr. Gustafson’s answers to questions about this in cross-  
examination may provide useful and relevant clarification.  
Page: 94  
[27] Permitting cross-examination will add a further step to the  
proceeding, but it will not unduly delay it or add great expense.  
Conversely, the absence of such an Order might result in an  
incomplete record for the hearing judge, thus impeding the Court’s  
ability to determine the matter in a just manner.  
[28] The cross-examination will be limited in scope, and should  
not therefore impose an undue burden on VFPA or its counsel. The  
questions raised by GCT about alleged inconsistencies or gaps in  
the disclosure, as revealed by the affidavit of Mr. Gustafson,  
should be answered so that the hearing judge will have a full  
understanding of the nature of the record.  
[172] At paragraph 31, Mr. Justice Pentney stated:  
[31] Therefore, I will order that GCT is permitted to cross-examine  
Mr. Gustafson, at a time and place to be agreed between the  
parties, only in relation to his evidence about the nature and scope  
of the search undertaken pursuant to my Order of June 17, 2021,  
and the documents that were found but not produced. No questions  
shall be asked of him relating to the merits of either the VFPA  
decisions being challenged or the VFPA decision-making process.  
[Emphasis added.]  
[173] The dispositive portion of the August 25, 2021 Order is consistent with paragraph 31. In  
addition, the June 17, 2021 Order provided the following, at paragraphs 71 and 72:  
[71] In light of this, I find that the disclosure of Board materials is  
incomplete, and it is troubling that there is no material provided for  
the entire 2019 year, given that the decisions being challenged  
were taken during that year.  
[72]At a minimum, VFPA must complete the disclosures it has  
already made, including the Board agenda, minutes, and any other  
materials that mention the DP4 project for the meeting of  
March 21, 2018. VFPA must also disclose the contents of the .zip  
file attached to the e-mail that refers to the Project Board meeting  
on February 25, 2019 (VFPA Production 00028), as well as any  
minutes produced from that meeting which will confirm for the  
reviewing judge whether this is a reference to a meeting of the  
Board, or a Project Board as contended by VFPA. Prior case-law  
Page: 95  
supports that where a disclosed document mentions an attachment,  
that document should also be disclosed (1185740 Ontario Ltd v  
Minister of National Revenue, 169 FTR 266, 1999 8774  
(FCA) at para 6).  
[174] Finally, the dispositive portion of the June 17, 2021 Order provides, inter alia:  
[4] VFPA is ordered to identify a senior official to supervise a  
review of its document holdings, including paper and electronic  
documents (including current holdings and any archives), to search  
for the following categories of documents:  
d. Internal Correspondence Related to DP4:  
i. VFPA shall conduct a search and produce  
any internal documents relating to the  
analysis that VFPA officials undertook of  
GCT’s PPE after it was submitted on  
February 5, 2019, and prior to the March  
2019 decision.  
[Emphasis added.]  
[175] GCT points to an email dated February 12, 2019within the range of dates covered by  
the June 17, 2021 Orderwhich is listed in the privilege log produced by the VFPA and which  
the port authority’s previous counsel sent to various people at the VFPA, including Mr. Bryan  
Nelson, identified as the Director of Infrastructure Sustainability for the VFPA; the email is  
described as, inter alia, draft responses to GCT’s PPE dated February 5, 2019.  
[176] GCT also asserts that previous counsel also copied in Ms. K. Bamford, identified as the  
Director of Trade Development for the VFPA. I do not follow GCT with this argument as the  
Page: 96  
email identified as involving Ms. Bamford was actually sent to her by Mr. Xotta, is dated a day  
earlier (February 11, 2019), and relates only to GCT’s submissions to the Review Panel.  
[177] In any event, the point of the matter is that GCT argues that both Mr. Nelson and  
Ms. Bamford are included in relevant communications which are subject to privilege, but are not  
included in the search criteria for the searches conducted in compliance with the June 17, 2021  
Order. During the cross-examination of Mr. Gustafson, the request by GCT for the VFPA to  
perform relevant searches of the records of Mr. Nelson and Ms. Bamford was refused on the  
grounds that their roles did not include any aspect of permitting approvals or preliminary project  
review and were thus not relevant.  
[178] First, I do not read either the June 17, 2021 Order or the August 25, 2021 Order as  
authorizing undertakings to be requested during the cross-examination. The August 25, 2021  
Order allowed for the cross-examination of Mr. Gustafson “in relation to his evidence about the  
nature and scope of the search undertaken pursuant to my Order of June 17, 2021, and the  
documents that were found but not produced[emphasis added]. In addition, I do not agree that  
the evidence pointed to by GCT supports the argument that the records of Ms. Bamford should  
have been included in the search criteria undertaken in compliance with the June 17, 2021 Order;  
however, I do agree as regards Mr. Nelson.  
[179] The sole document involving Ms. Bamford was sent to her by Mr. Xotta on February 11,  
2019, and is described as being GCT’s submissions to the Review Panel. As she was the Director  
of Trade Development, I can understand why she may have been interested to read what GCT  
Page: 97  
had to say before the Review Panel; however, that is a completely separate issue to the one at  
hand. There is no evidence that Ms. Bamford is part of the VFPA executives who met on  
February 13, 2019, and September 23, 2019, to make the March and September 2019 decisions  
or that she was involved in permitting approvals or preliminary project review or in any analysis  
that the VFPA officials undertook of GCT’s PPE after it was submitted on February 5, 2019, and  
prior to the March 2019 decision.  
[180] However, the situation is different as regards Mr. Nelson; his capture by the search  
engine may well have been a stray hit; however, he was copied on the VFPA’s previous  
counsel’s email, which attached draft responses to GCT’s PPE. I would have to think that  
counsel was instructed to copy him on it. It may well be that he was only copied on it because  
the email of February 12, 2019, also attached a draft response to the Review Panel regarding  
GCT’s submissions of February 8, 2019, an issue in which Mr. Nelson may have been involved.  
Be that as it may, and although it is not clear what role he may have had in any analysis that the  
VFPA officials may have undertaken of GCT’s PPE, to give full effect to the June 17, 2021  
Order, I find that he should have been included in the search. I accept that the search may have  
been restricted to those who the VFPA states were involved in permitting approvals or  
preliminary project review, but the June 17, 2021 Order called for a search of documents relating  
to the analysis that the VFPA officials undertook of GCT’s PPE after it was submitted on  
February 5, 2019, and Mr. Nelson’s capture in the privilege log has not been sufficiently  
explained by the VFPA.  
Page: 98  
[181] GCT argues that the failure to produce the requested documents is more evidence of a  
lack of transparency, which demonstrates a closed mind, and that the examples of Mr. Nelson  
and Ms. Bamford are but two more examples of an attempt to immunize the VFPA from judicial  
review and sanitize the March and September 2019 decisions. I do not agree, nor do I find that  
this was a situation of “hiding the pea” as Mr. Justice Phelan put it at paragraph 16 in Lafond v  
Ledoux, 2008 FC 1369; skirmishes between counsel regarding the scope of document production  
and disclosure orders is not uncommon, and I am not prepared to find that the omission to  
include Mr. Nelson in the search criteria is evidence of bad faith on the part of the VFPA; nor am  
I inclined to accept that the VFPA resorted to an overbroad assertion of solicitor-client  
privilege so as to immunize itself from judicial review. Keep in mind that as a result of the June  
17, 2021 Order, an additional 210 documents were produced. I am sympathetic to GCT’s cry of  
foul and its claim that obtaining document disclosure from the VFPAalthough nonetheless still  
deficientwas like pulling teeth. However, I am also conscious of the fact that we are dealing  
with a non-traditional regulatory decision maker whose tribunal record is not necessarily bundled  
up nicely within party records and, unlike traditional adjudicative regulatory decision makers,  
must resort to e-discovery tools to comply with production requirements; this is not, as alluded to  
by Mr. Justice Pentney, a more commonly found situation where the decision maker is not a  
party to the judicial review proceeding and provides its Rule 317 disclosure as a matter of  
course, typically based on a clear record that is essentially the evidence that was presented before  
it by the parties.  
[182] More to the point, and putting aside the issue of why undertakings would be taken on  
cross-examination, I fail to see why email responses and questions posed by board members, or  
Page: 99  
any of the documents listed by GCT in its Supplemental Memorandum of Fact and Law, would  
necessarily have formed part of the tribunal record. These proceedings are not in the nature of an  
action, and the cross-examination of Mr. Gustafson as ordered by Mr. Justice Pentney was not a  
discovery. Before adjudicative decision makers, the parties appear and submit their material,  
which together, and aside from certain exceptions, form the tribunal record. Here, the CMA has  
created what Mr. Justice Pentney referred to as an “unusual situation” whereby the VFPA is both  
the decision maker and a full party to the proceeding, an entity with a commercial mandate, and  
it is that situation which must guide us on what we should or should not expect to be found in the  
tribunal record. If I am to accept the assertions of GCT, I should expect to see every email to and  
from the VFPA addressing DP4, or at least relating to the VFPA concerns regarding DP4 which  
formed the rationale behind the March and September 2019 decisions, as far back as 2014, when  
GCT first began putting the DP4 project together. That is untenable as it completely disregards  
the nature of the decision maker.  
[183] As I stated earlier, in a commercial setting where large-scale projects have been front of  
mind for several years, decisions are regularly made based upon the appreciation, perspective,  
understanding and recollection of the business people called upon to make decisions on a day-to-  
day basis, without having to constantly gather up what may be thousands of previous emails,  
reports, submissions, presentations, notes and letters so that any decision can be made. That is  
not to say that had the PER Process continued, a fulsome record of any final decision would not  
have to be kepta record which I would think would include the application and submissions of  
GCT and all reports, analyses, and exchanges supporting that final decision as called for in the  
PER Process, as well as a justified, transparent and intelligible final decision. However, again,  
Page: 100  
the context of the March and September 2019 decisions was to determine whether to even allow  
the PPE through the PER Process. In that context, I have not been convinced that I should expect  
to find what GCT is stating that I should find as part of the documents that were before the  
VFPA executives when they rendered the March and September 2019 decisions, and I have been  
even less convinced that the failure to find such documents evidences a closed mind leading to  
impermissible bias against DP4 by the VFPA.  
4.  
Efforts to undermine DP4 to third-party stakeholders  
[184] GCT argues that the tribunal record, rather than demonstrating any foundation behind the  
decisions, depicts repeated efforts by the VFPA to undermine DP4 to third parties, further  
evidence of its closed mind. It is one thing, argues GCT, for a regulator to claim that it has a  
policy-based preference for one expansion project over another, but it is quite different for a  
regulator to perpetuate a campaign to actively undermine DP4 to other stakeholders, an activity  
that is found nowhere in the VFPA’s statutory mandate, and demonstrates its bias.  
[185] GCT points to the VFPA’s letter of April 27, 2018, to the then Minister of Transport and  
to the letter of May 5, 2018, to the then Minister of International Trade, sent just a few months  
following the Hemmera Report, which expressed the view that development in the area of the  
proposed DP4 project is “a highly sensitive location that the Minister of Fisheries stated  
unequivocally in 2003 would not be permitted.” GCT states that such a mischaracterization of  
the 2003 DFO letters was intentional given that the Hemmera Report was already in hand and  
that DP3 was in fact permitted to be built in that area in 2010.  
 
Page: 101  
[186] GCT also points to the March 29, 2019, email by the VFPA to the Prime Minister’s  
office, which was sent over four weeks after the March 2019 decision and the day after the  
present application for judicial review was filed and served, where the same mischaracterization  
took place; as stated earlier, the briefing note attached to the email stated that the VFPA had  
evaluated the same area as the one being proposed for DP4 as one of several option for RBT2,  
but rejected it because DFO advised that no Fisheries Act permits would be issued for that area  
given the sensitive intertidal waters, and thus the decision on where to build RBT2 was guided in  
large part by direction from DFO in 2003 that only expansion options beyond the existing  
Deltaport terminal in deeper water should be considered and that permits for options in highly  
sensitive habitat closer to the shore would not be granted.  
[187] GCT also highlights the meeting between the VFPA and the Prime Minister’s office on  
April 10, 2019. The next day, the VFPA sent over the briefing note, updated to April 3, 2019, as  
well as the PowerPoint presentation given during the meeting the day before, and the RBT2  
Project Rationale document, with the same mischaracterization of the purported environmental  
non-starter as expressed by the VFPA in previous correspondence.  
[188] GCT also cries foul because come the September 2019 decision, where the VFPA  
purports to reopen the PER Process for the PPE, it does not go and correct the record with the  
Prime Minister’s office or with any of the Ministers, who are left with the false impression  
created earlier regarding the purported environmental concerns with DP4.  
Page: 102  
[189] The assertions made by GCT of the mischaracterization by the VFPA of the 2003 DFO  
letters, given the Hemmera Report and the development of DP3, must be placed into context. In  
2003, the project that was being discussed with DFO was a larger terminal expansion at  
Deltaport, larger than what would eventually be built as DP3. In its letter of April 1, 2003, DFO  
stated at the time that it “will not be involved in any review of the Delta Port proposal as the only  
option proposed for that project results in the destruction of critical fish habitat on the east side  
of the causeway.” In its July 29, 2003 letter, the Minister of Fisheries and Oceans stated that  
“DFO will not consider issuing a Fisheries Act Section 35(2) authorization for the destruction of  
this critical fish habitat.” The letter went on to indicate that DFO had suggested that the VFPA  
“focus its efforts on options that have a lesser likelihood of damaging critical fish habitat … in  
deeper water, where construction would likely have less impact on the Estuary’s fish habitat …”.  
[190] DFO did eventually sign off on the construction of DP3, but only after the footprint of the  
project was reduced by about 30% on the norththe intertidal water areato accommodate  
DFO’s expressed concerns. The DP4 project, on the other had, as I read the “description project  
layoutschematics provided by GCT, is looking to develop not only the 30% which was not  
acceptable to DFO in 2003, but proposes to continue north, into the intertidal water area on the  
landward side of the causeway. To claim, as GCT does, that the building of DP3 is proof positive  
that the VFPA mischaracterized the 2003 DFO letters is unfair. If one considers the area of the  
proposed DP4 project, it is very much in the area that DFO considered to be a “critical fish  
habitat.”  
Page: 103  
[191] As regards the Hemmera Report, I do not agree with GCT’s assertion that there has not  
been any controversy, since 2017, over the fact that the report laid to rest the notion of any  
prohibition. It is true that the Hemmera Report was issued several months earlier and was in the  
hands of the VFPA at the time that it sent the briefing notes to the Minister of Transport and  
Minister of International Trade; however, as stated already, the report does not come to the  
conclusion that the 2003 DFO letters did not constitute a “prohibition” on development in the  
area proposed for DP4to the north and into shallower waters from the present DP3but rather  
simply provides guidance and suggestions on how to possibly mitigate the environmental risks  
expressed by DFO at the time for projects being built today.  
[192] As regards the legitimacy of the claim that the 2003 DFO letters constituted a  
“prohibition” against development in the area proposed for DP4, GCT says that the issue is  
conceded and that the record contains three separate confirmations of there being no prohibition  
against development of the area proposed for DP4. GCT first points to the testimony of  
Mr. Magnan, the DFO representative, during the RBT2 Review Panel hearing on May 22, 2019,  
regarding the 2003 DFO letters, as follows:  
MEMBER LEVY  
Okay. Given that the world has changed a lot since 2003, we have  
a new habitat policy, we have a new Fisheries Act that’s in front of  
the Senate right now, is it still DFO’s position that development in  
the intercauseway would be unacceptable?  
MR. MAGNAN  
And again, I just want to reference that the letter indicated that  
particular project based on a footprint and a time and a review, the  
legislation then, that development would not have been approved  
or issued an authorization. The letter was not meant to indicate that  
there was any kind of blanket statement in terms of any  
development in that area. It was very specific to that project.  
Page: 104  
So - - and again, each project is weighed and based on the  
application received, the current legislation and the current  
policies. So in the future, should a project come in, DFO will  
review the application and make a decision based on the  
information that’s presented to us.  
[193] GCT then points to the affidavit, dated August 12, 2020, of Mr. Dave Carter, who is with  
DFO and is one of the affiants for the Attorney General in these proceedings, who states the  
following at paragraph 12 of his affidavit:  
The [July 29, 2003 letter from the Minister of Fisheries and Oceans  
to the VFPA] was based on the specific project applications at the  
time. In the future, should a proponent apply to DFO for an  
authorization for its proposed project, DFO would review the  
application and make a decision based on the information that is  
presented.  
[194] Finally, GCT points to the cross-examination, on August 20, 2021, of Mr. Carter in these  
proceedings, as follows:  
Q. Mr. Carter, can you please confirm that if and when an  
application is provided for DP4 by GCT, DFO will review that  
application and make a decision based on the information  
requested - - or provided?  
A. Yes, it will.  
Q. And I take it from your evidence in paragraph 12 that that  
decision will include an objective review of the application  
material?  
A. It will definitely include a review of the application material.  
Q. And that review will be impartial?  
A. Yes.  
Q. And objective?  
A. Yes.  
Page: 105  
Q. Mr. Carter, can I just take you to paragraph 5 of your affidavit.  
It’s on page 2.  
A. Yes.  
Q. You’ll see there in the second sentence you describe the two  
2003 letters we were speaking of earlier and saying “the VFPA  
sought DFO’s advice to identify the options that presented the least  
risk to obtaining regulatory approval.” Do you see that?  
A. Yes, I do.  
Q. And I take it from you evidence that neither of the two letters  
prevented subsequent applications to be made to the DFO in  
respect of projects in that area?  
A. That’s correct. There was no blanket ---yeah.  
Q. No blanket prohibition?  
Yeah.  
Q. And by that I mean no blanket prohibition on further  
applications or further developments in the intercauseway area.  
A. That’s correct.  
[195] GCT says that DFO has confirmed three times what the VFPA knew since November  
2017, when it received the Hemmera Report, that is, that the suggestion of a prohibition on the  
development of DP4 is nonsense, but the VFPA was still promoting, through carefully worded  
language, the fiction of a prohibition well after the present application for judicial review was  
filed and served.  
[196] I do not agree with GCT. No doubt that following the testimony of DFO during the  
Review Panel hearings in May and June 2019, the 2003 DFO letters were not to be taken as a  
blanket prohibition regarding development of the area proposed for DP4. But again, that misses  
Page: 106  
the point. Hindsight is 20/20, and in fact, in the September 2019 decision, the VFPA clearly  
referenced the DFO testimony during the Review Panel hearings as one of the reasons why it  
was rescinding the March 2019 decision. The question, rather, is whether, at the time the March  
2019 decision was made (prior to the Review Panel hearings, and before the affidavit of  
Mr. Carter and his cross-examination), the claim of the existence of such a prohibition by the  
VFPA was evidence of bad faith, a closed mind beyond simple permissible pre-judgment, so as  
to constitute impermissible bias. Given the lack of clarity on this issue in the Hemmera Report, I  
am not prepared to say that it was. Again, as stated by Mr. Xotta during his cross-examination, at  
the time of the March 2019 decision, the VFPA executives, rightly or wrongly, understood such  
a prohibition to exist in the area north of what is presently DP3, and in the area of the proposed  
DP4 project.  
[197] GCT then points to the Malahat Nation letter dated May 25, 2020, as further evidence of  
a closed mind regarding DP4. The Malahat Nation letter states, amongst other things:  
The port authority is, under the [CMA], fully responsible for  
decisions related to developments on port lands. After many years  
of consideration, we decided to pursue the RBT2 project to meet  
growing container terminal needs in the future … .  
In making this decision, the port authority considered numerous  
options including further development on the east side of the  
causeway adjacent to GCT’s existing Deltaport terminal. This  
would generally correspond with what GCT refers to as the  
potential “DP4” project.  
That option was rejected by the port authority for a number of  
reasons, including environmental concerns with further  
development at that location, competition concerns and anticipated  
trade needs. The independent federal review panel expressly  
considered this issue and held a day of hearings specifically  
dedicated to alternatives. GCT participated extensively. The panel  
has now spoken and it has supported the port authority’s  
Page: 107  
conclusion to locate the terminal in deeper waters, stating at  
page 57 of its report:  
The Panel concludes that the Proponent’s assessment of  
alternative means of carrying out the Project was appropriate.  
To be clear:  
The port authority has no plans to pursue development  
adjacent to the existing GCT facility;  
GCT does not have the ability to pursue an expansion  
without the port authority’s approval (and in this regard it is  
noteworthy that the prior expansion of Deltaport Third  
Berth was initiated by the port authority not GCT);  
GCT is not engaging with the port authority in relation to  
any expansion of its facility; and  
Nothing requires the port authority to ensure GCT  
continues to be the only container terminal operator at  
Roberts Bank.  
[198] GCT argues that the VFPA, despite purportedly having an “open mind” and rescinding its  
March 2019 decision with the September 2019 decision, then asserted in the Malahat Nation  
letter that the DP4 project had been rejected by the VFPA for reasons which included  
environmental and competition concerns.  
[199] I do not think that GCT is giving the Malahat Nation letter a fair reading. As stated  
earlier, the letter must be read in the context of addressing questions which arose on account of  
information disseminated to the First Nations communities by GCT in support of DP4. The  
VFPA set out its role under the CMA and stated that after many years of consideration, it  
decided to pursue RBT2 to meet the future needs of the port. The VFPA stated that in coming to  
that conclusion, the port authority considered several options, including the DP4 project.  
Page: 108  
However, DP4 “was rejected by the port authority for a number of reasons, including  
environmental concerns with further development at that location, competition concerns and  
anticipated trade needs.” As at the March 2019 decision, that statement by the VFPA was  
correct. The VFPA also stated in the Malahat Nation letter that it “has no plans to pursue  
development adjacent to the existing GCT facility.” That statement was also correct, particularly  
given that GCT has not re-engaged the PER Process following the September 2019 decision.  
[200] What is central to understanding what the VFPA is saying is to recall that in the  
March 2019 decision, the VFPA made it clear that it would only consider DP4 as “subsequent  
and incremental to the RBT2 project.” I disagree with GCT that the letter to the Malahat Nation  
is a declaration by the VFPA that DP4 is “dead”. The evidence shows that the VFPA was  
concerned with the fact that it would take several years more for DP4 to achieve environmental  
assessment approval, if at all, than it would for RBT2, especially as it was looking to develop an  
area already flagged as problematic. The VFPA was also concerned with the fact that DP4 would  
be coming on stream when it was not clear just how much additional capacity would be needed  
beyond RBT2 and that its development timeline would conflict with that of RBT2. The  
September 2019 decision did not change that aspect of how the VFPA was inviting GCT to re-  
engage with the PER Process. That is also consistent with how the VFPA mentioned to GCT in  
its letter of February 2, 2018, that it would approach GCT’s application for DP4 if and when  
made. In that letter, the VFPA stated: “… it would be entirely appropriate and indeed incumbent  
upon VFPA to also consider the impacts of a DP4 project on the overall port operations. VFPA  
would also consider the issue of timing, recognizing the very significant lead times required for  
such projects, and the looming need for more near term capacity in the Port of Vancouver.”  
Page: 109  
[201] The concern regarding the delayed timing of DP4 was also expressed in the March 2019  
decision when the VFPA stated: “We note that your proposed development timeline would  
conflict with the implementation of RBT2 capacity.” In fact, the VFPA executive speaking notes  
for the March 21, 2018, board meeting include the subject of any alternatives to the RBT2  
project that were considered. Particularly regarding DP4, the speaking notes of Cliff Stewart  
provide:  
Further expansion at Deltaport, or DP4 as it is known, is not a  
viable solution for the following reasons:  
Past direction from [DFO], including a letter from  
the federal fisheries minister, that any further  
expansion on the east side of the intercauseway  
would not be given a permit due to environmental  
concerns. The proposed intertidal location would  
also destroy existing habitat compensation efforts  
from past expansion initiatives.  
Given its proximity to sensitive environmental  
areas, GCT’s proposal would likely be assessed as a  
designated project, which requires a lengthy federal  
review. As GCT has not commenced an  
environmental assessment of the project, it can be  
assumed that they are potentially up to 10 years  
behind RBT2 for delivery, even if their project was  
found to be approvable.  
[Emphasis added.]  
[202] I do not agree with GCT when it asserts that the Malahat Nation letter was a clear  
expression of opposition to DP4 after the VFPA claimed to no longer have a closed mind by  
rescinding the March 2019 decision. If there was a “closing of the mind” on the part of the  
VFPA, it was, as made clear in the March 2019 decision, only with respect to developing DP4  
“at this time”. That does not, in my view, suggest impermissible bias in this context, especially  
Page: 110  
given the concerns surrounding DP4; rather, that is a question of prioritizing conflicting projects,  
which was certainly within the bailiwick of the VFPA as constituted under the CMA. I accept  
that there may be an issue of whether the “prioritizing” function of the VFPA falls under its  
proponent role for RBT2 or its regulatory role as regards DP4, and I will deal with that below;  
however, for now, I do not consider this to be an attempt by the VFPA to undermine the DP4  
project.  
[203] As to the statement of the VFPA that “GCT is not engaging with the port authority in  
relation to any expansion of its facility”, as stated earlier, the port authority cannot be expected to  
suspend its development plans waiting for a particular proponent to engage its review process.  
[204] GCT also points to the Issues Management Plan developed just before the service and  
filing of the present application for judicial review, which, in addition to the financial  
compensation of the VFPA executives which I will deal with later on, reveals, according to GCT,  
the motivation behind the VFPA’s bias. GCT points to the statement made in the Issues  
Management Plan, under Analysis and Assumptions: “Given that the proposed DP4 cannot be  
built, according to the minister of fisheries in 2003, it is curious why GCT is proposing it.”  
[205] GCT says that that statement is not true. From what I can tell, it may have been shown  
not to necessarily be correct through the testimony of DFO during the Review Panel hearings  
held a few months later, but what seems to be the case is that at the time the statement was  
inserted in the document, the evidence is that the VFPA actually believed it to be true. The  
statement was included in the Analysis and Assumptions section of the Issues Management  
Page: 111  
Planin other words, the VFPA was speaking to itself and setting down what it believed to be  
the state of affairs. This statement does not appear to me to be a series of talking points prepared  
by a communications director to assist the VFPA in conveying its position to the public.  
Accordingly, from my perspective, that statement confirms the statement of Mr. Xotta during his  
cross-examination, to wit, that the VFPA truly believed the prohibitive effect of the 2003 DFO  
letters.  
[206] In addition, the Background section to the Issues Management Plan includes the  
following:  
GCT has begun a public campaign that includes, at least, the  
following:  
Video of the proposed project showing the  
expanded footprint (though the video description  
states additional capacity can be handled on the  
existing footprint)  
Robocalls to the Delta community, positioning DP4  
as a “better way”  
Extensive government and stakeholder lobbying  
Public engagement, such as organization of  
community and business roundtables  
We can expect that GCT will continue to reach out to key  
stakeholders, such as those who have registered to speak in support  
of RBT2 at the upcoming public hearing.  
[207] GCT argues that the Issues Management Plan equates to the VFPA setting out what it is  
going to do to undermine DP4, and a further indication of a closed mind amounting to  
impermissible bias on the part of the VFPA. I disagree. The evidence has me believe that, given  
the preference of the VFPA for RBT2, GCT had undertaken its own campaign to sell DP4 to the  
Page: 112  
public and the government. I would not expect anything less, and as mentioned earlier, that is  
fair game for any commercial operator which needs public and government support to move  
foreword with its development strategy; I see nothing wrong with such an approach. The VFPA  
says that this is not about RBT2 vs DP4; GCT says the opposite, that the present proceedings are  
all about RBT2 vs DP4. Whatever the true state of affairs may be, it does explain why the VFPA  
felt the need to have a concerted approach so as to respond to what may have become a battle for  
public opinion on further development of Deltaport. On the whole, and more to the point, I am  
not convinced that the VFPA undertook either an open or a clandestine campaign to undermine  
DP4. I have not been shown by GCT any statement in the Issues Management Plan that is  
incorrect, apart from opinions which later may have been found to not necessarily be correct;  
seeking to set the record straight is not evidence of insidious conduct.  
[208] GCT also asks that I compare and contrast the statement made in the Issues Management  
Plan to the effect that the Review Panel is not mandated to consider project need or alternatives  
and therefore cannot make a recommendation that favours one project over another, on the one  
hand, with the statement made by the VFPA to the Malahat Nation in its letter of May 25, 2020  
to the effect that “[t]he independent federal review panel expressly considered [the decision of  
the VFPA to reject DP4 for reasons of environmental and competition concerns] and held a day  
of hearings specifically dedicated to alternatives. … The panel has now spoken and it has  
supported the port authority’s conclusion to locate the terminal in deeper waters …”.  
[209] I accept that the manner in which the VFPA expressed the role of the Review Panel as  
endorsing the rejection of DP4 was imprecise; however, I am not convinced that it was  
Page: 113  
determinative of any closing of the mind leading to impermissible bias on the part of the port  
authority.  
[210] The GCT also wants me to compare and contrast the Issues Management Plan with how  
the board directed the VFPA during the board meeting of March 31, 2015 to review the DP4  
project with objectivity and with an open mind. I have not been convinced that since 2015, the  
VFPA has dealt otherwise with GCT and the DP4 project. Given that the VFPA had to respond  
to a concerted campaign by GCT to sell DP4 to the public and the government, I see no  
contradiction between the directive of the board in 2015 and the development of the Issues  
Management Plan. On the whole, I find that GCT’s argument that the VFPA was somehow  
strategically undermining DP4, and more so, that the VFPA was purposely mischaracterizing the  
consequences of the 2003 DFO letters, is not supported by the evidence.  
[211] Finally, GCT argues that a reasonable apprehension of bias arises from apparent  
predeterminations, even on a less stringent test of the appearance of a closed mind. In particular,  
GCT asserts that the reasons given in the March 2019 decision demonstrate that the VFPA made  
a predetermined decision in favour of the RBT2 project and that its comments, made publicly,  
suggest a pre-judgment or impartiality on its part (Chrétien v Gomery, 2008 FC 802 at paras 78  
to 80 and 106, aff’d 2010 FCA 283 [Gomery] and Canadian Broadcasting Corp v Canada  
(Human Rights Commission), 1993 16517 (FC) at para 43 [CBC]). Putting aside the fact  
that the situations in both Gomery and CBC were significantly different from the matter before  
me, under the circumstances, I am not prepared to find that the VFPA undertook a campaign to  
undermine DP4 or that its statements as regards the effect of the 2003 DFO letters were made in  
Page: 114  
bad faith, knowing them to be wrong. I am also not convinced that such public statements show a  
closed mind leading to actual impermissible bias. As stated by Mr. Xotta during his cross-  
examination, at the time the statements regarding the concerns over the 2003 DFO letters were  
made, the VFPA thought them to be correct; I have not been convinced otherwise.  
(iii)  
The declaration of preference for RBT2 without a proper evidence-  
based assessment  
[212] Finally, GCT argues that in addition to issues with the stated rationale of the March and  
September 2019 decisions and the tactical way that those decisions were orchestrated, the fact  
that the VFPA stated that RBT2 was its preferred project without first conducting a formal,  
evidence-based review of DP4 can only lead to a conclusion that the VFPA was biased in its  
decision-making process in relation to DP4. GCT asks that I keep in mind that such dogged  
preference for RBT2 emanates from the fact that there are people at the VFPA whose careers,  
salaries, and legacy are predicated upon RBT2 being completed; they have been working on the  
project since 2013 and thus have developed, says GCT, a mindset tantamount to bureaucratic  
inertia in their dedication to that project.  
[213] I should point out that GCT is not arguing that the VFPA’s regulatory role is to act as an  
independent arbiter, weighing RBT2 against DP4, or that in conducting its regulatory functions,  
the VFPA cannot have regard to the history of the projects, the port development priorities,  
decisions and commitments already made by the VFPA, past discussions and exchanges between  
the parties, the existing knowledge of both projects by the parties, or the stage of development of  
RBT2, in which the VFPA had already invested time and energy as part of its statutory mandate  
as commercial operator of the port. Rather, GCT argues that the port authority, before  
 
Page: 115  
determining that RBT2 was in fact its preferred projecta decision that the port authority may  
have made as part of its proponent role for RBT2nonetheless had the obligation on its  
regulatory side to allow DP4 to be reviewed under a fair, independent, objective, evidence-based  
decision-making process, and failing to do so under the circumstances is evidence of  
impermissible bias. Although at some point articulating that the issues of these proceedings are  
very much centered around RBT2 vs DP4, GCT also says that for the purposes of determining  
the VFPA’s bias here, it is not a question of weighing one project against another, but rather an  
issue of one project not even being allowed on the scale.  
[214] In any event, Mr. Grosman admitted in cross-examination to knowing that RBT2 was the  
VFPA’s preferred project from the time he joined GCT in July 2017; the VFPA’s preference for  
RBT2 was no secret well before GCT filed its PPE in February 2019; however, GCT argues that  
it was not aware that such a preference amounted to a “shutting of the door” to the review of  
DP4 without at least the prerequisite fair, independent, objective, evidence-based decision-  
making process being undertaken so as to justify the preference, and asserts that proceeding in  
the way it did was evidence of the VFPA’s bias against DP4, which only manifested itself with  
the March 2019 decision.  
[215] Again, I cannot agree with GCT. The March 2019 decision sets out in very clear  
language the reason why the VFPA decided not to process GCT’s PPE through its PER Process.  
[216] As I indicated earlier, the proposition that the VFPA closed its mind, an argument which  
GCT has promoted throughout these proceedings as an indicium of impermissible bias, seems to  
Page: 116  
me to rather be the natural consequence of the port authority making, rightly or wrongly,  
commercial decisions, and simply wanting to move on. For the VFPA, moving forward with  
RBT2 began in 2013if we do not consider the work undertaken prior to the completion of  
DP3and was several years ahead on a development timeline than the DP4 project. It is not for  
the port authority to delay making long term policy decisions on the development of port  
infrastructure until a proponent is ready to submit its proposal, which in this case took place in  
February 2019. Putting aside the issue of any breach of procedural fairness by the VFPA in not  
allowing at least an initial assessment of GCT’s PPE once submitted on February 5, 2019, I have  
not been convinced of any closing of the mind in the sense of creating impermissible bias on the  
part of the VFPA in having determined and expressed, prior to assessing the PPE through the  
PER Process, its preference for RBT2.  
(b)  
Failure to respect policy of separation of proponent and regulatory  
functions  
[217] GCT asserts that quite apart from whether the March and September 2019 decisions were  
reflective of actual bias on the part of the VFPA, that the bias of the VFPA may be seen in the  
manner in which it disregarded the admitted requirement on its part to keep its project proponent  
role separate from it regulatory role.  
[218] GCT argues that the VFPA recognizes the conflict of interest inherent in its dual roles as  
proponent and regulator and assures stakeholders that it takes steps to have a clear separation of  
the two functions to address this inherent conflict by making certain that those who work on the  
proponent side for RBT2 do not cross-contaminate, through their involvement, the regulatory  
role of the VFPA in respect of DP4.  
 
Page: 117  
[219] In the midst of the submission of GCT’s PPE for DP4, the VFPA was also stick-handling  
RBT2 through the regulatory process under the CEAA. In a letter dated February 22, 2019, to the  
Review PanelGCT points out that this letter was sent after the February 13, 2019, decision by  
the VFPA executives not to process its PPE through the PER Processmeant to address the  
ability of the VFPA to oversee and to direct compliance and how conditions would be enforced  
in the event that RBT2 was approved to proceed, the port authority also addressed its dual role as  
both proponent and regulator under the CMA. In the letter, Mr. Stewart, who is part of the  
proponent side for RBT2, stated:  
Port authorities are tasked with addressing the technical merits of a  
project, including environmental impacts and mitigation. …  
A Canada Port Authority’s role is to review project applications,  
including required studies, assess the technical merits of the  
application, and then make an evidenced-based permit decision. …  
The [VFPA] will not authorize or allow a proposed project to  
proceed if it is likely to result in significant adverse environmental  
effects that cannot be mitigated. Project permit applications may  
not be accepted if the port authority determines the project is not in  
the best interests of Canada’s overall trade objectives.  
Occasionally, like other federal agencies, a Canada Port Authority  
is required to act as both permitting agency and project proponent,  
typically on common-use infrastructure projects where no other  
proponent would be forthcoming. To ensure the permit review  
process is entirely objective, the [VFPA] ensures clear separation  
of the regulatory and project proponent functions of the  
organization. For example, projects reviewed by the [VFPA] are  
conducted by environmental scientists and specialists who do not  
work on port authority-led projects.  
[Emphasis added.]  
[220] GCT asserts that although admitting that this separation is a minimum requirement, the  
evidence actually demonstrates that, in breach of its own standard of natural justice and  
Page: 118  
procedural fairness, no such protections were implemented regarding DP4. GCT points to the  
privilege logs that show that Mr. Stewartwho, in cross-examination, Mr. Xotta described as  
the executive responsible for advancing RBT2 as well as other capital projects that VFPA was  
developingwas involved in both the March and September 2019 decisions and that  
Mr. Armstrong was, as GCT suggests, at the epicentre of the March 2019 decision despite his  
role as counsel for the proponent side of RBT2. Mr. Xotta also confirmed that the separation of  
functions described by Mr. Stewart was not reduced to a written policy of the VFPA and that no  
document exists setting out how that separation is to take place, but that the procedures  
associated with the project review were articulated in the Guide. GCT calls this a governance  
failure exemplifying once again the closed mindedness of the port authority in relation to the  
DP4 project; the element of bias is demonstrated, argues GCT, because after accepting that such  
a “church and state” separation is needed in order for stakeholders to be afforded proper  
procedural fairness, the VFPA secretly did the opposite, a fact discovered only after GCT  
undertook serial efforts to extract the true record.  
[221] I disagree with GCT. First, although GCT promotes the theory that both projects were  
competing with each other, it seems to me that it was so only in GCT’s mind. More importantly,  
I find that GCT is misapplying the principles addressed in Mr. Stewart’s letter to the Review  
Panel. Again, context is important. The Review Panel was set up to review RBT2, and in the  
February 22, 2019 letter, Mr. Stewart was addressing how the VFPA was to be set up in order to  
review RBT2, a project where the VFPA itself was acting as a proponent. It may well be that  
such a “church and state” separation would have been put in place had the VFPA moved forward  
as the proponent of DP4, just as it was the proponent of DP3 and other large-scale projects of  
Page: 119  
land reclamation in the Port of Vancouver, but the VFPA decided, in its discretion, that it did not  
wish to move forward with DP4, preferring the RBT2 project to meet the growth in demand for  
container terminal capacity, and I see nothing to suggest that it did so by breaching its own  
expressed commitment to the separation of proponent and regulatory functions.  
(c)  
Are the VFPA decision makers biased as a result of any financial interest  
in the development of the RBT2 project?  
[222] As made clear by the Supreme Court in Old St Boniface, in addition to having a closed  
mind to the point of intransigence, a disqualifying bias may also result from a conflict of interest  
on account of financial interest in the decision to be made. At page 1196, Justice Sopinka stated:  
I would distinguish between a case of partiality by reason of pre-  
judgment on the one hand and by reason of personal interest on the  
other. It is apparent from the facts of this case, for example, that  
some degree of pre-judgment is inherent in the role of a  
councillor. That is not the case in respect of interest. There is  
nothing inherent in the hybrid functions, political, legislative or  
otherwise, of municipal councillors that would make it mandatory  
or desirable to excuse them from the requirement that they refrain  
from dealing with matters in respect of which they have a personal  
or other interest. It is not part of the job description that municipal  
councillors be personally interested in matters that come before  
them beyond the interest that they have in common with the other  
citizens in the municipality. Where such an interest is found, both  
at common law and by statute, a member of Council is disqualified  
if the interest is so related to the exercise of public duty that a  
reasonably well-informed person would conclude that the interest  
might influence the exercise of that duty. This is commonly  
referred to as a conflict of interest.  
[Emphasis added.]  
[223] GCT argues that the VFPA executives who made the decisions in respect of DP4, both on  
the regulatory and the proponent side, were and are compensated based on the success of RBT2,  
 
Page: 120  
thereby creating a direct financial conflict that precludes lawful consideration of DP4 and gives  
rise to a reasonable apprehension of bias.  
[224] Articles 1.1 and 1.2 of the Code of Conduct provide that its object “is to preserve and  
enhance public confidence in the integrity and impartiality of directors and officers” of the  
VFPA by “establishing clear conflict of interest rules”, and that the Code of Conduct is to be  
interpreted in accordance with a series of general principles, to wit, that every director and  
officer shall discharge his or her duties as regards the preservation and enhancement of public  
confidence, that such discharge of duty may not necessarily be fulfilled by merely “acting in  
accordance with the technical requirements” of the governing instrument, and that the mere  
appearance of conflict, as opposed to actual conflict, may compromise public confidence and  
trust in the integrity and impartiality of the VFPA.  
[225] In addition, the VFPA’s Project and Environmental Review Policy [PER Policy] was  
created, inter alia, so as to establish a PER Process that meets the VFPA’s responsibilities under  
applicable legislation, makes certain that port development reflects environmental, economic and  
social objectives, and provides efficient and effective service to VFPA stakeholders. Under the  
PER Policy, the VFPA’s board of directors authorizes the President and CEO to establish  
procedures and issue permits, approvals and/or authorizations pursuant to the PER Policy and  
PER Process and to delegate this authority as appropriate to the VFPA executives and staff. In  
addition, the PER Policy makes it clear that the PER Process is to be “guided by principles and  
legal requirements of reasonableness, procedural fairness and ethical conduct.”  
Page: 121  
[226] GCT argues that the VFPA’s executives as decision makers must be presumed to be  
biased because of financial interest in the success of RBT2; a reasonable apprehension of bias  
can be presumed where a judge or member of a tribunal has an interest in the matter that he or  
she is called upon to adjudicate (Ireland v Victoria Real Estate Board, [1996] 1 WWR 349  
at p 385).  
[227] The VFPA argued initially that I should not consider this argument as GCT failed to  
plead this issue in its amended notice of application for judicial review and is now precluded  
from raising it (Tl’azt’en Nation v Sam, 2013 FC 226 at para 6 [Kenny Sam]; Air Canada v  
Toronto Port Authority, 2010 FC 774 at para 80). That is of course the general principle;  
however, as expressed by Justice O’Reilly in Kenny Sam, there is some room for discretion where,  
for example, the new issue is related to those set out in the notice and are supported by the  
evidentiary record, and where the respondent would not be prejudiced and no undue delay would  
result (Kenny Sam at para 7; Al Mansuri v Canada (Minister of Public Safety and Emergency  
Preparedness), 2007 FC 22 at paras 12-13). Here, I find that the prospect of the executives having a  
financial interest in RBT2 is significant in the context of possible bias. Given that bias is the  
overriding issue put forward by GCT, and the issue that permeates all others in this case, I think it  
appropriate to exercise my discretion and address the issue.  
[228] In this case, GCT submits that the decision-making of the VFPA was rife with a bias that  
each of the decision makers could not avoid in that each of the executive team members had a  
direct pecuniary interest in RBT2 being approved at the expense of DP4, and adds that at no time  
did any member of the executive declare such conflict at the time the March and September 2019  
Page: 122  
decisions were being contemplated. As an indicium of such bias and one more factor as to why  
the “mind was closed” over at the VFPA with respect to DP4, GCT points to the VFPA 2020  
Financial Report, which illustrates that medium-term incentive plan, being a three-year, cash-  
based performance-based compensation, which GCT argues is specifically linked to the building  
of capital projects, including RBT2.  
[229] I find that GCT is misconstruing the description of the incentive plan. The passage cited  
by GCT reads as follows:  
The medium-term incentive plan aligns executive compensation  
with completion of longer-term initiatives necessary to the port  
authority’s strategic plan and the larger success of the port. To  
ensure the port authority retains and motivates key talent over the  
span of these multi-year projects, all executives are eligible for the  
2019-2021 and future medium-term incentive plan grants.  
The 2019-2021 and 2020-2022 grants awarded in 2020 (referred to  
as “2020 Grant”) focuses on strategic capital projects to build  
urgently needed container capacity (the Centerm Expansion  
Project and Roberts Bank Terminal 2 Project) and road and rail  
projects throughout the gateway. Collectively these projects are  
critical to the ability of the port to meet Canada’s trade objectives.  
[230] GCT reads the passage as suggesting that the executive members who rendered the  
March and September 2019 decisions were biased as their financial compensation rested, at least  
partially, upon the completion of RBT2. That is not the way I read the passage. Clearly,  
performance matrices have been introduced into the executive remuneration package, as is  
common with many companies looking to attract talent at the executive level. However, I do not  
read the description of the package as performance incentives being based upon approving or not  
approving any specific project; the mention of RBT2 is but a coincidence as that project was  
already identified as one of the lead development projects undertaken by the Port of Vancouver.  
Page: 123  
[231] It seems to me that had the VFPA also decided to move forward with DP4, that project  
would also have been singled out in the passage upon which GCT relies to make its argument. In  
this case, the VFPA’s Land Use Plan dated October 28, 2014—in effect when the March and  
September 2019 decisions were madeidentifies as one of its objectives the development of  
RBT2, amongst other things, as part of the VFPA’s long-term strategy to meet projected growth.  
It makes perfect sense, therefore, that it would be RBT2 that is identified in the description of the  
executive package incentive plan as one of the relevant capital projects upon which the  
performance matrices is based.  
[232] GCT asserts that it does not matter what the financial interest is or how significant it is,  
but rather that it exists. If I am to accept GCT’s argument, the VFPA executives are in financial  
conflict every time they chose to move forward with any particular development project,  
regardless of which one they chose; that cannot be right. As was the case before Mr. Justice  
O’Reilly in Communities and Coal Society, the medium-term incentive plan in this case does not  
reward project approvals directly; the motivation for the executives is not to select one project  
over the other, but rather the see the project selected move forward in line with the port  
authority’s statutory obligations and objectives. I find GCT’s indignation to be misplaced.  
(d)  
Contradictions in the VFPA’s positions as evidence of bias  
[233] GCT asserts that the many contradictory positions of the VFPA reveal a desire to make  
up the rules as it goes along, to say things when it is expedient to do so, thus evidencing its bias,  
which is the inevitable result of those contradictions and untenable positions. GCT highlights the  
following:  
 
Page: 124  
The VFPA publicly asserts that separation is required between its proponent  
i.  
function and its regulatory function, but it failed to deliver on that requirement,  
and has no written policy to secure compliance.  
ii.  
Although the PER Process sets out steps that will be taken to ensure evidence-  
based, objective decision-making so that the regulatory function is exercised on  
the merits, such a policy was not followed by the VFPA when it rejected GCT’s  
PPE out of hand.  
iii.  
When GCT submitted its PPE on February 5, 2019, it was received and  
distributed amongst VFPA management with the expectation, even internally, that  
staff would begin the review of the proposal and that the PER Process would be  
followed; however, that process was halted by the VFPA executives.  
iv.  
The VFPA’s claim that it is entitled to have a closed mind on the regulatory side  
because of the structure under the CMA is at odds with its invitation to GCT to  
make submissions on its purported bias in its letter of October 2, 2019.  
v.  
The VFPA invited GCT to re-submit its PPE in September 2019, yet asserts  
before this Court that it has no ongoing role in respect of DP4 under the IAA.  
vi.  
Although the VFPA states that it is entitled to arrive at a decision preferring  
RBT2 over DP4, no documents or analysis engaging with the merits of both  
projects, or any evidence of any meetings or discussions reflecting this  
comparison, can be found in the tribunal record.  
Page: 125  
[234] I have already addressed the issues identified by GCT. I am of the view that any  
purported contradictions or inconsistencies in the VFPA’s conduct is better dealt with in relation  
to whether it breached procedural fairness by not respecting the legitimate expectations of GCT.  
I see no element of impermissible bias on the part of the VFPA in the elements raised by GCT.  
(e)  
Final thoughts on the bias issue  
[235] On the whole, and although I find, as I set out below, that the VFPA breached its  
obligation of procedural fairness owed to GCT by not allowing GCT to address the VFPA’s  
concerns within the regulatory process, I am not convinced that either the March or September  
2019 decisions were reflective of impermissible bias on the part of the VFPA. The concern over  
DP4’s timeline for coming on stream, if at all, had previously been expressed by the VFPA a  
year earlier in its letter of February 2, 2018, to GCT; the VFPA outlined the environmental  
hurdles that DP4 was expected to face in the regulatory approval process, and stated that when it  
comes time to formally review the project in conjunction with the PER Process, the port  
authority would have to consider the impacts of DP4 on overall port operations and in a  
cumulative context with RBT2, and that regarding the issue of timing, the port authority would  
have to recognize the very significant lead times required for the projects, and the increasing  
need for more near-term capacity in the Port of Vancouver. Accordingly, the VFPA advised in  
its March 2019 decision that it would not be processing GCT’s PPE through the PER Process at  
that time but would be open to reviewing development plans for Deltaport when it could more  
accurately project the need for incremental capacity beyond RBT2.  
 
Page: 126  
[236] Although I will deal with this issue in greater detail when I address GCT’s claim of  
breach of its legitimate expectations, I will say that a port authority under the CMA is a non-  
adjudicative decision maker, and its regulatory role is tethered to its role as manager and operator  
of the port. It seems to me that the March 2019 decision was more of a reflection of the VFPA  
improperly putting its commercial foot ahead of its regulatory foot. Although this may be a result  
of the overlapping structure created by Parliament in the manner that the CMA set up the VFPA,  
it is not, in my view, a manifestation of actual impermissible bias. Commercial people will act in  
commercial ways; that is not always a reviewable error.  
[237] If Parliament gave port authorities commercial and operational responsibilities for a port  
while at the same time giving them regulatory responsibilities, it could only be because the  
regulatory functions must be undertaken alongside the role that the port authorities play in the  
development of long-term strategic and logistical planning for the port so as to maintain  
commercial competitiveness and facilitate trade, with port authorities at the same time having to  
act as good stewards of the environment that they are managing. In the end, the VFPA is not, as  
GCT argues, a competitor of GCT that is promoting it own project ahead of that of GCT; VFPA  
is a port authority which has been authorized by statute to commercially run the Port of  
Vancouver, including developing its own infrastructure, and it is ultimately for the VFPA to  
decide which project gets to move to the head of the class. In a purely commercial setting, and  
outside of any contractual rights, tenants do not normally have the right to impose on landlords  
the obligation of having to consider the tenant’s further development projects. Here, I accept that  
we are not in a purely commercial setting, and the administrative requirements inherent in the  
VFPA’s regulatory role of the VFPA must be respected, however I make the point simply to  
Page: 127  
underscore the context in which the VFPA was operating, which went to inform the manner in  
which it developed its decision-making processes, and thereby whether the purported indicia of  
bias to which GCT points can fairly support a finding of a reasonable apprehension of bias on the  
part of the port authority. In this case, I find that such indicia cannot.  
[238] Moreover, I do not see that back-tracking on whether to have the PPE proceed through  
the PER Process a sign of bad faith or impermissible bias in any way. I can certainly understand  
the March 2019 decision from a business perspectiveI read it as the culmination of what has  
gone on with respect to RBT2 and DP4 until that point, in particular the expression of the  
VFPA’s concerns set out in its February 2, 2018 letter, save that the VFPA back-tracked on its  
previous invitation to process GCT’s PPE through its PER Process. Rather, the problem lies not  
so much in the reasons for the March 2019 decision, but rather, as I deal with below, in its timing  
in relation to the regulatory, decision-making process that GCT had triggered in filing its PPE  
through the PER Process portal. Here, the RBT2 train had been on the rails for some six years,  
heading down the track of development, and on the whole, I am not convinced that the  
March 2019 decision of the VFPA not to consider at that time a project that would add additional  
capacity of 2 million TEUs when the need for such extra capacity beyond RBT2 was not  
projected by the VFPA, was a sign of a closed mind on the part of the port authority in the sense  
postulated by GCT.  
[239] As regards the VFPA’s invitation of October 2, 2019 for GCT to make submissions in  
relation to its claim of bias so that the port authority could address it, GCT asserts the invitation  
was yet another tactical decision; it argues that the VFPA has no process to deal with a situation  
Page: 128  
where its bias is raised, that at no time during the present proceedings has the VFPA articulated a  
process on how such a review of a claim of bias was to be undertaken, and that in any event it  
would have been the same executive members against whom the allegation of bias was made that  
would have ruled on their own bias. I put it to GCT’s counsel whether in fact what the VFPA  
was inviting GCT to do was indeed to suggest an acceptable process whereby the port authority  
could address whether there existed any impermissible bias on its part, and if so, what steps need  
to be taken to alleviate it. GCT’s response was that this was not the proper way for a statutory  
decision maker to address its own bias. However, context is important, and we must not forget  
that the VFPA is not set up as a traditional regulatory boards or tribunals. GCT provided no  
example of a process for how a statutory decision maker of the type of the VFPA was to deal  
with allegations of its own bias, yet took issue with the fact that the VFPA was suggesting that it  
may rule on its own bias while there was a live application for judicial review to deal with the  
issue. A tribunal’s ability to rule on its own bias is a prominent feature of administrative law (Lin  
at para 6; CB Powell Limited at para 33; Eckervogt v British Columbia, 2004 BCCA 398).  
[240] GCT also takes issue with the fact that it was only with the affidavit of Mr. Xotta, filed in  
August 2021 as part of the present proceedings, that it first became aware that it was the VFPA  
executives who made the decisions reflected in the March 2019 and September 2019 decisions;  
until then, the decision-making process was “opaque” according to GCT. For my part, I see  
nothing nefarious in the fact that the VFPA only disclosed that it was its executive team that  
made the decisions reflected in the March 2019 and September 2019 decisions in the affidavits  
filed in support of its defence of GCT’s claim; I am not quite sure what earlier opportunity would  
have been more appropriate, notwithstanding that the March and September 2019 decisions were  
Page: 129  
signed by a VFPA executive. GCT concedes that it was the VFPA board of directors that would  
have delegated the decision-making to the port authority’s executives; it therefore only makes  
sense that it would have been the members of the VFPA’s executive team who made the relevant  
decisions.  
[241] According to GCT, the rescission of the March 2019 decision by the September 2019  
decision and the shielding of the documents that were before the VFPA executives who made  
both decisions behind a wall of solicitor-client privilege further demonstrate the VFPA’s bias  
and do not cure the procedural fairness issue arising from the March 2019 decision. I put it to  
GCT counsel during the hearing whether or not it was still open to the VFPA, after an  
application for judicial review was instituted regarding the March 2019 decision, to simply have  
a change of heart and rescind that decision. GCT asserted that once a matter was before the  
courts, the concept of self-help was no longer in the hands of the VFPA and that the  
September 2019 decision was a blatant litigation strategy by the VFPA, which was somehow  
gaming the system in an attempt to shield itself from judicial review. The furthest GCT would go  
was to concede that there could be circumstances where a port authority feels that it genuinely  
made a mistake and rescinds an earlier decision, but GCT’s counsel defied this Court to find a  
VFPA process that deals with rescission in the bias context. In essence, GCT is arguing that the  
March 2019 decision could not be rescinded in the context of bias, thus the VFPA is biased  
because it rescinded its March 2019 decision. I cannot agree as it seems to me that GCT is  
involved in an exercise of circular reasoning.  
Page: 130  
[242] In any event, this is again a tempest in a teapot. GCT argues that it could accept a  
scenario where a tribunal has a process for reconsideration and, in that context, finds that it made  
an error and rescinds an earlier decision. However, here there is an absence of such a process,  
thus no control and no ability to review because the tribunal record does not contain any  
document that was before the VFPA executives when the September 2019 decision was made.  
Again, I have not been convinced by GCT. I accept that the PER Process was not followed with  
the March 2019 decision, but that was the very reason the VFPA issued the September 2019  
decision. I also accept that there is no process for reconsideration of a decision of the VFPA  
other than judicial review, but if there was to be such an internal process, it would be for the  
benefit of the stakeholder seeking reconsideration of a decision of the VFPA. I have not been  
convinced that the VFPA requires a process for itself to reconsider its own decision.  
[243] On a final note on the issue of bias, GCT argues further that there can be no other way to  
interpret all the purported indicia of bias other than to find that the VFPA had a closed mind with  
respect to DP4, and that a closed mind necessarily implies actual bias. GCT asserts that it is one  
thing to exercise a discretion to refuse to approve a project after considering it on its merits,  
pursuant to the VFPA’s regulatory obligations under the CMA, but it is quite another to purport  
to exercise such a discretion to refuse to even consider DP4 on its merits; all that GCT is  
required to do, it argues, is to demonstrate that there exists a regulatory regime that the VFPA is  
tasked by statute with administeringa regime that has obligations of fairness, impartiality,  
transparency, and objectivityand which does not afford the port authority the right to have a  
closed mind and not even consider the project on an evidence-based basis. I agree with GCT, but  
find that although a purported exercise of discretion to refuse to consider DP4 on its merits may  
Page: 131  
constitute a breach of procedural fairness, it does not necessarily imply that the VFPA executives  
had a closed mind in the sense of creating an impermissible bias against DP4 in the present  
context. Rightly or wrongly, the VFPA may well have thought themselves justified to come to  
the March 2019 decision for the very reasons set out therein, reasoning which, again, rightly or  
wrongly, does not necessarily imply impermissible bias on its part.  
(2)  
Has the VFPA breached GCT’s legitimate expectations?  
[244] GCT made it clear before me that it is not arguing that once its PPE was submitted  
through the PER Process portal, the VFPA had the obligation to see the review process through  
to its completion before coming to a decision on the project which, it admits, the port authority  
already knew well prior to the submission of its PPE. Rather, what GCT is arguing is that  
engaging the VFPA on February 5, 2019, as a statutory decision maker undertaking a public law  
function that has administrative law requirements, with obligations of procedural fairness,  
objectivity and transparency, required the port authority to dedicate the needed resources in order  
to provide some semblance of consideration on the merits of the proposal.  
[245] GCT argues that the entire structure of the PER Policy is designed to deal with its PPE  
being allowed into the process, and thus, there is no room within the delegation, procedures and  
process that contemplates the VFPA being able to “shut the door” and not allow GCT to engage  
the PER Process. GCT asserts that the VFPA’s closed mind in dealing with the DP4 project  
thwarted the legitimate expectations that it, and the port community, had that the VFPA would  
abide by the PER Process that it itself had established, and whereby, as part of that review  
process, the VFPA was expected to confirm the category of review, appoint a project lead and  
 
Page: 132  
complete tactical studies, and that once GCT’s application was considered and confirmed  
complete, the technical review would go through and a final decision would be made, with the  
project permit being issued with conditions, if appropriate; DP4 should have been allowed to  
enter the PER Process but, as argues GCT, the VFPA summarily refused, with the March 2019  
decision, to allow its PPE to continue through the review process in good faith, and in doing so,  
barred the door to any consideration of the DP4 project.  
[246] The VFPA argues that I should not consider GCT’s argument regarding the doctrine of  
legitimate expectations as GCT did not specifically plead it in the amended notice of application  
for judicial review, raising it for the first time in its memorandum of fact and law. In any event,  
argues the VFPA, the PER Process does not create a substantive right on the part of an applicant  
to have its proposal considered, but is simply a non-binding guide provided to assist project  
proponents in making their application; in fact, the Guide contains a disclaimer on the first page,  
which reads: “This application guide and its supporting documents are provided as information  
and should not be taken as scientific, business, legal or other professional advice”. The  
introduction states: “this guide is provided for information purposes only and may be updated  
from time to time without notice”. Notwithstanding the objection raised by the VFPA, for my  
part, I find the issue important enough that it must be addressed, in particular considering the  
history of this matter and the relationship of the parties.  
[247] The doctrine of legitimate expectation was set out by the Supreme Court of Canada in  
Agraira v Canada (Public Safety and Emergency Preparedness), 2013 SCC 36 at paragraphs 93  
to 97:  
Page: 133  
[93]As this Court noted in Dunsmuir, at para. 79, “[p]rocedural  
fairness is a cornerstone of modern Canadian administrative  
law. Public decision makers are required to act fairly in coming to  
decisions that affect the rights, privileges or interests of an  
individual.” The Court’s comment that “[p]rocedural fairness has  
many faces” (Dunsmuir, at para. 77) is also relevant to this case.  
[94]The particular face of procedural fairness at issue in this  
appeal is the doctrine of legitimate expectations. This doctrine was  
given a strong foundation in Canadian administrative law in Baker,  
in which it was held to be a factor to be applied in determining  
what is required by the common law duty of fairness. If a public  
authority has made representations about the procedure it will  
follow in making a particular decision, or if it has consistently  
adhered to certain procedural practices in the past in making such a  
decision, the scope of the duty of procedural fairness owed to the  
affected person will be broader than it otherwise would have  
been. Likewise, if representations with respect to a substantive  
result have been made to an individual, the duty owed to him by  
the public authority in terms of the procedures it must follow  
before making a contrary decision will be more onerous.  
[95]The specific conditions which must be satisfied in order for  
the doctrine of legitimate expectations to apply are summarized  
succinctly in a leading authority entitled Judicial Review of  
Administrative Action in Canada:  
The distinguishing characteristic of a legitimate  
expectation is that it arises from some conduct of  
the decision-maker, or some other relevant  
actor. Thus, a legitimate expectation may result  
from an official practice or assurance that certain  
procedures will be followed as part of the decision-  
making process, or that a positive decision can be  
anticipated. As well, the existence of administrative  
rules of procedure, or a procedure on which the  
agency had voluntarily embarked in a particular  
instance, may give rise to a legitimate expectation  
that such procedures will be followed. Of  
course, the practice or conduct said to give rise to  
the reasonable expectation must be clear,  
unambiguous and unqualified.  
Page: 134  
[96] In Mavi, Binnie J. recently explained what is meant by “clear,  
unambiguous and unqualified” representations by drawing an  
analogy with the law of contract (at para. 69):  
Generally speaking, government representations  
will be considered sufficiently precise for purposes  
of the doctrine of legitimate expectations if, had  
they been made in the context of a private law  
contract, they would be sufficiently certain to be  
capable of enforcement.  
[97]An important limit on the doctrine of legitimate expectations  
is that it cannot give rise to substantive rights (Baker, at  
para. 26; Reference re Canada Assistance Plan (B.C.), 1991  
74 (SCC), [1991] 2 S.C.R. 525, at p. 557). In other words,  
“[w]here the conditions for its application are satisfied, the Court  
may [only] grant appropriate procedural remedies to respond to the  
‘legitimate’ expectation” (C.U.P.E. v. Ontario (Minister of  
Labour), 2003 SCC 29, [2003] 1 S.C.R. 539, at para. 131.  
[First emphasis added; second and third emphasis in original.]  
[248] At the outset, I find that the manner in which GCT approached the doctrine of legitimate  
expectations would suggest a merger of such a doctrine with the duty of procedural fairness,  
whereby a breach of the doctrine necessarily leads to a breach of the duty; such expression of the  
doctrine is incorrect. The doctrine of legitimate expectations is but one factor meant to inform  
the content or scope of the duty of fairness, a duty that varies from case to case (Baker at paras  
23-27). The content of such a duty must also be determined in conjunction with other factors,  
and in particular, the statutory scheme which created the VFPA.  
[249] Also, the doctrine of legitimate expectations cannot give rise to substantive rights;  
representations giving rise to the doctrine must be procedural in nature and must not conflict  
with the decision maker’s statutory duty (Canada (Attorney General) v Mavi, 2011 SCC 30 at  
para 68). As stated, the VFPA argues that the PER Process only provides guidance on the  
Page: 135  
procedure to be followed, and any claim or expectation that a project application would be  
assessed through the PER Process could only be a substantive right, if at all, and under the  
circumstances, may well dilute a port authority’s statutory duty to determine the projects that  
form part of the long-term strategic plan for the port. I agree. If I accept that the PER Process  
creates an obligation on the part of the VFPA to fully process any proposal under any  
circumstance, that would mean that any project proponent would be able to force the port  
authority to commit resources to reviewing an application for, say, a new liquid bulk terminal,  
when the addition of such a terminal is inconsistent with the commercial direction the port  
authority wishes to take at a particular time and for a particular area of the port, even where,  
quite possibly, the development of a new liquid bulk terminal at some point in the future is  
consistent with the goals, objectives, policy directions and land use designation included in the  
port authority’s Land Use Plan. To do so would be tantamount to the tail wagging the dog,  
especially where, as is the case here, the proponent knew of the port authority’s preference for  
another project well before it submitted its PPE.  
[250] However, GCT is not arguing that it has substantive rights such as a right to a specific  
outcome or that its legitimate expectations extend to having the right to see its proposal for DP4  
be run through the entire PER Process before the VFPA rendered its decision; what GCT is  
asserting is that once the PER Process is engaged, procedural fairness dictates that its PPE not be  
dismissed out of hand, in particular where the VFPA previously confirmed its right to access the  
PER Process. The VFPA does not seem to take issue with that aspect of GCT’s argument and  
concedes that although the PER Process cannot give rise to substantive entitlements, it may  
Page: 136  
engage the right to procedural fairness as part of the VFPA’s regulatory, decision-making  
function.  
[251] I accept that the Guide provides that before an existing tenant is to file its PPE, it should  
first review its property agreement “to ensure the proposed works and uses are permitted or if  
landlord consent or an amendment to an agreement is first required”; however, I do not read this  
guidance as a condition precedent to engaging the VFPA’s regulatory, decision-making process  
for projects requiring the port authority’s review. Prior to the formal submission under the PER  
Process, any discussions between project proponents and the VFPA regarding a project, or any  
meetings or project presentations by proponents, would not necessarily engage the decision-  
making role of the port authority for such projects. Regardless of the previous discussions it may  
have had with the VFPA, and the various presentations it made regarding DP4, I agree with GCT  
that the VFPA had not made a decision regarding DP4 and did not have to until its regulatory  
role as a statutory decision maker was engaged. It is the engagement of the port authority’s  
regulatory, decision-making functionwith the filing of a preliminary project review application  
under the PER Processwhich triggers the duty of procedural fairness, to which any project  
proponent has a right. As stated by the Supreme Court in Baker: “The fact that a decision is  
administrative and affects ‘the rights, privileges or interests of an individual’ is sufficient to  
trigger the application of the duty of fairness” (Baker at para 20; Cardinal v Director of Kent  
Institution, [1985] 2 SCR 643 at p 653).  
[252] Consequently, with GCT filing its application under the PER Process, I find that the  
VFPA owed a duty of procedural fairness to GCT in respect of its PPE. That said, the next issue  
Page: 137  
is the content and scope of such a duty. As instructed by the Supreme Court in Baker, the content  
and level of the duty of fairness varies from case to case depending upon applicable factors  
(Baker at paras 21 to 27). As made clear by the FCA in Canadian Pacific Railway Company, in  
assessing a procedural fairness argument, a court is required to consider whether the procedure  
was fair having regard to all of the circumstances, including the Baker factors (Canadian Pacific  
Railway Company at para 54). In particular, and relevant in this case, one of the factors to  
consider in assessing whether there was a breach of procedural fairness in the VFPA putting an  
end to the PER Process review of GCT’s PPE when it did includes, as indicated earlier, the  
“nature of the statutory scheme and the ‘terms of the statute pursuant to which the body  
operates’” (Old St Boniface at p 1191; Baker at para 23).  
[253] As stated earlier, the PER Policy makes it clear that the PER Process is to be “guided by  
principles and legal requirements of reasonableness, procedural fairness and ethical conduct.” In  
addition, the PER Policy contains a “Procedures” section, which provides, inter alia, that the  
President and CEO of the port authority is to establish procedures and standards to guide and  
administer the PER Process, which is to apply to all physical works and activities within  
VFPA-managed lands and waters, and which also ensures that each proposed project reviewed  
under the process receives a level of assessment sufficient to determine compliance with relative  
requirements. I should also add that the guiding principles of the PER Process indicate that the  
process is to be transparent, apply the appropriate level of review relative to any potential  
impacts, and provide for the efficient use of resources.  
Page: 138  
[254] As set out in the Guide, the PER Process has six steps, beginning with (1) the submission  
by the proponent of the PPE through the VFPA’s project and environmental review portal, (2)  
the assessment of the PPE, (3) submission of the full project application, (4) once the application  
is considered complete, the application is reviewed, (5) a project decision is made, and (6) if  
allowed, permitting conditions are issued. In this case, the VFPA acknowledged GCT’s right to  
engage the PER Process in its February 2, 2018 letter. Moreover, upon submission of the PPE a  
year later, an internal VFPA email circulated the PPE and indicated, consistent with Step 2 of the  
process, that a team leader would be named and that staff was to be undertaking a review of the  
preliminary submissions. It is at the implementation stage of Step 2 where, in the words of GCT,  
everything ground to a halt. Consequently, it is what happened between then and the March 2019  
decision that is at issue.  
[255] The Guide indicates that the process is to apply the appropriate level of review relative to  
any potential impacts and provide for the efficient use of resources. The Guide also provides that  
the PER Process is meant to ensure that proposed projects are “carefully considered in the  
process of determining if they should proceed.” Careful consideration does not imply a complete  
six-step assessment of the proposed project in all cases. If an element in a proposal is identified  
early by the port authority as being a non-starter, say, for example, where by-laws or regulations  
prohibit development in the proposed area of a project of the nature of the proposal, allowing the  
review process to proceed to the full application stage will not change matters and may not serve  
any purpose, and thus would not be an efficient use of resources. Although I agree with the GCT  
that the VFPA must “do what they say they will do”, commercial efficacy has a role to play in  
the manner that the review process is undertaken.  
Page: 139  
[256] Likewise, I can certainly envisage a situation where the commitment of resources to  
assess beyond the preliminary review stage a project which has already formed the subject matter  
of lengthy discussions, previous consideration and formal presentations by its proponent to the  
port authority’s directors and executives, may be unnecessary in the context of a fair process, and  
where it would not be unreasonable or a breach of procedural fairness for the port authority to  
postpone or cut short its protracted regulatory review process, and even more so where the  
VFPA’s own long-term strategic plan includes another similar project.  
[257] That said, however, having a proponent engage the decision maker in its regulatory role  
should be the right of all proponents. As stated, the PER Process is the VFPA-created portal  
through which project proponents engage the VFPA’s decision-making regulatory regime for the  
assessment of projects requiring the port authority’s review, and once a project proponent  
triggers the PER Process, the port authority could not simply give the proposal short shrift.  
[258] Looking at the Baker factors, which inform the content of the duty of procedural fairness,  
I accept that the nature of the decision being made by the VFPA is one of a non-adjudicative  
decision maker, with little resemblance to judicial decision-making, thus rendering it more likely  
that commercial considerations in how and to what extent the process is followed come into play.  
This is consistent as well with the nature of the statutory scheme as outlined earlier. The role of  
the VFPA within the statutory scheme, its letters patent and other indicia as the commercial  
operator of the port would also tend to support the proposition that commercial considerations  
and the need for the efficient use of resources must play a role in the determination of the duty of  
fairness underpinning the March 2019 decision, keeping in mind that any such commercial  
Page: 140  
considerations must operate within a regulatory context once the PER Process is engaged. There  
is also no doubt that moving forward with DP4 is of financial importance to GCT as it would  
create a significantly larger footprint for GCT within the Port of Vancouver, an issue, as  
mentioned earlier, which is also of concern for the VFPA. That said, a financial interest is much  
lower on the scale in determining the scope of procedural fairness than, say, a right to freedom or  
another Charter protected right, and GCT has not gone as far as to suggest that its economic  
livelihood is dependent on the decision to move DP4 forward, whether locally or even  
internationally.  
[259] The determination of when the review process can legitimately be cut short, if at all, so as  
to remain procedurally fair is, as set out in Baker, very much subject to a case-by-case  
determination of the surrounding circumstances. I agree with GCT that neither the CMA, nor its  
regulations, nor the VFPA’s letters patent grant authority for the port authority to refuse to  
process its PPE through the project review regulatory process that the port authority has created;  
it asserts that the delegated authority was for a processnot a refusal to enter into the process,  
which would otherwise require clear languageand that transparency and consistency of  
treatment of applications are the hallmark of what the port stakeholders should expect. However,  
there is also nothing in the CMA, the letters patent, or the delegation under the PER Policy  
requiring the VFPA to run all projects through all the phases of the PER Process. Rather, it  
seems to me that what is required, as stated earlier, is that the procedures and standards ensure  
that each proposed project reviewed under the process receives a level of assessment sufficient to  
determine compliance with relative requirements, requirements that include, amongst other  
Page: 141  
things, the commercial needs of the port and the fulfilment of long-term planning commitments  
and strategies.  
[260] GCT cites North End Community Health Association v Halifax (Regional Municipality)  
[North End Health], 2012 NSSC 330 at paragraph 52, for the proposition that a duty to act in  
accordance with legitimate expectations is owed, “particularly where the decision-maker has  
created a procedure which it says it will follow”. I agree that legitimate expectations, as a factor  
under Baker, could heighten the degree of procedural fairness owed by a decision maker to  
where, without anything else, a failure to follow such procedures will amount to a breach of  
procedural fairness; that was the case in North End Health; however, that is not the case here. In  
this case, one cannot deny that other factors must come into play, including the history of  
development of the area around the proposed DP4 project and the engagement of the parties, as  
well as the statutory scheme under the CMA, the port authority’s role as a non-adjudicatory  
regulator, and the commercial purpose for its continuation.  
[261] I should also point out that a PPE is meant to be, as described by GCT, a very high level  
description of the proposed project. If the VFPA is to cut short the review process, its decision  
for not moving forward with a project must nonetheless be reasonable; I can imagine a decision  
of the port authority to refuse to complete the review process of a proposed project being set  
aside by a court on judicial review where the very foundation of the refusal could only  
reasonably have been ascertained through the completion of the review process. That is not the  
case here and, in fact, not the argument advanced by GCT.  
Page: 142  
[262] That said, GCT must be allowed to know the case that it must meet, and this within the  
regulatory process created with the triggering of the PER Process. As mentioned, prior to the  
formal submission under the PER Process, any discussions between project proponents and the  
VFPA regarding a project, or any meetings or project presentations by proponents, were outside  
the port authority’s regulatory role, and would not necessarily engage the right to procedural  
fairness. Although the VFPA may have the right to exercise its discretion so as to put an end to  
the review process at a certain point, did the VFPA act fairly in “halting” the review process  
when it did? In fact, during his cross-examination, Mr. Xotta confirmed that the VFPA did not  
engage any of the steps of the PER Process, I take it, beyond Step 1.  
[263] Step 2 of the PER Process is the preliminary review stage, which includes, amongst other  
things, the assignment of a port authority project lead, meeting with proponents to discuss the  
project, and the identification by the port authority of additional information or studies that may  
be required to support a complete application. It seems as though that stage is meant to act as a  
clearing house, initially vetting a preliminary project review application at a high level to spot  
any non-starters, for the determination of the appropriate level of review and for the initial  
meeting with the proponent to address, amongst other things, deficiencies, concerns and the  
requirements for the project prior to moving to the full application submission and assessment  
stage, where the heavy lifting is to take place.  
[264] Here, there was no indication of any concerns expressed to GCT between the time it  
engaged the port authority’s regulatory decision-making process and the March 2019 decision  
that would have allowed the VFPA to engage GCT in how it was proposing to address the  
Page: 143  
VFPA’s concerns prior to the review process being shut down. In his cross-examination,  
Mr. Xotta suggested that the concerns were provided to GCT with the February 2, 2018 letter. As  
regard the reason why GCT’s PPE was halted before proceeding to Step 2, Mr. Xotta also stated  
as follows:  
Q. Somebody stopped the process that Mr. Yeomans thought he  
was moving forward with, correct?  
A. Again, the project did not proceed through the subsequent  
phases. In other words, it stopped at step 2.  
Q. Well, it did not get going in step 2, did it?  
A. That’s correct.  
Q. And it didn’t get going in step 2 because somebody at VFPA  
told Mr. Yeomans and/or you not to do so, correct?  
A. The PPE failed to fundamentally address the issue that was  
referred to in [the February 2, 2018 letter], which is the timing of  
projects conflicting with other ones.  
[265] In my view, every proponent has the right to engage the decision maker acting within its  
regulatory capacity, and the refusal of a decision maker to engage with the process that it itself  
created to trigger its regulatory function would be a breach of procedural fairness. Although I  
accept that the February 2, 2018 letter may have been the VFPA’s effort to put its concerns to  
GCT, it was done prior to GCT engaging the port authority’s regulatory process. In this case,  
GCT must be allowed to know the case that it must meet, and this within the regulatory process  
created with the triggering of the PER Process. Under the circumstances, allowing the process to  
move to the preliminary review stage by appointing a project lead and having the discussion and  
exchange with GCT within the regulatory context would have been, in my judgment, what the  
duty of fairness called for under the circumstances. That does not mean that the VFPA must  
Page: 144  
undertake self-induced amnesia in its consideration of DP4. It would make little commercial  
sense for the preliminary assessment process to begin from scratch every time an application is  
made under the PER Process; the port authority should be able to draw on its previous  
knowledge and discussions and exchanges with the proponent about a proposed project in  
determining whether to move beyond the preliminary project review stage.  
[266] I note in particular that following GCT’s submission of its PPE, the application was  
distributed internally amongst VFPA management confirming that staff would be doing an  
internal review over the coming days or weeks. The email highlights that GCT’s proposal was  
intended to be a two-stage development and that “no doubt, a number of initial meetings with  
GCT will be required.” As stated earlier, on February 7, 2019, the VFPA acknowledged receipt  
of the PPE and confirmed to GCT that staff “will undertake a review of the submission to better  
understand the project and determine if our submission criteria has been satisfied in order to  
continue processing.” It also appears that the proposed meeting for February 13, 2019, was  
deferred on account of VFPA staff not having completed their review of the information  
submitted by GCT, although on February 15, 2019, the VFPA confirmed that GCT’s request and  
submission materials were before VFPA senior management. In the end, it is not clear whether,  
or to what extent, if any, VFPA staff undertook their initial review of GCT’s submission.  
[267] Although the PPE is meant to be a high-level description of the project, it did provide  
insight regarding, amongst other things, the expectations of GCT undergoing PER Process  
review, a description of the project and its proposed location, project context and rationale, key  
elements of project scheduling and regulatory engagement, stakeholder outreach and, in  
Page: 145  
particular, environmental mitigation efforts and commitments. However, all the evidence  
establishes is that a project lead was not assigned for DP4, that no meeting took place between  
the VFPA and GCT, and that at no time was GCT advised of any concerns specifically  
addressing its submissions. The VFPA says that the deliberation of its executives is reflected in  
the March 2019 decision; however, I find that this was insufficient under the circumstances  
and—putting aside any issue of reasonableness and failure to engage with GCT’s submissions—  
a breach of the port authority’s duty of procedural fairness was owed to GCT.  
[268] Given confirmation of the initial review by the VFPA, the legitimate expectations of  
GCT weighed even more heavily in the determination of the scope of the duty for procedural  
fairness. There is no doubt that the VFPA has the right, and I dare say the obligation, to set  
development priorities for the Port of Vancouver and, wearing its commercial hat, to cease the  
review of a project which is inconsistent with such priorities at the time, and which may be  
riddled with other concernsconcerns which, I might add, were expressed in the March 2019  
decision. However, before ceasing such review, it was incumbent upon the VFPA, wearing its  
regulator’s hat, to put those concerns to GCT within the framework of the regulatory process,  
where the duty of procedural fairness is engaged, and at least at a stage where, on the spectrum  
of efficient and justifiable use resources, the port authority is still at the lower end of the usage  
metre. In fact, in his cross-examination, Mr. Xotta conceded that the intention of the PER  
Process is to also “help inform potential applicants of the depth of analysis and questions that  
might arise in the process.” This must be undertaken within the scope of the port authority’s  
regulatory, decision-making process, regardless of the commercial discussions that may have  
taken place prior to the formal engagement of that process.  
Page: 146  
[269] It may also well have been that following the completion of the preliminary project  
review stage, and the expected meeting between the parties, no further material addressing those  
issues or concerns would have been submitted by GCT as part of its more fulsome application;  
however, the process does envisage at an early stage for proponents to discuss those concerns  
with the port authority wearing its regulator’s hat, during which time the VFPA may well  
identify information that would be required if the process was to continue. Here, that part of the  
process was not fully undertaken. I accept that GCT was aware of the concerns that the VFPA  
had with DP4 well before February 5, 2019, and, as conceded by GCT before me, the nature of  
DP4 did not change significantly between the time GCT began discussing the DP4 project in  
detail with the VFPA in 2016 and the March 2019 decision. I also accept that the VFPA had put  
GCT on notice on February 2, 2018, regarding how it would view any formal application for  
assessment of DP4; however, the submission of the PPE through the PER Process was the first  
formal submission of DP4 by GCT to the VFPA. However as stated, up to that point, any  
discussions and concerns raised by the VFPA, such as those in the February 2, 2018 letter, were  
expressed prior to the triggering of the regulatory decision-making process and outside the  
protections afforded by such a process by its very naturethe February 2, 2018 letter contained  
no decision, and accordingly, could not form the subject matter of an application for judicial  
review.  
[270] Also, it is possible that the March 2019 decision would have met the requirements for  
procedural fairness had it been issued after the completion of the preliminary review stage,  
where the parties were to engage, for the first time, with the formal submission of GCT, but it  
was not; the VFPA simply jumped the gun.  
Page: 147  
[271] On the whole, I find that the VFPA breached its duty of procedural fairness in not having,  
in this case, undertaken the tasks set out in Step 2 of the PER Process, in not having proceeded to  
review GCT’s PPE at least through the preliminary review stage and, rather, in issuing its  
March 2019 decision when it did.  
[272] GCT further argues that I cannot separate the issue of bias from the issue of procedural  
fairness and that if I were to find that the VFPA breached procedural fairness by refusing to  
assess its PPE through the PER Process without first having reviewed it, such conduct was  
tantamount to an act of pre-judgment which could only be attributable to a closed mind. I  
disagree with GCT. As stated, I see this more as the VFPA executive team improperly putting its  
commercial foot ahead of its regulatory foot, relying on what it knew, or at least thought it knew,  
of the DP4 project and the manner in which it would affect RBT2, without allowing that  
determination to be made within the regulatory process which any proponent, GCT included, had  
a right to engage.  
[273] GCT also argues that according to Mr. Xotta, the decision not to move forward with  
processing GCT’s PPE was made in a meeting of the executives on February 13, 2019, yet on  
February 15, 2019, the VFPA advised GCT that the matter was before senior management—  
which I assume to be the VFPA executivesand then it took another two weeks to issue the  
March 2019 decision. I am not sure what to make of GCT’s insinuation, however I find nothing  
untoward in a decision having been made by the VFPA executives not to move forward with the  
review process and then, given the obvious magnitude of the decision, for the decision to be  
reviewed, and then for the VFPA to take the time needed to draft the appropriate response—  
Page: 148  
possibly even seeking legal advice regarding its drafting. In addition, as I stated earlier, the  
paucity of documents evidencing the decision-making process is not unusual, in my experience,  
in the context of this matter.  
[274] That said, and given my finding of no bias on the part of the VFPA with respect to its  
decision-making process, I also find that any breach of procedural fairness was corrected with  
the September 2019 decision, whereby the VFPA advised, following the enactment of the IAA,  
that it was rescinding the March 2019 decision and that port staff would be in contact with GCT  
to re-engage the PER Process. Clearly, the VFPA continued to have jurisdiction under the  
permitting process, save that with the enactment of the IAA, its role during and following the  
impact assessment process of the review would henceforth be limited.  
[275] I also find that the September 2019 decision corrects any concerns with the  
reasonableness of the March 2019 decision. In particular, I return to the February 22, 2019 letter  
from Mr. Stewart to the Review Panel, where he stated that the VFPA “will not authorize or  
allow a proposed project to proceed if it is likely to result in significant adverse environmental  
effects that cannot be mitigated” and that “[p]roject permit applications may not be accepted if  
the port authority determines the project is not in the best interests of Canada’s overall trade  
objectives.” Here, the landscape has now changed and environmental assessment will be  
undertaken under the IAA, with the decision of the Agency informing the remaining permitting  
process under the PER Process. Although it may well be that the port authority has the discretion  
not to accept a project permit application if the port authority determines that the project is not in  
the best interests of Canada’s overall trade objectives, that is not the reason why the VFPA  
Page: 149  
refused to allow GCT’s PPE to be run through the PER Process. The September 2019 decision  
rescinding the March 2019 decision and inviting GCT to re-submit its PPEarguably with any  
amendments to take into consideration the change in the regulatory landscape brought on by the  
enactment of the IAAcorrects any reviewable errors in the first decision.  
C.  
Mootness and prematurity  
[276] GCT does not truly address the issue of mootness other than to say that the matter is now  
res judicata. As I mentioned earlier, I disagree, yet I determined that the issue of mootness and  
prematurity were intrinsically bound to the issue of bias. Having now considered the bias issue  
and found no impermissible bias on the part of the VFPA, the issues of mootness and  
prematurity return.  
[277] GCT conceded before me that if I were to find no evidence of impermissible bias or no  
reasonable apprehension of bias on the part of the VFPA, it would be difficult for GCT to argue  
that the remedies it is seeking should be granted. I agree. In fact, GCT does not argue that I  
should nonetheless consider the matter further under the principles set down by the Supreme  
Court in Borowski.  
[278] Considering the effect of the September 2019 decision, I am of the view that the issues  
surrounding the March and September 2019 decisions are now moot as there no longer exists a  
live issue that would affect the interests of the parties. First, I find that the status of GCT’s PPE  
has been reset with the September 2019 decision. Also, the repeal of the CEAA and the  
enactment of the IAA has reshaped the landscape and regulatory relationship between the port  
 
Page: 150  
authority and GCT, with the need to significantly engage on DP4 having been punted well down  
the field of time.  
[279] Given the change in legislation, any perceived preferenceeven assuming that such a  
preference was impermissibleis no longer a live issue if the VFPA is one day called upon to  
consider DP4 under its PER Process because RBT2, under the IAA, will necessarily form part of  
the impact assessment process of DP4; unlike the Review Panel under the CEAA, the review  
panel under the IAA is required to consider several factors, including the need for a Designated  
Project, alternative means, and the cumulative effects of other projects to be carried out (IAA at  
ss 22(1)(a)(ii), (d) and (f)). Although the VFPA retains permitting authority, it is no longer the  
port authority but rather the Agency under the IAA that would decide whether an impact  
assessment is required, as well as the any adverse effects of DP4.  
[280] Given my finding that the matter has become moot, I need not address the issue of  
prematurity.  
D.  
Does this Court have the jurisdiction to grant the relief sought by GCT?  
[281] Given my findings that the evidence does not support the existence of impermissible bias  
on the part of the VFPA in relation to the March and September 2019 decisions, there is also no  
need to consider the availability of the remedies in the nature of mandamus being requested by  
GCT or any other relief claimed in the amended notice of application for judicial review.  
 
Page: 151  
Conclusion  
[282] I see no issue with the VFPA claiming, as a regulator, that it has a policy-based  
preference for one expansion project over another. Strategic decisions necessarily involve  
making choices between two competing visions for the development of the port. In this case,  
preferring to move forward with the RBT2 project did not constitute a closing of the mind on the  
part of the VFPA, as administrative decision maker, thus rendering it biased in the sense  
professed by GCT. Moving forward with infrastructure development necessarily includes putting  
other options aside - in a way, closing one’s mind to them - but that is part of the decision-  
making process which allows a port authority to move forward with development and does not  
necessarily evidence a reasonable apprehension of bias on the part of the port authority in favour  
of its preferred project, nor does it mean that proponents of those competing visions for  
development may compel the port authority to go back and review its strategic decisions by  
simply throwing a new shiny penny into the mix.  
[283] GCT has submitted a number of hypotheses purporting to be evidence of a closed mind  
on the part of the port authority in relation to the DP4 project, thereby constituting impermissible  
bias affecting the March and September 2019 decisions. Although providing an interesting  
perspective on the record, GCT has not convinced me that its perspective on the elements of fact  
that it gleans from the record is the one I should adopt. Cherry picking elements of the factual  
record in an attempt to create a reoccurring theme is difficult to uphold when the elements may  
be reasonably explained quite apart from that theme.  
 
Page: 152  
[284] Having found that GCT has failed to establish impermissible bias on the part of the  
VFPA, and in line with the reasons of my decision, I dismiss the present application for judicial  
review, with costs in favour of the respondents. As requested at the conclusion of the hearing  
before me, I will provide the parties time to submit written submissions on costs.  
Page: 153  
JUDGMENT in T-538-19  
THIS COURT’S JUDGMENT is that:  
1.  
2.  
The present application is dismissed, with costs in favour of the respondents.  
The parties are encouraged to confer and come to an agreement as to costs. If the  
parties are unable to agree, the respondents may serve and file written  
submissions on costs not exceeding three pages (excluding schedules or  
appendices) within 15 days of the present judgment. The applicant may then serve  
and file written submissions in response not exceeding three pages (excluding  
schedules or appendices) within 15 days thereof, with reply submissions from the  
respondents within 5 days thereafter. I shall remain seized of the matter for the  
purpose of issuing my decision on costs. .  
"Peter G. Pamel"  
Judge  
Page: 154  
ANNEX  
Canada Marine Act, SC 1998, c 10  
Purpose of the Act  
Objectifs  
4 In recognition of the  
significance of marine  
transportation to Canada and  
its contribution to the  
Canadian economy, the  
purpose of this Act is to  
4 Compte tenu de  
l’importance du transport  
maritime au Canada et de sa  
contribution à l’économie  
canadienne, la présente loi a  
pour objet de :  
(a) implement marine policies a) mettre en œuvre une  
that provide Canada with the  
marine infrastructure that it  
needs and that offer effective  
politique maritime qui  
permette au Canada de se  
doter de l’infrastructure  
support for the achievement of maritime dont il a besoin, qui  
national, regional and local  
social and economic  
objectives and will promote  
and safeguard Canada’s  
competitiveness and trade  
objectives;  
le soutienne efficacement dans  
la réalisation de ses objectifs  
socioéconomiques nationaux,  
régionaux et locaux aussi bien  
que commerciaux, et l’aide à  
promouvoir et préserver sa  
compétitivité;  
(a.1) promote the success of  
ports for the purpose of  
contributing to the  
a.1) promouvoir la vitalité des  
ports dans le but de contribuer  
à la compétitivité, la  
competitiveness, growth and  
prosperity of the Canadian  
economy;  
croissance et la prospérité  
économique du Canada;  
(b) base the marine  
b) fonder l’infrastructure  
infrastructure and services on maritime et les services sur  
international practices and des pratiques internationales  
approaches that are consistent et des approches compatibles  
with those of Canada’s major avec celles de ses principaux  
trading partners in order to  
foster harmonization of  
partenaires commerciaux dans  
le but de promouvoir  
standards among jurisdictions; l’harmonisation des normes  
qu’appliquent les différentes  
autorités;  
(c) ensure that marine  
transportation services are  
c) veiller à ce que les services  
de transport maritime soient  
organized to satisfy the needs organisés de façon à satisfaire  
 
Page: 155  
of users and are available at a les besoins des utilisateurs et  
reasonable cost to the users;  
leur soient offerts à un coût  
raisonnable;  
(d) provide for a high level of d) fournir un niveau élevé de  
safety and environmental  
protection;  
sécurité et de protection de  
l’environnement;  
(e) provide a high degree of  
e) offrir un niveau élevé  
autonomy for local or regional d’autonomie aux  
management of components  
of the system of services and  
administrations locales ou  
régionales des composantes  
facilities and be responsive to du réseau des services et  
local needs and priorities;  
installations portuaires et  
prendre en compte les  
priorités et les besoins locaux;  
(f) manage the marine  
f) gérer l’infrastructure  
infrastructure and services in a maritime et les services d’une  
commercial manner that  
encourages, and takes into  
façon commerciale qui  
favorise et prend en compte  
account, input from users and l’apport des utilisateurs et de  
the community in which a  
port or harbour is located;  
la collectivité où un port ou  
havre est situé;  
(g) provide for the disposition, g) prévoir la cession,  
by transfer or otherwise, of  
certain ports and port  
facilities; and  
notamment par voie de  
transfert, de certains ports et  
installations portuaires;  
(h) promote coordination and h) favoriser la coordination et  
integration of marine l’intégration des activités  
activities with surface and air maritimes avec les réseaux de  
transportation systems.  
transport aérien et terrestre.  
Definitions  
Définitions  
5 The definitions in this  
section apply in this Part.  
5 Les définitions qui suivent  
s’appliquent à la présente  
partie.  
airport means an airport  
situated in a port. (aéroport)  
aéroport Aéroport situé dans  
un port. (airport)  
letters patent means letters  
patent as amended by  
lettres patentes Les lettres  
patentes telles que modifiées  
par lettres patentes  
Page: 156  
supplementary letters patent,  
supplémentaires, le cas  
if any. (lettres patentes)  
échéant. (letters patent)  
port means the navigable  
port L’ensemble des eaux  
waters under the jurisdiction  
navigables qui relèvent de la  
of a port authority and the real compétence d’une  
property and immovables that administration portuaire ainsi  
the port authority manages,  
que les immeubles et les biens  
holds or occupies as set out in réels dont la gestion lui est  
the letters patent. (port)  
confiée, qu’elle détient ou  
qu’elle occupe en conformité  
avec les lettres patentes.  
(port)  
user, in respect of a port,  
means a person that makes  
commercial use of, or  
utilisateur À l’égard d’un  
port, personne qui utilise le  
port à des fins commerciales  
provides services at, the port. ou y fournit des services.  
(utilisateur)  
(user)  
Application of Part  
Application de la présente  
partie  
6(1) This Part applies to every 6(1) La présente partie  
port authority set out in the  
schedule and to every port  
authority for which letters  
patent of incorporation are  
issued or that has been  
s’applique aux administrations  
portuaires inscrites à l’annexe  
et à celles pour lesquelles des  
lettres patentes ont été  
délivrées ou qui ont été  
continued under this Part and prorogées sous le régime de la  
that has not been dissolved.  
présente partie et n’ont pas été  
dissoutes.  
Amendment of schedule  
Modification de l’annexe  
(2) The Minister may, by  
regulation, amend the  
schedule.  
(2) Le ministre peut, par  
règlement, modifier l’annexe.  
Agent of Her Majesty  
Mandataire de Sa Majesté :  
administration portuaire  
7(1) Subject to subsection (3), 7(1) Sous réserve du  
a port authority is an agent of paragraphe (3), les  
Her Majesty in right of  
administrations portuaires ne  
Canada only for the purposes sont mandataires de Sa  
of engaging in the port  
Majesté du chef du Canada  
que dans le cadre des activités  
Page: 157  
activities referred to in  
paragraph 28(2)(a).  
portuaires visées à l’alinéa  
28(2)a).  
Not an agent of Her Majesty Non-mandataire de Sa  
Majesté  
(2) A wholly-owned  
subsidiary of a port authority  
(2) Les filiales à cent pour  
cent des administrations  
is not an agent of Her Majesty portuaires ne sont pas  
in right of Canada unless,  
subject to subsection (3),  
mandataires de Sa Majesté du  
chef du Canada sauf si, sous  
réserve du paragraphe (3) :  
(a) it was an agent of Her  
a) d’une part, elles l’étaient au  
Majesty in right of Canada on 10 juin 1996;  
June 10, 1996; and  
(b) it is an agent of Her  
Majesty in right of Canada  
b) d’autre part, elles le sont en  
vertu d’une loi autre que la  
under an enactment other than présente loi.  
this Act.  
Borrowing restriction  
Réserve  
(3) A port authority or a  
(3) Ni les administrations  
wholly-owned subsidiary of a portuaires ni les filiales à cent  
port authority may not borrow pour cent des administrations  
money as an agent of Her  
Majesty in right of Canada.  
portuaires ne peuvent  
emprunter de fonds à titre de  
mandataires de Sa Majesté du  
chef du Canada.  
Letters patent  
Lettres patentes  
8(1) The Minister may issue  
letters patent that take  
effect on the date stated in  
them incorporating a port  
8(1) Le ministre peut délivrer  
des lettres patentes prenant  
effet à la date qui y est  
mentionnée pour la  
authority without share capital constitution d’une  
for the purpose of operating a administration portuaire sans  
particular port in Canada if  
the Minister is satisfied that  
the port  
capital-actions en vue  
d’exploiter un port spécifique  
au Canada, s’il est convaincu  
que les conditions suivantes  
sont réunies :  
Page: 158  
(a) is, and is likely to remain, a) le port est financièrement  
financially self-sufficient;  
autonome et le demeurera  
vraisemblablement;  
(b) is of strategic significance b) il présente une importance  
to Canada’s trade;  
stratégique pour le commerce  
du Canada;  
(c) is linked to a major rail  
line or a major highway  
infrastructure; and  
c) il est rattaché à une ligne  
principale de chemins de fer  
ou à des axes routiers  
importants;  
(d) has diversified traffic.  
d) il a des activités  
diversifiées.  
Contents of letters patent  
Contenu des lettres patentes  
(2) The letters patent shall set (2) Les lettres patentes  
out the following:  
doivent préciser ce qui suit :  
(a) the corporate name of the  
port authority;  
a) la dénomination sociale de  
l’administration portuaire;  
(b) the place where the  
registered office of the port  
authority is located;  
b) le lieu de son siège social;  
(c) the navigable waters that  
c) les eaux navigables qui  
are within the port authority’s relèvent de sa compétence;  
jurisdiction;  
(d) the federal real property  
d) les immeubles fédéraux et  
and federal immovables under les biens réels fédéraux dont  
the management of the port  
authority;  
la gestion lui est confiée;  
(e) the real property and  
immovables, other than the  
federal real property and  
federal immovables, held or  
occupied by the port  
authority;  
e) les immeubles et les biens  
réels, autres que les  
immeubles fédéraux et les  
biens réels fédéraux, qu’elle  
occupe ou détient;  
(f) the number of directors,  
between seven and eleven, to  
f) le nombre  
d’administrateurs, compris  
entre sept et onze, nommés en  
Page: 159  
be appointed under section 14, conformité avec l’article 14 et  
to be chosen as follows:  
choisis de la façon suivante :  
(i) one individual nominated  
by the Minister,  
(i) un administrateur est  
nommé sur la proposition du  
ministre,  
(ii) one individual appointed  
by the municipalities  
mentioned in the letters  
patent,  
(ii) un administrateur est  
nommé par les municipalités  
mentionnées dans les lettres  
patentes,  
(iii) one individual appointed  
by the province in which the  
port is situated, and, in the  
case of the port wholly or  
partially located in  
(iii) un administrateur est  
nommé par la province où le  
port est situé et, dans le cas du  
port situé partiellement ou  
complètement à Vancouver,  
Vancouver, another individual un second administrateur est  
appointed by the Provinces of nommé par les trois provinces  
Alberta, Saskatchewan and  
suivantes : l’Alberta, la  
Manitoba acting together, and Saskatchewan et le Manitoba,  
(iv) the remaining individuals (iv) le reste des  
nominated by the Minister in  
consultation with the users  
administrateurs sont choisis  
parmi les personnes dont la  
selected by the Minister or the nomination est proposée par le  
classes of users mentioned in  
the letters patent;  
ministre en consultation avec  
les utilisateurs qu’il choisit ou  
les catégories d’utilisateurs  
mentionnées dans les lettres  
patentes;  
(g) a code of conduct  
governing the conduct of the  
directors and officers of the  
port authority;  
g) le code de déontologie  
régissant la conduite des  
administrateurs et dirigeants  
de l’administration portuaire;  
(h) the charge on the gross  
h) le montant des frais ou  
revenues of the port authority, le mode de calcul de celui-ci  
or the formula for calculating — que l’administration  
it, that the port authority shall portuaire devra payer  
pay each year to the Minister  
on the day fixed by the  
annuellement au ministre, à la  
date fixée par celui-ci, pour le  
Minister to maintain its letters maintien en vigueur de ses  
patent in good standing; lettres patentes, ces frais étant  
Page: 160  
calculés sur les revenus bruts  
de l’administration;  
(i) the extent to which the port i) la mesure dans laquelle  
authority and a wholly-owned l’administration portuaire et  
subsidiary of the port  
les filiales à cent pour cent de  
l’administration portuaire  
peuvent exercer les activités  
portuaires visées à l’alinéa  
28(2) a) et les autres activités  
visées à l’alinéa 28(2) b);  
authority may undertake port  
activities referred to in  
paragraph 28(2)(a) and other  
activities referred to in  
paragraph 28(2)(b);  
(j) the maximum term of a  
j) la durée maximale des baux  
lease or licence of federal real ou permis octroyés à l’égard  
property or federal  
immovables under the  
management of the port  
authority;  
des immeubles fédéraux ou  
des biens réels fédéraux gérés  
par l’administration portuaire;  
(k) the limits on the authority k) les limites aux pouvoirs de  
of the port authority to  
contract as agent for Her  
Majesty;  
l’administration portuaire de  
conclure des contrats à titre de  
mandataire de Sa Majesté;  
(l) the limits on the power of  
the port authority to borrow  
money on the credit of the  
port authority for port  
l) les limites au pouvoir de  
l’administration portuaire  
d’emprunter des fonds sur son  
crédit pour l’exploitation du  
purposes or a code governing port ou le code régissant ce  
that power, as the case may  
be; and  
pouvoir;  
(m) any other provision that  
the Minister considers  
appropriate to include in the  
letters patent and that is not  
inconsistent with this Act.  
m) toute autre disposition que  
le ministre juge indiqué  
d’inclure dans les lettres  
patentes et qui n’est pas  
incompatible avec la présente  
loi.  
Status of letters patent  
Non-application de la Loi  
sur les textes réglementaires  
(3) Letters patent are not  
regulations within the  
meaning of the Statutory  
Instruments Act, but shall be  
published in the Canada  
(3) Les lettres patentes ne sont  
pas des textes réglementaires  
au sens de la Loi sur les textes  
réglementaires; elles sont  
toutefois publiées dans la  
Page: 161  
Gazette and are valid with  
respect to third parties as of  
the date of publication.  
Gazette du Canada et sont  
opposables aux tiers à  
compter de leur date de  
publication.  
When Ministerial approval  
required  
Approbation ministérielle  
(4) Any provisions of letters  
(4) Les dispositions des lettres  
patent relating to the extent to patentes relatives à la mesure  
which a port authority may dans laquelle l’administration  
undertake activities referred to portuaire peut exercer les  
in paragraph 28(2)(b) shall be activités visées à l’alinéa  
approved by the President of  
the Treasury Board and the  
28(2) b) doivent être  
approuvées par le président du  
Minister of Finance before the Conseil du Trésor et le  
letters patent are issued.  
ministre des Finances avant la  
délivrance des lettres patentes.  
When Governor in Council  
approval required  
Approbation du gouverneur  
en conseil  
(5) Any provisions of letters  
patent relating to limits on a  
port authority’s power to  
(5) Les dispositions des lettres  
patentes relatives à la mesure  
dans laquelle l’administration  
borrow money on its credit for portuaire peut emprunter des  
port purposes shall be  
approved by the Governor in  
Council, on the  
fonds sur son crédit pour  
l’exploitation du port doivent  
être approuvées par le  
recommendation of the  
Minister and the Minister of  
Finance, before the letters  
patent are issued.  
gouverneur en conseil, sur  
recommandation du ministre  
et du ministre des Finances,  
avant la délivrance des lettres  
patentes.  
Supplementary letters  
patent  
Lettres patentes  
supplémentaires  
9(1) The Minister may, either 9(1) Le ministre peut, soit de  
on the Minister’s own  
son propre chef et après avoir  
avisé le conseil  
d’administration des  
modifications proposées, soit  
sur demande de celui-ci  
initiative and after giving  
notice of the proposed  
changes to the board of  
directors, or when the board  
of directors has, by resolution, autorisée par résolution,  
requested it, issue  
supplementary letters patent  
délivrer des lettres patentes  
supplémentaires modifiant les  
Page: 162  
amending the letters patent of lettres patentes de  
a port authority if the Minister l’administration portuaire s’il  
is satisfied that the  
est convaincu que les  
amendment is consistent with modifications sont  
this Act, and the  
compatibles avec la présente  
supplementary letters patent  
take effect on the date stated  
in them.  
loi; les lettres patentes  
supplémentaires prennent  
effet à la date qui y est  
mentionnée.  
Notice  
Avis  
(2) Notice must be given in  
writing and set out a time  
limit within which the board  
of directors may comment to  
the Minister regarding the  
proposed changes.  
(2) L’avis est donné par écrit  
et prévoit le délai dans lequel  
le conseil d’administration  
peut faire parvenir au ministre  
ses observations sur les  
modifications proposées.  
[…]  
Capacity and powers  
Capacité et pouvoirs  
28(1) A port authority is  
incorporated for the purpose  
of operating the port in  
28(1) Une administration  
portuaire est constituée pour  
l’exploitation du port visé par  
ses lettres patentes et a, à cette  
respect of which its letters  
patent are issued and, for that fin et pour l’application de la  
purpose and for the purposes présente loi, la capacité d’une  
of this Act, has the powers of personne physique.  
a natural person.  
Activities  
Activités portuaires  
(2) The power of a port  
(2) L’autorisation donnée à  
authority to operate a port is  
une administration portuaire  
limited to the power to engage d’exploiter un port est  
in  
restreinte aux activités  
suivantes :  
(a) port activities related to  
shipping, navigation,  
transportation of passengers  
a) les activités portuaires liées  
à la navigation, au transport  
des passagers et des  
and goods, handling of goods marchandises, et à la  
and storage of goods, to the  
manutention et l’entreposage  
extent that those activities are des marchandises, dans la  
Page: 163  
specified in the letters patent; mesure prévue par les lettres  
and  
patentes;  
(b) other activities that are  
b) les autres activités qui sont  
deemed in the letters patent to désignées dans les lettres  
be necessary to support port  
operations.  
patentes comme étant  
nécessaires aux opérations  
portuaires.  
[…]  
Fisheries Act, RSC 1985, c F-14  
Harmful alteration,  
Détérioration, destruction  
disruption or destruction of ou perturbation de l’habitat  
fish habitat  
35(1) No person shall carry on 35(1) Il est interdit d’exploiter  
any work, undertaking or  
activity that results in the  
un ouvrage ou une entreprise  
ou d’exercer une activité  
harmful alteration, disruption entraînant la détérioration, la  
or destruction of fish habitat.  
destruction ou la perturbation  
de l’habitat du poisson.  
Exception  
Exception  
(2) A person may carry on a  
work, undertaking or activity  
without contravening  
(2) Il est permis d’exploiter un  
ouvrage ou une entreprise ou  
d’exercer une activité sans  
contrevenir au paragraphe (1)  
dans les cas suivants :  
subsection (1) if  
[…]  
(b) the carrying on of the  
work, undertaking or activity  
is authorized by the Minister  
and the work, undertaking or  
activity is carried on in  
accordance with the  
b) l’exploitation de l’ouvrage  
ou de l’entreprise ou  
l’exercice de l’activité est  
autorisé par le ministre et est  
conforme aux conditions que  
celui-ci établit;  
conditions established by the  
Minister;  
[…]  
Page: 164  
Canadian Environmental Assessment Act, 2012, SC 2012, c 19, s 52  
[Repealed, 2019, c 28, s 9] - 2019-08-28  
Project carried out on  
federal lands  
Project réalisé sur un  
territoire domanial  
67 An authority must not  
carry out a project on federal  
lands, or exercise any power  
or perform any duty or  
67 L’autorité ne peut réaliser  
un projet sur un territoire  
domanial ou exercer les  
attributions qui lui sont  
function conferred on it under conférées sous le régime  
any Act of Parliament other d’une loi fédérale autre que la  
than this Act that could permit présente loi et qui pourraient  
a project to be carried out, in  
whole or in part, on federal  
lands, unless  
permettre la réalisation en tout  
ou en partie du projet sur un  
tel territoire que si, selon le  
cas :  
(a) the authority determines  
that the carrying out of the  
project is not likely to cause  
significant adverse  
a) elle décide que la  
réalisation du projet n’est pas  
susceptible d’entraîner des  
effets environnementaux  
négatifs importants;  
environmental effects; or  
(b) the authority determines  
that the carrying out of the  
project is likely to cause  
significant adverse  
b) elle décide que la  
réalisation du projet est  
susceptible d’entraîner des  
effets environnementaux  
environmental effects and the négatifs importants et le  
Governor in Council decides gouverneur en conseil décide,  
that those effects are justified au titre du paragraphe 69(3),  
in the circumstances under  
subsection 69(3).  
que ces effets sont justifiables  
dans les circonstances.  
Impact Assessment Act, SC 2019, c 28, s 1  
Federal authority  
Autorité fédérale  
8 A federal authority must not 8 L’autorité fédérale ne peut  
exercise any power or perform exercer les attributions qui lui  
any duty or function conferred sont conférées sous le régime  
on it under any Act of  
d’une loi fédérale autre que la  
Parliament other than this Act présente loi et qui pourraient  
that could permit a designated permettre la réalisation en tout  
project to be carried out in  
ou en partie d’un projet  
whole or in part and must not désigné et ne peut accorder à  
Page: 165  
provide financial assistance to quiconque une aide financière  
any person for the purpose of en vue de permettre la  
enabling that designated  
project to be carried out, in  
whole or in part, unless  
réalisation en tout en partie  
d’un tel projet que si, selon le  
cas :  
(a) the Agency makes a  
decision under subsection  
16(1) that no impact  
assessment of the designated  
project is required and posts  
that decision on the Internet  
site; or  
a) l’Agence décide, au titre du  
paragraphe 16(1), qu’aucune  
évaluation d’impact du projet  
n’est requise et affiche sa  
décision sur le site Internet;  
(b) the decision statement  
b) la déclaration remise au  
with respect to the designated promoteur au titre de l’article  
project that is issued to the  
proponent of the designated  
project under section 65 sets  
out that the effects that are  
indicated in the report with  
respect to the impact  
65 relativement au projet  
donne avis d’une décision  
portant que les effets qui sont  
identifiés dans le rapport  
d’évaluation d’impact du  
projet sont dans l’intérêt  
assessment of that project are public.  
in the public interest.  
[…]  
Project carried out on  
federal lands  
Project réalisé sur un  
territoire domanial  
82 An authority must not  
82 L’autorité ne peut réaliser  
un projet sur un territoire  
domanial, exercer les  
carry out a project on federal  
lands, exercise any power or  
perform any duty or function  
attributions qui lui sont  
conferred on it under any Act conférées sous le régime  
of Parliament other than this d’une loi fédérale autre que la  
Act that could permit a project présente loi et qui pourraient  
to be carried out, in whole or  
in part, on federal lands or  
permettre la réalisation, en  
tout ou en partie, du projet sur  
provide financial assistance to un tel territoire ni accorder à  
any person for the purpose of quiconque une aide financière  
enabling that project to be  
carried out, in whole or in  
part, on federal lands, unless  
en vue de permettre la  
réalisation en tout ou en partie  
d’un projet sur un tel territoire  
que si, selon le cas :  
Page: 166  
(a) the authority determines  
that the carrying out of the  
project is not likely to cause  
significant adverse  
a) elle décide que la  
réalisation du projet n’est pas  
susceptible d’entraîner des  
effets environnementaux  
négatifs importants;  
environmental effects; or  
(b) the authority determines  
that the carrying out of the  
project is likely to cause  
significant adverse  
b) elle décide que la  
réalisation du projet est  
susceptible d’entraîner des  
effets environnementaux  
environmental effects and the négatifs importants et le  
Governor in Council decides, gouverneur en conseil décide,  
under subsection 90(3), that  
those effects are justified in  
the circumstances.  
au titre du paragraphe 90(3),  
que ces effets sont justifiables  
dans les circonstances.  
Vancouver Port Authority Letters Patent - P.C. 2007-1885 December 6, 2007  
CERTIFICATE OF AMALGAMATION OF PORT AUTHORITIES  
NOW THEREFORE under the authority of section 59.1 of the Port Authorities Management  
Regulations, it is hereby certified that the Vancouver Port Authority, the Fraser River Port  
Authority and the North Fraser Port Authority are amalgamated and continue as one port  
authority to be named the Vancouver Fraser Port Authority, with the letters patent for the  
amalgamated port authority contained herein. The amalgamation takes effect on January 1, 2008.  
VANCOUVER FRASER PORT AUTHORITY  
NOW THEREFORE, under the authority of section 9 of the Act, the Letters Patent of the  
Vancouver Fraser Port Authority are as follows:  
ARTICLE 4  
DIRECTORS AND DIRECTOR’ MEETINGS  
4.1 General Duties of the Board. The Board is responsible for the management of the activities  
of the Authority.  
Page: 167  
ARTICLE 5  
CODE OF CONDUCT  
5.1 The Code of Conduct governing the conduct of the directors and officers is set out in  
Schedule E hereto.  
ARTICLE 7  
ACTIVITIES AND POWERS OF THE AUTHORITY AND SUBSIDIARIES  
7.1 Activities of the Authority Related to Certain Port Operations. To operate the port, the  
Authority may undertake the port activities referred to in paragraph 28(2)(a) of the Act to the  
extent specified below:  
(a) development, application, enforcement and amendment of rules, orders, bylaws, practices or  
procedures and issuance and administration of authorizations respecting use, occupancy or  
operation of the port and enforcement of Regulations or making of Regulations pursuant to  
subsection 63(2) of the Act;  
SCHEDULE E  
VANCOUVER FRASER PORT AUTHORITY  
CODE OF CONDUCT  
ARTICLE 1  
OBJECTS AND INTERPRETATION  
1.1 Object of Code. The object of this Code is to preserve and enhance public confidence in the  
integrity and impartiality of directors and officers of the Authority and the business activities and  
transactions carried on by the Authority by establishing clear conflict of interest rules for  
directors and officers of the Authority.  
1.2 Principles. This Code shall be interpreted in accordance with the following general  
principles:  
(a) every director and officer shall discharge their duties and arrange their private affairs in such  
a manner so as to preserve and promote public confidence and trust in the integrity and  
impartiality of the Authority;  
(b) the obligations of a director or officer described in subsection 1.2(a) may not always be  
discharged merely by acting in accordance with the technical requirements of the Act, the  
Regulations, the Letters Patent, the by-laws and the policies and resolutions of the Board; and  
Page: 168  
(c) public confidence and trust in the integrity and impartiality of the Authority may be as  
equally compromised by the appearance of a conflict as with the existence of an actual conflict.  
1.3 Definitions. In this Code terms used herein shall have the meanings ascribed to them in the  
Act and the Letters Patent, and in addition the following terms shall have the following  
meanings:  
(a) “Giftincludes any good, service, benefit, hospitality, promise or favour; and  
(b) “Related Partymeans with respect to a director or officer of the Authority  
(i) a spouse, child, brother, sister or parent of such director or officer;  
(ii) a relative of such director or officer (other than a spouse, child, brother, sister or parent of  
such director or officer) or a relative of the spouse of such director or officer if the relative  
has the same residence as the director or officer;  
(iii) a corporation, partnership, trust or other entity which is directly or indirectly controlled  
by such director or officer or by a spouse, child, brother, sister or parent of such director or  
officer or any combination of such persons; and  
(iv) a partner of such director or officer acting on behalf of a partnership of which the  
director or officer and the partner are partners.  
1.4 Application of Code. This Code applies to all directors and officers of the Authority.  
1.5 Scope of Obligations. Conforming to the specific requirements of this Code shall not  
absolve a director or officer of responsibility for taking such additional action as may be  
necessary to conform with any standard of conduct or comply with any duty imposed by the Act,  
the Regulations, the Letters Patent, the by-laws and the policies and resolutions of the Board or  
otherwise by law.  
1.6 Acknowledgement by Directors and Officers. Each director and officer shall acknowledge  
in writing to the Governance Committee that  
(a) they have read and understood this Code;  
(b) to the best of their knowledge they are in compliance with this Code and neither they nor any  
Related Party to them has a conflict or a potential conflict within the meaning of Article 2 of this  
Code; and  
(c) in the case of each officer, compliance with this Code is a condition of their employment.  
1.7 Timing of Acknowledgement. Each director and officer shall deliver the acknowledgement  
described in section 1.6 of this Code to the Governance Committee:  
(a) with respect to the directors serving and officers employed on the date the Letters Patent take  
effect, forthwith upon the Letters Patent taking effect; and  
Page: 169  
(b) with respect to all other directors at the time of their appointment and with respect to all other  
officers at the time of the commencement of their employment.  
1.8 Annual Review. Each director and officer shall regularly review their obligations under this  
Code and shall on the 15th day of March of each year provide the Governance Committee with a  
written acknowledgement confirming such review and that, to the best of the knowledge of the  
director or officer,  
(a) they are in compliance with this Code; and  
(b) neither they nor any Related Party to them has a conflict within the meaning of Article 2 of  
this Code.  
ARTICLE 2  
CONFLICTS OF INTEREST  
2.1 Conflicts Generally. A director or officer shall not allow his or her personal interests or the  
personal interests of a Related Party to the director or officer to conflict with or to give rise to the  
appearance of a conflict with the duties and responsibilities of the director or officer to the  
Authority or the interests of the Authority.  
2.2 Specific Types of Conflicts. Without restricting the generality of section 2.1, the following  
represent examples of specific matters which give rise to a conflict or the appearance of a  
conflict on the part of a director or officer:  
(a) Competition with the Authority: A director or officer or a Related Party of a director or  
officer engages in any activity, or has a material interest in any person which engages in an  
activity, which is in competition or could reasonably be expected to be in competition with the  
Authority's present or proposed interests;  
(b) Transactions with the Authority or a User; Material Interests: A director or officer or a  
Related Party of a director or officer  
(i) has a material interest in a user;  
(ii) owes material obligations to the Authority or a user, other than in connection with the  
duties of the director or officer arising from their position with the Authority;  
(iii) conducts business with the Authority or a user; or  
(iv) holds a material interest in a person which conducts business with, or acts as a consultant  
or advisor to, the Authority or a user;  
(c) Interest in Material Contract: A director or officer  
(i) is a party to a material contract or proposed material contract with the Authority; or  
Page: 170  
(ii) is a director or officer of or has a material interest in any person who is a party to a  
material contract or proposed material contract with the Authority; and  
(d) Acceptance of Offices with Conflicted Entities: A director or officer accepts an appointment  
or a nomination for election to an office of, or employment with, any corporation, partnership,  
foundation, institute, organization, association or other entity, the business or activities of which  
are, or could reasonably be expected to be, in conflict with the interests of the Authority.  
2.3 Conflicts For Which Approval Satisfactory. Engaging in the following activities shall be  
deemed not to give rise to a conflict or the appearance of a conflict on the part of a director or  
officer within the meaning of Article 2 of this Code provided that the director or officer obtains  
the written approval of the Governance Committee prior to engaging in such activities:  
(a) Acceptance of Offices With Entities Benefiting From Authority: A director or officer accepts  
an appointment or a nomination for election to an office of, or employment with, any  
corporation, partnership, foundation, institute, organization, association or entity, the business or  
activities of which benefit or could reasonably be expected to benefit from the business of the  
Authority or decisions made by the Authority; and  
(b) Use of Authority Property: A director or officer uses property of the Authority or property  
managed by the Authority for the personal benefit of the director or officer or a Related Party of  
the director or officer.  
If a director or officer fails to obtain the written approval of the Governance Committee prior to  
engaging in any activity described in subsections (a) or (b) of this section, the engagement of the  
director or officer in such activity shall be deemed to give rise to a conflict of interest within the  
meaning of Article 2 of this Code.  
FEDERAL COURT  
SOLICITORS OF RECORD  
T-538-19  
DOCKET:  
GCT CANADA LIMITED PARTNERSHIP v  
VANCOUVER FRASER PORT AUTHORITY and  
ATTORNEY GENERAL OF CANADA  
STYLE OF CAUSE:  
VANCOUVER, BRITISH COLUMBIA  
OCTOBER 18, 2021  
PLACE OF HEARING:  
DATE OF HEARING:  
JUDGMENT AND REASONS:  
DATED:  
PAMEL J.  
JULY 26, 2022  
APPEARANCES:  
Peter H. Griffin  
FOR THE APPLICANT  
Matthew B. Lerner  
Christopher Yung  
Joan M. Young  
Komal Jatoi  
FOR THE RESPONDENT  
VANCOUVER FRASER PORT AUTHORITY  
Charlotte Conlin  
Sarah Bird  
FOR THE RESPONDENT  
Jordan Marks  
ATTORNEY GENERAL OF CANADA  
Shane Hopkins-Utter  
SOLICITORS OF RECORD:  
Lenczner Slaght Royce Smith  
Griffin LLP  
FOR THE APPLICANT  
Barristers and Solicitors  
Toronto, Ontario  
McMillan LLP  
FOR THE RESPONDENT  
Barristers and Solicitors  
Vancouver, British Columbia  
VANCOUVER FRASER PORT AUTHORITY  
Attorney General of Canada  
Vancouver, British Columbia  
FOR THE RESPONDENT  
ATTORNEY GENERAL OF CANADA  
Page: 2  


© 2022 IncJournal is not affiliated with or endorsed by the U.S. Securities and Exchange Commission