24
City of Toronto By-law -2022
c.
d.
obtain all necessary permits and design, financially secure, construct, and make
operational, all required internal infrastructure and external upgrades to the
existing municipal infrastructure identified in the accepted Functional Servicing
Report, Hydrogeological Report and Stormwater Management Report, to support
the development, all to the satisfaction of the Chief Engineer, the General
Manager, Toronto Water, and the City Solicitor; and
Regardless of which option set out in s.3 a, b, or c above is selected, the Owner
shall:
i.
submit all environmental site assessment reports describing the current site
conditions and the proposed remedial action plans in accordance with the
City's Environmental Peer Review Policy and obtain concurrence from the
third party peer reviewer to the satisfaction of the Chief Engineer; and
ii.
provide space within the development for installation of maintenance
access holes and sampling ports on the private side, as close to the
property line as possible, for both the storm and sanitary service
connections, in accordance with the Sewers Chapter 681.10 of the City of
Toronto Municipal Code.
4.
Prior to the issuance of any Above-Grade Building Permit for all or any part of the
development, including for clarity, any conditional Above-Grade Building Permit, the
Owner shall at no cost to the City design, financially secure, construct, and make
operational, all required internal infrastructure and external upgrades to the existing
municipal infrastructure identified in the accepted Functional Servicing Report,
Hydrogeological Report and Stormwater Management Report, to support the
development, all to the satisfaction of the Chief Engineer, the General Manager, Toronto
Water, and the City Solicitor.
5.
Prior to the issuance of any Above-Grade Building Permit for all or any part of the site,
including for clarity, any conditional Above-Grade Building Permit, the Owner shall at
no cost to the City conduct any remediation work for lands to be conveyed to the City
identified through the Peer Review to the satisfaction of the Peer Reviewer of the
Environmental Site Assessments and the Chief Engineer and Executive Director,
Engineering and Construction Services.
Child Care Centre
6. Prior to or concurrent with the earlier of first residential occupancy of Building C as
shown on Schedule 2 attached to and forming part of this By-law, registration of a
condominium under the Condominium Act, 1998 for Building C as shown on Schedule 2
attached to and forming part of this By-law, and in any event within 12 months of the
first residential occupancy of the development, unless otherwise agreed by the Chief
Planner in writing, the Owner, at its sole expense, shall design, construct, finish, furnish,